Abbott Builders (Qld) Pty Ltd v Forrest & Anor [2023] QCATA 141
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Abbott Builders (Qld) Pty Ltd v Forrest & Anor [2023]
QCATA 141
PARTIES: ABBOTT BUILDERS (QLD) PTY LTD
(appellant)
v
PHILLIP FORREST
(first respondent)
JAN FORREST
(second respondent)
APPLICATION NO/S: APL166-22
ORIGINATING
APPLICATION NO/S:
BDL280-19
MATTER TYPE: Building matters
DELIVERED ON: 1 November 2023
HEARING DATE: 14 August 2023
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
ORDERS: The application by the applicant to rely upon
further evidence is refused.
The application by the respondents to rely upon
further evidence is dismissed.
Leave to appeal is granted.
The appeal is allowed.
Order 1 of the decision of the Tribunal dated 4 May
2022 is varied by substituting ‘$42,425.50’ with
‘$38,496.59’.
The parties are to file and exchange submissions on
the costs of the appeal, not exceeding five (5) pages
in length within 14 days of the date of this decision.
The costs of the appeal will be determined on the
papers.
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – RIGHT OF APPEAL – NATURE OF
RIGHT – APPEALS IN THE STRICT SENSE AND
APPEALS BY WAY OF REHEARING – APPEALS BY
WAY OF REHEARING – WHEN REHEARING DOES
-- 1 of 19 --
2
NOT INVOLVE HEARING DE NOVO – where leave to
appeal should be granted on the basis that there was error in
the primary decision and is required to correct a substantial
injustice – where the appeal tribunal gives consideration to
the findings of fact of the primary tribunal – whether the
rehearing is limited to a consideration of those matters raised
in the grounds of appeal
APPEAL AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – POINTS AND OBJECTIONS NOT
TAKEN BELOW – WHEN ALLOWED TO BE RAISED
ON APPEAL – OTHER MATTERS – OTHER CASES –
where the appellant says the tribunal does not have
jurisdiction to decide a building dispute on the basis that s
77(2) of the QBCC Act has not been complied with – where
the matter was not raised in the proceeding below and
neither party led evidence on the issue – whether the
appellant may adduce fresh evidence – whether the tribunal
had jurisdiction to decide the dispute
CONTRACTS – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS –
INTERPRETATION OF MISCELLANEOUS
CONTRACTS AND OTHER MATTERS – whether the
tribunal erred in finding that a retaining wall was not
constructed in accordance with the terms of the contract –
whether the tribunal erred in finding that the contract
required a solid stud wall in an ensuite – whether the
tribunal erred in finding that the conduct of the appellant
deprived the respondents of the ability to claim off–set for
late completion damages under the contract – whether upon
a proper construction of the contract payment of the final
claim by the owners deprived them of the right to claim
liquidated damages
DAMAGES – ASSESSMENT OF DAMAGES IN
ACTIONS FOR BREACH OF CONTRACT –
PARTICULAR HEADS OF LOSS – FUTURE LOSS –
where the appellant says that the method of calculation is
erroneous and results in a windfall – whether the tribunal
erred in assessing the future costs of termite protection –
whether a discount rate should be applied
Civil Proceedings Act 2011 (Qld), s 3
Queensland Building and Construction Commission Act
1991 (Qld), s 77(2)
Codelfa Construction Pty Ltd v State Rail Authority of
NSW [1982] HCA 24
Drayton v Martin (1996) 67 FCR 1
Helu v Yuan [2023] QCATA 12
Hoad v Scone Motors Pty Ltd [1977] 1 NSWLR 88
-- 2 of 19 --
3
Michellis, M. & D. v Carlos Steenland Pty Ltd and Meier
Corporation Pty Ltd [2006] QCCTB 197
Ryan v Worthington [2015] QCA 201
APPEARANCES &
REPRESENTATION:
Appellant: Mr M Robinson, Solicitor, Robinson Locke Litigation
Lawyers
Respondent: Self-represented
REASONS FOR DECISION
[1] This appeal is about a building dispute.
[2] Abbott Builders (Qld) Pty Ltd built a home for Phillip Forrest and Jan Forrest. The
Forrests claimed that the building work did not conform with the terms of the contract
and/or was defective. They claimed that Abbott had failed to deliver up relevant
building certificates. The Forrests also claimed liquidated damages for late completion
of the works.
[3] The Tribunal ordered Abbott to pay the Forrests $42,425.50 plus costs fixed in the
amount of $6,535.80.1 Abbott appeals the decision.
The grounds of appeal
[4] Abbott relies upon the following grounds of appeal:
(a) Ground 1 – liquidated damages claim:
(i) The Tribunal erred in failing to apply clause 25.7 of the contract;
(ii) The Tribunal erred in finding that Abbott acted dishonestly in seeking
payment of the final stage claim before handing possession to the Forrests;
(iii) The Tribunal erred in finding that the conduct of Abbott deprived the
Forrests of the ability to claim off-set for late completion;
(b) Ground 2 – retaining wall:
(i) The Tribunal erred in accepting the evidence of the Forrests regarding the
structural purpose of the retaining wall;
(ii) The Tribunal erred in mistaking the true facts in that the retaining wall
was structural;
(iii) The Tribunal erred in finding that the retaining wall was not constructed
in accordance with the terms of the contract;
(iv) The Tribunal erred in rejecting the evidence of Mr Paterson, a qualified
builder;
(v) The Tribunal erred in drawing the inference that the retaining wall could
have been constructed as asserted by the Forrests;
1 Forrest & Anor v Abbott Builders (Qld) Pty Ltd [No. 2] [2022] QCAT 164.
-- 3 of 19 --
4
(vi) The Tribunal erred in reducing Abbott’s entitlement to recover for the
construction of the retaining wall;
(c) Ground 3 – ensuite shower wall:
(i) The Tribunal erred in finding that the contract required a solid stud wall;
(d) Ground 4 – termite protection:
(i) The Tribunal erred in assessing the future costs of termite protection;
(e) Ground 5 – no jurisdiction:
(i) The Tribunal did not have jurisdiction to decide the dispute on the basis
that the requirements of s 77(2) of the Queensland Building and
Construction Commission Act 1991 (Qld) (‘QBCC Act’) had not been
complied with by the Forrests before the proceeding below was
commenced.
