Choppair Helicopters Pty Ltd v AMT Helicopters Pty Ltd [2022] QDC 169
DISTRICT COURT OF QUEENSLAND
CITATION: Choppair Helicopters Pty Ltd v AMT Helicopters Pty Ltd
[2022] QDC 169
PARTIES: CHOPPAIR HELICOPTERS PTY LTD
(Plaintiff)
v
AMT HELICOPTERS PTY LTD & ANOR
(Defendants)
FILE NO/S: BD 2012/2018
DIVISION: Civil
DELIVERED ON: 1 August 2022
DELIVERED AT: Brisbane
HEARING DATE: 28, 29, 30, 31 March, 1 April, 6 May 2022
JUDGE: Barlow QC DCJ
ORDERS: There be judgment for the first defendant on the
plaintiff’s claim.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND
DEFENCES TO ACTION FOR BREACH – OTHER
MATTERS - the first defendant was the contractual bailee
of the plaintiff’s aircraft engine for the purpose of repair
of certain components - the first defendant sub-bailed the
engine to the second defendant, which sent them to another
party – the other party, with the sub-bailee’s consent (but
not that of the bailee or the owner) dismantled the engine
entirely and quoted for its repair – whether the first
defendant was entitled to sub-bail the engine – whether the
first defendant was in breach of the contract and bailment
BAILMENTS – BAILMENT FOR REWARD –
REMEDIES – PARTICULAR REMEDIES – DAMAGES
- the first defendant was the contractual bailee of the
plaintiff’s aircraft engine for the purpose of repair of
certain components - the first defendant sub-bailed the
engine to the second defendant, which sent them to another
party – the other party, with the sub-bailee’s consent (but
not that of the bailee or the owner) dismantled the engine
– the sub-bailee breached the bailment – whether the bailee
was liable to the owner for the actions of the sub-bailee –
what loss (if any) the owner suffered for which the bailee
was liable – what was the value of the engine
Baxter v Obacelo Pty Ltd (2001) 205 CLR 635, applied
-- 1 of 40 --
ii
Graham & Linda Huddy Nominees Pty Ltd v Byrne
[2016] QSC 221, distinguished
Haines v Bendall (1991) 172 CLR 60, followed
Hobbs v Petersham Transport Co Pty Ltd (1971) 124
CLR 220, applied
Jones v Dunkel (1959) 101 CLR 298, discussed
McKenna & Armistead Pty Ltd v Excavations Pty Ltd
(1956) 57 SR (NSW) 515, applied
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty
Ltd (2015) CLR 104, followed
Robinson v Harman (1848) 1 Ex 850, applied
Sellars v Adelaide Petroleum NL (1994) 179 CLR 332,
distinguished
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
(2009) 236 CLR 272, cited
Tang Man Sit v Capacious Investments Ltd [1996] AC
514, applied
The Anderson Group Pty Ltd v Tynan Motors Pty Ltd
(2006) 65 NSWLR 400, applied
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219
CLR 165, followed
Palmer on Bailment (Sweet & Maxwell, 3rd edition,
2009)
Barker et al, The Law of Torts in Australia (Oxford
University Press, 5th ed, 2012)
COUNSEL: J Ribbands, for the plaintiff
M Eade, for the first defendant
SOLICITORS: Maitland Lawyers for the plaintiff
Wilson Lawyers for the defendant
Contents
Introduction .......................................................................................................................... 1
Pre-contractual events .......................................................................................................... 2
What were the terms of the agreement? ............................................................................... 7
Bailment ............................................................................................................................. 13
The state of the engine........................................................................................................ 14
Events after the contract was made .................................................................................... 15
Was the agreement terminated, whether by agreement or by substitutional bailment? ..... 21
Did Airwork breach the agreement?................................................................................... 23
What loss has Choppair suffered? ...................................................................................... 24
The nature of Choppair’s claim and Airwork’s defence ................................................ 24
Principles ........................................................................................................................ 25
Choppair’s claim: the “trade-in value” ........................................................................... 26
-- 2 of 40 --
iii
Expert evidence of value ................................................................................................ 28
Determination of value ................................................................................................... 30
The settlement with Pacific ............................................................................................ 34
Choppair’s loss ............................................................................................................... 36
Conclusions ........................................................................................................................ 37
-- 3 of 40 --
1
Introduction
[1] The plaintiff (Choppair) operates a commercial helicopter hire business out of
Moorabbin Airport in Melbourne. Its managing director and chief pilot is Michael
van der Zypp. He is a very experienced pilot. He is not a maintenance engineer.
[2] In 2014, Choppair (or a subsidiary company, apparently on its behalf) bought an
Airbus AS350BA helicopter and imported it from Cambodia. It arrived in June. The
helicopter had installed in it an engine, known as an Arriel 1B and manufactured by a
French company known as Safran or one of its group of companies.1 Neither the
helicopter nor its engine was then in a state that would, under Australian civil aviation
laws, allow it to be operated. Upon its arrival at Moorabbin, the helicopter was taken
to the premises of the maintenance company used by Choppair, Whirlybird
Helicopters Pty Ltd (Whirlybird), which removed and stored the engine. The
director of Whirlybird was Russell Smedley.
[3] The first defendant (Airwork) is a licensed aircraft maintenance organisation
operating in Caboolture. Its director and chief pilot is Myles Tomkins. Mr Tomkins
is also a very experienced pilot and he is a grade 1 flight instructor. He is not a
maintenance engineer. Airwork is authorised by the Civil Aviation Safety Authority
(CASA) to do certain types of maintenance of aircraft, including one-hundred hourly
inspections of Bell and Safran helicopter engines. Airwork employs licensed aircraft
maintenance engineers (LAMEs) and aircraft maintenance engineers (AMEs) to
undertake that work. Mr Tomkins himself has no role in respect of maintenance work.
At the relevant times, Airwork’s chief engineer was Glenn Geange, who was
responsible for the maintenance work undertaken by Airwork.2
[4] In October 2015, Choppair sent the engine to Airwork. The reason and the terms on
which it was sent and received are in dispute. Putting it objectively for now, Choppair
wanted to have two modules and one other component of the engine “re-calendared”
and, after sending the engine to Airwork, it sought and received from Airwork a quote
to undertake those tasks.3
[5] Airwork sent the engine to another licensed aircraft maintenance organisation, Pacific
Crown Helicopters Pty Ltd (Pacific), which operates at the Sunshine Coast airport.
Pacific in turn sent it to the manufacturer (Safran4), in Sydney. Safran stripped down
the engine completely, inspected every part and wrote a report about the airworthiness
of every part. It sent Pacific a quote to re-assemble the engine, including to repair,
service or replace parts as necessary. The engine was never re-assembled. It was
returned (in its disassembled state) to Choppair by Pacific only shortly before trial.
1 The complete name of the French company is not in evidence.
2 T4-4:38 - T4-6:43.
3 The engine is “modular”, meaning that it has 5 principal modules, each of which can be separated
from the engine and serviced or replaced. It also has several other components, including
(relevantly) a fuel control unit (FCU). Each module (as well as individual components within it) and
each other component has a service lifetime, which is expressed both in the number of hours it has
been operated between services and the number of months between services (and, in some cases, the
number of “cycles”, which I understand normally to mean a completed take-off and landing of the
aircraft), as well as an overall life at the end of which it must be discarded. To “re-calendar” a
module is to have it serviced to an extent that it may be returned to service for a fresh period of time.
4 A French company, whose sales and maintenance facility in Australia was operated by Turbomeca
Australasia Pty Ltd or Safran Helicopter Engines Australia Pty Ltd. The names Turbomeca and
Safran appear to have been used interchangeably, at least in this country.
-- 4 of 40 --
2
[6] Choppair claims, in essence, that Airwork received the engine as contractual bailee
for Choppair and was obliged to return it to Choppair at least in the same condition as
Airwork had received it. In breach of that bailment, without Choppair’s consent it
passed on the engine to Pacific, which passed it to Safran, which stripped it down
without Choppair’s knowledge or consent. Choppair claims that the engine in its
current state is worthless. It contends that, had the engine not been disassembled,
Choppair could have traded it in for another engine, receiving value for it of about
€400,000. Choppair claims damages in that sum, claiming that that was the engine’s
value to Choppair, which is now lost.
[7] Airwork contends, in essence, that it received the engine without notice and before it
had made any agreement with Choppair, it had no personnel who were qualified,
under civil aviation laws, to undertake the work for which it later gave Choppair a
quote and it sub-contracted that work to Pacific (in accordance with ordinary industry
practice). It was not responsible for Pacific sending on the engine to Safran, nor for
Safran stripping it down. Furthermore, the bailment to it and its sub-bailment to
Pacific were ultimately superseded by a separate bailment directly between Pacific
and Choppair. Finally, it contends that the engine was never able to be restored to an
operable condition except by the work that Safran did and quoted to do and it was
never worth more than it now is (which is more than nothing: about $20,000).
[8] Choppair sued both Airwork and Pacific. Pacific (the second defendant)
counterclaimed for payment of a sum that Pacific had paid Safran for the cost of
“bagging and tagging” the component parts of the engine. Shortly before trial,
Choppair settled with Pacific on terms that Pacific return the engine parts to Choppair
and pay Choppair $40,000, with each party releasing the other from any other liability.
[9] The parties, in their submissions, have agreed that the following issues arise for
determination:
(a) what were the terms of the agreement for bailment between Choppair and
Airwork;
(b) was the agreement terminated and (or alternatively) did a substitutional bailment
between Choppair and Pacific arise; and
(c) if the court finds that Airwork breached its agreement or bailment with
Choppair, as a result did Choppair suffer any loss and, if so, in what sum?
[10] These issues elide an essential question: did Airwork breach its agreement?
[11] These questions must be considered in the context of the factual background to the
agreement, to which I shall now turn.
Pre-contractual events
[12] At about the same time as Choppair imported the helicopter, another company known
to Mr van der Zypp imported a similar helicopter (referred to by its callsign, VH-
WOP), also from Cambodia.
[13] Mr van der Zypp became aware that that company had engaged Airwork to obtain a
certificate of airworthiness for VH-WOP. Mr van der Zypp learned that, in the course
of undertaking that work, a LAME contracted to Airwork, Bill Owen, had reviewed
the engine logbooks and discovered discrepancies in them that resulted in none of the
modules being out of calendar limits, so that all that was required was a series of
-- 5 of 40 --
3
hourly inspections. He was able to undertake those inspections so that that engine
was then certified as serviceable.
[14] In about March or July 2015,5 Mr van der Zypp had a telephone conversation with
Mr Tomkins. Mr van der Zypp said Mr Tomkins told him, in that conversation:6
“You need to stop mucking around down there. Send the engine to me. I’ve
engaged the gentlemen Bill Owen and Glen Geange. Bill Owen knows Safran
engines because he worked on them for years in England. And, yeah, he knows
what he’s doing in regard to reservicing these engines and recertifying them.
So they managed to recertify one of John Taylor’s modules that we thought was
dead,” and, “Send them up.”
[15] Mr Tomkins said that, in March 2015, while he was talking to the owner of VH-WOP,
he was briefly put onto Mr van der Zypp and suggested that they talk later. Mr van
der Zypp then rang him and Mr Tomkins told him what Mr Owen had been able to do
with the logbooks of VH-WOP. Mr van der Zypp asked him if Mr Owen could look
at the logbooks for his helicopter. Mr Tomkins told him to send them up and he would
see what they could do.7
[16] Copies (and perhaps the originals) of the engine logbook and the log cards for its
modules for Choppair’s engine were sent to Airwork for Mr Owen to do a similar
review. Mr Owen reviewed the logbook and log cards in April 2015.8 He ascertained
that module 5 and the FCU needed re-calendar inspections9 and he was later informed
by Safran that module 1 also need such an inspection.10 He was also told by Alan
Whitten, a Safran field service representative, that the engine had not been stored
correctly at Whirlybird.11 Mr Owen said that, once he found that out, he was aware
that the engine could not be made serviceable until it had been fully inspected by
Safran, so he did little else apart from telling someone at Whirlybird (he could not
remember who) that he understood that the engine had not been stored correctly, so
he could not do anything to return the engine to service. He also told his supervisor
at Airwork (Glenn Geange) or Mr Tomkins12 that he could not do anything with the
logbooks to bring the engine back into service.13
[17] It is clear to me that the conversation between Mr Tomkins and Mr van der Zypp
occurred in March 2015, not in July, as it was followed by Mr Owen inspecting the
logbook and log cards in April. Mr Tomkins told Mr van der Zypp to send up the
logbook and log cards, not the engine, for Mr Owen to see what, if anything could be
done having regard to the logbook entries. I do not accept that Mr Tomkins told
Mr van der Zypp to send the engine.
