Carter v Queensland Building and Construction Commission & Ors [2023] QCAT 278
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Carter v Queensland Building and Construction
Commission & Ors [2023] QCAT 278
PARTIES: LOUISA CARTER
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
MAXCON CONSTRUCTIONS PTY LTD
BODY CORPORATE FOR THE JOHNSON CTS
49098
BODY CORPORATE FOR THE JOHNSON
APARTMENTS CTS 49099
(respondents)
APPLICATION NO: GAR259-19
MATTER TYPE: Building matters
DELIVERED ON: 26 June 2023
HEARING DATE: 16 February 2023
HEARD AT: Brisbane
DECISION OF: Member Scott-Mackenzie
ORDERS: The second respondent’s application filed 6 January
2023 for a stay of the proceeding is dismissed.
The second respondent’s application filed 10
January 2023 for an extension of the time to comply
with order 1 of the orders made by the Tribunal on
14 November 2022 is granted. The second
respondent comply with the order by 4.00pm on 15
August 2023.
The proceeding be fixed for hearing for four days
commencing on the next available hearing date after
15 August 2023.
The proceeding be listed for a directions hearing by
telephone after 15 August 2023 and not less than
fourteen days before the date fixed for the hearing
of the proceeding. The purpose of the directions
hearing is for the Tribunal to confirm with the
parties:
(a) the material they have filed and on which they
intend to rely at the hearing;
-- 1 of 14 --
2
(b) the precise issues to be determined at the
hearing;
(c) the witnesses, if any, they require for cross-
examination;
(d) whether it is proposed the witnesses will be
giving evidence in person or by remote means
(specifying the mode of attendance);
(e) any limitations on the time of availability of
witness; and
(f) any other issue necessary to ensure the
proceeding is ready for hearing.
5. This order be served on the parties by email.
CATCHWORDS: APPLICATION FOR STAY – where one respondent
commenced a proceeding in the Supreme Court of
Queensland against another respondent nearly four years
after commencement of the Tribunal proceeding – power to
grant stay - considerations for the grant of a temporary stay
– whether public interest or interests of justice favours grant
of stay – whether claim sufficiently particularized.
Body Corporate and Community Management Act 1997
(Qld)
Queensland Building and Construction Act 1991 (Qld)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 22(3), 58(1)
Chief Executive of the Department of Justice and Attorney-
General v Kollosche & Anor [2015] QCAT 145
JM Kelly (Project Builders) Pty Ltd v Queensland Building
Services Authority [2011] QCAT 60
Stirling Pharmaceuticals Pty Ltd v The Boots Company
(Australia) Pty Ltd [1992] FCA 72
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
First respondent:
Second respondent:
Third and fourth
respondents:
Ms Nean, Queensland Building and Construction
Commission
Mr Kidston, instructed by Diakou Faigen
Mr Robinson of Robinson Locke
REASONS FOR DECISION
Introduction
[1] On 2 July 2019 the applicant, Dr Louisa Carter, made application to the Tribunal for
-- 2 of 14 --
3
a review of two decisions of the first respondent, Queensland Building and
Construction Commission (QBCC). The first decision, given on 10 May 2018,
directed the second respondent, Maxcon Constructions Pty Ltd (Maxcon), to rectify
work in accordance with the direction to rectify work and/or complete work number
0103379 given under the Queensland Building and Construction Act 1991 (QBCC
Act) in respect of the premises at unit 1510, 477 Boundary Street, Spring Hill (Dr
Carter’s unit and her unit).
[2] The second decision, given on 14 June 2018, was to the effect Maxcon had complied
with the first decision.
[3] On 3 January 2020 the Tribunal directed that Maxcon and the third respondent, Body
Corporate for the Johnson CTS 49098 (Principal Body Corporate), be joined as second
and third respondents to the proceeding.
