Chelbrooke Homes Pty Ltd v Queensland Building and Construction Commission [2022] QCAT 83
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Chelbrooke Homes Pty Ltd v Queensland Building and
Construction Commission [2022] QCAT 83
PARTIES: CHELBROOKE HOMES PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR024-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 24 February 2022
HEARING DATE: 11 September 2019
HEARD AT: Brisbane
DECISION OF: Member Gunn
ORDERS: 1. The decision of the Queensland Building and
Construction Commission to issue Direction to
Rectify No 0251530 is varied as follows:
a. Item 1 of the Direction to Rectify No 0251530
made 18 December 2017, ie the minor
cracking in the concrete path is not defective
and does not require rectification, is
confirmed.
b. Items 2, 3 and 4 of the Direction to Rectify No
0251530 made 18 December 2017, ie Item 2
the fall away of the slab, Item 3 the
inconsistent colour and texture of the slab
and Item 4 the lack of articulation/isolation of
penetrations, are set aside as these Items are
not defects and do not require rectification.
CATCHWORDS: BUILDING DISPUTE – DIRECTIONS TO RECTIFY –
where direction was made that licensee rectify defective
building work pursuant to s 72 of the Queensland
Building and Construction Commission Act 1991 (Qld) –
where directions to rectify are set aside.
Building Act 1975 (Qld), s 5(1)(b)
Queensland Building and Construction Commission Act
-- 1 of 9 --
2
1991 (Qld), s 71J, s 72(1), s 72(3), s 72(5)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 19, s 20, s 24
Holtman v Sampson [1985] 2 Qd R 472
Jackson and Evans v Queensland Building and
Construction Commission [2016] QCAT 434
Jespersen v Queensland Building and Construction
Commission [2017] QCAT 459
Kitchen Plus (Nerang) Pty Ltd v Queensland Building
and Construction Commission [2014] QCAT 084
Landscaping Qld Pty Ltd v Queensland Building and
Construction Commission [2020] QCAT 130
Pappas v Queensland Building Services Authority [2002]
QDC 290
Peter Whalley Homes Pty Ltd v Queensland Building and
Construction Commission [2020] QCAT 454
Q M Properties Pty Ltd v Belscorp Pty Ltd [2019] QCA
138
APPEARANCES &
REPRESENTATION:
Applicant: Self represented
Respondent: D McNulty
REASONS FOR DECISION
Background
[1] On 28 April 2015, Mr and Mrs James (“the property owners”) entered into a
contract with the Applicant for the construction of a new single storey home in
Brisbane (“the property”).
[2] Construction of the home commenced on 23 July 2015.
[3] On 26 February 2016, the property owners contacted the Applicant via phone call to
relay their concerns regarding cracking in the concrete paving that had just been
poured. The Applicant requested the concrete supplier, Nucon Concrete, to conduct
an inspection of the works and provide their findings.
[4] On 16 March 2016, the property owners again raised the issue of the cracking in the
concrete driveway and paths during the Practical Completion Inspection. However,
this was not deemed to be a defect and was not noted on the Defects Document.
[5] On 22 March 2016, a Form 21 – Final Inspection Certificate was signed by the
building certifier. The property owners accepted handover of the home on 1 April
2016 without the cracking being noted as a defect.
-- 2 of 9 --
3
[6] On 5 December 2016, a Residential and Commercial Construction Work Complaint
Form (“the original complaint”) was received by the Queensland Building and
Construction Commission (“the Commission”) from the property owners. This
complaint comprised of 1 item being described as concreting cracking from the day
it was poured. This was first noticed by the property owners on 25 February 2015.
[7] On 21 February 2017, an inspection of the property was conducted by Mr Robert
Murphy on behalf of the Commission. From this, the first Inspection Report dated
21 February 2017 was produced. The report found that the dwelling did not comply
with the Building Code of Australia – Volume 2, Australian Standard 3727 – Guide
to Residential Pavements. This was because of:
a) a lack of articulation between the concrete and slab penetrations resulting in
undue stress and cracking;
b) insufficient fall away from the dwelling which could result in surface water
affecting building elements; and
c) inconsistent colour and texture of the exposed aggregate surface, presenting an
unacceptable finish.
