Aurizon Network Pty Ltd v Queensland Competition Authority & Anor [2023] QSC 167 [2023] 32 QLR
SUPREME COURT OF QUEENSLAND
CITATION: Aurizon Network Pty Ltd v Queensland Competition
Authority & Anor [2023] QSC 167
PARTIES: AURIZON NETWORK PTY LTD
ACN 132 181 116
(applicant)
v
QUEENSLAND COMPETITION AUTHORITY
(first respondent)
QUEENSLAND RESOURCES COUNCIL LTD
ACN 050 486 952
(second respondent)
FILE NO/S: SC No 837 of 2023
DIVISION: Trial Division
PROCEEDING: Hearing
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 28 July 2023
DELIVERED AT: Brisbane
HEARING DATE: 14 June 2023
JUDGE: Kelly J
ORDERS: 1. The originating application filed 20 January 2023 is
dismissed.
2. I will hear the parties as to costs.
CATCHWORDS: INTERPRETATION – GENERAL RULES OF
CONSTRUCTION OF INSTRUMENTS – GENERAL
MATTERS – where the applicant operates the Central
Queensland Coal Network (‘the Network’) under long term
leases granted by the State of Queensland – where an access
undertaking for the Network was approved by the first
respondent under s 138 of the Queensland Competition
Authority Act 1997 (Qld) – where the applicant seeks a
declaration as to the meaning of the term ‘Report Date’
contained in clause 12.1 of the access undertaking – where the
first respondent determined the Report Date to be 14 March
2022 – where the applicant contends that the proper
construction of the Report Date is 12 November 2021 – where
the application is resisted by the first and second respondents
– whether the Report Date, properly construed, is 14 March
2022 or 12 November 2021
-- 1 of 49 --
2
INTERPRETATION – GENERAL RULES OF
CONSTRUCTION OF INSTRUMENTS – GENERAL
MATTERS – where the applicant also seeks declaratory relief
to the effect that the first respondent erred in law by adopting
14 March 2022, rather than 12 November 2021, as the Report
Date for the purpose of calculating the ‘Revenue Adjustment
Amount’ in the context of the annual review of ‘Reference
Tariffs’ under the access undertaking – where the application
is resisted by the first and second respondents – whether the
first respondent erred in adopting 14 March 2022 as the Report
Date for this purpose
Acts Interpretation Act 1954 (Qld), s 14A, s 148
Queensland Competition Authority Act 1997 (Qld), 69E, 99,
100, 133, 134, 136, 136, 138, 142, 150A, 158A, 250
Statutory Instruments Act 1992 (Qld), s 7, s 15
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory
Revenue (2009) 239 CLR 27; [2009] HCA 41, cited
LCA Marrickville Pty Ltd v Swiss Re International SE (2022)
290 FCR 435; [2022] FCAFC 17, cited
COUNSEL: S A McLeod KC, with M R Wilkinson, for the applicant
J M Horton KC, with E L Hoiberg, for the first respondent
J C Sheahan KC, with C Schneider, for the second respondent
SOLICITORS: Quinn Emanuel Urquhart & Sullivan for the applicant
Clayton Utz Lawyers for the first respondent
Herbert Smith Freehills for the second respondent
TABLE OF CONTENTS
An application for declaratory relief ................................................................................ 3
Background matters ........................................................................................................... 3
A declared service ............................................................................................................ 3
The access undertaking for the Network ........................................................................ 4
An overview of UT5 and its material clauses ................................................................... 5
Objects, Access and Capacity .......................................................................................... 5
“Report Date” .................................................................................................................. 6
Part 7A: Capacity ............................................................................................................ 7
Relevant events following the approval of UT5............................................................ 15
The real issues in dispute ................................................................................................. 15
Applicable interpretation principles ............................................................................... 16
Aurizon Network’s arguments ........................................................................................ 18
Consideration .................................................................................................................... 19
-- 2 of 49 --
3
The pure question of construction ................................................................................ 19
Did the Preliminary Report provide the requisite notification? .................................. 25
Orders ................................................................................................................................ 28
An application for declaratory relief
[1] This proceeding is concerned with the proper construction of an access undertaking
(“UT5”)1 approved by the first respondent (“the QCA”) under the Queensland
Competition Authority Act 1997 (Qld) (“the Act”).2 The applicant (“Aurizon
Network”) has applied by way of originating application for declaratory relief. There
are two aspects to the declaratory relief. The first declaration concerns the meaning
of the term “Report Date” as contained in cl 12.1 of UT5. Aurizon Network contends
that, according to its proper construction, the Report Date was 12 November 2021,
not 14 March 2022 as determined by the QCA. The second declaration is to the effect
that, in the context of the annual review of “Reference Tariffs” under UT5,3 on
15 December 2022, the QCA erred in law by adopting 14 March 2022, rather than
12 November 2021, as the Report Date for the purpose of calculating a sum known
as the “Revenue Adjustment Amount”4. The application is resisted by the QCA and
the second respondent (“QRC”).
Background matters
A declared service
[2] Aurizon Network operates the Central Queensland Coal Network (“the Network”)
which comprises five “Coal Systems”5 linking approximately 40 mines railing coal
to five export terminals at three major ports. Aurizon Network operates the Network
under long term leases granted by the State of Queensland.
[3] The Coal Systems comprise:
(a) the Moura system, which links the Moura mine to Gladstone;
(b) the Blackwater system, which connects the Gregory and Rolleston mines to
Gladstone;
(c) the Goonyella system which connects the Gregory, North Goonyella and
Blair Athol mines to the port of Hay Point;
(d) the Newlands system which links the Newlands mine to the port of
Abbot Point; and
(e) the Goonyella to Abbot Point system.
1 UT5 is a reference to “Aurizon Network 2017 access undertaking (UT5)” dated 19 December 2019.
2 The approval of an access undertaking by the QCA is provided for by s 138 of the Act.
3 Exhibit 5, p 317.
4 Exhibit 5, pp 270, 321 and 361 (sch F, cl 4.3).
5 The term “Coal System” is referenced in the Act, s 250(1)(a).
-- 3 of 49 --
4
[4] The use of the Network for providing transportation by rail is a declared service under
the Act.6 Access to declared services is the subject of Part 5 of the Act. The object of
Part 5 is expressed as being to:7
“Promote the economically efficient operation of, and use of and
investment in, significant infrastructure by which services are
provided, with the effect of promoting effective competition in
upstream and downstream markets.”
[5] Two important mechanisms facilitate the regulation of access to a declared service,
access undertakings and access agreements.
[6] An access undertaking is a written undertaking setting out the terms on which the
owner or operator of the service undertakes to provide access to the service.8 Access
undertakings are dealt with in Div 7 of Pt 5 of the Act. The QCA may require an
owner or operator of a declared service to give the QCA a draft access undertaking
for the service.9 An owner or operator of a declared service may also voluntarily
submit to the QCA a draft access undertaking or a draft amendment to an existing
access undertaking.10 In either case, the QCA must consider the draft undertaking, or
draft amendment, and must approve or refuse to approve the draft.11 If the QCA
refuses to approve the draft, the QCA must give the owner or operator notice requiring
the draft to be amended and resubmitted.12 Upon being approved by the QCA, an
access undertaking binds the owner or operator of the declared service13 and is
enforceable by either the QCA or any person who considers that their interests have
been adversely affected by a breach of the undertaking.14
[7] An access agreement is relevantly an agreement between an access provider of a
declared service and another person providing for access to the service by the other
person.15 Access agreements are dealt with in Div 4 of Pt 5 of the Act. An owner or
operator of a declared service must, if requested to do so, negotiate with an entity who
seeks access to that service for the purpose of making an access agreement in relation
to the service.16 Subject to some exceptions, in negotiating access agreements, the
owner or operator of the declared service must not unfairly differentiate between
access seekers.17
The access undertaking for the Network
[8] On 30 November 2016, in response to an earlier notice issued by the QCA, Aurizon
Network submitted to the QCA a draft access undertaking for the Network for the
period commencing 1 July 2017 and ending 30 June 2021 (“the 2017 Draft Access
Undertaking”). On 6 December 2018, the QCA did not approve, and requested the
6 Queensland Competition Authority Act 1997 (Qld), s 250 (‘the Act’).
7 Ibid, s 69E.
8 Ibid, sch 2 “access undertaking”.
9 Ibid, s 133.
10 Ibid, ss 136 and 142.
11 Ibid, ss 134(1), 136(4) and 142(2).
12 Ibid, ss 134(2), 136(5) and 142(3).
13 Ibid, s 150A; see also the definition of “responsible person” in sch 2.
14 Ibid, s 158A.
15 Ibid, sch 2.
16 Ibid, s 99.
17 Ibid, s 100.
-- 4 of 49 --
5
amendment of, the 2017 Draft Access Undertaking. On 18 February 2019, Aurizon
Network submitted an amended version of the 2017 Draft Access Undertaking, which
the QCA approved on 21 February 2019. Upon approval, that draft became UT5.
[9] On 3 May 2019, Aurizon Network submitted to the QCA a draft voluntary
amendment to UT5 (“the 2019 Draft Amendment”). On 25 November 2019, the QCA
approved the 2019 Draft Amendment subject to certain amendments. On 4 December
2019, a revised version of the 2019 Draft Amendment was submitted to the QCA. On
19 December 2019, the QCA approved that version, which is the version of UT5 the
subject of this proceeding.
An overview of UT5 and its material clauses
Objects, Access and Capacity
[10] Clause 2.2 expresses the objective of UT5 as including to:
(a) ensure that the declared service is provided in a manner that does not unfairly
differentiate between access seekers or users in a way that has a material
adverse effect on the ability of one or more of the access seekers or users to
compete with other access seekers or users;18
(b) prevent Aurizon Network recovering through the price of access to the declared
service, any costs that are not reasonably attributable to the provision of that
service;19
(c) apply the provisions of the Act through the establishment of processes for
“Access” negotiations and the utilisation of “Capacity” that are expeditious,
efficient, timely, flexible, commercial and non-discriminatory;20
(d) apply the provisions of the Act through the establishment of processes and
principles to provide guidance in relation to the pricing, and the terms and
conditions, of Access;21
(e) provide that UT5, and actions taken under it, are consistent with the objectives
and provisions of the Act.22
[11] The concepts of “Access” and “Capacity” are the subject of specific definitions within
UT5. “Access” is, essentially, the non-exclusive utilisation of a specified section of
the rail infrastructure for the purpose of operating train services.23 “Capacity”
references a number of concepts24 but, fundamentally, is concerned with the number
of “Train Paths” that can be provided within each system, including the mainline and
branch line of each system.25 A “Train Path” is the occupation of a specified portion
of the rail infrastructure.26
18 Exhibit 5, p 160, cl 2.2 (a) read with the Act, s 137(3).
19 Exhibit 5, p 160, cl 2.2(b).
20 Exhibit 5, p 160, cl 2.2(d).
21 Ibid.
22 Exhibit 5, p 160, cl 2(f).
23 Exhibit 5, p 263.
24 Exhibit 5, p 274 (Capacity), p 291 (Existing Capacity), p 391 (Planned Capacity), p 263 (Absolute
Capacity).
25 Exhibit 5, p 263.
26 Exhibit 5, p 331.
-- 5 of 49 --
6
[12] Access to the Network is governed by the access agreements entered between
Aurizon Network and third-party access seekers.27 UT5 regulates the price which an
access seeker can be required to pay to Aurizon Network for access under an access
agreement. Access charges are calculated in accordance with Reference Tariffs
stipulated in UT5.28 The Reference Tariffs are adjusted annually29 by reference to,
among other things, a “Revenue Adjustment Amount”. Each financial year, Aurizon
Network is required to recover from, or return to, Access Holders the Revenue
Adjustment Amount, which comprises the difference between revenue earned
(referred to as “Total Actual Revenue”) and revenue allowed (referred to as “Adjusted
Allowable Revenue”).30 The “Adjusted Allowable Revenue” sum is calculated by
reference to, inter alia, the “Approved WACC” applicable during that year.31 The
prevailing amount of the Approved WACC bears upon the amount of the access
charges which Aurizon Network may levy upon current Access Holders and seek to
impose on new access seekers.
[13] The Approved WACC is defined as follows:32
“Approved WACC The post-tax nominal (vanilla) weighted average
cost of capital calculated as follows:
(a) from 1 July 2017 until the Initial Date 5.7% p.a.;
(b) from the Initial Date until the Report Date, 5.9%
p.a.;
(c) from the Report Date (where occurring prior to the
Reset Date), 6.3% p.a.;
(d) from the Reset Date until the Terminating Date,
the Reset WACC.”
[14] An event which triggers a change in the value of the Approved WACC is the
occurrence of the “Report Date”. Upon the occurrence of that event, the Approved
WACC increases from 5.9% to 6.3%.
“Report Date”
[15] The expression “Report Date” is defined as:33
“The date on which the last of the following events has occurred:
(a) the Independent Expert has provided the Initial Capacity Assessment
Report to Aurizon Network and the Chair of the Rail Industry Group; and
(b) Aurizon Network notifies the Chair of the Rail Industry Group of the
proposed options for addressing any Existing Capacity Deficits identified
in the Initial Capacity Assessment Report, provided that where the Initial
Capacity Assessment Report does not identify any Existing Capacity
Deficits, Aurizon Network will be deemed to have satisfied the
notification requirement in this paragraph (b) on the date that the Initial
27 Exhibit 5, p 166, cl 4.1(a) and p 196, cl 5.1(a).
28 Exhibit 5, p 201, cll 6.2.2 and 6.2.3.
29 Exhibit 5, p 355, sch F, cl 4.
30 Exhibit 5, p 361, sch F, cl 4.3.
31 Exhibit 5, sch F, cl 4.3(c)(i).
32 Exhibit 5, p 270.
33 Exhibit 5, p 319.
-- 6 of 49 --
7
Capacity Assessment Report has been provided in accordance with
paragraph (a).”
[16] The definition of Report Date includes several defined terms, namely:
(a) “Independent Expert” is defined as “The Independent Expert appointed under
clause 7A.3.1.”
