Body Corporate for Aurelia v Highlife Homes Pty Ltd [2024] QCAT 134
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Body Corporate for Aurelia CTS 55091 v Highlife Homes
Pty Ltd [2024] QCAT 134
PARTIES: BODY CORPORATE FOR AURELIA CTS 55091
(applicant)
V
HIGHLIFE HOMES PTY LTD
(respondent)
APPLICATION NO/S: BDL152-22
MATTER TYPE: Building matters
HEARING DATE: 12 February 2024
DELIVERED ON: 22 March 2024
HEARD AT: Brisbane
DECISION OF: Member Lember
ORDERS: The application for a domestic building dispute
filed 25 May 2022 is dismissed.
Any application for costs is to be made by filing in
the Tribunal two (2) copies and giving one (1) copy
of any submissions and evidence to be relied upon
to each other party by 4:00pm on 19 April 2024.
If an application for costs is made in accordance
with order number 2:
(a) the responding party is to file in the Tribunal
two (2) copies and give one (1) copy to the
party making the application any
submissions and evidence in response by
4:00pm on 3 May 2024; and
(b) the application will be determined on the
papers and without an oral hearing, not
before 4:00pm on 3 May 2024.
If no application for costs is made in accordance
with order number 2, there shall be no order as to
costs in this proceeding.
CATCHWORDS: TORTS – NEGLIGENCE – ESSENTIALS OF ACTION
FOR NEGLIGENCE – DUTY OF CARE – SPECIAL
RELATIONSHIPS AND DUTIES – OTHERS – building
and construction – where claim arises in negligence where
-- 1 of 16 --
2
there is no building contract between the parties - whether
subsequent body corporate owed a duty of care by builder –
whether subsequent body corporate was vulnerable -
whether building work was defective
Aquatec-Maxcon Pty Ltd v Barwon Region Water Authority
(No 2) [2006] VSC 117
Brookfield Multiplex Ltd v Owners Corporation Strata Plan
[2014] HCA 36
Body Corporate for Aurelia CTS 55091 v Highlife Homes
Pty Ltd [2023] QCAT 284
Bryan v Maloney (1995) 182 CLR 609
Canavan v Sutton [2020] QCAT 374
Donoghue v Stevenson [1932] AC 562
Graham Barclay Oysters Pty Ltd v Ryan [2002] HCA 54
Landman v Lauder & Anor [2018] QCAT 395
McSwan & Anor v Weaver [2023] QCAT 148
Ultramares Corporation v Touche (1931) 174 NE 441
Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004)
216 CLR 515
Body Corporate and Community Management Act 1997
(Qld) s 220, s 221, s 223, s 224
Civil Liability Act 2003 (Qld) s 7, s 9, schedule 2
Queensland Building and Construction Commission Act
1991 (Qld), s 43D, s 43E, s 47, s 77, schedule 2
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 100
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented by A and B van der Kwast (Body Corporate
committee members and lot owners).
Respondent: Self-represented by J George (director).
REASONS FOR DECISION
What is this application about?
Highlife Homes Pty Ltd (‘Highlife’) constructed a four-lot townhouse complex
(‘Aurelia’) for developer, AB Wilkinson Pty Ltd (‘Wilkinson’). Wilkinson sold the
townhouses off-the-plan to buyers whose interests are, effectively, represented in
these proceedings by the applicant Body Corporate for the Aurelia CTS 55091 (‘the
Body Corporate’). It is alleged by the Body Corporate that the concrete pathways and
driveway constructed by Highlife and forming part of the common property of the
Body Corporate, are defective and require rectification works.
The issue in this application is whether Highlife is responsible to the Body Corporate
for loss arising from defective building works.
By an application for a domestic building dispute filed 25 May 2022 the Body
Corporate asks the tribunal to order that Highlife pay it damages up to $27,880.00
-- 2 of 16 --
3
(being the highest quoted rectification costs),1 and its costs of the application,
including a filing fee and fees paid to their expert witness for an inspection, report,
and appearance at the hearing. Submissions on costs were not made at the hearing and
are called for in the directions made herein.
As Senior Member Brown observed in an interlocutory decision in Body Corporate
for Aurelia CTS 55091 v Highlife Homes Pty Ltd [2023] QCAT 284, the Body
Corporate did not have a contract with Highlife and, therefore, its claim lies only in
negligence. To succeed, the Body Corporate must establish that Highlife owed it a
duty of care, what the scope of that duty is, that Highlife breached that duty, the loss
caused by the breach and prove the loss.2
Highlife say that the building works are not defective, that any complaints about the
driveway are cosmetic in nature only and denies that it owed the Body Corporate a
duty of care because the Body Corporate was not ‘vulnerable’ to Highlife.
