Built Qld Pty Limited v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2022] QCA 266 (2022) 13 QR 148
SUPREME COURT OF QUEENSLAND
CITATION: Built Qld Pty Limited v Pro-Invest Australian Hospitality
Opportunity (ST) Pty Ltd [2022] QCA 266
PARTIES: BUILT QLD PTY LIMITED
ACN 108 064 099
(appellant)
v
PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (ST) PTY LIMITED (FORMERLY
KNOWN AS AUSTRALIAN HOSPITALITY
OPPORTUNITY (ST) PTY LTD) AS TRUSTEE FOR
THE PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (BRS SPRING HILL) TRUST
ACN 163 479 221
(respondent)
FILE NO/S: Appeal No 14730 of 2021
SC No 5426 of 2017
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane – [2021] QSC 224 (Williams J)
DELIVERED ON: 20 December 2022
DELIVERED AT: Brisbane
HEARING
DATES:
12 and 13 September 2022; further written submissions
received on 27 September 2022, 17 October 2022 and
14 November 2022
JUDGES: Morrison and Dalton JJA and Bradley J
ORDERS: 1. Appeal allowed.
2. Direct that the parties are to calculate the amount in
which the Court ought to order judgment, including the
amount for interest.
3. Direct that the parties are to attempt to agree an
appropriate order as to costs. If the parties cannot
agree, each party is to file written submissions as to
costs, no longer than five pages each.
4. The written submissions as to the amount in which the
Court should order judgment, and as to costs, are to be
filed by 15 February 2023.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
-- 1 of 50 --
2
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – where the respondent issued an
invitation to tender to design and construct a hotel – where the
invitation to tender required that tenders comply with the
respondent’s specifications and drawings (the Thwaite
Documents) – where the appellant submitted a tender on an
alternative basis for air conditioning (the Alternative Proposal)
– where the appellant and respondent entered into a contract
based on the acceptance of the appellant’s Alternative
Proposal, provided it met the performance requirements of the
Thwaite Documents – where the respondent issued a defects
notice to the appellant (the 11 August notice) – where the
11 August notice asserted that the air conditioning system
which was partly installed by the appellant was defective
because it did not allow mode control in individual rooms –
whether extrinsic evidence could be used to interpret the
meaning of the Alternative Proposal – the meaning of
“performance requirement” – whether the Thwaite Documents
contained a performance requirement as to mode control in
individual rooms – whether the air conditioning system which
was partly installed by the appellant was defective
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – VARIATIONS – where the
11 August notice directed a variation to the contract – where
the 11 August notice was a “qualifying cause of delay” under
the contract – where the contract required the appellant to give
the respondent a written claim for an extension of time (EOT)
within 14 days of when the appellant should reasonably have
become aware of the qualifying cause of delay – whether the
primary judge erred in finding that the appellant’s claim for an
EOT was delivered outside the 14 day period – when the appellant
became reasonably aware of the qualifying cause of delay
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – where the contract provided that
the appellant was not entitled to an EOT if it contributed to the
qualifying cause of delay – whether the appellant contributed
to the qualifying cause of delay by failing to provide shop
drawings when required to do so by the contract – where the
shop drawings would have revealed the lack of mode control
in individual rooms – where, prior to the contractual date to
provide shop drawings, the appellant provided schematics to
the respondent which indicated that the system would not have
mode control – whether the appellant contributed to the
qualifying cause of delay or to the delay in practical completion
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
-- 2 of 50 --
3
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – where the contract provided that
the appellant was entitled to an EOT if the appellant has taken
all reasonable steps to mitigate the effect of the delay – where
the appellant required equipment to install the new air
conditioning system as directed by the 11 August notice –
where, despite the appellant’s enquiries, the respondent did not
confirm whether it approved of the equipment the appellant
required – whether the appellant took all reasonable steps to
mitigate the delay caused by the need to order new equipment
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – where the appellant was entitled
to an EOT – where the primary judge did not make findings as
to the EOT to which the appellant was entitled – where the
primary judge did not give reasons – whether the contract
permitted a retrospective or prospective approach to assess the
delay to practical completion – whether the Court must
determine the EOT only on the material which was available
to the superintendent at the time the EOT was assessed –
assessment of the EOT
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – where the contract provided that
the appellant was entitled to a claim for delay damages
reasonably and necessarily incurred by the appellant by reason
of a variation – whether the appellant was entitled to delay
damages consisting of time-related on-site overheads incurred
during the period of critical delay – what is the time period
over which the delay damages were suffered – whether the
costs claimed by the appellant were necessarily and reasonably
incurred – whether the overhead costs were included in the
value of the variation under the contract
Akot Pty Ltd v Rathmines Investments Pty Ltd [1984]
1 Qd R 302, applied
Ascon Contracting Ltd v Alfred McAlpine Construction Isle
of Man Ltd (1999) 66 Con LR 119, cited
Bank of New Zealand v Simpson [1900] AC 182; [1900]
UKLawRpAC 6, cited
Beale v Government Insurance Office of NSW (1997)
48 NSWLR 430, cited
Beaufort Developments (NI) Ltd v Gilbert-Ash NI Ltd [1999]
1 AC 266; [1998] 2 All ER 778; [1998] UKHL 19, considered
Bwllfa v Merthyr Dare Steam Collieries (1891) Ltd v
Pontypridd Waterworks Co [1903] AC 426; [1903]
UKLawRpAC 46, applied
Civil Mining & Construction Pty Ltd v Wiggins Island Coal
Export Terminal Pty Ltd [2017] QSC 85, considered
-- 3 of 50 --
4
CMB No. 1 Pty Ltd v Cairns City Council [1999] 1 Qd R 1;
[1997] QCA 456, cited
Codelfa Construction Pty Ltd v State Rail Authority of NSW
(1982) 149 CLR 337; [1982] HCA 24, applied
Daysea P/L v Watpac Aust P/L [2001] QCA 49, cited
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978)
138 CLR 423; [1978] HCA 12, applied
Dura (Australia) Constructions Pty Ltd v Hue Boutique
Living Pty Ltd (2013) 41 VR 636; [2013] VSCA 179, considered
Elliott v Lawrence [1966] Qd R 440, cited
Euronav NV v Repsol Trading SA The MT MARIA [2022]
2 All ER (Comm) 65; [2021] EWHC 2565 (Comm), cited
Hope v RCA Photophone of Australia Pty Ltd (1937)
59 CLR 348; [1937] HCA 90, applied
House of Peace Pty Ltd v Bankstown City Council (2000)
48 NSWLR 498; [2000] NSWCA 44, cited
HTW Valuers (Central Queensland) Pty Ltd v Astonland Pty
Ltd (2004) 217 CLR 640; [2004] HCA 54, cited
Johnson Controls Australia Pty Ltd v Webb Australia Group
(NSW) Pty Ltd (2003) 96 ACSR 640; [2013] NSWSC 1511,
applied
Keays v JP Morgan Administrative Services Australia Ltd
(2012) 224 IR 406; [2012] FCAFC 100, applied
Kembla Coal & Coke Pty Ltd v Select Civil Pty Ltd [2004]
NSWSC 628, cited
King & Ors v Australian Securities and Investments
Commission [2018] QCA 352, cited
Kizbeau Pty Ltd v WG & B Pty Ltd (1995) 184 CLR 281;
[1995] HCA 4, cited
Macdonald v Longbottom (1859) 1 El & El 977;
120 ER 1177; [1859] EngR 635, considered
Macdonald v Shinko Australia Pty Ltd [1999] 2 Qd R 152;
[1998] QCA 53, considered
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104; [2015] HCA 37, applied
Prenn v Simmonds [1971] 1 WLR 1381; [1971]
3 All ER 237, applied
Proctor v Chahl [2008] NSWSC 1252, cited
Provincial Insurance Australia Pty Ltd v Consolidated Wood
Products Pty Ltd (1991) 25 NSWLR 541, applied
Republic of Turkey v Mackie Pty Ltd & Anor [2019]
VSC 103, cited
Rightside Properties Ltd v Gray [1975] Ch 72; [1974]
2 All ER 1169, cited
Schelde Delta Shipping BV v Astarte Shipping Ltd (The
Pamela) [1995] CLC 1011, cited
SDA v Corporation of the Synod of the Diocese of
Rockhampton (2021) 8 QR 440; [2021] QCA 172, cited
SSC Plenty Road Pty Ltd v Construction Engineering (Aust)
Pty Ltd & Anor [2016] VSCA 119, cited
Stockland Property Management Pty Ltd v Cairns City
-- 4 of 50 --
5
Council [2011] 1 Qd R 77; [2009] QCA 311, cited
TAL Life Ltd v Shuetrim; Metlife Insurance Ltd v Shuetrim
(2016) 91 NSWLR 439; [2016] NSWCA 68, cited
Thiess Watkins White Construction Ltd v Commonwealth
(1998) 14 BCL 61, cited
V601 Developments Pty Ltd v Probuild Constructions (Aust)
Pty Ltd [2021] VSC 849, cited
Walton v Illawarra [2011] NSWSC 1188, cited
Wesfarmers Kleenheat Gas Pty Ltd v Elgammal [2006]
NSWSC 1248, cited
COUNSEL: P L O’Shea KC, with M Steele and B A Reading, for the
appellant
T P Sullivan KC, with M Doyle, for the respondent
SOLICITORS: Clayton Utz for the appellant
Thomson Geer for the respondent
[1] THE COURT: By a contract, which was a modified version of AS 4902-2000, dated
29 April 2015, the appellant promised to design and construct a building to be known
as the Holiday Inn Express Spring Hill Hotel. The appellant was the plaintiff below.
It made several claims against the respondent arising out of the building contract.
This appeal is concerned with only one of them: the ramifications of a defects notice
issued to the appellant by the superintendent1 on 11 August 2016 (the 11 August
notice). It directed the appellant to remove such parts of the air conditioning system
as it had installed, and to install an air conditioning system which complied with the
contract. The appellant’s case was that the 11 August notice amounted to a direction
to vary the contract so that it was entitled to: (1) the price of the varied work; (2) an
extension of time (EOT), and (3) delay damages. The appellant was entitled to
succeed on these claims below. Therefore the appeal must be allowed.
The tender process
[2] The respondent issued an invitation to tender dated 1 November 2014. The invitation
to tender provided that the tenderer was to submit a tender in strict conformity with
the tender conditions. However, cl 8(4) of the invitation to tender provided:
“The Tenderer may also submit alternative tenders containing
qualifying conditions or exceptions and the sums of money which are
directly attributable to such conditions or exceptions set out in an
Alternative Tender Qualifications Form contained in Schedule 2. The
acceptance of any alternative tender subject to qualifying conditions
or exceptions is entirely at the discretion of the Principal.”
[3] To comply with the tender conditions it was necessary that the appellant specify an
air conditioning system which complied with a document called “Mechanical
Services Specification Hotel Project 168-184 Wharf Street, Spring Hill, Queensland”
prepared by Thwaite Consulting Group, and some drawings (the Thwaite
specification and the Thwaite drawings, compendiously the Thwaite documents). In
the Thwaite specification, Thwaite described itself as the “Consulting Engineer”,
which must mean the engineer consulting to the respondent.2 The Thwaite
1 Under the building contract the superintendent was the principal’s agent, cl 20.
2 This was apparently by way of a subcontract; Thwaite’s contract was with the respondent’s project manager.
-- 5 of 50 --
6
specification also described Thwaite’s role as including the review of tenders received
and the analysis of technical data and calculation methods.
[4] Despite the fact that the contract was a design and construct contract, the Thwaite
specification was prescriptive. It described in close detail a system which was to
provide air conditioning from “chilled water and heating hot water from a common
air-cooled 4 pipe chiller (heat recovery type) located on the roof” – cl 2.2.1.
[5] The appellant submitted a tender dated 19 January 2015. It provided a price of nearly
$34 million for a conforming design and construction, but presented an alternative
design and construction price for some elements, including the air conditioning. The
appellant’s alternative price for air conditioning was nearly $800,000 cheaper. The
tender contained a schedule entitled “Built Design & Construct Alternative Tender
Clarifications”. As to air conditioning, this said:
“Built in conjunction with our preferred subcontractors have reviewed
the documented design criteria and have offered an alternative Air
Conditioning system based on VRF type arrangement.
The system proposed provides a more efficient solution in terms of the
running costs due to the equipment operates on a variable power
supply and without the need for stand alone controls and variable
speed drives which inherently are costly and complex to program and
operate. Additionally, the proposal also adopts a revised pipe and duct
configuration, thus reducing the initial cost of these components.”
The contract
[6] The contract price was based on acceptance of the appellant’s alternative air
conditioning tender, and some other alternative tenders.
[7] The general conditions of contract obliged the contractor to prepare design documents
and then carry out the construction works in accordance with them – cl 2.2(a)(iii) and
(iv). This was called WUC (work under contract). This involved an obligation, where
there was a preliminary design prepared by the principal, to develop that design into
design documents and then construct in accordance with those design documents. In
relation to the air conditioning system there was a preliminary design, as that term is
defined in the contract; it was the Thwaite documents.3
[8] To cater for the fact that the contract was, in some respects, on the basis of alternative
(rather than conforming) parts of the appellant’s tender, the contract introduced
a defined term, “clarifications”. This meant “the clarifications to the Works or the
contract sum set out in Annexure Part O”. Clause 8.1(a)(ii) of the contract then
provided for an order of precedence including that “the clarifications have precedence
over the preliminary design”.
[9] Annexure O containing the clarifications was poorly drafted. It contained only one
provision, a cl 1 which began, “WUC includes:”. There followed a very long list of
sub-paragraphs, some of which were capable as being read with the short chapeau of
cl 1, and others of which were not. Subclause (u) provided:
3 Definition of preliminary design in cl 1 means “the documents stated in Annexure Part K”. In Part K
items M00 - M12 are the Thwaite drawings; the Thwaite Mechanical Services Specification October
2014 is a separate item in Annexure K.
-- 6 of 50 --
7
“The Contractor’s alternative proposal for structural and mechanical
systems on the basis that the Contractor meets the performance
requirement of the tender drawings and specifications.”
The description “mechanical systems” can be read as meaning air conditioning, at
least for the purpose of this judgment.
[10] The last of the sub-paragraphs in Annexure O, (ag), was not capable of being read as
following on from the cl 1 chapeau. It said:
“(ag) Refer VE items listed below:
(i) Mechanical Services: The Contractor, in conjunction
with its preferred subcontractors has reviewed the
documented design criteria and has offered an alternative
air conditioning system based on VRF type arrangement.
The system operates on a variable power supply and
without the need for stand alone controls and variable
speed drives. Additionally, the proposal also adopts
a revised pipe and duct configuration.
…”
[11] We were told the “VE” meant “value engineering”. It appears that sub-paragraph
(ag) lists (at least initially) information relevant to parts of the appellant’s alternative
(non-conforming) tender which are taken from the descriptions it provided of those
non-conforming items in its tender document. The information in subclause (ag)(i)
is of this type. Trying to give some meaning to subclause (ag)(i) in accordance with
the principles in Mount Bruce Mining v Wright Prospecting Pty Ltd,4 we interpret it
as giving some further information as to what “the Contractor’s alternative proposal”
in subclause (u) is. This interpretation is based on the substance of the information
in cl (ag)(i).
Types of air conditioning systems
[12] A difficulty which is at the factual centre of this dispute is that, even with the
additional detail contained in subclause (ag)(i), the contract contains little meaningful
definition about the alternative air conditioning system which the appellant
contracted to provide. The conforming system specified in the Thwaite documents
was for a 4 pipe heat pump system which air conditioned by providing chilled water,
or heated water, to each individual room on demand from the occupant of that room.