[4] On 8 October 2020 Body Corporate for the Johnson Apartments CTS49099
(Subsidiary Body Corporate) was joined as fourth respondent to the proceeding.
Background.
[5] Dr Carter is the owner of her unit. Maxcon is the builder of the building in which Dr
Carter’s unit is located. The building is known “The Johnson”.
[6] The Principal Body Corporate and Subsidiary Body Corporate (together, Bodies
Corporate) are the bodies corporate for The Johnson.
[7] Dr Carter complained about water entering her unit on 21 February 2018. She asked
that QBCC give a direction to Maxcon to rectify building work she considers is
defective or incomplete.
[8] On 10 May 2018 QBCC decided Maxcon is responsible “… in that the installation
of the rain water drainage system at the top units were not installed in
accordance with the relevant Australian Standards and or the BCA FF1.2 and
3.5.2 (gutters and downpipes) resulting in water being directed to the units below
and caused extensive damage to the adjacent building elements including the
carpets …” (first decision).
[9] On 11 June 2018 QBCC reinspected Dr Carter’s unit and, on 14 June 2018, decided
Maxcon had complied with the direction to rectify it having, amongst other things,
“… installed roofing tray flashing and spreaders to the drainage system to the lower
roof …” (second decision).
[10] On 2 July 2019 Dr Carter applied to the Tribunal for a review of the first and second
decisions (Tribunal proceeding).
[11] Progressing the Tribunal proceeding has been delayed for several years, in part
because of Maxcon’s disregard of directions given by the Tribunal. On 12 May 2022
the Tribunal afforded it a final opportunity to file material. It sought an extension of
the time to do so. Despite the extension being granted, it did not file any material.
The Tribunal proceeding was fixed for hearing for four days, commencing on 30
January 2023. The dates, on 3 January 2023, were vacated, and that the Tribunal gave
directions for the filing of any interlocutory application for the future conduct of the
Tribunal proceeding.
-- 3 of 14 --
4
Applications
[12] There are five applications before the Tribunal:
(a) an application by Maxcon filed 29 November 2022 for the following directions:
1. The proceeding be referred to and listed for a compulsory conference
before any hearing of the matter.
2. The compulsory conference be held in person at the relevant property
at The Johnson, 477 Boundary Street, Spring Hill, Queensland 4000.
3. The compulsory conference be held in the presence of each of the
parties’ experts who will be required to have an experts’ conclave as
soon as practicable after the compulsory conference to attempt to agree
a resolution of the matter.
4. The decision/orders of the Tribunal made 14 November 2022 be
vacated.
5. The hearing scheduled for 30 and 31 January 2023 and 1 and 2
February 2023 be vacated.
6. In the alternative to 4 above:
(a) the time and date for compliance with orders 1 and 3 be extended
to a date to be fixed after the compulsory conference/experts’
conclave;
(b) the time and date for attendance to give evidence referred to in
orders 2 and 3 be extended to a date to be fixed after the
compulsory conference/experts’ conclave.
7. In the alternative to 5 above, the hearing scheduled for 30 and 31
January 2023 and 1 and 2 February 2023 be adjourned to a date after
the compulsory conference/experts’ conclave.
The reasons for the application are in the following terms:
1. [Maxcon] wrote to the parties on 12 September 2022 providing them
with a without prejudice proposal for Maxcon to carry out certain
works to the roof drainage system the subject of this proceeding, at
its cost, which Maxcon and its hydraulic consulting engineer believe
will satisfy all of the parties’ concerns outlined in their respective
reports filed with the Tribunal in this matter and result in a fully
compliant roof drainage system (proposal).
2. On 17 November 2022 (after the Tribunal made the orders above on
14 November 2022) the solicitors for the [Bodies Corporate] sent a
letter to the solicitors for Maxcon, in essence agreeing to the proposal
subject to certain clarifications; a copy of which is attached. Maxcon
is of the strong view that those clarifications which are only minor,
can be provided to satisfy the [Bodies Corporate] to achieve a
resolution of the matter.