[8] On 14 March 2017, the Commission notified the Applicant of their decision (“the
original decision”) to request rectification by the Applicant of these defects. The
property owners informed the Commission on the 11 April 2017 that they had not
heard from the Applicant within 28 days.
[9] As a result, on 20 April 2017, the Commission issued Direction to Rectify and/or
Complete No. 0101949 to the Applicant in relation to these defects.
[10] On 17 May 2017, the Commission received an application for internal review of this
decision from the Applicant. Internal Review Officer, Leean Tyler, conducted the
review. In reaching her decision, Ms Tyler relied on the inspection report produced
by Senior Technical Review Officer, Mr Steve Noble.
[11] Ms Tyler informed the Applicant of her internal review decision on 18 December
2017. Her decision, based on the findings of Mr Noble’s report, was that:
a) There were minor and infrequent cracks of up to 1mm in size in the concrete
paths. This fell within the tolerance allowed by the Australian Standard 3727.
She did not direct the Applicant to undertake any rectification.
b) The fall ratio of the path was marginal at less than 25mm and was near level in
some areas. This was not in compliance with the National Construction Code
2015 Volume 2, Part 3.1.2.3. She directed that the Applicant rectify this item.
c) The exposed concrete to the rear of the dwelling lacked uniformity and was
distinctly dissimilar to adjoining areas. The Standards and Tolerances Guide
provides that paving finish is defective if it is inconsistent in appearance
within 12 months of completion. She directed that the Applicant rectify this
item.
-- 3 of 9 --
4
d) There had been no isolation/articulation installed to the stormwater drainage
systems that penetrated the slab. There were shrinkage cracks observed around
the perimeter of this pit. She directed that the Applicant rectify this item.
On 10 January 2018, the Applicant applied to this Tribunal for External Review of
the direction to rectify.
Evidence before the Tribunal
[12] The Applicant relies on an expert report produced by Eric Fox of EFC Consulting
Engineers dated 15 March 2018. They also rely on a supplementary report by the
same expert dated 13 November 2018, produced in response to the Commission’s
expert report and with the benefit of a site inspection.
[13] The Commission relies on an expert report produced by Adam Buckley of NJA
Consulting dated 24 October 2018. This report was produced on the basis of a site
inspection.
[14] On 14 February 2019, the two experts attended a conclave and produced a joint
report which was also presented to the Tribunal.
The review
[15] In accordance with section 19 of the Queensland Civil and Administrative Tribunal
Act 2009 (Qld) (‘QCAT Act’) the Tribunal must exercise its review jurisdiction in
accordance with both the QCAT Act and the Queensland Building and Construction
Commission Act 1991 (Qld) (‘QBCC Act’).
[16] By section 20 of the QCAT Act, the Tribunal must make its decision by way of a
fresh hearing, with the purpose being to reach the correct and preferable decision.
[17] By section 24 of the QCAT Act, the Tribunal can make orders that upon review:
(a) The decision is confirmed; or
(b) The decision is set aside and substituted for the Tribunal’s own decision; or
(c) The decision is set aside and the matter returned to the Commission to
reconsider the decision with directions the Tribunal considers appropriate.
[18] In deciding upon this review, the Tribunal operates within the same legislative
regime as the Commission did, being Part 6 Division 2 of the QBCC Act.
[19] In accordance with section 72 of the QBCC Act, the Commission is empowered to
issue directions to rectify work it views as defective or incomplete. Nothing in this
section requires a request made pursuant to section 71J to result in an order for
rectification of defective work.
[20] Defective, in relation to building work, is defined in Schedule 2 of the QBCC Act as
including faulty or unsatisfactory works.
[21] Section 72(3) of the QBCC Act requires that the Commission take into consideration
all circumstances it considers reasonably relevant when deciding whether to give a
direction.
-- 4 of 9 --
5
[22] Section 72(5) of the QBCC Act provides that the Commission is not required to give
a direction to rectify if it is satisfied that, in the circumstances, it would be unfair to
the person subject to the order.
