Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2021] QSC 224
SUPREME COURT OF QUEENSLAND
CITATION: Built Qld Pty Ltd v Pro-Invest Australian Hospitality
Opportunity (ST) Pty Ltd [2021] QSC 224
PARTIES: BUILT QLD PTY LIMITED
ACN 108 064 099
(plaintiff)
v
PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (ST) PTY LIMITED (FORMERLY
KNOWN AS AUSTRALIAN HOSPITALITY
OPPORTUNITY (ST) PTY LTD) AS TRUSTEE FOR
THE PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (BRS SPRING HILL) TRUST
ACN 163 479 221
(defendant)
FILE NO/S: BS No 5426 of 2017
DIVISION: Trial Division
PROCEEDING: Claim
ORIGINATING
COURT:
Supreme Court of Queensland
DELIVERED ON: 3 September 2021
DELIVERED AT: Brisbane
HEARING DATE: 28 September 2020 to 14 October 2020; 12 November 2020
to 13 November 2020
JUDGE: Williams J
ORDER: 1. Once the parties have had an opportunity to consider
these reasons, the parties are to confer to agree on a
timetable for directions on the following:
(a) the parties confer and agree on the headings and
structure (agreed form) of further submissions to
be provided as to the appropriate orders to be
made in light of these reasons.
(b) each party is to provide further written
submissions in the agreed form, not more than 25
pages (including attachments).
2. The draft directions should be provided to my
Associate. If draft directions cannot be agreed, then
each party is to provide draft directions and a brief
explanation for the disagreement.
3. If the parties consider that any additional findings of
fact are required at this stage, these should be
-- 1 of 210 --
2
identified in the written submissions. The written
submissions should also address interest and costs.
CATCHWORDS: CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA – THE
CONTRACT DOCUMENTS – THE INTERPRETATION OF
THE CONTRACT DOCUMENTS – where the parties entered
into a Formal Instrument of Agreement on or about 29 April
2015 – where Schedule 1 outlines the documents which
constitute the contract documents – where the contract
documents include the Formal Instrument of Agreement, the
General Conditions and Annexures Part A to P – where
Annexure Part O contains clarifications – where clause 1(u) of
Annexure Part O of the contract provides that work under the
contract includes the contractor’s alternative proposal for
structural and mechanical systems on the basis that the
contractor meets the performance requirement of the tender
drawings and specifications – where the meaning of
“performance requirement” is in dispute – where the plaintiff
contends that not every aspect of the tender drawings and the
specification amounts to a performance requirement – where
the defendant submits that the performance requirements are
to be found in the tender drawings and the specification –
where the plaintiff contends that it is necessary to have regard
to extrinsic evidence to identify the “alternative proposal” that
the plaintiff was obligated to install – where the plaintiff
contends that the words “alternative proposal” used in the
contract is a reference to a two pipe VRF heat pump system,
which cannot provide mode control to each guest room –
whether extrinsic material is admissible to interpret the words
“alternative proposal” contained in clause 1(u) of Annexure
Part O of the Contract – whether, on the proper construction of
clause 1(u) of Annexure Part O, mode control was a
performance requirement of the tender drawings and the
specification
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA –
VARIATIONS – GENERALLY – where the plaintiff and the
defendant entered into a contract for the design and
construction of a hotel in April 2015 for the sum of
$33,366,027.00 – where the hotel includes guest rooms, food
and beverage facilities, front of house facilities, back of house
facilities, two basement level carparks and a guest gymnasium
– where the plaintiff contends that the mechanical works,
including the air conditioning and heating system, did not
require the mechanical system installed by the plaintiff to
provide for mode control in each individual room – where the
plaintiff submits that the defendant’s requirement notified in
correspondence dated 11 August 2016, 16 August 2016 and 17
September 2016 (individually or together the “Mechanical
Direction”) that the mechanical system being installed be
-- 2 of 210 --
3
changed was a direction to undertake a variation under the
contract – where the defendant disputes this and contends that
the notices required that the plaintiff comply with its
obligations under the contract and install an air conditioning
system in accordance with the contractual requirements –
whether the plaintiff was required to design and install an air-
conditioning system allowing mode control in each room –
whether the notices given in August and September 2016 were
a direction to the plaintiff to undertake a variation or
alternatively constituted a notice to rectify defective work
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA –
VARIATIONS – GENERALLY – where the plaintiff
contends that by correspondence there was an express or
implied direction for the plaintiff to supply and install certain
bathroom fixtures and as a result, this amounted to a variation
within the meaning of the contract – where the plaintiff
contends that the plaintiff is entitled to an assessment of the
costs of the variation – where, if there is no entitlement to the
costs of the variation, the plaintiff contends that the defendant
is estopped from relying on or has waived its right to insist
upon satisfaction of clause 36.1 of the contract with respect to
this variation – where the defendant contends that the plaintiff
is not entitled to an increase in the contract sum in respect of
the alleged bathroom variation – whether there was a change
in the work to be undertaken within the scope of clauses
36.1(a) to (e) of the contract – whether there was a direction to
perform the variation as required by clause 36.1(f) of the
contract – whether the correspondence relied upon by the
plaintiff amounts to a direction to perform a variation pursuant
to clause 36.1(g)
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA –
VARIATIONS – LIABILITY TO PAY – where a number of
variations have been approved and certified by the
Superintendent – where it is accepted that the work has been
carried out and the defendant has paid the plaintiff the amounts
claimed, except for the amount identified as representing 7.5
per cent of the certified value of the variations – whether on a
proper construction of clause 36.4(d), the plaintiff is entitled to
an additional 7.5 per cent for preliminaries
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA – TIME
– LIQUIDATED DAMAGES – where the defendant seeks
payment of the amount of $196,623.21 by way of additional
liquidated damages calculated as a result of the correction of
an error in calculating the date for practical completion –
where the defendant contends that in calculating the adjusted
date for practical completion a five day work week was used
-- 3 of 210 --
4
when a six day work week should have been used – where the
plaintiff contends that the defendant is not entitled to the
additional amount of liquidated damages – whether the
defendant is entitled to the amount for liquidated damages
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA –
DEFECTS AND NEGLIGENCE – LIABILITY – whether the
air conditioning system being installed by the plaintiff prior to
the notices in August and September 2016 was defective
because it did not meet the performance requirements of the
contract, or alternatively, of the mechanical services
specification and the mechanical services preliminary design
drawings
CONTRACTS – AUSTRALIA – BUILDING AND
CONSTRUCTION CONTRACTS IN AUSTRALIA –
DEFECTS AND NEGLIGENCE – LIABILITY – where the
defendant claims the cost to rectify non-mechanical related
defects and defects which have been identified in relation to
the mechanical services system – whether the works are
defective works – whether the defendant is entitled to recover
any costs incurred to rectify the defective works
Civil Proceedings Act 2011 (Qld), s 58
Queensland Building and Construction Commission Act 1991
(Qld), s 67P
Australian Development Corporation Pty Ltd v White
Constructions (ACT) Pty Ltd (1996) 12 BCL 317, cited
Byrnes v Kendle [2011] HCA 26; (2011) 243 CLR 253, cited
Civil Mining & Construction Pty Ltd v Wiggins Island Coal
Export Terminal Pty Ltd [2017] QSC 85, considered
CMA Assets Pty Ltd Formerly Known as CMA Contracting
Pty Ltd v John Holland Pty Ltd (No 6) [2015] WASC 217,
cited
Codelfa Construction Pty Ltd v State Rail Authority (NSW)
[1982] HCA 24; (1982) 149 CLR 337, followed
Equuscorp Pty Ltd v Glengallan Investments Pty Ltd [2004]
HCA 55; (2004) 218 CLR 471, followed
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
[2015] HCA 37; (2015) 256 CLR 104, considered
Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken
(SA) Pty Ltd (1994) 11 BCL 360, cited
Westpac Securities Administration Ltd v Australian Securities
and Investments Commission [2021] HCA 3; (2021) 95 ALJR
149, cited
COUNSEL: P L O’Shea QC with M Steele and B Reading for the plaintiff
T P Sullivan QC with J Mitchensen for the defendant
-- 4 of 210 --
5
SOLICITORS: Clayton Utz for the plaintiff
Thomson Geer for the defendant
BACKGROUND .................................................................................................................. 8
THE MECHANICAL SERVICES SYSTEM ...................................................................... 9
Design and Construct Contract ....................................................................................... 10
Plaintiff’s contentions..................................................................................................... 23
Use of extrinsic material ............................................................................................. 24
Extrinsic evidence sought to be relied upon by the plaintiff ...................................... 27
Performance requirement of the tender drawings and the Specification ........................ 33
Defendant’s contentions ............................................................................................. 35
Consideration.............................................................................................................. 38
Construction of clause 1(u) Annexure Part O ................................................................ 43
Mechanical Direction / Variation ................................................................................... 48
JOINERY DELAY ............................................................................................................. 50
BATHROOM DESIGN VARIATION (VP32) ................................................................. 50
Alleged Direction ........................................................................................................... 52
What was required to be built under the Contract? .................................................... 53
Consideration.............................................................................................................. 57
Was there a change in the work to be undertaken within the scope of clauses 36.1(a) to
(e)? Was there a direction within clause 36.1(f) or does it amount to a direction to
perform a variation pursuant to clause 36.1(g)? ............................................................. 58
THE SCHEDULE 3 AND 4 VARIATIONS ..................................................................... 67
Schedule 3 - VP38 – “Ceilings and partition alterations in the Great Room” ............... 68
Schedule 3 - VP53 – “Back of House Corridor – second path of egress” ..................... 68
Schedule 3 – VP59 – “Admin and luggage change layout and joinery” ........................ 69
Schedule 3 – VP78 – “BWIC for boom gate” ................................................................ 69
Schedule 4 – VP58 – “BOH (back of house) ceiling” ................................................... 69
Schedule 4 – VP60 – “Bathroom light switch – off master switch” .............................. 70
Schedule 4 – VP64 – “Clipsal colour switchplates as per JPDC finishes schedule” ..... 75
Schedule 4 – VP66 – “Desk lamp hard wired” .............................................................. 79
Schedule 4 – VP67 – “Supply and installation of power sockets and wiring for LED
lighting” .......................................................................................................................... 81
Schedule 4 – VP73 – “Paint stair soffits/colour contrasting nosings” ........................... 85
Schedule 4 – VP76 – “Additional corridor lighting given flip of rooms” ..................... 87
Schedule 4 – VP114 – “Joinery – Damage to walls by separate contractors” ............... 88
SCHEDULE 5 PROVISIONAL SUMS ............................................................................. 89
Provisional Sum No 2 – “Joinery to Greatroom” ........................................................... 90
-- 5 of 210 --
6
Provisional Sum No 6 – “Landscaping, irrigation and paving including design, supply
& installation of streetscape trees, grates, kerbing and public artwork” ........................ 90
Provisional Sum No 8 – “Make good of the Council footpath to Wharf and Henry
Streets” ........................................................................................................................... 90
PRICING OF VARIATIONS SCHEDULE 6 - PRELIMINARIES .................................. 94
OTHER CLAIMS BY PLAINTIFF ................................................................................... 97
COUNTERCLAIM – ALLEGED NON-MECHANICAL DEFECTS .............................. 99
Defect Item One – “Crack in the basement level 2 slab” ............................................... 99
Defect Item Two – “The electrical penetration running through the mechanical services
slab needs to be adequately sealed and protected” ....................................................... 102
Defect Item Three – “The storm water pipes, and each penetration through which they
run, need to be adequately sealed and waterproofed” .................................................. 102
Defect Item Four – “The concrete structure around the basement staircase and
communications hub wall needs to be adequately waterproofed” ............................... 103
COUNTERCLAIM – ALLEGED MECHANICAL SERVICES SYSTEM DEFECTS . 104
Defect 1.1 – “Duct bends & detail design” .................................................................. 105
Defect 2.1 – “Air conditioning – simultaneous heating and cooling” .......................... 108
Defect 2.2 – “Air conditioner – air commissioning” .................................................... 112
Defect 2.3 – “Substation air intake” ............................................................................. 114
Defect 2.4 – “Office – carpark ventilation noise” ........................................................ 115
Defect 4.2 – “Guest room & maids room exhausts” .................................................... 116
Defect 4.3 – “Level 1 to 12 outside air supply” ........................................................... 120
Defect 4.4 – “Guest room toilet exhaust risers – fire rating” ....................................... 121
Defect 4.5 – “Guest room fan coil unit – interface with occupancy controls” ............. 121
Defect 4.6 – “Guest floor lift lobbies – moisture damage to ceilings and dripping air
conditioning grills” ....................................................................................................... 123
Defect 5.1 – “HX-1, HX-2 filter installation” .............................................................. 123
Defect 5.2 – “Roof mounted duct work – water pooling”............................................ 124
Defect 5.3 – “Insulation on roof duct work” ................................................................ 125
Defect 5.4 – “HX-1, HX-2 condensation traps omitted”.............................................. 126
Defect 5.5 – “Water in HX-1 isolating switch”............................................................ 127
Defect 5.6 – “HX-1, HX-2 filter gauges defective” ..................................................... 128
Defect 5.7 – “HX-2 – water pooling in outside air duct” ............................................. 129
Defect 6.1 – “As installed drawings (O&M manuals)” ................................................ 130
Defect 6.2 – “O&M manual content” ........................................................................... 131
DEFENDANT’S CLAIM FOR ADDITIONAL LIQUIDATED DAMAGES ................ 133
INTEREST ....................................................................................................................... 139
NEXT STEPS ................................................................................................................... 140
-- 6 of 210 --
7
ANNEXURE A – MECHANICAL VARIATION, COSTS, DELAY, EXTENSION OF
TIME AND LIQUIDATED DAMAGES ........................................................................ 141
Plaintiff’s claim for costs of carrying out the Mechanical Variation ........................... 141
Costs of the variation .................................................................................................... 144
Credit – contract works not required or incorporated due to Mechanical Variation 145
Additional works – three-pipe mechanical system ................................................... 146
Demolition ................................................................................................................ 148
Reinstatement works ................................................................................................ 149
Ceilings and partitions reinstatement .................................................................... 149
Tiling reinstatement ............................................................................................... 150
Electrical reinstatement ......................................................................................... 150
Fire ratings reinstatement ...................................................................................... 151
Hydraulics reinstatement ....................................................................................... 151
BWIC ..................................................................................................................... 151
Item 128 – “Core holes – 200mm through to 210mm post tension slab" .................... 152
Item 127 – “Core holes – 200mm through to 700mm post tension slab” .................... 152
Item 132 – “Road closure for craneage” ...................................................................... 152
Item 129 – “Craneage to lift plant to roof”................................................................... 152
Item 130 – “Mobilisation and de-mobilisation” ........................................................... 153
Item 131 – “Traffic control during crane days” ........................................................... 153
Item 126 – “X-ray scanning core holes” ...................................................................... 153
Summary .......................................................................................................................... 154
Delay and the Mechanical Variation ............................................................................ 155
Is the plaintiff entitled to an extension of time due to the Mechanical Variation? ...... 155
Delay analysis methodology ........................................................................................ 172
Reasonable steps to mitigate delay ............................................................................... 176
Contribution to cause of delay ...................................................................................... 181
Christmas shutdown ..................................................................................................... 187
Claim for EOT .............................................................................................................. 188
Delay Damages ............................................................................................................. 197
Liquidated damages .......................................................................................................... 209
-- 7 of 210 --
8
BACKGROUND
[1] On 29 April 2015, the plaintiff (Built) and the defendant (Pro-Invest) entered into a
contract for the design and construction of a hotel located at 168-184 Wharf Street,
Spring Hill (Spring Hill Hotel) for the sum of $33,366,027.00 (plus GST) (Contract).1
[2] The Spring Hill Hotel includes guest rooms over 12 levels, food and beverage
facilities, front of house facilities, back of house facilities, two basement level
carparks and a guest gymnasium located on level one.
