Axicom Pty Ltd v Bonney [2023] QSC 113
SUPREME COURT OF QUEENSLAND
CITATION: Axicom Pty Ltd v Bonney [2023] QSC 113
PARTIES: AXICOM PTY LTD
ACN 090 873 019
(applicant)
v
JODIE MARIE BONNEY
(respondent)
FILE NO: BS No 8185 of 2022
DIVISION: Trial Division
PROCEEDING: Originating Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 25 May 2023
DELIVERED AT: Brisbane
HEARING DATE: 27 April 2023 and 28 April 2023
JUDGE: Cooper J
ORDERS: 1. Orders in the form set out in the schedule to these
reasons.
2. I will hear the parties as to costs.
CATCHWORDS: REAL PROPERTY – TORRENS TITLE – LEASES –
GENERALLY – where the applicant and respondent entered
into a lease to permit the applicant to construct and operate a
telecommunications tower on the respondent’s premises –
where the respondent refused to permit the applicant access to
her property pursuant to the lease – where the respondent
refused to grant an easement over part of the property which
the energy provider has sought – where the applicant seeks
specific performance of the lease – whether the applicant is
estopped from enforcing the terms of the lease, or is entitled to
relief for misleading and deceptive conduct, by reason of
representations made which the respondent says induced her to
enter into the lease – whether the applicant should be refused
relief because it does not hold all environmental approvals
which the respondent says are required for the construction of
the communications tower and the installation of the
underground electrical cabling
Competition and Consumer Act 2010 (Cth), Schedule 2
Electricity Act 1994 (Qld), s 111
Environment Protection and Biodiversity Conservation Act
1999 (Cth), s 18, s 18A, s 20A, s 67, s 67A, s 68
-- 1 of 31 --
2
Environmental Protection Act 1994 (Qld), s 9, s 14, s 16, s
17, s 18, s 79, s 107, s 426, s 437, s 438
Environmental Protection Regulation 2019 (Qld), Sch 2
Evidence Act 1977 (Qld), s 92(1)(b)
Nature Conservation Act 1992 (Qld), s 14, s 89
Nature Conservations (Plants) Regulation 2020 (Qld), s
47(c)(ii), s 48(b)(ii)
Yango Pastoral Company Pty Ltd v First Chicago Australia
Ltd (1978) 139 CLR 410, cited
Gynch v Polish Club Ltd (2015) 255 CLR 414, cited
COUNSEL: P Somers for the applicant
R W Tooth for the respondent
SOLICITORS: K&L Gates for the applicant
KJ Seaniger & Associates for the respondent
Introduction
[1] The respondent has leased part of her property located at 80 Clayton Road,
Lammermoor to the applicant. The execution of that lease, and its written terms, are
not in contention.
[2] The respondent’s property, more particularly described as Lot 2 on Registered Plan
843157, is a rural lot of approximately 9 hectares. The area leased to the applicant
comprises approximately 225m 2 (Premises).
[3] The purpose of the lease is to permit the applicant to construct and operate a
telecommunications tower on the Premises, approximately 300 metres from the
respondent’s house. At the time the lease was executed there was no electricity
connection to the Premises. That remains the current position.
[4] The applicant has been unable to undertake works required to construct the
communications tower because the respondent has refused to permit access to her
property. Further, the applicant has refused to grant an easement over part of her
property which the relevant energy provider, Ergon Energy Network (Ergon), has
sought from the applicant. That easement covers the proposed route along which
underground electrical cables are to be installed on the respondent’s property to
provide an electricity connection to the Premises.
[5] By this proceeding, the applicant seeks specific performance of the respondent’s
obligations under the lease.
Issues
[6] The issues which were argued at trial fall broadly into the following areas:
(a) whether the respondent is required by the terms of the lease to do the things
which are the subject of the relief sought;
(b) whether the applicant is estopped from enforcing the terms of the lease by
reason of representations it made which the respondent says induced her to
-- 2 of 31 --
3
enter into the lease, or whether the respondent is entitled to relief under
Schedule 2 of the Competition and Consumer Act 2010 (Cth) (Australian
Consumer Law) with similar effect based on misleading and deceptive
conduct;
(c) whether the applicant should be refused relief because it does not hold all
environmental approvals which the respondent says are required for the
construction of the communications tower and the installation of the
underground electrical cabling.
Relevant terms of the lease
[7] The lease,1 which commenced on 13 October 2020, defined the Premises by reference
to an area hatched on a site plan of the respondent’s property.2
[8] Clause 5 of the lease addresses the use of the Premises. Clause 5.1 provides that the
applicant must use the Premises for the purposes of “constructing, maintaining and
operating a communications facility and incidental uses.” Clause 5.2 grants the
applicant the right to use so much of her property adjoining and adjacent to the
Premises “as is reasonably required during the installation, erection, construction,
dismantling, repair, replacement, renewal, maintenance and operation of the
Premises” for that permitted purpose.
[9] Clause 5.3 then addresses cabling on the respondent’s property in the following terms:
“5.3 Cabling
The Lessor grants to the Lessee, its sub-tenants and licensees the right
to install, maintain, repair, replace and use on the Land above or below
ground cabling to and from the Premises during the Term … and
where necessary to construct supports for such cabling. In exercising
its rights under this clause the Lessee must:
(a) provide the Lessor with proposed plans of the location of
cabling by way of notice, subject to final approval and
requirements of the relevant power authority;
(b) not cause any lasting material damage to the Land or material
interference to the Lessor; and
(c) restore the surface of the Land as used as nearly as practicably
possible to its state prior to use by the Lessee, its sub-tenants
and licensees to the Lessor’s reasonable satisfaction. …”
[10] A second, incorrectly numbered, cl 5.1 then provides that the respondent must sign
all documents and do all things reasonably necessary to authorise or assist the
applicant in obtaining consent or approval from any government agency to use or
develop the Premises for the construction and operation of the communications tower.
1 Affidavit of Michael Patrick Byrnes filed 12 July 2022 (Court document 2), pages 1 to 25 of exhibit
MPB-1.
2 Ibid, page 20 of exhibit MPB-1, forming part of Annexure B to the lease.
-- 3 of 31 --
4
[11] By cl 6.1 of the lease, the respondent grants the applicant the right to enter onto and
access her property “at any time during the day and night … for the purpose of
accessing the Premises and exercising its rights” under the lease.
[12] Clause 9 of the lease addresses the electricity supply to the Premises, in the following
terms:
“9 ELECTRICITY SUPPLY
(a) To enable the Lessee to use the Premises for the Permitted Use,
the Lessor must at the Lessee’s request and cost:
(1) connect the Premises to an electricity supply (including
making provision for and allowing connection to
emergency back-up power); and
(2) install on the Land such earthing apparatus as is necessary
for the safe continuous use of the Lessee’s Equipment for
the Permitted Use.
(b) The Lessor must provide the Lessee with all consents,
approvals, rights and easements necessary to enable the
Premises to be connected to an electricity supply. …”
[13] Clause 15.2 provides that the applicant may carry out what are called “Lessee’s
Works” on the Premises and adjoining land as necessary. The scope of the Lessee’s
Works is relevantly described in Annexure C to the lease as follows:
“All of the Lessee’s works to install on the Premises an operational
communications facility, including but not limited to the following
works:
1 the obtaining of any required planning and other consents with
respect to the Lessee’s access to, use and occupation of the
Premises and Land and any installation on the Premises or Land
in that regard;
2 the installation on the Land of above or below ground cabling
(including fibre optic cabling) to and from the Premises and
where necessary the construction of supports for such cabling;
…
4 the connection of the Premises to an electricity supply
(including making provision for and allowing connection to
emergency back-up power); and
5 the installation on the Land of such earthing apparatus as is
necessary for the safe continuous use of the Lessee’s Equipment
for the Permitted Use.”
[14] The applicant relies on those terms of the lease in claiming relief which, in summary,
comprises:
(a) orders compelling the respondent to:
-- 4 of 31 --
5
(i) grant access to the Premises and so much of her property as is reasonably
required to enable the applicant to undertake the work involved in
constructing and commissioning the communications tower;
(ii) permit, and not interfere with, the work involved in constructing and
commissioning the communications tower;
(b) an order requiring the respondent to deliver signed copies of an easement and
a consent to survey plan which, on the applicant’s case, is required to enable
the work involved in constructing and commissioning the communications
tower to be undertaken;
(c) an order authorising the Registrar of the court to execute the easement and the
consent to survey plan in the event that the respondent fails to do so.
[15] After the commencement of the proceeding, the respondent withdrew a consent she
had previously executed which concerned the clearing of vegetation from the
Premises and the proposed access track and cabling route. There was evidence that,
as a consequence of the respondent withdrawing her consent, an officer of the
Queensland Department of Resources informed the respondent that he had decided to
withdraw a notification concerning the clearing of vegetation on the respondent’s
property.3 The notification in question is an instrument provided to the department
by the applicant, not a permit issued by the department. Consequently, the effect of
this “withdrawal” is not entirely clear. To remove all doubt, the relief sought by the
applicant now also includes an order compelling the respondent to deliver a further
signed consent to clearing of vegetation from her property such that a fresh
notification of the intent to clear vegetation may be provided to the Department of
Resources. The respondent did not object to the applicant seeking that further relief.
