Budget Pools QLD v Queensland Building and Construction Commission [2022] QCAT 216
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Budget Pools QLD v Queensland Building and
Construction Commission [2022] QCAT 216
PARTIES: BUDGET POOLS QLD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR649-21
MATTER TYPE: General administrative review matters
DELIVERED ON: 14 June 2022
HEARING DATE: 14 June 2022
HEARD AT: Brisbane
DECISION OF: Member Olding
ORDERS: The applicant’s Application to extend or shorten a
time limit or for waiver of compliance with a
procedural requirement is refused.
The application for review is dismissed.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS –
STATUTORY INSURANCE SCHEME – where builder
applied for review of scope of works decision – where
application filed more than 28 days from notice of decision
– where 28-day time limit is not merely procedural but goes
to jurisdiction – held Tribunal has no jurisdiction to hear and
decide the application for review
Queensland Building and Construction Commission Act
1991 (Qld), s 86F(1)(c
Queensland Building and Construction Commission v
Crocker [2018] QCATA 194
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondent: Self-represented
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
-- 1 of 3 --
2
REASONS FOR DECISION
What is this case about?
[1] This matter concerns a dispute regarding a swimming pool the applicant contracted to
construct for a homeowner.
[2] The Queensland Building and Construction Commission decided to allow a claim by
the owner under the Queensland Home Warranty Scheme and served the applicant
with a notice of the decision. The applicant did not seek internal or external review of
that decision.
[3] On 17 September 2021, the Commission decided to approve a scope of works to be
undertaken in settlement of the insurance claim (“SOW decision”). The applicant
considers the cost of the works, which the Commission may seek to recover from the
applicant, to be excessive.
[4] However, although the Commission emailed the applicant a copy of SOW decision
on the same day, the applicant did not apply for a review of that decision until 17
November 2021. That is well outside the 28-day time limit for applying for review of
SOW decisions. The applicant has therefore sought an extension of time to apply for
the review.
[5] I have decided that the Tribunal does not have power to extend the time limit and that
the application for review must be dismissed. My reasons follow.
Should the time to apply for review be extended?
[6] Although there are provisions empowering this Tribunal to extend various statutory
time limits or waive procedural requirements, the Tribunal has no power to extend or
waive the 28-day time limit for applying for review of a SOW decision.
[7] This is because the Tribunal does not have jurisdiction to hear and decide an
application for review of a SOW decision if the building contractor does not apply for
review within 28 days of being served with notice of the decision.
[8] This circumstance arises out of s 86F(1)(c) of the Queensland Building and
Construction Commission Act 1991 (Qld) which provides that decisions that are not
reviewable include:
a decision about the scope of works to be undertaken under the statutory
insurance scheme to rectify or complete tribunal work if 28 days have elapsed
since the decision was served on the building contractor and the contractor has
not, within that time, applied to the tribunal for a review of the decision.
[9] It has been held that s 86F(1)(c) is not merely procedural but rather a “mandatory
substantive rule of law, and a condition of jurisdiction”.1 Accordingly, if the applicant
did not apply for review within 28 days of being served with notice of the SOW
decision, the Tribunal has no power extend the 28-day time limit and no jurisdiction
to hear and decide the application for review.
[10] The Commission sent a notice of the decision to the applicant’s email address on the
day the decision was made, 17 September 2021 - which the applicant acknowledged
1 See Queensland Building and Construction Commission v Crocker [2018] QCATA 194, [41] and the
authorities there cited.
-- 2 of 3 --
3
later that day - and also mailed a copy to the applicant. The applicant did not apply
for review until 17 November 2021. In those circumstances, there can be little doubt
that the applicant did not apply for review within 28 days of being served with notice
of the SOW decision. The applicant did not submit otherwise.
Disposition of this matter
[11] For the reasons outlined above, the Tribunal does not have power to extend the time
to apply for review of the SOW decision, nor does it have jurisdiction to hear and
decide the application for review because it was filed outside the 28-day time limit.
[12] It follows that I have no choice but to refuse the application for extension of time and
dismiss the application for review.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2022/216