CJM Innotrack Pty Ltd v Liang & Wang [2022] QCAT 53
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: CJM Innotrack Pty Ltd v Liang & Wang [2022] QCAT 53
PARTIES: CJM INNOTRACT PTY LTD
(applicant)
v
YONG CONG LIANG
(respondent)
XIAOFEI WANG
(respondent)
APPLICATION NO/S: BDL304-17
MATTER TYPE: Building matters
DELIVERED ON: 15 February 2022
HEARING DATE: 10 March 2020
11 March 2020
19 October 2020
20 October 2020
21 October 2020
17 December 2020
18 December 2020
(closing submissions filed 16 June 2021, 1 October 2021,
12 November 2021 and 13 December 2021).
HEARD AT: Brisbane
DECISION OF: Member Browne
ORDERS: 1. Xiaofei Wang is removed as second respondent
from the proceedings.
2. Yong Cong Liang must pay to CJM Innotrack Pty
Ltd the sum of $243,703.13 (inclusive of GST)
within sixty (60) days from the date of this order.
THE TRIBUNAL DIRECTS THAT:
3. Any application for costs together with written
submissions in support must be filed in the
Tribunal and a copy given to the other party, by:
4:00pm on 18 March 2022.
4. Any written submissions in response must be filed
in the Tribunal and a copy given to the other party
by:
4:00pm on 8 April 2022.
-- 1 of 39 --
2
5. Unless otherwise ordered and in the absence of a
request for an oral hearing, any application for
costs will be heard and determined by the
Tribunal on the papers by written submissions
filed by the parties and without an oral hearing on
a date not before:
4:00pm on 14 April 2022.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY ON QUANTUM MERUIT – IN
GENERAL – where owners engaged builder to develop
site – where builder unlicensed during discussions to
develop site – whether there is one agreement partly oral
and written – whether the builder performed unlicensed
building work – whether builder compliant with the
Queensland Building and Construction Commission Act
1991 (Qld) – whether builder reached practical
completion – whether builder lawfully suspended the
works – whether builder entitled to recover on quantum
meruit – whether builder entitled to claim for variations
not put in writing – whether owner entitled to recover
rectification costs, other costs and liquidated damages –
whether builder entitled to claim interests on
remuneration
PROCEDURE – CIVIL PROCEEDINGS IN STATE
AND TERRITORY COURTS – PARTIES AND
REPRESENTATION – PROPOER OR NECESSARY
PARTY AND STANDING – where respondents are joint
owners of property – where land developed by applicant
builder – whether applicant builder contracted with
respondent owners – whether respondents are in
partnership – whether respondents are jointly and
severally liable – whether second respondent should be
removed as a party
Queensland Building and Construction Commission Act
1991 (Qld), s 42, s 43, s 77(1)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 42
Sustainable Planning Act 2009 (Qld), s 580(1)
Planning Act 2016 (Qld), s 164
AJ Lucas Operations Pty Ltd v Gladstone Area Water
Board and Anor [2015] QCA 287
Baulkham Hills Private Hospital Pty Ltd v GR Securities
Pty Ltd Ors (1986) 40 NSWLR 622
Bellgrove v Eldridge (1954) 90 CLR 613
Brambles Holdings v Bathurst City Council (2001) 53
NSWLR 153
Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd
-- 2 of 39 --
3
(1982) 149 CLR 600
Cannon Street Pty Ltd v Karedis [2004] QSC 104
Cascol Constructions Pty Ltd v Blanchard & Anor[2013]
QCAT 270
Chapel of Angels Pty Ltd v Hennessey Builder Pty Ltd &
Anor [2018] QDC 218
Chapel of Angels Pty Ltd v Hennessey Builder Pty Ltd &
Anor [2020] QCA 219
Cochrane v Lees [2021] QCATA 74
Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd
(Formerly Stork Food Systems Australia Pty Ltd) [2009]
QCA 75
Dart Holdings Pty Ltd v Total Concept Group Pty Ltd
and Ors [2012] QSC 158
Electricity Generation Corporation t/as Verve Energy v
Woodside Energy Ltd (2014) 251 CLR 640
Evans v Federal Commissioner of Taxation (1989) 89
ATC 4540
Fletcher Construction Australia Ltd v Lines Macfarlane
& Marshall Pty Ltd (No 2) (2002) 6 VR 1 at 29
GR Securities Pty Ltd v Baulkham Hills Private Hospital
Pty Ltd (1986) 40 NSWLR 631
Hawley Partners Pty Ltd v Commissioner of Stamp Duties
(1996) 33 ATR 430
Hopkins v Prescott 4 CB 578
Integrated Computer Services Pty Ltd v Digital
Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11
Love & Stewart v S Instone & Co (1917) 33 TLR 475
Mann v Paterson Constructions Pty Limited (2019) 267
CLR 560
Masters v Cameron (1954) 91 CLR 353
Pavey & Matthews Proprietary Limited v Paul (1987)
162 CLR 221
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty
Ltd (2015) 256 CLR 104
Robinson v Harmon [1848] ER 135
Scott & Co v Naughton (1929) 43 CLR 310
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
(2009) 236 CLR 272.
APPEARANCES &
REPRESENTATION:
Applicant: DC Kissane instructed by Chris Toogood Legal
Respondent: CH Matthews instructed by Thomson Geer Lawyers
REASONS FOR DECISION
The issues to be decided in this matter arise from the performance of building work
by the applicant associated with the development of a site owned by the respondents,
Mr Liang and Ms Wang.
-- 3 of 39 --
4
The applicant seeks payment from the respondents for the cost of works associated
with the development of the site, the balance of the contract price for the
construction of a duplex on the site and additional money claimed to be owing for
variations to the scope of works, plus interest. There are further alternative claims
made by the applicant which arise as a consequence of the respondents’ counter-
claim.
The applicant claims that it entered into two agreements with the respondents for the
work performed on the site being a wholly oral agreement and a written agreement.
Although the written agreement was signed only by Mr Liang, the applicant
contends that Mr Liang and Ms Wang are in partnership together, Mr Liang signed
the written agreement on Ms Wang’s behalf and the respondents are therefore jointly
and severally liable under the written agreement and the oral agreement.1
The respondents counter-claim for damages for breach of contract.2 The respondents
argue that there is a single agreement by reason of the verbal terms that were
reduced into writing and the applicant undertook to carry out all of the work in
contravention of s 42 of the Queensland Building and Construction Commission Act
1991 (Qld) (the Act).3 Further to that, the respondents seek an order for the return of
money paid by Mr Liang to the applicant pursuant to s 42 of the Act on the basis that
the applicant was not licensed to perform certain work.
The respondents submit that the contract is one which falls within the first or fourth
class of Masters v Cameron.4 Further, the parties entered into verbal terms in about
March 2015 with the intention to make a further contract, in substitution of the first
agreement, with additional terms.5 The respondents also apply to remove Ms Wang
as a named respondent from the proceeding.6
Following a 7-day oral hearing before this Tribunal, the parties filed over 200 pages
of written submissions on 16 June 2021, 1 October 2021, 12 November 2021 and 13
December 2021, respectively, addressing the many contested factual and legal
issues.7 The parties have also settled an agreed list of issues for determination.8
The Tribunal is assisted by expert evidence from two quantity surveyors, Jock
Barnes of GRC Quantity Surveyors for the applicant and Paul Burgess of Burgess
Mitchell Brandtman for the respondents.9
1 See further amended application for domestic building dispute filed 19 October 2018, exhibit 3.
2 See response to further amended application and counter-application filed 24 October 2018, exhibit
3.
3 Respondent submissions filed 1 October 2021, p 10.
4 (1954) 91 CLR 353, see respondent submissions filed 1 October 2021, p 10.
5 See respondent’s submissions filed 1 October 2021, p 10.
6 Application filed on 11 March 2020 and see Tribunal’s Directions dated 24 April 2020 pursuant to s
42(2) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’).
7 See Tribunal Directions dated 17 December 2020, 26 March 2021, 16 August 2021, 11 October
2021, 17 November 202 and applicant’s closing submissions filed 16 June 2021, respondent’s
closing submissions filed 1 October 2021, applicant’s submissions in reply filed 12 November 2021
and respondent’s submissions in reply filed 13 December 2021.
8 See agreed list of issues for determination by the Tribunal prepared on behalf of the parties and filed
on 15 October 2020. The parties filed a joint hearing brief marked exhibit ‘3’.
9 See joint expert report dated 19 August 2019, exhibit 3, p 1463.
-- 4 of 39 --
5
I am satisfied that the Tribunal has the power to hear and determine this matter for
the purposes of s 77(1) of the Act. It is convenient to set out below the relevant
background to this matter and some of the contested factual and legal issues.
Relevant background
Mr Liang and Ms Wang acquired a site on the Gold Coast in or about April 2014
with plans to demolish the existing property and to build a duplex.
The respondents made enquiries about developing the site with Dixon Homes who
prepared plans and a quotation for the work.
Mr Matthew Xiu, Director of the applicant company, was introduced to the
respondents through a mutual friend sometime in late 2014.
At various times in late 2014 and early 2015, Mr Xiu and Mr Liang had discussions
about developing the site.
The applicant provided services to the site between mid to late 2015, inclusive, for
the benefit of the respondents (the ‘preliminary works’). Importantly, the applicant
did not hold a building licence until 24 August 2015. The parties do not agree as to
whether the applicant performed the preliminary works as the principal contractor
for which a building licence is required, whether the preliminary works were
performed under a separate oral agreement prior to signing a written agreement; and
whether the applicant was to retain the funds for the preliminary works (‘the
retention scheme issue’).
In or about December 2015, Mr Xiu and Mr Liang signed a written HIA agreement
for the construction of the duplex.
After construction of the duplex commenced, the applicant issued progress claims to
the respondents for payment. A claim for the practical completion stage issued on 20
February 2017.
The parties fell into dispute about payment for the work and the building work
performed. Attempts to resolve the dispute failed and proceedings followed in the
Tribunal.
Was there one or two agreements for work to be performed by the applicant?
The applicant contends that there are two agreements between the applicant and the
respondents. The first being a wholly oral agreement formed in March 2015 during
discussions between Mr Xiu and Mr Liang on behalf of the respondents that was
limited to providing assistance to the respondents up to, but not including the
building approval stage.10
Further to that, the applicant asserts that there was no agreement between the parties
in late March 2015 for the applicant to build the duplex for the respondents.11 The
applicant contends that there is a written HIA contract that was executed in
December 2015 between Mr Xiu on behalf of the applicant and Mr Liang on behalf
of the respondents.
10 Applicant’s closing submissions filed16 June 2021, p 9, 11-18.
11 Applicant’s closing submissions filed16 June 2021, p 18.
-- 5 of 39 --
6
The respondents submit that there is one agreement partly oral and written that falls
within the first or fourth class of Masters v Cameron, the fourth class as discussed in
Baulkham Hills Private Hospital Pty Ltd v GR Securities Pty Ltd Ors.12
Alternatively, if there are two distinct agreements, the written agreement is said to
be unenforceable by the applicant because it was a lump sum agreement which
included building work which was both undertaken to be carried out and in fact
carried out prior to the applicant obtaining the appropriate licence.13
The relevant passages from Masters v Cameron in respect of the different class of
contract is set out below:
Where parties who have been in negotiation reach agreement upon terms of a
contractual nature and also agree that the matter of their negotiation shall be
dealt with by a formal contract, the case may belong to any of three classes. It
may be one in which the parties have reached finality in arranging all the
terms of their bargain and intend to be immediately bound to the performance
of those terms, but at the same time propose to have the terms restated in a
form which will be fuller or more precise but not different in effect. Or,
secondly, it may be a case in which the parties have completely agreed upon
all the terms of their bargain and intend no departure from or addition to that
which their agreed terms express or imply, but nevertheless have made
performance of one or more of the terms conditional upon the execution of a
formal document. Or, thirdly, the case may be one in which the intention of
the parties is not to make a concluded bargain at all, unless and until they
execute a formal contract.