A guest in a hotel room equipped with the Thwaite designed air conditioning system
could select whether they wanted the system to provide heating or cooling (mode
control), and could specify the temperature (within a range) that the room was to
reach. The air would be conditioned by means of heated or chilled water being piped
to a fan coil unit (FCU) located in the ceiling of each individual room.
[13] The appellant’s alternative VRF (aka VRV) system was not a heat pump system, but
a reverse cycle system. It did not use heated or chilled water, but a piped system of
refrigerant gas. The occupant of the room had no option to choose between a heating
or cooling function, but simply an option to specify a desired room temperature.
4 (2015) 256 CLR 104.
-- 7 of 50 --
8
[14] Not all VRF systems are the same. They come in 2 pipe and 3 pipe systems. Unlike
the 2 pipe system which the appellant proposed in its alternative tender, a 3 pipe VRF
system will give the occupant of a room mode control. One manufacturer, Mitsubishi,
makes a 2 pipe VRF system which gives the occupant of each room mode control.
Two pipe VRF systems (other than Mitsubishi systems) work according to zones
ascribed to parts of the building which experience similar thermal conditions. For
example, if an individual room is located in a zone which is particularly sunny, the
air conditioner in that room is likely to operate primarily on cooling mode.
[15] The description of the appellant’s alternative proposal in its tender, and ultimately in
the contract, allowed the conclusion that it was obliged to provide a VRF system, but
did not allow a conclusion as to whether or not the occupant of each individual hotel
room would have mode control. An inherent feature of the 4 pipe chiller system
prescribed by Thwaite was that the occupant of each individual room would have
mode control.
CHARACTERISATION OF THE 11 AUGUST NOTICE
[16] On its face, the 11 August notice was a defects notice given pursuant to cl 29.3 of the
contract. That clause provided that if the superintendent became aware of work
performed by the contractor which did not comply with the contract, the
superintendent could order the contractor to demolish the work; remove it from site,
and make good the work. The 11 August notice specified 11 respects in which it was
said the air conditioning works installed to that point did not comply with the contract.
It was scattergun in its approach. Some of the complaints lacked particularity;5 others
did raise specific points said to be not in accordance with the performance
requirements of the contract.6 Some complaints seemed to cavil with the fact that
essential elements of a chilled water system, rather than a VRF system, had not been
provided.7
[17] The dispute litigated related only to complaints 10 and 11 which relied upon cll 9.4.2
and 9.4.5 of the Thwaite specification. These paragraphs of the 11 August notice
said:
“10. 9.4.2 Chiller Sequencing … This specification allowed fan coil
units in individual rooms to provide either cooling or
heating independently across all individual hotel guest
rooms. The Alternative VRV system offered by the
contractor does not comply with the Contract.
11. 9.4.5 CHW/HHW FCUS FOH+BOH areas … This specification
allowed different coils in rooms to have different cooling
or heating demands – this has not been satisfied with the
installed alternative.”
[18] The respondent’s case in this litigation was that the partly installed air conditioning
system was defective because it did not give the occupant of each individual room
mode control. It was not in dispute that the 2 pipe VRF system which the appellant
5 Complaint 2.1.2, “The alternate VRV system offered by the Contractor is required to meet the
performance requirements of the Chilled Water (CW) system”.
6 For example, complaints 2.2.1 and 2.2.2.
7 See complaints 2.2.1 and 4.2.
-- 8 of 50 --
9
had installed prior to 11 August 2016 did not allow mode control in individual guest
rooms. The appellant’s case was that the contract did not oblige it to make provision
for mode control in individual guest rooms. This argument had two independent
limbs. First, subclauses (u) and (ag)(i) did not give proper definition to the appellant’s
obligation to build the air conditioning system, so that resort to extrinsic evidence
was necessary and permissible to define its obligation. Secondly, subclauses (u) and
(ag)(i) obliged it to install a VRF system which complied with the performance
requirements of the Thwaite specification, and that there was no performance
requirement that each individual room have mode control. We will deal with each of
these limbs in turn.
Extrinsic evidence
[19] The appellant submitted that there was uncertainty in the contract as to what was
meant by the expression “the Contractor’s alternative proposal” in subclause (u). In
those circumstances, it asked the Court to look at emails exchanged between the
appellant and respondent between tender and contract in order to understand what it
was the parties had agreed the appellant would design and construct by way of air
conditioning system for the hotel. A summary of the emails which do no more than
describe the system the appellant proposed to design and construct is as follows.
(a) On 30 March 2015 the appellant wrote to the respondent’s project manager.
One of the attachments to the email was a drawing called “Typical Floor VRF
2-pipe.pdf”. The body of the email read:
“Please see attached the proposed AC layout and piping
configuration … for your acceptance prior to documenting the
design.
We note that A/C zones will be divided into two zones to cater
for different heat loads on the building façade and units will be
combined vertically over a number of floors off the same
condenser …
…
Could you please provide your approval/acceptance so we can
commence design documentation.”
The attached schematic drawing showed a 2 pipe VRF system and bore, in red,
the proprietary brand name Toshiba next to the depiction of the condenser.
(b) The project manager replied to the appellant on the same day saying that
Thwaite had raised a number of issues which needed clarification “on [or] prior
to confirming acceptance”. One issue raised by Thwaite was, “Are the VRV
systems proposed to be heat recovery type or reverse cycle type? If the former
are they 3 pipe or 2 pipe type? If the latter is the placement of FCUs proposed
to be consistent with the façade they are mounted on (similar thermal zone)”.
(c) The appellant replied on 31 March 2015:
“Our proposal utilises reverse cycle 2 pipe configuration. All
FCU’s will be located as per original design and all condensers
will be located on mechanical plant deck on roof”.
-- 9 of 50 --
10
The reply discloses the use of Toshiba equipment.
The appellant ended this email, “Please let me know if further clarification or
a meeting is required to discuss”.
(d) The appellant’s 31 March email was sent by the project manager to Thwaite.
Thwaite responded with an email sent to both the appellant and the project
manager saying, “I note your other comments and they are OK with the
exception of [a matter not relevant to this appeal]”.
Thwaite went on to say:
“The meeting proposed is to dot the iiiiis over what is the actual
scope of work of the mechanical services contract which you
believe that you have signed up for and to look at where it differs
from the specified/tender documents. The hotel operator also has
particular requirements which will need to be addressed as line
items and presented to them so that any non-compliances with
their standard brief are itemised and explained.
…
Regardless I think it is encumber on you to provide a signed off
‘contract document’ that clearly explains where you differ from
the tender documents so that it is recorded and leaves no doubt
on the scope.”
(e) The appellant responded to that email saying:
“We have not been provided with a [hotel operator] Brief other
than the Tender Drawings and specification, and as such this is
all we have to work with in terms of criteria (despite the
conforming being a Chilled Water System which is obviously
different in many ways). The offer of a conforming and
alternative were provided at Tender with the Client electing to
adopt the alternative at a significantly reduced price.
…
… We will certainly be providing an Engineered Certified
system, Form 15 with drawings. Prior to documenting we are
seeking acceptance of the system in terms of meeting the
performance requirements stipulated by the tender documents
and its ability to satisfy the clients requirements. Once agreed
we will formalise the design by way of Engineered drawings and
a Form 15 design certificate.
...”
(f) The other relevant email is one from the appellant to the project manager dated
9 April 2015. It read:
“See attached below and attached our Mechanical Consultants
comments regarding the proposed design as well as their
comments in relation to the [hotel operator] standards.
-- 10 of 50 --
11
Please note that largely the [hotel operator] Standard and Thwaite
design is based on Chilled Water therefore large sections of the
design are not applicable hence we have not marked up the
specification but rather commented separately.
…
We therefore seek your urgent approval of the proposed so we
can move forward on Design.”
The attached letter from the appellant’s mechanical consultants included the
following:
“Air conditioning for the building is proposed to be of the
Variable Refrigerant Flow (VRF) type, in lieu of chilled water
systems, with condensing units located on Level 1 podium and
roof (refer attached sketches).
The VRF systems will be of the 2-pipe heat-pump type, and
zoned such that areas with different solar loads are served by
separate plant.
…
In general, the remainder of the current building mechanical
services design (documented by Thwaite Consulting Group) will
not be altered in principle.”
[20] The appellant relied upon a series of cases, beginning with Macdonald v
Longbottom,8 for the proposition that facts known to both contracting parties could
be referred to in order to give meaning to the expression “the Contractor’s alternative
proposal” in subclause (u) of Annexure O. The primary judge rejected this contention
but erred, with respect, in thinking that the Macdonald v Longbottom line of cases
required ambiguity in the contract before resort was had to extrinsic evidence to
identify the meaning of a descriptive term in the contract. That is not so, and it is not
a conclusion required either by the judgment of Justice Mason in Codelfa
Construction Pty Ltd v State Rail Authority (NSW)9 or any of the judgments in Mount
Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd.10
[21] Like the job description in Keays v JP Morgan Administrative Services Australia
Ltd,11 the expression in subclause (u), “the Contractor’s alternative proposal”, has
virtually no meaning unless reference can be made to extrinsic circumstances. In that
sense it is like the expressions “my motor car” or “my shop” referred to by Latham CJ
in Hope v RCA Photophone of Australia Pty Ltd,12 and the expression “your wool” in
Macdonald v Longbottom. It fits comfortably within the exception to the parol
evidence rule recognised by Lord Wilberforce in Prenn v Simmonds: “Moreover, at
any rate since 1859 (Macdonald v Longbottom) it has been clear enough that evidence
of mutually known facts may be admitted to identify the meaning of a descriptive
8 (1859) 1 El & El 977; 120 ER 1177.
9 (1982) 149 CLR 337, 352.
10 Above.
11 (2012) 224 IR 406, 422, [69].
12 (1937) 59 CLR 348, 356.
-- 11 of 50 --
12
term”.13 This passage was cited with approval in DTR Nominees Pty Ltd v Mona
Homes Pty Ltd14 and both those cases were cited by Mason J in Codelfa Construction.15
[22] The judgment of McPherson J in Akot Pty Ltd v Rathmines Investments Pty Ltd16 is
on point. It concerned the sale of a residential unit yet to be constructed. The only
information in the contract was the description “unit sold … 115 Level 15 Tower”.
There were five units on Level 15 of the Tower. McPherson J allowed the seller’s
real estate agent to give evidence that the purchaser had identified a particular unit on
a plan shown to him at the time he inspected the site where the units were to be built.
McPherson J referred to the rule that “extrinsic evidence to a written contract, in itself
apparently entire and complete, is not ordinarily admissible to add to, subtract from,
vary or contradict the terms of the written instrument”. He cited established English
authority for this, and noted that it had been recently referred to by Mason J in
Codelfa. He then went on to describe the exception which had “long been established
by which extrinsic evidence is admitted to identify the subject matter and, to a much
lesser extent, the parties to a written instrument”. McPherson J cited a deal of
authority for this proposition, including Macdonald v Longbottom, which he noted
had been approved both by Lord Davey in Bank of New Zealand v Simpson17 and by
Mason J in Codelfa.
[23] In a subsequent case, Macdonald v Shinko Australia Pty Ltd,18 McPherson JA referred
to his earlier decision in Akot:
“It is well established that parol evidence is admissible to identify the
subject matter of a written contract. A recent example, which in some
ways resembles the present, is Akot … in that instance, and in the
decisions discussed in it, the written contract was, as regards subject
matter, expressed in an uncertain or ambiguous fashion.”
[24] Subclause (u) only defined the air conditioning work to be completed in the terms of
“the Contractor’s alternative proposal”. Subclause (ag)(i) added the information that
the contractor’s alternative air conditioning system was a VRF type, which would
have different pipe and duct configurations from the configurations shown in the
Thwaite documents. In truth this is not a much more useful definition.
[25] In these circumstances the authority discussed above supports resort to extrinsic
evidence to discover what the contractor’s alternative proposal was. The term in the
contract was not so much ambiguous as uncertain, to use McPherson JA’s term. To
use the term in Prenn v Simmonds and DTR Nominees Pty Ltd, it was a “descriptive
term” which lacked meaning unless resort was had to extrinsic evidence.
[26] Entire agreement clauses in the contract do not prevent resort to extrinsic evidence in
such a case, for the extrinsic evidence is not to add to or change the meaning of the
contract, but to know what the contract means.
[27] Nonetheless, the appellant’s case as to the use of the email correspondence as
extrinsic evidence fails not at a legal hurdle, but at a factual one. The email
13 [1971] 1 WLR 1381, 1384; [1971] 3 All ER 237, 240.
14 (1978) 138 CLR 423, 429.
15 Above, pp 349 and 351.
16 [1984] 1 Qd R 302.
17 [1900] AC 182.
18 [1999] 2 Qd R 152, 154.
-- 12 of 50 --
13
correspondence does not show the parties had a common understanding of what air
conditioning system the words in subclauses (u) and (ag)(i) referred to. To the
contrary, the email correspondence was no more than continued negotiations between
the parties as to the detail of the air conditioning system to be provided. The appellant
does not simply tell the respondent that it will be providing a Toshiba 2 pipe heat
pump system; it asks for approval of such a system, initially perhaps only in respect
of the piping configuration, but by the last email the appellant was “seeking
acceptance of the system in terms of meeting the performance requirements stipulated
by the tender documents”.
[28] In circumstances where that acceptance was not given before the contract, the parties
chose to document the provision of the contractor’s alternative VRF system in general
terms, and on the basis that it satisfied the performance requirements in the Thwaite
documents, see the terms of subclause (u). It is this contractual obligation which must
be examined in order to determine whether or not the 2 pipe VRF heat pump system
installed by the appellant prior to 11 August 2016 was defective, as the respondent
contended below.
Performance requirement – meaning
[29] The primary judge consulted a dictionary to ascertain what the words performance,
and separately, requirement, in subclause (u) meant. This led to the unsurprising, but
unhelpful, finding that the words performance requirement referred to “…
a requirement relating to performance. In this case, a requirement relating to
performance of a mechanical services system, being the air conditioning system.”
The primary judge then used a dictionary meaning of the word performance, namely,
“identifies a capability of a machine which is measurable”. She concluded that the
question for consideration was whether or not mode control was a measurable
capability of the air conditioning system which was required by the contract.
[30] The primary judge should not have used a dictionary.19 First, “performance
requirement” is a composite expression.20 Secondly, this is a case concerning
a building contract. Within the subset of contract cases dealing with building
contracts, there is a well known concept of a performance specification which has
a recognised meaning in the case law.21 In Johnson Controls Australia Pty Ltd v
Webb Australia Group (NSW) Pty Ltd22 McDougall J discussed this:
19 There are numerous authorities to the effect that in interpreting either legislation, or a contract, resort
to dictionaries is generally unhelpful in a “mature and developed jurisprudence”: SDA v Corporation
of the Synod of the Diocese of Rockhampton (2021) 8 QR 440, 449, [10] and [11]; TAL Life Ltd v
Shuetrim; MetLife Insurance Ltd v Shuetrim (2016) 91 NSWLR 439, 457, [80] and the authorities
there cited; House of Peace Pty Ltd v Bankstown City Council (2000) 48 NSWLR 498, 505, [28].
