Burton v Coast Wide Construction Group Trust [2023] QCAT 522
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Burton v Coast Wide Construction Group Trust [2023]
QCAT 522
PARTIES: LUKE BURTON
(applicant)
v
THE TRUSTEE FOR THE COASTWIDE
CONSTRUCTION GROUP TRUST
(respondent)
APPLICATION NO/S: BDL298-22
MATTER TYPE: Building matters
DELIVERED ON: 18 December 2023
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member King-Scott
ORDERS: The Respondent pay the Applicant the sum of $7,260.00
by 4:00 pm on 10 January 2024
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – builder
left site incomplete work
Queensland Civil and Administrative Tribunal Act 2009
(Qld)
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] By a contract in writing dated 5 May 2022 the Respondent builder, Coast Wide
Construction Group Trust agreed to construct a shed at the Applicant’s Tewantin
home.
[2] The Contract was for the sum of $6,800.00. Mr Burton paid a deposit of $680 on 24
May 2022.
[3] The Respondent is misdescribed in the proceedings, its correct name as appears on
the contract is The Trustee for Coastwide Construction Group Trust which is
consistent with its ABN number provided. Pursuant to s.64 of the Queensland Civil
-- 1 of 2 --
2
and Administrative Tribunal Act 2009 (Qld) I order that the proceedings be amended
to reflect the correct name.
[4] It would appear that the Respondent provided a false licence certificate to the
Applicant.
[5] Work commenced on 24 May 2022. Mr Burton ordered and paid $2,300.00 for
additional materials. On 4 June 2022 he paid the Respondent, 40% ($2,720.00) of the
contract sum for the frame stage. A further sum of $850.00 was paid for flashing on
10 June 2022.
[6] The Respondent left the site on 9 June 2022 and has not returned. Nor has it
communicated with the Applicant. The framework was partially completed but was
not square and had to be demolished and rebuilt by a builder retained by the Applicant
to complete the works.
[7] The Applicant alleges that, because of the delay in finding a new builder to complete
the work, he incurred additional storage costs for goods to be stored in the new shed.
[8] The Applicant claims the following:
(a) Cost to demolish the framing stage $1,360.00
(b) Material paid for by the applicant and taken by the respondent $2,300.00
(c) Framing stage paid $2,720.00
(d) Additional storage at $220 per month for 4 months $880.00
Total $7,260.00
[9] I am satisfied that the claim is reasonable and allow the sum of $7,260.00 as damages
for breach of contract.
[10] I order the Respondent pay the Applicant the sum of $7,260.00 by 4:00 pm on 10
January 2024.
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2023/522