Adani Abbot Point Terminal Pty Limited v Lake Vermont Resources Pty Limited & Ors [2021] QCA 187 [2021] 36 QLR
SUPREME COURT OF QUEENSLAND
CITATION: Adani Abbot Point Terminal Pty Ltd v Lake Vermont
Resources Pty Ltd & Ors [2021] QCA 187
PARTIES: ADANI ABBOT POINT TERMINAL PTY LTD
ACN 149 298 206
(appellant)
v
LAKE VERMONT RESOURCES PTY LTD
ACN 114 286 841
(first respondent)
QCOAL PTY LTD
ACN 010 911 234
(second respondent)
BYERWEN COAL PTY LTD
ACN 133 357 632
(third respondent)
SONOMA MINE MANAGEMENT PTY LTD
ACN 124 677 443
(fourth respondent)
FILE NO/S: Appeal No 10300 of 2020
SC No 9440 of 2017
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane – [2020] QSC 260 (Dalton J)
DELIVERED ON: 31 August 2021
DELIVERED AT: Brisbane
HEARING DATE: 24 March 2021; 25 March 2021; 26 March 2021
JUDGES: Fraser and McMurdo and Mullins JJA
ORDERS: 1. Allow the appeal against the judgments given and the
orders made on 26 August 2020 and 1 September 2020,
save for the declarations numbered 5 and 7 made on
26 August 2020, and the orders numbered 8 and 9 made
on 26 August 2020.
2. Set aside the judgments and orders made on those
dates, save for those two declarations, and the orders
numbered 8 and 9 made on 26 August 2020.
3. Give judgment for the appellant against the first
respondent on the first respondent’s counterclaim, save
for its claim for the declaration numbered 5 made on
26 August 2020.
-- 1 of 59 --
2
4. Give judgment for the appellant against the second and
third respondents on their counterclaims, save for the
declaration numbered 5 made on 26 August 2020.
5. Give judgment for the appellant against the fourth
respondent on its counterclaim, save for the
declarations numbered 5 and 7 made on 26 August
2020.
6. Declare that the appellant has demonstrated that the
OFC and OVC agreed between it and the operator for
the financial years commencing 1 July 2017 and 1 July
2018 represent reasonable charges having regard to the
efficient operation of the Terminal in accordance with
cl 7.6(b) of the user agreements between the appellant
and the respondents.
7. Give the appellant liberty to apply for such further
order, of the nature of that specified in paragraph 4 of
the orders sought in the notice of appeal, within 21 days
of the date of this judgment.
8. Direct the parties to provide, within 21 days of this
judgment, written submissions, not exceeding six pages
in length, as to the orders which are to be made about
the costs of the proceeding in the Trial Division and in
this Court.
CATCHWORDS: TRADE AND COMMERCE – COMPETITION, FAIR
TRADING AND CONSUMER PROTECTION LEGISLATION
– CONSUMER PROTECTION – UNCONSCIONABLE
CONDUCT – WHAT CONSTITUTES – where the respondents
are the users of a coal terminal – where the appellant is the
effective owner of the coal terminal – where the respondents
have separate user agreements with the appellant concerning
their use of the terminal – where a previous user paid the
respondent to be relieved of its obligations – where charges
payable by the existing users increased to account for the
previous user’s exit – where the trial judge found that, in all
the circumstances, the appellant had engaged in
unconscionable conduct – whether the appellant’s conduct was
unconscionable under s 21(1) of the Australian Consumer Law
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES –
CONSTRUCTION AND INTERPRETATION OF
CONTRACTS – where user agreements exist between the
appellant, as the owner, and the respondents, as users, of a coal
terminal – where the contract provides that the appellant must
demonstrate that its charges are reasonable having regard to
the efficient operation of the Terminal – where the trial judge
found that the appellant had not made such a demonstration as
the appellant had not demonstrated that the way the Terminal
-- 2 of 59 --
3
was operated was, itself, efficient – whether the appellant had
made the relevant demonstration
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES –
CONSTRUCTION AND INTERPRETATION OF
CONTRACTS – where user agreements exist between the
appellant, as the owner, and the respondents, as users, of a coal
terminal – where the fourth respondent’s user agreement
contains a clause which provides “… No other Access Holder
Presenting Coal for Handling at the Terminal will be charged
less than the User is charged at that time for a substantially
similar commercial arrangement” – where the appellant
charges another user less to handle its coal than it charges the
fourth respondent – where the trial judge found that the
appellants conduct was in breach of its contract with the fourth
respondent – whether the trial judge’s interpretation was in error
Competition and Consumer Act 2010 (Cth), The Australian
Consumer Law s 21, s 22
Australian Competition and Consumer Commission v
Quantum Housing Group Pty Ltd (2021) 388 ALR 577;
[2021] FCAFC 40, cited
Australian Securities and Investments Commission v Kobelt
(2019) 267 CLR 1; [2019] HCA 18, cited
Ipstar Australia Pty Ltd v APS Satellite Pty Ltd (2018)
356 ALR 440; [2018] NSWCA 15, cited
Paciocco v Australia and New Zealand Banking Group Ltd
(2015) 236 FCR 199; [2015] FCAFC 50, cited
Paciocco v Australia and New Zealand Banking Group Ltd
(2016) 258 CLR 525; [2016] HCA 28, cited
COUNSEL: B W Walker SC, L F Kelly QC, S Cooper QC with
M F Johnston for the appellant
S S W Couper QC, with A C Stumer and D L Tay for the first
respondent
J D McKenna QC, with N J Derrington, for the second, third
and fourth respondents
SOLICITORS: Clayton Utz for the appellant
DLA Piper for the first respondent
Arnold Bloch Leibler for the second, third and fourth
respondents
[1] FRASER JA: I agree with the reasons for judgment of McMurdo JA and the orders
proposed by his Honour.
[2] McMURDO JA: The Abbot Point coal terminal (the Terminal) has been in operation
since 1984, at first serving the needs of one coal mine operated by Mt Isa Mines
Limited (now called Glencore Coal Queensland Pty Ltd) and since 2005, a number
of coal mines in central Queensland. The users of the Terminal have no alternative
facility for loading their coal into ships.
-- 3 of 59 --
4
[3] Until 2011 the Terminal was owned by the Ports Corporation of Queensland Limited,
a Government-Owned Corporation. In 2011 the appellant became the sub-lessee and,
effectively, the owner of the Terminal. From 2000-2016, the Terminal was operated
by Abbot Point Bulkcoal Pty Ltd (APB). In October 2016 Abbot Point Operations
Pty Ltd (APO), a related company of the appellant, became the operator.
[4] The respondents to this appeal are some of the users of the Terminal. Each user has
a contract with the appellant (a user agreement), under which it may use the Terminal
to load a specified maximum quantity of coal each year, for which it must pay certain
charges. Each of the users entered into their user agreements with the Ports
Corporation. By a Transfer Notice and Project Direction made under the
Infrastructure Investment (Asset Restructuring and Disposal) Act 2009 (Qld), on
25 May 2011, the right, title and interest in, and obligations and liabilities were
transferred to the appellant.
[5] The user agreements are in largely identical terms. There are charges which are to be
paid by the users in order to provide the owner with an agreed rate of return on the
capital value of the facility. The primary charges in relation to the infrastructure are
the Terminal Infrastructure Charge (TIC), and the “take or pay” charge (TPC). The
TIC is paid at a certain dollar rate for each metric tonne of a user’s coal which is
shipped through the Terminal. To the extent that there is an unused portion of the
user’s annual maximum tonnage (AMT), the user pays the TPC, calculated at the
same dollar rate per metric tonne.
[6] The other category of charges paid by a user are handling charges. There is a Fixed
Handling Charge (HCF), which is a reimbursement to the owner of what the owner
pays to the operator under certain provisions of the operation and management
agreement between them. The HCF is comprised of a certain proportion of the
operator’s costs and the operator’s profit margin. There is also a Variable Handling
Charge (HCV), which is to reimburse the owner for the payments it makes to the
operator under other provisions of the operation and management agreement, again
for certain costs of the operator and its margin.
[7] The relevant user agreements provide a formula for the calculation of the TIC and
TPC, and another formula for the calculation of the HCF. In each case, the amount
of the charge is a function of the total number of the contracted tonnes of all users.
The TIC and the TPC are calculated by dividing an agreed present value of the annual
revenue which is required for the owner to derive a certain rate of return on its capital
investment, by a denominator which is the “Annual Maximum Tonnage for All
Access Holders”.1 As a result, the greater is the total, across all users, of their agreed
maximum annual tonnages, the higher is the denominator, and the lower is the amount
per tonne charged as a TIC or TPC.
[8] Similarly, the formula used for the calculation of the HCF2 provides for the fixed
operating costs (including the operator’s margin) to be divided by the “Annual
Relevant Tonnage”, which is the greater of either the total of all annual maximum
tonnages, or the annual tonnages which users have notified the operator that they
expect to present at the Terminal in a financial year.
[9] It is evident that it is in the interests of each user that the Terminal be operated as
close as practicable to its capacity. The user agreements differ in their
1 Schedule 7 of the standard user agreement.
2 Clause 7.2 of the standard user agreement.
-- 4 of 59 --
5
commencement dates and duration. However, the agreements are subject to the same
process of review of the TIC, the TPC and the HCF. There are agreed reviews, at
intervals of five years for the TIC/TPC, and annual reviews of the HCF. Under each
user agreement, there is a “Review Date” for the TIC/TPC of 1 July 2017, with
a further five yearly review to occur on 1 July 2022. The annual review date for the
HCF is 1 July.3
[10] In 2016, there were nine users of the Terminal, consisting of the four respondents to
this appeal and five others, of which one was Queensland Coal Pty Ltd (QCPL),
a subsidiary of Rio Tinto. QCPL had ceased to use the facility and wished to be
relieved of the burden of its user agreement, which was not to expire until
30 June 2028. After some months of negotiations, two agreements were made on
31 October 2016, having the effect of ending the QCPL User Agreement, and
requiring QCPL to pay amounts totalling $255 million.4
[11] By one of those agreements for the departure of QCPL, Adani Mining Pty Ltd
(AMPL), a related company of the appellant, became a user, under the same terms as
had applied to QCPL, for a period from 1 July 20225 to 30 June 2028. However, no
agreement was made with any existing or other potential user to use the capacity
created by QCPL’s departure ahead of the arrival of AMPL.
[12] The departure of QCPL had the effect of increasing the amounts to be paid (as TICs,
TPCs and HCFs) by other users, including the respondents, because the annual
maximum tonnages of users, in aggregate, were reduced. There was an increase in
the TIC/TPC from 1 July 2017 (the next Review Date), until 1 July 2022, and there
was an increase in the HCF from a date before 1 July 2017.
[13] The principal claim in this case was that in making, or causing to be made, the
agreements with QCPL, and by requiring users to pay higher charges according to
their user agreements, to the detriment of other users, the appellant engaged in
unconscionable conduct, as proscribed by s 21(1) of Schedule 2 of the Competition
and Consumer Act 2010 (Cth), The Australian Consumer Law (ACL). The trial judge
upheld that claim, and gave judgments in favour of the present respondents in varying
amounts totalling $106.8 million. The trial judge determined that the total of the
amounts received by the appellant ($255 million) was a fair measure of the damage
caused in aggregate to the remaining eight users, and that the four respondents should
be awarded damages for their proportions of that sum.6
[14] The trial judge held that it was unconscionable for the appellant to agree with QCPL,
for its departure as a user, in a way which cast an additional burden for these charges
upon the remaining users, whilst yielding $255 million, to the appellant. Her Honour
found that the appellant thereby would be “paid two sums of money” for the five
years from 1 July 2017 to 30 June 2022, “both [referable] to QCPL’s contractual
obligation to [the appellant]. Whereas, had the QCPL [User Agreement] remained
on foot, [the appellant] would only have received one such sum”.7
[15] The Notice of Appeal challenges the unconscionability awards on three grounds. It
is said that the finding of unconscionable conduct was erroneous, that the appellant
3 Being calculated for each relevant Financial Year: cl 7 of the standard user agreement.
4 These agreements were a ‘Deed of Novation ’ and a ‘Termination Agreement’.
5 Novation Agreement Schedule Item 5.
6 Adani Abbot Point Terminal Pty Ltd v Lake Vermont Resources Pty Ltd & Ors [2020] QSC 260 (the
Judgment).
7 Judgment [191].
-- 5 of 59 --
6
was denied procedural fairness in the making of that finding and that there were errors
in the determination of the damages.
[16] The respondents were given further relief, by two declarations.
[17] It was declared that the appellant had not demonstrated, as it was obliged to do, that
certain costs incurred by its operator (APO) were reasonably incurred, having regard
to the efficient operation of the Terminal.8 This order is challenged on the ground
that there was an error by the trial judge in the construction and application of the
relevant provision of the user agreements, namely cl 7.6(b).9 It was further declared
that from 1 July 2017, the appellant had been in breach of cl 25.1(a)(v) of the user
agreement between the appellant and the fourth respondent (Sonoma), which
precludes the appellant from charging another user less than Sonoma is charged to
handle coal through the Terminal under its user agreement.10 That order is challenged
on the ground that there was an error in the construction and application of that clause.
[18] By Notices of Contention, the respondents say that their awards should be affirmed,
in part, on another ground, namely that the amounts payable by the respondents, as
their shares of the costs payable by the appellant to the operator, should exclude such
of those costs for which, it is said, the appellant has been indemnified by the payments
made by QCPL under the agreements for its departure.
The user agreements
[19] Further terms of the user agreements must be discussed.
[20] The user agreements are for long terms, with limited opportunities for a user to
withdraw. Neither party may terminate the agreement, without the concurrence of
the other, except for the other’s breach.11 A user may only adjust its AMT in certain
circumstances.12 The user may request a reduction of that AMT, which the owner
“in its absolute discretion” may accept or reject. If a user wishes to increase its AMT,
it must make a request to the owner, which the owner may accept if it determines that there
is an available unallocated capacity of the Terminal to meet the requested increase.
[21] By cl 10.2, if a user has not presented for handling at least 90 per cent of its AMT
over a period of 18 months, and there are other users whose needs cannot be satisfied
from the available Terminal capacity, the owner may reduce the user’s AMT.
Clause 10.3 provides:
“Capacity to be taken into account only once
If [the appellant] reduces the User’s Annual Maximum Tonnage under
Clauses 4.6 or 10.2 of this Agreement and subsequently provides that
capacity to another Access Holder, it will not charge the User any TPC
or HCF in relation to that reduced tonnage from the time that it is
provided to the other Access Holder.”
[22] A user may assign all or part of its rights or entitlements under its agreement,
including all or part of its AMT, either “permanently or in respect of a period of time”,
8 Judgment [302]-[303].
9 Appellant’s Outline of Submission [101].
10 Judgment [346].
11 Clauses 3.2 and 3.3 of the standard user agreement.
12 Clause 10.1 of the standard user agreement.
-- 6 of 59 --
7
with the prior consent of the owner, which consent is not to be unreasonably
withheld.13 An effective assignment discharges the user from obligations under the
user agreement in respect of the rights and entitlements assigned.14 With the consent
of the owner, again not to be unreasonably withheld, a user may permit a third party
to present coal to the terminal.15
[23] The owner is obliged to operate the Terminal to enable a user’s AMT to be handled
each year,16 and it warrants that it will cause its operator to ensure that the Terminal
is maintained so that as far as practicable the Terminal operates at its design
capacity.17 By cl 25.1(a)(iv), the owner warrants that “to the extent that there is
demand, it will seek to contract all uncontracted Terminal Capacity from time to time
in accordance with [the owner’s] procedures for allocation of Terminal Capacity …”.
[24] Clause 24 contains provisions which are intended to protect the owner against an
impecunious user. Prior to the execution date of its user agreement, the user must
have provided to the owner “Credit Support”, in order to secure the user’s
performance of its obligations. The support must be from an entity which, in the
reasonable opinion of the owner, is reputable and of good financial standing, and with
the capability to satisfy or cause the satisfaction of the obligations of the user, or is
from an Australian Bank (as defined in the Corporations Act 2001 (Cth)).18
[25] After the execution date, if a user applies to increase its AMT or, in the reasonable
opinion of the owner, there is a likelihood that the user (or a provider of its Credit
Support) may have ceased or will cease to reputable or of good financial standing,
and with the capability to satisfy in full the user’s obligations, the user must provide
further information to the owner to establish its credit worthiness. In those
circumstances, the user may be required, by notice from the owner, to provide
information to establish its creditworthiness.19 There is another term by which further
information may be required in the event that the owner has agreed to increase the
user’s AMT conditionally on the provision of Credit Support.20
[26] A failure to provide Credit Support, after a notice given under one of these provisions,
constitutes a material breach of the user agreement, entitling the owner to call on any
existing Credit Support or to suspend the user’s rights to have its coal handled at the
Terminal.21
[27] The HCF is calculated according to cl 7.2 which is as follows:
“7.2 [The appellant] to Advise HCF
(a) As soon as practicable after consulting with the Operator, [the
appellant] must advise the User in writing of the HCF payable
by the User during the next Financial Year (and the current
Financial Year, in the case of the first Utilisation Advice).
13 Clause 14.2 of the standard user agreement.
14 Clause 14.2(d) of the standard user agreement.
15 Clause 14.3 of the standard user agreement.
16 Clause 4.2(a)(i) of the standard user agreement.
17 Clause 25.1(a)(ii), of the standard user agreement.
18 Clause 24.1 of the standard user agreement.
19 Clause 24.2(a) of the standard user agreement.
20 Clause 24.2(b), of the standard user agreement.
21 Clause 24.3 of the standard user agreement.
-- 7 of 59 --
8
(b) HCF per tonne of the User’s Coal for each Financial Year is
calculated as follows:
HCF = OFC
ART
Where: -
Subject to Clause 7.6(b), OFC comprises:
(i)
(A) the total costs payable by [the appellant] to the
Operator in respect of the total fixed operating
costs incurred by the Operator for the Financial
Year (excluding costs of Miscellaneous Services
referred to in Clause 7.4 of this Agreement); plus
(B) the Operator’s Margin on that amount.
ART is the Annual Relevant Tonnage, being the aggregate for
each Access Holder of the Terminal (including the User) of the
greater of:
(i) their respective Annual Maximum Tonnages; or
(ii) the annual tonnage which the User has notified the
Operator in good faith that the User expects to Present at
the Terminal in a Financial Year.
(c) The HCF is payable on each tonne of the User’s Annual
Maximum Tonnage or, if higher, the annual tonnage for the
relevant Financial Year which has been Handled for the User.”
[28] The HCV is calculated according to cl 7.3 as follows:
“7.3 [The appellant] to Advise HCV
(a) As soon as practicable after consulting with the Operator, [the
appellant] must advise the User in writing of the rate of HCV
payable by the User during the next Financial Year (and the
current Financial Year, in the case of the first Utilisation Advice).