(b) “Initial Capacity Assessment Report” has “the meaning given to that term in
clause 7A.4.1(g).”
(c) “Rail Industry Group” is a “forum of End Users” with its membership being
open to “all End Users, Access Seekers and Railway Operators”
(c) “Chair of the Rail Industry Group” is defined as “Such person as may (sic)
appointed as the chair of the Rail Industry Group from time to time and advised
to Aurizon Network and the QCA in writing.”
(d) “Existing Capacity Deficit” has “the meaning given to that term in clause
7A.5(a).”
Part 7A: Capacity
[17] Part 7A of UT5 is entitled “Capacity”. The purpose of the part is to provide for the
independent and realistic assessment of “the Deliverable Network Capacity” of the
rail infrastructure in each of the Coal Systems and, separately, “the System Capacity”
of each of the Coal Systems. The Deliverable Network Capacity of the Rail
Infrastructure is defined by reference to the maximum number of “Train Paths” that
can be utilised in each Coal System and the mainline and each branch line of that
Coal System.34 System Capacity is defined by reference to the capacity of “the Supply
Chain” in its entirety, including the maximum number of Train Paths that can be
utilised in each Coal System, and the mainline and each branch line of that Coal
System.35 The expression “Supply Chain” is defined to mean all aspects that affect
the transportation of coal from a mine to the end customer, including loading
facilities, Rail Infrastructure, Railway Operators, load out facilities and coal export
terminal facilities.36
[18] Clause 7A.3 contemplates the appointment of an Independent Expert. The provisions
of cl 7A.3 are set out in their entirety in Annexure A to these Reasons. The
contemplated appointment is a joint appointment by Aurizon Network and a group of
“End Users”.37 The Independent Expert is to be independent and impartial and
supported by suitably qualified and experienced personnel. Once appointed, the
Independent Expert is responsible for conducting various Capacity Assessments
under cl 7A.4 and determining rebates payable under cl 7A.6. The Independent
Expert’s costs are recoverable as a component of the Reference Tariff.
[19] Clause 7A.4 describes the procedures by which the Independent Expert is to conduct
the various Capacity Assessments and report on those assessments to the QCA and
34 Exhibit 5, p 205, cl 7A.2(a).
35 Exhibit 5, p 206, cl 7A.2(b).
36 Exhibit 5, p 326.
37 Exhibit 5, p 288 “End User” is defined as “Each Access Holder (other than an Access Holder that
holds Access Rights for the purpose of providing Train Services for a Customer) and each Customer.
-- 7 of 49 --
8
stakeholders. The provisions of cl 7A.4 are set out in their entirety in Annexure A to
these Reasons. By way of broad overview, cl 7A.4 contemplates three types of
Capacity Assessments namely an IE Initial Capacity Assessment, Annual Capacity
Assessment and System Capacity Assessment.
[20] UT5 acknowledges that the Independent Expert will use its best endeavours,
supported by the good faith actions of Aurizon Network and the members of the Rail
Industry Group, to undertake the IE Initial Capacity Assessment as quickly as is
reasonably possible having regard to the nature of the assessment and the need to
undertake an assessment that is both realistic and accurate.38 Within 10 business days
of its appointment, the Independent Expert is to commence an “Initial Assessment of
the Deliverable Network Capacity of each Coal System for the Capacity Assessment
Period” (“IE Initial Capacity Assessment”).39 The Independent Expert is to develop
System Operating Parameters for each Coal System having regard to the way each
Coal System operates in practice and must ensure that those parameters consider the
Deliverable Network Capacity and not place Aurizon Network in breach of UT5 or
any Access Agreement.40
[21] Certain obligations are imposed on various parties in relation to the preparation of the
IE Initial Capacity Assessment. The Independent Expert is obliged to consult with
and seek submissions from Aurizon Network, Access Holders and Access Seekers
(and their Customers and Train Operators) and all Supply Chain Participants for each
Coal System. Aurizon Network is obliged to promptly do everything reasonably
requested by the Independent Expert to assist it in carrying out the IE Initial Capacity
Assessment, including providing or making available all information and materials
relevant to the Deliverable Network Capacity. The members of the Rail Industry
Group are also obliged to provide to the Independent Expert, information in relation
to the Deliverable Network Capacity.
[22] The IE Initial Capacity Assessment must include:
(a) a dynamic model reflecting how each Coal System operates in practice;
(b) the System Operating Parameters for each Coal System;
(c) consideration of the outcomes of any consultation, or information received, by
the Independent Expert;
(d) a report which:
(i) identifies the Independent Expert’s assumptions affecting the
Deliverable Network Capacity;
(ii) describes any constraints which have reduced or are likely to reduce the
Deliverable Network Capacity of each Coal System; and
(iii) where the Independent Expert has identified an “Existing Capacity
Deficit” with respect to a Coal System, specifies the Coal System and
location of the Existing Capacity Deficit, the quantum of the Existing
Capacity Deficit and, if a specific cause or cause of the Existing Capacity
Deficit has been identified, the Access Holders affected by the Existing
38 Exhibit 5, p 214, cl 7A.4.1(g).
39 Exhibit 5, p 210-11, cl 7A.4.1(a).
40 Exhibit 5, p 211, cl 7A.4.1(b).
-- 8 of 49 --
9
Capacity Deficit with “reasonable detail” about “solutions which could
effectively and efficiently address the Existing Capacity Deficit”.41
[23] An “Existing Capacity Deficit” arises where the IE Initial Capacity Assessment
reveals a “Deliverable Network Capacity Shortfall” in a relevant Coal System.42
A “Deliverable Network Capacity Shortfall” is “a circumstance where the
Deliverable Network Capacity of a Coal System within the relevant Capacity
Assessment Period is less than the number of Train Paths required to meet train
service entitlements (without regard to exclusions and access agreements for the non-
provision of train service entitlements)”.43
[24] The Independent Expert is required to make available to Aurizon Network and the
QCA44 and to the Chair of the Rail Industry Group,45 the outcomes of the IE Initial
Capacity Assessment including its assumptions affecting Deliverable Network
Capacity relied upon for the IE Initial Capacity Assessment (“the Initial Capacity
Assessment Report”) and the System Operating Parameters.46 The QCA has an
obligation to promptly publish on its website the Initial Capacity Assessment Report47
and the System Operating Parameters of each Coal System.
[25] Clause 7A.5 addresses the situation where the IE Initial Capacity Assessment reveals
an Existing Capacity Deficit and describes a structured process in response to that
revelation. The provisions of cl 7A.5 are set out in their entirety in Annexure A to
these Reasons.
[26] The structured process may be broadly outlined as follows.
[27] As the first step, within 20 business days after the Initial Capacity Assessment Report
is published on the QCA website, Aurizon Network is required to:
“ … submit a preliminary report to the QCA (and publish such preliminary
report … on the Website) setting out:
(A) Aurizon Network’s consultation plan (which, when followed,
must satisfy the requirements of clause 7A.5(a)(ii)); and
(B) Aurizon Network’s preliminary views on:
(1) the cause or causes of the Existing Capacity Deficit
(including a response, in reasonable detail, to the cause
or causes identified by the Independent Expert); and
(2) solutions which could most effectively (including cost
effectively) and efficiently address the Existing
Capacity Deficit (including a response, in reasonable
detail, to the solutions identified by the Independent
Expert); and
41 Exhibit 5, pp 212-214, cl 7A.4.1(f).
42 Exhibit 5, p 218, cl 7A.5.
43 Exhibit 5, p 286.
44 On an unredacted basis.
45 On a redacted basis.
46 Exhibit 5, p 214, cl 7A.4.1(g).
47 Exhibit 5, p 214, cl 7A.4.1(h) and (i); the publication on the website may be redacted to protect
confidential information of an Access Holder, Customer or Train Operator.
-- 9 of 49 --
10
(3) the indicative timeframe within which it considers
each of the solutions could reasonably be
implemented”.48
[28] As the second step, Aurizon Network is required to:
“… consult with End Users, Customers and Access Holders of the
relevant Coal System and Train Operators, to identify and consider:
(A) whether changes can be made to:
(1) the operation and maintenance practices for the Rail
Infrastructure;
(2) the operations of Rollingstock by Railway Operators;
(3) the operation and maintenance practices in respect of
load-out facilities,
including in relation to interfaces with all facilities
forming part of the relevant Supply Chains (as set out
in the assumptions affecting Deliverable Network
Capacity and included in the Initial Capacity
Assessment Report) in order to increase the
Deliverable Network Capacity of the relevant Coal
System, provided that such changes would be
consistent with the System Operating Parameters
included in the IE Initial Capacity Assessment (and
would not require an Access Holder to revert to the
requirements in an Access Agreement where that
Access Agreement has not been modified to make it
consistent with the new System Operating
Parameters);
(B) whether an Access Holder wishes to voluntarily relinquish
any of its Access Rights if it is entitled to do so under, and in
accordance with, a relinquishment provision in its Access
Agreement (without being required to pay a Relinquishment
Fee to Aurizon Network) with the Access Holder to specify
the maximum and minimum number of Access Rights that the
Access Holder would be willing to relinquish; and
(C) options for Expansions,
(collectively, the Transitional Arrangements),
which could effectively and efficiently address the Existing Capacity
Deficit or whether affected Access Holders and Customers would
prefer not to do anything to address the Existing Capacity Deficit.”49
48 Exhibit 5, p 219, cl 7A.5(a)(i).
49 Exhibit 5, p 219, cl 7A.5(a)(ii).
-- 10 of 49 --
11
[29] As the third step,50 within three months after the Initial Capacity Assessment Report
has been published by the QCA on its website, Aurizon Network is required to:
“…submit a detailed report to the QCA, the Chair of the Rail Industry
Group and the Independent Expert showing the outcome of Aurizon
Network’s analysis and consultation on the Existing Capacity Deficit
and the Transitional Arrangements which it considers would most
effectively and efficiently address the Existing Capacity Deficit,
including:
(A) whether any Access Holder is willing to, within 30 days,
voluntarily relinquish any of its Access Rights if it is entitled
to do so under, and in accordance with, a relinquishment
provision in its Access Agreement (without being required to
pay a Relinquishment Fee that would otherwise be payable as
a result of such relinquishment under its Access Agreement)
and the extent to which any voluntary relinquishment will
address (up to a maximum of) the Existing Capacity Deficit
in that Coal System). If multiple Access Holders wish to
relinquish Access Rights, then the voluntary relinquishment
will be apportioned pro rata up to a maximum of the Existing
Capacity Deficit in that Coal System;
(B) whether changes could be made to:
(1) the operation and maintenance practices for the Rail
Infrastructure;
(2) the operations of Rollingstock by Railway Operators;
(3) the operation and maintenance practices in respect of
load-out facilities,
including in relation to interfaces with all facilities forming
part of the relevant Supply Chains (as set out in the
assumptions affecting Deliverable Network Capacity and
included in the Initial Capacity Assessment Report) that could
increase the Deliverable Network Capacity of the relevant
Coal System, provided that such changes would be consistent
with the System Operating Parameters included in the IE
Initial Capacity Assessment (and would not require an Access
Holder to revert to the requirements in an Access Agreement
where that Access Agreement has not been modified to make
it consistent with the new System Operating Parameters),
including:
(4) the extent to which the proposed operational changes
will address the Existing Capacity Deficit;
(5) a reasonable estimate of the cost of such operational
changes to Aurizon Network and/or Customers and
Access Holders; and
50 Exhibit 5, p 220, cl 7A.5(a)(iii).
-- 11 of 49 --
12
(6) if relevant, evidence of Aurizon Network’s
consultation under clause 7A.5(a)(ii) that explains
why such changes cannot address the Existing
Capacity Deficit;
(C) if relevant, a shortlist of Expansions considered by Aurizon
Network and through the consultation under clause
7A.5(a)(ii) (including reasonable estimates of costs to
undertake each Expansion); and
(D) subject to clause 7A.5(c), any proposed Expansion which
Aurizon Network and the affected Access Holders or Access
Seekers have agreed will address the Existing Capacity
Deficit.”51
[30] One of the Transitional Arrangements involves “options for Expansions”.52 If
Aurizon Network and affected End Users agree that an Expansion is the most
effective and efficient option to address the Existing Capacity Deficit and End Users
wish to rectify the Existing Capacity Deficit, or if the QCA otherwise determines that
an Expansion is the most effective and efficient option to address the Existing
Capacity Deficit, it is left to the Independent Expert to review and approve the
efficiency and prudence of the proposed Expansion.53
[31] If Aurizon Network and affected End Users do not reach agreement as to “which of
the Transitional Arrangements should be implemented,”54 the Independent Expert
must review the detailed report provided by Aurizon Network under cl 7A.5(a)(iii)
and promptly make “a recommendation to the QCA with respect to which of the
Transitional Arrangements of the type referred to in clause 7A.5(a)(iii)(A) – clause
7A.5(a)(iii)(C) it considers will most effectively and efficiently resolve the Existing
Capacity Deficit ….”55 Within 15 days (or such longer period as may be required by
the QCA) of receiving the Independent Expert’s recommendation, the QCA must
“make a determination as to which of the Transitional Arrangements of the type
referred to in clause 7A.5(a)(iii)(A) – clause 7A.5(a)(iii)(D) will most efficiently and
effectively resolve the Existing Capacity Deficit …”.56 Aurizon Network must
comply with any determination made by the QCA including by doing “everything
reasonably necessary to implement the type of Transitional Arrangements determined
by the QCA in a prudent and diligent manner so as to resolve the Existing Capacity
Deficit as soon as reasonably practicable, having regard to the nature and type of
Transitional Arrangements required”.57
[32] Clause 7A.6 applies from the Report Date and describes a process by which
payments, described as Rebates, may be made to affected End Users. The provisions
of cl 7A.6 are set out in their entirety in Annexure A to these Reasons. The process
by which Rebates are determined may be outlined as follows. From the Report Date,
the Independent Expert is required to identify if there has been “an AN Performance
51 Exhibit 5, pp 220-221, cl 7A.5(a)(iii).
52 Exhibit 5, p 220, cl 7A.5(a)(ii)(C).
53 Exhibit 5, pp 221-223, cll 7A.5(c)(i)-(ii) and (i)(ii).
54 Exhibit 5, p 222, cl 7A.5(d).
55 Ibid.
56 Exhibit 5, p 222, cl 7A.5(e).
57 Exhibit 5, p 222, cl 7A.5(f).
-- 12 of 49 --
13
Shortfall” resulting from an “AN Performance Breach in that Relevant Year”. If there
has been, the Independent Expert must determine the “Performance Rebate Amount”
that Aurizon Network must58 pay an affected End User.