20 “Dictionaries are not a substitute for the judicial determination of the interpretation and then
construction of statutes and other documents: Life Insurance Co of Australia Ltd v Phillips (1925)
36 CLR 60 at 78 per Isaacs J. The meaning of the words used in a statute or document is not merely
the sum of the individual meanings of the words used, ascertained from dictionaries.” – per
Mahoney JA in Provincial Insurance Australia Pty Ltd v Consolidated Wood Products Pty Ltd (1991)
25 NSWLR 541, 560.
21 We also note that witnesses expert in various aspects of construction gave evidence at the trial as to
what they understood by the term performance requirement, and that there was considerable cross-
examination of them about this. In our view, that evidence was inadmissible. The words used in the
contract ought to have been interpreted in accordance with recognised legal canons. We note that
although considerable time was spent, inadmissibly, discussing these matters with expert engineers,
the primary judge did not rely upon their views in construing the contract.
22 (2003) 96 ACSR 640, 663-664, [145]-[146].
-- 13 of 50 --
14
“… it is a statement of the standard of performance that the works are
to meet or to achieve. In essence, such a specification would tell potential
tenderers what it is that the works to be done and equipment to be
supplied are required to do, whilst leaving it up to the tenderers as to
the precise means by which they would achieve the specified result.
… The essential feature is that the new generator set must be capable
of working in parallel with the existing generator sets (in this case,
with their neutral terminals interconnected). That was what the
tenderers were required to achieve. It was up to them to work out how
to achieve it.” (underlining added).
[31] A performance specification may be contrasted with a prescriptive specification in
a building contract. A prescriptive specification will result from the owner having
chosen the exact system or equipment it wishes to have built, the role of the
specification is to name or describe it.
[32] When one looks at the phrase “performance requirement” in the context of subclause
(u); against the facts known to both parties ([2], [4], [5] and [6] above), and in the
context of the parties having tried and failed to agree on a precise description or
prescriptive specification of the alternative system prior to contract ([19](a)-(f)
above), it is clear that the expression “performance requirement” was one very closely
related to the notion of performance specification, and was designed to fill the same,
or a very similar, contractual purpose as the term performance specification. The parties
knew that they had contracted for the appellant’s alternative air conditioning system,
not the Thwaite specified system. However, it was up to the appellant in this case to
work out how its alternative system was to achieve any results specified by the
Thwaite documents, to draw on the language of McDougall J in the quotation above.
Performance requirements in the Thwaite Documents
[33] Having reached that point, there was an enquiry to be made as to whether or not the
Thwaite documents contained a performance requirement as to mode control. It was
conceded on the hearing of this appeal that the Thwaite drawings were irrelevant to
this enquiry.23 The enquiry is thus limited to the Thwaite specification, but it is
a difficult enquiry because: (1) largely the Thwaite specification is a prescriptive,
rather than a performance, specification, and (2) it is a prescriptive specification for
a 4 pipe chilled and heated water system, not a VRF system.
[34] The parties were agreed that cl 3.1 of the Thwaite specification contained
performance requirements. Relevantly here it provided as follows:
“3. DESIGN CRITERIA
3.1 DESIGN CRITERIA
• Design criteria presented herein form the basis for the design of the
works and for any alternative proposals submitted.
Item Design Criteria
External ambient conditions
(for air conditioning plant full
load performance)
Summer
33.1°C dry bulb maximum
23 Tt 1-43, 2-41. And indeed the 11 August notice relied upon the specification not the drawings.
-- 14 of 50 --
15
Based on Brisbane (AIRAH)
Internal conditions (for
conditioning plant full load
performance) general
Controls tolerance for air
conditioning system
Outside Air
Exhaust Air
Occupancy
Hours of Operation
24.8°C wet bulb maximum
Winter
6.0°C dry bulb minimum
Summer
23°C dry bulb maximum at
point of control
Winter
21.5°C dry bulb at the point of
control
+/-2.0°C dry bulb at point of
control (+/-1.0°C dead band)
In accordance with AS 1668.2
2013 requirements
In accordance with AS 1668.2
2013 requirements
Refer Table A
Continuous
…” (underlining added).
[35] This part of cl 3.1 contains criteria which the installed air conditioning system must
meet, but does not prescribe how the system is to achieve those criteria. It is that
characteristic which means it contains performance requirements. In fact, the part of
the Thwaite specification extracted above is a performance specification. The
appellant submitted, and we accept, that the underlined words are relevant here as an
indication that this part of the Thwaite specification contains performance
requirements within the meaning of subclause (u). Whether the Thwaite-prescribed
air conditioning system, or an alternative air conditioning system, forms part of the
work under contract, the air conditioning system which is designed, built and
installed, must meet the criteria, or performance requirements, in cl 3.1.
[36] Apart from two irrelevant occasions, the Thwaite specification does not otherwise
mention the possibility of an alternative proposal. We agree with the point made by
the appellant that that is an indication that the rest of the specification is largely
prescriptive, rather than based on criteria to be achieved, or performance
requirements. That prescriptive, rather than performance, nature of the Thwaite
specification is evident from the substance of the document (apart from cl 3).
[37] It was not controversial between the parties that the 2 pipe VRF system installed prior
to 11 August 2016 met the criteria in cl 3.1 of the Thwaite specification. For example,
-- 15 of 50 --
16
on a summer day when the outside temperature was 33.1°C or less, the occupant of
a hotel room could control the temperature down to 23°C, and on a winter day where
the outside temperature was 6°C or more, the occupant of a room could bring the
room temperature to 21.5°C. The occupant of the room could do these things using
the thermostat control in the room. That is, the occupant could do so without the need
for mode control in the room.
[38] The appellant submitted that nowhere in the Thwaite specification is there a
performance requirement that the occupant of the room have mode control. The two
clauses of the Thwaite specification referenced in the 11 August notice as requiring
mode control to individual rooms were not relied upon by the respondent in this
litigation. Nor were they relied upon by the primary judge as supporting the idea that
the Thwaite specification required mode control in each room.
[39] The primary judge found that there were performance requirements of the Thwaite
specification which required mode control to individual rooms:
“[158] While the drawings and the Specification were prepared on the
basis that the mechanical services system to be installed was
a ‘four pipe chiller (heat recovery type)’, there are several
aspects of the drawings and the Specification which support a
construction that the Independent Heating/Cooling Function
was a requirement applicable to an alternative proposal based
on a VRF air conditioning system. These include:
(a) Clause 2.2.1 of the Specification provides for an
‘air-cooled four pipe chiller (heat recovery type)’ system
which has a specific function that it can perform
independent heating/cooling. The requirement of an
Independent Heating/Cooling Function is an inherent
capability of that air conditioning system.
(b) Clause 2.2.3 of the Specification stipulates that each guest
room is to have its own indoor FCU with Chilled Water
Coils (CHW) and Heated Hot Water Coils (HHW),
together with wall mounted electronic controls.
Inherently, this would enable each guest to adjust the
heating and cooling in their room.
(c) Clause 9.8.2 of the Specification provides details about
the wall mounted controls to be installed in each room,
including functions for temperature control specifically
‘[c]hilled water and heating hot water control valve
modulation to satisfying [sic] cooling and heating load’.
The wall mounted controller was to be capable of
modulating the heating and cooling in the individual
guest room by controlling the CHW and HHW coils in
the FCU. Whilst under a VRF system CHW and HHW
coils would not be relevant, this requirement to be able to
modulate heating and cooling in an individual room tends
to support a requirement that whatever system was
actually installed, it was to be able to achieve this outcome.
-- 16 of 50 --
17
[159] The particular wording in clause 2.2.3 of the Specification
provides ‘[e]ach guest room shall be individually air
conditioned … which supply conditioned air to the room …’.
This reference to each room being individually air conditioned
and to conditioned air being supplied, tends to support the
construction as contended for by the defendant.
[160] The plaintiff argues that in effect, guests in individual rooms are
able to obtain temperature control with the two-pipe heat pump
system that was partially installed, by in effect, moderating the
zone temperature by switching off the conditioned air and
introducing ventilation. The use of the ventilation was a means
by which the guests could achieve temperature control within
the practical temperature range allowed. However, this is not
achieved by way of supply of ‘conditioned air to the room’, but
rather it is the use of ‘unconditioned air’ to the room in order to
achieve the temperature moderation.
[161] A reasonable businessperson in the position of the parties at the
time the Contract was entered into would understand that the
reference to ‘conditioned air’, either as heated or cooled, was
what was to be provided, not merely using ventilation to
moderate or control temperature in an individual guest room.
[162] Further, the Specification uses specific language to describe
when ventilation was to be provided as opposed to ‘conditioned
air’. For example, the requirements for mechanical ventilation
in clauses 2.2.13 to 2.2.19.”
[40] The primary judge erred in concluding that there were performance requirements in
the Thwaite specification requiring mode control in each individual room. We examine
the three parts of the Thwaite specification relied upon by the primary judge.24
[41] (1) Section 2.2.1 of the Thwaite specification is located in section 2, headed
“Description and Scope of Work”. Section 2.2 is headed “Mechanical Systems
Description” and section 2.2.1 is headed “Central Air-Cooled Heat Recovery
Chiller”. These are indications which tend against section 2 containing performance
requirements, and which tend to show it was descriptive, ie., a prescriptive
specification for a heat recovery chiller, rather than VRF, system.
[42] The first dot point in section 2.2.1 is that part of the Thwaite specification referenced
by the primary judge at [158](a) below: “The entire hotel … shall be provided with
chilled water and heat[ed] hot water from a common air-cooled 4 pipe chiller (heat
recovery type) located on the roof”. This is not a performance requirement. It is
a prescriptive specification for the Thwaite system (chiller not VRF) of air
conditioning to the hotel. Conforming tenders had to be on the basis that they were
a chilled water and heated hot water 4 pipe system. The appellant provided
a conforming tender, but it was its alternative proposal which was accepted. The
alternative proposal was not a chilled water and heated hot water system, and it was
not a 4 pipe system; it was a VRF system.
24 No others were relied upon by the respondent on appeal.
-- 17 of 50 --
18
[43] The parties accepted the primary judge was correct to say at paragraph [158](a) of the
judgment below, that mode control, or as she calls it, “Independent Heating/Cooling
Function”, is an inherent capability of the air conditioning system described at cl 2.2.1
of the Thwaite specification. It is not an inherent capability of a system simply
described as a VRF system. Some VRF systems will have that capability; some will
not. Clause 2.2.1 of the Thwaite specification did not contain a performance
requirement that any alternative proposal was to have mode control.
[44] (2) Section 2.2.3 of the Thwaite specification is still under the general heading
“Mechanical Systems Description”. It is under a sub-heading “Guest Room Air
Conditioning FCU’s”. FCU stands for fan coil unit. Section 2.2.3 says at dot point
one, “Each guest room shall be individually air conditioned by ceiling mounted
FCU’s which supply conditioned air to the room served via acoustically insulated
sheet metal duct work …”. At the third dot point, it says that the FCUs shall each
have a chilled water and heated water coil. In the final dot point it says that
“[impliedly, the installed air conditioning system will] provide electronic controls
with a wall mounted temperature sensor/switching/adjustment to control the FCU and
interface with the guest room energy management system provided as part of the
electrical trades work”.
[45] Again, this is a prescriptive, not a performance, specification; it does not contain
performance requirements. It is in section 2 of the specification, headed
“Description” and it is a description of the fan coil units in a chilled and heated water
recovery system. By contrast with the description in section 2.2.3, a VRF system will
not have chilled water and heated water coils, so that the prescription in the third dot
point could never apply to the alternative proposal.
[46] Section 2.2.3 of the Thwaite specification does not expressly require mode control in
every room. It is possible to read the word “switching” in the final dot point as
a reference to mode control, but that is by no means clear; it might equally refer to
each guest having the capacity to switch off the air conditioning to their individual
room. If the Thwaite specified system had been installed, the “switching” could refer
to switching between cooling and heating modes, because, by definition, the Thwaite
system would have had mode control. Where a VRF system was to be installed, there
is no such necessary implication.
[47] As to the first dot point in section 2.2.3, the same reasoning applies as is outlined in
respect of section 2.2.1. As the primary judge recognised at [159] of her judgment,
the 4 pipe chiller heat recovery system prescribed by the Thwaite specification would
have provided nothing but air conditioned air through the fan coil unit in the ceiling.
A VRF system would sometimes provide air conditioned air, and sometimes provide
outside air as ventilation. This dot point only contemplates that the fan coil unit will
provide conditioned air because it is a description of the 4 pipe chiller heat recovery
system, but it is not a performance requirement; it is not a requirement that an
alternate VRF system provide only air conditioned air through the fan coil unit.
[48] (3) Section 9.8.2 of the Thwaite specification is not a performance requirement that
the air conditioning system have mode control. Section 9 of the Thwaite specification
is headed “Control Systems” and cl 9.8.2 reads as follows:
“9.8.2 CHW/HHW FAN COIL UNITS GUEST ROOMS
The following mandatory items and control functions shall be
provided for each FCU system:
-- 18 of 50 --
19
(b) Start Stop Control and Indication
- Wall mounted combined FCU controller with ON-OFF
switch
- Interface with guest room energy management system
provided by the electrical trade
(c) Temperature Control
- Space temperature sensor integral to ON-OFF switch
- Chilled water and heating hot water control valve
modulation to satisfy cooling and heating load
- Each fan coil unit (and associated fans as applicable) shall
be started individually according to a pre-set schedule of
daily operation
- Control dead band to be +/-1.0°C from set point”
(underlining added).
[49] The initials CHW/HHW in the heading to this clause referred to chilled water and
heated water. A VRF system will not have chilled water and will not have heated
water. This clause could not contain a performance requirement for a VRF system;
it is a description of a fan coil unit in a 4 pipe chiller system.
[50] It is not sufficiently clear that the second dash point under sub-paragraph (c) does
prescribe mode control for each individual room, rather than a control in each
individual room to modulate or regulate the temperature in every room. The words
themselves are not clear, particularly when there is no other requirement in this
sub-paragraph for each guest room to have a control function to specify what
temperature the guest desires, and the sub-paragraph is headed “Temperature Control”.
[51] Even if it is assumed that the second dash point does refer to mode control, it specifies
a “chilled water and heating hot water control valve modulation”. This is something
which a VRF system will never have; for it will not have a chilled water coil and a hot
water coil. We cannot see an implication from this dash point that the alternative
VRF system which the appellant promised to provide was required to have individual
mode control in every room, rather than have a mechanism to satisfy the “cooling and
heating load” required; cl 3.1 speaks in terms of “load performance”.
Conclusions as to characterisation of 11 August 2016 notice
[52] In our view, contrary to the findings of the primary judge, the air conditioning system
which had been partly installed by the appellant prior to the receipt of the 11 August
notice was in accordance with the contract. It follows that the work was not defective,
and the respondent was not entitled to the damages for defective work awarded by
the trial judge.
VARIATION
[53] It also follows that the 11 August notice required the appellant to design and construct
an air conditioning system other than that which the contract required. Clause 36.1
of the contract provided for variations:
-- 19 of 50 --
20
“36 Variations
36.1 Directing variations
The Contractor shall not vary WUC except as directed in writing.
The Superintendent, before the date of practical completion, may
direct the Contractor to vary WUC by any one or more of the
following which is nevertheless of a character and extent contemplated
by, and capable of being carried out under, the provisions of the
Contract (including being within the warranties in subclause 2.2):
(a) increase, decrease or omit any part including the omission of
any part of WUC with a view to retaining a third party to
perform that part of WUC either prior to or after the date of
practical completion (with no liability to compensate the
Contractor for any loss of profit);
(b) change the character or quality;
(c) change the levels, lines, positions or dimensions;
(d) carry out additional work;
(e) demolish or remove material or work no longer required by the
Principal.
