Dixonbuild Pty Ltd v Queensland Building and Construction Commission & Anor [2024] QCAT 168
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Dixonbuild Pty Ltd v QBCC & Anor [2024] QCAT 168
PARTIES: DIXONBUILD PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
SCOTT NEWTON
(second respondent)
APPLICATION NO/S: GAR329-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 26 April 2024
HEARING DATE: 10 November 2023 and 21 March 2024
HEARD AT: Brisbane
DECISION OF: Member Howe
ORDERS: The Direction to Rectify issued 4 September 2020 is set
aside.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – where the builder had
constructed a dwelling but omitted work required under the
contract to install gully traps in the yard – where the home
was sold and the new home owner complained to the builder
and the Queensland Building and Construction Commission
about poor drainage affecting the building – where the
builder then installed the gully traps – where the Queensland
Building and Construction Commission issued a Direction
to Rectify the defective installation of the gully traps –
where the builder sought review of the decision to issue the
Direction to Rectify – whether the installation of the gully
traps was building work – where the gully traps were not
connected to the building or to a drainage main and therefore
not building work in respect of which a Direction to Rectify
could issue
Queensland Building and Construction Commission Act
1991 (Qld), Schedule 2
Queensland Building and Construction Commission
Regulation 2018 (Qld), s 5, Schedule 1 s 2, s 11
-- 1 of 7 --
2
Goldfield Projects Pty Ltd v QBCC [2016] QCAT 362
The Trustee for Hardev Property (Dev 10) Unit Trust v
Palmgrove Holdings Pty Ltd & Ors [2019] QSC 208
APPEARANCES &
REPRESENTATION:
Applicant: C H Matthews instructed by CDI Lawyers
First Respondent: R Ensbey, Gadens Lawyers
Second Respondent: Self-represented
REASONS FOR DECISION
[1] On 5 November 2013 the applicant builder (‘Dixon’) was engaged by a landholder to
build a dwelling at a property at Cedar Vale. The works were completed by 11
September 2014.
[2] The second respondent Mr Newton purchased the property from the original
landholder on 13 July 2017.
[3] In May 2019 Mr Newton complained to Dixon about the slab and site drainage. On
19 May 2019 he made a complaint about defective building work to the first
respondent (‘QBCC’).
[4] The original construction contract called for the installation of four field gullies
around the house. They had not been installed when the house was built. After Mr
Newton complained to QBCC and before QBCC arranged a site inspection, Dixon
sent out a plumber to install the field gullies. They were installed, with trenching,
generally in the positions noted for them in the original construction plans. Mr Newton
informed QBCC about that having been done.
[5] On 7 June 2020 Mr Newton forwarded a list of 69 complaint items to QBCC. With
respect to drainage, the complaints noted that drainage had finally been installed “as
per plan”.
[6] A QBCC building inspector, Mr Turkington, conducted an inspection of the property
on 11 August 2020. Mr Turkington prepared a report on 27 August 2020 noting that
with respect to the gully traps, the turf laid over excavated trenches between the
recently installed gully traps had left the field gullies higher than the adjacent ground
levels which prevented water flowing into the field gullies. Mr Turkington determined
the field gully drainage work did not meet a reasonable standard of construction or
finish expected of the holder of a competent contractor’s licence and the work required
rectification.
[7] On 4 September 2020, QBCC issued a Direction to Rectify (‘the DTR’) defective
building work concerning the drainage work. On 4 September 2020 Dixon also filed
an application in the Tribunal seeking review of the decision.
[8] An initial issue for determination is whether the installation of the gully traps was
building work in respect of which QBCC could issue the DTR.
[9] Dixon says there are two bases upon which the work installing the gully traps was not
building work as defined in the Queensland Building and Construction Commission
Act 1991 (Qld) (‘the Act’).
-- 2 of 7 --
3
[10] First, by s 2 of Schedule 1 of the Queensland Building and Construction Commission
Regulation 2018 (Qld) (‘the Regulation’), work of a value of $3,300 or less is not
building work as defined in the Act.
[11] Second, by Section 11 of Schedule 1 of the Regulation the work was drainage work
which did not connect the drainage system to a building and main of the system and
therefore not building work as defined in the Act.
Value less than $3300
[12] Building work is defined in Schedule 2 of the Act:
building work means—
…
(c) the provision of lighting, heating, ventilation, air conditioning, water
supply, sewerage or drainage in connection with a building;
…
but does not include work of a kind excluded by regulation from the ambit of
this definition.
