Ellis Developments Qld Pty Ltd v Lavis [2024] QCAT 80
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Ellis Developments Qld Pty Ltd v Lavis [2024] QCAT 80
PARTIES: ELLIS DEVELOPMENTS QLD PTY LTD
(applicant)
V
CALLAN JOHN LAVIS
(respondent)
APPLICATION NO/S: BDL213-21
MATTER TYPE: Building matters
DELIVERED ON: 14 February 2024
HEARD AT: Brisbane
DECISION OF: Member Lember
ORDERS: Within 21 days of the date of this order the
respondent must pay the applicant the sum of
$55,086.84 comprising:
(a) Claim $42,027.50;
(b) Interest $11,901.34;
(c) Costs $1,158.00.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
GENERALLY – where the parties entered a building
contract – where contract was not subject to finance – where
the homeowner did not have finance to complete – where
the builder seeks payment of the first progress payment,
damages, costs and interest
Queensland Building and Construction Commission Act
1991 (Qld), s 77, sch 2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 28, s 32
Australian Broadcasting Tribunal v Bond (1990) 170 CLR
321
Robinson v Harman [1848] Eng R 135; 1 Exch 850
APPEARANCES &
REPRESENTATION:
Heard and determined on the papers, pursuant to section 32
of the Queensland Civil and Administrative Tribunal Act
2009 (Qld) and directions made 9 February 2023.
-- 1 of 7 --
2
REASONS FOR DECISION
What is this application about?
A contract for the construction of a new home was terminated by the builder, Ellis
Developments Qld Pty Ltd (‘Ellis’) after the homeowner, Mr Lavis could not obtain
finance to fund the build, in circumstances where the contract was not subject to
finance.
By an application for a domestic building dispute filed 13 August 2021, Ellis sought
orders that Mr Lavis pay:
(a) $63,041.25 for work carried out under the contract; plus
(b) $67,244 in damages for breach of contract; plus
(c) Interest on the outstanding sum at 10% per annum; plus
(d) Costs.
In a response filed 19 September 2021 Mr Lavis resisted the claim and sought updated
contract pricing so that he can obtain a mortgage and complete the build. He says that
due to an illness in the family, and border closures during the COVID-19 pandemic,
he fell out of contact with Ellis for a time, but says that he had contacted their office
to tell them that he was applying for a mortgage to complete the build.
By directions made 9 February 2023 the application was to be determined on the
papers, based on the written evidence and submissions of the parties and the decision
now follows.
Does the tribunal have jurisdiction to hear this application?
Section 77 of the Queensland Building and Construction Commission Act 1991 (Qld)
(‘QBCC Act’) confers jurisdiction on the tribunal to hear building disputes.
A building dispute includes a “domestic building dispute”1 which, in turn, includes
(among other things) a claim or dispute arising between a building owner and a
building contractor relating to the performance of reviewable domestic work or a
contract for the performance of reviewable domestic work.
‘Reviewable domestic work’ means ‘domestic building work’,2 which includes the
construction of a detached dwelling.
It is clear from the material filed, and not disputed by either party, that the construction
of the detached dwelling to be undertaken by the applicant was domestic building
work, and that the claims relate to a contract for the performance of ‘reviewable
domestic work’.
By a letter dated 11 August 2021 the parties have established compliance with section
77(2) of the QBCC Act, that qualifies jurisdiction by first requiring an applicant to
comply “with a process established by the commission to attempt to resolve the
dispute” and, accordingly, I find that the tribunal has jurisdiction to hear the dispute.
1 QBCC Act, Schedule 2 (Definition of “building dispute”).
2 Ibid, Schedule 2 (“Definition of “reviewable domestic work”).
-- 2 of 7 --
3
The contract entered into by the parties
The parties signed a Master Builders Queensland Residential Building Contract –
Level 23 on 20 October 2020 (‘the contract’).
Among other things, the contract stated:
(a) In item 3(a) that the fixed price component was $420,275.00, payable by Mr
Lavis under clause 11.4.
(b) In item 4 that a deposit of $18,000.75 was payable by Mr Lavis on signing of
the contract under clause 11.5 (amended to $21,013.75, per the below).
(c) In item 5 that the building works comprised construction of a “5 bedrooms,
theatre room, 2 bathroom, double garage single dwelling”.
(d) In item 11 that the contract was not conditional upon Mr Lavis obtaining loan
approval to fund the build (and, according to Ellis,4 Mr Lavis had informed Ellis
that he was a “cash buyer”).
