Allen v Queensland Building and Construction Commission [2023] QCATA 66
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Allen v Queensland Building and Construction
Commission [2023] QCATA 66
PARTIES: REECE JUSTIN ALLEN AND CHANTELL RENEE
MARIA TAYLOR
(applicants/appellants)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: APL091-20
ORIGINATING
APPLICATION NO/S:
GAR136-18
MATTER TYPE: Appeals
DELIVERED ON: 15 June 2023
HEARING DATE: 17 December 2021
HEARD AT: Brisbane
DECISION OF: Judicial Member D J McGill SC
ORDERS: So far as the appeal was on questions of law, the
appeal is dismissed.
Leave to appeal on questions of fact or mixed fact
and law granted, limited to the issues of whether
the appellants were in the circumstances entitled to
terminate the building contract at common law for
repudiation, or for sufficiently serious breaches of
non-essential terms; otherwise leave to appeal
refused.
Appeal by leave dismissed.
The appellants pay the respondent’s costs of and
incidental to the appeal, on the scale appropriate
for a matter in the District Court of Queensland,
unless within twenty-eight days from the date of
this decision the appellants provide to the associate
to the Deputy President and to the respondent
submissions in writing as to why such order should
not be made.
If such submissions are provided, the respondent
may provide submissions in response to the
associate and to the appellants within twenty-eight
-- 1 of 68 --
2
days from receipt of the appellants’ submissions.
Subject to any further directions, the question of
costs will then be decided without an oral hearing
in accordance with the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) s 32.
CATCHWORDS: BUILDING ENGINEERING AND RELATED
CONTRACTS – REMEDIES FOR BREACH OF
CONTRACT – POWER TO SUSPEND OR DETERMINE
– termination under contract – termination at common law
– whether right to terminate arisen – whether substantial
breach of contract – whether builder repudiated – whether
substantial breaches of non-essential terms whether right to
claim on statutory insurance
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 147(2)
Queensland Building and Construction Commission Act
1991 (Qld) Part 5
Advance National Services Pty Ltd v Daintree Contractors
Pty Ltd [2019] NSWCA 270
Aurizon Network Pty Ltd v Glencore Coal Queensland Pty
Ltd [2019] QSC 163
Botros v Freedom Homes Pty Ltd [2000] 2 Qd R 377
Built Qld Pty Ltd v Pro-Invest Australian Hospitality
Opportunity (ST) Pty Ltd [2022] QCA 266
Bundanoon Sandstone Pty Ltd v Cenric Group Pty Ltd
[2019] NSWCA 87
Clarke v Japan Machines (Australia) Pty Ltd [1984] 1 Qd
R 404
CNY17 v Minister for Immigration and Border Protection
[2019] HCA 50, (2019) 268 CLR 76
Codelfa Constructions Pty Ltd v State Rail Authority of
NSW (1982) 149 CLR 337
Coulton v Holcombe (1986) 162 CLR 1
DCT Projects Pty Ltd v Champion Home Sales Pty Ltd
[2016] NSWCA 117
Dura (Australia) Constructions Pty Ltd v Hue Boutique
Living Pty Ltd (No 3) [2012] VSC 99
Ebner v Official Trustee in Bankruptcy (2000) 205 CLR
337
EMClarity Pty Ltd v BSO Network Inc [2022] QCA 177
Ergon Energy Corporation Ltd v Rice-McDonald [2009]
QSC 213
FPM Constructions v Council of the City of Blue
Mountains [2005] NSWCA 340
Hometeam Constructions Pty Ltd v McCauley [2005]
NSWCA 303
Hudson Crushed Metals Pty Ltd v Henry [1985] 1 Qd R
202
-- 2 of 68 --
3
Isbester v Knox City Council (2015) 255 CLR 135
Re JRL, ex parte CJL (1986) 161 CLR 342
Just GI Pty Ltd v Pig Improvement Co Aust Pty Ltd [2001]
QCA 48
Keswick Developments Pty Ltd v Keswick Island Pty Ltd
[2012] 2 Qd R 114
Koompahtoo Local Aboriginal Land Council v Sanpine Pty
Ltd [2007] HCA 61, (2007) 233
CLR 115
Mazelow Pty Ltd v Herberton Shire Council [2003] 1 Qd R
174
Michael Wilson & Oakey Coal Action Alliance Inc v New
Acland Coal Pty Ltd [2019] QCA 184
Mousa v Vukobratich Enterprises Pty Ltd [2019] QSC 49
Partners Ltd v Nicholls (2011) 244 CLR 427
R v Deputy Industrial Injuries Commissioner, ex parte
Moore [1965] 1 QB 456
Sekler v Kim Carroll Investment Pty Ltd [2021] QSC 312
Smits v Cugola [2022] QCA 262
Tullock Brae Pty Ltd v Environmental Protection
Equipment Pty Ltd [2021] QSC 213
Vision Eye Institute Ltd v Kitchen [2014] QSC 260
APPEARANCES &
REPRESENTATION:
Applicant: R J Allen in person
Respondent: S E Seefeld, instructed by the respondent
REASONS FOR DECISION
[1] The appellants made a claim to the respondent in relation to incomplete domestic
building work under the home warranty insurance scheme in the Queensland
Building and Construction Commission Act 1991 (Qld) (“the Act”) Part 5. On 19
March 2018 the respondent rejected the claim, on the ground that the appellants had
not validly terminated the contract with the builder. The appellants sought a review
of that decision by the Tribunal, and on 27 February 2020 the Tribunal confirmed
the decision of the respondent.1 The appellants now appeal against that decision of
the Tribunal. There are separate proceedings in the Tribunal in relation to a claim
for defective work.
[2] The appellant is entitled to appeal to the Appeal Tribunal on a question of law, but
requires the leave of the Appeal Tribunal to appeal on a question of fact, or of mixed
fact and law.2 As a general proposition, when leave to appeal to the Appeal Tribunal
1 For convenience I shall refer to Mr Allen and Ms Taylor as “the appellants” and to the Commission
as the respondent. The Tribunal was constituted by a Senior Member, but for convenience I shall
refer to him as “the Member”. I shall use the term “the builder” to refer to either the building
company which was a party to the contract, or the director of the company who gave evidence.
2 Queensland Civil and Administrative Tribunal Act 2009 (Qld) (“the QCAT Act”) s 142.
-- 3 of 68 --
4
is required, it will be granted only where there is a reasonable argument that the
decision was attended by error and an appeal is necessary to correct a substantial
injustice caused by that error, or where the appeal raises a question of general
importance upon which further argument and a decision of the Appeal Tribunal
would be to the public advantage.3 An Appeal Tribunal will not usually disturb
findings of fact on appeal if the evidence is capable of supporting the finding, and it
is not contrary to compelling inferences.4 If leave to appeal is granted, the appeal is
by way of rehearing so far as it is against a decision on a question of fact, or of
mixed fact and law: the QCAT Act s 147. Otherwise it is an appeal which will only
correct an error of law: the QCAT Act s 146.5
Additional evidence
[3] By an application filed in the appeal proceedings on 13 November 2020, the
appellants seek to rely on additional evidence in the appeal, namely two additional
reports by an expert who gave evidence for the appellants at the hearing, and an
affidavit of Mr Allen. The Appeal Tribunal proceeds on the basis that the usual tests
for fresh evidence, as set out for example in Clarke v Japan Machines (Australia)
Pty Ltd [1984] 1 Qd R 404 at 408, must be met for such evidence to be admitted on
appeal under the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (“the
QCAT Act”) s 147(2), at least in relation to additional evidence relevant to an appeal
on a question of fact, or of mixed law and fact.
[4] The appellants submitted that, because of the wording of s 147(2), which in terms
conferred an unfettered discretion on the Appeal Tribunal, such an approach was too
confining, and sought to fetter the statutory discretion. It was submitted that, in
Clarke (supra), Thomas J distinguished between an appeal from a judgment after
hearing a cause or matter upon the evidence and hearing an appeal generally, on the
basis of the wording of O 70 r 10 of the then Rules of the Supreme Court.
[5] The reason why additional evidence on appeal is confined as set out in Clarke
(supra) in cases where there has already been the opportunity to put forward
evidence at first instance is that otherwise the significance of the first proceeding is
diminished, and it becomes just a preliminary to an appeal, where the full range of
evidence is mounted.6 That is contrary to the efficient use of resources, and the
principle that there should be an end to litigation, both of which apply as much to
the Tribunal as to a court. So parties to a proceeding in the Tribunal are expected to
put forward full evidence at a hearing on the merits, and it is appropriate that the
discretion in s 147(2) be exercised in accordance with the fresh evidence rules in
such cases. So far as this appeal is concerned, I propose to apply the fresh evidence
rules to the additional evidence sought to be relied on by the appellants.
[6] As to the first supplementary report of the appellants’ expert witness, that was
sought and prepared after the decision and reasons of the Tribunal were available.
The report largely consists of the expert’s reconsidering and confirming the opinions
3 Crime and Corruption Commission v Lee [2019] QCATA 38 at [12], citing appellate authority. See
also Campbell v Queensland Building and Construction Commission [2021] QCATA 34 at [17].
4 Craig v Mark Kelada Auto Sellers [2016] QCATA 48 at [13].
5 See also Pivovarova v Michelsen (2019) 2 Q R 508 at [4], [9]. It is an appeal in the strict sense:
Albrecht v Ainsworth [2015] QCA 220 at [94].
6 Coulton v Holcombe (1986) 162 CLR 1 at 7.
-- 4 of 68 --
5
expressed in earlier reports which were before the Tribunal. This says nothing of
consequence, and should not be admitted on appeal. The witness has already given
that evidence. One part referred to some remedial work in relation to some
windows, which had not been done at the time of the hearing, and said that when it
was done it showed that windows had been installed without proper under-sill
window flashing, and that one window had not been properly sealed. This could
have been ascertained before the hearing if the windows had been removed. Further,
as appears from the analysis later, this issue is not of significance to the outcome of
the proceeding, and at best provides confirmation of evidence of a defect in
construction.7 No part of this report will be admitted.
[7] As to the further affidavit of Mr Allen, this covered a number of matters. One was
said to be of certain events which occurred after the hearing, which were said to be
relevant to his credit, which had been attacked during cross-examination. This is a
collateral issue. One was an email about which he was cross-examined, and which
he spoke about in “re-examination”, but which neither party tendered; that was their
decision as to the conduct of the proceeding, and they are bound by it. It does not
appear from the reasons of the Tribunal that the outcome of the matter turned on, or
was significantly influenced by, the Member’s views of the credibility of Mr Allen.
[8] The appellants seek to put in evidence additional photographs, which they concede
existed at the time but were not put in evidence, as they are said to be relevant to the
fair determination of the appeal and to correct an injustice. Some photos concern a
particular defect complained about by the appellants, and raised at the hearing, but
do not address the ground on which that issue was dealt with by the Tribunal, which
was that there was a defect but the builder was seeking to address it, so that it was
not a basis to terminate the contract: [70]. Some paragraphs concerned the work
required to complete the pool and surrounds at the house. This sort of material was
available at the time of the hearing but not put in evidence. This is what the
approach in Clarke excludes.
[9] The appellants sought to put in evidence a document from the Australian Bureau of
Statistics as to the number of deaths in Australia associated with steps or stairs.
Apart from the fact that this evidence was obviously available at the time of the
hearing, it is irrelevant and inadmissible. What the appellants rely on is that there
are certain requirements for stairs set out in the National Construction Code, not
why they may have been put there.
[10] The appellants also sought to rely on evidence of an encroachment by the builder
across the boundary of the neighbouring property. Mr Allen in his affidavit said that
after the hearing he had another survey done which confirmed his observation that
the visible footings were over the boundary, an encroachment of 3 – 8 cm. In
September 2020 building work started on the neighbouring property, which involved
demolition and some excavation. This revealed that under a previous concrete
surface beside the boundary there was a more substantial encroachment, about 7
metres long, up to 1 metre deep and .6 metre wide. Part of this sat on a pier which
also encroached in part over the boundary. Subsequently the builder of the adjacent
7 The evidence of the builder was that the work on the installed windows was not finished at the time
of termination of the contract: Day 2 p 69. On that basis, it was really incomplete work.
-- 5 of 68 --
6
property removed the encroachment of the foundations; the intention is that the
encroaching pier be left in place, as it is below the level of the building works on the
adjacent property.
[11] Evidence of what was discovered in October 2020 satisfies the first test in Clarke
(supra), since it could not be found without the demolition of a concrete driveway
on the adjacent property, and it is apparently credible. Whether it should be
admitted depends on whether it has an important influence on the issue of whether
the building contract was validly terminated by the appellants. I will admit it for
that purpose. The second additional report by the expert witness relates to the
encroachment, and would be admissible if it said anything on which expert evidence
is required. What is relevant for present purposes is that there was a breach of a
contractual requirement that there be no encroachments. That there was an
encroachment was proved by the evidence of Mr Allen and of the surveyor, to the
extent that it is not obvious from the photographs. This is not something on which
evidence from an expert in building construction is necessary; his report is therefore
unnecessary and would be inadmissible in a court. I will not admit it.
Grounds of appeal – apprehended bias
[12] The appellants in the Annexure to the Application for leave to appeal or appeal
relied on a failure to accord natural justice, and apprehended bias, on the part of the
Tribunal, and also alleged 79 errors of law, and 43 errors of fact. It is appropriate to
deal first with the issues of apparent bias,8 and failure to accord natural justice,
because if established they are likely to lead to a rehearing before a different
member. The test for apprehended bias is whether, in all the circumstances, a fair-
minded lay observer with knowledge of the objective facts might entertain a
reasonable apprehension that the Tribunal might not bring an impartial and
unprejudiced mind to the resolution of the issues in the proceeding.9
[13] Some of the matters relied on as showing apparent bias were things that happened
during the hearing, but no application was made for the member to disqualify
himself. The appellant relied on the statement by Sofronoff P in Oakey Coal Action
Alliance Inc v New Acland Coal Pty Ltd [2019] QCA 184 at [68] as showing that
what happened during the hearing could be relied on if further statements in the
reasons give rise to a fresh apprehension of bias. His Honour went on to consider
the background to the reasons, including what was said at the hearing, before
concluding that the test for apprehended bias was met: [103]. I accept that the
appellants can rely on matters that happened at the hearing, indeed on all the
circumstances of the matter.10
[14] The first matter relied on was that at the hearing the Member criticised the decision
of another Member not to join the builder as a party to the proceeding. Because the
8 Concrete Pty Ltd v Parramatta Design and Developments Pty Ltd (2006) 229 CLR 577 at [2], [117].
9 Ebner v Official Trustee in Bankruptcy (2000) 205 CLR 337 at [6]; Michael Wilson & Partners Ltd v
Nicholls (2011) 244 CLR 427 at [31]. This test applies to a proceeding in the Tribunal: Chandra v
Queensland Building and Construction Commission [2014] QCA 335 at [83].
10 CNY17 v Minister for Immigration and Border Protection [2019] HCA 50 at [135], where Edelman J
also cautioned against assessing comments in the reasons against an assumption of a reasonable
apprehension of bias.
-- 6 of 68 --
7
builder is subject to a statutory indemnity in favour of the respondent11 it would
commonly be appropriate for the builder to be joined, but an issue can arise if the
application for joinder is delayed; in such circumstances there will be a tension
between the efficiency of conducting just one proceeding, and the prejudice
associated with the delay, and how that is to be resolved is a matter on which minds
may reasonably differ.12 The statement was made in a context where the Member
appears to have been concerned about the respondent’s witness being difficult, and
may have reflected an assumption that the witness would have been more
cooperative if the builder had been joined. The comment is understandable, and I do
not regard it as a matter of any significance in relation to apparent bias.
[15] Next the appellants relied on what was said to be a statement that claims should only
be available against the respondent under the insurance scheme if the builder were
insolvent. It was submitted that this indicated that the Member believed that the
appellants should not be entitled to claim or to pursue the proceeding. The first
difficulty with that submission was that it is not what the Member said. Mr Allen
was being cross-examined about the significance of progress payments, and
accepted that the amount of a progress payment did not affect the amount the builder
ultimately was paid, just the timing of the payment: Day 1 p 85. He then added the
qualification that “It does not help if the builder goes broke” because in those
circumstances the overpayment will not be recoverable in practical terms. The
Member then commented “That’s why you have insurance.” That does not say or
imply that insurance should be available only if the builder is insolvent. The
submission is based on a false premise.
[16] I also do not accept that apparent bias would have been shown if the Member had
offered the opinion that the Act should permit claims only if the builder were
insolvent. It is clear from the reasons that the Member was well aware of the terms
and operation of the relevant Part of the Act. It is commonplace for judicial officers
to comment on or to criticise the wording or operation of legislation relevant to
matters which come before them.13 This does not suggest apparent bias, as long as
they apply the Act as it is.
[17] The appellants also relied on what was said to be a gratuitous apologia about this
statement, calculated to defuse the earlier remark, and drew a parallel with the
comments of the Land Court Member discussed by Sofronoff P in the New Acland
Case (supra) at [93] to [96]. Again, this is not what happened. In re-examination
Mr Allen said that it seemed to be implied that one could terminate only if the
builder goes broke: Day 1 p 103. Someone, apparently the Member, said “I don’t
think anyone is contending that.” Counsel for the respondent promptly said that he
was certainly not contending that. Mr Allen then said “No-one is contending that.
All right.” The Member then said that Mr Allen was the only one who raised that
when he was talking about the progress claims, but said nothing about his views, nor
11 The Act s 71.
12 Just GI Pty Ltd v Pig Improvement Co Aust Pty Ltd [2001] QCA 48 at [17]. I assume the builder was
not a necessary party, as discussed in China First Pty Ltd v Mt Isa Mines Ltd [2018] QCA 350, as a
person affected by the decision because of s 71: Lange v QBSA [2012] 2 Qd R 457 at [73]. This
issue has not arisen in this matter.
13 See for example MNM Developments Pty Ltd v Gerrard [2005] 2 Qd R 515 at [27].
-- 7 of 68 --
8
sought to modify them. Again, the submission is based on a false premise. The
reasons of the Member showed clearly that he was aware of the operation of the Act.
[18] The appellants also relied on the Member having said to the witness for the
respondent, a person associated with the builder, that it was a difficult site and a
difficult job.14 They said this suggested that the Member believed that the contractor
did not need to complete the contract work in the time agreed. There were also
complaints about the Member having said he could not help having to call the
witness back for further cross-examination on the third day of the hearing,15 thereby
impliedly criticising Mr Allen for the length of and approach to his cross-
examination. This was said to be expressing sympathy for the witness at the
expense of the appellants. The Member was also criticised for failing to exclude
unresponsive answers by the witness during cross-examination, despite objection;
and by saying to the witness that he knew that the witness had a lot of things to say
and was unhappy about all of this.
[19] I have already mentioned that the witness was difficult, and was at times
uncooperative under cross-examination. At one point the Member sought to calm
down both the witness and Mr Allen, who were said to be both becoming heated,
and asked them not to talk over each other.16 At the same time he asked the witness
to confine his answers to the questions asked. I noted from the transcript that the
witness had a tendency to give extended answers, which sometimes drifted off topic.
[20] Tribunal members often have to deal with difficult witnesses who are not happy to
be giving evidence, and a member may well feel that it is more helpful to appear
sympathetic and to encourage the witness to cooperate rather that to adopt a more
strict and hostile approach, which may simply prove counter-productive. In my
experience taking a strict approach to unresponsive answers will often just waste
time and provoke the witness more. There was no jury, and unresponsive answers
can easily be ignored.17 I do not consider that a well-informed lay observer would
have taken what occurred with this witness as more than an attempt by the Member
to complete the witness’s evidence as efficiently as possible; it would not have
suggested apparent bias.
[21] In written submissions the appellants complained that the Member had answered the
questions for this witness, and referenced some intervention by the Member in
questioning of the witness about a certificate showing unsatisfactory aspects of the
frame inspection, with a view to showing that further work done by the builder
breached a statutory prohibition. The certificate spoke for itself, the questioning
required to establish the appellants’ point was quite limited, and most of Mr Allen’s
questioning on this topic was unnecessary. It is unsurprising, and appropriate, that
the Member was trying to move things along. It does not suggest bias.
[22] The appellants complained of a number of matters in the reasons for decision. It
was said that the Member had been critical of hearsay evidence from Mr Allen, but
14 Day 2 p 56. If it comes to that, I can see from the architect’s drawings that this was no more than a
statement of the obvious.
15 Day 2 p 110.
16 Day 2 p 48, something I have had to do myself countless times.
17 See the comment at Day 2 p 45 lines 14-16.
-- 8 of 68 --
9
had accepted and acted on hearsay from the respondent. Reference was made to the
reasons at [145], [146], which as I read them are referring to three separate matters.
Evidence from Mr Allen that he was suspicious about the quality and structural
soundness of parts of the building does not prove anything, particularly when he had
lost confidence in the builder.18 The quote from paragraph 60 of the affidavit does
not appear to me to be relevant to anything; what might be relevant was whether the
superintendent did in fact issue such a variation.
[23] The problem with hearsay is that its reliability can vary enormously. In some
circumstances evidence which is hearsay will be obviously reliable, or quite likely to
be accurate, but in other circumstances there may be doubt about it, even substantial
doubt. Hearsay on hearsay may easily compound these problems. In circumstances
where the rules of evidence do not apply, it is a matter for the judgment of the
Tribunal to decide what weight, if any, to give to any particular piece of evidence.19
That some of the evidence put forward by the appellants was not given any or much
weight does not, in itself, suggest apparent bias. Similarly, that the respondent’s
witness gave evidence of things he had been told does not in itself suggest apparent
bias, particularly if the circumstances are such that it was likely that the people
informing him of things would have been at least trying to be honest and accurate.
When the reasons are considered as a whole, I do not consider that there is such a
disparity between the way in which material not within the rules of evidence put
forward by the appellants and that put forward by the respondent was treated as to
suggest to a well-informed lay observer that there was bias against the appellants.
[24] It was submitted that the finding that particular evidence of Mr Allen was unhelpful
was used to justify a finding that all of his evidence about the work was of little
assistance.20 This was not referenced, and I have not noticed the latter finding in the
reasons. It is also difficult to see that there was such a difference in treatment of the
evidence of Mr Allen and of that of the respondent’s witness as to suggest bias
against the appellants. Where the evidence of witnesses is in conflict, it is inevitable
that the evidence of one will be preferred to the other, but that does not show bias. It
seems to me that the Member was cautious about the evidence of the respondent’s
witness21 but the Member did accept some of his evidence, in a way which was not
obviously inappropriate.
[25] The appellants also submitted that apparent bias had been shown by the failure to
accept the evidence of their expert witness, who was the only expert and
independent witness; it was said that his evidence was largely ignored, or was not
applied.22 The evidence of the appellants’ expert was referred to at times by the
Member, generally in terms indicating that the Member accepted what was said by
the expert.23 At other times the evidence of the expert was referred to, but the issue
was not expressly resolved, because the Member decided the matter on another
18 Day 1 p 52: confidence was lost by 13 July 2017.
19 R v Deputy Industrial Injuries Commissioner, ex parte Moore [1965] 1 QB 456 at 488, which also
said that rules of evidence are not part of natural justice.