3. The proposal does not directly or adversely affect the [QBCC] and if
accepted, would lead to a favourable outcome for the benefit of all
-- 4 of 14 --
5
the residents including [Dr Carter] and the [Bodies Corporate] and if
that can be achieved, the QBCC should fully support the resolution
rather than standing in its way.
4. The proposal if accepted by the parties and their experts would
provide a full and final resolution to the proceeding without the
parties being required to incur further costs and inconvenience
including legal costs (resolution).
5. The resolution would provide a better and more certain outcome to the
parties than proceeding to a 4-day hearing of the matter simply to
review a decision made by QBCC the outcome of which is not
guaranteed to fix the roof drainage system the subject of this
proceeding.
The application has been overtaken by events and may be put to one side.
(b) an application by QBCC filed 22 December 2022 for a directions hearing. The
application, once again, has been overtaken by events and may be put to one
side.
(c) an application by Maxcon filed 6 January 2023 for a stay of the Tribunal
proceeding “… pending final determination, including all appeals, of Supreme
Court Proceeding No. BS10826/22 ...”;
(d) an application by Maxcon filed 10 January 2023 for an extension of the time for
compliance with the directions given by the Tribunal on 14 November 2022;
and
(e) an application by Dr Carter filed 24 January 2023 for leave to appear on 30
January 2023 and all future hearings of the review proceeding by telephone.
The application was granted in respect of the hearings on 30 January 2023 and
16 February 2023.
Hearing on 30 January 2023
[13] On 30 January 2023 the Tribunal directed as follows:
1. [Dr Carter] have leave to attend the hearing of the proceeding today and on
16 February 2023 by telephone.
2. [Maxcon] file and serve on the other parties by email any submissions in
support of its applications filed 6 and 10 January 2023 and any documents on
which it intends to rely, by:
4:00pm on 06 February 2023
3. The other parties file and serve by email any submissions in reply to
[Maxcon’s] submissions and documents on which they intend to rely, by:
4:00pm on 13 February 2023
4. In default of compliance with order 2, [Maxcon’s] applications filed 6 and 10
January 2023 be dismissed.
5. [Maxcon’s] applications filed 6 and 10 January 2023 are adjourned to 16
February 2023 for a half-day hearing at 1.30pm.
-- 5 of 14 --
6
Material
[14] The parties filed extensive material, both before and following the hearing on 30
January 2023. The material includes:
Dr Carter
(a) a letter addressed to the Tribunal and dated 9 January 2023;
(a) a letter addressed to the Tribunal and dated 27 January 2023; and
(b) a letter addressed to the Tribunal and dated 13 February 2023.
QBCC
(a) submissions filed 22 January 2023;
(b) submissions filed 27 January 2023; and
(c) submissions filed 14 February 2023.
Maxcon
(a) claim and statement of claim in proceeding number 1082 of 2022 commenced
by the Principal Body Corporate in the Supreme Court of Queensland against
Maxcon (Supreme Court proceeding);
(b) affidavit of Dimitrios Jimmy Diakou (Mr Diakou) filed 30 January 2023.
Exhibited to the affidavit is a draft defence in the Supreme Court proceeding;
(c) affidavit of Mr Diakou filed 6 February 2023. The affidavit exhibits the notice
of intention to defend and defence of Maxcon filed in the Supreme Court
proceeding and deposes to the truth of the defence, the status of the proceeding
and the estimated costs of Maxcon of a hearing of the Tribunal proceeding; and
(d) submissions filed 6 February 2023.
Bodies Corporate
(a) letter addressed to the Tribunal and dated 27 January 2023; and
(b) submissions filed 10 February 2023.