[33] To understand that process, it is necessary to have regard to the following definitions:
(a) “AN Performance Shortfall” is defined to mean:
“(a) In respect of the period between the Report Date and
the implementation of any Transitional Arrangements
to address any Existing Capacity Deficit, in respect of
each origin and destination combination specified in
an Access Holder’s Access Agreement and for that
period:
(i) the aggregate number of Train Service
Entitlements for the relevant origin and
destination combination for that period that the
Independent Expert determines could have been
utilised by the Access Holder having regard to
the IE Initial Capacity Assessment and any other
Access Holders affected by the Existing
Capacity Deficit (if any); less
(ii) the number of Train Service Entitlements for the
relevant origin and destination combination that
the Independent Expert determines were utilised
by the Access Holder during the relevant period.
(b) For all Years following the implementation of the
Transitional Arrangements, in respect of each origin
and destination combination specified in an Access
Holder’s Access Agreement and each Relevant Year:
(i) the aggregate number of Train Service
Entitlements specified in the relevant Access
Agreement for the relevant origin and
destination combination for the Relevant Year;
less
(ii) the number of Train Service Entitlements for the
relevant origin and destination combination that
the Independent Expert determines were utilised
by the Access Holder during the Relevant
Year.”59
(b) “AN Performance Breach” is defined to mean:
“(a) any breach by Aurizon Network of an obligation under
the Undertaking or any Access Agreement;
58 Subject to cll 7A.6(c) and (e).
59 Exhibit 5, p 268.
-- 13 of 49 --
14
(b) Aurizon Network acting inconsistently with the
Approved Maintenance Strategy and Budget,
Approved Renewals Strategy and Budget or Approved
Maintenance Approach other than where permitted by
clause 7A.11.3(q); or
(c) any failure by Aurizon Network (including by any
Aurizon Network Personnel) to comply with a System
Operating Parameter under its control,
except to the extent that any act or omission of Aurizon Network
under paragraphs (a) – (c) is directly attributable to the proper
performance, completion and/or implementation of any
Transitional Arrangements agreed to or determined under
clause 7A.5.”60
(c) “Performance Rebate Amount” is defined to mean:
“…. an amount calculated as follows:
PRA = A x R
Where:
PRA means Performance Rebate Amount (expressed in
dollars);
A means the AN Performance Shortfall for a Relevant Year
(expressed as a number of Train Service Entitlements) to the
extent attributable to an AN Performance Breach; and
R means the revenue from the Relevant Components of Access
Charges that Aurizon Network would have been entitled to earn
for the applicable Train Service Entitlement.”61
[34] Aurizon Network’s liability to pay a Rebate is not unqualified. Relevantly, the
liability is subject to and conditional upon the Access Holder and the End User:
(a) undertaking that the payment of the Rebate to the End User is, subject to certain
exceptions, “the sole right to compensation” and Aurizon Network is not
otherwise liable for any claim (whether based in contract or tort, under common
law or in equity or under statute), for any other loss or damage suffered or
incurred in respect of the Train Service Entitlements which were not provided
as a result of an AN Performance Breach;62
(b) in respect of the relevant Train Service Entitlement, not having commenced
any claim that would be in breach of such undertaking if the undertaking had
been given at the time the claim was commenced;63
60 Exhibit 5, p 267-268.
61 Exhibit 5, p 311.
62 Exhibit 5, p 225, cl 7A.6(c)(ii).
63 Exhibit 5, p 225, cl 7A.6(c)(iii).
-- 14 of 49 --
15
(c) agreeing as part of the undertaking not to set off any amounts due and payable
by the Access Holder or End User to Aurizon Network against the Rebate
payable by Aurizon Network to the Access Holder or End User.64
Relevant events following the approval of UT5
[35] On 27 October 2021, the Independent Expert made its Initial Capacity Assessment
Report (“the ICAR”) available to Aurizon Network, the QCA and the Chair of the
Rail Industry Group. The ICAR identified Existing Capacity Deficits in each of the
five Coal Systems within the Network.
[36] On 12 November 2021, Aurizon Network provided to the QCA and the Chair of the
Rail Industry Group, a report entitled “Aurizon Network’s Preliminary Report in
response to the Initial Capacity Assessment Report” (“the Preliminary Report”). The
Preliminary Report was the preliminary report contemplated by cl 7A.5(a)(i) of UT5,
save that, on the facts, it was submitted to the QCA and the Chair of the Rail Industry
Group, rather than just the QCA as contemplated by cl 7A.5(a)(i). Later in these
Reasons, I have dealt with some of the relevant content of the Preliminary Report.
[37] Following its delivery of the Preliminary Report, Aurizon Network conducted the
consultation process contemplated by cl 7A.5(a)(ii). On 14 March 2022, following
that consultation process, Aurizon Network submitted a detailed report as required by
cl 7A.5(a)(iii) (“the Detailed Report”).
[38] On 4 November 2022, Aurizon Network submitted its proposal for the Revenue
Adjustment Amount for the financial year 2022 which adopted a Report Date of
12 November 2021 (“the Revenue Adjustment Proposal”).
[39] In November and December 2022, Aurizon Network and the QRC made submissions
to the QCA about when the “Report Date” had occurred. In those submissions,
Aurizon Network contended that the Report Date was 12 November 2021 and QRC
contended that it was 14 March 2022.
[40] On 15 December 2022, the QCA issued a decision notice in response to the Revenue
Adjustment Proposal (“the QCA decision”).65 The relevant effect of the QCA
decision was that the QCA refused to approve the Revenue Adjustment Proposal and
required that the adjustment be calculated on the basis that the Approved WACC
increased from 5.9% to 6.3% on 14 March 2022.
The real issues in dispute
[41] This proceeding involves two principal issues.
[42] The first issue concerns what might be described as a pure question of construction.
That question may be framed as, is the “Report Date”, properly construed, a reference
to the date on which Aurizon Network submits the detailed report described by
cl 7A.5(a)(iii) of UT5 or is it a reference to the date of any communication from
Aurizon Network to the Chair of the Rail Industry Group by which Aurizon Network
notifies the proposed options for addressing any Existing Capacity Deficits identified
in the Initial Capacity Assessment Report?
64 Exhibit 5, p 225, cl 7A.6(c)(iv).
65 The QCA decision was made by the QCA under cl 4.3(s) of sch F to UT5.
-- 15 of 49 --
16
[43] The second issue arises if the construction question is answered so that the Report
Date is a reference to the date of any such communication as distinct from the date of
submission of the detailed report. In that event, there is a factual issue as to whether
the Preliminary Report was a communication from Aurizon Network to the Chair of
the Rail Industry Group by which Aurizon Network notified “the proposed options
for addressing the Existing Capacity Deficits identified in the Initial Capacity
Assessment Report”.
Applicable interpretation principles
[44] UT5 is a statutory instrument within the meaning of s 7 of the Statutory Instruments
Act 1992 (Qld) (“the Statutory Instruments Act”).66 The interpretation of UT5 is
governed by the Acts Interpretation Act 1954 (Qld) (“the Interpretation Act”), as
modified by the provisions of Pt 4 of the Statutory Instruments Act.
[45] The public character of an approved undertaking such as UT5 can be discerned from
the following circumstances:
(a) an approved access undertaking derives its legal force from the QCA’s
approval which is made pursuant to the Act;
(b) the matters to which the QCA must have regard in deciding whether to approve
an access undertaking, which include the public interest;67
(c) the Act obliges an owner or operator of a service to comply with an approved
access undertaking;
(d) an approved access undertaking may only be withdrawn with the approval of
the QCA;
(e) the purpose of an access undertaking is to serve as a charter of rights for access
seekers, current and future;
(f) the Act does not contemplate an approved access undertaking operating as a
contract but rather makes separate provision for an “access agreement” to be
negotiated between an access provider and an individual access seeker.
[46] Two matters are worth noting about the approach to the interpretation of UT5.
[47] First, it is not appropriate to have regard to extrinsic material such as the antecedent
negotiations or dealings about the instrument or the background facts known to
certain parties.68
[48] Secondly, the interpretation of UT5 which best achieves its purpose is to be preferred
to any other interpretation.69
66 Relevantly, UT5 is “made under” the Act because it derives its binding legal force from QCA’s
approval under the Act and it is a notification of a public nature or another instrument of a public
nature by which the entity making the instrument unilaterally affects a right or liability of another
entity.
67 The Act, s 138(2)(d).
68 Acts Interpretation Act 1954 (Qld) (‘the Interpretation Act’), s 148 (as modified by s 15 of the Statutory
Instruments Act 1992 (Qld) (‘the Statutory Instruments Act’)); Aurizon did not press its initial
submission that UT5 fell to be interpreted by reference to background facts known to the parties
involved in its negotiations: T1-5.45-T1-5.46.
69 The Interpretation Act, s 14A.
-- 16 of 49 --
17
[49] In Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue,70 the plurality
observed:
“... the task of statutory construction must begin with a consideration
of the text itself. Historical considerations and extrinsic materials
cannot be relied on to displace the clear meaning of the text. The
language which has actually been employed in the text of legislation
is the surest guide to legislative intention. The meaning of the text may
require consideration of the context, which includes the general
purpose and policy of a provision, in particular the mischief it is
seeking to remedy.”71 (footnotes omitted).
[50] It is uncontroversial that the text of UT5 is the starting point for the construction task.
Ultimately, the construction of the expression “Report Date” requires careful regard
to the text, in order to ascertain the meaning of the words used. In this regard, it is
necessary for the court to consider both the language of the clause, as well as the
commercial purpose and objects of the instrument as can be discerned from the text
of the instrument itself, read as a whole and in its statutory context.
[51] As to the requirement to read the instrument as a whole, in LCA Marrickville Pty Ltd
v Swiss Re International SE,72 Derrington and Colvin JJ (with whom Moshinsky J
agreed) relevantly said:
“[57] It is often identified as ‘trite law’ that the duty of a court when
construing a document is to discover its meaning by considering
it ‘as a whole’: Australian Broadcasting Commission v
Australasian Performing Right Association Ltd (1973) 129
CLR 99 at 109 per Gibbs J. The rationale is, as Gibbs J
observed, that “the meaning of any one part of it may be
revealed by other parts” and, as a corollary, “the words of every
clause must if possible be construed so as to render them all
harmonious one with another”. In Wilkie v Gordian Runoff Ltd
(2005) 221 CLR 522; (Wilkie v Gordian Runoff ), a majority of
the High Court observed that in construing a policy of
insurance, as with other instruments, ‘preference is given to a
construction supplying a congruent operation to the various
components of the whole’: at [16] citing Project Blue Sky Inc v
Australian Broadcasting Authority (1998) 194 CLR 355 at
[69]–[71]. Necessarily, the identification of that construction
can only be achieved by ascertaining how a contract or policy
might operate as affected by each of the competing
interpretations. This ‘iterative process’, involving ‘checking
each of the rival meanings against the other provisions of the
document and investigating its commercial consequences’,
‘enables a court to assess whether either party’s preferred legal
meaning gives rise to a result that is more or less internally
consistent and avoids commercial absurdity’: HP Mercantile
70 (2009) 239 CLR 27.
71 Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (2009) 239 CLR 27 at [47].
72 (2022) 290 FCR 435.
-- 17 of 49 --
18
Pty Ltd v Hartnett [2016] NSWCA 342 at [134] quoting Re
Sigma Finance [2010] BCC 40 at [12].
[58] In the interpretive process, the concept of reading a document
as a whole involves more than merely acquiring an awareness
of the surrounding and related provisions. It requires a
substantive intellectual process of evaluating the degree of
operative coherence and consistency between a proffered
construction and the instrument’s other terms…”73
Aurizon Network’s arguments
[52] Aurizon Network’s substantive submissions may be outlined as follows. The text of
UT5 is to be “construed commercially, having regard to the fact that it’s a public
document.”74 Adopting that approach, having regard to context and purpose, the
Report Date was 12 November 2021. The key question involved the meaning to be
given to the expression within the definition of Report Date, “Aurizon Network
notifies the Chair of the Rail Industry Group of the proposed options for addressing
any Existing Capacity Deficits identified in the Initial Capacity Assessment
Report…”. That expression was not tied to the preliminary report referred to in
cl 7A.5(a)(i) or the detailed report referred to in cl 7A.5(a)(iii). The inquiry was as to
when the Chair of the Rail Industry Group was notified of the proposed options. In
this case, notification was provided by the provision of the Preliminary Report, which
was objectively intended to notify preliminary views on “solutions which could most
effectively … and efficiently address the Existing Capacity Deficit”. The notification
of the preliminary views occurred in a context where the ICAR had identified “in
reasonable detail, solutions which could effectively and efficiently address the
Existing Capacity Deficit”75 and the Preliminary Report was required to respond, in
reasonable detail, to those solutions.76 The Preliminary Report as a matter of fact,
notified the proposed options that could most effectively and efficiently address the
Existing Capacity Deficits.