[18] It is convenient here to consider a submission by counsel for Airwork that I should
not accept Mr van der Zypp as a witness of credit. Mr Eade submitted that, in his
5 Mr Tomkins said it was in March, while Mr van der Zypp said it was in July.
6 T1-65:9-15.
7 T4-8:40 - T4-9:45.
8 That he did so in April 2015 is obvious from emails he exchanged with Safran on 14 and 15 April
2015: TB547-556.
9 T4-42:6-9.
10 Exhibit 1 (trial bundle or TB), p548; T4-46:14-24.
11 T4-44:21-26, 40-41.
12 T4-50:13 - T4-51:27.
13 Mr Tomkins said that he thought Mr Owen told him that in about July or August 2015: T4-10:36-38.
-- 6 of 40 --
4
evidence, Mr van der Zypp was evasive and not responsive to questions and his
evidence was irreconcilably inconsistent about a number of matters. In the course of
the evidence, in response to a submission about Mr van der Zypp’s credit,
Mr Ribbands, for Choppair, submitted that, “Credit … is the refuge of the forensically
destitute.”14
[19] As will become apparent, I do not consider that Mr van der Zypp was a deliberately
untruthful witness. However, I consider that he did not have a good memory of many
of the relevant events. However, he has – I consider not deliberately – reconstructed
events and his memories of them. As Mr Ribbands submitted in his closing written
submissions:
It is a not uncommon phenomenon that two individuals may tell divergent
stories pertaining to the same event, but each honestly believes they are telling
the truth. Such is the nature of the fallibility of the human memory that
recollections fade over the years and likewise, tend to be reinforced in favour
of a position which puts the person concerned in the best light. That is not to
say that anyone is being anything other than entirely truthful. It simply
recognises the fallibility of memory.
[20] An example of Mr van der Zypp’s poor memory is in the event that I have just
discussed. Mr van der Zypp’s evidence that he discussed with Mr Tomkins having
Mr Owen review the logbooks in July is demonstrably wrong, as Mr Owen and Safran
exchanged emails about the modules in April.
[21] Therefore, where Mr van der Zypp’s evidence is inconsistent with that of other
witnesses and surrounding events as shown in documents, I generally prefer that
revealed by the documents and, at least where it is not inconsistent with documents or
there are no documents, that of the other witnesses.
[22] Choppair, or Whirlybird on its behalf, sent the engine to Airwork in October 2015.
Mr van der Zypp said that he sent the entire engine, rather than simply the modules to
be re-calendared, because in his telephone conversation with Mr Tomkins in July
2015, Mr Tomkins had told him to just send the whole thing up (although, he said, it
wasn’t exactly said that way).15 As I said, I do not accept that Mr van der Zypp was
told, by anyone at Airwork, to send up the entire engine. I consider it more likely that
Mr Smedley or someone else at Whirlybird suggested that to him. Mr Smedley said
he did not recall Mr Owen ringing him to tell him that the engine would have to be
sent to Safran. However, at the time Whirlybird engaged a LAME by the name of
Dennis Bradley. It is quite possible that Mr Owen spoke to Mr Bradley, who had
worked on Choppair’s helicopter and, indeed, had removed the engine from it.16
[23] Mr Bradley was not called to give evidence. Counsel for Airwork, Mr Eade,
submitted that I should infer from his absence that he was not called by Choppair
because his evidence would not have assisted Choppair’s case.17 I do find it unusual
that he was not called, given his involvement with the engine and that he could be
expected to have given evidence about what happened to the engine after he had
14 T2-115:46-47. Clearly itself a forensic flourish that I do not accept as bearing on the issue here.
15 T1-69:20-25.
16 This appears from the engine logbook at TB553. Mr Smedley explained the relevant entry: T2-
125:43 – T2-126:13.
17 Relying on the principles in Jones v Dunkel (1959) 101 CLR 298, 320-321.
-- 7 of 40 --
5
removed it from the helicopter, including how and where it had been stored. He also
had a conversation in November 2014 with Allen Whitten of Safran and subsequently
exchanged emails with Mr Whitten and Mark Robinson,18 in which he said that the
owner of the engine would like to know an approximate cost of a calendar overhaul
of the engine and its trade-in value against a new Arriel 1D1 engine with an upgrade
of the helicopter.19
[24] Counsel for Choppair, Mr Ribbands, submitted that no such inference should be
drawn, as the court cannot conclude that he is in Choppair’s camp. He was a
contractor to Whirlybird, which was a contractor to Choppair, not an employee of
either.
[25] In my view, it is puzzling that Choppair did not call Mr Bradley, given that he had
direct involvement with the engine and that he made those enquiries on behalf of
Choppair. There was no explanation for not calling him. Should it be necessary, I
would draw an inference that his evidence would not have assisted the plaintiff.
[26] The evidence is insufficient to determine with any certainty what led to Choppair
sending the entire engine to Airwork rather than having Whirlybird take off the two
modules and the FCU and send only those items. The timing of that event (October
2015) is curious, given that the dealings with the logbooks had occurred in April. But
I do not accept that Mr Tomkins told Mr van der Zypp to do so, whether in March or
July 2015.
[27] Frankly, given the enquiries made by Mr Bradley about the cost of a full calendar
overhaul of the engine and the alternative cost and benefit of an upgrade of the
helicopter and a trade-in of the engine, I consider it likely that, having received a
response about the latter possibility and having been told what Airwork had done for
the owner of VH-WOP, Mr van der Zypp decided to explore whether some modules
could be re-calendared more cheaply than the other options. He was then told, in
April 2015, that modules 1, 5 and the FCU needed to be re-calendared, but he was
aware that the entire engine may have to be re-calendared. He decided to explore the
former first but, as the latter was a possibility, he decided to send the entire engine to
Airwork even though, at that stage, he only wanted a quote for re-calendaring the two
modules and the FCU. He therefore arranged for the entire engine to be packed and
sent to Airwork. However, while this scenario seems likely, I am unable to find
positively that it occurred, as the possibility was not explored in the evidence or in the
parties’ submissions.
[28] Mr Tomkins20 and Mr Owen21 said that the engine arrived without any prior notice
that it was on its way. There is no evidence that they were told that it was being sent
to Airwork and each of them said that he had not been told that it was on its way.22
Mr Owen said it arrived on 18 or 19 October 2015: he knows the date because he
took photographs of it which show that they were taken on 19 October.23 They did
18 Safran’s support services and business development manager.
19 Exhibit 17. Mr van der Zypp denied any knowledge at the time of those enquiries being made:
T2-5:32 – T2-7:1.
20 T4-10:41 - T4-11:16.
21 T4-52:30-42.
22 T4-11:7-12; T4-52:30-42.
23 T4-52:24, T5-35:1-7. The photographs are exhibit 12.
-- 8 of 40 --
6
not remove the engine from the container in which it had arrived. Mr Owen said that
the crate in which it arrived was not a suitable container for an aircraft engine. He
said that, having arrived in an unsuitable container, the engine could only be
considered unserviceable as a whole. Having arrived that way and in that condition,
he was not prepared to do any work on it.24 Mr Tomkins told him to find out what
they could do and to get some options and some quotes.25
[29] Mr Owen sent an email to Mr Bill Haffner (Pacific’s managing director) on 19
October 2015, attaching the log cards for modules 1 to 5 and the FCU,26 noting that
the engine had been left on a pallet uncovered in Whirlybird’s hangar for six months
and asking for a quote on various options to get the engine to a serviceable condition.
[30] Mr Haffner and Daniel Stromski from Pacific then exchanged emails with
Mr Robinson of Safran. Mr Haffner said he was trying to see if there was anything
that Pacific could do at a lower level of maintenance rather than sending it to Safran.27
They asked Mr Robinson what was required to get the engine serviceable and an
estimate of the cost “assuming everything is ok inside.” Mr Robinson said he would
say it would require a “full calendar reset strip.”28 As to cost, he said,29
It’s hard to put a figure on it but would expect it to be in range of 60,000 USD
plus parts required. So would expect to be around the 200K-300K USD but will
depend if the Life limited parts pass inspection then will push up price
dramatically.
[31] Mr Stromski30 passed on that email to Mr Owen, who recalled receiving it and said
he showed it to Mr Geange, but did not recall if he showed it to Mr Tomkins.
However, he said that he told Mr Tomkins that, because of the way the engine was
transported to Airwork, there was nothing that Airwork could do; the only option was
to have the engine inspected by Safran. While it was not clear whether he told
Mr Tomkins the following, in his evidence Mr Owen said that Airwork could not even
take off the modules and send them individually to be re-calendared because, if it did
so, it would take responsibility for properly preserving and packing the engine, which
would have involved extra costs for Airwork and there was also a risk that the owner
would deny that any damage that had been caused by the method of transport was the
owner’s fault.31 He said Mr Tomkins agreed to pass on the engine “to somebody who
knew what they were doing.”32 Mr Owen took more photographs of the engine in its
container33 and, on 11 November 2015, Airwork sent on the engine to Pacific, because
Pacific was Safran’s representative and Mr Whitten had told Mr Owen to send
everything through Pacific.34
24 T4-53:33-39; T4-59:41 – T4-60:3.
25 T4-11:38-42.
26 TB558-573.
27 T4-123:1-16.
28 TB575, emails 31 October, 4 and 5 November 2015.
29 TB574, email 9 November 2015 from Robinson to Stromski and Haffner.
30 Who said he understood that a full calendar reset strip was a maintenance activity to bring the
calendar time of the engine back to zero, because there are fixed calendar intervals when engines
need to be overhauled: T3-108:1-7.
31 T4-64:26-43.
32 T4-64:45-46.
33 Exhibit 13.
34 T4-65:5-19.
-- 9 of 40 --
7
[32] Mr Tomkins said that Mr Owen told him that, from the state of the logbooks and the
way the engine was shipped, nothing could be done without opening up the engine.
Mr Owen told him that he had a quote to re-calendar modules 1, 2 and the FCU, but
said it would be subject to them opening up the engine.35
[33] Mr Tomkins then added Airwork’s usual 30% margin to the amount of the quote that
Mr Owen had told him about, resulting in a price to Choppair of $78,000 plus GST
for re-calendaring those components. As I will discuss later, he sent a quote for that
work to Choppair and discussed it with Mr van der Zypp.
What were the terms of the agreement?
[34] The parties agree that the contract between them was made in November 2015. They
each contend that it was partly oral and partly in writing. They differ about what was
orally agreed and about the proper construction of the written part. Airwork also
contends that the written part comprised two documents, while Choppair contends it
comprised only one.
[35] Mr Tomkins said36 that, after Mr Owen told him Airwork could not itself do anything,
but he had a quote from Safran to re-calendar the modules that Choppair had asked
Airwork to do, he telephoned Mr van der Zypp. Mr Tomkins said that he told Mr van
der Zypp that it would be about $78,000 plus GST to do the work, but it would be
subject to them opening up the engine. They did not discuss the maintenance that
might or would need to be undertaken to the engine, because:37
Well, we couldn’t, because we didn’t know what it was until we opened the
engine up. The only thing that we could be sure of is the re-calendar of 1, 5 and
the FCU.
[36] Mr van der Zypp said that, in his conversation in about July 2015 with Mr Tomkins,
Mr Tomkins told him that Airwork had nearly finished with the helicopter bought by
the other company and Mr van der Zypp should send his engine up to Airwork.38 He
also said that he told Mr Tomkins that he did not want the engine to be sent to Safran.39
[37] Mr van der Zypp denied that he had a conversation with Mr Tomkins after the engine
was sent to Airwork. He denied that Mr Tomkins told him that Airwork had received
the engine and it had to be sent away to be opened up.40 However, he had earlier said
that he and Mr Tomkins “had another conversation, but purely over the fact that [the]
engine was there now.”41 They clearly had a conversation after their March
conversation. I accept Mr Tomkins’ evidence and find that they had a conversation
to the effect that he described, shortly before Airwork sent Choppair the quote.42
35 T4-12:2-18. Mr Tomkins said modules 1, 2 and the FCU, but he was obviously mistaken and
intended to refer to modules 1, 5 and the FCU. It seems that Mr Tomkins believed that the quote
from Mr Robinson was in fact only to re-calendar those components even though Mr Owen had
asked for the cost of what was required to get the engine serviceable.
