Field v Carey [2023] QCAT 196
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Field v Carey [2023] QCAT 196
PARTIES: KEITH JOHN FIELD AND MARIA FIELD
(applicant)
v
ADAM BRIAN CAREY
(respondent)
APPLICATION NO/S: BDL185-20
MATTER TYPE: Building Matters
DELIVERED ON: 28 April 2023
HEARING DATE: 20 October 2022
HEARD AT: Brisbane
DECISION OF: Member Richard Oliver
ORDERS: The Respondent must pay the Applicants the sum of
$48,667.74 by 31 August 2023
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – DEFECTIVE WORK –
where parties entered into a contract for the construction of
a paved concourse around an inground swimming pool –
where concrete slab supporting the pavers moved causing
cracking of pavers – where no engineering design – where
movement due to moisture in the subsoil – whether
movement caused by lack of design of reinforcing steel –
whether dowels from slab to pool coping sufficient –
whether rectification will result in a betterment for the
applicants – whether method and cost of rectification
reasonable
Fankhauser v Mission Beach Property Management [2017]
QCATA 65
Hyder Consulting (Australia) Pty Ltd v Wilh Wilhelmsen Agency
Pty Ltd & Anor [2001] NSWCA 313
Hoad v Scone Motors Pty Ltd [1977] NSWLA 88
Jones v Dunkel (1959)101 CLR 298
APPEARANCES &
REPRESENTATION:
Applicant: Mr Hick of counsel instructed by Robinson Locke Litigation
Lawyers
-- 1 of 13 --
2
Respondent: Irish Bentley Lawyers
REASONS FOR DECISION
[0] In February 2012 the applicants purchased an acreage property at Priors Pocket Road,
Moggill with the intention of renovating the property to use for their retirement. The
house and grounds needed substantial work. The applicants engaged an architect in mid
2013 drawings were prepared for the renovation work to be undertaken. The work
commenced after this and took some years to complete. Part of the renovation and re-
modelling work included refurbishment of the swimming pool at the rear of the house.
[1] The swimming pool is rectangular with a U shaped design in the middle of the long side
between the pool and the house. The U shape has steps to allow ingress and egress to and
from the pool. There is a bond beam coping on the perimeter of the pool with tiles on top
of the coping. The pool is separated from the house by lawn and enclosed with typical
pool fencing.1
[2] As part of the overall redesign of the grounds the applicants decided to integrate the pool
area into the new extended tiled back deck of the house so there was a seamless transition
from the deck area to the pool. This involved the construction of a concourse around the
pool, beyond the coping, with the tiled paving then going across the existing grassed area
to the back deck of the house.2
[3] The applicants contacted Mr Carey to inspect the works and provide a quotation to
undertake the pool work, as described to him by Mr Field. The quote, dated 29 August
2015, set out the work to be undertaken and generally included:
• sub grade around the pool, box and steel around pool; lay and broom finish 60m2 of
concrete;
• Remove old coping; prep re-bed and lay new coping grout and add expansion joints;
• Remove old water line tiles; clean, prep and lay-up level render bed to water line; lay
new ceramic tile band and grout;
• Cut and lay new surrounding pavers; grout new paver stone adding expansion joints.
[4] The total cost of the work specified in the quote was $24,682 including GST. The
applicants were to supply the tiles/pavers. The quote was generated from the discussions
between Mr Field and Mr Carey as to the work to be carried out. There was no other
specification, for example, from the architect who had prepared the drawings for the
renovation. After receiving the quote some queries were raised by the applicants, but they
did not concern the matters in dispute here.
[5] The work was completed by 21 March 2016 and the applicants paid the full quoted price.
Some months later the applicants noticed cracks in the paving on the western side of the
pool. Mr Field contacted the applicant in February 2017 to discuss the problem with the
cracking. Mr Carey agreed to replace the cracked tiles and an arrangement was made for
him to do that in early April 2017. However, Mr Field thought it better to wait another
year before replacing the tiles, in case there was further movement. Despite that
arrangement, by March 2017 there was more cracking and subsidence on the southern
1 To better understand the configuration a photo of the original pool is attachment “A” to these reasons.
2 Attachment “B” is a photo of the pool after the renovation.
-- 2 of 13 --
3
side to the point where the glass pool fencing panels, that replaced the old pool fence,
became misaligned.
