Agius v Queensland Building and Construction Commission & Anor [2023] QCATA 148
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Agius v Queensland Building and Construction
Commission & Anor [2023] QCATA 148
PARTIES: MARK ELLIOTT AGIUS
(applicant/appellant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
GEDOUN CONSTRUCTIONS PTY LTD
(second respondent)
APPLICATION NO/S: APL244-21
ORIGINATING
APPLICATION NO/S:
GAR140-21
MATTER TYPE: Appeals
DELIVERED ON: 2 November 2023
HEARING DATE: 11 May 2023
HEARD AT: Brisbane
DECISION OF: Acting Senior Member Fitzpatrick
ORDERS: 1. Leave to appeal is granted.
2. The decision of the Tribunal of 4 August 2021 is
set aside, and the following order is made in
substitution.
3. The preliminary issue is not suitable for
determination so that the preliminary issue
proceeding is dismissed.
CATCHWORDS: APPEAL AND NEW TRIAL – RIGHT OF APPEAL –
WHEN APPEAL LIES – FROM INTERLOCUTORY
DECISIONS – LEAVE TO APPEAL – Where a
preliminary issue as to whether work was “building
work” in whole or in part was determined - Whether there
is a reasonably arguable case of error on the part of the
Tribunal below - Whether the determination of the
preliminary issue in the Tribunal below should stand
Queensland Building and Construction Commission Act
1991 (Qld) s 72, sch 2
Queensland Building and Construction Commission
Regulation 2018 (Qld) s 5(2), sch 1
-- 1 of 10 --
2
Queensland Civil and Administrative Tribunal Act 2009
(Qld) ss 142(3), 146, 147
Byrne v People Resourcing (Qld) Pty Ltd & Ors [2014]
QSC 039
Gedoun Constructions Pty Ltd v Agius [2022] QCAT
446
Glen Williams Pty Ltd v Queensland Building Service
Authority [2012] QAT 127
Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986]
2 Qd R 388
McIver Bulk Liquid Haulage Pty LTd v Fruehauf
Australia Pty Ltd [1989] 2 Qd R 577
Pickering v McArthur [20005] QCA 294
Reading Australia Pty Ltd v Australian Mutual
Provident Society (1999) 217 ALR 495
Rintoul v State of Queensland & Ors [2018] QCA 20
APPEARANCES &
REPRESENTATION:
Applicant: A Tindall, instructed by Australian Law Partners.
First Respondent: SE Seefeld, instructed by Norton Rose Fullbright.
REASONS FOR DECISION
[1] This matter is one of a number of matters involving the parties, arising out of the
construction of a house for the applicant Mr Agius, by the builder Gedoun
Constructions Pty Ltd. In tandem with these proceedings Mr Agius has sought a
remedy against the builder for breach of statutory warranties, which has been
determined by the Tribunal in his favour.1 That decision was made after the decision
below, the subject of this application for leave to appeal or appeal. The building
dispute decision is the subject of an appeal, which to date has not yet been determined.
Although of some relevance to this appeal, I have not taken into account the findings
in the proceeding against the builder, because the task for me is not to determine the
correct and preferable decision in the review application. The issue for me is whether
the determination of a preliminary point in the Tribunal below should stand.
[2] Mr Agius applied to review a decision of the Queensland Building and Construction
Commission (QBCC) made on 30 March 2020.
[3] Relevant to this appeal is the decision not to issue a direction to rectify or remedy for
Complaint item 1 made 24 December 2019. Complaint 1 is that – “Builder incorrectly
designed and built house to wrong Wind Classification, downgrading from C3 to C2,
then attempted to downgrade further to C1 via an erroneous Form 15 in an attempt to
avoid attending to defective works.”
[4] A second Complaint in relation to an energy efficient certificate is not part of this
appeal proceeding.
1 Gedoun Constructions Pty Ltd v Agius [2022] QCAT 446.
-- 2 of 10 --
3
The QBCC decision dated 30 March 2020
[5] The QBCC in its reasons for decision said that it must first be determined whether
there is “building work” and only then consider if it is “defective” and if so whether
it is fair to issue a direction to rectify.
