Enhance Property Investments No 3 Pty Ltd v Pier Traders Pty Ltd [2022] QSC 160
SUPREME COURT OF QUEENSLAND
CITATION: Enhance Property Investments No 3 Pty Ltd v Pier Traders
Pty Ltd [2022] QSC 160
PARTIES: ENHANCE PROPERTY INVESTMENTS NO 3
ACN 614 011 175 AS TRUSTEE FOR THE ENHANCE
PROPERTY TRUST NO 3
ABN 13 408 805 139
(applicant)
v
PIER TRADERS PTY LTD
(respondent)
FILE NO/S: BS No 1076 of 2022
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland
DELIVERED ON: 3 August 2022
DELIVERED AT: Brisbane
HEARING DATE: 14 July 2022
JUDGE: Williams J
ORDER: 1. The applicant’s application for costs is dismissed.
2. The respondent’s application for costs is dismissed.
3. There be no order as to costs.
CATCHWORDS: PROCEDURE – COSTS – DEPARTING FROM THE
GENERAL RULE – COSTS FOLLOW THE EVENT – where
applicant applied for orders allowing its contractors access to
the respondent’s land to erect scaffolding on the common
boundary between the two properties – where orders made by
consent allowing access – where both parties seek their costs –
where respondent had legitimate interests to defend – where
the respondent contributed to the protraction of the
proceedings – whether special circumstances exist for award
of costs against servient owner under s 180(6) of the Property
Law Act 1974 – whether an order for costs against the applicant
is justified under s 180(5) of the Property Law Act 1974
Body Corporate for Torwood Hill Residential Retreat CTS
24557 v Fittell [2020] QSC 32, followed
Griffiths v Bradshaw (No 2) [2015] QSC 194, followed
Re: De Pasquale Bros P/L & NJF Holdings P/L [2000] QSC
4, followed
Property Law Act 1974 (Qld), s 180
Uniform Civil Procedure Rules 1999 (Qld), r 5, r 681
-- 1 of 13 --
2
COUNSEL: M S Trim for the applicant
K W Wylie for the respondent
SOLICITORS: Mills Oakley for the applicant
Ellison Moschella & Co for the respondent
[1] On 1 April 2022 Justice Kelly made orders by consent as follows:
“1. The applicant, and J Hutchinson Pty. Ltd. trading as Hutchinson
Builders and RB Scaffolding Pty Ltd be given a licence and
rights to access in connection with the property of the
Respondent at 537 South Pine Road, Everton Park, Queensland
in accordance with Schedule 1 & 2 to this application.
2. The Applicant shall pay the Respondent the sum of $15,000 for
the licence and rights.
3. The proceeding otherwise be adjourned to a date to be fixed for
argument as to costs.
…
6. By 14 April 2022, if either party seeks costs in this proceeding
(excluding previous costs orders) it is to file and serve any
further Affidavits it seeks to rely on in relation to costs and
written submissions regarding costs including orders sought,
the basis for those orders, reference to affidavits it proposes to
rely upon in support of its application, and any authorities or
legislative provisions upon which it seeks to rely.
7. By 28 April 2022, the parties to the proceeding are to file and
serve any affidavit material and submissions in reply to the
other party’s cost submissions and evidence.”
[2] This matter was listed for hearing in the civil list on 14 July 2022. The matter was
originally listed for a half day hearing but ultimately went for just under one day.
[3] There are two applications for determination by the Court. The applicant seeks an
order that the respondent pay the applicant’s costs of the proceedings, to be agreed or
assessed on the standard basis. The applicant makes the application on the basis that
there are “special circumstances” for the purposes of s 180(6) of the Property Law
Act 1974 (Qld) (Property Law Act) which justify the making of such an order.
[4] Also, the respondent seeks an order that the applicant pay the respondent’s costs of
the proceedings up to the date of filing the applicant’s reply material on 28 March
2022 pursuant to s 180(5)(e) of the Property Law Act.
[5] Both parties referred to the affidavit material which had been filed in support of the
substantive application in support of the arguments advanced in relation to costs.
[6] The originating application filed on 27 January 2022 sought orders pursuant to s 180
of the Property Law Act for a licence and rights to access property of the respondent
at 537 South Pine Road, Everton Park, Queensland.
