Brisbane Timber Decks Pty Ltd v Queensland Building and Construction Commission [2022] QCAT 67
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Brisbane Timber Decks Pty Ltd v Queensland Building and
Construction Commission [2022] QCAT 67
PARTIES: BRISBANE TIMBER DECKS PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR 135-21
MATTER TYPE: General administrative review matters
DELIVERED ON: 2 March 2022
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Deane
ORDERS: The application to review a decision of the Queensland
Building and Construction Commission made 8 June
2021 filed 3 November 2021 is a separate application to
matter GAR135-21.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COMMENCING
PROCEEDINGS - GENERALLY – whether an application
to review a decision purportedly filed in earlier review
proceedings is an application to commence separate review
proceeding
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 3, s 4, s 33, s 38, s 54, s 55, s 61, s 64
Body Corporate for Alto Gladstone v Queensland Building
and Construction Commission & Anor [2020] QCATA 6
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] Brisbane Timber Decks Pty Ltd (the Contractor) carried out decking work for
certain homeowners in 2019. The homeowners complained to the Queensland
Building and Construction Commission (QBCC), which after inspecting the works
issued a direction to rectify (DTR) to the Contractor. The QBCC decided that the
Contractor did not comply with the DTR and assessed the homeowners’ claim
-- 1 of 4 --
2
against the statutory insurance scheme. As part of that process the QBCC prepared
and approved a scope of works. The Contractor sought internal review of the scope
of works decision. By decision dated 5 February 2021 the internal review decision
was taken to be the same as the decision to approve the scope of works as the
internal review had not been completed within the review period.
[2] Shortly after, by decision dated 8 February 2021, the QBCC decided to approve an
amended scope of works (the Decision). The Contractor applied to the Tribunal to
review the Decision (the Application).1 The Registrar allocated the matter number
GAR135-21 to the Application. Initial directions for the conduct of the Application
were issued on 11 June 2021.
[3] The QBCC decided to approve a further amendment to the scope of works by
decision dated 8 June 2021(the 8 June Decision).
[4] On 22 June 2021 the Contractor sent a letter to the QBCC disputing the 8 June
Decision and sent a copy to the Tribunal. The 8 June Decision set out the
Contractor’s rights to an internal review or to an external review by the Tribunal. It
clearly set out the need to complete and lodge with the Tribunal a form 23,
Application to review a decision within 28 days of receiving it.
[5] At a compulsory conference on 6 October 2021 directions were issued for:
(a) the filing of an application to review the 8 June Decision and an application
for an extension of time to file the application to review the 8 June Decision
together with submissions in support of the application for an extension of
time;2
(b) submissions in response to the application for an extension of time by the
QBCC;3
(c) the application for an extension of time to be determined and for the making of
any consequential orders in relation to consolidation of proceedings or the
sequence of proceedings.4
[6] The Contractor sought an extension of time to comply with the 6 October 2021
directions.5
[7] Prior to that extension of time application being determined, the Contractor filed in
this proceeding a further Application to review a decision seeking to review the 8
June Decision (the Second Application) and an Application to extend or shorten a
time limit or for waiver of compliance with procedural requirement (EOT
Application).6
1 Application to review a decision filed 19 February 2021 at Caloundra, received at the Brisbane
registry on 22 February 2021.
2 Direction 1 made 6 October 2021.
3 Direction 2 made 6 October 2021.
4 Direction 3 made 6 October 2021.
5 Application to extend or shorten a time limit or for waiver of compliance with procedural
requirement filed 14 October 2021.
6 Filed 3 November 2021.
-- 2 of 4 --
3
[8] Directions were issued seeking submissions as to why the Second Application
should not be deemed a separate application given the 8 June Decision was not in
existence when GAR135-21 commenced and for the issue to be determined on the
papers.7
[9] The Contractor’s submissions in response to the 16 November 2021 Directions sent
by email to the Tribunal on 7 December 2021 state:
As far as I’m concerned the pc item should be part of application GAR135-21
considering I will disagree to the work carried out by the QBCC.
