Bluepoint Properties Pty Ltd & Anor v Zuri Properties Pty Ltd & Anor [2022] QSC 26
SUPREME COURT OF QUEENSLAND
CITATION: Bluepoint Properties Pty Ltd & Anor v Zuri Properties Pty
Ltd & Anor [2022] QSC 26
PARTIES: BLUEPOINT PROPERTY PTY LTD ACN 160 455
578
(First plaintiff)
AND
BLUEPOINT HENDRA PTY LTD ACN 622 756 389
AS TRUSTEE FOR THE WHITCOMBE HENDRA
TRUST, DORE HENDRA TRUST AND LINDSAY
HENDRA TRUST
(Second plaintiff)
v
ZURI PROPERTIES PTY LTD ACN 615 214 910 AS
TRUSTEE FOR THE HENDRA ARTERIAL UNIT
TRUST
(First defendant)
AND
BOARDWALK MARINE INVESTMENTS PTY LTD
ACN 151 110 995
(Second defendant)
FILE NO/S: 12390 of 2017
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT:
Supreme Court
DELIVERED ON: 8 March 2022
DELIVERED AT: Brisbane
HEARING
DATES:
14-16, 19-22, and 26 July 2021
JUDGE: Bradley J
ORDER: The Order of the Court is that:
1. Judgment be entered for the defendants on the
plaintiffs’ claims.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTURAL
-- 1 of 32 --
2
PRINCIPLES – DISCHARGE, BREACH AND
DEFENCES TO ACTION FOR BREACH –
CONDITIONS – CONDITIONS PRECEDENT AND
SUBSEQUENT – where the plaintiffs and defendants are
the only parties to the deed – where the due diligence
clause of the deed required the plaintiff to give notice –
where the plaintiff gave no notice to the defendant – where
the plaintiffs argue that the failure to give notice rendered
the deed voidable at the option of either party to the deed –
where the defendants argue that the plaintiffs’ failure to
give notice was that the deed terminated – whether the
failure on the part of the plaintiff to give notice by the
agreed time resulted in a failure to satisfy the express
condition precedent and thereby termination of the deed
DAMAGES – ASSESSMENT OF DAMAGES IN
ACTIONS FOR BREACH OF CONTRACT –
PARTICULAR HEADS OF LOSS – LOSS OF CHANCE
OR OPPORTUNITY – where the plaintiffs claim damages
for breach of the deed – where the damages are said to be
the loss of valuable commercial opportunity – where the
defendants argue that the deed was terminated and that the
plaintiffs have no entitlement to such damages – whether
the defendants caused the plaintiffs to lose a valuable
opportunity
INTELLECTUAL PROPERTY – CONFIDENTIAL
INFORMATION – USE OF THE INFORMATION –
where the plaintiffs seek damages from the defendants for
breach of a duty of confidentiality under the deed and in
equity – whether the defendants have breached their duty
of confidentiality under the deed and in equity
ESTOPPEL – ESTOPPEL BY CONDUCT – ACT,
OMISSION OR ASSUMPTION – WAIVER – where the
plaintiffs argue that the prevention principle means the
defendants are estopped from asserting that the deed
terminated – whether it was unconscionable for the
defendants to treat the deed as at an end by reason of the
non-delivery of a Due Diligence Notice
Transport Infrastructure Act 1994 (Qld), s 33, 62(1)
Sustainable Planning Act 2009 (Qld)
Badenach v Calvert (2016) 257 CLR 440, cited
Donaldson v Bexton (2007) 1 Qd R 525, cited
Gange v Sullivan [1966] 116 CLR 418, not followed
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104, 116 [47], followed
New Zealand Shipping Co Ltd v Societe des Ateliers et
Chantiers de France (1919) AC 1, cited
Perovich v Whitton (No 2) (2016) 250 FCR 272, applied
-- 2 of 32 --
3
Principal Properties Pty Ltd v Brisbane Broncos Leagues
Club Limited (2014) 2 Qd R 132, applied
Quinn Village Pty Ltd v Mulherin [2006] QCA 433, not
followed
Sellars v Adelaide Petroleum NL (1994) 179 CLR 332,
cited
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418,
considered
COUNSEL: G Handran QC with W LeMass for the plaintiffs
D Clothier QC with A Psaltis for the defendants
SOLICITORS: McBride Legal for the plaintiffs
Bartley Cohen for the defendants
[1] The plaintiffs’ claims against the defendants relate to real property at 132A East-
West Arterial Road, Hendra1 (the Property). They say they suffered loss, including
of a valuable opportunity to develop part of the Property, because the first defendant
(Zuri) breached an agreement. The plaintiffs also say Zuri and the second
defendant (Boardwalk) misused confidential information about the plaintiffs’
planned development to “springboard” Zuri’s own development on the Property.
Overview
[2] As the address indicates, the East West Arterial Road is the only roadway adjacent
to the Property. It forms the Southern boundary of the Property. It is a State-
controlled road. On 2 March 2015, the chief executive of the Department of
Transport and Main Roads (DTMR) had decided the location at which access
between the Property and the road was permitted and associated conditions and
restrictions, pursuant to s 62(1) of the Transport Infrastructure Act 1994 (Qld) (the
TIA). Any works on the road corridor or on the Property that would interfere with
the road or its operation required approval of the chief executive of DTMR under
section 33 of the TIA.
The deed
[3] On 16 December 2016, Zuri completed a contract to purchase the Property from
Stockland Development Pty Ltd, paying $8.69 million.
[4] On 5 January 2017, Zuri and the first plaintiff (Bluepoint) executed a deed (deed).
By it, they provided for Zuri to grant Bluepoint a call option for Bluepoint (or its
nominee) to purchase part of the Property (the Land), and for Bluepoint to grant
Zuri a put option for Zuri to sell the Land to Bluepoint. Zuri and Bluepoint agreed
that, if either option was validly exercised, then Zuri and Bluepoint (or its nominee)
would be deemed to have entered into a contract for the sale of the Land in the form
attached to the deed.
1 It was lot 20 on survey plan 236557.
-- 3 of 32 --
4
[5] The Land was to be generally in accordance with a proposed Lot 1 in a plan
attached to the deed. The proposed Lot 1 was about 5,000 m 2 in area and occupied
the Western portion of the Property.2
[6] On 6 January 2017, Bluepoint paid the Initial Security Deposit of $10,000 to the
solicitors for Zuri, who were the Stakeholder under the deed.
Due Diligence Investigations
[7] The deed was “subject to and conditional on” Bluepoint (or its nominee) being
“satisfied in its absolute discretion with its Due Diligence Investigations on or
before the Due Diligence Date.” Zuri and Bluepoint agreed that, on or before the
Due Diligence Date, Bluepoint “must by notice in writing” advise Zuri whether it is
satisfied or not satisfied with its Due Diligence Investigations, or “waives the
benefit” of the due diligence clause. If Bluepoint did not give one of these notices
to Zuri, then the due diligence clause “will be deemed to be not satisfied and this
deed will be deemed to be terminated” from 5pm on the Due Diligence Date.
[8] In the deed, Zuri and Bluepoint agreed that:
(a) “Due Diligence Investigations” means:
“the physical inspection, survey and testing of the Property and
such other investigations or inquiries in relation to the Property
or the Seller’s interest in the Property including (but not
limited to) any amendments of all or any town planning
approvals, enquiries of the Seller and discussions with
Consultants as the Buyer in its absolute discretion determines
is necessary.” And
(b) “Due Diligence Date” means “120 days from 22 December 2016”.
[9] On 1 February 2017, Bluepoint representatives had a pre-lodgement meeting with
the Brisbane City Council (BCC). They secured the BCC’s “in principle” support
for Bluepoint’s plans to build a service station, a food and drink premises and other
small business premises on the Land. The BCC recommended Bluepoint engage
with DTMR about their plans, as securing DTMR approval under s 33 of the TIA
would likely be required.
[10] Zuri had its own plans for the balance of the Property, after the subdivision to create
the Land. Those plans would also likely require approval from DTMR. Zuri asked
Bluepoint not to approach DTMR about plans for the Land until Zuri had
formulated and progressed its own plans and engagement with DTMR about
subdivision of the Property. Bluepoint agreed not to approach DTMR, at least for
some time. Instead, Bluepoint progressed its dealings with potential lessees of the
service station and food and drink premises on the Land.
[11] On 3 April 2017, Bluepoint told Zuri that, unless an extension of the Due Diligence
Date was agreed, Bluepoint would contact DTMR about its plans for the Land. On
4 April 2017, the first extension was agreed. The new date was 22 May 2017.
2 The whole of the Property, including the Land, was more than 20,000 m2 in area.
-- 4 of 32 --
5
[12] On 22 May 2017, a similar thing occurred, resulting in the second agreed extension
of the Due Diligence Date – to 21 June 2017.
[13] On 21 June 2017, a third extension was agreed, to 21 July 2017.
[14] By 7 July 2017, Zuri had concluded its discussions with DTMR and obtained a
development permit for the balance of the Property.
[15] On 10 July 2017, Bluepoint representatives had a pre-lodgement meeting with
DTMR. The DTMR representatives did not indicate support for Bluepoint’s plans
for a service station development on the Land.
[16] On 21 July 2017, Zuri and Bluepoint agreed to extend the Due Diligence Date a
fourth time, to 4 August 2017.
[17] On 27 July 2017, Zuri and Bluepoint representatives met. They shared a common
view that Bluepoint should arrange a second pre-lodgement meeting with DTMR.
Bluepoint requested a further extension of the Due Diligence Date.
[18] On 28 July 2017, Zuri agreed to a fifth extension, to 18 August 2017.