(e) In item 20 that the time for payment of a progress claim was within five business
days after the date Mr Lavis received the claim.
(f) In part D of the Appendix, that the designated stages to trigger progress claims
were:
Stage % of Contract Price $ Value (GST incl.)
Deposit 5% $21,013.75
Base Stage 15% $63,041.25
Frame Stage 20% $84,055.00
Enclosed Stage 25% $105,068.75
Fixing Stage 20% $84,055.00
Practical Completion 15% $63,041.25
Total 100% $420,275.00
The General Conditions to the contract included the following terms:
(a) in clauses 11.6 and 11.7 that the contractor is entitled to claim payment of the
contract price progressively and the owner must pay the contractor the claimed
progress payments claimed;
(b) in clause 11.9 (read with items 19 and 20 of the schedule) that if the owner fails
to make any payment to the contractor within five business days of the due date
for payment, the owner must pay interest at 10% per annum from the day after
the date that payment is due until the date of payment;
(c) in clause 21.1 that the contractor could give notice of intention to terminate the
contract if the owner failed to comply with obligations including any under
clause 11, giving ten business days to the owner to rectify the breach, and in
3 Version RBC-L2 07/2018.1.
4 Witness statement of Sarah Wheatley signed 28 September 2022.
-- 3 of 7 --
4
clause 21.2 that if the breach was not rectified, the contractor may terminate the
contract; and
(d) in clause 21.3 that if the contractor terminated the contract, it was entitled to
recover from the owner “all loss, costs, expenses and damages it incurs or
suffers as a result of, or otherwise in connection with the owner’s breach and
the termination”.
Relevant factual background to the dispute
According to a witness statement of Sarah Wheatley, Operations Manager for Ellis,
signed 28 September 2022:
(a) After signing the contract on 20 October 2020 and receiving the deposit around
that time, the parties undertook colour selections and pre-construction
processes, including the preparation of plans and interior design plans which
were signed off by Mr Lavis.5
(b) Construction was due to commence on 1 March 2021, confirmed in an email
sent to Mr Lavis on 25 February 2021.6
(c) In or around March 2021, Mr Lavis discussed with Ms Wheatley the prospect
of him applying for finance. Ms Wheatley informed Mr Lavis that while the
finance application was in progress, he would still be required to pay any claims
as construction had commenced and his contract was not subject to finance.
(d) Works reached base stage, as contemplated in the contract, on or around 8 April
2021,7 and a claim issued on that date.8
(e) Mr Lavis did not pay the progress claim by the due date for payment, or at all.
(f) On 9 April 2021 Kevin Paine from Aussie Home Loans emailed Ellis requesting
build specifications and plans, which were provided to him by Ellis on 12 April
2021.9
(g) On 15 April 2021 Mr Lavis informed Ms Wheatley that his finance application
was delayed due to outstanding documents required of him by the lender. Mr
Paine also confirmed this to Ms Wheatley.
(h) On 7 July 2021, solicitors for Ellis sent Mr Lavis a notice of intention to
terminate pursuant to section 21.1 of the contract, which demanded payment of
the base stage invoice.10
(i) Mr Lavis did not respond to the notice within the timeframe required by the
notice, or at all.
(j) On 27 July 2021, Ellis terminated the contract by notice of termination to Mr
Lavis.11
5 Signed plans marked ‘Attachment 2’ and ‘Attachment 3’ to Ms Wheatley’s statement.
6 Ibid, at ‘Attachment 4’.
7 A photo of the base stage as completed is marked ‘Attachment 6’ to Ms Wheatley’s statement.
8 Ibid, at ‘Attachment 5’.
9 Ibid, at ‘Attachment 7’.
10 Ibid, at ‘Attachment 8’.
11 Ibid, at ‘Attachment 9’.
-- 4 of 7 --
5
(k) On 4 August 2021 solicitors sent a letter of demand to Mr Lavis demanding
payment of the invoice and further costs, including legal costs of $800.00.12
Ms Wheatley’s evidence is uncontested and, in any event, supported by the documents
tendered with her statement. I accept her evidence in full.
Is Ellis entitled to payment of the progress claim?
I am satisfied that Ellis is entitled to payment of the progress claim because:
(a) The base stage was completed in accordance with the contract.
(b) Clauses 11.6 and 11.7 require Mr Lavis to pay Ellis for the base stage works
within five business days of receiving an invoice for the claim.
(c) The claim was invoiced on 8 April 2021 in the sum of $63,041.25, which is the
fixed price payable for that stage contemplated in the contract.