The Principal shall only be liable to the Contractor for the price of a
variation calculated in accordance with subclause 36.4 or for an EOT
for a variation where either:
(f) the direction to perform the variation given by the
Superintendent is in writing, expressly states that the direction
constitutes a direction for a variation and identifies the work the
subject of the direction; or
(g) before performing the variation and in any event within
5 business days of receiving the direction to perform the
variation, the Contractor has given the Superintendent a notice
in writing which identifies:
(i) the date the direction was given;
(ii) whether the direction was given orally or in writing;
(iii) the substance of the direction and, if it was in writing,
a copy of the direction must be attached;
(iv) the approximate cost of the variation including a detailed
breakdown calculated in accordance with subclause 36.4;
(v) whether a claim for an EOT will be made as
a consequence of the variation and if so, an estimate of
the period; and
(vi) where the variation relates to the design documents or
the Principal’s project requirements, by identifying the
relevant requirement and the change to that requirement.
-- 20 of 50 --
21
(h) Except where the Contractor is entitled to make a claim under
this subclause 36.1, the Contractor shall have no entitlement as
a consequence of complying with a direction for a variation.
(i) Where the Contractor wishes to make a claim for an EOT as
a consequence of a variation, in addition to the notices it is
required to give under this subclause 36.1, the Contractor shall
give all notices required under clause 34.”
[54] It was not in dispute on this appeal that if the 11 August notice was not correctly given
as a defects notice pursuant to cl 29.3, the work of removing the air conditioning
system installed prior to 11 August 2016, and complying with the direction to install
a different air conditioning system, should be regarded as a variation to the contract
works on the basis that the appellant did comply with cl 36.1(g). The price of the
variation was not in issue on this appeal.
EXTENSION OF TIME
[55] Clause 34.3 of the contract dealt with the contractor’s entitlement to extensions of
time:
“34.3 Claim
The Contractor shall be entitled to such EOT for carrying out WUC
(including reaching practical completion) as the Superintendent
assesses, if:
(a) the Contractor is or will be delayed in reaching practical
completion by a qualifying cause of delay;
(b) the Contractor gives the Superintendent, within 14 days of
when the Contractor should reasonably have become aware of
that qualifying cause of delay occurring, a written claim for an
EOT evidencing the facts of causation and of the delay to WUC
(including extent);
(c) the qualifying cause of delay was beyond the reasonable control
of the Contractor and affects the critical path of the activities
required to complete WUC as shown on the approved
construction program;
(d) the Contractor or others for whom it is responsible did not
contribute to the cause;
(e) the Superintendent is satisfied that WUC was actually delayed;
(f) the Contractor has taken all reasonable steps to mitigate the
effect of the delay; and
…” (underlining added).
Time for written claim, cl 34.3(b)
[56] The 11 August notice was sent by email at 7.20 pm. The relevant site personnel from
the appellant were still at the site office because they were waiting for some type of
direction in writing to come from the superintendent that evening. In fact one of
-- 21 of 50 --
22
them, Mr Cook, had been encouraging the superintendent to give a direction of some
kind to break the impasse which had prevailed since June when the superintendent
asserted that the air conditioning installed was non-compliant, and the appellant had
not accepted that characterisation.
[57] Six days previously, on 5 August 2016, Mr Cook had sent an email to the
superintendent asking for “a clear direction to proceed”. That email had discussed
the time and cost implications of the works the subject of such a direction, and
expressly mentioned that an EOT would be required if a direction was given.
Mr Cook agreed that at the time he wrote the 5 August 2016 email he was
contemplating that if the appellant was instructed to install a new air conditioning
system, there would be a requirement for an EOT (t 2-6). He agreed that when the
11 August notice arrived he held the view that the direction contained in it would be
a qualifying cause of delay within the meaning of cl 34.3, and that there was likely to
be the need for an EOT (t 2-7).
[58] Mr Cook’s evidence was that once the 11 August notice had arrived, he immediately
telephoned more senior personnel of the appellant, including its Commercial Manager
and General Manager. He thought that he probably emailed the 11 August notice to
those people that night.
[59] Mr Cook was asked whether or not he started drafting the EOT claim on the evening
of 11 August 2016. He could not recall. He was then asked:
“Whether or not you started drafting that, I take it there was discussion
on the evening of the 11th of August that you had to send the various
notices which you ultimately send on the 12th
?--- Not necessarily.
I think the first step was just understanding exactly what they were
requesting from this notice, rather than, you know, quickly trying to
reply.
No, I don’t think – sorry. Please finish?--- No, I just – I think the first
steps were just to understand exactly what the notice provided and the
information as part of the notice.” (t 2-7).
[60] Oddly, the building contract did not contain a typical clause providing for when
notices would be deemed to have been sent and accepted, and neither side before us
contended that there was any contractual implication to be made in that regard.25 It
was argued on both sides simply that the notice was given on 11 August 2016, and
that on the fifteenth day following, 26 August 2016, a written claim for an EOT was
given by the appellant to the superintendent.
[61] The respondent claimed, and the primary judge found, that the claim for an EOT was
delivered too late to be effective and that, as a consequence, the contractor was not
entitled to any EOT for carrying out the works under the contract. In our view, that
finding was in error.
[62] The primary judge referred to authority, which is not in doubt, to the effect that time
periods stipulated in clauses such as cl 34.3(b) of this contract mean what they say,
and will be enforced accordingly by the courts.
25 There are at least some English cases which suggest that notices sent outside business hours are not
taken to be received until the next day: Euronav NV v Repsol Trading SA The MT MARIA [2022]
2 All ER (Comm) 65, 74, [28]; Rightside Properties Ltd v Gray [1975] 1 Ch 72, 80; Schelde Delta
Shipping BV v Astarte Shipping Ltd (The Pamela) [1995] CLC 1011, 1014-1015.
-- 22 of 50 --
23
[63] Clause 34.3(b) does not provide that the contractor is to give the superintendent
a claim for an EOT within 14 days of a qualifying cause of delay occurring. It
requires that the claim for an EOT is given “…within 14 days of when the Contractor
should reasonably have become aware of that qualifying cause of delay occurring …”.
[64] At 7.10 am on 12 August 2016, Mr Cook sent an email to the appellant’s National
Commercial Director which attached the 11 August 2016 direction and asked how
the director wished to proceed. At 11.00 am on 12 August 2016 a meeting invitation
was sent, and later that day the Managing Director of the appellant, together with
General Counsel employed by the appellant, and Mr Cook, amongst others, met to
discuss the 11 August notice. On 12 August 2016 the appellant issued at least five
notices under the contract. These included a notice to the effect that the appellant
considered the 11 August notice was a direction to perform a variation – cl 36.1(g) of
the contract, and that it was an event which would cause delay to the work under the
contract – cl 34.2 of the contract.
[65] The primary judge thought that the evidence of the appellant’s preparedness, and
indeed anticipation, of a notice of some kind being received on 11 August, together
with its ability to give some contractual notices in response on 12 August 2016, meant
that, “not only did the [appellant] actually become aware of the qualifying cause of
delay on 11 August 2016, it also ‘should reasonably’ have become aware that same
day”. In our opinion, this conclusion is erroneous. Even against the background of
Mr Cook requesting and anticipating that a direction would be given in relation to the
air conditioning on 11 August 2016, we reject the idea that 11 August 2016 was the
date when the appellant should reasonably have become aware of that qualifying
cause of delay occurring.
[66] The 11 August notice was given well after the end of the working day. It is seven
pages long. On its face it is given pursuant to cl 29.3 of the contract (defective work).
It asserts that the air conditioning system does not meet the Thwaite specification in
11 enumerated respects (as opposed to the one fault complained of in this litigation,
ie., mode control). Some of the matters enumerated as defects are in very general
terms. No doubt each of the matters required consideration by the appellant so that it
could determine whether or not, in its view, the work it had completed did comply
with the contract, or alternatively was defective. That is, the 11 August notice
required an engineering opinion to be formed as to 11 separate alleged defects. Only
after that opinion was formed, could a legal opinion be essayed in relation to the
contractual effect of the notice, in terms of its characterisation (defects notice or
direction to perform a variation). Once that legal opinion was formed, an examination
of the contractual effect of the notice in terms of delay, extension of time, and the
requirement for notices to be given under the contract was necessary. Only once
decisions had been made as to the appellant’s view as to all these engineering and
legal matters, could a commercial decision be made by the appellant as to how it
would respond to the notice. It was not until all three of these decisions had been
made that the appellant could, or should reasonably, have become aware that the
receipt of the notice was a qualifying cause of delay. The phrase “qualifying cause
of delay” is one which is defined by the contract in 16 sub-paragraphs, relevantly
here, “a direction for a variation in accordance with subclause 36.1 or 36.2”.
[67] In our view, the primary judge erred in finding that the appellant “should reasonably
have become aware” that the 11 August notice was a qualifying cause of delay, at
-- 23 of 50 --
24
least, before 12 August 2016. The appellant’s claim for an extension of time was to
be given within 14 days of that date, ie., by 26 August 2016, and it was.26
Contractor’s contribution to qualifying cause of delay
[68] Below, the respondent argued that, even if the appellant had delivered its claim for
an EOT within the period limited by cl 34.3(b), the appellant was still not entitled to
an extension of time, because of the provision at cl 34.3(d). It argued that the
appellant contractor had contributed to the qualifying cause of delay in that it had
failed to provide shop drawings of the air conditioning system when required to do
so by the contract, 3 November 2015. It argued that, had the shop drawings been
provided, they would have revealed the lack of mode control in individual rooms, and
an equivalent to the 11 August notice would have been issued six months earlier.
[69] The appellant says that there was no evidence that the shop drawings would have
revealed that the air conditioning system the appellant intended to install did not allow
for mode control in individual rooms. We think the primary judge was correct in
finding that, probably, shop drawings would have revealed this. Under the contract
shop drawings were to, “show sufficient information to enable the Superintendent and
other appropriate consultants to check that the equipment can be installed, operated,
adjusted and maintained in the manner for which the system, into which they are to
be incorporated, was designed” – cl 8.8(f).
[70] The type of air conditioning system being installed by the appellant emerged as an
issue in June 2016 when one of Mr Thwaite’s employees, Mr Van Grootel, received
a schematic diagram of air conditioning piping. On 10 June 2016 he wrote to the
respondent’s project manager saying that “The piping systems indicate that individual
rooms cannot run heating and cooling when required” and that this was a “major
concern” because it meant that the air conditioning system was “outside our
specifications and [hotel operator] guidelines”.27
[71] On 14 June 2016 the respondent sent Mr Van Grootel’s email to the appellant and
said, inter alia:
“…
● Room heating and cooling – Each room must have the ability to
call for heating or cooling independently of other Guestrooms.
Again this is non negotiable and is in accordance with the
original design intent.
It should be noted that I believe the preparation and issuing of
workshop drawings for review prior to ordering or commencing
fabrication in accordance with Item 2.1.1.5 of the mechanical
specification would have assisted in identifying and resolving these
issues earlier.”
[72] The respondent’s project manager gave evidence that:
26 Wesfarmers Kleenheat Gas Pty Ltd v Elgammal [2006] NSWSC 1248, [8]; Proctor v Chahl [2008]
NSWSC 1252, [32]; Kembla Coal & Coke Pty Ltd v Select Civil Pty Ltd [2004] NSWSC 628, [53]ff.
27 We note that the contract was neither to build the air conditioning system to the Thwaite specification,
nor the hotel operator guidelines.
-- 24 of 50 --
25
“I am firmly of the belief that the issues identified in Thwaite
Consulting Groups mechanical contractor’s submissions tracking
document would have been identified a lot sooner and before any
mechanical work had commenced on site.”
[73] The appellant did not dispute that it was in breach of its obligation to provide shop
drawings on or about 3 November 2015. However it argued that by 3 November 2015
(at least) the respondent’s air conditioning consultants, Thwaite, knew that the air
conditioning system being installed by the appellant did not provide mode control, so
that the appellant’s failure to provide shop drawings on time was irrelevant or
immaterial. The difficulty with that argument is that Mr Thwaite was not called by
either party, so there is no evidence of what he knew. There is, however, evidence of
the information with which he was provided, see paragraph [19] above. On 30 March
2015 information was sent by the appellant to the respondent, and by the
respondent to Thwaites – see [19](a) and [19](b) above. The words of the email from
the appellant raised the high likelihood that the system which the appellant intended
to install would not have mode control.28 Conclusively though, the schematic
diagram attached to that email was to all intents and purposes identical to the one sent
to Thwaites in June 2016, from which Mr Van Grootel discerned the information that
there was no mode control in individual rooms. In our view then, whether or not
Mr Thwaite knew before the contract that the appellant intended to install an air
conditioning system which would not allow mode control to individual rooms, he
ought to have known that.
[74] The primary judge found that had the shop drawings been provided by 3 November
2015, an equivalent notice to the 11 August notice “could” 29 have been issued “in
late 2015 or early 2016 and the consequential delay could have been substantially
mitigated” – [1119]. She said, “Accordingly, … I find that the plaintiff contributed
to the cause of delay by the failure to provide design documents and shop drawings
as required by clause 8.5 and clause 8.8 of the Contract” – [1120].
[75] Shorn of irrelevant parts, cl 34.3(d) says that a contractor is entitled to an EOT if it
will be delayed in reaching practical completion by a qualifying cause of delay and if
it “did not contribute to the cause”. The words “the cause” in subclause (d) are untidy
because elsewhere in cl 34.3, where the “qualifying cause of delay” is referred to, it
is named in full and put in italics. Sensibly, the only other concept which
subclause (d) could be referring to is the delay in reaching practical completion.
Subclause (f) does refer to “the delay”, and we interpret those words in (f) as meaning
the delay in reaching practical completion.
28 This was an implication from the fact that it was described as a 2 pipe VRF system and that the system
would be divided into zones to cater for different heat loads on the building façade.
29 There is an issue lurking behind this finding. In fact, a finding that an equivalent notice to the
11 August notice would have been issued was necessary in order to make the respondent’s case. It
was submitted on appeal that there was no evidence on behalf of the respondent to support a finding
that such a notice would have been issued. The question was what inferences from the available
evidence could safely be drawn by the primary judge on the balance of probabilities. There was
evidence that the respondent called for shop drawings in respect of the air conditioning system on
2 December 2015, 10 December 2015 and 7 June 2016. There is an available inference on the evidence
that from December 2015 the respondent would have had Thwaites make a thorough check of the shop
drawings and the lack of mode control would have been revealed. If that were the judge’s factual
finding it ought to be expressed in the judgment and reasons for it ought to have been given.
-- 25 of 50 --
26
[76] The parties agreed, and we are independently of the view, that the words “the cause”
in cl 34.3(d) must be interpreted as a short form of “the qualifying cause of delay”.30
This is the most natural meaning of the words where the contract otherwise is
concerned to distinguish between the concepts of delay and its causes – cll 34.2 and
34.4. Thus, properly interpreted, cl 34.3(d) does not call for a factual enquiry into
whether or not the contractor contributed to the delay in practical completion, but
whether it contributed to the qualifying cause of delay. Here the qualifying cause of
delay was the direction for a variation given on 11 August 2016 – see the definition
of qualifying cause of delay, subclause (i).
[77] In our view, the appellant contractor did not contribute to the qualifying cause of
delay. Originally, it was not contractually bound to provide an air conditioning
system which allowed mode control to each guest room. The respondent directed the
appellant to perform a variation to the contract. That direction to vary was the
qualifying cause of delay. That was not something to which the appellant contributed.