20 Submissions in writing para 92.
21 See for example reasons [70], [130].
22 Submissions in writing para 94.
23 See for example paragraphs [62], [65]
-- 9 of 68 --
10
basis.24 There was an instance where the Member accepted the evidence of a
statement from the gasfitters involved about the significant of a fitting being left
uncrimped in preference to the evidence on that subject of the expert, which strikes
me as unsurprising in the circumstances: [132].25
[26] There was another occasion where the evidence of the manufacturer of particular
sarking as to the suitability of a particular product was accepted in preference to the
evidence of the expert, where the evidence of the expert was based on the
interpretation of the manufacturer’s data sheet: [127]. The expert said that the
sarking installed did not comply with the relevant part of the National Construction
Code because it was not vapour permeable sarking.26 A 2014 technical data sheet
shown in the report described it as a Medium Vapour Barrier, and the report does
not identify any statement that it is impermeable to vapour. It had a vapour
transmission of 1.44 grams per square metre, which the expert said was very low.
The expert identified another sarking which was described as a vapour permeable
membrane, and as having a very high water vapour transmission rate. Clearly it is
much more vapour permeable, but I have difficulty in seeing how the expert
concluded that the one used was not a vapour permeable sarking.
[27] A copy of the National Construction Code in Appeal Book Vol 12 does not include
any definition of vapour permeable sarking in Part 1.1, I have not found one
elsewhere in it, and the expert did not identify one. In the absence of a definition,
sarking is vapour permeable if it is not impermeable to water vapour, which the
sarking installed was not. The fact that other sarking is more vapour permeable, and
that the expert regarded it as more suitable in Brisbane, is irrelevant to whether there
was a breach of the Code. Apart from this, the builder said that the product in fact
installed was more vapour permeable than was shown by the 2014 data sheet, and
exhibited a 2017 data sheet which showed a higher water vapour transmission rate.27
This point was not dealt with by the Member, but it would have been open to reject
the expert’s conclusion on this ground also.
[28] I have not identified any occasion when the evidence of the respondent’s witness
was preferred to the evidence of the expert where there was a direct conflict
identified by the Member, and the Member acknowledged that there was some force
in the appellants’ submission that the former was not independent: [123].28 There
was some of the expert’s evidence which was not referred to expressly in the
reasons, apparently because the Member did not regard it as important to the
24 See for example paragraph [65], where the Member referred to the explanation offered by the expert
for how the problem with the ensuite door arose, and want on to say at [66] that it was not necessary
to decide this, since it was clear that a mistake had been made, but the true issue was decided on the
basis that the builder was working with the superintendent to resolve the problem: [67]. See also
[73], where his evidence on a different issue was treated in a similar fashion.
25 One would expect a gasfitter to know more about gasfitting than an expert in building in general.
Besides, the passage quoted at [130] makes sense.
26 Day 3 p 36; National Construction Code 2016 Part 3.5.3.2(b)(iii), quoted in his supplementary report
p 9, Appeal Book p 2563.
27 Under cross-examination the expert said that that product also did not comply with the code, he said
because the manufacturer’s website said something different, which I do not understand: Day 3 p 39.
28 There was at least one direct conflict between the expert and Mr Allen. The expert said that an issue
with the concrete hobs (discussed below) was an aesthetic issue – Day 3 p 48 – something Mr Allen
denied: Day 1 p 77.
-- 10 of 68 --
11
resolution of the issues to be decided. The expert spoke about relatively few of the
issues raised by the appellants.29 I do not regard the treatment of the evidence of the
expert as suggesting apparent bias; the treatment seems to me to be consistent with
the general basis on which the Member resolved the matter.
[29] The appellants submitted that the Member said at [94] that the appellants had made a
particular submission, when that submission had not been made. As I read [94], the
Member was saying something about the effect of the appellants’ submissions,
rather than just quoting a submission. This relates to the issue of overclaiming,
where the submissions of the appellants were that, in view of the statutory context of
a payment claim, to overclaim at all was a substantial breach, regardless of the
response to the claim.30 I am not sure that the submission has the effect attributed to
it by the Member in [94],31 but I do not consider that such a characterisation of the
appellants’ submissions provides any indication of apparent bias.
[30] The appellants complain that Mr Allen was not afforded appropriate respect as a
litigant during the hearing. The submissions of the appellants do not explain the
basis for this submission, even under the heading “Lack of respect for the applicants
as litigants” on p 21, where the matters discussed to paragraph [206] all relate to the
reasons for the decision. At p 30 there was a passage cited from the hearing when
the Member stopped Mr Allen from taking the respondent’s witness through the
terms of the building contract and aspects of the law, such as the National
Construction Code. Certainly it was relevant to show that there were breaches by
the builder, but that is shown by proving that the builder did, or did not do,
particular things. That those acts or omissions amounted to breaches of contract, or
of law, were questions of law, on which the views of the witness, indeed any
witness, were irrelevant. The witness’s knowledge of the terms of the contract, or
his acceptance of its terms in the witness box, was irrelevant. I agree with the
Member that such cross-examination was a waste of time.32 It was appropriate for
him to stop it. It is not disrespectful or inappropriate to prevent a litigant in person
from wasting time, and it does not suggest apparent bias.
[31] The appellants complained that the Member had been critical of the appellants or of
Mr Allen in his reasons, in various respects:
(a) Making submissions in reply that go further than the evidence: [65]. This
concerned an attack on the evidence of the witness for the respondent as to
how it came about that the ensuite door was too narrow, where it was said that
the evidence of the witness that the architect had nominated a commercial
29 Apart from comments on damage from vandalism, three issues in the first report, and six in the
second report.
30 See submissions at first instance, 15 July 2019, paragraphs [173] to [182].
31 The Member’s point was I suspect that the quantity surveyor would consider whether and to what
extent the claim was justified after it had been made: see reasons [89]. It was not that the builder
was claiming for more than had already been assessed by the quantity surveyor. The appellants’
argument was that the claim had to be limited to what was really claimable under the contract.
32 To be fair, a certain amount of the cross-examination of Mr Allen just involved looking at and
identifying documents already in evidence, and was also unnecessary.
-- 11 of 68 --
12
section for the frames was a lie.33 The appellants were entitled to refer to
evidence before the Tribunal to show that this evidence was untrue, but they
ought not to have been introducing new evidence at that stage in respect of this
matter. To the extent that that occurred, any criticism was justified.
(b) Not calling a witness from the superintendent (the architect): [143]. The
respondent’s witness gave evidence that the superintendent (who was also the
architect) had given various instructions to do various things, generally to
make the design workable, and this evidence was not contradicted. This
passage in the reasons occurred in a context where the builder relied on such
an instruction, and Mr Allen had given evidence of what he had been told by a
person from the superintendent. The Member preferred the former, on the
basis that what Mr Allen said he was told did not directly contradict the other
evidence, and no witness from the superintendent was called, a matter he said
was noteworthy. The Member did not say that he drew any inference against
the appellants because of such failure, and I will not assume that he did, but
the omission was noteworthy in view of the issues raised by the appellants and
by the builder, even if a number of documents from the Superintendent did go
into evidence.34
(c) Including evidence in submissions in writing: [147]. The appellants pointed
out that Mr Allen was both witness and advocate, but that did not justify the
introduction of additional evidence in submissions. To the extent that any
evidence was introduced for the first time in submissions, that should not have
happened and the criticism was justified. It did not indicate apparent bias.
(d) Filing multiple statements of evidence, said to be at [147]. That paragraph did
say, correctly, that the appellants had filed a significant volume of evidence,
and that much was repetitive. The appellants referred to the absence of
pleadings, and to directions of the Tribunal. The Member commented that it
was an onerous task to sift through the material, and to discern the substantive
issues. No doubt it was. In this case I suspect it would have been of
assistance to the Tribunal if there had been pleadings, or something like them,
to identify the issues, but that is not how things are usually done in the
Tribunal. In any case, there was no reference to “multiple statements”.
(e) Omitting to criticise the respondent for the volume of its evidence, which was
not that different from the volume of the appellants’ material. This was said to
indicate unequal treatment of the parties, but the statements otherwise
complained of were found largely in the conclusion of the reasons, where the
Member was summarising the essential reasons why the appellants’ case had
failed, despite the extensive evidence and large number of issues raised, and
was emphasising his approach to the central issue. A fair-minded lay observer
would expect this to focus on the case of the appellants, because it is important
33 Submissions in reply at first instance, paragraph [62]. There is a difference between evidence being
untrue and its being a lie, and strictly speaking the appellants should not have made this submission
unless the proposition that this was a lie had been put to the witness in cross-examination.
34 There was some material from the superintendent supporting an inference that, had they given
evidence, it would not have assisted the appellants: Email from superintendent, at p 510 of first
statement by builder, Appeal Book Vol 11 p 2923.
-- 12 of 68 --
13
that reasons explain why the case of the unsuccessful party has failed. This
did not suggest apparent bias.
(f) Being repetitive in evidence, when the respondent had also been repetitive:
[147]. Repetitive material of the respondent was said to justify the repetition.
I am not at all sure that that is a justification. There is a modern tendency for
pleadings and similar documents which respond to do so in full by reference to
each individual matter to which there is a response,35 which often leads to
repetition. Properly done, this may help to clarify the precise case being
made, but at least so far as it applies to factual matters, I expect that usually
the only effect is to lead to longer documents and more voluminous material.
In something which is just evidence, factual matters do not need to be
repeated, whatever the state of the other party’s material. On the whole the
criticism was justified, and does not suggest apparent bias.
[32] The appellants also complained that bias was shown by sympathy for the builder and
the respondent’s witness manifested in the reasons, by:
(a) Finding that the relationship between the appellants and the builder had not
deteriorated to the extent where the builder could reasonably expect
termination of the contract: [31]. It was submitted that once the show cause
notice was given to the builder termination could reasonably be anticipated,
which may well be true, but the Member’s point at [31] is that until then the
relationship had appeared not to have so deteriorated, because the context was
the contrast with another case36 where there had been much criticism of the
builder before the show-cause notice was issued. The relationship between
owners and a builder can deteriorate very quickly, but in the absence of some
specific trigger mechanism one would expect the relationship to deteriorate
over time.37 Whether the state of the pre-notice relationship was relevant to
the reasonableness of the response is another issue, but the making of this
finding, even if adverse to the appellants, does not suggest apparent bias.
(b) Criticising the actions of the appellants, in going onto the site and identifying
as substantial defects things which would normally be attended to during
completion of the works, as particularly unfair to the contractor, where there
was an explanation for why the works were in that state, and where the
contractor was ready, willing and able to complete the project: [148]. The
appellants submit that any defects or other failures by the builder amounted to
a breach of contract, and in some cases of statutory obligations, by the builder
as soon as they occurred, and that they were entitled to enforce the contract,
and their rights under the insurance policy. I shall return to this point.
(c) Giving primacy to the evidence of the respondent’s witness, referring
generally to the reasons of the Member. I have dealt with this point to some
extent already. I do not consider that there was any pre-conceived primacy
accorded to the evidence of that witness. There were a number of occasions
35 For example, a response of the kind that says: “In response to paragraph 17, (a) … (b) …” etc.
36 Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99
(“Dura”).
37 Thompson Residential Pty Ltd v Hart [2014] QDC 132 at [13], [14].
-- 13 of 68 --
14
on which his evidence was accepted, and in each case reasons were given
which appear plausible.38 The mere fact that on a number of occasions the
evidence of a witness was accepted when another party has submitted that it
should not be accepted does not suggest bias against that party.
[33] In submissions the appellants identified what they said were a number of errors of
law which they said indicated bias against them. I will consider separately whether
these were errors of law, but the mere fact that the Tribunal made an error or errors
of law does not demonstrate bias.39 One ground, 14(h), was not referenced to the
transcript or developed in submissions, and I cannot take it any further, except to say
that it does not obviously suggest bias.
[34] The only matter which I consider might suggest bias against the appellants is the
matter raised in ground 14(s)(ii), the comment about something being particularly
unfair to the builder. It was not relevant for the Member to make any finding as to
the fairness or otherwise of any particular conduct. The reasonableness of the
response of the builder to the show-cause notice was an issue to be decided, but that
did not involve the fairness of the action in giving the show-cause notice. On the
question of whether the conduct of the builder, and its acts and omissions,
collectively amounted to repudiation, the focus is on the objective assessment of
what the builder has or has not done, and its expressed attitude to its contractual
obligations, rather than on the fairness of the other party’s conduct.
[35] Courts have in the past sometimes expressed some dissatisfaction with the result
which they have been forced to come to by the strict application of the law,40 but
usually by expressing sympathy for the unsuccessful party.41 To characterise the
conduct of an unsuccessful party in this way does give rise to some concern, but the
real issue is whether it suggests that the attitude to the fairness of the appellants’
actions influenced the findings made, or whether it was simply a comment that the
outcome could be seen as satisfactory in terms of broader concepts of justice.42
[36] The fair-minded lay observer may be taken to have also read the earlier reasons,
where relevant issues were identified, and various conclusions were reached. Some
of those conclusions are challenged by the appellants, but in this context what
matters is the analysis in fact set out in those reasons. On the face of it the reasons
appear to address the relevant issues and resolve them in a rational way on evidence
referred to in the reasons, and lead to the conclusion that the appellants’ case on the
review was unsuccessful. I do not consider that they would suggest apparent bias.
[37] In this context, I do not consider that this comment might be enough to lead a fair-
minded lay observer to entertain a reasonable apprehension that the Member had not
brought an impartial and unprejudiced mind to the resolution of the issues in the
proceedings. To do otherwise would be to attribute too much significance to a
38 So far as I can tell from the transcript, most of the builder’s evidence was at least superficially
plausible, and Mr Allen achieved relatively little in lengthy cross-examination.
39 Nicholls (supra) at [67].
40 An example is the hostility courts have in the past manifested to reliance on the Statute of Frauds as
a defence, particularly in its former application to contracts for the sale of goods.
41 Comment adverse to the unsuccessful party is not unknown: for example, Pohlmann v Harrison
[1995] 2 Qd R 59 at 62.
42 Broader concepts of fairness and justice are not irrelevant in the Tribunal: the QCAT Act s 28(2).
-- 14 of 68 --
15
single comment. A finding of apprehended bias is not to be reached lightly.43 There
is some authority that decisions of Tribunals should not be scrutinised too closely to
detect error, even when there is an obligation to give reasons.44 I appreciate that
apparent bias can be shown by much less than the sort of evidence required to show
actual bias, but I do not consider that, in context, this comment is enough,
particularly when the reasons are read in full. Apparent bias has not been shown.
Breach of Natural Justice
[38] The appellants relied on thirteen reasons in support of the proposition that the
Tribunal failed to afford them natural justice, apart from the issue of apparent bias,
with which I have already dealt. To some extent the submissions covered matters
already discussed in relation to apparent bias, such as failing to accept the evidence
of Mr Allen and the expert witness (grounds 1, 6, 8), or affording excessive weight
to the evidence of the respondent’s witness: grounds 7, 8. Such matters do not give
rise to any natural justice issues. The reasons contain frequent references to the
evidence of Mr Allen, and a number of references to the evidence of the expert, and
they were obviously considered. The mere fact that some was not accepted does not
show that the consideration was not proper, genuine and realistic.
[39] The appellants complained of the failure to make available for cross-examination the
authors of two documents admitted into evidence, where the content of the
documents was accepted in preference to the expert witnesses, as discussed at [24],
[25] above, and referred to the QCAT Act s 95(1)(b).45 That section requires the
Tribunal to allow a party a reasonable opportunity to cross-examine witnesses. It
applies to persons called as witnesses at a hearing, as appears from the use of the
word “witnesses” and the terms of the balance of that section, and does not apply
when evidence in a document is put before the Tribunal, even if that evidence has
not been proved in accordance with the rules of evidence.46 There was no
requirement to produce the authors of these documents for cross-examination.
[40] The appellants complained that the evidence of the respondent’s witness had been
“elevated” to the status as if the builder were a party to the proceeding: ground 4.
Nothing said by the Member suggests that the evidence of this witness was treated
as if the builder were a party, and where his evidence was accepted it was for other
reasons stated by the Member, which are on the face of it plausible.47 I do not
understand a complaint that his evidence was treated as if it was the respondent’s
submissions: ground 5. Since he was the respondent’s witness, one would expect
some conjunction between his evidence and its submissions. It was submitted that
the reasons were written as if the builder were a party.48 That is not how I read
them. Given that the issue was whether a contract between the appellants and the
builder had been properly terminated, it was inevitable that what happened between
43 Re JRL, ex parte CJL (1986) 161 CLR 342 at 371; CNY17 v Minister for Immigration and Border
Protection [2019] HCA 50, (2019) 268 CLR 76 at [55]
44 See also Isbester v Knox City Council (2015) 255 CLR 135 at [22].
45 Grounds 9, 10.
46 In fact one of the documents would appear to have been admissible under the Evidence Act 1977
(Qld) s 92, as the maker of the statement was overseas. See also the QCAT Act s 95(4)(a).
47 I suspect the appellants’ point is that UCPR r 424(1)(a) did not apply. The UCPR did not apply
anyway.
48 Submissions on appeal [177].
-- 15 of 68 --
16
the parties to that contract would be central to the case, particularly because of the
basis on which the appellants supported their termination of the contract.
[41] The appellants complained that a finding, that the defects in existence as at 21
November 2017 would have been remedied by the builder if the contract had not
been terminated, was based on mere speculation: ground 12. I cannot identify a
finding in those terms in the reasons, although there were a number of findings
about specific defects,49 and a comment that the existence of a defects liability
period under the contract showed that the possibility of defects existing after the
appellants went into possession, with the defects to be fixed when identified, was
contemplated by the terms of the contract: [121]. It was not relevant to make a
finding about whether all defects would have been remedied by the completion of
the works by the builder. This does not involve a natural justice point.
[42] The remaining grounds, 2, 3, 11 and 13, alleged that matters relied on by the
appellants were not considered by the Member. This is a natural justice point,
although the grounds identify only one such matter, that the superintendent was
mistaken as to the reason for the defect in the stairs, at [146]: ground 13. This was a
reference to the submissions in reply by the appellants, to the proposition that the
excessive riser height in the top flight of stairs had been allowed by the
superintendent as a deviation. The points made in reply were, apparently, that the
builder was not relieved of responsibility for the defect because the superintendent
was mistaken, and that there were other problems with the stairs, such that all the
stairs have since been replaced.50
[43] I can understand why the Member described the submissions as confusing. Why the
approval of the deviation by the superintendent was ineffective was not explained,
and there was a reference to Mr Allen having been told something by the certifier,
which added nothing to the expert’s opinion, was hearsay, and should not have been
included in submissions.51 This does not show that the submission was not
considered, just that it did not prove persuasive, which is not a natural justice issue.
[44] In submissions on appeal the appellants outlined the experience of Mr Allen in
construction law, but that was not a matter of significance in considering the weight
of his factual evidence. It was not for him to be giving evidence about the relevant
law; that was a matter for submissions. I reject the submission in paragraph [162].
The appellants criticised52 the statement by the Member at [145] that Mr Allen’s
belief as to the quality or structural soundness of the work, such as a garage slab, is
of little assistance, but that was based on its being just a matter of belief, rather than
there being any evidence of any factual basis for such concern. I doubt if even an
engineer can tell just by looking at a garage slab if it is structurally sound; there is
no reason to think that a solicitor who specialises in construction law can do so.
[45] The statement in the reasons at [144], that part of Mr Allen’s affidavit was
perplexing because it did not set out evidence of what was discussed, was also relied
49 For example, reasons [135], [136], [137].
50 Submissions in reply of applicants [162] – [167]. I deal with the issue of the stairs further below.
51 It was not referenced to any evidence, and may have been an illustration of the Member’s complaint
of evidentiary material in submissions.
52 Submissions on appeal [163].
-- 16 of 68 --
17
on under this ground.53 This was apparently a reference to the affidavit of Mr Allen
sworn and filed 23 May 2019 paragraphs 43 to 52. I have looked at this material,
and perplexing, although not the term I would use, is a reasonable description. It
contains a mixture of submissions and speculation, with little relevant factual matter;
for example, it does not state either the ceiling height required by the contract, or the
ceiling height as constructed. It speculates about the effect of a change in thickness
of the slab above the ceiling, but does not contain evidence on the point, such as the
design height and the “as constructed” height of whatever is above the slab. It also
contains evidence about what in fact was done later to reconstruct the ceilings,
which involved demolishing the ceiling, moving the services to bulkheads at the
sides, and installing ceilings very close to the concrete slab.54
[46] Much of the submissions about natural justice were directed to other issues, that
findings were not open on the evidence or that errors of law were made, which are
not natural justice issues. It is not a breach of natural justice to prefer the evidence
of a non-expert to the evidence of an expert witness, nor is it a breach to reject the
evidence of an expert witness on a particular matter, even if it was not contradicted
by another expert witness. Evidence about what the builder did and why it did it,
and what it was intending to do, was properly given by the respondent’s witness, and
is not opinion evidence. Even if that witness did give opinion evidence, it was not
on that account inadmissible.55 It was not a breach of natural justice to accept other
evidence in preference to the evidence of the expert witness on particular points.
[47] The appellants also submitted that it was a breach of natural justice to fail to take
deemed admissions into account.56 This was referenced to ground of appeal 54,
challenging the finding that there was an explanation for the state of the works when
in many cases the defects were admitted, or the builder had not responded to them,
and were therefore taken to be admitted. I do not understand that proposition. It is
not for the builder to make admissions on behalf of the respondent, and a failure by
the builder to answer an allegation about a defect in the works cannot bind the
respondent. There are no pleadings or notices to admit in this proceeding, so there
can be no such thing as a deemed admission. There was no breach of natural justice
in failing to take into account something that did not exist.
[48] As to the proposition that the Member failed to consider all of the grounds
advanced, the appellants identified sixteen bases on which they said they had an
entitlement to terminate,57 and said the Member had given only some consideration
to six of these grounds. The count of sixteen was wrong; even on the appellants’
approach. Even if the six grounds in the Notice to Show Cause are treated as six
separate grounds, there were only five further bases for termination relied on:
termination at law on the six grounds; termination for repudiation; termination for
defects; termination for illegality; and termination for breach of the implied term of
53 Submissions on appeal [164].
54 This was something the builder was discussing doing with the architect anyway when the contract
was terminated: Day 2 p 46 line 40+.
55 The QCAT Act s 28(3)(b). This is not a natural justice point, and the weight of the evidence was a
matter for the Member: R v Deputy Industrial Injuries Commissioner, ex parte Moore (supra) at 488
56 Submissions on appeal [173].
57 Submissions on appeal [186].
-- 17 of 68 --
18
reasonable diligence. Termination for use of unapproved sub-contractors was one of
the six Grounds in the Notice, not an independent ground.
[49] At one point the argument was advanced that proper, genuine and realistic
consideration had not been given to the six grounds in the notice either.58 For
example, it was said that the matters raised in Grounds 2, 3 and 6 in the Notice to
Show Cause had not been properly considered because the three grounds had been
considered together. I do not consider that there was any breach of natural justice
because the grounds were considered together; all three related to the issue of delay,
and there was a substantial overlap of the relevant factual matters.
[50] The submissions here also relied heavily on what were said to be errors of fact or
law, and it is convenient to deal with those as separate issues. But the fact that such
an error has been made does not in itself mean that there was a breach of natural
justice in failing to consider the case advanced, otherwise every error would turn
into a natural justice point. Natural justice is concerned with procedural fairness,
not with substantive correctness.
