Dixonbuild Pty Ltd v QBCC [2024] QCAT 39
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Dixonbuild Pty Ltd v QBCC [2024] QCAT 39
PARTIES: DIXONBUILD PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
SCOTT NEWTON
(second respondent)
APPLICATION NO/S: GAR329-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 30 January 2024
HEARING DATE: 10 November 2023
HEARD AT: Brisbane
DECISION OF: Member Howe
ORDERS: Dixonbuild Pty Ltd pay the costs of the Queensland
Building and Construction Commission thrown
away by the adjournment of the hearing on 10
November 2023 on the District Court scale on a
standard basis.
The Queensland Building and Construction
Commission file in the Tribunal and serve a copy on
Dixonbuild Pty Ltd of its claimed costs of
adjournment with such copies of accounts, fee notes
and other material as support the claim by 13
February 2024.
Dixonbuild Pty Ltd file in the Tribunal and serve a
copy on the Queensland Building and Construction
Commission any submissions in reply by 27
February 2024.
The issue of such costs, including fixing the costs if
possible, shall be determined on the papers
thereafter.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – COSTS – whether
costs of adjournment should be paid – where evidence in the
form of an affidavit sworn the day before hearing raising a
-- 1 of 6 --
2
fresh issue in the review proceedings – where an
adjournment granted to the Commission – where two
opposing parties claimed costs of the adjournment against
the other – where the Commission had been taken by
surprise – where the builder had opportunity to raise the
evidence and lead the evidence well before hearing but had
not – where the Commission was entitled to the costs of
hearing thrown away because of the adjournment – where
costs should be fixed but could not be fixed – where
directions made to file material in support of the claim for
costs
Queensland Building and Construction Commission
Regulation 2018 (Qld), s 2
Stainton v Footlong Subs Employment Services Pty Ltd
[2011] QCAT 186
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] In 2013 Dixonbuild Pty Ltd (‘the builder’) contracted with then owners of land near
Brisbane to build them a house. The work was completed by September 2014. Those
owners sold the house to Mr Newton in 2017.
[2] Mr Newton claimed there were a number of things wrong with the house and he
complained to the builder. One problem was a drainage problem. The builder engaged
engineers to attend and investigate. This was in 2019. The engineers reported that 4
gully traps noted on the original drainage plans had not been installed.
[3] The builder engaged a plumber, Mr Scully, to attend the site on about 20 May 2020.
It seems Mr Scully installed 4 gully traps. Despite that, at or about that time Mr
Newton complained to the QBCC about 69 items of defective work, two of which
concerned the drainage problem.
[4] The QBCC inspected the work onsite which now included the presence of gully traps.
The QBCC issued the builder with a direction to rectify the drainage problem, which
was identified as defective building work.
[5] That has prompted the builder to commence the within review proceedings in the
Tribunal hoping to set aside the direction to rectify defective building work.
[6] The matter came on for hearing on 10 November 2023 but has been adjourned on the
application of the QBCC. Both the builder and the QBCC seek costs thrown away by
the adjournment. Mr Newton has not made any application for costs of the
adjournment. Mr Newton is not legally represented in the proceedings and it is
doubtful he has claimable legal costs.
[7] The review application was listed for hearing over two days. On the morning of the
first day of hearing, counsel for the builder tendered in evidence four affidavits
-- 2 of 6 --
3
deposed to by the builder’s managing director. The fourth (‘exhibit 4’) was sworn the
day before hearing and had only been served on the QBCC the day before hearing.
[8] The solicitor representing the QBCC objected to the affidavit being admitted into
evidence.
[9] The affidavit purports to show what is entitled a purchase order/subcontract agreement
from Mr Scully the plumber to the builder. It is not clear who prepared the document.
It is dated 20 May 2020. It says little about the work Mr Scully did onsite or was asked
to do. It does not mention the 4 gully traps he apparently installed on that date, nor the
excavation work associated with that. Its significance is apparently the cost claimed
for the work done by Mr Scully which is the amount of $500.50 including GST.
[10] Counsel for the builder made clear that the builder’s position will be that the value of
the defective work the subject of the direction to rectify is below the threshold value
for construction work to be building work (subject to directions to rectify) as provided
by s 2 of Schedule 1 of the Queensland Building and Construction Commission
Regulation 2018 (Qld).
[11] The affidavit also exhibits “the original site cost extension” which the managing
director swears “shows the site-specific extras included for the build at the site
address.” There is no mention of field gullies in that document.
[12] The solicitor representing the QBCC objected to the affidavit on the basis it had only
been received at 4.28pm the afternoon before the hearing commenced despite the
builder having since end March 2022 to comply with Tribunal directions to file and
serve statements of evidence. By directions dated 17 March 2022 the parties had been
directed by the Tribunal to file final statements of evidence by end of March 2022. In
particular, the builder had been directed to file its last statement of evidence on 31
March 2022. It complied (though late) by filing a statement of evidence on 5 April
2022, which was the affidavit tendered as Exhibit 3 at the hearing on 10 November
2023.
[13] By direction 4 of the directions of the Tribunal made 17 March 2022 the parties were
advised that no party would be allowed to present any evidence at the hearing not
contained in the statements, or material already filed, without justifying the need for
such additional evidence to the Tribunal.
[14] There was no attempt made to justify the need for the 4th affidavit of the managing
director prior to its tender.
[15] At a directions hearing on 17 April 2023, a member confirmed with the parties that
all material had been filed and the matter was otherwise ready for hearing. The
solicitor for the QBCC and Mr Newton verbally agreed that was the case and a
solicitor appearing for the builder voiced no contradiction.