[5] Both parties have applied for leave to rely upon further evidence. The Forrests say
that if Abbott’s application is refused, they are content for their application to be
dismissed.
Applications to rely upon further evidence
[6] Abbott seeks to rely upon further evidence comprising: (a) statement of evidence by
Mr Wayne Abbott, a director of the applicant going to the issue of compliance by the
Forrests with s 77(2) of the QBCC Act before commencing the proceeding below and
(b) evidence by an engineer regarding the issue of the retaining wall.
[7] The relevant principles for the admission of new evidence in an appeal are well
established:2
(a) The evidence could not have been obtained with reasonable diligence for use at
the original hearing;
(b) The new evidence would probably have an important influence on the result of
the case; and
(c) The new evidence is credible.
[8] All three requirements must be met.
[9] I will address the further evidence later in these reasons.
Appeals – the statutory framework
[10] A party may appeal a decision of the tribunal.3 An appeal on a question of law is as
of right.4 An appeal on a question of fact or mixed law and fact may only be made
with the leave of the appeal tribunal.5
[11] In deciding an appeal on a question of law, the appeal tribunal may confirm or amend
the decision, set aside the decision below and substitute its own decision or set aside
2 Pickering & Anor v McArthur [2010] QCA 341.
3 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 142(1) (‘QCAT Act’).
4 Ibid, s 146.
5 Ibid, s 143(3)(b).
-- 4 of 19 --
5
the decision and remit the matter to the tribunal for reconsideration.6 The Tribunal
may only substitute its own decision if the determination of the question of law
resolves the appeal entirely in the appellant’s favour.7
[12] An appeal on a question of fact or mixed law and fact the appeal must be decided by
way of rehearing, with or without the hearing of additional evidence as decided by the
appeal tribunal.8 In deciding the appeal, the appeal tribunal may confirm or amend
the decision, set aside the decision below and substitute its own decision or set aside
the decision and remit the matter to the tribunal for reconsideration.9
[13] The relevant principles applicable to an application for leave to appeal are well
established: is there is a reasonably arguable case of error in the primary decision?;10
is there a reasonable prospect that the appellant will obtain substantive relief?;11 is
leave needed to correct a substantial injustice caused by some error?;12 is there a
question of general importance upon which further argument, and a decision of the
Appeal Tribunal, would be to the public advantage?13
Consideration
[14] For reasons that will become apparent, I will first address ground of appeal 3.
Ground of appeal 3
[15] The learned member found that the contract required Abbott to construct a solid (stud)
wall for the ensuite shower.14 Abbott says that the finding is contrary to other findings
made by the learned member and was not supported by the evidence.
[16] It was Abbott’s contention below that the plans indicated that the third wall in the
ensuite was not a solid stud wall. The evidence of Mr Paterson, Abbott’s construction
manager, was that it was industry practice for solid walls on a plan to be depicted by
a double line. The Forrests’ quantity surveyor, Mr Burgess, gave similar evidence.
The learned member accepted that the plan showed the third wall in the ensuite as
only a single, and not a double, line and found that the single line drawing shown on
the plan would not mean a solid stud wall.15 However, the learned member found that
the specification required the construction of a solid stud wall and that the
specification took precedence over the plans.16
[17] It is not contentious in this appeal that, in construing the contract, the specification
took precedence over the plans. Abbott says however that the specification must be
relevant. It is therefore necessary to examine more closely the specification.
[18] Item 21.7 of the specification relates to ‘shower recess wall’. The specification
provided for ‘stud wall, rectified tiles as per Beaumont tile spec.’ The Beaumont Tiles
6 QCAT Act, s 146.
7 Ericson v QBCC [2014] QCA 297, [10] (Homes JA).
8 QCAT Act, s 147(2).
9 Ibid, s 147(3).
10 QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41 (‘QUYD’).
11 Cachia v Grech [2009] NSWCA 232.
12 QUYD (n 10).
13 Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388; McIver Bulk Liquid Haulage Pty
Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577.
14 Reasons [176].
15 Reasons [170].
16 Reasons [172].
-- 5 of 19 --
6
specification which pre-dates the contract was, by virtue of its being referred to in the
principal specification, incorporated into the principal specification.
[19] Abbott says that the Beaumont Tiles specification was confined to tile selection and
was not relevant to structural issues relating to the build.
[20] The learned member correctly identified that in construing the contract the
specifications took precedence over the plans. The learned member correctly
identified that the Beaumont Tiles specification formed part of the contractual
specifications. The principles applicable to the construction of a contract are well
established. The terms of a contract should be construed so as to give them the
meaning intended by the parties. That meaning is to be determined objectively: what
would a reasonable person think was intended by the term? Evidence of surrounding
circumstances is admissible to assist in the interpretation of the contract if the
language is ambiguous or susceptible of more than one meaning. But it is not
admissible to contradict the language of the contract when it has a plain meaning.17
[21] On a plain reading of the contract, the reference in item 21.7 of the specification to
‘stud wall, rectified tiles as per Beaumont tile spec’ is a reference to the stud walls as
indicated on the plans. There is no ambiguity in this regard. It is unnecessary to have
reference to the Beaumont Tiles specification in order to construe the meaning of the
item 21.7 of the specification. The finding by the learned member that the plans
provided the relevant wall in the ensuite separating the shower recess from the ensuite
was not a stud wall, is not appealed. There is no conflict between the specification and
the plans.