Hearing on 16 February 2023
[15] The focus of the hearing on 16 February 2023 was whether Maxcon should be granted
a stay of the Tribunal proceeding given commencement of the Supreme Court
proceeding. It was agreed by the parties Maxcon should be granted a stay of the
directions given on 14 November 2022 pending a decision on the application for a
stay, with further directions given if the application for a stay of the Tribunal
proceeding is refused.
[16] Also in issue was whether the claims made, and relief sought, by Dr Carter are
sufficiently particularized in the Tribunal proceeding.
-- 6 of 14 --
7
Supreme Court proceeding
[17] The Supreme Court proceeding was commenced by the Principal Body Corporate
against Maxcon on 8 September 2022. A notice of intention to defend and defence
were filed by Maxcon on 30 January 2023. The Principal Body Corporate filed a
reply on 30 May 2023.
Submissions
Maxcon’s submissions
[18] Maxcon, in submissions filed 6 February 2023, submits the application for review “…
is somewhat unclear and the various relief claimed is unavailable to Dr Carter …”
[19] The relevant contract is in dispute between the parties to the Supreme Court
proceeding. It will be necessary for the Tribunal to decide what is the contract in the
Tribunal proceeding, it is submitted by Maxcon.
[20] The Principal Body Corporate, in the Supreme Court proceeding, claims damages for
the consequential loss allegedly suffered by Dr Carter. In the circumstances, it is
submitted by Maxcon, it would be unfair to give the direction sought by Dr Carter.
[21] Mr Kidston of counsel, who appeared on behalf of the Maxcon on 30 January 2023
and 16 February 2023, expanded on the submissions.
Dr Carter’s submissions
[22] Dr Carter, in submissions filed 13 February 2023, submits:
(a) the Bodies Corporate acknowledge water is continuing to enter her unit; and
(b) in the Supreme Court proceeding, the Principal Body Corporate alleges “…
there are no issues raised by [Maxcon] in relation to building defects at The
Johnson.”
[23] Maxcon’s application to stay the review proceeding can be dismissed “… as it is
irrelevant to the workings of Australian Building Law …”, it is submitted. Dr Carter
further submits Maxcon’s submissions on costs are “unacceptable” she having
incurred significant costs.
[24] The submissions were expanded on by Dr Carter during the hearing on 16 February
2023.
QBCC’s submissions
[25] QBCC, in submissions filed on 14 February 2023, outlines the background to the
Tribunal proceeding. The submissions then identify the relevant allegations in the
Supreme Court proceeding, and Maxcon’s response to the allegations, and
summarises the issues in the Supreme Court proceeding in the following terms:
(a) whether the contract was a “sham”;
(b) the nature and terms of the “true contract” between Maxcon and [Asian Pacific
Group Pty Ltd] including the work undertaken by Maxcon pursuant to same;
-- 7 of 14 --
8
(c) the effect of the above issues on the operation of section 36(3) of the [Body
Corporate and Community Management Act 1997], if any;
(d) whether, in light of the above issues, Maxcon has breached the
contract;
(e) whether, in light of the above issues, Maxcon is liable for the defects and
associated damage and/or costs incurred alleged in the [statement of claim];
(a) whether the Principal Body Corporate has standing to bring the [Supreme
Court proceeding] so far as it relates to “scheme land” for which the Principal
Body Corporate is not the registered owner.
[26] Maxcon, QBCC submits, neither admits nor denies the defects in the design or
construction, nor damage or the cost to rectify the damage. Having pleaded non-
admissions, Maxcon may not give or call evidence in the Supreme Court proceeding
in respect of facts not admitted.
[27] QBCC submits the relevant question is whether it is in the interests of the justice to
stay the Tribunal proceeding. In deciding that question, QBCC submits, the Tribunal
may have regard to the following:
(a) whether Maxcon, as the party seeking the stay and a respondent, has met the
burden to justify a stay of this proceeding, interfering with Dr Carter's
entitlement to have the [Tribunal proceeding] determined; and
(b) in balancing the “the justice” between the parties, weighing:
(i) the effect on Dr Carter and the Bodies Corporate and the effect on
Maxcon of either refusing or granting the Stay Application; and
(ii) the objects of the QBCC Act, which includes both achieving a reasonable
balance between contractors and consumers and providing remedies for
defective building work.