[51] Grounds 2 and 3 both related to delay, and were considered by the Member by
reference to extensions of time for the works, which had been granted, or which the
Member considered ought to have been granted. Extensions of time are directly
relevant to Ground 3, and they are also relevant to Ground 2, as shown by a decision
frequently relied on by the appellants in submissions, Dura.59 That decision was
also considered, and distinguished, by the Member. The fact that the Member did
not reach the conclusion sought by the appellants does not mean that he did not
consider the submissions relating to these grounds.
[52] The appellants complained that in his consideration of these Grounds the Member
ignored Ground 6, which relied on what was said to be a substantial breach of a
different provision of the contract. That is true, but it is clear from the appellants’
submissions in writing below in relation to this Ground that it was based on a failure
to adhere to the time for practical completion stated in the contract.60 Given the
Member’s conclusion as to the extent to which the time for completion had been and
ought to have been extended, this Ground necessarily fell away, and on that
approach it did not require further consideration.
[53] The appellants complained that the Member did not consider their argument that the
breaches identified in the Notice to Show Cause gave an entitlement to terminate at
common law, preserved by the terms of the contract. In reasons [114] the Member
referred to the appellants’ reliance on the approach in Sheppard’s case, and, after
considering whether there was repudiation by the builder, addressed a number of
additional defects relied on as having been discovered later. He then concluded at
[148] that all the grounds of termination did not, individually or collectively,
constitute a substantial breach that would give rise to a right of termination. That
finding dealt with both the argument that there was a right to terminate at law
because of the matters raised in the Notice to Show Cause, and termination based on
them and on the other matters raised by the appellants as defects discovered later.
58 Submissions on appeal [187].
59 At [426] and [430], as cited by the appellants at submissions at first instance paragraph 70(b).
60 Submissions at first instance [190] to [196], especially [193].
-- 18 of 68 --
19
So two of the grounds said not to have been addressed by the Member were in fact
considered.
[54] The Member certainly addressed the ground of repudiation, and the appellants’
criticism of this was based on the proposition that the Member did not address it the
way they wanted it addressed, that is, he arrived at the wrong conclusion on it. As to
the argument that repudiation was shown by the accumulation of defective work,
that was dealt with by the rejection of the proposition that that accumulation
amounted to a substantial breach entitling the appellants to rescind. If it was not
that, it necessarily did not amount to repudiation.
[55] As to termination for illegality, this was raised in submissions at first instance as a
further ground justifying termination, but was not in those submissions developed in
any coherent way.61 Reference was made to a complaint made by Mr Allen to the
respondent, and to a term of the contract that the builder comply with legal
requirements, said also to be implied by statute. The submissions proceeded on the
basis that there was no evidence from the respondent of any response to that
complaint, which was relied on as amounting to the acceptance by the respondent
that there had been such illegality, which is wrong.
[56] The submissions did not identify the legal requirements said to have been breached
by the builder, or the evidence that that had occurred, and did not even make clear
whether what was relied on was that this justified termination under the contract, or
that the effect of the statutory provisions relied on was that the further performance
of the contract was prohibited. Some indication of what was in issue was given in
the submissions by the respondent.62 None of the deficiencies in the appellants’
submissions were remedied in the submissions in reply.63 From the respondent’s
submissions, it emerges that many of these raised matters otherwise complained of
by the appellants, and dealt with in the reasons separately.
[57] It is not for the Tribunal, confronted with a bald allegation of illegality, to have to
dig around to identify some relevant legal provision and then consider whether there
was any evidence of breach of it, and if so, what the consequences were under the
relevant legislation.64 I suspect that some, perhaps a lot, of the legal requirements
said to have been breached were really requirements as to the state of the premises at
the completion of the project. It appears that one of the allegations related to the
failure to clamp or crimp a gas pipe where it was fitted to a particular fitting, dealt
with by the Member at reasons [128] – [132] on the basis that the work on the gas
system had not been completed and the gas not connected when the contract was
terminated. I expect that any regulatory requirement as to the state of the gas
reticulation system would refer to the system in its finished state, not when it is still
under construction.
[58] It is true that the Member did not deal specifically with termination for illegality. It
is difficult to see however what the Member could have usefully said, in view of the
submissions made. The appellants had not shown a proper basis for termination
61 Submissions at first instance [214] to [220].
62 Paragraphs [156] to [159].
63 Paragraphs [181] to [183].
64 Cf Smits v Cugola [2022] QCA 262 at [16].
-- 19 of 68 --
20
under a legislative provision, and in so far as matters said to be breaches of contract
anyway also breached the provision requiring the builder to comply with legal
requirements, it is not clear that it added anything to the argument based on the other
breach. The appellants’ submissions were framed as if any breach of Schedule 1B
clause 21, or special condition 7, gave a right to terminate. Plainly they did not;
apart from anything else, they were expressed as warranties, not conditions.
[59] I expect that the short answer to this complaint is that the appellants’ submissions on
illegality did not deserve to be dealt with. There is authority that there is no
obligation on a decision maker in giving reasons to deal with every point raised, so
long as the true basis for the decision is disclosed. If there was a technical breach of
natural justice here in relation to the illegality ground, it was clearly of no
consequence in the outcome of the proceedings before the Member.
[60] The remaining ground, said not to have been addressed, was termination on the
ground of breach of an implied term to proceed with due diligence. What was said
in the submissions65 was that if a failure to proceed with due expedition or a failure
to proceed without delay was established, then a failure to proceed with reasonable
diligence was also thereby established. This was tucked away in submissions in
support of the second ground relied on in the Notice to Show Cause, and it is by no
means clear from those submissions that it was being relied on as a separate ground.
If it was, then in terms it was relied on only if Ground 2 were made out; but it
follows from the reasons of the Member that Ground 2 was not made out. In those
circumstances, there was no need to deal with this ground. If an argument is
advanced conditionally and the condition is not met, it is unnecessary to deal with it.
[61] In submissions on appeal the appellants argued that this ground should have been
addressed because it was derived from an implied term in Schedule 1B s 25, and the
respondent is the regulator of that section: [198]. Although the proceeding was
between the appellants and the respondent, what was in issue was the state and
consequences of the contractual rights between the appellants and the builder. The
position of the builder under the contract has nothing to do with the status of the
respondent as regulator, nor has the obligations of the Tribunal in giving reasons.
[62] The appellants’ submission that there was a breach of the rules of natural justice has
therefore not been made out. It follows that Grounds 1 to 14 in the annexure to the
application for leave to appeal or appeal have been dealt with. The annexure then
listed a number of alleged errors of fact, followed by a number of alleged errors of
law. The appellants are entitled to appeal on a question of law, but require leave to
appeal on a question of fact, or of mixed law and fact, so it is convenient to deal first
with the alleged errors of law relied on.66
Questions of Law
[63] The grounds alleging errors of law start at number 58. The first two grounds simply
alleged that the Tribunal erred in failing to find that the appellants lawfully
terminated the building contract. That does not raise a question of law. In this
65 Submissions at first instance [71], [72].
66 The appellants submitted at the hearing that the question of leave to appeal should be decided before
considering the appeal on questions of law, and cited Edwards v Sovereign Homes (Qld) Pty Ltd
[2020] QCATA 146. In that appeal also questions of law were decided first: [29].
-- 20 of 68 --
21
broad form, these are at least questions of mixed fact and law. It is certainly not the
case that on the primary facts found by the Tribunal the only conclusion open as a
matter of law was that the appellants had lawfully terminated the contract.
[64] Ground 60 was that the Tribunal failed properly to consider the terms of the
contract, including those terms implied by Schedule 1B of the Act or adopted by
Special Condition 7 and Clause 11.1 of the contract. The Act in Schedule 1B Part 3
incorporates certain warranties into regulated contracts: Schedule 1B s 19. Special
Condition 7 provided to the same effect, I expect unnecessarily, while General
Conditions Clause 11.1 imposed a prima facie obligation to comply with all
legislative requirements. I am not sure that Clause 11.1 “adopted” terms of the
contract; it was a term of the contract, but any legislative requirement operated of its
own force. In any case, without identification of which term or terms the Tribunal
failed to have regard to, this Ground is too general to be meaningful. The
submissions on appeal provided no particulars. No error of law has been shown.
[65] Ground 61 was that the Tribunal erred in finding that it was a sufficient response to
a Notice to Show Cause under General Condition Clause 39 of the contract to
respond to the particulars in the Notice. This ground appears to have been based on
a sentence in the Reasons [59] which referred to the builder’s “response to the
particulars of the Notice.” Under Clause 39.3(c) the builder is required to show
cause in writing why the Principal should not exercise a right referred to in Clause
39.4, with that right arising if the builder “fails to show reasonable cause” in
accordance with that provision. Obviously cause can be shown in a variety of ways
depending on the nature of the complaints and what the builder in fact says in
response to them. Ground 1 of the Notice referred to three specific examples of
what was said to be defective work, and the Member addressed each separately.
[66] For example, as to the alleged defects in the plasterwork, which were said by the
Member to have been unparticularised, the plasterwork had been inspected by
specialists selected by the builder and by the architect, and been found to be
satisfactory save for some minor defects. That was the basis of the response about
the plasterwork, which the Member regarded as reasonable: [58]. The appellants in
submissions referred to a passage from Dura (supra) at [386], that the response need
not be in the form of rectification, but is primarily concerned with future
performance. In a matter where the existence of the breach is not in dispute I would
agree, but if the builder’s position was that a particular defect relied on was not
present, or was not his fault, there is no reason why that cannot be a reasonable
response, and be part of a process of showing reasonable cause, at least if it is true.
Whatever particular responses are made to particular matters relied on in a Notice to
Show Cause, the ultimate issue is whether reasonable cause has been shown not to
act under Clause 39.4. No error of law has been shown.
[67] In submissions from [221] the appellants sought to develop an argument that the
builder, in responding to a Notice to Show Cause, needed to respond to any existing
defect known to it, not just those identified in the notice. Dura was cited, but it is
not authority for that proposition, which is clearly wrong.67 The process of showing
67 See, for example, Vision Eye Institute Ltd v Kitchen [2014] QSC 260 at [240]; FPM Constructions
(infra) at [174].
-- 21 of 68 --
22
cause must respond to the particular matters in the notice, which must be in terms
sufficient to identify to the builder, in the prevailing circumstances, what cause has
to be shown.68 It need not, and cannot sensibly, respond to matters not properly
raised in the notice. In the present case, it seems to me that the particulars given
were inadequate in some respects, but that issue was not decided by the Member.
[68] In other submissions the appellants again raised the proposition that they were not
confined by the particulars in the Notice to Show Cause. I do not agree; the Notice
must clearly identify what is alleged to be a substantial breach, and the particulars
are to show what is relied on for that purpose. I do not accept that breaches of
contract discovered afterwards can be relied on by the appellants in this way.
[69] In the submissions Grounds 62, 64 and 113 were dealt with together. Grounds 64
and 113 are in substance the same; Ground 62 asserted that a wide range of matters
had not been considered, but I take it from the submissions that this Ground was
advanced to support the appellants’ argument that the effect of Clause 11.1 of the
insurance policy was that there was a right on the part of the appellants to terminate
the building contract for any breach of contract by the builder.69 The Member
quoted Clause 1.2 of the policy, which provided that the respondent was liable to
pay for incomplete work only if the insured, here the appellants, have “properly
terminated the contract with the contractor.” What “properly terminated” meant was
explained in Clause 11.1 as “lawfully under the contract or otherwise at law, upon
the contractor’s default which extends to, but is not limited to, (relevantly) any
breach of the contract by the contractor.” The appellants’ submission was that the
effect of these words was that they had a right to terminate the building contract for
any breach of contract by the builder, at least for the purposes of the Policy. In
effect, the contract could be “terminated” for the purposes of the policy even though
it was not terminated as between the owners and the builder.
[70] This proposition needs only to be stated to be rejected. The insurance policy,
although operating under a statute, was in effect a contract between the appellants
and the respondent. It contained a condition for the respondent’s liability which
depended on the termination of the contract between the builder and the appellants,
which had to be done “lawfully under the contract” – that is, the contract between
the appellants and the builder – “or otherwise at law”. A term in the insurance
contract cannot affect the extent or operation of termination rights under a different
contract, between the appellants and the builder. Obviously it takes whatever rights
exist under that contract for the insured to terminate, and makes it clear that it is
only when that contract has been lawfully terminated for default70 that such a
termination counts. Clause 11.1 does not create or modify any rights of termination
by the insured; it simply requires that a right of termination lawfully arising under
the contract or otherwise at law has been exercised. Whether such a right existed,
and was lawfully exercised, depends on the terms of the building contract, and the
general law of contract.
68 Yendex Pty Ltd v Prince Constructions Pty Ltd [1988] QSCFC 62 at p 2, 3. Clause 39 uses the word
“stated” rather than “specified”, but the reasons requiring the relevant breaches to be identified still
apply, and I consider that the meaning is much the same.
69 Emphasis in submissions [228].
70 No doubt that was inserted to prevent sweetheart deals between the insured and the builder exposing
the respondent to liability under the insurance policy.
-- 22 of 68 --
23
[71] The home warranty insurance scheme may be a mechanism for consumer protection
but it is obvious from its terms71 that it is quite limited in its scope. If there were
some relevant statutory ambiguity the objects and context of the Act and its
consumer protection nature would be relevant matters for consideration; I cannot see
how the National Construction Code, the Building Act 1975 (Qld) and regulations
under it would be relevant to that issue. But the relevant words lack any ambiguity.
The Member made no error of law in not giving effect to this submission.
[72] Ground 63 assumed that the incorrect interpretation of the policy advanced by the
appellants was correct, and asserted that the real issue was whether there had been
some hypothetical termination for any breach by the builder for the purposes of the
policy. For the reasons just given, there was no such error of law.
[73] Ground 65 in substance alleged an error of law in considering what the builder
would have done if the contract had not been terminated by the appellants. There
was no error of law involved in this; the passage from the decision in Dura (supra)
at [386] cited earlier by the appellants72 shows that, at least in some cases, future
performance by the builder is relevant. In the case of the door in the ensuite, for
example, there was no dispute that the door as installed was not in accordance with
the drawings, but the matter was resolved on the basis that the builder and the
architect were working out how best to rectify it.73 Even if the details of that had not
been finalised, that they were working this out suggests that the matter would have
been resolved if the contract had not been terminated. For the purposes of the claim
on the policy, what mattered was whether the building contract was lawfully
terminated as between the parties to it. It was very much a termination dispute, and
no error of law has been shown.
- Termination under Clause 39
[74] In the submissions Grounds 65, 66 and 67 were dealt with together, under the
heading of “Evidence regarding termination”. The submission was that the Member
had in effect allowed the builder to show cause in response to the notice twice, by
giving explanations in evidence which had not been advanced in the response to the
notice to show cause, and in applying an objective test to the question of whether the
builder had shown cause, rather than a subjective test. As to the latter point, the
appellants cited the decision in FPM Constructions v Council of the City of Blue
Mountains [2005] NSWCA 340 at [164], but that paragraph was about whether the
validity of a show cause notice alleging a particular substantial breach depended on
the objective existence of the substantial breach, or the subjective view (in good
faith) of the principal that there had been a substantial breach. What was said there
suggested that the latter was the favoured view, but the paragraph did not contain a
clear decision on what was the correct view.
[75] On the other hand, at [174] Bastan JA said: “The relevant legal issue depended,
however, solely on whether there had been a breach of contract justifying
termination by the Council or there had not. … I would not be satisfied that the
71 And from the decision of the Court of Appeal in Schneider v Queensland Building and Construction
Commission [2021] QCA 155, where the scheme is explained.
72 Appellants’ submissions [222].
73 I will discuss the door issue further later.
-- 23 of 68 --
24
contract was terminated for any reason going beyond the matters identified in the
show cause notice … .” That looks as though his Honour was applying an objective
test to the existence of grounds to terminate, and that the grounds for termination
under the relevant clause in the contract were confined to the issues raised in the
notice to show cause. His Honour pointed out that once an entitlement to terminate
existed, there was no basis to challenge the exercise by the Council of the discretion
to terminate.
[76] In Dura (supra) at [566] Dixon J did appear to apply a subjective test to the question
of whether the contractor had shown reasonable cause, describing the issue as
whether the principal had decided that reasonable cause had not been shown
honestly and in good faith. Little explanation for the use of a subjective test at this
point was given by his Honour, although reference was made to Clause 44.4 (the
relevant clause) at [564] that “in order to act under [it] the principal must first be
satisfied that the contractor has failed to show reasonable cause.” The wording of
the clause was not quoted there, and I have not been able to find it elsewhere in the
reasons. At [566] he also said that the power to act under the clause fell within the
second category in “Tote Tasmania”. That was apparently a reference to the
decision of the Full Court in Tote Tasmania Pty Ltd v Garrott [2008] TASSC 86
where the Court at [17] referred to different categories of case in the context of
implying a requirement that a power be exercised in good faith. That was in a
context where a clause in a contract made satisfaction of a condition precedent
dependent on whether something was “acceptable to” one party.
[77] There can be a termination clause where the right to terminate depends on the
opinion of the party giving a notice to show cause as to the reasonableness of the
response to it, and I can only assume that Clause 44.4 considered in Dura was one of
them. Clause 39.4 is not. I consider that on the face of it Clause 39.4 of the General
Conditions of contract, by making the existence of the power of the principal
(relevantly) to terminate the contract dependent on a failure to show reasonable
cause in a timely way, imposes an objective test. If the issue is whether one party
has validly terminated a contract under the general law, the existence of
circumstances entitling that party to terminate is always determined objectively.74 If
the intention had been to provide a different test under this contract, I would expect
it to provide that the power to terminate arose if “in the opinion of the principal” the
contractor had failed to show reasonable cause, or something to that effect. I am not
persuaded that the appellants have shown that the application of an objective test
involved an error of law by the Member.
[78] Grounds 76 to 78 alleged error in imposing on the appellants an obligation to act
reasonably in considering whether the builder had shown cause. There is authority
supporting that approach, in particular decisions of the NSW Court of Appeal;75
those and other decisions were discussed by Jackson J in Aurizon Network Pty Ltd v
74 See for example Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623 at
657-8 per Deane and Dawson JJ, re repudiation.
75 See for example Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR
234 at 263, 279. See also Bundanoon Sandstone Pty Ltd v Cenric Group Pty Ltd [2019] NSWCA 87
at [154] – [160], a decision too recent to be considered in Aurizon v Glencore (supra). As to Renard
Constructions, see also QNI Resources Pty Ltd v North Queensland Pipeline No 1 Pty Ltd [2022]
QCA 169 at [120].
-- 24 of 68 --
25
Glencore Coal Queensland Pty Ltd [2019] QSC 163 at [227] – [240], in a discussion
focused on whether there was an implied term of good faith and fair dealing.76 This
issue arises only if the true interpretation of the contract is that the question of
reasonableness is one for the appellants, that is, the test is subjective. In my opinion,
under this contract the test for whether the builder had shown reasonable cause is
objective, and a matter for the Tribunal, and as I interpret the reasons of the
Member, that was also his approach. On that approach the issues in these grounds
do not arise. If a different view is taken elsewhere, that question of law can be
decided at that point.
[79] As to the complaint that the Member acted on evidence which went beyond the
material in the response to the Notice to Show Cause when determining if the
response was reasonable, my reading of the reasons indicated that in each respect the
Member referred to the content of the response when assessing its reasonableness,
although he did have regard to the situation of the works generally at that time, and
other matters which would have been known to both parties at the time, when
assessing the matters to be determined. No error of law has been shown in this
respect.
[80] Ground 68 alleged that the Member erred in law in failing to “admit” evidence of
further breaches or particulars after termination to establish the degree of the alleged
breach in the notice to show cause. In submissions this was developed as failing to
act on evidence from Mr Allen and the appellants’ expert to prove the breaches
alleged in the Notice to Show Cause. Although the submissions do not link this
complaint to any finding on the part of the Member, this may be a reference to the
statement in reasons at [59] that defects in the plasterwork discovered later were not
relevant to the builder’s response to the particulars in the notice to show cause. The
Notice to Show Cause, in the particulars of the first breach relied on, said of the
plasterwork only that it was “the subject of defects and does not in all respects meet
the standards of work under the contract.” That in my opinion does not amount to
proper particulars, but there had been an issue between the parties as to whether the
plastering had been done properly, and the supervisor had issued a defect notice
about the plastering. That led to an inspection by two specialists who concluded
that, save for some minor defects, the plasterboard had been fixed in accordance
with the manufacturer’s specifications: reasons [56]. The Member concluded that in
these circumstances, a response relying on that report was reasonable.
[81] It is difficult to see how the builder could have been expected to respond to any
other complaints about the plastering when notice of them had not been given by the
appellants.77 The response to the Notice to Show Cause can only respond to matters
raised by the notice, which must be understood by reference to the common
understanding of the parties as at the date it was given. It is one thing to say that the
appellants were entitled to gather evidence after termination to prove allegations of
substantial breach identified in the Notice to Show Cause. It is a different matter to
say that the appellants were entitled to rely, for the purposes of termination under
76 On appeal the Court upheld the judgment but on a different basis: [2020] QCA 182. McMurdo JA,
with whom the other members of the Court agreed, described the discussion of the authorities by
Jackson J as “illuminating” – [125] – but said that it was not necessary to express a concluded view
on this issue, although he had some difficulty with the finding of breach of any implied term: [135].
77 See Dura (supra) at [396], and decisions cited earlier on this point.
-- 25 of 68 --
26
Clause 39, on matters not specified in the Notice to Show Cause in order to show an
absence of a reasonable response by the builder. The passage referred to earlier
from the judgment in FPM Constructions shows that the question of termination
under the contract has to be decided by reference to the matters in the Notice to
Show Cause. His Honour rejected suggestions in the judgment at first instance that
the approach in Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR 359
could be applied to such a process of termination. I respectfully agree, and consider
it clear that it cannot.
[82] In Shepherd Dixon J spoke of a right in a party terminating a contract for breach to
rely on a breach of condition which existed but of which the party was unaware at
the time: p 377-8. A breach of condition is a breach entitling the other party to
terminate, but clause 39 does not make the right to terminate under that clause
dependent on a breach of contract alone, but upon the failure of the builder to show
reasonable cause in response to a notice to show cause. If the principal purported to
terminate under Clause 39 and there was then a separate breach of condition
entitling the principal to terminate at common law, the approach in Shepherd would
apply, but Shepherd does not entitle the principal to add to the matters raised in the
Notice to Show Cause for the purpose of supporting termination under Clause 39. I
am not persuaded that the Member made an error of law in the approach adopted in
[59]. In no other particular was the issue of extra defects discovered later relevant.
[83] Ground 69 alleged error in finding that the appellants contended that defective
building work was the only ground justifying termination at common law, whereas
the appellants submitted many other grounds justifying termination at common law.
That is difficult to reconcile with the reasons [113], and at [148] the Member said
that he had considered all the grounds for termination put forward by the appellants.
The Member also dealt specifically with the appellants’ submissions that there was a
right to terminate for repudiation. I have already said something about the grounds
advanced at the hearing to justify termination. This ground did not identify and
establish any error of law on the part of the Member.