[22] The learned member erred in finding that the contract required a solid stud wall for
the ensuite shower. It was unnecessary for the learned member to have regard to the
Beaumont Tile specification in circumstances where, on a plain reading of item 21.7
of the specification, the rectified tiles in accordance with the Beaumont Tiles
specification were only to be affixed to the stud walls identified on the plans. The
relevant wall in the ensuite was not a stud wall.
[23] The proper construction of a contract is a question of law.18 The learned member erred
in law in failing to properly construe the contract.
[24] The consequence of the learned member’s error in construing the contract was that he
erred in assessing the Forrests’ entitlement to damages. The assessment of damages
is a question of fact.19 Ground of appeal 3 involves questions of both law and fact.
Leave to appeal should be granted on the basis that there was error in the primary
decision and is required to correct a substantial injustice to Abbott caused by the error.
Rehearing
[25] An appeal by way of rehearing involves a fresh determination of the rights and
liabilities of the parties and is not confined to merely correcting error in the
determination of the tribunal below.20
[26] An appeal by way of rehearing under s 147 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) is not a rehearing de novo. The
17 Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24.
18 Ryan v Worthington [2015] QCA 201.
19 Hoad v Scone Motors Pty Ltd [1977] 1 NSWLR 88.
20 Moose Plastering Pty Ltd v Habul [2014] QCATA 354, [72].
-- 6 of 19 --
7
Appeal Tribunal must make its own determination on the material before the Tribunal
below (supplemented, if necessary by additional evidence if permitted under s 147(2))
with due respect for the findings of fact of the primary Tribunal, and due consideration
of the advantages enjoyed by it.21
[27] In rehearing the matter the learned member’s primary findings of fact have been
adopted other than where those findings have been challenged in the appeal or where
there is doubt as to the findings below. Otherwise, I have formed my own views on
the evidence in accordance with the relevant principles applicable in appeals by way
of rehearing on the record of proceedings before a primary tribunal .22
[28] I will confine the rehearing to a consideration of those matters raised in the grounds
of appeal, the other relevant findings and conclusions by the learned member not being
contested.
The ensuite shower wall
[29] The Forrests’ claim the amount of $3,928.91 being the cost of removing the shower
door and screen installed by Abbott and replacing it with a tiled stud wall.
[30] I have found that on a plain reading of the contract, the reference in item 21.7 of the
specification to ‘stud wall, rectified tiles as per Beaumont tile spec’ is a reference to
the stud walls as indicated on the plans. The plans did not provide for a third stud wall
in the ensuite shower. Accordingly Abbott was not required to construct a solid stud
wall for the ensuite shower.
[31] It follows that the claim by the Forrests is not allowed.
The retaining wall
[32] Before addressing the issue of the retaining wall it is necessary to deal with the
application by Abbott to rely upon the further evidence of the engineer. In Helu v
Yuan the Appeal Tribunal stated:
While the Appeal Tribunal has an overriding discretion to permit additional
evidence in order to prevent a miscarriage of justice, the fact that the evidence
may of itself have had an important impact on the result at first instance does
not mean that in every case such evidence will be permitted to be adduced in a
rehearing. The Appeal Tribunal will consider a range of factors including the
factors usually considered in an application to adduce new evidence on appeal.
One of these factors is whether the evidence, with reasonable diligence, could
have been obtained at the time of the original hearing. As the Appeal Tribunal
observed in Queensland Vedic Cultural Centre Pty Ltd v Lal, if the evidence
could have been obtained by the party seeking to rely upon it, then it is difficult
to see how not permitting the evidence in the appeal will result in a miscarriage
of justice. Parties are responsible for the conduct of their own case and should
present it at one time and not in a piecemeal fashion. Accordingly, unless the
interests of justice demand it, additional evidence should not be permitted upon
a rehearing.23
21 WJ v Chief Executive Officer, Public Safety Business Agency [2015] QCATA 190.
22 Cairns Regional Council v Carey [2012] QCATA 150.
23 [2023] QCATA 12.
-- 7 of 19 --
8
[33] The further evidence consists of a two-line email sent by the engineer to Mr Abbott.
The evidence is not contained in a report and does not comply with the requirements
for expert evidence.24 Abbott concedes that the evidence could have been adduced at
the hearing below. Abbott is now seeking to plug the evidentiary holes in the case it
ran below by seeking to rely upon an extremely brief two-line email. I do not consider
that the interests of justice require that the evidence be permitted in circumstances
where the appellant concedes that the evidence could have been obtained and where
the proposed evidence is not particularly compelling. The application to rely upon the
evidence of the engineer is refused.
[34] The retaining wall was identified in the plans. The Forrests said that the wall, as
constructed, was shorter than identified on the plans and that they should have been
credited for the reduction in size of the wall.
[35] In the proceeding below, Abbott said that the change in dimensions of the wall arose
out of amended plans provided by the Forrests. It was not contentious below that the
house as constructed was 500 millimetres lower than indicated on the plans. It was
this reduction in height, said Abbott, that resulted in the wall being reduced in length.
Abbott contended that the result of the height reduction was that it was not possible
for the wall to be constructed in accordance with the plans.
[36] The learned member found that it was possible for the wall to be built to the full design
length.25 The learned member found:
It must have been possible for the retaining wall to be built to the full design
length, since the Forrests say they incurred considerable cost constructing block
walls to retain ground that otherwise would have been removed during
construction or retained by RW2.