(b) HCV per tonne of the User’s Coal Handled is calculated as
follows:
HCV = OVC
FT
Where:-
Subject to Clause 7.6(b), OVC comprises:
(i)
(A) the total costs payable by [the appellant] to the
Operator in respect of the Operator’s total variable
operating costs (excluding costs of Miscellaneous
-- 8 of 59 --
9
Services referred to in Clause 7.4 of this
Agreement) incurred by the Operator for the
Handling of all Coal through the Terminal for
a Financial Year; plus
(B) the Operator’s Margin.
FT (or “Forecast Throughput”) is the sum of forecast throughput for
all Access Holders based on Utilisation Advices received by [the
appellant] for the relevant Financial Year, at a given point in time, of
the total number of tonnes of Coal Handled through the Terminal
(which as at the start of any Financial year is nil) and proposed to be
Presented at the Terminal (as advised by each Access Holder to [the
appellant]) by all Access Holders during the Financial Year.”
[29] By cl 7.6, where the operator is neither the operator existing as at the execution date
of the user agreement, nor an entity owned and/or controlled by at least 60 per cent
of the users (by tonnage), then clauses 7.2(b) and 7.3(b) will apply only if the owner
demonstrates “that the OFC and the OVC as agreed between [the owner] and the
Operator represent a reasonable charge having regard to the efficient operation of the
Terminal.”
[30] At any relevant time, the operator (APO) was not controlled by 60 per cent of the
users; it was a company in the Adani group. It was, therefore, for the appellant to
demonstrate that the OFC and OVC, under its agreement with APO, represented
reasonable charges having regard to the efficient operation of the Terminal. It was
on that question that the respondents were granted the declaration to which I have
referred at [17].
[31] Clause 8 provides for a review of the TIC and TPC on each Review Date, by a process
initiated by the owner, which must notify the users of its determination of the amount
of the TIC and TPC to apply from the Review Date, by a notice given at least eight
months prior to then. Any dispute about those amounts can be resolved by an
arbitration, in which the arbitrator must apply the relevant pricing provisions of the
user agreement. As I will discuss, the proposed TIC and TPC charges, to commence
on 1 July 2017, were the subject of a dispute which was resolved by an arbitrator in
the appellant’s favour.
The QCPL transactions
[32] The appellant made two agreements with QCPL, each made on 31 October 2016.
[33] One agreement was a so-called Deed of Novation, to which the parties were the
appellant, QCPL and AMPL. It recited that QCPL had no further need for any
capacity under its user agreement and that it had been unable to identify any potential
user for that capacity. It recited that the user agreement permitted an assignment of
part of the rights or entitlements of QCPL, as would occur by this Deed. It further
recited that it was a requirement of the user agreement that a proposed assignee enter
into a deed of assignment under which it agreed to be bound by the terms, conditions
and obligations of the user agreement in respect of the assigned rights, and that AMPL
had agreed to do so, in consideration of QCPL agreeing to make a payment to AMPL
of $138 million (plus GST).
-- 9 of 59 --
10
[34] By cl 3.1, QCPL assigned “absolutely to AMPL the Annual Contract Tonnage
Assigned”, which was defined22 to be the AMT for the six financial years,
commencing on 1 July 2022 and ending on 30 June 2028, to which QCPL had been
entitled. By cl 3.1(b), AMPL assumed and agreed to perform the obligations of
QCPL under the user agreement, to the extent that those obligations related to the
assigned AMT. By cl 3.1(d), the appellant and AMPL were deemed to have entered
into an agreement in respect of that assigned tonnage, upon the same terms as in
QCPL’s user agreement. By cl 3.1(g), it was agreed that the so-called Security
Deposit Terms should be deemed to be added to this user agreement between the
appellant and AMPL. Those terms were the subject of a recital that AMPL had
satisfied the appellant that AMPL would provide adequate Credit Support under and
for the purposes of cl 4.2(b)(ii), by the Security Deposit Terms.23 Those terms were
also the subject of a separate agreement, dated 31 October 2016 and made between
the appellant and AMPL, which is discussed below.
[35] By cl 8.1, it was provided that “[in] consideration for AMPL’s acceptance of the
obligations under the novations or assignments provided for in this Deed, QCPL will
pay to AMPL the Novation Payment of $138 million …”. This was to occur by three
instalments, the last of which was to be paid on 15 June 2017.24
[36] The second of the agreements which the appellant made with QCPL was the so-called
Termination Agreement. That agreement recited the history of the QCPL User
Agreement (although the recitals made no reference to the partial assignment under
the Deed of Novation).25 It recited that QCPL no longer needed any capacity under
its user agreement, and that it had been unable to identify any user with a demand for
that capacity.26 Further, it recited that QCPL had not provided information, as
requested by the appellant on 10 March 2016, concerning QCPL’s credit standing,
and that QCPL’s stance was that it would not respond to such a request.27
[37] By cl 3 of this agreement, the appellant and QCPL agreed to terminate the user
agreement on and from the Effective Date, which (again) was 31 October 2016.28 By
cl 3.2, the appellant released QCPL from its obligations, save for those which by then
had accrued.
[38] By cl 3.4, the appellant indemnified QCPL (and its related companies) against any
claim made not only by the appellant or its related companies, but also, importantly,
by any other user of the Terminal. I will call this term, which was particularly
important in the judge’s reasoning, the Indemnity.
[39] By cl 4.1, QCPL agreed to pay to the appellant a “Termination Payment” of
$117 million, payable by three instalments, contemporaneously with the payment of
the instalments under the Deed of Novation.
[40] The appellant made a third agreement simultaneously with the QCPL transactions.
Again, on 31 October 2016, the appellant and AMPL agreed that AMPL was to pay
22 By Item 7 in the Schedule to the Deed.
23 Recital J.
24 By Item 8 in the Schedule to the Deed.
25 Recital H.
26 Recital G.
27 Recital H.
28 However, it further provided that the parties should account as if the termination had occurred on
1 July 2016.
-- 10 of 59 --
11
to the appellant the $138 million which AMPL was to receive from QCPL under the
Deed of Novation. This was to be paid to the appellant as security for the performance
by AMPL of the user agreement between them. The companies agreed to add a clause
to their user agreement, by which AMPL would pay to the appellant, upon receiving
each instalment under the Deed of Novation, the amount of that instalment as Credit
Support under cl 24 of AMPL’s user agreement. It was further provided that “for the
avoidance of doubt”, AMPL would not have any right, title or interest in the money
so paid to the appellant.29
[41] By another term to be added to AMPL’s user agreement, the appellant was authorised
to use that money paid to it as Credit Support. And the appellant’s obligation to repay
any of this security was conditional upon the appellant being permitted to do so under
what were described as “the Secured Documents”. That was a reference to a deed
between the appellant and some of its creditors, by which the appellant was
constrained in applying its funds except according to a certain order of priority, by
which those creditors were to be paid before, in particular, a related company of the
appellant such as AMPL. The practical effect of the Security Deposit Agreement was
to pass on to the appellant the benefit of the novation payments of $138 million.
[42] The effects, of the three agreements made by the appellant on 31 October 2016, were
that:
• QCPL ceased to be a user as and from that date;
• QCPL paid sums, under the two agreements to which it was a party, totalling
$255 million;
• by July 2017, the whole of that $255 million would be received by the
appellant;
• AMPL would become a user of the terminal, for a period of six years
commencing on 1 July 2022 with an entitlement to the AMTs which QCPL
would have had under its user agreement.
[43] It is then necessary to consider the appellant’s conduct, in its negotiations with QCPL,
which resulted in those agreements.
The negotiations with QCPL
[44] The trial judge noted that the appellant had called no evidence from anyone who had
made the decisions to enter into the QCPL transactions and the Security Deposit
Agreement.30 The evidence in chief in this trial was by affidavit, and there was only
one affidavit in the appellant’s case which addressed the three agreements, which was
from Mr Christopher Wicks. There was also affidavit evidence from another Adani
employee, Mr Dwayne Freeman, whom her Honour said was far more involved in
negotiating these agreements than Mr Wicks, although Mr Freeman’s affidavit did
not deal with the QCPL transactions.31 Nevertheless Mr Freeman gave evidence in
cross-examination about the QCPL transactions. The trial judge considered
Mr Freeman to be an honest witness, and she accepted his evidence except in certain
particular respects.32 She was less impressed with the evidence of Mr Wicks, finding
29 Clause 2.1(b) Annexure A.
30 Judgment [59].
31 Judgment [59].
32 Judgment [60].
-- 11 of 59 --
12
that his evidence was “false in significant respects” and she was unimpressed with
his demeanour.33
[45] As the trial judge discussed, the course of much of the negotiations was evidenced by
emails and other documents.
[46] In 2014 QCPL sold such of its coal mining interests as had been served by the
Terminal. The negotiations were initiated by QCPL. In October 2015, and again in
February 2016, QCPL enquired of Mr Freeman whether “Adani” (the name used in
the correspondence to refer to the group of companies which included the appellant)
wished to acquire QCPL’s capacity.
[47] The trial judge found that from the outset, Adani made it clear that what had to be
negotiated was the price which QCPL would pay to be relieved of its obligations, and
that this was accepted by QCPL by February 2016.34
[48] On 18 March 2016, QCPL sent a “Term Sheet” to the appellant, which set out draft
terms for its departure on and from 1 July 2016. The proposed consideration was
a “relinquishment payment” by QCPL to the appellant by four annual instalments,
commencing on 30 June 2017. By this document, QCPL did not propose a particular
amount to be paid by it. It did so in a further Term Sheet which it submitted in April
2016,35 when QCPL proposed a figure of $180 million as the price it would pay.36
[49] On 9 May 2016, Mr Gibbons of Rio Tinto emailed Mr Freeman (copied to Mr Wicks
and another at Adani) proposing a series of payments, in total having a net present
value of $186.53 million. The derivation of that figure appeared from a table in which
the anticipated cost to QCPL of its ongoing performance of its user agreement was
set out, year by year, from which a net present value of that burden was shown at
$423.05 million. The table detailed payments, proposed to be made by QCPL over
the next five financial years, totalling $227.3 million, the present value of which was
that sum of $186.53 million.
[50] In the email, Mr Gibbons made these points:
“• You will understand that I am seeking to keep my annual
payments under what I would otherwise have paid in terms of
the total T/P (TIC/HCF)
o I suspect this may also suit your preferred tax effective
position
• From your perspective this $186.53m should more than
compensate for the expected loss of income likely in the next
price reset
o This represents around 6 years of our forecast TIC
payments or around 4.5 years of our forecast (TIC+HCF)
payments
33 Judgment [61].
34 Judgment [66].
35 The trial judge said that this was done by a term sheet submitted on 6 April 2016, within exhibit 8.
However the relevant email from QCPL (or Rio Tinto) was dated 22 April 2016.
36 Judgment [68].
-- 12 of 59 --
13
• Whilst the NPV provides a reference point for both parties the
only certainty in this equation is what is able to be agreed.
$186.59m [sic] is a considerable sum on money with certainty
attached.
o Adani Ports in addition to acquiring the $186.59m [sic]
contract relinquishment fee retains the upside of on
selling/reusing this capacity all the while also maintaining
its socialised port revenue base.”
In that last point, the appellant’s “socialised port revenue base”, to which Mr Gibbons
was referring, was the appellant’s ability to pass on the cost of the departure of a user
to the remaining users, through the higher charges, as I have discussed.
[51] Mr Freeman replied on 12 May 2016, making a counter offer under which QCPL
would make three payments, in the years ended 30 June 2017, 2018 and 2019,
totalling $350 million of which the net present value was said to be $310.68 million.
Mr Freeman there wrote:
“We continue to recognize [sic] that this needs to be a value sharing
process but also believe that this must be framed within the context of
risk and heavy weighting should not be applied to potential future
incomes which may or may not eventuate.”
By “the context of risk”, Mr Freeman’s evidence was that he was referring to the risks
of the damage to reputation and of litigation arising from the implementation of
“socialisation”.37 He said that his superiors regarded this as a real risk. By “potential
future outcomes”, it appears that Mr Freeman was referring to the potential for the
appellant to find another user, or to pass on the cost of QCPL’s departure to the
remaining users.
[52] In its email sent on 18 March 2016, QCPL requested a term whereby the appellant
would “grant an indemnity in favour of QCPL in respect of any claim against, or loss,
damage or increased cost to QCPL arising out of any dispute or litigation in
connection with the relinquished terminal capacity after 1 July 2016.” In an email
of 29 April 2016, Mr Freeman resisted the inclusion of the proposed indemnity,
saying that it could not be “accepted in its current form”. The trial judge referred to
Mr Freeman’s evidence that QCPL was then wanting an indemnity against claims
from other users, and that Rio Tinto had concerns about “reputational risks”
associated with relinquishing its user agreement.38 Mr Freeman said that Rio Tinto’s
concern was that “… if the other users found out about what had happened [QCPL]
might get sued”.39 Her Honour accepted that QCPL did apprehend that it might be
sued by other users.
[53] The trial judge noted that Mr Freeman acknowledged that the appellant intended to
“socialise the effect of the proposed QCPL transactions.” She also found that
Mr Freeman was “concerned to make it clear in his evidence that it was not his plan,
but the plan of others controlling [the appellant] who “instructed” him.40 Her Honour
said that Mr Freeman was there attempting to “distance himself from the actions of
37 Transcript 3-48, Judgment [82].
38 Judgment [73]
39 Transcript 3-43 quoted in the Judgment [73].
40 Judgment [78].
-- 13 of 59 --
14
his employer”, which indicated to her that Mr Freeman, as an honest witness, had not
wished to be associated with such a “socialisation”.41
[54] It was put to Mr Freeman, and accepted by him, that the then proposed effective date
of the QCPL transaction, which was 1 July 2016, was significant in that it was “the
date [which] marked the beginning of the review process for the TIC.”42 Her Honour
noted Mr Freeman’s evidence that this was the date which the appellant wanted, and
commented that Mr Freeman had “again sought to distance himself personally from
this matter”.43
[55] Rio Tinto continued to negotiate by emphasising its “sensible value sharing
approach”,44 a term which conveyed that Rio Tinto/QCPL would not pay an amount
which represented the present value of its entire burden under its user agreement.
[56] On 11 June 2016, an email was sent by Mr Gupta of Adani to others within the Adani
group, describing a proposal to be put by the appellant. The email was forwarded to
Mr Freeman two days later. The proposal contained an updated calculation sheet,
although the calculations of what would have been the cost to QCPL, year by year,
over the life of its user agreement, remain unchanged from those which had passed
between the parties from 9 May 2016. This was a proposal for QCPL to pay
$260 million as an initial payment,45 subject to a later adjustment depending upon
whether “socialisation” was “successful”. If socialisation was successful, the
appellant would repay to QCPL $50 million;46 if it was unsuccessful, QCPL would
pay a further $50 million.47 As Mr Gupta’s email summarised the proposal, “Adani
would either get $210m or $310m (plus associated tax)”.
[57] In his email of 13 June 2016 to Rio Tinto’s representatives, in which that proposal
was made, Mr Freeman wrote:
“… we would like to table a suggested approach to achieving an
outcome that meets the reasonable expectations of both organizations.
This is based on a pure 50% split of the value and risks of the
transaction including taxation implications and legal risk.”
The email referred to a meeting between the parties which was to take place on that day.
[58] At that meeting, there were discussions in which the proposal for adjusting the price,
according to whether there was socialisation, was abandoned. Mr Freeman’s
evidence was that the parties recognised that this “was going to be too difficult and
we’re better off just negotiating a number”.48
[59] At that meeting49 consensus was reached on a figure of $255 million as the amount
which QCPL would pay to end the relationship once and for all.50 This required the
approval of Mr Gautam Adani.51
41 Judgment [78].
42 Judgment [79].
43 Judgment [79].
44 Email 3 May 2016 referred to in the Judgment [74].
45 Plus 50 per cent of a tax benefit which would accrue to QCPL from the transaction, then estimated at
$39 million. AR 5692.
46 And some of the amount paid for the tax benefit.
47 With a further amount for the tax benefit.
48 Transcript 3-54; Judgment [88].AR 6429.
49 Or perhaps at a meeting on 14 June 2016, as the trial judge found at Judgment [89].
50 Transcript 3-55; Judgment [89].
51 Transcript 3-55; Judgment [89].
-- 14 of 59 --
15
[60] The trial judge noted that there was no further evidence as to how the parties
negotiated the final terms of the QCPL transactions, because Mr Freeman had little
to do with the negotiations after 14 June 2016.52 However, as her Honour discussed,
light was thrown upon the matter by a document prepared by PricewaterhouseCoopers
(PwC), dated June 2016, entitled “Analysis of options to allocate termination
payment”.
[61] The PwC report recorded its tasks as follows:
“Adani has negotiated a proposed payment of $255 million from
Queensland Coal (a wholly-owned subsidiary of Rio Tinto), as
consideration for Queensland Coal exiting its existing user agreement
with AAPT. The existing user agreement is for 9.3 million tonnes per
annum for the period FY2017 to FY2028 … .
The negotiated arrangement contemplates that the obligation under the
user agreement for an initial six year period FY2017-FY2022 would
be cancelled. The obligation relating to a second six year period
FY2023-FY2028 would be assigned to AMPL, which does not
anticipate a requirement for physical shipping capacity under the
assigned user agreement until FY2023.
Consequently, Adani needs to determine the appropriate share of the
total $255 million payment that would be provided to AAPT as
compensation for the cancellation of the initial period of capacity, and
that share which would be retained by AMPL for accepting Queensland
Coal’s obligation under the remaining term of the user agreement.
Adani has requested that PricewaterhouseCoopers Australia (PwC)
provide an opinion on the appropriate allocation of the total
$255 million payment between the two six year periods:
• FY2017-FY2022, to be paid as termination compensation
to AAPT (actual period ends March 2022), and
• FY2023-FY2028, to be retained by AMPL (actual period
commences April 2022).”
(emphasis in original)
[62] The report referred to modelling which estimated the TIC to be paid in future years,
whilst noting:
“However, the $255 million payment from [QCPL] is not directly
linked to, or derived from, forecasts in this model. Instead, it
represents a negotiated outcome between [QCPL] and AMPL, where
the amount would be paid in three instalments over the 12 months
comprising FY17. This prevents direct analysis of value drivers
behind the calculation of the $255 million amount, as a means of
determining an allocation between the two periods. The relatively
high level of uncertainty around value drivers in the AAPT draft tariff
model in later tariff reset periods adds further complication to attempts
to derive an appropriate allocation between time periods.”
