Burke v Brown [2023] QCAT 322
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Burke v Brown [2023] QCAT 322
PARTIES: KIRSTY BURKE
(applicant)
v
SIMON BROWN
(respondent)
APPLICATION NO/S: BDL004-20
MATTER TYPE: Building matters
DELIVERED ON: 18 August 2023
HEARING DATE: 14 August 2023
HEARD AT: Brisbane
DECISION OF: Member King-Scott
ORDERS: The Applicant’s claim is dismissed
CATCHWORDS: CONTRACTS - BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF WORK
- REMEDIES FOR BREACH OF CONTRACT –
DAMAGES - where applicant alleges defective building
work – where respondent pleads s 10 of the Limitation of
Actions Act 1974 (Qld) – where 6 years is the period of
limitation prescribed – where cause of action for a claim in
a breach of contract arose in 2005 – where the claim should
have been commenced by 2011 - where claim in tort arose
when latent defect became manifest - where homeowner
exercising reasonable diligence would have become aware
of defect before 2014 - where claim brought in 2020 - where
the claim for damages was not commenced within the period
of limitation prescribed
Limitation of Actions Act 1974 (Qld)
Domestic Building Contracts Act 2000 (Qld)
Ramm v Ramm [2020] QCAT 102
Pullen v Gutteridge, Haskins & Davey Pty Ltd [1993] 1
VR 27
Melisavon Pty Ltd v Springfield Land Development
Corporation Pty Ltd (2015) 1 Qd R 476
APPEARANCES &
REPRESENTATION:
Applicant: Self represented
-- 1 of 8 --
2
Respondent: Self represented
REASONS FOR DECISION
[1] The Applicant (Kirsty Burke) wished to build underneath her existing home in Camp
Hill, Brisbane. In June 2004 she engaged the Respondent (Simon Brown) a builder to
raise her house on steel posts and construct accommodation underneath for her aged
mother. Work commenced either late in 2004 or early 2005 and was completed by
July 2005. Ms Burke and her family, at the time, were impressed by Mr Brown’s
attention to detail, the quality of his workmanship and his professional manner in
which he completed the build.1
Background to the dispute
[2] In 2019, Ms Burke was desirous of selling the property and an interested purchaser
commissioned a building inspection which revealed corrosion issues involving the
steel posts. An initial engineer’s report opined that the cause was the failure to protect
the steel posts where they entered the edge of the new concrete slab with a corrosive
resistant paint/coating. The manufactured posts2 had a proprietary name of Duragal
and had a hot dip galvanised 100g/m 2 coating. In about 2002 the manufacturer of
Duragal considered the coating to be inadequate protection against corrosion in certain
circumstances and recommended the application of a further primer.3 The position of
some of the posts left them exposed to the elements. The damage was said to be
extensive, and Ms Burke says she has been unable to sell the property. Ms Burke says
she was unaware of the damage as it was concealed by a thin layer of concrete.
[3] There is no copy of the contract in existence. I was informed at the hearing it was a
standard “HIA Alteration and Addition” contract. Both parties had discarded the
documentation. This is not surprising considering the lapse of time since completion
of the works.
[4] Mr Brown says that Ms Burke’s late mother and then partner Steven Lockhart were
also parties to the contract. This appears not to be disputed by Ms Burke. There is
sufficient material including quotes to provide some indication of some of the terms.
There is not any great dispute between the parties as to the relevant terms. It was a
cost-plus contract. An early quote put the assessed cost at about $200,00.00. Although
supplied with a number of invoices, I do not have detail of the final cost.
[5] Landscaping and painting were not included. What constituted painting is in issue and
I will refer to this later in these reasons. Indeed, the principal issue in the matter is
whether the steel posts were treated appropriately with a corrosive resistant
paint/coating and whose responsibility it was to carry out this task. Ms Burke says it
was Mr Brown, Mr Brown says it was Ms Burke’s partner Mr Lockhart.
1 Applicant’s documents page 58 letter 6 May 2005.
2 Secure Steel Pty Ltd supplied 75 x 75 x 4. 0 DURAGAL SHS which complied with Australian
Standards. See letter dated 20 June 2020.
3 In 2001 One Steel Ltd published a guide recommending that Duragal product be painted with a an
anti-corrosive barrier coat 100 mm above and below contact with soil. See Joint Expert Report
paragraph 10.