-- 2 of 13 --
3
[7] Section 180 of the Property Law Act deals with the imposition of statutory rights of
user in respect of land and relevantly states as follows:
“180 Imposition of statutory rights of user in respect of land
(1) Where it is reasonably necessary in the interests of
effective use in any reasonable manner of any land (the
dominant land) that such land, or the owner for the time
being of such land, should in respect of any other land
(the servient land) have a statutory right of user in respect
of that other land, the court may, on the application of the
owner of the dominant land but subject to this section,
impose upon the servient land, or upon the owner for the
time being of such land, an obligation of user or an
obligation to permit such user in accordance with that
order.”
[8] The statutory right of user imposed under s 180(1) may take the form of an easement,
licence or otherwise. Section 180(2) also provides that it may be exercisable by
conditions specified in the order including on one or more occasions, until a certain
date or in perpetuity or for some fixed period. It may also be declared who is able to
exercise the right and the manner and conditions of the exercise.
[9] Section 180(3) states:
“An order of the kind referred to in subsection (1) shall not be made
unless the court is satisfied that—
(a) it is consistent with the public interest that the dominant land
should be used in the manner proposed; and
(b) the owner of the servient land can be adequately recompensed
in money for any loss or disadvantage which the owner may
suffer from the imposition of the obligation; and
(c) either—
(i) the owner of the servient land has refused to agree to
accept the imposition of such obligation and the owner’s
refusal is in all the circumstances unreasonable; or
(ii) no person can be found who possesses the necessary
capacity to agree to accept the imposition of such
obligation.”
[10] Section 180(4) sets out what an order may include.
[11] Section 180(5) deals with the Court’s power and includes in subsection (5)(e) that the
Court may make orders in respect of the costs of any of the preceding matters and of
proceedings generally.
-- 3 of 13 --
4
[12] Also relevantly, s 180(6) states:
“In any proceedings under this section the court shall not, except in
special circumstances, make an order for costs against the servient
owner.”
[13] Generally, s 180 of the Property Law Act gives the Court power to interfere with the
private rights of owners where the conditions set out in the section are met and to
impose liabilities upon those rights. Without this statutory power there would be no
ability to achieve this.
[14] Prior to the originating application being filed on 27 January 2022, there was
considerable correspondence between the applicant and the respondent in respect of
the access sought. This included draft terms for access. There were also meetings in
person to discuss the access requirements.
[15] The applicant owned land neighbouring the respondent’s land and had a building
approval to construct a new building on the land at 535 South Pine Road, Everton
Park. The applicant had also entered into a building contract for the construction
work to be undertaken. Limited access rights to the respondent’s property were
sought to enable temporary scaffolding to be erected so that the construction of the
building could be undertaken.
[16] Prior to the commencement of the Court proceedings, it appears from the material in
respect of the various dealings between the applicant and the respondent that it was
not clear precisely why the scaffolding was required, the impact of the scaffolding on
the respondent’s land and precisely where the scaffolding would be located. This last
point is particularly evident from a marked-up copy of draft terms of access which
the respondent returned to the applicant just prior to the commencement of
proceedings.1
[17] The applicant contends that it was clear on the material and from discussions to that
point that the applicant was seeking access to erect scaffolding in both the car park
area and also along what is described as the laneway. That is the full length of the
property boundary. The respondent marked-up the draft terms of access and returned
it to the applicant highlighting that it understood that the scaffolding was only to be
erected in relation to the car park area.2
[18] As the applicant and respondent were unable to agree on terms of access and the
applicant was faced with a pressing need for the issue to be resolved so that the
construction contractor could undertake the work, the Court proceedings were
commenced.
[19] The matter first came before the Court on 8 February 2022 in the applications list
when I made orders listing the matter for a one day hearing in March 2022 and also,
directions for the filing and serving of affidavit material and submissions by the
applicant and the respondent.
[20] On 16 March 2022 Justice Martin varied the previous orders extending the timetable
for various steps and adjourning the hearing of the matter to 1 April 2022. A specific
1 Affidavit of Jason William Blair sworn 25 January 2022, Exhibit JWB-19.
2 Affidavit of Jason William Blair sworn 25 January 2022, Exhibit JWB-19, Schedule 2.
-- 4 of 13 --
5
costs order was made in respect of the adjournment of the hearing date on the basis
that the respondent pay the applicant’s costs of the application to adjourn the hearing
and costs thrown away by reason of the adjournment to be agreed or assessed on a
standard basis.
