Cape Byron Power 1 Pty Ltd & Ors v Downer Energy Systems Pty Limited & Ors [2023] QSC 76 (2023) 14 QR 104
SUPREME COURT OF QUEENSLAND
CITATION: Cape Byron Power 1 Pty Ltd & Ors v Downer Energy
Systems Pty Limited & Ors [2023] QSC 76
PARTIES: CAPE BYRON POWER I PTY LTD ACN 074 408 923
(formerly known as Delta Electricity Australia Pty Ltd)
and CAPE BYRON POWER II PTY LTD ACN 095 991
638 (formerly known as Sunshine Renewable Energy Pty
Ltd) as joint venturers in the Sunshine Electricity Joint
Venture
(first plaintiffs)
CAPE BYRON POWER II PTY LTD ACN 095 991 638
(formerly known as Sunshine Renewable Energy Pty Ltd)
(second plaintiff)
NEW SOUTH WALES SUGAR MILLING CO-
OPERATIVE LIMITED ACN 051 052 209
(third plaintiff)
v
DOWNER ENERGY SYSTEMS PTY LIMITED ACN
067 158 954
(first defendant)
DMH PLANT SERVICES PTY LTD ACN 010 975 256
(formerly known as MHPS Plant Services Pty Ltd and
Clyde Babcock-Hitachi Pty Ltd)
(second defendant)
DOWNER EDI LIMITED ACN 003 872 848
(third defendant)
FILE NO: BS 11011 of 2014
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 14 April 2023
DELIVERED AT: Brisbane
HEARING DATE: Written Submissions
JUDGE: Applegarth J
ORDER: 1. The period over which interest should be awarded
should be a period of 8 years between 10 July 2010 and
9 July 2018.
2. Direct the parties to calculate interest according to the
applicable Practice Direction rates for the relevant
period.
-- 1 of 18 --
2
CATCHWORDS: INTEREST – RECOVERABILITY OF INTEREST – IN
GENERAL – where the defendants allege that there were
unreasonable delays by the plaintiffs in initiating and
litigating its claims – where the defendants contend the
period of interest should be the period from 14 November
2019 to the date of judgment – where the plaintiffs contend
that the period of interest should be the total period of 12
years from the incident date when loss was first suffered to
the date of judgment – whether the plaintiffs’ delay was
unreasonable so as to warrant a reduction of the interest
awarded
Civil Proceedings Act 2011 (Qld), s 58
Uniform Civil Procedure Rules 1999, r 5
Bishopsgate Insurance Ltd (in liq) v Deloitte Haskins & Sells
[1999] 3 VR 863, cited
Brisbane South Regional Health Authority v Taylor (1996)
186 CLR 541, cited
Cape Byron Power 1 Pty Ltd & Ors v Downer Energy
Systems Pty Limited & Ors [2022] QSC 294, cited
Cerutti v Crestside Pty Ltd [2016] 1 Qd R 89, cited
Department of Transport v Chris Smaller (Transport) Ltd
[1989] AC 119, cited
Fulcher v Knott Investments Pty Ltd [2012] QSC 232, cited
Interchase Corporation Ltd (in liq.) v Grosvenor Hill
(Queensland) Pty Ltd (No. 3) [2003] 1 Qd R 26, cited
Jackamarra v Krakouer (1998) 195 CLR 516, cited
Latrobe Country Credit Co-operative Ltd v Smith [1999] 1
VR 44, cited
The Queen v Edwards [2009] HCA 20; (2009) 255 ALR 399,
cited
COUNSEL: Ms B O’Brien for the plaintiffs
Mr M T Hickey for the defendants
SOLICITORS: Carter Newell for the plaintiffs
Clayton Utz for the defendants
[1] The defendants accept that, in the light of my reasons,1 the first plaintiffs (“the
plaintiffs”) are entitled to judgment for a certain sum, namely, $2,230,447.2 They
also agree that the plaintiffs are entitled to an award of interest on that amount. The
Court has a discretion under s 58 of the Civil Proceedings Act 2011 (Qld) to give
interest “at the rate the court considers appropriate for all or part of the amount and
for all or part of the period between the date when the cause of action arose and the
date of judgment”.
1 Cape Byron Power 1 Pty Ltd & Ors v Downer Energy Systems Pty Limited & Ors [2022] QSC 294.
2 This differs slightly from the figure of $2,107,152 stated in [754], [806], and [844] of the reasons.
-- 2 of 18 --
3
[2] The usual practice of the Court is to apply the rates of interest prescribed in Practice
Directions for default judgments, and neither party suggests a departure from that
practice.
The issue
[3] The issue is the period over which interest should be calculated. The plaintiffs submit
that it should run from the incident date (5 July 2010) when loss was first suffered to
the date of judgment.
[4] The defendants submit that interest should not be awarded for that period because of
the plaintiffs’ unreasonable delay in initiating and litigating its claims to trial. They
submit that the period of interest should be from 14 November 2019 (when the matter
was placed on the Case Flow List) to the date of judgment.