The parties came before me for a Tribunal Hearing on 12 February 2024. Evidence
was given by Mr and Mrs van der Kwast, for the Body Corporate, by Mr George for
Highlife and by expert witnesses, Mr Ferris (for the Body Corporate) and Mr
Carpenter (for Highlife Homes).
My decision, and the reasons for it, follow.
Is the application a “building dispute” over which the tribunal has jurisdiction?
Section 77 of the Queensland Building and Construction Commission Act 1991 (Qld)
(‘QBCC Act’) confers jurisdiction on the tribunal to hear building disputes.
A building dispute includes a “domestic building dispute”3 which, in turn, includes
(among other things) a claim or dispute in negligence, nuisance or trespass related to
the performance of reviewable domestic work other than a claim for personal
injuries.4
‘Reviewable domestic work’ means ‘domestic building work’,5 which includes work
comprising the erection or construction of a detached dwelling, which I am satisfied
the townhouses are.
As it is clear from the material filed, and not disputed by either party that the work the
subject of the claim is domestic building work, and that the claim against Highlife lies
in allegations of negligence with respect to that work. Therefore, I am satisfied that
the dispute the subject of the application is a ‘domestic building dispute’.
Section 77(2) qualifies the tribunal’s jurisdiction to hear building disputes by
stipulating that an application cannot be made to the tribunal unless the applicant “has
complied with a process established by the commission to attempt to resolve the
dispute”.
1 Affidavit of Jeannene Lovett sworn 27 October 2022 (Exhibit 4), Annexure 17.
2 Landman v Lauder & Anor [2018] QCAT 395 at [3].
3 QBCC Act, Schedule 2 (definition of “building dispute”).
4 Ibid, Schedule 2 (definition of “domestic building dispute”).
5 Ibid, Schedule 2 (definition of “reviewable domestic work”).
-- 3 of 16 --
4
A letter from the Queensland Building and Construction Commission (‘QBCC’) dated
19 May 20226 confirms that the requirements of section 77(2) have been met and that
the tribunal has jurisdiction to hear this dispute.
Factual background to the dispute
Building works by Highlife (contracted by Wilkinson)
Highlife and Wilkinson entered a Commercial Building Contract dated 21 December
2020 for the construction of the Aurelia project.7 That contract relevantly provided
that:
(a) In item 1 of the Schedule, read with clause 1, the “Principal” was Wilkinson and
its “administrators, permitted assignees and transferees”.
(b) In clause 8 read with clause 1, that Highlife will comply with all statutory
requirements for the building work.
(c) In clause 10.2 that Highlife warrants that it will carry out the work with
reasonable care and skill, in accordance with drawings and specifications, with
reasonable diligence and in accordance with all laws and requirements,
including the Building Act 1975 (Qld).
(d) In clause 20 read with item 10 of the schedule, that the during the defects
liability period of twelve months from the day following the date of practical
completion the Principal could give Highlife written notice of defects and
Highlife was required to rectify them.
(e) In clause 31.4 that neither party may assign the contract or any right, benefit,
obligation, or liability under it without the written consent of the other party.
On 4 February 2022, the City of Gold Coast (Council) deemed the practical
completion inspection unsatisfactory, requiring certain stormwater and drainage
works, asphalt patching and joins works, driveway frontages and other works to be
undertaken.8
A Form 11 Certificate of Occupancy issued on 22 February 2022.9
The practical completion defect works were undertaken such that on 25 July 2022, the
property passed its reinspection.10
Sale Contracts between Wilkinson and lot owners
Each buyer entered a contract with Wilkinson to purchase their respective townhouse
lot in the Aurelia complex, once constructed. Not all contracts are in evidence, but
the Lovett contract (lot 4) was entered into on 5 May 2021,11 the van der Kwasts gave
evidence that each buyer purchased “pre-construction” and it is understood each
contract adopted the same or substantially similar terms.
6 Affidavit of Jeannene Lovett sworn 3 December 2022 (Exhibit 3).
7 Affidavit of James George sworn 28 November 2022 (Exhibit 9).
8 Ibid.
9 Ibid.
10 Ibid.
11 Affidavits of Jeannene Lovett sworn 16 June 2022, Annexure 1 (Exhibit 8).
-- 4 of 16 --
5
Relevantly, those terms included:12
(a) In clauses 4.4(3) that the Body Corporate would be established by Wilkinson
prior to settlement and in clause 6.1(1) that settlement would be triggered,
among other things, by the establishment of the scheme creating the Body
Corporate.