[3] The plaintiff commenced proceedings claiming the sum of $6,158,864.22. The
defendant brought a counterclaim in respect of alleged defects, additional liquidated
damages and alleged lost wages.
[4] The proceedings include a number of issues which are in dispute between the parties
including the entitlement to variations, costs of alleged variations, extensions of time
and delay damages, the defendant’s entitlement to liquidated damages for late
completion and also amounts in respect of rectification of alleged defective work.
[5] The issues in dispute have been described under the following general headings:
(a) the mechanical services system;
(b) alleged joinery delay;
(c) liquidated damages;
(d) alleged bathroom design variation;
(e) the Schedule 3 and 4 variations;
(f) the Schedule 5 provisional sums;
(g) pricing of previously certified variations;
(h) alleged non-mechanical defects;
(i) alleged mechanical services system defects;
(j) wrongful set-off, deductions and withholding of payments;
(k) the defendant’s claim for additional damages; and
(l) interest.
[6] Depending on the findings in respect of certain issues in dispute, some of the issues
identified may not need to be determined. However, due to the nature of the
proceedings, these issues will be addressed, to some degree, at this initial stage and
relevant findings made.
[7] The parties have also prepared a list of the issues of law in dispute between the parties
to this proceeding. This has been broken down into liability and quantum. These
issues will be considered under the headings identified above.
1 BUI.001.001.61820.
-- 8 of 210 --
9
THE MECHANICAL SERVICES SYSTEM
[8] The most significant issue in dispute between the parties is in relation to the air
conditioning system to be installed at the Spring Hill Hotel. The plaintiff contends
that by notices given in August and September 2016 there was a variation to the air
conditioning system required to be installed under the Contract (Mechanical
Variation). The defendant disputes this and contends that the notices required that
the plaintiff comply with its obligations under the Contract and install an air
conditioning system in accordance with the contractual requirements.
[9] The parties have agreed that the following facts and issues are not in contention in
respect of the alleged Mechanical Variation:
“1. In respect of the alleged Mechanical Variation:
(a) that the Mechanical Direction (consisting of written
notices given on 11 August 2016, 16 August 2016 and 17
September 2016 (together or individually)) was given to
the plaintiff [SOC [6]; Def [7]];
(b) that the plaintiff performed the additional works required
by the Mechanical Direction [SOC [8]; Def [9]].”
[10] In respect of the substantial issues of law in dispute between the parties in relation to
the Mechanical Variation, the parties have agreed the following:
“1. In respect of the alleged Mechanical Variation:
(a) whether, on a proper construction of the Contract, the
plaintiff was required to design and install an air-
conditioning system allowing mode control in each room
[SOC [7]; Def [8]; R [7];
(b) whether the air-conditioning system being installed by
the plaintiff prior to the Mechanical Direction (consisting
of written notices given on 11 August 2016, 16 August
2016 and 17 September 2016 (together or individually))
was defective because it did not meet performance
requirements [SOC [7]; Def [8(a)(ii)]; R [7](ab)]]:
(i) of the Contracts; or alternatively
(ii) of the Mechanical Services Specification and the
Mechanical Services Preliminary Design
Drawings;
(c) whether, on a proper construction of the Contract, the
Mechanical Direction:
(i) was a direction to the plaintiff to undertake a
variation in respect of the mechanical works, within
the meaning of clause 1 and clause 36 of the
Contract [SOC [7]; Def [8]; R [7]]; or instead
-- 9 of 210 --
10
(ii) constituted a notice of defective work pursuant to
clause 29.3 or alternatively directions under clause
8.1 of the Contract [Def [7]-[8]; R [6]-[7]].”
[11] The starting point is to consider the terms of the Contract.
Design and Construct Contract
[12] The parties entered into a Formal Instrument of Agreement on or about 29 April 2015.
[13] Clause 2 states:
“2. PERFORMANCE
(a) The Contractor shall carry out the Works in accordance
with the Contract.
(b) The Principal shall pay the Contractor the contract sum
at the times and in the manner provided for in the
Contract.
(c) Each of the parties shall perform the obligations imposed
on it by the Contract.”
[14] Further, clause 3 provides:
“3. CONTRACT DOCUMENTS
The Contract comprises the Contract Documents.”
[15] Pursuant to clause 1, the defined terms in the Formal Instrument of Agreement have
the same meaning as in clause 1 of the General Conditions.
[16] Clause 4 states:
“4. ENTIRE CONTRACT
(a) The Contract Documents constitute the entire agreement
between the parties in respect of the Works and the
Contract supersedes all previous agreements.
(b) The Contract may be varied only by written instrument
executed by both parties.”
[17] Schedule 1 outlines the documents which constitute the “Contract Documents”. The
documents include the Formal Instrument of Agreement, the General Conditions and
Annexures Part A to P. Relevantly to the current issue, Annexure Part K includes the
preliminary design, Annexure Part L outlines the principal’s project requirements,
Annexure Part O contains clarifications and Annexure Part P contains provisional
sums.
[18] The General Conditions are the Australian Standard General Conditions of Contract
for Design and Construct (as Amended) AS4902-2000 (Incorporating Amendment
No. 1).
-- 10 of 210 --
11
[19] Clause 1 of the General Conditions contains definitions where the words and phrases
have that meaning unless the context requires otherwise.
[20] The defined terms include as follows:
(a) Contractor’s design obligations means:
“all tasks necessary to design and specify the Works required by
the Contract, including preparation of the design documents
and, if the Principal’s project requirements include a
preliminary design, developing the preliminary design.”
(b) Preliminary design means:
“the documents stated in Annexure Part K.”
(c) Principal’s project requirements means:
“the Principal’s written requirements for the Works described
in the documents stated in Annexure Part L which:
(a) shall include the purpose;
(b) may include the Principal’s design, timing and cost
objectives for the Works; and
(c) shall include a preliminary design.”
(d) WUC (from ‘Work under the Contract’) means:
“the work which the Contractor is or may be required to carry
out and complete under the Contract and includes variations,
remedial work, construction plant and temporary works.”
[21] Clause 2 sets out the Nature of Contract and provides as follows:
“2.1 Performance and payment
The Contractor shall carry out and complete WUC in
accordance with the Contract and directions authorised by the
Contract.
Subject to the express provisions of the Contract and the
performance by the Contractor of its obligations pursuant to
the Contract, the Principal shall pay the Contractor the
contract sum adjusted by any additions or deductions made
pursuant to the Contract.
2.2 Contractor’s warranties
Without limiting the generality of subclause 2.1, the Contractor
warrants to the Principal that:
(a) the Contractor:
(i) at all times shall be suitably qualified and
experienced, and shall exercise due skill, care and
diligence in the carrying out and completion of
WUC;
-- 11 of 210 --
12
(ii) has examined any preliminary design included in
the Principal’s project requirements and that such
preliminary design is suitable, appropriate and
adequate for the purpose stated in the Principal’s
project requirements;
(iii) shall carry out and complete the Contractor’s
design obligations to accord with the Principal’s
project requirements and, if subclause 9.4 applies,
accept the novation and retain the Principal’s
consultants for any work the subject of a prior
contract with the Principal; and
(iv) shall carry out and complete WUC in accordance
with the design documents so that the Works, when
completed, shall:
(A) be fit for their stated purpose; and
(B) comply with all the requirements of the
Contract; and
(b) subject to clause 9, the consultants identified in the
Contractor’s tender are suitably qualified and
experienced.
…
2.6 Performance specifications
Where the Principal’s project requirements include
performance specifications:
(a) the Contractor shall ensure that the performance
specifications are satisfied when:
(i) completing the design, specification,
documentation and construction of the Works; and
(ii) making any selection of any materials, goods, plant
or equipment for inclusion into the Works; and
(b) the Contractor shall ensure that:
(i) its obligations under this clause are carried out in
accordance with the standard expected of a
contractor competent in designing and constructing
works of the kind the subject of the performance
specification; and
(ii) the works and materials the subject of the
performance specification are fit for the purpose.”
…
-- 12 of 210 --
13
2.10 Clarifications
The parties agree that the clarifications apply to the Works or
the contract sum.”
[22] Clause 8 deals with the Contract documents and includes as follows:
“8.1 Discrepancies
When construing the Contract Documents the following rules
of construction apply:
(a) in the event of any inconsistency between the Contract
Documents:
(i) the formal instrument of agreement and these
general conditions have precedence; and
(ii) the clarifications have precedence over the
preliminary design;
(b) despite the previous subclause 8.1(a):
(i) where inconsistent levels of quality are required,
the higher level of quality shall apply;
(ii) figured dimensions shall take precedence over
scaled dimensions; and
(iii) drawings made to larger scales shall take
precedence over drawings made to smaller scales;
(c) where the requirements of quality or any aspect of WUC
is not expressly specified or depicted, the quality shall be
consistent with the purpose; and
(d) drawings showing particular parts of WUC shall take
precedence over drawings for more general purposes; and
(e) in all cases, the interpretation to be followed by the
Contractor will be as reasonably determined by the
Superintendent.