The respondent’s arguments concerning entitlement under the lease
[16] The respondent’s position is that, even if the terms of the lease are enforceable against
her, the applicant is not entitled to the relief it seeks in the circumstances of this case.
[17] There are two bases to that argument. First, the applicant asserts that, contrary to cl
5.3(b) of the lease, the installation of the cabling which the applicant has proposed to
connect the Premises to the electricity supply will cause lasting material damage to
her property or material interference to her use and enjoyment of the property.
Secondly, she argues that, contrary to cl 9(b) of the lease, it is not necessary for
cabling to be installed along the route proposed by the applicant in order to enable the
Premises to be connected to the electricity supply.
Clause 5.3(b) “lasting material damage” or “material interference”
[18] The proposed route for the laying of underground electrical cabling is shown on an
overhead photograph of the respondent’s property and surrounding properties.4 It
commences at the point at which the respondent’s property joins Clayton Road, at the
top right hand corner of the photograph, and proceeds in a westerly direction along a
narrow strip of land which the respondent referred to in her evidence as the “category
A area” and which is used by her as the driveway into her property. The driveway
3 Affidavit of Jodie Marie Bonney filed 22 March 2023 (Court document 25), exhibits DN-1 and DN-2.
4 Exhibit 2. The proposed route is shown by the orange line referred to as “Easement SP332715”.
-- 5 of 31 --
6
has a short dog-leg to the south before continuing westward towards a property
identified on the photograph as Lot 1 on RP843157. At that point it turns south and
continues towards the respondent’s house.
[19] The proposed route for the cabling does not follow the driveway as far as the
respondent’s house. At a point just south of the southern boundary of Lot 1 on
RP843157 it turns in a south-westerly direction and follows what was described in
the evidence as an “access track” to the Premises where the communications tower is
to be constructed. In part at least, that access track is to follow an existing track which
is wide enough to allow a vehicle to travel along it. The respondent gave evidence
that she uses that existing track to get to the back of her property.5
Lasting material damage
[20] The process of installing the electrical cabling will involve the digging of a trench
along the proposed route that is approximately 500mm wide and 1000mm deep, into
which the applicant will install a PVC pipe conduit for the cabling. The applicant
will then backfill the trench and reinstate the surface of the land. The backfilling
process involves the installation of a rubber “tracer”, designed to prevent accidental
excavation into the conduit, which is to run along the route about 300mm above the
conduit. To limit the area affected by the construction works at any one time, the
applicant will undertake the process of digging the trench, installing the conduit and
the tracer, and backfilling in sections of approximately 10m to 15m.
[21] That work will inevitably involve some damage to the respondent’s property.
However, I accept the submission made by Mr Somers, who appeared as counsel for
the applicant, that cl 5.3 of the lease contemplates some damage resulting from the
installation of below ground cabling. The applicant is not required to install the
cabling in a manner which causes no damage at all to the respondent’s property. It is
only prohibited from causing damage which satisfies the descriptors “lasting” and
“material” within the meaning of cl 5.3(b).
[22] In his closing address, Mr Tooth, who appeared as counsel for the respondent, argued
that the proposed electrical cabling met that description because there was no
obligation on the applicant to remove the electrical cabling once the lease has expired.
This argument relied upon cl 10.3(a) of the lease which limits the applicant’s
obligation to remove its equipment to items up to a depth of 500mm below ground.
[23] I am unable to accept that submission. As a matter of construction, the parties’
acceptance that, at the expiry of the lease, the applicant would be free to leave in place
any equipment located below the specified depth of 500mm suggests that, considered
objectively, the parties did not regard such equipment as causing any lasting impact
on the respondent’s property. Even if that were not the case, I accept the evidence of
Mr Peter Burke, the applicant’s project director for the construction of the
communications tower on the respondent’s property, that, notwithstanding the fact
that there is no obligation under the lease, the applicant would remove the electrical
cabling upon the expiry of the lease.6
5 Transcript 1-80:33-43.
6 Transcript 1-37:1-20.
-- 6 of 31 --
7
[24] A further submission directed towards establishing that the proposed work would
cause lasting material damage to the respondent’s property, made in the respondent’s
written outline of argument,7 relied on her property having significant environmental
value. In his closing address, Mr Tooth did not raise the environmental effect of the
proposed works in the context of cl 5.3(b) of the lease, but the submission was not
expressly abandoned.
[25] The submission relies upon numerous reports created when the respondent undertook
searches of her property on a variety of government databases. The relevant reports
are described as:
(a) EPBC Act Protected Matters Report created 11 March 2023, obtained from the
Commonwealth Department of Climate Change, Energy, the Environment and
Water;8
(b) Matters of State Environmental Significance Report created 1 March 2023,
obtained from the Queensland Department of Environment and Science
(QDES);9
(c) WildNet Records Conservation Significant Species List created 1 March 2023,
obtained from QDES;10
(d) WildNet Records Species List created 1 March 2023, obtained from QDES;11
(e) Wildlife Online Extract created 9 February 2021, obtained from the
Queensland Department of Science, Information Technology and Innovation.12
[26] Each of these documents provides information going to the likelihood that flora and
fauna covered by relevant environmental legislation would be present on the
respondent’s property. For example, the EPBC Act Protected Matters Report
identifies plants, animals and birds considered to be endangered, vulnerable or
threatened species which “may occur”, which are “likely to occur” and which are
“known to occur” within the relevant area.
[27] The applicant objected to the tender of these reports, through the respondent, as
hearsay statements relied on as to the truth of their contents concerning the presence
of endangered species of plants or animals on the respondent’s property. I accept that
the respondent does not have personal knowledge of the information used to create
the government databases from which the reports were created. When the objection
was raised on the afternoon of the first day of trial, I invited Mr Tooth to consider that
question overnight in order to identify any basis upon which the respondent wished
to argue that the reports could be admitted under an exception to the rule against
hearsay.13 Ultimately, Mr Tooth did not press any exception to the hearsay rule as a
basis for the tender of the reports.14
7 Court document 37, paragraph 39. That written outline was not prepared by counsel who appeared for
the respondent at the hearing of the originating application.
8 Affidavit of Jodie Marie Bonney filed 22 March 2023 (Court document 25), exhibit CR1. “EPBC
Act” refers to the Environmental Protection and Biodiversity Conservation Act 1999 (Cth).
9 Ibid, exhibit MSES1.
10 Ibid, exhibit DS1.
11 Ibid, exhibit DS2.
12 Ibid, exhibit DS3.
13 Transcript 1-61:5 to 1-62:11.
14 Transcript 2-4:1 to 2-5:6.
-- 7 of 31 --
8
[28] I reserved my ruling on the admissibility of the reports at that time to consider for
myself whether any relevant exception to the hearsay rule might apply. In taking that
course, I had in mind s 92(1)(b) of the Evidence Act 1977 (Qld) which permits the
admission in certain circumstances of a document which:
“… is or forms part of a record relating to any undertaking and made
in the course of that undertaking from information supplied (whether
directly or indirectly) by persons who had, or may reasonably be
supposed to have had, personal knowledge of the matters dealt with in
the information they supplied…”
[29] The term “undertaking” is relevantly defined to include “public administration and
any … undertaking” engaged in by the Crown (in right of the State of Queensland or
any other right), or by a statutory body.
[30] While the form of the reports themselves might be sufficient to support a finding that
they form part of a record relating to an undertaking, no evidence was led about the
sources of the information recorded in the government databases from which the
reports were created. In those circumstances, I am unable to be satisfied that the
reports, and the databases from which they were created, were made from information
supplied by persons who had, or may reasonably be supposed to have had, personal
knowledge of the presence or otherwise of particular species of flora and fauna on the
respondent’s property. For that reason, I uphold the applicant’s objection in respect
of the reports referred to in [25] above.
[31] Even if I had admitted those reports, I would not have been satisfied that they support
a finding that the environmental impact of the proposed works would be such as to
cause lasting material damage within the meaning of cl 5.3(b) of the lease. The
reports contain disclaimers as to the accuracy or reliability of the information drawn
from the government databases. Both the EPBC Act Protected Matters Report and
the Matters of State Environmental Significance Report contain statements to the
effect that the information provided in the reports should only be relied upon as a
general guide. Further, the Matters of State Environmental Significance Report
expressly stated that a field survey may be required to validate the information drawn
from the database. Had I concluded that the reports were admissible, I would not
have placed significant weight on the general information in those reports, without
evidence of the process by which the database was created and the reliability of the
information sources used in that process.