(b) In clause 7.2 that Wilkinson was to repair any defects in the lot at its cost, on
notice given by the buyers within sixty days of the completion date.
(c) In clause 7.4, that the buyers could not require the seller to repair any defects in
the lot before completion, to delay completion pending repair of the defects, to
withhold any part of the sale price pending repair of the defects, or to claim
compensation other than the repair cost of any defect if the seller fails to rectify.
(d) In clause 7.5 that the architect retained by Wilkinson will act as an expert in any
dispute regarding lot defects and their decision will be final and binding on the
parties.
(e) In clause 7.7 that the seller’s warranties were as set out in the contract and in
section 223 of the Body Corporate and Community Management Act 1997 (Qld)
(‘BCCMA’) and record “the seller’s entire responsibility to the buyer in relation
to the property” and that “no other warranties or representations are express or
implied”.
The sale contracts were silent on the issue of the buyers’ rights regarding defects in
the common property, as opposed to their individual lot.
Sections 220 to 224 of the BCCMA deal with warranties that are implied in contracts
for the sale of proposed lots in a community title scheme and grants termination
rights that override the terms of a sale contract in the event of a breach of those
warranties.
Section 223 details the implied warranties as follows (emphasis added):
223 Implied warranties
(2) The seller warrants that, as at the date of the contract—
(a) to the seller’s knowledge, there are no latent or patent defects in the
common property or body corporate assets, other than the following—
(i) defects arising through fair wear and tear;
(ii) defects disclosed in the contract; and
(b) the body corporate records do not disclose any defects to which the
warranty in paragraph (a) applies; and
(c) to the seller’s knowledge, there are no actual, contingent or expected
liabilities of the body corporate that are not part of the body corporate’s
normal operating expenses, other than liabilities disclosed in the contract;
and
(d) the body corporate records do not disclose any liabilities of the body
corporate to which the warranty in paragraph (c) applies.
12 Affidavits of Jeannene Lovett sworn 16 June 2022 (Exhibit 8).
-- 5 of 16 --
6
(3) The seller warrants that, as at the completion of the contract, to the seller’s
knowledge, there are no circumstances (other than circumstances disclosed in
the contract) in relation to the affairs of the body corporate likely to materially
prejudice the buyer.
Examples for subsection (3)—
1 An administrator has been appointed under the order of an adjudicator under the
dispute resolution provisions.
2 The body corporate has failed to comply with the provisions of this Act to the
extent that its affairs are in disarray, records are incomplete and there is no
reasonable prospect of the buyer finding out whether the warranty mentioned in
subsection (2)(b) has been breached.
(4) For subsection (2), a seller is taken to have knowledge of a matter if the
seller has actual knowledge of the matter or ought reasonably to have
knowledge of the matter.
The defects did not exist at the contract date, and it cannot be said that the defects best
summarised at paragraph [61] are matters likely to materially prejudiced the buyers,
and, therefore, the implied warranties in section 223 of the BCMA were not breached
by Wilkinson in the course of the sale.
Settlement of Sale Contracts
Mr Wilkinson did not attend the hearing. He gave written evidence that:13
(a) He was “very happy with the end result of this project”.
(b) He understands that the development was completed to a “good standard as all
necessary milestones were met” and all final approvals and certificate from
relevant consultants including builders, engineers and Council were received.
(c) There were some minor defects that the buyers requested attention to during the
pre-handover stage, but these were attended to by Highlife prior to settlement
occurring and, as far as he was aware, there was no evidence whatsoever of any
major defects or issues.
(d) In January 2022, Mr and Mrs Lovett conducted a pre-purchase inspection and
contacted Mr Wilkinson afterwards to advise that they were not happy with the
finish of the driveway. They requested that Highlife redo the driveway to a
better standard.
(e) By 6 February 2022, three of the four buyers had undertaken pre-purchase
inspections and given a list of rectifications to Wilkinson.
(f) On 6 February 2022, Highlife declined to Wilkinson to redo the driveway,
stating that it was within necessary standards and tolerances.
(g) Mr and Mrs Lovett, “continued to insist that [Wilkinson] do something about
the driveway for the next few months”.
(h) On 25 February 2022, Mr Lovett sent an email in which he states, among other
things, that:
13 Affidavit of Alex Wilkinson sworn 25 November 2022 (Exhibit 11).
-- 6 of 16 --
7
This property was handed back to the developer in the middle of
December. We are now at the end of February; one would think that
ample time to rectify any issues.