Where the Contractor considers that there is any ambiguity or
discrepancy between the Contract Documents, it shall promptly
advise the Superintendent in writing, who shall, subject to this
subclause 8.1, give the Contractor a direction as to the
interpretation to be followed.
The Contractor shall have no entitlement as a consequence of
a direction given by the Superintendent under this subclause
8.1 which is consistent with the rules of construction in this
clause 8.1.
…
-- 13 of 210 --
14
8.4 Contractor’s obligations in relation to the Principal’s
project requirements
The Contractor shall:
(a) ensure that the information provided by the
Superintendent defines the Principal’s project
requirements in sufficient detail for the Contractor to
complete the design documents;
(b) determine what additional information it needs from the
Principal to clarify the Principal’s project requirements;
and
(c) make requests in writing to the Superintendent to provide
that information and include with those requests
whatever information the Principal may reasonably
require in order to make a decision.
If in the Superintendent’s opinion the information sought by the
Contractor under this subclause is reasonably necessary to
clarify the Principal’s project requirements, the Superintendent
may refer the request to the Principal and obtain a response to
such request.
Neither the Superintendent nor the Principal shall be bound by
any information provided to the Contractor in relation to the
Principal’s project requirements unless it is in writing and
signed by the Superintendent and expressly provides that the
information forms part of the Principal’s project requirements.
8.5 Contractor’s design obligations
The Contractor shall as part of the Contractor’s design
obligations:
(a) ensure that the design documents (including any design
documents which were not produced by the Contractor
or are Principal’s materials) satisfy the Principal’s
project requirements;
(b) ensure that the design documents contain sufficient detail
to construct the Works so that the Works, when
completed, satisfy the warranties in subclause 2.2;
(c) ensure that the details contained in any design documents
are co-ordinated with the details contained in all other
design documents;
(d) ensure that any approval that needs to be obtained, can be
obtained from the relevant authority in relation to the
design documents;
(e) allow the Superintendent, the Principal or any person
nominated by the Principal access to partially completed
design documents at any time;
-- 14 of 210 --
15
(f) keep the Superintendent informed of the progress of the
design documents;
(g) conduct sufficient investigations to ascertain the
existence and extent of any latent conditions which may
have an effect on the Works.”
[23] Clauses 29.3 and 29.4 deal with Defective work and provide as follows:
“29.3 Defective work
If the Superintendent becomes aware of work done (including
material provided) by the Contractor which does not comply
with the Contract, the Superintendent shall as soon as
practicable give the Contractor written details thereof. If the
subject work has not been rectified, the Superintendent may
direct the Contractor to do any one or more of the following
(including times for commencement and completion):
(a) remove the material from the site;
(b) demolish the work;
(c) redesign, reconstruct, replace or correct the work; and
(d) not deliver it to the site.
If:
(a) the Contractor fails to comply with such a direction; and
(b) that failure has not been made good within 5 days after
the Contractor receives written notice from the
Superintendent that the Principal intends to have the
subject work rectified by others,
the Principal may have that work so rectified and the
Superintendent shall certify the cost incurred as moneys due
from the Contractor to the Principal.
29.4 Acceptance of defective work
Instead of a direction pursuant to subclause 29.3, the
Superintendent may direct the Contactor that the Principal
elects to accept the subject work, whereupon there shall be a
deemed variation.”
[24] In addition to the entire contract clause in the Formal Instrument of Agreement, clause
44.5 of the General Conditions provides:
“44.5 Entire understanding
The Contract:
(a) is the entire agreement and understanding between the
parties on everything connected with the subject matter
of the Contract; and
-- 15 of 210 --
16
(b) supersedes any prior agreement or understanding on
anything connected with that subject matter.
Each party has entered into the Contract without relying on any
representation by any other party or any person purporting to
represent that party.”
[25] Annexure Part L sets out the Principal’s project requirements as follows:
“Principal’s project requirements
(Clause 1)
The Principal’s project requirements:
1. include the purpose;
2. include the preliminary design;
3. include:
(a) all work necessary for the development of the preliminary
design;
(b) all work necessary to comply with legislative requirements;
(c) all work necessary for the design and construction of the
Works;
(d) all work to be completed pursuant to the Contract.
4. are:
(a) the Contractor shall carry out and install all incidental
services and works to achieve practical completion in
accordance with the Contract whether or not those
incidental services are specifically identified in the
Contract; and
(b) to the extent qualified within Annexure Part O, the
Contractor is responsible pursuant to Annexure Part J to
negotiate as required with all authorities having jurisdiction
over WUC to obtain at the Contractor’s cost all necessary
permits, consents, approvals, certificates and the like from
authorities that have not already been obtained by the
Principal prior to the date of the Contract in order to
complete the whole of the Works by the date for practical
completion.”
[26] Annexure Part O sets out the clarifications and includes:
“1. WUC includes:
…
(u) The Contractor’s alternative proposal for structural and
mechanical systems on the basis that the Contractor
-- 16 of 210 --
17
meets the performance requirement of the tender
drawings and specifications.
…
(ag) Refer VE items listed below:
(i) Mechanical Services: The Contractor, in
conjunction with its preferred subcontractors has
reviewed the documented design criteria and has
offered an alternative air conditioning system based
on VRF type arrangement. The system operates on
a variable power supply and without the need for
standalone controls and variable speed drives.
Additionally, the proposal also adopts a revised
pipe and duct configuration. …”
[27] The preliminary design documents include the Mechanical Services Specification
reference 3235 dated October 2014 prepared by Thwaite Consulting Group
(Specification).2
[28] The Specification contains a number of relevant provisions including:
“1.2.2 SPECIFICATION OBJECTIVES
• The intent of this Specification and the associated
documents is:
I. To provide a basis for competitive tendering
II. To allow competent Contractors to price the works
III. To provide documentation to demonstrate to the
Client the scope and quality of the project
IV. To define the expectations upon the installer, by the
Consulting Engineer
…
1.2.3 OBLIGATIONS OF THE MECHANICAL
CONTRACTOR
• In writing this Specification the Client expects and relies
upon the tenderers’ possessing specialist trade expertise
necessary to complete the works in accordance with the
documentation
• To raise in good time, issues requiring design input or
clarification from the Consulting Engineer, particularly
in respect to:
I. interpretation of the Specification or drawings
II. problems in complying with the Specification
2 BUI.001.002.34972.
-- 17 of 210 --
18
III. omissions from the tender documents
IV. suggested alternatives/substitutions
• To provide fully co-ordinated mechanical services shop
drawings with adequate provision for access and
maintenance
• To certify compliance with Contract documents,
including all variation instructions, at Practical
Completion as required by this Specification
…
[29] 1.3 MECHANICAL CONTRACTOR’S DESIGN
RESPONSIBILITY
• The mechanical contractor shall be responsible for
ensuring that the detailed design which they undertake is
fully co-ordinated and compatible with the remainder of
the project design
• The mechanical contractor’s design obligation shall
include all:
I. Heat load calculations
II. Equipment selections
III. Duct work and pipe work distribution system
design …”
[30] Clause 2 of the Specification identifies the scope of work as follows:
“2.1 SCOPE OF WORK
2.1.1 GENERAL SCOPE OF WORK
• The general scope of work of the mechanical services
shall comprise:
1. Detailed thermal and/or capacity calculations as
required to size all plant and equipment
2. Detailed design and documentation of the
mechanical services layout
…
5. Preparation of work shop drawings for review
prior to ordering or commencing fabrication of
plant and duct work systems
6. Supply and installation of complete and operating
mechanical systems and associated controls and
electrical works
…
-- 18 of 210 --
19
2.1.2 SPECIFIC SCOPE OF WORK
• The specific scope of work of the mechanical services
shall comprise the following:
1. Central air-cooled chilled water and heating hot
water system serving the building
2. Air conditioning to guest room corridors L1-12
3. Air conditioning to guest rooms L1-12
4. Air conditioning to gym L1
5. Air conditioning to FOH areas GF
6. Air conditioning to BOH areas GF
7. Air conditioning to meeting rooms GF
…
22. All associated controls works and BMCS to
provide complete and operating mechanical
systems
…
2.1.3 DESIGN CALCULATIONS
• The mechanical contractor shall provide all necessary
heat load calculations, ventilation rate calculations,
system operating pressures calculation, duct sizing and
pipe sizing calculation etc. to support the selection of all
plant and equipment used in the installation
• The calculations shall be presented to the consultant
who will check that they meet specification
requirements. The mechanical contractor shall ensure
that they are technically correct and in accordance with
their or an appropriate quality assurance system.
2.1.4 PREPARATION OF DOCUMENTATION
• The mechanical contractor shall prepare workshop
drawings of their design layouts
• All workshop drawings shall be submitted in accordance
with program requirements for the approval of the
Superintendent prior to installation. Approval, as
appropriate, shall be granted by the Superintendent in
principal only, such approval does not relieve the
Contractor of their responsibility to comply with the
requirements and intent of the specification and
drawings.
…
-- 19 of 210 --
20
• Provide details of all proposed equipment, including but
not limited to equipment schedules and technical data,
method of support, platforms.
…
2.1.7 SAMPLES, PROTOTYPES AND APPROVED
EQUIPMENT
• Samples of materials and items required to be approved
shall be delivered to site a minimum of 10 working days
prior to approval being required. Sample fittings and
accessories are required to be approved include but are
not limited to:
1. Air diffusion equipment
2. Thermostats and sensors
3. Duct manufacturing method
• A schedule of approved equipment manufacturers is
detailed below. The contract is deemed to include
equipment of this standard or ‘approved equal’ as
approved by the Consultant.
VRV plant
Air-cooled chiller
Fans – centrifugal
Fans – axial
Air filters
Dampers
Air Diffusion equipment
Mitsubishi Electric, Daikin
Aermec, Carrier
Fantech, Richardson, Phoenix
Fantech, Ziehl-Abegg
Airpure, Email, and Camfil Farr
Holyoake, Blendair
Holyoake, Air Grilles
[31] Section 2.2 outlines the Mechanical Systems Description.
[32] Section 2.2.1 deals with the “central air-cooled heat recovery chiller CH-1, CH-2
CHW/HHW” and states as follows:
“The entire hotel (excluding specialist areas which have stand-alone
DX air conditioning systems) shall be provided with chilled water
and heating hot water from a common air-cooled 4 pipe chiller (heat
recovery type) located on the roof …”
[33] Clause 2.2.3 deals with the “guest room air conditioning FCU’s”. “FCU” refers to
Fan Coil Unit. This includes the following:
“2.2.3 GUEST ROOM AIR CONDITIONING FCU’S
• Each guest room shall be individually air conditioned by
ceiling mounted FCU’s which supply conditioned air to
the room served via acoustically insulated sheet metal
-- 20 of 210 --
21
duct work (discharge and suction sides) connecting to a
wall mounted linear grille
…
• Provide electronic controls with a wall mounted
temperature sensor/switching/adjustment to control the
FCU and interface with the guest room energy
management system provided as part of the electrical
trades work.”
[34] Clause 3 of the Specification deals with the design criteria.
[35] Clause 3.1 states as follows:
“3.1 DESIGN CRITERIA
• Design criteria presented herein form the basis for the
design of the works and for any alternative proposals
submitted.
Item Design Criteria
External ambient conditions
(for air conditioning plant full
load performance)
Summer
33.1℃ dry bulb maximum
24.8℃ wet bulb maximum
Winter
6.0℃ dry bulb maximum
Internal conditions (for
conditioning plant full load
performance) general
Summer
23℃ dry bulb maximum at
point of control
Winter
21.5℃ dry bulb at the point of
control
Controls tolerance for air
conditioning system
+/-2.0℃ dry bulb at point of
control (+/- 1.0℃ dead band)
Outside Air In accordance with AS 1668.2
2013 requirements
Exhaust Air In accordance with AS 1668.2
2013 requirements
Occupancy Refer Table A.
Hours of operation Continuous
-- 21 of 210 --
22
Table A. Internal Loads
Area People Outside Air Lighting
Density
W/m²
Power
Density
W/m²
Equip.
KW
Gym 8 10L/s/p 15 15
Guest rooms 2 25L/s/room 15 5 -
General office areas 1/10m2 10L/s/p 15 10 -
FOH lounge 1/3m2 10L/s/p 15 10 -
FOH lobbies areas 1/3.5m2 10L/s/p 15 10 -
Building Construction Details Refer to architectural drawings.