[6] Arrangements were made to meet earlier and after inspecting the work in June 2017 Mr
Carey agreed to replace the cracked tiles. The applicants raised the question of
subsidence and Mr Carey firmly rejected any responsibility for ground movement. He
asserted that all “sub-grading, box up, steel and concrete slab (work) was done correctly
and was also inspected by Mary’s (Mrs Field) brother (Mr Einsenreich) a licensed builder
before the pour”.3 This assertion about Mr Eisenreich’s involvement is contested but at
this point, it was apparent that a dispute was looming.
[7] Given the position taken by Mr Carey, Mr Field engage professional engineers to inspect
the site. On 31 May 2017 Mr Peter Wright, of Hughes Beal and Wright, inspected the
pool surrounds. After a further visit he provided a report on 6 October 2017. In summary
he found that the construction joint in the substrate had not been carried through to the
tiles, in other words the tiles straddled the joint between the existing coping and the new
concrete slab. Also the steel dowel bars from the pool bond beam (or coping) to the new
slab were rusting. He suggested that stainless steel dowels ought to have been used or the
joints be sealed to prevent moisture accessing the dowels.
[8] All of this was put to Mr Carey in an email from Mr Field on 9 October 2017 with the
intention of having him carry out some rectification work. In his response, Mr Carey
denied any responsibility saying that there was no warranty with the job, tiles were laid
over the expansion joints at the specific request of Mr Field and the differential in height
of the tiles was because of the tiles the applicants supplied. He says that he did just what
the applicants wanted him to do. In other words, he did what was required under the
contract. Mr Carey says he told Mr Field the tiles should not be laid over the expansion
joint but for aesthetic reasons, he says, Mr Field did not want a joint line where the coping
and the slab met. It would seem that irrespective of Mr Field’s request, if Mr Carey knew
that the movement of the slab would cause cracking on the joint line, he should not have
agreed to Mr Field’s instruction.
[9] As a result of this stand-off Mr Field then made a complaint to the Queensland Building
and Construction Commission (“QBCC”). An inspection was carried out by Mr Rendell
from the QBCC on 17 January 2018 and a report prepared. He found that:
• The contractor had as part of his works added a concrete surround to the pool.
• The pool is salt treated.
• The dowel bars used in the concrete surround to the pool copping have corroded.
• NCC part P2-1(a) & (b) list the performance criteria for a structure and in particular,
section (b) the structure must be designed to resist action by water.
• The construction joint has not been constructed or had subsequent treatment to the joint
to prevent moisture entering the joint and corroding the reinforcement.
• AS3958 part 5-4-5-2 states in part “Movement joints should be carried through the bed
and tiles/paving.
• Figure 5-1 of AS3958 details various treatments for movement joints, none of which
could be identified as having been used in this instance
• No evidence of control joints to be paving could be seen.
• A number of tiles/paving were drummy and caused lippage issues when walked on.
3 Exhibit 9 Statement of Keith Field [50].
-- 3 of 13 --
4
• the cracking of the tiles/paving over the construction joint has caused sharp edges to the
paving which is a health and safety issue.
[10] As a consequence, the QBCC issued a Direction to Rectify to Mr Carey on 19 January
2018. It said that the QBCC found Mr Carey responsible for:
The failure to instal reinforcement dowel bars to comply with NCC P2-1 concrete
sub-grade to the pool surround causing premature rusting; and
the installation of the pool surround paving which has not been installed to allow for
movement in the construction joint causing the paving to crack and present a safety
issue.
[11] Mr Carey carried out the rectification work within the time required by the Direction. In
a follow up email, the applicants confirmed with the QBCC that “the rectification work
required has been completed and that the pool and surrounds have been left in an
immaculate state”.
