Core Concrete Pty Ltd v Murtrack Pty Ltd t/a R & F Steel Building Cairns [2024] QCAT 475
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Core Concrete Pty Ltd v Murtrack Pty Ltd t/a R & F Steel
Building Cairns [2024] QCAT 475
PARTIES: CORE CONCRETE PTY LTD
(applicant)
v
MURTRACK PTY LTD TRADING AS R & F STEEL
BUILDING CAIRNS
(respondent)
APPLICATION NO/S: BDL200-19
MATTER TYPE: Building matters
DELIVERED ON: 29 October 2024
HEARING DATE: 29 July 2024
HEARD AT: Brisbane
DECISION OF: Member Lumb
ORDERS: 1. The Respondent must pay to the Applicant the
amount of $1,436.95 within twenty-one (21) days of
the date of this Decision.
2. Any party seeking an order for costs must file with
the Tribunal two (2) copies of, and give to the other
party one (1) copy of, written submissions, no longer
than four (4) pages, within 14 days of the date of the
Decision.
3. If written submissions as to costs are filed, the party
against whom an order for costs is sought must file
with the Tribunal two (2) copies of, and give to the
other party one (1) copy of, written submissions in
response, no longer than four (4) pages, within 14
days of receipt of the written submissions.
4. If no written submissions as to costs are filed within
14 days of the date of the Decision, there shall be no
order as to costs of the proceeding.
5. If written submissions as to costs are filed, the
application for costs will be determined on the
papers, without an oral hearing.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF WORK
– REMEDIES FOR BREACH OF CONTRACT –
DAMAGES – MEASURE OF – where commercial building
-- 1 of 8 --
2
dispute under the Queensland Building and Construction
Commission Act 1991 (Qld) – where
applicant/subcontractor performed concreting and
associated work for respondent/head contractor – where
respondent claimed work was defective – where respondent
did not pay applicant moneys all owing under the agreement
and under a previous agreement – whether work defective –
whether set-off available
Queensland Building and Construction Commission Act
1991 (Qld), s 75, s 76, s 77, Schedule 2
Allen & Anor v Contrast Constructions Pty Ltd (No 2)
[2021] QCATA 43
Murphy and Anor v GDS Building Services Pty Ltd t/as Zen
Roofing and Anor [2022] QCAT 197
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Introduction
[1] By an Application for domestic building disputes filed on 25 July 2019 (‘the
Application’), the Applicant (‘Core Concrete’) claims the amount of $9,428.00 being
the balance of moneys owing by the Respondent (‘Murtrack’) for the performance of
concreting and associated work. The amount claimed comprises two separate amounts
of $880.00 and $8,548.00.
[2] By a Response and/or counter-application filed on 10 February 2020 (‘the Counter-
application’), Murtrack claims the amount of $10,907.06 against Core Concrete as
damages for breach of contract.
[3] In considering the Application and the Counter-application, it is first necessary to give
consideration to the issue of jurisdiction.
Jurisdiction
[4] Subsection 77(1) of the Queensland Building and Construction Commission Act 1991
(Qld) (‘the QBCC Act’) provides that a person involved in a ‘building dispute’ may
apply, as provided under the Queensland Civil and Administrative Tribunal Act 2009
(Qld) (‘the QCAT Act’), to have the Tribunal decide the dispute.
[5] I am satisfied that the present matter involves a ‘building dispute’ within the meaning
of s 77. The definition of a ‘building dispute’ in Schedule 2 to the QBCC Act includes
‘a minor commercial building dispute’. The phrase ‘minor commercial building
dispute’ means ‘a commercial building dispute where neither the claim nor the
counterclaim exceeds $50,000’. Plainly, the amount of the claim and of the claim
made by Counter-application is less than $50,000.00.
[6] The phrase ‘commercial building dispute’ is defined to mean, relevantly, ‘a claim or
dispute arising between two or more building contractors relating to the performance
of reviewable commercial work or a contract for the performance of reviewable
-- 2 of 8 --
3
commercial work’. The phrase ‘reviewable commercial work’ is defined to mean
‘tribunal work other than reviewable domestic work’. The phrase ‘tribunal work’ is
defined by reference to sections 75 and 76 of the QBCC Act.
[7] Section 75(1) provides, relevantly, that the following is ‘tribunal work’:
…
(b) the renovation, alteration, extension, improvement or repair of a
building;
…
(e) any site work (including the construction of retaining structures,
driveways, landscaping and the construction of a swimming pool)
related to tribunal work of a kind mentioned in paragraphs (a) to (d);
…
[8] The definition of ‘building’ includes, relevantly ‘generally, includes any fixed
structure’.