[53] The Report Date was said to not contemplate the notification being provided by the
detailed report referred to in cl 7A.5(a)(iii) for six reasons. First, cl 12.1 did not
specifically state that the Report Date was the date of submission of the detailed report
referred to in cl 7A.5(a)(iii).77 Secondly, “submitting” a detailed report was quite
different to “notifying” proposed options. Further, the detailed report contemplated
matters beyond “proposed options”. In this regard, “the proposed options”
contemplated by UT5 were not to be equated with “the Transitional Arrangements”.78
Thirdly, the purpose of “notifying” the Chair of the Rail Industry Group was to
provide the basis for the consultation required under cl 7A.5(a)(ii) which was to
precede the submission of the detailed report.79 Fourthly, treating the submission of
the detailed report as the Report Date would give rise to perverse incentives
inconsistent with the consultation obligation imposed by cl 7A.5(a)(ii). Rather than
undertaking that consultation in a considered and complete manner, Aurizon Network
73 LCA Marrickville Pty Ltd v Swiss Re International SE (2022) 290 FCR 435 at [57]-[58].
74 T1-5.46-48.
75 UT5, cl 7A.4.1(f)(v).
76 UT5, cl 7A.5(a)(i)(B)(2).
77 Applicant’s Outline of Submissions, [103].
78 Ibid, [104] to [111].
79 Ibid, [112].
-- 18 of 49 --
19
would be incentivised to complete the consultation and prepare a detailed report in “a
hurried or perfunctory fashion” so as to trigger the uplift in the WACC. It was
commercially sensible for the parties to have agreed on a mechanism that incentivised
Aurizon Network to propose “preliminary consultation options” with an onus then
falling on Aurizon Network “to perform in light of those new circumstances”.80
Fifthly, treating the date of the submission of the detailed report as the Report Date
was inconsistent with the terms and object of the Rebates in that it would hinder,
rather than promote, the timely and effective provision of Rebates to End Users.81
Finally, the commercial purpose of Pt 7A was relevantly said to be “to make
[Aurizon] Network’s entitlement to an increase in WACC dependent upon the
completion by [Aurizon] Network of an investigation that identified proposed options
to remedy any deficit (and which options were to be the subject of formal,
consultation, analysis and implementation), with any later poor performance by
[Aurizon] Network after that time subject to the payment by it of a penalty in the form
of the [Rebates].”82
Consideration
[54] I have dealt with the issues in turn.
The pure question of construction
[55] The critical language within the definition of “Report Date” is “Aurizon Network
notifies the Chair of the Rail Industry Group of the proposed options for addressing
any Existing Capacity Deficits identified in the Initial Capacity Assessment Report
...”. The text does not make specific reference to the detailed report referred to in
cl 7A.5(a)(iii). Aurizon Network emphasised that, had the contemplated notification
been intended to reference that detailed report, it would have been a simple thing for
the text to have made that clear. It was also noted that the definition of Report Date
utilised defined terms but did not make specific reference to the detailed report.
[56] It can be accepted that, as a matter of syntax, the critical language is not expressed in
terms of notification by “the detailed report referred to in cl 7A.5(a)(iii)”. However,
nor is that language expressed in terms of notification by “the preliminary report
referred to in cl 7A.5(a)(i)”, “the detailed report referred to in cl 7A.5(a)(iii) or the
preliminary report referred to in cl 7A.5(a)(i)” or “the detailed report referred to in
cl 7A.5(a)(iii), the preliminary report referred to in cl 7A.5(a)(i) or any other report”.
Language of that kind may have achieved perfect clarity. As it was not used, the Court
is left to ascertain the meaning of the words actually used, having regard to their
context and the purpose of the instrument.
[57] The text describes an event by which Aurizon Network notifies the Chair of the Rail
Industry Group “of the proposed options for addressing any Existing Capacity
Deficits identified in the Initial Capacity Assessment Report”. That event is
contemplated to occur in circumstances involving an unresolved Existing Capacity
Deficit. Aurizon Network disavowed any suggestion that the event was not
contemplated by cl 7A.5.83 That concession was correctly made. Reading UT5 as a
80 Ibid, [117]-[118].
81 Ibid, [119]-[120].
82 Ibid, [121].
83 Applicant’s Reply, [10] read with Outline of Submissions on behalf of QCA, [52(a)].
-- 19 of 49 --
20
whole, the definition of Report Date contemplates an event of notification occurring
in circumstances involving an unresolved Existing Capacity Deficit, which event
must have been within the contemplation of cl 7A.5 as that clause concerned the
structured process for resolving Existing Capacity Deficits. This is a matter of some
significance because cl 7A.5 did not contemplate the preliminary report being
provided by Aurizon Network to the Chair of the Rail Industry Group. Rather, cl 7A.5
contemplated one event of notification by Aurizon Network to the Chair of the Rail
Industry Group, namely the submission of the detailed report.
[58] The notification event described by the definition of Report Date, was not
contemplated to occur in a contextual vacuum. Rather, it was contemplated as
occurring in the context of a mandatory structured process described by cl 7A.5. That
process was structured as follows:
(a) Aurizon Network was required to submit a preliminary report to the QCA but,
as has been observed, there was no obligation to submit such a report to the
Chair of the Rail Industry Group or the Independent Expert;
(b) there was to be analysis and consultation as described by cl 7A.5(a)(ii);
(c) the analysis and consultation were to “identify and consider” the Transitional
Arrangements which “could effectively and efficiently” address the Existing
Capacity Deficit;
(d) it was only after the consultation and analysis, that Aurizon Network was
required to submit a detailed report to the QCA, the Chair of the Rail Industry
Group and the Independent Expert;
(e) the detailed report was to be a report “showing the outcome of Aurizon
Network’s analysis and consultations on the Existing Capacity Deficit and the
Transitional Arrangements which it considers would most effectively and
efficiently address” the Existing Capacity Deficit;84
(f) only one step in the structured process contemplated Aurizon Network
providing any kind of notification to the Chair of the Rail Industry Group, that
step being the submission of the detailed report;
(g) if Aurizon Network and affected End Users had not reached agreement about
which of the Transitional Agreements should be implemented, the Independent
Expert was required to review the detailed report and promptly make a
recommendation to the QCA with respect to “which of the Transitional
Arrangements of the type referred to in clause 7A.5(a)(iii)(A) –
cl 7A.5(a)(iii)(C)”85 it considered would most effectively and efficiently
resolve the Existing Capacity Deficit;
(h) the “Transitional Arrangements of the type referred to in clause 7A.5(a)(iii)(A)
– clause 7A.5(a)(iii)(C)”86 were the Transitional Arrangements which Aurizon
Network considered “would most effectively and efficiently address the
Existing Capacity Deficit” as shown by the detailed report but excluding any
proposed Expansion which Aurizon Network and affected Access Holders or
Access Seekers agreed would address the Existing Capacity Deficit;
84 Exhibit 5, p 220, cl 7A.5(a)(iii).
85 Exhibit 5, p 222, cl 7A.5(d).
86 Ibid.
-- 20 of 49 --
21
(i) within 15 days of receiving a recommendation from the Independent Expert,
the QCA was required to determine “which of the Transitional Arrangements
of the type referred to in clause 7A.5(a)(iii)(A) – clause 7A.5(a)(iii)(D)”87
would most efficiently and effectively resolve the Existing Capacity Deficit;
(j) the “Transitional Arrangements of the type referred to in clause 7A.5(a)(iii)(A)
– clause 7A.5(a)(iii)(D)”88 were all of the Transitional Arrangements which
Aurizon Network considered “would most effectively and efficiently address
the Existing Capacity Deficit”89 as shown by the detailed report;
(k) any proposed Expansion, whether agreed between Aurizon Network and
affected End Users or determined by the QCA, was to be reviewed by the
Independent Expert with a view to its approving “the efficiency and prudency”
of the proposed Expansion.
[59] The structured process contemplated that an Existing Capacity Deficit would be
resolved by Aurizon Network submitting a detailed report to the QCA, the
Independent Expert and the Chair of the Rail Industry Group which showed the
outcome of its analysis and consultation and the Transitional Arrangements which
Aurizon Network considered would most effectively and efficiently address the
Existing Capacity Deficit. It was contemplated that, absent agreement between the
affected End Users and Aurizon Network, the resolution of an Existing Capacity
Deficit would be a matter for recommendation by the Independent Expert and
determination by the QCA by reference to the Transitional Arrangements shown in
the detailed report. In those circumstances, the Transitional Arrangements of the type
referred to in cl 7A.5(a)(iii)(A) – cl 7A.5(a)(iii)(D) were to provide the parameters
for resolution of the Existing Capacity Deficit.
[60] Some matters can be noted about the expression “Transitional Arrangements”.
Aurizon Network was required to consult with End Users, Customers and Access
Holders of the relevant Coal System and Train Operators to identify and consider
matters which were collectively referred to as “the Transitional Arrangements”. The
matters to be identified and considered through that consultation process were set out
in cl 7A.5(a)(ii).90 The Transitional Arrangements the subject of cl 7A.5(a)(ii) were
yet to be identified or considered. However, the Transitional Arrangements referred
to in cl 7A.5(a)(iii) are of a different character. They are Transitional Arrangements
which had been identified and considered during the consultation process and which
Aurizon Network considered would most effectively and efficiently address the
Existing Capacity Deficit.91 It is objectively apparent that UT5 contemplated “the
Transitional Arrangements” as an evolving, rather than static, concept.
[61] Clause 7A.5 makes clear that, at the time of the preliminary report, the Transitional
Arrangements are yet to be identified and considered. Further, it is only Transitional
Arrangements put forward in the detailed report which:
(a) are the product of identification and consideration during the consultation
process;
87 Exhibit 5, p 222, cl 7A.5(e).
88 Ibid.
89 Ibid.
90 Exhibit 5, p 219, cl 7A.5(a)(ii)(A)-(C).
91 Exhibit 5, p 220, cl 7A.5(a)(iii)(A)-(D).
-- 21 of 49 --
22
(b) Aurizon Network considers would most effectively and efficiently address the
Existing Capacity Deficit; and
(c) are to be considered by the Independent Expert and the QCA in the process of
resolving an Existing Capacity Deficit.
[62] QRC emphasised the use of the definite article in the expression “the proposed
options for addressing any Existing Capacity Deficits”. In my consideration, it is
appropriate to attach significance to the use of the definite article because of the
context of the structured process in which that use occurs. By the time the structured
process reaches the point of the detailed report, Aurizon Network’s reporting has
progressed from its preliminary views on “solutions which could most effectively …
and efficiently address the Existing Capacity Deficit” to identifying the Transitional
Arrangements which it considers “would most effectively and efficiently address the
Existing Capacity Deficit”. The notification of those Transitional Arrangements is
properly characterised as being the notification of the proposed options for addressing
an Existing Capacity Deficit because only those Transitional Arrangements are put
forward by Aurizon Network as the most effective and efficient options to address
the Existing Capacity Deficit and fall to be considered by the Independent Expert and
the QCA in the resolution of the Existing Capacity Deficit. To the extent that the
detailed report shows “the Transitional Arrangements which Aurizon Network
considers would most effectively and efficiently address the Existing Capacity
Deficit”, it is providing the notification of “the proposed options for addressing any
Existing Capacity Deficits”.
[63] Aurizon Network submitted that it was inapt to describe the detailed report as
containing “proposed options” because some recommendations in a detailed report
might be self-executing if they were agreed.92 This submission seemed to assume that
cl 7A.5(e) only applied where Aurizon Network and affected End Users “have not
reached an agreement as to which of the Transitional Arrangements should be
implemented”.93
[64] This assumption was not the subject of any detailed submissions. In my consideration,
the better view is that, whilst the Independent Expert is not required to review a
detailed report if affected End Users and Aurizon Network have reached an agreement
about which of the Transitional Arrangements “should be implemented”, in those
circumstances, the QCA must still determine which of the Transitional Arrangements
will most effectively and efficiently resolve the Existing Capacity Deficit. Although
cl 7A.5(e) speaks in terms of the QCA making its determination “within 15 days …
of receiving a recommendation from the Independent Expert”, I am not satisfied that
those words mean that a determination by the QCA is not required in circumstances
of an agreement between the affected End Users and Aurizon Network. In those
circumstances, the QCA will have received a detailed report revealing the
Transitional Arrangements agreed, as between Aurizon Network and the affected End
Users, as being the Transitional Arrangements which “would most effectively and
efficiently address the Existing Capacity Deficit” (to adopt the language of
cl 7A.5(a)(iii)) or which “should be implemented” (to adopt the language cl 7A.5(d)).
It remains for the QCA to determine whether those agreed Transitional Arrangements
will most efficiently and effectively resolve the Existing Capacity Deficit. That the
92 Applicant’s Reply, [17].
93 See opening words of cl 7A.5(d).
-- 22 of 49 --
23
QCA retains a power of determination in these circumstances is more consistent with
the object of Part 5 of the Act, the object in cl 2.2 (f) of UT5 and the QCA’s function
as described by s 10(o) of the Act.
[65] Further, if I am wrong about that interpretation and, in circumstances of an agreement
between affected End Users and Aurizon Network, some recommendations in a
detailed report are properly described as self-executing, as at the time of the
submission of the detailed report, those recommendations are yet to be implemented.
It is also clear that, absent such an agreement and in cases of proposed expansion, the
Transitional Arrangements in a detailed report are put forward for review by the
Independent Expert and consideration by the QCA. Having regard to these matters,
as a matter of substance, it is not inapt to refer to the content of the detailed report as
containing “proposed options”.
[66] Aurizon Network noted that the preliminary report submitted under cl 7A.5(a)(i) was
to provide Aurizon Network’s preliminary views on the cause or causes of the
Existing Capacity Deficit and solutions which could most effectively and efficiently
address the Existing Capacity Deficit, including a response in reasonable detail to the
solutions identified by the Independent Expert. The expression of those preliminary
views is not properly characterised as Aurizon Network putting forward the options
proposed for resolving the Existing Capacity Deficit. At the time of the preliminary
report, the Transitional Arrangements are not yet identified, let alone considered. The
preliminary report is submitted at a point in time prior to consultations with End
Users, Customers and Access Holders of the relevant Coal System and Train
Operators. The preliminary report is not required to be submitted to the Independent
Expert. The preliminary report is not required to be considered by the Independent
Expert when it makes its recommendation in relation to the resolution of an Existing
Capacity Deficit. The preliminary report is not required to be considered by the QCA
when it makes its determination as to which of the Transitional Arrangements of the
type referred to in cl 7A.5(a)(iii)(A) – cl 7A.5(a)(iii)(D) would most effectively and
efficiently resolve the Existing Capacity Deficit. The QCA’s determination could not
be made by reference to the preliminary report because it was not contemplated as
identifying, considering or recommending any Transitional Arrangements.