[84] Ground 70 alleged that the Member erred in law in construing Clause 39 as
requiring a “two stage test”, requiring the appellants to prove that agreed substantial
breaches were really substantial, contrary to authority.78 The submissions referred
to the reasons [38], where the Member, after citing passages from Dura (supra) at
[447] and Stojanovski (supra) at [55] said that it was against these criteria that the
Tribunal will determined whether the breaches alleged by the appellants in the
notice “are substantial and give rise to an entitlement to terminate under Clause 39.”
I do not read this as posing a two stage test, rather as saying that, if a breach is
substantial, it will give rise to a right to terminate. In Dura at [440] Dixon J said
that a two stage approach was appropriate to determine if there was a substantial
breach of a requirement to proceed with due expedition and without delay: “First,
has a failure to proceed with the work with due expedition and without delay been
shown? And if so, second, does it constitute a substantial breach?” What his Honour
said is consistent with the proposition that the second stage of the two stage test
might be answered, in an appropriate case, by saying that it was a substantial breach
78 Relying on Dura (supra), FPM Constructions (supra), and Stojanovski v Australian Dream Homes
[2015] VSC 484.
-- 26 of 68 --
27
by definition. If the Member had posed a two stage test, it would not have been
inconsistent with this authority.
[85] The submissions also referred to the reasons [36] where the Member said “An
example of what might be a substantial breach is set out in Clause 39 itself but that
is not exhaustive.” The appellants’ point is that Clause 39.2 identifies a list of things
which are, rather than “might be” substantial breaches. This strikes me as an
example of the kind of overly pedantic analysis of the wording of the reasons of a
tribunal which has often been criticised by courts in the past.79
[86] In submissions at [257] the appellants quote a statement from Dura (supra) at [447]:
“The requirement for a substantial breach is not that high” as though this proposition
stood alone. His Honour was there commenting on a passage from Mazelow Pty Ltd
v Herberton Shire Council [2003] 1 Qd R 174 at 182, where McPherson JA
distinguished between the acts or omissions covered by a definition of “substantial
breach” and repudiatory conduct. The point of the comment was that the
requirement for a substantial breach was not as high as the requirement for conduct
showing repudiation of the contract. The passage quoted by the Member from
Stojanovski (supra) at [37] ended with the proposition that it is preferable to apply
the language chosen by the parties, which is clearly right. In cases which were not
substantial breaches by definition, the question is, was the breach substantial, and
that is the test the Member applied. He made no error of law in doing so.
[87] Clause 39.2 of the General Conditions lists eight things which are included in the
concept “substantial breaches”, although the concept is not limited to them. Most
are things which have either happened or not happened, and some incorporate
qualifiers, such as the requirement in (c) “substantial departure from a construction
programme…”.80 Paragraph (a)(iv), “failing to use the materials or standards of
work required by the contract” is curious, in that it is not difficult to imagine a case
where there would be such a failure of a trivial nature, depending on the width of
meaning attributed to the terms “materials” and “standards of work”. I suppose if a
trivial failure to use the materials or standards of work required by the contract is
notified, it will be easy enough for the builder to show reasonable cause (at least on
an objective test), but this part of Clause 39.2 still strikes me as odd.
[88] This issue however is not determinative of the outcome. In respect of the grounds in
the Notice to Show Cause, the only finding of the Member relevant to this ground of
appeal was the alternative finding in relation to the defective window in the ensuite.
The Member found at [70] that the response of the builder in relation to this was
reasonable, and then said that it did not amount to a substantial breach of the
contract. If this was a failure to use the materials or standards of work required by
the contract, and if clause (a)(iv) means that any such failure was substantial, that
was an error. However, because it was an alternative basis for rejecting the
appellants’ case on this point, it was not determinative of the outcome, and not a
ground to allow the appeal.
79 See for example Collector of Customs v Pozzolanic Enterprises Pty Ltd (1993) 43 FCR 280 at 287;
Cypressvale Pty Ltd v Retail Shop Leases Tribunal [1996] 2 Qd R 462 at 485; Ergon Energy
Corporation Ltd v Rice-McDonald [2009] QSC 213 at [11] – [17].
80 So a departure is a substantial breach by definition if it is substantial. This document must have been
drafted by a committee.
-- 27 of 68 --
28
[89] Ground 71 was that the Tribunal erred in establishing the wrong test as to the
requirement to show cause as established in Dura (supra). I do not consider that
Dura establishes any specific test for the requirement to show cause, and comments
there about how cause could be shown need to be read in the light of the
circumstances of that case. I do not consider that the only way a builder can show
cause, in a case where there really is a defect, is to admit that there is a defect and
say it has been (or will be) fixed, although obviously that would be one way. The
test is whether the cause shown is reasonable, about which I have had something to
say already. This ground is not made out.
- Extension of Time, due expedition and delay
[90] Grounds 72, 73, 74, 75, 84, 98, 100, 101, 102 103 and 110 were dealt with together
in submissions, under the heading “Extensions of Time”.81 These covered a number
of arguments about the approach of the Member to questions of extensions of time
under the contract, all of which approach the question of assessing claims for
extensions of time strictly in accordance with the contract provisions governing such
extensions for the purpose of changing the date for practical completion under the
contract. The appellants relied in particular on certain statements in Dura (supra).
The difficulty with these submissions is that the issue was not one of what
extensions of time the builder was entitled to under the contract in the
circumstances. The issues were whether the builder had failed to proceed with due
expedition and without delay, and whether the builder had shown reasonable cause.
[91] In Hometeam Constructions Pty Ltd v McCauley [2005] NSWCA 303 the Court had
to consider whether the principal was entitled to terminate for breach by the builder
of a requirement to proceed with the works with due diligence. The Court stated a
number of propositions relevant to that issue:
(a) The onus of proving the builder was in substantial breach of the contract was
on the principal: [166].
(b) The meaning of a contractual requirement to proceed with “due diligence” was
not clear [170] which makes the task of showing a breach more difficult:
[172].
(c) Whether a contractor is proceeding with due diligence is a question of fact:
[176].
(d) It was relevant to consider what was a reasonable time, in all the
circumstances, and to the extent that the builder had failed to do the work in
that time, whether the explanations for the failure were acceptable: [179].
(e) A lack of due diligence can be shown by reference to a lack of activity on site
over a significant period that could not be satisfactorily explained: [181].
(f) A failure to seek a formal extension of time cannot be determinative of
whether the works were performed with due diligence: [194].
(g) If there had been a breach of the contractual obligation, the builder could
remedy it, by working diligently before the termination of the contract: [279].
81 There were also further submissions later in support of ground 100.
-- 28 of 68 --
29
[92] As far as I am aware, that decision remains authoritative. It was cited recently for
the proposition that a reasonable time means a reasonable time under the
circumstances.82 It was cited in submissions in DCT Projects Pty Ltd v Champion
Homes Sales Pty Ltd [2016] NSWCA 117, a decision about repudiation. I am also
aware of the decision in Torbey Investments Corporated Pty Ltd v Ferrara [2017]
NSWCA 9, where the Court adopted a flexible construction of Clause 33 of a
contract dealing (in different terms) with termination so as to give effect to its
commercial purpose: [34].83
[93] In my opinion the concept of due diligence is similar to the concept of due
expedition and without delay, or at least sufficiently similar for the propositions
stated by the Court in Hometeam to be applicable. They show that what is due
expedition is to be determined in the context of the work required to be carried out
under the contract, and the time allowed under the contract for the work, which can
be adjusted under the contract for various reasons. If the proprietor relies on a
comparison of the time allowed to practical completion under the contract with the
amount of work done to prove lack of due expedition and delay, it becomes relevant
to consider, firstly, to what extent the terms of the contract allow any extension of
that time, and to what extent the builder ought to be allowed an extension of time,
even if the relevant extension of time has not been allowed under the contract, for
one reason or another (as well as whether there was in practical terms a reasonable
explanation for the delay). If it was relevant for the Court in Hometeam to take into
account a potential extension of time which had not even been applied for, it must
have been appropriate for the Member in this case to take into account extensions of
time which had been applied for, whether or not rejected, if he considered them to be
reasonable.
[94] In later submissions, the appellants said that the Member erred in not taking into
account delay which had been the subject of applications for extension of time
which had been agreed to at the time, on the basis that it was delay throughout the
project which was relevant to this issue, relying on Hometeam. Certainly delay
throughout the project can be relevant, but, where there has been an extension of
time agreed to, I consider that the delay the subject of that extension does not count
as “delay” for the purposes of Clause 39, or show a want of due diligence on the part
of the builder. That was the approach of the Member, and I consider that there was
no error of law in his doing so. Indeed, I consider that it would have been an error
of law if he had approached the question in the way outlined in the appellants’
submissions.
[95] I consider that “due expedition” means such expedition as it is reasonable for the
builder to have exercised in all the circumstances. That was essentially the approach
in Hometeam, and I consider it was the practical approach adopted by the Member.
The relevant issue did not depend on whether the technical requirements for an
extension of time had been complied with, but whether in the circumstances the time
taken was or was not consistent with due expedition on the part of the builder. If
under the general conditions of the contract the builder was reasonably entitled to an
82 Armada Balnaves Pty Ltd v Woodside Energy Julimar Pty Ltd [2022] WASCA 69 at [552].
83 See also Tullock Brae Pty Ltd v Environmental Protection Equipment Pty Ltd [2021] QSC 213 at
[15], for authorities on giving a commercial construction to ambiguous terms in a contract.
-- 29 of 68 --
30
extension of time, I do not consider that the appellants can put the builder in breach
of this clause by exercising their power to refuse to agree to that extension.84 To
allow that would I consider be to adopt an interpretation of this contract which was
not reasonable or commercial.
[96] It is convenient at this point to interpolate a reference to Ground 92, which asserted
that the fact that the Member found that only 70% of the work required to be done
under the contract had been completed at the time of termination meant that, as a
matter of law, the Member was bound to find that there had been a failure to proceed
with due expedition and without delay. It is sufficient to say that I consider that the
propositions stated in Hometeam are inconsistent with such an approach, and that
the proposition advanced in this ground is wrong. It all depends on the
circumstances.
[97] The question of what is meant by delay in clause 39.2(d) involves some ambiguity.
There are several possible meanings, ranging from any delay at all, through delay
which involves a breach of contract by the builder, to unreasonable delay which is
the fault of the builder. The appellants in submissions appeared to approach the
matter as if any delay was enough to trigger this provision, and was a substantial
breach by definition. Such a construction does not have regard to the provisions of
the contract as a whole.
[98] The term “delay” is not defined in the contract. Clause 34 deals with Time and
Progress. Clause 34.2 requires notice to the Superintendent of anything which will
probably cause delay. Clause 34.3 says that “the contractor shall be entitled to such
extension of time for carrying out” the works as the Superintendent assesses, if the
delay in reaching practical completion is due to a qualifying cause of delay, and the
contractor gives a written claim for an extension of time. Clause 34.4 provides that,
in assessing such a claim, the Superintendent shall disregard whether the contractor
can nevertheless reach practical completion without an extension of time, or whether
the contractor can accelerate the work, a provision which is inconsistent with some
of the appellants’ submissions.
[99] The term “qualifying cause of delay” is defined as any act, default or omission of the
Superintendent, the Principal or its consultants, agents or other contractors not
employed by the builder, or “other than (i) a breach or omission by the contractor;
(ii) industrial conditions or inclement weather occurring after the date for practical
completion; and (iii) stated in Item 23.” Presumably this means “a cause of delay
other than” as stated. Item 23 assumed that there was an allowance of ten days for
delay due to inclement weather built into the contractual date for practical
completion, and excluded an extension of time for this until the ten days had been
exhausted. It would be inconsistent with the provisions under which the builder is
“entitled” to an extension of time under the contract, and with the notion that ten
days delay is to be built into the time for completion, for any delay to give rise to an
entitlement to the appellants to terminate for substantial breach.
84 That power is implied by the Act Schedule 1B s 42. I have difficulty in accepting that this section
means that the owner has an unfettered discretion to refuse to agree to a reasonable request for an
extension of time in accordance with the contract, in the light of the objects of the Act.
-- 30 of 68 --
31
[100] Further, “delay” in Clause 39 must take some colour from the fact that it is part of a
definition of “substantial breach”, and from the other parts of that definition. In
order to give a practical, commercial interpretation of the contract which fits in with
the other parts dealing with delay, it must mean unreasonable delay on the part of
the builder. Such an approach is consistent with the authorities on similar terms
concerning due diligence.
[101] In these circumstances the technical requirements for an extension of time are not
relevant to the question of whether there has been a substantial breach under clause
39. It follows that the submissions of the appellants in relation to these grounds of
appeal were not directed to the relevant issues, and the grounds are not made out.
[102] Grounds 89, 90 and 94 were dealt with together in submissions, and relate to Ground
2 in the Notice to show cause. The first, that this Ground was not dealt with by the
Member, has already been dealt with in substance as it was relied on as part of the
breach of natural justice submissions.85 The Member did deal with it. Ground 90,
alleging that the Member applied the wrong test for failing to proceed with due
expedition and without delay, I have just dealt with. The submissions of the
appellants appear to be based on the proposition that it was sufficient for them to
show any delay, by reference to the original date for completion under the contract.
I do not agree with that approach, which is inconsistent with Hometeam (supra), as
explained. That decision shows that extensions of time which have been or ought to
have been granted are relevant when assessing this, which was the approach of the
Member.
[103] Ground 94 was that the Member erred in finding that delay by the appellants
relieved the builder of any breach of this provision. I do not consider that the
Member approached the matter in that way. I do consider however that in principle
any delay by the appellants which had the effect of causing delay for the builder
would be relevant in determining whether there had been unreasonable delay on the
part of the builder. Grounds 89, 90 and 94 are not made out.
[104] Ground 84 was that the Member erred in taking into account an extension of time
which had not been agreed to by the appellants, as required by the Act schedule 1B s
42, and special condition 10.3. I have already said something about this. The
argument is inconsistent with the reasoning in Hometeam (supra). Whether there
was a failure to proceed with due diligence or delay does not depend on whether an
extension of time has actually been granted under the contract, but on whether the
circumstances leading to the application for the extension provided a justification or
excuse for any delay.
[105] Appeal Grounds 111 and 112 were also concerned with the technical working of the
contract provisions for extensions of time. In view of the approach adopted by the
Member, which I consider to have been correct, these grounds are also beside the
point.
- Defective Work
[106] Grounds 79 and 80, which were addressed together in submissions, concerned the
approach of the Member to Ground 1 in the notice to show cause, concerning defects
85 Supra [49] – [51].
-- 31 of 68 --
32
in the work. The first submission was that the appellants were not confined to the
particulars given in the notice to show cause. I do not agree; it is clear from the
authorities discussed already, and from the terms of the contract, that, in relation to
the show cause procedure, the appellants are confined to the terms of the notice,
both as to grounds and as to particulars.
[107] The approach of the Member to the issue of the ensuite door was that the builder
was working on a solution with the architects, and in those circumstances there had
been a reasonable response, that the issue was being attended to. In evidence the
builder explained that the contract specified commercial sections for this window,
which included a glass door, and that the effect of using commercial sections was
that the door ended up much narrower than as shown on the plan. A detail drawing
had been provided later, which required something to be done86 but which in the
response the builder claimed was a variation.87 The builder said in evidence that at
the time they were working with the architects to solve the problem of the door.
That was not expressed very clearly in the response to the notice,88 but that response
did refer to the instructions from the architect, and implied that work would be done
in response to that notice, although the builder was in effect reserving its rights in
respect of a variation claim. The question of whether the builder has shown
reasonable cause must be decided by reference to the situation as at the date of
termination of the contract; it would not help the builder to be reasonable, or more
reasonable, later. Nevertheless, I consider that it was open to the Member to accept
that this was a reasonable response. No error of law has been shown.
[108] One issue which appears to have been glossed over however is whether building the
door too narrow amounted to a failure to use the materials and standard of work
required by the contract. The problem with this installation was not that the wrong
materials were used, or that it was not constructed to the required standard;89 it was
that the dimensions were wrong. Clause 39.2(a)(iv) was not intended to cover any
defect in the works, because that was covered by Clause 39.2(a)(iii), although by
reference to a failure to comply with a direction of the Superintendent under Clause
29.3. That clause covers work not in accordance with the contract, and requires
notice from the Superintendent, and if the matter is not rectified, a direction from the
Superintendent. It seems to me that this part of Ground 1 did not fall within Clause
39.2(a)(iv) at all, but that point does not seem to have been raised before the
Member, and no finding was made on it. It was raised in appeal ground 79, and I
suspect it was an error of law, involving the construction of the contract, but if so, it
was an error in favour of the appellants, and they cannot complain about it.
[109] Ground 80 was that the Member erred in treating the potential remedy of defects
after the Notice to Show Cause was given or after practical completion as an answer
to Ground 1 in the Notice to Show Cause. That the former could be a sufficient
86 Appeal Book Vol 7 p 2075, an email from the architects to the builder on 17 November 2017.
87 The appellants characterized this as a refusal to fix the door unless additional payment was made,
Read carefully, it was not that, but a claim that there was an entitlement to additional payment as a
variation, which depended on an agreement that it was a variation, or such a finding on dispute
resolution.
88 See Appeal Book Vol 1 p 944.
89 The expert witness called by the appellants said that there was nothing wrong with the workmanship,
and no breach of the National Construction Code: Day 3 p 37.
-- 32 of 68 --
33
answer was shown by the decision in Dura (supra), where it was said that cause
could be shown by admitting the defect and agreeing to remedy it. In the present
case, the builder denied there were defects but said that, if there were, they were
minor or would be remedied by it in the completion of the work. The contract does
provide for a period after completion during which the builder is to rectify any
defects: Clause 35, which contemplates the existence of defects at the date of
practical completion. I do not accept that the way in which a builder can show
reasonable cause in response to the notice is confined in the way alleged by the
appellants.
[110] Ground 81 was grouped in submissions with grounds 121 to 128, 130 and 136, dealt
with under the heading “Temporary Disconformity”. I do not think that the Member
ever used the term “temporary disconformity” in his reasons, but the appellants’
argument was that, if something has been done incorrectly, it amounted to a breach
of contract even if it might well be rectified by the builder in the course of
completing the works, or during the defect liability period. That is correct, although
rectification is relevant to the issues of whether a breach is substantial, and whether
the response to the notice was reasonable, but it is not the full story. There is a
difference between something which has been done incorrectly and something
which has not been done yet.90 Plumbing and electrical work for example are
commonly “roughed in” at one stage in the process, and are then finished off at a
later stage. In that situation, the fact that the roughing in has been done without also
finishing off does not mean that there has been any breach of the contract.
[111] That was of some relevance in this matter, as one issue raised by the appellants was
a failure to crimp the end of a gas pipe, which was found not to be a defect on the
bases that the gas installation had not yet been finished off, and that the crimping
would be done in connection with that. There was some conflict of evidence on this,
but on the evidence the Member accepted, that was the situation.91 It followed that
there was no breach in failing to crimp the gas pipe. Other defects were dealt with
however on the basis that there was at the relevant time no defect covered by the
Notice (in the case of the plasterwork), or that the response of the builder was
reasonable, as the builder was rectifying, or was going to rectify, the defect relied
on. That was the relevant issue for the purposes of termination under Clause 39.
[112] When considering the issue of repudiation, it is relevant to consider the attitude of
the builder at the time of the alleged repudiatory conduct, so the builder’s attitude to
breaches of the contract which have been raised with it is relevant in showing
whether or not the builder is repudiating. A breach of contract which the builder
indicates a willingness to rectify would ordinarily not support an allegation of
repudiation, and the existence of breaches of contract which have not been drawn to
the attention of the builder would support one only if they were so numerous and
substantial as to amount to repudiation in themselves. The presence in the contract
of clause 29 is relevant here. As to whether a breach was a sufficiently serious
breach of a non-essential term to give a right to terminate, the contract contemplates
90 This was the approach in Mousa v Vukobratich Enterprises Pty Ltd [2019] QSC 49, discussed below,
where some matters were regarded as not defects if they could have been examples of incomplete
work.
91 I discuss this matter and the evidence later.
-- 33 of 68 --
34
that the benefit to the owners will accrue at the end of the construction process. It
follows that it will be more difficult to show that a breach of a non-essential term is
sufficiently serious to justify termination of the contract if the builder has the
opportunity, during the balance of the construction work, to rectify the breach.
[113] A breach of contract may give a right to terminate under the contract, depending on
the nature of the breach and what happens when the procedure in the contract is
followed,92 and will give a right to terminate if the breach is of a condition. The
tests for repudiation and termination for a sufficiently serious breach of a non-
essential term are more complicated. That a defect which is a breach of contract may
be able to be described as a “temporary disconformity” will, depending on the
circumstances, not necessarily be irrelevant to the question of whether there is a
right to terminate. These grounds are not made out.
[114] Grounds 82 and 83 were grouped in submissions with grounds 120, 134 and 135,
under the heading “Defects at Law”. The point was that the Member had failed to
appreciate the true legal significance of defects in the work, although to some extent
these submissions have already been dealt with. Ground 82 complained of a failure
to consider the requirements of the contract, Schedule 1B of the Act, the National
Construction Code, the Building Act 1975(Qld) and the common law in relation to
defects. This appeared to be based on the appellants’ argument that the effect of the
Act was to give a right to terminate for any defect in the work, which I have already
rejected.
[115] The argument was also presented on the basis that the appellants wanted a strict and
precise compliance in all respects with the contract, including the plans and
specifications, so that any such defect was a breach of an essential term. This is
related to Ground 117, that, in determining whether certain terms of the contract
were conditions (or essential terms), the Member had failed to apply the test in
“Tramways”, presumably that expressed by Jordan CJ in Tramways Advertising Pty
Ltd v Luna Park (NSW) Ltd (1938) 38 SR (NSW) 632 at 641-2:93
The test of essentiality is whether it appears from the general nature of the
contract considered as a whole, or from some particular term or terms, that the
promise is of such importance to the promisee that he would not have entered
into the contract unless he had been assured of a strict or a substantial
performance of the promise, as the case may be, and that this ought to have
been apparent to the promisor.
[116] It is immediately apparent from its terms that the test focuses on the terms of the
contract, and what can be inferred about the attitudes of the parties from them. That
was confirmed by the judgment of Stephen, Mason and Jacobs JJ in DTR Nominees
Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423 at 431:
The quality of essentially depends … on a judgment which is made of the
general nature of the contract and its particular provisions, a judgment which
takes close account of the importance which the parties have attached to the
92 The decisions cited by the appellants were both concerned with termination under the contract.
93 This decision was reversed on other grounds by the High Court but the test has been subsequently
endorsed by that Court.
-- 34 of 68 --
35
provisions evidence by the contract as applied to the surrounding
circumstances.
[117] On the basis of this test, the various terms relied on by the appellants have not been
shown to be essential. This is because there is nothing in the contract which shows
that the parties have attributed particular significance to any particular term or terms
of the contract, apart from Clause 39, which contains its own mechanism for
termination. What provisions of a contract are essential so that any breach of them
gives rise to a right in the other party to terminate depends on the terms of the
contract, not the assertion of subjective attitudes of one party to the contract. Often
the contract will identify particular terms as essential, but if it does not, the matter is
one for construction in the light of the terms of the contract as a whole. In the case
of this contract, it may be noted that:
(a) There is a specific mechanism in Clause 39 giving a right to terminate, which
is dependent on giving a notice to show cause to the builder, and contemplates
that the builder may show reasonable cause in response.