We think that the appellant is correct in submitting that, despite correctly stating the
effect of subclause (d) at [1109], [1114] and [1117] of her reasons for judgment, the
trial judge did confuse the concepts of “qualifying cause of delay” and “delay to
practical completion” in her conclusions at [1119] and [1120].
[78] It follows that we do not consider it relevant to enquire whether or not the respondent
would have (not could have) issued a direction in terms of the 11 August notice six
months earlier, had shop drawings been provided by 3 November 2015. That is
a different factual enquiry, namely one as to whether the failure to provide shop
drawings contributed to the delay in practical completion. We merely note that if
(contrary to our view) that were the correct enquiry to make, the fact that Thwaites
had the schematics showing that there was no mode control by 30 March 2015, is an
answer to the respondent’s contention that the appellant’s failure to provide shop
drawings in November 2015 contributed to the delay in practical completion.
Failure to mitigate
[79] This appeal ground is based on cl 34.3(f) which provides that the contractor is entitled
to such EOT as the superintendent assesses if “the contractor has taken all reasonable
steps to mitigate the effect of the delay”.
[80] The air conditioning system which the appellant had partly installed before the
11 August notice was manufactured by Toshiba. Having received the 11 August
notice, the appellant proposed to convert its system to a 3 pipe system. The most
obvious way to do that was to ask Toshiba to supply the necessary equipment to make
the conversion (condensers, flow selector boxes and branch boxes). However, there
was a difficulty with the appellant doing this because the 11 August notice
complained that the respondent required equipment manufactured either by
Mitsubishi or Daikin to be used and that “the manufacturer of the alternate VRV
system [Toshiba] is not an approved equipment manufacturer”.
[81] On 16 August 2016 the appellant received an email from its air conditioning engineer
with designs to convert the air conditioning system to a Toshiba 3 pipe system. The
appellant sent that to the respondent the same day saying that the new proposal would
30 Why the short form was used at cl 34.3(d), but not at cl 34.3(f) (a conceptually similar sub-clause) is
not readily explicable, except by poor drafting.
-- 26 of 50 --
27
“have the ability to simultaneously heat and cool each room when required”. The
letter also said:
“Please also note the following:
● This design takes into consideration minimal impact and cost
implications to change over from 2 pipe system.
● Currently the condensing units selected are available in
Australia and New Zealand, which have a lead time of 9 days.
● The condensers selected within the proposed design are
currently set up for approx. 60% load as these condensers have
a lead time that suits the project. If alternative condensers
are required the lead time on these items would be between
8-10 weeks.
● There are 24 flow selector boxes available immediately, with
the remainder 4 weeks away with a supply from the Toshiba
workshop in Japan.
● The Branch boxes will be installed utilising the access panels
within each room thus reducing the impact on the finishes.
Could you please provide a response on the above proposal or
alternatively we are happy to arrange a meeting or teleconference to
further discuss.”
[82] The respondent replied that the conversion proposal would be the subject of
discussion at a without prejudice meeting on 18 August 2016. Nothing was resolved
at the meeting. On 22 August 2016 the respondent raised issues with the proposed
conversion process. These issues were answered by the appellant’s air conditioning
engineer on 24 August 2016. On 25 August 2016 there was another meeting. The
appellant asked for a clear direction as to the principal’s requirements, and in response
received an email from the superintendent saying:
“The [11 August notice] was issued in accordance with the Contract
and is current.
There is no qualifying cause of delay to warrant an EOT. The EOT is
assessed as 0 days.”
[83] We accept the appellant’s submission that this response continued to assert that
Toshiba equipment was unacceptable.
[84] On 16 September 2016 the appellant sent advice in relation to the costing and timing
of alterations to be carried out to the air conditioning system. A response was sent
on 17 September 2016 which said:
“Thank you for providing this information.
We are assessing this final information for compliance with the
Contract, with discussions to progress on a Without Prejudice basis
between the representatives of the Contractor and Principal.
We advise that the notice issued under sub clause 29.3 for Defective
Works remains valid and current.
-- 27 of 50 --
28
We look forward to resolution of the situation and progression of the
works.” (underlining added)
[85] We accept the appellant’s submission that this response continued to assert that
Toshiba equipment was not acceptable.
[86] On 19 September 2016 the appellant wrote to the superintendent saying:
“…
2. All parties are aware there is a difference of opinion as to what
the requirements of the Contract are in respect to mechanical
services. Given that difference of opinion, advice as to what the
Principal’s requirements are is critical to ensure that when
completed, the mechanical services operate as the Principal
expects. This has been the subject of meetings, correspondence
and discussions. …
3. Built is, as at today, still awaiting confirmation as to the
Principal’s requirements in respect of the mechanical services.
4. Given the difference of opinion as outlined above, assessment
of what Built has provided ‘for compliance with the Contract’
as you have indicated, is not likely to assist resolving this matter
and will likely further cause delay.
We await your clear direction as to the Principal’s requirements.”
[87] It seemed that some solution to the impasse may have been reached on 20 September
2016 when the managing director of the respondent wrote to his counterpart in the
appellant saying, “We confirm that the proposed 3 pipe system should achieve our
objectives and our position is that it meets the objectives of the Contract”. That same
email posed questions about the system the appellant then proposed, which were
addressed by the appellant’s air conditioning engineers and sent back to the
superintendent on 23 September 2016. Unfortunately, that response met with the
following email from the superintendent:
“Thanks for your below response.
We are assessing your responses for compliance with the Contract.
We confirm that no direction has been given to proceed with any
pre-conditioning option or any other element of the mechanical system
that is outside of that required under the Contract.”
[88] On 30 September 2016 the appellant wrote to the superintendent asking him to,
“Please confirm whether the Superintendent considers that all Toshiba equipment is
to be removed and replaced”. The letter ended saying:
“Upon receipt of the above clarification, Built will proceed with
implementation of the material elements of the Principal’s
requirements outlined within the ‘Defective Works’ notice,
specifically that ‘fan coil units in individual rooms [are to] to provide
either cooling or heating independently across all individual hotel
guest rooms’. Built acknowledges that it is the opinion of the
-- 28 of 50 --
29
Superintendent that this requirement forms part of the Contract
scope.”
[89] This letter was sent as an attachment to an email. The email was sent in the same
thread as the email of 16 September above. The superintendent’s response to the
appellant’s letter of 30 September was, “Please issue under the correct thread”. That
was sent on 4 October 2016 and attached a letter which said:
“In relation to the notice received on 30 September 2016 pursuant to
CA57 – Mechanical 3 Pipe Alterations and the 30 September 2016
Letter requesting Clarification contained therein, the Superintendent
advises the Contractor the communication has been issued under an
incorrect Acconex thread.
The correct thread for the subject notice from the Contractor relates to
the Defective Works Notice pursuant to Sub Clause 29.3 of the
Contract and issued under Acconex thread ID Tactical-GCOR-000371
by the Superintendent on 11 August 2016. The Contractor is requested
to reissue the clarification notice under the correct thread to which it
relates.
The Superintendent also explicitly confirms the following:
1. The notice pursuant to subclause 29.3 of the Contract dated
11 August 2016 issued by the Superintendent to the Contractor
(Subclause 29.3 Notice):
(a) was not issued in error; and
(b) does not involve a variation;
2. Any communication from the Superintendent to the Contractor
pursuant to CA57 – Mechanical 3 Pipe or any other
communication related to mechanical installations installed or
otherwise:
(c) does not constitute a variation under subclause 36.1 or
36.2 of the Contract.”
[90] On 11 October 2016 the appellant sent a letter to the superintendent, this time in a
thread of emails which had a re line “Superintendent Direction 9 – Mechanical
System Specification – Defective Work Notice Pursuant to Subclause 29.3 of the
Contract”. The email said:
“Just to confirm that we have not in our request for clarification,
requested ‘approval’ for Toshiba. We simply requested clarification
of your 11 August 2016 direction – the clarification request was
simply: ‘Can you please confirm whether the Superintendent has any
objection to Toshiba as an equipment manufacturer if the equipment
complies with the performance requirements set out in the direction
dated 11 August 2016 and the Contract.’ This question is capable of
response now and continued delay [in] answering this is further
delaying the project. …”
-- 29 of 50 --
30
[91] The response was sent on 12 October 2016, “The Superintendent looks forward to
receiving the Contractor’s submission for approval of an alternate manufacturer in
accordance with the Contract”.
[92] On 14 October 2016 the appellant responded as follows:
“It is clear that you will not respond to our specific request for
clarification of your direction dated 11 August 2016 issued under
cover of Tactical-GCOR-000371 (‘Direction’) and instead require
Built to submit certain information in order to facilitate ‘approval’ of
the equipment manufacturer.
In the absence of the requested clarification, Built will implement the
Direction, on the assumption there is no objection to Toshiba as
equipment manufacturer. As advised in previous correspondence and
notices, Built considers that the Direction involves a Variation and will
cause delay.
In relation to the equipment manufacturer, Built does not consider that
‘approval’ is required for Toshiba as equipment manufacturer but will
nevertheless endeavour to provide the information requested. If
following the provision of information the Superintendent
subsequently directs that Toshiba is not an approved manufacturer,
Built will consider that a further variation will have been directed.”
[93] In accordance with what is stated in its 14 October 2016 email, the appellant went
ahead and ordered the condensers and flow boxes necessary to convert the air
conditioning system to a 3 pipe system. It ordered the equipment from Toshiba,
essentially taking the risk on its interpretation of the contract, despite the respondent’s
insistence, current as at that date, that Toshiba was not an approved manufacturer of
air conditioning equipment under the contract.
[94] The primary judge’s findings as to these matters were as follows:
“[1081] From [the time of delivery of the 11 August notice] onwards,
the plaintiff acting reasonably would have been aware that the
delay would increase if steps were not taken to order the
necessary equipment.
[1082] The [appellant’s] design for the three-pipe mechanical system
was finalised on 23 August 2016, which included the number
and type of condensers and branch boxes.
[1083] Accordingly, a contractor acting reasonably would have taken
steps to mitigate the delay at least by 23 August 2016 when the
design was finalised.
[1084] Whilst the plaintiff says the use of Toshiba was still uncertain,
that did not mean that the plaintiff was entitled to take no steps.
Reasonable steps would include considering arrangements to
reserve condensers so they were available. This is particularly
so given the awareness that the condensers were time sensitive.
[1085] It is clearly open that the plaintiff should have taken reasonable
steps to mitigate the effect of delay from 11 August 2016 when
-- 30 of 50 --
31
the [11 August notice] was received. It was clear that the
procurement time for the necessary equipment was a key factor
in the delay. Pursuant to clause 34.3(f), this would result in the
plaintiff not being entitled to an extension of time for the whole
period claimed.
[1086] However, I accept that until the design was finalised, arguably
it was not reasonable to be required to place orders for
equipment as the number of branch boxes and condensers was
not known.
[1087] If it is necessary to consider the operation of clause 34.3(f) of
the Contract, I find that the plaintiff should have placed the
order for the condensers no later than 23 August 2016. Placing
the order for the condensers after that was a failure to take all
reasonable steps to mitigate the effect of the delay.”
[95] The decision of the primary judge based on this finding must be set aside. It fails to
deal with the evidence outlined above.
[96] At [1084] the primary judge reasoned that the appellant ought to have taken steps to
“reserve condensers so they were available”. In fact, the evidence before the primary
judge was that the appellant did attempt to reserve the condensers, but failed in that
attempt through no fault of its own.31 The primary judge did not deal with that
evidence either. In any event, the conclusion at [1087] of the reasons below is not
based on a failure to reserve condensers, but a failure to order them by 23 August
2016.
[97] Having regard to the evidence we have set out above, the appellant did not act
unreasonably and did not fail to take any reasonable steps to mitigate the delay caused
by the need to order (and await arrival of) new equipment for the Toshiba 3 pipe
system.
[98] In written submissions before this Court, the respondent said that the appellant ought
to have sought approval for the use of Toshiba equipment as and from 23 August
2016. There is no reason to think that an earlier enquiry as to this would have
produced any earlier clarification or better co-operation from the superintendent.
Conclusions as to extension of time
[99] As explained above, our view is that the appellant was entitled to an EOT consequent
on the issue of the 11 August notice.
QUALIFICATION OF DELAY CAUSED BY 11 AUGUST NOTICE
[100] Because we have concluded that the appellant was entitled to an EOT, it is necessary
to assess the delay to practical completion caused by the 11 August notice. Each of
the appellant and the respondent called a programming expert. The appellant’s
expert, Mr Bell, made a prospective analysis of the delay caused by the 11 August
notice. It was said both at the trial, and on appeal, that Mr King, the respondent’s
31 See witness statement of Thomas Cook, paragraph 306, and paragraphs 303 and 304 of the appellant’s
submissions below.
-- 31 of 50 --
32
expert, took a retrospective approach to the task. In fact, as discussed below, that
might not be entirely accurate, however, the dichotomy is central to the first point we
must determine as to this issue.
The judgment below
[101] Although the primary judge did not find that the appellant was entitled to an EOT,
she should have gone on to assess the EOT which ought to have been granted, if her
conclusion was wrong.32 The primary judge heard the expert programmers
cross-examined; had the opportunity to ask them questions to clarify her
understanding of the evidence, and heard full submissions as to the issue. To an
extent the primary judge essayed this task. At [1133]-[1167] the primary judge
describes some aspects of the competing expert views, and some aspects of the
competing submissions about the expert views. She then said:
“[1168] If it is necessary to consider the plaintiff’s claim for an
extension of time and it is necessary to consider the expert
reports in respect of the analysis of the delay. I make the
following findings:
(a) Consistent with my earlier findings under the Contract it
is open to consider a prospective or a retrospective delay
analysis.
(b) Mr King’s incremental delay analysis is to be preferred as
it more closely accords with the requirements of the
Contract in clauses 1, 32.2 and 34.3(c).
(c) Mr King’s analysis needs to be further considered in light
of the other findings in these reasons, including in respect
of the Christmas shutdown period.”
[102] The appellant challenges the finding that the contract permits either a prospective or
a retrospective methodology to determine the extent of an EOT; challenges the
preference expressed for Mr King, and challenges the failure to find that Mr Bell’s
calculation of EOT was correct. As well, ground of appeal 2(f) is that the judge gave
no reasons in relation to her findings. That must be accepted; but there is a more
fundamental point, the judge did not make a finding as to the EOT due to the
appellant.
[103] Reasons for judgment must describe the conflict between the parties in sufficient
detail that someone reading the judgment understands the factual basis for the judge’s
decision. However, reasons for judgment need not, and indeed should not, contain
any more descriptive detail than that.33 They should not aim to provide a comprehensive
description of the dispute. There will be much evidence and many submissions which
at the end of a trial will fall away as not being relevant to the findings of fact and
determinations of law which are necessary to resolve the dispute according to law.
[104] Separately, reasons for judgment must expose the reasoning process which has led to
the judge’s determination. This will include explaining why the judge has made
32 Elliott v Lawrence [1966] Qd R 440, 444-445; Stockland Property Management Pty Ltd v Cairns City
Council [2011] 1 Qd R 77, 99, [55], per Keane JA.
33 Beale v Government Insurance Office of NSW (1997) 48 NSWLR 430, 442 and 444, and the authorities
cited there.
-- 32 of 50 --
33
findings of fact; explaining preferences for one part of the evidence over other parts,
and an analysis and resolution of the conflicts thrown up by the factual and legal
aspects of the case.34
[105] The judgment below expresses a conclusion as to the interpretation of the contract,
and a preference for one aspect of Mr King’s evidence, but there is no analysis or
reasoning exposed to support the preference. There is no factual finding as to the
EOT to which the judge considered the appellant was (hypothetically) entitled. This
means that this Court must undertake the task.