52 Judgment [91].
-- 15 of 59 --
16
[63] Nevertheless, PwC used this modelling of the future TIC to apportion the amount of
$255 million between the two periods.53 Forecast charges in the modelling were
converted by PwC to present value amounts, and this determined the apportionment
of the $255 million payment.54 PwC thereby arrived at an allocation approximating
$118 million for the first period and $138 million for the second period, which
became the apportionment which was employed in the termination and novation
agreements. Mr Wicks agreed that the Adani companies decided between themselves
the apportionment of the sum of $255 million between the two QCPL transactions.55
The Arbitration
[64] In March 2017, the respondents referred a dispute about the TIC/TPC to apply on and
from 1 July 2017 to arbitration under cl 8.1 of their user agreements. The parties
agreed to the appointment of the Honourable Michael McHugh AC QC as the
arbitrator. An arbitration hearing was held in February 2019, and the relevant award
was delivered in May 2019.
[65] Of the many issues determined by the arbitrator, the presently relevant dispute
concerned the calculation of “Tonnes” in Schedule 7 of the user agreements, arising
out of what the arbitrator said were “competing views of the parties as to the
consequences of the termination of [the QCPL User Agreement] and termination
payments received from QCPL.”
[66] The arbitrator discussed the terms of the Deed of Novation and the Termination
Agreement. He discussed the respondent’s arguments by which they ultimately
contended that, consistently with their user agreements, the appellant was not entitled
to retain the benefit of the QCPL payments “without considering and ameliorating its
effect on the TIC to be paid by the Users.”56
[67] The arbitrator saw a flaw in the respondents’ case, which was that their arguments
effectively treated the individual user agreements “as an interlocking arrangement
under a single agreement with common terms to which each User is a party.”57 The
arbitrator observed that “the individual User Agreements with Adani, though in
similar form, entitle Adani to deal with individual Users in very different ways.”58
He noted that:
1. the duration of individual user agreements, and the TICs and TPCs payable
under those agreements, could vary significantly;
2. the user agreements did not purport to limit Adani’s freedom to contract with
any user, potential user or former user;
3. there was nothing which prevented user agreements between Adani and other
users ending, on the terms of those agreements, shortly before a Review,
leaving the remaining users to pay a higher TIC than if the other user
agreements had remained on foot;
53 FY2017-FY2022 and FY2023-FY2028.
54 With some adjustments for items which need not be discussed here.
55 Transcript 2-97.
56 Award para 299.
57 Award, para 300.
58 Award, para 300.
-- 16 of 59 --
17
4. the position the respondents now found themselves in was the same as if the
QCPL agreement had expired by effluxion of time at the end of the previous
review period;
5. the only relevance of any other agreement to a particular user was the other
user’s AMT which was part of the input to determine the “Tonnes” under
Item 3 became Schedule 7 of the particular user’s agreement;
6. the user agreements permitted Adani to settle access prices with any user,
whether or not in accordance with Schedule 7, with the result that the total
revenue to Adani was not necessarily based on a proportionate basis.59
[68] The arbitrator rejected a contention that the appellant was in breach of an implied
term to do all such things as are necessary to enable the other party to have the benefit
of the contract. He referred to what he saw as the unambiguous effect of Schedule 7
of the respondents’ agreements, and said that “any implied duty to cooperate cannot
be used to re-write the parties’ rights and obligations under their contract.”60
[69] The arbitrator rejected a further submission that the user agreements had an implied
term that the appellant would not terminate another user agreement “except in good
faith and for reasonable cause”. He held that such an implied term would not satisfy
any of the five conditions necessary to establish an implied term in fact.61 In
particular, he held that such a term would not be reasonable and equitable “given that
nothing in the User Agreement expressly restricts Adani’s freedom of contractual
relations with other third parties.”62
[70] The arbitrator rejected a contention that there was an alternative implied term that the
appellant would “give credit for any payments received to release another user from
obligations under a User Agreement”.63 He said that the user agreements gave no
basis for the implication of such a term, one reason being that “[i]n whole or in part,
the payment received is the consideration for Adani giving up rights that it had against
QCPL.”64 He rejected a further contention by the respondents that the appellant was being
reimbursed “twice for the same costs”,65 and said that “all that has occurred is that
Adani has done what the User Agreements permitted it to do [and that] [t]here is no
basis for the claim that a payment reimbursed it twice for the same costs.”66
[71] Further, the arbitrator rejected the premise that the payments, totalling $255 million,
represented the charges which QCPL would have had to pay in the five years
ending 30 June 2022, and which the remaining users would have to pay because of
QCPL’s departure. The arbitrator’s analysis was that:
(a) QCPL’s agreement had a duration until 2028, “well beyond” the current review
five year period, so that any payments made by QCPL could not be equated as
payments for QCPL’s obligation to pay the TIC between 1 July 2017 and
30 June 2022;67
59 Award, paras 300-306.
60 Award, para 324.
61 Award, para 331, citing BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266,
282-283.
62 Award, para 331(b).
63 Award, para 332.
64 Award, para 333.
65 Award, para 334.
66 Award, para 335.
67 Award, para 334(a).
-- 17 of 59 --
18
(b) the $138 million paid to AMPL under the novation agreement was for that
company to take on the risk of QCPL’s contracted tonnes from 1 July 2022 in
circumstances where it then had no operational mine and was taking on
a substantial risk with developing a mine. The payment of $138 million concerned
QCPL’s assigned tonnes for the next review period from 1 July 2022 and beyond;68
(c) in respect of the $117 million paid under the Termination Agreement, that
agreement had an “Effective Economic Date” of 1 July 2016, one year prior to
the present review date of 1 July 2017, and that agreement provided that the
parties should account as if the respective terminations for which the agreement
provided had occurred on 1 July 2016. This had the effect that QCPL was not
required to pay the TIC and the HCF fixed for the period 1 July 2016 to
30 June 2017, resulting in QCPL saving $51.9 million, which it would have
had a liability to pay Adani for that year;69
(d) in the circumstances, and at the best for the respondents, only $65.1 million of
the payment under the Termination Agreement could be said to have had any
connection with the five year review period under consideration by the
arbitrator.70
[72] As the trial judge correctly observed, the arbitrator’s award did not determine any
part of the unconscionability claim in the present proceeding, and nor did not decide
the questions about handling charges. The arbitrator recorded the concession by the
respondents that he had no power to determine their unconscionability claim.71
Unconscionability: the reasons of the trial judge
[73] Without referring to the arbitrator’s characterisation of the QCPL payments,72 the
trial judge reached a different view. Her Honour found that the amount of
$255 million which the appellant received from QCPL was “referable” to the period 1
July 2016 to 30 June 2022.73
[74] Her Honour reached that finding in this way. She referred to a “gap in the evidence”74
about what happened between the time at which the figure of $255 million was agreed
on 13/14 June 2016 and the signing of the agreements on 31 October 2016. She noted
that at that earlier date, the basis for agreement on that figure was the present value
of QCPL’s obligations over a period from 30 June 2016 to 30 June 2028, with
a discount for “value sharing”.75 But her Honour then remarked that “the amount of
$255 million was very close indeed to the present value of the amount which QCPL
would have paid for TIC and HCF for the period up to 30 June 2022.”76 This was an
apparent reference to a calculation of that value in a report of a witness, Mr Houston.
Mr Houston calculated the worth of QCPL’s obligations to pay the TIC/TPC and HCF
in each of the six years to 30 June 2022, expressed in 2017 dollar terms, as
$266.5 million.77 Her Honour continued:78
68 Award, para 334(b).
69 Award, para 334(c).
70 Award, para 334(c), (d).
71 Judgment [16]-[17].
72 Discussed at [67]-[71] above.
73 Judgment [136].
74 Judgment [133].
75 Judgment [133].
76 Judgment [135].
77 Houston Report [112].
78 Judgment [135].
-- 18 of 59 --
19
“Perhaps the pre-agreed figure determined the two time periods
evident in the QCPL transactions (2016 to 2022 and 2022 to 2028).
Perhaps the date of 1 July 2022 was the time when AMPL thought it
might need terminal facilities. While these are possibilities, the lack of
evidence prevents me making a finding.”
[75] Her Honour continued:79
“Clearly, although both the termination agreement and the novation
agreement are dated 31 October 2016, the novation agreement must
have been first in time. If it were not, QCPL would have had nothing
to assign. Thus, once the assignment effected by the novation
agreement had occurred, the only obligations which QCPL had to the
[appellant] were in respect of the period 1 July 2016 to 30 June 2022.
I find, therefore, that the amount of $255 million which the [appellant]
has received from QCPL is referrable to that period.”
[76] That finding featured in her Honour’s subsequent consideration of whether, in the
language of s 22(1)(b) of the ACL, the users had been required to comply with
conditions which were not reasonably necessary for the protection of the appellant’s
legitimate interests. The trial judge there said:
“[191] The $255 million payment was agreed when the [appellant]
intended not to be out of pocket as a result of QCPL’s departure:
until 1 July 2022 the remaining users would pay QCPL’s share
of TIC and HCF, and after that AMPL would (ex 3). The
[appellant] will be paid two sums of money for the period 1 July
2017-30 June 2022, both referable to QCPL’s contractual
obligation to it. Whereas, had the QCPL [User Agreement]
remained on foot, it would only have received one such sum.
The $255 million payment is a large extra payment compared to
the [appellant]’s entitlements under the default pricing
mechanism provided by the user agreements. The [appellant]
has become entitled to that extra payment without cost to itself,
and without having to provide anything extra to any remaining
user. In that sense there is a quality of windfall about the
$255 million payment.
[192] As discussed above, the [appellant] went out of its way to
structure the transactions so that it received an extra
$255 million payment. The way it achieved that was to impose
a detriment on the remaining users. In that sense the payment is
at the expense of the users.”
[77] The same finding was a premise for her Honour’s assessment of damages, as I will
later discuss below.
[78] The trial judge described “[t]he nub of the respondent’s unconscionable conduct case”
as being that “in receiving the $255 million consideration under the QCPL
transactions, the [appellant] in effect accepted payment for QCPL’s future TIC and
HCF obligations until 30 June 2022 but required the remaining users to pay the
79 Judgment [136].
-- 19 of 59 --
20
equivalent of QCPL’s TIC and HCF obligations during this period.”80 By that
statement, it was the appellant’s insistence upon the performance by the respondents
of their user agreements, that was found to have been unconscionable.
[79] The judge found, in the appellant’s favour, that it had “not breached any of the user
agreements”, and that its “conduct in demanding a price from QCPL to be relieved of
its obligations under its user agreements appears ordinary enough.”81 She further
found that it “must have been in the objective contemplation of the parties” and was
“plainly foreseeable” that a user might agree to terminate its user agreement “on terms
that it paid the owner [the appellant] to be relieved of its obligations.”82 The trial
judge observed, correctly, that “the fact that there is no breach of contract is not a bar
to the availability of the statutory remedy”.83
[80] However, in other parts of the Judgment, the judge seemed to take a broader view of
what constituted the appellant’s unconscionable conduct. One of the reasons for her
Honour’s ultimate conclusion of unconscionable conduct, was that the appellant
“attempted to disguise its behaviour in complex transactions”.84
[81] As already noted, her Honour made adverse credit findings against Mr Wicks.85
Those findings are not challenged. However what is challenged is the judge’s use of
the performance by Mr Wicks, as a witness, as an indication of the appellant’s
unconscionability in the events in question.
[82] Her Honour was critical of affidavit evidence from Mr Wicks that the termination
payment of $117 million “represented a negotiated settlement between the parties and
was not an amount worked out by reference to a calculation based on forecast charges
payable by QCPL under the QCPL User Agreement.” Her Honour considered this to
be plainly false because what stood out from the documents evidencing the
negotiations, she said, was that the amounts to be paid “were very much based on its
future obligations under its user agreement.”86
[83] Her Honour was critical of affidavit evidence of Mr Wicks, as to a suggested concern,
by the Adani companies, that there existed a real risk of QCPL ceasing to be of good
financial standing so as to be able to fulfil its obligations under its user agreement.
Mr Wicks swore that a significant factor for Adani in these transactions was “the
presence of these risks”.87 Her Honour found that the “idea of QCPL’s
creditworthiness was only raised as a construct to show some commercial purpose for
payment by QCPL to the [appellant] and AMPL which was not related to the
extinguishment of QCPL’s future financial obligations under its user agreement.”88
She found that there was “no genuine concern about QCPL’s credit at 10 March 2016,
or at any time subsequent to that. Want of Credit Support was not the reason or
a reason, for the QCPL transactions.”89 She found that an email sent by Mr Freeman
80 Judgment [57].
81 Judgment [164].
82 Judgment [164].
83 Judgment [165].
84 Judgment [207]. See also Judgment [103], [120]-[122], [143].
85 Judgment [59]-[63].
86 Judgment [96].
87 Affidavit of Mr Wicks, 12 February 2019, quoted in the Judgment [104].
88 Judgment [113].
89 Judgment [120].
-- 20 of 59 --
21
on 15 July 2016, which suggested otherwise, was “an attempt to document an
apparent reason for the QCPL transactions which did not exist.”90
[84] On this point, her Honour referred to recitals G and H of the Termination Agreement,
which were as follows:
“G QCPL no longer has need for any capacity under the User
Agreement at the [Terminal] and has been unable to identify
willing acquirers with demand for that [Terminal] capacity.
H QCPL has not provided information as requested to [the
appellant’s] request of March 10, 2016 concerning QCPL’s
credit standing, and QCPL’s position is that it will not be
responsive to requests from [the appellant] for Credit Support.”
[85] Her Honour found that these recitals were “irrelevant to the QCPL transactions and
represent the last vestiges of the disguise which the [appellant] attempted.”91
[86] The judge found that the terms of the three agreements, made on 31 October 2016,
did not correspond in all respects with the appellant’s commercial objective, which
was that it should receive the entirety of the monies paid by QCPL. The judge
rejected the appellant’s pleaded case that the payment by QCPL to AMPL under the
novation agreement “was a commercial payment justified by AMPL agreeing to
assume QCPL’s rights and liabilities under its user agreement … from 1 July 2022
onwards …”.92
[87] The judge suggested that there were other ways in which the same outcome, between
the appellant and QCPL, could have been achieved, and that the appellant’s deliberate
choice to structure the transactions dealing with QCPL’s departure was relevant to
the question of unconscionability. Her Honour queried why “there was not
a straightforward novation of the entire QCPL [User Agreement] to AMPL”93 and
that “[i]t would have been simple to provide for [the amount of $255 million] to have
been paid either (a) to AMPL to compensate it for its having to bear these burdens
before it had coal to be handled at the terminal, or (b) to the [appellant] as a pre-
payment of those obligations.”94 Her Honour appeared to consider that the avoidance
of that “straightforward scenario”95 was explicable, upon the basis that under it “the
QCPL tonnes would have remained the denominator for calculating TIC and HCF, so
the users would not have paid more.”96 The judge noted that “[t]o achieve
socialisation of the burden of QCPL’s departure, it was necessary to have both the
[Termination Agreement] and the novation agreement”.97 In her view, the Security
Deposit Agreement was a means of providing the appellant with the entirety of the
$255 million, “but covertly”.98
[88] The judge concluded that the three agreements were “more complicated than
necessary to document the real transaction between QCPL, AMPL and the [appellant]
90 Judgment [121].
91 Judgment [122].
92 Judgment [132].
93 Judgment [139].
94 Judgment [139].
95 Judgment [140].
96 Judgment [140].
97 Judgment [141].
98 Judgment [142].
-- 21 of 59 --
22
because they sought also to achieve socialisation of the burden of QCPL’s departure
and to disguise or camouflage this.”99
[89] The judge said that under a straightforward “price for relinquishment” agreement, the
appellant would have received the whole of the consideration, but that would have
had the “socialisation apparent on the face of the documents” and it would not have
advantaged AMPL.100 She said that the three transactions were made “in the interests
of not just the [appellant], but at least of the [appellant] and AMPL, and possibly the
wider Adani Group.”101
[90] After some discussion of the authorities, her Honour then considered the case in the
framework of s 22 of the ACL. At this point, it is convenient to set out the terms s 22(1):
“(1) Without limiting the matters to which the court may have regard
for the purpose of determining whether a person (the supplier)
has contravened section 21 in connection with the supply or
possible supply of goods or services to a person (the customer),
the court may have regard to:
(a) the relative strengths of the bargaining positions of the
supplier and the customer; and
(b) whether, as a result of conduct engaged in by the supplier,
the customer was required to comply with conditions that
were not reasonably necessary for the protection of the
legitimate interests of the supplier; and
(c) whether the customer was able to understand any
documents relating to the supply or possible supply of the
goods or services; and
(d) whether any undue influence or pressure was exerted on,
or any unfair tactics were used against, the customer or
a person acting on behalf of the customer by the supplier
or a person acting on behalf of the supplier in relation to
the supply or possible supply of the goods or services; and
(e) the amount for which, and the circumstances under
which, the customer could have acquired identical or
equivalent goods or services from a person other than the
supplier; and
(f) the extent to which the supplier's conduct towards the
customer was consistent with the supplier's conduct in
similar transactions between the supplier and other like
customers; and
(g) the requirements of any applicable industry code; and
(h) the requirements of any other industry code, if the
customer acted on the reasonable belief that the supplier
would comply with that code; and
99 Judgment [143].
100 Judgment [144].
101 Judgment [144].
-- 22 of 59 --
23
(i) the extent to which the supplier unreasonably failed to
disclose to the customer:
(i) any intended conduct of the supplier that might
affect the interests of the customer; and
(ii) any risks to the customer arising from the supplier's
intended conduct (being risks that the supplier
should have foreseen would not be apparent to the
customer); and
(j) if there is a contract between the supplier and the
customer for the supply of the goods or services:
(i) the extent to which the supplier was willing to
negotiate the terms and conditions of the contract
with the customer; and
(ii) the terms and conditions of the contract; and
(iii) the conduct of the supplier and the customer in
complying with the terms and conditions of the
contract; and
(iv) any conduct that the supplier or the customer
engaged in, in connection with their commercial
relationship, after they entered into the contract; and
(k) without limiting paragraph (j), whether the supplier has a
contractual right to vary unilaterally a term or condition
of a contract between the supplier and the customer for
the supply of the goods or services; and
(l) the extent to which the supplier and the customer acted in
good faith.”
[91] The trial judge recorded that she had considered all the subsections of s 22(1) and
could see no relevance in this case of paragraphs (c), (d), (g), (h) or (k).
[92] As to the matter in s 22(1)(a), the judge said that the evidence about the negotiations
about the respondents’ user agreements, which had been between the Ports Corporation
and the respondents negotiating as a group, “[did] not disclose anything relevant”.102
[93] Referring to s 22(1)(j)(ii) and (iii), her Honour noted that there was no allegation by
the respondents that the appellant had breached the terms of their user agreements,
which she said was a “very relevant factor”, and tended against a finding of
unconscionable conduct.103 Her Honour added that this was “particularly so … where
what the respondents complain of, is the exercise of a contractual entitlement, namely,
to charge TIC and HCF determined in accordance with the contract.”104
[94] The trial judge said that the fact that the appellant had not breached the user
agreements, and that it was entitled to a price to relinquish its rights against QCPL
102 Judgment [160].
103 Judgment [161].
104 Judgment [161].
-- 23 of 59 --
24
under the QCPL User Agreement, were “very strong points in its favour”.105
However, her Honour said, there were two respects in which the user agreements
were “unusual” and which diminished the strength of the appellant’s case.