36 T4-12:29-41.
37 T4-12:38-41
38 T1-64:12-14, T1-65:7-15.
39 T1-72:32-36.
40 T2-44:36 – T2-45:10; T2-45:36-43.
41 T1-72:28-30
42 See [40] below.
-- 10 of 40 --
8
[38] Choppair pleaded that the contract included a term that Airwork was not to send the
engine to Safran and Airwork itself was to do the work of re-calendaring the three
components. I do not accept that. The evidence about not sending the engine to Safran
was that of Mr van der Zypp referred to above.43 But that conversation, if it occurred,
took place many months before the contract was in fact made. Even if Mr van der
Zypp had told Mr Tomkins, in a conversation in March or July 2015, that he did not
want the engine sent to Safran, on an objective analysis from the point of view of
reasonable business people, a statement made so long before the contract date and not
repeated or referred to at the time the contract was made in November 2015, nor
reflected in the written documents comprising (or forming part of) the contract, would
not constitute a term of the contract. Furthermore, Mr van der Zypp knew that
Airwork was not able itself to perform the re-calendaring and that it had to be done
by a level 4 facility (of which Safran was the only one in Australia).44 In such
circumstances, no reasonable business people in the parties’ positions would consider
that there was such a term in the contract ultimately made.
[39] On 11 November 2015, Mr Tomkins sent an email to Mr van der Zypp,45 saying:
Attached is a copy of the tax invoice/quote for the re-calendaring of your engine.
The re-calendar modules 1 & 5 as well as the FCU. The price quoted is of
course subject to them opening up the engine.
[40] Mr Tomkins said that he sent this email after his conversation with Mr van der Zypp.46
I accept that evidence, as Mr Tomkins appeared to have a clear recollection of the
sequence of events. It is also not surprising that, before sending a quote that was not
precise, especially after a long gap since the last communication between them, a
person in Mr Tomkins’ position would telephone the customer to inform him that the
quote was about to be sent.
[41] The document attached to the email47 is set out below:
43 Paragraph [36].
44 See [49] below.
45 TB579.
46 T4-13:16-17.
47 TB580.
-- 11 of 40 --
9
[42] The parties disagree about which of those documents comprise the written part of the
agreement between them and how they should be construed. Before I consider that
issue, I record that, on 16 November 2015, Mr Tomkins sent Mr van der Zypp an
email attaching an invoice for the 25% deposit provided for in the 11 November
-- 12 of 40 --
10
document.48 Choppair (or another company in Mr van der Zypp’s group) paid that
amount, apparently some time later in November 2015.49
[43] The “tax invoice/quote” sent by Mr Tomkins to Mr van der Zypp on 11 November
2015 was clearly a quote, not an invoice. That was subsequently clarified by Airwork
sending to Choppair a credit note for the amount in the invoice and expressly
confirming that it had been a quote, not an invoice.50 The invoice for the deposit also
referred to the “quote 8994 11/11/2015”. The parties agree that it was a quote, not an
invoice.
[44] The quote was therefore an offer to do the work described in it. The quote was
accepted by Choppair, at the latest, when it paid the deposit for which the invoice was
sent on 16 November 2015.51
[45] I find that the contract was purely in writing. The terms of the contract were set out
in the quote sent by Airwork to Choppair on 11 November 2015. The terms were
agreed by Choppair when it paid the deposit. All conversations before 11 November
2015 were discussions that led to the contract, but none of the matters said in those
discussions comprised a term of the contract.
[46] The contract was therefore that Airwork would have modules 1, 5 and the FCU re-
calendared. The price quoted was not a fixed price but was “subject to inspection
after disassembling.” It falls to me to determine what that phrase meant. Airwork
contends that it meant “after the entire engine is disassembled” because, by that stage,
Airwork understood (from Pacific and Safran) that the engine could not be returned
to service, nor could any module be re-calendared, without the engine being fully
inspected by Safran. Choppair contends that it meant “after the modules are
disassembled.”
[47] Of course, the meaning of the contract terms must be determined objectively, having
regard to what a reasonable business person would understand by the language of the
contract and the parties’ conduct and also having regard to the circumstances
addressed by the contract and the commercial purposes or objects to be secured by
it.52 As the High Court has said:53
It is not the subjective beliefs or understandings of the parties about their rights
and liabilities that govern their contractual relations. What matters is what each
party by words and conduct would have led a reasonable person in the position
of the other party to believe.
[48] I have discussed Airwork’s knowledge above: particularly that of Mr Owen and
Mr Tomkins. Mr Owen knew that the entire engine had to be disassembled before it
could be returned to service. He told Mr Tomkins that nothing could be done without
opening up the engine. Although Mr Tomkins is not a LAME, I infer that he knew
(and Mr Owen clearly knew) that, for a module to be re-calendared, that module
needed to be disassembled and its component parts to be inspected and repaired or
replaced as necessary. Mr Owen knew that the quote provided by Safran was for
48 TB581, 583.
49 T2-65:16-22; T4-16:26-32.
50 TB585, 586.
51 There is no evidence of any earlier express acceptance of the quote. Mr Tomkins was not asked and
did not say whether Mr van der Zypp told him to go ahead on the quote provided.
52 Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) CLR 104, [47].
53 Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165, [40].
-- 13 of 40 --
11
labour only and that, with the cost of parts, to re-calendar modules 1, 5 and the FCU
could well cost several hundred thousand dollars. But it does not appear that he told
Mr Tomkins either that the entire engine had to be disassembled before it could be
placed back into service, nor that the cost to re-calendar the particular modules would
possibly be so high. Mr Tomkins knew only that Safran had quoted US$60,000 to re-
calendar those items and that the engine had to be “opened up.” The question is what
aspects of that corporate knowledge Airwork passed on to Choppair.
[49] For Choppair, Mr van der Zypp was aware that a re-calendar of a module involved
the module being stripped down into its constituent parts and fully inspected. He also
knew that to overhaul an FCU required it to be disassembled, at least partly, by a fuel
service shop. He did not believe (although he did not know) that Airwork itself would
overhaul the FCU.54 He also knew that a re-calendar could only take place at a level
4 maintenance facility for Safran. He said that Mr Tomkins told him that Mr Owen
“had the contacts to get that done.”55 He also knew that Airwork was not itself
authorised by the regulations to open up the engine, though it was allowed to separate
it into modules.56 In those circumstances, I do not accept that he believed that Airwork
itself could do the work to re-calendar those modules. I do not accept that Airwork
told him, or led him to believe, that it would necessarily do the work itself.
[50] Mr Tomkins did not tell Mr van der Zypp what the full price might be, nor that the
entire engine had to be disassembled. He said that he and Mr van der Zypp did not
discuss any other maintenance that might need to be done to the engine because he
did not know what it would be until the engine was opened up. The only thing he
could be sure of was the re-calendar of modules 1, 5 and the FCU.57 He said that he
told Mr van der Zypp, in November 2015, that to re-calendar modules 1, 5 and the
FCU would cost about US$78,000 plus GST, but that price was subject to the engine
being opened up. He reiterated, in his email of 11 November 2015, that the price
quoted was “subject to them opening up the engine.” In the quote attached to that
email, the price was “subject to inspection after disassembling.”
[51] Mr van der Zypp did not ask Airwork to do whatever was necessary to return the entire
engine to service. He asked only that the two modules and the FCU be re-calendared.
Airwork’s counsel relied on statements that Mr van der Zypp made in his evidence
that his agreement with Mr Tomkins was that Mr Tomkins would “get … this engine
running”58 and that Airwork would undertake “anything to do to get the engine
running”.59 However, it seems to me, viewing those statements in the evidentiary
context in which they were made, that it was Mr van der Zypp’s understanding that
the likely outcome of re-calendaring modules 1, 5 and the FCU would be that the
engine would then be “running”: that is, serviceable. He and Mr Tomkins did not
agree that Airwork would have any work done that was necessary to get the engine
running. Airwork was only to have those modules and the FCU re-calendared. I do
not accept the proposition by Airwork’s counsel that it was an express or implied term
of the agreement that the entire engine would be stripped down.
54 T1-96:18 – T1-97:2.
55 T1-97:4-7.
56 T2-51:20-21.
57 See [35] above.
58 T2-57:43-45.
59 T2-66:5-10.
-- 14 of 40 --
12
[52] I accept Mr Tomkins’ evidence that he had a telephone conversation with Mr van der
Zypp shortly before he sent the quote. It would be unusual simply to send the quote,
after a long gap in communication, without informing Mr van der Zypp orally. I
accept that he told Mr van der Zypp that it would cost US$78,000 plus GST to re-
calendar modules 1, 5 and the FCU, but that quote was subject to opening up the
engine. He did not tell Mr van der Zypp that the quoted price was for labour only
(and indeed, for labour to strip down the engine, not just to re-calendar two modules
and the FCU) and parts would be likely to cost significantly more. He did not tell him
that the entire engine would have to be stripped down in order for it to be rendered
serviceable. He had been asked to have only the two modules and the FCU re-
calendared (as they had been identified by Mr Owen as needing to be re-calendared)
and that is what he discussed with Mr van der Zypp.
[53] Airwork’s counsel submitted that, in order to determine the terms of the contract, I
must take into account the legislative regime that governs aircraft maintenance and
who may undertake what levels of maintenance to different aircraft and engines and
their components. Mr Eade set out, in his written submissions, considerable and
helpful detail about the relevant statutory requirements. He relied in particular on
requirements that:
(a) the maintenance of all aircraft and engines and their components must be
completely and accurately recorded in the relevant manuals and maintenance
cards;
(b) if a step is not recorded in the relevant manual, it is taken not to have happened;
(c) the manufacturer’s manual for an engine (once approved by CASA) takes on a
quasi-legislative character and must be complied with;
(d) therefore, if the manual requires that an engine or its modules be returned to the
manufacturer or its representative for certain work to be done, or if certain work
has not been done, then only the manufacturer or its authorised (and properly
licensed) representative can do that work.
[54] I accept that that regime is a relevant factor in determining the terms of this contract
between the parties. I do take it into account. It is the regime in which the parties
operated their respective businesses and all the witnesses demonstrated that they have
at least a broad (and in some cases, a very specific) knowledge of the requirements of
the legislation. Mr van der Zypp’s knowledge that I have found in paragraph [49]
above was in part informed by that regime.
[55] The contract scope and price were stated in the quote. As I have said, the email by
which the quote was given to Choppair was not part of the contract. Nor do I consider
that the words of the email, nor any conversation between Mr Tomkins and Mr van
der Zypp, qualified or constituted terms of the contract. The email and the contractual
document must be considered in the context of each other. The contract was to re-
calendar the two modules and the FCU, which was the work that Choppair had asked
Airwork to have done. In that context, and given also that Airwork did not tell
Choppair that the entire engine would have to be disassembled to return the entire
engine to service, the “disassembling” referred to in the quote was disassembling the
modules and the FCU specifically referred to in the quote. Consistently with those
facts, a reasonable person in the parties’ situations would understand the email to be
referring to the same qualification to the price: opening up the modules concerned
could be described relevantly as opening up the engine but, in the context in which it
-- 15 of 40 --
13
was described that way, it would be understood by the putative reasonable
businessman as meaning opening up the three parts of the engine that were to be re-
calendared.60 Furthermore, given that the price was subject to disassembly, in my
view it went without saying and was obvious that, after the modules had been
disassembled, Airwork would inform Choppair of the final price, at which time
Choppair could decide whether or not the re-calendaring should proceed further.
[56] In other words, Airwork was engaged by Choppair to take possession of the engine,
to arrange to have modules 1, 5 and the FCU stripped down (by a properly qualified
maintenance facility) in preparation for re-calendaring, to provide to Choppair a quote
for the re-calendaring once they had been stripped down and the parts required were
known and, if it was subsequently authorised by Choppair to do so, to have the re-
calendaring undertaken.
[57] There was no term of the contract that Airwork would not have the engine or the
modules sent to a third party, including Safran if necessary, to undertake the work.
Nor was it a term of the contract that Airwork would do the work itself. It was to do
such work (if any) as it was licensed to do and to organise for the balance of the work
to be done by appropriately licensed people.
[58] Nor was there any agreement that the entire engine would be disassembled, even if
that were necessary to restore it to a serviceable condition. The only parts that
Choppair authorised Airwork to have disassembled were modules 1, 5 and the FCU;
such disassembly being necessary in order for them to be re-calendared.
Bailment
[59] Choppair’s claim relies not only on breach of contract, but also on the law of bailment.
Choppair contends that, the engine having been delivered to Airwork, as bailee
Airwork had an obligation to return it to Choppair in no less than the same state or
condition as it was when received by Airwork.
[60] If the two modules and the FCU had been stripped down in preparation for re-
calendaring and a quote had been provided to Choppair, which then did not authorise
that the re-calendar work proceed, then Airwork’s obligation would have been to
return the stripped down modules and FCU, together with the rest of the engine, unless
it was instructed otherwise by Choppair.