[5] According to the defendants, the total period of about 12 years between the incident
in July 2010 and the trial in mid-2022 is prima facie excessive in the absence of an
explanation for the plaintiffs’ delay. They develop that submission by dividing the
period into five stages:
(a) the period from the grate failure (5 July 2010) until the commencement of the
proceedings (20 November 2014) (the pre-commencement stage);
(b) the period from the commencement of the proceedings (20 November 2014)
until service of the Claim and Statement of Claim upon the defendants (30 June
2015) (the delay in service);
(c) the period from service upon the defendants (30 June 2015) until the date of
receipt of a Case Flow Intervention Notice from the Court (14 November 2019)
(the initial stage);
(d) the period during which the matter was subject to the Case Flow review process
(from 14 November 2019) until the matter was listed on the Supervised Case
List (31 May 2021) (the Case Flow intervention stage); and
(e) the period between listing the matter on the Supervised Case List (31 May
2021) until the commencement of the trial (30 May 2022) (the Supervised
Case review stage).
[6] The plaintiffs submit that periods of delay are explained and that there is an
insufficient basis to deprive them of interest for any period since the incident. They
say that they have been kept out of the damages to which they are entitled, and the
defendants have had “the benefit of the money, and may be assumed to have put it to
good use”.3
Relevant principles
[7] An award of interest is not designed to punish a defendant for not having paid the
successful plaintiff sooner. Instead, its purpose is restitutionary and to compensate
3 Interchase Corporation Ltd (in liq.) v Grosvenor Hill (Queensland) Pty Ltd (No. 3) [2003] 1 Qd R 26
at 53 [61] (“Interchase”).
-- 3 of 18 --
4
the plaintiff for having been kept out of the use of money as a result of the defendant’s
wrong.4
[8] McPherson JA observed in Interchase:5
“In a perfect world, a defendant who injured a plaintiff would
immediately recognise the wrong done and pay the amount of
compensation but that ‘never happens in practice’ so the ‘justification’
for interest is to compensate for delay in payment.”
His Honour continued:6
“[i]t is…not immediately apparent why, as a matter of justice, that
delay should operate to defeat or reduce a plaintiff’s right to receive
interest…for the whole of the period during which the amount was not
paid. Quite apart from the loss to the plaintiff, the defendant has had
the benefit of the money, and may be assumed to have put it to good
use.”
[9] The Court of Appeal in Interchase,7 and subsequently in Cerutti,8 recognised that
“unreasonable delay in prosecuting the claim” may be one reason not to award interest
for the whole period. That is especially so in cases in which the plaintiff’s delay has
caused the defendant detriment.9
[10] In Cerutti McMurdo P and Gotterson JA agreed with my statement that:
“There is no rule that delay in itself restricts the period over which
interest may be awarded. Unreasonable delay may be taken into
account, but even in such a case, the plaintiff has been kept out of its
money for the entire period.”
[11] I went on to observe:10
“Reducing the period over which interest is awarded is not the most
appropriate device to ensure that a plaintiff conducts proceedings with
expedition, and the governing principle remains that interest is
awarded to compensate the plaintiff for having been kept out of money
from the date the cause of action accrues.”
[12] Little is to be gained by simply comparing the periods of delay in different cases that
have applied these general principles. For example, Cerutti was a simple defamation
case in the District Court in which the trial judge was entitled to take into account the
unexplained delay in taking seven years between the publication and the matter
coming on for trial. Interest was awarded over a period of five years. Interchase
involved a total period of 12 years. The trial judge in that case was satisfied that the
plaintiff had provided a detailed explanation as to why the proceeding was not
4 Interchase at 52-53 [59]-[61]; Cerutti v Crestside Pty Ltd [2016] 1 Qd R 89 at 120 [90] (“Cerutti”).
5 Interchase at 52 [59].
6 Interchase at 53 [61] (footnote omitted).
7 Interchase at 53-54.
8 Cerutti at 120 [90].
9 Fulcher v Knott Investments Pty Ltd [2012] QSC 232 at [165].
10 Cerutti at 123 [102] (emphasis added).
-- 4 of 18 --
5
instituted or brought to trial sooner than it was. That explanation included a lack of
funds due to the plaintiff’s insolvency and liquidation to which the defendants’
negligence must have contributed.
[13] There is no period fixed by law or by the authorities between the date when a cause
of action accrues and the date of trial, beyond which delay becomes unreasonable.
The finding of unreasonable delay depends upon the facts of each case, including its
complexity and what each party did to resolve it. Moreover, whatever period may
emerge from old authorities in comparable cases is an uncertain guide. Rules and
practices change, as do waiting times for matters to be set down for trial.
Developments have included the enactment of rule 5 of the Uniform Civil Procedure
Rules 1999 (“UCPR”).
[14] In some cases, the facts are reasonably ascertainable from the outset and there may
be no real issue on liability. Other cases are more legally and factually complex.
They require extensive investigation to ascertain if there is a viable claim and what
its quantum might be, to engage expert witnesses, to obtain legal advice, and for the
client to make commercial decisions about the merit of pursuing litigation that is
uncertain. In some cases, the anticipated aggregate legal costs of all the parties may
exceed the realistic quantum of the prospective claim. That said, every claim, whether
large and complex or small and simple, having been initiated is to be conducted
according to the implied undertaking that each party gives to the Court and to the
other parties to proceed in an expeditious way.11
[15] Although expressed in different legal contexts, including issues governing dismissal
for want of prosecution, it has been said that when a party starts proceedings at the
very end of the limitation period, there is an obligation to proceed with due
expedition, and any later delay is less likely to be excused.12
[16] One reason is the potential for prejudice from delay. Limitation periods have a variety
of justifications, and in certain circumstances they may be extended. The rules
permit, in certain circumstances, causes of action to be added after the expiry of a
relevant limitation period. McHugh J observed in Brisbane South Regional Health
Authority v Taylor13 that legislatures enact limitation periods because they make a
judgment that the chance of an unfair trial occurring after the limitation has expired
is sufficiently great to require termination of the plaintiff’s right of action at the end
of that period.