[95] The first of them was that the user agreements were for lengthy durations. Therefore
there was “an increased chance of the factual circumstances against which the parties
contracted changing substantially over time”, such as in this instance the “significant
change to the identity of the owner of the terminal”.106
[96] The second aspect of the user agreements was that they formed “part of a set of
standard form agreements regulating the rights of all of the users who share the
terminal”,107 which accorded with “the reality that the terminal is shared by several
users”.108 Her Honour said that “expressly and implicitly, the user agreements
recognise that all the users’ economic fortunes are to some extent linked because of
their shared use of the terminal”, making each user “vulnerable to the commercial
effects of the owner dealing with another user”.109
[97] Addressing s 22(1)(e), the trial judge said that this was a relevant consideration
because of the monopolistic position of the appellant, with the respondents having no
option but to deal with the appellant in order to export their coal.110 Her Honour saw
their position as analogous to that of the successful respondent in Ipstar Australia Pty
Ltd v APS Satellite Pty Ltd.111
[98] Also relevant, in her Honour’s view, was the restriction on the rights of the users to
terminate their agreements, and the take-or-pay nature of them. Her Honour said that
“[t]he respondents are contractually locked into a long term, [financially] onerous
relationship with the owner.”112 All of those factors, in her Honour’s view, put the
respondents in a position of economic vulnerability.113
[99] Next, the trial judge discussed “the identity of the Supplier and its Commercial
Motivations”, which her Honour related to s 22(1)(b) “to some extent”.114 Her
Honour saw as a relevant factor, that the appellant had become the supplier of the
service in place of the Ports Corporation.115 That was significant in the circumstance
that the appellant had become the effective owner of the Terminal, not under the
assignability provisions of the user agreements, but pursuant to “an act of State
power”.116 Also significant in her Honour’s view was the circumstance that the
transfer by Ports Corporation was made “in favour of the Adani Group which
included AMPL, a company which aims to develop a very large coal mine, and export
coal through the terminal”.117 Further, at the time of the conduct in question, the
appellant was a related entity of the operator of the Terminal (APO).118 The relevance
105 Judgment [167].
106 Judgment [168].
107 Judgment [169].
108 Judgment [170].
109 Judgment [172].
110 Judgment [174].
111 (2018) 356 ALR 440; [2018] NSWCA 15.
112 Judgment [175].
113 Judgment [176].
114 Judgment fn 73.
115 Judgment [178].
116 Transfer pursuant to the Infrastructure Investment (Asset Restructuring and Disposal) Act 2009 (Qld).
117 Judgment [181].
118 Judgment [182].
-- 24 of 59 --
25
of these matters, in her Honour’s view, was that “the users were not only locked into
long term contracts with a monopolistic supplier who controlled an asset vital to their
businesses, but that supplier was no longer a Government entity which did nothing
but operate the port; it was a private company with its own profit motives”,119 and
that profit motive was “potentially at odds with the users”.120 Her Honour found these
circumstances increased the “vulnerability” of the users.121
[100] Her Honour then addressed the question of whether, in the terms of s 22(1)(b), the
users were required to comply with conditions that were not reasonably necessary for
the protection of the appellant’s legitimate interests. In the discussion which
followed, her Honour does not appear to have considered that any of the conditions
of the user agreements, most importantly the Schedule 7 pricing mechanism which
was common to all user agreements, was unnecessary for the protection of the
legitimate interests of the supplier (the appellant). Rather, her Honour accepted the
respondents’ argument that the agreements of October 2016 made compliance with
that pricing mechanism unnecessary for the protection of the appellant’s interests.
There followed the discussion by the trial judge at [191] and [192] of the Judgment
which I have set out earlier.
[101] The trial judge went yet further, saying that the appellant “went beyond acting in its
own interests and acted in the interest of AMPL in structuring and entering into the
QCPL transactions and the [Security Deposit Deed]”.122 This, in her view, “was not
part of the ordinary or legitimate aspects of the business of a terminal owner”.123
[102] Her Honour did not accept an argument for the respondents that the appellant had
acted unconscionably by structuring the QCPL transactions so that there was only
a relatively short period of time in which there was excess capacity, from the
departure of QCPL, before the arrival of AMPL. It was said that the shortness of this
period made it impossible for the capacity to be utilised by another miner. Her Honour
noted the evidence that the appellant had offered the remaining users an increase on
their AMT, and that only one of the respondents had shown interest. That respondent
had asked for a substantial increase from 2020 until 2029, which was rejected by the
appellant except for the period of two years preceding the arrival of AMPL.124
[103] Her Honour returned to the subject of the alternative courses, which were available
to the appellant in structuring the transactions for the departure of QCPL, which, in
her view, would have protected the appellant’s “own legitimate interests”.125 She
said that the structure which was effected required “[m]ore effort and some
sophistry”, and did not “document the bargain reached by Mr Freeman”.126 Referring
to judgments in Australian Securities and Investments Commission v Kobelt
(“Kobelt”),127 her Honour said that “the existence of an alternative means of
achieving its ends without causing detriment to the respondents” was relevant.
119 Judgment [183].
120 Judgment [183].
121 Judgment [184].
122 Judgment [193].
123 Judgment [193] citing Keane J in Paciocco v Australia and New Zealand Banking Group Ltd (2016)
258 CLR 525 [2016] HCA 28 at [274].
124 Judgment [194], [195].
125 Judgment [196].
126 Judgment [196].
127 (2019) 267 CLR 1; [2019] HCA 18 at [43] per Kiefel CJ and Bell J; [98] per Gageler J.
-- 25 of 59 --
26
[104] Her Honour remarked that the appellant’s conduct was “deliberate, not just heedless
or indifferent to the position of the remaining users”, which was evident from the
timing and structure of the QCPL transactions.128
[105] Referring to s 22(1)(l), her Honour then considered whether the appellant had acted
in good faith. Acknowledging that unconscionability under this provision required
“an objective value judgment on behaviour”, her Honour said that it had been
recognised that “the subjective state of mind of the alleged contravener whether actual
or constructive is relevant in the broader sense”.129 In that way, her Honour saw
relevance in what “the [appellant], QCPL, and Mr Freeman thought of the conduct
sought to be impugned.”130
[106] The judge noted that the appellant had recognised a risk that its conduct might be
successfully impugned in subsequent litigation, and had legal advice on its position
before April 2016.131 The appellant was “aware of risks to its reputation and of
litigation” and had "attempted to disguise the fact that its bargain with QCPL involved
no more than fixing a price for QCPL’s departure, based on QCPL’s future
obligations”.132 By the “convoluted terms of the [Security Deposit Agreement]”, the
appellant was said to have “camouflage[d] the fact that, at its discretion, it could keep
the whole $255 million payment.”133
[107] Her Honour inferred that QCPL’s state of mind, as to the commercial morality of
socialisation, was similar to that of the appellant.134 QCPL had insisted on the
Indemnity being included in the Termination Agreement. Her Honour appeared to
have inferred from QCPL’s concern that QCPL had believed that it was doing
something which was commercially immoral.
[108] Her Honour considered that Mr Freeman had “spontaneously distanced himself from
the conduct which the respondents seek to impugn” which was an indication to her of
“some shame or repugnance at the conduct”.135
[109] Her Honour returned to her earlier findings that the appellant’s behaviour, in
attempting to disguise or camouflage the true basis of its dealings with QCPL,
involved “serious dishonesty”,136 saying that it had been designed “to prevent
remaining users having a true appreciation of the QCPL transactions, and thus their
legal rights”.137
[110] Her Honour’s conclusions, as to unconscionable conduct, were summarised in this
passage:
“[207] As explained at [172], [176] and [184] above there were several
factors which made the respondents vulnerable to an exercise of
128 Judgment [197], citing Keane J Kobelt at [118], who referred to Kakavas v Crown Melbourne Ltd
(2013) 250 CLR 392 at 439 [161].
129 Citing Australian Competition and Consumer Commission v Medibank Private Ltd (2018)
267 FCR 554; [2018] FCAFC 235 at [247] per Beach J.
130 Judgment [199] (emphasis added).
131 Judgment [200].
132 Judgment [200].
133 Judgment [200].
134 Judgment [201].
135 Judgment ]202].
136 Judgment [203].
137 Judgment [204].
-- 26 of 59 --
27
contractual power by the [appellant]. Counsel for the second to
fourth respondents characterised the result of these matters as
“situational disadvantage and vulnerability” to the [appellant]
within the meaning of the decided cases. I accept that. The
[appellant] exercised contractual power to obtain a large
financial reward. It deliberately chose to do so knowing that it
would thereby disadvantage the respondents. It was not just
acting in its own commercial interests as port owner; it was
acting on instructions from, and in the interests of AMPL. There
were alternatives available which would have enabled it to
protect its own interests; advantage AMPL, and not
disadvantage the respondents. It, QCPL and Mr Freeman
recognised that its conduct was not within the boundaries of
normal commercial behaviour. It attempted to disguise its
behaviour in complex transactions. It attempted to include
dishonest recitals in those transactions. It pleaded matters which
were false in this proceeding and had Mr Wicks give false
evidence in its case. In my view these matters establish
unconscionable conduct as alleged by the respondents. They
overwhelm the fact that the [appellant] was contractually
entitled to act as it did.”
Damages: the trial judge’s reasons
[111] After quoting s 236(1) of the ACL, her Honour said that the Court’s task was to
compare the position in which the respondents were in, with the position in which
they would have been, had there been no contravention.138 The appellant had
“socialised, or shared the burdens of the QCPL transactions, but not their benefits.”139
In her view, damages were to be calculated on the basis that the appellant “ought to
have brought into account the money it received from QCPL.”140 Alternatively, her
Honour said, damages could be assessed by “effectively putting the QCPL tonnes
back into the denominator for the formulas for TIC and HCF and describing the extra
that the respondents have paid as loss because of the unconscionable conduct.”141 In
a footnote, her Honour said “[b]ecause the amount of $255 million is so close to being
the present value of QCPL’s obligations under its user agreement between 1
July 2016 and 30 June 2022, damages calculated on this alternative basis are not very
different from those calculated on the basis I adopt; they are slightly more.”142 Her
Honour continued:
“[211] Although it is a slightly more sophisticated approach, I think
that the conduct in contravention should be regarded as charging
pursuant to the user agreements without bringing into account
the $255 million payment. If that is so, the basis for calculation
of damages which I have adopted produces loss and damage
suffered because of the conduct.
[212] The respondents have suffered loss from 1 July 2017 and will
continue to do so until 30 June 2022. The amount of
138 Judgment [208]-[209].
139 Judgment [209].
140 Judgment [209].
141 Judgment [210].
142 Judgment fn 91.
-- 27 of 59 --
28
$255 million was paid in respect of the period 1 July 2016 to
30 June 2022. To put the respondents in the position they would
have been had the [appellant] shared the benefits of the QCPL
transactions, as well as the burden of those transactions,
a proportionate amount of the $255 million payment ought to be
paid to the respondents as damages. Understandably
calculations in relation to this were somewhat complex and
were the subject of evidence. Except for one point, the
economists Mr Houston and Professor Grey agreed as to what
the amount of damages was.”
The nature of unconscionability
[112] Section 21(1) of the ACL provides that a person must not, in trade or commerce, in
connection with the supply of services to a person, engage in conduct that is, in all of
the circumstances, unconscionable.
[113] By s 21(4) it is the stated intention of the Parliament that (relevantly):
• the section is not limited by the unwritten law relating to unconscionable
conduct; and that
• in considering whether conduct to which a contract relates is unconscionable,
a court’s consideration of the contract may include consideration of the terms
of the contract, the manner in which and the extent to which the contract is
carried out and is not limited to consideration of the circumstances relating to
the formation of the contract.143
[114] Section 22(1) of the ACL prescribes a non-exhaustive list of considerations to which
a Court may have regard for the purpose of determining whether a supplier has
contravened s 21.
[115] In Kobelt, the High Court considered the relevantly identical provisions of the
Australian Securities and Investments Commission Act 2001 (Cth) (the ASIC Act).144
Each of the five judgments described the necessary level of gravity of conduct for it
to be unconscionable in this statutory sense.
[116] Kiefel CJ and Bell J said that the term unconscionable, being undefined in the ASIC
Act (and the ACL), “is to be understood as bearing its ordinary meaning.145 Their
Honours said:146
“The proscription in s 12CB(1) is of conduct in connection with the
supply of financial services that objectively answers the description of
being against conscience. The values that inform the standard of
conscience fixed by s 12CB(1) include those identified by Allsop CJ
in Paciocco v Australia & New Zealand Banking Group Ltd: certainty
in commercial transactions, honesty, the absence of trickery or sharp
practice, fairness when dealing with customers, the faithful
performance of bargains and promises freely made, and:
143 Section 21(4)(a), (c).
144 Section 12CB(1), (4) and s 12CC(1).
145 Kobelt at [14].
146 Kobelt at [14].
-- 28 of 59 --
29
“the protection of those whose vulnerability as to the protection
of their own interests places them in a position that calls for
a just legal system to respond for their protection, especially
from those who would victimise, predate or take advantage”.”
[117] Justice Gageler said that the function of a court exercising jurisdiction in a matter
arising under this section is to recognise and administer the normative standard of
conduct which the section itself marks out.147 In his view, it was significant that the
Parliament had appropriated “the terminology of courts administering equity in the
expression of the normative standard which the section prescribes”,148 signifying “the
gravity of the conduct necessary to be found by a court in order to be satisfied of
a breach of that standard”.149 He acknowledged that this statutory standard had
a “potential application within a range of factual scenarios not all of which would be
recognised in equity as giving rise to relief on the basis of unconscionable
conduct”.150 But the appropriation of the terminology of equity and the expression
of the normative standard, he said, did not authorise a court exercising jurisdiction
under that section “to dilute the gravity of the equitable conception of unconscionable
conduct so as to produce a form of equity-lite”.151 His Honour expressed regret for
having described, in his judgment in Paciocco,152 the required conduct as involving
“a high level of moral obloquy”. He explained that by that description, he meant to
convey that “conduct proscribed by the section as unconscionable is conduct that is
so far outside societal norms of acceptable commercial behaviour as to warrant
condemnation as conduct that is offensive to conscience”.153
[118] Justice Keane said:
[118] The use of the word “unconscionable” in s 12CB – rather than
terms such as “unjust”, “unfair” or “unreasonable” which are
familiar in consumer protection legislation – reflects
a deliberate legislative choice to proscribe a particular type of
conduct. In its ordinary meaning, the term “unconscionable”
requires an element of exploitation. The term imports the “high
level of moral obloquy” associated with the victimisation of the
vulnerable. As five members of this Court observed recently in
Thorne v Kennedy, a finding of unconscionable conduct
requires the unconscientious taking advantage of a special
disadvantage, which has “been variously described as requiring
‘victimisation’, ‘unconscientious conduct’, or ‘exploitation’”.
And in Kakavas v Crown Melbourne Ltd, this Court
unanimously confirmed that “[h]eedlessness of, or indifference
to, the best interests of the other party is not sufficient” to
establish the “predatory state of mind” that must be shown.
[119] The legislative choice of “unconscionability” as the key
statutory concept, rather than less morally freighted terms such
as “unjust”, “unfair” or “unreasonable”, confirms that the moral
147 Kobelt at [87].
148 “ Kobelt at [88].
149 Kobelt at [88].
150 Kobelt at [89].
151 Kobelt at [90].
152 (2016) 258 CLR 525.
153 Kobelt at [91]-[92].
-- 29 of 59 --
30
obloquy involved in the exploitation or victimisation that is
characteristic of unconscionable conduct is also required for
a finding of unconscionability under s 12CB. Section 12CB(4)(a) of
the ASIC Act does not require a contrary conclusion. The
direction in s 12CB(4)(a) means that the application of
s 12CB(1) is not limited to conduct that has been held to be
“unconscionable” under the general law, but it does not operate
to give the term “unconscionable” a meaning different from its
ordinary meaning. Adherence to the ordinary meaning of the
term “unconscionable” is appropriate for two reasons rooted in
the nature of the judicial function. First, the courts must give
effect to what Parliament has enacted. Here, it must be
acknowledged that the Parliament has deliberately chosen to use
this expression as the focus of attention, and not a more open-
textured or morally neutral expression that would be less certain
in its scope. And secondly, the appellant did not propound
a meaning for “unconscionable” different from its ordinary
meaning; and so the respondent had no occasion or opportunity
to meet such a contention.”
(Footnotes omitted.)
[119] Justices Nettle and Gordon said that the list of factors set out in s 12CC (the equivalent
of s 22(1) of the ACL) “necessarily implies that the statutory conception of
unconscionability is more broad-ranging than that of the unwritten law”, but that
“[n]evertheless, the unwritten law has a significant part to play in ascribing meaning
to the term “unconscionable” under s 12CB(1).”154 They extensively discussed the
unwritten law of unconscionable conduct, which signified the gravity of the conduct
which was required for unconscionability in the statutory sense. They said that under
the unwritten law, unconscionable conduct does not require a finding of dishonesty,
although it is not merely concerned with what is “fair” or “just”.155
[120] Justice Edelman described the background of the statutory proscription of
unconscionable conduct as being “in equitable doctrine and the repeated responses
by parliaments to that equitable doctrine.”156 He described the series of amendments
of that statutory proscription as involving “continued efforts to require courts to take
a less restrictive approach shorn from either of the equitable preconditions imposed
in the 20th century, by which equity had raised the required bar of moral
disapprobation.”157 His Honour said:158
“Like other open-textured criteria, such as “unfair” or “unjust”, there
is no clear baseline moral standard for what constitutes
“unconscionable” conduct within s 12CB of the ASIC Act.
Nevertheless, the history of development of that statutory proscription
demonstrates a clear legislative intention that the bar over which
conduct will be unconscionable must be lower than that developed in
154 Kobelt at [144].
155 Kobelt at [149] citing Commercial Bank of Amadio [1983] HCA 14; (1983) 151 CLR 447 at 478 per
Deane J and Attorney-General (NSW) v World Best Holdings Ltd (2005) 63 NSWLR 557;
223 ALR 346; [2005] NSWCA 261 at [121].
156 Kobelt at [279].
157 Kobelt at [295].
158 Kobelt at [295].
-- 30 of 59 --
31
equity even if the bar might not have been lowered to the
“unreasonableness” and “unfairness” assessments in the various
categories in 19th century equity.”