[6] The QBCC said that building work is defined in Schedule 2 of the Queensland
Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’) to include the
erection or construction of a building. However, the definition of building work is
limited by specific work listed under Schedule 1 of the QBCC Regulation, including
work performed by engineers and architects.
[7] Despite setting out the order of its required decision making, the QBCC went first to
the question of whether building work was defective. It concluded that because the
builder performed works in line with the council decision notice and approved plans
with a Wind Classification of C2, the building work undertaken by the builder, being
the erection and construction of the dwelling is not defective.
[8] The QBCC then noted that the structural drawings were by Northern Consulting
Engineers (NCE) job no: GED890 as was the Wind Classification Report and Form
15.
[9] The QBCC referred to Mr Agius’ argument that design and specification work, being
in relation to the construction of a residential house, falls within the definition of
building work as defined under Schedule 2 of the QBCC Act. The QBCC then referred
to the whole definition which says that building work does not include work of a kind
excluded by regulation from the ambit of this definition. The QBCC noted that work
performed by engineers, including design and specification work, is a specific
exclusion under the QBCC Regulation and therefore cannot be included within the
definition of building work.
[10] As a result, it was concluded that the QBCC could not give a direction to rectify to
the builder because the wind classification is not “building work”.
[11] Mr Agius sought external review of that decision in this Tribunal.
Preliminary issue and its determination
[12] The determination of a preliminary issue was flagged in a Direction made 7 October
2020 following a compulsory conference between the parties.
[13] An application for miscellaneous matters filed by the QBCC on 21 October 2021,
sought orders striking out what it termed Complaints 1A and 2. An application for
miscellaneous matters filed by Mr Agius on 22 October 2021 sought Directions for
the future conduct of the matter. Those applications were addressed in a Directions
Hearing on 8 February 2021 when it was directed that it be determined as a
preliminary issue:
whether the work was “building work” in whole or in part.
[14] Member Cranwell determined the preliminary issue on the papers. The Member said
that for convenience he adopted the QBCC categorisation of Mr Agius’ first
Complaint into two parts:
(a) the design of the wind classification for the property (Complaint 1A); and
-- 3 of 10 --
4
(b) the construction of the property, based on the wind classification (Complaint
1B).
[15] The Member noted it was not in dispute that Complaint 1B was building work.
[16] The Member proceeded from a factual premise that Complaint 1A relates to structural
engineering plans prepared by NEC on 4 December 2017 and a Form 15 Compliance
certificate for building design or specification dated 15 December 2017, which
specifies a wind classification of C2. The Member reasoned that, accordingly
Complaint 1A relates to work performed by an engineer, which is excluded from the
definition of “building work” by item 5 of Schedule 1 of the QBCC Regulation.
[17] The Member noted that it is the engineer, and not the building designer, who is
responsible for determining the wind classification. The Member said that while the
plans prepared by the building designer refer to the wind classification of the property
as determined by the engineer, s 5(2) of the QBCC Regulation makes it clear that this
does not prevent the application of Schedule 1.
[18] The Order made is that: Complaint 1A and Complaint 2, as defined in these reasons,
do not relate to ‘building work’ as defined in Schedule 2 of the QBCC Act. If I insert
the adopted definition of Complaint 1A, the Order is that: the design of the wind
classification for the property (Complaint 1A) does not relate to ‘building work’ as
defined in Schedule 2 of the QBCC Act.