[17] It might be suggested that delay in starting a proceeding and delay after having
commenced cut both ways, and disadvantage the claimant that has the onus of proof
as much as it disadvantages the defendant. The loss of witnesses, documents, and
other detriments through delay may disadvantage a claimant as much as they
disadvantage a defendant. But that does not alter the general proposition that a party
that has unreasonably delayed commencing proceedings until close to the end of the
limitation period, is expected to proceed with due expedition once the proceeding is
commenced, and that a defendant can complain if the claimant does not do so.
11 UCPR, rule 5(3).
12 Department of Transport v Chris Smaller (Transport) Ltd [1989] AC 1197 at 1207-8; Bishopsgate
Insurance Ltd (in liq) v Deloitte Haskins & Sells [1999] 3 VR 863 at 874-5; Latrobe Country Credit
Co-operative Ltd v Smith [1999] 1 VR 440 at 445-6.
13 (1996) 186 CLR 541 at 555 (“Taylor”).
-- 5 of 18 --
6
[18] The law tolerates delay and the detriment suffered to a defendant by loss of evidence
during the limitation period, and for some period after it. In the context of the criminal
law, the High Court has observed that trials involve reconstruction of events and:14
“…it happens on occasions that relevant material is not available;
documents, recordings and other things may be lost or destroyed.
Witnesses may die. The fact that the tribunal of fact is called upon to
determine issues of fact upon less than all of the material, which could
reasonably bear upon the matter, does not make the trial unfair.”
The same general observation applies to the loss of relevant material during a
limitation period and during the course of civil proceedings. While the law tolerates
delay as an inevitable aspect of the initiation and conduct of complex cases, it should
not be so tolerant of unreasonable delay.
[19] The case for compensating the plaintiff for being kept out of the use of money for the
entire period that the defendant has had the benefit of that money is weakened where
the claimant has been responsible for unreasonable delay. One reason is that
unreasonable delay contributes to a diminution in the quality of evidence, and that
detriment may not be recognised, even by the parties.15 Whereas, specific prejudice
may be able to be identified, general prejudice may be inferred from a lengthy delay.
The longer the delay in commencing proceedings, and then in prosecuting them, the
more likely it is that the case will be decided on less evidence than would have been
available if the case had been commenced within a reasonable time and prosecuted
without unreasonable delay.
[20] Unreasonable delay adds to costs. So does forcing a matter to trial in an excessively
short period. Doing so may increase costs above the amount that would be incurred
during an optimal period for preparation for trial. Few proceedings are able to be
litigated over what, in retrospect, may be an optimal period in terms of minimising
aggregate costs. However, at a certain point, unreasonable delay in prosecuting a
claim or in defending it adds unnecessarily to costs. One aspect is the stop-start
process. Personnel, including legal representatives, witnesses, and representatives of
clients who are familiar with the matter, come and go. This adds to costs. Even if
the personnel remain constant, excessive delay means that they have to reacquaint
themselves with a matter after memories have faded and, to some extent, duplicate
work that has already been done.
[21] Defendants that encounter unexplained delay by a plaintiff in litigating a claim are
not without a remedy. They can protect themselves by making timely offers to settle
and seek directions, including in appropriate circumstances, guillotine orders. They
can apply for a proceeding to be case managed on a list such as the Supervised Case
List. In this matter the defendants did not do so. Instead, the matter was placed by
the Court on the Case Flow List. Both parties must share some responsibility for the
fact that there was no active case management between mid-2015 and late 2019.
[22] The fact remains, however, that the plaintiff is the party which is usually in the driving
seat. That is so, even if it is possible for a defendant to ask the court to direct the
14 The Queen v Edwards [2009] HCA 20 at [31]; (2009) 255 ALR 399 at 405.
15 Taylor at 551.
-- 6 of 18 --
7
plaintiff to not take the scenic route, and instead to reach the trial destination as soon
as is reasonably possible.
[23] A defendant which can point to actual prejudice as a result of unreasonable delay may
have a higher claim to the favourable exercise of the discretion to not award interest
over a certain period, than a defendant who cannot point to such a detriment.
However, where the proceeding has been unreasonably delayed by the plaintiff’s
conduct or inactivity, the discretion to confine the period over which interest is
awarded should not depend on the defendant proving specific detriment. Delay that
is attributed to the plaintiff is usually taken to have caused financial detriment to the
defendant. As Gummow and Hayne JJ stated in Jackamarra v Krakouer:16
“Delay in a case will almost always add to the costs.”
[24] The purpose of civil litigation, as stated in rule 5, namely the just and expeditious
resolution of the real issues in civil proceedings at a minimum of expense, is better
advanced by ensuring that unreasonable delay by a party in prosecuting or defending
a proceeding should have consequences. One such consequence is to deprive the
plaintiff of interest for part of the period in question.