Maximum External Noise Levels To meet the Local Authority
requirements nominated in the
Development Application
conditions and Wilkinson Murray
Acoustic Report
Maximum Vibration Levels Tactile structure vibration levels due
to plant not to exceed the lower end
of the range specified in AS 2670.2.
Equipment Balancing AS 2625 for rotating and
reciprocating machines
…
3.4 ACCEPTANCE CRITERIA
• Acceptance of Practical Completion and of Final
Completion will require at least the following:
(a) Compliance Certification to the requirements of
Statutory Authorities.
(b) Signed off commissioning schedules to confirm
that systems operate in a stable and automatic
manner under all conditions of full and partial load
– full commissioning data and operating and
maintenance manuals.
(c) Certification that capacities and efficiencies of
equipment and systems satisfy specified
requirements where specifically nominated to do so
in the Specification.”
[36] Relevantly, clause 9.8.2 deals with “CHW/HHW fan coil units guest rooms” and
outlines certain mandatory items and control functions to be provided for each FCU
system which includes:
“(b) Start Stop Control and Indication
-- 22 of 210 --
23
- Wall mounted combined FCU controller with ON-OFF
switch
- Interface with guest room energy management system
provided by the electrical trade
(c) Temperature Control
- Space temperature sensor integral to ON-OFF switch
- Chilled water and heating hot water control valve
modulation to satisfy cooling and heating load
- Each fan coil unit (and associated fans as applicable) shall
be started individually according to a pre-set schedule of
daily operation ...”
Plaintiff’s contentions
[37] The plaintiff contends that on the proper construction of the Contract, the mechanical
works, including the air conditioning and heating system, did not require the
mechanical system installed by the plaintiff to provide for “mode control” (as
opposed to temperature control) in each individual room. As a result, the defendant’s
requirement notified in correspondence dated 11 August 2016, 16 August 2016 and
17 September 2016 (individually or together, the “Mechanical Direction”) that the
mechanical system then being installed be changed was a direction to undertake a
variation within the meaning of clauses 1 and 36 of the Contract, being the
Mechanical Variation.
[38] There is no dispute that the plaintiff performed the work required (subject to the
defects which are alleged by the defendant).
[39] The plaintiff also contends that the Mechanical Variation caused a delay to the date
for practical completion of 117 days.
[40] Overall, in respect of the Mechanical Variation, the plaintiff contends that the
defendant is liable to the plaintiff in the amount of $2,076,392.25 (plus GST), being
$1,074,577.25 (plus GST) for the WUC and $1,001,815 (plus GST) for delay
damages.
[41] The first step in the plaintiff’s case is to consider what the Contract required the
plaintiff to build and install by way of the mechanical system. The plaintiff refers to
clause 1(u) of Annexure Part O and also clause 1(ag) of Annexure Part O.
[42] The plaintiff contends that these two clauses are insufficient to identify the alternative
proposal and as the plaintiff had an obligation to install the alternative proposal (on a
certain basis), the first step is to identify that proposal.
[43] The plaintiff concludes that:
“It is necessary, and entirely orthodox, to have regard to extrinsic
evidence to answer [the question ‘what was that alternative
proposal?’]. After examining the legal principles, the evidence is
-- 23 of 210 --
24
analysed, and the alternative proposal is identified as a two pipe VRF
heat pump system.”
[44] To reach this conclusion, the plaintiff in its closing submissions, undertakes the
exercise of examining case law in relation to the use of extrinsic evidence identifying
the subject matter of a contract, consideration of the relevant clauses in the Contract
and also extrinsic evidence relevant to the alternative proposal consisting of a number
of documents and emails exchanged as part of the precontractual negotiations leading
up to the Contract being entered into.
[45] It is necessary to consider each of these steps in turn.
Use of extrinsic material
[46] The plaintiff acknowledges that on the settled authorities in respect of the objective
theory of contract, the following principles apply:
(a) The meaning of a contract is to be decided in accordance with what the terms
of the contract would convey to a reasonable person in the position of the
parties, rather than by reference to the subjective intentions of one, or even
both, parties to the contract.
(b) In determining the meaning of the terms for a commercial contract, it is
necessary to ask what a reasonable businessperson would have understood
those terms to mean.
(c) Unless a contrary intention is indicated in the contract, a court is entitled to
approach the task of giving a commercial contract an interpretation on the
assumption that the parties intended to produce a commercial result, and to
avoid working “commercial inconvenience”.
(d) Determining the meaning of a written contractual term, or words used in a
contract, ordinarily occurs by reference to the contract alone, being the
contractual text and contextual matters.
(e) There are a number of recognised exceptions that allow reference to be made
to contextual matters which are extrinsic to the language used in the contract
to determine the meaning of words used in a contract.
[47] The principal exception to the parol evidence rule is as framed by Mason J (as his
Honour then was) in Codelfa Construction Pty Ltd v State Rail Authority (NSW):3
“The true rule is that evidence of surrounding circumstances is
admissible to assist in the interpretation of the contract if the language
is ambiguous or susceptible of more than one meaning. But it is not
admissible to contradict the language of the contract when it has a
plain meaning.”
[48] After referring to this quote from Codelfa, the written submissions on behalf of the
plaintiff go on to state:
“Another exception to the parol evidence rule referred to by Mason J
in Codelfa was extrinsic evidence which assists in the identification
3 (1982) 149 CLR 337 at 352.
-- 24 of 210 --
25
of the subject matter of the contract. At 349, his Honour cited with
approval Lord Davey in Bank of New Zealand v Simpson4 who in turn
quoted with approval the remarks of Lord Campbell in Macdonald v
Longbottom5 as follows:
‘I am of opinion that, when there is a contract for the sale or
[sic] a specific subject-matter, oral evidence may be received,
for the purpose of shewing what that subject-matter was, of
every fact within the knowledge of the parties before and at the
time of the contract.’”
[49] It is important to note that this reference to Macdonald v Longbottom occurs in the
reasons of Mason J when he is undertaking a review of the then authorities in relation
to recourse to extrinsic evidence. This occurs prior to his statement at page 352 that
is referred to as “the true rule”. The plaintiff’s submissions suggest that Mason J
identified the circumstances in Macdonald v Longbottom as a specific exception to
the parol evidence rule. Rather, a reading of the reasons of Mason J tends to support
that this needs to be considered in light of the statement of principle as set out in the
“true rule”.
[50] The statement of principle of the “true rule” by Mason J continues on after the quote
that has been identified in the plaintiff’s submissions. It is necessary to consider the
whole of the statement of principle which continues:
“Generally speaking facts existing when the contract was made will
not be receivable as part of the surrounding circumstances as an aid
to construction, unless they were known to both parties, although, as
we have seen, if the facts are notorious knowledge of them will be
presumed.
It is here that a difficulty arises with respect to the evidence of prior
negotiations. Obviously the prior negotiations will tend to establish
objective background facts which were known to both parties and the
subject matter of the contract. To the extent to which they have this
tendency they are admissible. But in so far as they consist of
statements and actions of the parties which are reflective of their
actual intentions and expectations they are not receivable. The point
is that such statements and actions reveal the terms of the contract
which the parties intended or hoped to make. They are superseded by,
and merged in, the contract itself. The object of the parol evidence
rule is to exclude them, the prior oral agreement of the parties being
inadmissible in aid of construction, though admissible in an action for
rectification.
Consequently when the issue is which of two or more possible
meanings is to be given to a contractual provision we look, not to the
actual intentions, aspirations or expectations of the parties before or
at the time of the contract, except in so far as they are expressed in
the contract, but to the objective framework of facts within which the
contract came into existence, and to the parties’ presumed intention
4 [1900] AC 182 at 188–9.
5 (1859) 1 E & E 977 at 983, 120 ER at 1179.
-- 25 of 210 --
26
in this setting. We do not take into account the actual intentions of
the parties and for the very good reason that an investigation of those
matters would not only be time consuming but it would also be
unrewarding as it would tend to give too much weight to these factors
at the expense of the actual language of the written contract.”6
[51] The plaintiff’s submissions contend that the relevant principle is that “if the subject
matter of a contract cannot be ascertained by reference to the terms of the contract
itself, then extrinsic evidence may be referred to, and relied upon by the Court ‘to
identify the meaning of a descriptive term’.”7
[52] The plaintiff refers to a number of relevant circumstances in the current matter:
(a) The Contract does not define the words “alternative proposal”.
(b) There were no drawings or specifications with respect to the alternative
proposal.
(c) The tender drawings and the Specification set out details of the mechanical
system in accordance with the original tender proposal.
[53] The plaintiff contends that the tender drawings and the Specification cannot be used
to define the alternative proposal.
[54] In relation to clause 1(u) and clause 1(ag) of Annexure Part O, the plaintiff submits:
“Clause 1(u) does nothing to describe the alternative proposal, other
than to refer to the fact that the alternative proposal exists. However,
this clause does say, unambiguously, that the WUC which Built was
obliged to perform included the installation of the alternative
proposal. It is therefore critical that the alternative proposal be
accurately identified in order for the Court to know what Built’s
obligation to perform the WUC was with respect to the mechanical
system.”
[55] In relation to clause 1(ag) the plaintiff also submits that whilst this does provide some
assistance, it does not provide enough information to make any concluded findings
as to what the alternative proposal was.
[56] The reference in clause 1(ag) to “VRF type arrangement” assists in showing that the
obligation was to build a VRF type arrangement, and not a chilled water system which
was originally in the tender proposal. However, the plaintiff submits that there are at
least two different types of VRF systems and a generic reference does not assist in
determining which of the two different systems was to be installed.
[57] Evidence was led at trial in relation to the two different types of VRF system, namely:
(a) A VRF heat pump system where all indoor units can either heat or cool, but not
at the same time. This system requires two pipes to operate, where one pipe
delivers either cooling or heating and the second pipe extracts air.
6 At 352.
7 Plaintiff’s written closing submissions at [26].
-- 26 of 210 --
27
(b) A VRF heat recovery system where cooling and heating may be available to
each indoor unit, independently, at the same time. This usually requires three
pipes to operate, although the plaintiff recognises that Mitsubishi does
manufacture a two-pipe heat recovery system. Under this system, the first pipe
delivers cooling, the second pipe delivers heating and the third pipe is a return
pipe.
[58] The plaintiff submits that the other words in clause 1(ag) do little to assist the Court
in identifying what was the alternative proposal other than the words “the proposal
also adopts a revised pipe and duct configuration”. Whilst these words do not identify
a specific pipe and duct configuration, they make it clear that the pipe and duct
configuration was not to be the same as that set out for the mechanical system in the
tender proposal.
[59] The plaintiff also acknowledges that the words “has reviewed the documented design
criteria and has offered an alternative air conditioning system” may also be of
assistance in construing the words “performance requirement” in clause 1(u).
[60] Ultimately, the plaintiff contends that:
“Extrinsic evidence must be admitted in order to ascertain what the
alternative proposal was. That is critical to understanding Built’s
obligations, including assessing Built’s claim for a variation to the
mechanical system”.8
[61] Prior to undertaking a review of the extrinsic evidence, the plaintiff also submits that
when considering the extrinsic evidence it is important to “contemplate the caveat on
the alternative proposal, that is, ‘… on the basis that the Contractor meets the
performance requirement of the tender drawings and specification’.”
[62] The plaintiff contends in this respect that:
“Considered objectively and leaving aside any express requirement to
the contrary, the ‘performance requirement of the tender drawings
and specification’ could not include a ‘performance requirement’ that
the alternative proposal could never achieve, or was, in fact, not
designed to achieve – imposing such a requirement would be
fundamentally inconsistent with the alternative proposal being part of
the agreed WUC. Accordingly, identifying the alternative proposal is
a critical first step before considering what the performance
requirement of the tender drawings and specification was”.9
[63] This statement is relevant to what the plaintiff is attempting to achieve by resort to
the extrinsic evidence. This will be further explored later in these reasons.
Extrinsic evidence sought to be relied upon by the plaintiff
[64] The plaintiff seeks to rely upon the following extrinsic evidence:
(a) the invitation to tender response; and
8 Plaintiff’s written closing submissions at [35].
9 Plaintiff’s written closing submissions at [36].
-- 27 of 210 --
28
(b) correspondence evidencing negotiations between the submission of the
plaintiff’s tender on 19 January 2015 and the execution of the Contract on 29
April 2015.