[19] On 16 August 2017, the parties agreed to extend the date a sixth time, to 31 August
2017.
[20] On 28 August 2017, Bluepoint arranged a second pre-lodgement meeting with
DTMR. It was to be held on 11 or 12 September 2017. Zuri offered to extend the
Due Diligence Date to 12 September 2017, but Bluepoint did not agree. Instead, it
requested an extension to 30 September 2017.
[21] On 1 September 2017, Zuri agreed to an extension to 30 September 2017.
[22] On 11 September 2017, the second pre-lodgement meeting between Bluepoint and
DTMR was held. Zuri’s director Balfour Irvine, and its traffic consultant Mr
Johnston, also attended. At the meeting, the indication from the DTMR
representatives was supportive of the Bluepoint plans.
A replacement contract of sale
[23] Between about May and September 2017, Zuri and Bluepoint had also been
negotiating the terms of a contract of sale for the Land. If agreed, it would replace
the contract attached to the deed. On 9 August 2017, Zuri indicated the replacement
contract would replace the deed (not just the attached contract), but Bluepoint
asserted (correctly) that the deed would continue to bind the parties at least until the
Due Diligence Date.
[24] From 13 September 2017, after the second pre-lodgement meeting with DTMR, the
negotiations over the replacement contract intensified. However, no agreement was
reached. The sticking point was the date for completion (or settlement) under the
contract, i.e. the date Bluepoint (or its nominee) would pay the balance of the
purchase price in exchange for title to the Land.
-- 5 of 32 --
6
The easement
[25] In this same period, Zuri and Bluepoint negotiated and, it appears, reached
consensus about an Instrument of Easement, to be registered on the title for the
Land, permitting access from the balance of the Property to the East-West Arterial
Road.
[26] On 15 September 2017, Zuri had provided a draft easement. On 19 September
2017, Bluepoint sought some amendments. On 21 September 2017, Zuri submitted
a further draft, which accommodated some Bluepoint amendments. Bluepoint
sought no further changes. It appears Zuri’s further draft was acceptable to it.
Due Diligence Date and “termination”
[27] The Due Diligence Date of 30 September 2017 was a Saturday, followed by a
Sunday, and then by the Queen’s Birthday public holiday. None of these was a
Business Day within the meaning of the deed. By the deed, Zuri and Bluepoint had
agreed that where “the day on which any thing is to be done is not a Business Day”
the thing “must be done on or by the next Business Day.” Tuesday 3 October 2017
was the next Business Day after Saturday 30 September 2017. If the deed required
a notice to be given on or before 30 September 2017 or by 5:00 pm on that day, it
appears the notice was to be given on or before 3 October 2017 or by 5:00 pm on
that day. This was the common position of the parties at the trial.
[28] Bluepoint gave no notice to Zuri, in the relevant terms, on or before 3 October 2017
or by 5:00 pm on 3 October 2017.
[29] On Friday 6 October 2017, by 12:21 pm, Zuri had communicated to Bluepoint that
it was not prepared to grant any further extension of Due Diligence Date and that it
regarded the deed as terminated. At 4:20 pm that day, Bluepoint gave notice to Zuri
that it was satisfied with its Due Diligence Investigations.
[30] On Monday 9 October 2017, Zuri confirmed the position it had communicated on 6
October 2017, namely: no extension of the Due Diligence Date had been agreed; no
notice had been provided by the time fixed in the deed; the due diligence clause had
operated to terminate the deed; and Zuri no longer considered it was bound by the
deed.
[31] On 10 November 2017, Bluepoint gave notice that it was nominating the second
plaintiff (BPH) as the Buyer under the deed; and BPH gave notice that it was
exercising the call option in the deed as the nominee of Bluepoint.
[32] On 20 November 2017, Zuri returned BPH’s documents and the accompanying
cheques to BPH, on the basis that the deed had been terminated.
[33] On 23 November 2017, the plaintiffs commenced this proceeding.
-- 6 of 32 --
7
The parties’ primary contentions
[34] The plaintiffs contend that the failure of Bluepoint to give any notice by 5 pm on 3
October 2017 rendered the deed voidable at the option of Bluepoint or Zuri.3 They
say the deed was not terminated “automatically” or without any further step. The
defendants contend that, as between the parties to the deed, the consequence of
Bluepoint failing to give any notice by the stipulated time was that the deed
terminated at 5 pm on the Due Diligence Date. The defendants also contend that, if
Zuri had to act to terminate the deed, after Bluepoint failed to give a notice, then it
did so.
[35] As well, the plaintiffs contend that Zuri is estopped from asserting that the deed
terminated. Zuri joins issue with this contention.
[36] The parties agree that their primary competing contentions are to be resolved by the
proper interpretation of the relevant provisions of the deed. This is the first matter
to be decided.
[37] The other matters in issue, save for the confidentiality claim, may have varying
importance depending upon the proper interpretation of the deed.
The proper interpretation of clause 2.1(d) of the deed
[38] All parties submit that, as a commercial contract, the terms of the deed are to be
construed in accord with what a reasonable businessperson would have taken them
to mean. This requires consideration of the language used by the parties to the
deed, the surrounding circumstances known to them both and the purposes or
objects to be secured by the deed.4
Outline of the deed
[39] Zuri and Bluepoint are the only parties to the deed. Zuri is designated as “Seller”
and Bluepoint as “Buyer”.5
[40] The meanings of defined terms used in the deed are set out in clause 1.1. The deed-
specific rules for interpretation are in clause 1.2. In clause 1.3, Zuri and Bluepoint
agreed that where a thing must be done on or by a day that is not a Business Day,
then it must be done on or by the next Business Day. In clause 1.4, capitalised
3 In the pleadings, the plaintiffs claimed, in the alternative, that if Zuri prevented or interfered with
Bluepoint giving a notice, then the deed was voidable at the option of Bluepoint only. The plaintiffs
did not press this alternative claim at the trial.
4 Electricity Generation Corporation v Woodside Energy (2014) 251 CLR 640, 656-657 [35] (French
CJ, Hayne, Crennan and Kiefel JJ); Australian Special Opportunity Fund LP v Equity Trustees
Wealth Services Ltd (2015) 323 ALR 570, 585 [69]; Mount Bruce Mining Pty Ltd v Wright
Prospecting Pty Ltd (2015) 256 CLR 104, 116 [47].
5 By clause 1.1, the deed gave “Buyer” the meaning “the Buyer or the Nominee, as the context
requires.” The “Nominee” means “the party, if any, nominated by the Buyer as purchaser of the
Property [sic] under clause 8.1.” As Bluepoint did not nominate another purchaser before 10
November 2017, at all earlier times, the “Buyer” was Bluepoint. From 10 November 2017, it is
possible the Buyer may mean BPH, if the context requires. “Seller” includes Zuri’s successors and
permitted assigns, of which there were neither.
-- 7 of 32 --
8
words in the deed are given the same meaning as in the Sustainable Planning Act
2009 (Qld) (SPA), where the context permits.
[41] The provisions at the centre of the interpretation issues are in clause 2. There, Zuri
and Bluepoint recorded their agreement about Bluepoint’s due diligence, the giving
of notices and their effect, the termination of the deed, and an easement permitting
ingress and egress access over the Land from and to the East West Arterial Road.
Clause 2 is considered in some detail below.
[42] By clause 3, Zuri and Bluepoint agreed that the Buyer may make a development
application. They also agreed the exercise of either option was not subject to the
outcome of the Buyer’s development application.
[43] By clause 4, they agreed that Zuri must prepare and lodge a subdivision to create a
separate certificate of title for the Land; and Zuri must use reasonable endeavours to
have it processed and approved. The Buyer could terminate the deed by notice, if
by nine months after the Due Diligence Date (the Development Approval Date), a
development approval had not issued for the subdivision on terms and conditions
satisfactory to Zuri and taken effect pursuant to the SPA. Alternatively, the Buyer
could extend the Development Approval Date by another three months. If the
development approval was not issued and in effect by the extended date, the Buyer
could terminate the deed.
[44] In clause 5, Zuri and Bluepoint dealt with the grant and exercise of the Call Option.
In clause 6, they dealt with the grant and exercise of the Put Option and with the
consequences of exercise or non-exercise of the options.6
[45] In clause 7, Zuri and Bluepoint dealt with the security deposit, including its various
instalments.
[46] By clause 8, they provided that Bluepoint could nominate a party as purchaser by
delivering a Nominee Notice to Zuri “at the time of exercising the Call Option”.7
[47] In clause 9, Zuri and Bluepoint provided for the Buyer and its consultants to have
access to the Property until the Due Diligence Date, for the purpose of carrying out
Due Diligence Investigations.
[48] In clause 10, they dealt with default and its consequences. In clause 11 they set out
the respective warranties of the Seller and the Buyer. In clause 12, they dealt with
public announcements relating to the deed, and confidentiality of information. It
will be necessary to return to the second topic. Clause 13 is concerned with GST.
6 Bluepoint or Nominee could exercise the Call Option “at any time during the Call Option Period”.
The Call Option Period would begin to run from “9:00 am on the day immediately after the
Conditions Precedent Date”. The Conditions Precedent Date is two business days after “the later of
the Due Diligence Date and or the Development Approval Date”. The Due Diligence Date was 30
September 2017. The Development Approval Date was nine months from the Due Diligence Date.
On 10 November 2017, when BPH purported to exercise the call option, it appears the Call Option
Period had not commenced to run.
7 This was the only way Bluepoint could nominate a Nominee: clause 8.2.
-- 8 of 32 --
9
[49] In clause 14, Zuri and Bluepoint dealt with various matters, including agreeing that
the deed and the attached contract for sale were the entire agreement between them
in respect of their subject matter.