Application of these principles
[25] These principles raise issues about:
(a) The periods of delay in the proceeding being ready for trial;
(b) The extent to which the plaintiff may be said to be wholly or partly responsible
for periods of delay;
(c) The plaintiff’s explanation for periods of delay;
(d) The extent to which the defendant contributed to delay, including by not
applying to have the matter actively case-managed; and
(e) The specific and general prejudice caused to the defendant by any unreasonable
delay by the plaintiff.
[26] The ultimate issue remains whether unexplained delay by the plaintiff should deprive
it of interest for part of the period that it has been kept out of the damages to which it
is entitled, and during which the defendants have had the benefit of that money.
[27] The following discussion of the lengthy history of the claim and the proceeding does
not recite the large amount of detail that appears in the parties’ respective
chronologies and their solicitors’ substantial affidavits relating to that history. The
chronologies are exhibited to the relevant affidavits. I will grant leave to the parties
to file their written submissions on interest and the associated chronologies. It is
convenient to address the various periods that are the subject of the parties’
submissions and evidence. In the following sections, I draw extensively upon the
parties’ written submissions as a convenient summary of that evidence.
16 (1998) 195 CLR 516 at 526 [29].
-- 7 of 18 --
8
Pre-commencement stage: 5 July 2010 – 20 November 2014
[28] The plaintiffs do not seek to claim interest for the period immediately after their
claims for breach of contract accrued. Understandably, they seek interest for the
period after 5 July 2010, when the breaches were productive of substantial loss.
[29] The defendants note that the proceeding was not filed until 20 November 2014, one
day short of six years after the Date of Practical Completion, which was the expiry of
the limitation period in contract. The plaintiffs explain their conduct during the
relevant period as follows:
“(a) despite the incident occurring on 5 July 2010, the plaintiffs did
not discover its cause until around 25 August 2010 and did not
complete the repairs (which the defendants partially carried out
and were paid for) until May 2011;
(b) during the period from May 2011 to November 2014:
(i) Carter Newell were instructed by AAI Limited t/as Vero
Insurance (the lead co-insurer) to commence a subrogated
recovery action against the defendants in March 2013;
(ii) the plaintiffs sent letters of demand to the defendants in May
2013;
(iii) the plaintiffs’ legal representatives carried out
investigations, interviews, gathered relevant material for the
purposes of preparing the claim, provided advice and
received instructions and documents, and attended a site
inspection at the BCP;
(c) the plaintiffs commenced the proceeding within the 6 year
limitation period of the contractual cause of action (as they were
entitled to do so).”
[30] The defendants say in response that although Carter Newell were instructed by the
insurer to commence a recovery action in March 2013, it is not clear whether those
were the first instructions received, or that Carter Newell was previously instructed
to advise or investigate the matter. I will assume that it had previously advised in the
matter, and that either it or loss assessors and other agents had advised the insurer
prior to March 2013.
[31] The essential point is that the cause or causes of the loss and damage were and
remained complex and controversial. The quantum and calculation of each plaintiff’s
claim under different categories of loss and damage also remained an area of
complexity.
[32] It was not unreasonable for a commercially-minded insurer considering the prospects,
costs, benefits and risks of pursuing a subrogated recovery action against the
defendants to carefully assess the matter and obtain advice. I am not persuaded that
the period that was taken to commence proceedings was unreasonable in all the
circumstances.
-- 8 of 18 --
9
[33] As for any prejudice caused by delay during this period, the alleged cause or causes
of the loss and who was responsible for the loss were the subject of meetings and
investigations by the parties shortly after the incident. Some matters might have been
agreed, but many remained in contention. The defendants had an opportunity to
assemble evidence and did so prior to May 2013, when the plaintiffs’ solicitors issued
letters of demand. Those letters advised that the plaintiffs’ solicitors were currently
liaising with their client to quantify any further losses. The defendants’
representatives denied liability in May 2013, and in June 2013 the defendants’ current
lawyers were engaged. A partner of that firm, Mr Brackin, has had the day-to-day
conduct of the matter ever since. Prior to mid-2013, the defendants were in a position
to obtain witness statements and confer with potential witnesses, including potential
witnesses who had been employed by the defendants.
The delay in service: 20 November 2014 – 30 June 2015
[34] The plaintiffs did not effect service until 30 June 2015, seven months after the
proceedings were filed. It is not to the point that they did not need leave under rule
24 to serve the proceeding within a year after filing. The relevant issue is why they
delayed in serving the proceeding after it was filed. The plaintiffs’ solicitors
explained that during this period they continued investigations, conducted interviews,
liaised with counsel, gathered more documents, and attended a further site inspection
at the plant.
[35] If those steps were required in order to confirm matters that had been pleaded in the
Statement of Claim, to amend certain matters in that document that required
amendment in the light of further investigations, or to supplement that pleading with
additional particulars, then a six-month period is not unreasonable to conduct those
investigations and to discuss matters with counsel. That period does, however, need
to be seen in the light of the lengthy period that was taken to commence proceedings,
and the substantial period that followed service.
The initial stage: 30 June 2015 – 14 November 2019
[36] The defendants note that it took almost two years to resolve issues in relation to
pleadings and particulars and that, although reasonable progress was maintained
between 31 October 2017 and 30 January 2018, little progress was achieved for
almost two years thereafter, until 14 November 2019, when the parties received a
Case Flow Intervention Notice from the Court.
