Bace Investments Pty Ltd t/as Stroud Homes Brisbane North v Queensland Building Construction Commission [2022] QCAT 170
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bace Investments Pty Ltd t/as Stroud Homes Brisbane
North v Queensland Building Construction Commission
[2022] QCAT 170
PARTIES: BACE INVESTMENTS PTY LTD TRADING AS
STROUD HOMES BIRSBANE NORTH
(applicant)
V
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR316-18 and GAR319-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 28 April 2022
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Cranwell
ORDERS: The direction to rectify in respect of the driveway
is confirmed.
The direction to rectify in respect of the onsite
dispersion system is set aside, and a new decision is
substituted not to issue a direction to rectify in
respect of the onsite dispersion system.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE RECTIFICATION
OF DEFECTIVE OR INCOMPLETE BUILDING WORK
– where decision made to issue a direction to rectify to the
builder – where the builder filed an application to review the
decision – whether items of work are defective work –
whether fair to give a direction to rectify
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 86C
Queensland Building and Construction Regulation 1998
(Qld), Schedule 1
Jarvis v Queensland Building and Construction
Commission [2014] QCAT 693
Morley v Queensland Building and Construction
Commission [2017] QDC 95
-- 1 of 8 --
2
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondent: K Joyce
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] Bace Investments Pty Ltd trading as Stroud Homes Brisbane North (‘Bace’) entered
into a contract for the construction of a new residential dwelling on property owned
by David Simmonds, Julie Simmonds and Marie Jarick (‘owners’) on or about 30
March 2016.
[2] Construction on the dwelling commenced on or about 15 November 2016, and was
completed on 22 May 2017.
[3] The owners lodged a complaint with the QBCC on 24 March 2018, which is the
complaint to which these proceedings relate. The subsequent complaint made on 16
December 2018 is not the subject of these proceedings.
[4] The decision under review is a decision made by the Queensland Building and
Construction Commission (‘QBCC’) on 26 October 2018. This was a deemed
decision under s 86C(3) of the Queensland Building and Construction Commission
Act 1991 (Qld), which is taken to be the same as the original decision made on 18 July
2018. The original decision required Bace to rectify the what the QBCC considered
to be defective building works as follows:
(a) the concrete driveway has worn prematurely resulting in the exposure of
aggregate and causing an unsatisfactory appearance; and
(b) the onsite dispersion system is significantly undersized to accommodate the
volume of stormwater conveyed by the roof drainage system, resulting in
excessive stormwater overflowing from the gutter during normal showers and
is not fit for purpose.
[5] Bace seeks to have both directions to rectify set aside. I will deal with each direction
separately.
Legislative framework
[6] The power to issue a direction to rectify is contained in s 72 of the QBCC Act.
Relevantly, that decision provides:
(1) This section applies if the commission is of the opinion that—
(a) building work is defective or incomplete; …
(2) The commission may direct the person who carried out the building work to
do the following within the period stated in the direction—
(a) for building work that is defective or incomplete—rectify the building
work; …
-- 2 of 8 --
3
…
(3) In deciding whether to give the direction, the commission may take into
consideration all the circumstances it considers are reasonably relevant and, in
particular, is not limited to a consideration of the terms of the contract for
carrying out the building work (including the terms of any warranties included
in the contract).
…
(5) The commission is not required to give the direction if the commission is
satisfied that, in the circumstances, it would be unfair to the person to give the
direction.
Example for subsection (5)—
The commission might decide not to give a direction for the rectification of
building work because an owner refuses to allow a building contractor to
return to the owner’s home or because an owner’s failure to properly
maintain a home has exacerbated the extent of defective building work
carried out on the home.
[7] The issues for determination which arise were set out in Jarvis v Queensland Building
and Construction Commission [2014] QCAT 693 at [3] as follows:
(a) is the work ‘building work’?
(b) is the building work ‘defective’?
(c) is the applicant responsible for the defective building work?
(d) is it fair or reasonable in the circumstances to direct the applicant to rectify the
defective building work?