[121] In the present case, the trial judge found that the appellant exploited a vulnerability
of the respondents. More recently, in Australian Competition and Consumer
Commission v Quantum Housing Group Pty Ltd,159 the Full Court of the Federal
Court (Allsop CJ, Besanko and McKerracher JJ), in an analysis of Kobelt, observed
that in only one of the judgments (that of Keane J) was there said to be a requirement,
in every case, for “some form of pre-existing disability, vulnerability or disadvantage
of which advantage was taken.”160 Nevertheless, as I will discuss, the judge’s error
in finding this vulnerability is important for the outcome of this appeal.
[122] Section 21(1) proscribes conduct that is in all the circumstances, unconscionable. As
s 21(4)(c) illustrates, the circumstances will include the contractual context in which
the conduct occurred, whether in the formation, enforcement or performance of that
contract. Section 21 operates to require a standard of conduct, in a contractual
context, which involves a fidelity to the bargain. In his judgment in the Full Court of
the Federal Court in Paciocco & Anor v Australia and New Zealand Banking Group
Ltd,161 Allsop CJ said:
“The variety of considerations that may affect the assessment of
unconscionability only reflects the variety and richness of commercial
life. It should be emphasised, however, that faithfulness or fidelity to
a bargain freely and fairly made should be seen as a central aspect of
legal policy and commercial law. It binds commerce; it engenders
trust; it is a core element of decency in commerce; and it gives life and
content to the other considerations that attend the qualifications to it
that focus on whether the bargain was free or fair in its making or
enforcement.”
Consideration of the appellant’s conduct: unconscionability?
[123] As can be seen, there were many considerations which contributed to the trial judge’s
ultimate conclusion of unconscionable conduct. However, the case which the judge
upheld had two core elements.
[124] The first of them was that the appellant had received $255 million, which was said to
be referrable to the charges which would have been paid by QCPL for the six year
period ending on 30 June 2022. Put another way, QCPL had paid that sum for the
termination of its user agreement, under which, by then, QCPL’s liability had been
confined to that period.162
[125] The second element was that the appellant had then insisted upon the performance by
the other users of their agreements, by which the appellant would receive substantially
the same sum. The other users were required to pay more, so that the appellant could
be paid twice for the provision of the same service.
159 (2021) 388 ALR 577; [2021] FCAFC 40.
160 Australian Competition and Consumer Commission v Quantum Housing Group Pty Ltd (2021)
388 ALR 577; [2021] FCAFC 40 at [78].
161 (2015) 236 FCR 199 at 275; [2015] FCAFC 50 at [297].
162 By the effect of the Deed of Novation.
-- 31 of 59 --
32
[126] It is convenient to discuss first the judge’s finding that the sum of $255 million was
referable to QCPL’s obligations for the period from 1 July 2016 until 30 June 2022.
That finding, in my respectful view, was inconsistent with the evidence of the
negotiations by which that sum was agreed.
[127] Those negotiations occurred in the context that QCPL had not used the Terminal since
2014, and that consequently, it was in breach of its user agreement. By cl 4.4 of the
agreement, QCPL was obliged to use all reasonable endeavours to present its AMT
through the Terminal each financial year.
[128] QCPL had no need for the Terminal. It was unable to terminate unilaterally its
agreement. In the absence of a breach by the appellant, QCPL could be released from
its agreement only with the appellant’s concurrence. It was unremarkable, and indeed
inevitable, that QCPL would be required by the appellant to pay a substantial
consideration to be released from its contract.
[129] Their negotiations proceeded upon the basis of a set of projections of the anticipated
costs to QCPL of remaining bound by its user agreement, year by year, to 2028.163
The projections were presented by QCPL soon after the commencement of the
negotiations, and were not challenged by the appellant at any stage.
[130] The course of the negotiations, culminating in a consensus on the amount of
$255 million, is clear from the evidence which I have discussed. QCPL’s position
was that it should be permitted to depart at a price which was a substantial discount
on the projected cost to it of remaining bound by its contract. QCPL pointed to the
possibility of the appellant finding a new user, or an existing user or users, who would
agree to take up all or some of QCPL’s tonnage. It pointed also to the possibility that
existing users might be required to pay more, under their agreements, by
“socialisation”. These possibilities were just that; at that time, the appellant could not
have been certain about when, if at all, any of them would eventuate. The possibility
of socialisation was subject to an uncertainty as to whether that course would be
inconsistent with the express and implied terms of the user agreements, as the
respondents subsequently argued in the arbitration.
[131] Importantly, QCPL insisted that the parties would “share” the appellant’s loss from
QCPL’s departure, measured over the entire duration of its user agreement.
[132] It is also clear that whilst the parties did explore, briefly, the possibility of an agreed
price varying according to whether the socialisation was effected, QCPL quickly and
firmly rejected that proposal. QCPL’s position was that the possibility of socialisation
should affect the price, without that possibility being given a particular value.
[133] The amount of $255 million was agreed before the legal structure for the transaction
was developed. That is evident, for example, from the PwC report. It was the Adani
side which proposed that the agreed amount of $255 million would be paid under
what became the Deed of Novation and the Termination Agreement. The trial judge
considered that there was something of an evidentiary gap, about the dealings
between the parties in the few months prior to the signing of these agreements.
However, just what that evidence might have revealed, which could have mattered to
an understanding of the transaction as ultimately agreed, was not explained.
163 See [49] of these reasons.
-- 32 of 59 --
33
[134] Clearly then the price to be paid by QCPL for its release was struck by July 2016, and
it was not a price referable only to what would have been QCPL’s liability to 30 June
2022.
[135] At [74] and [75], I have set out the trial judge’s reasoning in reaching her finding that
the amount of $255 million was referable to the six year period to 30 June 2022. In
my respectful opinion, that reasoning was erroneous.
[136] It may be accepted that, as her Honour reasoned, the Termination Agreement took
effect only after the operation of the Deed of Novation, so that what was terminated
was a user agreement with a life until 30 June 2022. But as her Honour otherwise
reasoned, it was necessary to take a broader view of the QCPL transaction, in order
to identify the appellant’s commercial objectives and to assess whether its conduct
was unconscionable. In substance, the sum of $255 million was the result of arm’s
length negotiations of the price which QCPL was prepared to pay, and the appellant
was prepared to accept, for QCPL to be relieved of a contract by which it was bound
until 2028.
[137] Her Honour saw significance in the fact that the amount of $255 million was “very
close indeed” to an economist’s calculations which he made some years later for his
evidence in the case of the present value of the amount which QCPL would have paid
until 30 June 2022. However, that was not a basis for a finding that the appellant and
QCPL had reached the figure of $255 million by reference to the present value of the
charges for that period only, when the evidence of their negotiations demonstrated
otherwise.
[138] The agreed sum could be fairly described, in part, as compensating the appellant for
the lost benefit of its contract. And the error by the trial judge in attributing all of the
agreed consideration to this six year period, is not fatal to the respondents’ case.
However the case was weaker when the error is identified.
[139] I go then to the second core element, namely the appellant’s insistence of the
respondents’ performance of their contracts.
[140] In this case, there was no vitiating factor affecting the respondents’ user agreements.
The respondents, each a large commercial entity, were bound by the terms of the user
agreements, as interpreted by the arbitrator.
[141] There were issues between the parties as to the effect of their contracts on the HCF,
which were not referred to the arbitrator and which were resolved by declarations
made by the judge and are challenged in this appeal. The respondents now accept,
however, that according to their user agreements, the appellant was entitled to an HCF
calculated by removing what had been QCPL’s tonnage.
[142] By the respondents’ contracts, there was no impediment to the appellant agreeing
with QCPL as it did. As the arbitrator held, “the individual User Agreements with
Adani, though in similar form, entitle Adani to deal with individual Users in very
different ways”, and “there is nothing in the User Agreements which limits or restricts
the ability of Adani to agree upon an early termination of any other User Agreement
to handle coal.” As he also observed, “the position the Users now find themselves in
is the same as if the QCPL Agreement had expired by effluxion of time at the end of
the previous Review Period.”164
164 Award paras 300, 302.
-- 33 of 59 --
34
[143] The consequence of QCPL being released from its user agreement was that a higher
burden was placed on those who continued to use the facility. The operation of the
user agreements that way did not create a burden upon the respondents, which they
could not have anticipated when they entered into their user agreements.
[144] The trial judge held that, in good conscience, the appellant should have taken other
courses, so that that burden to the respondents could have been avoided. The judge
queried why there had not been “a straightforward novation of the entire QCPL [User
Agreement] to AMPL”, so that as at the Review Date, the aggregate AMT would
have been unchanged. There are three things which must be said about that
suggestion.
[145] The first is that, notwithstanding that the appellant and AMPL are members of the
same corporate group, they are distinct entities and with distinct interests. AMPL did
not then have a coal mine, its proposed mine was the subject of a substantial public
controversy and it had not been granted all necessary regulatory approvals. In those
circumstances, it is not apparent that it would have been in the interests of AMPL to
take over QCPL’s contracted tonnes from July 2017 or earlier.
[146] Secondly, this would have required the appellant to mothball that part of the capacity
of the Terminal, for a period of five to six years, to the potential disadvantage of
another miner which might have had a real use to make of it for at some of that period.
[147] Thirdly, this course would have required an agreement to be made with AMPL, in
terms which would have been artificial. AMPL would have been entitled to use the
Terminal, whilst having no means of doing so, unless and until it had a mine.
[148] Another alternative course which was suggested by the trial judge was that the
appellant could have simply accepted $255 million in consideration for the
termination of the QCPL User Agreement. Under this “price for relinquishment”, her
Honour said, the “socialisation” would have been apparent on the face of the
documents, and there would have been no advantage to AMPL.165 However, had that
become the agreed structure for QCPL’s departure, the respondents would have
suffered the same damage of which they complained, and for which they were
compensated. I will return to the relevance of her Honour’s findings as to the
appellant’s conduct lacking transparency and involving attempts to disguise aspects
of the QCPL transactions.
[149] The first respondent pleaded that there was another alternative course which could
have been taken by the appellant. It was alleged that the appellant could have reduced
QCPL’s AMT pursuant to cl 10.2 of its user agreement, upon the ground that QCPL
was not presenting at the Terminal its AMT for handling. Clause 10.3 of QCPL’s
user agreement provided that if the AMT was so reduced, QCPL remained obliged to
pay the relevant charges on its AMT (before reduction) unless and until the appellant
provided that capacity to another Access Holder. The trial judge did not discuss this
alternative. The first respondent’s point was without merit. Clause 10.2 permitted
the reduction of the AMT only where there was one or more requests from others
wishing to use the Terminal which the owner could not satisfy from “uncommitted
terminal capacity”. The trial judge found (in response to another argument) that
“there were indications that no other user wished to take up any extra capacity at
165 Judgment [144].
-- 34 of 59 --
35
around this time”, and that it was because QCPL could not find anyone to take over
its tonnage, it approached Adani.166
[150] There is another alternative, which although not discussed by the trial judge, might
be mentioned. The damage of which the respondents complained would have been
avoided, at least for the TIC and TPC calculations, if the appellant and QCPL had
agreed to terminate the user agreement from a later date, and after the Review Date.
However, the evidence of the negotiations with QCPL provided no indication that
QCPL would have so agreed. QCPL was prepared to pay $255 million for an
immediate termination of its user agreement, and with effect from 1 July 2016.
[151] The trial judge viewed the case as one of the exploitation by one party to a contract
of the vulnerability of the other(s). That vulnerability resulted from a number of
circumstances, in her view. The appellant was a monopolistic supplier of its services:
the users had no choice but to export their coal through this facility. The users were
bound by long term contracts which gave very little scope for withdrawing from them.
The fortunes of the users were in the hands of the owner and another user. They were
exposed to the consequences of the appellant acting not only in its own commercial
interests, but in the interests of a related company, AMPL. And their vulnerability
was enhanced by the effective ownership of the Terminal, and the rights of the owner
under their user agreements, having passed from a government owned corporation to
an entity whose objects were entirely commercial.
[152] From those circumstances, her Honour likened the case to Ipstar Australia v APS
Satellite Pty Ltd,167 saying:168
“There is an analogy between [the respondents’] position and the
position of SkyMesh in the Ipstar case. SkyMesh sold internet services
for which Ipstar’s hardware was necessary. When Ipstar wished to
increase the price of the services (as it was entitled to do in a
contractual renegotiation), SkyMesh needed to agree with Ipstar as to
price, or effectively start its business again, with a new supplier of
hardware, at a cost of tens of millions of dollars.”
[153] However, Ipstar did not have the likeness to the present case which her Honour
perceived. The impugned conduct in that case occurred in the context of negotiations
between the parties as to the price which SkyMesh would pay. In the present case,
the price was already agreed, by the provisions for the review of charges according
to the application of agreed formulae. Further, there were other aspects of Ipstar’s
unconscionability. Ipstar had misleadingly concealed relevant information.
[154] The user agreements, by their provisions for the review of these charges, made the
respondents susceptible to the effects of commercial dealings in which they would
not be participants. However that was simply the consequence of their agreements
containing no provision by which one user could affect the duration of another user’s
agreement. This was a position to which the users had agreed, by contracts which
were unaffected by any vitiating factor.
[155] The fact that the respondents had contracted not with the appellant, but with the Ports
Corporation, was of no importance in the assessment of whether the appellant acted
166 Judgment [195].
167 [2018] NSWCA 15.
168 Judgment [174].
-- 35 of 59 --
36
unconscionably. The premise of her Honour’s reasoning in that respect seems to have
been that the Ports Corporation, as the owner of a major piece of infrastructure and
as a party to commercial contracts made with substantial commercial entities, would
not have sought to secure the full benefit of its contract with a user who was in default
of that user’s agreement and enforce the other user agreements according to their terms.
[156] The relationship between the appellant and AMPL was unimportant to the question
of whether the appellant acted unconscionably. The appellant was entitled to prefer
the interests of AMPL, as well as its own interests, over the interests of the
respondents. Its conduct was not made unconscionable by its transacting with QCPL
on terms which were intended to accommodate the future needs of AMPL for the use
of the Terminal.
[157] The trial judge found that the appellant had attempted to disguise or camouflage the
basis of its dealings with QCPL, by conduct which she said involved “serious
dishonesty”. The appellant’s conduct, her Honour concluded, had been designed to
prevent the remaining users having a “true appreciation of the QCPL transactions,
and thus their legal rights.”
[158] The “legal rights” to which her Honour referred were not described. As the
respondents had to accept, they had no contractual rights for which they could have
obtained relief against the appellant. Their only legal rights could have been their
rights of action for what the judge held was the appellant’s contravention of s 21.
[159] This was not a case, such as Ipstar, where a benefit was obtained, unconscionably, by
the deception of an innocent party. The detriment for which the respondents sought
to be compensated in this case, was not caused, or contributed to, by what was found
to have been the appellant’s deception. Had the respondents always known
everything which was known by the conclusion of the trial, the respondents would
have been no better off.
[160] A dishonest cover up of conduct might evidence, in some cases, a party’s subjective
belief as to the propriety or otherwise of its conduct. However the conduct must be
assessed objectively. If, on an objective view, the conduct which caused the detriment
of which complaint is made, was not unconscionable, it would not be made so by
a dishonest attempt to disguise it.
[161] The point is most starkly illustrated by her Honour’s reliance upon what she found
was the falsity of the testimony of Mr Wicks. If the appellant’s conduct had not been
unconscionable before Mr Wicks testified, a contravention of s 21 did not occur as
his evidence was given.
[162] Further, there was evidence which indicated that there had not been such a sustained
cover up as the trial judge understood had occurred. An affidavit by Mr Mitchell, the
solicitor for the second, third and fourth respondents, contained extracts from the
published financial reports of Adani Enterprises Limited and the appellant, for the
year ended 31 March 2017. The report by Adani Enterprises, which was published
in May 2017, disclosed and described the effect of the Deed of Novation and the
Security Deposit Agreement. The report by the appellant, which was published in
July 2017, described the effect of the Termination Agreement with QCPL, the Deed
of Novation and the Security Deposit Agreement. From those reports, Mr Mitchell
was able to swear to his belief, in October 2017, as to the aspects of those transactions
-- 36 of 59 --
37
which became his clients’ unconscionability case. From the fact that these details
were published in the financial reports, it may be inferred that the Adani companies
anticipated that they would be so published, when these agreements were signed
in 2016. The trial judge did not discuss this evidence.
[163] The trial judge was persuaded by arguments for the respondents that to require the
respondents to perform their contracts, would provide the appellant with a windfall.
These arguments appealed to notions of unjust enrichment, as reflected in her
Honour’s remark that the payment of $255 million was “at the expense of the
users”.169 As I have said, there were two core elements to the case which the judge
accepted. The first was that the appellant had successfully negotiated agreements by
which it received $255 million from QCPL. The second was that the appellant had
insisted upon performance by the other users of their agreements, with the consequence
that the appellant would be paid twice for the provision of the same service.
[164] The appellant enjoyed that position by the force of its contracts, and not by any
deception, trickery or intimidation. It was under no contractual obligation, or any
other obligation under the general law, to effectively elect between the benefits the
QCPL contract and the benefits of the respondents’ contracts. It was entitled to
enforce each contract, or in the case of the QCPL contract, to negotiate a substantial
payment by a defaulting party for its release.
[165] How then, it may be asked, was it “offensive to conscience” for it to enjoy the benefit
of both sets of contracts? More particularly, how was it offensive to conscience for
it to retain the benefit of its contract with QCPL, rather than passing that on to the
respondents and other remaining users?
[166] It is evident from the terms of the user agreements that the broad objective of the
terms for the calculation of the TIC, TPC and HCF was to provide the owner, to an
extent which was possible and practicable, with an income which, aggregated with
like payments made by other users, would provide a certain level of return on the
owner’s capital investment and a reimbursement of the owner’s fixed handling
charges as paid to the operator.
[167] However the provisions for the quantification of these charges were an imperfect
means of achieving that objective. The TIC and the TPC were to be reviewed at five
yearly intervals, and the HCF at yearly intervals. The charges might be fixed at
a review date when the Terminal was operating with a substantial amount of unused
capacity. If, well before the following review date, that capacity came to be used, the
owner would benefit from the price per tonne having been fixed when it was.
Conversely, if a substantial unused capacity arose soon after a review date, it would
be the owner which bore the burden. They were risks which the parties accepted by
the terms of their contracts.
[168] What happened here was that this risk to the users eventuated, and not by the
appellant’s contrivance or breach of a legal obligation.
[169] Like the trial judge, I will record that I have considered all of the paragraphs of
s 22(1). It is unnecessary to repeat my reasons by cross referencing them to parts of
s 22(1). However, something should be said about paragraph (b) of s 22(1), which is
169 Judgment [192].
-- 37 of 59 --
38
“whether, as a result of conduct engaged in by the supplier, the customer was required
to comply with conditions that were not reasonably necessary for the protection of
the legitimate interests of the supplier”.