[37] The written evidence of Mr Paterson, Abbott’s construction manager, was that the
lowering of the finished pad resulted in additional material being required to be
removed and higher and wider retaining walls installed.26 Mr Paterson’s written
evidence was that as a result of the change in height, the start and finish points in the
retaining wall moved slightly as the site had a steep gradient from right to left.27 The
evidence of Mr Paterson was that as a result of the amended plans the retaining wall
under the study was decreased by approximately 1 metre ‘…as with a drop in
designated height for the slab junction point moves which is unavoidable.’28
[38] Mrs Forrests’ written evidence was that the retaining wall was constructed
approximately 2 metres shorter than indicated on the plans.29
[39] A Scott Schedule was filed. The claim by the Forrests relating to the reduction in size
of the retaining wall was based upon the report of Mr Burgess, a quantity surveyor. In
his report, Mr Burgess stated that the retaining wall should have been 3.71 metres in
length however as constructed the wall was 1.4 metres long, a difference of 2.31
metres. Mr Burgess calculated an amount of $2,910.96 as the saving resulting from
the reduced wall length.
24 QCAT Practice Direction no. 4 of 2009.
25 Reasons [97].
26 Exhibit 23.
27 Ibid.
28 Ibid.
29 Exhibit 3.
-- 8 of 19 --
9
[40] Abbott’s response in the Scott Schedule was that the reduction in construction height
caused major changes to the construction:
The RW2 Wall is drawn to finish at ground level to match onto upper slab
footing, with the 500mm drop from the amended plan it changed the meeting
point of the SF2 footing to SF1 footing – refer to attachment 9.
[41] Mrs Forrest was cross examined at the hearing by Mr Paterson. The evidence of Mrs
Forrest was as follows:
And they actually admitted, in their statements, that the wall was constructed
shorter because the house was lower. They didn’t – correct me if I’m wrong, or
if I’ve misunderstood your statements, but the wall – you were digging into rock
or something, and so you didn’t need to dig into rock to create the wall longer.
The decision was made to build the wall shorter.30
[42] It is sufficient to observe that the oral evidence given at the hearing was not
particularly illuminating regarding the issue of whether the retaining wall could have
been constructed in accordance with the plans.
[43] Both parties filed written submissions after the hearing. In their submissions, the
Forrests said a number of things: that the retaining wall did not directly support the
house; the wall was primarily a retaining wall and was included for landscaping
purposes and to provide greater access around the house; they had incurred
considerable additional costs constructing block walls to retain ground that would
otherwise have been removed during construction or contained by the wall; and
Abbott offered no valid reason why the wall could not have been constructed in
accordance with the contract.
[44] Abbott’s submissions stated that the wall as constructed was ‘what could be
constructed … due to plan error.’ There was no reference in the submissions to the
retaining wall being structural.
[45] The contract documents included the construction drawings. While it is true to say
that the dimensions of the retaining wall were not specifically identified in the
drawings, it is clear from the drawings that, by extrapolating and applying the
identified exterior dimensions of the house, the dimensions of the retaining wall are
clearly ascertainable. The relevant part of the retaining was, in accordance with the
plans, required to be 3.7 metres long.
[46] Abbott says that the learned member erred in failing to find that the retaining wall was
structural. This submission rests on two bases: firstly, the evidence of the Abbotts
should not have been preferred over the evidence of Mr Paterson; secondly, reliance
upon the fresh evidence sought to be adduced by Abbott.
[47] As to the first basis, it is first necessary to observe that the hearing was conducted in
a somewhat informal manner. This is not unusual in Tribunal proceedings where both
parties are acting for themselves nor is there any criticism of the learned member
intended. In the course of cross-examining Mr Forrest, the following exchange took
place:
MEMBER: So it’s – the wall is to, as it were, prop out or protect the horizontal
pad of the house?
30 T1-94, lines 24 – 29.
-- 9 of 19 --
10
MR PATERSON: Yes.
…
MEMBER: Do you understand that, Mr Forrest? … The retaining wall is that
part which props up that part of the house?
MR FORREST: That retaining wall does not prop up the house… The retaining
wall holds back dirt.
…
MEMBER: So I think I understand, which is the purpose of the retaining wall
is to, as it were, separate the ground from the house?
MR FORREST: Yes.
[48] Accepting that the above exchange between the learned member and Mr Paterson
involved Mr Paterson giving evidence, the exchange was the highest at which one
might view Mr Paterson’s evidence on the function of the retaining wall. Mr Paterson
agreed with the learned member’s proposition that the retaining wall ‘propped out’ or
‘protected’ the horizontal pad of the house. This is, in my view, well short of evidence
that the retaining wall was structural in nature and supported the house pad.
[49] Mr Paterson did not assert in his written evidence that the retaining wall was
structural. Neither Abbott’s response to the building dispute application nor its
response to the Scott schedule included an assertion that the retaining wall was
structural.
[50] In conducting a proceeding the Tribunal may inform itself in any way it considers
appropriate, and the Tribunal is not bound by the rules of evidence. The Tribunal must
act fairly and according to the substantial merits of the case. Although the Forrests’
post hearing submissions contain what is in fact further evidence addressing the issue
of the purpose and function of the retaining wall, Abbott does not appeal the reliance
by the learned member on the parties’ submissions filed after the hearing. Nor is there
any submission by Abbott that, in the event the appeal is required to be conducted by
way of rehearing, no regard should be had by the Appeal Tribunal to the submissions.
I therefore propose to have reference to the submissions by the parties.
[51] Abbott says that the evidence of Mr Paterson should be preferred over the Forrests as
he is a qualified builder. Mr Paterson’s evidence is not expert evidence as that term is
recognised and understood in Tribunal proceedings. It is ultimately a matter of
weighing up the evidence of each of the parties and making a determination as to what
evidence is preferred.