[28] It is also relevant, QBCC submits, to have regard to whether the Supreme Court
proceeding impedes the Tribunal being able to reach the correct and preferable
decision in the Tribunal proceeding.
[29] QBCC submits there is a clear overlap between the subject matter of the Supreme
Court proceeding and the Tribunal proceeding. There is limited potential for issue
estoppel to arise from a decision in the Tribunal proceeding prior to a decision in the
Supreme Court proceeding. The overlap mentioned weighs in favour of the grant of
a stay of the Tribunal proceeding, QBCC submits. However, having regard to matters
weighing against the grant of a stay, it submits the potential prejudice does not justify
departing from the ordinary course of the Tribunal proceeding being determined.
Bodies Corporate’s submissions
[30] The Bodies Corporate’s submissions filed 10 February 2023 respond to Maxcon’s
submissions. They helpfully summarised the items of complaint the subject of the
Tribunal proceeding. Then, they summarise the scope and issues in the Supreme
Court proceeding and submit Maxcon’s position is as follows:
(a) work was performed by it, but not pursuant to the contract signed by it, rather
-- 8 of 14 --
9
pursuant to a verbal side-deal (i.e., via an alleged sham, the real transaction
is the “true contract”);
(b) does not admit, but also does not deny, the defects;
(c) raises a legal point about responsibility for consequential loss.
[31] The “interplay” between the Tribunal proceeding and the Supreme Court proceeding,
the Bodies Corporate submit, is as follows:
Issue QCAT Supreme Court
Whether the respective
items are building work as
apart from other types of
work
In issue.
Note, this is a legal point only
Not in issue, as this arises from
the statutory test
Responsibility for the work
performed
In issue - but pursuant to
statutory test.
However, sham has not been
asserted in QCAT as,
notwithstanding directions for
filing of evidence, there is no
evidence of alleged sham.
In issue - but as per
contractual responsibility
Whether work is defective In issue - but based on statutory
test.
In issue - based on the
contract or “True Contract”
Notwithstanding direction,
Maxcon has not adduced
evidence
Maxcon cannot adduce
evidence
Whether it would be fair to
issue a direction
In issue Not in issue
Consequential damages
argument
Not in issue In issue
[32] The submissions then continue:
Accordingly, in relation to contentious points upon which Maxcon would
adduce evidence, the real issue is responsibility for the work. However, in the
absence of the filing of any evidence by Maxcon deposing to having been
involved in a sham, there is no controversy before this tribunal of same.
[33] Maxcon deposes to being involved in a sham. It is not in issue in the Tribunal
proceeding, it is further submitted. It has not produced evidence on whether the work
was defective in the Tribunal proceeding and it cannot do so in the Supreme Court
proceeding.
[34] The submissions conclude the application for a stay of the Tribunal proceeding should
be dismissed.
Discussion
[35] Section 58(1) of the Queensland Civil and Administrative Tribunal Act 2009 (QCAT
Act) empowers the Tribunal to make an interim order it considers appropriate in the
-- 9 of 14 --
10
interests of justice before making a final decision. The examples include to protect a
party’s position for the duration of the proceeding.1
[36] A specific power to make an order staying the operation of all or part of a reviewable
decision if a proceeding for the review of the decision has started under the Act is
found in section 22(3). The Tribunal may make the order under the subsection only
if it considers the order is desirable after having regard to the following:
(a) the interests of any person whose interests may be affected by the making of
the order or the order not being made;
(b) any submission made to the tribunal by the decision-maker for the reviewable
decision; and
(c) the public interest.2
[37] It is well-settled the Tribunal has power to make the orders sought by Maxcon.3 It
was not suggested otherwise by the parties.