Leave to appeal or appeal
[19] As this is an application for leave to appeal or appeal an interlocutory decision, the
leave of the Appeal Tribunal is required before the appeal may proceed. Leave of the
Appeal Tribunal is also required to the extent that the appeal is on a question of fact
or mixed law and fact.2
[20] Leave will usually be granted only where an appeal is necessary to correct a
substantial injustice to the applicant, and there is a reasonable argument that there is
an error to be corrected.3 In deciding whether to grant leave to appeal, an assessment
of the prospects of the proposed appeal is undertaken.4
[21] The other consideration which may be relevant to the grant of leave is if there is a
question of general importance upon which further argument, and a decision of the
appeal tribunal would be to the public advantage.5
[22] If leave to appeal is granted the appeal is dealt with under s 146 of the QCAT Act in
the case of an appeal on a question of law, and under s 147 in the case of appeal on a
question of fact or mixed law and fact.
[23] In this case interpretation of the QBCC Act raises a question of importance to the
public generally, that is to what extent does work excluded from the definition of
building work infect the whole of the building process to take all of what would
otherwise be building work outside the definition and therefore the remedial reach of
the QBCC. The issue for Mr Agius is whether it is correct that work carried out by
2 Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 142(3).
3 Pickering v McArthur [20005] QCA 294, [3].
4 Rintoul v State of Queensland & Ors [2018] QCA 20, [10].
5 Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388, 389; McIver Bulk Liquid Haulage
Pty LTd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577, 578, 580.
-- 4 of 10 --
5
builders (and building designers) in designing or constructing a building which
allegedly fails to comply with regulatory requirements as to wind loadings, cannot be
“building work” for the purposes of the QBCC Act, merely because there was an
engineer involved in the project who specified and certified structural elements based
on an incorrect wind classification.
[24] That issue has broad significance but also fundamentally affects any remedies
available to Mr Agius under the QBCC Act for rectification of allegedly defective
work. That raises a matter of substantial injustice.
[25] The question of whether there is a reasonably arguable case of error on the part of the
Member will be addressed by a consideration of the grounds of appeal.
Observations
[26] As I understand the submissions made on behalf of Mr Agius, his overarching concern
with the decision under review and determination of the preliminary issue is that to
date the QBCC has contended the builder has no responsibility in relation to
construction of the house because he is simply complying with the design based on
the engineer’s determination of the wind classification. Mr Agius says that such a
contention ignores the builder’s responsibilities to comply with the Building Code and
relevant Australian Standards.
[27] It is plain the basis of the QBCC’s decision is that because the builder complied with
the engineer’s wind classification of C2, his work could not be defective and because
the wind classification is engineer’s work, the Complaint did not relate to building
work with the result that no direction to rectify would issue.
[28] It became apparent in the course of the QBCC’s submissions that its position has
changed from that set out in its decision and from its written submissions. First, the
QBCC acknowledged that the question of whether a direction to rectify should be
issued in circumstances where a builder has relied on a design is a matter for the
tribunal in the actual review proceedings. The QBCC notes that the purpose of the
separate question was to define what is within the scope of the review and what is not.
Next it was acknowledged that the work of the building designer is building work and
the physical construction of the house by the builder is building work.
[29] Following a question from me, Counsel for the QBCC made a submission as to the
effect of the decision made by the Member and its effect on the ultimate remedies
available to Mr Agius. Counsel said that the effect is quite narrow. That is, there is no
jurisdiction for the tribunal standing in the shoes of the QBBC to require the engineer
to take any step. However, it would be open to the tribunal to require the builder to
rectify work which, for example, did not meet Australian standards. It would be open
to the builder to argue that he relied on the engineer, and in those circumstances it
would not be fair to issue a direction to rectify. Counsel observed that the Glen
Williams6 case may be relevant. However, Counsel said that those matters are not
something the appeal tribunal needs to decide.
[30] Again, in response to a question from me, Counsel for the QBCC agreed that in the
substantive review it is possible that Mr Agius could achieve an order that the builder,
for example correct the cladding or the width of the house or the other things which
are said to flow from a wrong wind classification and which do not comply with
6 Glen Williams Pty Ltd v Queensland Building Service Authority [2012] QAT 127.
-- 5 of 10 --
6
Australian standards. Counsel said that one could tick off that itis building work, ask
is it defective and then get to the third question for a tribunal which is, is it fair to
direct rectification. When I put to Counsel that was not how the QBBC approached
the issues in its original decision he agreed and said that the original decision is still
in review.