I approach Mr Wilkinson’s evidence regaling the quality of the concreting work with
a measure of caution because:
(a) he concedes that he has “a very limited development/construction experience
with this in fact being my first project”; and
(b) he “relied heavily on the building Highlife Homes and all the consultants I
engaged for guidance”; and
(c) his location interstate and COVID-19 border closures and lockdowns restricted
his ability to visit the site. It is not clear that he ever, in fact, inspected the
property after the driveway works had been undertaken.
However, to the extent Wilkinson gives evidence of the pre-purchase inspections by
and discussions with the lot owners, it is consistent with the evidence given by those
lot owners, via the Body Corporate in these proceedings.
It is also noted that Wilkinson controlled the Body Corporate from the date the scheme
was established until after the lot owners settled their purchase contracts. He took no
steps as the Body Corporate during that time to make demand upon Highlife to rectify
their work, because he did not consider the work to be defective.
The Body Corporate’s evidence
Lot owners
The Lovetts gave evidence that Wilkinson was made aware of defects in the driveway
in December 2021,14 supported by text messages exchanged around 23 December
2021 with Wilkinson’s agent, Mr Yu wherein they raise concerns about works,
including the driveway.
On 19 January 2022, Mr Lovett received an email from Mr Smith, Hanson Concreting
who had inspected the driveway and observed that “the finish is poor with varying
levels of exposure across the length of the driveway”. Mr Smith suggested that
“honing or covercrete would be the only options available to enhance the appearance”.
Nitin Kumar (lot 2) gave evidence that they attended the property on 25 April 2022
for a pre-purchase inspection of the property, walking through the house and the
driveway and “all seemed ok”. However, following settlement and a period of rain,
the driveway began collecting/pooling water and random rust marks appeared.15
Dearne Dragicevic (lot 1) gave evidence that they purchased the property on 6 May
2022 and observed that “the driveway is poor, varying in colour throughout, holds
water, uneven in parts, rust marks starting to appear, with all the recent rain we have
had”.16
The van der Kwasts (lot 3) took possession of their lot on 13 May 2022. They gave
evidence that prior to possession they had temporary access to the property and
considered the driveway to the property to be “only just adequate and sound”. Since
14 Affidavit of Jeannene Lovett sworn 3 December 2022 (Exhibit 3).
15 Affidavit of Jeannene Lovett sworn 16 June 2022 (Exhibit 8).
16 Ibid.
-- 7 of 16 --
8
taking possession, they have seen a significant deterioration in the quality and
standard of the driveway, including discolouration, ponding, and rust marks.
The van der Kwasts also gave evidence that lot owners were not provided with a copy
of the building contract between Highlife and Wilkinson until June 2022.
Finally, the van der Kwasts spoke for the lot buyers in saying that they were due to
settle on the lots, originally, in around November 2021 but were delayed several
months. They were “living out of suitcases” and “homeless” because of project
delays. They feel the driveway and concreting were “rushed through” as the last
portion of work for the project. Each lot owner did building inspections and raised
concerns about common property defects and the situation became “very messy and
complicated” and involved what they described as “ducking and weaving” by
Wilkinson and his agents.
Expert evidence of Mr Tilney
Mr Tilney is a concreter of over 30 years’ experience. Following an inspection of the
driveway he wrote a letter dated 14 September 2022 in which he observed the
following:
1. Inconsistent colour and the levels of wash off for exposed concrete. Not
matching each pour.
2. The falls are incorrect to the water pits, as they are holding water and not
going into the pits. Will need to have concrete removed to re-lay concrete to
allow the correct falls for water to go into pits. Due to the poor workmanship, I
would suggest a camera be put down the pits to ensure the stormwater is not
blocked by slurry from the wash off of Exposed Concrete.
3. In-consistent saw cuts and width of the cuts. These cuts should be all the
same width to be pleasing to the eye.
4. Joint sealing is recommended to rectify these cuts to be more consistent with
each other.
5. The quality of the job in general is unsatisfactory, and the standard of the
prep work needs to be looked into to ensure the base has been prepped to the
engineers’ requirements. I would suggest an x-ray to ascertain thickness and
steel size and if construction joints are in the correct positions as per the
Engineers details.
6. The quality of this job is very poor workmanship, and I assume a Licence
would be held by the Concretor who did this job. I believe this Concretor should
not hold a licence due to the very poor standard of work on this job.