In each of the first two cases there is a binding contract: in the first case a
contract binding the parties at once to perform the agreed terms whether the
contemplated formal document comes into existence or not, and to join (if
they have so agreed) in settling and executing the formal document; and in the
second case a contract binding the parties to join in bringing the formal
contract into existence and then to carry it into execution. …14
In Baulkham Hills15 a fourth class Masters v Cameron contract was discussed:
There is in reality a fourth class of case additional to the three mentioned in
Masters v Cameron, as recognised by Knox CJ, Rich J and Dixon J, in
Sinclair, Scott & Co v Naughton (1929) 43 CLR 310 at 317, namely, ‘…one in
which the parties were content to be bound immediately and exclusively by
the terms which they had agreed upon whilst expecting to make a further
contract in substitution for the first contract, containing, by consent, additional
terms”. Their Honours refer to the speech of Lord Loreburn, in Love &
Stewart v S Instone & Co (1917) 33 TLR 475 at 476, where his Lordship said
that:
‘It was quite lawful to make a bargain containing certain terms which one was
content with, dealing with what one regarded as essentials, and at the same
time to say that one would have a formal document drawn up with the full
expectation that one would by consent insert in it a number of further terms. If
that were the intention of both parties, then a bargain had been made, none the
12 (1986) 40 NSWLR 622.
13 Respondents’ submissions filed 1 October 2021, p 10.
14 Masters v Cameron, 360-361.
15 GR Securities, per McLelland J, at 628.
-- 6 of 39 --
7
less that both parties felt quite sure that the formal document could comprise
more than was contained in the preliminary bargain.’
Relevant to the issue of whether the parties intended to be bound by certain terms
upon acceptance and offer and, further to that, whether the intention of the parties
was that the written agreement replace any pre-existing contract, is the evidence of
Mr Xiu and Mr Liang.
Mr Xiu’s evidence is that he had two site meetings in March 2015 with Mr Liang. In
early March 2015, Mr Xiu says he and Mr Liang walked the site and Mr Liang
informed him that he was not happy with the Dixon Homes plans, did not have the
cash to build on site yet and intended to borrow the money to pay for the
construction.16 Mr Xiu says that he told Mr Liang that he does not have a building
licence yet, the applicant could possibly help out with some development of the site
up to but not including the building approval stage but he had to discuss this with the
other owners of the applicant company.17
Later in March 2015, Mr Xiu says he had a second site meeting with Mr Liang
during which an agreement was reached for the applicant to assist the respondents
on a limited basis.18 Mr Xiu says that Mr Liang agreed to reimburse the applicant for
its help for the associated outlays and that he (Mr Liang) would reimburse the
applicant for any outlays after he has the finance approved and the applicant would
be his preferred builder assuming that a building licence is obtained and the quote is
acceptable.19
Based on the evidence of Mr Xiu, the applicant contends that there was a binding
agreement reached between the applicant and respondents in late March 2015 on
three terms:
(a) The applicant would provide consultancy service to the respondents to assist
them with the development of the site up to but not including the building
approval stage;
(b) The respondents were to pay the applicant for its time providing that
assistance and to pay for any outlays that the applicant pays on behalf of the
respondents; and
(c) The respondent owners were obliged to pay the applicant once they obtained
their finance for the development.20
In my view, the evidence does not support a finding that there is a single agreement
partly oral and partly written with the applicant, as contended by the respondents.21
The evidence about the discussions between Mr Xiu and Mr Liang do not support a
finding that the parties intended to have terms restated in a written agreement or that
16 Applicant’s closing submissions filed16 June 2021, p 15.
17 Statement of Mr Xiu dated 29 November 2018, exhibit 3, document 10, p 652. See also applicant’s
submissions filed 16 June 2021, p 16.
18 Ibid.
19 Ibid.
20 Ibid, p 17.
21 Respondent’s submissions filed 1 October 2021, p 9. See also submissions in reply filed 13
December 2021.
-- 7 of 39 --
8
one or more of the terms discussed in early 2015 was conditional upon the execution
of written agreement or contract.
It is established law that in determining what are the terms of a contract that is said
to be partly written and partly oral, the surrounding circumstances can be looked at
to find what in substance the parties agreed.22 The conduct of the parties must be
capable of proving all of the essential elements of an express contract.23 In Brambles
Holdings Ltd v Bathurst City Council24 Heydon JA in citing McHugh JA in
Integrated Computer Services Pty Ltd25 said:
…Nevertheless, a contract may be inferred from the acts and conduct of
parties as well as or in the absence of their words….The question in this class
of case is whether the conduct of the parties, viewed in the light of the
surrounding circumstances shows a tacit understanding or agreement. The
conduct of the parties, however, must be capable of proving all the essential
elements of an express contract…’.26
I am satisfied based on the evidence before me that Mr Xiu and Mr Liang met twice
in 2015. For reasons further explained below, I prefer and accept Mr Xiu’s evidence
about what he says was discussed with Mr Liang.
I find that in March 2015, Mr Liang agreed orally to certain terms such as, amongst
other things, to pay the applicant for its time in providing assistance up to but not
including the building approval stage. The terms discussed between Mr Xiu and Mr
Liang were sufficiently clear to bind the parties.27
I accept the evidence of Mr Xiu that he told Mr Liang that he had started a building
company and did not have a building licence.28 Mr Xiu’s evidence that he told Mr
Liang that he did not have a building licence is supported by the witness Sitong Li.
Mr Li is a friend of both Mr Xiu and Mr Liang. Mr Li witnessed a conversation take
place between Mr Xiu and Mr Liang in December 2014. Mr Li’s evidence is that he
heard Mr Xiu tell Mr Liang that he had started a building company referring to them
as introducing themselves.29
I do not accept, as contended by the respondents, that Mr Li’s evidence is unhelpful
or ambiguous by reason of the answers given by him at the oral hearing.30 Mr Li was
assisted in giving his evidence at the hearing by an interpreter. During re-
examination Mr Li confirmed his evidence that he heard Mr Xiu tell Mr Liang that
he does not have a builder’s licence.31 I accept Mr Li’s evidence and find that Mr
22 Masterton Homes Pty Ltd v Palm Assets Pty Ltd (2009) 261 ALR 382 at [90], per Campbell J and
with whom the other members of the Court agreed. See applicant’s submissions filed 16 June 2021, p
13.
23 Brambles Holdings v Bathurst City Council (2001) 53 NSWLR 153 at 178 per Heydon JA referring
to Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11.
See applicant’s submissions filed 16 June 2021, p 13.
24 Ibid.
25 (1988) 5 BPR 11.
26 Brambles Holdings v Bathurst City Council (2001) 53 NSWLR 153 at 178.
27 Ibid.
28 Exhibit 3, p 652.
29 Statement of Sitong Li dated 28 May 2019, exhibit 3, p 931.
30 Respondent’s submissions filed 1 October 2021, [72]. See Transcript 19.10.2020, 1-22.
31 Transcript 19.10.2020, 1-23, L45.
-- 8 of 39 --
9
Xiu told Mr Liang in late 2014 words to the effect that he did not have a builder’s
licence.
I do not accept, as contended by the respondents, that the evidence including oral
and written communications as between the applicant and the respondents supports a
finding that the parties had an intention to create legal relations that was later put in
writing in December 2015.32
As observed by Lyons J in AJ Lucas Operations Pty Ltd v Gladstone Area Water
Board and Anor33 in citing McHugh JA in GR Securities Pty Ltd v Baulkham Hills
Private Hospital Pty Ltd34 the decisive issue in determining whether there was an
intention to be bound is whether such an intention can in fact be ‘objectively
ascertained from the terms of the document when read in light of the surrounding
circumstances’.35 In AJ Lucas Operations Lyons J went on to say that the
surrounding circumstances include the conduct of the parties as well as the
correspondence and other words used.36
The respondents rely on an exchange of communication between Mr Liang and the
applicant in late 2014 for the supply and installation of flooring and other associated
work for an unrelated property.37 The respondents say that the applicant provided
Mr Liang a quotation for the supply and installation of flooring, tiling and ducted
air-conditioning for the unrelated property.38 The respondents submit that
contemporaneous quotes for building work are consistent with a builder operating as
if they had a licence.39
I accept that Mr Xiu may have been undertaking certain work as evidenced by the
various quotations provided to Mr Liang for an unrelated property. Indeed, Mr Xiu’s
evidence given at the hearing about the relevant quotations provided by the applicant
to Mr Liang in late 2014 is that he (Mr Xiu) believed that the building work did not
require him to hold a licence.40 Mr Xiu concedes that he did not tell Mr Liang he
would be engaging trade contractors to carry out the building work.41
The evidence does not support a finding that the parties intended to be bound by
certain verbal terms settled upon between Mr Xiu and Mr Liang in meetings that
took place between them in late 2014 and 2015 and later put in writing in December
2015. There is no certainty regarding the essential elements such as, amongst other
things, contract price and scope of the works, of the alleged contract for the
construction of the duplex until December 2015 when the agreement was put in
writing.
32 Respondent’s written submissions filed 1 October 202, p 11.
33 [2015] QCA 287 at [28] citing GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd
(1986) 40 NSWLR 631 at 634 and see respondent’s written submissions filed 1 October 2021, p 11.
34 40 NSWLR 631.
35 Ibid.
36 [2015] QCA 287 at [28] citing Muir J in Cannon Street Pty Ltd v Karedis [2004] QSC 104.
37 Respondent’s written submissions filed 1 October 202, p 14.
38 Ibid. See statement of Yongcong Liang dated 28 June 2019, exhibit 3, p 1314 and p 1320.
39 Ibid.
40 Transcript 19.10.2020, 1-43, p 39 L8 to 9. See respondent’s written submissions filed 1 October 202,
p 15.
41 Transcript 19.10.2020, 1-43. See also respondent’s written submissions filed 1 October 2021, [77] to
[79] and see the applicant’s submissions filed 16 June 2021, [409 to [414].
-- 9 of 39 --
10
The evidence does not support a finding that there are contractual relations that have
retrospective effect to a date before that on which the formal contract was executed
or event concluded.42 Further to that, the evidence does not support a finding that
there is a Masters v Cameron contract in the first or fourth class in which the parties
were bound immediately before work commenced on the site such that the
development of the site should be governed solely by the provisions of the written
contract executed after the preliminary works were undertaken by the applicant.43
I find on the evidence that there are two separate agreements, an oral agreement
formed in March 2015 during discussions between Mr Xiu and Mr Liang and a
separate written agreement being a HIA contract signed by Mr Xiu and Mr Liang in
December 2015.
In relation to the oral agreement, I find the following:
(a) Mr Xiu told Mr Liang in late 2014 words to the effect that he did not have a
builder’s licence;
(b) In or about March 2015, Mr Xiu told Mr Liang that the applicant would
provide consultancy service to the respondents to assist them with the
development of the site up to but not including the building approval stage and
such costs were to be paid to the applicant by the respondents;
(c) The respondent owners were obliged to pay the applicant once they obtained
their finance for the development; and
(d) The applicant was unlicensed to perform building work.
Did the parties agree on a retention scheme?
Mr Liang’s evidence is that during a meeting with Mr Xiu in March 2015, Mr Xiu
made certain representations to him such as, amongst other things, the applicant was
able to offer an attractive retention scheme whereby the applicant builder would not
bill all or part of its initial progress claims which Mr Liang would hold as security
for the applicant’s work.44
There is evidence before me of an email exchanged between the applicant and Mr
Liang in early 2015 in relation to the work performed by the applicant on the site. It
is clear from the email that Mr Liang gave the Dixon Homes plans to the applicant
on 27 February 2015.45 The Dixon Home plans were prepared for Ms Wang in
2014.46
As discussed above, I accept Mr Xiu’s evidence that he first met with Mr Liang on
site in early 2015. As evidenced by the exchange of emails in early 2015, Mr Xiu
and Mr Liang met after Mr Liang had forwarded the Dixon Home plans to Mr Xiu.
42 Hawley Partners Pty Ltd v Commissioner of Stamp Duties (1996) 33 ATR 430 per Macrossan CJ and
McPherson JA at 434 and Byrne J at 437 and see respondent’s written submissions filed 1 October
202, p 13.
43 See respondent’s written submissions filed 1 October 202, p 13.
44 Hearing brief, exhibit 3, volume 3, para 15, p 997. See respondent’s submissions filed 1 October
2021, p 16. See also Transcript 17.12.2020, p 6-39, L45.