-- 2 of 8 --
3
[6] The plans were drawn up by Magnic Drafting Service and a Mr John Quak was
engaged to provide an engineer’s report.
[7] The home was completed by July 2005 when a Final Inspection Certificate issued.4
The Joint Expert Report
[8] Both parties engaged building experts. Mr Peter Wright provided a report to Ms
Burke, Mr John House provided a report to Mr Brown. Both are qualified engineers
specialising in construction. The Tribunal directed an expert conclave which was held
on 25 March 2022 and resulted in a joint report authored by both experts.
[9] I was the Tribunal Member who convened the Conclave. Through an oversight I was
delegated to hear this matter. Paragraph 15 of QCAT Practice Direction No 4 of 2009
directs that the convenor of the conclave cannot be a member of the tribunal that hears
the matter unless all parties consent. At the outset of the hearing, I advised both parties
of the Practice Direction and that I had conducted the conclave and if they wished me
to hear the matter their consent would be required. Both parties consented to me
hearing the matter.
[10] In the Joint Report the experts agreed on the following:
(a) The bases of Seventeen Steel Post supporting the upper floor of the dwelling
were inspected. Approximately ten were not visible. They were concealed by
paving.
(b) The condition of the bases of the 17 posts inspected varied greatly.
(c) The experts agree that the exposed sections of the steel posts between the tops
of the concrete piers and the underside of the wall cladding is described in the
Building Code of Australia as a MODERATE environment with respect to
corrosion of steelwork.
(d) The “Duragal” coating on the steel posts installed by the Respondent is
considered to be equivalent to “Hot dip galvanize 100g/m2 ”
(e) The Building Code of Australia, Amendment dated 2002, applicable at the time
of construction (2005) required a minimum protective coating be applied over
the Duragal of either “solvent based vinyl primer” or “vinyl gloss, or alkyd” to
the Duragal exposed to the moderate external environment. Where the Duragal
was in contact with concrete, the surface was passivated. See an extract from
the Building Code of Australia 1996 Volume Two - Amendment 13 below,
adopted in Queensland on 1 July 2003. Relevant sections have been highlighted
for convenience. (Extract omitted)
(f) Corrosion requires moisture and oxygen. There is an abundance of both of these
elements where the posts are exposed between the tops of the piers and the
underside of the wall cladding.
(i) The posts beneath the back veranda have all four faces exposed.
(ii) At the external corners of the building, six locations in total, two faces of
the steel posts were exposed.
4 Applicant’s statements page 55
-- 3 of 8 --
4
(iii) At the internal corners of the building, three locations in total, only one
edge of the steel posts were exposed.
(iv) All other steel posts have one face exposed to moisture between the top
of the concrete piers and the underside of the wall cladding.
(g) The thin cementitious coat over some of the exposed 300mm height of the posts
was Parging applied during the application of Termimesh the termite protection
applied to the building. Mr House is of the view that the Parging would have
slowed the corrosion, but was not enough to prevent the rusting that occurred.
(h) The design drawings were organized by the Applicant.
[11] The parging was applied by installing a stainless steel mesh skirt to the post base and
then the parge, a cement based product was worked through the mesh bonding to the
underlying surface of the steel. According to Mr Brown it was impracticable to apply
the paint before installing the posts but it could be applied over the dry parging.
[12] Ms Burke submitted a number of quotations for the cost of rectification varies between
$72,883.505 and $17,490.00.6 Mr Brown offered to carry out the work in accordance
with Mr House’s findings for $4,642.00 inclusive of GST.
Limitation Period
[13] Ms Burke in her application does not specify whether she makes the claim in contract,
negligence or for breach of warranty under the repealed Domestic Building Contracts
Act 2000 (Qld) (DBCA). In her submissions, at the hearing, she clarified her claim as
being one in tort.
[14] The contract was entered into some time in 2004 and the work was completed by July
2005. Ms Burke says she first became aware of the problem when she attempted to
sell the property and a building inspection report carried out by a prospective
purchaser revealed the rust damage to the posts. That was on 24 September 2019.7 It
is noteworthy that the inspection was limited to ‘readily accessible areas and was
based on a visual examination of the surface work’.
[15] Section 51 of the DBCA provides that a proceeding for a breach of warranty in relation
to a regulated contract must be started within 6 years and 6 months after the subject
work finished.