(b) There is a provision in Clause 29.3 dealing with defects, providing for the
superintendent to give the builder notice of a defect, and (assuming the defect
is not remedied) allowing the superintendent to give a direction for the defect
to be remedied, with consequences under Clause 39 to follow if it is not
remedied.
(c) There is a defects liability period, with provisions for the builder to remedy
defects of which notice is given.
[118] If the presence of any defect in the work gave the appellants an immediate right to
terminate the contract, all these terms would be unnecessary. In those
circumstances, it seems to me that the argument of the appellants on this point
cannot be right. I do not consider that there is any substance to grounds 82 or 83. It
also follows that the Member has not been shown to have erred in failing to apply
the Tramways test, as alleged in ground 117.
[119] Ground 120 alleged that there was an error of law in failing to consider all of the
defects raised by the appellants, including the evidence of the appellants’ expert in
relation to them. There was no obligation on the Member to refer to all of the
evidence led, or to deal with all the submissions of the appellants, so long as the
reasons for his decision were clear enough.94 To overlook critical evidence is an
error of law,95 but to advance such a ground the appellants need to identify specific
evidence overlooked, and why it was critical. That was not done in relation to
Ground 120. I have already said something about the evidence of the appellants’
expert witness.
[120] In submissions to the Member, the appellants did not identify the defects relied on,
simply relying in general terms on all the defects in the work.96 Certain specific
94 Torbey Investments Corporated Pty Ltd v Ferrara [2017] NSWCA 9 at [66]; Built Qld Pty Ltd v
Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2022] QCA 266 at [103], [104].
95 Ibid, at [68].
96 See also Allen Day 1 p 94. The only defects the existence of which was supported by expert
evidence were those nine covered by the reports of the appellants’ expert witness.
-- 35 of 68 --
36
defects, apart from those identified in the Notice to Show Cause, were identified in
the respondent’s submissions to the Member, and the appellants replied to these
submissions. These were the main defects which were in fact litigated at the
hearing. The appellants had included in their material lists of defects which were
very long. I have looked at part of one of them, and it included many items which
were, or could have been, properly classified as uncompleted work rather than
defects, and many defects which were quite trivial, and could not be relevant to
termination at common law.97 It was a matter for the appellants to identify what
their case was for termination at common law, which involved at least identifying a
list of defects of some significance. This ground is not made out.
[121] Grounds 134 and 135 also appear to be based on the incorrect proposition that any
breach entitled the appellants to terminate. It is true that the term “substantial
breach” is given a defined meaning and particular significance under Clause 39 of
the contract, and for that reason it might have been better, when discussing
termination at common law, for the Member to have used different terminology, but
in substance he applied the correct test for termination at common law, which is
what matters. These grounds are not made out.
[122] Ground 85 was that the Member erred in failing to follow sufficiently the decision in
Dura (supra), presumably by not coming to the same result as was reached in that
case. The Member did have regard to it, and did cite some passages from it, as have
I, but thought it was distinguishable on the facts, for reasons he gave. Whether there
was an error of law in the reasons of the Member depends on whether some
proposition he stated was wrong in law, or whether his analysis was such that an
error of law was demonstrated. That is not shown simply by arguing that the
Member did not follow a particular earlier decision closely enough.
[123] The factual basis for the distinction drawn by the Member was the reasonable
expectation by the builder in Dura of steps to terminate on the part of the owners
prior to the notice to show cause being given. Obviously in the present case when
the Notice to Show Cause was given, the builder could reasonable anticipate at least
a threat of termination. I think the Member’s real basis for the distinction was that
in Dura there had been a long period of acrimony between the parties, possibly
aggravated by the fact that it was a case of friends who had fallen out, before notices
to show cause issued, whereas here the relationship between the parties had been
fairly cordial, or at least a functioning working relationship, before the Notice to
Show Cause was issued: Reasons [28].98
[124] Ground 86 was that the Member had erred in applying a proposition of law on the
basis of Dura (supra) which was not stated in Dura. It is true that the proposition
stated at reasons [32], for which Dura at [525] – [537] was cited, does not appear in
terms in Dura; but the proposition stated was a description of some of the things
Dixon J discussed, and presumably took into account as relevant, in that part of the
97 See also the evidence of the builder, Day 2 p 11: the majority of the “defects” on the appellants’ list
were uncompleted work.
98 It appears that things began to go bad after Mr Allen read a decision in another matter involving the
builder, but it took some time before this was manifested to the builder: Affidavit of Allen sworn 3
September 2018 paras 83, 84, Appeal Book Vol 4 p 1160. See also Allen Day 1 p 52: By 13 July
2017 he considered that he may need to terminate.
-- 36 of 68 --
37
judgment. In submissions the appellants referred to something said in Dura at [522]
about the need for a communication between the parties in response to a notice to
show cause, so that reasonable cause would not be shown by rectifying the relevant
defect if there was no formal advice that that had occurred. That point does not arise
in this case, but my initial impression is that, whatever may have been the position
with the contract in Dura, Clause 39.4 does not require cause to be shown in any
particular way, and if the relevant defect has in fact been rectified it is not obvious to
me that cause has not been shown so long as the owners are in fact aware that that
has occurred. There is no substance in either of these grounds.
[125] Grounds 87 and 88 were directed to the way in which the Member dealt with the
various grounds in the Notice to Show Cause issued by the appellants. The same
points were raised as aspects of the argument in support of a breach of natural
justice, in failing to consider all the matters raised by the appellants. For the reasons
given earlier, there is no substance to these grounds. These particular grounds do
not raise any specific error of law said to have been made in the course of dealing
with the grounds.
[126] Ground 91 was that the Member erred in failing to consider ground 6 in the Notice
to show cause at all. I have already dealt with this ground under the heading of
breach of natural justice.99 Because of the basis on which the ground was argued
before the Member, it necessarily fell away as a consequence of his approach to
grounds 2 and 3.
[127] Ground 93 asserted an error of law in failing to consider and to find that the six
grounds in the Notice to show cause justified termination at common law. The
Member certainly did consider whether termination at common law was justified, by
reference to the grounds in the notice to show cause, with or without a consideration
of additional defects relied on by the appellants. The question of whether there was
any error of law in that consideration was argued is respect of other grounds; this
ground was not clarified in submissions, and does not otherwise identify any
specific question of law for me to consider.
[128] Ground 99 was that the Member erred in finding that the failure to achieve practical
completion by the date for practical completion was not fault based. I have some
difficulty understanding that ground, but it appears from the submissions that the
point was that the contractual obligation to achieve timely practical completion did
not depend on whether the builder was at fault in some other way, causing that
failure. Reference was made to Bartlett v Contrast Constructions Pty Ltd [2016]
QCA 119 at [25] and [36], but that was a case about an entitlement to liquidated
damages for delay in completion, which was said to be a contractual right to be paid
something under the contract. That did depend on the date for practical completion
as extended, and subject to any further claims for extension of time, which were said
to be for the member in that case to decide: [25]. It did not depend on whether the
owner should have terminated the building contract sooner than he did. There was
no duty to mitigate the claim for liquidated damages.
[129] The approach of the Member in the present case was that there had been no failure
to complete by the date for practical completion, because on his view the builder
99 See [52] above.
-- 37 of 68 --
38
ought to have been entitled to extensions of time which took that date to after the
date of termination by the appellants. Such a finding was a complete answer to this
claimed basis for termination. Hence the question of fault on the part of the builder
did not arise.
[130] The appellants also relied on the decision in Hopper v Queensland Building and
Construction Commission (No 2) [2019] QCAT 212. That was a case where a
failure to complete by the date for practical completion was relied on in a notice to
show cause. The builder argued that requests for extension of time had been made
and not responded to, but the Tribunal found that the requests had not been given to
the owners, and were otherwise defective. The Tribunal noted substantial delay,
including for more than six months after the contract before work even started, the
building was described as relatively modest and unremarkable in terms of
complexity, and the notice to show cause was given over two months after the date
for practical completion. I have found the decision a little confusing about the basis
for termination, but it appears that the breach constituted by the failure to complete
by that date was regarded as sufficiently serious to amount to a substantial breach,
and also amounted to repudiation and a sufficiently serious breach of the term to
justify termination at common law.
[131] The Tribunal in Hopper noted that in an earlier decision, Mitchamy Developments
Pty Ltd v Adams [2010] QCAT 484, it had been said that a failure to reach practical
completion on time does not, in itself, amount to a substantial breach of contract. A
failure to reach practical completion by the date for practical completion is not one
of the breaches made a substantial breach by definition in Clause 39, so that, in
order to rely on this as a ground for a notice to show cause, the owner had to show
not merely that this contractual obligation had been breached, but that it was a
substantial breach. On the approach of the Member in this case, there was no such
breach, and this issue did not arise. This ground is not made out.
- Illegality
[132] Ground 95 alleged that the Member erred in law in failing to consider the appellants’
submissions that they were entitled to terminate on the ground of illegality by the
builder. I have mentioned this issue as part of the grounds relating to alleged breach
of natural justice. Ground 97 alleged that the Member erred in law in failing to
uphold that submission. The short answer to that ground, as I pointed out earlier, is
that there was no proper submission advanced before the Member for termination
for illegality, because the illegality relied on was not identified by the appellants.
Even before me, the written submissions do not state specifically what conduct was
relied on for this purpose, and how it was said to be illegal.
[133] Their oral submissions on appeal did however identify as relevant provisions the
Building Regulation 2006 (Qld) s 28 and s 34. The former applied if a builder for
assessable building work had given a notice for inspection for a stage of the work,
and provided that the builder must not start the next stage of the work until the
builder has been given a certificate of inspection for the relevant stage stating that
the stage complied with the building development approval. A penalty was
provided. The term “relevant stage” was explained by s 24; it was any stage at
which inspection was required by the terms of the building development approval,
-- 38 of 68 --
39
together with the stages set out in s 24(3).100 A builder was to give a notice to the
building certifier that a relevant stage was ready for inspection: s 27. If on the
inspection the stage was found not to comply with the building development
approval, the inspector was to give a non-compliance notice to the builder (s 33) and
the builder was then obliged to ensure that the stage complies with the development
approval: s 34.
[134] The consequences of not complying with the obligation in s 34 are set out in s 35.
That section does not refer to any consequences for the contract between the owners
and the builder. Nor, so far as I can see, does the Building Act 1975 (Qld); I was not
referred to any relevant provision. This however is by the way; the appellants’
argument was based on the proposition that a breach of this provision gave an
entitlement at common law to terminate the contract, on the ground of illegality.
[135] Courts do not readily interpret statutes which prohibit conduct, and provide a
penalty for breach, as impliedly rendering illegal any contract in breach of the
prohibition, or indeed, any entitlement to recover under a contract for work done in
breach of such a provision, without some indication in the statute of a legislative
intention to bring about that result.101 The leading case is Yango Pastoral Company
Pty Ltd v First Chicago Australia Ltd (1978) 139 CLR 410, which was applied by
the Court of Appeal in Botros v Freedom Homes Pty Ltd [2000] 2 Qd R 377 to
conclude that a contract in breach of the Queensland Building Services Authority Act
1991 (Qld) s 58 was not thereby invalidated.102
[136] The appellants referred to Byers v Dorotea Pty Ltd (1986) 69 ALR 715 as an
example of a case where a term of a contract requiring the builder to be licensed was
characterised as a condition. That was a dispute between a developer and some
purchasers of units “off the plan” seeking to escape from the contracts. It was held
that they had been induced to enter into them by statements in breach of the Trade
Practices Act 1974 (Cth) s 52, and that there was an implied condition of the
contract that the building to be constructed would be built by a licensed builder,
which had been breached. The point was different from the point in the present
case.
[137] As well, in the case of an unlicensed builder the relevant legislation does expressly
provide civil consequences for a breach: the builder is unable to recover
remuneration on any basis for the work done, and has to repay any amount paid,103
although the builder is entitled to recover reasonable remuneration for work done
100 As well, s 25 permits a local government to exempt particular assessable building work from
particular stages of inspection. Section 24 does not depend on the progress payment stages under the
contract. One difficulty here is that it is not clear that the appellants were speaking about a “frame
stage certificate” by reference to the requirements of the approval or the regulation, rather than by
reference to a term of the contract.
101 Cheshire and Fifoot’s Law of Contract, (8th Aust Ed, 2002) p 843-4.
102 See also Schiliro v Peppercorn Child Care Centre Pty Ltd [2000] QCA 18 and the authorities cited at
[10], [11] for the related question of whether a statutory provision creates a cause of action for
breach.
103 The Act s 42; Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd [2009] QCA 75 at [53].
-- 39 of 68 --
40
which is within any licence in fact held by it, and can recover limited remuneration
under a statutory modification of quantum meruit in respect of other work.104
[138] The appellants’ submissions were based on the proposition that there was an
entitlement to terminate at common law. There is nothing in the contract to the
effect that Clause 11.1, which requires the builder to satisfy all legislative
requirements, was to be regarded as a condition. It was not included in the
provisions breach of which were under clause 39 made a “substantial breach” by
definition.105 The term “legislative requirements” was in clause 1 of the contract
defined very widely, and clearly could apply to a wide range of requirements many
of which could have no possible significant impact on the owners.106 The appellants
did not refer me to any authority to the effect that such a provision was a condition
of the contract. In the circumstances, I consider it clear that Clause 11.1 of the
contract was not a condition in the relevant sense.
[139] The appellants also relied on the terms implied into the contract by the Act Schedule
1B, as was recognised by special condition 7 of the contract. As I have mentioned
previously, these are described in the Schedule as warranties, which is applied to a
term of a contract where the only remedy for breach is damages. There is nothing in
the Act to indicate that a failure to comply with any of them on the part of the
builder gives a right to the owners summarily to terminate the contract. Schedule
1B s 44 provides expressly that a breach does not render the contract illegal, void or
unenforceable. That the statutory warranties give a right to damages for breach only
is made clear by the provisions in Division 4 of Part 3 of the Regulation, particularly
s 29.
[140] The remaining issue is whether this can be characterised as a sufficiently serious
breach of an “intermediate” term, so as to entitled the owners summarily to
terminate. The appellants relied on the decision of Koompahtoo Local Aboriginal
Land Council v Sanpine Pty Ltd [2007] HCA 61, (2007) 233 CLR 115 where the
Court adopted the approach of an earlier decision of the English Court of Appeal.107
The Court held that, where there had been a joint venture agreement between the
parties for the development of land, and numerous breaches of a term dealing with
the generation and provision by the respondent of proper financial records for the
joint venture, the breaches were sufficiently serious to allow the appellant to
terminate the contract. The test for this was whether the effect of the breach was to
deprive the innocent party of substantially the whole benefit it was intended to
obtain under the contract.108 In Koompahtoo that was determined by the Court
essentially on the analysis of the terms of the contract itself.109
104 Chapel of Angles Pty Ltd v Hennessy Building Pty Ltd [2020] QCA 219.
105 I note that Clause 39.11 gave a right to terminate without going through the show cause procedure in
certain, limited circumstances, not including illegality. It is not necessary to consider whether this
amounted to a substantial breach on another basis, because it was not relied on in the Notice to Show
Cause, and because clause 39 is not otherwise relevant.
106 For example, breach of a local government by-law prohibiting parking on a footpath.
107 Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26.
108 See for example Sekler v Kim Carroll Investment Pty Ltd [2021] QSC 312 at [28].
109 That appears to have been the approach also in Sekler (supra); in Gough v South Sky Investments Pty
Ltd [2012] QCA 161 the court had regard to the terms of the contract, and to some extent also to the
practical consequences of the breach.
-- 40 of 68 --
41
[141] In submissions to the Tribunal the appellants claimed that the requirement to comply
with all legislative requirements was an essential term of the contract, ie a condition,
or in the alternative that it was a sufficiently serious breach of the term to justify
termination, on the basis that it rendered the house unfit for occupation. It was not
made clear how not obtaining frame stage approval in itself had that result; certainly
continuing to work in breach of the Regulation s 28 could not have that
effect. According to the submissions of the respondent, there were three things
preventing the issue of the frame stage certificate, two of which were simple matters
to address110 and one of which (the ceiling height issue) was being sorted out with
the architects at the time the appellants terminated the contract.
[142] In the appellants’ submissions on appeal reference was made at [374] to Instyle
Homes (Qld) Pty Ltd v Middler [2017] QCAT 376 at [41] as if that decision was
authority for the proposition that continuing to work without frame stage
certification was a matter justifying termination at common law. It is not. In that
case a notice of default was given under a term of the contract by reference to a
number of grounds, including failing to carry out the work under the contract
competently, the Member found that the defects had not been rectified as required,
and the builder had not addressed the issue of a premature claim, so that the owner
was entitled to terminate under the contract. The decision is of no present
relevance.
[143] There was evidence about this matter given by Mr Allen, but it was confined to
asserting breach of a number of provisions of the Act, many of which were not made
offences.111 In the case of those that were, the matters complained of were generally
matters which would have no significant effect on the process of providing a
functioning dwelling for the appellants. Breach of them did not deprive the
appellants of the substantial benefit of the contract, in the sense contemplated by the
authorities.
[144] The builder in a statement of evidence annexed the report of the certifier dated 31
July 2017.112 This confirmed that the issues were the ceiling height in one room
(this was 2380 mm when it should have been 2400 mm), tie-down in the upper level
(triple grips on trusses and location rods not secure) and wall bracing panels not
completed. The builder maintained that the room had been constructed in
accordance with the plans in the contract, and this had not been sorted out before
termination.113 One matter noted was that termite protection certificates had not
been sighted. The builder annexed to the statement copies of such certificates in
Form 16, in respect of parts of the work, dated 19 and 28 January 2017.
[145] There is nothing I can locate in the material (and I have not been referred to any
evidence by the appellants) which shows how they seek to establish that the house is
110 The builder said that both had been addressed before termination: Day 2 p 50.
111 Affidavit of Allen sworn 3 September 2018 paras 245, 246; Exhibit RJA31: Appeal Book Vol 4 p
1195, Vol 5 p 1601.
112 Annexure BCD13; Appeal Book Vol 7 p 2169 – 2171.
113 Appeal Book Vol 7 p 1892, 3. The appellants said that, when a concrete floor above the room was
made thicker by 50 mm, the builder had maintained the prior level of the top of the floor, instead of
maintaining the prior level of the bottom of it. This was not resolved by the Tribunal, but is wrong.
I return to this point later.
-- 41 of 68 --
42
unable to be occupied as a result of a breach by the builder of this provision. In an
affidavit of Mr Allen sworn 19 October 2018 he explained that, as they did not have
all the certificates they required, it was necessary for various inspections to be done
again.114 In submissions on the appeal, Mr Allen complained that, although at the
hearing the builder and the respondent had said they held various relevant
certificates, they had never been produced to the appellants. I cannot see how this
involved any error by the Member, or is relevant to the appeal. The evidence does
not establish that the absence of certificates rendered the house unable to be
occupied. At most, it showed that, with a relatively small amount of trouble, any
such absence could be overcome by further inspections.
[146] Accordingly whether one looks at the matter with the focus on the terms of the
contract, or whether one looks also at the practical consequences of the breach, what
was relied on by the appellants did not satisfy the test in Koompahtoo for a
sufficiently serious breach to justify termination for breach of a non-essential term in
a contract. The case presented by the appellants to the Member was not capable, as
a matter of law, of sustaining an entitlement to terminate the contract on the ground
of illegality. Grounds 95 and 97 are not made out.
[147] Ground 96 alleged that the Tribunal had erred in law in failing to consider a
submission that termination was justified by the builder’s failure to comply with the
obligation implied by the Act Schedule 1B s 25 to proceed with reasonable
diligence. That was correct in that it was not dealt with specifically as a separate
point, but the implied obligation is in substance the same as the obligation in Clause
39 to proceed with due expedition and without delay. The Member did consider that
issue, and rejected it, and in substance this dealt with the submission based on the
implied term as well. This ground is not made out.
- Overclaiming
[148] Ground 104 – 106 were dealt with together in the submissions for the appellants,
under the heading “overclaiming”. They relate to Ground 4 in the Notice to show
cause. This asserted that the relevant breach consisted of claiming payment:
(a) In excess of the value of the work under the contract.
(b) For unfixed plant and materials.
(c) Not directly related to the progress of the carrying out of the subject work at
the building site.
(d) Not proportionate to the value of the subject work.
[149] Reference was made to Clauses 37.1 and 11.1 of the contract, and the Act Schedule
1B s 34. I cannot see anything in Clause 37.1 limiting the amount which can be
claimed, and it expressly contemplates that a claim may include any other money
said to be payable to the contractor.115 Clause 37.3 excludes payment for unfixed
plant and materials, but does not in terms prohibit a claim for payment for them.
114 Paragraphs 23 – 25, Appeal Book Vol 6 p 1752. The builder said it was the usual practice for all the
certificates to be provided to the owners at the end of the construction: Appeal Book Vol 7 p 1894
para 46. But as to certificates of the building certifier, see the Act Sch 1B s 17(2).
115 The appellants’ submissions at [382] involved a misreading of Clause 37.1.
-- 42 of 68 --
43
The Act Schedule 1B s 34 covers the other two matters, which are made offences by
that section, but they are not within the warranties implied into the contract. Nor are
they covered by s 21, since s 34 is not a statutory requirement for carrying out the
subject work, but s 34 would be covered by Clause 11.1 of the contract, so that
potentially there could be a breach of contract in this way. The particulars given
related to payment claims 10 – 14.
[150] The Member dealt with this on the basis that it was not a substantial breach, because
the amount paid depended on the amount found to be payable by a quantity surveyor
employed by the appellants, who assessed the correct value of each claim, which
was then certified by the superintendent (except for the last one116), with the builder
then invoicing for the amount so certified, which was paid. That was consistent with
the response to the Notice to Show Cause of the builder.
[151] The submissions on appeal of the appellants proceed on the basis that a breach of s
34 by the builder was necessarily a substantial breach of contract. I do not agree. It
was not made a substantial breach by definition, and in view of the fact that payment
was by reference to the amount certified, any “overclaiming” was necessarily
harmless to the appellants. It did not affect the amount they actually paid. It was a
technical breach only. For the same reason, it could not possibly satisfy the test in
Koompahtoo for a breach entitling the appellants to terminate, and I have already
said that Clause 11.1 was not a condition.
[152] The proposition that overpayment of the builder could adversely affect the owners
under a claim on the statutory insurance scheme was not relevant, because that
relates to amounts paid, not amounts claimed. The hypothetical possibility of an
excessive claim being allowed because of the absence of a timely response by the
superintendent is of no relevance in this case. The appellants referred to Instyle
Homes (supra) but in that case there were a number of breaches which were
regarded as much more serious than the breach here. There is no substance to these
Grounds.
- Unapproved subcontractors
[153] Appeal Grounds 107, 108 and 119 all related to matters arising in respect of Ground
5 in the Notice to Show Cause, subcontracting part of the work under the contract
without the approval of the superintendent. This was based on Clause 9.2 in the
contract, and the particulars referred to the engagement of a plastering subcontractor
and a painting subcontractor by the builder. The failure to obtain prior written
approval was not a substantial breach by definition, and the Member found that this
did not amount to a substantial breach for the purposes of Clause 39. He found that
the superintendent did ultimately give approval for the plastering subcontractor, and
that the painting subcontractor was just a painter employed to do some touch-up
jobs, so that his involvement in the project was not of significance.