45 Exhibit 3, p 1013
46 Ibid, para 16 to 19, p 997.
-- 10 of 39 --
11
I accept Mr Xiu’s evidence that he did not tell Mr Liang at the first site meeting in
early 2015 that the applicant was prepared to offer an attractive retention scheme.
When questioned about the retention scheme issue at the hearing, Mr Xiu said that
he did not say that (meaning the retention scheme) to Mr Liang because he did not
know anything about the project and Mr Liang’s circumstances. Mr Xiu stated that
he and Mr Liang had only just met and they had not established a relationship of
trust.47
In my view, Mr Xiu’s evidence about the retention scheme is plausible having found
that Mr Xiu had recently received the Dixon Homes plans when he first met with Mr
Liang to discuss the project in early March 2015.
I had the opportunity to observe and listen to Mr Xiu and Mr Liang give their oral
evidence at the hearing. I found Mr Liang’s evidence about his meetings with Mr
Xiu in 2014 and 2015 was at times vague and uncertain. When giving his evidence
about the retention scheme, Mr Liang accepted that if there was such a scheme then
the terms must be put in writing. Mr Liang accepted, however, that in the present
matter the agreed terms for the alleged retention scheme were not put in writing.
Mr Liang’s evidence given at the hearing is that the retention scheme was attractive
for him and would cover the difference between the contract price and the
borrowings from the bank.48
The applicant’s submission that it is implausible that a builder would agree to the
quantum of the retention being determined by the owners is compelling.49 It is open
for me to draw the reasonable inference that had the parties agreed on a retention
scheme, Mr Liang who has commerce and accounting experience, would surely
insist upon the important terms of the retention scheme, to be put in writing. Indeed,
Mr Liang accepts that the retention scheme would cover the extra money needed for
the development. It is open for me to draw the reasonable inference that had there
been a retention scheme agreed upon, Mr Liang would surely have insisted that the
important terms be put in writing.
Further to that, when questioned at the hearing about the proposed retention scheme
issue, Mr Liang accepted that if there was such a scheme then the applicant builder
could be waiting some years after construction was completed for payment of the
retention should the respondent decide to hold the units in the duplex. Mr Liang
accepted that the scheme, as put to him is ‘extraordinary’.50 Mr Liang said:
…Yeah. That’s why I go for CJM even they [sic] don’t have experience. It’s
very attractive profile for me.51
When questioned about applicant’s quotation for work received later in 2015 and the
fact that there was no mention of a retention scheme, Mr Liang accepted that nothing
was put in writing. Further, Mr Liang accepted that he did not send an email to the
47 Transcript 19.10.202, p 41.
48 Transcript 17.12.2020, p 36.
49 Applicant’s submissions filed 16 June 2021, p 25.
50 Transcript 17.12.20, p 6-38, L 26 to 33.
51 Transcript 17.12.20, p 6-38, L 26 to 33.
-- 11 of 39 --
12
applicant about the retention scheme. Mr Liang’s evidence is that he trusted the
applicant.52 Mr Liang also said that the retention scheme is for his benefit.53
There is no objective evidence before me as to the existence of the retention scheme.
Relevantly, there is no mention of the retention scheme in a letter sent on 18 April
2017 by the respondents’ solicitors to the applicant builder outlining purported
breaches of the agreement.54
On balance, I prefer Mr Xiu’s evidence about his discussions with Mr Liang
including discussions about the retention scheme. I am not satisfied that the
applicant agreed to a retention scheme with Mr Liang. Indeed, Mr Liang concedes
that the pleaded retention scheme would contravene s 16 of the Building and
Construction Industry Payments Act 2004 (Qld), as it applied at the relevant time, if
the retention could be withheld after the proposed duplexes were sold.55
I accept Mr Xiu’s evidence that at the second site meeting with Mr Liang in March
2015 they talked about the project and Mr Xiu had at that stage recently received
and reviewed the drawings or plans for the development of the site. I accept Mr
Xiu’s evidence that during the second site meeting Mr Liang told Mr Xiu that he
was not in a good financial situation and wanted the applicant to provide preliminary
funds. When questioned about the conversation between him and Mr Liang, Mr Xiu
said that the conversations were in Mandarin but they would use English for some
technical terms to communicate with each other.
It is open for me to prefer Mr Xiu’s evidence about his discussions with Mr Liang in
responding to the assertion made by the respondents that there was an agreed
retention scheme.
I find that there was no retention scheme agreed between Mr Xiu on behalf of the
applicant and Mr Liang.
The preliminary works and payment of fees - the oral agreement
The respondents identify 13 items of preliminary works performed by the applicant.
Mr Liang more generally describes the 13 items of preliminary works as being
essential to obtain all necessary approvals and to prepare the site for construction of
the new dwelling.56 The 13 items of preliminary works include the building
approval; development approval and fees (or council approved fees); local council
sewage application; local council lands and vegetation fee; town planning and
drafting; 3D graphic perspective; demolition of existing house and any demolition
approval fees; gully pit relocation; engineering fees; soil testing and footing design;
surveyors fees; home owners warranty; and water meter fee.57
52 Ibid, p 44.
53 Ibid.
54 Hearing brief, exhibit 3, document 19(z), p 1211 and see applicant’s submissions filed 16 June 2021,
p 27.
55 See respondent’s written submissions filed 1 October 2021, p 17.
56 Statement of evidence of Mr Liang, exhibit 3, volume 3, para 20, p 997.
57 Ibid.
-- 12 of 39 --
13
Mr Xiu accepts that he had some part in co-ordinating the preliminary works and
that he was involved in relaying information from the respondents regarding the
design though to the town planner and to the architect, John McDonald.58
Mr Xiu also accepts that he discussed some of the items of preliminary work with
Mr Liang during their two site meetings such as, town planning and drafting,
development approval application and fees, demolition of the existing premises,
surveyors fees, the soil testing and engineering footing design, engineering fees and
the building approval.59
I accept Mr Xiu’s evidence that other items such as 3D graphic perspective, the
homeowner’s warranty, the council sewage application (not operational works
approval), the local council land and vegetation fee were discussed with Mr Liang at
a later meeting in 2015.60 Relevantly, Mr Xiu says and I accept that Ms Wang
arranged to get the quotation for the 3D graphic perspective and he did not know
about it until she emailed him in September 2015.61 On balance, I am satisfied that
these items also fall within what was to be the preliminary works performed by the
applicant pursuant to the oral agreement. This seems plausible given that, as
submitted by the respondents, the home warranty must be paid prior to the
demolition works being undertaken.62
I do not accept the applicant’s contention that it was mainly responsible for paying
the invoices.63 As discussed above, Mr Xiu accepted during cross-examination at the
hearing that he had some part in coordinating the relevant works such as relaying
information through to the town planner and the architect.64
The evidence about what role the applicant played with respect to the preliminary
works is important because any person who carries out or undertakes to carry out
building work must hold a contractor’s licence of the appropriate class.65 Relevantly,
s 42 of the Act, provides that it is unlawful to carry out unlicensed building work. If
a person contravenes s 42 of the Act they are precluded from any entitlement to
monetary or other consideration for carrying out building work subject to statutory
ability to claim reasonable remuneration for the work under subsection (4).
It is settled law that s 42 of the Act is aimed at unlicensed performance of building
work and prohibits the formation of the contract itself.66 The result is to make the
contract unenforceable.67 Section 42(3) of the Act prohibits recovery by the builder
on a quantum meruit basis for the unlicensed work.68 The limitations as to the
58 Transcript of hearing 19.10.20, p1-51, L8 and transcript dated 20 October 2020, p 2-58, LL8 to 2-60,
L 15. See applicant’s submissions filed 16 June 2021, p 18.
59 Hearing brief, exhibit 3, volume 2, doc 12, para 11(c) and (d), p 857. Applicant’s submissions filed
16 June 2021, p 24.
60 Ibid. Applicant’s submissions filed 16 June 2021, p 25.
61 Ibid, para 11(e).
62 Respondents submissions filed 1 October 2021, p 16.
63 Applicant’s closing submissions filed 16 June 2021, p 18.
64 Ibid and see transcript 19.10.20, p 1-51, L8 and see Transcript 20.10.20, p 2-58, L 8 to 2-60, L 15.
65 See the Queensland Building and Constructions Commission Act 1991 (Qld).
66 Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196, [3] and [6].
67 Ibid.
68 Chapel of Angels Pty Ltd v Hennessey Builder Pty Ltd & Anor [2018] QDC 218 upheld on appeal
before the Court of Appeal, see Chapel of Angels Pty Ltd v Hennessey Builder Pty Ltd & Anor
[2020] QCA 219.
-- 13 of 39 --
14
amount which can be claimed by the builder under s 42(4) applies to the building
work for which the contractor did not have the appropriate licence.69
I do not accept, as submitted by the respondents, that the applicant has contravened s
42 of the Act and triggered the preclusion in s 42(3) by entering into a contract when
unlicensed and has carried out building work under a lump sum written contract
which includes the unlicensed work.70
As discussed above, there are two agreements, an oral agreement for the preliminary
works and a written agreement for the construction of the duplex. I prefer Mr Xiu’s
evidence that he told Mr Liang that the applicant would provide consultancy service
to the respondents to assist them with the development of the site and such costs
were to be paid back to the applicant. Further to that, as discussed above, Mr Xiu
told Mr Liang that the applicant was unlicensed in late 2014 and the applicant was
unlicensed to perform building work in relation to the oral agreement.
The applicant was, however, doing more than assisting the respondents with respect
to the preliminary works. I am satisfied that the applicant carried out building work
that includes carrying out the work, directly or indirectly carrying out the work or
carrying out building work services.71
Schedule 2 of the Act provides that building work services is administration
services, advisory services, management services and supervisory services.
Administrative services includes calling and selecting tenders, arranging and
conducting on-site meetings and inspections, arranging payment of subcontractors,
arranging for certificates, including certificates from a local government to be
issued. The Act also defines management services as coordinating the scheduling of
the work by building contractors including as agent for another person. Supervisory
services includes the coordination or management of person undertaking the
supervision of work, the personal supervision of the work and any other supervision
of the building work.72
Mr Xiu’s evidence is that he was acting as the ‘middleman’ and assisting the
respondents up to the building approval stage. As discussed above, Mr Xiu
previously provided to the respondents a quotation for work on an unrelated
property and Mr Xiu said that if the quotation was accepted he would have engaged
a licensed contractor to perform the work.73
Mr Xiu accepted, when questioned at the hearing about his involvement that he
coordinated work with the demolition contractor, arranged time for the work and
paid the fees. In addition to paying the invoices for the preliminary works, the
applicant assisted in applying for the Development Application approval in July
2015. There are a number of emails from Mr Jerome Fang of Oasis Town Planning
that identify the applicant as the only contact person for the building approval. The
69 Dart Holdings Pty Ltd v Total Concept Group Pty Ltd and Ors [2012] QSC 158, [40].
70 Respondent’s submissions filed 1 October 2021, p 24 and reply fled 13 December 2021.
71 Respondent’s submissions filed 1 October 2021, p 26.
72 See Schedule 2 and definitions under the Act.
73 Applicant’s submissions filed 16 June 2021, [409].
-- 14 of 39 --
15
applicant helped with paying the costs.74 The building approval also identifies the
applicant’s name.
Further to that, Mr Xiu met with Mr Fang on site in March 2015. The applicant sent
a tax invoice received from Oasis Town Planning to the respondents in April, May
and June 2015, respectively. Importantly, Mr Xiu accepted when questioned at the
hearing that he did not confirm in any email with Oasis that he was acting in his
capacity as a consultant.75
The applicant has failed to convince me that Mr Xiu was acting, as stated by Mr Xiu
at the hearing, ‘the middleman’. The evidence supports a finding that the applicant
directly or indirectly performed unlicensed building work when it assisted the
respondents by paying invoices, coordinating the works and relaying information
that more broadly includes building work services.
I do not accept, as contended by the applicant, that the respondents knowingly
engaged the applicant to perform unlicensed building work in contravention of s 42
of the Act.76 Further to that, I do not accept as submitted by the applicant that the
respondents may be held to be pari delicto (in equal defence) with the applicant
builder so as to be outside the class of people for whose benefit a right of recovery is
made available in consequence of the operation of s 42(3) of the Act.77 As discussed
above, I accept that Mr Xiu told Mr Liang that the applicant could provide
assistance with the preliminary works. For reasons discussed below, Mr Xiu was
doing more than simply acting as the ‘middleman’ when he agreed to terms that
form part of the oral agreement including to assist Mr Liang with the preliminary
works.