[67] Aurizon Network submitted that UT5 contained a defined expression “Transitional
Arrangements” which was not used in the definition of Report Date. That matter was
relied upon to contend that “the proposed options” were intended to be something
other than “the Transitional Arrangements”.94 It was contended that the respondents’
arguments equated “the Transitional Arrangements” with “the proposed options”.
Although UT5 contains a defined expression “the Transitional Arrangements,”95 the
defined expression is directed to the spectrum of arrangements yet to be identified
and considered during the consultation process. The UT5 does not contemplate that
all “the Transitional Arrangements” would be put forward by Aurizon Network as
options to address the Existing Capacity Deficit. Rather, cl 7A.5(a)(iii) contemplates
that only those arrangements which Aurizon Network considered would most
effectively and efficiently address the Existing Capacity Deficit would be put forward
or proposed in any detailed report. The defined expression “the Transitional
Arrangements” did not neatly encapsulate what was in contemplation as being
ultimately put forward in any detailed report. The construction advanced by the
94 Applicant’s Reply, [21].
95 Exhibit 5, p 220, cl 7A.5(a)(ii).
-- 23 of 49 --
24
respondents does not equate the proposed options with the defined expression “the
Transitional Arrangements”.
[68] Having regard to the text and the context in which it appears, I find that the date on
which “Aurizon Network notifies the Chair of the Rail Industry Group of the
proposed options for addressing any Existing Capacity Deficits identified in the Initial
Capacity Assessment Report” was objectively intended to refer to the date on which
Aurizon Network submits the detailed report contemplated by cl 7A.5(a)(iii).
[69] The conclusion I have reached from the analysis of the text and its context, is
consistent with the relevant objective commercial purpose of UT5 which I find to be
to correlate the uplift in the WACC with the point in time when Aurizon Network has
engaged in the requisite consultation and analysis and reported on the particular
Transitional Arrangements which it considers will most effectively and efficiently
address the Existing Capacity Deficit. From that point in time, UT5 contemplates that:
(a) the Independent Expert will be able to promptly make a recommendation to the
QCA with respect to which of the Transitional Arrangements referred to in
cll 7A.5(a)(iii)(A)-(C) will most effectively and efficiently resolve the Existing
Capacity Deficit;
(b) the QCA will be able to determine which of the Transitional Arrangements
referred to in cll 7A.5(a)(iii)(A)-(D) will most efficiently and effectively
resolve the Existing Capacity Deficit;
(c) nothing further is required from Aurizon Network to facilitate the resolution of
the Existing Capacity Deficit, other than to comply with the ultimate
determination made by the QCA.
[70] Conferring the benefit of an uplift in WACC in circumstances where Aurizon
Network has effectively done all that it can to facilitate the resolution of an Existing
Capacity Deficit promotes the economically efficient operation and use of the
Network and. is consistent with the objects of Part 5 of the Act. In the context of the
structured process described by cl 7A.5, linking the uplift in WACC to the submission
of the detailed report is reflective of an expeditious, efficient and commercial process
ultimately concerned with the availability and utilisation of Capacity and is consistent
with the object enshrined in cl 2.2(d) of UT5. There is also a discernible synergy in
the requirements that the Initial Capacity Assessment Report and the detailed report
be provided to the Chair of the Retail Industry Group. The Initial Capacity
Assessment report notifies the Chair of the Rail Industry Group of the Existing
Capacity Deficit. The submission of the detailed report effectively gives notice to the
Chair of the Retail Industry Group that Aurizon Network has done all that it is
required to do to facilitate the resolution of the Existing Capacity Deficit and that
Rebates are from that point potentially available.
[71] By way of contrast, to confer upon Aurizon Network the benefit of the uplift in
WACC at any time prior to its submission of the detailed report would, from a
commercial perspective, involve an arbitrary or haphazard outcome. The outcome
would involve conferring a benefit upon Aurizon Network at a point in time when it
was yet to undertake the required analysis and consultation and identify the most
effective and efficient Transitional Arrangements for addressing the Existing
Capacity Deficit. The Transitional Arrangements were not matters for private
reflection by Aurizon Network but rather were intended to be identified and
-- 24 of 49 --
25
considered through consultation with End Users, Customers and Access Holders of
the relevant Coal System and Train Operators. The contention that the uplift in
WACC was triggered by the expression of Aurizon Network’s preliminary views
when the Transitional Arrangements were yet to be identified and considered, casts
the uplift in WACC as a fortuitous rather than commercial milestone. I discern no
commercial reason as to why the uplift in WACC should apply to preliminary views
not reflecting any consultation with other interested parties and which were not
matters required to be considered by the Independent Expert and the QCA when
resolving an Existing Capacity Deficit.
[72] UT5 regulates the position by acknowledging, through the Rebate provision, an
effective obligation on the part of Aurizon Network to maintain the capacity status
quo as at the Report Date pending the resolution of the Existing Capacity Deficit.
UT5 contemplates that, in the period between the Report Date and the implementation
of any Transitional Arrangements remedying any Existing Capacity Deficit, affected
End Users will be entitled to Rebates where there is a shortfall in the aggregate
number of Train Service Entitlements that the Independent Expert determines could
have been utilised by the Access Holder having regard to the IE Initial Capacity
Assessment. To the extent that Aurizon Network does not maintain the status quo
pending the resolution of the Existing Capacity Deficit, Rebates are payable. The
calculation of the Rebate during this period references not the loss suffered by the
User referable to the capacity shortfall but an amount which references the revenue
Aurizon Network would have gained from the capacity shortfall had it been made
available. In that sense, the Rebates are a payment reflective of a burden imposed
upon Aurizon Network rather than true compensation for the affected End User.
Further, at the time of submitting the detailed report, Aurizon Network is not just
exposed to the prospect of Rebates but an imminent obligation to do “everything
reasonably necessary to implement the type of Transitional Arrangements determined
by the QCA in a prudent and diligent manner”. Those realities mean that there is a
commercial imperative for Aurizon Network to put forward properly considered
options in any detailed report.
Did the Preliminary Report provide the requisite notification?
[73] I have answered the pure question of construction in favour of the respondents. As a
result, the second issue is not determinative of the outcome of this proceeding. I will
however briefly express my reasoning in relation to the second issue.
[74] The second issue proceeds on the assumption that the “Report Date”, properly
construed, refers to the date of any communication from Aurizon Network to the
Chair of the Rail Industry Group by which Aurizon Network notified the proposed
options for addressing Existing Capacity Deficits identified in the Initial Capacity
Assessment Report. If that were the proper construction of the “Report Date”, I find
that the Preliminary Report did not notify the Chair of the Rail Industry Group of the
proposed options for addressing Existing Capacity Deficits identified in the ICAR.
[75] I make that finding by reference to the following matters:
(a) the Preliminary Report was expressed as detailing “Aurizon Network’s
preliminary review of the … ICAR”.96
96 Exhibit 5, p 566, overview.
-- 25 of 49 --
26
(b) That preliminary review was undertaken for a specific purpose which was
identified as follows:97
“… in this preliminary response to the ICAR, Aurizon Network
seeks to begin the consultation process by providing our
Customers with Aurizon Network’s view as to the causes of the
Existing Capacity Deficits identified in the ICAR for each of the
… systems.”
(c) This specific purpose was reinforced by the following defined terms:
(i) “Preliminary Report” was the report which “… provides our Customers
with our initial views on the causes of the Existing Capacity Deficits and
potential Transitional Arrangements”;98 and
(ii) “Detailed Report” was a report by which “Aurizon Network will
consolidate customer feedback and finalise our recommendations on
Transitional Arrangements in the Detailed Report and provide to the
QCA, the Independent Expert and the Chair of the [Rail Industry
Group]”.99
(d) According to its terms, the Preliminary Report was not proposing any
Transitional Arrangements as the proposed options for addressing any Existing
Capacity Deficit.
(e) Rather, the Preliminary Report was intended to be used to commence a
consultation process with Aurizon Network’s Customers and was to have
utility for that process.
(f) The Preliminary Report was not proposing any Transitional Arrangements to
the QCA, the Independent Expert and the Chair of the Rail Industry Group. As
much was made clear by the following statement:100
“Aurizon Network will engage with our Customers to discuss
the outcomes of the ICAR and seek to agree on a plan that best
addresses the Existing Capacity Deficits for the relevant Coal
Systems. This Report provides the intended process for Aurizon
Network’s engagement on Transitional Arrangements, and
further information on the process once Transitional
Arrangements have been either agreed or proposed to the QCA,
the Independent Expert and the Chair of the [Rail Industry
Group]”.
(g) The Preliminary Report contemplated that the process of engagement with
Customers would result in Transitional Arrangements being “either agreed or
proposed to … the Chair of the [Rail Industry Group]”.101
(h) The Preliminary Report made clear that the Transitional Arrangements were a
matter for future agreement or future proposal to the QCA, the Independent
Expert and the Chair of the Rail Industry Group.
97 Ibid.
98 Exhibit 5, p 569.
99 Ibid.
100 Exhibit 5, p 567, Customer Engagement.
101 Exhibit 5, p 568.
-- 26 of 49 --
27
(i) In providing its “Preliminary Review” or “Preliminary Response” as to
“potential solutions”,102 Aurizon Network had not had the benefit of the
Independent Expert’s model and had relied upon its own internal modelling.
As a result, the Preliminary Report acknowledged that a verification process
was yet to be undertaken to develop final recommendations”.103
(j) The Preliminary Report went on to “propose”104 or “recommend”105 so called
Transitional Arrangements106 to rectify the Existing Capacity Deficits in the
various Rail Systems. On an objective reading of the Preliminary Report,
insofar as “Transitional Arrangements” were being proposed or recommended,
they were being put forward to Aurizon Network’s Customers as reflecting
Aurizon Network’s “initial views” on “potential Transitional
Arrangements”.107
(k) One of the first matters to be considered in the resolution of the Existing
Capacity Deficits concerned whether any Customer wished to relinquish access
rights in accordance with the terms of their access agreements.108 The
Preliminary Report made clear that where a customer made a request to
relinquish access rights, any such request would be “considered first in
resolving an Existing Capacity Deficit”.109 It was accepted that any
relinquishments would be likely to assist in resolving the Existing Capacity
Deficit.110
(l) At the time of the Preliminary Report, Aurizon Network did not know the
position in relation to whether there would be, and the extent of any, requests
for relinquishment. The Preliminary Report relevantly noted:
“Aurizon Network will be requesting customers to formally
notify it whether they wish to relinquish access rights through
the consultation process. Where requests for relinquishment are
received, they will be factored into the final Transitional
Arrangements recommendations”.111
(m) The potential Transitional Arrangements identified in the Preliminary Report,
were the subject of heavy qualification.112
102 Exhibit 5, p 572, Assessment Process.
103 Exhibit 5, p 572, Results Verification.
104 Exhibit 5, p 579, Proposed Transitional Arrangements.
105 Exhibit 5, p 581, Recommended Transitional Arrangements.
106 Under UT5, a Transitional Arrangement was to be identified and considered during consultation with
End Users, Customers and Access Holders of the relevant Coal Systems and Train Operators. To the
extent that the Preliminary Report defined Transitional Arrangements as identified prior to the
consultation process called for by cl 7A.5(a)(ii), it was using that expression differently to the sense in
which it was used in UT5.
107 Exhibit 5, p 569, definition of ‘Preliminary Report’.
108 Exhibit 5, p 579, Overview.
109 Ibid.
110 Exhibit 5, p 580, Relinquishment.
111 Ibid.
112 For example, further investigations were required in relation to economic viability of potential
arrangements (for example, refer to the Connor’s Range Headway Reduction, Exhibit 5, p 594) and
some arrangements involved speculation about matters not under the control of Aurizon Network (for
example see “mine and port delays”, Exhibit 5, pp 595-596).
-- 27 of 49 --
28
[76] My finding in relation to the intended purpose of the Preliminary Report, is further
supported by Aurizon Network’s subsequent characterisation of the Preliminary
Report. By a letter to the QCA dated 6 December 2021, Aurizon Network relevantly
stated:
“The purpose of this letter is to provide the Queensland Competition
Authority (QCA) with an update on the consultation on the Existing
Capacity Deficit (ECD) within the Initial Capacity Assessment Report
(ICAR) under Clause 7A.5(a)(iii) of the 2017 Access Undertaking
(UT5).
UT5 requires that within 3 months after the ICAR has been published,
Aurizon Network must submit a detailed report to the QCA, the Chair
of the Rail Industry Group and the Independent Expert showing the
outcome of Aurizon Network’s analysis and consultation of the ECD’s
and the Transitional Arrangements which it considers would most
effectively address those (detailed report). With the ICAR being
published by the QCA on the 1 November 2021, the detailed report is
due by 1 February 2022 (Due Date).
The development of the detailed report is highly reliant upon
consultation with Stakeholders to develop suitable options. Since the
publication, Aurizon Network has been consulting with Stakeholders
to understand the ICAR outputs and commence developing options to
address any ECD’s within the relevant systems.
….
Aurizon Network have asked Stakeholders to provide
acknowledgement of support to the QCA for this new date and we will
also include this as a timing breach on our monthly Breach Report to
the QCA in March 2022.”113
[77] By this correspondence, Aurizon Network made clear that it had not yet developed
options to address any of the Existing Capacity Deficits identified by the ICAR within
the Coal Systems. The QRC submitted that this letter contained an admission against
interest in relation to the purpose of the Preliminary Report. The letter contains clear
and unambiguous language and was sent for a considered purpose of obtaining an
extension of time to enable consultation for the purpose of developing suitable
options.114 I find that the 6 December 2021 letter was a subsequent communication
constituting an informal admission that the Preliminary Report did not as matter of
fact provide notification of the proposed options for addressing the Existing Capacity
Deficits identified by the ICAR.
