Body Corporate for Beachfront Towers CTS 10075 v Queensland Building and Construction Commission & Anor [2023] QCAT 198
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Body Corporate for Beachfront Towers CTS 10075 v
Queensland Building and Construction Commission &
Anor [2023] QCAT 198
PARTIES: BODY CORPORATE FOR BEACHFRONT TOWERS
CTS 10075
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
MIDSON CONSTRUCTION (QLD) PTY LTD
(respondent)
APPLICATION NO/S: GAR071-20
MATTER TYPE: Building matters
DELIVERED ON: 15 May 2023
HEARING DATE: 22 October 2021
HEARD AT: Brisbane
DECISION OF: Member Holzberger
ORDERS: The application for miscellaneous matters filed by
BODY CORPORATE FOR BEACHFRONT
TOWERS CTS 10075 on 19 March 2021 is
dismissed.
The application for miscellaneous matters filed by
MIDSON CONSTRUCTION (QLD) PTY LTD on
24 March 2021 is dismissed.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – ENDING PROCEEDINGS
EARLY – SUMMARY DISPOSAL – SUMMARY
JUDGMENT FOR DEFENDANT OR RESPONDENT:
STAY OR DISMISSAL OF PROCEEDINGS - general
administrative reviews – building matters – applications for
determination of preliminary issue – application to strike out
application to stay when building work completed – whether
sufficient evidence to determine – where applicant had
proceedings in the tribunal and the Supreme Court – whether
application vexatious, abuse of process
Queensland Building and Construction Commission Act
1991 (Qld), s 72A(4)
-- 1 of 7 --
2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 24, s 47
JM Kelly (Project Builders) Pty Ltd & Anor v Queensland
Building Services Authority [2011] QCAT 463
UBS AG v Tyne (2018) 265 CLR 77
APPEARANCES &
REPRESENTATION:
Applicant: I. Erskine (counsel, instructed by Barclay Beirne Lawyers)
for Body Corporate for Beachfront Towers CTS 10075
First Respondent: S.E Seefeld (counsel, instructed by QBCC) for QBCC
Second Respondent: B.E Codd (counsel, instructed by Bathersby Legal) for
Midson Construction (QLD) Pty Ltd
REASONS FOR DECISION
[1] Body Corporate for Beachfront Towers CTS 10075 (Beachfront Towers) engaged
Midson Construction (QLD) Pty Ltd (Midson) to carry out building works to a unit
complex at 4 Aerodrome Road Maroochydore.
[2] The building work commenced in or about February 2013 and a “partial” practical
completion certificate was issued by Beachfront Towers property manager Stephen
Ingram “as at” 21 June 2013.
[3] Beachfront Towers wrote to Midson regarding alleged defects on 17 October 2019.
Midson responded on 27 November 2017 effectively denying liability.
[4] On 21 June 2019 Beachfront Towers commenced proceedings in the Supreme Court
against both Midson and Stephen Ingram, claiming in each case damages for breach
of contract and in the alternative damages for negligence.
[5] On 6 September 2019 Beachfront Towers made a complaint to the Queensland
Building and Construction Commission (the Commission), citing as the completion
date for the works 21 June 2013.
[6] On 19 December 2019 the Commission issued a direction to rectify in respect of 16
items to Midson.
[7] On 15 January 2020 Midson applied for an internal review of that decision.
[8] The internal review decision made on 22 January 2014 set aside the previous direction
to rectify on the basis that at the time the internal review decision was made it was
more than six years and six months from the completion of the works.1 The power to
issue the direction to rectify had expired on 21 December 2019.
[9] It is Beachfront Towers’ contention that while its claim specified a completion date
of the works of 21 June 2013 there is evidence that the works continued beyond that
date. To succeed in the originating proceedings it must establish that the works in fact
continued until 22 July 2013 or beyond.
1 Queensland Building and Construction Commission Act 1991 (Qld) s 72A(4).
-- 2 of 7 --
3
[10] Beachfront Towers applied to the tribunal for a review of the decision of the
Commission not to issue a direction to rectify to Midson on 19 February 2020
(originating application).
[11] Midson was joined as a respondent in that proceeding on 6 October 2020.
[12] On 19 March 2021 Beachfront Towers filed an application for miscellaneous matters
seeking that the tribunal determine as a preliminary issue the date on which the
building works relevant to the application were completed (the Beachfront Towers
application).
[13] On 24 March 2021 Midson filed in the tribunal an application for miscellaneous
matters seeking to have the originating proceedings struck out as an abuse of process
or in the alternative stayed pending the determination of proceedings brought by
Beachfront Towers in the Supreme Court.
[14] Beachfront Towers opposes the Midson application. Midson opposes the Beachfront
Towers application.