I am not satisfied that the respondents knowingly engaged the applicant to perform
unlicensed building work. On balance, I accept that the respondents engaged the
applicant to assist them with the 13 items of preliminary works on the terms
discussed in early March 2015.
I reject the respondents’ claim that the applicant is required to disgorge the
respondents’ payments made to the applicant under the written agreement.78 As
discussed above, the building work was performed on terms agreed under an oral
agreement that sit outside the written agreement. Further, the applicant signed a
written contract for the construction of the duplex when it was licensed to perform
the work.
I am satisfied based on the evidence before me that the applicant performed
unlicensed building work in contravention of the Act when Mr Xiu undertook to
directly or indirectly carry out the preliminary work in March 2015.79 As discussed
74 Hearing Brief, exhibit 3, volume 3, pp 1019 to 1021 and volume 2, p 824.
75 Transcript 19.10.2020, p 47.
76 See respondent’s submissions filed 1 October 2021, p 28.
77 Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd (Formerly Stork Food Systems Australia Pty
Ltd) [2009] QCA 75 at [58] and [59]. See applicant’s submissions filed 16 June 2021, p 76 and see
respondent’s submissions filed 1 October 021, p 28.
78 Applicant’s submissions filed 16 June 2021, p 77 and respondent’s submissions filed 1 October
2021, p 26.
79 Applicant’s submissions filed 16 June 2021, [403].
-- 15 of 39 --
16
below, the applicant is entitled to recover reasonable remuneration for the impugned
building work that it carried out while it was unlicensed.
The requirement to hold a building licence and the costs of the preliminary works
I am satisfied that Mr Xiu was aware of the requirement to hold a building licence.
Mr Xiu was cross-examined at the hearing about the requirement to be licensed.
When questioned about whether he would be in breach of the law if he provided
assistance to the respondents to the building approval stage, Mr Xiu said, ‘yes’.80
Despite Mr Xiu’s evidence that he was fully aware of his obligations as director of
the applicant company to be licensed before performing building work, I am
satisfied that the applicant performed unlicensed building work. Further, I am
satisfied that the unlicensed work included coordinating the building approval for
the respondents.
I accept Mr Xiu’s evidence that he did not send the invoices for payment to the
respondents because Mr Liang wanted him (Mr Xiu) to pay the fees.
I find that the unlicensed work was performed by the applicant on the understanding
that Mr Liang would, as contended by the applicant, pay for any outlays that the
applicant had paid on behalf of the respondents and the respondents would pay the
applicant once they obtained their finance for the development.
I am satisfied, however, that Mr Xiu failed to inform Mr Liang prior to performing
the items of preliminary work that Mr Liang would be charged for the consultancy
services or preliminary works outside any agreement.
A quotation prepared by the applicant included in the written contract for the
preliminary works includes some of the preliminary work items such as demolition
costs for the existing house. Mr Xiu said that the demolition costs were included in
the lump sum contract price (the written agreement) because he had those fees so he
had to show the fees in the written contract to get them back. When asked if he was
claiming for money paid when he did not have a building licence, Mr Xiu said that
the only reason for including the fees was to get the money back. Mr Xiu accepted,
when questioned, that he charged as part of a lump sum contract price for work that
he coordinated prior to holding a licence.81 Similar evidence was given by Mr Xiu
when questioned about other items of work such as the 3D perspective work and soil
testing.
Mr Xiu’s evidence is that some of the preliminary work items were included in a
quotation (the Bill of Quantities) prepared by the applicant and sent to the
respondents on 7 December 2015 as office overheads because he wanted to ensure
the applicant was reimbursed.82 The relevant evidence given by Mr Xiu at the
hearing is now set out below83:
Question: And the quote is dated the 28 th of November 2015?
80 Transcript 19.10.2020, p 46.
81 Transcript 19.10.20, p 1-58.
82 Transcript 19.10.20, p 1-58, L 37 to 39, p 1-59, L 1-2. See Exhibit 1, p 1080 to 1097 and the
respondents submissions filed 1 October 2021, p 17.
83 Transcript 19.10.20, p 58-59.
-- 16 of 39 --
17
Mr Xiu: Yes
Question: And you’re quoted for a lump sum price of $676,888.31?
Mr Xiu: Yes
Question: And that lump sum price covered all of the items identified in the
quote from pages 1060 through to 1077
Mr Xiu: Yes
Question: Now, if we look at page 1060…would you agree with me that the
office overheads and preliminaries for demolishing the existing
house…you arranged and coordinated that before you had a
building licence?
Mr Xiu: Just as I said before, I was only doing some coordination work.
The reason I put it down there was because he hadn’t paid me
back, so I wanted to show it up there.
Question: So you were charging Mr Liang for work you had performed prior
to having a building licence?
Mr Xiu: No, I didn’t charge….I paid those fees and I had to get the money
back. That’s why I needed to show in the building contract
Mr Xiu’s evidence is that it was not until he prepared the quotation in October or
November 2015 that he decided to include those items meaning the items of work
associated with preparing the site and that this was not discussed with Mr Liang in
the March 2015 meeting.84 Notably there are a number of items of preliminary work
omitted from the applicant’s quotation provided to the respondents such as the town
planning services, fees payable to the Gold Coast Council for the development
application, real estate marketing campaign fees, engineering services provided by
Knobel Consulting and landscape design fees.85
I do not accept, the applicant’s contention that the practical effect of s 42(3) and
subsection (4) of the Act and relying on Cascol Constructions Pty Ltd v Blanchard
& Anor,86 is that any work carried out by the builder on or after it is licensed will not
be impugned under the Act such that the builder is entitled to all of its remuneration
under the contract.87
As held in Dart Holdings Pty Ltd v Total Group Pty Ltd and Ors88 the limitations as
to the amount which can be claimed, consistently with s 42(4), applies only to
building work for which the contractor did not have the appropriate class of
licence.89 In Dart McMurdo J said, the builder is entitled to be paid upon a
restitutionary basis, for the work which it lawfully performed under its licence.90
McMurdo J said that where a contract was a lump sum contract for which the
84 Transcript 20.10.20, p 2-80, L 15 to 16 and p 2-78, L 25 to 32.
85 Applicant’s closing submissions filed 16 June 2021, p 21.
86 [2013] QCAT 270.
87 Applicant’s submissions filed 16 June 2021, p 78. See also the respondents’ submissions filed 1
October 2021, p 22.
88 [2021] QSC 158.
89 Ibid, [40].
90 Ibid.
-- 17 of 39 --
18
subcontractor did not hold the appropriate class of licence the work could not be
severed from the contract, the consequence is that a court will not enforce the
contract. McMurdo J cited Hopkins v Prescott91 and said that s 42(1) affects the
contract as a whole rendering it unenforceable. Further, s 42(1) has the consequence
of precluding the enforcement of such provision or provisions of the contract which
would otherwise entitle the defendant to payment.92
In the present matter the applicant performed unlicensed building work pursuant to
verbal terms agreed with Mr Liang. The costs of the preliminary works that were
performed when the applicant was unlicensed will be caught by s 42 of the Act. This
includes those items of preliminary work included in a quotation prepared by the
applicant included in the written agreement on the basis that the applicant could get
paid.
The preliminary works performed by the applicant under the oral agreement are
caught by s 42 of the Act and are rendered unenforceable by the applicant. That said,
s 42 is not engaged here to apply to the entire written contract for the construction of
the duplex.93
The facts in the present matter can be distinguished from Chapel of Angels Pty Ltd v
Hennessey Builder Pty Ltd & Anor94 that concerned a builder who undertook to
carry out building work without the appropriate class of license in breach of s 42(1)
of the Act.
Here, the applicant was licensed to perform the work when it contracted with Mr
Liang to construct the duplex pursuant to the terms of the written contract.
I accept Mr Xiu’s evidence that he included the costs of the preliminary works in a
quotation included in the written contract and he had not discussed this with Mr
Liang. In my view, had the parties intended for there to be one agreement that is
partly oral and partly written then presumably all of the preliminary work items
would be included in the quotation and the lump sum contract price.
The applicant’s claim for expenses in relation to the oral agreement in the total
amount of $19,022.01 does not include all of the work that I have found is
unlicensed work that forms part of the oral agreement.95 I accept the applicant’s
submission that it is possible to severe the work the subject of the oral agreement
from the scope of works payable under the written contract.96 I am not satisfied,
however, that any remuneration received after the applicant obtains the appropriate
licence will not fall within the ambit of a contravention of s 42(3) of the Act because
some of the work was performed under the oral agreement as preliminary work that
was unlicensed work.
The applicant claims and I accept that even if there was no binding agreement then it
may still seek payment of expenses it has incurred for the unlicensed preliminary
work on a quantum meruit basis in accordance with the principles in Pavey &
91 4 CB 578 at 595-6.
92 Dart, [39].
93 See respondents’ reply filed 13 December 2021.
94 [2018] QDC 218.
95 Applicant’s submissions filed 16 June 2021, p 40 to 42.
96 Applicant’s reply submissions filed 11 November 2021, p 12.
-- 18 of 39 --
19
Matthews v Paul.97 Such remuneration even on a quantum meruit basis is limited by
s 42(4) of the Act because I have found that the applicant performed unlicensed
building work.
The applicant relies on Cascol Constructions Pty Ltd v Blanchard & Anor98 and
submits that any remuneration received after the applicant obtains its licence will not
fall within the ambit of a contravention of s 42(3) of the Act.
The facts in Cascol Constructions are very different to the present matter. In Cascol
Constructions representations were made to the home owners that the works would
be performed by registered builders. In Cascol the Tribunal found that after
registration as a builder the contractor was not working in breach of s 42 and any
money paid after registration by the homeowners are not moneys recoverable
pursuant to s 42(3).99 The Tribunal did, however, recognise that some payments
made by the contractor after the date of registration should be taken into account in
determining reasonable remuneration on the basis that the money was paid in
advance prior to registration.100
In the present matter, there are some invoices relatable to unlicensed work
performed with respect to the preliminary work items under the oral agreement
included in the lump sum written contract. I am not satisfied that the applicant’s
claim of $19,022.01 represents reasonable remuneration for all of the work that is
captured by the oral agreement.
The issue now is what is a reasonable remuneration for the 13 items of preliminary
work performed under the oral agreement.
I am assisted by the expert evidence of each of the quantity surveyors, Mr Burgess
and Mr Barnes. Both experts assess the work performed by the applicant up to 24
August 2015 the date the applicant obtained its building licence.
Mr Barnes relies on invoices for work up to 24 August 2015. On the other hand, Mr
Burgess relies on invoices for work up to 24 August 2015 that includes work that
would have been done before 24 August 2015 thus relying on the assumption that
invoices in the construction industry are usually submitted after the works are
complete.
The difference between the assessments is that Mr Burgess has included five
additional items of work demolition works, advertising and related costs with the
Base 3D. The applicant’s contention that the five additional costs were incurred at a
time when the applicant was licensed is rejected.101 It matters not when the invoices
were dated because the applicant agreed to assist the respondents with the 13 items
of preliminary works pursuant to the oral agreement when it was unlicensed.
I prefer and accept Mr Burgess’ assessment of the unlicensed work in the amount of
$35,584.01 (exc GST).
97 (1987) 162 CLR 221, see applicant’s submissions filed 16 June 2021, p 44.
98 [2013] QCAT 270.
99 Ibid, [43].
100 Ibid, [45].
101 Applicant’s submissions filed 16 June 2021, p 79, p 80.
-- 19 of 39 --
20
I am satisfied that Mr Burgess’ assessment includes items of work that form part of
work to be performed under the oral agreement.102 Those items relate to the
demolition works, advertising costs and related costs with the Base 3D that found
form part of the preliminary works.103
I am satisfied that the amount of $35,584.01 (exc GST) less profit margin in the
amount of $2,846.72 is reasonable remuneration for unlicensed work carried out by
the applicant
Who are the parties to the oral agreement and written contract?
In December 2015, the applicant and Mr Liang signed a HIA written agreement.104
It is uncontroversial that the respondents owned the site that was developed by the
applicant. Further to that the respondents were both the borrowers and guarantors of
the loan facility with the relevant bank to fund the construction of the duplex.105 The
objective evidence including invoices and emails exchanged between the applicant
and the respondents identify Ms Wang as the site owner.
