Aurizon Network Pty Ltd v Queensland Competition Authority & Anor (No 2) [2023] QSC 210
SUPREME COURT OF QUEENSLAND
CITATION: Aurizon Network Pty Ltd v Queensland Competition
Authority & Anor (No 2) [2023] QSC 210
PARTIES: AURIZON NETWORK PTY LTD
ACN 132 181 116
(applicant)
v
QUEENSLAND COMPETITION AUTHORITY
(first respondent)
QUEENSLAND RESOURCES COUNCIL LTD
ACN 050 486 952
(second respondent)
FILE NO/S: SC No 837 of 2023
DIVISION: Trial Division
PROCEEDING: Application as to costs
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 15 September 2023
DELIVERED AT: Brisbane
HEARING DATE: Heard on the papers. Applicant’s written submissions filed
7 August 2023; first respondent’s written submissions filed
11 August 2023; second respondent’s written submissions
filed 11 August 2023.
JUDGE: Kelly J
ORDER: 1. The applicant pay the respondents’ costs of and
incidental to the originating application filed
20 January 2023 to be assessed on the standard basis.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – GENERAL RULE:
COSTS FOLLOW EVENT – COSTS OF AND
INCIDENTAL TO PROCEEDING – where the applicant filed
an originating applicating seeking declaratory relief concerned
with the construction of an access undertaking – where the
originating application was dismissed – where the parties
provided written submissions on costs – where the applicant
accepts that it should pay the second respondent’s costs –
where the applicant contends that there should be a departure
from the usual rule that costs follow the event in respect of the
first respondent’s costs – where the applicant contends that the
extent of the first respondent’s participation in the proceeding
was unnecessary and inappropriate – where the applicant
contends that the first respondent should bear its own costs in
-- 1 of 3 --
2
the proceeding or that the applicant should be ordered to pay
only a small proportion of the first respondent’s costs –
whether the applicant should pay the respondents’ costs of and
incidental to the originating application to be assessed on the
standard basis
Aurizon Network Pty Ltd v Queensland Competition
Authority & Anor [2023] QSC 167, related
R v Australian Broadcasting Tribunal; Ex Parte Hardiman
(1980) 144 CLR 13; [1980] HCA 13, cited
COUNSEL: S A McLeod KC, with M R Wilkinson, for the applicant
J M Horton KC, with E L Hoiberg, for the first respondent
C Schneider, for the second respondent
SOLICITORS: Quinn Emanuel Urquhart & Sullivan for the applicant
Clayton Utz Lawyers for the first respondent
Herbert Smith Freehills for the second respondent
[1] Aurizon Network applied by way of originating application for declaratory relief
concerned with the construction of an access undertaking (“UT5”). On 28 July 2023,
I dismissed the originating application and published reasons.1 I directed the parties
to provide written submissions in relation to costs. These are my reasons in relation
to that issue. I have adopted defined terms from my earlier reasons.
[2] As between Aurizon Network and QRC, there is no issue about the appropriate costs
order. Aurizon Network accepts that it should pay QRC’s costs of and incidental to
the originating application to be assessed on the standard basis.
[3] In relation to the QCA’s costs, Aurizon Network submits that there should be a
departure from the usual rule that costs follow the event and that the QCA should bear
its own costs of the proceeding or Aurizon should be ordered to pay only a small
proportion of the QCA’s costs. Essentially, Aurizon Network submits that the extent
of the QCA’s participation in the proceeding was unnecessary and inappropriate.
[4] The originating application identified the QCA as a respondent. In addition to the
declaratory relief sought, Aurizon Network sought costs against each respondent.
Aurizon Network filed Points of Claim2 which alleged that matters relevant to the
interpretation of UT5 included background facts and circumstances known to all
parties including the respondents. The QCA filed evidence in the proceeding
disputing its alleged state of knowledge.3 At the hearing, Aurizon Network abandoned
its contention that UT5 fell to be interpreted by reference to the alleged background
facts.4 In making that concession, Aurizon Network accepted as correct, written
submissions filed by the QCA as to the proper approach to the interpretation of UT5
as a statutory instrument.5
1 Aurizon Network Pty Ltd v Queensland Competition Authority & Anor [2023] QSC 167.
2 Points of Claim filed 23 March 2023.
3 Affidavit of Paul Gold filed 3 May 2023 [11], [14], and [18]–[19].
4 T1-5.45-50.
5 T1-6.5-10.
-- 2 of 3 --
3
[5] In my consideration, given that its state of mind was placed into issue by the Points
of Claim, the QCA acted reasonably in filing evidence. The evidence it filed was
essentially limited to its state of mind, the procedures which it had followed and the
documents which were before it at the time of its determination. The submissions
made by the QCA were substantively concerned with the correct approach to the
construction of UT5. Ultimately, those submissions were adopted as correct by
Aurizon Network and QRC. Further, the QCA’s conduct did not infringe the principle
identified in R v Australian Broadcasting Tribunal; Ex Parte Hardiman.6 In the
present case, there was no prospect of any subsequent proceeding or the matter being
remitted back to the QCA for further decision. In relation to the QCA’s costs, I am
unable to discern any proper reason for departing from the usual rule that costs should
follow the event.
Order
[6] The order as to costs is that Aurizon Network pay the respondents’ costs of and
incidental to the originating application to be assessed on the standard basis.
6 (1980) 144 CLR 13 at 35–36.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2023/210