[32] In this case there was evidence of a field survey having been undertaken on the
respondent’s property. The applicant engaged a company called Eco Logical
Australia Pty Ltd (Eco Logical) to prepare an ecological assessment of the impact of
the construction of the communications tower and the installation of necessary
infrastructure, including the underground electrical cabling.
[33] On 16 and 17 March 2021, Mr Jarman, an ecologist then employed by Eco Logical,
attended and inspected the respondent’s property by walking around it for a total of
13 hours, including along the length of the proposed access track from the point where
it turned away from the respondent’s driveway to the point where it reached the
Premises. This inspection was undertaken for the purpose of:
-- 8 of 31 --
9
(a) identifying and quantifying the occurrence of endangered, vulnerable or
threatened plant species identified from desktop research as potentially
occurring or known to occur within the area;
(b) mapping regulated categories of vegetation and recording the location of
mature trees within the area impacted by the construction, including a 10 metre
buffer;
(c) recording the presence of animal habitat by reference to habitat preferences of
species identified as likely to occur based on desktop research.
[34] The observations which Mr Jarman made during his survey, and the data he collected,
were set out in an ecological assessment report issued by Eco Logical on 9 June
2021.15 Although he was involved in the preparation of that report, Mr Jarman left
Eco Logical approximately a month before it was finalised and issued. Nevertheless,
Mr Jarman confirmed in his evidence that the report accurately set out the
methodology he adopted in inspecting the respondent’s property, his observations
from that inspection and the identity, location and extent of the species he observed
on the property.
[35] Paragraph 4.2.1 of the report records that Mr Jarman observed two endangered
species of plant on the property, Cycas ophiolitica and Macrozamia serpentina. The
location where each species was observed is recorded in Figure 5. Neither species
was observed within the area that will be impacted by the construction work.
Nevertheless, the report stated that the work would require a permit to clear regulated
vegetation.16 Table 5 of the report also sets out a suite of mitigation and management
measures developed to mitigate the environmental impact of the work.
[36] The impact of the construction work is described in section 5 of the report, as follows:
“5.1.1. Clearing and earthworks
5.1.1.1. Flora
Clearing vegetation and subsequent earthworks will be required to
allow for the establishment of the project infrastructure, as shown in.
Vegetation within and surrounding the impact area has been identified
as RE 11.11.15 (least concern) which occurs as both Category B
remnant vegetation and Category C regrowth vegetation (see Figure
5). 0.24 ha of proposed clearing will occur within regrowth areas, to
allow for construction of the telecom tower. The project impact area
covers 0.01 ha of Category A, 0.23 ha Category B vegetation and 0.24
ha of Category C vegetation. There will be no clearing or impact
within Category A vegetation as the access track is already established
in this area.
As the access track is pre-existing (Figure 12), and any additional
clearance required will be limited to the 10 m buffer area to meet the
requirements of the [Vegetation Management] Act, impacts to
vegetation due to clearance and earthworks for the access tack [sic]
will be minimal. The total amount of regulated vegetation required to
15 Affidavit of Steven Jarman filed 19 April 2023 (Court document 38), exhibit SJ-1.
16 Ibid, section 3.2.3 at page 15 of the report.
-- 9 of 31 --
10
be cleared for the project is approximately 0.5 ha; there are no habitat
trees within the 10 m buffer area; and there will be limited clearing of
native trees.
Two significant flora species were identified onsite, Cycas ophiolitica
and Macrozamia serpentina; however, direct clearance of these
species will not be required. The proposed impact area is however
within 100 m of the identified endangered species and therefore,
clearing of the impact area is considered an indirect impact on the
protected plants under the Nature Conservation (Plants) Regulation
2020: Protected Plants Assessment Guidelines (NC Reg. PPAG).
Cycas ophiolitica was found within disturbed (regrowth) vegetation,
while Macrozamia serpentina was found within remnant vegetation to
the south of the impact area.
Given that the total clearance required for the project will be minimal
(approximately 0.5 ha), the impact area is largely already disturbed,
and the surrounding remnant vegetation exists as a patch within a
highly fragmented landscape, it is unlikely that the vegetation
clearance will result in a significant loss or fragmentation of habitat
for the protected plants and impact the survival of the protected plants
in the area.
5.1.1.2. Fauna
There was a total of eight significant fauna species considered likely
or having the potential to occur in the Project Area. A majority of the
clearing will occur within disturbed regrowth habitat which is not
considered core habitat for the species; and large areas of high value
remnant vegetation to the west of the site will be retained, with only
minimal clearing for the access track required. Significant impacts to
fauna species due to the loss and or fragmentation of habitat as a result
of clearing for the project are therefore considered unlikely.
Clearing and construction works pose a direct threat to fauna species
present in the impact area due to injury or mortality from vehicle or
machinery strike. These impacts will be mitigated and managed as
outlined in Section 6.
5.1.2. Habitat degradation or species disturbance
Construction activities can increase access by feral predators (e.g. wild
dogs, cats and foxes) to areas of retained vegetation and habitat
thereby increasing the level of predation. Additionally, clearing of
vegetation may force fauna to move through cleared areas to reach
suitable habitat. These altered movement patters may result in
increased predation of threatened species by feral predators, causing
injury and mortality; however, no pest species have been recorded in
the Project Area.
In addition to disturbance caused by vegetation clearing, the
construction phase for the Project has the potential to disturb habitat
and species through dust emissions, noise and vibration impacts and
light emissions.
-- 10 of 31 --
11
The hydrology of the site will not be significantly impacted due to
construction and given the small impact area and the implementation
of mitigation and management measures (Table 5), changes to water
quality and sediments loads are not likely to occur due to construction
activities.
Inappropriate disposal of liquid and solid waste, including spills and
leaks from transfers (fuel, chemicals) and inadequate storage of wastes
may result in contamination of surrounding land. Direct impacts may
include toxic impacts on vegetation (resulting in degradation or loss
of habitats) and direct toxic impact on fauna (from contact, inhalation,
or ingestion).
Given the suite of mitigation and management measures being
implemented during construction (see Table 5), it is unlikely that any
significant impacts to environmental values as a result of habitat
degradation or species disturbances are likely to occur.”
[37] I accept that these conclusions, which are based upon Mr Jarman’s detailed field
study, accurately describe the environmental impact of the proposed work. I prefer
that evidence to the more general statements the respondent made about the impact
of the work.17
[38] The environmental mitigation measures identified by Eco Logical were subsequently
incorporated in an impact management plan for the construction of the
communications tower.18
[39] The applicant included the impact management plan, along with a protected plant
report prepared in August 2021 based on Mr Jarman’s observations, with its
application to the QDES for a clearing permit in respect of the proposed works.19
[40] QDES issued a clearing permit to the applicant on 23 November 2021.20 That permit
approves the clearing of vegetation within the 0.5 hectare area of the respondent’s
property referred to in the extract from section 5.1.1.1 of the ecological assessment
report set out above. However, the permit prohibits the clearing of the two
endangered plant species identified during Mr Jarman’s field study and imposes a
condition that the applicant undertake clearing activities in accordance with the
procedures and actions outlined in Eco Logical’s impact management plan, including
the environmental mitigation and management measures contained in that report.
[41] Having regard to the conclusions reached in the ecological assessment report set out
above, and the conditions imposed on the clearing permit based upon the results of
the field study undertaken by Mr Jarman, I do not accept the submission that the
environmental impact of the proposed construction work meets the description of
17 For example, see the affidavit of Jodie Marie Bonney filed 22 March 2023 (Court document 25),
paragraph 4.
18 Affidavit of Andrew McLane filed 6 September 2022 (Court document 17), pages 91 to 124 of exhibit
AM-1.
19 Affidavit of Andrew McLane filed 6 September 2022 (Court document 17), pages 41 to 124 of exhibit
AM-1.
20 Affidavit of Andrew McLane filed 6 September 2022 (Court document 17), pages 125 to 128 of exhibit
AM-1.
-- 11 of 31 --
12
“lasting material damage” to the respondent’s property within the meaning of cl
5.3(b) of the lease.
Material interference
[42] The respondent submitted that “material interference” was established in
circumstances where the easement sought by the applicant will prevent her
subdividing part of her property near the entrance from Clayton Road into at least
four eco-friendly residential allotments.21
[43] The respondent’s evidence indicated that her subdivision proposal would create the
residential allotments in the “category A area” used by the respondent as the driveway
into her property (see [18] above).22 As the respondent stated in cross-examination,23
that area has an existing right of way easement over it in favour of Lot 1 on
RP843157.24
[44] Nothing in the evidence explains how the respondent’s proposed subdivision of that
area would accommodate the right of way easement in favour of her existing
neighbour or her own need for access from Clayton Road. Absent such evidence it is
difficult to see how the easement which the applicant seeks for the proposed cabling
route, over the same driveway area, creates any greater obstacle to subdivision than
the existing right of way easement.
[45] On the evidence, I am not satisfied that the easement sought by the applicant would
constitute “material interference” within the meaning of cl 5.3(b).