[31] Finally, Counsel for the QBCC made the point that this appeal may have little utility,
because regardless of whether there was error on the part of the Member, the work of
the engineer will not be building work, but the work of the builder in building the
house is building work and will be considered by the tribunal.
[32] I also observe that the meaning of the words in the preliminary question is vague.
There is no attempt to describe what “work” is being considered by reference to the
wording of the Complaint made by Mr Agius.
[33] In his reply submissions Mr Agius makes the point that there is no attempt by the
QBCC or the Member to consider the work by reference to the work done by the
engineer, the work done by the building designer and the work done by the builder.
The Member only considered if the work of the engineer was building work. Counsel
for Mr Agius submitted that the question asked of the Member goes to the work of the
building designer. The question asks if the “design of the wind classification for the
property” is building work. Counsel for Mr Agius says that for the first time, on the
hearing of the appeal, it was said that it is not disputed that the building designer’s
work is building work. Counsel for Mr Agius says that the Member was not asked if
determination of the wind classification for the property is building work. That is, if
the engineer’s work is building work. If that was the issue, then it would be conceded
that it is not building work. In any event, Mr Agius points to the actual order made
which is that the design of the wind classification for the property is not building work.
[34] The QBCC maintain that the question asked of the tribunal was about the engineering
plans. It was conceded that the question was not framed as well as it could be, but the
question was not whether the work of the building designer was building work.
[35] Given clarification of the QBCC’s position which emerged at the hearing, and which
appeared to meet some of Mr Agius’ concerns as to the meaning and effect of the
order made by the Tribunal, the parties agreed to take some time to discuss the matter
further and if possible to reach agreement as to the disposition of the appeal. The
parties were unable to reach any agreement.
[36] In my view confusion has been caused by very loose language around what ‘work’ is
being analysed as to whether it is ‘building’ work’ and what the words ‘design of” the
wind capacity means. I note that it has variously been described as
“designing/calculating the wind classification for the property”7, “determination of
the wind capacity of the building”8 and “the design to the wind classification upon
which the construction proceeded”.9
[37] Mr Agius’ reply submissions isolate the fundamental problem with the unclear
language used to formulate the question for determination by the Tribunal and the
reframing of the Complaint by the QBCC. The Complaint is reframed by the QBCC
7 First Respondent’s submissions in response to application for leave to appeal, filed 10 November 2022,
paragraph 4.2.
8 Ibid 1.5.
9 Ibid 4.12.
-- 6 of 10 --
7
to relate to “the design of the wind classification for the property”, rather than being
a Complaint about the design of the property to the wind classification. Mr Agius
makes the point that wind classifications are not “designed”, rather certain Australian
Standards prescribe set criteria for determining the wind classification or wind loading
that are applicable to a particular building.
Grounds of appeal
[38] I intend to deal with the third ground of appeal first as I consider it is established.
[39] The ground is that the Member erred in law in failing to dismiss the application for
determination of a preliminary issue on the basis that the separate question posed by
the QBCC was not based on facts, found or agreed, but on the QBCC’s interpretation
of the nature of work the subject of Complaint item 1 which was disputed by Mr
Agius.
[40] Mr Agius says that he expressly disputed the QBCC’s assertion that the item of work
the subject of his claims related to “the design of the wind classification for the
property (Complaint 1A) and Complaint 1A pertains to the Engineering Plans.”
[41] I accept that Mr Agius position was clearly put to the Member on the material before
him.10
QBCC’s submissions
[42] The QBCC’s written submissions are that Mr Agius asserts the engineer’s plans are
not relevant to the wind classification. I consider that misstates Mr Agius’ submission.
The QBCC construes the ground of appeal as mere disagreement with the decision of
the Member, which it says is not a ground of appeal.