[154] Ground 107 alleged an error of law, but did not identify the error. Ground 108 was
based on a misunderstanding of the Member’s reasons. He did not find that Clause
116 The last progress claim lodged by the builder had been assessed by the quantity surveyor and was
ready to be certified by the Superintendent when the contract was terminated: Builder Day 3 p 21, 2.
As a result, the builder has received no payment for the work done in the last six weeks before
termination. It is unsurprising that the builder was unhappy about having to give evidence.
-- 43 of 68 --
44
9.2 did not apply, but that the breach was not substantial. He did comment on the
prevalence of the use of contractors rather than employees in the building industry,
and that almost anyone who did any work on the site would be a “contractor”, so
that if prior written approval was needed for each of them the consequence would be
considerable delay to the project,117 but he did not decide that the clause did not
apply to the painter, only that the breach was not substantial. The proposition that
every such person would require prior written approval of the superintendent does
seem, at best, to be an “uncommercial” arrangement, but whether that is the correct
interpretation does not arise in this appeal. For reasons given earlier, I do not accept
that breaches of Clause 9.2 discovered afterwards can be relied on by the appellants
for termination under Clause 39.
[155] Reference was made to the decision in Advance National Services Pty Ltd v
Daintree Contractors Pty Ltd [2019] NSWCA 270, which the appellants concede
was given after the decision of the Member. In that case it was said to be an
essential term of the contract between the parties that the work to be done under the
contract was to be performed by the contractor itself, unless prior approval had been
obtained for assignment or subcontracting. Such a conclusion in that case was not
difficult: the relevant clause stated expressly that any breach of it would be a
fundamental breach entitling the other party to terminate at once. That matter was
not in issue in that case; the issue was whether the party in breach was entitled to
payment under the contract for work done by the unauthorised subcontractors. The
question of termination of the contract did not arise. The decision is of no relevance
to this appeal, except by way of contrast to this contract.
[156] The appellants also submitted that Clause 9.2 was a condition (or fundamental term)
which entitled them to terminate summarily, or that what occurred was a sufficiently
serious breach of Clause 9.2 to entitle them to terminate, matters said not to have
been considered by the Member. I do not agree that he did not consider this,
although it was considered as part of the overall argument that there was an
entitlement to terminate at common law, which was rejected. In any case, I do not
regard Clause 9.2 as a condition. It is not said to be one, and there is nothing in the
contract to suggest that it was treated that way by the parties. Breach of it was not
made a substantial breach by definition by Clause 39, nor did that clause give a right
of summary termination. In the context of the building industry, where
subcontracting is rife and it is commonplace for almost every person who does any
actual work on a building site to be a contractor rather than an employee, it would
not be a commercial construction of the contract to treat Clause 9.2 as a condition.
[157] The appellants complained that the Member ignored their evidence of the
importance to them of having only approved subcontractors.118 If so, he was correct
to do so. The subjective intention of one of the parties to a contract as to its
operation is not relevant in the interpretation of the contract.119 The respondent in
117 Particularly since, under Clause 9.2, the Superintendent was allowed fourteen days to respond to any
request for approval.
118 Allen Day 1 p 47; he did not explain why.
119 Codelfa Constructions Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337 at 352. There was
no suggestion that this represented a mutual agreed understanding.
-- 44 of 68 --
45
submissions pointed to the builder’s evidence that the original list of subcontractors
approved in the contract was almost entirely created by it.120
[158] As to whether it was a sufficiently serious breach of a non-essential term to justify
termination, I do not consider that it meets the test in Koompahtoo. Whether or not
a particular subcontractor is approved will not in itself deprive the appellants of any
substantial benefit of the contract. As well, the plastering contractor was ultimately
approved, and the timing of the approval cannot be of any real significance to the
appellants. The painter was a sub-sub-contractor, and had only a very small role in
the overall construction process, and failing to have him approved cannot be
regarded as a matter of any real consequence.
[159] I may add that it is by no means clear to me that the contract, and Clause 9.2,
operated in the way the appellants alleged anyway. Clause 9.2 provided, so far as is
relevant:
The contractor shall not without the Superintendent’s prior written approval
(which shall not be unreasonably withheld):
a) Subcontract or allow a subcontractor to subcontract any work described in
Item 17.
b) Allow a subcontractor to assign a subcontract or any payment or any other
right, benefit or interest thereunder.
[Reference was made to the process for gaining approval, and the clause
continued:]
Approval may be conditional upon the subcontract including … provision that
the subcontractor shall not assign nor subcontract without the Contractor’s
written consent.
[160] So the clause is concerned with the subcontracting of work “described in Item 17.”
Item 17 appears in Annexure Part A to the general conditions of contract, in these
terms:
17 Subcontract work requiring approval (subclause 9.2): All subcontract
work other than the pre-approved subcontractors for the category or
subcontract work stated in Section 4 and selected subcontractors named in the
finishes and fixtures schedule.
[161] I expect that the word “or” in Item 17 should be the word “of”, although if I am
wrong about that, the practical effect is the same. The function of Item 17,
according to Clause 9.2(a), is to identify the work the subcontracting of which is the
subject of the restriction in that clause. Item 17 starts with “all subcontract work’,
but then contains an exception, for the subcontract word stated in Section 4
subcontracted to the pre-approved subcontractors in Section 4. This is a reference to
Section 4 to the general conditions of contract, which contains a long list of
categories of work, and “nominated” subcontractors, presumably the pre-approved
ones. It seems to me that work the subject of a subcontract with a subcontractor
120 Submissions in writing of respondent [106], citing the statement of reasons of the respondent at p
793. The appellants sent a draft list of nominated subcontractors to the builder which contained only
seven names, including one supplier, and invited it to fill in the remaining nineteen spaces, including
by multiple names if desired: Appeal Book Vol 6 p 1886.
-- 45 of 68 --
46
listed in Section 4 was in the exception in Item 17. Hence it was not subject to the
restriction in Clause 9.2(a).
[162] It follows that, not only did the builder not require approval to subcontract the
relevant category of work to a subcontractor listed in Section 4, but the builder did
not require approval to allow that subcontractor to further subcontract any part of
that subcontractor’s work. It does not appear whether the unapproved painter was
subcontracted by a nominated subcontractor, but if so, I consider there was no
breach at all. This issue does not appear to have arisen before the Member, and I
have not received submissions on it, so I specifically do not decide this aspect of the
appeal on this basis.
- Repudiation
[163] Appeal Grounds 115 and 116 related to the rejection by the Member of the
submission that the builder had repudiated the contract, although Ground 116 was
expressed as a conclusion and did not identify a question of law. The Member at
[116] referred to the decision in Koompahtoo (supra) and correctly stated the test
stated there for repudiation. The appellants complained that the Member had not
referred to a decision cited to him, Hudson Crushed Metals Pty Ltd v Henry [1985] 1
Qd R 202 at 205-6, where it was held that repudiation could be found on the basis of
persistent breaches in several different respects of the provisions of the relevant
agreement. However, the Member at [115] expressly recognised that the appellants
were complaining about the attitude of the builder in its performance throughout the
contract as amounting to repudiation. Clearly the Member was conscious that
repudiation could be established in such a way.
[164] In Hudson Crushed Metals (supra) the Court upheld a finding that a party with the
benefit of a grant of a right for two years to excavate and remove material from land
had repudiated the agreement. This was on the basis that that party had failed to
comply in four respects with the conditions on the grant of permission to do this by
the local authority, in breach of the contract,121 something which imperilled the
whole enterprise; failed to construct a cattle grid at the access point to the
property;122 and failed, despite persistent requests, to provide tally sheets for the
material extracted, which were the records from which the royalty payments due
under the contract could be calculated or checked, copies of which were by the
contract required to be provided. There were found to be breaches of eleven
different obligations, some of which had continued for a considerable period, and
one in particular, the provision of copies of tally sheets, the appellant was effectively
refusing to carry out.
[165] Interestingly, the Court also held that a breach of a clause to report the size and
depth of the excavation was of no practical consequence, because the other party
was well aware of the situation, and (presumably) that breach did not contribute to
the repudiation of the contract. The trial judge had expressed an adverse view of the
manager of the appellant, describing him as irresponsible as a witness, and in his
121 By failing to pay six monthly road maintenance contributions, failing to provide visibility widening
at the point of access, failing to widen a culvert at the point of access, and working outside the
permitted hours of operation.
122 Of importance because this operation was carried out within the respondent’s cattle station.
-- 46 of 68 --
47
dealings with the respondent: p 205. It was said that the behaviour of the appellant
indicated that it was prepared to carry out its part of the contract only if and as it
suited it, and that it showed an almost complete disregard of its obligations under the
contract: p 207. Thomas J, agreeing, stressed the importance of the obligation to
provide copies of tally sheets, which was constantly and almost totally breached: p
208. Overall, that was a much stronger case for repudiation than was the present.
[166] That decision was applied by McPherson J in Aquamere Pty Ltd v Exelman Pty Ltd
[1988] QSC 329 to find repudiation by a franchisee who had persistently breached
the provisions of the agreement relating to the shelf life of ingredients, the payment
of correct award wages, and the payment of a royalty based on gross takings. His
Honour analysed the significance of the breaches in terms of their potential for an
adverse effect on the franchisor, and noted that the third breach, effected by
artificially depressing the amount of gross income by money taken from the till by
the franchisee, was systematic and deliberate, and not the result of inadvertence or
oversight. The franchisor had an interest in protecting the good name of businesses
in the overall group, and the payment of the royalty was the principal practical
benefit to it of the agreement. Again, a much stronger case for repudiation. Another
example of persistent breaches of contract amounting to repudiation is Tulloch Brae
Pty Ltd v Environmental Protection Equipment Pty Ltd [2021] QSC 213, a contract
for the provision of services, where the level of performance was persistently
inadequate: [55]. The trial judge accepted evidence that the party in breach could
have done more to perform the contract.
[167] The Member also cited Keswick Developments Pty Ltd v Keswick Island Pty Ltd
[2012] 2 Qd R 114, where the Court upheld a finding that a tenant had not
repudiated a lease notwithstanding non-payment of rent, non-payment of outgoings,
non-payment of rates and breach of a covenant to insure. There were particular
circumstances surrounding these breaches. The rent was nominal, the lessor had
failed to advise the amount of the outgoings (which was said not to remedy the
breach but to be relevant when assessing the tenant’s conduct), the leased land was
vacant and nothing was being done on it, and the obligation to provide confirmation
of cover had been remedied, albeit late. Muir JA, with whose judgment the other
members of the Court agreed, said at [56] that repudiation was a serious matter not
to be lightly found or inferred, and stated the tests for repudiation in terms of the
existing authorities at [57] and [58], including that it depended on the objective
assessment of the conduct and what it would convey to a reasonable person. In that
case the Court, in assessing whether the conduct amounted to repudiation, had
regard to various difficulties facing the tenant.
[168] A fairly recent appellate authority on repudiation of a contract to do building work is
the decision of the New South Wales Court of Appeal in DCT Projects Pty Ltd v
Champion Home Sales Pty Ltd [2016] NSWCA 117. Gleeson JA, with whom the
other members of the Court agreed, said at [39] to [43]:
For the conduct of a party to constitute a renunciation of its contractual
obligations it must be shown that the party is either unwilling or unable to
perform its contractual obligations, that is, it has evinced an intention to no
longer be bound by the contract, or stated that it intends to fulfil the contract
only in a manner substantially inconsistent with its obligations and in no other
way: Shevill v Builders Licensing Board [1982] HCA 47; 149 CLR
620 (Shevill) at 625-626 (Gibbs CJ); Laurinda Pty Ltd v Capalaba Park
Shopping Centre Pty Ltd [1989] HCA 23; 166 CLR 623 at 634, 647-648,
-- 47 of 68 --
48
658; Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007]
HCA 61; 233 CLR 115 (Koompahtoo) at [44]. Repudiation is a serious matter
and is not to be lightly found or inferred: Shevill at 633 (Wilson J).
Where inability to perform is declared the conduct amounts to a refusal to
perform and the innocent party need not prove that the other party was
actually unable to perform when the time for performance came: Universal
Cargo Carriers Corporation v Citati [1957] 2 QB 401 at 437.
A renunciation can be made either by words or conduct, provided it is clearly
made: Universal Cargo Carriers Corporation v Citati at 436. The test is
whether the conduct of one party is such as to convey to a reasonable person,
in the situation of the other party, renunciation either of the contract as a
whole or of a fundamental obligation under it: Koompahtoo at [44]; Laurinda
Pty Ltd v Capalaba Park Shopping Centre Pty Ltd at 659 (Deane and Dawson
JJ) and 647 (Brennan J).
So far as factual inability to perform is concerned, what needs to be shown is
that the party in question has become wholly and finally disabled from
performing the essential terms of the contract altogether: Rawson v
Hobbs [1961] HCA 72; 107 CLR 466 at 481; Almond Investors Ltd v
Kualitree Nursery Pty Ltd [2011] NSWCA 198 at [62] (Bathurst CJ; Giles JA
and Handley AJA agreeing). It is well accepted that factual inability must be
proved “in fact and not in supposition”: Universal Cargo Carriers
Corporation v Citati at 450.
[169] In that matter there was some conflict between the parties, and allegations that the
work was proceeding too slowly, for which excuses were offered, and that some
other breaches of contract had occurred. The Court upheld a finding that repudiation
had not been proved, adopting what strikes me as a pragmatic approach to the
question of delay. What matters more are the statements of principle set out above.
[170] Overall I do not consider that any error of law on the part of the Member has been
exposed in his consideration of the issue of repudiation. Whether the builder’s
conduct overall amounted to repudiation is a question of fact, or of mixed law and
fact, and is not appropriate for consideration at this point. In the light of my
conclusion later about that issue, it is clear that the evidence was not such that the
Member was bound as a matter of law to find repudiation.
Termination for serious breach
[171] Ground 118 was that the Member failed properly to apply and follow the alternative
test for termination at common law, for a sufficiently serious breach of a non-
essential term of the contract. Reference was made to Koompahtoo at [47]. At that
point in the decision the majority was speaking about the traditional distinction
between conditions and warranties, and cited the analysis of Sir Frederick Jordan CJ
in the Tramways case. It was later that the majority adopted the analysis in Hong
Kong Fir, of a sufficiently serious breach of a non-essential term to justify
termination, and at [55] said that the test was whether the breach was such as to
deprive the injured party of a substantial part of the benefit to which that party is
entitled under the contract, said to depend primarily on the terms of the contract.
[172] The Member, at [147], after considering in some detail the various defects relied on
by the appellants to show a right to terminate at common law, found that he was not
satisfied that, individually or collectively, they constituted a substantial breach
which would give rise to a right to termination. That finding was expressed in
-- 48 of 68 --
49
general terms, and was sufficient to cover both termination for breach of an essential
term, and termination for a substantial breach of an inessential term. The Member
had previously rejected termination for repudiation, at [117].
[173] Although the Member did not specifically reference Koompahtoo his finding
covered it, and that is all that is required. He referenced Koompahtoo in relation to
repudiation at [116], so he was aware of the decision, and in any case, having
considered myself the breaches relied on, none of them would in my opinion be
capable of being found to be a sufficiently serious breach of a non-essential term to
justify termination; none of them had the effect of depriving the appellants of a
substantial part of the benefit to which they were entitled under the contract.
Ground 118 is not made out.
- Other grounds of appeal
[174] I cannot understand Ground 129, which appears to be a complaint about the way the
Member dealt with delay on the part of the supplier of pivot doors, referenced to
reasons [140] – [142]. The Member did discuss pivot doors at that point in the
reasons, but said nothing about delay; he did say that the builder was responsible for
the doors, as between it and the appellants. It appears from the evidence that there
was an issue about whether the pivot doors could be certified for the purposes of the
National Construction Code, since they were not waterproof.123 The appellants
admitted that the front door could not be installed until after the joinery had been
installed, something that did not occur before termination, so if there was any delay
installing the front doors, it was not in fact a problem. This was really not an issue,
and no error has been shown.
[175] Ground 131 was that the Member erred in failing to accept the evidence of the
appellants’ expert witness in relation to the allegation of defective stairs. This does
not raise a question of law, as the Member was not obliged as a matter of law to
accept that evidence. In any case, it is not clear that the evidence was not accepted.
The Member accepted that the stairs were constructed in accordance with a direction
of the Superintendent, which the builder was obliged to follow: [133]. That on its
face is a complete answer to this complaint, regardless of the evidence of the expert.
There is no substance to this ground. I consider the factual position in relation to the
stairs later.
[176] Ground 132 alleged that the Member had failed properly to consider the appellants’
submissions in reply, on the ground that they went beyond a reply, which was not
correct. The appellants’ written submissions in reply were structured so as to relate
to specific parts of the submissions for the respondent, and as a result their overall
structure was much clearer than the original written submissions for the appellant,
which have limited structure. They certainly referred to a large amount of factual
material not contained in the original submissions in writing.
[177] I believe that at one time it was the practice of courts to confine submissions in reply
to submissions of law, but I do not understand that that applies as a rule of practice
in the Tribunal. Nevertheless, it is preferable for factual material to be included in
the original submissions of the applicant, in order to give the respondent a fair
123 Reference is made to the relevant evidence at [242] below.
-- 49 of 68 --
50
opportunity to respond to it. There was really no opportunity to respond to such
material raised for the first time in the reply. The Member’s complaint may have
been poorly expressed, but the following reference, to sifting through the material to
discern the substantive issues, shows that it did not lead him to disregard the content
of the submissions in reply. The appellants’ real complaint is that their submissions
were unsuccessful. No error of law of any consequence has been shown.
[178] Ground 133 raised the proposition that it was an error of law to describe the
possession of the builder of the building site as exclusive,124 because of the terms of
the contract and of the Schedule to the Act. The contract provided in Clause 24.1
that the appellants shall give possession of the site or part of the site to the builder.
Although the adjective “exclusive” was not used, the existence of Clause 24.2,
providing for access to the site by the appellants, subject to conditions, indicates that
otherwise the possession is exclusive of the appellants.
[179] The appellants also referred to the Act s 109, which requires a builder to allow a
consumer, here the appellants, reasonable access to a building site, at their request.
Again, the existence of such a provision assumes that otherwise the builder has
exclusive possession of the site. If the owners retained possession, or some
possession, there would be no need for such a provision. It allows “access”, not
possession, only reasonable access, not unfettered access, and there must be a
request to the builder first, although the section does not require the request to be in
writing. The question of what is reasonable access might be difficult to define in
general, but I expect that any access which had the effect of impeding the progress
of the work, as mentioned in Clause 24.2, would not be reasonable.
[180] That does not mean that the builder has the sort of right of exclusive possession of
the site that would be enjoyed by an owner or lessee. The builder has no interest in
the land constituting the site,125 and the right of a builder has been described for a
long time as a licence.126 But the builder had under the contract exclusive
possession of the site, except to the extent that that right was cut down by contract or
statute.127 The appellants had rights of access by contract and by statute, but that fell
short of possession of the site.
[181] In a sense then what the Member said was right, although it did not describe the
position fully. In so far as the Member’s point was that the possession was (or
perhaps ought to have been) exclusive of the appellants, so that they had no right to
come onto the site at all, that was not the legal position of the builder as against the
owners. This error however was of no consequence to the outcome of the
proceeding. It was just part of the Member’s critique of what he regarded as a petty
accumulation of a large number of inconsequential “defects” by the appellants, in an
exercise of attempting to manufacture a justification for termination of the contract.
That was not the basis of the decision, so any error was of no consequence, and this
ground is not made out.
124 Reasons [147].
125 The Act Schedule 1B s 43(1).
126 Cowell v Rosehill Racecourse Co Pty Ltd (1937) 56 CLR 605 at 621 per Latham CJ, in dicta which
has been widely followed, eg in Duzenli Developments Pty Ltd v Benuga Pty Ltd [2020] NSWSC
1667 at 28.
127 See also Bailey “Construction Law in Australia” (4th Ed, 2018) p 247 [9.210].
-- 50 of 68 --
51
[182] Appeal Ground 109 as written is almost unintelligible, but appears to take issue with
a finding that the fact that more work would have been done under the contract to
achieve practical completion had it not been terminated relieved the builder of
liability for a prior breach of contract justifying termination. That was not what was
found at all. What the Member concluded at [112] was that there was no right to
terminate in response to the Notice to Show Cause under Clause 39, either because
there were no breaches as relied on, the breaches were not substantial breaches,
justifying termination or the response of the builder was reasonable. This was after
he had dealt with the various grounds relied on by the appellants, and was simply a
general summary of his earlier findings. I have already discussed the operation of
Clause 39, and will not repeat what I have said. There is no substance in this
ground.
[183] Appeal Ground 114, concerned with the question of whether incorrect sarking was
used, did not raise a question of law. As expounded in the submissions, it was a
challenge to a finding of fact by the Member, and is covered by other, more
appropriate grounds.
Leave to appeal
[184] It follows that the appellants have failed to show that the Member made any error of
law which justifies allowing the appeal. The next issue is whether leave to appeal
should be granted. I have already said something about the tests for leave. In
respect of one matter, it is appropriate to give leave to appeal, in order to consider
whether there was an entitlement to terminate at common law because of the
encroachment by part of the concrete foundations onto the neighbouring land. Since
the hearing, work on that land exposed such an encroachment, more extensive that
what had been suspected by the appellants previously. This was covered in the
admitted fresh evidence.128 Leave to appeal should be given in order to consider that
issue.
[185] As to the various grounds in the annexure to the application for leave to appeal and
appeal, some such as ground 15 simply assert that factual conclusions were wrong.
Others assumed a view of the legal position different from that I have set out earlier.
For example, a number of findings about extensions of time were challenged on the
basis of an assumption that all that was relevant was extensions validly granted,
which I regard as wrong. Most of the rest just listed factual findings adverse to the
appellants, and asserted that they were wrong. As well, the substance of many of the
grounds has been dealt with already earlier in this decision.
[186] Grounds 16, 17 and 19 challenged the finding about the timeliness of the builder’s
notice showing cause, based on the proposition that the respondent had the onus of
proving that the notice was given within time. That is not correct. To the extent that
it is appropriate to speak of onus in this context, the appellants had the onus of
showing that their claim on the policy was good, which relevantly means that the
contract was validly terminated. If they sought to show that that occurred because of
a failure of the builder to show cause within time, they had to show that the notice
showing cause was not given within time. Any onus was on the appellants, and no
error has been shown.
128 Affidavit of Allen sworn 13 November 2020, bundled separately.
-- 51 of 68 --
52
[187] Ground 18 challenged the finding that the builder intended to remedy defects and
non-conformities, because the builder did not. To some extent this missed the
Member’s point, which was that the termination of the contract deprived the builder
of the opportunity to do further work under the contract, including work which
would have remedied such matters as contemplated by the contract. But in its own
terms, the submission in support of this ground relied on isolated propositions cited
out of context. As to door W3.09, the position of the builder was that a remedy was
being worked out with the superintendent, and although there was a claim for this as
a variation, that was not identified as a pre-requisite to fixing the door, as mentioned
earlier. The same applied to the state of the roof top hobs, where the statement
relied on in the submissions on appeal was actually evidence of an intention to do
further work on them.129 Reliance on the AWCI report was in the context where no
issue had arisen as to backblocking.130 The fact that additional defects were
discovered later says nothing about the intention of the builder. The appellants have
no plausible challenge on this ground.