Orders
[78] The orders I make are as follows:
(a) The originating application filed 20 January 2023 is dismissed.
(b) I will hear the parties as to costs.
113 Exhibit 6.
114 Phipson on Evidence, Sweet & Maxwell, 16th ed, [4-09] and [4-14].
-- 28 of 49 --
Annexure A
7A.3 Engagement of Independent Expert
7A.3.1 Appointment of Independent Expert
(a) Aurizon Network and a Special Majority of End Users will use their
best endeavours to jointly appoint an Independent Expert, which
expert will be responsible for, amongst other things:
(i) conducting Capacity Assessments in accordance with this Part 7A
(which includes developing and amending the System Operating
Parameters);
(ii) reviewing performance information including source data received
from Aurizon Network, Access Holders and other Supply Chain
Participants for the purpose of the Independent Expert’s reporting
obligations under clause 10.8.3;
(iii) reporting on actual performance data and maintenance information to
the QCA, Aurizon Network and relevant stakeholders for the purpose
of the Independent Expert’s reporting obligations under clause 10.8.3;
and
(iv) determining any Rebate payable by Aurizon Network to End Users in
accordance with clause 7A.6.
(b) Subject to clause 7A.3.3, the Independent Expert’s appointment under this
clause 7A.3.1 expires at the completion of the Term or such later time as may
be specified in the contract of appointment.
(c) If at any time during the Term, no Independent Expert is appointed (for
example due to the resignation or termination of the Independent Expert), the
members of the Rail Industry Group and Aurizon Network must consult with
each other and Aurizon Network and a Special Majority of End Users must
seek to agree on the appointment of a new independent expert on terms
substantially similar in all material respects to the terms of the appointment of
the previous independent expert (or such other terms agreed).
(d) If a Special Majority of End Users and Aurizon Network cannot agree on:
(i) the appointment of the Independent Expert by the date that is 30 days
after the Approval Date; or
(ii) a new independent expert under clause 7A.3.1(c) within within 30 days
of the cessation of the previous appointment,
-- 29 of 49 --
the appointment of the Independent Expert under this Part 7A must be referred
for resolution as a Dispute under clause 11.1.1(a)(iii) of this Undertaking.
(e) On the resolution of the dispute under clause (d) Aurizon Network and a
Special Majority of End Users will use their best endeavours to jointly appoint
an Independent Expert to fulfil the obligations as set out in this Undertaking
and on the terms provided for in this Part 7A.
(f) The Independent Expert appointed under clauses 7A.3.1(a) or, 7A.3.1(c) must:
(i) be independent and impartial;
(ii) engage personnel with appropriate qualifications and practical
experience having regard to the nature of the appointment (including
qualifications and experience in modelling the capacity of coal chain
infrastructure) provided
that if the Independent Expert is a new entity, this requirement will be
satisfied where the employees and personnel of the new entity are
appropriately qualified and experienced;
(iii) have no interest or duty which conflicts or may conflict with their
function as an Independent Expert, or where it believes it has such an
interest or duty, the Independent Expert must fully disclose that interest
or duty by notice to the members of the Rail Industry Group, Aurizon
Network and the QCA
prior to their appointment; and
(iv) be required to manage the confidential nature of all information and
matters coming to their knowledge by reason of their appointment and
performance of their duties including in accordance with the terms of
any confidentiality
agreement in favour of Aurizon Network and if requested, any other
entity providing information under this Part 7A.
7A.3.2 [Not used]
7A.3.3 Termination of engagement of Independent Expert
(a) On the date that is four (4) years after the Approval Date, the QCA must
review the appointment of the Independent Expert.
(b) Following this review:
(i) Aurizon Network and a Special Majority of End Users may agree; or
(ii) the QCA may, in its absolute discretion, elect,
to terminate the engagement of the Independent Expert and appoint a
replacement independent expert in accordance with this Part 7A.
-- 30 of 49 --
(c) The Independent Expert’s contract of appointment must include provisions
enabling termination of the appointment of the Independent Expert as follows:
(i) if, at any time, the Independent Expert is in default of its obligations
under the contract of appointment, either the Chair of the Rail Industry
Group (on behalf of the Special Majority of End Users) or Aurizon
Network (as applicable) may provide a written termination notice to the
Independent Expert (with a copy to the other party) in accordance with
the terms of that contract; or
(ii) if, at any time, the Chair of the Rail Industry Group (on behalf of the
Special Majority of End Users) and Aurizon Network mutually agree to
terminate the appointment of the Independent Expert, both the Chair of
the Rail Industry Group (on behalf of the Special Majority of End
Users) and Aurizon Network may provide a written termination notice
to the Independent Expert in accordance with the terms of that contract.
(iii) if the QCA elects to terminate the appointment under clause (b)(ii) or
clause (e)(iii).
Any party who issues a written notice of termination under this clause
7A.3.3(c) must also promptly provide a copy of that notice to the QCA.
(d) If, at any time during the term of their appointment, the Independent Expert
becomes aware of any circumstances that might reasonably be considered to
adversely affect the Independent Expert’s ability to act independently or
impartially, the Independent Expert must notify the QCA immediately in
writing.
(e) Upon receiving a notice under clause 7A.3.3(d), or if the QCA otherwise
becomes aware of any circumstances that might be considered to adversely
affect the Independent Expert’s ability to act independently and impartially
(including if the QCA has received a notice from any stakeholders to this
effect) the QCA must promptly:
(i) notify the Chair of the Rail Industry Group and Aurizon Network of its
receipt of any notice received under clause 7A.3.3(d);
(ii) consider, on the basis of the notice and other information reasonably
available to the QCA (including any information provided by the Chair
of the Rail Industry Group or Aurizon Network), whether the
circumstances would likely affect the ability of the Independent Expert
to act independently or impartially; and
(iii) terminate the engagement of the Independent Expert if it considers the
ability of the Independent Expert to act independently or impartially
has been, or is likely to be, affected (in its absolute discretion),
in which case a new Independent Expert must be appointed in accordance with
the procedure outlined in this clause 7A.3.
-- 31 of 49 --
7A.3.4 Costs
(a) The Independent Expert’s costs of performing its role will be a pass through
cost recoverable as a component of the Reference Tariff by which Access
Charges are calculated (IE Pass Through Cost).
(b) The IE Pass Through Cost will be based on the forecast provided by the
Independent Expert under clause 7A.3.4(c) and will not be part of Aurizon
Network’s Allowable Revenue.
(c) With effect from 14 February 2020, by 14 February of each Year, the
Independent Expert will notify Aurizon Network (in writing) of its forecast IE
Pass Through Cost for the next Year (including details of any adjustments
made by the Independent Expert in calculating the forecast as a result of any
over or under recovery of the Independent Expert’s costs (if any) in the
previous Year and an estimate in respect of the balance of the Year in which
the forecast is being provided).
(d) Any under recovery of the Independent Expert’s costs in respect of the Year
ending 30 June 2020 will be the subject of an adjustment by the Independent
Expert when advising the IE Pass Through Cost for 2021.
(e) Aurizon Network will calculate the IE Fee component of Access Charges for
each Access Holder on a $ per net tonne basis, which will be payable by
Access Holders in their Monthly invoices.
(f) With effect from 28 February 2020, by 28 February of each Year Aurizon
Network will notify the QCA of the forecast IE Pass Through Cost advised by
the Independent Expert under clause 7A.3.4(c) as part of its submission on the
annual review of Reference Tariffs under clause 4.1 of Schedule F.
(g) In the event that the Independent Expert has not advised Aurizon Network of
the forecast IE Pass Through Cost for the Year ending 30 June 2021 by 14
February 2020, the Independent Expert will advise Aurizon Network of the
forecast IE Pass Through Cost for 2021 as soon as it is known and Aurizon
Network will notify the QCA of that forecast IE Pass Through Cost which will
constitute an Endorsed Variation Event under clause Schedule F5.2(d) of
Schedule F.
7A.3.5 Appointment of initial Independent Expert
For the purpose of appointing the initial Independent Expert under clause 7A.3.1(a), a
determination as to whether the thresholds in the definition of a “Special Majority of
End Users” have been met will be made by Aurizon Network.
7A.4 Capacity Assessments by Independent Expert
7A.4.1 IE Initial Capacity Assessment
(a) As soon as reasonably practicable and by no later than ten (10) Business Days
after its appointment, the Independent Expert must commence its initial
assessment of the Deliverable Network Capacity of each Coal System for the
-- 32 of 49 --
Capacity Assessment Period in accordance with the procedure outlined in this
clause 7A.4.1 (IE Initial Capacity Assessment).
(b) As part of the IE Initial Capacity Assessment, the Independent Expert must
develop the System Operating Parameters for each Coal System having regard
to the way in which each Coal System operates in practice. The Independent
Expert must seek to ensure that the System Operating Parameters:
(i) include a consideration of the factors set out in the definition of
Deliverable Network Capacity as such factors apply as at the date the
System Operating Parameters are developed; and
(ii) would not place Aurizon Network in breach of its obligations under
this Undertaking or any Access Agreement (assuming that any Access
Agreement could be amended to reflect the System Operating
Parameters in accordance with clause 7A.12),
having regard to (among other things) the information received from Aurizon
Network and Access Holders and Access Seekers (and their Customers and
Train Operators, as applicable).
(c) The Independent Expert must seek to consult with, and seek submissions from,
Aurizon Network, Access Holders and Access Seekers (and their Customers
and Train Operators, as applicable) and all Supply Chain Participants for each
Coal System on:
(i) subject to any confidentiality restrictions, information that relates to the
operation of Train Services in that Coal System and the actual
performance of that Coal System for the purpose of the IE Initial
Capacity Assessment (including the development of the dynamic
model required to undertake the Deliverable Network Capacity
Analysis); and
(ii) the proposed System Operating Parameters,
and the Independent Expert will seek to obtain such information from Supply
Chain Participants by the date the earlier of the date that is 2 months after the
appointment of the Independent Expert or the Approval Date.
(d) Aurizon Network must promptly do everything reasonably requested by the
Independent Expert to assist the Independent Expert in carrying out an IE
Initial Capacity Assessment under this clause 7A.4.1, including providing or
making available to the Independent Expert, as soon as reasonably practicable,
all information and materials in its possession or control relevant to those
matters listed in the definition of Deliverable Network Capacity and otherwise
requested by the Independent Expert by the earlier of the date that is 2 months
after the appointment of the Independent Expert or the Approval Date, which
may include, subject to the relevant Access Holders and Customers providing
consent to Aurizon Network disclosing information relevant to their Access
Agreements:
-- 33 of 49 --
(i) copies of any Access Agreements entered into by Aurizon Network;
(ii) the System Rules;
(iii) Possession Protocols;
(iv) Rollingstock Interface Standard;
(v) Approved Derogations;
(vi) Aurizon Network’s internal modelling of the Capacity of each Coal
System (including access to the relevant models);
(vii) Aurizon Network’s Maintenance Strategy and Budget, Renewals
Strategy and Budget and operational plans; and
(viii) actual performance information (including all source and underlying
information and data) for each Coal System for at least the previous
three years, or such longer period as reasonably requested by the
Independent Expert and in respect of which the information is readily
available in the form requested.
(e) The members of the Rail Industry Group must provide to the Independent
Expert, and the Independent Expert must consider, any information it has in its
possession or control in relation those matters listed in the definition of
Deliverable Network Capacity by the earlier of the date that is 2 months after
the appointment of the Independent Expert or the Approval Date and as
otherwise requested by the Independent Expert.
(f) The IE Initial Capacity Assessment must:
(i) include a dynamic Deliverable Network Capacity Analysis based on a
dynamic model developed by the Independent Expert (to be owned by
the Independent Expert) that reflects how each Coal System operates in
practice (having regard to the information received from Aurizon
Network and Access Holders and Access Seekers (and their Customers
and Train Operators, as applicable)) to determine the Deliverable
Network Capacity for each Coal System. Subject to any confidentiality
and intellectual property restrictions, the Independent Expert must
provide a copy of the dynamic model developed by the Independent
Expert to Aurizon Network and the QCA in a non-hard coded form for
use by Aurizon Network and the QCA for internal purposes only;
(ii) set out the System Operating Parameters for that Coal System as
determined by the Independent Expert in accordance with clause
7A.4.1(b);
(iii) include consideration of:
(A) outcomes of any consultation by the Independent Expert with
Aurizon Network, Access Holders and Access Seekers (and
their Customers and Train Operators, as applicable) and any
-- 34 of 49 --
other Supply Chain Participants for each Coal System in
relation to that assessment;
(B) any information received from Aurizon Network under clause
7A.4.1(d); and
(C) any information received from the members of the Rail Industry
Group under clause 7A.4.1(e).
(iv) include a report that sets out:
(A) the Independent Expert’s assumptions affecting Deliverable
Network Capacity and relied upon for the IE Initial Capacity
Assessment which:
(1) must address each of the assumptions contained in the
definition of Deliverable Network Capacity and the
System Operating Parameters, and used to develop the
model required to undertake the Deliverable Network
Capacity Analysis; and
(2) may include such other assumptions as are reasonably
considered relevant by the Independent Expert to its
assessment of Deliverable Network Capacity and relied
upon for the IE Initial Capacity Assessment in its
absolute discretion (including any assumptions
regarding Rollingstock, section run times and loading
and unloading times);
(B) any constraints the Independent Expert has identified which
have reduced or are likely to reduce the Deliverable Network
Capacity of each Coal System, including;
(1) any constraints identified within the Supply Chains
operating within that Coal System (including in respect
of loading facilities, load out facilities and coal export
terminal facilities); and
(2) any constraints identified within the whole of the Rail
Infrastructure; and
(C) if the Independent Expert identifies in the IE Initial Capacity
Assessment that there is an Existing Capacity Deficit with
respect to a Coal System:
(1) specify the relevant Coal System and the location in that
Coal System where the Existing Capacity Deficit arises;
and
(2) specify the quantum of the Existing Capacity Deficit;
-- 35 of 49 --
(v) if the Independent Expert identifies a specific cause or causes of the
Existing Capacity Deficit:
(A) specify the Access Holders affected by the Existing Capacity
Deficit; and
(B) include in reasonable detail, solutions which could effectively
and efficiently address the Existing Capacity Deficit.