[170] The “conditions” of which the respondents’ compliance, on their case, caused them
damage, were the contractual terms for the calculation of these charges. It may be
doubted whether “conditions” in this paragraph could include “the terms and
conditions of the contract”, which are the subject of paragraphs (j) and (k). The
customer here (the user) was not required to comply with the conditions “as a result
of conduct engaged in by the supplier”. It was required to perform the conditions as
terms of its contract, as it had contracted with the Ports Corporation.
[171] I have discussed earlier the judgments in Kobelt, and the various descriptions of
unconscionability in this statutory sense which were there provided. A common view
in the judgments was that the choice of the word “unconscionable” signifies the
gravity of misconduct which constitutes a contravention of s 21(1). The word
“unconscionable” is not synonymous with “unjust”, “unfair” or “unreasonable”.
I should add, however, that I would not characterise the appellant’s conduct even in
those terms.
[172] In my conclusion, the appellant’s conduct cannot be characterised as conduct which,
in the words of Gageler J, “is so far outside societal norms of acceptable commercial
behaviour as to warrant condemnation as conduct that is offensive to conscience.” 170
The trial judge was in error in finding that the appellant’s conduct was unconscionable, and
the respondents should not have been given any relief upon this ground.
[173] Because of that conclusion, I will discuss only briefly the ground of appeal which
complains of a denial of procedural fairness.
Denial of procedural fairness?
[174] The first of the appellant’s complaints of this kind is that the judge found that AMPL
aimed to become a coal miner, a user of the Terminal and that it intended “to operate
at the same level of the market as the respondents”,171 when those facts were not
pleaded. After the trial had concluded, and the judgment was reserved, the judge
convened a further hearing on 20 May 2020. Her Honour then raised with the parties
a submission, which had been made by the second, third and fourth respondents, that
the appellant had acted in the interests of AMPL, and beyond the appellant’s self
interest. Her Honour then said that although, in her view, “it’s quite a significant
point in favour of unconscionability”,172 she could not see that it had been pleaded.
This issue resulted in an “appendix” to the reasons for judgment, in which the judge
discussed whether the point had been pleaded, and in which her Honour concluded
that it had been pleaded in the Rejoinder.173 At the same time, she accepted that it
was not pleaded that AMPL was or would become a competitor of the respondents,
so that, her Honour recorded, in making her findings about unconscionability she had
“respected this distinction and proceeded on the basis that there is no pleading or
evidence that AMPL is or will be a competitor of the respondent.”174 However, that
170 Kobelt at [92].
171 Judgment [193].
172 Transcript 1-3.
173 Appendix [13].
174 Appendix [14].
-- 38 of 59 --
39
distinction may not have been observed in her Honour’s finding that AMPL intended
to operate at the same level of the market as the respondents, a matter which she found
had increased the vulnerability of the users.175
[175] A related complaint is that the judge was wrong to hold that the second, third and
fourth respondents had pleaded that the appellant was acting in the interest of AMPL.
That complaint cannot be accepted, having regard to the terms of paragraph 39A of
the Rejoinder and I agree with the judge’s ruling on that point. That fact was not
pleaded by the first respondent. However it was a live issue on the pleading of the
other respondents, and there was no injustice in treating it as a plea which was relevant
to the first respondent’s case.
[176] The next complaint is that the trial judge denied the appellant procedural fairness in
considering, and then finding,176 an attempt to disguise or camouflage its conduct in
the QCPL transactions, where those allegations were not pleaded. The parties each
presented written submissions before the trial. In its opening submissions, in reply to
the respondents’ submissions on the question of unconscionability, the appellant
itemised the pleaded allegations, and then the unpleaded allegations, which were the
subject of the respondents’ opening submissions. Most notably, the appellant pointed
to the submission that the QCPL transactions were “artificial and appear to have been
designed to avoid scrutiny or challenge” and were “manufactured”. Counsel for the
appellant said that the judge should ignore such unpleaded allegations. However, no
application was made by the respondents to amend their pleadings accordingly. In
my respectful opinion, the trial judge ought to have ruled upon that objection at the
commencement of the trial. An allegation of misconduct, of the nature of unconscionable
conduct, was one which required a pleading in strict compliance with the pleading
rules. That case should have been pleaded, and the judge was incorrect to consider it.
[177] A further complaint is that the trial judge denied the appellant procedural fairness in
considering, and then finding,177 that Mr Freeman and QCPL held views about the
morality or appropriateness of the QCPL transactions, when there was no evidence
of those subjective views and the allegations were not pleaded.
[178] As for Mr Freeman, no such allegation was put to him in cross-examination. As for
QCPL, her Honour inferred that its state of mind, as to the commercial morality of
“socialisation”, was similar to that of the appellant.178 The apparent basis for this
inference was QCPL’s insistence upon the Indemnity being included in its
Termination Agreement. In my opinion, that inference ought not to have been drawn.
QCPL’s insistence upon the Indemnity evidenced a concern that other users would
make claims, potentially in large sums, against it. It was not proof of a guilty mind.
Moreover there had been no witness from QCPL or Rio Tinto, to whom such an
allegation could have been put.
[179] The remaining complaint, under this ground of appeal, is that the trial judge denied
the appellant procedural fairness in considering, and finding, that the appellant “[had]
Mr Wicks give false evidence …”.179 This was said by the trial judge in her
discussion of an email of 15 July 2016, from Mr Freeman to an employee of Rio
175 Judgment [184].
176 Judgment [207].
177 Judgment [207], [201] and [202].
178 Judgment [201].
179 Judgment [121].
-- 39 of 59 --
40
Tinto. Attached to the email was a draft letter to be sent by the appellant to QCPL,
in the form of a letter of demand for credit support pursuant to cl 24.2 of the user
agreement. The judge found that there was no genuine concern as to QCPL’s
creditworthiness and that the extent of its credit support was not a reason for the
QCPL transactions. Those findings can be accepted. However, her Honour went on
to find that the email was clearly an attempt to document an apparent reason for the
QCPL transactions which did not exist. This was a falsity which, it was further found,
infected the appellant’s instructions for its pleadings in the case and resulted in
Mr Wicks giving false evidence.
[180] I have discussed the irrelevance of Mr Wicks giving false testimony, as an indication
that the appellant’s conduct, in 2016-2017, had been unconscionable. I have also
discussed why the respondents’ allegations of deception and disguise are ultimately
inconsequential. This confirms my impression that, with respect, her Honour’s
characterisation of the appellant’s relevant conduct as unconscionable was unduly
influenced by her disapproval of Mr Wicks as a witness.
Damages for unconscionable conduct: consideration
[181] Had I agreed with the trial judge’s conclusion that the appellant contravened s 21,
I would have disagreed with her Honour’s assessment of damages for that contravention.
[182] In assessing damages, her Honour said that “the conduct in contravention should be
regarded as charging pursuant to the user agreements without bringing into account
the $255 million payment”.180 Her Honour said (again) at this point that the amount
of $255 million was paid in respect of the period from 1 July 2016 to 30 June 2022.181
She said that in order to put the respondents in the position they would have been had
“the [appellant] shared the benefits of the QCPL transactions”,182 a “proportionate
amount of the $255 million payment ought to be paid to the respondents as damages.”183
[183] I have explained why I disagree with her Honour’s characterisation of the sum of
$255 million as being referable only to that six year period. However, the error by
her Honour in that respect was not of itself fatal to the respondent’s case. To an
extent, the $255 million was to compensate the appellant for the loss of the benefit of
its contract with QCPL in that period. However, to a substantial extent, it was also to
compensate for the lost benefit of the contract beyond that date.
[184] According to the judge’s reasoning, apart from that error, the respondents would be
compensated by being placed in the position they would have enjoyed had the
appellant passed on such part of the $255 million which could be attributed to that six
year period.
[185] A rational apportionment of the $255 million to the six year period was provided by
the PwC Report of June 2016. That report attributed approximately $118 million to
the six year period.
[186] The trial judge accepted evidence to the effect that the present value of QCPL’s
obligations under its user agreement, between 1 July 2016 and 30 June 2022 was
180 Judgment [211].
181 Judgment [212].
182 Judgment [212].
183 Judgment [212].
-- 40 of 59 --
41
$266.5 million.184 However, consistently with her Honour’s reasoning, that would
not have been an appropriate amount from which to assess the damages for the
appellant’s contravention. This was because, on her Honour’s reasoning, the
appellant’s contravention was in not passing on to the remaining users the fruits of its
negotiations with QCPL.
[187] Her Honour discussed a point of difference between two economists who gave
evidence, namely Mr Houston, who was called in the respondent’s case, and
Professor Grey, who was called in the appellant’s case. The point related to an
amount of approximately $41.9 million, which was the TIC for the 2017 financial
year, which was lost to the appellant by the departure of QCPL from an effective date
of 1 July 2016. Because the remaining users were not affected until the
commencement of the 2018 financial year, Professor Grey considered that this
amount should be excluded from the calculation of damages. Her Honour noted that
this point was relevant, according to Professor Grey’s analysis, even on the basis, as
he suggested was appropriate, that the damages were assessed from a starting point
of $117 million, rather than $255 million.185 Her Honour rejected Professor Grey’s
opinion on the point.
[188] In the appellant’s challenge to the assessment of damages, it is submitted that the
respondents suffered no loss at all from the conduct which was alleged, so that they
should not have been awarded any damages. The argument is that the appellant could
have transacted with QCPL upon the alternative basis suggested by the trial judge,
under which the appellant would have been paid $255 million simply for its
agreement to the termination of the QCPL contract. In that event, the remaining users
would have been no better off. Consequently, it is said, by dealing with QCPL as the
appellant did, the appellant caused no loss to the remaining users.
[189] That argument could not be accepted, because it misstates the conduct which the
judge found was unconscionable. The judge’s conclusion was that the conduct in
contravention should be regarded as charging pursuant to the user agreements without
bringing into account the $255 million payment. If that finding stood, the remaining
users were worse off for not receiving their shares of that payment.
[190] An alternative argument for the appellant is that only an amount of $50 million should
have been used as the starting point in the calculation of damages. The submission is
that this was a value attributed to “socialisation” in the appellant’s negotiations with
QCPL. As I have discussed, the appellant at one stage suggested that the amount to
be paid by QCPL should vary according to whether socialisation was effected, and
more particularly, the appellant suggested that the amount which QCPL agreed to pay
be increased by $50 million in the event that socialisation was not effected. However,
as I have discussed, that proposal was promptly and firmly rejected by QCPL. That
piece of evidence provided no rational basis for the assessment of the respondents’
damages. The primary judge was correct in rejecting this argument.186
[191] However, I would accept the appellant’s other arguments in their challenge to the
assessment of damages. One of them has been discussed already, namely that some
of the $255 million was attributable to a period beyond 30 June 2022. Secondly, it is
argued that the judge was wrong to reject the analysis of Professor Grey, on the point
184 Judgment fn 45, apparently referring to the Houston Report [112].
185 Judgment [213]; fn 92.
186 Judgment [217].
-- 41 of 59 --
42
to which I have referred.187 He said that the charges which were lost to the appellant
by the departure of QCPL, before the “socialisation” took effect, should be excluded.
I respectfully disagree with the judge who said that she could see no logic in Professor
Grey’s point.
[192] Consistently with her Honour’s reasoning, the appellant, in good conscience, should
have passed on to the remaining users such part of the $255 million which was fairly
attributable to the period in which the remaining users had to pay higher charges
because of QCPL’s departure. Consequently, the starting point in the assessment of
damages ought to have been $118 million (as per the PwC report), reduced by a sum
which fairly represented a share of QCPL’s payments for any period prior to
30 June 2017.
[193] Consequently, had I upheld the judge’s conclusion as to unconscionability, I would
have varied the damages as follows. Consistently with Professor Grey’s evidence,
I would have deducted an amount of $41.9 million from $118 million, resulting in an
amount of $76.1 million as the sum which ought to have been passed on to the
remaining users. This means that the respective awards in favour of the respondents
would be commensurately reduced. The first respondent’s award would have been
$11.309 million, the second respondent’s award ought to have been $7.549 million,
the third respondent’s award would have been $9.464 million, and the fourth
respondent’s award would have been $3.547 million.
The calculation of handling charges
[194] The user agreements provide for two types of handling charges. One is the HCF, and
the other is the “HCV” (“Handling Charge – variable”). By cl 5.2 of the agreements,
the user must pay the HCF and HCV, as determined in accordance with cl 7, for each
tonne of the user’s coal handled through the Terminal in a financial year.
[195] Subject to the issue I am about to discuss, the users are to pay handling charges to the
appellant which, in aggregate, will reimburse the appellant for the handling charges
which it pays to the operator. The amounts payable by the appellant to the operator
relevantly comprise payments for the operator’s fixed costs (OFC) and for its variable
costs (OVC).
[196] At [27]-[28], I have set out clauses 7.2 and 7.3 of the user agreements. They require
the owner to advise the user, as soon as practicable after consulting with the Operator,
of the HCF and HCV which are to be paid by the user during the next financial year.
By cl 7.5, as soon as practicable after the end of each financial year, there is an annual
reconciliation of these charges by which they are adjusted to accord with the actual
costs which were payable by the appellant to the Operator, and the actual volumes of
coal handled for that user and for all access holders during that year.
[197] The controversy concerns the interpretation and application of cl 7.6, which is as
follows:
“7.6 Determination of OFC and OVC
(a) While the Operator is either:
(i) the Operator existing as at the Execution Date; or
187 See [187] of these reasons.
-- 42 of 59 --
43
(ii) an Operator owned and/or controlled by at least
sixty per cent (60%) of [the users] by tonnage,
then, Clauses 7.2(b) and 7.3(b) will apply.
(b) Whilst Clause 7.6(a) does not apply, then Clauses 7.2(b)
and 7.3(b) will apply, provided that PCQ must demonstrate
that the OFC and the OVC as agreed between PCQ and
the Operator represent a reasonable charge having regard
to the efficient operation of the Terminal.”
[198] The issue arose when the appellant advised the respondents of their handling charges
ahead of the 2018 financial year. The Operator was then APO, which was neither the
operator existing at the execution date of any of the user agreements, nor an entity
owned or controlled by at least 60 per cent of the access holders. Therefore by
cl 7.6(a), cl 7.2(b) and cl 7.3(b) were not to apply, except if the proviso in cl 7.6(b)
was satisfied. The respondents disputed that the proviso had been satisfied. By cl 6.3
of the user agreements, if the user disputes the quantum of an invoice from the owner,
the user must pay the whole of the undisputed part of the invoice and 50 per cent of
the disputed portion, pending a resolution of that dispute. The respondents withheld
amounts constituting 50 per cent of all of the handling charges invoiced by the
appellant, and they have withheld, or threatened to withhold, the same percentage for
each year since. The amounts withheld totalled more than $30 million over the 2018
and 2019 years.
[199] The respondents’ stance was that the appellant had failed to demonstrate the
reasonableness of the operator’s chargers having regard to the efficient operation of
the Terminal, with the result that they need pay nothing for the costs of operating the
Terminal.
[200] The trial judge agreed, and made this declaration:
“Declare that the [appellant] has not demonstrated that the OFC and
OVC agreed between it and the operator in the financial years
commencing 1 July 2017 and 1 July 2018 represent reasonable charges
having regard to the efficient operation of the Terminal in accordance
with cl 7.6(b) of the user agreements between the [appellant] and the
respondents.”
[201] There was no finding that the OFC or the OVC, or any element of them, was an
unreasonable charge. Indeed the judge found, that in the way that the Terminal was
being operated, these were reasonable charges.188
[202] Further, there was no finding that, in any respect, the way in which the Terminal was
being operated was inefficient. The judge said that the operation may have been, or
may not have been, efficient.189
[203] The reason for the declaration made by the judge was that, in her conclusion, the
appellant had failed to prove that the way in which the Terminal was being operated
was efficient. This was not because of any evidence tendered by the respondents. It
was because of what her Honour saw as an evidentiary gap in the appellant’s case.
188 Judgment [303].
189 Judgment [303].
-- 43 of 59 --
44
She reasoned that because it was “entirely possible” that “the terminal’s operational
processes are themselves inefficient due to its design, [setup], age, or any number of
other factors”,190 the appellant had failed to demonstrate the reasonableness of the
operator’s charges.
The operators’ agreements
[204] When the respondents entered into their user agreements, the operator was APB. It
was a related entity of Glencore Coal Queensland Pty Ltd, which, from 1984 to 2005,
had been the only user of the Terminal.191 When the respondents became users, APB
had an Operation and Maintenance Contract with the Ports Corporation (the 2000
OMC). The 2000 OMC was for an initial term of 10 years from July 2000, with
options to extend for periods totalling up to a further 10 years.192 The options were
dependent upon APB’s related entity remaining a user of the Terminal for the period
of the extension.193 The 2000 OMC provided that no person, who was not a related
body corporate of a user, could acquire a shareholding or beneficial interest in the
operator without the owner’s approval.194
[205] The 2000 OMC was extended until 30 June 2020. When the appellant became the
owner of the Terminal, in June 2011, it replaced the Ports Corporation under the 2000
OMC and APB continued as the operator.
[206] In July 2015, the appellant entered into another Operation and Maintenance Contract
for the Terminal, under which a related entity, APO, would be the operator (the 2015
OMC). However, this OMC did not have an immediate effect, and APB continued
as the operator.
[207] In October 2016, APO acquired the shares in APB and at about the same time,
the 2015 OMC took effect. APO became the operator and it then engaged APB as its
subcontractor. The effect of these dealings was that APB continued to provide the
same services as it had provided as the operator under the 2000 OMC. The 2015
OMC contained relevantly the same terms as those of the 2000 OMC.
[208] By cl 28.1 of the 2000 OMC or cl 27.1 of the 2015 OMC, either party might propose
any “Enhancement” of the Terminal. The word “Enhancement” was defined to mean:
“(a) the construction, installation or erection of new buildings, plant
equipment, facilities or other things at or for the Terminal;
(b) the alteration or renovation of existing buildings, plant,
equipment, facilities or other things at or for the Terminal;
(c) the provision of any new or modified technology; or
(d) the acquisition of new land intended to form part of the
Terminal.
for the purpose of increasing the Nominal Throughput Capacity or for
the purpose of enhancing the efficiency, Environmental performance,
190 Judgment [302].
191 Judgment [2].
192 Clause 6.2(b)(i).
193 Clause 6.2(b)(ii).
194 Clause 39.2.
-- 44 of 59 --
45
or economy of the operation, safety or maintenance of the Terminal or
the performance of the Services.”195
Importantly, it is the owner which is to carry out any Enhancement.196
[209] By cl 10.2 of each OMC, the operator was bound to ensure that the Terminal was
maintained and operated so as to achieve “Optimum reliability and efficiency of the
Terminal”,197 and to keep and maintain the Terminal “in good and substantial repair
and condition”.198 The word “Optimum” was defined as the “achievement, as far as
practicable, of the best and most cost-effective outcome,”199 taking into account,
amongst other considerations, in the case of competing interests of users and persons
other than users, fairness and the efficiency and economy of the Coal Transport Chain
as a whole.