Clause 9(b): whether the easement sought by the applicant is “necessary”
[46] The respondent’s property is currently connected to the electricity grid through an
overhead power line that extends from Clayton Road, across the neighbouring
properties to the east of the respondent’s property, before connecting to the
respondent’s house.
[47] Mr Farrell, a project manager for the applicant, gave evidence that this existing
overhead power line does not have capacity to supply power to the communications
tower, even if that line was extended from the respondent’s house to the Premises. I
accept that evidence, which was not challenged in cross-examination. It is consistent
with a notation on a location plan provided by Bill Limpus of Ergon25 to Mr Farrell
which stated, in reference to the existing overhead power line connecting to the
respondent’s house:26
“Our Low Voltage calculations fail due to the distance from the
Transformer to the proposed Tower Site. Have tried using different
conductor types but the LV Drop is still outside stat limits.”
21 Affidavit of Jodie Marie Bonney filed 18 August 2022 (Court document 11), paragraph 16.
22 Affidavit of Jodie Marie Bonney filed 24 August 2022 (Court document 13), exhibit ED-1.
23 Transcript 1-66:1-2.
24 That right of way easement is recorded as Easement A on Registered Plan 843157. Affidavit of Sui
Ann Lim filed 4 August 2022 (Court document 4), pages 23 to 24 of exhibit ASL-1.
25 Ergon being the only electricity supplier in the area where the respondent’s property is located.
26 Affidavit of Paul Farrell filed 4 August 2022 (Court document 3), page 3 of exhibit PF-1.
-- 12 of 31 --
13
[48] The applicant applied to Ergon for an electrical connection to the Premises. There
was evidence that, following this application, Ergon investigated whether the
overhead power line to the respondent’s house could be upgraded to provide the
necessary capacity. In an email sent on 15 March 2021,27 Mr Limpus informed the
applicant that the neighbouring property owners, over whose land the power line
travelled, had refused to give their consent to the installation of an upgraded power
line. Mr Farrell responded to that email on 17 March 2021, asking whether it would
be possible for Ergon to provide the upgraded connection through a power line
installed along the driveway into the respondent’s property.28
[49] On 13 April 2021, Mr Limpus informed Mr Farrell that Ergon had determined that it
was possible to provide power to the Premises from a power line installed along the
driveway provided the respondent’s consent was obtained.29
[50] In May 2021, Mr Limpus informed Mr Farrell during a telephone conversation that
Ergon would proceed to install the upgraded power line along the driveway, subject
to Ergon and the applicant entering into Ergon’s standard “Network Connection
Contract” and associated documents.30
[51] Ergon provided a copy of the “Network Connection Contract” for the proposed
electricity connection to the Premises on 11 June 2021.31 Clause 6.2(i) of the
Negotiated Connection Establishment Contract (Site Specific Terms) provided by
Ergon requires that the applicant provide an easement from the respondent in favour
of Ergon covering the proposed route for the new underground cable route.32
[52] On 14 October 2021, Ergon provided to the applicant a copy of the form of easement
it required.33 It is that form of easement which the applicant now seeks to compel the
respondent to provide.
[53] In written submissions, the respondent argued that these communications are not
sufficient to establish that the easement is “necessary” to enable the Premises to be
connected to the electricity supply.34 Two bases were advanced for that argument.
[54] The first basis concerns the wording of the email from Ergon which attached the form
of easement it required. That email, which was sent by a member of Ergon’s property
services team, stated: “I am not across this project but I think that you [the applicant]
are proposing to register an easement over freehold lands for underground
infrastructure.” It was sent in response to an email from Mr Farrell which indicated
he had been directed by Mr Limpus to the property services team to assist with the
process of obtaining an easement for the new underground power supply.
27 Ibid, pages 2 to 3 of exhibit PF-1.
28 Ibid, page 4 of exhibit PF-1.
29 Ibid, pages 7 to 8 of exhibit PF-1.
30 Ibid, paragraph 11.
31 Ibid, pages 11 to 39 of exhibit PF-1.
32 Ibid, page 35 of exhibit PF-1.
33 Ibid, pages 40 to 52 of exhibit PF-1.
34 Court document 40, paragraphs 13 to 15. These submissions were prepared by counsel who did not
appear at the trial. Mr Tooth did not press this submission in closing address, but did not expressly
abandon it.
-- 13 of 31 --
14
[55] In my view, the fact that Ergon’s property services team had not, to that point in time,
been involved in the project and did not have knowledge of details beyond those
provided in Mr Farrell’s email inquiry does not matter. The understanding expressed
in the email as to the nature of the proposed easement was correct. Consequently, I
am satisfied that the form of easement which was provided to Mr Farrell is a
requirement of Ergon before it provides the electrical connection to the Premises.
[56] The second basis arises from the fact that the applicant has not yet signed any contract
with Ergon for the establishment of the electrical connection through the proposed
underground cabling. In cross-examination, Mr Farrell accepted that it was possible
that, in circumstances where Ergon has not yet commenced designing the
underground cabling, the plans for that cabling could change in the future.35 I did not
understand that to be a concession that a route other than the one now proposed by
the applicant would be chosen for the electrical cabling required to provide the
connection to the Premises. On the evidence, there is no other route which could be
adopted without the consent of neighbouring landowners and that consent has already
been sought and been refused.
[57] I am satisfied that the proposed route for the underground cabling along the driveway
area of the respondent’s property is the only means of installing an electrical
connection to the Premises. I am also satisfied that the easement is necessary to
enable the Premises to be connected to an electricity supply, it being a requirement
of Ergon before it provides that electrical connection.
Conclusion on the respondent’s obligations under the lease
[58] I do not accept the respondent’s arguments concerning the application of cll 5.3(b) or
9(b) of the lease.
[59] I am satisfied that the respondent is obliged:
(a) by cll 5.2, 5.3, 6.1 and 9(a) of the lease, to grant access to the Premises and so
much of her property as is reasonably required to enable the applicant to
undertake the work involved in constructing and commissioning the
communications tower and to permit, and not interfere with, the work involved
in constructing and commissioning the communications tower;
(b) by cl 9(b) of the lease, to deliver signed copies of the easement and the consent
to survey plan sought by the applicant to enable the work involved in
constructing and commissioning the communications tower to be undertaken;
(c) by the second (incorrectly numbered) cl 5.1 of the lease, to deliver a further
signed consent to clearing of vegetation from her property.
[60] By denying the applicant access to her property and refusing to deliver signed copies
of the documents referred to above, the respondent has breached her obligations under
the lease. As the lease involves a disposition of an interest in the land, the equitable
remedy of specific performance is available on the basis that damages alone may be
an inadequate remedy. For those reasons, subject to the further matters raised by the
respondent considered below, I am satisfied that the applicant is entitled to the relief
it seeks.
35 Transcript 1-23:5-23.
-- 14 of 31 --
15
The alleged representations: estoppel or misleading and deceptive conduct
[61] The respondent’s estoppel argument is based upon a representation36 she asserts was
made to her, prior to the execution of the lease, to the effect that the only power source
required for the communications tower would:
(a) be from the power pole adjacent to her house which connects her property to
the existing low voltage overhead power lines (see [46] above);
(b) only follow the route identified in pre-lease negotiations; and
(c) come from no other source.
The respondent’s evidence
[62] On the respondent’s evidence, the representation was made during a visit to her
property by two representatives of the applicant, David Hughes and Peter Burke, on
29 April 2020. The respondent swore two affidavits in which she gave evidence about
what occurred during the site visit.
[63] In her first affidavit, sworn on 8 August 2022, the respondent deposed as follows:37
“The first site meeting with Axicom was held with the [sic] David
Hughes and Peter Burke who appeared to have more technical
knowledge than David Hughes. They mentioned to me the Company
already had some plans where the site would be and after walking the
area it was worked [sic] where the Tower would go. During this
discussion I was told it would be a 10 x 10 m square site with a 25 m
single poll [sic] and that the power would come from my house. I was
concerned and the three of us then walked over to the house and looked
at the power there. We had a discussion concerning the route the
power line would take. I was told a power Expert from an independent
company could come out and do an assessment. I was asked to be
home at the time of the proposed visit. …”
[64] The respondent provided a more detailed account of that visit in her second affidavit,
sworn on 19 August 2022:38
“On the 29 April 2020 there was the first site visit by David Hughes
and Peter Bourke. They were looking at the power pole beside the
house. Peter Bourke was examining the top of the pole and said to me
‘that is good you have 3 phase power’. I said ‘really I didn’t know
that, that’s great’ We chatted about that and he explained amps to me
and that this power was sufficient for the type of power required
required [sic] by using the words spoke [sic] about the power required
for the tower.