The alleged defects
Cracking in the slab – Item 1
[23] The Commission decided in both its original decision and upon internal review not
to issue a direction to rectify the cracks that had appeared in the concrete paths. The
cracks were small and fell within the 1.5mm permitted in the Australian Standard
3727. This part of the decision was not in dispute between the parties. This was the
sole original complaint to the Commission by the property owners.
[24] I confirm the Commission’s decision not to order rectification in relation to this
category being item 1 – the cracking in the slab.
[25] This was not the end of the matter for the Applicant builder. The Commission raised
three further matters as a result of their officers’ attendance at the property in
relation to the investigation of the cracks complained of in the slab. It is of note that
these further matters were not initially complained of by the property owners.
Fall away of the slab from the house – Item 2
[26] The Commission submitted that the construction of the slab at the rear of the house
departed from the engineering plan, the site plan, and a number of industry
standards. On these bases, they alleged that the fall away of the slab was defective.
[27] At the hearing, it was common ground between the two experts,1 that the departure
from the engineer’s plan was necessary due to the later inclusion of a retaining wall,
1.8m from the residence. The Tribunal heard that strict compliance with the original
specification, once the retaining wall was added, would have resulted in a slab that
was unattractive and less serviceable2 and importantly, very difficult to traverse.3 Mr
Fox also noted that the slab now had to drain away from the retaining wall as well as
the house, otherwise the wall would be weakened.
[28] It was submitted by the respondent that Mr Buckley said that this was reasonably
defective building work4 the departure from building standards rendered the work
defective. The installation did not comply with Australian Standard 2870 or the
National Construction Code which both require 50mm falls in the first metre.5 There
is also non-compliance with CSIRO publication BTF18-2011, which requires 1:60
falls away from the building6.
[29] These standards are relevant in determining what constitutes a defect. In the QBCC
Rectification of Building Work Policy, defective building work is said to include
1 Mr Fox for the Applicant builder and Mr Buckley for the Respondent Commission.
2 Report (supplementary) of Mr Eric Fox dated 13 November 2018, p 10.
3 Ibid p 14.
4 Report of Mr Buckley dated 24 October 2018, p 15.
5 Building Code of Australia - Volume 2, Part 3.1.2.3 – Site Preparation; Australian Standards -
AS2870-2011 – Clause 5.2.1. cited by Mr Buckley, pp 6, 8.
6 Report of Mr Buckley dated 24 October 2018, p 15.
-- 5 of 9 --
6
work that does not comply with the Australian standards or the National
Construction Code.7
[30] However, as testified by Mr Fox, for the Applicant, the Building Code of Australia
is a performance-based code. It is possible to meet the performance requirements
without following the Deemed-to-Satisfy provisions of the code.8
[31] In this instance, the relevant requirement would be that the slab as built, conveys
water to an appropriate outfall and avoids surface water damaging the building.9 The
evidence presented from both experts suggests that the slab does drain, albeit slowly
but effectively, when tested with a garden hose. I note that the greater the volume of
water, the faster the slab will drain.
[32] It was agreed between the experts that if there was a sealant over the joint as per the
engineer’s design the amount of water able to infiltrate beside the foundations would
be negligible.10
[33] Mr Fox also noted that long term ponding would leave a dirty residue that would be
visible after it has dried. He did not see any residue during his inspection, supporting
the notion that any ponding had been temporary. 11 I infer that the drainage
performance of the slab is satisfactory, and thus not defective.
[34] For these reasons, I find that the slab as constructed has met the performance
requirements in regard to drainage. I therefore do not believe the fall away from the
house constitutes a defect. I set aside the order for rectification of this item.
Inconsistent colour and texture ie variability of finish of slab – Item 3
[35] The Commission submitted that variability in the distribution of exposed aggregate
in the apron slab was a defect requiring rectification. Evidence of variability of
exposure, of the aggregate contained in the concrete of the slab was given by the
experts. I understand that the aggregate is exposed when the cement between pieces
of aggregate in the concrete of the slab is partially washed away to expose the
aggregate contained within.
[36] On this issue, the experts agreed that the surface was indeed variable. What was not
agreed upon as between the experts, was whether this finish was of a standard which
would be reasonably expected a competent contractor.