[16] Any claim that Ms Burke may have had under the DBCA for breach of warranty has
now expired.
[17] The Limitation of Actions Act 1974 (Qld) provides:
10. Actions of contract and tort and certain other actions
(1) The following actions shall not be brought after the expiration of six years
from the date on which the cause of action arose:
5 Quotation from Salmon Building Services Pty Ltd dated 1 June 2020.
6 Paul Simpson quotation dated 3 August 2020
7 Report of Rapid Building Inspections. Report dated 24 September 2019.
-- 4 of 8 --
5
(a) … an action founded on simple contract or quasi-contract or on tort where
the damages claimed by the plaintiff do not consist of or include damages in
respect of personal injury to any person;
[18] These proceedings were commenced on 7 January 2020 and, if the cause of action
arose prior to 7 January 2014 then it will be statute barred.
[19] A cause of action for breach of contract accrues when the breach occurred. In this
case, that is according to Ms Burke, when Mr Brown failed to apply the corrosive
coating to the steel posts. The limitation period expired 2011.
[20] In the Court of Appeal decision of Melisavon Pty Ltd v Springfield Land Development
Corporation Pty Ltd 8 the members of the Court disagreed as to the issue of when the
cause of action accrued.
[21] In Melisavon, negligence was alleged in respect of the design and engineering of a
concrete slab and surrounds. The building design was completed in 2003 and the
construction of the building subsequently undertaken. The building owner alleged that
in 2009 and 2010 the building slab and surrounds were damaged or failed. The
engineer claimed that the damage first occurred in late 2003 or early 2004 and the
building owner’s claim, commenced in 2011, was therefore statute barred
[22] McMurdo P expressed the opinion that ordinarily, a cause of action for tortious
negligence is complete when there is any manifestation of damage which is ultimately
found to be connected to the alleged negligence.9 (The emphasis is mine.)
[23] Ann Lyons J agreed with the orders proposed by the President but did not address the
issue as to when an action accrues. Holmes J (as Her Honour then was) preferred the
conventional approach in Pullen v Gutteridge, Haskins & Davey Pty Ltd10 that the
cause of action accrues where actual damage caused by a latent defect is manifested
or the existence of the underlying defect is known or ought to be known.11 The nice
distinction raised in the decision was not addressed by Ann Lyons J. I accept the
conventional approach as expressed by Holmes J.12
[24] It is apparent that significant rust damage was visible at the time of the inspection in
2019. Contrary to the assertion of Ms Burke and others it was not concealed. Some
posts were coated with cementious material described as parging. Its purpose was not
to conceal the exposed steel but as part of the termite treatment by Termi-mesh. It was
necessary for the steel post to remain unpainted so that the parging could be properly
applied.13
[25] Mr Brown’s case is that the Applicant and her partner were to paint the posts which
they failed to do. I will return to that issue later in these reasons.
[26] Some photographs14 of the steel posts depict rusting at the base of the posts as well as
green material perhaps an algae or moss suggestive of reasonably high moisture levels
around the base of the slab.
8 (2015) 1 Qd R 476
9 Ibid p. 495 [28]
10 [1993] 1 VR 27
11 (2015) 1 Qd R 476 at 509 [65]
12 See also Ramm v Ramm [2020] QCAT 102
13 Email Gavin Clarke to Brown from Trmimesh barrier and steel posts
14 Exhibit 3 photograph 5,8 and 9
-- 5 of 8 --
6
[27] Mr Wright says that the skim coat (I take to mean the parging) concealed the corrosion
problem until it had advanced and spalled the cementious coat away. However, that
only concerned a number of posts. Other posts were exposed and showed rusting
around the base sufficient to put any homeowner on notice that a problem existed.
[28] Ms Burke says that whilst her mother was living in the lower level she (Ms Burke)
had little reason to inspect the area. It is not known whether her mother, now deceased,
who was a party to the contract had observed the development of rust on the posts. It
was noticeable that the garden and surrounding area, where a number of the posts
were located, was very damp.
[29] The report of Rapid Building Inspections, in addition to their findings relating to the
steel posts also found significant wood rot to ground floor windows indicative of a
lack of maintenance.