[12] Despite making this statement, the Mr Field says he remained concerned about the
integrity of the new slab and effects of further subsidence. As it transpired, by August
2019 the paving on the far western side of the pool had again subsided to about 8mm. In
a text message to the respondent, Mr Field said that “the four corner tiles to the new
expansion joint are real loose and or cracked or both”. Mr Carey was invited to further
inspect the work and discuss rectification.
[13] The further inspection was carried out on 8 November 2019. Mr Carey attended with a
representative from the Master Builders Association, Karen Hayworth. Mr Field’s
evidence is that Karen Hayworth advised Mr Carey that he should engage with
Mr. Field’s engineer, Mr Wright, and carry out rectification work in accordance with his
direction. However, Mr Carey indicated he wanted to have an independent engineer look
at the job. He engaged Matthew Tompkins of Structerre Consulting Engineers to inspect
the works and provide a report. According to Mr. Field, a report was prepared but he was
never given a copy due to client confidentiality reasons.
[14] No report was produced at the hearing of the application. Mr Carey's response to this
assertion is contained in his statement in that he contends that the applicants would not
allow Mr Tompkins to remove tiles for an invasive inspection and therefore the
consultation with Mr Tompkins did not provide any meaningful results. Mr Tompkins
was not called at the hearing to give any evidence about the inspection and provide any
opinion as to the cause of the damage even though he was not able to remove tiles. The
only evidence is that attached to Mr Carey’s affidavit which is a letter of engagement and
terms and conditions. There is a handwritten note of that document, by Mr Carey, which
states “they would not let the inspector remove any tiles so he had to go back”.
[15] When Mr Tompkins inspected the works on two occasions it would seem, if the evidence
of Mr. Field is accepted, a report was prepared but not produced to the Tribunal or to the
applicants. That evidence is contrary to what Mr Carey says about Mr Tomkins
inspection.
After consultation with Mr Tomkins did not provide any meaningful results, I
decided not to go forward with a formal engineering report given the QBCC and the
Applicants were satisfied with the renovations and the rectification works and
especially given the significant time that had elapsed since completion of these.
-- 4 of 13 --
5
[16] Although I accept that a formal report may not have been prepared, the only inference
that can be drawn from the failure to provide any evidence from Mr Tompkins is that his
conclusions are adverse too the respondent’s case.4
[17] When Mr. Field inquired after the Tompkins report, Mr Carey advised him by text
message that:
I do not feel responsible for further movement after being ordered to repair and doing
as told. Then after rectification work as ordered being completed and then it being
approved by yourself and Master Builders I feel I have for filed (sic) my
responsibility in this matter.
[18] There was no further communication between the applicants and Mr Carey. A further
report was obtained from Mr. Wright on 13 March 2020 which again reported that the
ongoing problems with the concourse around the pool is as a result of soil movement and
that the foundations had not been securely tied into the bond beam with dowels at
appropriate centres.
[19] Because all negotiations had broken down, the applicants commenced the proceeding in
the Tribunal.
[20] Given that background the parties have agreed a list of issues for consideration by the
Tribunal. They are:
1. Whether, prior to accepting the respondents quote an engineer should have been engaged
to provide drawings and specifications suitable to the site conditions as stated in the
Australian standard.
2. Determination of the cause of damage to the tiles, including if that damage is caused:;
a) Solely by movement in the soil;
b) Solely by defective building work; or
c) Partially by movement in the soil and partially by detective defective building
work.
3. Whether the damage to tiles constitutes or arises from defective building work performed
by the respondent.
4. Whether the damage to the tiles is due to the respondent’s breach of implied contractual
terms to carry out the renovation works in a proper and workmanlike manner and with
reasonable care and skill.
5. Whether the damage to the tiles is due to the respondents breach of a duty of care owed
to the applicants to carry out the renovation with reasonable care and skill of an
experienced licenced pool contractor.