7. The builder should have stopped work on this prior to the additional pours
on the job. This would have alleviated the mess it now is, and a new Contractor
should have been engaged to rectify the job, before it went any further. You
could see from the first pour of concrete, it was not a great job. The owner has
paid for an Australian Standard build, and this is not in the standard. It should
be rectified, and a new Contractor appointed to complete to the Australian
Standards. A very poor job in my opinion. I would be disappointed if this job
was completed for me as a home builder.
Mr Tilney was not made available to give evidence or be cross-examined at the
hearing.
-- 8 of 16 --
9
Expert evidence of Mr Ferris
Mr Ferris is the general manager/ building inspector for K-Spec Building Consultants.
He holds a QBCC Residential Building Inspectors licence, a Cert IV in Building and
Construction and a QBCC Building Supervisors licence in addition to other
qualifications. On 24 October 2022 he inspected the pathways and driveway following
a period of prolonged rain.
Among other things Mr Ferris states in his report that:
(a) There are inconsistencies to the surface of the exposed aggregate across all areas
of the concrete including pathways, such inconsistencies not being typical of a
licenced tradesperson in Queensland. Photographs showing inconsistencies in
exposed finish included at paragraph 1.14 of the report:
(b) Whilst the variations in consistency will not affect the serviceability or intended
use of the area, it is reasonable to assume that it will lead to accelerated
deterioration of the surface and potential for ongoing maintenance.
(c) Water ponding and undulations could pose a potential safety hazard to
residents/pedestrians and should be addressed.
(d) The construction joint in the centre of the drive between the front and rear
boundary has viable signs of concrete spatter and footprints, indented 6mm to
8mm and holding water in the initial stages of the inspection.
(e) Isolation joints to lots 1, 2, 3 or the driveway to kerb and channel junction were
not observed, and only partially identified to the rear courtyard of lot 1 per
requirements of AS3727.1:2016 Part 5.4.3.
-- 9 of 16 --
10
(f) The driveway pavement control joints have been installed and are performing,
with no evidence of significant cracking identifiable a the time of inspection.
Any fine cracking identified did not exceed the tolerations outlines in AS2870-
2011 table C2.
(g) Given the general coverage of defective surface and incorrect or missing
isolation joints, it is recommended that remedial works be considered
reasonable, with the best option being and cover and conceal to all exposed
concrete throughout the site.
On cross-examination Mr Ferris conceded the following:
(a) AS3727.1:2016 is not part of the Building Code or NCC.
(b) AS2870-2011 does not apply to driveway slabs and only applies to residential
slabs and footings. In referring to that standard in his report, his intention was
to simply to indicate that the minor cracking observed did not even exceed
tolerations in that higher, albeit not applicable standard.
(c) There is no structural cracking and, structurally, the driveway is “very good”,
which is why he was not advocating to remove and to re-lay the driveway.
(d) The potential for trip or slip hazards arising from the driveway and concreting
work was “unlikely” and there was a “slim chance” of a safety hazard, but still
a chance.
Highlife’s evidence
Mr George
Mr George had little evidence to offer, other than to rely on the evidence of Mr
Wilkinson, Mr Carpenter and his cross-examination of Mr Ferris.
Expert evidence of Mr Carpenter
Mr Carpenter is a ‘Defects and Quality Expert” at Datum Building Consultancy Pty
Ltd. He holds QBCC licenses for Residential Building Inspection – Nominee
Supervisor, Builder – Open - Site Supervisor, and Builder - Medium Rise - Nominee
Supervisor.
His report17 was prepared following a fifteen-minute site inspection, during a period
of rain, and when vehicles were parked on and, therefore, partially obscuring the
driveway.
In Mr Carpenter’s opinion:
(a) The appearance of the concrete surface of the driveway has defects which
include water ponding mainly in two areas, and cosmetic defects in other areas
across the surface.
(b) The defects are “cosmetic and minor” when assessed in relation to, for example,
the QBCC Rectification of Building Work Policy.
(c) There is no suggestion or evidence the driveway is not performing its intended
function.
17 Exhibit 2.
-- 10 of 16 --
11
(d) There is no evidence to support the proposition that the concrete will degrade
over time or to cause ongoing maintenance, except for that normally expected
(for example, periodic washing).
On cross-examination Mr Carpenter said that:
(a) The fifteen-minute timeframe of his inspection was sufficient for him to walk
the area ‘two to three times’ and he considered he spent enough time to assess
the surface of the concrete, particularly given that he was armed with Mr Ferris’
report, including his measurements and the photographs he took.