The three of us went to view the actual tower site. I said to them ‘how
much land do you need to use and how big would the site be’ David
Hughes stated ‘it will only be a 10x10 site’ and Peter Bourke agreed
36 Court document 39, paragraph 5.
37 Affidavit of Jodie Marie Bonney filed 18 August 2022 (Court document 11), paragraph 4.
38 Affidavit of Jodie Marie Bonney filed 24 August 2022 (Court document 13), paragraphs 4 to 9.
-- 15 of 31 --
16
by nodding his head and saying ‘yes that [sic] right’. David Hughes
said ‘it will be a 25 meter [sic] high single pole tower so not much
higher than those tree tops so it’s only a small site’ I said ‘ok, will you
have to clear those trees’ and I pointed to a line of maturing native
eucalyptus and Norfolk pine trees close to my boundary line about 15
meters [sic] in height.’ I sensed they could see this bothered me and I
was scanning the vegetation in the area of the site. They said ‘We
don’t know and are not sure’. I then said ‘I don’t think I can do that if
they (the trees) had to go because the [sic] they are not in the way. It
was clear by the words ‘do that’ I meant allow the tower to be built.
At the same meeting I told them ‘there has been illegal excavation to
the front of the property at [sic] front entrance to Clayton Street.’ I
asked both of them but mainly directed to Peter Bourke ‘so you
wouldn’t need to have anything to do with any other area of my
property?’. They both assured me they would not, by saying ‘no We
don’t’ and David Hughes said ‘We only need access to get in and out.’
At the same site inspection We discussed the options of the potential
power line route (to take power from my House power pole back to
the Tower). I asked them again ‘you’re telling me that no other area
of my property will be affected apart from the site and needing an
access track in somewhere from the house to the back where the site
would go?’. They both nodded and agreed saying ‘that’s right’ and
David Hughes said ‘yes that is correct and we will maintain the access
tracks at our own expense for the term of the lease’. We returned to
the power pole beside my house. Peter Bourke said something like,
‘we can use this power from here and run a line to the site’ and
mentioned 3 phase power again. Peter Bourke said ‘the power source
was good and power won’t be a problem, that’s good’.
At the same meeting David Hughes said to me ‘Pete … knows his stuff
and has worked on a lot of different projects and has extensive
experience with building tower sites. Peter is the main man on a large
number of the [sic] Axicom’s thousands of towers’. I was convinced
Peter Bourke was an Expert and from that tome onwards I had no
doubt the Power supply was coming from the House power pole.
During our discussions Peter Bourke displayed a great deal of
knowledge of exactly what would happen. I had confidence in what
he said.
… It was said to me by Peter Bourke ‘the power supply was ‘perfect’
at 63 amps 3 phase Low Voltage and that there would be no
interruption to my property power supply or any changes to household
power supply’. …”
The applicant’s evidence
[65] By the time of this proceeding, Mr Hughes no longer had any recollection of the detail
of the discussion he and Mr Burke had with the respondent at the site visit. He only
recalled having a high level discussion about the respondent’s preferences for the
-- 16 of 31 --
17
potential location of the proposed tower.39 In cross-examination, Mr Hughes
specifically denied the proposition that he had avoided reference to high voltage
power lines in later communications with the respondent because he knew that, prior
to entering into the lease, he had agreed with the respondent that the power source for
the site would be low voltage.40 Otherwise, Mr Hughes confirmed in cross-
examination that he did not recall the detail of the discussions at the first site visit.41
[66] Mr Burke’s evidence42 was that, at the time of the first site visit, he was aware that
the specific route and specification for the electrical cabling to the proposed tower
site would ultimately depend on the requirements of Ergon, the only electricity
network owner in the area, and those requirements would only be confirmed as the
project progressed. He deposed that, when he visited the respondent’s property with
Mr Hughes on 29 April 2020, he did not know if the existing power supply to the
respondent’s property would be sufficient for the proposed communications tower.
[67] Mr Burke’s recollection of the first site visit was as follows:43
(a) he told the respondent that the applicant would pay for its own power and
would not be relying upon the respondent’s power supply;
(b) the respondent asked that the applicant adopt a route that did not require
clearing, or at least minimised the amount of clearing, and for that purpose they
discussed and walked along a number of different potential routes for the power
supply to the site before ultimately discussing with the respondent that the route
could not be determined during that visit;
(c) the respondent stated that if the applicant was going to do anything to her
driveway, which is dirt, that she wanted the applicant to add bitumen to a
section of it when performing the make-good, and the applicant agreed to that;
(d) consistently with his general practice, he said to the respondent:
(i) Ergon was the power provider present in the area;
(ii) an application for power supply to the tower site would need to be made
through Ergon;
(iii) finalising the route for the electrical cabling and final site design would
require some further steps and would have to be determined later;
(e) in response to an indication from the respondent that she would prefer the
electrical cabling to run underground, he said to her that the applicant could
run the power underground but the exact route it would take was not known at
that time and is always noted as “indicative” on the design;
(f) neither he nor Mr Hughes made any statements to the respondent to the effect
that the electrical cabling that would ultimately be necessary would be of any
particular specification, size or take any particular route;
39 Affidavit of David Hughes filed 6 September 2022 (Court document 15), paragraph 3.
40 Transcript 1-26:26 to 1-27:24.
41 Transcript 1-27:26-28; 1-27:42 to 1-28:2; 1-29:1-10.
42 Affidavit of Peter Burke filed 6 September 2022 (Court document 16), paragraphs 5 to 7.
43 Ibid, paragraphs 8(a) to (h).
-- 17 of 31 --
18
(g) he did state words to the effect that “we ensure that each operator has a
minimum of 63 amp or 3 phase at the site location to operate on its own”.
[68] As to the matters deposed to by the respondent, Mr Burke:44
(a) denied that he stated words to the effect that the “power was sufficient for the
site”, in circumstances where he did not know Ergon’s network requirements
at that time and he knew that site designs are susceptible to change;
(b) denied that the respondent stated that there had been illegal excavation at the
front of her property, but recalls that she said words to the effect that she was
“in court with a developer over taking soil and dumping soil on her land” and
that she had “won that fight in court”;
(c) denied that there was any decision taken or agreement made to take power from
the power pole next to the respondent’s house, but recalls stating to the effect
that it was good that the respondent had a 3 phase supply running to her house
because it meant that there was 3 phase power supply in the area;
(d) denied that the respondent sought confirmation that no area of her property
would be affected other than the proposed site and an access track, or that he
(or to his recollection, Mr Hughes) provided such confirmation;
(e) denied that he stated word to the effect that “we can use this power from here
and run a line to the site”;
(f) denied that he gave any indication to the respondent as to “exactly what would
happen”;
(g) recalled telling the respondent that the electrical cables could be installed
underground and saying words to the effect that the type of supply the applicant
needed to run its equipment is 3 phase supply and that the applicant would not
impact her house supply;
(h) did not recall Mr Hughes saying the words attributed to him by the respondent
concerning Mr Burke’s knowledge and experience.
Written communications after the site visit
[69] On 1 May 2020, Mr Hughes sent an email to the respondent with various documents
attached.45
[70] One of the attachments was a photograph showing a route, marked by an orange line,
between the power pole near the respondent’s house to the site proposed for the
communications tower.46 In cross-examination, Mr Hughes stated that, although he
had not prepared the markings on the photograph (Mr Burke had), his understanding
was that the orange line represented “the indicative potential power”.47 Mr Burke
was not shown the marked-up photograph, or asked any questions about it, during his
cross-examination.
44 Ibid, paragraphs 8(i) to (l); Transcript 1-34:17-18; 1-34:29-42; 1-35:1-27; 1-36:36-39.
45 Affidavit of David Hughes filed 6 September 2022 (Court document 15), pages 1 to 8 of exhibit DH-
2.
46 Ibid, page 6 of exhibit DH-2.
47 Transcript 1-28:41-44.
-- 18 of 31 --
19
[71] On 19 May 2020, Mr Hughes sent a further email to the respondent attaching what
he described as “the preliminary design” for her review and approval if satisfactory.48
The respondent confirmed in cross-examination that she read the email when she
received it and carefully reviewed the plans attached to it.49
[72] That preliminary design consisted of three drawings: a “Draft Site Layout” which
provided an overall view of the respondent’s property; a “Draft Site Elevation” which
provided a side view of the proposed design of the communications tower and its
surrounding infrastructure; and a “Draft Property Layout” which provided a plan view
of the proposed tower site itself.
[73] The “Draft Site Layout” contained the following notes:
“1. BASIS OF DESIGN
SITE INSPECTION 29/04/2020
…
9. POWER SUPPLY
PROPOSED 63 AMP 3-PHASE LV SUPPLY TO BE
PROVIDED TO SITE (DETAILS TO BE
CONFIRMED/ADVISED)”
[74] It also depicted a route for electrical cabling, similar to that shown in the earlier
marked up photograph, between the power pole near the respondent’s house and the
proposed site for the tower. That route bore the following notation:
“PROPOSED UNDERGROUND ELECTRICAL APPROX 300m
(INDICATIVE ONLY) ROUTE (TBC)”
[75] The same notation appeared on the “Draft Property Layout”. The “Draft Site
Elevation” referred to the route identified in the preliminary design as “PROPOSED
U/G POWER SUPPLY ROUTE (APPROX. 300m – TBC)”.