Driveway
[8] In its submissions filed on 10 August 2020, Bace conceded that the driveway is
‘building work’ as defined in Schedule 2 of the Queensland Building and
Construction Commission Act 1991 (Qld) (‘QBCC Act’).
[9] Bace also conceded that driveway is defective in that dusting has occurred.
[10] However, Bace disputes that it is responsible for the defective building work. It also
submits that it would be unfair to direct it to rectify the driveway. An assessment of
these issues requires a detailed examination of the factual circumstances relating to
the driveway.
[11] It is not in dispute that the concrete driveway was constructed in or about April 2017.
[12] Aaron O’Neill, a building supervisor employed by Bace, gave evidence that there
were communications exchanged between the owners and Bace between May 2017
and October 2017 in relation to the driveway.
[13] Mr O’Neill went on to state that Holcim sent out a technical representative to inspect
the driveway in or around October 2017. The representative noted cracks of
approximately 0.5mm concentrated around the control joints, as well as areas of
dusting. The dusting was worst around the areas where the cars had to turn or pivot
as they used the driveway.
-- 3 of 8 --
4
[14] Mr O’Neill stated that in or around March 2018, Bace offered to coat the surface of
the driveway with a chemical hardener. The owners refused that offer.
[15] Bace has relied upon the following passage from a report of NJA Consulting Pty Ltd
dated 18 April 2019:
The concrete driveway is exhibiting signs of dusting on the surface and
subsequently the appearance of the concrete is not uniform. There are many
areas where the sand and cement has been worn from the surface leaving
exposure of the larger aggregates. The initial problem with the driveway
appears related to dusting of the surface. On-going usage of the driveway has
led to a weathering of the surface and created a non-uniform appearance to the
driveway. It appears likely that the driveway has been subjected to frequent
usage since the dusting problem was first noticed.
[16] The report noted the following from the CCCA Publication on ‘Dusting of Concrete
Surfaces’:
• It is indicated that dusting is caused by the wearing surface being weak and
the matrix not properly bonding to the fine aggregates.
• It is indicated that dusting is caused by inadequate concrete specification,
the addition of water in excess of that required, premature finishing, use of
excessive water during finishing , or rainfall during placement.
[17] The report also stated:
One recommended method of repair is the application of a surface hardener
(applied to concrete at least 28 days old). This method, while possibly
rectifying the problem, would not change the visual appearance of the concrete.
[18] I make the following observations:
(a) The defect with the driveway arose during construction. The NJA Consulting
Pty Ltd report indicates that dusting is related to conditions and factors that
occurred during construction.
(b) Mr O’Neill’s evidence is that Bace and the owners communicated in relation to
the driveway as early as May 2017. I note that the driveway was constructed in
or about April 2017, and dwelling was completed on 22 May 2017. In other
words, there does not appear any meaningful period of time where the owners
were not in communication with Bace about the driveway.
(c) Bace did not offer to apply a chemical hardener until March 2018, which was
10 months after first entering into communications with the owners about the
driveway and six months after the dusting was reported by the technical
representative from Holcim in October 2017. By this time, as noted by the NJA
Consulting Pty Ltd report, applying a surface hardener would not have rectified
the existing surface deterioration.
(d) In these circumstances, I consider the owners’ refusal of Bace’s offer to apply a
chemical hardener to be reasonable.
(e) I consider the timing of the owners’ lodgement of a complaint with the QBCC
on 24 March 2018 to be reasonable. This occurred in the same month as Bace’s
offer to apply a chemical hardener was made. Up to that point, the owners may
-- 4 of 8 --
5
have entertained some hope that Bace would offer to remedy the existing
deterioration on the surface of the driveway.
(f) I also consider the owners’ continued use of the driveway to be reasonable. The
evidence before me indicates that dwelling was built on a battle axe block, and
the driveway runs for approximately 95 metres. It would be unreasonable to
expect the owners and any visitors to park on the street and traverse that distance
on foot over a period of months.
[19] In these circumstances, I find that Bace is responsible for the concrete driveway, and
that it is fair and reasonable to give Bace the direction to rectify the driveway.
[20] For completeness, I note that the ‘Rectification of Building Work Policy’ took effect
on 10 October 2014, and remains in force.