[21] As required by the directions, the applicant filed and served the affidavit material and
written submissions. The respondent then filed and served its affidavit material and
also written submissions. The applicant filed and served affidavit material in reply
and further written submissions.
[22] It is submitted that by the provision of the applicant’s reply material, the further
information clarified the issues that had earlier been unclear to the respondent.
[23] In particular, it is submitted that a particular three dimensional drawing which was
provided as part of that reply material satisfied the respondent as to the impact on the
respondent’s land. It is submitted that until that point, it was not clear to the
respondent the practical impact of the scaffolding being both over the car park area
and also the laneway.
[24] I also note that the respondent’s affidavit material identified that the respondent had
a particular concern about the impact on the respondent’s land due to lease obligations
including requiring the granting of access to facilities that were to be accessed by the
tenants in the laneway area.
[25] Ultimately, the orders were agreed resolving the access issue. The form of orders
made on 1 April 2022 are in a different form to that sought in the originating
application.
[26] The applicant submits that the 1 April 2022 order reflects an outcome that it sought
from the beginning; that is:
(a) limited access to the respondent’s property in order to partially shut the
respondent’s car park for two five day periods while scaffolding was erected
and dismantled; and
(b) to allow the scaffold to encroach into the air space by the southern boundary of
the property by approximately two metres while work building the premises on
the applicant’s adjoining land was finalised.
[27] The respondent submits that the level of detail and precision in the terms of the order
made on 1 April 2022 was different from that contained in the originating application.
[28] In particular, the definition of “access area” was amended and an additional definition
of “volumetric easement area” was added. Further, the Schedule containing the terms
of access also includes assurances which go beyond what was originally included.
The diagram at Schedule 2 which shows the access area was also revised from that
provided with the originating application.
[29] The Schedule attached to the originating application showed red shading in respect
of the access area. This appeared to be the car park area only and not the laneway
area along the entire length of the respondent’s land. The revised diagram in Schedule
2 makes this clear and removes the previous ambiguity.
-- 5 of 13 --
6
[30] The parties accept that the ultimate order was appropriate to be made pursuant to
s 180 of the Property Law Act.
[31] The submissions do raise whether the issues in dispute could have been resolved
without the need to institute these proceedings.
[32] Further, submissions have been made as to whether the respondent’s concerns had
been met in the original material even though the respondent may not have fully
understood or appreciated that position. The respondent did have the benefit of
assistance from an expert and it is submitted by the applicant that an expert who had
been fully briefed with the relevant plans and diagrams would have understood how
they were to be interpreted.
[33] Section 180 of the Property Law Act provides a mechanism by which a dispute of
this nature can be brought before the Court to have the issue of access determined. In
circumstances where the refusal is said to be unreasonable, it is likely that that
requirement will be satisfied where it becomes extremely unlikely that any further
negotiations will produce an agreement within the reasonably foreseeable future.
[34] That is really what occurred here. Given the time pressures to have the matter
resolved to enable the construction work to be undertaken so that penalties were not
imposed under the construction contract, the applicant took steps to bring the matter
before the Court to have the issue determined.
[35] Further, as envisaged by s 180(5)(d), the Court gave directions for the conduct of the
proceedings. The directions in relation to the delivery of material on a staggered basis
enabled both parties to put forward their material in support or defence of the
application and for there to be a direct traverse of the real issues in dispute.
[36] Ultimately, as often happens with contentious matters, the delivery of the material
clarified issues in dispute and ultimately the orders for access were able to be made
by consent.
[37] The only outstanding issue is in relation to costs. It is appropriate to consider relevant
authorities in respect of costs orders involving applications pursuant to s 180 of the
Property Law Act.
[38] In the matter of Re: De Pasquale Bros P/L & NJF Holdings P/L,3 Chesterman J
considered the meaning of “special circumstances” in a respect of an application for
the award of costs against a servient owner under s 180(6) of the Property Law Act.