6. What work is required to remedy the defects to the tiling?
7. Whether the Wright proposal will address ground movement?
8. Whether the Darestani proposal will prevent further damaged?
9. What are the further cost to the Darestani proposal to remedy the concourse and/or tiles?
4 Jones v Dunkel (1959)101 CLR 298.
-- 5 of 13 --
6
10. Quantum of rectification costs
[21] In hindsight, it would have been prudent for the Fields, or their architect, based on the
soil test they already had to have engaged an engineer to design the slab similar to what
occurs for a new house built on a slab. However, there are a few things that can be said
about this job. Firstly, the existing pool had been in place for many years. Mr Carey
acknowledged this by saying the pool was ‘well settled and stable”.5 This was obviously
correct because there have been no issues with the pool itself. Although there was no
specific discussion about the pool surrounds, it is reasonable to assume in those
circumstances that the surrounding ground would be well compacted and stable as well.
This is borne out by the site classification of “S”. Secondly, the new surround slab was
not structural in the sense that it was to support a structure or a significant load. Thirdly,
the purpose of the new concourse slab was to support the extended paved area from the
pool coping.
[22] The Fields wanted a contractor to refurbish the pool and the pool surrounds and sought
advice from the technical services manager at one of the local pool shops, Pool Mart
Kenmore. The particular expertise sought by them was primarily with respect to the pool
itself but in discussions with Mr Carey the further work was discussed.
[23] Mr Field now says that in discussions with Mr Wright that an engineering specification
should have been prepared prior to the work commencing. That is not surprising, given
the current problems, but that would have been Mr Field’s responsibility to obtain and
provide to Mr Carey for the purposes of quoting the job. However, there was no
discussion about an engineered design, just the soil test.
[24] Given the nature of the work to be undertaken being a paved pathway around the pool,
and for the reasons above, I conclude that at the time of giving the quote it was not
anticipated that a detailed engineered design the slab was necessary.
[25] It is now apparent from Mr Wright’s reports that the slab has failed for two reasons,
firstly not sufficient dowels were used to tie the new slab into the pool coping and
secondly, the soil conditions under the new slab, when wet is causing heave and
movement. There really is no dispute about this being the cause of the movement.
[26] It is also apparent from Mr Carey’s evidence that he did not construct the slab to take
into account soil movement to the extent now experienced. In the absence of engineering
drawings/specification he placed dowels at about 3 metre centres to secure the new slab
to the existing coping of the pool obviously to prevent lateral movement, or the slab
pulling away from the coping. I find that the dowels he used were never intended to be
structural in the sense of preventing vertical movement because this was never part of
the contract given the assumptions that the ground around the pool was stable. Had an
engineered design slab specification been given to Mr Carey, he would have, no doubt,
priced the slab accordingly and constructed it to the design.
[27] Insofar as it is argued that there was an implied term that Mr Carey would construct the
slab in accordance with an engineered design, I reject that proposition. I do so for the
reasons referred to above and Mr Carey certainly does not have the professional
qualifications to do so. The contract works are those described in the quote, accepted by
Mr Field, which Mr Carey carried out.
5 Mr Field’s statement paragraph 21.
-- 6 of 13 --
7
[28] In the absence of an engineered specification, can it be said that the works constituted
defective building work. It was left to Mr Carey to prepare the slab and use the dowels
to secure it to the coping of the existing pool. Mr Wright is of the opinion that there were
insufficient dowels to prevent vertical movement and this is borne out by the
consequential damage to the surrounds of the pool. The difficulty for Mr Carey is that he
took it upon himself to effectively decide the placement of the dowels and the reinforcing
steel which was ultimately inadequate. I find that to be the case on the basis of Mr
Wright’s evidence.
[29] This of course was all done with the concurrence of Mr Field in the sense that despite
engaging an architect for the renovation work, he chose not to engage an engineer for the
outside pool area. I am not suggesting he is at fault but when the project was discussed
with Mr Carey, he was content to go along with and accept the works set out in the quote.
Had an engineer been engaged and a more detailed specification been prepared to include
the work recommended by Mr Wright, the cost of the job would no doubt have increased.
[30] In respect of a negligence claim, had there been any inkling that there would be soil
movement to the extent that there was, then it was foreseeable that damage to the slab
was likely to occur.
[31] A report from Strusol Pty Ltd, its author being Mr Ario Darestani a civil engineer with
extensive experience in the building industry, has been tendered on behalf of the Mr
Carey.6 The report largely agrees with the reports of Hughes Beale and Wright as to the
extent and cause of the pavers moving because of movement in the soil below the slab.