(3) Notification of defects
1. It is a policy of the Board that if a consumer is seeking the assistance of the
Queensland Building and Construction Commission (QBCC) to issue a
direction to a building contractor to rectify defective building work, the
consumer must lodge a formal complaint with the QBCC of defective building
work as soon as possible but no later than within 12 months of becoming aware
of the defects.
2. The QBCC will then consider the issuing of direction to rectify to a building
contractor:
a. for structural defective building work, within 6 years and 3 months of the
building work being completed; or
b. for non-structural defective building work, within 12 months of the
building work being completed.
[21] Bace submits that it was not open to the QBCC to issue a direction to rectify on 18
July 2018 as this was more than 12 months after the building work was completed.
[22] In my view, this submission misconstrues the policy. The first paragraph excerpted
requires the making of a complaint. The second paragraph provides that the QBCC
will then consider the issuing of a direction to rectify within particular timeframes
depending on the category of defective building work. It is tolerably clear that the
QBCC’s consideration relates to complaints made within those timeframes.
[23] Even if I am incorrect in my construction, the complaint in the present case was made
within 12 months after the building work was completed. Had the QBCC made a
decision to issue a direction to rectify within 58 days of the complaint being made,
such a direction would have been made within 12 months after the building work was
completed. In my view, the remedies available to a home owner should not be held
hostage to length of the QBCC’s deliberations on a complaint. I do not consider that
the policy precludes the issuing of a direction to rectify merely because it took the
QBCC 116 days rather than 58 days or less to make its decision.
Onsite dispersion system
[24] The parties disagree with respect to whether the onsite dispersion system is ‘building
work’.
[25] Schedule 2 of the QBCC Act defines building work relevantly to mean:
-- 5 of 8 --
6
(a) the erection or construction of a building; or
…
(c) the provision of lighting, heating, ventilation, air conditioning, water supply,
sewerage or drainage in connection with a building; or
(e) any site work (including the construction of retaining structures) related to
work of a kind referred to above; …
but does not include work of a kind excluded by regulation from the ambit of
this definition.
[26] ‘Building’ is in turn defined to include ‘any fixed structure’. The definition provides
the following examples of a fixed structure:
Examples of a fixed structure –
• a fence other than a temporary fence
• a water tank connected to the stormwater system for a building
• an in-ground swimming pool or an above-ground pool fixed to the ground
[27] It appears to me, on its face, that the onsite dispersion system, as a fixed structure, is
properly to be considered as a building. Even if the onsite dispersion system is not a
building, it would otherwise fall within ‘the provision of … drainage in connection
with a building’ for the purposes of paragraph (c) of the definition of building work.
[28] Bace submits that the onsite dispersion system is excluded from the definition of
building work by the Queensland Building and Construction Regulation 1998 (Qld).
Item 11 of Schedule 1 provides that the following types of work is not building work:
11 Work for water reticulation systems, sewerage systems or stormwater
drains
(1) Construction, extension, repair or replacement of a water reticulation
system, sewerage system or stormwater drain, other than works connecting a
particular building to a main of the system or drain.
(2) In this section –
building includes a proposed building.
[29] The submission put by Bace is that the online dispersion system is the last point of
discharge for the stormwater before being dispersed onto the ground. As such, it does
not connect the building in question to a main of the system or drain.
[30] However, what this submission overlooks is that the online dispersion system is not a
‘main … drain’. As Judge Kent QC observed in Morley v Queensland Building and
Construction Commission [2017] QDC 95 at [11]:
Item 11 may be seen as exempting from this scheme the situation where a local
authority is constructing the overall infrastructure or headworks; this is not such
a case.
[31] Accordingly, the online dispersion system is not excluded from the definition of
building work.
[32] The QBCC provided a report from BT Plumbing Service dated 12 July 2018. That
report relevantly stated:
-- 6 of 8 --
7
The rubble pit was examined to determine it’s suitability. Moreton Bay regional
council has a preferred method of installation which shows a sizing of 1m wide
by .5m deep by 1m long for every 50m2 of roof area …
The current installation is not as per the preferred method …
It is my opinion that the likely cause of the overflowing of the yard gullies and
the gutters is the design of the rubble pit not allowing enough flow through the
pit and the pipes are backing up during heavy rain.