[13] Section 5 of the Regulation states that for Schedule 2 of the Act, definition building
work, the work stated in Schedule 1 of the Regulation is not building work.
[14] Schedule 1 s 2 of the Regulation excludes, from the definition of building work, work
of a value of $3,300 or less.
[15] On the morning of the first day of hearing on 10 November 2023 an affidavit sworn
by Mr Bartholomaeus, a director of Dixon, was tendered exhibiting a purchase
order/subcontract agreement between Dixon and a plumber, Mr Scully, engaging the
latter to install the gully traps at the property. That was done by Mr Scully on about
20 May 2020. The total cost of the job noted in the purchase order/subcontract
agreement was $500.50.
[16] That evidence about Mr Scully’s charges for the work was new and took the
respondents by surprise at hearing. The hearing was adjourned to enable QBCC to
obtain instructions about it and to tender evidence if necessary concerning the value
of the work.
[17] The purchase order/subcontract agreement says nothing about the cost of trenching.
The description of the work done for $500.50 is generally unclear. It states:
DR – Stormwater – Extra For Stormwater $275
camera inspection required was not needed, p.o going
towards field gullies for Scully to cover the rest of the cost.
as agreed by Jackie & Ian/Anita
F Travel Drainer – Extra Travel Allowance per Quote $180
Per Tim b urgent QBCC matter
Attend site to pressure test property and provide report
-- 3 of 7 --
4
Labour + materials = $180 Plus GST
Total Incl GST $500.50
[18] Apart from no mention of trenching, there is no mention of time taken to do the work,
nor mention of an hourly rate. The purchase order suggests Mr Scully is to absorb “the
rest of the cost”.
[19] The amount claimed as the cost of the work was challenged on the first day of hearing,
but despite that there was no additional statement of evidence provided by Mr Scully
and he did not attend the adjourned hearing to explain the purchase order.
[20] The QBCC inspector Mr Turkington says in a statement of evidence1 that using the
Cordell cost estimator the reasonable value of the drainage work including excavation
work was $4,059.20 exclusive of GST. He attaches a copy of his calculations to his
statement of evidence.
[21] I prefer the evidence as to true cost of the work estimated by Mr Turkington to the
cost items noted in the purchase order/subcontract agreement as the reasonable cost
of the job.
[22] I determine the value of the gully trap work exceeded $3,300 and the exclusion to be
found in s 2 of Schedule 1 of the Regulation does not apply.
Drainage work not connecting a building to a main
[23] Section 11 of Schedule 1 of the regulation provides:
Work for water reticulation systems, sewerage systems or stormwater drains
(1) Construction, extension, repair or replacement of a water reticulation
system, sewerage system or stormwater drain, other than works
connecting a particular building to a main of the system or drain.
(2) In this section—
building includes a proposed building
[24] “Building” is defined in schedule 2 of the QBCC Act to mean:
(a) generally, includes any fixed structure; or
Examples of a fixed structure—
• a fence other than a temporary fence
• a water tank connected to the stormwater system for a building
• an in-ground swimming pool or an above-ground pool fixed to the ground
….
[25] Dixon says the purpose of the field gullies was to divert stormwater from the yard of
the property, not the house. The field gullies are a stormwater drain. The field gullies
are not connected to the dwelling. They are not connected to a stormwater main. The
field gullies were not a mandatory requirement for the construction of the building
pursuant to either the National Construction Code or any relevant Australian Standard.
1 Exhibit 11.
-- 4 of 7 --
5
[26] QBCC submits the installation of the gully traps was building work and the exclusion
under s 11 of Schedule 1 of the Regulation does not apply because they provided
drainage in connection with the building. Whilst the four field gullies were installed
late after the initial construction of the building (some 6 years later) the work was
done in the context of omitted work from the original construction and in accordance
with the approved plans. In that context, the installation of the four field gullies
amounts to drainage in connection with the building within the definition of building
work in Schedule 2 of the QBCC Act. The words “in connection with” a building used
in the Schedule 2 definition of building work should not be given a narrow meaning.
[27] QBCC further submits that the engineer, Mr Williamson, from STA Consulting
Engineers (‘STA’) referred to the absence of the four field gullies as a matter relevant
to the structural stability of the building.
[28] Dealing first with the engineer’s evidence, Mr Williamson in fact said good drainage
around the building was important to maintain its structural stability, but not the
presence of the field gullies to achieve that.