[210] Anything which was required of APB as the operator under the 2000 OMC, was
required of APO under the 2015 OMC, and, in turn, was required of APB under its
sub-contract. There was no finding that in any respect, APO’s performance of its
OMC had fallen short of APB’s performance of the 2000 OMC. Nor was there
a finding that, in any respect, the operation of the Terminal under the 2000 OMC had
been inefficient.
[211] The two OMCs contained relevantly identical remuneration provisions. Each
expressed the intention that the rates to be paid to the operator, over an operating year,
would reimburse the operator for its costs, and would include an operator’s margin
of 10 per cent or such other margin as the owner and operator might agree.200
However the user agreements limited the operator’s margin, for which reimbursement
could be sought by the owner from the users, to 10 per cent.201
The respondents’ cases at the trial
[212] Before discussing the evidence, it is necessary to explain the ways in which the
respondents’ challenges to their handling charges were pleaded.
[213] The appellant’s pleading addressed a particular interpretation of cl 7.6(b), which, as
appears from the absence of any consideration of the point by the trial judge, was
apparently not argued at the trial. This was an interpretation of the proviso by which
it would be satisfied only if the respondents were themselves “subjectively satisfied”
that the OFC and OVC were reasonable charges.
[214] The appellant’s pleading sought a further declaration, which was that certain
amounts202 were reasonable charges having regard to the efficient operation of the
Terminal, for the 2018 financial year. The respondents’ pleaded case in answer to
that claim was as follows.
[215] Each of the respondents pleaded a point which is now the subject of the Notice of
Contention, which is that upon the proper interpretation of cl 7.2 of the user
195 Clause 2.1 of each OMC.
196 Clause 28.1(b) of the 2000 OMC; Clause 27.1(b) of the 2015 OMC.
197 Clause 10.2(b)(i).
198 Clause 10.2(e).
199 Clause 2.1 of each OMC.
200 Schedule 5 of each OMC.
201 Definition of “Operator’s Margin” in Schedule 2 of the standard user agreement.
202 $60,339,094 for the OFC and $8,954,229 for the OVC.
-- 45 of 59 --
46
agreements, the “total costs payable by [the owner] to the operator”, in the definition
of OFC, excludes any amount for which the owner has been indemnified. The
respondents pleaded that the appellant had been indemnified by the payments which
it received from QCPL.
[216] Each of the respondents pleaded, in effect, that the appellant had not presented
material, in support of its claims for handling charges, which demonstrated that the
operator’s charges were reasonable having regard to the efficient operation of the
Terminal. The respondents alleged that the material which was provided to them by
the appellant, which included two reports of PwC respectively addressing the 2018
and 2019 claims, fell short of proving the reasonableness of the charges. There was
no specific plea that the Terminal had been operated inefficiently.
[217] However, in the first respondent’s pleading,203 it was alleged that the PwC Report for
the claim for the 2018 financial year was insufficient, because (amongst other
reasons) “the review scope [of the Report] was limited in that it did not include
a detailed bottom-up technical efficiency and effectiveness review of the operator’s
operational policies, business processes, work practices or equipment (e.g. labour
force structure, salary/wage levels, maintenance strategy, etc) …”.204 (That plea was
evidently derived by a disclaimer, in identical words, in the PwC report itself.)
[218] The first respondent counterclaimed for declarations that:
(a) the appellant had not demonstrated that the OFC and OVC for the 2018
and 2019 financial years represented a reasonable charge having regard to the
efficient operation of the Terminal;
(b) the appellant had not demonstrated that the sum claimed by it pursuant to cl 7.5
in respect of the OFC and OVC for the 2017 financial year was based upon
a reasonable charge having regard to the efficient operation of the Terminal.
[219] The first respondent’s pleading did not suggest an amount that would be a reasonable
charge. Apart from its allegation that a “bottom up analysis”, had not been done by
PwC, it pleaded nothing about the efficiency of the operation of the Terminal.
[220] The other respondents (“the QCoal Respondents”) pleaded a letter which they had
written to the appellant, on 24 July 2017, in response to the appellant’s invoices for
the charges for the 2018 financial year. They pleaded, as they had written, that the
appellant should have provided detailed information, which included a detailed break
down of each cost component comprising the OFC, a similar break down for each
cost component comprising the OVC, information as to the operator’s margin and
“[v]erifiable evidence demonstrating that the OFC and OVC as agreed between [the
appellant] and the operator represent a reasonable charge having regard to the
efficient operation of the Terminal.”205 They pleaded that the PwC reports were
inadequate in several respects, one being that the reports did not “establish that the
Operator’s operational policies, business processes, work practices or equipment,
including its labour force structure, salary and wage levels, and maintenance strategy,
are technically efficient, or that despite changes to the cost of providing these services
and undertaking these tasks, they remain technically efficient …”.206
203 The First Respondent’s Second Further Amended Defence and Counterclaim dated 17 June 2020.
204 Paragraph 40(c)(ii) of that pleading.
205 Paragraph 50(b)(iii), (iv), (v) and (vi) of the Second to Fourth Respondents’ Second Further
Amended Defence and Counterclaim, dated 17 February 2020.
206 Paragraph 58(b)(iii) and paragraph 62J(b)(i) of the pleading.
-- 46 of 59 --
47
[221] The QCoal respondents pleaded a specific non-admission “that an actual OFC of
$58,668,000.00 would be reasonable having regard to the efficient operation of the
Terminal, and thus in fact the OFC.”207
[222] They counterclaimed for declaratory relief in the same terms as claimed by the first
respondent, and claimed a further order that the appellant refund to them “any
difference between the HCF, calculated using an OFC that has been demonstrated to
be reasonable having regard to the efficient operation of the Terminal, and the HCF
in fact paid by [them] for the [2018 and 2019] financial years.”
[223] The case of all respondents was that the proviso was unsatisfied, not because the
operation of the Terminal was inefficient, but because the appellant had not
demonstrated otherwise.
[224] The absence of any pleaded criticism of the operation of the Terminal is remarkable.
The respondents, of course, had not themselves operated the Terminal. However their
use of the Terminal well pre-dated the arrival of the Adani Group in 2011.
[225] Further, the user agreements established a regime under which they were able to
participate in a consideration of the efficiency of the Terminal’s operations.
Clause 29 of the user agreements provided for a User Committee, constituted by
a representative of each of the owner, the operator and each user.208 By cl 29.2, the
User Committee was established for the following purposes:
“(a) to provide a forum for discussion between all participants on
matters relating to the operation and performance of the
Terminal, including (without limitation) any factors relating to
any participant which may impact on the future performance or
efficiency of the Terminal;
(b) to enable discussion between all participants on current and
planned Terminal facilities, including all proposals for any
enhancement of the Terminal;
(c) to provide a forum for discussion between all participants on
matters relating to Coal Transport Chain efficiencies and co-
ordination; and
(d) to discuss and comment on matters relating to the Terminal
Regulations, including (without limitation) any proposed
changes to the Terminal Regulations.”
By cl 29.3, the User Committee was to meet at the least on a quarterly basis, and by
cl 29.5, the owner had to cause the operator to provide appropriate support to the User
Committee, including the provision of any relevant operational reports, as the
Committee might reasonably request the operator to provide from time to time.
The evidence about handling charges
[226] Three witnesses testified in the appellant’s case about the operator’s charges. One
was Mr Fenton, the author of the PwC reports. Another was Mr Poulton, a chartered
207 Paragraph 6(aa)(i) of the Counterclaim.
208 And any Access Seeker, meaning the party seeking access under a user agreement.
-- 47 of 59 --
48
accountant who was employed from 2012 until 2018 by APB as the Commercial
Manager in relation to the operation of the Terminal, and from October 2018, was
employed by the appellant as its Financial Controller. The third witness was
Mr Freeman (whose evidence in other respects was discussed earlier for the
unconscionability case).
[227] PwC was engaged to provide a report in April 2017, in anticipation that users, or some
of them, would challenge the reasonableness of the amounts paid to the operator. The
appellant engaged PwC to undertake a review of the proposed operator charges for
the 2018 financial year, and to report on the reasonableness of them having regard to
the efficient operation of the Terminal.
[228] The trial judge was critical of Mr Fenton’s initial response to this retainer, which her
Honour thought introduced a gloss upon it.209 Mr Fenton wrote that his assistance
was being sought on “whether the proposed FY 2018 operations charges for T1 are
consistent with the requirements of clause 7.6(b) of the user agreement”. Although
the point is not important for my conclusion, I have to say that I do not discern the
gloss to which her Honour referred. Her Honour was also critical of Mr Fenton’s
reports, both for the 2018 financial year and for the 2019 year, being provided later
than the time which he had indicated, although the significance of that was not
explained.
[229] Mr Fenton’s methodology was as follows. He assumed that the budgets for the
operating costs for the years 2014-2017 were reasonable having regard to the efficient
operation of the Terminal. He then compared the budgets for the 2018 and 2019
financial years with those budgets, and compared the actual costs in those earlier years
with the 2018 and 2019 budgets. In his second report he included the actual costs of
the 2018 year as an additional comparator.210 He looked at particular items for which
the cost had increased in the 2018 and 2019 budgets from their cost in the previous
year, and recorded the appellant’s explanation for those increases. He compared the
2018 and 2019 budgets with the operating costs, as far as they were known, for
another coal handling terminal, at Dalrymple Bay.211
[230] As her Honour recognised, the comparisons in the reports showed that the budgeted
OFC and OVC for the 2018 and 2019 financial years were “not greatly different from
those in the years 2014-2017”.212 She said that there was more difference shown in
a comparison in between those budgets and the actual spend in 2014-2017.213
[231] Her Honour was critical of Mr Fenton’s analysis, in that it simply compared total
numbers, either budgeted or actual, against the 2018 and 2019 budgets.214 She saw
another limitation in his analysis from his assumption that the budgets and charges in
the 2014-2017 period were reasonable charges having regard to the efficient operation
of the Terminal.215 She was also critical of his reports for having relied upon evidence
which was “essentially hearsay from employees of the operator” which Mr Fenton
had not checked or analysed in any critical way.216 And her Honour saw no value in
209 Judgment [258].
210 Judgment [270].
211 Judgment [270].
212 Judgment [273].
213 Judgment [273].
214 Judgment [274].
215 Judgment [275].
216 Judgment [276].
-- 48 of 59 --
49
the comparison with the Dalrymple Bay coal terminal, which she said differed in
many respects from this Terminal.217
[232] Mr Poulton was responsible for preparing the operator’s budgets for the Terminal.
From October 2016 until October 2018, he reported to Mr Freeman, who was the
CEO of both APO and APB.218 Mr Poulton gave evidence that APB continued to
provide the same services, and perform the same functions, after its shares were
acquired by APO. Her Honour remarked that Mr Poulton’s employment had “straddled
the transition from the original operator to the Adani operator”, as had the employment of
the production manager and the maintenance manager at the Terminal.219 She noted
that there was no challenge to Mr Freeman’s evidence that this continuity in
management resulted in a significant part of the corporate knowledge and experience
of the original operator being transferred to the Adani operator.220
[233] Mr Poulton said that APB budgeted for the future costs of operating and maintaining
the Terminal five years in advance, and reviewed that budget on a monthly basis. He
attended two meetings a month with the personnel responsible for the operations of
the Terminal, focussing upon the performance against budget, when the site personnel
would be challenged where cost or lead times associated with planned activities
required that challenge.221 The judge said that it was evident that these twice monthly
reviews were “disciplined, detailed and thorough.”222 The judge described these five
year budgets, as well as budgets produced each year for the next three years, as “very
detailed”.223
[234] Mr Poulton gave a detailed explanation of the increased costs within the 2018 budget
and in the 2019 budget.224 In describing the process of the preparation of the Annual
Operation Maintenance and Capital Plan and Budget for the Terminal, he said its
purpose was to “identify the resources the Operator will require to perform the
Services in accordance with its contractual and legislative obligations and to forecast
the costs the Operator will incur in providing those Services.”225
[235] The judge found Mr Poulton to be “honest and meticulous”.226
[236] Mr Freeman’s academic qualifications, like those of Mr Poulton, are in the financial
field. He joined the Adani Group at the end of 2014, having had “extensive port and
infrastructure services related experience through a range of Commercial Manager
roles” with other large organisations for more than a decade.
[237] Mr Freeman was directly involved in the budgetary development process for the
Terminal. He reviewed drafts of the budget and provided comments on the
assumptions and inputs which informed the budget, and he sought to understand the
reason for any variation from a previous year’s projected cost in order to satisfy
217 Judgment [278].
218 Judgment [285].
219 Judgment [288].
220 Judgment [288].
221 Judgment [290].
222 Judgment [290].
223 Judgment [291].
224 Judgment [293]-[294].
225 This is a document which cl 5.1 of the 2015 OMC was required to be prepared and submitted in June
each operating year by the operator to the owner.
226 Judgment [286].
-- 49 of 59 --
50
himself that it was appropriate. He said that in considering the budget for the 2018
year, he was of the opinion that it reflected a reasonable estimate of the cost to APO
of providing the operations and maintenance services required of it in accordance
with its contractual and legal obligations.227 Referring to that evidence, the judge
noted that Mr Freeman had earlier detailed the operator’s obligations with respect to
efficiency under the 2015 OMC. He gave the same evidence about the 2019 budget.
[238] Her Honour said that Mr Freeman impressed as “more robust and businesslike” than
Mr Poulton.228 Referring to his “extensive port and infrastructure services related
experience”, the judge thought that Mr Freeman was “more able to, and concerned
to, look at the overall operations of the terminal to address inefficiencies and poor
systems.”229
[239] Mr Freeman’s oral evidence featured in the judgment under a heading entitled
“Indications as to Inefficiency”. In this section, her Honour referred to “some aspects
of the evidence which indicated that the operations of the Terminal may not be
efficient.”230 Importantly however, none of those “aspects” was found to constitute
an inefficiency.
[240] One of those aspects involved the absence of “a formal asset management strategy or
maintenance plan for the terminal”, with the maintenance of machinery and
equipment being instead based upon a series of rolling work orders based on the
manufacturer’s recommendation for that item.231 Mr Poulton said that this was
a sufficient strategy, but Mr Freeman thought that the Terminal ought to have had
a formal asset management strategy.232 Mr Freeman expected the implementation of
such a strategy would cost two or three million dollars in total, which he said would
be a worthwhile spend in terms of the efficient operation of the Terminal.233
However, Mr Freeman said that such a strategy was “fundamental” from “the owner’s
perspective”, and not from the operator’s perspective. That distinction was critical,
as I will discuss.234
[241] Another aspect of Mr Freeman’s evidence was that he had formed a view, at one
stage, that the operator was using more contractors that he was comfortable with, and
that had he been charge of the Terminal five years earlier, than would have been
addressed then.
[242] Her Honour referred to Mr Freeman’s evidence that he hoped to achieve the
introduction of computer logistics information, rather than manual spreadsheets, to
organise the arrival and departure of coal from the Terminal. She referred also to his
evidence that as at October 2016, there had been no external reviews of the systems
of work employed by the operator, and that his initial familiarisation with the business
then had led him to conclude that there was “room for improvement” in the efficiency
with which the Terminal was operating.235 Under his management, a Five Year
Operation, Maintenance and Capital Plan was developed (as part of the 2017-18
227 Judgment [296].
228 Judgment [309].
229 Judgment [309].
230 Judgment [304]. (emphasis added).
231 Judgment [310].
232 Judgment [313].
233 Judgment [313].
234 See [251]-[253] of these reasons.
235 Judgment [318].
-- 50 of 59 --
51
Annual Operations, Maintenance and Capital Plan and Budget). This Five Year Plan
outlined goals for “Operating Performance” and “Asset Management”. Her Honour
noted that there was no evidence that those strategies had been implemented, or that
they had been successful.236
[243] These “indications” of inefficiency, in her Honour’s view, strengthened the
conclusion which she had reached and showed what she perceived was a gap in the
evidence.237
[244] The two economists gave evidence on the cl 7.6(b) issue, Professor Grey in the
appellant’s case and Mr Houston who was (jointly) called by the respondents. Her
Honour found the evidence of both witnesses to be of “limited value” on the question,
based as it was on a “partial understanding of the facts of this matter and assumptions
not made out in the evidence.”238
[245] Her Honour rejected Mr Houston’s evidence that when Glencore (APO) was the
operator, it had had an incentive to allocate costs to the operating budget of the
Terminal rather than to where those costs belonged, in some other part of the overall
Glencore operation.239 Mr Poulton’s evidence was that he had never seen evidence
of such a practice. Her Honour accepted Mr Poulton’s evidence and added that the
evidence was that when Glencore was replaced with the Adani operator, the
operator’s costs increased in some respects because of the advantage which the
Glencore operator had received from sharing services that were part of the wider
Glencore operation.240 Her Honour therefore dismissed Mr Houston’s “speculative
ideas” about common costs.241
[246] Her Honour rejected also Mr Houston’s evidence that the operator had a cashflow
incentive not to capitalise items of expenditure but to recover them in the financial
year in which they were incurred. Her Honour accepted Mr Poulton’s evidence that
there were well established procedures to categorise, allocate and charge expenditure
as capital, and found there was nothing relevant in Mr Houston’s evidence about
capitalisation.242
[247] Her Honour rejected other opinions of Mr Houston, which need not be discussed here,
because she accepted evidence relevant to those points which was given by Mr Poulton.243
An evidentiary gap?
[248] The trial judge referred to a submission by the respondents that the appellant had not
provided any information, either before the proceeding or in the evidence in the
appellant’s case, as to the efficiency of the operations of the Terminal, but only about
the costs of those operations. She referred to a submission that none of Mr Fenton,
Mr Poulton nor Mr Freeman could speak “with any authority as to whether or not the
tasks, resources and labour (however well-priced) were reasonably necessary for the
efficient operation of the Terminal.”244
236 Judgment [319].
237 Judgment [304].
238 Judgment [320].
239 Judgment [327].
240 Judgment [329].
241 Judgment [332].
242 Judgment [336].
243 Judgment [337]-[344].
244 Judgment [297].
-- 51 of 59 --
52
[249] At the trial, the appellant described the respondents’ case as being that the only way
in which a demonstration could be made in accordance with cl 7.6(b) was for
a “bottom up assessment to be made of how the terminal operates and the costs of its
operating.”245 The trial judge said that she did not understand the respondents to go
that far. It should be noted, however, that this was the respondents’ pleaded case, as
I have discussed at [217] to [220].