In that matter, the trial had commenced and after a number of days a compromise was
reached in respect of the relevant part of the application. The issue of costs remained
unresolved. His Honour relevantly states:
“[9] A pre-condition to an order imposing a right of user is that the
owner of the land to be affected unreasonably refuses to benefit
the applicant’s land. In addition, the section contemplates that
an order for costs against the respondent to the application, the
owner of the affected land, is not to be made except in special
circumstances. The terms of the section suggest that an
3 [2000] QSC 4.
-- 6 of 13 --
7
unreasonable refusal to allow land to be used is not enough to
justify an order for costs. Something more is needed. However,
the generality of the language of sub-section (6) suggests that
the respondent’s conduct which amounts to an unreasonable
refusal may be of such a character as to constitute a “special
circumstance”.
…
[11] It is at once apparent that there are features which distinguish
the application from the typical situation for which s 180 was
enacted. The norm is a case where a land owner seeks to impose
an easement or licence on neighbouring land in order to better
enjoy his own. A burden is imposed upon the other land which
will often, if not usually, be indefinite in duration. The burden
imposed will diminish the extent to which the servient owner
can enjoy his own land.
[12] These features are missing from the present application. The
right of entry to inspect the building and the insertion of the
measuring devices would have been of limited duration.
Moreover, the order was sought for the protection of the NJF
building not as a means of increasing De Pasquale’s enjoyment
of his own land. Thirdly, the imposition of the conditions would
not have diminished NJF’s ability to enjoy its own property.
[13] Individually and collectively these three factors are
circumstances which are “special” in the context of an
application under s 180 of the Property Law Act. They may not,
by themselves, be of sufficient importance to justify an order
for costs against NJF, but there are other circumstances which
make that order appropriate.”
[39] His Honour considered the correspondence between the parties and also the basis for
resisting the order to pay costs. In that case, the respondent sought to resist the order
for costs on the basis that the applicant would not have obtained relief pursuant to
s 180 of the Property Law Act: that is the refusal was not unreasonable. His Honour
did not accept that premise.
[40] The applicant points to and relies upon the additional comments of his Honour at
paragraph 34 of the reasons where his Honour states:
“But the time to test its likely outcome is mid 1999 when it and the
action came on for trial. By this time some engineering and
geotechnical issues had been clarified and refined.”
[41] The applicant relies on this comment in support of its application for costs. That is,
the relevant time to consider the likely success of the application was the time that
the reply material was filed. The fact that there was some “clarification and
refinement” of the material after the originating application is not unusual.
-- 7 of 13 --
8
[42] The decision of Justice Davis in Body Corporate for Torwood Hill Residential Retreat
CTS 24557 v Fittell4 is also of some assistance in considering the issue of the
appropriate costs order. That case concerned an application by a body corporate of a
unit block for orders allowing its contractors to access the respondent’s land to rectify
a retaining wall sitting on a common boundary between the two properties. The
parties ultimately agreed a form of order allowing access which is set out in full in
his Honour’s reasons. The Court was required to determine the issue of costs.
[43] Justice Davis relevantly stated:
“[17] Section 180(6) ousts the ‘general rule’ enshrined in r 681 of
Uniform Civil Procedure Rules 1999 that costs follow the
event. … the fact that [the applicant] obtained relief of a kind
sought in the application is not sufficient by itself to justify a
costs order against [the respondent]. The [applicant] must show
“special circumstances” to secure such an order.
[18] Re De Pasquale Bros Pty Ltd v NJF Holdings Pty Ltd5 is a case
where Chesterman J (as his Honour then was) held that special
circumstances existed and ordered costs against a respondent to
an application under s 180. De Pasquale bears some factual
resemblance to the current case in that the applicant there, like
[the applicant] here, brought the application not to enhance its
land but to protect it. However, comparison of the facts in cases
where “special circumstances” have been found or not found is
unlikely to be of assistance.