[50] By clause 15, they agreed the Buyer must not lodge a caveat, but may lodge a
settlement notice not earlier than three business days before the proposed settlement
date in the contract.
[51] There are four attachments to the deed: the Call Option Notice, the Put Option
Notice, the Nominee Notice, and the contract. The contract included some special
conditions. Special condition 1.2 provided that the contract was conditional on Zuri
procuring registration of the subdivision plan and the issue of a separate certificate
of title for the Land.
[52] As the parties’ counsel observed in submissions, the deed contains several obvious
typographic errors, such as references to the Property which should be read as
references to the Land. None of these was in issue and none was significant for the
determination of the plaintiffs’ claims.
The due diligence clause
[53] The relevant agreement of Zuri and Bluepoint that “the deed will be deemed to be
terminated” is in clause 2.1(d) of the deed. Its immediate context is clause 2 of the
deed, which is in these terms:
“2. Conditions Precedent
2.1 Due Diligence
(a) This deed is subject to and conditional on the Buyer
being satisfied in its absolute discretion with its Due
Diligence Investigations on or before the Due Diligence
Date.
(b) On or before 5pm on the Due Diligence Date, the Buyer
must by notice in writing to the Seller advise the Seller
whether the Buyer:
(1) is satisfied with its Due Diligence Investigations;
(2) is not satisfied with its Due Diligence
Investigations; or
(3) waives the benefit of this clause 2.1.
(c) If the Buyer gives a notice to the Seller pursuant to
clauses 2.1(b)(1) or (3), then this clause 2.1 will be
deemed to be satisfied.
(d) If the Buyer:
(1) gives a notice to the Seller pursuant to clause
2.1(b)(2); or
(2) does not give a notice pursuant to clause 2.1(b),
-- 9 of 32 --
10
by 5pm on the Due Diligence Date, then this clause 2.1
will be deemed to be not satisfied and this deed will be
deemed to be terminated from 5pm on the earlier of:
A. the date the Buyer gives a notice to the Seller
pursuant to clause 2.1(b)(2); and
B. the Due Diligence Date.
(3) In which event the provisions of clause 2.2 will
apply.
(e) This clause 2.1 is for the benefit of the Buyer and only
the Buyer may waive it.
(f) For the purpose of clarity, if the Buyer gives the Seller
notice that it is satisfied with its Due Diligence
Investigations then both the Initial Security Deposit8 and
the Second Security Deposit9 will be released to the
Seller.
2.2 Termination of this deed
If this deed is terminated under clause 2.1(d) then:
(a) no party shall have any other Claim10 against another
party arising under or in respect of this deed; and
(b) each party retains the rights it has against the other in
respect of any:
(1) breach of this deed occurring before termination;
or
(2) obligations otherwise agreed under this deed to
remain in full force and effect after termination of
this deed.
(c) the Seller will immediately consent to the Stakeholder
refunding the Initial Security Deposit and Second
Security Deposit to the Buyer without deduction.
2.3 Instrument of Easement
(a) The Seller will prepare the Instrument of Easement and
submit a draft to the Buyer within forty five (45) days
from the date of this deed.
(b) The Buyer, acting reasonably, will have fourteen (14)
days to make any requests for amendments to that
instrument.
8 “Initial Security Deposit” means $10,000 payable to the Stakeholder on the date of the deed.
9 “Second Security Deposit” means $40,000 payable to the Stakeholder within two business days of
Zuri advising the Buyer that the Development Approval had taken effect pursuant to the SPA.
10 “Claim” is very broadly defined in the deed, including claims based in contract, tort, common law
and under statute.
-- 10 of 32 --
11
(c) For the avoidance of doubt the agreed terms of the
Instrument of Easement will form part of the Due
Diligence Investigations.”
[54] By clause 2.1(a), the parties agreed the deed was subject to this condition. In this, it
was unlike the approval of the plan of subdivision, which triggered the start of the
Call Option Period and so was, in effect, a condition precedent to the exercise of the
Call Option. It was also unlike the issue of a separate certificate of title for the
Land, which was a condition precedent to completion of the contract of sale
attached to the deed.
[55] Although broadly expressed, in the context of the specific provisions in the deed,
clause 2.1(a) is not a true condition precedent to the deed. It does not affect the
respective rights and obligations of Zuri and Bluepoint under the deed that accrue or
are to be performed before 5pm on the Due Diligence Date. These are not deferred
until the condition in clause 2.1(a) is fulfilled. These include: Zuri’s obligation to
prepare the Instrument of Easement and submit a draft of it to the Buyer (clause
2.3(a)); the Buyer’s right to make any requests for amendments to the draft within
14 days (clause 2.3(b)); Bluepoint’s obligation to provide the Initial Security
Deposit (clause 7.1(a)); the Buyer’s right to access the Property (clause 9.1(a));
Bluepoint’s obligation to act reasonably, not cause damage and not interfere with
the quiet enjoyment of the Property when accessing it (clause 9.1(b)); and the
mutual confidentiality obligations (clause 12). Nor are accrued rights lost if the
condition is not fulfilled, as clause 2.2(b)(1) expressly preserves them.
[56] By clause 2.1(b) the parties agreed that, by 5 pm on the Due Diligence Date, the
Buyer was required to give written notice to Zuri advising whether it was satisfied
or not satisfied with its due diligence investigations or that it waived the benefit of
clause 2.1. This was a positive obligation of the Buyer.
[57] For the plaintiffs it was submitted that:
“The evident object of the Due Diligence provision was to enable
[Bluepoint] to determine to its own satisfaction the feasibility of the
“Project” before it (or its nominee) committed to the call option, or it
subjected itself to the put option, under the Deed. The Due Diligence
condition was satisfied by [Bluepoint] delivering a written notice of
satisfaction or waiver.”
[58] The plaintiffs also accepted that the Buyer “could expressly waive the benefit of the
due diligence provision” and that “the provision conferred an unfettered discretion”
on the Buyer. By including the waiver provision, the parties to the deed expressly
contemplated that Bluepoint “might not, based on its own unfettered enquiries,
reach the necessary degree of satisfaction, but nonetheless want to keep the Deed on
foot.”
[59] It was for the Buyer to decide whether to retain the right to exercise the call option
at the cost of exposing itself to the risk that Zuri might exercise the put option.11
The Buyer was to make this decision by 5:00 pm on the Due Diligence Date, on the
11 In each instance the exercise of the option would be subject to its own conditions precedent.
-- 11 of 32 --
12
basis of the information it had found and assessments it had made by that time. Zuri
and Bluepoint could agree to defer the Due Diligence Date from time to time,
giving the Buyer further time to make this decision. It was for the Buyer alone to
decide whether it was satisfied or would waive the benefit of the provision.
[60] By clause 2.1(c), the parties agreed that if the Buyer gave notice that it was satisfied
or that it waived the benefit of the clause, then the condition precedent to the deed
“will be deemed to be satisfied.” A party who waives a contractual condition
entirely for its benefit may sue or be sued on the contract as if the condition was no
longer operative or had been fulfilled. To the extent there might have been any
doubt about this, by clause 2.1(c), Zuri and Bluepoint removed it.
[61] There is no provision in the deed that sets out any other means by which the
condition in clause 2.1(a) could be satisfied.
[62] In the examination of other agreements, it has been noted that the phrase “will be
deemed” could either “create a fictitious situation”,12 or “state an indisputable
conclusion.”13 The later sense, of introducing “a conclusive state of affairs” has
been said to be “the natural meaning” of the word “deem.”14
[63] Neither in clause 2.1 nor elsewhere in the deed did Zuri and Bluepoint agree that
this deemed state of affairs was provisional, in the sense that it was a presumption
that might be disproved. In the deed, they gave no indication that a deemed state of
affairs was not to survive in any particular situation. Nor was there anything in the
surrounding circumstances that would ground such meanings.
[64] Zuri and Bluepoint used the same expression in clause 6.3(a) to agree on the first
consequence of the valid exercise of either option, namely:
“the Seller and the Buyer (or a Nominee) are deemed to have entered
into the Contract(s) as Seller and Buyer respectively.”
[65] In the final sentence of clause 6.3(c), Zuri and Bluepoint offer further clarification
of the deemed effect of the valid exercise of the option:
“To avoid doubt, the Contract is formed and remains on foot
irrespective of whether the parties execute and return an original of
the Contract as required by this clause.”
[66] Zuri and Bluepoint had agreed a different set of rights in clause 4(c). If Zuri did not
obtain approval of the subdivision by the Development Approval Date, then “the
Buyer may elect to extend” the time “or terminate this Deed by giving written
notice to the Seller”. Similarly, in clause 4(d), following an election to extend, if
the approval had not taken effect by the extended Development Approval Date,
then, Zuri and Bluepoint had agreed, “the Buyer may terminate the Deed”.
[67] The deeming provisions in clause 2.1(c) and (d) have an evident purpose. Each
provides a fixed date and time by which the parties are to have certainty as to an
12 Muller v. Dalgety & Co Ltd (1909) 9 CLR 693, 696 (Griffiths CJ).
13 See: Abigroup Contractors Pty Ltd v ABB Services Pty Ltd [2004] NSWCA 181, [56] (Giles JA).
14 Starmark Enterprises Ltd v CPL Distribution Ltd [2002] Ch 306, 324 [77] (Arden LJ).
-- 12 of 32 --
13
important but entirely subjective matter, namely the satisfaction of the Buyer with
its own investigations. The certainty arises by deeming the giving of a notice of
satisfaction or a notice of waiver to satisfy the condition precedent and deeming the
giving of a notice of non-satisfaction or the failure to give any notice by the
specified time to be a failure to satisfy the condition precedent. By specifying the
effect of each of the four possibilities, Zuri and Bluepoint sought to put beyond
dispute whether the condition precedent is satisfied or not satisfied. In the former
circumstance, they put beyond dispute that the deed has ceased to be conditional on
the Buyer being so satisfied. In the later circumstance, they put beyond dispute that
the deed is terminated. They did not leave a gap where the Buyer could do nothing
and the deed continue, its fate uncertain.