He provides a summary of the Wright proposal for rectification as follows:
Finally, they recommend to remove the concrete slab, provide 12mm stainless steel
dowels at 900mm centres, saturate the ground surface for a week prior to casting
concrete, cast a new concrete 100mm thick slab with a layer of SL82 mesh at mid
height, with lay new tiles with a movement joint strictly above the joint.
[32] Mr Darestani describes the state of the movement and tile cracking he observed and
attributed the cause to increase and decrease of moisture under the slab. He also attributed
other causes to the disruption of the slab being:
Other factors such as drying shrinkage, thermal movement, movement associated with soluble
salts, and trees’ roots may also be considered as possible causes of tile cracking.
[33] He referred to the Australian Standard 3958-2–1992 which describes when concrete jobs,
no matter how small should have a specification. However, it also recognises that where
repetitive jobs are being performed it may not be necessary when certain items are
specified7 in the contract. Having considered all of that Mr Darestani provided the
following opinion with respect to this job:
Based on the abovementioned information I believe that the project lacks proper
design drawings and specifications. Unless the contractor signed a design and
construct contract to AS 4902-2000 [general conditions of contract for design and
construct] with the owner, it is unlikely that any of the above mentioned activities
becomes part of the contractors responsibilities. The contractor’s is original quote
also did not include or allow for any engineering work.
6 Exhibit 10
7 Ibid page 10 - 11
-- 7 of 13 --
8
[34] There was also discussion about the function of the dowel system and how it worked. He
expressed the view that even when creating a free movement dowelled joint this cannot
eliminate the cracking of tiles cast over problematic soil.8 This was mainly because of
the problematic supporting soil properties causing the differential vertical and horizontal
movement of the slab and the coping. I would say in passing that there is no evidence of
the coping having moved prior to the work undertaken by Mr Carey. Mr Darestani went
on to say:
By provision of a dowelled joint, the future design must also tackle rotational
movements of the slab about the centre of the joint. The use of an isolation joint
together with my recommendations provided in item 8.111.b result in a better long-
term performance.
[35] His recommendation for rectification was to engage a geotechnical engineer to assess the
soil condition under or in the vicinity of the slab. Engage a qualified engineer to prepare
drawings and specifications for this project. For cost-effective outcome, the engineer
should have experience in developing a rectification plan. He then went on to set out
what he described as “temporary work” to address the drainage issues in and around the
pool with further soil tests, root barriers, drainage trenches with gravel and drainpipe (as
described with a detailed plan and section.9
[36] This rectification approach differs from the Wright approach. It contends that if the slab
can be stabilised the tiles will have to be relaid or repaired. In my view there is much
uncertainty about this approach. However, it is much cheaper that the Wright option.
[37] The joint experts report of 14 March 2022 prepared by Donald Dixon from D & D Dixon
Pty Ltd and Damien Moloney from Capital Building Consultants put the cost of the
Darestani rectification work at between $16,299.79 and $17,419.46. Obviously, if the
drainage system does not work then the whole thing will have to be removed, including
the slab and the Fields will have to start again. I also accept what Mr Wright had to say
about the drainage of moisture from this type of soil and just how difficult that would be
to achieve.
[38] Although I found the Darestani report very helpful in setting out the problems and issues
with this job, I am of the view that the only way rectification work can be achieved with
certainty on the evidence, is for the slab to be removed and replaced with a proper
engineered designed structure to be able to cope with the movement in the underlying
soil. Even Mr Darestani says that this project should have had an engineered specification
to start with.
[39] The cost of this method of rectification is substantially more than the Darestani method.
Messers Dixon and Moloney estimate the rectification works as recommended by Mr
Wright would cost between $61,753.94 and $57,322.41.10
[40] The difficulty with this approach as I see it is that in the end the Fields will be getting
more than what they contracted to get from Mr Carey or be unjustly enriched at Mr
Carey’s expense. They will ultimately have a fully engineer designed slab. That is not
what Mr Carey contracted to build nor is that what the Fields expected to get in the
absence of an engineered design slab. However, what Mr Carey did build has failed. and
the consideration for that work failed. There is no complaint about the work associated
8 Ibid page 8.
9 Ibid page 13-14.
10 Exhibit 17.
-- 8 of 13 --
9
with the pool renovation work it is only the contract for the slab, both jobs on the quote
provided were priced individually.