[15] The Commission's position is that the Beachfront Towers application should be
determined in its favour, the originating proceedings should not be struck out as an
abuse of process and in view of a substantial overlap of factual issues in the tribunal
and the Supreme Court, proceedings should not run in parallel.
[16] Both applications were heard on 22 October 2021. All parties have been granted leave
to be legally represented. The tribunal has had the benefit of detailed written and oral
submissions by the parties’ respective representatives.
Strike out application
[17] Midson seeks to have the review application struck out pursuant to section 47 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) because:
(a) the relief sought in the review application cannot be granted by the tribunal and
accordingly the application is “frivolous, vexatious or lacking in substance”;2
and/or
(b) the proceeding is an “abuse of process,”3 the applicant having elected previously
to commence proceedings in respect of the alleged defective works in the
Supreme Court.
Frivolous, vexatious or lacking in substance
[18] Beachfront Towers was apparently self-acting at the time of drafting and filing the
review application.
[19] The review application clearly identifies the internal review decision as the decision
to be reviewed.
[20] The printed application to review a decision contains a section headed “briefly
describe what you want to happen" in which Beachfront Towers states that it wants
the internal review decision “declared void” and the original decision “reinstated”.
2 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 47(1)(b).
3 Ibid, s 47(1)(c).
-- 3 of 7 --
4
[21] Under section 24(1) of the Queensland Civil and Administrative Tribunal Act 2009
(Qld) the power of the tribunal on review is limited to:
(a) confirming or amending the decision;
(b) setting aside the decision and substituting its own; or
(c) setting aside the decision and returning it to the decision-maker for
reconsideration with directions it considers appropriate.
[22] It is not in dispute that the relief identified in the review application is beyond the
scope of section 24(1) but it is the submission of Beachfront Towers and the
Commission that that in itself does not support the striking out of the action. I agree
with them.
[23] The substance of the relief it seeks, however poorly worded the application may be,
is also clear in my view. It is seeking to have the internal review decision set aside
and a decision in terms of the original decision substituted for it. I am unable to see
except theoretically how Midson is disadvantaged by the wording contained in the
application. In any event the written and oral submissions by the parties’
representatives in respect of these application should leave it in no doubt as to the
nature of these proceedings and the relief actually sought. There has been no denial
of natural justice or lack of procedural fairness.
[24] I agree with the submission of Beachfront Towers that to strikeout elevates form over
substance and it is not consistent with the underlying legislative purposes namely
consumer protection.4
[25] Although Beachfront Towers has indicated that the review application will be
amended it is perhaps unfortunate that Beachfront Towers did not take steps to amend
its application to avoid the argument. In my view the review application is not
frivolous, vexatious or lacking in substance.
Abuse of process
[26] In addition and prior to the review proceedings Beachfront Towers commenced
proceedings in the Supreme Court against Midson and Stephen Ingram who at the
relevant time was Beachfront Towers’ project manager. The action is for damages for
defective building works, breach of contract and negligence.
[27] Commencing and pursuing these review proceedings while the Supreme Court
proceedings remain on foot is, it is submitted by Midson, an abuse of process which
should result in the review proceedings being struck out or permanently stayed or in
the alternative stayed until the Supreme Court proceedings have been determined.
[28] Mr Codd, Counsel for Midson, referred at length in written and oral submissions to
the decision of the High Court in UBS AG v Tyne (2018) 265 CLR 77.
[29] In that case Tyne as trustee of a family trust commenced action in the Federal Court
against a bank claiming damages arising from advice given by the bank to Tyne and
a former trustee of the trust. Tyne, the former trustee and related company had earlier
commenced proceedings against the bank in essentially the same terms in the Supreme
Court of New South Wales.
4 Beachfront Towers' submissions in reply, para. 15.
-- 4 of 7 --
5
[30] Tyne and the former trustee discontinued the Supreme Court action leaving only the
related company as sole plaintiff. The Supreme Court proceedings were stayed
permanently and Tyne commenced the Federal Court action.
[31] The majority characterised Tyne’s actions as “hiving off the Trust's claim, with a view
to bringing it in another court after the determination of the New South Wales
Supreme Court proceedings…"5
[32] It is not controversial that there is a standard substantial factual overlay in the two
proceedings but in my view that is as far as it goes. The review application and
Supreme Court proceedings are in my view very different proceedings.
[33] The decision under review in the review proceedings is the Commission decision not
to issue a direction to rectify to Midson.
[34] The Commission's power to issue a direction to rectify and consequently the tribunal's
power under review is defined and limited by the provisions of Part 6 of the
Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act).
[35] The Commission may issue a direction to rectify if it is of the opinion that building
work is defective or incomplete or consequential damage has been caused by it.6
[36] “Building work" is defined by the QBCC Act. There are limitations including time
limitations on the issue of a direction to rectify.7
[37] There is no remedy provided outside rectification. The Commission cannot
compensate a party for the losses that may flow from the defective works or the
rectification process (such as the cost of alternative accommodation) or determine
contractual disputes.