(b) His inspection took place eighteen months after Mr Ferris’ and that this was
ample time for him to observe deterioration, if there was going to be any.
(c) There are no structural defects in the driveway, and only minor cosmetic
concerns.
(d) Ponding water is a ‘major issue” and the footprints and tool indentations should
have been attended to by the concreter prior to handing over the works as they
were defects caused by inattention and indifference in the laying process by the
concreters themselves.
(e) However, the ponding will not have a health and safety impact and will not
impact the life of the driveway - it is a mere nuisance only. Nor will it ever
worsen to be a trip hazard, including by the build-up of mould, because typical
maintenance and cleaning would attend to that risk.
Did Highlife owe the Body Corporate a duty of care?
At common law a duty of care will generally arise when the defendant should have
foreseen that their conduct could result in injury to the plaintiff.18
The Civil Liability Act 2003 (Qld) (‘CLA’) must be applied to all civil claims for
damage to property or economic loss where a duty of care is alleged. Schedule 2 of
the CLA defines relevant terms as follows:
(a) “Damages” is defined as including any form of monetary compensation;
(b) “Duty” includes a duty of care in tort, under contract that is concurrent and
coextensive with a duty of care in tort or duty under statute;
(c) “Duty of care” means a duty to take reasonable care or to exercise reasonable
skill (or both duties); and
(d) “Harm” means harm of any kind, including damage to property and economic
loss.
Though not codifying the common law,19 the CLA restates common law principles,
with some modifications.
It is well-established that the relationship of a professional licensed builder to a
homeowner client is a category of relationship where a duty of care is owed because
18 Donoghue v Stevenson [1932] AC 562.
19 7(5) of the Civil Liability Act (2003).
-- 11 of 16 --
12
it is reasonably foreseeable that if care is not taken by the builder the client is likely
to suffer loss and damage.20
In determining whether a builder owes a duty to subsequent owners the current
approach of the High Court begins with the test of reasonable foreseeability of harm,
followed by a consideration of ‘salient factors’.21
Foreseeability of harm
There is a high probability of needing to rectify defective building work if care is not
taken in the build, therefore, the out-of-pocket costs of undertaking those rectification
works is a reasonably foreseeable economic loss arising from defective building work.
However, where a purchaser under a contract of sale can negotiate or exercise a
contractual right to protect itself from potential loss under the terms of the contract
with the seller, it is difficult to see how a likelihood of economic harm to the
purchaser, caused by the original builder, can arise.
Salient factor: Vulnerability
Vulnerability has emerged as an important requirement in cases where a duty of care
to avoid economic loss has been held to have been owed. Vulnerability considers not
what the person who suffers harm did, but what they could have done, to protect
themselves, with a balance to be struck between “the traditional cornerstone of
foreseeability and commercial realities”.22
As to the vulnerability of subsequent purchasers:
(a) In Bryan and Maloney (1995) 182 CLR 609 (‘Bryan’) it was affirmed that a
builder owed the first owner a duty of care to avoid economic loss of [defects
in construction, and that it may be (and in that case was) liable in negligence for
damages to a subsequent purchaser.
(b) In Woolcock Street Investments Pty Ltd v CDG Pty Ltd [2004] HCA 16
(‘Woolcock’) the question was whether a consulting engineer owned a duty of
care to the subsequent owner of a warehouse which was found to suffer from
substantial structural distress. There was no evidence that the subsequent
purchaser could not protect itself, but rather that it had not done anything to
protect itself (no warranty from the vendor obtained about the structural
integrity of the building, no assignment of the vendor’s rights against the
builder, no pre-purchase inspection).
The capacity of a party to protect themselves from damage by contractual means
was said to be one – but often a decisive – reason for rejecting the existence of
a duty of care in tort for cases of economic loss.
(c) In Brookfield Multiplex Ltd v Owners Corporation Strata Plan [2014] HCA 36
(‘Brookfield’) the NSW Court of Appeal had held that Brookfield as the builder
which had contracted with a developer to design and construct a strata-titled
serviced apartment building owed a duty to exercise reasonable care in the
construction of the building to avoid causing the subsequent body corporate to
20 Canavan v Sutton [2020] QCAT 374 at paragraph [44].
21 Graham Barclay Oysters Pty Ltd v Ryan [2002] HCA 54 at [149].
22 Aquatec-Maxcon Pty Ltd v Barwon Region Water Authority (No 2) [2006] VSC 117 at [267].
-- 12 of 16 --
13
suffer economic loss because of latent defects in the common property. On
appeal, the High Court of Australia found that where:
(i) Brookfield had negotiated a sophisticated contract with the developer
including detailed provisions for dealing with defects and limiting
liability; and
(ii) the standard form contract of sale to purchasers of the serviced apartments
conferred on each subsequent purchaser of the units’ specific contractual
rights against the developer in relation to defects in the property for a
specified period of time,
there was no duty of care to avoid pure economic loss flowing from latent
defects owed by Brookfield to the developer or to the subsequent owners of each
of the apartments.