[65] The documents relied upon in relation to the tender process establish that the
invitation to tender allowed, and the plaintiff submitted, a conforming tender and also
an alternative tender. The tender summary identified a cost difference between the
conforming tender and the alternative tender with respect to the alternative
mechanical system in the amount of $786,567.00. Further, reference is made to a
statement under the heading “Schedule Two – Section One – Built Design &
Construct Alternate Tender Clarifications” at page 62, where it states under
subheading four “Mechanical Services”:
“Built in conjunction with our preferred subcontractors have reviewed
the documented design criteria and have offered an alternative Air
Conditioning system based on VRF type arrangement.
The system proposed provides a more efficient solution in terms of
the running costs due to the equipment operates on a variable power
supply and without the need for standalone controls and variable
speed drives which inherently are costly and complex to program and
operate. Additionally, the proposal also adopts a revised pipe and
duct configuration, thus reducing the initial cost of these
components.”
[66] The language used is reflected (largely) in clause 1(ag) of Annexure Part O and clause
1(u) of the Contract. The plaintiff submits that this is relevant as “objectively, it may
be inferred that the parties intended to adopt the alternative proposal envisaged by
Built’s ‘non-conforming’ tender”.
[67] The second category of extrinsic evidence sought to be relied upon by the plaintiff is
the precontractual negations from the period between when the tender response was
submitted and the Contract was signed. The plaintiff identifies that there are
numerous meetings, discussions and extensive correspondence between the plaintiff
and the defendant, including through the defendant’s agents:
“(a) to clarify what was included in, and excluded from, Built’s
tender; and
(b) to negotiate the terms of the Contract, with a focus on the final
scope of the WUC and the final Contract price.”
[68] The plaintiff also seeks to rely on information in relation to its subcontractor, Batec,
continuing to develop the design and provide further details of the alternative
proposal.
[69] This evidence includes:
(a) An email on 6 March 2015 from Mr Collison of Tactical to Mr Thwaite stating
“Pro Invest have agreed to proceed with a VRV system”10 and Mr Thwaite’s
10 PRO.020.001.2336.
-- 28 of 210 --
29
response “[h]ow interesting. After all the words from holiday inn about
complying with their brief”.11
(b) Email dated 30 March 2015 at 2.35pm from Mr Meredyth of the plaintiff to Mr
Collison of Tactical which attached a proposed air conditioning layout and
piping configuration sample “for your acceptance prior to documenting the
design”. The email states that the “A/C zones will be divided into two zones
to cater for different heat loads on the building façade and units will be
combined vertically over a number of floors off the same condenser”. The
email confirms the temperature set point will range between 22 and 24 degrees
celsius and requests approval/acceptance.12
(c) An email dated 30 March 2015 at 5.30pm from Mr Collison of Tactical to Mr
Meredyth of the plaintiff,13 which includes in the email chain as follows:
(i) At 2.46pm Mr Collison forwarded Mr Meredyth’s email to Mr Thwaite
asking for advice and stating that subject to that advice he would “issue
appropriate instructions to Built”.
(ii) At 4.54pm, Mr Thwaite responded to Mr Collison including as follows:
“7. Are the VRV systems proposed to be heat recovery
type or reverse cycle type? If the former are they 3
pipe or 2 pipe type? If the latter is the placement of
FCUs proposed to be consistent with the façade
they are mounted on (similar thermal zone).”
(iii) At 5.30pm, Mr Collison forwarded Mr Thwaite’s comments to Mr
Meredyth and requested clarification prior to confirming acceptance.
(d) An email dated 31 March 2015 at 2.31pm from Mr Meredyth of the plaintiff to
Mr Thwaite responding to the questions as follows:
“Our proposal utilises reverse cycle 2 pipe configuration. All
FCU’s will be located as per original design and all condensers
will be located on mechanical plant deck.”14
(e) The same email contained a further response from Mr Meredyth stating that
“[m]aximum allowable refrigerant lift for Toshiba VRF system is 80metres”.
(f) An email dated 31 March 2015 at 2.47pm from Mr Thwaite responding as
follows:
“… I note your other comments and they are OK with the
exception of the ground floor AC systems. The location of any
condensing units at low level would be a point of great concern
for the architect …The meeting proposed is to dot the iiiis [sic.]
over what is the actual scope of work of the mechanical
services contract which you believe that you have signed up
11 PRO.020.001.2336.
12 BUI.001.002.27678.
13 BUI.001.004.23878.
14 BUI.100.002.6309.
-- 29 of 210 --
30
for … The hotel operator also has particular requirements
which will need to be addressed …”15
(g) An email dated 31 March 2015 at 3.11pm from Mr Meredyth responding to Mr
Thwaite’s comments as follows:
“We have not been provided with a [sic] IHG Brief other than
the Tender Drawings and specification, and as such this is all
we have to work with in terms of criteria (despite the
conforming being a Chilled Water System which is obviously
different in many ways). The offer of a conforming and
alternative were provided at Tender with the Client electing to
adopt the alternative at a significantly reduced price.”16
(h) Meeting minutes dated 25 February 2015 between various personnel of
Aurecon, Tactical and the defendant recorded under the heading “VRV –
Chilled Water” which state as follows:
“It was agreed that VRV is the solution for HIE, subject to the
system being designed with belts and braces to ensure issues
such as gas leakage are covered, as well as servicing.
JR noted that VRV can and has been used successfully up to
30 stories and can be used in mixed-use however the metering
issue needs to be addressed.
JR will seek to meet with IHG in Singapore next week to
outline the background to the proposal to use VRV as IHG
have a preference for a traditional chilled water system.
GC [Glenn Collison] noted the savings in Spring Hill were in
the order of $700,000 (in mechanical and structure).
The Ibis Adelaide has a VRV system and the Ibis Brisbane will
have an [sic] VRV system.”17
(i) An email dated 9 April 2015 from Mr Meredyth of the plaintiff to Mr Collison
of the defendant forwarding an email from Cushway Blackford.18 Mr
Meredyth’s covering email refers to the email from Mr Brock of Cushway
Blackford and stated:
“Please note that largely the IHG Standard and Thwaite design
is based on Chilled Water therefore large sections of the design
are not applicable hence we have not marked up the
specification but rather commented separately.”
(j) The email from Mr Brock of Cushway Blackford stated:19
“… please find attached concept sketch & supporting brief
description of the proposed mech systems.
15 BUI.001.004.23883.
16 BUI.100.002.6329.
17 PRO.020.001.0070.
18 BUI.001.002.27682.
19 BUI.001.002.27682.
-- 30 of 210 --
31
Note there is only one (1) material change from the current
mechanical design, which is VRF in lieu of chilled water.
Detailed summary of current proposal (for reference):
- 2-pipe heat pump VRF systems, zoned north/south over 2
floors each (total 12x systems + ground) …”
(k) Attached to the email was also a letter from Cushway Blackford dated 9 April
2015,20 which stated:
“Air conditioning for the building is proposed to be of the
Variable Refrigerant Flow (VRF) type, in lieu of chilled water
systems, with condensing units located on Level 1 podium and
roof (refer attached sketches).
The VRF systems will be of the 2-pipe heat-pump type, and
zoned such that areas with different solar loads are served by
separate plant.
The above proposal is based on our understanding of the IHG
Engineering Standards (Asia Pacific) Section 9 (Holiday Inn
Express Supplement), generally as follows:
- Clause 9.2.1 nominates VRF as an option for air
conditioning
- Clause 9.2.3 allows the use of 2-pipe systems, with
electric re-heat in temperate climates only (Brisbane is
sub-tropical climate).
In general, the remainder of the current building mechanical
services design (documented by Thwaite Consulting Group)
will not be altered in principle.”
(l) An email dated 15 April 2015, from Mr Collison of Tactical responding to Mr
Meredyth’s email of 9 April 2015 stating:
“Grant
As discussed, we have received confirmation from the Principal
to proceed with the mechanical design development in
accordance with information summarised in the email
below…”21
[70] The plaintiff contends that based on this extrinsic evidence the words “alternative
proposal” used in the Contract, is a reference to a two-pipe VRF heat pump system.
Further, the plaintiff contends that it “is uncontroversial that this type of system [a
two-pipe VRF heat pump system] cannot provide mode control to each individual
guest room”.22
20 BUI.001.002.27683.
21 BUI.001.002.18824.
22 Plaintiff’s written closing submissions at [79].
-- 31 of 210 --
32
[71] The submissions made by the plaintiff from paragraphs [50] to [79] of the plaintiff’s
written closing submissions contain commentary based on each of the pieces of
extrinsic evidence claimed to be admissible on the approach identified above.
[72] Some of the submissions contain conclusions based on knowledge outside of what is
stated on the face of the documents. For example, in paragraph [52] reference is made
to the email of 6 March 2015 referring to a VRF system. Discussion then ensues as
to the two different types of VRF system being the heat pump system where units can
either heat or cool, but not at the same time, and heat recovery systems where cooling
and heating are available independently, at the same time.
[73] Further, at [55] in considering the email dated 30 March 2015 the inference is drawn
from the reference to “A/C zones” and “two zones to cater for different heat loads on
the building façade” as being a statement that “could only be a reference to a VRF
heat pump system”. This seeks to infer a conclusion that the referenced words support
a conclusion that the alternative proposal could not heat or cool at the same time.
[74] At this point in the submissions, reference is also made to evidence from Mr Lord in
his expert report dated 22 July 2019. This was obviously not material that was known
to the parties as an independent objective fact prior to the Contract being entered into.
Submissions occur in paragraphs [57] to [59] in relation to the operation of a two-
pipe VRF heat pump system which is not apparent from the extrinsic material referred
to above.
[75] For example, paragraph [58] involves a discussion of how the occupants in rooms
within the “zoned” areas do have temperature control under a two-pipe VRF heat
pump system. An occupant is said to be able to adjust the temperature by regulating
the amount of cooling received (if the system is in cooling mode) or the amount of
heating received (if it is in heating mode). Further, it is identified that if the system
was in cooling mode and an occupant wanted a warmer temperature, the occupant
could select the temperature and the system would respond by providing ventilation,
not chilled air. Thus, the temperature in the room would change as requested by the
occupant. This also applies in the reverse scenario where the system is in heating
mode and an occupant wants a cooler temperature.
[76] At paragraph [60], it is expressly acknowledged that the subjective understanding of
the parties is not relevant. Therefore, it does not matter whether or not Mr Collison
understood that what was being proposed was a two-pipe VRF heat pump system.
What is relevant is the objective position.
[77] The submissions also refer to the piping schematic attached to the email dated 30
March 2015 as evidencing that:23
(a) the manufacturer would be Toshiba;
(b) it was a two-pipe system; and
(c) it did not have branch boxes.
23 BUI.001.002.27681.
-- 32 of 210 --
33
[78] The submissions again extrapolate from this evidence that the piping schematic could
“only be depicting a VRF heat pump system” because that system uses two pipes and
it could not be a heat recovery system, as that system uses three pipes.
[79] Further, at paragraph [64] of the plaintiff’s written closing submissions, reference is
made, in particular, to comments from Mr Thwaite by email dated 30 March 2015 at
4.54pm containing comment number seven. The submission is phrased as being that
Mr Thwaite “was clearly mindful of the fact that if the system was a heat pump VRF
system it would be designed such that there would be ‘zones’ and that those ‘zones’
would need to be ‘consistent with the façade they are mounted on’.” Again, it is
extrapolated that the reason for the zoning is that it is a heat pump system and
simultaneous heating and cooling would not be provided to the individual indoor
units.
[80] At paragraph [70] of the submissions, the plaintiff mixes what it is seeking to rely on
from the extrinsic material with the current expert evidence. The plaintiff refers to
the conclusion in Mr Dowden’s report24 that a reverse cycle system or heat pump
system can only distribute heating or cooling at one time and not simultaneously to
establish that “an inherent feature of a heat pump system is that it can only distribute
heating or cooling at one time and not simultaneously”. This is not an objective fact
established by the extrinsic material, but the plaintiff seeks to use it to bolster its case
through an interpretation of the extrinsic material that it seeks to rely upon.
Performance requirement of the tender drawings and the Specification
[81] The second aspect to be considered is the phrase in clause 1(u) of Annexure Part O:
“on the basis that the Contractor meets the performance requirement
of the tender drawings and specifications”.
[82] The meaning of “performance requirement” is in dispute. It is not defined in the
Contract.
[83] It is accepted by the plaintiff that the reference to “tender drawings and
specifications” is a reference to the tender drawings and the Specification.
[84] Whilst both parties have referred to expert evidence in relation to the meaning of
“performance requirement”, the plaintiff’s primary position is that the question of
interpretation of the Contract is a matter for the Court and not expert evidence. That
is the correct approach.