[61] Of course, at the time the agreement was reached, the engine was already in Airwork’s
possession, having arrived at its premises in October 2015. In other words, Airwork
was already bailee of the engine. As bailee, Airwork was obliged to redeliver the
engine to Choppair or to deal with it in the way stipulated by Choppair.61 In this case,
Airwork had possession of it in order to have work done on it under the terms of the
contract: that is, to re-calendar modules 1, 5 and the FCU (subject to further
instructions from Choppair). In order to get that work done, it was entitled to deliver
it to others to do the work, which would give rise to a sub-bailment. But ultimately,
unless the bailment from Choppair to Airwork was terminated, it was Airwork’s
obligation, as bailee, to return the engine, with modules 1, 5 and the FCU re-
60 The same must be said for Mr Tomkins’ statement to Mr van der Zypp, in their conversation, that the
price of $78,000 (which was for re-calendaring the three items) was subject to the engine being
opened up.
61 Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220, 238 (Windeyer J).
-- 16 of 40 --
14
calendared if that work was done, or in their stripped down state if Choppair did not
authorise further work to be done.
[62] As bailee for reward, it was Airwork’s obligation to Choppair, while the bailment
persisted, to keep the engine safe. Airwork could not escape that duty (nor did the
bailment to it cease) by delivering the engine to Pacific. Ordinarily in the case of
bailment:
If the goods are lost or damaged, whilst they are in [the bailee’s] possession, he
is liable unless he can show - and the burden is on him to show - that the loss or
damage occurred without any neglect or default or misconduct of himself or of
any of the servants to whom he delegated his duty.62
[63] One of the issues in this case is whether the bailment from Choppair to Airwork ended
and, if so, when and by what method. I shall consider that issue later, but at this stage
it is relevant to set out the duties of a principal bailee when the relevant goods are
passed on to someone else to undertake work on them. In such a case, ordinarily the
principal bailee continues to owe the duties of a bailee to the bailor, while the sub-
bailee also owes those duties to the principal bailor, as well as to the principal bailee.63
Furthermore:64
If, on a proper analysis, [the principal bailee] has accepted overall responsibility
for the performance of a task, albeit with a power to delegate it wholly or in part
to another, the mere fact of delegation will not exonerate him if, as a result, the
goods are wrongfully lost or damaged. … If, on the other hand, the original
bailee has agreed only to perform and to be responsible for one link in a chain
of successive services, … he will be liable only for those services he has
undertaken personally and (excluding unauthorised dispositions) will not be
answerable for anything happening to the goods while they are out of his
possession.
[64] Having regard to the terms of the contract, I find that Airwork took possession of the
engine in order to have modules 1, 5 and the FCU re-calendared (whether it did any
of the work itself or it delegated it to others), subject to first obtaining a quote for the
work and confirming with Choppair that it should go ahead to have it done. It was
authorised to delegate that work to others, but it retained responsibility to Choppair to
obtain the quote and then (if authorised by Choppair to do so) to have the work done.
In either case it was (and remained) responsible for returning the engine to Choppair,
either in the state in which it received it or with the three modules stripped down (for
quotation purposes) or re-calendared.
[65] Whether that situation later changed and Airwork was relieved of those obligations
(as Airwork contends) must be determined by examining what occurred after
Choppair authorised Airwork to proceed, by accepting Airwork’s offer. But first it is
necessary to consider the state of the engine when it arrived at Airwork’s premises.
The state of the engine
[66] By November 2015, it was known to Pacific and Airwork that the engine was required
by law to be returned to Safran for a complete strip-down and inspection before it or
62 124 CLR 220, 234 (Menzies J). The same applies if Airwork, as bailee from Choppair, “delegated
its duty” to a sub-bailee such as, in this case, Pacific.
63 Palmer on Bailment (Sweet & Maxwell, 3 rd edition, 2009), [23-002].
64 Palmer on Bailment, [23-006], pp 1246-1247.
-- 17 of 40 --
15
any of its modules or components could be returned to service. That requirement
stemmed from a number of factors.
[67] First, the logbooks showed that little or no maintenance had been done on the engine
since 2014. None of the steps required by the engine manual had been taken (such as
running the engine periodically) to maintain its calendar or life currency. In the
absence of any maintenance, the manual required that it be returned to the
manufacturer for inspection.
[68] Secondly, the logbooks did not record that the engine had ever been stored in
accordance with the manual. In short, the manual required that, if the engine was not
used (that is, flown) and maintained regularly, it was required to be stored in very
particular ways, depending on the period over which it was to be out of use. As with
all maintenance, storage requirements had to be strictly observed and recorded in the
engine logbook. There were no entries in the logbook showing any storage.
[69] Furthermore, Mr Whitten from Safran had observed the engine in Whirlybird’s hangar
on two occasions approximately six months apart. He observed that it had not been
stored in accordance with the manual. I accept his evidence that it was this engine
that he saw and that it was not properly stored.
[70] Mr Smedley, the director of Whirlybird, gave evidence that this engine had been
stored in his office, not in the hangar, so Mr Whitten must have seen another engine
in the hangar. But even if that were so, Mr Smedley did not say, nor show, that the
engine in his office was stored in accordance with the manual’s requirements and the
logbook showed no entries for its storage. Therefore, it must be assumed – and in any
event I infer - that it was not properly stored, even if in his office. In this respect, the
absence of evidence from Mr Bradley that might have confirmed or conflicted with
Mr Smedley’s evidence makes it easier for me to draw this inference.
[71] Thirdly, when transported from Choppair to Airwork, the engine was not in a proper
container, nor on a proper support system, nor was it properly sealed and covered for
transportation in accordance with the manual. Rather, it was in a crate, on a home-
made stand and it suffered apparent contact damage during transport. In all those
circumstances, it was compulsory that it be sent to the manufacturer for a full strip-
down inspection before any component, module or the engine could be returned to
service.
[72] For some or all of these reasons, by November 2015 none of the engine’s modules
could be re-calendared without the manufacturer inspecting them.
[73] This was known by Safran (Mr Whitten and Mr Robinson), Pacific (Mr Stromski and
Mr Haffner) and Airwork (Mr Owen, although not Mr Tomkins), but not by Choppair.
Events after the contract was made
[74] It had not been necessary for Choppair to send the entire engine to Airwork in order
for two modules and the FCU to be re-calendared. Whirlybird could have removed
them and packaged them to send to Airwork.
[75] As the entire engine was sent to Airwork for the re-calendaring to be done, one might
have expected Airwork to remove the two modules and the FCU and to send only
them to one or more appropriately licensed maintenance facilities to have each of them
re-calendared.
-- 18 of 40 --
16
[76] However, having received the engine and given Choppair a quote to re-calendar
modules 1, 5 and the FCU, Airwork sent on the engine to Pacific. As I have already
recorded, Mr Owen said that, the engine having arrived in an unsuitable container and
improperly packed, he was not prepared to do any work on it.65 He arranged to have
it sent to Pacific because Pacific was Safran’s representative and Mr Whitten had told
him that everything needed to go through them.66 The engine left Airwork’s premises
on 11 November 2015.
[77] Mr Haffner said that he was present at Pacific when the box containing the engine
arrived there. He did not see the engine itself. He was not involved in it leaving
Pacific.67
[78] Mr Stromski said he was present on the day that the engine arrived at Pacific.68 He
saw the box in which it was packed and he saw it opened by unscrewing the lid.69 The
documentation for the engine arrived separately and Pacific had been asked to pack it
into the box with the engine to send on to Safran, which they did. He did not observe
the engine itself.70
[79] On 1 December 2015, Pacific sent the box containing the engine to Safran.
Mr Stromski sent an email to Mark Robinson,71 saying:
The engine from below is on its way down to Bankstown for Inspection and
Calendar Reset now. Please find attached our RO. As this is not our engine,
please keep us updated in regards to cost. If possible, please provide me a quote
after initial inspection and review of Log cards, so I can communicate this with
our customer and ask for a deposit, based on the initial results.
Engine Log Book and Cards are included in the shipment. Please confirm once
the engine arrived. …
[80] The “RO” (repair order) attached to that email was from Pacific to Turbomeca.72 It
required shipment to Pacific (presumably of the engine after the works were
completed). The description of the work to be done was:
INSPECTION AND CALENDAR RESET
PLEASE CONFIRM QUOTE FOR LABOUR USD 60,000 EQUIVALENT IN
AUD PRIOR COMMENCING WORK.
FINAL INVOICE IN AUD PLEASE.
[81] On 7 December 2015, Mr Stromski received two emails from Mr Robinson (also
copied to Mr Haffner). In the first,73 Mr Robinson said:
The engine has arrived and bad news, it was loose (not bolted) in the box.
Engine arrived leaning to one side of box and sitting on power shaft. Was not
65 See [28] above.
66 T4-65:9-19.
67 T4-126:32-33, T4-127:11-31.
68 T3-95:23.
69 T3-96:11-19.
70 T3-96:21-26.
71 TB587.
72 That is, Safran. TB588.
73 TB589.
-- 19 of 40 --
17
even clamped into the cradle. We will send thru photos when available. There’s
a nut on bottom of box and bolt in one flange. …
This shipping issue will add costs, as more work will be involved.
[82] In the second email,74 Mr Robinson said:
Please find attached photos of engine loose in transit box.
Please advise how you wish to proceed asap, engine will require full strip as
will be treated as a heavy landing due way was transported.
Engine is now on hold awaiting further instructions.
Please advise how you wish to proceed.
The email recorded that 15 photographs were attached, nine of which are in
evidence.75
[83] That afternoon, Mr Stromski responded by email,76 saying:
Apart from registering SN of the engine modules and attaching the logbooks to
the crate our storeman did not inspect the shipping crate and fixtures. The crate
came to our facility the same way you received it at TAA as we only shipped it
further on to you without [sic]. I will have to get in touch with the owner of the
engine and confront him with the news and see how we want to go ahead.
[84] Nothing appears to have happened between that day and 11 February 2016, when
Mr Robinson sent the following email to Mr Stromski (copying Mr Haffner):77
Can you advise how you wish to proceed with this engine?
Is it to proceed for for [sic] quote or return as-is to PCH.
Let us know how you wish to proceed asap.
[85] Mr Stromski and Mr Robinson then exchanged the following emails that day (copying
Mr Haffner):78
Stromski to Robinson:
I talked to the customer the other day and we need a quote also for the
damage through transport.
Robinson to Stromski:
Can you please clarify you mean
1. Quote for original reason sent in (calendar etc) plus any transport
damage that has occurred? Y/N
If so can you send thru a revised purchase order for the additional
workscope for transport damage.
Stromski to Robinson:
74 TB590.
75 TB592-600.
76 TB601.
77 TB601.
78 TB604 (the first email carrying on to TB601).
-- 20 of 40 --
18
I confirmed with the owner and please go ahead as described below, i.e.
Y.
Attached is the amended RO. Please bear in mind that we need a quote
first (especially on the damage), before commencing the work.
[86] The repair order attached to the last of these emails repeated the original order set out
above and added the following:79
REPAIR TRANSPORT DAMAGE
PLEASE QUOTE FOR LABOUR AND MATERIAL IN AUD PRIOR
COMMENCING WORK.
[87] Mr Stromski was asked who he was referring to as “the owner” in his emails. He
responded that he was probably referring to Mr Owen, because he was his “focal point
of contact.” He said he had no actual recollection of speaking to Mr Owen, but he
was sure he must have because he had to let him know that there was bad news. He
had never had any contact with the real owner.80
[88] Mr Stromski was clearly mistaken about having contacted Mr Owen in February
2016, as Mr Owen stopped working for Airwork in December 2015. Mr Owen said
that he could not recall having any conversation with anyone, let alone Mr Stromski,
about the engine between December 2015 and May 2016 and he never received any
phone call or email seeking approval, or asking him to get Airwork’s approval, for
Safran to do the work of disassembling the entire engine.81 Although Mr Owen did
work with Pacific in December 2015, when Mr Stromski told Mr Robinson that he
would have to contact the owner, there is no evidence that he spoke to Mr Stromski
about the engine then.
[89] Mr Haffner explained the difference between a “full calendar reset strip” and a “full
strip”: the latter involved more work than the former.82 He said that he thought that
Pacific notified Mr Owen about Safran’s email of 7 December 201583 and that the
engine now required a “full strip” as it would be treated as a heavy landing. He said
he remembered talking to Mr Owen about it in December 2015, saying, “But it had to
go in for inspection anyway, so … we’re not going to stop everything.”84 When asked
if he personally got the go ahead to ask Safran to disassemble the engine, he said:85
Well, … we had the go ahead prior to that. This was … the additional – the
hard landing which is just – is going to be additional parts replacement. …
There wasn’t going to be really – wasn’t enormous amount of cost for the
additional – for the shipping damage. … But I mean, we kind of expected that.