[9] I am satisfied that s 76 of the QBCC Act (which provides what is not tribunal work)
has no application to the present case.
[10] I find that:
(a) the work performed by Core Concrete was ‘tribunal work’ within the meaning
of s 75(1)(b) or (e) of the QBCC Act;
(b) this matter involves a minor commercial building dispute, specifically, a claim
or dispute arising between two or more building contractors relating to the
performance of reviewable commercial work or a contract for the performance
of reviewable commercial work;
(c) the dispute the subject of the Application is a ‘building dispute’ for the purposes
of s 77(1) of the QBCC Act.
[11] A person may not apply to the Tribunal unless the person has complied with a process
established by ‘the commission’ (the Queensland Building and Construction
Commission (‘the QBCC’)) to attempt to resolve the dispute (see s 77(2) of the QBCC
Act).1 Core Concrete lodged a complaint form dated 24 June 2019 with the QBCC in
relation to the non-payment by Murtrack. By email from the QBCC to Core Concrete
dated 12 July 2019, the QBCC advised that it could not assist Core Concrete and
stated, amongst other matters, that: ‘Or you can apply to QCAT the using this e-mail
[sic] as evidence that you have satisfied Section 77 of the Queensland Building and
Construction Commission Act 1991.’ I am satisfied that s 77(2) of the QBCC Act has
been complied with.
[12] I find that the Tribunal has jurisdiction to hear and determine the Application and the
Counter-Application.
[13] I now turn to the merits of the matter.
1 Allen & Anor v Contrast Constructions Pty Ltd (No 2) [2021] QCATA 43.
-- 3 of 8 --
4
Core Concrete’s claim
[14] There is no dispute that the respective amounts of $880.00 and $8,548.00 were unpaid
to Core Concrete under two separate agreements between the parties.
[15] With respect to the amount of $8,548.00, Murtrack’s case is that it has a right of set-
off against Core Concrete, by way of damages for breach of contract, in an amount
that exceeds the amount of Core Concrete’s claim. This is addressed below.
[16] With respect to the amount of $880.00, Murtrack formed the view that it was entitled
to, and did, deduct that amount (which is inclusive of GST) by way of a ‘backcharge’
as a result of a deduction made by the principal on a previous contract in order to
‘Rectify floor falls’. Murtrack had subcontracted work to Core Concrete (involving
the construction of a concrete slab).2 Murtrack contended that Core Concrete did not
allow sufficient fall in the slab and the slab had to be rectified.
[17] Core Concrete’s case is that the amount of $880.00 was wrongfully deducted.
[18] Core Concrete points out that the plans for the works in question did not show any fall
in the slab as alleged by Murtrack. Core Concrete has provided a copy of the relevant
plans.3 On viewing the plans, it is evident that no fall is shown on them. Murtrack
does not dispute that no fall is shown on the plans. In cross-examination, Mr Lammert
asserted that Dean Arnold (‘Mr Arnold’), who performed the work, was aware of the
falls. However, no evidence as to any such conversation had been filed by Murtrack.
[19] In my view, the evidential burden falls upon Murtrack to establish, first, that there was
‘insufficient’ falls in the slab; second, that this amounted to a breach of the agreement
by Core Concrete; and, third, that the work required rectification to comply with the
agreement, the reasonable cost of which was the amount of $800.00 plus GST. On the
evidence as a whole, I find that Murtrack has failed to establish such matters on the
balance of probabilities. I find that Murtrack was not entitled to deduct the unpaid
amount of $880.00.
[20] I now turn to the Counter-application.
The Counter-application
[21] Murtrack’s case is that:
(a) it was an implied term of the contract for the performance of the work by Core
Concrete that the work would be carried out:
(i) in an appropriate and skilful way;
(ii) with reasonable care and skill;
(iii) in accordance with the various identified project drawings (for a loading
area and a workshop);
(b) in breach of the implied terms:
(i) with respect to the loading area, Core Concrete incorrectly positioned steel
posts in the concrete slab with:
2 See exhibit 5, p 80.
3 Exhibit 2, p 8.
-- 4 of 8 --
5
A. three of the four steel posts being positioned 4655 mm and 4630 mm
apart rather than 4616 mm and 4566 mm apart as shown on the plan;
B. three of the four steel posts being positioned 4640 mm and 4644 mm
apart rather than 4616 mm and 4566 mm apart as shown on the plan;
C. the posts from front to back were positioned 157 mm wider than as
shown on the relevant plan;
(ii) with respect to the workshop, Core Concrete incorrectly positioned steel
posts in the concrete slab, the three left-hand side steel posts were
positioned 6050 and 6054 mm apart, and the three right-hand side steel
posts were positioned 6050 mm and 6056 mm apart, rather than 5874 mm
apart as shown on the relevant plan;
(c) as a consequence the breaches, Murtrack has suffered loss and damage in
rectifying the work in the amount of $10,907.06.