Mr Xiu was obviously aware at the time of signing the written agreement that Ms
Wang’s name was missing. Indeed, Mr Xiu concedes that he was negligent in not
including Ms Wang as a guarantor.106 Mr Xiu’s evidence is that he filled out the
relevant details on the contract such as the price, builder details, scheduled items and
planning and building approval details.
I am satisfied that Mr Liang’s wife is not a party to either the oral agreement or
written agreement. As discussed above, Mr Xiu and Mr Liang met on site in 2015 to
discuss the preliminary works. Further to that, the contract was signed by Mr Xiu as
Director of the applicant company. Mr Xiu accepted when questioned at the hearing
about the written contract that only Mr Liang signed the deed of guarantee and only
Mr Liang’s name appears in the contract. Further to that, Mr Xiu accepted when
questioned that Mr Laing’s wife was involved before the written contract was
signed. When questioned about why he (Mr Xiu’s) did not insist that Ms Wang sign
the HIA contract, Mr Xiu said that he assumed they, meaning Mr Liang and Ms
Wang, were a couple and held joint assets.107
The applicant has failed to convince me that the respondents are in partnership and
therefore jointly and severally liable with respect to the building work performed by
the applicant.108
As discussed above, Ms Wang was involved in the project particularly in relation to
the preliminary works. The evidence in my view supports a finding that only Mr
Liang contracted with the applicant. Mr Liang’s evidence that the proceeds of sale
would go to his personal account and be used for his family’s benefit, not for a
business is in my view consistent with the objective evidence such as the written
102 Applicant’s reply submissions filed 11 November 2021, p 27.
103 See applicant’s submissions filed 16 June 2021, p 79.
104 Hearing Brief, exhibit 3, volume 2, para 35, doc 10, p 655 and see pp 722 to 792, inclusive.
105 Respondent’s submissions filed 1 October 2021, p 50.
106 Ibid, p 1-65, L 22-23.
107 Transcript 19.10.20, p 1-65.
108 Ibid.
-- 20 of 39 --
21
contract that was only signed by Mr Liang and the applicant.109 If, as contended, by
the applicant the respondents are in business there needs to be objective evidence
determined by the nature and extent of the activities carried on.110
There is no objective evidence before me of a partnership, business address or tax
returns. That said, Ms Wang was involved in the project in the early stages including
obtaining a quotation from David Wright Properties for demolition costs and
sending emails to the applicant in relation to some of the items that form part of the
preliminary works. On balance, I am satisfied that Ms Wang’s involvement in the
development of the site is as the wife of Mr Liang and in her capacity as joint owner
of the site with Mr Liang.
I do not accept, as contended by the applicant, that the respondents are jointly and
severally liable under the oral agreement nor the written contract. Mr Xiu was aware
of Ms Wang’s involvement when he signed the contract with Mr Liang. Mr Xiu
signed the contract without Ms Wang’s name as appearing in the contract.111
The applicant has failed to convince me that Mr Liang and Ms Wang are jointly and
severally liable with respect to the work performed by the applicant in developing
the site owned by the respondents. I will allow the respondents’ application to
remove Ms Wang as a named respondent to the proceeding pursuant to section 42(2)
of the QCAT Act. I am satisfied that Ms Wang is not a proper or necessary party to
the proceeding.112 I order that Ms Wang is removed as a second Respondent from
the proceeding. I will, however, for continuity in my reasons, continue to refer to the
relevant parties and their respective claims as the applicant and the respondents.
The written contract
I find that the written HIA contract entered into between the applicant and Mr Liang
is solely for the construction of the duplex that was not intended to include the
preliminary works undertaken by the applicant. Indeed, correspondence sent by Mr
Liang’s former solicitors to the applicant on 18 April 2017 makes reference to a
building contract to construct the duplex entered into in December 2015.113 In the
relevant letter the solicitors state as follows:
We are instructed that you entered into a building contract with our client on 1
December 2015 (“the contract”) to construct two units (“the works”) at [the
property].114
I find that the HIA contract is a complete contract that was executed by Mr Xiu and
Mr Liang on 15 December 2015.115
The HIA contract includes essential elements for the construction of the duplex such
as a lump sum amount, scope of works and specifications, a promise by the
applicant to undertake the work and a commitment by Mr Liang to pay the contract
109 Transcript, 19.10.20, p 50, Transcript 17.12.2020, p 6-72, L45 to 47 and p 6-73, L1 to 10.
110 See Evans v Federal Commissioner of Taxation (1989) 89 ATC 4540 at 4556. See also the
respondent’s submissions filed 1 October 2021, p 49.
111 Transcript 19.10.2020, p 1-64, L 20 to 45.
112 QCAT Act s 42 (2) (b)
113 Applicant’s closing submissions filed 16 June 2021, p 22, Hearing brief, exhibit 3, doc 19(z).
114 Ibid.
115 Applicant’s closing submissions filed 16 June 2021, p 10.
-- 21 of 39 --
22
price. Although the contract includes some of the items of work that fall within the
preliminary works to be performed under the separate oral agreement, I accept Mr
Xiu’s evidence that he included those items because he wanted to get paid. It is
established law that an incomplete agreement being no more than an agreement of
the parties to agree is unenforceable.116 I am satisfied the evidence supports a
finding that the parties agreed on essential terms such as the scope of works and
amongst other things a promise by the applicant to perform the work as to be bound
by the written agreement or contract.117
I accept Mr Xiu’s evidence that prior to the contract being signed, the applicant
provided its quotation to the respondents to build the proposed duplex on 7
December 2015 such that this was an offer to perform the works and he and Mr
Liang did not agree in March 2015 that the applicant would undertake the building
works.118
When read as a whole the wording used in the quotation supports a finding that, as
contended by the applicant, it (the quotation) was clearly an offer to perform the
work.119 The quotation states that if builders are offering different designs and
different inclusions, then the price will be different.120
Mr Xiu’s accepts when questioned at the hearing that work under the written
contract commenced at the latest by 7 March 2016 when the footing work was
inspected. I find that the applicant did not give Mr Liang notice as required under
clause 2.9 of the contract after commencement of the work.
I accept the applicant’s contention that based on Mr Liang’s evidence who asserts
that there is only one agreement partly oral and partly written that binds the parties,
the contract price is uncertain such that there was no agreement regarding how much
the contract price would be.121
A finding that the contract price is uncertain presuming there is only one agreement
as contended by Mr Liang, is consistent with the evidence given by Mr Liang who
said that he wanted a detailed quotation to be provided. Mr Liang conceded during
cross-examination that there was no contract price agreed upon with the applicant
during the March 2015 meeting and that the quotation was only necessary to match
against what had already been agreed, which he was unable to recall.122
Mr Liang’s evidence about the contract price is that the price was already decided by
a rate per square metre and he needed it to be written down in a quote because it was
a six-digit number and at the time, they did not have a computer or a pen and paper
116 Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600 at 604 per Gibbs CJ
and Murphy and Wilson JJH. See applicant’s submissions filed 16 June 2021, p 20.
117 Ibid.
118 Hearing Brief, exhibit 3, Volume 2, doc 10, p 654 and doc 10(g). See applicant’s closing
submissions filed 16 June 2021, p 19 to 21.
119 Applicant’s closing submissions filed 16 June 2021, p 20 to 21.
120 Ibid, p 21. See Hearing brief, exhibit 3, p 689, doc 10(g).
121 Ibid, p 30.
122 Transcript dated 17.10.20, p 6-44, L1-2 and p 6-49, L 20-25.
-- 22 of 39 --
23
to enable them to do the sum.123 Mr Liang could not recall a particular rate nor the
various other items that needed to be added to the figure.124
I find that the written contract is a complete agreement for the construction of the
duplex. Further to that, the obligation to pay for the work performed by the applicant
under the written contract sits outside any other obligation for Mr Liang to pay for
the unlicensed work under the oral agreement.125
Did the applicant reach practical completion for the purposes of the written
contract?
The applicant asserts that practical completion was reached on 20 February 2017
and it accrued the right to payment for the stage 6 progress claim on that date.126 The
total amount said to be owing for that stage is $101,533.20.127
Practical completion under the written contract is the day the works were completed.
Clause 1.1 of the contract requires the applicant to complete the works in accordance
with the contract and comply with all lawful requirements of any statutory or other
authority with respect to the carrying out of the works.128
I accept, as submitted by the respondents, that statutory requirements applying to the
work includes compliance with Development Approval.129 Further, the work must
comply with all relevant laws and plans and specifications for the work that form
part of the contract.
The respondents assert that practical completion was not reached because the works
had three major defects identified as follows:
(a) the sewer inspection opening was continuously flowing from the cover to
duplex 1;
(b) the stormwater inspection opening had ‘opposed open’ from previous rain
events to duplex 1; and
(c) the driveway drainage was not adequate causing dampness to the side entry
from water runoff to duplex 1.130
The respondents rely upon and I accept the evidence of Brad Neaves of Excel
Property Consultants who inspected the property on 29 March 2017 and 8 May
2017, respectively, and prepared a report in relation to the inspection.131
At the oral hearing, Mr Neaves was questioned about his experience. Mr Neaves
said that he is a carpenter by training and holds a licence grade of nominee
supervisor. He also has 9 years’ experience in supervising plumbing work.
123 Ibid, p 6-43, L30 to 23.
124 Applicant’s submissions filed 16 June 2021, p 30.
125 See applicant’s submissions in reply filed 11 November 2021, p 12.
126 Applicant’s closing submissions filed 16 June 2021, p 45.
127 Ibid.
128 See clause 35.1 of the contract for the meaning of a ‘statutory or other authority’.
129 Respondent’s submissions filed 1 October 2021, p 32 and see s 580(1) of the Sustainable Planning
Act 2009 (Qld) and s 164 of the Planning Act 2016 (Qld).
130 Respondent’s submissions filed 1 October 2021, p 33.
131 Exhibit 3, p1417 to 1461.
-- 23 of 39 --
24
I accept Mr Neaves is suitably qualified for the purposes of giving evidence about
the works he inspected and the three alleged defective items of work. Mr Neaves
confirmed his evidence during cross-examination about the items of work. In
relation to the sewer, Mr Neaves said that there was evidence of brown water.132
When questioned about the driveway drainage Mr Neaves said that driveway drain
was a foot short from the edge which caused the interior corner of the garage to be
wet.133
I accept the respondents’ submission that it ought not be necessary for Mr Neaves to
hold a plumber’s licence to identify overflowing from a sewer inspection point
which should not be overflowing.134 Mr Neaves’ evidence about what he saw during
his inspection particularly in relation to water overflowing is relevant to the issue of
defects.
Carl Hagar from Knobel Consulting (Engineers) also gave evidence about the sewer
connection and relocation of the water meter. Mr Hagar’s evidence is relevant to the
issue of whether the applicant has complied with all laws and lawful requirements
for any statutory or other authority with respect to carrying out the works and
carrying out the works in accordance with the written contract including the
Development Approval issued by the council.135
Mr Hager identified that the applicant failed to construct the sewer connection in
accordance with the council’s approved and stamped drawings.136 The respondent
contends and I accept based on Mr Hager’s evidence that the consequence of the
failure to complete the upgraded 150mm sewer connection in accordance with the
council drawings or apply and receive retrospective approval for the use of the
existing 100mm sewer connection was that the applicant could not obtain a
certificate of classification from the builder certifier and thereby could not reach
practical completion.137 Indeed Mr Liang undertook the exercise himself of
obtaining approval from council for the existing connection.138
On balance, I am satisfied that as at 20 February 2017, the works had defects and the
applicant did not comply with all relevant laws particularly in relation to the sewer
connection. Further to that, it is open for me to find on the evidence that the
applicant continued to purchase materials and carry out work at the property after
the alleged date of practical completion.
Mr Xiu conceded during cross-examination that the applicant was carrying out work
under the written contract after it had purportedly suspended the work and reached
practical completion.139 Mr Xiu accepted when questioned that James Boakes, site
132 Transcript 17.12.2020, p 6-58.
133 Transcript 17.12.2020, p 5-59.
134 Respondent’s submissions filed 1 October 2021, p 33.
135 Ibid.
136 Exhibit 3, p 1330.
137 Respondent’s submissions filed 1 October 2021, p 34.
138 See applicant’s submission in reply filed 11 November 2021, p 14. See also the respondents
submissions in reply filed 13 December 2021, p 5.