[41] The question then arises as to how the Fields’ damages should be assessed. If the
assessment was approached on a restitutionary basis because of the failure of the slab, or
the consideration for the slab, the Fields should be put back into the position they would
be in if the work was not carried out at all. That can be achieved by refunding the Fields
for the money paid for the concourse slab and compensating them for returning the site
to its original state.
[42] Restitution for failure of consideration has not been specifically raised by the parties. As
there are no pleadings in the tribunal, one has to work out the various causes of action by
reference to the evidence put forward by the parties and the arguments and submissions
by their respective legal representatives. The Fields say that there has been a breach of
contract because they did not get what they bargained for. There is no real dispute from
Mr Carey that this is the case and the hearing proceeded on that basis but the real
contentious issue is the assessment of damages. Even with the negligence claim the
damages are to put the injured party in the position it would have been had the breach of
the duty of care not occurred. If pleadings, were relied on one could envisage a plea of
contributory negligence in that the Fields did not engage an engineer. Similarly, in
respect of the contract claim a defence could be mounted that the Fields would be unjustly
enriched, or better off, if by the means of rectification, they were to get something
substantially more than they bargained for. In other words should there be an offset from
the assessed damages by reason of the betterment.
[43] In Fankhauser v Mission Beach Property Management [2017] QCATA 65 the then
President, Justice Carmody considered the question of betterment. The argument in that
case revolved around the damages assessed for the replacement of carpet in a rental
property, being new for old and whether the respondent obtained a benefit. He found
there was betterment and provided a useful summary of cases where the issue of benefit
was considered as follows:11
[24] In the early 19th century case of Yates v Dunster, for example, the cost of repairing
damaged premises was reduced for the value that was added.
[25] Lord Kenyon applied the standard one third deduction historically used in marine
insurance policies to assess compensation for tortious land damage in Lukin v Godsall but
an award for loss was not decreased in The Gazelle for betterment on the basis that any
enhanced value or collateral benefit “derives incidentally” from the absence of alternative
methods of indemnification.
[26] Widgery LJ refused to decrease damages for a contract breach to reflect betterment in
Harbutt’s “Plasticine” Ltd v Wayne Tank and Pump Co on the ground that “to do so would
be the equivalent of forcing the plaintiffs to invest their money in the modernising of their
(destroyed factory) which might be highly inconvenient for them”. As Lord Denning MR
pointed out in the same case the owners really had no choice but to replace the building as
quickly as possible to mitigate profit losses and therefore acted out of necessity.
[27] A compromise option was approved by the House of Lords in Ruxley Electronics &
Construction Pty Ltd v Forsyth Laddingford Enclosures Ltd where an intermediate figure
between full replacement and the reduced market value of the premises representing the
11 At [24] footnotes omitted
-- 9 of 13 --
10
loss of the enjoyment of a swimming pool constructed to six (6’) feet instead of 7 feet 6
inches (7’6”) but otherwise perfectly safe and serviceable.
[28] In Bellgrove v Eldridge, however, the trial judge awarded a building owner £4,950 for the
cost of demolishing a house constructed on dangerous faulty foundations and replacing it
with the one she paid £3,100 to have built according to plans and specifications. The
builder contended on appeal that the proper measure of damage was the difference between
the value of the house as it stood and what it would have been worth if the contract had
been properly performed.
[29] The High Court disagreed and said:
“... the respondent was entitled to have a building erected upon her land in
accordance with the contract ... her damage is the loss which she has sustained
by the failure of the appellant to perform his obligation to her. ... cannot be
measured by comparing the value of the building which has been erected with
the value it would have borne if erected in accordance with the contract; her
loss can, prima facie, be measured only by ascertaining the amount required
to rectify the defects complained of and so give to her the equivalent of a
building on her land which is substantially in accordance with the contract.”