[37] As for the first two years of this period, the defendants submit that although the
plaintiffs’ chronology refers to matters taking place during that period, they do not
justify the period of two years that was taken. In response, the plaintiffs submit that
there was not unreasonable delay on their part during the initial period because:
“(a) the defendants issued multiple requests for rule 222 documents
and further particulars and raised various complaints about the
plaintiffs’ pleading (which necessitated amendments to the
plaintiffs’ pleading);
(b) between July 2015 to May 2016, the plaintiffs’ legal
representatives were required to liaise with the plaintiffs, their
representatives, relevant co-insurers and counsel about potential
-- 9 of 18 --
10
recovery of uninsured losses of the plaintiffs that were relevant
to the events the subject of this proceeding;
(c) alternative junior counsel for the plaintiffs was engaged in
December 2015;
(d) the plaintiffs’ legal representatives received instructions to
engage Queens Counsel in November 2016, and took steps to
advance and finalise the amendments to the pleading which were
not resolved until June 2017;
(e) the defendants did not file their notice of intention to defend and
defence until 3 August 2017, and there was reasonable progress
of the matter between 31 October 2017 to 30 January 2018 (as
the defendants acknowledge at [31] of their submissions);
(f) the defendants inspected the Broadwater and Condong plants on
two separate occasions in April 2018 and June 2018;
(g) despite the plaintiffs proposing in March 2018 that a mediation
occur, the defendants did not agree to participate in a mediation
and postpone disclosure until January 2019;
(h) the parties agreed to postpone disclosure until a mediation had
occurred;
(i) during the period from January 2019 to August 2019, the parties
liaised about agreeing on a mediator and the parties agreed to
the mutual exchange of expert reports before mediation (such
exchange occurring on 14 November 2019);
(j) between June 2019 and November 2019, the parties liaised
about a suitable date for mutual exchange of expert reports (such
exchange occurring on 14 November 2019);
(k) the caseflow intervention notice was sent on 14 November 2019,
a period of approximately 2 years since the defendants filed their
notice of intention to defend.”
[38] In reply the defendants submit that the plaintiffs’ account of factual events during the
two-year period does not sufficiently explain the delays and that, having taken until
the very end of the limitation period to commence the proceeding, the plaintiffs
should have acted with greater expedition.
[39] In my view, the plaintiffs have explained events during this period. Incidentally, the
plaintiffs served an application in September 2016, and the defendants consented to
the orders proposed.
[40] It was reasonable for the parties to agree to postpone disclosure until a mediation had
occurred, but the defendants did not agree to this until January 2019. The mediation
could not occur until expert reports were exchanged.
[41] The relevant period of approximately four years between mid-2015 and late 2019 is
very substantial. In retrospect, it may have been better to hold a mediation after
disclosure. I am unable to conclude that the plaintiffs were wholly responsible for
-- 10 of 18 --
11
this period of delay, as the defendants contend. Both parties were responsible in
varying degrees for the slow progress of the matter and must share some
responsibility for the delay.
[42] Moreover, any dissatisfaction by the defendants with the slow rate of progress did not
prompt it to apply to place the matter on the Supervised Case List, which would have
been appropriate for a matter of this complexity. Rather than seek active case
management, both parties waited for the court itself to intervene in November 2019,
when they received a Case Flow Intervention Notice from the court.
The case flow intervention stage: 14 November 2019 – 31 May 2021
[43] After November 2019, Bowskill J (as the Chief Justice then was) conducted regular
reviews. The plaintiffs defaulted on certain orders about disclosure and filing and
serving evidence. In November 2020, the plaintiffs foreshadowed supplementary or
additional lay evidence, the last of which was not produced until December 2021, and
only after Brown J had made a guillotine order at a supervised case review.
[44] The defendants note that four of the additional statements, or supplementary
statements, substantially changed the evidence that had been presented in earlier
witness statements.
[45] The plaintiffs submit that it was not unreasonable to conduct matters during the case
flow stage as they did. This is because:
“(a) a mediation occurred on 24 February 2020, and the parties had
agreed to postpone disclosure until after a mediation had
occurred;
(b) despite the plaintiffs having first proposed a Document Plan and
Categories for Disclosure to the defendants in March 2018, the
Document Plan and Categories for Disclosure were not agreed
by the parties until April 2020;
(c) in respect of disclosure:
(i) the plaintiffs’ legal representatives were required to review
80,000 documents, and the plaintiffs then produced 5,418
documents in July 2020 and further documents thereafter;
(ii) the defendants produced disclosure of 3,233 documents in
June 2020 and then produced further documents thereafter
(including 1,245 documents in March 2021);
(d) in September 2020 and October 2020, the plaintiffs served on the
defendants the affidavit of Mr Lowry (exhibiting his reports
dated 14 November 2019 and 3 x reports dated 24 September
2020), an affidavit of Martin Miller, and witness statements of
Chris Connors, David Moller, David Ells, Ian Fletcher, Regan
Sawatzki and Daniel Rojo;
(e) the experts (Mr Lowry and Dr Dixon) delivered their expert
reports which the parties had exchanged on 14 November 2019.