[38] By an administrative decision or series of them the Commission identifies defective
building work, gives directions as to the approach of the appropriate remedies and
determines if necessary whether those directions have been complied with.
[39] The remedies contained in Part 6 are in addition to the claimant's rights under the
building contract or at common law. It is not uncommon that a direction to rectify,
even if completed, will not provide a complete remedy to an aggrieved party.
[40] The Supreme Court action is an action for damages for breach of contract and
negligence. That action is not constrained or even informed by the provisions of the
QBCC Act. It is as characterised by the tribunal in JM Kelly (Project Builders) Pty
Ltd v Queensland Building Services Authority [2011] QCAT 463 as “just about
money".8
[41] I am of the view that the circumstances here, where the overlay is factual and claims
for relief sought in each case so different, both legally and practically are very
different from those in UBS and are distinguishable on that basis.
5 UBS AG v Tyne (2018) 265 CLR 77, [55] ( Kiefel CJ, Bell and Keane JJ).
6 QBCC Act, s 72.
7 Ibid, s 72A.
8 [2011] QCAT 463, [37].
-- 5 of 7 --
6
[42] While the Supreme Court could order specific performance of the contract building
rectification of defective building works it is difficult to imagine it exercising its
discretion to do so where complex construction issues are involved.
[43] I do not accept that allowing the two proceedings to continue results in an
impermissible double recovery. Should Midson carry out rectification works either
pursuant to a direction to rectify or voluntarily by agreement Beachfront Towers
cannot claim the value of those works as damages.
[44] Any damages ultimately awarded by the Supreme Court are likely to differ from those
claimed in a statement of claim even if only as a result of the effluxion of time.
[45] In those circumstances the strikeout application was dismissed.
Stay
[46] For the same reasons I'm not prepared to stay the review proceedings pending
determination of the Supreme Court proceedings.
[47] In JM Kelly the tribunal discussed a similar application for stay stating:9
It is clear that, in exercising its review jurisdiction, the Tribunal must have
regard to the objects of both the QCAT Act and the enabling Act. Therefore,
my determination of a procedure that is both fair and quick must be informed
by the objects of the QBSA Act.
[48] Clearly it is consistent with the objects of the QBCC Act and public safety that the
actual rectification of defective building work be undertaken properly and as quickly
as practicable and that will not be achieved if the review proceedings are stayed.
Preliminary issue application
[49] Beachfront Towers applies to the tribunal to determine as a preliminary issue the date
on which the building works to which the direction to rectify relates were completed
for the purposes of section 72A(4) of the QBCC Act.
[50] It is the basis of the internal review decision that a direction to rectify could not be
issued because more than six years and six months had elapsed since completion of
the building works and that is indeed the case if Beachfront Towers’ claim to the
Commission which disclosed a completion date of 21 June 2013 accurately defines
the completion date.
[51] Beachfront Towers says that material which has since come to light indicates that
building work continued beyond that date.
[52] For Beachfront Towers to bring itself within the six years and six months limitation it
must establish the building work was completed on or after 22 July 2013. I am
indebted to Mr Seefeld, counsel for the Commission, for his helpful written
submissions setting out the further works in tabular form.10
[53] Mr Seefeld's submissions concluded:11
9 [2011] QCAT 463, [31].
10 Commission's submissions in response para. 111.
11 Commission's submissions para. 125.
-- 6 of 7 --
7
the available evidence indicates that the date that the building work was
completed was between 31 July 2013 and 22 August 2013 (with 22 August 2013
being the better position).
[54] The materials referred to were annexures to an affidavit of Michael Perren dated 7
July 2020.
[55] The difficulty I have with Mr Perren’s affidavit and the various annexures is that Mr
Perren does not and presumably cannot give direct evidence as to those matters.
Instead he relies on the various documents which he has apparently sourced from the
historical records of Beachfront Towers. There is no other evidence on the point on
behalf of Beachfront Towers.
[56] It appears likely that Midson may be able to shed some light on the actual completion
date but it declined to file any material on the report on the point despite directions to
allow it to.
[57] Clearly there is an issue here as to the admissibility of all or any of the materials in
this. In oral submissions Mr Codd has foreshadowed Midson’s objection to that
material. But before considering the point the issue is whether the tribunal should,
having regard to the limitations of the evidence, determine the issue as a preliminary
point prior to the proceeding.
[58] I appreciate that such a determination of the point could lead to a disposal of the action
and potentially save a great deal of time and money for the parties in the tribunal.
[59] I do not however believe that it is just and convenient on the available evidence before
all witness statements have been lodged for the tribunal to make a decision. It may be
that the evidence of the parties does little to clarify the point, however I am of the
view that it is unfair to decide the point on the evidence as it currently stands.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2023/198