[68] This purpose – of providing certainty to the commercial parties – would be defeated
if the deeming provisions were construed as not specifying indisputable
conclusions. If Zuri might avoid being bound by proving that, in fact, the Buyer
was not satisfied with its investigations when it gave a notice to that effect, the
commercial certainty would be lost. Without the certainty found in the deeming
provisions, Zuri might hold the Buyer to the deed, by proving it was satisfied with
the same, notwithstanding that the Buyer gave a notice it was not satisfied.
[69] As the plaintiffs submitted, it was for the Buyer to decide whether or not to retain its
period of exclusivity beyond the Due Diligence Date.
[70] Although clause 2.1(e) explains that clause 2.1 is for the benefit of the Buyer, which
could waive it unilaterally, Zuri had an interest in knowing for how long its liability
was to remain unresolved.15 The prospect of the call option effectively restricted
Zuri from dealing with the whole of the Property.16 By clause 2.1, they agreed that,
from the Due Diligence Date, Zuri would be relieved of any further restriction if, by
then, the Buyer had not bound itself by giving a notice it was satisfied or by waiving
the condition.
[71] If the deeming provision in clause 2.1(d) did not operate in the same way when the
Buyer fails to give a notice as when the Buyer does so, another consequence would
be that the Buyer who fails to give a notice would be in breach of clause 2.1(b) of
the deed. Such an outcome (and its consequences) is avoided by the expedient of
deeming the Buyer to be not satisfied and the deed to be terminated. Even without
deeming the deed to be terminated, the deemed “not satisfied” might be sufficient
for the condition precedent in clause 2.1(a) to operate.
[72] The intention of Zuri and Bluepoint, viewed objectively, based on the language they
used in clause 2.1, the context in which those words were used, including the deed
as a whole, and the purpose and object of the transaction to be effected by the deed,
the deeming provisions in clause 2.1(d), would be understood by a reasonable
businessperson in the position of Zuri and Bluepoint to render the deed relevantly
15 Gange v Sullivan (1966) 116 CLR 418, 443 (Windeyer J): Perri v Coolangatta Investments Pty
Ltd (1982) 149 CLR 537, 565 (Brennan J).
16 By the deed, Zuri and Bluepoint had agreed the development approval for the subdivision was to be
obtained within nine months after the Due Diligence Date, so that Zuri did not have to obtain such
approval unless Bluepoint was satisfied with its Due Diligence Investigations or had waived the due
diligence condition.
-- 13 of 32 --
14
unconditional or terminated by the fixed time and date, depending on whether the
Buyer gave a notice of a particular kind or failed to do so by the stipulated time.
[73] Zuri and Bluepoint assigned the consequence of a failure to give a notice on or
before the Due Diligence Date. The consequence is that “clause 2.1 will be deemed
to be not satisfied and the deed will be deemed to be terminated from 5pm on … the
Due Diligence Date.” There is no ambiguity. The expression carries its natural
meaning, that of a conclusive state of affairs. It plainly provides that a failure on the
part of the Buyer to give a notice required by clause 2.1(b) results in a failure to
satisfy the condition precedent in clause 2.1(a) and the termination of the deed.
[74] Clause 2.1(d) is not consistent with an intention that each of the Buyer and the
Seller (or one of them) was to have an election as to whether or not the deemed
result would occur. Zuri and Bluepoint ascribed great importance to the
consequence of giving or not giving a notice by the stipulated time. The clear
intention was to require strict adherence to the time stipulation. The election lay in
the hands of the Buyer. No further step was required. The agreed timing of the
termination “from 5pm” is also inconsistent with each of the parties having some
time (after the stipulated time) in which to elect the result.
The Suttor principle?
[75] The plaintiffs sought to avoid the consequence of clause 2.1(d) applying in
accordance with the settled approach to contractual interpretation. They did so on
the basis of a “principle” attributed to the decision of the High Court in Suttor v
Gundowda Pty Ltd.17
[76] In Suttor, the provision was relevantly, in these terms:
“in the event of the consent of the Treasurer not being obtained
within two months from the date hereof or within such further period
as may be mutually agreed upon by the parties hereto, this contract
shall be deemed to be cancelled …”18
[77] The contracting parties had agreed on an extension of time for the fulfilment of the
condition, which would otherwise have been 20 December 1947. The High Court
accepted there was evidence:
“quite sufficient to prove an oral agreement prior to 20th December
that the time for the Treasurer's consent should be extended for a
reasonable period after that date.”19
[78] The Court also found that, after 20 December 1947, the parties:
“treated the contract as still being on foot, and that the defendant had
been informed that the consent would be obtainable within a very
short time, and that he led them to believe that the contract would be
completed by him”20
17 (1950) 81 CLR 418 (Latham CJ, Williams and Fullagar JJ).
18 421.
19 440.
20 425.
-- 14 of 32 --
15
and “the defendant was treating the contract as still on foot”.21
[79] The consent of the Treasurer was obtained on 5 January 1948.22
[80] The High Court found the agreement to extend the time for the Treasurer’s consent
was the “first” answer to the contention of the appellant that the contract should be
deemed to have cancelled on 20 December 1947.23
[81] In the present case, the plaintiffs rely on the High Court’s second answer to the
appellant’s case in Suttor. In this part of the reasons, the High Court approved the
analysis in New Zealand Shipping Co Ltd v Societe des Ateliers et Chantiers de
France,24 quoting the following passage from Lord Atkinson’s speech:
“It is undoubtedly competent for the two parties to a contract to
stipulate by a clause in it that the contract shall be void upon the
happening of an event over which neither of the parties shall have
any control, cannot bring about, prevent or retard. For instance, they
may stipulate that if rain should fall on the thirtieth day after the date
of the contract, the contract should be void. Then if rain did fall on
that day the contract would be put an end to by this event, whether
the parties so desire or not. … But if the stipulation be that the
contract shall be void on the happening of an event which one or
either of them can by his own act or omission bring about, then the
party, who by his own act or omission brings that event about, cannot
be permitted either to insist upon the stipulation himself or to compel
the other party, who is blameless, to insist upon it, because to permit
the blameable party to do either would be to permit him to take
advantage of his own wrong, in the one case directly, and in the other
case indirectly in a roundabout way, but in either way putting an end
to the contract.” 25
[82] The High Court then expressed the following as the “second” answer to the
appellant’s contention:
“Where the event in question is one which cannot occur without
default on the part of one party to the contract, the position is clear.
The provision is then construed as making the contract not void but
voidable: only the party who is not in default can avoid it, and he
may please himself whether he does so or not. In the present case
the happening of the event (not obtaining the Treasurer’s consent)
may be brought about by failure on the part of either party to take
certain necessary steps (…) or it may be brought about without any
default on the part of either party. In fact, although there was some
argument to the contrary, it was, we think, brought about without any
default on the part of either party. Such a case is perhaps not quite so
clear as the simpler case where the event cannot occur without
21 442.
22 442.
23 440.
24 (1919) AC 1.
25 9.
-- 15 of 32 --
16
default on one side or the other. But we are of the opinion that the
New Zealand Shipping Case requires the same construction to be
given to the contract in both classes of case. The provision in
question is to be construed as making the contract not void but
voidable. The question of who may avoid it depends upon what
happens. If one party has by his default brought about the happening
of the event, the other party alone has the option of avoiding the
contract. If the event has happened without default on either side,
then either side may avoid the contract. But neither need do so, and,
if one party having a right to avoid it does not clearly exercise that
right the other party may enforce the contract against him.”26
[83] As the High Court noted, Lord Atkinson “may perhaps be regarded as expressing a
different view” in the New Zealand Shipping Case. There, the two parties were
“equally blameless.” As Lord Atkinson explained:
“By the act or omission of neither has the event been brought about
on the happening of which the contract was to become void. The
principle that a man shall not take advantage of his own wrong does
not apply, and the contract becomes null and void absolutely, as its
words in their natural meaning provide that it should.”27
[84] Both Suttor and, as Lord Atkinson noted, New Zealand Shipping are specific
instances of the broader principle that a party to a contract shall not be permitted to
take advantage of its own wrong.28 There was no need to impinge upon the rules of
contractual interpretation to apply the prevention principle.
[85] The second answer in Suttor was followed in Gange v Sullivan [1966] 116 CLR
418. There, a contract for the sale of land was subject to the purchaser obtaining
development approval for certain purposes. The relevant clause stated:
“in the event of the said Council not granting such approval for the
purpose aforesaid by the 31st day of May, 1965, then this Contract
shall be deemed to be at an end and all moneys paid by the Purchaser
to the Vendor shall be refunded but in the event of Council granting
the approval aforesaid then the Purchaser will complete the Contract
within twenty days of the granting of such consent.”
[86] In Quinn Village Pty Ltd v Mulherin [2006] QCA 433, Cullinane J found a clause
identical to that in Gange v Sullivan justified the trial judge construing the clause in
accordance with that decision and Suttor.29
[87] In the present case, Zuri and Bluepoint agreed that the deed was conditional on the
Buyer “being satisfied in its absolute discretion with its Due Diligence
Investigations on or before the Due Diligence Date.” Such a condition is quite
unlike “an event over which neither of the parties shall have any control, cannot
bring about, prevent or retard”, to which Lord Atkinson referred.