(g) As soon as reasonably practicable (it being acknowledged that the Independent
Expert will be engaged on terms that require the Independent Expert to use its
best endeavours and Aurizon Network and the members of the Rail Industry
Group to act in good faith to enable the Independent Expert to undertake the
IE Initial Capacity Assessment as quickly as is reasonably possible having
regard to the nature of the assessment and the need to undertake an assessment
that is both realistic and accurate), the Independent Expert must make:
(i) the outcomes of the IE Initial Capacity Assessment, including its
assumptions affecting Deliverable Network Capacity and relied upon
for the IE Initial Capacity Assessment (Initial Capacity Assessment
Report); and
(ii) the System Operating Parameters,
available to Aurizon Network, and the QCA on an unredacted basis and to the
Chair of the Rail Industry Group on a redacted basis.
(h) Subject to clause 7A.4.1(i), Aurizon Network and the QCA must promptly
publish on the Website or its website (as applicable):
(i) the Initial Capacity Assessment Report in a redacted form that does
not disclose information that is confidential to an Access Holder,
Customer or Train Operator and unable to be disclosed; and
(ii) the System Operating Parameters of each Coal System.
(i) An Access Holder, Customer or Train Operator may provide its prior written
consent to Aurizon Network and the QCA for its confidential information to
be disclosed in the Initial Capacity Assessment Report on an unredacted basis.
7A.4.2 Annual Capacity Assessment
(a) The Independent Expert must undertake an annual assessment of the
Deliverable Network Capacity of each Coal System for the relevant Capacity
Assessment Period (each being an Annual Capacity Assessment). The first
Annual Capacity Assessment will be undertaken for the first Year after the
Initial Capacity Assessment Report has been completed.
(b) As part of each Annual Capacity Assessment, the Independent Expert must:
(i) review the System Operating Parameters for that Coal System; and
-- 36 of 49 --
(ii) consider whether any variation of the System Operating Parameters is
required, provided that any amendments to the System Operating
Parameters:
(A) include a consideration of the factors set out in the definition
of Deliverable Network Capacity;
(B) would be consistent with the applicable Approved
Maintenance Strategy and Budget and Renewals Strategy and
Budget; and
(C) would not place Aurizon Network in breach of its obligations
under this Undertaking or any Access Agreement (assuming
that any Access Agreement could be amended to reflect the
System Operating Parameters in accordance with clause
7A.12).
(c) The Independent Expert must seek to consult with, and seek submissions from,
Aurizon Network, Access Holders and Access Seekers (and their Customers
and Train Operators, as applicable) and all other Supply Chain Participants for
each Coal System on:
(i) any information that relates to the operation of Train Services in that
Coal System for the purpose of the Annual Capacity Assessment; and
(ii) the proposed, and any variation of, the System Operating Parameters
(as applicable).
(d) The Independent Expert must promptly make:
(i) the outcomes of its Annual Capacity Assessment, including its
assumptions affecting Deliverable Network Capacity and relied upon
for the Annual Capacity Assessment (Annual Capacity Assessment
Report); and
(ii) the current System Operating Parameters,
available to Aurizon Network and the QCA on an unredacted basis.
(e) For the purpose of this clause 7A.4.2, each of the obligations listed in clauses
7A.4.1(d) – 7A.4.1(f) and clauses 7A.4.1(h) – 7A.4.1(i) apply as if they were
duplicated here, except that:
(i) each reference to an IE Initial Capacity Assessment will be a
reference to an Annual Capacity Assessment;
(ii) each reference to an Initial Capacity Assessment Report will be a
reference to an Annual Capacity Assessment Report; and
(iii) each reference to “the earlier of the date that is 2 months after the
appointment of the Independent Expert or the Approval Date” will be
-- 37 of 49 --
a reference to the “within the timeframe requested by the Independent
Expert”.
7A.4.3 System Capacity Assessments
(a) The Independent Expert must undertake a System Capacity Assessment for
each Coal System as soon as reasonably practicable after the date that the
Independent Expert publishes its Initial Capacity Assessment Report and
thereafter on each anniversary thereof. It is acknowledged that the initial
System Capacity Assessment should not delay the Independent Expert in
undertaking the IE Initial Capacity Assessment in accordance with this Part
7A.
(b) A System Capacity Assessment will be produced by the Independent Expert
for information purposes only for the benefit of Aurizon Network, Access
Holders and Access Seekers (and their respective Customers and Train
Operators) for a Coal System and a copy of that report will be provided by the
Independent Expert to Aurizon Network, the Chair of the Rail Industry Group
and the members of the Rail Industry Group on a redacted basis.
(c) Aurizon Network must promptly do everything reasonably requested by the
Independent Expert to assist the Independent Expert in carrying out a System
Capacity Assessment under this clause 7A.4.3, including providing or making
available to the Independent Expert, as soon as reasonably practicable and
subject to any confidentiality restrictions, all information and materials in its
possession or control relevant to those matters listed in the definition of
System Capacity and as otherwise requested by the Independent Expert, which
may include, subject to the relevant Access Holders and Customers providing
consent to Aurizon Network to disclose information relevant to their Access
Agreements:
(i) copies of any Access Agreements entered into by Aurizon Network;
(ii) the System Rules;
(iii) Possession Protocols;
(iv) Rollingstock Interface Standard;
(v) Approved Derogations;
(vi) Aurizon Network’s internal modelling of the Capacity of each Coal
System (including access to the relevant models);
(vii) Aurizon Network’s Approved Maintenance Strategy and Budget,
Renewals Strategy and Budget and operational plans; and
(viii) actual performance information (including all source and underlying
information and data) for each Coal System for at least the previous
three years, or such longer period as reasonably requested by the
Independent Expert and in respect of which the information is readily
available in the form requested.
-- 38 of 49 --
(d) Access Holders and Customers must provide to the Independent Expert, and
the Independent Expert must consider, any information it has in its possession
or control in relation those matters listed in the definition of System Capacity
and as otherwise requested by the Independent Expert.
(e) A System Capacity Assessment must include:
(i) consideration of outcomes of any consultation by the Independent
Expert with Aurizon Network, Access Holders and Access Seekers
(and their Customer and Train Operator, as applicable) for Train
Services operating in that Coal System;
(ii) consideration of outcomes of any consultation with any Supply Chain
Group for the relevant Coal System;
(iii) consideration of outcomes of any consultation with port operators; and
(iv) a report that sets out the Independent Expert’s assumptions affecting
System Capacity and relied upon for the System Capacity Assessment
which must be consistent with those assumptions listed in the definition
of System Capacity and may include such other assumptions as are
reasonably considered relevant by the Independent Expert to its
assessment of System Capacity and relied upon or the System Capacity
Assessment.
(f) Nothing in this Undertaking:
(i) obliges Aurizon Network to implement any changes to its provision of
Access as a result of any System Capacity Assessment; or
(ii) allows the Independent Expert to alter the IE Initial Capacity
Assessment or any Annual Capacity Assessment as a result of the
System Capacity Assessment.
7A.4.4 Capacity Assessments to be final and binding
(a) In the absence of fraud or manifest error, the Independent Expert’s Capacity
Assessment is final and binding.
(b) If any person reasonably affected by the outcome of a Capacity Assessment
believes that there has been a manifest error or fraud in the Capacity
Assessment (or in its preparation), or that the Independent Expert has not
complied with or satisfied the requirements of clause 7A.3.1(f), it may refer
the matter to the QCA for a determination.
(c) If the QCA determines that there has been a manifest error or fraud or that the
Independent Expert has not complied with or satisfied the requirements of
clause 7A.3.1(f), the Capacity Assessment is not final and binding and the
Independent Expert must promptly commence a new Capacity Assessment in
accordance with this Part 7A.
-- 39 of 49 --
(d) Subject to clause 7A.4.4(f), at all times after the Initial Capacity Assessment
Report is published by the QCA on its website as contemplated by clause
7A.4.1(h), where Aurizon Network is required to have regard to Capacity in
performing any of its obligations under this Undertaking (including in relation
to the provision of Access), Aurizon Network must only have regard to the
most recent Capacity Assessment undertaken by the Independent Expert or
other information provided by the Independent Expert as expressly
contemplated in the Undertaking (other than in the case of an IE Initial
Capacity Assessment) and must not, for the avoidance of doubt, have regard to
any of Aurizon Network’s internal modelling of the Capacity of the relevant
Coal System or any other form of Capacity modelling.
(e) For the avoidance of doubt, any determination by the Independent Expert of
the System Capacity is provided for information purposes only.
(f) Aurizon Network and an Access Seeker (and Train Operator as applicable)
may, acting reasonably and in good faith, negotiate Access Agreements and
Train Operations Deeds for non-coal carrying Train Services that do not reflect
the System Operating Parameters, and for the purposes of engaging in such
negotiations Aurizon Network will not be bound by the System Operating
Parameters which are developed by the Independent Expert as part of a
Capacity Assessment referred to in clause 7A.4.4(d).
7A.5 Existing Capacity Deficit
(a) if the IE Initial Capacity Assessment reveals a Deliverable Network Capacity
Shortfall in a relevant Coal System (Existing Capacity Deficit), Aurizon
Network must:
(i) within twenty (20) Business Days after the Initial Capacity Assessment
Report has been published by the QCA on its website, submit a
preliminary report to the QCA (and publish such preliminary report in a
prominent place on the Website) setting out:
(A) Aurizon Network’s consultation plan (which, when followed,
must satisfy the requirements of clause 7A.5(a)(ii)); and
(B) Aurizon Network’s preliminary views on:
(1) the cause or causes of the Existing Capacity Deficit
(including a response, in reasonable detail, to the cause
or causes identified by the Independent Expert); and
(2) solutions which could most effectively (including cost
effectively) and efficiently address the Existing Capacity
Deficit (including a response, in reasonable detail, to the
solutions identified by the Independent Expert); and
(3) the indicative timeframe within which it considers each
of the solutions could reasonably be implemented;
-- 40 of 49 --
(ii) prior to publishing a detailed report under clause 7A.5(a)(iii), consult
with End Users, Customers and Access Holders of the relevant Coal
System and Train Operators, to identify and consider:
(A) whether changes can be made to:
(1) the operation and maintenance practices for the Rail
Infrastructure;
(2) the operations of Rollingstock by Railway Operators;
(3) the operation and maintenance practices in respect of
load-out facilities,
including in relation to interfaces with all facilities
forming part of the relevant Supply Chains (as set out in
the assumptions affecting Deliverable Network Capacity
and included in the Initial Capacity Assessment Report)
in order to increase the Deliverable Network Capacity of
the relevant Coal System, provided that such changes
would be consistent with the System Operating
Parameters included in the IE Initial Capacity
Assessment (and would not require an Access Holder to
revert to the requirements in an Access Agreement where
that Access Agreement has not been modified to make it
consistent with the new System Operating Parameters);
(B) whether an Access Holder wishes to voluntarily relinquish any
of its Access Rights if it is entitled to do so under, and in
accordance with, a relinquishment provision in its Access
Agreement (without being required to pay a Relinquishment Fee
to Aurizon Network) with the Access Holder to specify the
maximum and minimum number of Access Rights that the
Access Holder would be willing to relinquish; and
(C) options for Expansions,
(collectively, the Transitional Arrangements),
which could effectively and efficiently address the Existing Capacity
Deficit or whether affected Access Holders and Customers would prefer
not to do anything to address the Existing Capacity Deficit; and
(iii) within three (3) Months after the Initial Capacity Assessment Report has
been published by the QCA on its website, submit a detailed report to
the QCA, the Chair of the Rail Industry Group and the Independent
Expert showing the outcome of Aurizon Network’s analysis and
consultation on the Existing Capacity Deficit and the Transitional
Arrangements which it considers would most effectively and efficiently
address the Existing Capacity Deficit, including:
-- 41 of 49 --
(A) whether any Access Holder is willing to, within 30 days,
voluntarily relinquish any of its Access Rights if it is entitled to
do so under, and in accordance with, a relinquishment provision
in its Access Agreement (without being required to pay a
Relinquishment Fee that would otherwise be payable as a result
of such relinquishment under its Access Agreement) and the
extent to which any voluntary relinquishment will address (up to
a maximum of) the Existing Capacity Deficit in that Coal
System). If multiple Access Holders wish to relinquish Access
Rights, then the voluntary relinquishment will be apportioned
pro rata up to a maximum of the Existing Capacity Deficit in that
Coal System;
(B) whether changes could be made to:
(1) the operation and maintenance practices for the Rail
Infrastructure;
(2) the operations of Rollingstock by Railway Operators;
(3) the operation and maintenance practices in respect of
load-out facilities,
including in relation to interfaces with all facilities forming part
of the relevant Supply Chains (as set out in the assumptions
affecting Deliverable Network Capacity and included in the
Initial Capacity Assessment Report) that could increase the
Deliverable Network Capacity of the relevant Coal System,
provided that such changes would be consistent with the System
Operating Parameters included in the IE Initial Capacity
Assessment (and would not require an Access Holder to revert to
the requirements in an Access Agreement where that Access
Agreement has not been modified to make it consistent with the
new System Operating Parameters), including:
(4) the extent to which the proposed operational changes will
address the Existing Capacity Deficit;
(5) a reasonable estimate of the cost of such operational
changes to Aurizon Network and/or Customers and
Access Holders; and
(6) if relevant, evidence of Aurizon Network’s consultation
under clause 7A.5(a)(ii) that explains why such changes
cannot address the Existing Capacity Deficit;
(C) if relevant, a shortlist of Expansions considered by Aurizon
Network and through the consultation under clause 7A.5(a)(ii)
(including reasonable estimates of costs to undertake each
Expansion); and
-- 42 of 49 --
(D) subject to clause 7A.5(c), any proposed Expansion which
Aurizon Network and the affected Access Holders or Access
Seekers have agreed will address the Existing Capacity Deficit.