[52] I accept the assertion by the Forrests that they incurred expense in undertaking work
that should have been undertaken by Abbott in completing the construction of the
retaining wall and that the wall could have been built in accordance with the plans.
The member at first instance was clearly in a better position to assess the demeanour
of the witnesses and form a view as to the reliability of the witnesses and the weight
to be given to their evidence. Nevertheless, even at the remove of these appeal
proceedings, it is apparent that the Forrests were thoughtful and careful witnesses who
thoroughly prepared their case and gave considered and detailed evidence. There is
no reason to doubt the veracity of their evidence including their assertion regarding
the retaining wall. That assertion is consistent with the retaining wall not being a
-- 10 of 19 --
11
structural wall. It follows that the claim by the Forrests relating to the reduction in
size of the retaining wall should be allowed.
The termite barrier
[53] It is not contentious in this appeal that the termite barrier was damaged by Abbott.
The learned member found that the consequence of Abbott’s breach of contract was
that the Forrests would incur an annual sum of $395.00 over a period of ten years.
This finding is not appealed.
[54] The learned member calculated the loss in the amount of $3,950.00 being $395.00 per
year over ten years. Abbott says that this method of calculation is erroneous and
results in a windfall to the Forrests on the basis that they are recovering an amount
now that will be incrementally incurred over a number of years.
[55] At the hearing of the appeal, Abbott sought to rely upon s 61 of the Civil Proceedings
Act 2011 (Qld) in relation to the application of a discount rate in calculating future
loss. However, that Act does not apply in the Tribunal.31 The assessment of damages
in building dispute proceedings in the Tribunal falls to be determined in accordance
with established principles.
[56] Damages are compensatory in nature. The governing principle was stated in Robinson
v Harman:
The rule of the common law is, that where a party sustains a loss by reason of a
breach of contract, he is, so far as money can do it, to be placed in the same
situation, with respect to damages, as if the contract had been performed.32
[57] Damages for breach of contract are assessed as at the date of the breach. However, it
is often the case that it is not until the hearing that the most appropriate way to give
effect to the compensatory principle of damages can be determined.33
[58] A discount rate is a mechanism used to calculate the present value of compensation
for future loss and expenses. In Todorovic v Waller34 the High Court set the discount
rate for personal injury and death claims at 3 percent. By way of illustration, applying
an annualised 3 percent discount to the Forrests claim for the cost of regular termite
inspections, one arrives at a figure of $3,369.34.
[59] In Michellis, M. & D. v Carlos Steenland Pty Ltd and Meier Corporation Pty Ltd35
the former QCCT constituted by (now) Bradley J, considering a claim for future
storage expenses, stated:
The applicants are likely to have to continue to store their chattels for a further
period of 12 months while rebuilding plans are approved and the building work
is undertaken. It follows that further storage costs of $4,620.00 are to be
incurred. I will make no deduction from this sum for early payment, as I accept
that the monthly charge is likely to increase by an amount equal any relevant
discount factor.
31 Civil Proceedings Act 2011 (Qld), s 3.
32 (1848) 1 Exch 850, 855; 154 ER 363, 365.
33 Gagner Pty Ltd t/a Indochine Cafe v Canturi Corporation Pty Ltd, [2009] NSWCA 413.
34 (1981) 150 CLR 402.
35 [2006] QCCTB 197.
-- 11 of 19 --
12
[60] Abbott cites no case law establishing the principle that future loss in a case such as
this must be assessed by reference to a specified discount rate. Todorovic v Waller
was a claim for damages for personal injury, not a commercial dispute. The
determination of the Forrests’ loss is not to be undertaken by a slavish adherence to a
method of assessing damages relevant in personal injuries claims and must necessarily
take into consideration the particular facts of the case.
[61] It is unlikely that the annual cost to be incurred by the Forrests will remain static.
Common sense dictates that they will likely incur increased annual costs in having the
termite barrier inspection undertaken. Of course, what these increases may be
precisely is not known. Noting however the relatively minor difference in calculation
even if an annualised 3% discount were applied to the claim, taking into consideration
the increased cost likely to be incurred by the Forrests leads me to conclude that the
assessment by the learned member of the cost of future termite inspections was
justified and I see no reason to depart from it upon rehearing.
Liquidated damages
[62] The Forrests say that the works did not reach practical completion within the time
stipulated by the contract and that, as a result, they are entitled to liquidated damages.
Abbott resists the claim, relying upon clause 25.7 of the contract, asserting that
payment of the final claim by the Forrests relieved Abbott of any liability to pay
liquidated damages. In order to understand the position taken by the parties it is
necessary to say something about the relevant provisions of the contract.
[63] Clause 25 of the contract deals with practical completion. By clause 25.2 when the
builder believed the works had reached practical completion, the builder was required
to give to the owner a defects document, a notice of practical completion and the final
claim. By clause 25.3 the owner was required to pay the final claim within five
working days of receiving the final claim. This obligation was subject to clause 25.4
which provided that if the owner disputed that the works had reached practical
completion, the owner was required to give written notice to the builder, within 5
working days of receiving the notice of practical completion, a written notice stating
the owner’s requirements for practical completion to be reached and the provisions of
the contract relevant to each requirement. By clause 25.5 the builder was required to
complete the requirements necessary, in the opinion of the builder, for the work to
reach practical completion. After completing those requirements, the builder was
required by clause 25.6 to give to the owner a further notice of practical completion
and the owner was required to pay the final payment within 5 working days of
receiving the notice.
[64] The contract defined practical completion as the day when the subject work is
completed: (a) in compliance with the contract, including all plans and specifications
for the work and all statutory requirements applying to the work; (b) without any
defects or omissions, other than minor defects or minor omissions that will not
unreasonably affect occupation; and (c) if the building owner claims there are minor
defects or minor omissions the building contractor gives the building owner a defects
document for the minor defects or minor omissions.