If something gets damaged in shipping, I mean, Safran were going to tell us it’s
damaged, sort it out. It’s not worth – it only went down there for a quote to get
repaired, so it still needed to get quoted for repair even if you get it quoted to
see what damage was done in shipping as well. … So we’re still at – at this
79 TB605.
80 T3-100:40 – T3-101:35
81 T4-74:45-47; T4-75:35-44; T4-107:1-6.
82 T4-130:24-35.
83 Although there is no evidence that Mr Stromski sent it to anyone at Airwork.
84 T4-132:1-13.
85 T4-132:15-30, 42-43.
-- 21 of 40 --
19
point chasing a quote, we weren’t repairing the engine at this stage. … At any
stage.
He could not remember having any conversation with Mr Tomkins about the engine
at around that time (nor in February 2016).
[90] Mr Tomkins said that he had no contact with Choppair, Whirlybird or Pacific (apart
from one possible conversation with Mr Haffner in about May 2016) about this engine
after about November 2015.86
[91] Mr van der Zypp said that he was not told in December 2015 that the engine had been
damaged in transit and Safran required it to be treated as a hard landing and to have a
full strip. He also said that he was not told in February 2016 and asked for permission
to go ahead with the full strip. He never gave permission for Safran to disassemble
the engine. He did not even know it was at Safran until later.87
[92] On the basis of this evidence, I am not satisfied that Mr Stromski or Mr Haffner spoke
to Mr Owen to seek permission to instruct Safran to go ahead and strip down the
engine. Mr Haffner seems to have been of the view that the engine went to Safran to
get a quote for it to be repaired, which had already been authorised. I consider that he
was mistaken in his somewhat hazy belief that he spoke about it to Mr Owen and they
agreed that it had to be stripped down anyway. I consider that Mr Owen would not
have authorised any such work without first speaking to Mr Tomkins about it. There
is no evidence of any conversation between those gentlemen at that time.
[93] It may be that, by February 2016, Mr Stromski had a recollection (apparently
incorrect) that he had sought and obtained permission from someone at Airwork,
which led him to authorise Safran to do the work. But, as I said, I consider it highly
unlikely that Mr Owen would have taken it upon himself to authorise the work,
particularly when he no longer worked at Pacific in February 2016. Rather, he would
have referred the question to Mr Tomkins, who would probably then have asked
Mr van der Zypp. Given the damage to the engine and that it appeared to have been
caused in transit and given Mr Owen’s view, when he saw the box and the engine
inside it, that he wanted nothing to do with it, I am sure that, if it had been raised with
him or Mr Tomkins, they would have remembered. I find that Mr Haffner’s
“recollection” is, rather, an inadvertent reconstruction in the light of Mr Stromski’s
email exchange with Mr Robinson.
[94] Regardless of how it came about that Mr Stromski thought he could authorise Safran
to proceed, it is crystal clear that nobody told Choppair about the damage and sought
its permission to instruct Safran to do a full strip to the engine. Mr van der Zypp had
no idea, in December 2015 or February 2016, that the engine was at Safran or that
anything other than re-calendaring of two modules and the FCU was to be done. The
decision to authorise Safran was taken by Mr Stromski without any authority from
Choppair nor, I find, from Airwork.
[95] Having been authorised by Mr Stromski to go ahead and strip the engine, Safran did
so. It then provided to Pacific a detailed report into the state of the engine, including
each of its individual components, a quote to restore the engine to a serviceable
86 T4-20:12-19; T4-21:9-17.
87 T1-78:18-26; T1-79:38 – T1-80:3; T1-80:31-35; T1-81:5-39.
-- 22 of 40 --
20
condition and a list of parts needed for that purpose.88 The repair quote was for
$608,014.79 (after a 10% discount for Pacific).
[96] Ultimately, nobody accepted that quote and instructed Safran to proceed with that
work. Instead, in November 2016 Mr Haffner spoke to Mr van der Zypp and
suggested that the disassembled engine be “bagged and tagged”89 and returned to
Pacific, as Safran wanted to return the engine because it was due to shut down its
Australian facility. Mr Haffner said that Mr van der Zypp agreed to that happening.90
Mr van der Zypp disagreed that he did so, saying that he thought it had already been
bagged and tagged by the time of that conversation.91
[97] Mr van der Zypp is clearly wrong in that recollection. In June 2016, Safran sent an
invoice for $19,078.29 to Pacific for “labour charges up to Quote only,” which on its
face was for stripping down the engine, producing the technical report and the quote
to repair the entire engine.92 Pacific initially sent an invoice for that work to Airwork
on 5 July 2016, charging $21,198.10.93 On 12 August 2016, Pacific sent an invoice
for that work in that sum to Choppair.94 That is the only invoice that Choppair had
received from Pacific by November 2016. On 16 December 2016 Safran sent Pacific
an invoice for $27,042.84 for “labour charges to return the engine U/S ‘as is’.”95
[98] In an outline of evidence made and signed by Mr van der Zypp on 20 January 2022,96
he said:
In a further discussion with Haffner in or about late November 2016, I asked
him where the Engine was at that time. Haffner said the Engine was still in
Sydney with Safran and disassembled. … I said to Haffner that I needed time
to work out what to do with the situation but in the meantime, I asked Pacific
Crown to bag and tag the Engine and return it to Choppair.
[99] That statement was put to Mr van der Zypp in cross-examination, but he persisted in
his evidence that, at the time of that conversation, he thought it had already been
bagged and tagged.
[100] In the light of Mr van der Zypp’s written statement that he asked Pacific Crown to bag
and tag the engine and return it to Choppair and his error in thinking that the prior
invoice (which Choppair did pay) was for that process, I do not accept his oral
evidence that he did not authorise Mr Haffner to get the engine bagged and tagged.
88 Exhibits 3, 4 and 5 respectively. The email under which Safran sent these documents to Pacific is at
TB606-607 (13 April 2016). The report itself was 170 pages long. Safran subsequently sent
Mr Stromski an additional copy of the list of parts in which the parts needed due to the transport
damage were identified: TB609 (19 April 2016), exhibit 15.
89 A process involving putting each component into a plastic bag suitable for its preservation and
tagging the bag with information identifying the component and whether it was serviceable,
unserviceable but repairable, or unrepairable.
90 Haffner, T5-18:9-20.
91 T2-102:24 – T2-103:23.
92 Exhibit 16.
93 Exhibit 6.
94 Exhibit 7.
95 TB662.
96 Exhibit 9, [41].
-- 23 of 40 --
21
His written statement was no doubt written after careful consideration by him and his
lawyers and is more likely to be accurate than his clearly mistaken oral evidence.
[101] I therefore accept Mr Haffner’s evidence on this point and I find that Mr van der Zypp
did authorise Mr Haffner to arrange for the engine to be bagged and tagged.
[102] Safran then went ahead with the process of bagging and tagging the engine and, on 16
December 2016, invoiced Pacific for that work.97 Pacific paid the Safran invoice and
itself invoiced Choppair on 1 July 2017 for $30,047.6098. Pacific retained the
components pending payment to it by Choppair of that invoice. Pacific claimed that
sum from Choppair in its counterclaim in this proceeding. Eventually Pacific returned
the components to Choppair and abandoned its counterclaim as part of the settlement
between them shortly before trial.
Was the agreement terminated, whether by agreement or by substitutional bailment?
[103] In the written submissions of counsel for Airwork, he contended:99
The legal relationship between Choppair and Airwork was at an end in 2016 in
that:
(a) the bailment relationship was superseded and terminated by a
substitutional bailment between Choppair and Pacific Crown; and
(b) the contractual relationship with (sic) terminated by agreement or
abandonment,
through:
(c) the dealings between Mr Haffner on behalf of Pacific Crown and Mr van
der Zypp on behalf of Choppair between July 2016 to (sic) March 2017,
to the exclusion of Airwork; and
(d) Airwork, upon demand, returning Choppair’s deposit to it.
Thus, irrespective of whether Airwork was authorised to sub-bail the Engine to
Pacific Crown (and thereafter Safran) for the purposes of its disassembly,
Airwork’s involvement and liability thereafter ceased by no later than
December 2016.
[104] Counsel went on to submit that, although Airwork remained principal bailee and
Pacific was sub-bailee until about July 2016, between July and December 2016 certain
events occurred that resulted in the bailment to Airwork ceasing to exist and Pacific
becoming the principal bailee. By December 2016:100
the common intention of both Airwork and Choppair was that Airwork had
withdrawn entirely from any future obligations with respect to the Engine and,
with Choppair’s acquiescence if not consent, had been substituted by Pacific
Crown as (principal and sole) bailee
and
97 TB662. The invoice described the work as “labour charges to return the engine U/S ‘as is’” and
showed a price of $27,316, reduced by a 10% discount to $24,584.40, plus GST of $2,458.44.
98 Exhibit 10: being for $27,316 plus GST of $2,731.60.
99 Defendant’s outline of submissions, 3 May 2022, [149]-[150].
100 Defendant’s outline, [170], [179].
-- 24 of 40 --
22
Airwork and Choppair mutually agreed their contractual relationship was at an
end or alternatively were both mutually content to abandon any future
obligations pursuant to it.
[105] Airwork particularly relied on the following facts as demonstrating the end of the
agreement between it and Choppair and the substitution of an agreement between
Pacific and Choppair:101
(a) first, Mr van der Zypp was informed by Mr Haffner that the Engine was at
Safran where it had been disassembled;102
(b) second, Mr Haffner sent to Mr van der Zypp a copy of Safran’s email and the
enclosed Safran report, quote and list of parts;103
(c) third, Mr Haffner informed Mr van der Zypp of the costs of the disassembly and
that Pacific had been charged those costs and had invoiced Airwork for that
amount;104
(d) fourth, Choppair requested that it be invoiced directly by Pacific for the costs
of the disassembly and the provision of the quote;105
(e) fifth, Choppair was subsequently directly invoiced by Pacific Crown for those
costs106 and Choppair paid that amount;107
(f) sixth, Choppair sought to recover,108 and in fact recovered,109 the deposit it had
paid to Airwork;
(g) seventh, Pacific Crown cancelled its invoice to Airwork;110
(h) eighth, aside from the return of the deposit, no other correspondence occurred
between Choppair and Airwork;111
(i) ninth, Mr Haffner and Mr van der Zypp spent almost 12 months exploring
options to obtain a serviceable engine for Choppair (to the exclusion of
Airwork)112; and
(j) tenth, Mr van der Zypp agreed to the engine being bagged and tagged and
returned to Pacific Crown113 while they continued to explore options (again to
the exclusion of Airwork).114
101 Defendant’s outline, [169].
102 This occurred either in April, May or June 2016 (Mr van der Zypp: T1-75:3-22, T2-71:12-30) or in
July 2016 (Mr Haffner: T5-6:31 to T5-7:46). Given the following emails, I find that it was in July
2016.
103 Email, Mr Haffner to Mr van der Zypp, 13 July 2016: TB616-617.
104 Email, Mr Haffner to Mr van der Zypp, 13 July 2016: exhibit 6.
105 T2-87:14-27; T2-90:10-22.
106 Exhibit 7.
107 T2-89:4 - T2-91:19.
108 Email, Mr Johan de Vries (Choppair’s business manager) to Mr Tomkins, 13 October 2016, and
attachments: TB625-627;
109 By two payments, on 25 November and 9 December 2016: TB675.
110 TB637-639.
111 T2-100:5-15; T2-106:17-18.
112 T5-20:41-46.
113 Exhibit 9, [7]; T5-18:9-20.
114 T5-20:41-46.
-- 25 of 40 --
23
[106] Choppair’s counsel submitted that the bailment agreement and contract between
Choppair and Airwork was not terminated or substituted by a bailment between
Choppair and Pacific. He submitted that:115
By the time Van der Zypp began discussions with Haffner in or about May
2016, the engine had already been disassembled. The damage was done – the
agreement had already been breached as previously described. Any discussions
after the fact of the breach and the occurrence of damage must be seen and
construed in that context.
[107] In fact, the parties’ submissions on this issue appear to have passed each other like
unlit ships in the night. The crucial question is whether the bailment agreement
between Choppair and Airwork ended before any breach of it by Airwork and any
consequent loss to Choppair occurred. On that issue, the facts are clear. The engine
was sent to Safran and stripped down with the consent of Pacific (but not with the
knowledge or consent of Choppair) while the bailment from Choppair to Airwork and
the sub-bailment from Airwork to Pacific were in existence. There is no doubt that,
by November 2016 (upon Airwork’s return to Choppair of part of the deposit), the
contract between them was ended. However, that end to the contract did not release
Airwork from any liability for any prior breach of its obligations under the contract
and as bailee.