[85] The plaintiff contends that not every aspect of the tender drawings and the
Specification amounts to a performance requirement. That is, it is relevantly a subset
of statements within those documents where there is a requirement for performance
of the mechanical system. The plaintiff also seeks to distinguish the method by which
that performance is achieved.
24 EXP.001.001.0012.
-- 33 of 210 --
34
[86] This consideration leads to the contention as outlined in paragraph [89] of the
plaintiff’s written closing submissions as follows:
“Because Part O, clause 1(u) limits Built’s obligation to the
performance requirement of the tender drawings and specification,
the methods by which these systems achieve particular minimum and
maximum temperatures is immaterial – what matters is whether the
systems in fact achieve particular minimum and maximum
temperatures because that is the performance requirement of the
Thwaite specification.”
[87] This contention is reliant upon the plaintiff’s focus on the design criteria set out in
clause 3.1 of the Specification. The argument proceeds that the alternative proposal
originally being installed by the plaintiff could have achieved the temperatures set out
in the design criteria in clause 3.1 of the Specification and therefore the performance
requirement of the Contract had been met.
[88] The plaintiff also seeks to rely on the expert evidence in relation to the practical
realities of an occupant of a room being able to control the temperature outside a
designated temperature range. However, there is no articulation of the basis upon
which it is contended that this extrinsic evidence can be relied upon to interpret the
clause in the Contract.
[89] This contention is expressed at paragraph [104] of the plaintiff’s written closing
submissions as follows:
“In Built’s submission the ability of the air conditioning system to
achieve particular temperature ranges was the relevant performance
required by the Thwaite Specification … The fact that the Thwaite
specification offered a different method of achieving that same
performance cannot mean that the particular method adopted in that
case (i.e. mode control to each individual guestroom) was the relevant
performance requirement. The requirement was to achieve a
particular temperature range. Guests using the alternative proposal
would have … been able to achieve that range of temperatures. That
a different method was to be utilised is of no relevance.”
[90] There is a difference between the plaintiff’s written closing submissions and the oral
submissions made on 13 November 2020. At paragraph [106] of the written closing
submissions it states “[a] reasonable person in the position of the parties at the time
of contract would not consider clause 2.2.1 (and those that follow) of the Specification
to have any relevance in circumstances where the alternative proposal was not an ‘air-
cooled 4 pipe chiller (heat recovery type)’”. However, at the hearing it was conceded
that there may be some performance requirements contained in the Specification and
drawings that were not contained in clause 3.1 Design Criteria.25 However, this was
not explored further but the concession was made and it was noted by Senior Counsel
for the defendant.26
[91] Further, the plaintiff contends that hotel guests in individual rooms had the ability to
heat or cool their rooms and that “the alternative proposal allowed individual guests
25 T15-5, L27; T15-5, L42-43.
26 T15-69, L34-37.
-- 34 of 210 --
35
to set their thermostat so as to achieve their desired temperature within those limits,
by way of obtaining conditioned air or simply ventilation”.27
[92] The plaintiff also submits that the parties cannot have intended the Contract to mean
that the requirements of virtually all parts of the Specification were performance
requirements as this would in effect negative the obligation to install the alternative
proposal. Further, it is contended the parties cannot have intended the Contract to
mean that the alternative proposal should be installed on the basis that it meets a
requirement of the Specification that the alternative proposal, of its very nature, could
not meet.
[93] Reference is made to the fact that clause 1(u) of Annexure Part O uses the singular
“performance requirement”, rather than the plural “performance requirements”.
While the Contract provides that words in the singular include the plural “according
to the requirements of the context”, the plaintiff contends that the context here means
that the use of the singular indicates the performance outcome set out in the design
criteria in clause 3.1 of the Specification. The plaintiff says this is also reinforced in
clause 1(ag) of Annexure Part O by the reference to “documented design criteria”.
[94] Reliance is also placed on the introductory words to clause 3.1 of the Specification
which state as follows:
“Design criteria presented herein form the basis for the design of the
works and for any alternative proposals submitted”.
[95] The plaintiff points to the absence of similar words in relation to sections 2.2 and 2.3
of the Specification as the basis for the submission that they do not have any
application to an alternative proposal.
Defendant’s contentions
[96] The defendant contends that the Contract required that the mechanical services
system meet “the performance requirement of the tender drawings and
specifications”. A key requirement was that the mechanical services system be
capable of independently heating and cooling individual guest rooms. This meant
that each guest could choose heating or cooling, independently from other guests.
[97] The defendant’s position is that the Mechanical Direction was a notice to rectify
defective work as the system being installed by the plaintiff did not perform the
Independent Heating/Cooling Function.
[98] Further, the defendant contends that whilst there was correspondence between the
parties between the submission of the tender proposal (including the alternative
proposal) and the Contract being executed, the Contract itself is what needs to be
considered as being the agreement reached between the parties.
[99] The defendant submits as follows:
“Rather, what the parties did was the exact opposite. They chose to
insert a ‘clarification’ in the Contract that specifically allocated the
risk to Built that the alternative mechanical services system would
27 Plaintiff’s written closing submissions at [112].
-- 35 of 210 --
36
meet the performance requirement of the Tender Drawings and
Specification. There are two sophisticated commercial parties
entering into a $32 million Contract for the design and construction
of a hotel. This is how the parties chose to deal with any risk which
existed in respect of this particular issue. The basis for this agreement
of course is consistent with the entire understanding clause contained
in clause 44.5 of the Contract …”28
[100] In respect of the approach to the proper construction of the Contract, including clause
1(u) of Annexure Part O, the defendant submits:
(a) it is not permissible to use the functionality of the alternative proposal to dictate
what the performance requirement is.29
(b) the knowledge or understanding of the defendant in respect of the two-pipe
VRF system is not relevant to the operation of clause 1(u).30
(c) the evidence does not support a fact objectively known by the defendant that
the alternative system did not provide the Independent Heating/Cooling
Function.31
(d) the parties could have included particulars of the alternative proposal in the
Contract. However, this was not done. Clause 1(u) was inserted, together with
two entire agreement clauses in the Contract.32
(e) clause 1(u) refers to the performance requirements of the “tender drawings and
specifications”. This is a compound expression, and the phrase must be read
together. The words support reading “performance requirement” in the
plural.33
(f) every word in clause 1(u) must be given effect to “so as to preserve the bargain
reached between these two commercial parties”. The plaintiff’s construction
does not do this.34
(g) the parties intended that the performance requirements be found in both the
tender drawings and the Specification.35
(h) this construction is consistent with clause 1(u) being a risk allocation provision.
That is:
“It provides that in exchange for a $33 million contract, it is
Built who assumes the risk that the mechanical services system
it designs and constructs will meet the performance
requirements of the tender drawings and specifications.”36
(i) clause 1(u) does not use the phrase “the documented design criteria” and the
deliberate choice of words used tends to support a different meaning. This in
28 Defendant’s written closing submissions at [25].
29 Defendant’s written reply submissions at [7].
30 Defendant’s written reply submissions at [10].
31 Defendant’s written reply submissions at [11]-[12].
32 Defendant’s written reply submissions at [13].
33 Defendant’s written reply submissions at [16]-[18].
34 Defendant’s written reply submissions at [19].
35 Defendant’s written reply submissions at [20].
36 Defendant’s written reply submissions at [20].
-- 36 of 210 --
37
turn, tends to support a construction that the performance requirements are to
be found in both the tender drawings and Specification.37
[101] As to the approach to the construction of clause 1(u) of the Contract, the defendant
contends:
(a) it is not correct to undertake the exercise proposed by the plaintiff to identify
the alternative proposal.
(b) but, even if that is done, and the alternative proposal is a “VRF two pipe heat
pump system”, it is still to meet the performance requirements in the tender
drawings and the Specification.38
[102] Further, the defendant submits there is no ambiguity in clause 1(ag) of Annexure Part
O – it says a VRF type arrangement. But even if it is assumed to be a two-pipe VRF
system, the risk allocation remains in favour of the defendant.39
[103] The defendant acknowledges that parol evidence is admissible to identify the subject
matter of a written contract but this is in circumstances where the subject matter is
expressed in an uncertain or ambiguous fashion. That is not the case here.40
[104] In response to the plaintiff’s submission on the correct construction of the Contract,
the defendant refers to and relies on MacDonald v Shinko Australia Pty Ltd.41
[105] In that case, McPherson JA stated:42
“It is well established that parol evidence is admissible to identify the
subject matter of a written contract. A recent example, which in some
ways resembles the present, is Akot Pty Ltd v. Rathmines Investments
Pty Ltd [1984] 1 Qd.R. 302. But in that instance, and in the decisions
discussed in it, the written contract was, as regards subject matter,
expressed in an uncertain or ambiguous fashion. Here there is no
uncertainty or ambiguity in the contractual identification of the
subject matter. The designation in the written contract of 29 August
1995 may have been the result of a mistake; but on its face it is
perfectly plain. Parol evidence of pre-contractual statements is not
needed in order to identify it from the description given in the written
contract.”
[106] Further, Davies JA stated:43
“… the appellant submits that because of cl. 28.1 of the instrument of
contract between the parties the respondent cannot refer to evidence
outside the instrument to prove a prior oral contract or a continuing
common intention of the parties to buy and sell a unit different from
37 Defendant’s written reply submissions at [25].
38 T14-11, L15-T14-12, L5.
39 T14-12, L7-26.
40 T15-66, L37-T15-67, L18.
41 [1999] 2 Qd R 152 (McPherson and Davies JJA and Moynihan J).
42 At 154.
43 At 156.
-- 37 of 210 --
38
that identified in the contract in order to seek rectification of that
instrument. The clause is in the following terms:
‘ENTIRE AGREEMENT
This Agreement constitutes the entire agreement of the parties
as to its subject matter and supersedes and cancels all prior
arrangements, understandings and negotiations in connection
with it.’
The purpose of that clause, it seems to me, is to exclude any such
evidence either to prove terms additional to or different from the
written instrument or collateral contracts or to construe the instrument
in a way different from the meaning to be inferred solely from its
terms.”
[107] As there is no uncertainty or ambiguity here, the defendant contends it is not
permissible to undertake the task as proposed by the plaintiff of looking at the pre-
contractual documents.
[108] On the proper construction of the Contract, the defendant’s position is that the
plaintiff was required to build a mechanical services system that satisfied the
performance requirement of the Contract to provide the Independent Heating/Cooling
Function. In these circumstances, the Mechanical Direction was not a variation but
was a notice to rectify defective work.
Consideration
[109] Following consideration of the relevant authorities and submissions on behalf of both
parties, I have reached the conclusion that extrinsic material is not admissible to
interpret the words “alternative proposal” contained in clause 1(u) of Annexure Part
O of the Contract.
[110] This conclusion is reached on the following reasoning.
[111] The “true rule” as identified by Mason J in Codelfa Construction Pty Ltd v State Rail
Authority (NSW) remains binding authority in relation to this issue.
[112] Often reference is made to the first two sentences of “the true rule” without
consideration of the discussion which immediately follows that statement. It is
necessary to consider the full statement of the rule.
[113] Further, the decision of the High Court in Mount Bruce Mining Pty Ltd v Wright
Prospecting Pty Ltd,44 considered the applicable legal principles. French CJ, Nettle
and Gordon JJ in joint reasons stated as follows:45
“The rights and liabilities of parties under a provision of a contract are
determined objectively, by reference to its text, context (the entire
text of the contract as well as any contract, document or statutory
provision referred to in the text of the contract) and purpose.
44 (2015) 256 CLR 104.
45 At 116-7 [46]-[52].
-- 38 of 210 --
39
In determining the meaning of the terms of a commercial contract, it
is necessary to ask what a reasonable businessperson would have
understood those terms to mean. That inquiry will require
consideration of the language used by the parties in the contract,
circumstances addressed by the contract and the commercial purpose
or objects to be secured by the contract.
Ordinarily, this process of construction is possible by reference to the
contract alone. Indeed, if an expression in a contract is unambiguous
or susceptible of only one meaning, evidence of surrounding
circumstances (events, circumstances and things external to the
contract) cannot be adduced to contradict its plain meaning.
However, sometimes, recourse to events, circumstances and things
external to the contract is necessary. It may be necessary in
identifying the commercial purpose or objects of the contract where
that task is facilitated by an understanding ‘of the genesis of the
transaction, the background, the context [and] the market in which
the parties are operating’. It may be necessary in determining the
proper construction where there is a constructional choice. The
question whether events, circumstances and things external to the
contract may be resorted to, in order to identify the existence of a
constructional choice, does not arise in these appeals.