[16] In his opening, Counsel for the builder identified 3 issues to be resolved by the tribunal
as follows: that any defect associated with the drainage was not a structural defect and
the time to issue a direction to rectify had expired when it was issued; the
circumstances prevailing made it unfair for the QBCC to issue any direction to rectify;
and, and the main issue relied on by the builder was that the building work identified
as defective, was not ‘building work’ within the meaning of that term used in the
legislation.
-- 3 of 6 --
4
[17] The solicitor for the QBCC said the issue about the value of the work being less than
the threshold amount was new, it had not been raised before, and QBCC would need
to consider the matter; instructions would have to be taken and the QBCC would have
to assess the value of the work done.
[18] The builder says the QBCC building inspector involved in this matter should
reasonably have known that the value of Mr Scully’s work to install field gullies
would be less than $3,300.
[19] Mr Newton, himself a builder, said he doubted the amount claimed in the purchase
order was true or accurate. He thought the amount of $500.50 for the work done by
Mr Scully was too cheap.
[20] Apart from that, it seems clear that another issue potentially arising from this and not
addressed by either party is whether Mr Scully’s work installing 4 gully traps (and
associated trenching and levelling) was new work as claimed by the builder or
building work within the scope of the original construction contract, and if the latter
whether the $3,300 threshold was relevant.
[21] Counsel for the builder said the QBCC had always had to prove that the work
concerned was building work. The QBCC knew that was an issue and knew that for
some time. In that sense, claims the builder, it is the builder who has suffered prejudice
in that the QBCC never explained in its statements of evidence how the work was
‘building work’. Hence the builder was obliged to obtain the evidence about the value
of the work to show that the work did not fall within the $3,300 threshold.
[22] This does not explain why the builder failed to file and serve its evidence about the
cost of the work being less than $3,300 much earlier than the afternoon prior to
hearing.
[23] Insofar as Counsel suggests the issue about the drainage work, the subject of the
direction to rectify not being ‘building work’ because it had a value less than $3,300,
had been raised, directly or indirectly, before tendering the affidavit exhibiting the
purchase order, I cannot agree.
[24] Neither the purchase order nor the claim that the cost of the building work had a value
less than the threshold amount of $3,300 had ever been raised by either party until the
morning of hearing. The purchase order says nothing about gully traps, and indeed its
relevance to proving the drainage work, which arguably at least concerns the work
putting in the gully traps, cost less than $3,300 is not clear on the face of the document.
[25] In the initial application for review the builder submits the direction to rectify should
be set aside for a number of reasons, but not because the claimed value of the defective
work is less than $3,300.
[26] By the affidavit of the managing director of the builder, Exhibit 1, the issue of the
drainage work not being building work was expressly addressed under a heading
“Building work”. The submission was limited to field gullies not being a mandatory
drainage requirement for the building nor connected to the building’s drainage system,
and that the direction to rectify should be understood to address the height of the turf
laid on top of the drainage trenches for the gully traps, which was not building work
as defined in the QBCC Act.
[27] That position was repeated in the further affidavits of the managing director, Exhibits
2 and 3.
-- 4 of 6 --
5
[28] The claim that the value of the work done by Mr Scully was less than the threshold
minimum of $3,300 was never raised as an issue in the proceeding until the morning
of hearing.
[29] The new issue is significant if established. If accepted it would prove determinative
in favour of the builder. It should have been raised much earlier than the day of the
hearing.
[30] There are no pleadings in the Tribunal identifying and limiting the issues in dispute
in a proceeding. The issues are derived from the statements of evidence.
[31] In Stainton v Footlong Subs Employment Services Pty Ltd [2011] QCAT 186, Senior
Member Endicott said:
[9] It is a (sic) obligation of the tribunal under section 28(3)(e) of the
Queensland Civil and Administrative Tribunal Act 2009 to ensure that all
relevant material is disclosed to the tribunal to enable it to decide the proceeding
with all the relevant facts. For this reason directions are made for the filing of
witness statements and documents to be relied on before the hearing of a
proceeding. Parties are expected to take active steps to engage in a proceeding
and have a specific duty in section 45 of the Queensland Civil and
Administrative Tribunal Act 2009 to act quickly in any dealing relevant to the
proceeding.
[10] The tribunal controls the hearing process not the parties. The tribunal will
not permit evidence being withheld and produced only at a hearing by a
party. Disclosure of the evidence in support of a matter is required to be made
well before a hearing so that no party is taken by surprise or rendered at a
disadvantage at the hearing.
[32] The QBCC says the builder has failed to comply with the directions of the Tribunal
to file its statements of evidence by 31 March 2022. In result the QBCC was taken by
surprise with the new claim about the building work being less than the $3,300
threshold. I accept that is the case. I accept it was reasonable for the QBCC to request
an adjournment to address this new issue.
[33] I determine it is in the interests of justice to award the QBCC its costs thrown away
as a result of the adjournment, and those costs should be paid by the builder.
[34] The builder has acted in a way that unnecessarily disadvantaged both respondents.
The hearing has been further delayed with the adjournment, and the respondents
inconvenienced.
[35] There is no explanation offered by the builder why the late evidence was so late. The
purchase order/subcontract is dated 20 May 2020 and the site costs extension
document dates back to the time of the original construction contract.
[36] There is no issue about the decision maker not affording natural justice to the applicant
builder in considering whether or not a costs order is called for.
[37] The QBCC seek an award of costs on the standard basis on the District Court scale.
That seems appropriate. By s 107 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld), if I make a cost order I should fix the costs if possible. I
cannot fix the respondents’ costs of adjournment thrown away now, as there are no
particulars of the costs claimed and there is no supporting material evidencing the
-- 5 of 6 --
6
costs claimed. I shall give directions for the parties to file submissions and supporting
material to that end.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2024/039