26 (1950) 81 CLR 418, 441.
27 (1919) AC 1, 10, 11.
28 See: Donaldson v Bexton [2007] 1 Qd R 525, 536 [28] (Keane JA).
29 [2006] QCA 433, [51] (Cullinane J; McMurdo P at [1] and Holmes JA at [2] agreeing).
-- 16 of 32 --
17
[88] If the approach in the second answer in Suttor were applied here, it would be for
Zuri to terminate or affirm the deed. However, Zuri and Bluepoint agreed that the
Buyer could bring the deed to an end at its own discretion. So, the second answer in
Suttor would produce a result contrary to the clear intention of the parties and the
settled principles of contractual interpretation.
[89] As Jackson J observed in Principal Properties Pty Ltd v Brisbane Broncos Leagues
Club Limited:30
“[78] The application of the principle in the context of the failure of
contingent conditions has been closely analysed in a number of
recent cases at intermediate appellate court level in Australia.
In particular, the question has been considered in Rudi’s
Enterprises Pty Ltd v Jay,31 MK & JA Roche Pty Ltd v Metro
Edgely Pty Ltd32 and Ruthol Pty Ltd v Tricon (Australia) Pty
Ltd.33
[79] In my view, the principle to be adopted in this context was
succinctly expressed by Hodgson JA in MK & JA Roche as
follows:
‘Thus, as asserted in Rudi’s Enterprises, where the
parties have clearly stipulated for automatic termination
upon the occurrence of an event which could occur
either without the default of either party or with the
default of one or other party, and if the event occurs
through the default of one party, then, although in
general terms this would mean automatic termination,
the party whose default caused the event can be
prevented from taking advantage of this by direct
application of the principle that a party cannot take
advantage of its own wrong, rather than through
construing the contract contrary to its clear meaning.’”
[90] The same approach was followed by the Full Court of the Federal Court in Perovich
v Whitton (No 2) (2016) 250 FCR 272.34 As Siopis, Gleeson and Edelman JJ
explained:
“[62] In other words, the authorities relied upon by the debtors do
not establish an incontrovertible rule of law which applies
despite the words of the contract and despite the context in
which those words appear. The underlying principle is
naturally subject to clear and unambiguous words and context
to the contrary. In Rudi’s Enterprises Pty Ltd v Jay (1987) 10
NSWLR 568 at 579, Samuels JA (Priestley and McHugh JJA
agreeing) said:
30 (2014) 2 Qd R 132, 146. These observations were not the subject of challenge on appeal in (2018) 2
Qd R 584.
31 (1987) 10 NSWLR 568, 576–580 (Samuels JA; Priestly and McHugh JJA agreeing).
32 [2005] NSWCA 39, [44]-[47] (Hodgson JA; Beazley P and Ipp JA agreeing).
33 [2006] NSW ConvR 56-145, [19]-[25] (Giles JA; Santow JA and Hunt AJA agreeing).
34 282-285 [58] – [67] (Siopis, Gleeson and Edelman JJ).
-- 17 of 32 --
18
I cannot think that the Court in Suttor intended to lay
down the proposition that parties could not stipulate for
automatic termination of a contract save upon the
occurrence of an event which, objectively, lay beyond
their control. Effect must be conceded to the parties’
intention.
[63] Again, in MK & JA Roche Pty Ltd v Metro Edgley Pty Ltd
[2005] NSWCA 39 at [44] Hodgson JA (Beazley and Ipp JJA
agreeing) said that the passage in Suttor could be read as
setting out a principle of law rather than a mere guide to
construction, but to so read it would in my opinion be against
very well-established principles concerning the construction of
contracts, including the principle that, if words used in a
contract are unambiguous, the Court must give effect to them:
Australian Broadcasting Commission v. Australasian
Performing Rights Association (1973) 129 CLR 99 at 109.”
[91] I respectfully adopt the analysis of Jackson J in Principal Properties and of the Full
Court in Perovich v Whitton (No 2).
[92] It follows that Suttor should not be considered as an exception to the settled
approach to contractual interpretation. If an issue arises as to a party taking
advantage of its own wrong, it is to be dealt with according to principle. It is
neither necessary nor appropriate to vary the proper construction of the contract for
that purpose. In short, the decision in Suttor establishes no principle that governs
the proper interpretation of commercial agreements, such as that in clause 2.1(d) of
the deed. To the extent is may have been applied as such in the past, that approach
has not survived the High Court’s articulation of now settled interpretation
principles summarised at [38] above.
[93] At the trial, the plaintiffs advanced their claims in reliance on the alleged Suttor
principle as a rule of contractual interpretation. On their case it was not necessary
to prove that Zuri had or was taking advantage of its own wrong. They did not do
so.
[94] For the reasons set out above, on its proper construction clause 2.1(d) of the deed
brought about the termination of the deed with prospective effect if the Buyer failed
to give a notice required by clause 2.1(b) by the stipulated time. The plaintiffs’
alternative construction is rejected.
The prevention principle
[95] As noted above, the prevention principle holds that a party to a contract is not
permitted to take advantage of its own breach of duty owed to the other party under
the contract.35 In their pleadings, the plaintiffs alleged that Bluepoint was prevented
from giving a clause 2.1(b) notice by Zuri’s conduct in failing to give Bluepoint a
draft Instrument of Easement in accordance with clause 2.3 of the deed.
35 Cheall v Association of Professional Executive Clerical and Computer Staff [1983] 2 AC 180, 189
(Lord Diplock).
-- 18 of 32 --
19
[96] By clause 2.3(c), Zuri and Bluepoint had agreed that the terms of the easement were
part of Bluepoint’s Due Diligence Investigations. If Zuri had prevented Bluepoint
from giving a notice under clause 2.1(b), then it would be an instance where the
prevention principle might operate in the way explained by the authorities at [89]
and [90] above. This would be consistent with Lord Atkinson formulation:
“The application to contracts such as these of the principle that a man
shall not be permitted to take advantage of his own wrong thus
necessarily leaves to the blameless party an option whether he will or
will not insist on the stipulation that the contract shall be void on the
happening of the named event. To deprive him of that option would
be but to effectuate the purpose of the blameable party. When this
option is left to the blameless party, it is said that the contract is
voidable, but that is only another way of saying that the blameable
party cannot himself have the contract made void, cannot force the
other party to do so, and cannot deprive the latter of his right to do
so.”36
[97] Zuri accepted that it failed to give Bluepoint the draft Instrument of Easement
within the 45 days agreed in clause 2.3(a), which expired on about 19 February
2017. Each of the extensions to the Due Diligence Date was agreed after this
breach occurred and while it continued.
[98] On 15 September 2017, Zuri’s solicitors provided the draft Instrument of Easement
to Bluepoint’s solicitors. This was 15 days before the Due Diligence Date, and 18
days before Bluepoint was required to give a notice under clause 2.1(b) of the deed.
Bluepoint raised no objection to its late provision.
[99] On 19 September 2017, by its solicitors, Bluepoint responded to the draft. On 21
September 2017, the easement was discussed between the solicitors, and Zuri’s
solicitors provided a further draft to Bluepoint’s solicitors. Bluepoint sought no
further changes to this draft. The two Bluepoint directors who gave evidence at the
trial said they were satisfied with the terms of the instrument of easement sent on 21
September 2017. This was consistent with the evidence of Mr Bates, the real estate
agent, who said Mr Dore told him on 21 September 2017 that Bluepoint was
satisfied with the size and location of the easement and prepared to take the risk that
DTMR would approve it and “go unconditional” on the transaction. This was nine
days before the Due Diligence Date and 12 days before Bluepoint was required to
give a notice.
[100] On 6 October 2017, when Bluepoint’s solicitors gave notice it was satisfied with its
Due Diligence Investigations, they explained Bluepoint had been unable to
complete those investigations “until your client had finalised the plan” lodged with
the BCC on 22 September 2017. This was the plan of subdivision. Zuri had
produced several draft plans before this date. These varied in the area of the Land
and the location of the easement (or easements). None was contrary to the deed.
Zuri was not in breach due to the date of this “finalised” plan. As noted above, the
deed did not require development approval for the subdivision until nine months
after the Due Diligence Date.
36 (1919) AC 1, 9.
-- 19 of 32 --
20
[101] Appropriately in the circumstances, at the conclusion of the trial, the plaintiffs did
not press their prevention case against Zuri.
Election by Zuri to terminate the deed
[102] If the proper construction of clause 2.1(d) advanced by plaintiffs were correct, then
Bluepoint’s failure to give a notice by 5:00 pm on 3 October 2017 rendered the deed
voidable at the election of either party.37 Where such a construction has been found,
the election to avoid the contract can be effected without notice by any party not in
breach.38
[103] On 6 October 2017, at about 12:21 pm, the real estate agent, Mr Bates, told Mr Dore
that Zuri “would not proceed with the Deed.” He was passing on a message from
Mr Irvine of Zuri. As well, Mr Bates forwarded to Mr Dore an email he had
received from Mr Irvine:
“In regards to the offer from Bluepoint Properties, a decision has
been made not to grant any extension on the terms that were offered
and agreed on in early September”
…
We will not be moving forward with the start of Bluepoint at this
stage. In order to remove uncertainty, we may choose to lodge our
own DA. Any further negotiations are now at an end. However, as
circumstances change, we will be happy to advise you accordingly.”
[104] Mr Dore, in turn, sent Mr Irvine’s email on to his fellow Bluepoint director, Mr
Whitcombe that day.