Approaches to assessment of delay under the contract
[106] The primary judge found that the building contract permitted either a retrospective or
prospective approach to assess delay under the contract. We think this conclusion
was correct based on the language of cl 34.3. That clause provides that the contractor
“shall be entitled to such EOT … as the Superintendent assesses, if: (a) the Contractor
is or will be delayed in reaching practical completion … [and] (e) the Superintendent
is satisfied that WUC was actually delayed” (underlining added). It seems to us that
this language is sufficiently similar to the language in Civil Mining & Construction
Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd (WICET),35 “has been or will
be actually delayed”, that the reasoning in that case applies here. In WICET
Flanagan J said:
“[657] The issue is whether the Contract permits both a prospective and
retrospective delay analysis. WICET submits that Mr King’s
retrospective delay analysis in respect of Delay Event 9 using
an ‘as planned’ v ‘as built’ analysis is not permitted by
clause 35.5 of the Contract.
[658] In my opinion the better view is that the Contract permits both
a prospective and retrospective delay analysis.
[659] Paragraph 3 of clause 35.5 provides that:
‘If the Contractor is or will be delayed in reaching
Practical Completion … and within 28 days after the
delay occurs the Contractor gives the Principal’s
Representative a written claim … the Contractor shall be
entitled to an extension of time for Practical Completion.’
Clause 35.5 further provides:
‘The Contractor will only be entitled to an extension of
time for Practical Completion pursuant to this Clause if –
(B) the Contractor –
(5) demonstrates to the satisfaction of the
Principal that the Contractor has been or will
be actually delayed in achieving Practical
Completion.’
34 King & Ors v Australian Securities and Investments Commission [2018] QCA 352, [39]ff.
35 [2017] QSC 85, [657]ff.
-- 33 of 50 --
34
[660] The use of the disjunctive ‘or’ gives the Contractor a choice to
demonstrate that either it has been actually delayed or it will be
actually delayed in achieving Practical Completion. The past
tense ‘has been’ as CMC submits, contemplates looking
backwards, after the delay event has expired, to demonstrate
that (with knowledge of hindsight) the Contractor has actually
been delayed in achieving Practical Completion. CMC further
submits that the retrospective approach is particularly appropriate if
the activity delayed occurs towards the end of the project, such
that the time at which the claim for the extension comes to be
assessed is after Practical Completion has been achieved.
[661] WICET makes the following submission:
‘Whilst the word “has” (much like the word “is”) might,
viewed in isolation, suggest a retrospective analysis, the
word is immediately followed the critical words by “or
will be”. The phrase “has or will be actually delayed”
should have the same meaning as “is or will be delayed”.
Further the insertion of the word “actually” does not
require a retrospective analysis. If that were intended, the
word “actually” would not have been proceeded by “will
be”. On a proper construction, the word “actually” simply
emphasises that CMC is only entitled to a EOT if
Practical Completion is affected.’
[662] I do not accept this construction. The use of the words ‘has been
… actually delayed’ addresses past delay permitting or indeed
inviting retrospective analysis. A Contractor would be entitled
to an extension of time for Practical Completion if it
demonstrates either a past or future delay. Further as CMC
correctly submits, WICET’s construction does not give the
word ‘actually’ any work to do.
[663] My interpretation of clause 35.5 as permitting both a
prospective and retrospective delay analysis rest on the ordinary
meaning of the term ‘has been or will be actually delayed’. …”
[107] In arguing that the contract did not permit a retrospective analysis as the basis for
assessment of delay, the appellant said that for delays longer than about 12 days, the
contractor could only submit a claim on a prospective basis because it was obliged by
cl 34.3(b) of the contract to make its claim to the superintendent within 14 days. For
that matter, the superintendent was obliged to assess the claim within 28 days.
[108] The time limits in cl 34.3 may affect what course is taken by the parties as a matter
of practicality in cases of lengthy delay. But in our view, this cannot affect the
language discussed at [106] above which allows claims to be made and assessed on
either basis.
[109] In considering the time limits in cl 34.3, questions will arise as to whether or not the
superintendent’s initial assessment of delay and allowance of EOT is final, having
regard to the second paragraph of cl 34.5:
-- 34 of 50 --
35
“Notwithstanding that the Contractor is not entitled to or has not
claimed an EOT, the Superintendent may at any time and from time to
time before issuing the final certificate direct an EOT. The
Superintendent is under no obligation to exercise this discretion
reasonably, fairly or for the benefit of the Contractor.”
[110] This clause might well be interpreted in accordance with well-established case law36
that certificates other than the final certificate have a provisional effect only, which
common law rule is a term of cl 37.2 of this contract, at least so far as progress
certificates are concerned. Assessment of EOT is directly related to monies certified
to be due and owing between the contractor and principal because of its connection
to the owner’s entitlement to liquidated damages, and the builder’s entitlement to
delay damages. One can imagine circumstances where, say, a lengthy extension of
time was granted on the basis that procurement of relevant equipment would take
months but then, by chance, a third party cancelled an order with the same
manufacturer, and the equipment became available immediately. It is hard to imagine
that the superintendent would not have the right to issue a further assessment of EOT,
effectively a negative one.
[111] The appellant argued that if cl 34.3 permitted either a prospective or retrospective
methodology, the superintendent ought to have assessed delay on a prospective basis
because the appellant chose to submit its claim on a prospective basis. We reject that
as a general proposition. Having regard to the language used in this contract, if the
appellant contractor lodged a claim on the basis of a prospective assessment, it was
open to the superintendent to assess it on a prospective basis, a retrospective basis, or
on an incremental basis.
Assessment of delay by a court or arbitrator
[112] We also reject the related submission by the appellant that this Court “stands in the
shoes of the superintendent” and must assess the delay caused by the 11 August notice
as the superintendent should have assessed it, ie., in this case, on a prospective basis.
The case cited as authority for these propositions was Beaufort Developments (NI)
Ltd v Gilbert-Ash NI Ltd.37 This case is not authority for the propositions put forward
by the appellant, and in fact is to the opposite effect. It is a well-known case largely
because it overruled obiter dicta in Northern Regional Health Authority v Derek
Crouch Construction Co Ltd38 to the effect that the court has no authority to open up
a certificate given by, relevantly here, a superintendent under a building contract. A
summary of the particular obiter dicta in Derek Crouch is:
“Derek Crouch was a decision of the Court of Appeal in the United
Kingdom which involved a construction contract which provided for
reference to arbitration in the event of any dispute or difference arising
between the parties. The arbitration clause expressly empowered the
arbitrator ‘to open up, review and revise the architect’s certificates,
opinions, decisions, requirements or notices’.
Disputes arose concerning decisions of the architect extending time.
… The Principal under the contract sought and failed to obtain
36 For example, Daysea Pty Ltd v Watpac Aust Pty Ltd [2001] QCA 49, [18]-[21].
37 [1999] 1 AC 266.
38 [1984] QB 644.
-- 35 of 50 --
36
injunctions restraining the Contractor from proceeding to arbitration.
The appeal was dismissed.
In the course of argument a submission was made that unless the court
did have power to do all the things the arbitrator could do, it would be
unfair to deprive a party of the right to arbitrate. Although it was not
necessary to rule on that argument to dispose of the appeal, the Court
expressed the view that whilst the arbitrator had powers to open up,
review or revise the architect’s certificates, the Court did not. That
conclusion was founded upon the contractual intention revealed by the
conferral of the express open up and review power on the arbitrator
but not on the Court.”39
[113] The same commentator said this of the decision in Beaufort:
“The effect of the decision of the House of Lords is correctly
summarised by the headnote:
‘The arbitration clause was intended to confer on the arbitrator
the plenitude of powers possessed by the court to determine the
rights of the parties; … it was necessary to spell out those
powers in the case of the arbitrator but not in the case of the
court since his powers were derived from the contract under
which he was appointed, whereas the court’s jurisdiction was
unlimited; … therefore, the fact that power to open up, review
and revise was expressly conferred upon the arbitrator but not
upon the court could not be construed as removing the court’s
power; … .’”40
[114] Beaufort Developments made a distinction between contracts which use machinery to
give effect to the terms of the contract, and contracts which provide that parties’ rights
are to be determined only by means of prescribed machinery.41 In the former case,
the court or an arbitrator will have power to determine whether or not the machinery
in the contract has been properly applied by, say (relevantly), a superintendent under
a building contract. The contract here is within this first category.42
[115] One result is that if this court finds the superintendent wrongly determined a matter,
we are not bound to determine the question only on the basis of material which could
have been known to the superintendent. Authority for that stretches back at least to
Bwllfa and Merthyr Dare Steam Collieries (1891) Ltd v Pontypridd Waterworks Co.43
In a passage which has become famous, Lord Macnaghten held that:
“If the question goes to arbitration, the arbitrator’s duty is to determine
the amount of compensation payable. In order to enable him to come
39 John Bond QC, ‘Has Derek Crouch Risen from the Dead?’ (2014) 33 (1) Arbitrator & Mediator, p 111,
114-115.
40 Above, p 115.
41 Above, p 288.
42 Walton v Illawarra [2011] NSWSC 1188; Republic of Turkey v Mackie Pty Ltd & Anor [2019] VSC 103; SSC
Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd & Anor [2016] VSCA 119.
Particularly having regard to [75] of that later decision, we do not see that the earlier decision of Dura
(Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (2013) 41 VR 636 has any application
to this case, or should be understood as compelling any reasoning contrary to Beaufort Developments.
43 [1903] AC 426.
-- 36 of 50 --
37
to a just and true conclusion it is his duty, I think, to avail himself of
all information at hand at the time of making his award which may be
laid before him. Why should he listen to conjecture on a matter which
has become an accomplished fact? Why should he guess when he can
calculate? With the light before him, why should he shut his eyes and
grope in the dark?”
[116] This passage was approved in this Court in CMB No. 1 Pty Ltd v Cairns City Council44
and by the High Court in Kizbeau Pty Ltd v WG & B Pty Ltd.45 The passage from
Kizbeau and the passage from Bwllfa was approved in HTW Valuers (Central Qld)
Pty Ltd v Astonland Pty Ltd.46 Bwllfa was approved as applicable in a building
contract case – V601 Developments Pty Ltd v Probuild Constructions (Aust) Pty Ltd.47
We would extend this to say that if, because of time limitations in the contract, the
superintendent had no option but to assess delay on a prospective basis, that does not
mean that, years after the relevant events, the court must do the same. Further, even
though the contractor has chosen to submit a claim based on a prospective analysis,
neither the superintendent, nor a court or arbitrator need assess the claim on
a prospective basis.
[117] In summary, as to the basis for assessment of delay in this case, based on the reasoning
in WICET, we find that the appellant was allowed by the contract to prepare its delay
claim under cl 34.3(b) of the contract based on a prospective analysis. The
superintendent assessed it at nil. That was because he was mistaken about the nature
of the 11 August notice. It was open to the primary judge to assess delay on
a prospective basis as the appellant urged; it was also open to her to assess it on
a retrospective, or partly retrospective basis, even though that course would not have
been available to the superintendent (at least on an initial assessment) because of the
time constraints on his response to the appellant contractor’s claim for an EOT.
Assessment of the programming evidence in this case
[118] The appellant’s expert, Mr Bell, said an EOT of 117 days was warranted. The
respondent’s expert, Mr King, said 83. The difference between them came down to
three matters which we deal with in turn. The first is by far the most significant.
(1) Starting date for calculation of delay
[119] Clause 1 of the building contract defined the term “approved construction program”
as being one of the documents annexed to the building contract, and “any revised
approved construction program approved by the Superintendent from time to time
pursuant to subclause 32.2”. Clause 32.2 obliged the contractor to issue a revised
approved construction program at least once a month and provided that the current
construction program was to be used to “assess delays and any EOT”.48
[120] The additional activities necessary by reason of the 11 August notice were assessed
by Mr Bell to be:
44 [1999] 1 Qd R 1, 13 and 20-21.
45 (1995) 184 CLR 281, 293.
46 (2004) 217 CLR 640, 658, [39].
47 [2021] VSC 849, [623] and [627].
48 Both parties and both the expert programmers were content to work on the basis that all the revised
programs relevant to this issue had been approved by the superintendent.
-- 37 of 50 --
38
“(a) A mobilisation period of 1 week for design and ordering of plant
and equipment. There would be two separate crews working on
the corridor works impacted by the Mechanical Variation; one
team from Levels 1 to 6 and another from Levels 7 to 12;
(b) A 12-week procurement period for the condensers and a further
12 days for installation; and
(c) A 5-week procurement period for the branch boxes and a further
14 days for installation over the 12 floors.”
[121] This was not controversial between the parties. Nor was it controversial that the
condensers did not arrive for 10 days after they were scheduled to arrive.
[122] A particular feature of the activities made necessary by the 11 August notice
(emphasised by both Mr King and Mr Bell in their evidence) was that the delay
consequences were largely in procuring the necessary equipment.
[123] Another feature of the effect of the 11 August notice was that it added over three
months delay to the project at a time when the programming showed that there would
otherwise have been only around three months of work still to be performed under
the contract.49
[124] The third peculiar feature relevant to assessing delay caused by the 11 August notice
was that, because the appellant contractor was uncertain as to what it was required to
do to comply with the 11 August notice, see [81]-[91] above, it did not write this additional
work and associated delay into its construction program until 28 October 2016.
Mr Bell’s analysis
[125] The appellant’s expert, Mr Bell, took the view that the appropriate program to use as
the starting point for assessment of delay was the 1 August 2016 program. This was
the most recent version of the program before the 11 August notice. It was not
impacted by the delay due to the 11 August notice. Mr Bell took the 1 August
program, rewrote it to include the activities necessary as a result of the 11 August
notice, and added time to reflect the actual date of the condensers arriving on site.
[126] Mr Bell used a prospective delay analysis because he thought the contract required
it50 (wrongly on our analysis). He acknowledged both in his report,51 and when he
was cross-examined,52 that such an analysis is to some extent hypothetical and thus
may be inaccurate. A passage in his cross-examination was as follows:
49 T 10-18 per Mr Bell. The exact date upon which practical completion might have been achieved as
at, say 10 August 2016 was somewhat controversial between the programming experts, but in general
terms this proposition was not.
50 Paragraphs 46-53 of his report, and t 10-35.
51 Paragraph 48, “The product of this method of analysis is a conclusion as to the likely delay of the
modelled delay events on the program/critical path that is most reflective of the contemporaneous
position when the delay events arose. This method usually does not capture the eventual actual delay
caused by the delay events as subsequent project progress is not considered”; paragraph 49, “Where
an EOT application is assessed after completion of the works, or significantly after the effect of an
Employer Risk Event, then the prospective analysis of delay referred to in the guidance to Core
Principle 4 may no longer be appropriate.” (his emphasis).
52 Tt 10-35-36, where he acknowledges that it is a “recognised drawback of a prospective approach” that
it “does not capture the eventual delay”.
-- 38 of 50 --
39
“So do you accept that one – that is, the retrospective as-planned
as-built – captures the actual delay and the other only captures the
hypothetical possible likely delay?---Well, an as-planned versus
as-built, if it’s properly done or done at all, will capture – it will rely
on the events as they actually unfolded and requires judgment of the
analyst to work out why or what was going on or – or what the cause
of those events was. The prospective approach, if not corrected for
actual dates, will be a theoretical forecast of what was expected at that
time, but, in this instance, it’s been corrected for the actual date of
delivery.” – t 10-38.