[19] Of importance and assistance though, is his Honour’s analysis
of s 180. His Honour observed that s 180 only vests jurisdiction
in the court to make orders where the owner’s refusal to accept
the obligations sought to be imposed upon the land “is in all the
circumstances unreasonable”.6 His Honour reasoned that
because s 180(6) requires ‘special circumstances’ before a costs
order is made against a respondent, it must follow that
unreasonable refusal is not sufficient itself to engage the
jurisdiction to award costs against a respondent. However, his
Honour observed ‘… the respondent’s conduct which amounts
to an unreasonable refusal may be of such a character as to
constitute a ‘special circumstance’”.7 I accept and follow his
Honour’s reasoning.
[20] [Counsel for the respondent] submitted that the usual order is
that a respondent to a s 180 application ought be favoured with
a costs order. Section 180 though says nothing about the
circumstances under which a respondent should recover costs
against an applicant. Where, unlike this case, an order has been
secured against a respondent other than by consent, a finding
must be made that the respondent unreasonably refused the
4 [2020] QSC 32.
5 [2000] QSC 4.
6 Section 180(3)(c).
7 At [9].
-- 8 of 13 --
9
applicant’s request to burden the land with the obligation before
the jurisdiction to make an order is triggered. There cannot be
a presumption in favour of granting costs to a party who has
acted unreasonably.
[21] However, on any application under s 180 of the Property Law
Act, an applicant seeks orders interfering with proprietary rights
vested in the land owner.8 The respondent to an application
under s 180 is entitled to argue for the imposition of conditions
under s 180(4) and the reasonableness or otherwise of the
stance which a respondent adopts on that issue must be relevant
to the question of costs of the application.”
[44] It is clear from a review of all the material filed in relation to this matter that the
applicant thought it was clear what it was asking for and the respondent remained
uncertain as to why the access requested was required and the impact of the
scaffolding on the respondent’s land.
[45] The respondent had a legitimate interest in understanding the impact on its land,
particularly in circumstances where it had obligations to tenants under the lease of the
buildings on the respondent’s land.
[46] Further, whilst the applicant says that the relevant information was contained in
numerous drawings provided prior to the commencement of the proceedings, a
perusal of the schematic diagrams does not clearly show the precise impact on the car
park area and the laneway area of the respondent’s land. Further, given the
inconsistency between various descriptions and the marked up diagram attached to
earlier versions of the access terms and the originating application, there was some
ambiguity as to whether the access was sought over both the car park area and the
laneway area.
[47] The erection of the scaffolding for the period, whilst limited in duration, would have
an impact upon the respondent’s enjoyment of the property and potentially upon its
obligations to its tenants. Given those circumstances, it was understandable that the
respondent sought a clear understanding of the precise nature of the access sought
and the impact from a practical perspective. This included the potential impact of the
scaffolding on the car parking areas and also the access by persons to the laneway
area.
[48] Whilst the negotiations had proceeded for some time, these issues were not ultimately
clarified until the delivery of the reply material. The respondent points to the three-
dimensional drawings at page 22 to 25 of exhibit CSW-2 to the affidavit of Callan
William Sipthorp filed 28 March 2022 as finally clarifying this issue. Further, these
specific drawings were incorporated into the definition of volumetric easement area
which were ultimately part of the terms of access attached to the orders dated 1 April
2022.
8 Lang Parade Pty Ltd v Peluso & Ors [2006] 1 Qd R 42 at [23], Ex parte Edward Street Properties Pty
Ltd [1977] Qd R 86 at 91, Lambert Property Group Pty Ltd v Body Corporate for Castlebar Cove
[2015] QSC 179 at [132] and 2040 Logan Road Pty Ltd v Body Corporate for Paddington Mews [2016]
QSC 40 at [39]-[42].
-- 9 of 13 --
10
[49] The applicant contends that the long history of negotiations between the parties,
including Mr Farmer on behalf of the respondent not raising any concerns or seeking
any further information at various points in time, supports the existence of “special
circumstances” to justify a costs order in its favour.
[50] Generally, the applicant submits that the Court has jurisdiction to make an order in
respect of the costs of the proceedings by virtue of s 180(5)(e) of the Property Law
Act and also r 681 of the Uniform Civil Procedure Rules 1999 (Qld) (UCPR). The
applicant contends that it has been the successful party and has obtained the orders it
sought. Further, the applicant acknowledges that the normal rule that costs follow the
event is dislodged by s 180(6) of the Property Law Act.