Further reports from Mr Lowry and Dr Dixon were served on 25
-- 11 of 18 --
12
September 2020 and they then participated in three joint expert
conferences in October 2020 and produced a joint report in
November 2020;
(f) given the volume of issues in dispute in the proceeding (as is
apparent from the Court’s reasons for judgment), the process of
preparing expert evidence and lay witness evidence (which was
given by statement) was obviously complex and lengthy;
(g) junior counsel for the plaintiffs did not have the necessary
availability required to continue to assist with these proceedings
and new junior counsel was then engaged in late 2020;
(h) there was an impact on the plaintiffs’ prosecution of the proceeding
due to the COVID pandemic during this period, in relation to the
ability of solicitors, counsel, lay and expert witnesses to meet in
person due to Qld/NSW border closures, causing delays with
preparation of evidence and receipt of signed statements for filing
and service in the Court.”
[46] In reply, the defendants reiterate that the one-and-a-half-year period that the
proceeding was subject to case flow involved slow progress by the plaintiffs and
defaults by them in complying with directions. They submit the delays were
unreasonable and have not been properly explained. I disagree. The delays during
this period were unfortunate, but had been explained.
[47] The plaintiffs, the defendants and the court might have hoped that the completion of
disclosure, witness statements and expert evidence would have taken less time. I have
had the advantage of reading the relevant witness statements and expert reports. This
was an extraordinarily complex matter involving a wide range of factual issues about
the plant’s performance, both before and after the incident, the losses that the various
plaintiff entities suffered, their proof and quantification.
[48] The onset of COVID in March 2020, shortly after the case flow stage commenced,
slowed proceedings.
The supervised case review stage: 31 May 2021 – 30 May 2022
[49] The defendants make similar points about the plaintiffs’ delay during this period. The
matter was the subject of regular reviews by Brown J, as part of the Supervised Case
List. The material and submissions point to non-compliance with orders in relation
to the filing and service of lay evidence. They also point to the fact that an earlier
substantial report by an expert who “professed to be a forensic accountant” in
September 2020, was overtaken by a decision to call that expert as a factual witness
and to engage KordaMentha to prepare a forensic accounting report.
[50] The plaintiffs explain the delay during the supervised case review stage partly as a
result of further document review, further disclosure by both parties and for a number
of other reasons. These other reasons are as follows:
“(b) in assisting the witnesses with preparation of their statements
during this period, the plaintiffs’ legal representatives were faced
with some difficulties associated with the witness’ interstate
location, lack of or limited computer access, requirements for
-- 12 of 18 --
13
documents for the witness’ review and draft statements to be sent
to the witness by post, witness availability, personal matters and
communication capabilities;
(c) given the volume of issues in dispute in the proceeding (as is
apparent from the Court’s reasons for judgment), the process of
preparing expert evidence and lay witness evidence (which was
by statement) was obviously complex and lengthy;
(d) in July 2021 and August 2021, following case review and the
complaint of the defendants’ solicitors about Martin Miller’s
report, the plaintiffs’ counsel took a period of time to provide
advice on that matter and during that period, preparation of Bruce
O’Shea’s report was put on hold;
(e) in August 2021 and September 2021, the plaintiffs served on the
defendant witness statements of Paul Stanley-Jones, Stephen
McLennan, Dougal Forsyth, David Timms and Gavin Dann;
(f) in early September 2021, the plaintiffs’ senior counsel (Declan
Kelly QC, as his Honour then was) was appointed as a judge of
the Supreme Court of Queensland. Tom Sullivan QC (as his
Honour then was) was then retained in the matter in
mid-September 2021 and required time to read into the matter
(including providing input into the witness statements delivered
by the plaintiffs in September 2021 and thereafter);
(g) on 24 September 2021, the parties were notified (during a case
review before Brown J) that the matter had been listed for trial
commencing on 30 May 2022.
The trial dates were not adjourned at any time after 25 September
2021.
On that basis, in the plaintiffs’ submission, any complaints on the
part of defendants about events that occurred after 25 September
2021 (such as the timing of delivery of further witness
statements) are not relevant to consideration of the award of
interest.”
[51] The plaintiffs also note that the trial dates were not adjourned at any time after 25
September 2021.
[52] The relevant period, in my view, is not the period of a year between the matter going
on to the Supervised Case List and the date when the trial commenced. The relevant
period is when the matter was considered ready for trial, and listed for trial.
[53] In my view, the plaintiffs have sufficiently explained how it attempted, with
difficulty, to progress the matter to trial. I do not consider their conduct during this
period was unreasonable. They were entitled to make forensic decisions about proper
proof of their economic loss claim, which was hard-fought by the defendants.
-- 13 of 18 --
14
Evidence of prejudice to the defendants
[54] Mr Brackin’s evidence is that, as a result of the plaintiffs’ repeated delays in
prosecuting the proceedings, the defendants suffered prejudice in relation to:
(a) the unavailability of witnesses;
(b) the unavailability of documents; and
(c) additional legal costs the defendants incurred.
[55] In response, the plaintiffs contend that it is unsurprising that both the defendants and
the plaintiffs had difficulty with the availability of witnesses in circumstances in
which practical completion of the May 2005 contract was not achieved until 21
November 2008, the incident did not occur until 5 July 2010, its suspected cause was
not discovered by the plaintiffs until 25 August 2010, that cause was not accepted by
the defendants at the time or subsequently, the matter remained controversial,
required further investigation and did not result in proceedings commencing until
November 2014.