Consideration
[43] The principles that govern the circumstances in which an order will be made for the
separate trial of preliminary issues are settled. Determination of a preliminary
question must involve “a conclusive or final decision based on concrete and
established or agreed facts for the purpose of quelling a controversy between the
parties”.11 The point of determining a preliminary issue is to dispose of an issue
between the parties so that remaining issues are also resolved or at least limited. The
history of the matter is that the QBCC has sought to dispose of the whole of Mr Agius’
Complaint relevant to the review by determination of a preliminary issue. That would
not appear to be the QBCC’s current position.
[44] Applegarth J provided a useful summary of the established principles in Byrne v
People Resourcing (Qld) Pty Ltd & Ors:12
a declaration or other order which is “not based on facts, found or agreed, will
be purely hypothetical and at best…do no more than declare that the law dictates
a particular result when certain facts in the material pleadings are established.”
If the assumed facts are in dispute, then the answers may be of no use at all to
10 Applicant’s response to Respondent’s submissions dated 28 October 2020, Vol 4 Appeal Book
commencing page 1728.
11 Reading Australia Pty Ltd v Australian Mutual Provident Society (1999) 217 ALR 495, [8] following
Bass v Perpetual Trustee Co Ltd (1999) 198 CLR 334.
12 [2014] QSC 039, [5] following King’s College v Allianz Insurance [2004] 1 Qd R 394, 398-401 and
BOQ Ltd v Chartis Australia Insurance Ltd [2012] QSC 319, [31]-[40].
-- 7 of 10 --
8
the parties. It may be no part of judicial power to effect a determination of
rights by applying the law to facts which are neither agreed nor determined by
reference to the evidence in the case. It has been said that “judicial decisions
based on assumed facts are suitable only for questions of law and then only if
the facts as pleaded exhaust the universe of relevant factual material”.
(footnotes omitted)
[45] In this matter it is no longer a question of whether a preliminary determination should
proceed, but rather, once a preliminary determination has been directed to occur on
what terms should it have proceeded. The established principles should have been
observed because they certainly flag the pitfalls if they are not. In my view the parties
have ended up with a determination which is of no utility because it does not address
the real issues in dispute.
[46] The Member did not address Mr Agius’ concerns in relation to re-framing of his
Complaint by the QBCC, he did not address the meaning of the words “design of the
wind classification” or refer to all the evidence as to what type of work associated
with construction of the house might be caught by the phrase. The Member erred in
law by proceeding to determine the preliminary issue without first establishing that
the facts were concrete and established or agreed.
[47] The result is the Member found that engineering work is not building work within the
terms of the QBCC Act, which is uncontroversial between the parties and in the end
of no utility in quelling the actual dispute between the parties. However, the additional
problem arises that the order made does not on its face refer to engineering work and
is not plain as to its meaning. The order has been construed by Mr Agius as having
the effect of determining the review application without reference to the evidence or
the real issues in dispute. I find that Mr Agius construction is fairly available, given
the various descriptions by the QBCC of what is meant by “design of” the wind
classification. A determination of the review application without the need for a full
hearing was in fact the outcome originally sought by the QBCC.
[48] I conclude that there has been an error of law by the Member in proceeding to
determine a preliminary issue by reference to facts not agreed by both parties and
making an order which on Mr Agius’ construction disposes of his review application
without reference to the facts raised by Mr Agius as to the responsibilities of the
builder and building designer to comply with the Australian Standards and Building
Code with respect to wind classification.
[49] The other grounds of appeal feed into the final ground of appeal which I have
considered.
[50] The first ground of appeal asserts an error of fact and law in misconstruing the nature
of the work the subject of the Complaint relevant to the application to review the
QBCC’s decision. I accept the submission that by reframing the terms of Mr Agius’
Complaint the QBCC erroneously categorised and identified the work, leading the
Member into error, whereby the Member identified the relevant work as being the
structural engineering plans prepared by Northern Consulting and work performed by
an engineer, when Mr Agius says that was not the work the subject of his Complaint.