[76] On 17 June 2020, the respondent sent an email to Mr Hughes which attached a
document containing comments from the respondent’s solicitor on a draft lease
provided by the applicant.50 That document included the following comment on cl
5.3 of the draft lease which dealt with electrical cabling:51
“Note 5.3 Cables -- plan to be given to Lessor, --- position of Cables -
-- any Excluded position of cables”
[77] On 30 June 2020, Mr Hughes sent an email to the respondent providing the
applicant’s response to the matters raised by her solicitor in relation to the draft
lease.52 The solicitor’s comment concerning the cabling was addressed in paragraph
17 of the email as follows:
48 Exhibit 1.
49 Transcript 1-71:40 to 1-72:3.
50 Affidavit of David Hughes filed 6 September 2022 (Court document 15), pages 42 to 49 of exhibit
DH-2.
51 Ibid, page 49 of exhibit DH-2.
52 Ibid, pages 60 to 62 of exhibit DH-2.
-- 19 of 31 --
20
“Cables – This will be a part of the FC Drawings (for construction)
and will be available as Axicom progresses with the power authority
etc. Axicom can agree to provide the proposed plans noting location
of cables to the Lessor, however, final location will be subject to the
relevant power authority’s approval and requirements.
Cables are generally placed to avoid any future interruption (i.e. along
building edges and access tracks / fence lines, rather than straight
across land).”
[78] That the respondent accepted the applicant’s position on the issue of the cabling as
set out in this exchange of correspondence can be seen in the inclusion of the words
“subject to final approval and requirements of the relevant power authority” in the
final form of cl 5.3(a) of the lease extracted at [8] above.
[79] Further, a version of the preliminary plan provided to the respondent on 19 May 2020,
which retained the notations referred to in [73] to [75], was included as the “Premises
Plan” in Annexure B of the lease.53
Findings as to the making of the representation
[80] On the evidence, it is clear that there was some discussion during the site visit of the
existing power supply to the respondent’s property, including the fact that this was a
3 phase supply. I am also satisfied that there was some discussion of a potential route
by which power to the tower site could be connected to the grid through the existing
power pole near the respondent’s house, as shown in the marked-up photograph and
the preliminary design which were sent to the respondent after the site visit. However,
I am not satisfied that Mr Burke or Mr Hughes made any representation during the
site visit to the effect that the only source of connecting the tower site to the electricity
network would be the power pole near the respondent’s house, or that the electrical
cabling required to connect the tower site would only follow the route identified in
pre-lease negotiations. On those questions, I prefer the evidence of Mr Burke to that
given by the respondent as to what was said during the site visit. My reasons for
reaching that conclusion are set out below.
[81] First, I accept Mr Burke’s evidence that at the time of the site visit he did not know
what Ergon’s requirements for the installation of an electrical connection to the tower
site would be and that, in those circumstances, it was not his practice to make
definitive statements about such matters at the commencement of a tower
construction project. That evidence was not challenged in cross-examination. It
would be surprising if a person in Mr Burke’s position did not adopt the practice he
described. In circumstances where Ergon’s requirements were not known, it is
inherently unlikely that Mr Burke would have made definitive statements of the kind
which the respondent attributed to him.
[82] Secondly, the respondent’s account of the discussion at the site visit is inconsistent
with the notations on the preliminary design which stated that the electrical cabling
route shown on that design was “indicative only” and “to be confirmed”. Those
notations reflect the potential for changes as the project progresses and the applicant
is informed of Ergon’s requirements for the electrical connection. Likewise, the
53 Affidavit of Michael Patrick Byrnes filed 12 July 2022 (Court document 2), pages 20 to 22 of exhibit
MPB-1.
-- 20 of 31 --
21
respondent’s evidence that she was told that an expert from an independent power
company would attend her property to perform an assessment of the existing power
supply (see [63] above) is not consistent with Mr Burke or Mr Hughes having made
the definitive statements she attributes to them.
[83] During cross-examination, the respondent rejected the suggestion that these matters
were consistent with the qualified nature of the statements made by Mr Burke and Mr
Hughes during the site visit. She asserted that, after the site visit, the applicant, and
particularly Mr Hughes, repeatedly confirmed to her that the power to the tower site
would come from the power pole near her house.54
[84] The respondent gave evidence in cross-examination that she had queried Mr Hughes
as to why words such as “preliminary” and “indicative” were used on the design
provided to her, given what she called the “guarantee”55 given by the applicant during
the site visit. She said Mr Hughes told her this was simply part of the applicant’s
process, but that it was always clear that the power to the tower site would be coming
from the power pole near her house.56 I do not accept the respondent’s evidence about
these matters. She did not refer in her affidavits to having questioned Mr Hughes
about the inclusion of the words “indicative” or “to be confirmed” on the preliminary
design, or to Mr Hughes’ response to such queries. Nor were those matters put to Mr
Hughes in cross-examination.
[85] The respondent also gave evidence of her understanding that the descriptors
“indicative” and “to be confirmed” on the preliminary design were because the route
for the electrical cabling between the house power pole and the tower site had not
been confirmed.57 I do not accept that explanation. It does not take account of the
fact that the applicant did not know Ergon’s requirements. I also note that this aspect
of the respondent’s evidence appears to be inconsistent with her case, as expressed in
the List of Issues, concerning the making of a representation that the electrical cabling
would only follow the route identified in pre-lease negotiations.58
[86] The respondent’s evidence about having been told that an independent expert would
assess the existing power supply to her property and the description of the electrical
cabling route on the preliminary design both support Mr Burke’s account of the
discussion during the site visit.
[87] Thirdly, the respondent’s conduct in accepting the applicant’s position regarding the
wording of what became cl 5.3(a) of the lease (see [77] - [78] above) is not consistent
with her account of the discussion during the site visit. There is no evidence that the
respondent ever complained, whether directly or through her solicitor, that the
54 Transcript 1-68:16-24; 1-68:43 to 1-69:4; 1-73:16-24; 1-89:3-35. At several points during her cross-
examination the respondent expressed her evidence differently, saying that after the first site visit up
to (as I understood her evidence) her entry into the lease the applicant gave no indication that it might
need to connect the tower site to the electrical grid by some means other than the house power pole –
see Transcript 1-74:17-18 and 1-75:16-19. Even if that evidence is accepted it falls short of the
definitive, positive statement upon which the respondent’s estoppel and misleading and deceptive
conduct case was based.
55 Transcript 1-81:7-13.
56 Transcript 1-71:4-20; 1-76:10-46.
57 Transcript 1-72:25-36; 1-81:1-16.
58 Court document 39, paragraph 5(b).
-- 21 of 31 --
22
position the applicant took in that exchange contradicted any statements Mr Burke or
Mr Hughes had previously made to her.59
[88] The respondent said in cross-examination that Mr Hughes had told her not to worry
about this issue and that it was all “just legal jargon”.60 Again, that evidence was not
included in her affidavits, and it was not put to Mr Hughes in cross-examination. I
do not accept it.
[89] The position taken by the applicant in the exchange of correspondence concerning cl
5.3 of the draft lease, and the respondent’s acceptance of that position without
complaint, support Mr Burke’s account of the discussion during the site visit.
[90] Fourthly, the respondent agreed after the lease had been executed to change the route
for the electrical cabling. That agreement was given after the respondent had walked
around the property with a surveyor engaged by the applicant and identified the route
which allowed for minimal clearing of vegetation.61 I note that this agreement
preceded the proposal to install underground cabling along the respondent’s
driveway. It involved a variation of the route between the house power pole and the
tower site. I have already explained why I do not accept the respondent’s explanation
that the precise route between the house power pole and the tower site remained
subject to confirmation, but the connection to the power supply through the house
power pole was a constant. In my view, the respondent’s agreement to vary the
electrical cabling route, even though it still involved a connection to the house power
pole, reflects the prospect that such details could change over the course of the project
and that the respondent was aware of that prospect.
Reliance on the alleged representation
[91] My finding that the applicant did not make the representation alleged by the
respondent is sufficient to dispose of the respondent’s case that the applicant ought
be estopped from relying upon its rights under the lease or that the respondent is
entitled to similar relief under the Australian Consumer Law for misleading and
deceptive conduct.
[92] Even had I not reached that conclusion, I accept the applicant’s submission that the
exchange of correspondence about cl 5.3 in the draft lease in June 2020, before the
lease was executed, means that reliance upon any earlier representation concerning
the electrical cabling route would not have been reasonable.