[127] This cross-examination highlighted that one difficulty with a prospective approach is
that it assumes that the forecast of time necessary to attend to new activities is
accurate. A little later in cross-examination Mr Bell acknowledged that, apart from
the adjustment to account for late delivery of the condensers, he had simply adopted
the appellant’s estimates of the activities, and durations of those activities, as being
the basis for impacting the 1 August program – tt 10-41-42.
[128] A second factor capable of producing inaccuracy when a prospective approach is
taken, is that events which occur after the impact analysis, and which delay the works,
are ignored. In fact it is possible to perform a prospective analysis and then, as an
additional step, consider the later history of the works shown in revised programs in
order to “determine whether the criticality of the relevant activity [is] maintained”.53
[129] In cross-examination Mr Bell acknowledged that this second factor might be a
problem “in different circumstances”. However, he thought it was not a problem in
the current case because at August 2016 the project had about three months left to run
and in effect a single activity (most of which consisted of procurement time) was
impacted into the program – t 10-42, and see t 10-81 ll 5-15.
Mr King’s analysis
[130] Mr King chose a different starting point for his analysis. He looked for the first
program to show the effect of critical delay54 resulting from the 11 August notice and
found that it was a program produced on 28 October 2016. Mr King then chose the
preceding program, dated 18 October 2016, as the starting point to calculate the effect
of the 11 August notice.55
[131] There was no case run by the appellant that there was any theoretical or
methodological error in Mr King’s selecting the 18 October 2016 program as his
starting point. The argument was that he ought not to have done so in this case
because, although the program of 18 October 2016 did not show air conditioning as
on the critical path, that was because the appellant had not yet made a decision as to
what works were required by the 11 August notice, and therefore had not revised its
program to show the effect of delay caused by the 11 August notice. In effect, the
appellant said delay existed but had not been recorded in the program. We accept the
logic of the appellant’s argument to this point.
53 WICET above, [643]. That was the approach taken by the preferred programmer in that case (Mr King,
as it happened).
54 Critical delay is delay to an activity on the critical path, that is, it is delay which will affect the date for
practical completion.
55 Air conditioning was not on the critical path to practical completion on the 18 October program, or
those which preceded it.
-- 39 of 50 --
40
[132] The appellant’s argument continued that, because the court is undertaking this
assessment with the benefit of hindsight, the court knows the duration of the extra
activity required by the 11 August notice and therefore the court can conclude that,
although it was not documented in the 18 October 2016 program, air conditioning
was in fact on the critical path and a cause of critical delay as at that date.56 It was
said therefore, to be an error on Mr King’s part to use the 18 October 2016 program.
[133] The fallacy in this argument is that although one might readily accept that, in fact,
there was critical delay caused by the 11 August notice as at 18 October, that delay
had not been written into the 18 October 2016 program. Other delays, caused by
other things, to other parts of the work, had been. These things had an effect on the
time of performance of the air conditioning works which was independent of the
effect of the 11 August notice: the 1 August 2016 program showed that air
conditioning installation was to finish on 1 September 2016 and the 18 October 2016
program showed it finishing on 2 November 2016, a difference of 32 days.57 In our
view, it was correct to take that independent delay to the air conditioning works into
account in assessing delay to practical completion attributable to the 11 August notice.
[134] In fact, Mr Bell explained how an incremental or windows analysis is performed at
t 10-81 ll 10-15. The programmer is required to take the programs subsequent to the
emergence of delay; remove the delayed activity, and then re-impact the programs,
month by month, with the delay to be assessed. In this way other events causing delay
on site and thus potentially reducing critical delay caused by, in this case the
11 August notice, are accounted for, and the assessment of delay becomes less
prospective and theoretical, and more realistic. By using the 18 October 2016
program this is what Mr King was doing, the only difference (which is immaterial) is
that because the appellant had been unable to write the delay into the program at that
stage, Mr King did not have to first “remove the delay[ed] activity”, to use Mr Bell’s words.
[135] When the appellant’s programs from 1 August 2016 through to 18 October 2016 are
examined, they show that the façade works were on the critical path and a cause of
critical delay. That delay slipped, so that the programs of 3 September 2016,
27 September 2016 and 18 October 2016 saw the date for practical completion extend
from: 14 November 2016 to 1 December 2016; 1 December 2016 to 2 December
2016, and 2 December 2016 to 16 December 2016 respectively. These delays were
due to façade works and joinery works which Mr Bell agreed were not related to the
air conditioning.58
[136] It follows in our view that Mr King’s choice of the 18 October 2016 program was not
erroneous, and in fact led to an analysis which was superior to Mr Bell’s analysis,
because it took account of events between 11 August and 18 October 2016 which
caused delay to the contract works, and extended the time to practical completion, but
were not associated with the 11 August notice.
[137] It remains to deal with a subsidiary argument advanced on behalf of the appellant
about Mr King’s use of the 18 October 2016 program as a starting point. This was
56 Mr King was asked to address a hypothetical scenario in which the activity required by the 11 August
notice was inserted into the 1 August 2016 program. That scenario showed that air conditioning
became critical.
57 When 32 days is added to Mr King’s 81 days, it yields the figure of 113 days, delay which the appellant
was prepared to accept as accurate for the purpose of this appeal.
58 See the cross-examination at t 10-66 to t 10-74.
-- 40 of 50 --
41
that the slippage in the dates for practical completion recorded in [135] above were
in some indirect way related to the 11 August notice. Mr Cook’s evidence about this
was:
(a) immediately after the 11 August notice:
“… the ongoing mechanical design issues started to impact the
progress of works on site. Next to no mechanical work was being
done, and the word had got out to many other trades about what was
likely to happen - that is, work that had been completed, or was being
carried out, would probably need to be demolished and re-done.
As a result, the motivation of the workers on site was low and
productivity began to be impacted. I remember that during this period,
many subcontractors were ringing me asking what was going on but
I could not tell them as Built did not know ourselves.”
(b) by September 2016:
“… All mechanical works had stopped, as Batec’s59 workers had all
walked off site due to the ongoing uncertainty and would not come
back. All other trades were moving very slowly up the building; their
numbers were down and there was little momentum.”
[138] The highest the evidence got at an expert level was Mr Bell who said, of the slippage
in the date for practical completion between August and October, “Well, I’m not sure
if it is unrelated to the [11 August notice]. There’s a range of matters that it’s my
understanding weren’t progressed during that period pending resolution of the scope.
And, depending on those items, that may well have had an impact on the critical path
as it progressed.” – t 10-67. Mr Bell also made mention of the fact that by the
18 October 2016 program one of the critical paths ran through finishes, and he said
that finishes would have been affected by the work required by the 11 August notice
– t 10-74. He could not articulate any more precise concern than this, and he did
accept that finishes were on what he called a “secondary critical path, not the primary
critical path” – t 10-74.
[139] It may be that there was some indirect effect of the 11 August notice which
contributed to the slippage in the date for practical completion between 1 August 2016
and 18 October 2016. If there was, it was not able to be articulated or quantified by
any witness. The slippage in practical completion was through the critical path
showing façade works to be critically delayed, and in cross-examination Mr Bell
agreed that: (1) that work was not related to the air conditioning work, and (2) work
on the façade continued into February 2017, beyond the period he had identified as
the period of critical delay attributable to the 11 August notice – t 10-70 and t 10-77.
In these circumstances we do not consider that any adjustment to Mr King’s figure is
warranted in respect of this point.
(2) Further reduction to 81 days
[140] Mr King gave it as his view that his 83 day figure ought to be reduced by another two
days. We reject this. Eighty-one days is the measure of time between the late
completion date for the air conditioning in the 18 October 2016 program and
59 The appellant’s air conditioning subcontractors.
-- 41 of 50 --
42
28 January 2017, which is the date the air conditioning equipment arrived on site.
Clause 34.3 allows an extension of time if the contractor is “delayed in reaching
practical completion”. The correct analysis should rest on the comparison of the dates
for practical completion in the 18 October program and 26 October program (adjusted
to allow for delayed delivery of the condensers on 28 January 2017).
(3) Christmas shutdown
[141] The building site was programmed to be shut down between 18 December 2016 and
3 January 2017. The period of delay caused by the necessity to comply with the
11 August notice spanned that shutdown period.
[142] Mr King does not go so far as to say that it is correct to take that period into account;
he simply does the mathematics to say that if it were taken into account, the period of
delay is only 64 days.
[143] We cannot see that there is any sound reason to reduce the EOT period by the
Christmas shutdown period. The procurement period was measured as the time it
actually took to get the relevant equipment on site. It seems to us that that is the only
relevant fact in calculating the EOT period.
[144] We find that the EOT ought to have been 83 days.
DELAY DAMAGES
[145] Clause 34.9 of the contract provided as follows:
“34.9 Delay damages
For every day the subject of an EOT for a compensable cause, the
Contractor shall be entitled to give the Superintendent a claim for
delay damages reasonably and necessarily incurred by the Contractor
by reason of that compensable cause. The Principal must pay the
amount of the delay damages certified by the Superintendent pursuant
to this subclause 34.9.
The maximum amount payable by the Principal to the Contractor for
every day the subject of an EOT for a compensable cause is the actual
cost incurred by the Contractor up to the maximum specified in
Item 31A.
Nothing in this subclause 34.9 shall oblige the Principal to pay delay
damages for:
(a) the costs of delay which have already been included in the value
of a variation or any other payment under the Contract; or
(b) any qualifying cause of delay which is not a compensable cause
of delay.”
[146] A compensable cause is defined to include a variation. The appellant’s case at trial
was that, pursuant to cl 34.9, it was entitled to delay damages consisting of: (1) on-site
overheads incurred during the period of critical delay, and (2) off-site overheads
incurred during the period of critical delay. The trial judge was against the appellant
on both claims. The appeal is only against the finding in relation to on-site overheads.
-- 42 of 50 --
43
On-site overheads
[147] The appellant made a claim for delay damages for on-site overhead costs during the
period of critical delay caused by the 11 August notice. As described in its
submissions in this Court, “These costs are not directly related to any particular item
of work, but are time related, essentially for Built’s on-site costs of being at the
Project Site for a prolonged time due to the [11 August notice]”.
[148] A claim was allowed on this basis in WICET.60 The relevant clause in WICET was
differently worded to cl 34.9.61 The clause in WICET made it clear that on-site
overheads attributable to delay were recoverable, and identified that category of costs
separately from costs “necessarily incurred by the Contractor by reason of the delay”.
Nonetheless, the respondent did not challenge the idea that time-related on-site
overheads could be the subject of delay damages within the meaning of cl 34.9. Its
submission was that the evidence did not show that the amounts claimed by the
appellant were “reasonably and necessarily incurred by the Contractor by reason of
[the 11 August notice]”, within the meaning of cl 34.9. The respondent argued that
the appellant had failed to prove this aspect of its case. The appellant’s case for delay
damages was advanced on a minimum of evidence. We deal with the arguments in
three stages.
1. Incurred
[149] Mr Bell was briefed with the part of the appellant’s job costs for the project
categorised as ‘preliminaries’, which term was used to mean on-site overheads.62 He
prepared a report in which he assumed those costs were incurred, and were on-site
overheads. He examined them, and deleted from the list those costs which he thought
were not time-related.63 It was only those costs which were time-related which he
used to assess delay costs. He did that by calculating an average daily time-related,
on-site overhead cost for each month occurring in the period of delay caused by the
11 August notice, and applied those average daily cost rates to the number of days in
the months during the period of critical delay.
[150] The appellant proved the costs in the preliminaries document provided to Mr Bell
were actually incurred, as that document was tendered by consent.64 It was thus
evidence of what it appeared to be. It was not put to any witness that the costs were
not actually incurred.
2. Necessary by reason of 11 August notice
[151] So far as the requirement that the costs be necessarily incurred by reason of the
11 August notice, the appellant relied upon the same argument which was accepted
60 Above, at [810] and [812].
61 “Where the Contractor has been granted an extension of time under Clause 35.5 for any delay caused
by an event listed in clause 35.5(b)(i), the Principal shall pay to the Contractor such extra Direct Costs
as are necessarily incurred by the Contractor by reason of the delay and for on-Site overheads
attributable to the delay valued by the Principal’s Representative under Clause 40.5. The Principal’s
Representative’s valuation shall exclude any off-Site overheads or profit.” (underlining added).
62 See the statement of Peter Lincoln and part 4.2.2 of Mr Bell’s report.
63 There were other items deducted by Mr Bell, but they were not contentious and it is not necessary to
mention the details of them.
64 See Ascon Contracting Ltd v Alfred McAlpine Construction Isle of Man Ltd (1999) 66 Con LR 119,
134, [42].
-- 43 of 50 --
44
in WICET, namely that, as compliance with the 11 August notice caused it to take
extra time to achieve practical completion thus justifying an EOT, it incurred a
corresponding number of days on-site overheads.
[152] There were some areas of agreement between Mr Bell and the respondent’s expert,
Mr Hardiman, about this issue. In Mr Hardiman’s report he says:
“6.2.37 In my opinion, on-site overheads comprise both fixed costs
(i.e. costs that do not have a relationship to time at site such
as setting up site offices, installation of temporary
telephones) and time-related costs. On-site overheads are
distinct from the cost of the resources (production resources)
that create revenue by working at site.”
[153] Mr Hardiman reviewed Mr Bell’s assessment of what were time-related, on-site
overheads and he agreed with it, “with the possible exception of the Ambiguous
Items” – paragraphs 6.2.31 – 6.2.38 of Mr Hardiman’s report. The Ambiguous Items
were four costs (casual labour; leading hand/carpenter; hoist driver, and nipper)
which, in Mr Hardiman’s view, related “to costs which, based on their description,
could either be costs relating to direct work on site or could be overheads or a
combination of the two” – paragraph 6.2.32. Mr Hardiman said that in order to work
out which the costs were, he would need to examine documents such as site diaries,
job sheets, timesheets, etc, but had not been provided with them. In response to this
aspect of Mr Hardiman’s opinion Mr Bell conceded that the item for casual labour
should not be included in his calculations, and further conceded that an arbitrary
amount of 50 per cent of the costs associated with leading hand/carpenter should be
excluded from his assessment.65 Mr Bell continued to claim the full amounts for hoist
driver and nipper on the basis that these costs related to persons performing support
roles, and undertaking other tasks which were not direct costs of any particular
productive work.66
[154] We would resolve such conflict as exists as to the items to be classified as time-related
on-site overheads in favour of Mr Bell’s evidence. First, because Mr Hardiman did
not give a definite view that Mr Bell’s categorisation was wrong, but merely raised
a question. Secondly, because Mr Bell responded with concessions to Mr Hardiman’s
queries and, after that, Mr Hardiman said nothing more.
[155] Mr Bell and Mr Hardiman used different periods for the calculation of delay damages.
Mr Bell took the view that the calculation involved the costs relevant to the days of
critical delay. Mr Hardiman did not give his view on this issue; he said he was
instructed to assume the period ending on the “adjusted date for practical
completion”.67 These approaches may be philosophically different, however in
practical terms the period identified by each expert was not much different. Both
calculations were based on the programming evidence.68
65 Pages 14 and 15 of the joint report.
66 Pages 15 and 16 of the joint report.
67 Page 10 of the joint report.
68 The appellant’s original claim, based on Mr Bell’s 117 day EOT, was for delay damages from
4 October 2017 to 28 January 2018. In contrast Mr Hardiman’s report identifies the period of delay
identified in Mr King’s report, which was 81 days “ending on either 16 January 2017 (assuming an
adjusted date for practical completion of 27 October 2016) or 30 January 2017 (assuming an adjusted
date for practical completion of 10 November 2017)” – paragraph 6.2.41.