Mr Agius says that his Complaint relates to the design of the building by the builder
generally and through its building designer, which concerns an entirely different
aspect of works to the engineering plans prepared and certified by the engineer. I
accept that was Mr Agius’ Complaint and that was apparent on the material before the
-- 8 of 10 --
9
Member.13Mr Agius’ submissions were not dealt with by the Member as he moved to
the QBCC’s categorisation of the Complaint “for convenience”. I conclude that the
Member made an error of fact as to the nature of Mr Agius’ Complaint.
[51] It is asserted that the Member erred in law in failing to construe the work the subject
of the actual Complaint as building work for the purposes of s 72 of the QBCC Act.
That is, the Member failed to construe as building work the builder’s work in
designing the home and preparing design drawings which failed to comply with
Australian standards, when that work was not work performed by an engineer. The
Member did not undertake that interpretation task because of his mistaken finding as
to the nature of Mr Agius’ Complaint. I cannot take the further step and find that an
error of law occurred in a process of construing the facts by reference to legislation
when that process did not occur.
[52] Except for the way in which the order of the Member is cast, I agree with the position
put by the QBCC at the hearing that in the end the decision of the Member has a very
narrow compass as in substance it relates only to work performed by the engineer.
Insofar as the work of the building designer and builder are concerned, the QBCC
acknowledged that their work is building work and that subject to a question of
fairness they may be subject to a direction to rectify once the review is finally
determined. The QBCC acknowledged that its decision remains open to ultimate
review by the Tribunal.
[53] The second ground of appeal canvasses a matter addressed in the other two grounds
of appeal that by adopting the QBCCs categorisation of the nature of the work the
subject of Complaint item 1, the Member failed to take into account that the work was
design and construction of the house. I have accepted that an error of fact occurred
and that the Member did not refer to Mr Agius’ material as to the true nature of his
Complaint and did not demonstrate the basis for his conclusion as to the nature of the
work the subject of the Complaint.
[54] I do not consider that there has been an error of law associated with the Member’s
conclusion as to the nature of the work the subject of the Complaint. I think Mr Agius
makes a strained argument when he submits that the Member’s decision was affected
by jurisdictional error by the adoption of an illogical and irrational reasoning process
and a failure to disclose the evidence on which he relied.
Conclusion
[55] On the basis that an error of law is made out with respect to appeal ground 3 and an
error of fact is made out with respect to appeal grounds 2 and 3, leave to appeal is
granted.
[56] In relation to an error of law s 146 of the QCAT Act sets out the Appeal Tribunal’s
powers. Mr Agius submitted that in the event it is concluded there has been an error
of law as submitted with respect to ground of appeal 3, the appropriate order is that
the application for determination of a preliminary issue should be dismissed and the
order made on 4 August 2021 set aside. The QBCC did not expressly address the relief
sought by Mr Agius in the event an error of law is found.
13 Applicants Response to Respondent’s submissions dated 28 October 2020, vol 4 Appeal Book, page
1728.
-- 9 of 10 --
10
[57] In relation to errors of fact Mr Agius submits that by way of a rehearing under s 147
of the QCAT Act the Appeal Tribunal may find that the work the subject of Mr Agius’
Complaint is building work as defined by the QBCC Act and may make an order to
that effect, in substitution for the Order made below.
[58] The QBCC submits that is not an order which I should make as the order goes beyond
what the Member was asked to consider by the QBCC. I have noted the
acknowledgements made by the QBCC in these proceedings that the work of the
building designer and the builder was building work as defined. I do not intend to
make findings or orders in this regard because I agree that would determine a matter
not decided by the Member. I think that matter is more properly a consideration in the
review proceeding. It is also possible that the findings of the Tribunal and the Appeal
Tribunal in the litigation between Mr Agius and the builder may be relevant in the
ultimate review.
[59] I consider the appropriate relief in this matter is that the decision of the Tribunal on 4
August 2021 is set aside and in lieu thereof an order made that the preliminary issue
is not suitable for determination so that the preliminary issue proceeding is dismissed.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2023/148