[108] As Airwork’s counsel accepted, upon the termination of its contract with Choppair,
the bailment from Choppair to Airwork ended and Airwork withdrew from any future
obligations then existing under the contract.116 However, notwithstanding the end of
the contract and bailment, Airwork would remain liable for any breach of its contract
with Choppair that had occurred during the period of that contract and bailment.
[109] I find that the agreement between Airwork and Choppair, pursuant to which Airwork
was bailee of the engine, was terminated by mutual agreement when Airwork returned
the first part of the deposit to Choppair at Choppair’s request. That occurred on 25
November 2016. At that stage the engine was still at Safran’s premises. Pacific then
became principal bailee of the engine in the state in which it then existed, while Safran
remained sub-bailee.
[110] Safran later returned the engine parts (bagged and tagged) to Pacific, which then held
the parts in that state as principal bailee for Choppair.
Did Airwork breach the agreement?
[111] As I have found, Airwork was engaged by Choppair to take possession of the engine,
to have modules 1, 5 and the FCU stripped down in preparation for re-calendaring, to
provide to Choppair a quote for the re-calendaring once they had been stripped down
and the parts required were known and, if it was subsequently authorised by Choppair
to do so, to have the re-calendaring undertaken. For those purposes, Airwork was
entitled to send the engine, or those modules and the FCU, to an appropriately licensed
facility for that specific work to be done. Airwork was not authorised by Choppair to
have any other work done to the engine. As principal bailee, it was responsible for
the return of the engine to Choppair with the work for which it had been engaged done
or, if it could not get it done, in the state that it received the engine.
115 Plaintiff’s outline of closing submissions, 3 May 2022, [47].
116 Defendant’s outline, [170], [177].
-- 26 of 40 --
24
[112] I have set out the relevant principles, as explained by Professor Palmer, in paragraph
[63] above. In this case, Airwork agreed to be responsible for getting the work done
on the two modules and the FCU. It was therefore responsible for more than one link
in the chain of work to be done. The mere fact that it delegated that work to Pacific or
(through Pacific) to Safran did not exonerate Airwork from liability to Choppair for
any loss of or damage to the engine. It remained answerable to Choppair for what
happened to the engine while it was out of Airwork’s possession. The sub-bailee of
the engine, Pacific, was of course answerable to Airwork and to Choppair.
[113] Airwork breached its obligation to return the engine because it did not do so.
Although it did not authorise Pacific or Safran to strip down the entire engine, as
principal bailee it remained responsible to Choppair for the return of the engine in the
relevant state; not stripped down, bagged and tagged.
[114] I find, therefore, that Airwork breached its agreement with Choppair and its
obligations as bailee of the engine. It did so in two respects: first, it did not have the
two modules and the FCU re-calendared, nor obtain a full quote for doing so (once
the cost of relevant parts was known) and seek Choppair’s consent to proceed with
the work. Secondly, from the time that the engine was stripped down Airwork became
unable to return the engine in the proper state (unless it paid the cost of doing so) and
it did not, during the term, return the engine to Choppair. Those breaches occurred
while the agreement and bailment were on foot, so Airwork remains liable to Choppair
for any loss117 suffered by Choppair as a result.
What loss has Choppair suffered?
The nature of Choppair’s claim and Airwork’s defence
[115] It is necessary to determine what loss, if any, Choppair has suffered as a result of
Airwork’s breaches.
[116] In its further amended statement of claim, Choppair pleaded that it had suffered loss
as a consequence of the loss of use of the engine. However, in its prayer for relief, it
sought the return of the engine and damages for breach of contract, detinue,
conversion and negligence. It did not set out any particulars or amount of the damages
sought except that, in the notice under rule 150(3) of the Uniform Civil Procedure
Rules, it said that it claimed $675,000118 in damages for the engine and an amount
(unspecified) for “the loss of profits to the business because of the loss of the engine.”
[117] In the plaintiff’s closing submissions, Mr Ribbands said:119
The loss to Choppair is the value of the engine that it would have received on a
trade-in: €400,000.120 That may not equate to the second hand value of the
engine if it were to be sold in some other marketplace, but it is the value of the
engine to Choppair. That is the measure of its loss.
117 By this I mean any recoverable loss in accordance with the ordinary principles for the determination
of damages for breach of contract or breach of bailment.
118 This figure is the amount quoted by Safran to Pacific before allowing for the discount.
119 At [4].
120 Relying on exhibit 17, to which I shall refer in detail later. For now it suffices to say that the figure
is based on the difference between the list price for a new engine of a different sort (an Arriel 1D1) at
€696,500 and the price payable for that engine (€296,400) if it was bought as part of an upgrade to
Choppair’s helicopter and after a trade-in of the Arriel 1B engine.
-- 27 of 40 --
25
[118] Later, he contended that the engine is now beyond economic repair.121 The initial
preservation provided by “bagging and tagging”, which preserved some value in the
component parts, is now more than 5 years old and has expired. Therefore the present
value of the engine is nil.122 He went on:123
The critical question that then arises is to ask what is the loss suffered by
Choppair? The starting point for the determination of that question would be a
comparison of the value of the engine prior to its bailment to [Airwork], as
compared to its present value as a consequence of the disassembly. The proper
answer to the question as to the original value however is not simply determined
by reference to the value of the engine by way of a second hand sale. In the
circumstances of this case, it is more appropriately a consideration of the loss
sustained to Choppair as a result of the loss of the capacity to trade the engine
in.
[119] In opening Choppair’s case at the commencement of the trial, Mr Ribbands expressly
disavowed pursuing the pleaded claim for loss of use of the engine. In the face of an
objection from Airwork’s counsel to any claim for damages based on the loss of an
opportunity to obtain a greater than normal value for the engine, or a new engine for
a lower than normal price (neither of which has been pleaded), he also disavowed
making any such claim. Rather, he said, Choppair was seeking damages comprising
the value of the engine. That value, he contended, is to be determined by the value
that Choppair could have obtained by trading it in for a new engine as part of an
upgrade of a helicopter.
[120] Airwork maintains that this is not the true value of the engine, but is an un-pleaded
claim for a lost opportunity to obtain more than its true value.124 As it is un-pleaded,
the plaintiff cannot pursue it. That leaves the question of the true value of the engine.
The expert evidence was that its true value, both when it was transported to Airwork
as a complete (but in fact unserviceable) engine and in its bagged and tagged separate
components, is the same: no more than $25,000.
[121] Airwork also contends that Choppair has already recovered more than that loss
because, in settlement of its claim against Pacific, it received the engine (in its
component parts), it was paid $40,000 and Pacific forgave its own claim of $30,047.60
against Choppair for the cost of Safran bagging and tagging the engine components,
which Pacific had paid. Therefore Choppair has suffered no loss as a result of any
breach by Airwork.
Principles
[122] The basic principle for the award of damages for breach of contract is well known:
the plaintiff is entitled to be placed in the same position as if the contract had been
performed, so far as money can compensate for that position.125 That principle applies
in this case to Choppair’s claim for breach of contract.
121 This is agreed and is obvious.
122 Plaintiff’s closing outline, [27].
123 At [28].
124 On principles elicited in cases such as Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 335.
125 Robinson v Harman (1848) 1 Ex 850, 855; 154 ER 363, 365; Commonwealth v Amann Aviation Pty
Ltd (1991) 174 CLR 64, 80, 98, 116, 117, 134, 148, 161; Tabcorp Holdings Ltd v Bowen Investments
Pty Ltd (2009) 236 CLR 272, 286 [13].
-- 28 of 40 --
26
[123] The basic principle for the award of damages for conversion is usually the full market
value of the goods at the time of conversion. However, if the goods are returned to
the plaintiff, the damages would either be nominal (if returned in the same condition
as when taken) or may be the difference between their market value at conversion and
at return, together with any foreseeable and not remote consequential losses. The
same is normally the case for damages in detinue.126
[124] The same is also normally the case where a bailee has breached a bailment. If the
bailed goods are returned in the same state as delivered, the plaintiff may be entitled
only to nominal damages, but if the goods are damaged then damages would usually
be determined as the difference between the value of the goods at the commencement
of the bailment and their value in the state in which they were returned. If the bailed
goods are not returned at all, then damages would normally be the market value of the
goods at the date of the bailment.
[125] Where a bailment is contractual, the measure of damages is usually the same as for
breach of contract. Professor Palmer refers to an “apparent exception” to this rule
where the bailee commits a deviation (ie, radical departure) from the terms or purpose
of the bailment, in which case the bailee is liable for all loss occurring to the goods.
He points out that that is not universally accepted.127 However, it has been accepted
in Australia for the principle that “an unauthorized departure from the terms of the
bailment renders the bailee liable for damage which results from it” and, “There is no
doubt that a bailor is entitled to sue a bailee for any damage resulting from an
unauthorised departure from the terms of bailment.”128
[126] Choppair and its counsel did not seek to distinguish the principles on which it sought
the loss that it claimed. Nor did Airwork and its counsel make any distinction between
the relevant causes of action in submissions about damages.
[127] Essentially, as I understand Choppair’s case, it is that its loss was the value of the
engine to Choppair, which had reduced (due to its disassembly) from €400,000 to nil
and it is entitled to recover that loss on any of the bases pleaded in its prayer for relief.
As I have said, it disclaims any claim based on a loss of a valuable commercial
opportunity. It is therefore sufficient for me simply to consider the issues concerning
that claim. The questions are what was the value of the engine when it was delivered
to Airwork and what is its value now. If it is now worth less than it was then worth,
because it has been disassembled, then that difference would comprise the amount of
Choppair’s loss.
Choppair’s claim: the “trade-in value”
[128] The principal issue is the basis on which the value of the engine must be determined.
[129] Choppair bases the amount of its claim on an email dated 11 December 2014 from
Mr Robinson of Safran to Mr Bradley when he was contracted to Whirlybird. The
email was in the following terms:129
Hi Denis,
126 Barker et all, The Law of Torts in Australia (Oxford University Press, 5 th ed, 2012), 140-141, 143.
127 Palmer on Bailment, [37-005], citing Lilley v Doubleday (1881) 7 QBD 510, 511.
128 McKenna & Armistead Pty Ltd v Excavations Pty Ltd (1956) 57 SR (NSW) 515, 518; The Anderson
Group Pty Ltd v Tynan Motors Pty Ltd (2006) 65 NSWLR 400, 412 [79].
129 Exhibit 17.
-- 29 of 40 --
27
We have a special price for the AS350BA to B2 Engine upgrade when carried
out through AIRBUS Helicopters.
Price list for NEW ARRIEL1D1 is 696,500 Euro
Pricing when under a AS350BA to B2 conversion is 389,700 Euro
we will then offer an additional incentive
credit for the as removed ARRIEL1B SN 4810TEC engine of -93,300 Euro
Which will mean a total cost to customer of 296,400 Euro +GST
296,400 Euro for a Brand New Arriel 1D1 engine exchange for ARRIEL1B
Core SN 4810TEC, engine will come with 2 years or 1000 hours warranty.
If your customer wishes to secure a production slot at 2014 prices he will need
to place a PO and pay deposit before end of this month. Then can just advise
when required in 2015.
Regards
Mark Robinson
[130] Choppair submits that it was seeking to have a fully serviceable helicopter. It has a
recurring need for engines and engine parts. If Mr van der Zypp had known that this
engine was beyond economic repair (because it would have to be fully stripped down
and rebuilt), then its true value to Choppair was by way of a trade in for an upgrade
to a 1D1 engine. When the above offer was made it was not pursued because the
recalendar was thought to be viable and more cost-effective. If Airwork had informed
Choppair that the engine was in such a state that it required a complete strip down,
Choppair would have opted for the trade in and upgrade that was available to it. It
would therefore have realised the value to it of the engine, which it has now lost.
[131] Airwork disputes that method of calculating any loss to Choppair. It submits that the
offer by Safran to allow a high value for the engine, as part of an upgrade and toward
the purchase of a new engine, was not its true value or its market value, but rather was
a commercial opportunity for Choppair to obtain a benefit for the engine that was
greater than its actual value. The loss of the trade-in amount offered was therefore a
loss of opportunity that is not a subject of the claim for damages. The plaintiff has
not purported to plead any of the necessary facts to give rise to a claim for a lost
valuable commercial opportunity.130 There had therefore been no opportunity for the
defendant to put such facts in issue, to obtain disclosure about them and to cross-
examine the plaintiff’s witnesses about them. Therefore the plaintiff should not be
allowed to claim damages based on such a claim. Rather, it is restricted to its pleaded
claim for the lost value of the engine.