[30] Farmers replaced an old tractor destroyed by fire with a new one in Hoad v Scone Motors
Pty Ltd because they could not find a comparable second hand vehicle and had to act
quickly to avoid crop losses. They were clearly better off after the purchase than they were
before the fire and were going to sell the old tractor when their non-renewable lease ran
out in a couple of years’ time anyway.
[31] The majority (Moffit P and Hutley JA) held that betterment should be taken account of in
measuring damages.
[32] Samuels JA (dissenting) thought the duty to mitigate and the unavailability of a suitable
replacement of the same age and condition made it reasonable for the farmers to buy the
new one and, therefore, they were entitled to recover the full replacement cost as damages
without any deduction for depreciation even though they were “left with the price of
equipment...substantially more valuable than that which he lost, and will have lost no
profits.”
[33] In Hyder Consulting (Australia) Pty Ltd v Wilh Wilhelmsen Agency Pty Ltd & Anor,
Sheller JA held it was inappropriate to reduce damages for betterment if there was no
evidence that the plaintiff had any reasonable alternative remedy other than to replace
property damaged by the defendant’s negligence.
[34] Meagher JA, by contrast, would have reduced the amount of damages by (an arbitrary) 20
per cent as reasonable allowance for the replacement of a defective pavement about
halfway through its 20-year designated life on the basis that the owner had obtained a
windfall gain.
[44] Hyder Consulting has a somewhat similar factual basis as the circumstances here. The
constructed pavement referred to above had been in use for about 5 years before
proceedings were commenced by the owner of industrial premises, Wilh Wilhelmsen
Agency Pty Ltd. against Hydra Consulting Australia Pty Ltd, the engineers, and James
Thiessen & Associates Pty Ltd, the architect. At first instance the court ordered that the
owner recover the full cost of replacing the pavement but on appeal, per Meagher JA
-- 10 of 13 --
11
reduced the damages by 20% to take into account the betterment, or windfall to the owner
of getting a new pavement. Sheller JA and Giles JA disagreed with this approach on the
basis that if the plaintiff had no choice but to replace the defective pavement with a new
pavement it could not do so by paying less to take into account the use of pavement over
a 5-year period. To adopt an arbitrary percentage discount was not appropriate in that
case. However, it should be noted in Hyder Consulting, the design and specification of
the pavement in question was undertaken by professional engineers and architects with
full design plans drawn up for the work. That did not happen in this case, but rectification
will include that work.
[45] Other cases referred to by the President in Frankhauser where betterment was allowed
such as Hoad, did take into account the use of the particular product and a new
replacement would be a windfall.
[46] I remain of the view, that what the Fields will get by the expenditure of the full
rectification costs allowed in the Dixon/Maloney report will be something more superior
than what they intended to get under the contract with Mr Carey being a fully engineered
designed slab, keyed into the existing coping. How the difference in the ultimate product
is measured is difficult. To adopt an arbitrary percentage allowance would be inconsistent
with what the Court of Appeal said in Hyder Consulting.
[47] With respect to the actual cost of rectification, fortunately Mr Dixon and Mr Maloney
generally agreed on most rectification costs, except for temporary fencing. There was
some argument about the type of temporary fencing that should be used during the work.
Mr Moloney argued that normal security fencing could be used but because this work
involved a swimming pool, Mr Dixon said compliant temporary pool fencing should be
used. Once work starts the site will effectively be a construction site, with demolition
works, machines on site and then concreting with tiling. As a construction site, there will
be workers on site and also the Fields will be living there. Therefore, normal construction
security fencing would be sufficient to carry out the necessary work. I therefor prefer Mr
Moloney’s costings on this point. I find that the cost of rectification is in the sum of
$57,322.41.