[93] The respondent was unwilling or unable to explain what she understood was meant
by the statement in paragraph 17 of the applicant’s email of 30 June 2020 that the
final location of electrical cabling would be “subject to the relevant power authority’s
approval and requirements”.62
[94] In my view that statement, the substance of which was repeated in cl 5.3(a) of the
lease the parties executed, could only be reasonably understood as indicating to the
respondent that, regardless of what might have passed between the parties previously,
59 Transcript 1-89:3-29.
60 Transcript 1-90:8-10. See also 1-87:34 to 1-88:15.
61 Affidavit of Jodie Marie Bonney filed 22 March 2023 (Court document 25), exhibit PF2; Transcript
1-79:22 to 1-80:43.
62 Transcript 1-88:1-13.
-- 22 of 31 --
23
the location of the electrical cabling might change if that was necessary to
accommodate Ergon’s requirements. Having been told that prior to executing the
lease, and having agreed to it by her entry into the lease containing cl 5.3(a), I would
not have accepted the respondent’s evidence that she relied upon the alleged
representation even if I was satisfied that the applicant made the representation.
[95] That is a further reason why the respondent’s arguments concerning estoppel and
misleading and deceptive conduct do not prevent the applicant from seeking to
enforce its rights under the lease.
Environmental approvals
[96] The issues identified for determination in the List of Issues are framed as follows:63
“6. Whether, before the applicant is entitled to the relief sought in
the Originating Application, the applicant is required to hold the
statutory approvals and permissions that the respondent has
contended in sections 13 to 16 of her submissions dated 11 April
2023 are required to construct the Communications Tower and
install the Electrical Cabling.
7. Whether the applicant has the statutory approvals and
permissions required to undertake the work to construct the
Communications Tower and install the Electrical Cabling, or
whether the applicant will in constructing the Communications
Tower and installing the Electrical Cabling breach:
(a) Environment Protection and Biodiversity Conservation
Act 1999 (Cth), sections 18, 18A and 20A;
(b) Nature Conservation Act 1992 (Qld), section 89;
(c) Electricity Act 1994 (Qld), section 111;
(d) Environmental Protection Act 1994 (Qld), sections 426,
437 and 438.”
Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act)
[97] Section 18 of the EPBC Act prohibits a person from taking an action that has had, or
will have, or is likely to have, a significant impact on:
(a) a listed threatened species included in one of four specified categories;64 or
(b) a listed threatened ecological community included in one of two specified
categories.65
[98] Civil penalties are provided for action taken in breach of the prohibition.
[99] Section 18A of the EPBC Act provides that a person commits an offence if the person
takes an action that results, or will result, in a significant impact, or is likely to have
63 Court document 39.
64 The categories are: “extinct in the wild” under s 18(1); “critically endangered” under s 18(2);
“endangered” under s 18(3); and “vulnerable” under s 18(4).
65 The categories are “critically endangered” under s 18(5) and “endangered” under s 18(6).
-- 23 of 31 --
24
a significant impact, on a species that is a listed threatened species or an ecological
community that is a listed threatened ecological community. Such offences are
punishable on conviction by imprisonment, a fine or both.
[100] Section 20A of the EPBC Act provides that a person commits an offence if the person
takes an action that results, or will result, in a significant impact, or is likely to have
a significant impact, on a species that is a listed migratory species. Again, such
offences are punishable on conviction by imprisonment, a fine or both.
[101] None of these sections impose a requirement on a person to obtain an approval.
However, the effect of ss 67 and 67A of the EPBC Act is that a person must not take
an action prohibited by any of ss 18, 18A or 20A without obtaining an approval.
[102] The respondent relies upon the reports created when she undertook searches of her
property on government databases (identified in [25] above) to argue that one or more
of ss 18, 18A or 20A prohibit the work required to construct the tower and install the
electrical cabling without an approval under the EPBC Act. She further argues that
the applicant should be denied the relief it seeks in circumstances where the lease,
although lawful according to its own terms, may be performed in a manner prohibited
by statute.66
[103] I have ruled the reports upon which the respondent seeks to rely inadmissible (see
[27] to [30] above). The only other evidence led about environmental matters is of a
very general nature. For example, the respondent deposed that a number of
endangered plant and wildlife species are present on her property, including a large
resident colony of echidnas.67 She also deposed that a number of protected species
of plant occur throughout her property and the area that would be affected by the
tower project. That evidence does not, however, descend to identifying the location
of any of these protected species and so does not, in my view, provide a basis to
conclude that the work required to construct the tower and install the electrical cabling
will engage the statutory provisions.
[104] Put simply, there is insufficient evidence for me to be satisfied of the matters which
would engage the operation of the sections the respondent relies upon under the EPBC
Act. That is, there is insufficient evidence for me to conclude that the work involved
in constructing the tower and installing the electrical cabling:
(a) will have, or is likely to have, a significant impact on a listed threatened species
or a listed threatened ecological community in one of the relevant categories;68
(b) will result in, or is likely to have, a significant impact on a species that is a
listed threatened species or an ecological community that is a listed threatened
ecological community;69
(c) will result in, or is likely to have, a significant impact on a species that is a
listed migratory species.70
66 Yango Pastoral Company Pty Ltd v First Chicago Australia Ltd (1978) 139 CLR 410, 413 [3]; Gynch
v Polish Club Ltd (2015) 255 CLR 414, 424-5 [35]. In this regard, the respondent also referred to ss
196 and 196A of the EPBC Act which also create criminal offences.
67 Affidavit of Jodie Marie Bonney filed 18 August 2022 (Court document 11), paragraph 3.
68 EPBC Act s 18.
69 EPBC Act s 18A.
70 EPBC Act s 20A.
-- 24 of 31 --
25
[105] Then there is evidence suggesting that the work does not engage the provisions of the
EPBC Act. The respondent herself deposes to having spent two days with a qualified
ecologist employed by the applicant (presumably Mr Jarman) and a surveyor
concentrating on “mapping out the particular area to be used for the power line so
that there would be minimal disruption to the wildlife and trees…”71 That occurred
after the lease had been executed and, as already referred to in [90] above, resulted in
a change in the proposed route for the electrical cabling to follow the existing access
track to the back of the respondent’s property. That change, and the evidence of Mr
McLane (which I accept) that the work to install the electricity cabling along the
driveway from Clayton Road will not result in any clearing of vegetation,72 suggest
that the work is unlikely to engage the provisions of the EPBC Act.
[106] Further, I note that the ecological assessment report issued by Eco Logical on 9 June
2021 stated that, in circumstances where the tower project is unlikely to result in a
significant impact to any Matters of National Environmental Significance, it was not
considered necessary to refer the proposed work under the EPBC Act.73
[107] Having regard to the available evidence, I am not satisfied that:
(a) the applicant is required to hold an approval under the EPBC Act before it
would be entitled to the relief it seeks; or
(b) if it undertakes the work required to construct the tower and install the electrical
cabling without an approval under the EPBC Act, the applicant would breach
any of the provisions of the EPBC Act identified by the respondent.
Nature Conservation Act 1992 (Qld)
[108] Section 89 of the Nature Conservation Act prohibits a person from taking a protected
plant that is in the wild unless the plant is taken under, inter alia, a licence, permit or
other authority issued or given under a regulation.
[109] Clearing is not permitted within 100 metres of a protected plant unless a permit is
obtained.74
[110] The field survey undertaken by Mr Jarman identified the presence of two protected
plant species within 100 metres of proposed clearing. It was for that reason that the
ecological assessment report issued by Eco Logical on 9 June 2021 identified the need
for the applicant to apply for a clearing permit from the QDES (see [35] above). As
I have already noted (see [40] above), the applicant has obtained that permit.
[111] Having regard to that evidence, I am not satisfied that:
(a) the applicant is required to hold any additional approval or permit under the
Nature Conservation Act before it would be entitled to the relief it seeks; or
71 Affidavit of Jodie Marie Bonney filed 18 August 2022 (Court document 11), paragraph 6. See also
the affidavit of Jodie Marie Bonney filed 24 August 2022 (Court document 13), paragraph 10.
72 Transcript 1-40:39-46; 1-41:11-28.
73 Affidavit of Steven Jarman filed 19 April 2023 (Court document 38), exhibit SJ-1, section 3.3.1 on
page 19 of the report. As to the referral process, see s 68 of the EPBC Act.
74 Nature Conservations (Plants) Regulation 2020 (Qld), ss 47(c)(ii) and 48(b)(ii).
-- 25 of 31 --
26
(b) if it undertakes the work required to construct the tower and install the electrical
cabling without any additional approval or permit under the Nature
Conservation Act, the applicant would breach any of the provisions of that
legislation.
Electricity Act 1994 (Qld)
[112] Section 111(1) of the Electricity Act provides that an electricity entity must not build,
replace or alter electric lines or other works in a “protected area” unless the entity acts
under a written agreement of the Minister administering the Nature Conservation Act.
[113] The term “protected area” is defined in Schedule 5 of the Electricity Act to mean a
protected area under the Nature Conservation Act.
[114] Section 14 of the Nature Conservation Act then lists 10 classes of protected areas to
which that Act applies: five classes of national parks; conservation parks; resources
reserves; special wildlife reserves; nature reserves; and coordinated conservation
areas.