Each of the events, circumstances and things external to the contract
to which recourse may be had is objective. What may be referred to
are events, circumstances and things external to the contract which
are known to the parties or which assist in identifying the purpose or
object of the transaction, which may include its history, background
and context and the market in which the parties were operating. What
is inadmissible is evidence of the parties’ statements and actions
reflecting their actual intentions and expectations.
Other principles are relevant in the construction of commercial
contracts. Unless a contrary intention is indicated in the contract, a
court is entitled to approach the task of giving a commercial contract
an interpretation on the assumption ‘that the parties … intended to
produce a commercial result’. Put another way, a commercial
contract should be construed so as to avoid it ‘making commercial
nonsense or working commercial inconvenience’.
These observations are not intended to state any departure from the
law as set out in Codelfa Construction Pty Ltd v State Rail Authority
(NSW) and Electricity Generation Corporation v Woodside Energy
Ltd.” (Footnotes omitted)
-- 39 of 210 --
40
[114] The reasons of Kiefel J (as the Chief Justice was then) and Keane J recognise that the
“ambiguity” referred to in Codelfa arises when the words are “susceptible of more
than one meaning”. However, their Honours noted:
“His Honour did not say how such an ambiguity might be identified.
His Honour’s reasons in Codelfa are directed to how an ambiguity
might be resolved.”46
[115] Their Honours then considered the refusal of special leave to appeal in the matter of
Western Export Services Inc v Jireh International Pty Ltd.47 In the reasons for refusal
of special leave, reference was made to a requirement that it is essential to identify
ambiguity in the language of the contract before the Court may have regard to the
surrounding circumstances and the object of the transaction. Their Honours noted
“[t]here may be differences of views about whether this requirement arises from what
was said in Codelfa. This is not the occasion to resolve that question.”48 French CJ,
Nettle and Gordon JJ in their joint reasons agreed with the observations of Kiefel and
Keane JJ in respect of this issue.49
[116] The appeal in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd proceeded
on the basis that any possible ambiguity as to the meaning of the words being
considered in that case arose from the terms of the clause in the contract itself.
Whether an ambiguity in the meaning of terms in a commercial contract may be
identified by reference to matters external to the contract did not arise in that case.50
[117] This may be relevant to considerations in the current case as discussed further below.
[118] While Codelfa remains binding authority, the question whether ambiguity must be
shown before a Court interpreting a written contract can have regard to background
circumstances has received differing applications. It could be said that the existence
and scope of the ambiguity required is a matter of judicial controversy. A
consideration of this controversy is summarised by Jackson J of this Court in a first
instance decision in Aurizon Network Pty Ltd v Glencore Coal Queensland Pty Ltd &
Ors.51 Whilst this matter was overturned on appeal, and the Court of Appeal reached
a different construction of the contract, the summary of some of the relevant issues
and differing views as to the approach to extrinsic evidence as set out in paragraphs
five to 122 has not been disturbed.
[119] One of the difficulties identified in the overview of the authorities and approaches is
“drawing the line between admissible evidence of extrinsic facts that are raised in
negotiations and inadmissible evidence of prior negotiations that would tend to reveal
or prove the parties’ subjective intentions”.52 That line is also relevant here when
consideration is given to the particular extrinsic material that the plaintiff has sought
to rely on and also other material including the current expert reports and inferences
sought from what appears to be a combination of the pre-contractual negotiations and
the opinions contained in the expert reports. It is important to keep in mind that it is
46 At 132 [110].
47 (2011) 86 ALJR 1 at 2 [2].
48 At 132 [111].
49 At 117 [52].
50 At 133 [113].
51 [2019] QSC 163.
52 At [62].
-- 40 of 210 --
41
“objective facts” known to both parties that may be admissible if the ambiguity
“gateway” is established. The consideration of extrinsic facts, being facts that were
known to all relevant parties at the time of making the contract, is substantially
different to attempts to find meaning of terms in pre-contractual negotiations and then
to import them into terms used in the contract.
[120] In these circumstances I consider that the extrinsic material sought to be relied upon
is inadmissible on the basis that the plaintiff is seeking to rely on more than the
objective facts known to the parties at the time the Contract was entered into. This is
evidenced by consideration of the plaintiff’s submissions in respect of the individual
extracts of the emails and other documents sought to be relied upon by the plaintiff.
[121] Further, I am not satisfied that the ambiguity threshold has been made out. The
reference to “alternative proposal” in clause 1(u) is informed by clause 1(ag) of
Annexure Part O of the Contract. This clearly states:
“The Contractor, in conjunction with its preferred subcontractors has
reviewed the documented design criteria and has offered an
alternative air conditioning system based on VRF type arrangement”.
[122] There is no ambiguity as to what the alternative proposal is. It is a VRF air
conditioning system. The second and third sentences in clause 1(ag) also add a level
of detail to the “alternative proposal”.
[123] In these circumstances I do not consider that the “gateway” has been satisfied so as
to enable recourse to extrinsic material to interpret clause 1(u).
[124] It is not expressly raised in submissions but it is open to be inferred from the plaintiff’s
submissions that they are seeking to identify the ambiguity through the extrinsic
material itself. This is the issue that was identified in the reasons of Kiefel and Keane
JJ in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd. The issue is
therefore whether reference to matters external to the Contract can be relied on to
identify the ambiguity.
[125] This appears to be directly at odds with the parol evidence rule itself and also with
the fact that there are two entire agreement clauses in the current Contract: one in the
Formal Instrument of Agreement and one in the General Conditions.
[126] The parol evidence rule remains a fundamental rule in relation to the construction of
contracts. This was confirmed by the decision of the High Court in Equuscorp Pty
Ltd v Glengallan Investments Pty Ltd.53 In the joint judgment of Gleeson CJ,
McHugh, Kirby, Hayne and Callinan JJ, their Honours stated:
“The respondents each having executed a[n] … agreement, each is
bound by it. Having executed the document, and not having been
induced to do so by fraud, mistake, or misrepresentation, the
respondents cannot now be heard to say that they are not bound by
the agreement recorded in it. The parol evidence rule, the limited
operation of the defence of non est factum and the development of
the equitable remedy of rectification, all proceed from the premise
that a party executing a written agreement is bound by it …
53 (2004) 218 CLR 471 at 483 [33].
-- 41 of 210 --
42
There are reasons why the law adopts this position. First, it accords
with the ‘general test of objectivity [that] is of pervasive influence in
the law of contract’. The legal rights and obligations of the parties
turn upon what their words and conduct would be reasonably
understood to convey, not upon actual beliefs or intentions …
Where parties enter into a written agreement, the Court will generally
hold them to the obligations which they have assumed by that
agreement. At least, it will do so unless relief is afforded by the
operation of statute or some other legal or equitable principle
applicable to the case …
It is a time to maintain those rules. They are not unbending. They
allow for exceptions. But the exceptions must be proved according
to established categories. The obligations of written agreements
between parties cannot simply be ignored or brushed aside.”54
(Footnotes omitted)
[127] The parol evidence rule itself would operate to exclude extrinsic evidence for the
purpose of interpretation. One of the issues to be considered, however, is whether the
parties as a matter of fact, determined the whole of the Contract would be in writing.
In this case where there are two entire agreement clauses this may be sufficient to
satisfy that issue without further consideration.
[128] The existence of the entire agreement clauses evidences express statements that the
written Contract represents the whole of the agreement.
[129] There is a view that where an entire agreement clause is included, the result may be
that the parties have “contracted out of contextualism”. This may be an additional
basis for excluding reference to extrinsic evidence for the purpose of contractual
interpretation.55
[130] The High Court in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd clearly
identified that the task involves an interpretation on the assumption that the parties
intended to produce a commercial result. The plaintiff has made submissions that it
is necessary to identify the subject matter with precision so that it can be known with
certainty what the alternative proposal is and also that it would be a commercial
absurdity if, in effect, the alternative proposal was incapable of complying with the
“performance requirement of the tender drawings and specifications”.
[131] Conversely, the defendant submits that the parties could have inserted particular
details as reflected in the emails and documents sought to be relied on as extrinsic
evidence. However, they chose not to do that. There is some force in the submission
that the parties chose to insert the particular “clarification” that identified the
alternative proposal at a more general level with a specific qualification allocating the
risk to the plaintiff.
[132] The defendant submits that this is consistent with the entire agreement and
understanding clause and is a result of two sophisticated commercial parties entering
into a design and construct contract. This will be considered further below in relation
54 At 483-4 [33]–[35].
55 Hon JJ Spigelman AC, “Contractual Interpretation: A comparative perspective” (2011) 85 ALJ 412.
-- 42 of 210 --
43
to the interpretation of clause 1(u). However, this is also relevant to the consideration
of the admissibility of the extrinsic material.
[133] The maintenance of the parol evidence rule and the upholding of entire agreement
clauses in contracts is consistent with recognising a commercial objective for
certainty. This could be described as a “fundamental commercial objective for all
parties … to know where they stand without undergoing the risks and uncertainties
of litigation”.56
[134] Phrasing this a different way, at the time of contracting commercial parties may
attribute significant value to certainty. Allowing extrinsic evidence to be introduced
which may cut across that certainty and the allocation of risk would be contrary to a
commercial result. Some go further and describe this as follows:
“[T]he idea that an arbitrator or a judge would be called upon to
determine the true intention of the parties by going beyond the written
contract to encompass anything which disputing parties can
relevantly imagine, would be regarded by most parties, at the time of
formation of the contract, to constitute a commercial disaster.”57
[135] It is in these circumstances that an entire agreement clause being upheld and enforced
provides a commercial result consistent with the express agreement by the parties that
the written Contract forms the whole agreement between the parties and replaces all
previous representations and drafts.
[136] The allocation of risk between the parties is recognised as being a significant purpose
of contract law but is particularly so in relation to construction contracts. This is a
design and construct contract and the allocation of risk in relation to design is
something that is considered further below.
[137] In these circumstances I consider that the extrinsic material sought to be relied upon
by the plaintiff is not admissible.
Construction of clause 1(u) Annexure Part O
[138] The task is then to consider more broadly what is meant by clause 1(u) of Annexure
Part O.
[139] In Byrnes v Kendle,58 Heydon and Crennan JJ observed in relation to contractual
construction as follows:
“The approach taken to statutory construction is matched by that
which is taken to contractual construction. Contractual construction
depends on finding the meaning of the language of the contract – the
intention which the parties expressed, not the subjective intentions
which they may have had, but did not express. A contract means
what a reasonable person having all the background knowledge of the
‘surrounding circumstances’ available to the parties would have
56 Hon JJ Spigelman AC, “Contractual Interpretation: A comparative perspective” (2011) ALJ 412 at
429.
57 Ibid.
58 (2011) 243 CLR 253.
-- 43 of 210 --
44
understood them to be using the language in the contract to mean.
But evidence of pre-contractual negotiations between the parties is
inadmissible for the purpose of drawing inferences about what the
contract meant unless it demonstrates knowledge of “surrounding
circumstances”.59
[140] In the context of statutory construction, in the recent decision of Westpac Securities
Administration Ltd v Australian Securities and Investments Commission,60 Gordon J
commented:
“[The clause] is to be read as a whole and given its ordinary meaning,
in light of its context and purpose. It is not to be dissected into
separate words or phrases, the meanings of which are then
amalgamated into some composite meaning.”61 (Footnotes omitted)
[141] There is a risk in this case of doing exactly what Gordon J warned about. The plaintiff
has focused on two distinct aspects of clause 1(u) and then contended that they would
be inherently inconsistent and therefore that could not be the meaning. However, if
the clause is read as a whole and given its ordinary meaning, in light of its context
and purpose, then the tension identified falls away.
[142] As submitted by the defendant, clause 1(u) makes it clear that the alternative proposal
was only being accepted on the basis that it met the performance requirement of the
tender drawings and the Specification. It also clearly allocates the risk that the
mechanical services system will meet the performance requirement set out in both the
tender drawings and the Specification to the plaintiff.
[143] The issue is then, on the proper construction of clause 1(u) of Annexure Part O
whether independent heating and cooling (or referred to as mode control) was a
performance requirement of the tender drawings and the Specification.