139 Transcript, 20.10.2020, p 2-21 to 2-24.
-- 24 of 39 --
25
supervisor employed by the applicant, performed work onsite after 1 March 2017
and that the work was building work under the written contract.140
There are a number of invoices dated after 20 February 2017 that evidence materials
purchased by the applicant from Bunnings and other suppliers for the purchase of
materials used on site.141 The reasonable inference to be drawn from the objective
evidence is that the applicant continued building work after the alleged date of
practical completion.
I accept the respondents’ contention that the applicant failed to achieve practical
completion on 20 February 2017. I find that the applicant continued to carry out
building work under the written contract after purporting to reach practical
completion on 20 February 2017. Further to that, I find that progress claim 6 and the
applicant’s assertion that practical completion was reached on 20 February 2017 was
premature and not issued pursuant to a contractually accrued right.142 The
applicant’s claim for the work is therefore limited to a claim on a quantum meruit
basis.
Did the builder lawfully suspend the works?
The applicant contends that the works were suspended under Clause 19.1(a) of the
written contract on 8 February 2017 when Mr Xiu handed Mr Liang the notice of
suspension.143 The applicant contends that the suspension of works arose from the
respondents’ failure to pay progress claims 1, 2 and 3.144
Mr Liang agrees that he had not paid the applicant for progress claims 1, 2 and 3 and
says that he was entitled to withhold payment in accordance with the ‘verbal terms’
that Mr Liang says he agreed upon with Mr Xiu with respect to the retention
scheme.145 Further, it is contended that the applicant could not insist on payment for
progress claims 1, 2 and 3 and the same were being retained until the applicant
obtained a certificate of classification or all disputes subject to the work were
resolved.146
Mr Liang disputes that the applicant suspended the works. The respondents submit
that Mr Xiu’s evidence that he hand delivered a notice of suspension to Mr Liang in
early February 2017 should be rejected.147
As discussed above, the respondents’ contention that there was an agreed retention
scheme is rejected. Further, I have found that there were outstanding issues in
relation to the works as at 20 February 2017, the date the applicant says it reached
practical completion.
With respect to the delivery of the notice of suspension, it matters not whether the
notice was properly delivered to Mr Liang in early February 2017. There is evidence
before me that the applicant continued to purchase materials and supplies and carry
140 Ibid.
141 See Exhibit 3, pp 459 to 461, p 465, 462, 487, 464, 466, 468.
142 See Respondent’s submissions filed 1 October 2021, p 36.
143 Applicant’s submissions filed 16 June 2021, p 60.
144 Ibid.
145 Respondent’s submission filed 1 October 2021, p 29.
146 Ibid.
147 Ibid.
-- 25 of 39 --
26
out work after the purported suspension in early February 2017. At the oral hearing,
Mr Xiu conceded that he continued to carry out work after issuing the purported
notice.148 Further to that, Mr Xiu said that he marked the progress claims 1, 2 and 3
as ‘paid’ on 30 June 2016. Mr Xiu’s evidence is that he did this because Mr Liang
told him that the bank would not release the payments unless he confirmed the
progress claims for stages 1 and 2 were paid.149
I accept Mr Xiu’s evidence that he repeatedly asked Mr Liang to pay the applicant
and he did not issue invoices for payment at the time the relevant stage was
completed because Mr Liang did not have his loan approved. Mr Xiu maintained his
evidence at the hearing that he repeatedly asked Mr Liang to pay the applicant and
he (Mr Xiu) knew that Mr Liang did not have the money to pay.
I find that the works were not lawfully suspended in February 2017. Even if the
notice was validly given by the applicant, I find that the applicant waived the
suspension by continuing to carry out work immediately after 8 February 2017.
Was there a variation to omit works by reason of the respondents’ conduct?
The applicant contends that it was not required to complete the balance of any work
under the written contract on 25 September 2018 when it issued a variation to omit
works in accordance with clause 26.3(c), 26.6 and 25 of the general conditions.150
The applicant says that Mr Liang engaged various contractors and consultants to
remedy defects on his behalf between May 2017 and January 2018, inclusive, the
effect of which was to take control of, possession of, or use of the works or part of
the works.151 Further to that, the effect of the variation document was to
retrospectively omit that part of the works that had not been carried out and
completed by the applicant as at the date that the respondents first engaged the
consultants and contractors in breach of clause 26.1152
I have found that the builder did not lawfully suspend the works and that practical
completion was not reached on 20 February 2017. Further to that, I have found that
despite the applicant’s purported suspension of works in early February 2017, the
applicant continued to complete building work.
In my view the evidence supports a finding that the applicant had an opportunity to
attend to any rectification and completion of building work until at least 15 August
2017 when Mr Liang says that he changed the locks.153 I accept the respondents’
submission that the applicant had 6 months within which to complete the work it had
not carried out.154 Indeed, the applicant had an opportunity to complete work after
receiving correspondence from the respondents’ solicitors in April 2017.155
Relevantly, on 18 April 2017 the respondents’ solicitors wrote to the applicant
identifying a number of issues in relation to the development of the site and building
148 Transcript, 20.10.2020, p 2-18, L 6.
149 Exhibit 3, p 861, [21].
150 Applicant’s submissions filed 16 June 2021, p 62.
151 Ibid.
152 Ibid.
153 Respondents’ submission filed 1 October 2021, p 36.
154 Respondents’ submission filed 1 October 2021, p 36.
155 Ibid.
-- 26 of 39 --
27
works. In the letter dated 18 April 2017 the applicant is put on notice that it is in
substantial breach of the contract and pursuant to clause 28.3 it is required to rectify
the breaches within the stipulated timeframe.156
I find that the right conferred to the applicant in clause 26.3 cannot be exercised in
circumstances where the applicant is in breach of the written contract by failing to
complete the works by the date of practical completion.
Is the applicant entitled to restitution for the completed works on a quantum
meruit basis?
It is uncontroversial that the applicant is entitled to a claim in quantum meruit for
the work carried out at the property.157 The applicant’s entitlement to recover
payment for the incomplete stages on restitution upon a claim for quantum meruit is
supported by established authority in Mann v Paterson Constructions Pty Ltd.158
Here, the respondents have had the benefit of the work performed by the applicant.
Further, they have built on the work done by the applicant including attending to
rectification of some of the works that form part of their counter-application. The
applicant is entitled to recover the fair and reasonable value of the work performed
to be determined according to all of the circumstances.159
Consistent with my earlier findings, the applicant’s quantum meruit claim in respect
of the oral agreement for the unlicensed work is limited by s 42(4) of the Act.
The respondents’ submit that the applicant is entitled to a common law quantum
meruit claim for the work carried out after 24 August 2015.160 The value of the work
assessed on a quantum meruit basis is a fair commercial rate for that work.161 The
inquiry to arrive at a ‘just sum’ in every reasonable remuneration claim is a
principled one.162 Further, the assessed amount for the quantum meruit claim should
not exceed a fair value calculated in accordance with the contract price or the
appropriate part of the contract.163
The applicant contends that the reasonable value of the works performed for the
practical completion stage is equal to the value of that completed stage under the
contract that is $101, 533.20.164 Further, the applicant contends that this valuation is
consistent with the opinions of both quantity surveyors Mr Burgess and Mr Barnes,
excluding variations.
On the other hand, the respondents assert that the applicant’s entitlement to recover
on a quantum meruit basis should be limited in circumstances where the builder did
not have a duly appointed nominee under the Act.165
156 Exhibit 3, p 1213.
157 Respondents’ submission filed 1 October 2021, p 37.
158 (2019) 267 CLR 560.
159 Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221 at 263.
160 Respondents’ submissions filed 1 October 2021, p 37.
161 Ibid, p 38.
162 Fletcher Construction Australia Ltd v Lines Macfarlane & Marshall Pty Ltd (No 2) (2002) 6 VR 1 at
29, [92].
163 Mann, at 584, [31].
164 Applicant’s submission filed 16 June 2021, p 64.
165 Ibid, p 39.
-- 27 of 39 --
28
The respondents rely on Mr Burgess assessment with some reductions. The
respondents assert that the applicant failed to appoint a nominee who holds a
contractor’s licence or nominee supervisor’s licence to carry out building work or
undertake to carry out building work under the builder’s class of licence.166 The
respondents say that the appointed nominee (Mr Peter Schrader) was not an officer
nor employee of the applicant builder.167
Put simply, the respondents seek to water down the expert quantity surveyor’s
assessment of the works that includes an amount of $6,769.00 for alleged
supervision of the project by Mr Schrader.168 Further, the respondents contend that
the applicant was required to complete the work under the written contract by 20
July 2016 and any costs for ongoing overheads after this date should not be
allowed.169
There are reductions sought by the respondents including, amongst others, no
inclusion of the builder’s margin, a reduction for a claim for wages paid to Mr
Boakes that the respondent says was reduced to $35,971.85 on the basis that the
applicant had other jobs that Mr Boakes was supervising at the relevant time. A
reduction of $15,289.25 for ongoing overheads after the date for practical
completion is claimed. There are further costs of $8,014.86 that the respondents say
Mr Burges, expert for the respondents identified as being unsubstantiated by way of
an invoice.170 Reductions are also claimed for certain out of pocket expenses and
invoices considered by both expert witnesses.
The respondents claim that the proper assessment of the work carried out (excluding
variations) on a quantum meruit basis is $619,335.35 after taking into account the
various reductions claimed.171
Both expert quantity surveyors adopt different methodologies in assessing the work
performed by the applicant. Mr Burgess did a benchmark analysis and an elemental
costs analysis and valued the works at $635,857.67 including margin and excluding
GST.172 Mr Burgess determined the actual costs incurred as $699,443.44 plus a
profit margin of 8%.173
On the other hand, Mr Barnes did a comparison between the invoices claimed by the
applicant broken down by individual trades.174 Mr Barnes valued the works at
$643,872.53 including margin and excluding GST. Mr Barnes determined the actual
costs incurred as $708,259.78 plus a profit margin of 8%.175
I prefer and accept Mr Burgess assessment of the work. At the oral hearing, Mr
Burgess explained that his methodology included taking a sample of similar projects
between 2014 to 2017, inclusive. Mr Burgess said his methodology would have been
166 Ibid.
167 Respondent’s submissions filed 1 October 2021, p 39.
168 Ibid.
169 Ibid, p 41.
170 Respondent’s submissions filed 1 October 2021, p 42.
171 Ibid, p 44.
172 Exhibit 3, Hearing Brief, volume 4, p 1399.
173 Transcript 18.12.2020, p5-69.
174 Ibid, volume 3, p 955.
175 Ibid.
-- 28 of 39 --
29
to look at the total cost and then to do a quick bench mark analysis to determine
whether those costs are reasonable or not and that analysis demonstrated that the
average cost is approximately $1,600 per square metre whereas the actual costs are
coming in at $1590 per square metre.176 When questioned about Mr Barnes’
assessment, Mr Burges said that the assessment is $1850 per square metre which is
17% higher than the actual costs. Mr Burgess said that Mr Barnes’ estimate had
some flaws because the costs are significantly higher.177
The respondent has failed to convince me that Mr Burgess’ assessment of
$635,857.67 for the licensed work should be reduced. Both Mr Barnes and Mr
Burgess agreed at the oral hearing that the actual costs incurred by the builder were
reasonable and that the contract sum specified is $676,888.30.178 In relation to the
assessed work, both experts confirmed that an amount of 8% profit margin is in
addition to the actual cost of the work assessed.179
I am not satisfied that there is any detriment to the respondents by reason of any, as
contended by the respondents, failure by the applicant to have a duly appointed
nominee under the Act. Although Mr Burgess identified a component of the
applicant’s labour costs as supervision, he also confirmed during cross-examination
that the longer the project takes, the higher the costs that relate to supervision,
management and labour costs on site. Mr Burgess’ evidence is that he assumed the
actual costs for labour or supervision would be higher because the project, as he
understood it, took longer than was originally intended.180 Mr Burgess confirmed
that when he did his independent costs assessment he specified the construction
period to be 19 weeks.181
Mr Barnes accepted when questioned at the hearing that if the building contractor
went over the 19 week period the contractor would have to pay supervisor expenses
past the date for practical completion.182
I am not satisfied that there should be a deduction for the overheads incurred after
the date of practical completion. It is noncontentious that the applicant held the
requisite licence to perform the work from 24 August 2015. I have found that the
applicant continued work after 20 February 2017, being the date the applicant says it
reached practical completion.