[188] I have already dealt in substance with Grounds 21 and 22, where the same issue was
raised as an error of law. Ground 23 challenged the finding about the appearance of
the concrete hobs on the roof, on the basis that they did not satisfy the applicable
Australian Standard. There was evidence from the appellants’ expert witness that
the finished appearance did not meet the finish specified in the Australian Standard
for a visually exposed exterior concrete surface; he recommended four possible
means of rectification, including just painting,131 The builder maintained that he
was working on this at the time of termination and was prepared to do more work on
this, including if necessary removing the hobs and recasting them.132 There was
some issue about the wording of the response by the builder, but the Member
accepted, I think correctly, that it showed a willingness to do further work on this,
which the Member regarded as reasonable. I agree. Strictly speaking this was a
failure to comply with an applicable standard, but the response was reasonable and
as an aesthetic issue only, which was potentially easily fixed, it was really a minor
matter.
[189] Appeal Ground 24 challenged a finding about the involvement of Mr Allen in
supervising the work, as having “effectively” taken over the role of the
superintendent, as if the finding did not include the word “effectively”. It does, so
this ground is misconceived. Mr Allen admitted that he became further involved in
supervising the work,133 and for example by 8 November he was approving a
subcontractor,134 something which under the contract was a matter for the
Superintendent: Clause 9.2. The finding made was clearly open on the evidence.
[190] Ground 25, although listed under errors of fact, actually alleged an error of law,
about the significance of a finding that the concrete hobs did not comply with the
applicable Australian Standard in a matter of aesthetics. The issue as I have said
129 Paragraph 436(b). See also builder Day 2 p 10.
130 This also deals with appeal grounds 20 and 44.
131 Affidavit of Allen sworn 3 September 2018 Exhibit RJA 40, Vol 5 p 1736.
132 Day 2 p 10. The builder said the hobs were not in fact constructed as part of the roof, but separately,
so they could be removed without any impact on the structure of the building: Day 2 p 6.
133 Day 1 p 25; affidavit of Allen sworn 3 September 2018 para 118, Appeal Book Vol 4 p 1164.
134 Second statement of builder Attachment 21, Appeal Book Vol 11 p 3063.
-- 52 of 68 --
53
turned on the finding that the response was reasonable, so this point is not relevant
to the outcome of the matter.
[191] Ground 26, dealing with requests for information, and Ground 29, concerning the
percentage of work completed, are complaints about findings of fact which are not
central to the resolution of the dispute between the parties, and therefore do not
justify a grant of leave. Grounds 27, 28, 33 and 36 are concerned with details of
things said about requests for extensions of time. As explained previously, a precise
analysis of this issue was also not central to the resolution of the dispute, so the
position is the same here. Grounds 30 and 31, about the significance of requests for
extension of time accepted by the appellants, do not raise questions of fact but issues
of law, and are based on a misinterpretation of the reasons of the Member.
[192] The submissions in relation to Ground 32, 34 and 35 were advanced on the basis that
the appellants were not responsible for the delay associated with the refusal of the
original cabinet work subcontractor to do the work.135 Such an event is outside the
control of the builder, who cannot force the subcontractor to do the work, and the
process of obtaining a replacement subcontractor for this work was bound to take
some time, and involve some delay, depending on the circumstances. The
requirement to have a replacement subcontractor approved by the appellants can
only increase any such delay, and if the work is then taken out of the hands of the
builder136 and the appellants deal with the replacement cabinetmaker direct, it would
be natural enough for that to produce further delay for the builder. The submissions
for the appellants do not suggest to me that there was any error in the finding of the
Member about this. Whether or not it justified an extension of time under the
contract, it was not what I would regard as the sort of delay relevant to Clause 39, or
showing a want of due expedition.
[193] Ground 37 is curious. It challenged a finding that it was reasonable for the builder
to delay tiling the kitchen area because it was usual for cabinets to be installed
before floor tiles were laid, said to be contrary to a drawing which seemed to show
tiles covering the whole area including the footprint of the cabinets, as the builder
admitted: Day 3 p 18, 9. In fact the area was ultimately tiled before termination of
the contract. The evidence that it was usual to install cabinets first was
uncontradicted and plausible, in view of the risk of damage to tiles during the
installation work, and because that would reduce the area of tiling required, so there
was no reason not to accept it. Laying the tiles first does not necessarily follow
from the drawing, but the builder accepted that he was (at some point) instructed to
lay the tiles first, and that was what he then did: Day 3 p 18. All the builder
admitted was what the drawing showed on its face. In any case, this finding is mixed
up with the issue of delay, and I consider the technical justification of requests for
extension of time is not relevant.
[194] Grounds 39, 40 and 41 concern what are said to be factual errors in relation to the
issue of overclaiming in progress claims. I have already dealt with the legal position
135 According to the builder, the nominated subcontractor closed its cabinetry division: First statement
para 55, Appeal Book Vol 7 p 1896.
136 The variation to achieve this from the Superintendent was dated 9 November 2017: Appeal Book
Vol 12 p 3182.
-- 53 of 68 --
54
in relation to progress claims, and as a result of my analysis the detail of any factual
finding in relation to such claims is irrelevant.
[195] Ground 42 was another ground which really alleged an error of law, in failing to
have regard to the Act Schedule 1B s 34, which regulated the entitlement to claim
progress payments. The situation here is that the contract contained a mechanism
for quantifying the entitlement to progress payments, and the contract did not
become illegal void or unenforceable even if there was a breach of s 34 involved in
complying with it.137 That is consistent with the ordinary assumption of courts, that
when a statutory requirement imposes a penalty for breach that is the only
consequence of a breach, as discussed above. As mentioned earlier, it may have
amounted to a breach of clause 11.1 of the contract, but I regard it as no more than a
technical breach. This ground is not made out.
[196] Ground 43 claimed that the failure to obtain prior approval for the plastering sub-
contractor remained a breach of contract, even though that contractor was approved
after it had started work. The Member’s point about the late approval of the
plastering subcontractor was not that it waived the original breach, but that it meant
that the breach was not substantial, a proposition I regard as obvious.
[197] Ground 47 complained about a reference to the builder having done certain work in
the reasons of the Member, when it was said someone else actually did it. The point
here was an issue of whether the work was defective, and the Member was
obviously speaking of the builder having done the work in the sense that it was done
as part of the work under the contract. The Member went on to accept evidence
about the state of the work, which was at that stage in substance only “roughed in”,
and would have been finished off before connection to the gas supply had the
contract not been terminated. The submissions provide no reason to doubt this
finding.
[198] Ground 48 complained about the finding made by the Member about a complaint
about defective internal stairs in the house, which the Member dealt with on the
basis that the superintendent had approved risers which were slightly over-height
(1.4 mm over the limit of 190 mm). The difficulty arises here because of the
inadequacy of the submissions made by the appellants to the Member. The specific
complaints about the internal stairs were not raised until the submissions in reply,
although the issue as to the internal stairs was addressed by the respondent in its
submissions, which referred to there being other issues with the stairs. The
respondent’s approach was that any defects with the stairs were not sufficiently
serious to justify termination at common law. The appellants’ complaint was that
the problems with the stairs were more extensive than the issue dealt with by the
Superintendent, and that in any case the Superintendent had been mistaken in
accepting the riser height. Since I propose to reconsider the issue of termination at
common law anyway, as mentioned earlier, this can be dealt with at the same time.
[199] Ground 49 challenged the finding of the Member that the breach in the termite
barrier was not a ground entitled the appellants to terminate at common law. There
was evidence that the termite barrier had originally been installed properly, and that
it had subsequently been breached, something which no doubt could be remedied
137 The Act Schedule 1B s 44.
-- 54 of 68 --
55
one way or another.138 To some extent these submissions appear to be based on the
proposition that the appellants were entitled to terminate for any defect or breach of
contract, which I do not accept, and even accepting that termites can be a real
problem in Brisbane, there is nothing in the submissions which suggests that this
could amount to grounds for termination at common law.
[200] Ground 50 challenged a finding that the builder intended to rectify defects in
existence at the date of termination. A finding in those terms was not made by the
Member, the reference being to a finding that at that date the builder was ready
willing and able to complete the work. The point of that finding was that the builder
was not repudiating the contract, and was willing to proceed with it in the usual way.
It is common enough for there to be defects in the work identified, and remedied,
before or indeed after practical completion, and the contract provided for a defect
period. Whether they would have all been rectified, so as to satisfy the appellants,
may be another issue, and some claimed defects may have been the subject of a
dispute anyway, but it does not follow that the appellants were entitled to terminate.
There is no reason to investigate a finding that was not made.
[201] Ground 51 challenged a finding that the builder intended to remedy a defect
allowing water penetration to a small number of windows. In evidence the builder
accepted that this was a defect, and what the Member was saying was that this was
the sort of thing one would expect to be remedied in the ordinary course of finishing
the job. But the important finding was that the matter was not sufficiently serious to
entitled the appellants to terminate, which was the real issue at that point.
[202] Ground 53 asserted that the Member erred in failing to take into account further
defects found or admitted by the builder would cause further delay, when deciding
whether there had been a failure to perform the work under the contract with due
expedition and without delay. If there was no finding, no question of fact or mixed
fact and law arises, although there may be a question of law as to whether this was a
relevant consideration. If so, it was clearly not. The effect of the Notice to Show
Cause was to assert that there had been a lack of due expedition, and delay, and that
was the issue for the purpose of termination under the contract. The appellants were
not entitled to rely on possible future delay to strengthen their argument on this
point.139 The position is the same for termination at common law. There could be
an anticipatory breach of contract which, if sufficiently serious, could justify
termination, but nothing of that kind existed here. It is also not clear that the
appellants raised this proposition before the Member. There is no substance to this
ground.
[203] Ground 54 was also based on a misinterpretation of the reasons of the Member,
treating a statement that there was an explanation as if it were a finding that there
was not a defect. Ground 55 is a re-hash of a ground I have previously dealt with,
about the absence of timely certification. I do not need to consider it again. Ground
56 challenged something said in the course of distinguishing the circumstances of
138 The expert recommended that a report on remediation be obtained from a pest control specialist, but
no such report was put in evidence by the appellants. There was no evidence that remediation was
not possible.
139 The position is the opposite: an earlier lack of due expedition can be remedied by the builder’s
working with due expedition more recently, as shown by Hometeam (supra): see [91](g) above.
-- 55 of 68 --
56
this matter from those under consideration in Dura (supra), saying that unlike that
case there had been no significant defects identified or defects lists submitted to the
builder: [31]. The challenge was based on the proposition that a defects list was
provided to the builder on 23 October 2017, which was true, but the work had been
carried on for over eighteen months at that stage, and the Notice to Show Cause was
issued less than three weeks later, on 10 November. That is a very different
background from that in Dura, and the Member’s point was a good one.
[204] Ground 57, as developed in submissions, in effect complained about the failure of
the Member to have regard to the fact that the Insurance Policy issued by the
respondent expired two years after work commenced under the contract, so that the
appellants had to terminate the contract or lose the benefit of the policy. It is true
that the conditions of the insurance policy provided in clause 1.7 that the respondent
was liable to pay only if the contract was properly terminated within two years from
the date of the payment of the premium, or the date of entering into the contract,
whichever is the earlier.140 The relevance of this however to the process of
termination under the contract or at common law is not at all clear.
[205] It could not be relevant to the question of whether or not a term of the contract was a
condition, because that depends on the terms of the contract, not the terms of a
separate contract entered into with a different party. Even if this limitation on the
standard insurance policy were known to both parties when the building contract
was entered into, there is no provision in the building contract to the effect that,
notwithstanding any extensions of time, it was an essential term that the work be
completed within a period of time less than two years, and no such term could be
implied.
[206] Whether there has been repudiation of the contract by the builder is to be assessed
objectively, and I consider that the same applies to the question of whether there has
been a sufficiently serious breach of an intermediate term. In neither case could the
existence of a collateral motive on the part of the owner for wanting the contract
terminated be relevant. It follows that this matter was irrelevant to the question of
whether the appellants had validly terminated the contract at common law, and was
correctly disregarded by the Member when considering that point.
[207] As to termination under the contract, if I am correct that the reasonableness of the
response to the show cause notice has to be assessed objectively, again this issue is
irrelevant. If, as was held by the New South Wales Court of Appeal in Bundanoon
Sandstone (supra),141 there is an implied obligation on the owner to act reasonably
and in good faith in giving a notice to show cause, it could be argued that the
existence of this collateral motive for giving the notice showed that the appellants
were in breach of that obligation; but that point does not seem to have been argued
before the Member.
[208] What was argued before the Member was the closely related point, that there was
such an implied obligation in assessing the reasonableness of the builder’s response
140 Appeal Book p 175. I do not know the date on which the premium was paid, but the contract was
dated 17 February 2016. The existence of such a clause reinforces the proposition that the
“consumer protection” aspect of this insurance scheme is decidedly limited.
141 [2019] NSWCA 87 at [154] – [160].
-- 56 of 68 --
57
to the notice, which was breached if the attitude of the appellants was that, come
what may, they were going to terminate because of the time limit in the insurance
policy. This was argued by the respondent, and could have provided another reason
why the appellants had not validly terminated the contract under the contract. If
however the Member approached the issue on the basis of an objective assessment,
as I do, it ceased to be relevant. On my approach, there was no error of law in
disregarding this point; on the alternative approach, any error was one in favour of
the appellants, so they can hardly complain about it.
[209] Overall therefore the various errors of fact, or mixed law and fact, sought to be
raised by the appellants (apart from the specific issue referred to above) do not
suggest that there is a sufficient likelihood that any finding of fact, which was of
importance in the final outcome before the Member, would be overturned in the
event of a rehearing, to justify a grant of leave to appeal. Accordingly, there will be
leave to appeal only on the question of whether, taking into account the
encroachment over the side boundary of the concrete now shown to have occurred,
the appellants were entitled to and did terminate the building contract at common
law, for either repudiation or sufficiently serious breaches of non-essential terms.
That the appeal is by way of rehearing. It is well established that, on an appeal by
way of rehearing, the Appeal Tribunal is required to conduct a real review of the
hearing, and the Member’s reasons, and make its own determination of relevant
facts in issue from the evidence, giving due deference and attaching a good deal of
weight to the Member’s view.142 Nevertheless, in order to succeed on such an
appeal, the appellants must establish some legal, factual or discretionary error.143
Termination at common law
[210] The test for repudiation of a contract is, relevantly, conduct evincing an intention to
fulfill the party’s contract only in a manner substantially inconsistent with the
party’s obligations, so as to convey to a reasonable person in the situation of the
other party, renunciation of a fundamental obligation under the contract.144 Such a
situation can arise with a building contract, although it is well established that
repudiation is something not lightly found, and where, as here, the owners rely on
defects in the work constructed, they must collectively amount to something a good
deal more serious than just the usual collection of defects and deficiencies which
might easily occur in connection with the construction of any dwelling. The Court
of Appeal has held that contracts have not been repudiated despite frequent and
persistent breaches of terms, and emphasized that repudiation is not lightly found.145
If something done by one party can be characterized as effectively a refusal to
perform it will amount to repudiation, but it needs to be fairly clear and relate to all
142 Fox v Percy (2003) 214 CLR 118 at [25]; Rowe v Kemper [2009] 1 Qd R 247 at [3]; White v
Commissioner of Police [2014] QCA 121 at [6]; McDonald v Queensland Police Service [2018] 2
Qd R 612 at [47].
143 Fox v Percy (supra) at [27]; Teelow v Commissioner of Police [2009] 2 Qd R 489 at [4];
Commissioner of Police v Al Shakarji [2013] QCA 319 at [7], [65]; White v Commissioner of Police
(supra) at [8]; McDonald v Queensland Police Service (supra) at [47].
144 Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115 at [44], as
quoted in Gramotnev v Queensland University of Technology [2019] QCA 108 at [207].
145 Keswick Developments Pty Ltd v Keswick Island Pty Ltd [2011] QCA 379, admittedly a case about a
long lease at a nominal rent. See also Wash Investments Pty Ltd v SCK Properties Pty Ltd [2016]
QCA 258 at [35].
-- 57 of 68 --
58
or at least a substantial part of the obligations under the contract.146 I have already
discussed a number of decisions on repudiation, and will not repeat that discussion.
[211] The test for a sufficiently serious breach of a non-essential terms, also established in
Koompahtoo (supra), is that it has the effect of depriving the injured party of “a
substantial part of the benefit to which he is entitled under the contract.”147 In the
previous paragraph the majority referred to the relevance of the adequacy of
damages as a remedy for breach. They also said that this depended on the terms of
the contract.
- Encroachment
[212] I have referred earlier to the fresh evidence about the extent of the encroachment
exposed in the course of building work on the neighbouring property. I suspect
what happened was that, when the foundations were being excavated, the side of the
cut fell in, and this was then not blocked off with formwork, but this does not really
matter. In the event this was rectified by cutting off the encroaching bulge of
concrete, although a further encroachment, by the end of a pier at a lower level, was
left in place as it did not interfere with the works on the other property. I suspect it
will never be touched. The presence of the encroachment did not affect the
structural integrity or liveability of the house built by the builder, and the only
consequence was a liability for the cost of the removal work undertaken, which has
not been disclosed. It follows that damages are an adequate remedy, so it was not
itself a breach serious enough to justify termination, and is obviously not a
repudiation of the contract.
[213] The next issue is whether, taken with the other matters raised during the hearing, the
builder had repudiated the contract or committed sufficiently serious breaches of
inessential terms to entitle the appellants to terminate the contract at common law.
In relation to this, the appellant have unhelpfully not focused their submissions on
the more significant breaches, and have sought to rely on all defects in the work for
this purpose. After the hearing the written submissions of the respondent identified
a list of breaches other than the matters referred to in the notice to show cause, and
these were addressed by the appellant in the reply, and in submissions for the appeal.
I expect these were the matters actually litigated at the hearing, or at least the more
significant of the defects. I do not propose to trawl through the material to identify
and address everything that the appellants have ever referred to as a defect in the
work amounting to a breach of contract.
- Notice to Show Cause issues and backblocking
[214] Most of these individual matters have already been addressed in the course of these
reasons. With regard to the matters referred to in the Notice to Show Cause, the first
covered three alleged defects, plasterwork, the ensuite door and the concrete hobs.
[215] There had been some complaint about the plasterwork, investigated by experts who
found only minor defects, of no significance in this context. The appellants also rely
on the later discovery of an absence of backblocking, as shown by the evidence of
146 EMClarity Pty Ltd v BSO Network Inc [2022] QCA 177; Wash Investments (supra) at [33].
147 Koompahtoo (supra) at 140; cited in Gough v South Sky Investments Pty Ltd [2012] QCA 161 at
[31].
-- 58 of 68 --
59
the building expert called by them. As clarified in cross-examination, there was an
absence of backblocking in the upper level ceiling, although it was present in the
ceilings of the master bedroom and nursery.148 It was also absent from the library
and bedroom 2. The remedy was to remove the ceilings without backblocking, and
replace them with it. I accept that this was a matter of some significance, and could
contribute to a case justifying termination, although insufficient on its own.
[216] The next matter was the incorrect size of the ensuite door. The true position here
was that the builder was working with the architect to identify a suitable solution,
indicating that the defect would be remedied. The fact that the builder claimed an
entitlement to payment for a variation under the contract for this does not amount to
repudiation, as it was asserting a right under the contract, not insisting on something
regardless of the contract. This was something which required fixing, either by the
builder or someone else, but in the overall scheme of things, it was not a major
problem, and damages are an adequate remedy.149 The third issue was a visual
deficiency in the concrete hobs of the rooftop terrace. This is something which was
of no structural significance, did not prevent the occupation and use of the house,
and should have been easily remedied.150 Apart from the backblocking, none of
these matters was of any real significance.
- Delay etc
[217] The second ground in the notice, failing to proceed with due expedition and without
delay, has already been addressed. I do not regard it as a matter contributing much
to a case of repudiation. There was no apparent abandonment of the project, or any
lengthy period when no progress was made with the works (except at the beginning,
when there was a redesign because of an issue with a neighbour)151, a number of
extensions of time were given, and in other cases the refusal of extension of time did
not show an absence of due expedition or unreasonable delay. This was obviously a
complicated and difficult project, being constructed on a steep slope, and one where
there were a large number of changes to the design in the course of the works, many
of them in response to problems identified by the builder.152 The same applied to
ground 3. At the time the notice was given, the work was only about one month past
the date for practical completion as extended by agreed extensions. I do not accept
that the appellants can manufacture a ground for termination by refusing to agree to
requests for extension of time which were reasonable. Ground 6 is really in the
same category, and was largely dependent on grounds 2 and 3.
148 Day 3 p 42 – 46.
149 The appellants’ expert estimated that rectification would take two men half a day: Day 3 p 49.
150 According to the expert, one way to fix it was by painting the hobs: Affidavit of Allen sworn 3
September 2018 Exhibit RJA 40, Vol 5 p 1736. The expert said it was not necessary or reasonable to
replace the concrete hobs: Day 3 p 48.
151 Builder Day 2 p 52.
152 There were 106 formal requests for information to the Superintendent (Vol 7 p 1899) and the builder
said that there were many more informal ones: Day 3 p 16. Many revisions to the drawings were
issued, particularly in June, July and August 2017: Appeal Book Vol 8 p 2459, 60. Mr Allen said
that one fundamental drawing was reissued 27 times: Day 1 p 83. See also builder first statement
para 65, Vol 7 p 1898.
-- 59 of 68 --
60
- Overclaiming and subcontractors
[218] Ground 4 was the claims for payment in excess of the amount actually payable. I
have discussed this ground already, and regard these as mere technical breaches,
which are irrelevant for present purposes. Ground 5 was failing to obtain prior
approval for subcontracting. I have also discussed this ground earlier, and regard
these as little more than technical breaches as well, of no significance for present
purposes. None of the matters properly covered by the Notice to Show Cause
amounted to a sufficiently serious breach of non-essential terms, or made a
significant contribution to a plausible case of repudiation.
[219] The appellants submitted that there were twenty-four other subcontractors who had
not been approved,153 and that this was a more substantial issue than was indicated
at the time of the Notice to Show Cause, and showed that the builder was not willing
to comply with this obligation under the contract. The builder said that most of
these covered quite small amounts of work, usually just one man doing a bit of
work.154 Even if these were breaches of the contract, it is difficult to see that the
absence of approval had any significant effect on the delivery to the appellants of the
substantial benefit of the contract. On their own, I regard the breaches in this
category as of little significance. They would not contribute much to a case for
repudiation by the builder.
- Other Defects relied on
- Sarking
[220] Turning to the other issues litigated, the first was the complaint about the use of
sarking said not to comply with the National Construction Code. This was said to be
significant because to remedy it required the removal of the timber cladding and
replacement of the sarking, and the cladding. I have mentioned the evidence on this
topic earlier.155 Having considered it, including the oral evidence of the appellants’
expert witness, I agree with the Member that the appropriate conclusion is that there
was no breach of the Code, and hence no breach of contract by the builder at all.