[29] Mr Newton had made complaints about cracking and damage to the dwelling before
the gully traps were installed. After he made complaint to Dixon in 2019, STA was
engaged by Dixon to provide a report. STA had drawn the initial drainage plan at the
time of construction of the house with the field gullies noted on the plan. The report
considered the complaints made by Mr Newton but concluded the house slab was
performing satisfactorily and no significant damage had occurred.
[30] Indeed in a letter from Mr Williamson to Mr Bartholomaeus dated 13 September 2021
the engineer states the foundations were not reliant on the field gullies. He said:
The supplied STA drainage plan (the Foundation Design Report) is a guide
only, for the property owner…. The engineered foundation was not reliant on
the placement of the suggested gully pits in the nominated areas, and therefore
not detrimental to the foundations in their absence, providing measures are
implemented to achieve compliance of 25 mm fall over first 1 metre from the
building in low rainfall intensity areas or 50 mm fall over first 1 metre from the
building and any other areas as per NCC clause 3.1.2.3...
[31] Turning to the exclusion in s 11 of Schedule 1 of the Regulation, the provision
specifically excludes from the definition of building work, work that is constructing,
extending, repairing or replacing a water reticulation system, sewerage system or
stormwater drain not connecting a building to a main of the system or drain.
[32] Where the exclusion applies, a broad interpretation of building work as defined in
Schedule 2 of the QBCC Act based on the context of the work in the course of
completion of a building contract holds no sway.
[33] The gully traps are not connected to the building, not connected to the building’s
drainage system,2 nor to any other fixed structure, such as a water tank. There is no
suggestion that the gully traps were ever intended to be connected to the building. The
drainage plans from 2013 simply show the position of individual gully traps in the
yard of the property without more. The water flows into the gully traps from the
ground, not via downpipes from the roof of the building.
2 Ex 1 [75].
-- 5 of 7 --
6
[34] The legislation seems clear. Work associated with installation of a water reticulation
system, sewerage system or stormwater drain where there is no connection to a
particular building or to a main of the system or drain is not building work as defined
under the QBCC Act.
[35] Even if the gully traps did connect to the building, they do not connect to any main of
the system or drain. The word connect used in the phrase “connecting a particular
building to a main” suggests a requirement of actual physical connection, not broad
brush contextual connection absent physicality.
[36] The word ‘main’ is defined in the online Macquarie Dictionary as “a principal pipe,
wire, cable or duct in a system used to distribute water, gas, electricity, etc”. The
words ‘the mains” is defined as “the principal distribution system for water, gas,
electricity, etc.: turn the water off at the mains”.
[37] In Goldfield Projects Pty Ltd v QBCC [2016] QCAT 362 Member Traves considered
the connection requirement of s 11 of Schedule 1 of the Regulation a physical one:
24 In my view, the intention of the Act and Regulations was to exclude
construction of the sewerage or drainage infrastructure but to include work
involved in connecting the building to that infrastructure and any site work
associated with that.
[38] In The Trustee for Hardev Property (Dev 10) Unit Trust v Palmgrove Holdings Pty
Ltd & Ors [2019] QSC 208 a contractor entered into a contract for the construction of
a 23 lot subdivision. The contract concerned, amongst other things, the contractor’s
provision of water and sewerage services to each lot. The developer contended that
the work to be performed was building work as defined in Schedule 2 of the QBCC
Act for which a licence was required, and the contractor had contravened section 42(1)
of the Act by entering into the contract.
[39] At the time of the contract the contractor had undertaken to provide branch
connections which would make the relevant services available to proposed lots which
had not at that time come into existence. A broad brush contextual relationship was
rejected. Lyons SJA said:
It is apparent that the sewer connection works and the water reticulation works
would not be building work, unless, as a result of the extended definition of the
term “building”, they are works connecting a particular proposed building to a
main of the system. In my view, it cannot be said that the works connect a
particular proposed building to the relevant main.3
…
At the time of the contract between the parties, no proposed building was
identified, and accordingly it cannot be said that the respondent undertook to do
works to connect a particular proposed building to a main.4
[40] I find the absence of any physical connection of the gully traps to the building (or to
any other structure), and further, the absence of a connection of the gully trap drainage
system to any main, conclusive in the matter.
3 The Trustee for Hardev Property (Dev 10) Unit Trust v Palmgrove Holdings Pty Ltd & Ors [2019]
QSC 208, [28].
4 Ibid, [30].
-- 6 of 7 --
7
[41] The work performed by Dixon installing the gully traps was not building work as
defined by the Act. There was therefore no power in QBCC to issue the DTR of 4
September 2020. The DTR is set aside.
-- 7 of 7 --