[51] In favour of a finding of special circumstances, the applicant contends that each of
the matters identified by Justice Chesterman in Re: De Pasquale Bros P/L & NJF
Holdings P/L is present here. That is:
(a) a right of entry was of limited duration;
(b) the fact that the imposition of conditions would not have diminished the
respondent’s enjoyment of the land;
(c) the abandoning of grounds for resisting the application; and
(d) an ulterior purpose for the refusal.
[52] It appears that the ulterior purpose referred to by the applicant was that the respondent
had been seeking, at earlier points in the negotiations, to also settle a claim in respect
of damage to the property. This was ultimately not pursued as part of the Court
proceedings. I do not consider that matter is relevant to the current considerations.
[53] As to the submission that the respondent abandoned the grounds for resisting the
application, I also do not consider that the current factual circumstances establish that
proposition.
[54] The respondent upon receiving the reply material had its concerns satisfied and acted
appropriately under the obligation in r 5 of the UCPR. As the concerns had been met,
it was appropriate for the respondent to, at that stage, acknowledge that its concerns
could be adequately addressed in the appropriately worded consent orders and revised
access terms and avoid the need for the matter to proceed to a hearing.
[55] Further, in relation to whether the imposition of conditions diminished the
respondent’s enjoyment of the land, there was some impact on the land and also
potential impacts on the respondent’s obligations under the lease agreements. To say
that there was no diminution in the enjoyment of the land is not entirely accurate.
[56] I consider that at least from the respondent’s point of view there existed an ambiguity
in the relief sought and that it was understandable that further information was sought
to clarify the impact on the car park area and the laneway area.
[57] Whilst the applicant was successful in obtaining the relief sought, there was a
refinement of the precise terms of the access. The terms of access also included
assurances.
-- 10 of 13 --
11
[58] Further, whilst the applicant was ultimately successful in obtaining the relief sought,
the respondent also achieved some level of success in having its concerns met by the
precision in the definitions and terms of the grant of access.
[59] In the circumstances I am not satisfied that the applicant has made out “special
circumstances” in order to support an award of costs against the respondent.
[60] It remains necessary to consider the respondent’s application in respect of costs being
awarded to it up until the filing of the reply material on 28 March 2022.
[61] The respondent relies upon s 180(5)(e) to give the Court a power to make a costs
order including in circumstances where consent orders are made granting access. The
respondent acknowledges that the order made does grant a right of access to the
applicant and to that extent the applicant could be said to be “successful”.
[62] However, it is contended that s 180(5)(e) enables the Court, in appropriate
circumstances, to order that an applicant pay the respondent’s costs even when the
applicant is ultimately successful in respect of an application. This is supported by
the orders made by Davis J in Body Corporate for Torwood Hill Residential Retreat
CTS 24557 v Fittell [2020] QSC 32.
[63] The respondent also points to the decision of McMurdo J in Griffiths v Bradshaw
(No 2)9 where both parties applied for costs following a contested hearing which
resulted in the grant of a statutory right of user. In that case, his Honour stated:
“The applicant seeks the costs of his proceeding from the respondent.
Section 180(6) of the Property Law Act 1974 (Qld) provides that in a
case under this section, the court shall not, except in special
circumstances, make an order for costs against the servient owner.
The applicant submits that there are special circumstances.
The respondent submits that there are no special circumstances
warranting an order for costs against her. Further, she submits that
the applicant should pay her costs.
The factors which are relevant to each of these submissions are as
follows:
(a) The respondent’s case, although unsuccessful, was arguable,
the case ultimately turning upon questions of degree.
(b) The respondent acted honestly.
(c) The respondent offered to pay more than $100 000 towards the
construction of a new road, in order to avoid this litigation.
(d) The respondent did not resist the proceeding in order to secure
some financial gain.
(e) The case was appropriately conducted by each side at the trial.
(f) The respondent permitted the continued use of these roads
during the progress of the proceeding.
9 [2015] QSC 194.
-- 11 of 13 --
12
(g) The respondent was motivated to refuse access for reasons
which were unrelated to the use of the roads.
Of those factors, all but the last are in the respondent’s favour. As to
the last factor, the respondent was motivated by her grievance about
the controversy relating to the bore. That may or may not have been
a justifiable grievance and the court should not explore it in the
present context.