[105] The same day, Mr Dore wrote directly to Mr Irvine, “Earlier today Aaron [Bates]
from JLL informed me you want to terminate our agreement.”
[106] This sentiment that made its way into the solicitors’ letter sent at about 4:20pm the
same day:
“We are instructed by our client that your client has indicated to the
agent a desire to terminate the option.
We would submit of course that there is no ability on your client’s
behalf to do so because of what transpired with your client’s
development application and the extensions of time agreed to along
the way.
Notably, our client has to date been unable to complete its diligence
until your client had finalised the plan that your client intended for
the land, which we are advised was only lodged with the Brisbane
City Council on 22 September 2017, with notification of receipt on
37 Noting that the plaintiffs did not press a case that Zuri had prevented or interfered with Bluepoint
giving a notice under clause 2.1(b).
38 See: Bowen v Alsanto Nominees Pty Ltd [2011] WASCA 39, [13] (McLure P), citing Gange v
Sullivan (1966) 116 CLR 418; Sandra Investments Pty Ltd v Booth (1983) 153 CLR 153; and Perri v
Coolangatta Investments Pty Ltd (1982) 149 CLR 537.
-- 20 of 32 --
21
27 September 2017. Your client failed to give us notice of that
lodgement, but a copy of the plan (attached) has been obtained from
the Council website.
Having obtained that plan, we now give notice pursuant to clause
2.1(b) of the Option Deed that our client is satisfied with its Due
Diligence Investigations.
We await your notice that the Development Approval has taken
effect as is set out in clause 4(b) of the Option Deed.”
[107] As Mr Irvine stated in his email, Zuri had merely decided not to grant any further
extension to the Due Diligence Date. It is possible Zuri’s desire to communicate
this decision was a response to Mr Dore’s email to Mr Bates of 8:35 am on 3
October 2017, to the effect that if the settlement date was not agreed and the
replacement contract was not signed that day, Bluepoint would “need more time”.
See [128] below.
[108] I reject the plaintiffs’ submission, based on Mr Dore’s evidence, that these
communications passing between him and Mr Irvine (through the agency of Mr
Bates) on 3 and 6 October 2017 concerned only the replacement contract. The
communications from Zuri were plainly about the deed. At the time, Mr Dore
understood them to be so. His own contemporaneous communications and his
instructions to Bluepoint’s solicitors confirm this.
[109] In cross-examination, Mr Dore accepted that he understood from Mr Irvine’s
forwarded email that Zuri was not proceeding with the sale to Bluepoint. As he put
it, “we had been told we were terminated.” He also said, “We could not believe that
we had been terminated” and he understood, “We had already been terminated.”
These admissions were made frankly. I accept them as truthful.
[110] The evidence establishes that on 6 October 2017, Zuri clearly and unequivocally
indicated to Bluepoint that it was treating the deed as being at an end, because
Bluepoint had not given a notice pursuant to clause 2.1(b) by the stipulated time,
and no extension of the Due Diligence Date had been agreed.
[111] If Zuri had to elect to avoid or terminate the deed, then its conduct at about 12:21
pm on 6 October 2017, objectively considered, was such an election. It was
consistent with the deed having been terminated. It was justifiable only on that
basis. It made manifest Zuri’s position that it intended no longer to be bound by the
deed.
[112] There were additional later acts by Zuri to the same effect.
(a) On Monday 9 October 2017, at about 5:15pm, the solicitors for Zuri
responded to the email of 6 October 2017 from the solicitors for Bluepoint.
The response included the following:
“Your correspondence below purports to provide notice
pursuant to clause 2.1(b) of the Put and Call Option Deed,
dated 5 January 2017 (’the Deed’).
To the extent that our correspondence of 13 September 2017
reflects an extension of the Due Diligence Date, then the latest
-- 21 of 32 --
22
possible date for notice to have been given under clause 2.1(b)
would have been 28 September 2017.
Your client has not requested, nor has our client agreed to, an
extension of the Due Diligence Date beyond that date set out
in our correspondence of 13 September 2017.
We also note that there has been no intention on our client’s
behalf to terminate the contract. Rather, clause 2.1(d) contains
a clear, self-executing mechanism which has operated to cause
the Deed to come to an end.
We note further that the operation of the Due Diligence clause
is in no way linked to the operation of clause 4 of the Deed.
Accordingly, we note that your client did not give notice
pursuant to clause 2.1(b) by 5:00pm on the Due Diligence
Date, and pursuant to clause 2.1(d), the Deed is deemed to be
terminated.
In order that the Initial Security Deposit can be returned to
your client, please advise your client’s preferred bank account
details and we will arrange for that to be deposited into that
account. Alternatively, we will arrange for a cheque payable
to your client, to be delivered to your office.”
(b) From about 9 October 2017, Zuri commenced negotiations with potential
lessees of service station and fast-food premises to be developed on the Land.
(c) On 20 November 2017, Zuri returned to Bluepoint the signed nominee notice,
call option notice, and contract, and the accompanying cheques, which had
been served on 10 November 2017, in purported exercise of the rights to
nominate BPH and exercise the call option.
(d) On 23 November 2017, the plaintiffs commenced this proceeding. On 21
December 2017, Zuri filed a defence asserting that the deed had terminated,
in accordance with its terms, on 3 October 2017.
(e) On 17 July 2020, Zuri sold the Land to APM Investments Pty Ltd.
[113] On this alternative construction of clause 2.1(d), Zuri’s right to terminate the deed
would not have been lost by any act of Zuri affirming the deed, as the vendor had
done in Suttor. Bluepoint’s notice of 6 October 2017 would not have affected
Zuri’s right to terminate.39
Estoppel
[114] The plaintiffs also advanced a case that Zuri was estopped from treating the deed as
having come to an end on the failure of Bluepoint to give a notice by 5 pm on the
Due Diligence Date. They alleged Zuri had impliedly represented to Bluepoint that
the deed would not terminate if Bluepoint did not give a notice by the stipulated
39 See: Donaldson v Bexton (2007) 1 Qd R 525, 532 [20]-533 [22] (Keane JA) and his Honour’s more
detailed consideration of the authorities at 533 [24]–547 [54].
-- 22 of 32 --
23
time.40 The plaintiffs alleged Bluepoint had relied on this implied representation in
not giving a notice within time. They alleged it would be unconscionable for Zuri
to assert that the deed had terminated, in all the circumstances.
[115] The start of this part of the plaintiffs’ case is described in this way in their Counsels’
closing submissions:
“Beginning in early August 2017, Zuri had extended the Due
Diligence Date on the express basis that the extension would enable
a meeting with DTMR to occur, [Bluepoint] would then ‘advise that
it wants to pursue the purchase’ and then enter into a contract which
did not have a Due Diligence clause.”
[116] The “contract” had been the subject of exchanges between Zuri and Bluepoint since
about 4 May 2017. It was proposed as a replacement for the contract of sale
attached to the deed. As Bluepoint noted on 9 August 2017, the deed continued to
bind the parties until at least the Due Diligence Date. If the parties executed and
exchanged a replacement contract, then Bluepoint would have a direct path to
purchase the Land, without the need for the Call Option. However, without the
option in the deed, Bluepoint would be bound to complete the purchase, subject to
the terms of the replacement contract and the events that might come to pass.
[117] On 13 September 2017, after Bluepoint’s second pre-lodgement meeting with
DTMR, Zuri’s solicitors wrote to Bluepoint’s solicitors:
“First we understand the meeting with DTMR has been held and that
your client wants to proceed. We understand your client is going on
leave and we have received instructions to submit to you the
following:
1. Contract of Sale.
2. Special Conditions.
Please seek your client’s instructions and advise any amendments.
We make the usual reservation in relation to any further changes our
client may wish to make to these documents.
Our instructions are that the Due Diligence Date is fixed at 29
September 2017. Subject to what transpires and when your client
wants to exchange you can insert a short due diligence clause
provided the date is fixed.
In respect of our client’s minor approval application for the plan, that
application is being lodged by Friday 15 September 2017. In respect
of the DTMR section 33 approval we understand that is to be
expected within the week.
We look forward to hearing from you.”
40 This was also put in other ways, including that Zuri had represented that it was not necessary for
Bluepoint to give a notice to keep the option to purchase “alive”.
-- 23 of 32 --
24
[118] The enclosed contract was a standard REIQ/QLS Contract for the Sale of
Commercial Land and Buildings. The special conditions were the main subject of
interest.
[119] The parties exchanged communications about the special conditions and the date for
completion (or “settlement”) of the contract. The latter seems to have been a
particular point of contention, with Zuri seeking completion in 2017, and Bluepoint
wanting to “push it back” to 29 June 2018, in version of the new contract sent on 19
September 2017.
[120] On 21 September 2017, there were several email exchanges between Bluepoint’s
solicitor Mr Boston and Mr Baynes of Zuri’s solicitors.
(a) At 12:48 pm, Mr Boston informed Mr Baynes:
“I’ve spoken to Marcus Dore following our conversation this
morning.
The big issue is because of the delay in the approvals and plan,
my client’s path to getting an approval now is much more
difficult since the legislation changed. That’s why they need
time.
Marcus said JLL41 spoke to Balfour42 this morning regarding
the settlement date and he is going to get back to them. We’ll
wait for that.
In the meantime, can you confirm your client is in agreement
with the other matters we raised?”
(b) At 2:13 pm, Mr Baynes advised Mr Boston that:
“The latest date I have been given is not before 31 December
2017 … If that is okay I am about to return the documents. I
think we are close.”