The respondents have failed to convince me that there should be further deductions
for Mr Boakes’ wages ($26,885.44), the missing invoices for costs claimed by the
applicant ($8,014.86), reductions for invoices attributable to defects and value of
tools ($3,954.45) and invoices issued by Mr Boakes ($18,679.53).183
Each of the items identified by the respondents clearly fall within the ambit of the
applicant’s claim for quantum meruit which is unrestrained by s 42(3) and (4) of the
Act. I have carefully considered the evidence of the expert quantity surveyors. I am
176 Transcript 18.12.2020, p 5-56.
177 Ibid, p 5-57.
178 Transcript 18.12.2020, p 5-61.
179 Ibid, p 5-68.
180 Ibid, p 5-83.
181 Ibid.
182 Ibid, p 5-85.
183 See respondent’s submissions filed 1 October 2021, p 42.
-- 29 of 39 --
30
satisfied that Mr Burgess’ assessment of the work should be allowed without
reduction. As discussed above, Mr Burgess further explained his methodology when
giving his evidence at the oral hearing. Mr Burgess assessed the work based on his
methodology to arrive at a figure that is a fair and reasonable price for the works.
I allow the amount of $635,857.67 (exc GST) for the total cost of the work
performed by the applicant builder.
To determine remuneration payable for the licensed work under the written contract,
it is necessary to deduct the profit for the remuneration I have found payable to the
applicant for the unlicensed work carried out under the oral agreement from the
reasonable costs of the work assessed by Mr Burgess. This is because I have found
that some of the unlicensed work was invoiced after the applicant obtained its
licence and Mr Xiu included items for payment that included the preliminary works
in the written contract.
As discussed above, Mr Xiu conceded that he did not discuss with Mr Liang that he
would seek payment for the preliminary works outside any agreement. Further, Mr
Xiu included some of the preliminary work items in the written contract outside any
earlier discussions with Mr Liang about who he would seek to recover payment.
I prefer and accept Mr Burgess’ assessment of remuneration for all of the work
using a methodology that looked at the total cost of the project and similar projects
built during the relevant time of construction.
Doing the best I can with the evidence before me and having preferred Mr Burgess’
methodology, the applicant’s remuneration for the licensed work should in all of the
circumstances be adjusted to ensure that it does not exceed the contract price
because some of the unlicensed work is included in Burgess’ assessment. I adopt the
applicant’s calculation of the remuneration for the licensed work now set out as
follows:184
Value of works performed (inc GST) $ 635,857.67
LESS value of unlicensed work $ 35,584.01
LESS 8% profit margin185 $ 2,846.72
Subtotal $ 597,426.94
Total (inc GST) $ 657,169.63
The amount of restitution payable to the applicant cannot exceed the written contract
price of $676,888.30. The applicant’s quantum meruit claim for the licensed work
performed under the written contract must be further reduced to ensure that when
added to the quantum payable for the unlicensed work, the total remuneration will
not exceed $676,888.30. Again I adopt the applicant’s assessment now set out as
follows:186
184 Applicant’s submissions in reply filed 11 November 2021, p 24.
185 This accounts for any profit margin that would have been applied to the works carried out by the
applicant prior to the licence registration date and is based on 8% of Mr Burgess’ value of the
unlicensed work calculated at $35,584.01.
186 Applicant’s submissions in reply filed 11 November 2021, p 24.
-- 30 of 39 --
31
Remuneration for unlicensed work (inc GST) $ 38,854.38
Adjusted figure for licensed work (inc GST) $ 657,169.63
Subtotal $ 696,024.01
Combined non-contractual claim187 (inc GST) $ 19,135.71
Based on Mr Burgess assessment, there needs to be a further reduction of
$19,135.71 resulting in a quantum meruit claim for the licensed work being
$638,033.92.188
I am satisfied and find accordingly that the amount of $638,033.92 represents
reasonable remuneration for the licensed work performed by the applicant. The
applicant is entitled to reasonable remuneration assessed at $638,033.92 (inc GST
and profit margin) less any other claims or deductions I allow.
For reasons discussed below, the respondents have a right to off-set the payments
already made under the written contract in the amount of $409,977.10. This leave a
balance of remuneration payable to the applicant under the written contract for the
works carried out by the applicant after the licence registration date of
$228,056.82.189
The applicant’s entitlement to variations under the written contract
The applicant seeks payment for the reasonable value of the work that it performed
at the request of the respondents for five variations on a quantum meruit basis.190
The expert quantity surveyors each agree as to the value of the variations now set
out below:191
(a) Sliding door to duplex 2 garage between laundry and garage valued at $470.00
(b) Remove two installed windows in the living room in duplex 1 valued at $710.00.
(c) Add a toilet to room in duplex 1 valued at $6,770.00
(d) Enlarge the toilet in duplex 2 on the first floor and add shower valued at $6,888.00
(e) Add a toilet into bathroom on the first floor of duplex 2 valued at $1,220.00
Subtotal = $16,058.00
Margin agreed at 20% = $3,211.60
Subtotal = $19,269.60
PLUS GST in the amount of $1,926.96
TOTAL = $21,196.46
187 Ibid, this is the amount combined that exceeds the contract price.
188 Ibid. This figure represents the amount of $657,169.63 less $19,135.71.
189 See applicant’s submissions filed 16 June 2021, p 94 and submissions in reply filed 11 November
2021, p 25.
190 Applicant’s submissions filed 16 June 2021, p 52. The applicant abandons its claims for payment
with respect to the gully pit, change of brick to rendered brick for the external wall and the upgrade
to the garage doors for duplexes 1 and 2.
191 See applicant’s submissions filed 16 July 2021, p 52.
-- 31 of 39 --
32
The first issue to be considered with respect to the claims for variations is whether
the former Domestic Building Contracts Act 2000 (QLD) (DBC Act) prior to the
repeal of the DBC Act on 1 July 2015, applied at the relevant time.
As discussed above, there are two agreements. The written contract was entered into
on 15 December 2015 after the repeal of the relevant DBC Act. The DBC Act does
not apply to the applicant’s claims for the variations.
The respondents dispute that the applicant is entitled to payment for variations on a
quantum meruit basis as a consequence of non-compliance with the Act.192 Put
simply the respondents argue that the relevant s 40 and s 41 of the Act, as it applied
at the relevant time, gives rise to an implied statutory prohibition against recovery
for the variations by the applicant. Further, the respondents contend that if the
Tribunal finds that the applicant is entitled to its reasonable costs for the variations
they should be limited to the cost without the inclusion of any margin for the same
reasons expressed in relation to the applicant’s quantum meruit claim as discussed
above.193 The respondents calculate the adjusted figure for the variations as follows:
(a) $16,058.00 for the cost of the variations claimed by the applicant.
(b) ADD 10% for GST equalling $17,663.80.
It is noncontentious that the applicant failed to comply with the Act in that the
variations were not put in writing. Indeed, it is fair to say that having heard and
observed Mr Xiu give his oral evidence, he made many concessions about the
applicant’s non-compliance with the Act in a number of respects with the written
contract.
On balance, I am satisfied that Mr Liang requested the changes to the work that form
part of the variations and that the respondents benefited from each of the variations
claimed by the applicant.
In relation to the sliding door item, Mr Liang concedes during cross-examination
that he did request the change, the change was important and that the door was not
included in the original design.194 Mr Liang disputed, however, that Mr Xiu gave
him an estimate for the door.195
In relation to the windows in duplex 2, Mr Liang concedes during cross-examination
that he requested the change.196 I am satisfied that the relevant approved drawings
and plans show the dimensions of the existing windows that were replaced with a
larger window to allow the extra light.197 Mr Liang accepts that he had told Mr Xiu
that the room was too large, he thought the windows were too small and the removal
of the two windows to be replaced with ‘one big one’ would increase the light in the
room.198
192 Respondent’s submissions filed 1 October 2021, p 45.
193 Ibid, p 48.
194 Transcript, 17.12.2020, p 6-76.
195 Ibid.
196 Transcript 17.12.2020, p 6-76.
197 See applicant’ submissions filed 16 June 2021, p 57.
198 Transcript 17.12.2020, p 6-77.
-- 32 of 39 --
33
In relation to the variations required for the toilets in both duplex 1 and 2, I am
satisfied that Mr Liang requested the changes so that the duplex would be
comparable to other properties that were in the market, as contended by Mr Xiu.199
Further, I prefer Mr Xiu’s evidence about the timing of the requested change by Mr
Liang. On a fair reading of the written quotation provided to Mr Liang that only two
bathrooms and two ensuites in total are provided for in the development.200 Further,
the approved plans do not include the additional toilets and showers.201
I am satisfied that the applicant is entitled to payment for the variation works on a
quantum meruit basis. I do not accept, as contended by the respondents, that the
relevant s 42 of the Act gives rise to an implied statutory prohibition against
recovery.202 In the absence of a statutory intention that prohibits a non-compliant
builder’s right of recovery for a non-compliant variation at common law, the
applicant builder may seek to recover any non-compliant variations on a quantum
meruit basis where recovery under the contract is not available.203
I am satisfied that the applicant is entitled to payment for the variation works in the
amount of $21,196.56 as assessed by the expert quantity surveyors. For reasons
discussed above, I am not persuaded that the applicant’s entitlement to profit should
be reduced. The respondents have benefited from the work performed by the
applicant. The expert quantity surveyors have assessed the applicant’s reasonable
remuneration for the work performed in the amount of $21,196.56 including GST
and margin as agreed at 20%.204
The applicant has failed to convince that it is entitled to interest at the rate of 5% for
the assessed variation works. Indeed, the applicant concedes that there is no power
to award interest in relation to a quantum meruit claim.205 Here, the applicant is non-
compliant with the relevant provisions of the Act with respect to the variations. Even
if there is power to award interest under the Act, the applicant has failed to convince
me that I should allow interest in circumstances where there is non-compliance with
the Act. The applicant’s claim for interest is refused.
The respondents’ entitlement to rectification costs
The respondents claim the total sum of $21,771.27 as costs incurred to rectify
defects following the applicant failing to reach practical completion and unlawfully
suspending the work under the written contract.206
The respondents submit and I accept that the applicant warranted that the works
would be carried out with reasonable diligence.207 As discussed above, the applicant
did not lawfully suspend the works and had an opportunity to attend to rectification
and completion of any works. Further, the applicant was on notice from 16 April
199 Transcript 17.12.2020, p 6-76.
200 See applicant’s submissions filed 16 June 2021, p 59 and exhibit 3, p 688.
201 Ibid, exhibit 2 and exhibit 3, p 135(A) to 135(K).
202 See Cochrane v Lees [2021] QCATA 74, [161] to [168].
203 Ibid, [168].
204 Applicant’s submissions filed 16 June 2021, p 52 and see joint expert report, exhibit 3, p 1470.
205 Applicant’s submissions in reply filed 11 November 2021, p 37.
206 Respondent’s submissions filed 1 October 2021, p 57.
207 Exhibit 3, clause 36 of the written contract, p 758.
-- 33 of 39 --
34
2017 when it received the respondents’ notice to remedy, that there were defects to
the driveway drainage and sewer and wastewater outlets.208
I accept that it was necessary for Mr Liang to engage contractors to rectify the
defective work at the property completed on 20 July 2017.209 Mr Liang deposes to
the costs incurred for the expenses in obtaining the retrospective approval for the
water connections and relocation. The costs incurred include the amount of
$2,178.00 for Knobel Consulting in relation to the sewer connection and $726.00 for
the amended water meter location and inspection on 15 June 2017. Further costs in
the amount of $3,427.22 for the water meter relocation and $777.00 for Survey
Mark to locate the new water meter and perform a survey for the stormwater, were
incurred by Mr Liang.210 I also accept Mr Liang’s evidence in relation to further
defective work which was required to be rectified that is supported by the relevant
invoices for the work.211
Mr Liang is entitled to be restored to the position which he would have been had the
wrongful act not occurred.212 The damage is the loss which Mr Liang sustained by
failure of the applicant to perform its contractual obligations and can be measured by
determining the amount required to rectify the defects.213
I am satisfied that the amount of $21,771.27 are necessary and reasonable costs in
all of the circumstances to rectify the work I have found is defective. The work was
reasonable and necessary to rectify the sewer inspection opening that was
continuously flowing, the stormwater opening that had opened from previous rain
events and the driveway drainage that resulted in dampness to the side entry of the
property.214
The applicant’s entitlement to payment for unpaid progress claims
It is noncontroversial that the respondents did not pay to the applicant the progress
claims for stages 1, 2, 3 and 6 when the applicant says the claims were due and
owing under the written contract.