[56] As to the defendants’ lay witnesses and potential lay witnesses, the plaintiffs note that
the defendants had five lay witnesses at trial and it has not been suggested that the
defendants could not have subpoenaed witnesses, including former employees. They
further submit that Mr Brackin has not explained the points of time at which potential
witnesses were contacted by the defendants’ legal representatives. Given the history
of the matter, it seems unlikely that the potential witnesses were only contacted by
the defendants’ investigators or solicitors at a late stage close to trial. If this is the
case, then the defendants’ delay in doing so is largely unexplained. Further, according
to the plaintiffs, it was always likely that there were going to be difficulties with the
availability or willingness of some witnesses to assist because:
“(a) Rick Phillips was engaged by the defendants on a contract basis
(not as an employee) and had not been engaged by any entity
associated with the defendants for ‘several years’;
(b) Keith Harvey was engaged by the second defendant on a contract
basis and ceased his engagement ‘shortly after practical
completion in approximately late 2008’;
(c) Terry Cole left his employment with the second defendant in mid
to late 2012;
(d) Adrian Hughes left his employment with the second defendant
‘shortly after practical completion of the Broadwater co-
generation project in or about late 2008.”
[57] The defendants respond that the plaintiffs’ criticisms of Mr Brackin’s evidence about
prejudice should be rejected because of the inherent difficulty in pin-pointing such
prejudice with any precision.
[58] I accept, consistent with the authorities to which I have referred, that some general
prejudice may be inferred by reason of delay itself. However, the plaintiffs make a
valid point about the lack of clarity as to whether any of the potential witnesses who
were not called were approached years earlier, why their accounts of events were not
-- 14 of 18 --
15
the subject of statements soon after the events, or at least soon after the May 2013
letters of demand. I cannot be satisfied that the potential witnesses were not spoken
to by the defendants’ representatives, loss adjusters or solicitors at an early stage. I
cannot conclude that their evidence would have been of any great assistance to the
defendants had they been approached sooner and been prepared to talk. Moreover, if
potential witnesses were expected to give evidence favourable to the defendants, but
were not willing to provide statements, they might always have been subpoenaed.
Overall, I am not satisfied about the extent of prejudice claimed by the defendants
due to the unavailability of potential witnesses.
[59] As to the availability of documents, the plaintiffs submit that:
“…it is unsurprising that both the defendants and plaintiffs would have
had difficulty with the availability of documents given the matters set
out [in paragraph 29] above. Further it is noted that:
(a) Mr Brackin does not identify the basis upon which he gives
evidence of the matters about availability of documents at
[74] of his affidavit;
(b) Mr Brackin does not identify at [74(a)] of his affidavit which
(or what type of) commissioning documents could not be
located, that were not otherwise produced by the plaintiffs
in the plaintiffs’ disclosure;
(c) a significant number of operator logs were included in
Annexure A of Mr Rossner’s statement for the period from
10 July 2008 to 31 October 2008;
(d) it was not apparent that the DCS was actually even recording
information at all relevant times.”
Additional legal costs attributable to delay
[60] Mr Brackin says that the extended duration of the proceeding caused legal costs
incurred by the defendants to substantially increase through additional court
attendances, additional administration and reporting to the client, and staff turnover.
These matters are said to inevitably cause additional legal costs to be incurred over
the extended duration of the matter. I accept his evidence.
[61] The plaintiffs submit that:
“…it is difficult to envisage how mere delay on the part of the
plaintiffs could have caused the defendants to incur additional legal
costs (of the type referred to in Mr Brackin’s affidavit at [75]) that
would not have otherwise occurred in the course of the litigation. In
complex case managed litigation with a trial of the duration as like in
this proceeding, it is to be expected that the duration of the proceeding
will be of some length and that, in that time, there will be legal staff
turnover.”
[62] Mr Brackin has not purported to quantify the legal costs that are attributable to further
court attendances, additional administration and additional reporting. The plaintiffs
submit that, in any event, there were cost orders made in the defendants’ favour during
-- 15 of 18 --
16
the course of the proceeding, in relation to some delay, including orders made on 21
August 2020 and 3 December 2021.
[63] I consider that it would have been invidious, and not particularly helpful, for Mr
Brackin to hazard a guess about the additional legal costs that the defendants incurred
as a result of specific delays or certain periods of what the defendants contend are
unreasonable delays. I am prepared to conclude that any period or periods of
unreasonable delay by the plaintiffs led to additional costs.
[64] That consideration needs to be tempered by the realisation that, even if the proceeding
had been conducted with greater expedition, its nature was such that many years
would be occupied in the pre-trial process, with changes in personnel including
counsel, solicitors, potential experts, and representatives of clients.
An overall assessment as to the delay
[65] I have considered each period of delay, including the sufficiency of the plaintiffs’
explanation for the long period, overall, between the incident and the matter finally
being ready for trial in September 2021. That substantial period is confronting. The
plaintiffs’ various explanations have rejected the defendants’ contention that each
period of delay was unreasonable in all the circumstances. I conclude that many of
those explanations have substantial validity. However, I regard the relevant period
as excessive, even for a matter of such complexity. The matter entailed an enormous
body of lay evidence, records, observations and opinions of engineers who were
associated with the project or the plant, and expert reports and opinions that required
a great amount of effort to assemble, distil, and present at trial.