[65] Clause 25.7 provided as follows:
25.7 The owner’s payment of the final claim is conclusive evidence of the
builder’s satisfaction, and discharge of the builder’s obligations in
connection with the subject matter of this contract except for:
-- 12 of 19 --
13
(a) fraud, dishonesty or fraudulent concealment relating to the works;
(b) the builder’s liability under Clause 27.1; and
(c) the builder’s liability under a statutory warranty set out in Clause
36.
[66] Finally, by clause 25.8 the date stated in the last notice of practical completion was
deemed to be the date of practical completion unless the owner gave to the builder,
within 5 working days, notice disputing the date and detailing why the date was
disputed.
[67] Of relevance to clause 25.7, clause 27.1 provided a defects liability period of 12
months from the date of practical completion during which the builder was liable to
rectify non-structural defects. Clause 36 reflected the statutory warranties found in
Schedule 1B of the QBCC Act implied into every regulated contract for domestic
building work.
[68] Clause 32 of the contract deals with late completion damages. Of relevance to the
present dispute, the Forrests were entitled to liquidated damages from the date of the
end of the building period until the earlier of the date of practical completion or the
date the Forrests took possession of the works. Clause 32.1 of the contract provided
that ‘the owner may set-off or deduct its claim for liquidated damages under clause
32.1 from the final claim payment to the builder.’
[69] It was not contentious below that the ‘building period’ under the contract ended on 24
October 2017 and that the date of practical completion was 20 June 2018, a period of
240 days. It was also not contentious below that the Forrests paid the final claim on
20 June 2018.
[70] Abbott relies on clause 25.7 to assert that the Forrests are prevented from making a
claim for liquidated damages.
[71] Below, the Forrests contended that Abbott acted dishonestly in requiring payment of
the final claim as a condition for handing over possession of the works to the Forrests.
[72] The learned member made a number of findings relevant to the issue of, and the
Forrests’ entitlement to claim, liquidated damages:
[44] I find as a fact that Abbott insisted on payment of the invoice for the final
claim, without deduction for any late completion claim, as a condition for
handover of possession to the house on 20 June 2018. Clause 25.3 of the
contract allows the owner five working days from receipt of the final claim to
pay it to the builder. By insisting on payment of the final claim in full as a
condition of handover, which is not a contractual entitlement in favour of
Abbott, Abbott deprived the Forrests of the period of five days to make payment
of the final claim and also to avail themselves of the opportunity to set off the
claim for liquidated damages for late completion under clause 32.2. That
conduct also set up, on the face of it, the reliance by Abbott on clause 25.7.
[45] In those circumstances, I find that the conduct on behalf of Abbott in
insisting on full payment of the final claim, without deduction for late
completion damages, or even giving the Forrests the opportunity to make a
claim of that kind by setoff, as a prerequisite for handover, triggering what
would otherwise be application of clause 25.7 was dishonest, relating to
completion of the works. In those circumstances, I find that cause 25.7 does not
prevent the Forrests from a successful claim under clause 32.
-- 13 of 19 --
14
[73] The finding of dishonesty is contested by Abbott.
[74] Ultimately it is not necessary to determine whether Abbott acted dishonestly in
deciding the issue of the Forrests’ entitlement to liquidated damages. The resolution
of the issue turns upon the application of orthodox principles of construction of the
terms of the contract.
[75] As I have observed earlier in these reasons, the proper construction of a contract is a
question of law and requires the determination of what a reasonable person in the
position of the parties would have understood or assumed. The meaning of clause 25.7
is to be construed in the context in which it operates within the broader contractual
framework.
[76] Clause 25.7 refers to the ‘builder’s obligations in connection with the subject matter
of the contract.’ (emphasis added) Although the term is not defined, clause 1 of the
contract refers to the ‘Builder’s obligations’ as:
1.1 The builder must:
(a) complete the works in accordance with the contract; and
(b) comply with all laws and lawful requirements of any statutory or
other authority with respect to the carrying out of the works.
[77] The contract defines ‘the works’ as ‘the works to be carried out, completed and handed
over to the owner in accordance with this contract as shown in the contract documents
including variations.’ The reference in clause 25.7 to the ‘subject matter of the
contract’ is clearly a reference to the construction of the dwelling.
[78] While it is accepted that the phrase ‘in connection with’ has a wide meaning, the
breadth of that meaning must be construed according to the context in which it
appears, including the purpose of clause 25.
[79] In Drayton v Martin, Sackville J stated:
Of course, the meaning of the phrase "in connection with", whether used in a
statute or in a contract, must depend on the context: Burswood Management Ltd
v Attorney-General (Cth) (1990) 23 FCR 144 at 146. Nonetheless, the width of
the ordinary meaning of the phrase is indicated by a passage from the judgment
of Wilcox J in Our Town FM Pty Ltd v Australian Broadcasting Tribunal (1987)
16 FCR 465, at 479-480:
"The words 'in connection with' have a wide connotation, requiring
merely a relationship between one thing and another. They do not
necessarily require a casual (sic) relationship between the two things: see
Commissioner for Superannuation v Miller (1985) 8 FCR 153 at 154,
160, 163. They may be used to describe a relationship with a
contemplated future event: see Koppen v Commissioner for Community
Relations (1986) 11 FCR 360 at 364; Johnson v Johnson [1952] P 47 at
50-51. In the latter case the United Kingdom Court of Appeal applied a
decision of the British Columbia Court of Appeal, Re Nanaimo
Community Hotel Ltd [1945] 3 DLR 225, in which the question was
whether a particular court, which was given 'jurisdiction to hear and
determine all questions that may arise in connection with any assessment
made under this Act, had jurisdiction to deal with a matter which
preceded the issue of an assessment. The trial judge held that it did, that
-- 14 of 19 --
15
the phrase 'in connection with' covered matters leading up to, or which
might lead up to, an assessment. He said, [1944] 4 DLR 639:
"One of the very generally accepted meanings of "connection" is
"relation between things one of which is bound up with or involved
in another"; or, again, "having to do with". The words include
matters occurring prior to as well as subsequent to or consequent
upon so long as they are related to the principal thing. The phrase
"having to do with" perhaps gives as good a suggestion of the
meaning as could be had."