[22] Murtrack relied upon four affidavits in support of the Counter-application; three from
Mr Lammert, the director of Murtrack;4 and one from Mr Clinton Clark,5 the Project
Manager for the work performed by Murtrack (as main contractor) and Core Concrete
(as subcontractor) in respect of the loading bay and workshop.
[23] Core Concrete’s primary position was that Murtrack had not moved the alleged
wrongly positioned posts.
[24] However, that is not Murtrack’s case. Rather, Murtrack’s case is that it made
adjustments to the loading bay and workshop roofs so that the roofs would fit the
incorrectly positioned posts.6
[25] I find that there are implied into the agreement the following terms:
(a) a term implied by law that Core Concrete would exercise reasonable care, skill
and diligence in performing the work;7
(b) a term implied by fact, that the work would be carried out in accordance with
the plans provided by Murtrack.
[26] With respect to the term implied by fact, I am satisfied that it meets each of the
following conditions identified by the High Court in BP Refinery (Westernport) Pty
Ltd v The Shire of Hastings:8
(a) it must be reasonable and equitable;
(b) it must be necessary to give business efficacy to the contract, so that no term
will be implied if the contract is effective without it;
(c) it must be so obvious that it ‘goes without saying’;
(d) it must be capable of clear expression; and
4 Exhibit 6, 7 and 8.
5 Exhibit 9.
6 Exhibit 6, [5].
7 See Wilmar Sugar Australia Limited v Queensland Sugar Limited [2019] QSC 116, [114]-[118].
8 (1977) 180 CLR 266.
-- 5 of 8 --
6
(e) it must not contradict any express terms of the contract.
[27] Mr Lammert has provided evidence that establishes that the posts were not located in
the positions identified by the plans.9
[28] Mr Lammert has also given the following further evidence:10
[3] When the incorrect positions the poster identified, I contacted Dean
Arnold of Core Concrete and said words the effect of, “Mate, I don’t
know what we going to do because all your posts or incorrectly
positioned?” Mr Arnold responded with words to the effect, “Well can
we just send the kits back and get new kits?”
[4] I responded, “No, they are purpose-built. The kits are made to order and
are not returnable and we’ll need new materials to fit the incorrectly
positioned posts.”
[5] Mr Arnold did not have anything further to say.
[29] No contrary evidence was adduced by Core Concrete. Mr Arnold was not called as a
witness by Core Concrete.
[30] In cross-examination, Mr Lammert maintained the evidence given by way of affidavit.
In particular, he maintained that the kits were ‘purpose-built’ and that the new
materials were required in order to fit the (incorrect) positions of the posts.
[31] Mr Clark’s affidavit evidence included the following:11
[4] Midway through the loading bay and workshop works project – After the
concrete and posts were completed, I was informed by [Mr Lammert] of
a construction issue. [Mr Lammert] asked me to assist in measuring the
work carried out by the concrete contractor, as he believed there was an
issue with the steel post locations. This post location issue was confirmed
when we measured the post location.
[5] Steel posts were incorrectly positioned in the concrete slabs.
[6] I can no longer recall the precise details of the incorrect positioning of
the steel posts but I do recall the Respondent had to re-order materials to
suit the incorrectly positioned posts.
[7] I have been shown the Project Drawings and drawings prepared by the
Respondent’s director, [Mr Lammert], depicting the incorrect positioning
of steel posts … and the drawings depicting the incorrect positioning of
steel are generally in keeping with my recollection of how the posts were
incorrectly positioned.
[32] This evidence was not challenged by cross-examination.
[33] Having regard to the evidence as a whole, I find that:
(a) Core Concrete erected the various steel posts in the wrong locations, that is, not
in the locations identified by the plans provided to Core Concrete for the
performance of the work;
9 Exhibit 7, [6]-[7]; Exhibit 5 pp 69-70.
10 Exhibit 8, [3]-[5].
11 Exhibit 9, [3]-[6].
-- 6 of 8 --
7
(b) the incorrect locations were as identified by Mr Lammert;
(c) in erecting the steel posts in the wrong locations, Core Concrete breached each
of the implied terms identified in paragraph [25] above;
(d) as a result of the breach of contract by Core Concrete, Murtrack was required to
rectify the work.