[48] Included in the rectification costs are the costs to remove the existing slab and make good
the surrounds for the new work. The total cost of that is $30,230.74.00 including GST
and builder’s margin as particularised in the joint expert report of Dixon and Moloney:
Item No Work Amount
4 Private certifier fee to submit application for demo and reconstruct
plus site inspection/ form 17 certificates for installation of salvage
glass pool barrier [layout 50% cost of new]
$1,092.73
5 Service call to decommission pool pump equipment disconnect
power supply cool to make safe for demolition works
$180.00
6 Labour to dismantle existing glass pool barrier and spigots set aside
for later re-instalment
$564.64
8 Hire of 22.6 metres of temporary pool fencing $814.00
10 Installation of compliant temporary pool fencing with gate to full
perimeter to comply with QDC MP3.4
$310.30
-- 11 of 13 --
12
11 Temporary pool blanket for debris $65.33
12 Carefully remove tiles over the original 700 mm wide perimeter
concrete apron two depth of cement bed only includes coping tiles
$1,454.00
13 Break up tiles, including cut concrete on concourse up to original
edge of pool concrete apron
$3,237.17
14 Carefully break up and remove concrete concourse up to original
edge of concrete apron
$4,433.25
15 Labour to cut original steel doused flush with face edge $125.96
16 Labour to apply engineer specified brushable bituminous product
to raw steel cut end of original dowels
$82.95
17 Supply tiles for 66 m2 of tiles (including 6m2 wastage) x $120/m $7,920.00
Sub Total $22,826.33
Add builder’s margin 20% $4565.26
Sub Total 27391.59
Add GST $2,739.15
Sub Total $27,584.74
[49] Because the Fields supplied the tiles and there was no direct evidence as to the cost of
the tiles/pavers I have allowed $120/m2 on the following basis. Mr Carey’s quote for the
slab was $5,900.00 for 60m2 of concrete. The joint report, at Item 28, allowed $12,184.00
to supply and lay “tiles – floor – ceramic/porcelain – prestige”. Allowing for price
increases, in the intervening period, and general knowledge the price adopted for the tiles
seems reasonable.12
[50] Mr Carey is liable for this part of the rectification cost as it flows directly from the
defective work.
[51] The balance of the work will cost about $31,623.00 when adjusted for the fencing. The
original contract price for the concrete work was $10,770.00
Remove fence, subgrade around pool; box and steel around pool; lay and
broom finish approx. 60m2 concrete:
$5,900.00
Clean and prep surrounds, cut and lay new surrounding pavers grout new paver
stone adding expansion joints:
$4,870.00
Total $10,770.00
[52] It is evident on this differential, even allowing for inflation and the time difference that
the Fields are getting a better product in the end. Also, they have had the advantage of
use of the concourse now for over 8 years. The other point to make is that the whole of
the concourse has not failed even though it all has to be demolished for rectification to
12 QCAT Act s 28(3).
-- 12 of 13 --
13
be carried out. When combining all of these factors together and having regard to the
costs differential for the new actual slab works an allowance of one third or $10,540.00
would be an appropriate adjustment for betterment. That then reduces the costs of
rectification to $21,083.00.
[53] That sum in addition to the re-instatement costs of $27,584.74 results in damages of
$48,667.74. In the end Mr Carey must pay to the Fields the sum of $48,667.74.
[54] There is an application for costs by the Fields, legal representatives. I have been asked to
make directions for the filing of submissions on costs. This will result in the parties
incurring further legal costs which, ideally, should be avoided if possible.
[55] Under s 77(3)(h) of the Queensland Building and Construction Commission Act 1991
(Qld), the Tribunal can award costs, and the restrictions on allowing costs under s 100 of
the QCAT Act do not apply. Clearly the Fields have been successful in the application,
and without actually deciding the point there are strong arguments as to why they should
get their costs. If costs were to be awarded, and there being no mechanism of assessing
costs under the QCAT Act as such, I am guided by Rule 86 (of the QCAT Rules) which
provides for “reasonable costs” with respect to offers of settlement. Given the amount of
damages, reasonable costs would be assessed under the Magistrates Court scale of costs
where the amount recovered is less than $50,000.
[56] I make these observations in the hope that the parties can come to some agreement about
costs. If not, on the application (Form 40) of either party I will make directions as to the
filing of submissions on costs.
[57] There will be orders accordingly.
-- 13 of 13 --