[115] There is no evidence that the respondent’s property falls within one of those classes
such that it is a protected area for the purposes of the Nature Conservation Act or the
Electricity Act. This was accepted by Mr Tooth in his closing address.75
[116] Even if I had admitted the reports created when the respondent undertook searches of
her property on government databases, the reports created from QDES databases
would not have assisted the respondent. Those reports include a locality map
identifying the location of protected areas. All the identified areas are outside the
boundaries of the respondent’s property.76 Those reports also include the following
in the section titled “Summary Information”:77
“Protected Area(s)
No estates or reserves are located within the area of interest [that being
a reference to the respondent’s property].”
[117] On that basis, I am not satisfied that:
(a) Ergon is required to obtain a written agreement of the Minister administering
the Nature Conservation Act before the applicant would be entitled to the relief
it seeks; or
(b) if Ergon installs the underground electrical cabling without obtaining a written
agreement of the Minister administering the Nature Conservation Act, it would
breach s 111(1) of the Electricity Act.
75 Transcript 2-45:12-24.
76 Affidavit of Jodie Marie Bonney filed 22 March 2023 (Court document 25), exhibit DS-1 at page 2
and exhibit DS-2 at page 2.
77 Ibid, exhibit DS-1 at page 3 and exhibit DS-2 at page 3.
-- 26 of 31 --
27
Environmental Protection Act 1994 (Qld)
[118] The respondent’s written submissions refer to s 426, which provides that a person
must not carry out an “environmentally relevant activity” unless the person holds, or
is acting under, an environmental authority for the activity.
[119] The term “environmentally relevant activity” is defined in s 18 to include three classes
of activity. Two of those classes could not apply to the applicant’s project.78 The
third class is an activity prescribed as an environmentally relevant activity by
regulation. The power to prescribe an activity by regulation is conferred by s 19
which requires that:
(a) the release of a contaminant when the activity is carried out will, or may, cause
environmental harm; or
(b) the activity will, or may, otherwise adversely affect an environmental value of
the marine environment; or
(c) the activity be carried out in a relevant Great Barrier Marine Park area.
[120] The respondent’s written submissions, which were prepared by counsel who did not
appear at the trial, do not identify any regulation which has the effect of making the
applicant’s tower project an “environmentally relevant activity” for the purpose of s
426 of the Environmental Protection Act. Having reviewed Sch 2 of the
Environmental Protection Regulation 2019 (Qld), I am unable to see how the
applicant’s tower project could be considered an environmentally relevant activity.
[121] The respondent’s written submissions also address ss 437 and 438 of the
Environmental Protection Act. Section 437 makes it an offence for a person to
unlawfully cause serious environmental harm. Section 438 makes it an offence for a
person to unlawfully cause material environmental harm.
[122] The concept of “environmental harm” is defined broadly in s 14 of the Environmental
Protection Act to mean “any adverse effect, or potential adverse effect (whether
temporary or permanent and of whatever magnitude, duration or frequency) on an
environmental value”. Section 9 provides that an “environmental value” is “a quality
or physical characteristic of the environment that is conducive to ecological health or
public amenity or safety”.
[123] “Material environmental harm” is defined in s 16 and “serious environmental harm”
is defined s 17. It is not necessary to consider those definitions in detail. The
respondent’s written submissions did not address, by reference to any admissible
evidence, how the work involved in constructing the tower and installing the electrical
cabling came within either definition. During his closing address, Mr Tooth (who did
not prepare the written submissions) accepted that the evidence did not support a
finding that the work would amount to an offence under the Environmental Protection
Act.79 Having regard to the matters I have discussed at [24] to [41] above, that
concession was appropriate.
78 The applicant’s project is not an “agricultural ERA” (see ss 18(a) and 79) nor is it a “resource activity”
(see ss 18(b) and 107).
79 Transcript 2-46:6-9.
-- 27 of 31 --
28
Conclusion on environmental approvals
[124] I am not satisfied that the applicant is required to hold any further statutory approvals
to construct the tower and install the electrical cabling, or that such construction and
installation would breach the environmental legislation upon which the respondent
sought to rely.
Summary and orders
[125] I am not satisfied that any of the matters raised by respondent preclude the grant of
the relief sought by the applicant.
[126] I will make orders in the form set out in the schedule to these reasons.
[127] I will hear the parties as to costs.
-- 28 of 31 --
29
SCHEDULE
THE ORDER OF THE COURT IS THAT:
The following definitions apply in this order:
(a) Land means Lot 2 on Registered Plan 843157, located at 80 Clayton Road,
Lammermoor;
(b) Lease means registered lease number 720638047 dated 13 October 2020 and
any extension, renewal or replacement thereof (including any additional or
renewed term) in respect of the Premises;
(c) Permitted Use means the use of the Premises for the purpose of constructing,
maintaining and operating a communications facility and incidental uses;
(d) Premises means Lease P on SP323626, as described in the Lease;
(e) Works means:
(i) constructing, maintaining and operating a communications facility and
incidental uses on the Premises;
(ii) installing, maintaining, repairing and using on the Land, above or below
ground, cabling (including any cabling to provide power sufficient to
construct, maintain and operate a communications facility and incidental
uses on to the Premises) and where necessary to construct supports for
such cabling;
(iii) connecting the Premises to any electricity supply sufficient to construct,
maintain and operate a communications facility and incidental uses on to
the Premises;
(iv) installing, or doing all things necessary to install, on the Land such
earthing apparatus as is necessary for the use of any of the applicant’s
equipment on the Premises; and
(v) the installation of an access track connecting from the existing tracks or
driveway on the Land to the Premises, along the approximate route
shown as Easement Q on the Consent to Survey Plan set out in Annexure
B to the Originating Application filed 12 July 2022, and works incidental
thereto, in so far as it is necessary for the purpose of constructing,
maintaining and operating a communications facility and incidental uses
on the Premises.
Access and Works
1. From on or before 4.00pm on the day seven clear days of the date of this order
and for the duration of the Lease, the respondent is to give the applicant (and
any sub-tenants or licensees of, or persons authorised by, or acting for and on
behalf of, or engaged by the applicant) free and unfettered access to the Land
and the Premises in order to:
(a) undertake the Works; and
(b) access and use the Premises during the Lease for the Permitted Use.
-- 29 of 31 --
30
2. The respondent is to permit, and not interfere with, the applicant (and any sub-
tenants or licensees of, or persons authorised by, or acting for and on behalf of,
or engaged by the applicant) to:
(a) undertake the Works; and
(b) access and use the Premises during the Lease for the Permitted Use.
3. In undertaking the Works, the applicant is to comply with the terms of the
Lease, any lawful requirement to obtain and hold any permit or approval from
any government authority, including in relation to the clearing of vegetation
and protection of the environment, necessary to undertake the Works.
Easement, consents and documents
4. On or before 4.00pm on the day seven clear days of the date of this order, the
respondent is to sign and deliver to the applicant (at its solicitors’ office or as
otherwise reasonably directed by the applicant) in a form capable of
registration:
(a) a Form 9 Easement in the form set out in Annexure A to the Originating
Application filed 12 July 2022;
(b) a Form 18A Consent to Survey Plan in the form set out in Annexure B to
the Originating Application filed 12 July 2022;
(c) a consent to exempt clearing on the Land under the Vegetation
Management Act 1997 (Qld) and Planning Regulation 2017 (Qld), in the
form set out in the letter from the applicant’s solicitors to the
respondent’s solicitors dated 29 March 2023.
5. Within seven clear days of the applicant requesting, in writing, the respondent
to provide the applicant with any other consents, approvals, easements or forms
necessary to enable the Premises to be connected to an electricity supply, or to
undertake the Works or use the Premises for the Permitted Use, the respondent
is to sign and deliver to the applicant (at its solicitor’s office or as otherwise
reasonably directed by the applicant), any such consent approval, easements or
form duly signed and executed.
6. It is declared that the applicant is irrevocably authorised, under the Lease, to
(on behalf of the Respondent) submit any application for consent or approval
to any government agency to use or develop the Premises for the Permitted
Use.
7. Pursuant to rule 899 of the Uniform Civil Procedure Rules 1999 (Qld) and the
court’s inherent jurisdiction, upon the applicant’s solicitors filing a written
request or affidavit of the applicant (or its solicitors) in a form acceptable to the
Registrar, the Registrar of the Supreme Court is authorised and appointed to
execute in place of the respondent:
(a) the Form 9 Easement and Form 18A Consent to Survey Plan referred to
in paragraphs 4(a) and 4(b) of this order;
(b) the consent referred to in paragraph 4(c) of this order;
-- 30 of 31 --
31
(c) any other consents, approvals, easements or form necessary to enable the
premises to be connected to an electricity supply or to undertake the
Works.
8. The respondent is prohibited from communicating any revocation or
withdrawal of any consent or approval referred to in this order or that the
respondent has previously provided in connection with the Lease or Works.
-- 31 of 31 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2023/113