The evidence showed that another sarking was more vapour permeable than the one
used, but that did not mean that the one used was not vapour permeable. The one
used was described as a Medium Vapour Barrier according to the expert. On the
data sheet produced by the builder it was more vapour permeable than the product
said by the expert to have been used, but in either case, the sarking was not
impermeable to vapour, so it was vapour permeable. The expert did not provide any
reason, such as a reference to a definition in the Code, to show that that was not
so.156 Even if the expert regarded the other sarking as more appropriate for use in
this context, his evidence did not show a breach of the Code. I consider this was
not proved to be a breach of contract at all.
153 Day 1 p 31.
154 Day 2 p 92.
155 See [26], [27] above.
156 I found his evidence as to what was vapour permeable membrane at Day 3 p 36 confusing.
-- 60 of 68 --
61
- Uncrimped gas pipe join
[221] The next issue was the failure to crimp an end of a gas pipe which had been
installed. Again I have already mentioned this issue. There was a short length of
copper piping which ran between the outside of the house near the corner of the
garage into an area above part of the ceiling of a room immediately below that part
of the garage, a store opening off the home office.157 The length of copper pipe was
quite short, and penetrated the concrete through a bored hole, then ran into a
connection with a different type of gas pipe as installed in the building, described by
the expert as PEX poly-pipe. There was to be a connection to the gas meter and
hence to the gas supply, but none of that had been done when the contract was
terminated. A photograph in his report showed the poly-pipe connection to the
connector had been crimped, but that the connection with the copper pipe had not
been crimped.158
[222] Accepting that the connection had been covered by the plasterboard, I consider that
this is properly regarded as an instance of incomplete work, an unfinished part of the
process after “roughing in” the gas piping. The evidence was that this piece of
copper pipe was really a “place filler” until they were in a position to connect the
gas to the external meter, which had not yet occurred.159 It was only when that
connection was put in that the need for crimping arose. That makes sense, and is
supported by evidence, and I accept it. I am not persuaded that it is a defect and
breach of contract at all; it is simply an example of uncompleted work. Even if it
were a breach, and crimping this connection had been overlooked, it was quite a
minor matter to rectify, since it was simply a matter of accessing the connection
through the plasterboard and crimping the end. This would have been picked up on
pressure testing before the gas was turned on, and really posed no risk.160
- Internal stairs
[223] The next issue was the internal stairs, which the appellants say were constructed
contrary to the National Construction Code and applicable standards, and have had
to be demolished and rebuilt. The expert identified problems with the stairs, that at
one point the head clearance was below the minimum of 2 m, and that some risers
were above the maximum of 190 mm.161 As well, there were gaps between the tops
and bottoms of the treads which were greater than permitted by the Construction
Code.162 He apparently did not check all the stairs, and by the time he saw the house
again, the stairs had been demolished. The builder agreed with the expert’s figures,
and said that there were problems with the stairs, caused by the design of the stairs
and changes in the levels of the slabs, and that he had been working with the
157 Report of expert Appeal Book Vol 9 p 2569. The site dropped steeply from the road, and the garage
was on a level above the level of the store room and the rest of the “ground floor”.
158 Report of the expert Appeal Book Vol 9 p 2570.
159 Letter from gasfitter Appeal Book Vol 11 p 2991.
160 Ibid.
161 Report of the expert in Appeal Book Vol 9 p 2574.
162 It is not clear from the report whether this last problem was due to an absence of the detailed edge
upstand along the back edge of the treads, mentioned in the report, or that it was inadequate, as
explained below.
-- 61 of 68 --
62
architects to try to work out a solution.163 The stairs had not been finished when the
contract was terminated.
[224] My examination of the plans demonstrated to me that there were design issues with
the stairs. I have looked at the design details for the stairs in the plans.164 The
elevation showed four flights of stairs, including two below the Ground Level,
which had risers of 180 mm; but the flights up and down from the (higher) Garage
Level were shown with risers of 190 mm. The Garage Floor level was shown as
44800, but there was a step down to 44620 to a landing at the top of the stairs down
to the Ground Level. Those stairs had only five steps before they passed under the
floor above the Ground Level, at 190 mm each, a drop of 950 mm. On the drawing
the landing had clearance to the base of the First Level of 1340 mm, giving a head
clearance of a minimum of 2290 mm.
[225] There must have been further changes, however, because the builder included in his
second statement part of Revision A of a drawing, which showed the garage floor
level of 44.700, although the floor level below remained at 42.100 m.165 The
drawing does not show the slab thickness, but I suspect this was before it was
increased to 250 mm.166 That occurred because the builder pointed out that the
office on the level below the garage extended beyond the garage door, and
something needed to be done to waterproof the slab at this point.167 This was passed
on to the engineers, and in the event the garage slab was increased in thickness to
250 mm. If the top of the slab had been 44.700 and the slab was 200 mm think, that
would have allowed exactly 2400 mm clearance above a floor at 42.100. That a
battened and lined ceiling produced a clearance of 2380 mm shows that the garage
slab was actually moved up in connection with these changes, not down as the
appellants suggested.168 But the real point here is that design changes were needed
because of deficiencies in the original design, which were not the builder’s fault.
[226] Subsequently on 15 September 2917 the architects gave a direction to the builder to
provide risers of 191.4 on the step down to the landing, and on the steps up from the
landing to the First Level.169 At some point as well, it appears that the level of the
garage floor was raised by the architect, perhaps by 100 mm,170 and as a result the
landing was raised, and that caused difficulties with the stairs down to the Ground
Level, as identified by the expert. As a result, the two flights of steps really required
redesigning, but that was not done before the contract was terminated. The problem
here is that the levels changed, but how this affected the stairs was not worked out
by the architects at the time, as it should have been.171
163 Day 2 p 29, 30.
164 Drawings 614 and 615, Appeal Book Vol 4 p 1275, p1265. See also Plan A3, at p 1243.
165 Appeal Book Vol 11 p 2782.
166 The original thickness was 200 mm: Engineers drawing 4.0 (Revision J), Appeal Book Vol 12 p
3150. Increased to 250 mm: Drawing 5.0 (Revision G) Appeal Book Vol 12 p 3156.
167 Email builder to architect 27 March 2017, Appeal Book Vol 11 p 2964. A solution was proposed to
the architects: p 2963, 4.
168 Affidavit of Allen sworn 23 May 2019 para 44; Appeal Book Vol 12 p 3109.
169 Appeal Book Vol 11 p 2295, p 2296.
170 Builder Day 2 p 28, 9.
171 See also letter architects to Mr Allen 22 May 2019, Appeal Book Vol 12 p 3116.
-- 62 of 68 --
63
[227] An examination of drawing 615 shows how the architects proposed originally to
ensure that the steps would be compliant with the maximum gap requirement. There
was to be a backboard 70 mm by 20 mm fixed to the back of each tread, so that the
gap above the backboard was 118 mm, within the 125 maximum. (The treads
tapered slightly from the front underneath.) Unfortunately this detail was based on a
tread spacing of 180 mm. If the tread spacing was 190 mm, unless the backboard
was changed, the gap would become 128 mm, non-compliant. Increasing the tread
spacing to 191.4 mm would only make this worse. The builder said in evidence that
the expert’s figures were correct, and he had raised the gap with the architects, and
they were proposing to put something in to narrow the gap again: Day 2 p 29, 30.172
[228] The builder said that the architects believed that they could get approval for the
over-height and changing risers, and the low ceiling, the latter on the basis that the
relevant rooms were not habitable rooms, but that did not occur.173 So far as the
variation in the stair risers was concerned, there was some justification for this, in
view of an email from the certifier on 11 September 2017.174 The builder was
confronted with the problem that the garage floor was changing, and hence the
levels were changing, and essentially this was because deficiencies in the design
emerged during construction. The builder has to follow the instructions of the
architect, who was also the superintendent, and it seems to me that essentially that
was what the builder was doing. After the termination of the contract, the stairs
were rebuilt to a different design.175 That shows that the real problem here was one
of design, and that the design issues had not been finalised at the time the contract
was terminated. I am not persuaded that this issue involved any breach of contract
by the builder at all, and this issue does not contribute anything to a case for
termination at common law.
[229] The appellants, in submissions on appeal para 513(a), said that the design issue was
in relation to the stairs leading up from the garage, not down to the kitchen level.
Those stairs had design faults, but that was not the stairs the expert was speaking of
in relation to the 2 m clearance issue. In relation to the stairs up from the Garage
Level, it is clear that the builder was just following directions of the architect, as it
was bound to do, and any problems were the fault of the architect, and involved no
breach of contract by the builder. The appellants’ submissions do not answer the
real point.
[230] The contract required the builder to construct the works in accordance with the plans
and specifications: Special condition 6.1. It also required the builder to comply with
all legislative requirements: Clause 11.1. In the event of an inconsistency, the
matter was to be referred to and resolved by the Superintendent: Clause 8.1. As
well, at the start of the architects’ drawings there is a General Note including the
statement that the architect’s interpretation of the contract documents shall be
final.176 As the architect was the Superintendent, both applied, and it follows that, in
172 Mr Allen said he would not have approved what the architect was proposing: affidavit sworn 23 May
2019 Appeal Book Vol 12 p 3112. This was a matter between him and the architect.
173 Builder second statement Appeal Book Vol 11 p 2782; Day 2 p 47
174 Appeal Book Vol 11 p 2992, stating tolerances in assessment of compliance of risers.
175 Affidavit of Allen sworn 23 May 2019 para 49; Appeal Book Vol 12 p 3110, 1. See also Report of
the expert in Appeal Book Vol 9 p 2576.
176 Appeal Book Vol 4 p 1225.
-- 63 of 68 --
64
essence, under the contract the builder had to do what the architect said to do, even
if it was contrary to the National Construction Code. Doing so involved no breach
of contract by the builder. It follows that it was not helpful for the appellants to
argue (as they did) that the architect had made a mistake, even if that were true.
[231] In my opinion, it follows that the demolition and reconstruction of the stairs was
essentially the result of design errors and changes made by the architects, and even if
the builder contributed to the problems in some small way, which I have not
identified, the reconstruction would have been necessary anyway and was not made
necessary by any breach of contract by the builder. Certainly the builder cannot be
blamed for doing what the architect instructed, and that cannot be part of a case for
termination. I doubt if there was a breach of contract at all, but it cannot contribute
to a case of repudiation. It was reasonable for the builder to have proceeded on the
basis that compliance with the design would satisfy the relevant legislative
requirements until the contrary emerged. It seems to me that, if the builder was just
doing what the Superintendent directed, the builder was not in breach of the contract
at all, because of Clause 8.1. At the very least, because the builder was trying to
comply with the contract, this could not amount to part of a case of repudiation.
Any problems sourced to the builder were not the major problems, and this also
cannot contribute to a case of substantial breach of inessential terms.
- Wet area work
[232] The next issue was what was said to be defective or incomplete work in wet areas.177
This largely consisted of a failure to install metal angles at the edges of wet areas,
where the tile floors would abut other floors. Such angles are certainly required, but
in circumstances where the tiling had also not yet been installed, the required angles
could easily have been installed, by the tiler or by someone else, before the tiles
were installed.178 This is an example of incomplete work, rather than defective
work.
[233] Apart from this, the expert identified a couple of areas where the waterproofing had
small penetrations, either nail holes or a corner scraped off.179 Accepting that these
were really defects, they were obviously minor and could not really contribute to a
case of repudiation, or of substantial breach.
- Water penetration at windows
[234] The next issue is some water penetration, to two areas of the house. The expert
identified some indicia of water penetration near the eastern windows of the library
on the first floor, and offered the plausible opinion that this had been driven through
inadequate sealing by north-easterly winds.180 He said that scaffolding or a cherry-
picker would be required to identify and reseal the leaks, although I cannot see from
the plans how a cherry-picker could be brought to the necessary position. At the
time the contract was terminated, scaffolding was in position to access these
windows from outside, so any absence of scaffolding is not the builder’s
responsibility.
177 As described by the expert, Appeal Book Vol 9 p 2577 – p 2580.
178 As the builder said was intended: Day 2 p 19.
179 The builder disputed that it was responsible for these: Second statement Appeal Book Vol 11 p 2789.
180 Appeal Book Vol 9 p 2584.
-- 64 of 68 --
65
[235] The other area identified was in the home office, which is located at the western end
of the ground level, essentially under the garage.181 There was evidence of water
staining on the plasterboard identified by the expert, at the bottom of a wall, and on
the ceiling next to a window, and the expert said the latter was typical evidence of
water penetration due to defective or omitted flashing or other sealing at the top of
the window frame. This could have also caused the other water problem, or it may
have been due to a waterproof membrane outside the retaining wall being penetrated
or otherwise failing to exclude water from the interior. The builder said that these
were examples of incomplete work, and final sealing had not yet occurred.182 The
Member said that rectification of them was the builder’s responsibility: [137]. The
expert witness said that he would have expected windows to be properly sealed
before plasterwork was put in place inside them.183 That makes sense, and I expect
that it was a mistake on the part of the builder to do the internal plasterwork as soon
as it did, for this and other reasons.184 There was no expert evidence however that
the plasterwork had been done too early. The Member seems to have accepted that
this was defective work, and I shall assume that it was.
[236] This water penetration was a matter of some significance, but not of great
significance. I assume it required proper sealing of the windows, and replacement of
the damaged plasterboard. It was certainly not grounds for termination alone; it may
contribute to grounds for termination, depending on the overall collection of relevant
defects.
- Penetrations of termite barrier
[237] The next issue was that there were penetrations to the termite barrier, which was in
the form of a chemical impregnated polymer sheet which lined the relevant walls.
The expert reported that on his inspection he saw multiple small punctures to the
sheets, likely to have occurred in the course of carrying out other work, and that
there had been larger penetrations to route gas, plumbing, electrical and air-
conditioning lines through vertical surfaces.185 He recommended that the installer
investigate the barrier, and carry out all necessary remedial work. Presumably that
was done, but there was no evidence about the extent of the work or how substantial
it was.186 In the circumstances, I assume that the necessary repair work was not
particularly substantial.
[238] It was submitted that this was really an example of incomplete work, as one would
expect penetrations to the termite barrier, including some clearly deliberate, would
entail subsequent rectification of the barrier. The Member appears to have treated it
as an example of defective work, and on that basis it could amount to a part, albeit a
small part, of a case for termination. I would expect however that, in a situation
where there had been only limited certification of the termite proofing to that point,
181 Appeal Book Vol 9 p 2585, 2586.
182 Builder Day 2 p 69; second statement para 45; Appeal Book Vol 11 p 2789. This was supported by
the glaziers: Appeal Book Vol 11 p 2938. The appellants’ evidence was that the relevant windows
were finished, even if others were not: affidavit sworn 23 May 2019 para 21.
183 Day 3 p 50.
184 The builder may have felt under pressure from the appellants to expedite the job.
185 Appeal Book Vol 9 p 2588.
186 Reports from the pest control specialist exhibited to the affidavit of Mr Allen sworn 26 March 2019
as RJA 108 and RJA 109 Appeal Book Vol 10 p 2735, 2738, deal with other matters.
-- 65 of 68 --
66
further termite-proofing work would have been done on the house before completion
and it may well have been convenient to have rectified these penetrations at that
point.187 In any case, there was no expert evidence that the penetrations of the
termite barrier were not susceptible to reasonable repair. It was not suggested that
the significant wall penetrations shown in the photographs were not in accordance
with the design, and if so, there was not much else the builder could have done.
Overall, in my opinion this is an example of incomplete work.
- Unapproved subcontractors
[239] There were some other matters relied on by the appellants as grounds for
termination, or as contributing to an overall case for termination. The appellants
relied on additional instances of unapproved sub-contractors. As I said before, I
really cannot regard this as a matter of any great importance, since the important
objective of the contract was to provide the appellants with the house in accordance
with the contract, and it is difficult to see how they are worse off in any practical
sense if some work is done by unapproved subcontractors, so long as it is properly
done. If it was not properly done, that is the real issue, not whether or not the
subcontractor was approved. I do not regard this as contributing to a case for
termination at common law. It certainly did not deprive the appellants of a
substantial part of the benefit to which they were entitled under the contract.
- Other issues
[240] Some other issues seem to have been at least ventilated at the hearing. The
appellants complained that the house as built was too close to the boundaries in
breach of the development approval, requiring an application for amended approval,
which was granted.188 Given the absence of any significant consequences, this is
really not a relevant issue, as the Member said: Day 2 p 43. In any case, it was not
claimed that the house was not built in accordance with the design, and if the house
was not designed to fit the required set-backs, that was a defect in the design, not the
fault of the builder.
[241] The appellants complained that the windows supplied were not the brand specified.
That was true, because, according to the builder, the nominated window supplier
stopped dealing with that brand, and used a different brand instead, said to be just as
good.189 That last point was not contradicted, and if true this was a technical breach
only and could not contribute to a case for termination.
[242] The appellants complained about the failure to install the pivot doors at the front and
one side.190 These were frameless glass doors, and said by the builder (and by the
supplier) to be uncertifiable under the National Construction Code as they were not
waterproof.191 Mr Allen disputed this, but on my reading the Code does not provide
187 The builder said that additional termite protection work was to be done: Day 2 p 109.
188 Affidavit of Allen sworn 13 November 2020 Exhibits RJA150, RJA151.
189 Builder second statement, Appeal Book Vol 11 p 2778.
190 Affidavit of Allen sworn 23 May 2019 para 30, Appeal Book Vol 12 p 3107. In this case, he seems
to be insisting on the drawings and specifications in preference to the requirements of the National
Construction Code.
191 Builder Day 3 p 25 – 30. As well, he was waiting for details about the type and location of the lock:
Second statement para 10, Appeal Book Vol 11 p 2780. Supplier: Appeal Book Vol 11 p 2938.
-- 66 of 68 --
67
for frameless glass doors as a waterproofing method. However, Mr Allen admitted
that the front door could not be installed until the cabinetwork had been delivered, to
allow access for it,192 which had not occurred when the contract was terminated.
This was therefore not an issue, and at best an example of incomplete work.
[243] There was a complaint about the thickness of the external fibre cement sheeting,
covered by the Member at reasons [143]. The position was as he described, and I
agree with his conclusion. This is not an issue. As to the issues of illegality, the
only one identified of any real significance was continuing to work before obtaining
a clear certificate at the frame stage, discussed earlier, and the only adverse
consequence was that an inspection or inspections had to be done again. I do not
regard this as contributing to a case for termination, in view of the absence of
evidence of impact on the appellants.
[244] There were complaints that some gas lines had not been run as required by the
drawings, and that some of the electrical work was defective.193 This does not
appear to have been raised with the builder in cross-examination, or to be supported
by other evidence, or evidence about rectification, and in those circumstances I
cannot draw any conclusions about it as a matter of any real significance. This is a
consequence of the appellants’ failure properly to identify the factual basis for their
case for termination. As I have said, I am not going to dig around in the material to
attempt to identify any other examples of defects or other breaches which would be
capable of making a real contribution to a case for termination.
Consideration and conclusion
[245] I have mentioned a number of cases dealing with, and to some extent applying, the
relevant legal principles, generally cases involving different types of contracts.
Those principles were applied, in a case involving a domestic building contract, in
Mousa v Vukobratich Enterprises Pty Ltd [2019] QSC 49. In that matter the builder
was found to have repudiated the contract by an inability to perform. A large
number of individual defects, found to be the fault of the builder, were identified in
the decision. The major ones were inadequate waterproofing of retaining walls
leading to water seepage (rectification cost estimated at $223,642), inadequate
undercroft retaining walls (rectification cost $42,268), groundwater collection at
undercroft (rectification costs $19,511), extensive water penetration of external
doors and windows (rectification cost $160,000 if the doors and windows can be
reused), extensive problems in the roof construction (rectification costs $116,000),
inadequate structural support for the atrium glass wall (rectification costs $22,500),
cracking of the concrete pool (rectification costs $21,195), spalling of a blockwork
wall (rectification cost $18,500), ceiling height lower than specified in the contract
(rectification costs $44,348) and poor external painting (rectification costs $65,494).
There were a further eighteen more minor defects, and the total cost of rectification
of all defects was found to be $818,227 plus GST.
[246] The cost of completing the construction of that house as required by the contract was
found to be $1,145,661.67, not including rectification costs, although there was a
deduction of $575,130.62 as the unpaid balance of the contract amount. The
192 Affidavit of Allen sworn 26 March 2019 page 21, Appeal Book Vol 10 p 2623.
193 Affidavit of Allen sworn 19 October 2018 paras 44 – 59, Appeal Book Vol 6 p 1756, 7.
-- 67 of 68 --
68
original contract sum was $2,100,000, and there were found to be a number of
variations for which an additional $180,758.51 was allowed. By contrast, in the
present case the builder said that there was $778,893.99 owing for work done but
not paid for,194 covering six weeks work, the last progress claim having been due to
be certified just after the contract was terminated.195 He also said there was another
$600,000 left to claim in the contract.196 Mr Allen said that the estimated cost of
his brother’s finishing the house was $761,000.197
[247] In Mousa the owners terminated for repudiation in December 2015, and that
entitlement was upheld by his Honour. The owners relied on the defects, and on
unjustified claims for variations, non-compliant progress claims and unfounded
claims for sundries. The evidence was that the builder sought payment of various
amounts from time to time, not related to the scheme for payment under the contract.
But repudiation was found on the basis of the extensive defects providing
“overwhelming evidence of repudiation”, showing that the construction was beyond
the builder’s competence: reasons [193].
[248] Obviously that represents a very clear case of repudiation, and does not represent a
necessary standard of default to be attained. But it stands as a very marked contrast
to the present case, where the only significant defects were the encroachment onto
the neighbouring land, the absence of backblocking in parts of the plaster ceilings,
and to a lesser extent water penetration through inadequately sealed windows. There
were some additional minor matters, but on the whole they do not show either a
refusal, or an inability, to perform the contract other than in a manner substantially
inconsistent with its terms. Applying the approach in the authorities referred to
earlier, in my opinion the behaviour of the builder in the present case has not been
shown to have amounted to repudiation of the contract, so as to give rise to an
entitlement to terminate on that basis at common law.
[249] As for the alternative ground, on the basis of a collection of breaches amounting to
sufficiently serious breaches of non-essential terms, I do not consider that the
breaches of contract which have been demonstrated, taken together, amount to a
sufficiently serious set of breaches of non-essential terms to entitle the appellants to
terminate on that basis at common law, since they did not deprive the appellants of a
substantial part of the benefit which they were entitled to under the contract. I
consider that damages were an adequate remedy for such breaches as have been
proved by the appellants. It follows that, on this basis as well, the appellants were
not entitled to terminate the building contract at common law.
[250] There is therefore no reason to interfere with the conclusion of the Member, that the
appellants had not validly terminated the contract with the builder, and accordingly
the decision of the respondent to reject their claim under the insurance policy was
correct. The decision of the Appeal Tribunal is that the appeal is dismissed, and
although leave to appeal was granted, limited to one ground, the appeal by leave is
also dismissed. Otherwise, the application for leave to appeal is refused. I shall
give directions as to any dispute as to costs.
194 First statement para 79, Appeal Book Vol 7 p 1900.
195 Day 3 p 21, 2.
196 Day 2 p 76.
197 Day 1 p 94. The figure was presented as if it included rectification of existing defects.
-- 68 of 68 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2023/066