[66] The last few years of the proceedings were delayed due to COVID, which limited
personal contact between interstate witnesses and Brisbane-based lawyers for
substantial periods.
[67] The proceeding might have proceeded through interlocutory stages, with inevitable
and substantial amendments to pleadings, witness statements and supplementary
statements, expert reports, ongoing disclosure and all that occurred in this proceeding
in less than the six-and-a-half years that this proceeding took. This fact alone does
not necessarily prove that the plaintiffs’ conduct was unreasonable. Also, the
defendants must share some responsibility for the matter not being case-managed
until the court itself intervened in November 2019.
[68] If the period of more than six years between the commencement of the proceeding in
November 2014 and the matter being ready to be listed for trial does not itself bespeak
unreasonable delay on the part of the plaintiffs, that substantial period cannot be
viewed in isolation. It must be viewed against the period of years between when a
probable cause of the July 2010 damage was identified in August 2010, and the
commencement of proceedings in November 2014. The plaintiffs’ apparent delay in
this pre-commencement phase has been explained and that explanation has
considerable validity.
[69] However, having regard to the various periods and the overall period that the
plaintiffs’ insurer took to commence the proceeding and then litigate it to trial, I
conclude that the plaintiffs did not conduct the proceeding with appropriate
expedition. There were periods of unreasonable delay that have not been sufficiently
-- 16 of 18 --
17
explained. Because of unreasonable delay, the proceeding took too long to be set
down for trial.
[70] The evidence of prejudice and escalating costs has been addressed by me. It is not
possible to quantify how much costs escalated due to periods of unreasonable delay
on the part of the plaintiffs. I am prepared to assume that additional substantial costs
were incurred as a result of periods of unreasonable delay by the plaintiffs.
[71] The fact that the proceeding might have been commenced sooner, and litigated with
greater expedition, does not establish a case of unreasonable delay. This includes
periods when the plaintiffs were unable to comply with court directions in providing
lay witness statements and expert reports, for reasons that they explained at the time.
On occasions, the defendants received cost orders in their favour. Moreover, I am
not considering issues of costs at this stage, including whether the costs of reviews
would have been incurred in any event. Had the plaintiffs not obtained the
indulgences that they did to have additional time, then there may have been
applications to supplement the lay statements with additional oral evidence that could
not have been reasonably included in the original statements. This would have
delayed the fair conduct of the trial.
[72] In retrospect, the parties may have been well-advised to settle the matter years ago,
possibly at the mediation. However, for whatever reason or reasons, they were unable
to settle the matter. Therefore, an enormously complicated piece of litigation had to
be prosecuted to trial at great expense.
[73] Substantial delay was inevitable in a matter of this complexity. The defendants’ case
itself evolved on the eve of trial and during the course of trial when I allowed new
evidence from it to be introduced via Mr Stirling. In the circumstances, the plaintiffs
should not be unfairly criticised because over the years their pleaded case was
amended, the evidence of lay witnesses supplemented, and supplementary expert
reports were obtained.
[74] Despite these considerations in the plaintiffs’ favour, I consider that it is appropriate
to deprive the plaintiffs of what otherwise would be an entitlement to interest over
the entire period between when it first suffered loss and judgment.
[75] The defendants’ contention that the plaintiffs should be awarded interest only from
when the case flow intervention notice was issued on 14 November 2019 until
judgment, is unmeritorious. In any event, the plaintiffs should be presumptively
entitled to interest between September 2021 when the matter was ready to be set down
for trial and the date of judgment. The defendants’ contention would, in effect, award
interest only for an additional period of about two years between November 2019 and
late 2021. Such a short period cannot be justified for a matter of such complexity and
in circumstances in which the defendants had the financial benefit of the damages to
which the plaintiffs are entitled for a period of more than 12 years after the date of
loss.
[76] By the same token, the period between the plaintiffs suffering loss in July 2010 and
the matter being ready for trial in late 2021, is an excessive period over which to
award interest. I accept that the potential claim required a long period of investigation
and careful consideration before letters of demand were sent, and also before
proceedings were commenced. The plaintiffs’ insurer, which was subrogated to its
-- 17 of 18 --
18
rights against the defendants, was entitled to carefully assess the strengths and
quantum of the plaintiffs’ case and to make a difficult commercial judgment about
commencing proceedings.
[77] The pleading and particulars stage of such a proceeding was always likely to be
lengthy. Once the issues were defined, disclosure would take a very substantial
period.
[78] Unfortunately, neither party sought case management on the Supervised Case List.
The defendants’ solicitors once foreshadowed an application to place the matter on
the Commercial List, but that was not pursued by them.
[79] The matter took longer than it should have. Both parties bear some responsibility for
this delay. However, there were periods of unreasonable delay and, overall, the
plaintiffs did not act with the expedition required of them.
[80] In all the circumstances, I consider that the period over which interest should be
awarded should be confined to a period of 8 years between 10 July 2010 and 9 July
2018.
[81] I direct the parties to calculate interest according to the applicable Practice Direction
rates for the relevant period. I will make further directions for the early submission
of any submissions on costs, so that, if required, I can decide any outstanding issue
of costs.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2023/076