[132] Airwork also submits that the opportunity to trade in the engine at the price offered
by Safran was also only available if Choppair were to agree to upgrade an existing
AS350BA helicopter into a B2 helicopter, with the upgrade to be performed by
Airbus. Choppair was not prepared to agree to have such an upgrade undertaken.
Therefore, the trade-in amount offered was not really available to Choppair.
[133] Finally, Airwork submits that, even if the trade-in value were considered to be the
value of the engine, a substantially similar offer was made to Choppair in November
130 As described by Jackson J in Graham & Linda Huddy Nominees Pty Ltd v Byrne [2016] QSC 221,
[50].
-- 30 of 40 --
28
2016, after the engine had been disassembled, and it remains on foot. Therefore
Choppair has not lost the opportunity.
Expert evidence of value
[134] Each party called a witness purporting to be an expert to give evidence about a number
of matters, including the value of the engine when delivered to Airwork and its value
once stripped down into its component parts. Each purported expert provided a report
to the court. The experts then conferred and produced a joint report.
[135] Choppair’s “expert” was Barry Foster, who has a commercial pilot’s licence and is a
licensed aircraft maintenance engineer. In his report,131 Mr Foster said he is not
familiar with the Arriel 1B engine, but he is familiar with “the requirements and
procedures of removing engines and components to be sent to a third party for
inspection, repair or overhaul.”
[136] Much of Mr Foster’s report was of little assistance to me. For example, he expressed
the view that:132
According to the log book entries the engine at the time it was sent to the first
defendant did not require a complete disassembly to re-calendar,
but he did not explain that opinion, nor address whether the logbook entries indicated
that the entire engine was unserviceable due to failure to maintain it and to store it in
accordance with the manual.
[137] However, he did go on to say:133
After the inspection and re-calendar of modules 1 and 5 and the fuel control unit
the engine cannot just be reassembled as all the modules have been deemed
unserviceable and an entry made into the log book to cover the unserviceability.
It now means that to bring the engine back to a serviceable state, Safran or any
other overhaul facility will have to check each part of each module as to the
serviceability state of the part.
[138] Mr Foster was asked what was:
(a) the approximate value of the engine in its disassembled condition;
(b) the approximate cost of a replacement engine in the same condition and hours
as the plaintiff’s engine when it was sent to Airwork; and
(c) the approximate value of the engine if it had undergone the maintenance
proposed by Safran in its quote.
[139] In response, he said:134
As I have not had cause to have any dealings in the Arriel 1B engine it is hard
from me to give you any pricing, however I have found an Arriel 1B engine
from a dealer in the USA with similar times for approximately USD
$380,000.00. As for the price of the engine in its present state it would be like
131 TB176-191.
132 TB180, [4.4].
133 TB181, [4.6].
134 TB181, [4.7]
-- 31 of 40 --
29
any other turbine engine core value between USD $10,000.00 and USD
$50,000.00.
[140] The evidence about the cost of a replacement engine is effectively worthless, given
that there is no information about the engine to which he refers from which a
comparison with the state of Choppair’s engine can be drawn and Mr Foster states
that he has no experience with Arriel 1B engines. I can give little weight to his opinion
about the “core value” of turbine engines without corroborating evidence, as he has
not explained what that means nor the basis of his opinion as to value. However, the
latter is the subject of an opinion of the expert called by Airwork, to which I now turn.
[141] Airwork engaged Peter MacKenzie as its expert.135 Mr MacKenzie has far more
relevant experience than Mr Foster. He is a licensed aircraft maintenance engineer
with over 45 years’ experience in the industry. He has experience in the maintenance
of Safran engines, including the Arriel 1 series and is familiar with the Arriel 1B
engine.
[142] Mr MacKenzie disagreed with Mr Foster’s unexplained conclusion that I have set out
in paragraph [136] above. He explained a number of reasons why, at the time the
engine was sent to Airwork, it was required to be completely disassembled by Safran
before it could be deemed serviceable. Those reasons not only included the time-
expired modules 1, 5 and the FCU, but also the absence of log book entries recording
any of the required maintenance of the engine since September 2012, or recording the
removal of the engine from the aircraft, or recording the proper storage of the engine.
In all those circumstances, the engine had to be inspected by Safran, which required
its complete disassembly and repair, before it could be made serviceable.136
[143] As to the value of the engine, Mr MacKenzie expressed the view137 that, as the engine
was not serviceable when Airwork received it, its value:
would be based on a core engine price and dependant on its modification status.
I would estimate a value of between $25,000.00 AUD to $70,000.00 AUD. …
I would estimate the current value of the Engine to be in the range of $20,000.00
AUD to $25,000.00 AUD.
[144] The experts made a joint report about the matters about which they agreed and
disagreed.138 In that report, Mr Foster agreed with (among others) paragraphs [46] to
[50], [125] and [127] of Mr MacKenzie’s report,139 thus apparently disavowing the
opinions on those matters that he had expressed in his report with which
Mr MacKenzie disagreed.
[145] In the joint report, Mr Foster said that he disagreed with Mr MacKenzie’s valuation
of the engine at the time it was delivered to Airwork. He did not state the basis of that
disagreement, but presumably he relied on the value he had expressed in his report at
135 Mr MacKenzie’s report, including annexures, is at TB192-331.
136 TB202-203, [46]-[50]; TB217, [125], [127].
137 TB215, [111], [113].
138 TB332.
139 See [142] above.
-- 32 of 40 --
30
[4.7]. But he agreed that the current value of the core engine is A$20,000 to
$25,000.140
[146] Messrs Foster and MacKenzie gave oral evidence together.141 Contrary to his view
expressed in the joint report, Mr Foster agreed with Mr MacKenzie’s view that,
assuming that the engine was unserviceable when it was delivered to Airwork, it was
worth $25,000 to $70,000.142
[147] Neither expert made it clear what factors would affect where in that range the engine’s
actual value fell. As best I can glean from their evidence, it depended on the likely
extent of serviceable parts, having regard to its history (as recorded in the logbooks),
and the amount of work likely to be needed to make it serviceable at the time.143
Before it was stripped down, its core value may have been higher, as only two modules
and the FCU were time expired. But once stripped down and inspected, the state of
each component and the extent of work required to render it serviceable (where it was
possible) was obvious, especially with the assistance of the Safran report. So that
shows that the core value was in fact comparatively low.144
Determination of value
[148] I do not consider that the offer by Safran to Choppair in November 2014 demonstrates
that the engine had a value of €400,000. There are a number of reasons.
[149] First, while the effect of the offer, if accepted, would have been that Choppair would
have acquired a new Arriel 1D1 engine for about €400,000 less than its retail price,
that amount was not the trade-in value attributed to the engine. The offer included a
substantial discount for the new engine. The price would be €389,700 instead of
€696,500: a discount of €306,800. Then Safran offered, in effect, a trade-in value of
€93,300 for Choppair’s Arriel 1B engine. That sum was the amount that was open
for Choppair to receive for the engine if it agreed to a helicopter upgrade by Airbus.
[150] Secondly, Mr Haffner’s evidence was that the cost for Airbus to upgrade a helicopter
under such an arrangement would have been €200,000 to €350,000.145 Mr van der
Zypp did not give evidence that Choppair was prepared, or even financially able, to
pay such an amount, particularly on top of the amount of €296,400 plus GST that it
would have to pay to Safran for the Arriel 1D1 engine (after the discount and the
trade-in). That is probably because that evidence would only be relevant to a claim
for a lost commercial opportunity, which is not pleaded and was disavowed by
Choppair’s counsel.
[151] Thirdly, after Mr van der Zypp was told that the engine had been stripped down, he
received a similar offer from Safran, although the pricing was different. That offer
was made on 7 November 2016 in an email from Mr Robinson to Mr van der Zypp:146
Hi Michael,
140 Although this was contrary to his expression of the core value as US$10,000 to $50,000: see [139]
above.
141 Commencing at T5-96.
142 T5-96:29 to T5-97:3.
143 Mr MacKenzie at T5-97:5 - T5-98:20; Mr Foster at T5-100:11-20.
144 Mr MacKenzie at T5-101:27 - T5-102:24; T1-103:37 - T5-104:25.
145 T5-25:20.
146 TB632.
-- 33 of 40 --
31
Thank you for your inquiry in regard upgrading to an ARRIEL1D1 engine.
The 2016EC special pricing for a NEW ARRIEL ID1 Engine under the upgrade
of AS350BA, trading in the removed ARRIEL1B engine is as follows:
Brand New Engine 425300 Euro
Buyback ARRIEL1B credit -101900 Euro
Total 323400 Euro
All prices in Euro and are Plus GST
FYI if you place a PO and pay 30% deposit before 15 Dec 2016 with delivery
by June 2017 then can hold 2016 pricing.
Delivery
As of today available New Production slots available for NEW ARRIEL 1D1
Engines (actual delivery date to be confirmed at time of receipt of deposit and
Purchase order) currently March 2017.
Price valid for orders received and deposit paid at time of order by 15th Dec
2016.
Production slots are subject prior sale.
We would require an upgrade contract to be signed for the special pricing.
Please contact myself or Bill if you have any questions.
Regards
Mark Robinson
[152] It can be seen that there are material differences from the offer made two years earlier.
(a) First, the list or retail price of an Arriel 1D1 engine was not stated.
(b) Secondly, the price for a “Brand New Engine” increased to €425,300.
(c) Thirdly, the amount offered for the Arriel 1B engine increased to €101,900.
(d) Fourthly, the amount payable by Choppair for the new engine increased to
€323,400.
(e) Finally, it expressly required that an upgrade contract be signed as a condition
of getting the special pricing.
[153] The offer remained contingent on Choppair agreeing to an upgrade of an AS350BA
helicopter. Although it did not expressly state that it was to be carried out by Airbus,
in my view that would be implied, given the reference to an “upgrade contract”.
[154] In my view, therefore, if the correct method of determining the loss were the trade-in
value of the engine, that value would be the amount offered as a trade-in: either
€93,300 or €101,900. The other benefits related to other parts of an overall
proposed “deal” that were unrelated to the value attributed to the Arriel 1B engine.
[155] If it were necessary, I would find that Choppair has not proved that it would ever
have accepted either offer. First, there was no evidence that it was in a financial
position to do so. Secondly, when the second offer was made in November 2016, it
chose not to take it up. That was its decision.
[156] Therefore, even if the opportunity to obtain the trade-in value for the engine were
claimed by it in this proceeding, it was not prevented from doing so by any action or
-- 34 of 40 --
32
default of Airwork. It made its own conscious decision not to take up the
opportunity, or it was unable to do so, or both.
[157] There was even a suggestion that Safran might still now be prepared to make such
an offer in order to take Arriel 1B engines out of service. However, there was no
evidence directly to that effect and, even if it were still prepared to make a similar
offer to the owner of a serviceable (or even an unserviceable but still entire) Arriel
1B engine, I am not satisfied that it would now be prepared to make such an offer
for Choppair’s engine, given what it knows about that engine and the long delay
since it stripped down and inspected it.
[158] However, I do not consider that the offers that were made, or any such offer that
might now be made is, or is reflective of, the true value of the engine. Each offer
created a commercial opportunity for Choppair to obtain a fixed price for the engine
that was not related to or reflective of its actual value. The opportunity would only
arise if Choppair were to accept an offer from Safran on the terms stated, which
would include spending a considerable additional amount on upgrading a helicopter.
[159] In my view, the value of the engine when it was delivered to Airwork was that
eventually deposed to by both experts: that is, $25,000 to $70,000. As to where,
within that range, the value of this engine actually fell, the most useful evidence can
be found in the following exchange with Mr MacKenzie:147
HIS HONOUR: Again, with regard to the value range you’ve put in paragraph
111 of your report, you said, as I understood it, that the actual value within that
range would be determined by the – effectively, the condition of the engine; is
that right? Did I understand you correctly?
MR MACKENZIE: Yes. Yes, your Honour.
HIS HONOUR: But you don’t know the condition. The whole purpose of that
range is that you don’t know the condition, and - - -
MR MACKENZIE: I don’t know the condition unless it’s – had been inspected
and the outcome of that inspection had been divulged.
HIS HONOUR: Yes, so in that case, it’s really just – if anyone were prepared
to pay between 25 and 70,000, they’re just take a pot – taking pot luck on what
they get for that money, is it?
MR MACKENZIE: It’s – it’s ju – it’s a – it’s just a range. You would have to
go and inspect and have the – to be convinced yourself that it was worth that
amount of money.