The High Court in Brookfield also found that there was no independent duty of
care owed to the body corporate, distinguishing Bryan because the subsequent
purchasers and the body corporate did not suffer from the same vulnerability as
the original owner or subsequent purchasers in Bryan. Specifically, the
existence of contracts that expressly provided for the promised quality of works
and the consequences of failure to meet it demonstrated that the parties had the
ability to protect their own interests against the consequences of defective work.
(d) In McSwan & Anor v Weaver [2023] QCAT 148, applying Woolcock and
Brookfield, the Tribunal found that in circumstances where the owners failed to
protect themselves by reducing their agreement with the builder to writing,
which would have provided them with the benefit of statutory warranties, there
was no duty of care for pure economic loss.
Highlife say that:
(a) The Body Corporate and its lot owners had contracts with Wilkinson, not
Highlife. The communication they had with Wilkinson, pre and post settlement
of their contracts is in evidence. Highlife handed over the project to Wilkinson
who then went on to settle the contracts, after Wilkinson, for a time, controlled
the Body Corporate.
(b) Wilkinson when acting as the Body Corporate did not enforce rights under its
contract with Highlife because it does not consider the contract to have been
breached.
(c) Vulnerability to the Brookfield standard requires a party to be incapable of
protecting themselves, and it was up the lot owners to do their own inspections
and pursue their contractual rights arising from them, if any, against Wilkinson.
The Body Corporate submit that Brookfield is distinguished from their situation
because:
(a) the chain of events in the lead up to the discovery of defects was different,
(b) the parties involved were different, and
(c) the terms of the contracts between parties were different.
In this case:
-- 13 of 16 --
14
(a) The lot owners purchased ‘off the plan’ knowing that Wilkinson was not the
builder and that a builder had been engaged by Wilkinson to construct the
property according to the disclosed plans and specifications.
(b) The sale prices, exceeding $800,000 were not modest – the van der Kwasts gave
evidence that they had “paid good money” for the properties – this attributes a
level of sophistication to the buyers.
(c) The lot owners were legally represented in the purchases although it is not
known which lot owners had advice on the contracts before the signed them and
what the nature of that advice was, if sought. Certainly, they had an opportunity
prior to signing their purchase contracts to seek advice, to ask to see the building
contract between Wilkinson and Highlife and to negotiate terms.
(d) The lot owners were aware, from the plans and body corporate disclosures, that
the construction of the building involved the creation of a body corporate,
common property, and a scheme to manage that.
(e) The lot owners were aware that building defects were a risk, because their
contracts made provision for a process to follow upon discovery of defective
building work in their lots.
(f) The lot owners could have, but did not, negotiate similar protections for defects
in the building work to common property, despite knowing that clause 7.6 of
the contract applied only to their lot and not to common property, and despite
having been referred to implied warranties in section 223 of the BCCMA which
ought to have turned the buyers’ minds to seeking extended warranties to protect
them.
(g) Nothing in their contract with Wilkinson assigned Wilkinson’s rights under the
building contract to the lot owners or to the Body Corporate and this too ought
to have been considered and addressed in the terms of their contract. The QBCC
decided not to direct Highlife to rectify the defects. The reason given for their
refusal was because the defects were noticed before the settlement and purchase
of the lots.
Unlike cases like Bryan where the defect was latent and undiscoverable by inspection,
the driveway and concreting defects identified as defective building works were not
latent and each lot owner settled their lot purchased with actual notice of the common
property defects.
The Body Corporate existed prior to settlement of the sale contracts. Under the control
of Mr Wilkinson, it was happy with the standard of the building works. The Body
Corporate under the subsequent control of the purchasing lot owners was not.
I am bound to adopt the High Court’s view in Woolcock and Brookfield that it is the
capacity of a party to protect themselves from damage by contractual means that
defines vulnerability and not what it did do that is relevant. The current case is not
distinguished from Brookfield and is in fact analogous to it.
This factor weighs heavily against a finding that Highlife owed the Body Corporate a
duty of care.