[38] Maxcon’s application is for a temporary stay of the Tribunal proceeding. As was said
in Re Sterling Pharmaceuticals Pty Ltd v The Boots Company (Australia) Pty Ltd4,
there is significant difference between a permanent stay or dismissal of a proceeding,
and a temporary stay or lengthy adjournment of the proceeding. If a temporary stay
of the Tribunal proceeding is granted, the Tribunal remains in control of the
proceeding.
[39] In Sterling, Lockhart J, at [16], set out a non-exhaustive list of the considerations for
the grant of a temporary stay of a proceeding:
• Which proceeding was commenced first.
• Whether the termination of one proceeding is likely to have a material effect on
the other.
• The public interest.
• The undesirability of two courts competing to see which of them determines
common facts first.
• Consideration of circumstances relating to witnesses.
• Whether work done on pleadings, particulars, discovery, interrogatories and
preparation might be wasted.
• The undesirability of substantial waste of time and effort if it becomes a common
practice to bring actions in two courts involving substantially the same issues.
• How far advanced the proceedings are in each court.
1 Section 58(1)(a) of the QCAT Act.
2 Section 22(4) of the QCAT Act.
3 See, for example, JM Kelly (Project Builders) Pty Ltd v Queensland Building Services Authority [2011]
QCAT 60 and Chief Executive of the Department of Justice and Attorney-General v Kollosche & Anor
[2015] QCAT 145.
4 [1992] FCA 72.
-- 10 of 14 --
11
• The law should strive against permitting multiplicity of proceedings in relation
to similar issues.
• Generally balancing the advantages and disadvantages to each party.
[40] The list of considerations was approved by the High Court of Australia in Henry v
Henry5, and more recently referred to in Langford v RCL Cruise Ltd trading as Royal
Caribbean Cruises6.
Which proceeding was commenced first?
[41] The Tribunal proceeding was commenced by Dr Carter on 2 July 2019, long before
the Supreme Court proceeding. In the former proceeding, voluminous material has
been filed by Dr Carter, QBCC and the Bodies Corporate. The material includes
statements of evidence, documents and submissions filed by Dr Carter, the statement
of reasons for decision and the accompanying documents, other documents and
submissions filed by QBCC and statements of evidence, documents and submissions
filed by the Bodies Corporate.
[42] As I have said, Maxcon has not filed material on which it intends to rely at the hearing
of the Tribunal proceeding. It has been given several opportunities to do so.
[43] The Supreme Court proceeding was commenced on 8 September 2022. A notice of
intention to defend and defence were not filed by Maxcon until almost 4 months later,
on 30 January 2023. A reply was filed by the Principal Body Corporate more than
three months later, on 13 May 2023.
[44] The Tribunal proceeding has progressed to the point it was fixed for hearing.
Pleadings have closed in the Supreme Court proceeding. Notwithstanding, and given
the leisurely pace to date, it is unlikely the Supreme Court proceeding will be heard
and decided for many months, perhaps years. Any appeal, or appeals, from the
decision and orders at first instance is likely to add significantly to the delay in finally
concluding the proceeding.
[45] The fact the Tribunal proceeding commenced long before the Supreme Court
proceeding and it has progressed to the point it was fixed for hearing, whereas the
Supreme Court proceeding has not progressed beyond the close of pleadings, are
significant matters weighing against the grant of a stay of the Tribunal proceeding.
Public interest
[46] The public interest favours the early and economic resolution of disputes before the
Tribunal and proceedings being concluded in an informal way that minimises costs to
the parties, and is as quick as is consistent with achieving justice.7 The interests of
justice will be better served by allowing the Tribunal proceeding, a proceeding before
the Tribunal for nearly four years and in which the parties, other than Maxcon, have
filed voluminous material thereby incurring significant cost and expense, to continue
rather than staying the Tribunal proceeding in favour of the Supreme Court proceeding
only recently commenced and it and any appeal or appeals unlikely to finally resolve
5 (1996) 185 CLR 571, per Dawson, Gaudron, McHugh and Gummow JJ at 590.