This statement was upheld on appeal."36
[80] Clause 25, being concerned with practical completion, is therefore concerned with the
actual physical performance of the contractual works. This is apparent from the
various sub-clauses dealing with the requirement for the builder to give to the owner
a defects document, the entitlement of the owner to give a notice to the builder
disputing that the works had reached practical completion, and the requirement for the
builder to complete the works the builder considers are necessary to bring the works
to practical completion. In addition, clause 25.7 specifically preserves the owner’s
entitlements in respect of defective work during the defects liability period and in
accordance with the statutory warranties implied by schedule 1B of the QBCC Act.
[81] Seen in this context, the reference in clause 27.1 to Abbott’s obligations under the
contract is not to be confused with, and was quite separate and distinct from, any
liability incurred by Abbott as a consequence of its failure to comply with such
obligations. This includes the liability to pay late completion damages.
[82] As noted by the learned authors of Halsbury’s Laws of Australia:
The function of an agreed damages clause is to overcome the requirement of
proof of loss in a claim for damages. If damages have been liquidated by the
parties, there is no requirement that the plaintiff prove a loss and recovery of
compensation is thereby facilitated. The clause fixes the amount recoverable by
the plaintiff without the need for litigation at all unless the defendant denies that
the contract has been breached or refuses to pay.37
[83] Liquidation of damages does not alter the character of a respondent’s liability for
damages.38
[84] Abbott was not obligated to pay late completion damages to the Forrests. Abbott was
obligated to bring the works to practical completion within the period stipulated by
the contract. Clause 25 of the contract was concerned with the obligation imposed
upon Abbott to bring the works to practical completion being the physical completion
of the building works. On a proper construction of clause 25.7 in the overall context
of clause 25 and the purpose of the clause, the liability of Abbott for late completion
damages was not an ‘obligation’ within the meaning of clause 25.7. Rather, the
payment of such damages was a liability accruing to Abbott as a result of Abbott’s
failure to bring the works to practical completion within the time stipulated by the
36 (1996) 67 FCR 1, 32.
37 LexisNexis, Halsbury’s law of Australia, 110 – Contract, ‘(3) recovery of sums fixed by contract’
[110-11465].
38 Hungerfords v Walker (1989) 171 CLR 125.
-- 15 of 19 --
16
contract in circumstances where a claim for liquidated damages was raised by the
Forrests.
[85] This construction is consistent with clause 32.1 of the contract. The Forrests were not
required to offset a claim for late completion damages from the final claim. The use
of the permissive ‘may’ in clause 32.1 There was no contractual obligation imposed
upon the Forrests to act in accordance with clause 32.1 at the time of making the final
claim payment. Nor does the contract, unlike some building contracts, provide that
the claim for liquidated damages was required to be made within a specified period
failing which the owner would have no entitlement to such damages. Indeed, the
contract did not prescribe any consequences if a claim for liquidated damages was not
made and the appropriate offset not deducted from the final claim. It follows that it
would be inconsistent with the plain meaning of clause 32.1 to construe clause 25.7
as requiring the deduction by the owners of any amount for liquidated damages in
order to preserve a claim for such damages.
[86] It follows from the foregoing that the payment by the Forrests of the final claim did
not compromise their entitlement to claim liquidated damages. The calculation of the
liquidated damages claim is not contested by Abbott, only the entitlement of the
Forrests to recovery. The Forrests claim for liquidated damages is allowed.
Compliance by the Forrests with the requirements of s 77(2) of the QBCC Act before
commencing the proceeding
[87] Abbott asserts that the Forrests failed to comply with the requirements of s 77(2) of
the QBCC Act before commencing the proceeding.
[88] I will address the application by Abbott to rely upon further evidence in the form of a
statement by Mr Wayne Abbott. I have addressed earlier the relevant matters when
considering an application to rely upon further evidence in an appeal conducted by
way of rehearing. Abbott concedes that the evidence of Mr Abbott could have been
adduced at the hearing below. It should be noted that Mr Abbott did not give evidence
at all in the proceeding below either by written statement or at the hearing. As with
the evidence of the engineer, Abbott is simply seeking to address fundamental
deficiencies in the way in which it conducted its case below. The application to rely
upon the evidence of Mr Abbott is refused.
[89] Sections 77(1) and 77(2) of the QBCC Act provide:
77 Tribunal may decide building dispute
(1) A person involved in a building dispute may apply, as provided
under the QCAT Act, to the tribunal to have the tribunal decide the
dispute.
(2) However, the person may not apply to the tribunal unless the
person has complied with a process established by the commission
to attempt to resolve the dispute.
[90] It is not contentious in this appeal that compliance by a person with s 77(2) is a
mandatory pre-condition to the jurisdiction of the Tribunal to decide a building
dispute. Section 77(2) must be complied with before a proceeding for a building
dispute is commenced.
[91] In the originating application filed in the proceeding below, the Forrests stated:
-- 16 of 19 --
17
(a) They had made a complaint to the QBCC about the dispute;
(b) They had not participated in a QBCC dispute resolution process; and
(c) They had attached the formal notification letter from the QBCC stating that the
dispute resolution process required by the QBCC Act had been complied with.