HIS HONOUR: And if it wasn’t - - -
MR MACKENZIE: You’re – you’re taking – you’re taking that on the value
and the inspection of the logbooks of the aircraft or the engine to evaluate what
value you would put – put on that as a core engine.
HIS HONOUR: So in the case of this aircraft – or this engine, if you hadn’t
inspected it but you had the logbooks available, one would expect the person
looking at buying the engine to say, well, those logbooks indicated that it hasn’t
been stored or maintained correctly, therefore I’ll offer 25,000 or less, instead
of 70,000; is that right?
MR MACKENZIE: Yes, sir.
147 T5-105:31 - T5-106:21.
-- 35 of 40 --
33
HIS HONOUR: So its true value – it was probably, at the time, less than
twenty - - -
MR MACKENZIE: Twenty-five thousand dollars or even less.
[160] Having regard particularly to the extent of unserviceability arising from the
inadequate maintenance and storage, as recorded (and not recorded) in the logbook,
which would be known to any reasonable but not over-anxious prospective buyer
and meant that it was necessary to strip down the entire engine, I find that the value
of the engine when it was delivered to Airwork was no higher the lower end of that
range, namely $25,000. I shall adopt that figure as its value at that time.
[161] Again on the basis of the experts’ evidence, I find that the engine’s value once
“bagged and tagged” was $20,000 to $25,000. It had that value when the bailment
to Airwork ended in November 2016 and when Safran returned it to Pacific soon
thereafter. Of course, some of the damage to the engine that likely reduced its value
was not caused by Airwork, Pacific or Safran, but by Choppair having packed and
transported it to Airwork in an unsuitable manner and container.148
[162] The “bagging and tagging” of the component parts involved Safran inspecting each
part and identifying whether or not it was serviceable or repairable and then
preserving it in a proper preservation bag. Mr Haffner said that serviceable parts
that are bagged and tagged are quite valuable.149 However, that process of
preservation of the parts has a life limit of five years, after which even items tagged
as serviceable must be re-inspected before they can be returned to service.150
Mr MacKenzie was not aware of that requirement.151 Choppair contends that that
has rendered them now valueless.
[163] In Mr MacKenzie’s evidence he reiterated that the core value of the engine is still
now in the range of $20,000 to $25,000.152 However, he later accepted the
proposition that the value he attributed to the bagged and tagged components was on
the basis that some items were serviceable and able to be returned to service without
further inspection.153 The report, if I understand it correctly, revealed that about 33
out of over 145 parts (that is, about 23%) were deemed repairable. None was said to
be serviceable. The cost to repair items was quoted at a total of $25,880. Having
regard to all the evidence, their value after that process was completed would have
been no more than the low end of the range, namely $20,000. I find that that was
the engine’s value after bagging and tagging.
[164] In the light of that evidence and Mr MacKenzie’s explanation of the value derived
from the bagging and tagging and the Safran report,154 none of which was
contradicted by Mr Foster, I can infer that, after the expiration of the validity of the
bagging and tagging process, the value is now well below the bottom of the range
given by Mr MacKenzie. However, the evidence does not demonstrate how much
less that value is. I infer that some parts would still have value. But, given the
148 The damage caused in transport was identified in exhibit 15. The indicated prices for the necessary
replacement of those parts totalled over $55,000.
149 T5-17:45 - T5-18:7.
150 T5-19:13-30.
151 T104:27 - T5-105:16.
152 T5-99:43 - T5-100:4; T5-100:19 - T5-101:25.
153 T5-104:21 - T5-105:23.
154 TB215, [113]-[115].
-- 36 of 40 --
34
expiry of the tags and the small number of repairable parts, it is appropriate to select
a figure well below the bottom figure in the range. Doing the best I can and having
regard in particular to the proportion of repairable parts, I shall adopt approximately
that proportion as the value of the parts now. Therefore I find that the bagged and
tagged component parts still retain a core value of $5,000.
[165] However, the component parts of the engine are worth less now than they were in
2016 because the bagging and tagging has now expired. That diminution in value
was caused by the effluxion of time while the parts were in the possession of Safran
or, for most of the time, Pacific. The diminution in value caused by the expiration
of the tags occurred in December 2021, well after Airwork’s contract with Choppair
was terminated by mutual agreement. I consider that any loss to Choppair of the
value of those parts was caused, not by Airwork’s breach of its contract and
bailment, but by Pacific refusing to return the parts to Choppair until after the five
years had expired. It is not, therefore, a loss claimable against Airwork.
[166] Consequently, I find that the engine was worth $25,000 when it was delivered to
Airwork. Once stripped down, bagged and tagged by Safran, it was worth about
$20,000. Thus, the consequence of stripping down the engine and bagging and
tagging it instead of returning it to Choppair in its pre-stripped down state was that it
diminished in value by $5,000.
The settlement with Pacific
[167] On 15 March 2022, Choppair settled its claim against Pacific and Pacific’s
counterclaim, on terms that Pacific return the engine parts to Choppair and pay
Choppair $40,000, with each party releasing the other from any other liability.155
Pacific has paid that sum and returned the engine parts to Choppair.156
[168] By the settlement deed, the mutual releases included a release by Pacific of its claim
for $30,047.60 against Choppair. As Choppair had asked Pacific to arrange for the
engine to be bagged and tagged, the cost of that process is likely to have been payable
by Choppair.157 At the least, the release of Pacific’s claim for that sum was a valuable
benefit to Choppair.
[169] Airwork submits that the value of that settlement to Choppair should be deducted from
any loss suffered by Choppair for which Airwork may be liable, as to do otherwise
would infringe the so-called rule against double recovery.
[170] In response, counsel for Choppair submitted that I should infer that the amount paid
by Pacific was a token contribution toward Choppair’s costs of conducting the
proceeding against Pacific and therefore it should not be considered a repayment of
any loss suffered by Choppair. It would only become relevant if Choppair were to
succeed in its claim against Airwork and were to be awarded the costs of the
proceeding, when the amount received from Pacific might then be taken into account
in any assessment of costs that were incurred for steps in the overall proceeding
against both defendants.158 He submitted that the return of the parts to Choppair was
155 The deed of settlement is exhibit 14.
156 Haffner, T4-109:1-10.
157 Although I do not have to reach a final conclusion on that question.
158 Transcript of the proceeding on 6 May 2022, T1-77:26 to T1-78:9.
-- 37 of 40 --
35
of no value to it, as he contended that they are now worthless. I infer that he would
submit that the release of Pacific’s counterclaim was also of little or no value to
Choppair.
[171] Lord Nicholls of Birkenhead, delivering the advice of the Privy Council in 1996,
said:159
Faced with cumulative remedies a plaintiff is not required to choose. He may
have both remedies. He may pursue one remedy or the other remedy or both
remedies, just as he wishes. It is a matter for him. He may obtain judgment for
both remedies and enforce both judgments. When the remedies are against two
different people, he may sue both persons. He may do so concurrently, and
obtain judgment against both. Damages to the full value of goods which have
been converted may be awarded against two persons for successive conversions
of the same goods. Or the plaintiff may sue the two persons successively. He
may obtain judgment against one, and take steps to enforce the judgment. This
does not preclude him from then suing the other. There are limitations to this
freedom. … A third limitation is that a plaintiff cannot recover in the aggregate
from one or more defendants an amount in excess of his loss. Part satisfaction
of a judgment against one person does not operate as a bar to the plaintiff
thereafter bringing an action against another who is also liable, but it does
operate to reduce the amount recoverable in the second action. However, once
a plaintiff has fully recouped his loss, of necessity he cannot thereafter pursue
any other remedy he might have and which he might have pursued earlier.
Having recouped the whole of his loss, any further proceedings would lack a
subject matter. This principle of full satisfaction prevents double recovery.
[172] That part of his Lordship’s speech was referred to and applied by Gleeson CJ and
Callinan J in the High Court in 2001. Having referred to it, their Honours went on to
say:160
Discussion of this subject often contemplates judgment entered by a court
following a judicial assessment of damages. That will ordinarily involve a
judicial assessment of the entire extent of the plaintiff's loss or damage. Or
judgment may be entered by consent, and this may be by way of compromise.
Recoupment of the whole of a plaintiff's loss may not be the only circumstance
in which it might be unconscientious to pursue a claim against another. Subject
to those qualifications, the principles stated by his Lordship are in point. …
If there has been no judicial assessment of damages, then, … [i]f it would be
unconscientious of the plaintiff to pursue a claim against another tortfeasor, or
if the amount received pursuant to the settlement is, or ought to be regarded as,
recoupment of the whole of the plaintiff's loss or damage, then action against
another tortfeasor, whether in separate proceedings, or, where the other
tortfeasor was a party to the original proceedings, by way of continuation of
those proceedings, must fail.
[173] This is a clear equitable principle that applies to the assessment of damages, whatever
be the cause of action. Indeed, the High Court has referred to it as “the ‘universal’
159 Tang Man Sit v Capacious Investments Ltd [1996] AC 514, 522.
160 Baxter v Obacelo Pty Ltd (2001) 205 CLR 635, [40], [47]; similarly, Gummow and Hayne JJ, [57],
[64].
-- 38 of 40 --
36
rule that a plaintiff cannot recover more than he or she has lost.”161 As Gleeson CJ
and Callinan J said,162
The principles respecting ‘double satisfaction’ may be seen as a particular
application of that rule. That particular application involves the
unconscientious exercise of legal rights.
[174] In my view, Airwork’s submission is correct. Choppair sought the same relief against
both Airwork and Pacific. The value of Choppair’s settlement with Pacific, which
Choppair has received, must be deducted from its total loss and from the amount of
any damages that might otherwise be recoverable by it against Airwork. If that were
not the case, then Choppair would recover more than its overall loss.
[175] I do not accept that I should infer that the amount received was a token amount toward
Choppair’s costs of the proceeding against Pacific. The deed of settlement does not
say that. There was no evidence that that was what the parties meant by the deed.
Nor was there any evidence that Choppair applied that sum toward the costs that it
had incurred.163 But even if there were evidence to the latter effect, how Choppair
chose to apply a sum paid to it in settlement of its claim against one defendant does
not affect how the law applies the benefits of that settlement in determining whether
the plaintiff has recouped some or all of the loss that it claimed against both
defendants.
[176] Furthermore, in addition to the payment of $40,000, Choppair received the benefit of
the release of Pacific’s counterclaim and the return of the engine. Neither of those
benefits was capable of being applied to Choppair’s costs and therefore their value
must be applied against Choppair’s loss. That value is $5,000 for the engine and at
least some proportion of the amount of the counterclaim. For the reasons discussed
below, even if the cash of $40,000 were disregarded, the value of the returned engine
is the same as the amount of Choppair’s loss for which Airwork might otherwise have
been liable. It is therefore unnecessary for me to determine the actual value of the
release, although Pacific’s claim was apparently strong and therefore that value would
be a considerable proportion of Pacific’s claim and of the costs of the counterclaim
(from which Pacific also released Choppair).
Choppair’s loss
[177] Choppair sent to Airwork an engine that was worth $25,000. At the time the contract
between them was terminated, the engine (then in its bagged and tagged component
parts) was worth $20,000. Therefore, Airwork caused Choppair a loss of $5,000 in
the value of the engine. Even if I had found that the parts are now worthless,
Choppair’s loss would have been only $25,000.
[178] That loss was contributed to by Pacific. But, in settlement of Choppair’s claim against
Pacific, claiming the same loss, Choppair received cash of $40,000 and the
forgiveness of Pacific’s counterclaim. It also recovered and retains possession of the
bagged and tagged items which, I have found, have a residual value of $5,000.
161 Haines v Bendall (1991) 172 CLR 60, 63, citing Lord Reid in Parry v Cleaver [1970] AC 1, 13.
162 Baxter v Obacelo, [57].
163 Contrary to Mr Ribband’s opening and closing addresses, in which he said there was evidence to that
effect: T1-3:45-46; T1-77:34-36 (6 May 2022).
-- 39 of 40 --
37
[179] Given the amount of Choppair’s loss and the benefits it received from Pacific
(including its recovery of the bagged and tagged engine components), I find that
Choppair has recovered the loss in value of the engine caused by Airwork’s breach of
its contract and bailment. Therefore, it has now suffered no loss recoverable from
Airwork.
Conclusions
[180] Although Airwork breached its contract and the terms of the bailment of the engine
to it and, as a consequence, Choppair did originally suffer a loss of $5,000, it has
recouped that loss (and more) from Pacific.
[181] In those circumstances, Choppair is not entitled to any damages from Airwork.
[182] Consequently, I shall give judgment for Airwork.
[183] I shall hear from the parties about the costs of the proceeding.
-- 40 of 40 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2022/169