With these matters considered, special circumstances are not
established for the imposition of an order for costs against the
respondent. However, the applicant has been successful and having
conducted its case appropriately, should not have to pay costs. In my
conclusion, there should be no order for the costs of the proceeding
and there’ll be an order as per that amended draft.”
[64] The respondent points to the factors identified by McMurdo J and contends that
material factor for determining whether costs ought to be ordered in favour of the
respondent is the reasonableness of the respondent’s conduct.
[65] The respondent contends that the resistance to the orders sought in the originating
application was reasonable, prudent and appropriate. It submits that the proposed
terms of access and the area identified in the Schedule attached to the originating
application were defective and vague. The respondent also points to the applicant’s
“disrespectful and bullish conduct in their dealings with the respondent”.
[66] The respondent submits that it acted reasonably throughout particularly given that
there was insufficient evidence to support the originating application, particularly
“given the fact that [the respondent] was obliged to ensure that its tenancies would
not be unduly impacted by the relief sought by the applicant”.
[67] The respondent also submits that it acted reasonably as evidenced by its change of
position upon receipt of the material of the applicant in reply.
[68] I accept that the respondent’s position was arguable given the concerns of the
respondent about the impact on its tenancies.
[69] For anybody attempting to read the schematic diagrams (even for persons with some
experience in interpreting schematic diagrams) at least some of the schematic
diagrams provided were not clear as to the precise impact on the car park area and the
laneway area of the respondent’s land. In particular, there was some ambiguity as to
the impact on vehicles using the car parks underneath the scaffolding and also for
access to the storage facilities and other amenities in the laneway area.
[70] However, I am not satisfied that at the time that the originating application was filed
that any shortcoming in the applicant’s material meant that the applicant would be
unsuccessful in its application pursuant to s 180 of the Property Law Act.
[71] The Court proceedings were commenced after a protracted period of negotiations
where an agreement could not be reached and by then time was of the essence in
relation to the construction contract.
-- 12 of 13 --
13
[72] There was a significant level of detail in the applicant’s material and had the matter
proceeded to a contested hearing, it may have been that the trial judge could have
been satisfied on that material that the relevant statutory requirements had been met.
[73] However, I consider that the nature of the issues are not of such a nature as to justify
the making of a costs order in favour of the respondent. This is also in circumstances
where on the evidence, the respondent did not clearly articulate the concerns it had
with the material provided when given the opportunity to do so. There were several
opportunities in the negotiations prior to the commencement of proceedings when
these issues could have been clearly ventilated and were not, or alternatively, were
not done in such a way as to convey to the applicant the precise matters requiring
further clarification.
[74] Both parties missed opportunities at earlier points in time to address some of these
issues. Unfortunately, a level of miscommunication persisted for a considerable
period of time through the negotiations that could have been rectified with clear
communication and engagement.
[75] Ultimately, the applicant needed to commence the Court proceedings in order to
facilitate the making of orders granting a right of access to enable it to undertake the
approved building work. Section 180 operated as intended.
[76] The directions made by this Court for the exchange of material also enabled the
relevant information to be provided so that the proceeding could be dealt in the most
efficient and expeditious way possible. This is evidenced by the delivery of the
respondent’s material which clearly identified the areas of concern of the respondent
and also the applicant’s reply material which addressed those concerns to a
satisfactory level.
[77] Where an application is made under s 180 of the Property Law Act and the applicant
is successful in obtaining an order, generally10 the applicant is not awarded the costs
of successfully obtaining the orders. There may be some circumstances where the
applicant is required to pay the respondent’s costs.
[78] However, where there has been the need to commence the proceedings, it would not
be the automatic outcome that a respondent would have its costs paid where
ultimately there has been an “unreasonable” refusal to agree to the terms sought which
found the basis for making the order. Here, the process operated as intended and
ultimately the issues in dispute were resolved so that a consent order could be made.
[79] In the circumstances and balancing the various relevant factors, I consider that the
appropriate order is that there be no order for costs of the proceeding. Accordingly,
the order of the Court is that:
1. The applicant’s application for costs is dismissed.
2. The respondent’s application for costs is dismissed.
3. There be no order as to costs.
10 Except in special circumstances.
-- 13 of 13 --