[30] Ms Burke says that she is not a builder and could not be expected to have the requisite
knowledge or skill to identify a problem and consequences of the posts rusting. I
would expect that any homeowner acting reasonable, on becoming aware of the rust,
would have investigated the matter further. In my opinion, Ms Burke appears to have
been neglectful of maintaining her home as demonstrated by the extent of dry rot and
absence of paint on the windows.15
[31] Mr Brown says that during the build he advised Ms Burke and her partner separately
of the importance of keeping the landscaping away from the house and to direct water
away from the house as well as constructing small concrete domed pads around the
base of each external steel post when carrying out the landscaping.
[32] Mr House considered that some of the moisture in the area and damage to the steel
post at the corner of the laundry could have come from wastewater disposed from near
the laundry. This was denied by Ms Burke. Irrespective of the source of the moisture
at that point, Mr House opined that the post near to the laundry would have rusted
through anyway, even if properly treated.
[33] In my opinion, a homeowner exercising reasonable diligence would have investigated
the appearance of rust at an earlier stage and certainly before January 2014. Although,
it is not necessary for me to address whether Ms Burke ought to have discovered the
damage and its link to the defect I am prepared to find that any examination of the
posts would have raised as an issue the cause of the rust and link to the initial build,
as subsequently occurred.
[34] In my opinion Ms Burke’s claim is statute barred.
Merits of the Applicant’s claim
[35] In any event, I believe Mr Burke would fail on the merits of the case for the following
reasons.
[36] It was agreed that painting was excluded from the contract. It was also accepted that
the Duragal posts required additional protection in the form of an anticorrosive paint
or coating.
15 See Rapid Building Inspections report dated 24 September 2019
-- 6 of 8 --
7
[37] Mr Brown says that the application of suitable paint was the responsibility of Ms
Burke and/or her partner. Unfortunately, there has been no evidence from Mr Lockhart
who is separated from Ms Burke. She is unaware of his present whereabouts.
[38] Ms Burke interprets painting as being decorative and not a protective anti-corrosive
coating. Obviously, depending on the circumstance paint can also be applied for
protection as well as decoration. I do not agree with her interpretation.
[39] The recollections of both Ms Burke and Mr Brown have been affected by the elapse
of time. I believe both witnesses attempted to provide their honest recollection of
events although they disagreed on some issues. However, I consider that Mr Brown
has the better recollection. I accept that he had the conversations in relation to the
protection of the posts from moisture and the need to keep ground water away from
the base of the posts when landscaping the area .
[40] Mr Wright says that it is unreasonable to require a lay person to apply the protective
coating to the steelwork during construction prior to the posts being attached to the
timber framework and prior to the casting of concrete around the steelwork.16 Mr
House disagreed and considered the exposed posts could have been painted before the
ground floor was built in. He did not consider that it was his professions’ view that
the posts should be painted before being encased in concrete. He noted that the vertical
joint each side of the post against the concrete is tight with no gap for moisture to
enter. When investigated the steel against the concrete was found to be clear of rust,
indicating that the steel tight against the concrete had passivated the steel and
protected it from corrosion.17
[41] Ms Burke relies upon the endorsement on the plans by Magnic Drafting Service that
“All steel work shall be protected by zinc rich paint”. Mr House found that instruction
vague and unhelpful and said it was the engineer Mr John Quak who should have
provided guidance but failed to do so. Mr Wright agrees that Mr Quak’s drawings
provided no information but says Mr Brown should have followed Magnic Drafting
Service notes. Mr House was of the opinion that the engineer’s drawings were
paramount on this issue.
[42] As to the posts affected, Mr Wright suggested that once the flaking on nine of the
posts was removed holes in the posts may be revealed. Mr House says that only the
exposed posts are affected and that despite flaking rust they are axially immensely
strong.
[43] In relation to maintenance Mr House says that the post near the laundry (because of
the level of moisture) would have corroded anyway even if appropriate anti corrosive
coating had been applied. Mr Wright disagrees but concedes that the parging
prevented a problem with respect to maintenance and application of a protective
coating.
[44] I prefer Mr House’s evidence where he disagrees with Mr Wright.
[45] It should be noted that at completion and during all stages the work was passed by a
certifier and an engineer, probably by Mr Quak, without comment in relation to how
the steel posts were installed.
16 Exhibit 4 paragraph 7.5.6
17 Hendriks/House (C
-- 7 of 8 --
8
[46] I do not consider that Mr Brown had breached his duty of care to Ms Burke.
[47] For the reasons given I dismiss the Applicant’s claim.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2023/322