(c) At 3:00 pm that same day, Mr Boston sent an email to Mr Baynes attaching
three documents. His covering email stated:
“Special Conditions
The final tracked changes are attached for the Special
Conditions. I have left some balloon comments from my
client as I believe they explain matters in more detail. …
The DTMR Approval Section 33 of the [TIA] has been
obtained. I have also attached the letter from the Department
of 15 September 2017 which confirms the approval.
…
41 This is a reference to the real estate agent Mr Bates.
42 This is a reference to Balfour Irvine, a director Zuri.
-- 24 of 32 --
25
In relation to the Minor Change Approval this application was
lodged with BCC on 18 September 2017. We will keep you
advised of updates.
Easement
This document is attached with our client’s comments. …
We look forward to hearing from you so we can issue the
Contract for execution.
We will exchange on the basis that your client confirms that it
is satisfied with its due diligence.”
[121] This last communication conveyed Zuri’s “final” position on the special conditions
for the replacement contract, including a varied settlement date of 31 January 2018.
Zuri did not alter its position after that time.
[122] On Monday 25 September 2017, the parent company of Bluepoint (BMI) held a
management meeting and discussed the sale by Zuri to Bluepoint. The minutes
noted that Bluepoint’s due diligence was due on Thursday 28 September 2017.43
[123] On Wednesday 27 September 2017:
(a) Zuri’s solicitor Mr Baynes wrote again to Mr Boston:
“Just thought I would see if there is any progress on your end.
I am going on leave this evening.”
(b) Mr Boston replied:
“I’m told they have been further discussing via the agent and
Balfour is mulling over it.”
[124] On Friday 29 September 2017, Mr Dore of Bluepoint told the real estate agent Mr
Bates that Bluepoint “can probably live with an April [2018] settlement” for the
proposed new contract. In submissions, Bluepoint described this as putting “a
compromise position to Zuri”. It was a gesture in the on-going negotiation. It was
not a statement of a firm position. It was merely an indication of a probable basis of
compromise.
[125] For the plaintiffs, it was submitted that the communications passing between the
parties between 13 and 29 September 2018 conveyed to Bluepoint “that the only
outstanding issue between the parties on the replacement contract was the
settlement date.” Whether this is an accurate analysis of the communications is not
determinative. The parties knew they had not reached any binding agreement –
other than the deed.
[126] With considerable experience in such transactions, and with experienced solicitors
acting on each side, the parties were aware that the various things that had been
43 During September 2017, both parties referred to 28 September 2017 or to 29 September 2017 as the
extended Due Diligence Date. It was not until closer to the trial that, on careful examination of the
contemporaneous documents, all parties concluded that the agreed extended date was 30 September
2017.
-- 25 of 32 --
26
“agreed” in September correspondence were merely steps in a negotiation. No such
partial “agreement” was legally enforceable. There would be no binding agreement
until a written contract was signed and exchanged between them.
[127] Zuri and Bluepoint had agreed to extend the Due Diligence Date to 30 September
2017. They could have agreed to extend the date once again. They did not.
[128] Tuesday 3 October 2017 was the day Bluepoint was obliged to give a notice
pursuant to clause 2.1(b) of the deed. At about 8:35 am that day, Mr Dore sent an
email to Mr Bates, the real estate agent:
“We’re in a holding pattern again and need this one wrapped up
today, otherwise we’ll need more time.”
[129] Mr Dore does not seem to have raised the topic of “more time” until the morning of
3 October 2017. In the context of their relationship, this is not surprising. Earlier
extensions had been sought and agreed on the Due Diligence Date, e.g. on 22 May,
21 June, 21 July and on 1 September 2017.
[130] This part of the 3 October email, the BMI management committee minutes and
Bluepoint’s earlier care to see that the Due Diligence Date was extended, lead me to
accept the plaintiffs’ submission that it is unlikely Bluepoint “merely forgot about
the Due Diligence Date.” Bluepoint had not forgotten.
[131] In the absence of an agreed extension, Bluepoint had until 5:00 pm on 3 October
2017 to act. To retain its future rights under the deed Bluepoint had to give a notice
of satisfaction or waiver. Alternatively, it could end the deed by giving a notice it
was not satisfied or by failing to give any notice, with the result it would lose those
rights.
[132] Bluepoint’s rights included, relevantly, a right to require Zuri to use reasonable
endeavours to have a plan of subdivision processed and approved, creating the Land
as a separate lot with its own title, and, if a separate title issued, a right to exercise
the Call Option and so require Zuri to sell the Land to it (or its nominee) on the
terms set out in the contract attached to the deed.
[133] As noted above, on 21 September 2017, Zuri’s solicitors had advised Bluepoint’s
solicitors that “We will exchange on the basis that your client confirms that it is
satisfied with its due diligence.” As the plaintiffs put their estoppel case, this
communication “effectively did away with the need to give a Due Diligence Notice
by the Due Diligence Date”.
[134] Having considered the communications between the parties put into evidence and
the evidence of the witnesses called at the trial, I am not persuaded that Zuri
represented to Bluepoint that it was unnecessary for Bluepoint to provide a notice in
accordance with clause 2.1(b) of the deed. The communications of 21 September
2017 do not convey such a representation. On the contrary, Zuri raised the topic of
Bluepoint being satisfied with its due diligence. It required notice that Bluepoint
was satisfied as a condition of the exchange of a replacement contract. The effect
alleged by the plaintiffs is contrary to the natural meaning conveyed by the words.
Even if, with the application of wishful thinking, the communications could be
moved from that meaning, they would be ambiguous. In the context in which they
-- 26 of 32 --
27
occurred, the emails passing between the respective solicitors would not convey to a
person in the position of the directors of Bluepoint a clear, unambiguous
representation to the effect the plaintiffs allege.
[135] The plaintiffs’ estoppel case is not aided by the evidence of the two Bluepoint
directors. Mr Whitcombe did not rely on the September 2017 emails (or the parts of
them important for the estoppel case). He was interested only in the attached
documents. In particular, he was interested in the special conditions and the
settlement date for the proposed replacement contract. Somewhat incredibly, Mr
Dore said the Due Diligence Date was not on his mind, nor was the deed, at this
time. He said he thought:
“I was required to resolve the outstanding matters on the
[replacement] contract, execute and be given executable versions of
both the easement and the contract by signing and returning them
was my acknowledgment that I was satisfied with my due diligence.”
[136] If that is what he thought, he did not do it. He did not resolve the outstanding issue
of the settlement date. He did not execute the easement or the replacement contract.
He did nothing at all to notify Zuri that Bluepoint was satisfied with its Due
Diligence Investigations.
[137] In prepared evidence, the Bluepoint directors said they would have given a notice to
Zuri within time, if they thought they needed to do so. That was not the position
Bluepoint put, by their solicitors, on 6 October 2017, much closer to the material
time.
[138] Having seen each director give evidence, I am satisfied that each expected Zuri to
agree to altered terms with Bluepoint for the replacement contract, including a later
settlement date. Their experience, in the negotiations for other like projects and
their experience with Zuri over the life of this negotiation, led them to assess as low
the risk that Zuri would walk away from the deal. They were astonished when Zuri
did not return to the negotiation and instead insisted that the deed had been
terminated. Their recollections were affected by this profound surprise.
[139] When the plaintiffs’ claim was first formally advanced, there was no estoppel case
and no reference to the communications on which that case was advanced at the
trial. It was first made in the fourth amended statement of claim, filed on 17 June
2019, in reliance on the 13 September 2017 letter alone. The 21 September 2017
communication, which has such a prominent role in the estoppel case pressed at
trial, did not find its way into the pleaded case until the 11 May 2020. By the trial,
nearly four years had passed since the events in question. Over time, the estoppel
claim has increased in importance to the plaintiffs. It had plainly affected the
recollections of the two directors who gave evidence.
[140] Considering the evidence as a whole, giving due weight to the contemporaneous
and near contemporaneous records, I find the plaintiffs have failed to prove it to be
more likely than not that Bluepoint relied on the alleged implied representation and
was induced by it not to give a notice on or before the Due Diligence Date or by
5:00pm on 3 October 2017.
-- 27 of 32 --
28
[141] There is no evidence from which I could conclude that Zuri, though any of its
human agents, knew or intended Bluepoint to act or refrain from acting in reliance
on the September communications as a representation that the deed would not
terminate if Bluepoint failed to give a notice required by clause 2.1(b) on or by the
Due Diligence Date.
[142] The plaintiffs’ estoppel case fails. Zuri is entitled to rely on the failure of Bluepoint
to give a notice by the stipulated time and to assert that the deed terminated in
accordance with its terms or, in the alternative, that Zuri elected to terminate it,
following Bluepoint’s failure to give a notice.
Damages claimed by the plaintiffs
[143] The plaintiffs claimed damages for breach of the deed. The primary damages were
said to be the loss of a valuable commercial opportunity to develop the Land at a
profit. The parties agree that such claims are based on the principles laid down by
the High Court in Sellars v Adelaide Petroleum NL (1994) 179 CLR 332 and
Badenach v Calvert (2016) 257 CLR 440.
[144] I have concluded that Zuri’s insistence that the deed was terminated was not a
breach or repudiation of the deed. The plaintiffs have no entitlement to such
damages.
[145] The plaintiffs’ case is that they would have developed it as a service station, food
and drink premises with some other retail uses.
[146] Evidence was led by the plaintiffs and the defendants about the value of the
opportunity the plaintiffs’ claimed to have lost. Principally, this was expert
valuation evidence. It is convenient to deal with this evidence briefly.
[147] The evidence adduced on both sides was to the effect that the Land could have been
developed at a profit. The contest was about the quantum of the likely profit.
[148] The plaintiffs relied on the opinion of Mr Crawford. He valued the Land, if
developed in accordance with three of the plans contemplated by the plaintiffs from
time to time at between $12.2 million and $12.6 million. He assessed the profit the
plaintiffs would have made at between $5.2 million and $5.5 million.