-- 14 of 16 --
15
Salient factor: The harm suffered
Parts of the driveway and pathways are not acceptable to the Body Corporate in
appearance and finish, but the experts agree that:
(a) the driveway is fit for purpose,
(b) the driveway is unlikely to result in a safety hazard,
(c) the missing isolation joint, if it is missing, is not a requirement under the
Building Code of Australia,
(d) the driveway is in good structural condition, and
(e) the cosmetic defects are not likely to impact the durability of the driveway.
The Body Corporate in closing submissions disagreed with their expert and insisted
that the driveway is not fit for purpose, the defects are not merely cosmetic and the
defects the durability and the safety of the driveway.
Given their independence, their overriding obligation to assist the Tribunal23 and their
relevant experience, I accept the evidence of Mr Ferris and Mr Carpenter and find that
the defect is cosmetic in nature only, and that the driveway is fit for purpose, not
unsafe, durable and in a good structural condition.
The minor, cosmetic nature of the ‘harm’ does not weigh in favour of finding a duty
of care exists.
Salient factor: Assumption of liability and known reliance upon skills
In Bryan it was noted that “by virtue of superior knowledge, skill and experience in
the construction of houses, it is likely that a builder will be better qualified and
positioned to avoid, evaluate and guard against the financial risk posted by latent
defects in the structure of a house”.24
Importantly, the current circumstances are distinguished because the defects were not
latent – the buyers purchased with actual knowledge of the defects, and they were
obvious almost immediately after the poured concrete set. They also entered off-the-
plan contracts with capacity to negotiate terms to specifically address the foreseeable
risk of common property building defects.
These factors weigh against a finding that Highlife assumed liability to, or knowledge
that subsequent owners would rely upon its skills as a builder, as opposed to
contractual rights they had, or could have negotiated with Wilkinson.
Salient factor: Relationship of proximity between the parties
The Court in Bryan was satisfied that the connection between a builder and a
subsequent owner of a property – whilst it may be limited only to the “house itself”25
– nonetheless was marked by proximity in several respects, noting that:
The connecting link of the house is a substantial one. It is a permanent structure
to be used indefinitely and, in this country, is likely to represent one of the most
23 Practice Direction 4 of 2009: Expert Evidence.
24 At [19] per Mason CJ, Deane and Gaudron JJ.
25 Ibid at [16] per Mason CJ, Deane and Gaudron JJ.
-- 15 of 16 --
16
significant, and possibly the most significant, investment which the subsequent
owner will make during his or her lifetime.
When…economic loss is eventually sustained and there is no intervening
negligence or other causative event, the causal proximity between the loss and
the builder’s lack of reasonable care is unextinguished by either lapse of time
or change of ownership.26
There might be, on that basis, to be a relationship of proximity between the parties to
this proceeding that weighs in favour of a finding of duty of care, but for the reference
to “intervening negligence” in the nature of the buyers failing to secure contractual
terms protecting themselves against the risk.
Salient factor: Indeterminacy of liability
As suggested in Bryan several policy considerations may mitigate against the finding
of a duty of care where the loss is economic and in particular:
…the law’s concern to avoid the imposition of liability “in an indeterminate
amount for an indeterminate time to an indeterminate class”.27
It was also noted by Justice Toohey that:
..particularly in the area of non-dangerous defects...as time goes on it may be
more difficult to show that the defect was the result of negligence and not of
wear and tear or factors not associated with the standard of construction.28
These factors weigh against a finding that the Body Corporate is owed a duty of care
by Highlife.
Decision
I am not satisfied, applying Woolcock and Brookfield and considering the salient
factors relevant to these parties – placing particular weight on the issue of
vulnerability (or lack thereof) – that Highlife owed the Body Corporate a duty of care
to protect it from economic loss and I find, accordingly, that it did not.
As this is a necessary cornerstone to a finding of negligence, the application must fail.
Costs
Section 77(3)(h) of the QBCC Act empowers the tribunal to award costs in building
disputes, displacing the usual position in tribunal proceedings that each party bear
their own costs.29
Having said that, the applicant was the only party to apply for costs and their
application has not succeeded. To that end, unless an application for costs is made and
a decision made awarding costs pursuant to directions, there will be no order as to
costs in this proceeding.
26 Ibid.
27 At [7] per Mason CJ, Deane and Gaudron JJ citing Ultramares Corporation v Touche (1931) 174 NE
441 at 444 per Cardozo CJ.
28 At [28].
29 Section 100, Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2024/134