The applicant contends that the total amount owing is $266,911.20 comprising:215
(a) Stage 1 (deposit stage) being progress claim dated 15 January 2016 and given
on 29 June 2016 in the amount of $33,844.40;
(b) Stage 2 (base stage) being progress claim dated 20 April 2016 and given on 29
June 2016 in the amount of $101,533.20;
(c) The balance of $30,000 owing for stage 3 (frame stage) being progress claim
dated 15 June 2016 and given on 29 June 2016 (the total value of this progress
claim was $135,377.66); and
208 Respondent’s submissions filed 1 October 2021, p 57.
209 Exhibit 3, p 1007.
210 Ibid, p 61 and see Exhibit 3, pp 1260, 1296, 1297, 1271 and 1305.
211 See exhibit 3, pp 1262 to 1267 and respondent’s submissions filed 1 October 2021, p 61.
212 Robinson v Harmon [1848] ER 135 and Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009)
236 CLR 272.
213 See Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272, [15].
214 See Bellgrove v Eldridge (1954) 90 CLR 613. See also respondent’s submissions filed October 2021,
p 59.
215 Applicant’s submissions filed 16 June 2021, p 50.
-- 34 of 39 --
35
(d) Stage 6 (practical completion stage) progress claim initially claimed on 20
February 2017 in the amount of $101,533.20.
As discussed above, the applicant unlawfully suspended the works and did not
attend to rectification of defective work despite being given an opportunity to do so
after it received the respondents’ notice to remedy. Further, the applicant waived any
non-compliance by Mr Liang with the written contract. I am not satisfied that the
applicant is entitled to any of the amounts claimed under the written contract for
unpaid progress claims and is limited to claiming any outstanding money on a
quantum meruit basis. Further, I reject the applicant’s claim for interest for the
unpaid progress claims pursuant to the terms of the contract for reasons as discussed
above.
The respondents’ entitlement to reimbursement of various fees
Mr Liang claims the amount of $28,000.00 being the infrastructure charge that he
says he was required to pay to the Gold Coast Council for a notice issued on 6
February 2017.216
The issue before me now is whether the infrastructure charge is payable by the
applicant builder on the basis that it forms part of the contract works. This is to be
determined by reference to the written contract alone.217 If an expression in a
contract is unambiguous or susceptible of only one meaning, evidence of
surrounding circumstances cannot be adduced to contradict its plain meaning.218 It is
established law that the meaning of a commercial contract is to be determined by
what a reasonable business person would have understood those terms to mean.219 It
will require a consideration of the language used by the parties, the surrounding
circumstances known to them and the commercial purpose or objects to be secured
by the contract.220
In my view the infrastructure charge clearly falls within the exclusion identified in
item 2 of Schedule 1 of the written contract such that it is a cost for conveying
services to the site, connecting or installing services for use at the site, or issuing a
development approval or similar authorisation that are related to the carrying out of
the works.
The City of Gold Coast website provides relevant information about the meaning of
infrastructure charge that is now set out below as follows:
Infrastructure charges help fund essential infrastructure such as local roads,
parks, stormwater, water supply and sewerage for new and growing
communities.
Infrastructure charges are levied on approved developments. Infrastructure
charges and development approvals attach to the land. They are binding on the
owner and subsequent owners of land title.
216 Respondents’ submissions filed 1 October 2021, p 54 and see exhibit 3, pp 1160-1166.
217 Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104 at 116.
218 Ibid, [48] and see the respondents’ submissions filed 1 October 2021, p 55.
219 Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd (2014) 251 CLR 640
at 656-7, [35].
220 Ibid.
-- 35 of 39 --
36
On a fair reading of the exclusion identified above in item 2 of Schedule 1 of the
written contract, the infrastructure charge clearly relates to the conveying of services
to the site and therefore falls within the exception referred to in item 2 of Schedule
1.
Mr Liang has failed to convince me that it was the intention of the parties that the
infrastructure charge would form part of the contracted works based on the ‘bill of
quantities’ prepared by the applicant and provided to Mr Liang. The relevant
quotation lists a number of council and approval fees including more generally
‘council approval fees’ in the sum of $30,800.00.221
As discussed above, the quotation provided to Mr Liang by the applicant was an
offer to perform the work. On balance, Mr Liang has failed to satisfy me that the
written contract included an obligation on the applicant to pay the infrastructure
charge and that the amount claimed is payable.
Mr Liang also seeks reimbursement of surveyor’s fees in the sum of $1,540.00 being
a fee incurred for the preparation of an as-constructed survey in May and June
2017.222
As discussed above, the applicant unlawfully suspended the work and failed to
attend to rectification and completion of work after receiving a notice to remedy
issued by the respondents.
I will allow the claim for surveyor’s fees in the amount of $1,540.00 on the basis
that the fee was necessary to achieve practical completion and obtain the necessary
final certificate from the local council.
The respondents’ claim for liquidated damages
It is noncontentious that Mr Liang is entitled to liquidated damages for the late
completion of the works.223 Further, clause 32 of the written contract provides that
the owner is entitled to be paid a liquidated sum of $50.00 per day if the applicant
builder did not reach practical completion by the end of the building period.
As discussed above, the work commenced under the written contract at the latest on
7 March 2016. This finding is supported by the evidence. The engineers carried out
a pre-construction inspection of the footings on 7 March 2016 and Mr Xiu conceded
that the applicant commenced work under the written contract at the latest by 7
March 2016.
Allowing for 135 days after the date of commencement, as provided under item 13
of Schedule 1, the applicant was required to reach practical completion by 20 July
2016.
As discussed above, Mr Liang completed the defects on 20 July 2017 and took
possession of the property on 1 August 2017 by changing the locks. I accept the
221 See exhibit 3, pp 709-718.
222 Respondents’ submissions filed 1 October 2021, p 63.
223 Applicant’s submissions filed 16 June 2021, p 656 and respondents’ submissions filed 1 October
2021, p 61.
-- 36 of 39 --
37
respondents’ assessment for late completion damages in the amount of $18,250.00
representing the payment of $50.00 per day.224
Conclusion
I am not satisfied that a further oral hearing is necessary for the purposes of
determining any consequential orders arising my findings.225 Both parties have
prepared and filed extensive written submissions addressing the many contested
factual and legal issues. It is desirable to bring this matter to an end and to make
final orders arising from my findings, some of which are now set out below:226
(a) There are two agreements. An oral agreement made in March 2015 for the
preliminary works and a separate written agreement being a HIA contract
signed by Mr Xiu and Mr Liang in December 2015 for the construction of the
duplex.
(b) The applicant was unlicensed to perform building work when it agreed to
assist the respondents with the preliminary work pursuant to the oral
agreement.
(c) The respondents’ contention that there is a retention scheme is rejected.
(d) Mr Liang and Ms Wang are not jointly and severally liable with respect to the
work performed by the applicant in developing the site. Ms Wang is removed
as a second respondent from the proceedings.
(e) The respondents’ claim that the applicant is required to disgorge the
respondents’ payments under the written contract pursuant to s 42 of the Act is
rejected. The applicant was licensed to perform the work when it signed the
written contract. The preclusion in s 42(3) of the Act is not triggered here
because the work performed under the written contract was licensed work,
save for some of the items of preliminary work that Mr Xiu included in the
lump sum contract so that he could get paid.
(f) The written HIA contract entered into between the applicant and Mr Liang is
solely for the construction of the duplex. Some items of the preliminary works
were included in the lump sum written contract because Mr Xiu wanted to get
paid for the work.
(g) The applicant performed unlicensed building work for the purposes of the Act
when it paid invoices and coordinated the preliminary works pursuant to the
oral agreement. The applicant’s claim that the respondents knowingly engaged
the applicant to perform unlicensed building work in contravention of s 42 of
the Act is rejected. I do not accept as submitted by the applicant that the
respondents may be held to be pari delicto (in equal defence) with the
applicant builder so as to be outside the class of people for whose benefit a
right of recovery is made available in consequence of the operation of s 42(3)
of the Act.
224 Respondent’s submissions filed October 2021, p 62.
225 See respondent’s submissions filed October 2021, p 66 and applicant’s submissions in reply filed 11
November 2021, [225].
226 The summary is not intended to displace any of the findings I have made in the preceding paragraphs
of my reasons.
-- 37 of 39 --
38
(h) Mr Liang has had the benefit of the work performed by the applicant. The
applicant is entitled to a claim in quantum meruit for the unlicensed work
carried out under the oral agreement that is limited by s 42(4) and a common
law quantum meruit claim for licensed work carried out pursuant to the written
contract. Any quantum meruit assessment cannot exceed the contract price.
(i) The applicant is not required to repay the sum of $409,977.10 paid by the
respondents pursuant to the written contract. I am satisfied that that the
applicant did not give an undertaking to carry out work that forms part of the
written contract until it was licensed to do so.
(j) The applicant is entitled to recover the amount of $36,011.02 (inc GST) for the
preliminary works on a quantum meruit basis under the oral agreement.
(k) The works did not reach practical completion for the purposes of the written
contract as contended by the applicant. Further, the applicant did not accrue
the right to payment for that stage.
(l) The applicant did not lawfully suspend the works due to the respondents’
failure to pay progress payments. There is no variation to omit that part of the
work not carried out or completed by the applicant.
(m) The applicant is entitled to reasonable restitution for the works completed
calculated on a quantum meruit basis.
(n) The value of the completed licensed works performed is assessed at
$638,033.92 (inc GST). The amount of $409,977.10 being the payments made
by the respondents after the applicant obtained its licence should be deducted
from applicant’s claim for remuneration for the work.
(o) The applicant is entitled to payment for the variations on a quantum meruit
basis assessed at $21,196.56.
(p) The balance of the unpaid progress claims is off-set from the money payable
by the respondents.
(q) The applicant is not entitled to interest on the money found to be payable by
the respondents on a quantum meruit basis.
(r) The respondents are not entitled to be reimbursed for the various fees they say
the applicant remains liable to pay in the amount of $28,000.00 for the
infrastructure charge. The respondents are entitled to the amount of $1,540.00
for surveyors fees.
(s) The respondents are entitled to the rectification costs or costs to complete the
work assessed in the amount of $21,771.27.
(t) The respondents are entitled to liquidated damages in the amount of
$18,250.00.
(u) The applicant is in breach of the contract for failing to reach practical
completion, unlawfully suspending the work and failing to rectify defective
work. The applicant is not entitled to recover the final payment owing under
the contract. The respondents are entitled to a remedy for the applicant’s
breach.
-- 38 of 39 --
39
The assessment of the claims for the application and counter-application that I
have allowed are set out below as follows:
Reasonable renumeration for work performed by the
applicant (including GST and profit as adjusted with respect
to the amount of unlicensed building work) $638,033.92
LESS payments made by the respondents - $409,977.10
Balance payable to the applicant $228,056.82
PLUS variations payable to the applicant $21,196.56
LESS rectification costs payable to Mr Liang - $21,771.27
LESS surveyor’s fees payable to Mr Liang - $1,540.00
LESS liquidated damages payable to Mr Liang - $18,250.00
TOTAL $207,692.11
Mr Liang is required to pay the amount of $36,011.02 (inc GST) for the preliminary
works as assessed by Mr Burgess in addition to the licensed work performed under
the written contract that I have assessed in the amount of $207,692.11.
The final order is that Mr Liang pay the total amount of $243,703.13 (inclusive of
GST) to the applicant within sixty (60) days from the date hereof in full and final
satisfaction of all work performed by the applicant.
-- 39 of 39 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2022/053