[37] Mr Fox gave evidence that the variability in distribution of exposed aggregate was
above average. 12 However, the slabs in question were relatively small, being located
between the house and retaining wall. In his view, this makes it more difficult to
control slab finishing, and greater variability is not unexpected13. In this instance, a
7 Queensland Building and Construction Commission, Rectification of Building Work Policy (20 June
2014) s 5 cited by Mr Buckley at p 15.
8 Building Act 1975 (Qld) s 5(4)(b).
9 Building Code of Australia – Volume 2, Part 2.2.1 – Drainage Performance Standards.
10 Joint Expert Report (Messrs Buckley and Fox) dated 14 February 2019, p 2.
11 Report (supplementary) of Mr Eric Fox dated 13 November 2018, p 14 and reiterated at the Hearing
by Mr Fox.
12 Ibid p 11.
13 Ibid p 14.
-- 6 of 9 --
7
competent contractor may have had difficulties producing an even surface.
Therefore, he did not believe rectification is required.14
[38] Mr Buckley characterised the variation as excessive. He did not agree that the finish
is of a standard that would be expected by a reasonably competent contractor15. In
support of this view, he provided to the Tribunal a selection of images of Mount
Cotton driveways obtained through Google Street View. These showed a relatively
consistent level of aggregate exposure. He also provided images of an adjacent
section of pavement at the property, which had been constructed at a later date by a
different contractor, which also had a uniform appearance. Mr Buckley concluded
that this slab is of insufficient standard and requires rectification.16
[39] It is well established that, where experts differ, the Tribunal must apply its own logic
and common sense. In the case of Holtman v Sampson17 the Queensland Court of
Appeal held:
The primary duty of a Tribunal is to find ultimate facts, and so far as is
reasonably possible to do so, to look not merely to the expertise of the expert
witnesses, but to examine the substance of the opinion expressed; and in doing so,
the Tribunal may not accept the opinion of an expert witness, and in cases where
the experts differ, the Tribunal will apply logic and common sense to the best of
its ability in deciding which view is to be preferred or which parts of the evidence
are to be accepted.18
[40] This common-sense approach has since been upheld in a number of more recent
decisions.19
[41] I therefore take the view that the evidence regarding neighbouring driveways is not
particularly helpful to the Tribunal. These images depict wide driveways with plenty
of space around them. This contrasts with the apron slab in question which is located
in a confined space at the back of the property. I prefer the evidence of Mr Fox in
this respect that the amount of variability is not a defect and thus does not require
rectification.
[42] I am not persuaded on the evidence before me that the finish as completed represents
defective work. In circumstances where the experts disagreed, I had to rely on the
photographs provided by the parties, and evidence given. While there was some
variance, it is not so variable as to support a finding of defective work.
[43] However, even if I were to find that the slab was defective, I am not required to give
a direction to rectify if I am satisfied that, in the circumstances, it would be unfair to
the person to give the direction.20
14 Joint Expert Report (Messrs Buckley and Fox) dated 14 February 2019, p 2.
15 Ibid p 2.
16 Ibid p 2.
17 [1985] 2 Qd R 472.
18 Ibid p 474, cited in Peter Whalley Homes Pty Ltd v Queensland Building and Construction
Commission [2020] QCAT 454, [103].
19 Q M Properties Pty Ltd v Belscorp Pty Ltd [2019] QCA 138, [154]; Pappas v Queensland Building
Services Authority [2002] QDC 290 cited in Peter Whalley Homes Pty Ltd v Queensland Building
and Construction Commission [2020] QCAT 454, [104].
20 Queensland Building and Construction Commission Act 1991 (Qld) s 72(5).
-- 7 of 9 --
8
[44] It is true that one of the reasons that the Commission issues rectification orders is to
uphold industry standards.21 Nevertheless, these standards cannot overshadow the
need for proper deliberation of all factors by the Tribunal, including the question of
unfairness.22 Were this the case, the unfairness discretion would never have been
included in the QBCC Act.23
[45] In order to assess unfairness, the Tribunal must take into consideration all
circumstances it believes are reasonably relevant.24 The fact that I do not specifically
refer to a consideration in this decision does not mean that I have not had regard to
it.