(d) Mr Lavis has not paid the claim.
As Ellis has received from Mr Lavis the deposit of $21,013.75 and the contract was
terminated such that there will be no further claims, the deposit amount sets off the
sum claimed, for a net result requiring payment by Mr Lavis to Ellis of $42,027.50.
Damages
Pursuant to clause 21.3 of the contract, Ellis claims damages for loss of profit
quantified in the sum of $67,244.00 calculated as follows “using a reasonable industry
standard percentage for the contractor’s margin”:13
Contract Sum: $420,275.00
Less amounts already paid $ 21,013.75
Less invoice claim $ 63,041.25
Multiplied by 0.2 $ 67,244.00
The basic purpose of any award of damages is to restore an injured party to the
position they would have been in had the wrongful act not occurred: Robinson v
Harman [1848] Eng R 135; 1 Exch 850, 855:
The rule of the common law is, that where a party sustains a loss by reason of a
breach of contract, he is, so far as money can do it, to be placed in the same
situation, with respect to damages, as if the contract had been performed.
I accept that Ellis suffered a loss of profit on the basis that the full contract was not
completed by reason of Mr Lavis’ breach and inability to complete.
However, Ellis has not made adequate submissions or filed adequate evidence to
support its damages claim, despite an explicit opportunity given to it to do so by
directions made 15 December 2023.
12 Ibid, at ‘Attachment 10’.
13 Application for a domestic building dispute filed 13 August 2021.
-- 5 of 7 --
6
For example:
(a) The contract does not provide for a builder’s margin as Part A and Part B of the
Appendix have been left silent on point.
(b) Ellis has not filed any empirical evidence supporting the claimed percentage as
an industry standard builder’s margin.
(c) Ellis has not filed any evidence, by way of financial or accounting records or
other data to establish the profit it reasonably expected to make on the build.
(d) The contract having ended early, Ellis might reasonably have been expected to
commence another project sooner, or to otherwise redirect its resources (labour
and equipment) to other projects to mitigate its losses. Ellis did not lead any
evidence addressing this.
(e) Ellis not having to expend materials, equipment or resources to complete the
build would necessarily have resulted in some savings to it from expenses not
incurred. This has not been adequately addressed in submissions or evidence
filed, risk being that it might profit from an award of damages in the sum
claimed.
Whilst the rules of evidence are relaxed in the tribunal and the tribunal may inform
itself in any way it considers appropriate,14 it would amount to an error of law to make
a decision that is entirely unsupported by evidence.15
As I cannot, on balance, be sure that the sum claimed will place Ellis in the same
situation, with respect to damages, as if the contract had been performed by Mr Lavis,
and I do not have sufficient evidence that would enable me to calculate with a
reasonable degree of confidence what such a sum might be, the damages claim is
dismissed.
Interest
The contract provides that interest is payable at the rate of 10% on payments that are
outstanding five business days after they fall due.
Progress Claim Invoice 02148 was issued on 8 April 2021 and expressed to be payable
within seven days, namely, by 15 April 2021. Less the deposit held by Ellis, the net
claim payable by Mr Lavis is $42,027.50.
I award interest on the net claim at 10% per annum from 16 April 2021 until today’s
date, 14 February 2024, being a period of 1,034 days, for a total of $11,901.34.16
Costs
Section 77(3)(h) of the QBCC Act empowers the tribunal to award costs in building
disputes, displacing the usual position in tribunal proceedings that each party bear
their own costs.
14 Queensland Civil and Administrative Tribunal Act 2009 (Qld), section 28(3)(b).
15 Australian Broadcasting Tribunal v Bond (1990) 170 CLR 321, 356.
16 $42,027.50 x 10%/365 days = $11.51 per day x 1034 days.
-- 6 of 7 --
7
As Ellis has been largely successful in these proceedings and was put to expense
running the claim where Mr Lavis was largely unresponsive, I see no reason to depart
from the parties’ contractual agreement on debt recovery costs.
The only evidence before me as to those costs is the demand for $800.00 for legal
costs incurred on the breach and termination and the $358.00 filing fee paid.
I award Ellis the sum of $1,158.00 for its costs in the proceeding.
Decision
The decision of the tribunal is that, within 21 days of the date of this order, Mr Lavis
must pay Ellis the sum of $55,086.84 comprising:
(a) Claim $42,027.50;
(b) Interest $11,901.34; and
(c) Costs $1,158.00.
-- 7 of 7 --