[92] With the originating application filed in the proceeding below the Forrests filed a copy
of a letter from the QBCC dated 28 August 2019 in which it was stated:
If you wish to pursue the matter further, you may now apply to QCAT for
assistance.
This correspondence serves as notification you have participated in the QBCC’s
dispute resolution as prescribed by legislation and your case has now been
finalised.
Please present this letter to the QCAT Registry staff at the time of application,
quoting case number 523680.
[93] Although the appeal is being conducted by way of rehearing it is relevant to note that
in the proceeding below Abbott did not take issue with the compliance by the Forrests
with the requirements of s 77(2). The issue is raised for the first time in this appeal.
Abbott says that as the ground of appeal raises a question of law, it can be raised as a
new issue on appeal. In Water Board v Moutsakas it was stated:
More than once it has been held by this court that a point cannot be raised for
the first time upon appeal when it could possible have been met by called
evidence below. Where all the facts have been established beyond controversy
or where the point is one of construction or of law, then a court of appeal may
find it expedient and in the interests of justice to entertain the point, but
otherwise the rule is strictly applied …
…
In deciding whether or not a point was raised at trial no narrow or technical
view should be taken. Ordinarily the pleadings will be of assistance for it is one
of their functions to define the issues so that each party knows the case which
he is to meet. In cases where the breach of a duty of care is alleged, the
particulars should mark out the area of dispute. The particulars may not be
decisive if the evidence has been allowed to travel beyond them, although where
this happens and fresh issues are raised, the particulars should be amended to
reflect the actual conduct of the proceedings.39
[94] I do not accept the submission by Abbott that the issue of jurisdiction is confined to a
question of law. Whether a party has complied with s 77(2) of the QBCC Act raises a
question of mixed law and fact. First, findings of fact are required as what steps were
taken by the parties vis-à-vis the QBCC and any dispute resolution process established
by the commission. The evidence may be that there is no such process relevant to a
particular building dispute. Whether the facts as found fall within the meaning of s
77(2) will then be a question of law.
[95] As the matter was not raised below, neither party led evidence on the issue.
39 (1988) 180 CLR 491, 497.
-- 17 of 19 --
18
[96] In Allen & Anor v Contrast Constructions Pty Ltd (No 2) the Appeal Tribunal
constituted by Deputy President Allen KC and Senior Member Traves stated:
[27] Here, the builder did attempt to comply with a process established by the
commission to attempt to resolve the dispute. The builder received a formal
notification from the QBCC that it had attempted to do so but was outside the
scope of the established process. In our view, this is sufficient to comply with
s 77(2) of the QBCC Act. If there is no process to deal with the dispute then
there is no “established” process to deal with the dispute within the meaning of
s 77(2). It follows that a person can not be in breach for a failure to comply with
a process that does not exist, to resolve their dispute.
[28] Having said that, the builder here applied to the Commission in any event.
This is a prudent step to take, particularly when it is not clear exactly what the
established process is or to which disputes it applies. It also avoids the Tribunal
having to determine the extent of its jurisdiction by reference to the nature and
extent of the QBCC’s dispute resolution processes that may have existed at the
time. In that respect we note the Consumer Building Guide published pursuant
to s 46 of Schedule 1B of the QBCC Act which provides that the QBCC’s EDR
(early dispute resolution) process is a free service which offers a facilitation-
based approach to resolving disputes while the contract is “still on foot”. There
are also fact sheets which refer to the EDR process published from time to time
by the QBCC which refer to contracts which are “still active”, in which case
EDR will aim to facilitate an acceptable agreement between both parties.
[29] Accordingly, in circumstances where the building contract was terminated
and the builder had attempted to comply with the QBCC’s dispute resolution
process before applying to the Tribunal, we find that the builder had complied
with s 77(2) of the QBCC Act.40
[97] The statement by the Appeal Tribunal is directly relevant for present purposes. The
Forrests applied to the QBCC in relation to the dispute. This was an appropriate and
prudent step to take. The QBCC wrote to the Forrests advising them that they had
participated in the QBCC’s dispute resolution as prescribed by the QBCC Act with
the result that the Tribunal was not required to determine the extent of its jurisdiction
by reference to the nature and extent of the QBCC’s dispute resolution processes that
may have existed at the time. If Abbott wished to challenge the issue of compliance
by the Forrests with s 77(2) it had the opportunity to do so in the proceeding below
including, for example, by leading evidence as to its involvement with the QBCC and
any relevant dispute resolution process (or absence thereof). The only evidence before
the Tribunal below on the issue of compliance by the Forrests with s 77(2) was the
letter from the QBCC dated 28 August 2019. That letter is sufficient to conclude that
the Forrests complied with the requirements of s 77(2) before commencing the
proceeding.
Conclusion
[98] The learned member assessed the Forrests entitlement to damages in the amount of
$42,425.50. The only items of damage contested by Abbott in the appeal relate to the
claim for liquidated damages, and the claims relating to the retaining wall, the ensuite
wall and the termite protection. Of these claims, only the finding allowing for the cost
40 [2021] QCATA 43.
-- 18 of 19 --
19
of the ensuite shower wall is infected by error. Accordingly, the total amount payable
by Abbott to the Forrests is reduced by an amount of $3,928.91.
[99] I make the following orders:
(a) The application by Abbott to rely upon further evidence is refused.
(b) The application by the Forrests to rely upon further evidence is dismissed.
(c) Leave to appeal is granted.
(d) The appeal is allowed.
(e) Order 1 of the decision of the Tribunal dated 4 May 2022 is varied by
substituting ‘$42,425.50’ with ‘$38,496.59’.
(f) The parties are to file and exchange submissions on the costs of the appeal, not
exceeding five (5) pages in length within 14 days of the date of this decision.
(g) The costs of the appeal will be determined on the papers.
-- 19 of 19 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2023/141