-- 44 of 50 --
45
[156] The condensers necessary for the air conditioning works, as varied, arrived on site on
28 January 2017. Mr Bell’s unchallenged view was that as at that date the appellant
was back in the position it would have been had the 11 August notice not been issued
– t 10-18. It seems to us that this ought to be the end date of the period for delay
damages. The point of delay damages is to compensate the contractor for the delay
costs actually incurred. To do this, the actual period of critical delay should be used,
rather than an equivalent number of days at the end of the building works.69 The
“cost” of days in the two different periods will not necessarily be the same. In general,
it might be assumed that the closer to the end of the building job, the less on-site
overhead costs will be incurred on a daily basis.
[157] The remaining difference between the two experts was a philosophical one: whether
or not the appellant had proved sufficient connection between the 11 August notice
and the costs it claimed. Mr Hardiman said of Mr Bell’s analysis that:
“6.2.39 However, a delay to construction work does not
automatically produce a commensurate retention of all site
overhead resources throughout a period of prolongation.
…
6.2.42 To determine whether the ‘time related site overheads’
identified represent actual costs which were reasonably and
necessarily incurred by reason of the [11 August notice]
under clause 34.9, I have considered whether there is any
documentation or other evidence to show that each item of
time-related overhead resource was on site during the
Assessment Period because of the [11 August notice], and
that such time-related overhead resource would not have
been on site at that time if the [11 August notice] had not
occurred.” (underlining added).
[158] Mr Hardiman notes (and it was uncontroversial), that there were other works,
unrelated to the works caused by the 11 August notice, continuing on site at all times.
He then concludes:
“6.2.44 Based on the documents provided to me, it is not possible to
identify that any of the ‘time-related site overheads’ were
necessarily retained on site during the assessment period
because of the [11 August notice] rather than because of
other work. …
6.2.45 Based on my review of Mr Bell’s report, he also has not
identified documents or other evidence showing that the
costs he identifies would not have been expended in any
event, if the compensable cause of delay had not occurred.
6.2.46 For these reasons, I am unable to conclude that [the
appellant] actually incurred additional time-related
overhead resources during the Assessment Period.
69 Thiess Watkins White Construction Ltd v Commonwealth (1998) 14 BCL 61, 67, per Giles J cited at
[807] of WICET, above; Ascon Contracting (above), [43]. When there was authority on the point, it
is a shame that Mr Hardiman was instructed otherwise. It is also undesirable that he would be given
an instruction as to this matter, rather than simply be asked to express a view within his expertise.
-- 45 of 50 --
46
Accordingly, I have assessed [the appellant’s] claim for
time-related site overhead costs at $NIL.”
[159] Mr Bell accepted that there were other activities on-site during the period of critical
delay – t 10-10. He accepted that labour costs which were included in his time-related
on-site overhead category were not shown to be the costs of working on the
mechanical services variation brought about by the 11 August notice. He said:
“The measure of inclusion is not that [the persons concerned] are
directly working on the mechanical variation, but that they are
working during the period of time which arises due to the mechanical
variation, and they are entirely different things”. – t 10-20.
[160] In cross-examination Mr Bell explained:
“So time-related overheads costs are by definition not attributable to
particular pieces of work. If they were attributable to particular pieces
of work they would simply not be in the overhead category at all; they
would be in the façade category or the, you know, plasterwork
category. So what we’re really saying is that we have to have a certain
level of time-related resources which are on-site for a given month
whether façade works are going on or whether they’re not or whether
mechanical works is going on or whether they’re not. The – the
linkage I have drawn between these costs and the mechanical variation
is that the period of time that arises due to the mechanical variation is
a period of time that would otherwise not be incurred on-site by the
[indistinct] and, therefore, it is additional for that reason.
… There would be all sorts of work, I would expect, going on between
the dates of October and January which would need to be carried out
and would need supervision or management. The whole concept is
that but for the [11 August notice] those things would have been
carried out and the resources would have been incurred in a different
time.” – tt 10-15-16.
[161] Thus it can be seen that the appellant’s case was that it had to keep its site open and
operating for the period of the EOT, and that it should be entitled to its time-related
on-site overhead costs of doing so. Some of those costs were labour costs, but labour
costs which were for supervision, rather than productive work, for example project
managers, not bricklayers. The costs of Mr Meredyth as project manager were
included as time-related on-site overheads. There was cross-examination as to
whether Mr Bell contended that he was supervising air conditioning works for the
period of the delay costs. Mr Bell did not know, and did not regard it as relevant. His
point was that to have the site open and functioning, the project manager needed to
be there, and that because of the 11 August notice that requirement was extended for
the period of the EOT granted.70
[162] The respondents cited Gemmell in support of the idea that it was necessary for the
appellant to show that labour costs included in time-related on-site overheads were
costs of working on the air conditioning system: “In relation to site staff, it will be
necessary to identify the functions of the staff being claimed and that their tasks
70 Tt 10-14-15.
-- 46 of 50 --
47
undertaken correspond to the reason(s) for delay.”71 We certainly agree that it is
necessary to identify the functions of the staff being claimed in order to decide
whether their costs are in truth time-related on-site overheads, or should be
categorised as belonging to other particular productive work, eg façade work.
However, so far as Mr Gemmell’s passage says that the costs of staff which are
properly characterised as time-related on-site overheads must be costs of staff actually
employed on work the subject matter of the variation before their costs are delay
costs, we respectfully disagree.
[163] As Giles J said in Thiess Watkins White Construction (above), whether or not costs
are caused by delay, is a question of fact. What will amount to sufficient proof in one
case may not be sufficient in another. Here, there was a relatively large project
underway, meaning that there was a large building site and many different resources
deployed on it. The 11 August notice was given at a time when (as programmed)
there were three months of the contract to run. In fact there was around seven months’
work completed after it was given. In those circumstances it is not unreasonable for
the appellant to have put forward its delay damages claim on the basis that it did. Had
the respondent wished to argue that some of the resources (human or otherwise)
classified by the appellant as preliminaries ought to have been otherwise classified, it
was open for it to do that. Likewise, had it wished to argue that some of the resources
classified as preliminaries ought to have been demobilised, and then remobilised
towards the end of the EOT period, it was open for it to do that. However, that was
not the approach taken by the respondent. The only cross-examination by the respondent
as to this topic was conducted at a level of philosophical approach to the question.
[164] Mr Hardiman said in his report that he did not have the accounting document which
showed the appellant’s preliminaries (tendered by consent) and which formed the
basis of Mr Bell’s opinion. If he needed that document to make his assessment, he
should have called for it before he signed his report, and the respondent’s solicitors
should have provided it to him. Mr Hardiman further said that Mr Bell should have
gone beyond that document to look at timesheets, invoices, workplace diaries etc.
Mr Hardiman seems to have made that comment on the wrong assumption that it was
necessary for the appellant to prove that the labour costs and other resources included
as time-related on-site overheads had to be shown to be working the air conditioning
system. Nevertheless, if there were other documents such as invoices, timesheets etc
which Mr Hardiman needed, he likewise ought to have called for them before he
signed his report, and they ought to have been provided to him by the respondent’s
solicitors.72
3. Reasonably incurred
[165] The only question remaining as to the application of the first paragraph of cl 34.9 is
whether or not the appellant proved that the costs in Mr Bell’s time-related on-site
overhead schedule were reasonably incurred by reason of the 11 August notice.
Again, the appellant did the bare minimum to make its case.
71 Robert J Gemmell, Quantification of Delay and Disruption in Construction and Engineering Projects
Lawbook, 2 nd ed, 2021, p558.
72 We assume these documents were disclosed. Perhaps some of them such as work diaries, timesheets,
invoices etc may not have been disclosed because they were primary, or source, documents and thus
excluded by a disclosure protocol adopted by the parties. Even if that were so initially, if an expert
reported to his instructing solicitors that he required the documents, one would hope that they would
have been disclosed by the appellant’s solicitors. They certainly would have been ordered to be
disclosed on an application, had there been a real demonstrated need for them.
-- 47 of 50 --
48
[166] Mr Bell gave evidence that he thought the fact that costs were incurred was an
indication that they were reasonably incurred: “in my experience, it typically is a good
indicator that costs were reasonably incurred, because contractors seldom spend
money they don’t have” – t 9-105. He made no investigation as to whether or not the
costs were reasonably incurred. He was not provided with the source documents
which underlay the entries in the accounting document showing preliminaries.
[167] Proof that costs were reasonably incurred by reason of the 11 August notice is a matter
of fact. What will need to be proved in any particular case may differ. Here, the costs
were put forward as costs necessary to keep the site open and functioning. The type
of costs in each case was apparent from its description in the appellant’s preliminaries
document. In the context described at [163] keeping the site open and functioning
was apparently reasonable. If there were types of cost, or amounts of particular costs,
which the respondent wished to challenge as unreasonably incurred having regard to
the 11 August notice, it was able to do so by obtaining and briefing Mr Hardiman
with the documents he said he needed to perform such an exercise. The respondent
chose not to do it.
[168] While it is somewhat unsatisfactory that determination of questions such as this come
down to narrow considerations based on the onus of proof, in our view the appellant
did prove a basis for its costs as reasonably and necessarily incurred by reason of the
11 August notice; it was up to the respondent to challenge it, and it did not.
[169] We allow the appeal as to on-site delay damages. The primary judge’s conclusion
was incorrect. She said:
“[1220] The difficulty with the plaintiff’s proposition is highlighted by
the consideration of the onsite labour costs claimed in respect of
Mr Meredyth. There is no consideration of what Mr Meredyth was
doing on site during this period. He may have been doing work
totally unrelated to the Mechanical Variation. He may have been
doing a mixture of work and some component may have related
to the Mechanical Variation. The plaintiff would only be
entitled to the costs in respect of Mr Meredyth if they were
reasonably and necessarily incurred by reason of the Mechanical
Variation. On the evidence, it is established that he was on site
during the period of critical delay. But it is not established that the
costs for his labour were “by reason of the Mechanical Variation”.
[1221] On the evidence it is not possible to be satisfied that the onsite
overhead costs claimed were reasonably and necessarily
incurred by reason of the Mechanical Variation as required by
clause 34.9. The plaintiff has not established an entitlement to
the costs under clause 34.9 of the Contract. Accordingly, if it is
necessary to consider the claim in respect of delay damages, this
part of the plaintiff’s claim must fail.”
[170] These paragraphs reveal that the primary judge failed to appreciate the nature of the
appellant’s claim, as explained at [161] above.
Overhead costs included in value of variation
[171] The respondent argued that the third paragraph of cl 34.9, see [145] above, meant that
the appellant was not entitled to delay damages because part of the cost to which it
-- 48 of 50 --
49
was entitled for a variation of contract included an amount allowed for overheads.
Clause 36.4(d) of the contract provided, that in pricing variations, the superintendent
was to include, “reasonable rates or prices, which shall include an amount equivalent
to the percentage set out in Item 32A for profit and overheads”. Item 32A of the
schedule to the contract provided that the percentage for profit and overheads in
cl 36.4 was “10% of the cost of the work comprising the variation”. It was common
ground between Mr Bell and Mr Hardiman that the 10 per cent represented 8 per cent
for overheads and 2 per cent for profit.73 Further, both experts agreed that Item 32A
did not distinguish between on-site and off-site overheads, and thus was attributable
to both. As noted above, it was not for the building experts to be proffering opinions
on the construction of the contract. As the parties, in effect, allowed the experts to
define the issues in dispute, we deal with the question of construction of Item 32A on
the basis that it was agreed between the parties, and thus not a matter for our
determination.
[172] As a matter of construction of the contract, the respondent’s argument must be
rejected. The 8 per cent allowed for overheads as part of the value of a variation is
a nominal figure agreed in advance of any dispute. Its relation to delay damages
caused by a variation will vary from case to case. We do not construe cl 34.9(a) as
disentitling a contractor from making a claim for delay damages which includes
overhead costs. Very often overhead costs will be a significant part of a delay claim.
It would require clear express language to bring about the result contended for by the
respondent. There is no such language in either cl 34.9 or cl 36.4(d).
[173] The respondent argued in the alternative, that if delay damages included on-site
overheads, the amount of overheads included in the 8 per cent allowed by Item 32A
should be deducted, because those costs had already been included in the value of the
variation. Mr Bell’s report expressly did not address this question, see section 4.1.
Mr Hardiman expressed the view relied upon by the respondent, but gave no reasons
for it – paragraph 6.2.35.74 In the joint report, Mr Bell argued against Mr Hardiman’s
proposition. First, he said that a valuation made under cl 36 for a variation did not
preclude a claim for delay damages. That is so, but could not be regarded as decisive
of this alternative point. He then remarked on the differences between the 8 per cent
allowance for overheads and delay damages namely: (1) that the 8 per cent figure
applied in an automatic way, whether there was associated delay or not; (2) that the
percentage allowed could not constitute delay damages because it was not an actual
cost incurred; and (3) that delay damages are applicable to the period of delay only,
whereas the applied percentage is not applicable to any time period.
[174] It may be accepted that the 8 per cent allowance, and delay damages as defined, are
different things. It must also be accepted that, depending on the facts of the case, they
may overlap, either to a certain extent, or in total. Again, resolution of this matter
which comes down to proof. The 8 per cent allowance for overheads amounted to
about $80,000 on the appellant’s case at trial.75 On the basis agreed by Mr Bell and
Mr Hardiman that was an allowance for on-site and off-site overheads. The
appellant’s claim for delay damages was in the vicinity of $800,000 for on-site
overheads and about $200,000 for off-site overheads. In another case it might be
73 Page 8 of the joint report.
74 In saying this we would not expect Mr Hardiman to give a view as to the construction of the contract.
He might however have expressed a view as to the factual overlap, or otherwise, between items allowed
in the 8 per cent uplift and the items which the appellant claimed as delay damages.
75 Mr Watson’s report; t 10 – 29, and the respondent’s submissions on trial, paragraph 271.
-- 49 of 50 --
50
obvious, but here, if the respondent principal wished to assert that some of the delay
damages claimed by the appellant must, as a matter of fact, have been included in the
value of the air conditioning variation by reason of the 8 per cent uplift, then it was
a matter for the respondent to prove that, either through evidence, or through putting
the proposition to Mr Bell in cross-examination. There was no evidence called by the
respondent. In cross-examination Mr Bell agreed that the point of cl 34.9 was to make
sure that there was no “double-dipping”. He also agreed that in his calculations he
had not taken into account the 8 per cent allowance for overheads. He essentially said
that because of the differences between the 8 per cent allowance, and what the
contract defined as delay damages, he was not sure that he was able to compare the
amounts, or that the contract required him to: he described it as an “apples and oranges
situation”.76 There the matter rested.
[175] Again it is somewhat unsatisfactory, but having regard to the onus of proof, the
respondent’s contention as to this point must fail.
Appropriate orders
[176] We allow the appeal. Our factual findings as to EOT will have ramifications for the
calculation of delay damages; the amount of liquidated damages which must be
refunded to the appellant, and the amount of damages for defective work which will
need to be refunded to the appellant. The parties did their best to calculate these
amounts at or soon after the hearing of the appeal. However, because the EOT which
we find was not assumed by either party in their calculations, there is a need to
recalculate. Accordingly we direct that the parties are to calculate the amount in
which this court ought to order judgment, including the amount for interest. We
further direct that the parties attempt to agree an appropriate order as to costs. If they
cannot, each party is to file written submissions as to costs, no longer than five pages
each. These further documents are to be filed by 15 February 2023.
76 tt 10 – 30 – 32.
-- 50 of 50 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2022/266