6 [2023] FCA 626, per Jackman J at [26].
7 Section 4(b) and (c) of the QCAT Act.
-- 11 of 14 --
12
the proceeding for an indefinite time.
Parallel proceedings
[47] There is an overlap between the issues in dispute in the Tribunal proceeding and those
in dispute in the Supreme Court proceeding. The central issues, however, are
different.
[48] In general terms, it is undesirable for parallel proceedings to be conducted in two
jurisdictions, thereby putting the parties to the two proceedings to additional cost and
expense. However, in the Tribunal proceeding significant cost and expense has
already been incurred whilst significant cost and expense is yet to be incurred in the
Supreme Court proceeding.
[49] Additionally, the Tribunal is conscious of the effect of the circumstances giving rise
to the Tribunal proceeding on the health and well-being of Dr Carter. A stay of the
review proceeding after nearly four years of litigation is likely to have a profound
effect on her.
Witnesses
[50] The parties did not raise for consideration the circumstances relating to witnesses. A
consideration of significance relating to witnesses is the effect of an indefinite delay
on their recollection of the events.
Wasted work
[51] The extent to which work done in the Tribunal proceeding might be wasted if the stay
of the proceeding were granted was not addressed by the parties in submissions. An
indefinite stay is likely to give rise to some waste.
Summary
[52] I am not satisfied it is in the public interest, or the interests of justice, to grant the stay
of the Tribunal proceeding. Maxcon’s application for a stay of the proceeding is
dismissed.
Dr Carter’s claims
[53] Maxcon submits it is entitled to know the case it is required to meet and Dr Carter’s
original application in the Tribunal proceeding fails to identify the case with sufficient
particularity. It would be a denial of natural justice, the submissions continue, to allow
the proceeding to continue without sufficient particulars of what is sought by Dr
Carter from the Tribunal.
[54] It is unclear whether the submissions were put as a ground for a stay of the Tribunal
proceeding or the giving of directions for particulars. Whatever be the reason, the
submissions are rejected.
[55] Dr Carter’s original application, in part B, is a brief summary of why she thinks the
decision is wrong or not properly made. The case Maxcon is required to meet is
adequately particularised in the material filed since the application, in particular
QBCC’s statement of reasons for the decision and the accompanying documents.
-- 12 of 14 --
13
-- 13 of 14 --
14
Directions
[56] Directions will be given for Maxcon complying with order 1 of the orders made by
the Tribunal on 14 November 2022, the proceeding being fixed for hearing and a
directions hearing.
Decision
[57] The decision of the Tribunal is as follows:
(a) Maxcon’s application filed 6 January 2023 for a stay of the review proceeding
is dismissed;
(b) Maxcon’s application filed 10 January 2023 for an extension of the time to
comply with order 1 of the orders made by the Tribunal on 14 November 2022
is granted. Maxcon comply with the order by 4.00pm on 15 August 2023;
(c) the Tribunal proceeding be fixed for hearing for four days commencing on the
next available hearing date after 15 August 2023;
(d) the Tribunal proceeding be listed for a directions hearing by telephone after 15
August 2023 and not less than fourteen days before the date fixed for the hearing
of the proceeding. The purpose of the directions hearing is for the Tribunal to
confirm with the parties:
(i) the material they have filed and on which they intend to rely at hearing;
(ii) the precise issues to be determined at the hearing;
(iii) the witnesses, if any, they require for cross-examination;
(iv) whether it is proposed the witnesses will be giving evidence in person or
by remote means (specifying the mode of attendance);
(v) any limitations on the time of availability of witness; and
(vi) any other issue necessary to ensure the proceeding is ready for hearing;
and
(e) this order be served on the parties by email.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2023/278