(b) The QCA may publish any report provided by Aurizon Network under clause
7A.5(a) on its website.
(c) If:
(i) Aurizon Network and the affected End Users jointly agree:
(A) that an Expansion is the most effective and efficient option to
address the Existing Capacity Deficit; and
(B) on the terms of the Expansion proposal to be submitted to the
Independent Expert,
then clause 7A.5(i) will apply.
(ii) Aurizon Network and the affected End Users jointly agree that an
Expansion is the most effective and efficient option to address the
Expansion Capacity Deficit but have not agreed on the terms of the
Expansion proposal to be submitted to the Independent Expert by the
date the Aurizon Network is due to submit the report under clause
7A.5(a)(iii) then Aurizon Network may, acting reasonably, determine
the Expansion proposal to be submitted to the Independent Expert and
clause 7A.5(i) will apply and Aurizon Network must submit the
Expansion proposal to the Independent Expert for review under clause
7A.5(i)(i).
(d) If affected End Users and Aurizon Network have not reached an agreement as
to which of the Transitional Arrangements should be implemented, the
Independent Expert must review any report provided by Aurizon Network under
clause 7A.5(a)(iii) and promptly make a recommendation to the QCA with
respect to which of the Transitional Arrangements of the type referred to in
clause 7A.5(a)(iii)(A) – clause 7A.5(a)(iii)(C) it considers will most effectively
and efficiently resolve the Existing Capacity Deficit, including with regard to
which of the Transitional Arrangements will result in the lowest net present cost
applying the Discount Rate to all Access Holders without prejudice to the
reliability and performance (in the long and short term) of the Rail
Infrastructure.
(e) Within 15 days (or such longer period as may be required by the QCA) of
receiving a recommendation from the Independent Expert, the QCA must make
a determination as to which of the Transitional Arrangements of the type
referred to in clause 7A.5(a)(iii)(A) – clause 7A.5(a)(iii)(D) will most
efficiently and effectively resolve the Existing Capacity Deficit, including with
regard to which of the Transitional Arrangements will result in the lowest net
present cost applying the Discount Rate to all Access Holders without prejudice
to the reliability and performance (in the long and short term) of the Rail
Infrastructure provided that the QCA’s determination must be consistent with
-- 43 of 49 --
the System Operating Parameters other than as is required to accommodate an
operational change deemed prudent by the QCA for the purpose of rectifying
the Existing Capacity Deficit.
(f) Subject to clause 7A.5(h), Aurizon Network must comply with any
determination made by the QCA under clause 7A.5(e) including by doing
everything reasonably necessary to implement the type of Transitional
Arrangements determined by the QCA in a prudent and diligent manner so as
to resolve the Existing Capacity Deficit as soon as reasonably practicable,
having regard to the nature and type of Transitional Arrangements required.
(g) Aurizon Network’s obligation under clause 7A.5(f) to implement the
Transitional Arrangements (other than Expansions) is limited to the extent that
such Transitional Arrangements:
(i) are within the control of Aurizon Network;
(ii) would not place Aurizon Network in breach of any applicable
Safeworking Procedures and Safety Standards; and
(iii) would not place Aurizon Network in breach of its obligations under this
Undertaking or any Access Agreement. In determining whether a
Transitional Arrangement would put Aurizon Network in breach of an
Access Agreement, that determination would be made on the basis that
any change in a System Operating Parameter had been reflected in the
relevant Access Agreement as contemplated by clause 7A.12.
(h) To the extent Aurizon Network is required to implement operational changes
and, in doing so, incurs costs that it would not otherwise be entitled to recover
in accordance with this Undertaking, Aurizon Network will be entitled to
recover such costs (provided those costs are reasonable and pre-approved by the
QCA).
(i) If Aurizon Network and affected End Users agree that an Expansion is the most
effective and efficient option to address the Existing Capacity Deficit and End
Users wish to rectify the Existing Capacity Deficit, or if the QCA otherwise
determines that an Expansion is the most effective and efficient option to
address the Existing Capacity Deficit, then:
(i) the Independent Expert must review and approve the efficiency and
prudency of the proposed Expansion prior to Aurizon Network incurring
any construction expense in relation to the proposed Expansion. Where
the Independent Expert does not approve the efficiency and prudency of
the Expansion, Aurizon Network must submit an alternative proposal
that:
(A) Aurizon Network and the affected End Users have agreed will
address the Existing Capacity Deficit for approval; or
(B) (if Aurizon Network and the affected End Users have not agreed
an alternative proposal within 20 Business Days after the
-- 44 of 49 --
Independent Expert decides not to approve the efficiency and
prudency of the Expansion), Aurizon Network (acting
reasonably) determines will address the Existing Capacity
Deficit;
(ii) any alternative proposal required to be submitted by Aurizon Network
in accordance with this clause 7A.5(i)(i) will be reviewed by the
Independent Expert for efficiency and prudency. Unless and until the
Independent Expert approves the efficiency and prudency of the
proposed Expansion (as set out in any alternative proposal required to
be submitted by Aurizon Network in accordance with this clause
7A.5(i)(i)), Aurizon Network must not incur any construction
expenditure in relation to the proposed Expansion. Subject to clause
7A.5(i)(iv), Aurizon Network is obliged to promptly undertake and fund
the Expansion at the Approved WACC applicable from time to time;
(iii) the value of the Expansion will be included in the Regulatory Asset
Base;
(iv) Aurizon Network will only be obliged to undertake and fund an
Expansion up to an amount of $300 million (in aggregate across all
Expansions required in accordance with this clause); and
(v) for clarity, the pricing principles to apply to an Expansion are set out in
Part 6 and Schedule F.
(j) Aurizon Network acknowledges that an Existing Capacity Deficit does not
reduce an Access Holder’s entitlement to Access Rights under an existing
Access Agreement, except to the extent an Access Holder elects to voluntarily
relinquish its Access Rights under this Part 7A.
(k) Nothing in this clause 7A.5 affects or limits Aurizon Network’s obligations or
liabilities in respect of an Access Agreement or any other agreement entered
into in accordance with this Undertaking.
(l) Despite clause 2.4(f) and anything contrary in an Access Agreement, where this
Part 7A specifies that a Relinquishment Fee is not payable, Aurizon Network
will not collect, and will not be deemed to collect (for the purposes of the
calculation of Total Allowable Revenue under Part 7A), any Relinquishment
Fee.
7A.6 Rebate
(a) This clause 7A.6 commences to apply from the Report Date.
(b) From the Report Date, the Independent Expert must identify if there has been
any AN Performance Shortfall resulting from an AN Performance Breach in
that Relevant Year. If there has been an AN Performance Shortfall resulting
from an AN Performance Breach, the Independent Expert must determine the
Performance Rebate Amount that Aurizon Network must, subject to clause
7A.6(c) and clause 7A.6(e), pay an affected End User (Rebate). In determining
-- 45 of 49 --
the Performance Rebate Amount for the Year in which the Report Date occurs,
the Independent Expert will only have regard to any AN Performance Shortfall
resulting from an AN Performance Breach that occurred between the Report
Date and the end of that Year. In subsequent Years following the Year in which
the Report Date occurs, the Independent Expert will have regard to AN
Performance Shortfalls resulting from an AN Performance Breach for all of the
Relevant Year.
(c) Aurizon Network’s liability to pay an End User any Rebate under clause 7A.6(a)
is conditional upon:
(i) the Access Holder (where it is not the End User) or the End User
advising Aurizon Network in writing of the identity of the End User to
whom the Rebate is payable;
(ii) the Access Holder and the End User first undertaking in writing in
favour of Aurizon Network that:
(A) the payment of the Rebate to the End User is the sole right to
compensation;
(B) for clarity, where the Access Holder and the End User are
different entities, the Access Holder does not have a separate
right of compensation from the End User; and
(C) Aurizon Network is not otherwise liable to the Access Holder or
End User for any claim (whether based in contract or tort, under
common law or in equity or under statute) for any other loss or
damage suffered or incurred,
in respect of the Train Service Entitlements which were not provided as
a result of an AN Performance Breach, subject only to any other rights
available to the Access Holder or End User:
(D) for a wilful breach by Aurizon Network of any Access
Agreement or the Undertaking;
(E) under the termination provisions of any Access Agreement; and
(F) under the Act;
(iii) prior to giving such undertaking, the Access Holder and End User in
respect of the relevant Train Service Entitlement not having commenced
any claim that would be in breach of such undertaking if such
undertaking had been given at the time the claim was commenced; and
(iv) the Access Holder and End User agreeing, as part of the undertaking
referred to in clause 7A.6(c)(ii), that it will not set off any amounts
which are due and payable by the Access Holder or End User (as
applicable) to Aurizon Network against the Rebate payable by Aurizon
Network to that Access Holder or End User.
-- 46 of 49 --
(d) Aurizon Network must:
(i) issue a recipient created tax invoice (RCTI) within 5 Business Days after
the Independent Expert determines any Rebate that Aurizon Network
must pay an affected End User;
(ii) pay the affected End User the amount set out in an RCTI given under
clause 7A.6(d)(i) within 20 Business Days after the RCTI is given to the
affected End User;
(iii) pay the Rebate:
(A) in Australian currency; and
(B) by direct deposit into one Australian bank account notified by
the End User to Aurizon Network; and
(iv) not set off the Rebate against any amounts which are due and payable
by the affected Access Holder or End User (as applicable) to Aurizon
Network.
(e) Aurizon Network will not be liable to pay a Rebate to an End User where the
AN Performance Shortfall resulted from an AN Performance Breach related to
the breach of a System Operating Parameter that that End User did not agree to
be reflected in the relevant Access Agreement for that End User following a
request from Aurizon Network to amend the Access Agreement to incorporate
that System Operating Parameter in accordance with clause 7A.12.
(f) On 13 January 2023 (Review Point), if requested by an End User, at least 30
days prior to the Review Point, the QCA must consider whether the Rebate
mechanism as described in this clause 7A.6 is achieving the Rebate Objectives
(Review).
(g) For the purposes of clauses 7A.6(f), 7A.6(h), 7A.6(i), 7A.6(j) and 7A.6(k),
“Rebate Objectives” means:
(i) provision of comprehensive and transparent information, and support by
Aurizon Network for the Independent Expert’s work in relation to the
determination of the Rebate;
(ii) accurate, reliable and timely root cause analysis of the reasons why an
End User’s Train Service Entitlements are unable to be ordered, are
ordered but not provided, or are not utilised; and
(iii) timely and effective provision of an individual Rebate to End Users
calculated in accordance with clause 7A.6(b) in circumstances where an
End User has received less than their Train Service Entitlements in a
Year due to an AN Performance Breach.
(h) In conducting a Review, the QCA must seek submissions from End Users,
Aurizon Network, the Independent Expert and Train Operators on whether they
-- 47 of 49 --
consider the Rebate Objectives, have been met in a material way, including
supporting evidence.
(i) The QCA must determine, on the basis of the information received under clause
7A.6(h) and any other information reasonably available to the QCA, whether
the Rebate Objectives have been met in a material way.
(j) If the QCA considers that the Rebate Objectives have not been met in a material
way, the QCA must review the Rebate mechanism and:
(i) determine whether amendments can be made to the Undertaking in order
to ensure that the Rebate Objectives are achieved;
(ii) publish any recommended amendments referred to in clause 7A.6(j)(i);
(iii) provide End Users, Aurizon Network, the Independent Expert and Train
Operators with a reasonable opportunity to make submissions on the
QCA’s recommended amendments under clause 7A.6(j)(ii) within a
time period specified by the QCA; and
(iv) provide a final decision on recommendations for End Users and Aurizon
Network to consider for inclusion in the Undertaking.
(k) In the event that:
(i) the QCA determines in the final decision referred to in clause 7A.6(j)(iv)
that the Rebate Objectives have not been met in a material way; and
(ii) within 90 days of the QCA’s final decision referred to in clause
7A.6(j)(iv) Aurizon Network has not submitted a draft amending access
undertaking that either:
(A) reflects the recommendations in the QCA’s final decision as to
changes required to the Undertaking; or
(B) is in a form that has been agreed by Aurizon Network and a
Majority of End Users, which must include all End Users that
requested the QCA undertake the Review,
(each, a Reset WACC Reduction Event),
the Undertaking will (without the need for any other action to be taken by
Aurizon Network or the QCA) be deemed to have been amended so that the
definition of ‘Reset WACC’ will, effective from the Reset Date, be amended
such that:
(iii) the reference to ‘6.3%’ in paragraph (a)(i) of the definition of ‘Reset
WACC’ is replaced with ‘6.0%’; and
(iv) the reference to ‘0.4%’ in paragraph (b) of the definition of ‘Reset
WACC’ is replaced with ‘0.1%’.
-- 48 of 49 --
(l) Aurizon Network must do all things reasonably required to give effect to a
deemed amendment under clause 7A.6(k), including making any other
necessary consequential amendments to this Undertaking.
(m) The QCA will endeavour to make its determination under clause 7A.6(j) by the
Reset Date.
(n) If a Reset WACC Reduction Event occurs then:
(i) clauses 7A.6(a) to 7A.6(e) will cease to apply with effect from the Reset
Date provided however that those clauses will continue to apply, to the
extent required, with respect to any Rebates that accrued during the
period prior to the Reset Date; and
(ii) Aurizon Network must do all things reasonably required to give effect
to clause 7A.6(n)(i), including making any other necessary
consequential amendments to this Undertaking.
(o) To the extent that the Independent Expert determines that:
(i) Aurizon Network is liable to pay a Rebate and Aurizon Network does
not dispute that determination within 20 Business Days after the
Independent Expert makes its determination but fails to pay the Rebate
within the timeframe required by clause 7A.6(d); or
(ii) Aurizon Network failed to provide the information required for the
Independent Expert to make a decision as to whether a Rebate is payable
or to determine the Performance Rebate Amount,
the affected End User may raise a dispute under Part 11.
-- 49 of 49 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2023/167