[33] The QBCC also provided a report from Steven Noble, a senior technical internal
review officer. In his report dated 11 September 2018, Mr Noble concluded:
[E]ach pit of 0.5m3 is expected to service a 40m2-50m2 area of roof drainage
system. Given the roof drainage system exceeds 300m2 to each put, it is clear
that the onsite dispersion system is significantly undersized to accommodate the
stormwater surcharge.
…
It is determined that the onsite dispersion system provided to the South Western
elevation is significantly undersized to accommodate the volume of stormwater
conveyed by the roof drainage system, resulting in excessive stormwater
overflowing from the gutter during normal showers and is not fit for purpose.
[34] In an addendum report dated 4 January 2019, Mr Noble stated:
The reduced capacity of the outlets to the onsite drainage system prevents the
roof drainage system from conveying stormwater effectively via the down
pipes, causing the gutter to reach capacity and discharge via the overflow
provision at the top of the gutter. The roof drainage system forms part of a
system that relies upon the adequate dispersion of stormwater at the legal point
of discharge.
[35] Bace maintains that the overflowing gutters were caused by an insufficient number of
downpipes, and that the issue of overflowing gutters was not resolved until after it
installed additional downpipes.
[36] In my view, Bace’s submission misses the point. The expert evidence provided by
the QBCC all points to the onsite dispersion system as being undersized for the roof
area. Bace provided no expert evidence to indicate that the onsite dispersion system
was appropriately sized. In these circumstances, the only conclusion that I can reach
is that the onsite dispersion system was defective. I note that the definition of
‘defective’ in Schedule 2 of the QBCC Act includes work that is ‘faulty or
unsatisfactory’. The undersized onsite dispersion system was at the very least
unsatisfactory.
[37] Bace submits that it would not be fair and reasonable to order rectification, as the issue
was resolved by the installation of additional downpipes. I accept Bace’s conclusion,
but not its reasoning.
[38] The complaint relating to the onsite dispersion system was resolved by BT Plumbing
Service connecting the stormwater pipes to a previously unknown Council stormwater
pit on the neighbouring property. In a statement dated 2 April 2019, Ben Theslow
stated:
During the site inspection for the beginning the rectification works it was noted
that a council stormwater pit was close to the boundary of Mr David Simmons
-- 7 of 8 --
8
(near one of the rubble pits) and a neighbouring property. A stormwater pit is,
to my understanding, Moreton Bay Regional Council’s preferred legal point of
discharge, over a rubble pit. As connecting the stormwater to the adjoining
property’s stormwater pit instead of new rubble pits would save costs, reduce
maintenance for the home owner and provide a better outlet for the stormwater
(the stormwater will flow freely out of the two stormwater lines installed into
the stormwater pit as opposed to filling and overflowing out of a rubble pit) I
spoke and sent email correspondence with Sedgwick Building Consultants who
conferred with QBCC as to whether this was an acceptable alternative to the
original scoped works. I received approval via email to alter the scope on 5 th
November 2018 …
Works were then carried out on Mr Simmons property with two new 150mm
stormwater lines installed to the new pit and connected with the four existing
stormwater lines to the roof and site drainage.
[39] In other words, the complaint relating to the undersized onsite dispersion system was
not resolved by increasing the size of the system. Instead, the complaint was resolved
by connecting to a previously unknown Council stormwater pit. There is no evidence
before me that the existence of the Council stormwater pit was known to Bace, and it
is not the QBCC’s case that Bace should have known about the existence of the pit at
the time the online dispersion system was installed.
[40] In those circumstances, I do not consider that it is fair and reasonable to give Bace a
direction to rectify the onsite dispersion system where rectification of the onsite
dispersion system was not required.
Disposition
[41] The direction to rectify in respect of the driveway is confirmed.
[42] The direction to rectify in respect of the onsite dispersion system is set aside, and a
new decision is substituted not to issue a direction to rectify in respect of the onsite
dispersion system.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2022/170