[46] The experts agreed that the only feasible method of rectification would be the
removal and replacement of the slab. They also noted that the slab may need to be
constructed in stages to achieve the necessary standard of finish, which would only
increase the cost of rectification.25
[47] In similar matters, the Tribunal has refused to order the reconstruction of a large area
of slab to correct minor flaws, as the expense is unfair to the builder.26 The same
consideration applies here. I infer that it would also cause significant disruption to
the property owners. No evidence was adduced that the property owners sought the
rectification of the finish of the slab.
[48] I have also considered the nature of the material in question. The exposure of
aggregate by removing some of the cement, carries with it the risk of heterogenous
or different sized, coloured and shaped aggregate being used, and different amounts
of aggregate being exposed. In this circumstance, it is very possible that rectification
of part of the slab will still result in a variation as between the existing slab and any
newly rectified part.
[49] I also consider that exposed aggregate slabs do by their nature change in colour as
they weather and age. Dirt accretes, mould grows, and pavements discolour. I note
that traffic over the exposed aggregate by humans, animals and vehicles will all be
part of the continual, temporal erosion of the amount of cement. Such is the nature
of an exposed aggregate path or driveway.
[50] I consider that exposed aggregate slabs serve practical as well as aesthetic purposes.
They serve to reduce slippage on the slab surface or to conceal dirt or other marks.
The slab as constructed still adequately serves these purposes, which also weighs
against a rectification order.
[51] I also note that this issue was not the subject of the complaint by the property
owners. While this does not preclude the making of an order for rectification, it is
perhaps indicative that the inconsistency does not indicate a defect as such and a
need to rectify. There is also an element of unfairness in the Applicant not having
been giving notice of the alleged variability being a defect earlier.
21 Peter Whalley Homes Pty Ltd v Queensland Building and Construction Commission [2020] QCAT
454, [109].
22 Jackson and Evans v Queensland Building and Construction Commission [2016] QCAT 434, [49].
23 Kitchen Plus (Nerang) Pty Ltd v Queensland Building and Construction Commission [2014] QCAT
084, [24].
24 Queensland Building and Construction Commission Act 1991 (Qld) s 72(3).
25 Joint Expert Report (Messrs Buckley and Fox) dated 14 February 2019, p 2.
26 Jespersen v Queensland Building and Construction Commission [2017] QCAT 459, [56].
-- 8 of 9 --
9
[52] It is therefore clear to me that the uneven appearance of the finish is not a defect.
The Tribunal has previously refused to order the rectification in similar
circumstances.27 I therefore set aside the order made for rectification of the slab
finish.
Lack of articulation/Isolation –item Four
[53] In the initial report by Mr Murphy, the Commission considered the lack of isolation
between the apron slab and both the downpipes and drainage pits to be defective and
ordered rectification. Ms Tyler agreed with and upheld the making of this order to
rectify in her internal review decision.
[54] In the joint expert report, however, it was agreed that the slab penetrations were in
fact constructed in accordance with the engineer’s design. 28 Flexible subsurface
joints had in fact been inserted underneath the slab. These were not visible from the
surface and had been missed in previous inspections. As a result, the parties through
their experts’ concurrence now agree that the slab penetrations as constructed are not
defective.29
[55] Having the benefit of this expert evidence, the correct and preferable decision is to
not require rectification.
[56] I therefore set aside the Commission’s decision to order for rectification in relation
to this alleged lack of articulation being item 4.
Orders
[57] I order that the decision of the Queensland Building and Construction Commission
to issue Direction to Rectify No 0251530 is varied as follows:
a. Item 1 of the Direction to Rectify No 0251530 made 18 December 2017, ie the
minor cracking in the concrete path is not defective and does not require
rectification, is confirmed.
b. Items 2, 3 and 4 of the Direction to Rectify No 0251530 made 18 December
2017, ie Item 2 the fall away of the slab, Item 3 the inconsistent colour and
texture of the slab and Item 4 the lack of articulation/isolation of penetrations,
are set aside as these Items are not defects and do not require rectification.
27 Landscaping Qld Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 130, [43].
28 Joint Expert Report (Messrs Buckley and Fox) dated 14 February 2019, p 2.
29 Ibid, p 2.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2022/083