[149] The defendants relied on Mr Schultz. He valued the Land on the same development
scenarios as Mr Crawford. However, he concluded the developed value would be
between $11.1 million and $11.7 million. He assessed the profit the plaintiffs
would have made at between $3.9 million and $4.3 million.
[150] The valuers agreed that the appropriate method for valuing the Land (as developed)
was by using a capitalisation rate of 5.75 %.
[151] The differences between the parties may be summarised and resolved in this way.
(a) Mr Crawford assumed that if the plaintiffs had developed the Land, they
would have secured a tenant for the food and drink tenancy on terms like
those the plaintiffs had been negotiating with Starbucks, before the
termination of the deed. The evidence for the Queensland Property Manager
of Starbucks, Mr Smith, was that Starbucks had decided it would not be
-- 28 of 32 --
29
proceeding with the site. Mr Shultz had adopted the terms Zuri had secured
for a smaller area. In cross-examination, Mr Schultz expressed the opinion
that the annual market rent for the food and drink tenancy was about
$115,000. This was a little above the rent Zuri had agreed with its tenant,
Zarraffa’s Coffee. In their closing submissions, the plaintiffs accepted that
the court should accept Mr Schultz’s opinion of the market rental as the likely
rental return on the tenancy, if developed by the plaintiffs. I accept that
submission.
(b) Mr Crawford adopted a more conservative market rental for the small shop
tenancies the plaintiffs intended to develop on the Land, than Mr Schultz.
The plaintiffs led no evidence that they had identified any retail tenants. I
accept Mr Crawford’s assessment of the market rental as the likely rental
return on the tenancy, had it been developed by the plaintiffs.
(c) Mr Crawford assumed the plaintiffs would have sought approval and
developed the Land in accordance with revision I of their plan. Mr Shultz
assumed the plaintiffs’ development would have been in accordance with
revision D(2). Had the plaintiffs been able to proceed with the development
of the Land, it is likely they would have considered the comments made by
DTMR at the second pre-lodgement meeting and more closely considered
their plan and adapted it to achieve the highest likely return on their
investment. I accept the plaintiffs’ submission that they would likely have
developed the Land in accordance with revision I or J of their plan.
(d) Mr Crawford assumed the vendor’s works (to be completed by Zuri) would
have been completed three weeks earlier than Mr Schultz assumed. Mr
Crawford’s assumption was based upon the time Zuri took to develop the
Land. The plaintiffs submitted that the evidence of Mr Stokes, under cross-
examination, did not support Zuri’s submission that an extra three weeks
should be allowed for vendor’s works. I accept that submission. The time
Zuri took to complete the relevant works is an appropriate measure of the
likely time in which those works would have been completed, had the
plaintiffs proceeded with the development of the Land.
(e) Mr Crawford assumed Zuri would have granted the plaintiffs an additional
easement to allow the plaintiffs to develop the Land in accordance with
revision I of their plan. Mr Schultz did not. Zuri, as the owner of the
Property, granted the additional easement to facilitate its own development of
the Land and the balance of the Property. The defendants called no evidence
of the attitude of the director of Zuri on this point. Little appears to turn on
this point. Both Mr Crawford and Mr Schultz express the opinion that the
value of the Land as if developed in accordance with revision I is very similar
as if developed in accordance with revision J; and that the profit the plaintiffs
would likely have made in developing the Land under each revision would be
about the same. On balance, I accept the plaintiffs’ submission that Zuri
would likely have agreed to grant the same additional easement as it did, if
the plaintiffs had proceeded with their proposed development t of the Land.
This would have facilitated a development in accordance with revision I, but
it makes no difference to the value of the opportunity the plaintiffs contend
they lost.
-- 29 of 32 --
30
(f) The defendants also submitted that the plaintiffs’ timeline for completion of
their proposed development was unrealistic, because they would not likely
have identified and secured a tenant for the food and drink premises by
October 2017. I accept this submission. It is likely the plaintiffs would have
taken as long as Zuri did to identify such a tenant, namely 15 months.
(g) The defendants submit that the plaintiffs would not have been able to finance
their proposed development of the Land in the manner they allege. As both
valuers conclude the development would have been profitable, I find it was
likely the development would have been financed from the BMI group’s
usual funding sources, being Mr Lindsay and the ANZ Bank.
[152] Taking these matters in account, the opportunity the plaintiffs allege they lost was
the chance of making a profit of about $5 million, allowing for the contingencies
associated with the commercial development of vacant land.
Duty of confidentiality
[153] The plaintiffs have another damages claim for breach of a duty of confidentiality
under the deed and in equity. The claim is expressed to be against both Zuri and
Boardwalk. BPH and Boardwalk were not parties to the deed. Neither could have a
claim for breach of it.
[154] By clause 12.2 of the deed, Zuri and Bluepoint agreed that:
“Each party (recipient) shall keep secret and confidential, and shall
not divulge or disclose any information relating to another party or
its business (which is disclosed to the recipient by the other party, its
representatives or advisers) or this deed”
[155] The clause exempted the disclosure in five circumstances. The first was “to the
extent that:”
“the information is in the public domain as at the date of this deed (or
subsequently becomes in the public domain other than by breach of
any obligation of confidentiality binding on the recipient);”
[156] The second was where disclosure is required by law or by a stock exchange.
[157] The third was to the extent that:
“the disclosure is made by the recipient to its financiers or lawyers,
accountants, investment bankers, consultants or other professional
advisers (including directors, partners, officers and employees of its
advisers) to the extent necessary to enable the recipient to properly
perform its obligations under this deed or to conduct their business
generally, in which case the recipient shall take reasonable steps to
ensure that such persons keep the information secret and confidential
and do not divulge or disclose the information to any other person;”
[158] The fourth was disclosure required for use in legal proceedings about the deed or
the sale of the Property. The fifth was with the prior written consent of the non-
disclosing party.
-- 30 of 32 --
31
[159] The plaintiffs seek an equitable remedy granted where a party has used confidential
information as “a springboard” to place itself in a better position that it could have
achieved from its own skill and ingenuity. The use must be in breach of either a
contractual or an equitable duty of confidentiality. This is commonly referred to as
the springboard doctrine. They submit the appropriate measure of damages is the
amount necessary to make the wrongdoer:
“accountable to the person who was the original source of the
information – but only to the extent by which he has gained an
advantage by virtue of having had information in advance of the
general public...the advantage is unfairly gained can be measured in
terms of time saved and, thence, in terms of money.”
[160] The plaintiffs’ case is an inferential one. It begins with evidence that the following
information was provided to Zuri:
(a) Mr Dore’s statement to Mr Irvine on 8 December 2016 that proposed Lot 1
was suitable for a service station and fast-food development;
(b) Bluepoint’s draft subdivision plan sent to Zuri on 16 December 2016;
(c) Bluepoint’s architectural plans provided to Zuri on 20 February 2017;
(d) A sketch by Bluepoint’s traffic engineer shown to Zuri’s traffic engineer on
27 July 2017;
(e) The second pre-lodgement between Bluepoint and DTMR on 11 September
2017;
(f) The identity of Bluepoint’s prospective tenants for the premises to be
developed on the Land; and
(g) Bluepoint’s prospective consultants for the development.
[161] The plaintiffs did not show the information at paragraphs (a), (f) and (g) above to be
secret or confidential or to have the necessary quality of confidence to make good a
claim of breach of duty of confidentiality.
[162] The plans at (b) and (c) above and in the sketch at (d) above each contain much
information, as such documents commonly do. As the defendants submitted, the
plaintiffs did not identify the information in each that they contend was secret or
confidential or had the necessary quality of confidentiality. The documents
identified in each of these items comprise information about the Property and the
Land that was known to Zuri and could be obtained from public domain sources,
including the dimensions of the Property and the Land, their location, the DTMR
approved access, and the surrounding land and road corridors. The internal
roadways proposed by Zuri were, of course, known to Zuri. I reject the submission
that each document was itself confidential information within clause 12.2 or the
equitable duty.
[163] As well, the plaintiffs did not prove that the disclosure of any of these documents by
Zuri to its consultants and professional advisers was beyond the extent necessary to
enable Zuri to conduct its business generally or that Zuri’s consultants and advisers
failed to keep any confidential information secret and confidential or that they
divulged or disclosed it to any other person.
-- 31 of 32 --
32
[164] The information at (e) above, to the extent it may be identified, was not shown to be
secret or confidential. Nor was it identified sufficiently to conclude that it was
information disclosed to Zuri by Bluepoint.
[165] The plaintiffs contend that Zuri obtained a “gain” in the form of:
(a) a headstart by skipping the ‘preliminary design’ phase of the development
process; and
(b) starting from a position where DTMR was already persuaded to approve a
service station development on the Land that ‘provided a pathway to
approval, which required only a few relatively minor technical issues to be
addressed.’
[166] In substance the plaintiffs’ complaint is that Zuri benefited from work Bluepoint
had done to advance its proposed development, when Zuri proceeded to develop the
Land (and the balance of the Property) after the termination of the deed. Neither the
deed nor the equitable duty prevented Zuri from so benefitting. Each could provide
a remedy only were there was a relevant breach.
[167] The plaintiffs failed to prove any relevant breach of either clause 12.2 of the deed or
the equitable duty of confidence. Their claim for damages for breach of confidence
fails.
Final disposition
[168] For the reasons set out above, the order of the court should be judgement for the
defendants on the plaintiffs’ claims.
[169] Subject to any further submissions that might be made, costs should follow the
event.
-- 32 of 32 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2022/026