[250] Her Honour’s critical finding, and her single reason for it, were expressed in these
two paragraphs of the judgment:
“[302] I do not consider that a demonstration in accordance with
cl 7.6(b) has occurred, even taking into account the evidence in
this proceeding. The reason is that the information given by
Mr Poulton and Mr Freeman, impressive as far as it goes, does
not address the operational processes in the terminal. It is
entirely possible that although the financial managers of the
operator have done a good job over the years in making sure
that expenditure on the terminal’s operation has been organised
and scrutinised, the terminal’s operational processes are
themselves inefficient due to its design, set up, age, or any
number of other factors.
[303] No evidence at all was produced by the [appellant] from the
operational or engineering equivalent of Mr Poulton or
Mr Freeman to explain how the terminal operates. It would not
in my view be necessary to have an independent expert conduct
a review of the terminal in order to satisfy the requirements of
cl 7.6(b). Evidence from the experienced Production Manager
or Maintenance Manager, mentioned by Mr Freeman… would
likely have been sufficient, if it had been of the calibre and detail
given by Mr Poulton. However, without some evidence as to the
operational side I cannot see that the [appellant] has
demonstrated that the OFC and OVC produced by its budget
processes in 2018 and 2019, and agreed with the operator, are
reasonable charges having regard to the efficient operation of
the terminal. As I have endeavoured to explain, on the present
state of the evidence it is only possible to conclude that they are
reasonable charges having regard to the way the terminal is
operated. That may, or may not, be efficient. The evidence that
Glencore had an incentive to keep costs to a minimum and the
weight that adds to Mr Fenton’s comparisons is not sufficient to
remedy this deficit. It is the [appellant] which must make the
demonstration under cl 7.6(b), and in my opinion it has not done
so. I will make the declaration sought by the respondents. It
follows that I refuse the relief sought in the originating
application and statement of claim.”
Analysis of the judge’s reasoning
[251] Her Honour accepted that the OFC and OVC produced by the budget processes
in 2018 and 2019 were reasonable charges having regard to the way in which the
245 Judgment [298].
-- 52 of 59 --
53
Terminal was operated. The difficulty, in her view, was that that operation may, or
may not, have been efficient. The possibility about which the judge speculated was
that “the terminal’s operational processes [were] themselves inefficient due to its
design, set up, age, or any number of other factors.” The expression of that possibility
revealed an error.
[252] The reasonableness of the operator’s charges could be assessed only by reference to
the content of the operator’s contractual obligations. The operator was bound to
operate the Terminal efficiently, and to keep and maintain the Terminal in good and
substantial repair and condition. But the operator was not required to effect any
“Enhancement” of the facility. Enhancement was defined in the 2015 OMC to
include improvements such as the construction, installation or erection of new
buildings, plant, equipment, facilities or other things at or for the Terminal, the
alteration or renovation of existing buildings, plant, equipment, facilities or other
things and the provision of any new or modified technology for purposes including
enhancing the efficiency or the economy of the operation of the Terminal.246 As I have
discussed, if that is to occur, it is to be done by the owner. The operator must operate
and maintain the Terminal as it is, as distinct from how it might be “Enhanced”.
[253] That error is the apparent explanation for her Honour’s perception of a “deficit” in
the appellant’s case. There was no evidentiary gap as to the efficiency of operation
of the Terminal as it then was. The efficient operation of the Terminal was proved,
to the requisite standard, by the combined effect of several parts of the evidence.
[254] Her Honour’s distinction between accounting or commercial evidence, and
operational evidence, was too strict. Mr Freeman was the CEO with a responsibility
for all of APO’s business operations, including the day to day operation and
maintenance of the Terminal under the OMC. He was involved in the preparation of
the annual terminal operations and maintenance budgets, which required an
identification of the resources required by the operator to provide the operator’s
services. That was not a task of simply costing those resources.
[255] The judge recognised that Mr Freeman had an experience and expertise from which
he was “able to, and concerned to, look at the overall operations of the terminal to
address inefficiencies and poor systems”.247 Her Honour instanced Mr Freeman’s
concerns about aspects of the operations, in her discussion of “indications” of
inefficiency. At that point of the Judgment, she appears to have accepted that
Mr Freeman was able to speak about the efficiency of the operations.
[256] Tellingly, there was no evidence that he had identified any inefficiency which ought
to have been, but was not remedied. As for the “indications” which the judge
discussed, it would have been remarkable if, over the years, there had been nothing
which had seemed to Mr Freeman to be inefficient. With a facility of this scale,
inevitably there would be some things from time to time which could be improved.
Their identification and their improvement would be marks of efficiency, not
inefficiency.
[257] Mr Poulton’s evidence was not unimportant on the question of efficiency.
Mr Poulton described one purpose of the annual budget as being the identification of
246 Definition of “Enhancement” in cl 27.1, set out above at [208] of these reasons.
247 Judgment [309].
-- 53 of 59 --
54
the resources which would be required in the operation of the Terminal. He described
the twice monthly reviews, at which site personnel were challenged on planned
activities as to their costs and lead times. Mr Poulton was thereby routinely engaged
in assessments of the efficiency of aspects of the Terminal’s operation. It is telling
that, as an honest and meticulous witness, Mr Poulton saw no unremedied inefficiency.
[258] Her Honour was critical of Mr Fenton’s evidence in several respects. I have identified
two of those criticisms with which I would not agree. Mr Fenton’s evidence as to his
reports, given in 2017 and 2018, was important. It showed that there was no
significant difference between the costs of operations before the change of operator,
and those after it. That evidence was to be considered with the evidence that the
Terminal continued to be operated in the same way after the change of operator, and
under the management of the same key personnel.
[259] Her Honour observed that this continuity did not demonstrate the reasonableness of
APO’s charges, because those of APB (the Glencore operator) may not have been
reasonable either, because there may have been an inefficiency in the Terminal’s
operation. Yet, in the critical passage set out earlier, her Honour indicated at least
one circumstance which, in my view, strongly indicated the probability that
Glencore’s operation was efficient. There were other circumstances which
contributed to that likelihood. For years before the arrival of the Adani Group, APB
operated the Terminal without, it appears, any apparent concern from the respondents
about the efficiency of the Terminal.
[260] At the end of the part of the judgment which related to the cl 7.6(b) issue, her Honour
again referred to the incentive which Glencore had to minimise costs during its
operation of the Terminal,248 before remarking that until AMPL became a user of the
Terminal, there would be “no disadvantage to the Adani group generally if the
operator’s costs are higher than they need be; to the contrary.” She said that “these
considerations supported her conclusion that the appellant had not made the
demonstration requirement by cl 7.6(b) …”.249 That observation, with respect, is
difficult to reconcile with her Honour’s complete acceptance of the evidence of
Mr Poulton and Mr Freeman on this part of the case. Each referred in detail to the
process of managing the operations of the Terminal, and the care taken in the
processes of budgeting for and reviewing the costs of the operation. The notion that,
at the same time, they would be recklessly indifferent to the efficiency of the
operation, or even inclined towards inefficiency, is impossible to reconcile with
evidence which the judge accepted.
[261] I do not understand her Honour to have characterised this suggested deficit in the
evidence in a Jones v Dunkel250 sense. There is no indication in the judgment that
her Honour saw the absence of evidence from someone from “the operational side”
as the basis for an inference that it would not have assisted the appellant’s case.
[262] The evidence, which her Honour accepted, as to the efficiency of the operation of the
Terminal, had to be considered in combination. The Terminal was operated from
2016 as it had been for many years previously, when its operation was in the hands
of a well resourced operator with a strong commercial incentive to conduct the
248 Judgment [344].
249 Judgment [344].
250 [1959] HCA 8; (1959) 101 CLR 298.
-- 54 of 59 --
55
operation efficiently. The costs of the operation did not change significantly with the
change of operator. The terms of the 2015 OMC were relevantly identical to those of
the 2000 OMC. Senior managers, including the operator’s CEO, gave detailed
evidence of processes to ensure the prudent use of the resources in the Terminal’s
operation. The respondents, each of whom had used the Terminal for many years
prior to 2016, offered no evidence of any waste or other inefficiency.
[263] Ultimately, the appellant’s case failed because her Honour was left in doubt as to
whether the Terminal itself, as a piece of infrastructure, was of optimal efficiency.
That was not the question. It was whether the operator was efficient in its operation
of the Terminal, as the Terminal was.
[264] The judge ought to have held that the operator’s charges were reasonable for the
efficient operation and maintenance of the Terminal.
[265] At this point, however, there are two further things to be considered. The first is that
raised by the Notice of Contention. The second is the effect of another declaration
which was made in the respondents’ favour (against which there is no appeal) in
relation to berthage and mooring charges.
The Notice of Contention
[266] This contention was made against the possibility, as I would hold, that this Court
should overturn the judge’s conclusion that the appellant engaged in unconscionable
conduct.
[267] The respondents contend that the trial judge ought to have found that on the proper
construction of cl 7.2, the “total costs payable by [the owner] to the operator”, in the
definition of OFC, excludes any amount of costs payable by the appellant to the
operator for which the appellant has, in substance, been indemnified.
[268] The trial judge recorded this argument, as advanced at the trial, as a complaint that
“in calculating the OFC [the appellant] has not taken into account any part of the
money it received under the QCPL transactions” which “was in substance an
indemnity for the HCF which QCPL would have paid, had it remained a user and not
entered into the QCPL transactions”.251
[269] Her Honour rejected their argument as inconsistent with the unambiguous text of the
contract. She said:
“[228] … The word “costs” is used twice in the definition of OFC.
Under the operating agreement the owner is obliged to pay the
operator its total fixed costs and a margin. Whether or not the
owner recovers these costs from anyone else is irrelevant to the
owner’s obligation to pay the operator. Here, whether or not the
owner received an amount which “in substance” indemnified it
for the QCPL’s share of the OFC, the owner was still obliged to
pay the operator under the operating agreement and it is those
costs, payable by the owner to the operator, which are the
subject matter of the definition of OFC.
251 Judgment [227].
-- 55 of 59 --
56
[229] Likewise, so far as the text of the user agreements is concerned,
after the QCPL transactions, QCPL was not an Access Holder
and it did not have an Annual Maximum Tonnage. There was
no basis to include its previous Annual Maximum Tonnage
when calculating the ART.”
[270] The respondents argue that her Honour’s reasoning at [228] of the Judgment was
wrong. They submit that an alternative construction, which excludes from “the costs
payable by [the appellant]” amounts for which it has already been indemnified, would
fulfill the purpose of the user agreements of providing the appellant with
reimbursement of its obligation to pay the operator, “but no more”.
[271] The trial judge was correct to reject this argument. The OFC comprises two
components: the total costs payable to the operator in respect of the operator’s total
fixed operating costs, and the operator’s margin on that amount. The OFC is
quantified by the operator’s costs, and such of those costs which the operator is
entitled to be paid by the owner under their contract. There is no ambiguity in the
word “costs” in either of its uses in cl 7.2(b). None of the amount paid by QCPL went
to the operator so that none of it affected, in any sense, the operator’s costs. The OFC
was unaffected by the suggested “indemnity”.
[272] The respondents’ argument depended upon the OFC having to be quantified by
allowing for something from the QCPL payments. The respondents’ contention must
be rejected.
Berthage and mooring charges
[273] The issue here involved berthage and mooring charges, levied on ships at the
Terminal being loaded with coal. The trial judge said that it had always been the
operator which was paid these charges, on invoices issued by it. Prior to
October 2016, the operator had offset the income from these charges against what it
charged the owner for its variable operating costs. That changed in October 2016.
The charges were still levied by the operator, and the operator then notified the
appellant of the berthage and mooring charges collected and the operator’s own costs
in earning that income. The operator paid to the appellant the berthage and mooring
charges received by it, less its costs of deriving that income.252
[274] The question was whether the change in 2016 affected the HCV payable by the
respondents to the appellant. The trial judge considered that “the Operator’s total
variable operating costs” had to be construed to mean “costs less the berthage and
mooring fees”, because those fees were received by the operator for doing what the
operator was obliged to do under its contract, namely load the coal onto ships.253
[275] The trial judge declared that:
“…on the proper construction of the user agreements between the
[appellant] and the respondents, revenue received by the operator as
charges for berthage and mooring from ships to be loaded with coal
pursuant to a user agreement must be deducted from the operator’s
variable operating costs in calculating OVC as defined by
cl 7.3(b)(i)(A) of those agreements.”
252 Judgment [236].
253 Judgment [244].
-- 56 of 59 --
57
[276] That declaration is not challenged in this Court. It may be noted that there is no
inconsistency between the judge’s reasoning on this question and her rejection of the
argument which was the subject of the Notice of Contention. In this instance, the
money which had to be brought into account in calculating the operator’s operating
costs was money received by the operator.
[277] The present relevance of this unchallenged declaration is that it should not be affected
by the orders in this Court in consequence of the outcome of the controversy about
cl 7.6(b).
[278] In this Court, the appellant does not seek relief in terms which would specify specific
amounts as the HCV to which it was entitled from the respondents. The relief sought
is a declaration that:
“… the appellant has demonstrated that the OFC and OVC agreed
between it and the operator in the financial years commencing 1 July
2017 and 1 July 2018 represent reasonable charges having regard to
the efficient operation of the Terminal in accordance with cl 7.6(b) of
the user agreements between the appellant and the respondents.”
That order would not compromise the outcome from the trial on the issue of berthage
and mooring fees.
Clause 25 of the Sonoma user agreement
[279] The user agreement with the fourth respondent (Sonoma) contained this provision at
cl 25.1(a)(v):
“… no other Access Holder Presenting Coal for Handling at the
Terminal will be charged less than the User is charged at that time for
a substantially similar commercial arrangement. For the purposes of
comparison of charges, amounts payable for TIC, TPC, HCF and
HCV, and any rebates receivable by the User and other relevant
Access Holder will be taken into account.”
[280] From 1 July 2017, the appellant charged another user,254 which was not a party to the
litigation, an HCF and an HCV at the same rates as it has charged Sonoma, but the
appellant charged the other user a TIC at a lower rate than Sonoma.
[281] At the trial there was an issue about whether Sonoma’s user agreement was
sufficiently different in its terms from those of the other user (which had the standard
user agreement) that the two did not have “a substantially similar commercial
arrangement”. That argument is not pressed by the appellant here.
[282] The trial judge declared that:
“…since 1 July 2017 the [appellant] has been in breach of cl 25.1(a)(v)
of the user agreement it has with the fourth respondent because it has
charged Clermont Coal Mines Ltd less than Sonoma is charged to
handle the coal which it presents to the terminal under its user
agreement.”
254 Clermont Coal Mines Pty Ltd.
-- 57 of 59 --
58
[283] The appellant advanced two reasons why the trial judge erred in finding that it was in
breach of cl 25.1(a)(v). One of them was that the judge erred by failing to take into
account any of the damages awarded to Sonoma for unconscionable conduct. That
point is irrelevant if, as I would order, the awards of damages for unconscionable
conduct are set aside. In any case, I would reject that argument. It was submitted
that Sonoma’s damages were, in the terms of cl 25(a)(v), something in the nature of
a “rebate receivable by the user”. However the damages awarded in Sonoma’s favour
were in the nature of a statutory remedy for the contravention of a statute, the ACL.
They were not awarded to give effect to Sonoma’s contract. In my opinion, “rebates
receivable by [Sonoma]” would be any amounts which, according to Sonoma’s user
agreement, would reduce amounts otherwise payable for TIC, TPC, HCF and HCV.
The damages awarded for unconscionable conduct were not “rebates” of this kind.
[284] The other argument which is advanced by the appellant is based upon the effect of
cl 6.3(a)(ii) of the Sonoma user agreement. This provision is identical to cl 6.3(a)(ii)
of the standard user agreement, to which I have referred earlier at [198].
[285] As I have discussed, Sonoma, like the other respondents, disputed the entirety of the
appellant’s invoices for handling charges, and paid only 50 per cent of the invoiced
amounts, pending resolution of that dispute. The appellant’s argument is that, in the
terms of cl 25.1(a)(v), the necessary comparison is between the “amounts payable”
by Sonoma and the “amounts payable” by the other user. The “amounts payable” by
Sonoma, at what is said to have been any relevant time, were reduced by the operation
of cl 6.3(a).
[286] However, what must be compared, under cl 25.1(a)(v), are the charges levied by the
owner. The comparison is between what the owner is entitled to charge Sonoma and
what it is entitled to charge the other user. The “amounts payable” are those which
the owner is entitled to charge. I agree with the reasoning of the trial judge as
follows:255
“[353] In my view this argument must fail. Clause 25.1(a)(v) focuses
on amounts which the user is charged. Here there is no doubt
that the full HCV and HCF have been charged to Sonoma since
1 July 2017. For this period Sonoma has been charged more
than the other user. The fact that Sonoma had, and continues to
have, a lawful reason not to pay the handling charges does not
derogate from that point. The clause is concerned with what the
owner is entitled to charge Sonoma.”
[287] The appellant’s argument sought to make something of the words “at that time” in
cl 25.1(a)(v). However those words do not assist the argument. The words define
the necessary comparison by requiring a comparison of what the two users are
charged at that time.
[288] The challenge to this declaration fails.
Orders
[289] I would order as follows:
255 Judgment [353].
-- 58 of 59 --
59
1. Allow the appeal against the judgments given and the orders made on 26 August
2020 and 1 September 2020, save for the declarations numbered 5 and 7 made on
26 August 2020, and the orders numbered 8 and 9 made on 26 August 2020.
2. Set aside the judgments and orders made on those dates, save for those two
declarations, and the orders numbered 8 and 9 made on 26 August 2020.
3. Give judgment for the appellant against the first respondent on the first
respondent’s counterclaim, save for its claim for the declaration numbered 5 made
on 26 August 2020.
4. Give judgment for the appellant against the second and third respondents on their
counterclaims, save for the declaration numbered 5 made on 26 August 2020.
5. Give judgment for the appellant against the fourth respondent on its counterclaim,
save for the declarations numbered 5 and 7 made on 26 August 2020.
6. Declare that the appellant has demonstrated that the OFC and OVC agreed
between it and the operator for the financial years commencing 1 July 2017 and
1 July 2018 represent reasonable charges having regard to the efficient operation
of the Terminal in accordance with cl 7.6(b) of the user agreements between the
appellant and the respondents.
7. Give the appellant liberty to apply for such further order, of the nature of that
specified in paragraph 4 of the orders sought in the notice of appeal, within
21 days of the date of this judgment.
8. Direct the parties to provide, within 21 days of this judgment, written
submissions, not exceeding six pages in length, as to the orders which are to be
made about the costs of the proceeding in the Trial Division and in this Court.
[290] I propose order number 7 because the order sought by the appellant in paragraph 4 of
its notice of appeal, in my view, would be unsatisfactory. Possibly there could be
a controversy as to the amounts which would have to be paid under such an order. If
such an order is to be made, it is preferrable that it specify the amounts involved.
[291] MULLINS JA: I agree with McMurdo JA.
-- 59 of 59 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2021/187