[10] A similar email was sent by the Contractor on 7 December 2021 to the QBCC.8
[11] The QBCC filed submissions in response to the EOT Application and the direction
of 16 November 2021.9 The QBCC’s submissions focus upon the EOT Application.
Is the Second Application a separate application to review a decision?
[12] I find that the Second Application is a separate application and should not be part of
GAR135-21.
[13] The Contractor is self-represented. Its submissions, somewhat understandably, are
not particularly helpful or persuasive. The QBCC’s submissions focus upon its
contention that the EOT Application and therefore the Second Application ought to
be dismissed.
[14] The Appeal Tribunal has previously accepted that a separate application to review a
decision is required for each decision sought to be reviewed, with the consequence
that a separate filing fee is required to be paid.10
[15] The Tribunal’s objects include to promote the quality and consistency of tribunal
decisions11 and to achieve the Tribunal’s objects the tribunal is to ensure like cases
are treated alike.12
[16] The Contractor has not made any submissions that there are special circumstances in
this case as to why the Tribunal should not follow the Appeal Tribunal’s decision.
[17] These proceedings had been commenced well before the 8 June Decision was made
and therefore well before any rights to have it externally reviewed arose. On the
material before me there are no special circumstances. I accept the Appeal
Tribunal’s decision that a separate application to review a decision is required for
each decision sought to be reviewed.
[18] An applicant for an application must pay the prescribed fee and the Tribunal is
prohibited from taking any action on an application until the fee is paid.13 No filing
fee is noted as having been paid in respect of the Second Application, which is
7 16 November 2021.
8 QBCC submissions filed 23 December 2021, [11].
9 Filed 23 December 2021.
10 Body Corporate for Alto Gladstone v Queensland Building and Construction Commission & Anor
[2020] QCATA 6.
11 QCAT Act, s 3(c).
12 Ibid, s 4(d).
13 Ibid, s 38.
-- 3 of 4 --
4
perhaps understandable as the Contractor has purported to file it in the current
proceedings.
[19] The 6 October 2021 Directions do not contemplate that the Contractor is to file an
application for leave to amend the current proceedings to include a review of the 8
June Decision.14 The 6 October 2021 Direction 3 specifically contemplates that the
Second Application and EOT Application would be filed in a new review
proceeding and that if the EOT Application was allowed the Tribunal would make
orders in relation to consolidation or sequencing.
[20] Section 54 of the QCAT Act provides that the tribunal may direct that 2 or more
proceedings concerning the same or related facts and circumstances be consolidated
into 1 proceeding.
[21] Section 55 of the QCAT Act provides that the tribunal may direct that 2 or more
proceedings concerning the same or related facts and circumstances remain as
separate proceedings but be heard and decided together or be heard in a particular
sequence.
[22] If a separate proceeding was not to be commenced by the filing of the Second
Application, there would be no need to contemplate whether orders for consolidation
or sequencing were required.
[23] Section 33 of the QCAT Act provides that it applies if the QCAT Act or an enabling
Act, in this case the Queensland Building and Construction Commission Act 1991
(Qld), provides that a person may apply to the tribunal to deal with a matter. It sets
out the requirements for making an application including that if the application is for
the review of a reviewable decision the application must be filed in the registry
within 28 days after the applicant is notified of the decision.15 The notes to section
33 of the QCAT Act refer to the power under section 61 of the QCAT Act to extend
the period within which a person must make an application.
[24] The Second Application is a separate application to GAR135-2116 and the EOT
Application is an application pursuant to section 61 of the QCAT Act for relief from
procedural requirements in that separate application.
[25] If the Contractor wishes to pursue the Second Application and have the EOT
Application determined it must pay the prescribed fee.
14 Ibid, s 64.
15 Ibid, s 33(3), s 33(4).
16 Ibid, s 33.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2022/067