[34] The amounts claimed by Murtrack in its Counter-application are itemised in a tax
invoice to Core Concrete dated 1 July 2019.12 A number of the items are corroborated
by invoices issued by third parties to Murtrack. Having regard to those invoices, I
consider that Murtrack has established that it suffered the following damages
(totalling $7,991.05) in rectifying the defective or non-compliant work by Core
Concrete:
(a) the purchase of new materials from Lysaght for the loading bay in the amount
of $4,442.56;13
(b) work performed by Gilman Contracting on the loading bay in the amount of
$572.00;14
(c) provision of additional screws by Normist in the amount of $162.03;15
(d) the purchase of new materials from Lysaght for the workshop in the amount of
$2,143.46;16
(e) work performed by Gilman Contracting in respect of the workshop in the
amount of $396.00;17
(f) further work performed by Gilman Contracting in respect of the workshop in
the amount of $275.00.18 Whilst the total amount of the invoice is $407.00, I
have disallowed $132.00 on the basis that, on the face of the invoice, that
component of the rectification work refers to ‘mistakes on canteen’ which
indicates that it related to separate work performed by Core Concrete, and, in
respect of which there was no evidence to justify the basis for claiming that
component.
[35] As to the balance of the items claimed in the tax invoice dated 1 July 2019, I find that
Murtrack has failed to establish an entitlement to those amounts. There is an absence
of corroborating evidence to establish that that Murtrack incurred costs in the amounts
claimed. Additionally, with respect to the amounts claimed as ‘hours’ for performing
various work, there is an absence of corroborating evidence of the number of hours of
work, and how that work relates to the rectification of the loading bay and workshop
respectively. I find that Murtrack has established that it has suffered damages for
breach of contract in the amount of $7,991.05.
[36] I am satisfied that there is such a connection between that component of Core
Concrete’s claim in the amount of $8,548.00 and the subject matter of the Counter-
12 Exhibit 5, p 71.
13 Exhibit 5, pp 72-73.
14 Exhibit 5, p 74.
15 Exhibit 5, p 75.
16 Exhibit 5, pp 76-77.
17 Exhibit 5, p 78.
18 Exhibit 5, p 78.
-- 7 of 8 --
8
application as can be said to ‘impeach’ that component of the claim so as to make it
unfair for the claim to be allowed without taking account of the Counter-application.19
I find that Murtrack is entitled to set off the amount of $7,991.05 against Core
Concrete’s claimed amount of $8,548.00. This leaves a balance of $556.95 to be added
to the separate amount of $880.00 also owing by Murtrack to Core Concrete. The total
of the two amounts is $1,436.95.
Order
[37] Pursuant to s 77 of the QBCC Act, the Respondent is ordered to pay to the Applicant
the amount of $1,436.95 within twenty-one (21) days of the date of this Decision.
Costs
[38] In circumstances where both parties were self-represented, where Core Concrete had
success on the Application, where Murtrack had substantial success on the Counter-
application, where each of the parties incurred a filing fee of $345.80, and where the
amount recoverable by Core Concrete is less than $1,500.00, my provisional view is
that the starting or default position under s 100 of the QCAT Act, namely that each
party must bear the party’s own costs for the proceeding, should apply here.
[39] However, to allow either party to make a costs order if they so wish, I make the
following orders as to costs:
(a) any party seeking an order for costs must file with the Tribunal two (2) copies
of, and give to the other party one (1) copy of, written submissions, no longer
than four (4) pages, within 14 days of the date of the Decision;
(b) if written submissions as to costs are filed, the party against whom an order for
costs is sought must file with the Tribunal two (2) copies of, and give to the
other party one (1) copy of, written submissions in response, no longer than four
(4) pages, within 14 days of receipt of the written submissions;
(c) if no written submissions as to costs are filed within 14 days of the date of the
Decision, there shall be no order as to costs of the proceeding.
(d) if written submissions as to costs are filed, the application for costs will be
determined on the papers, without an oral hearing.
19 See Murphy and Anor v GDS Building Services Pty Ltd t/as Zen Roofing and Anor [2022] QCAT 197,
[96]-[100] (and the cases cited therein).
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2024/475