[144] The preliminary design documents are contained in Annexure Part K and incorporate
the drawings and Specification. It is not contentious that these are the documents that
the original tender proceeded on.62
[145] The reference to “tender drawings and specifications” in clause 1(u) Annexure Part
O is therefore to be interpreted as a reference to the drawings and specifications
included in the Contract.
[146] These documents also form part of the “Principal’s project requirements”. The
express purpose of the Principal’s project requirements is the design and construction
of the “project”, namely, the Spring Hill Hotel.
[147] The relevant clauses of the Contract are set out in full above. These include:
(a) Clause 2.2 of the Contract which requires the plaintiff to carry out and complete
its design obligations in accordance with the “Principal’s Project
Requirements” and to complete the WUC in accordance with the drawings and
59 At 284 [98].
60 [2021] HCA 3.
61 At [54].
62 Subject to one revision with the Roof Level Plan issued as series “A”, rather than “Rev.01”.
-- 44 of 210 --
45
specifications in Annexure Part K so that the works, when completed, would
be fit for their stated purpose and comply with all requirements of the Contract.
(b) Clause 2.6 of the Contract which provides that where the “Principal’s project
requirements” include “performance specifications”, the plaintiff was required
to ensure that the performance specifications were satisfied when completing
the design and construction of the works and in making any selection of
materials, plant or equipment for inclusion in the works so that the works would
be fit for purpose.
[148] The term “performance requirement” is not used in clause 2.6.
[149] The critical issue for determination in this matter is whether or not the Independent
Heating/Cooling Function was a performance requirement of the tender drawings and
the Specification.
[150] It is not a task before this Court to interpret all or any other performance requirement
or performance requirements of the tender drawings and the Specification.
[151] Applying the ordinary meaning, the term refers to a requirement relating to
performance. In this case, a requirement relating to performance of a mechanical
services system, being the air conditioning system.
[152] The defendant refers to the Macquarie Dictionary definition of these terms as follows:
“Performance: ‘the way in which something reacts under certain
conditions or fulfils the purpose for which it was intended’.
Requirement: ‘that which is required; a thing demanded or
obligatory’.”
[153] Reference is also made to the definition of “performance” in the Australian Oxford
Dictionary to mean “the capabilities of a machine”.
[154] The shorter Oxford English Dictionary defines “performance” as including:
“The capabilities of a machine, esp. a motor vehicle or aircraft,
measured under test.”
[155] This definition identifies a capability of a machine which is measurable. This appears
to be an apt definition for the current consideration.
[156] The question may then be considered as whether independent heating or cooling was:
(a) Required, obliged or demanded.
(b) A capability of the air conditioning system.
(c) Measurable.
-- 45 of 210 --
46
[157] The clause is also to be considered in the context of the Contract itself. There are
several preliminary matters which are relevant to these considerations including:
(a) The performance requirement is to be ascertained, identified or otherwise
derived from the tender drawings and specifications. This task does not require
a consideration of the alternative proposal.
(b) The reference is to “tender drawings and specifications” and the reference to
both would support a construction that draws on requirements from both
sources. This is of particular significance given the plaintiff’s submission that
clause 3.1 of the Specification sets out all of the relevant performance criteria
which could constitute performance requirements for the purposes of clause
1(u). This cannot be the meaning intended by the language used. Otherwise,
there would be no need for “drawings” to be included.
(c) The term “performance requirement” is not used elsewhere in the Contract. It
is to be contrasted with other terms such as “performance specification” (clause
2.6 of the Contract), “acceptance criteria” (clause 3.4 of the Specification) and
“design criteria” (clause 3 of the Specification). Objectively, the use of a
specific and different term supports a conclusion that it was intended to mean
something different to those other terms and should not be limited to the
meaning in those other terms.
[158] While the drawings and the Specification were prepared on the basis that the
mechanical services system to be installed was a “four pipe chiller (heat recovery
type)”, there are several aspects of the drawings and the Specification which support
a construction that the Independent Heating/Cooling Function was a requirement
applicable to an alternative proposal based on a VRF air conditioning system. These
include:
(a) Clause 2.2.1 of the Specification provides for an “air-cooled four pipe chiller
(heat recovery type)” system which has a specific function that it can perform
independent heating/cooling. The requirement of an Independent
Heating/Cooling Function is an inherent capability of that air conditioning
system.
(b) Clause 2.2.3 of the Specification stipulates that each guest room is to have its
own indoor FCU with Chilled Water Coils (CHW) and Heated Hot Water Coils
(HHW), together with wall mounted electronic controls. Inherently, this would
enable each guest to adjust the heating and cooling in their room.
(c) Clause 9.8.2 of the Specification provides details about the wall mounted
controls to be installed in each room, including functions for temperature
control specifically “[c]hilled water and heating hot water control valve
modulation to satisfying [sic] cooling and heating load”. The wall mounted
controller was to be capable of modulating the heating and cooling in the
individual guest room by controlling the CHW and HHW coils in the FCU.
Whilst under a VRF system CHW and HHW coils would not be relevant, this
requirement to be able to modulate heating and cooling in an individual room
tends to support a requirement that whatever system was actually installed, it
was to be able to achieve this outcome.
[159] The particular wording in clause 2.2.3 of the Specification provides “[e]ach guest
room shall be individually air conditioned … which supply conditioned air to the
-- 46 of 210 --
47
room …”. This reference to each room being individually air conditioned and to
conditioned air being supplied, tends to support the construction as contended for by
the defendant.
[160] The plaintiff argues that in effect, guests in individual rooms are able to obtain
temperature control with the two-pipe heat pump system that was partially installed,
by in effect, moderating the zone temperature by switching off the conditioned air
and introducing ventilation. The use of the ventilation was a means by which the
guests could achieve temperature control within the practical temperature range
allowed. However, this is not achieved by way of supply of “conditioned air to the
room”, but rather it is the use of “unconditioned air” to the room in order to achieve
the temperature moderation.
[161] A reasonable businessperson in the position of the parties at the time the Contract was
entered into would understand that the reference to “conditioned air”, either as heated
or cooled, was what was to be provided, not merely using ventilation to moderate or
control temperature in an individual guest room.
[162] Further, the Specification uses specific language to describe when ventilation was to
be provided as opposed to “conditioned air”. For example, the requirements for
mechanical ventilation in clauses 2.2.13 to 2.2.19.
[163] What the language in clause 1(u) does is to provide for a VRF air conditioning system
to be designed which adapts and applies the performance requirements that were set
out in the tender drawings and specifications in respect of the four-pipe chiller (heat
recovery) air conditioning system.
[164] The plaintiff’s argument that this renders nugatory the alternative proposal is
incorrect. It is accepted that it is possible to design a VRF air conditioning system
which does provide for independent heating and cooling. That is what has happened.
The question to be determined is whether clause 1(u) of Annexure Part O required
that or not.
[165] It is also important to keep in mind that this a design and construct contract. The
preliminary drawings that were included at the tender stage and were incorporated
into the final Contract required further detailed design to be undertaken and a process
followed by which compliance with the Specification was considered and further
liaising with the defendant prior to construction as part of the contractual obligations.
A contract of this nature requires design work to be undertaken and then an evaluation
against the requirements and if there was any deviation or variation from that then
further consultation with the principal needed to occur.
[166] Accordingly, clause 8.4 (Contractor’s obligations in relation to the Principal’s project
requirements) and 8.5 (Contractor’s design obligations) of the General Conditions are
also important contextual considerations. These provisions are set out in full above.
[167] Clause 8.1 also provides some context. The provision that the clarifications have
precedence over the preliminary design recognises that changes by way of
clarifications such as in the current case are foreseeable. However, the design
obligations such as clause 8.5(a) tend to suggest that the extent that the clarifications
override the preliminary design are to occur only to the extent necessary and the
-- 47 of 210 --
48
overall project requirements are to be kept in mind. This is captured by clauses
8.1(b)(i) and (c) where considerations of quality and purpose are maintained.
[168] The plaintiff’s argument that clause 3.1 of the Specification contains the only
performance requirements is not persuasive. As indicated previously, the language
of “performance requirement” is different from “design criteria”, “acceptance
criteria” and other terms used in the Contract. The incorporation of the phrase “tender
drawings and specifications” indicates a wider and more comprehensive application.
[169] If the parties had intended that “performance requirement” in clause 1(u) of Annexure
Part O would be the same as clause 3.1 in the Specification then they could have
easily specified that clearly. Instead, alternative language was used including an
express reference to both the Specification and drawings. This alone tends to support
a construction that the performance requirements in clause 1(u) of Annexure Part O
are wider than those in clause 3.1 of the Specification.
[170] The plaintiff’s obligation pursuant to clause 1(u) of Annexure Part O was that the
plaintiff was required to install an air conditioning system based on a VRF type
arrangement on the basis that the plaintiff met the performance requirement of the
tender drawings and specifications.
[171] The Independent Heating/Cooling Function is a performance requirement of the
tender drawings and specifications. Accordingly, the mechanical system to be
installed pursuant to the Contract by the plaintiff was to include the capability of
independent heating and cooling in individual guest rooms.
[172] Consequently, the first question on the list of issues (question 1(a)) is to be answered
in the affirmative. That is, on a proper construction of the Contract, the plaintiff was
required to design and install an air conditioning system allowing mode control in
each guest room, with the ability for occupants of individual guest rooms to select
temperatures utilising the heating system or cooling system independently of other
guest rooms.
Mechanical Direction / Variation
[173] As a consequence of these findings, the next issue to be considered is whether the
notice provided on 11 August 2016 was a notice to rectify defective work as it
purported to be, or whether it constituted a direction for a variation.
[174] By the time of the 11 August 2016 notice, an issue had arisen between the parties as
a result of the two-pipe system that had been designed and partially installed by the
plaintiff not being capable of performing the Independent Heating/Cooling Function.
The two-pipe system which was in the process of being installed operated in either
heating or cooling mode and also grouped multiple rooms together into single zones.
[175] The plaintiff at that time and at the hearing, maintained that the two-pipe system it
had designed and partially installed complied with the requirements of the Contract.
[176] Given my finding above, this position has not been made out.
-- 48 of 210 --
49
[177] The notice given on 11 August 2016 was issued pursuant to clause 29.3 of the
Contract as a notice to rectify defective work. In summary, the Mechanical Direction:
(a) Notified the plaintiff that the mechanical services system being installed did
not comply with clause 1(u) of Annexure Part O of the Contract because it did
not meet the performance requirements of the Specification.
(b) Set out the ways in which the mechanical services system did not meet the
performance requirement of the Specification, including its inability to perform
the Independent Heating/Cooling Function.
(c) Directed the plaintiff to remove or redesign the mechanical services system and
replace it with a mechanical services system that would meet the performance
requirements of the Specification.
[178] Subsequent notices on 16 August 2016 and 17 September 2016 were consistent with
the original Mechanical Direction. The 16 August 2016 notice confirmed that the
original Mechanical Direction had not been given in error, did not constitute a
direction for a variation and further directed the plaintiff to comply with the original
notice. The further notice given on 17 September 2016 again advised that the
Mechanical Direction was valid and current.
[179] The expert evidence at the trial established that the two-pipe VRF system that was
being installed was incapable of performing the Independent Heating/Cooling
Function.63 This was not contentious.
[180] As a result of the language used in clause 1(u) of Annexure Part O, the risk in respect
of the VRF air conditioning system meeting the performance requirement of the
tender drawings and specifications was allocated to the plaintiff. In circumstances
where the mechanical services system installed fell short of that requirement then the
liability of any remedial action that needed to be taken was the responsibility of the
plaintiff.
[181] In these circumstances, the Mechanical Direction was a valid notice to rectify
defective work and was not a direction to undertake a variation. Further, the plaintiff
was required to rectify the defective mechanical services system at its own cost and
is not entitled to the costs of carrying out that work, an extension of time, delay
damages or the return of any liquidated damages set-off by the defendant.
[182] Accordingly, question 1(b) is to be answered in the affirmative.
[183] Question 1(c) of the list of issues is to be answered on the basis that subparagraph (ii)
is the proper construction of the Mechanical Direction.
[184] Given these findings, it is not relevant to consider questions six, 13 and 18 of the list
of issues. These relate to the plaintiff’s claims in relation to the costs of undertaking
the work, its claim for an extension of time and delay damages and the return of any
liquidated damages.
63 See for example EXP.001.001.0012 at p 0033 [12.1].
-- 49 of 210 --
50
[185] However, it is appropriate that I consider these issues and make the necessary findings
in case I am in error in respect of the admissibility of the extrinsic material and the
construction of the Contract. I deal with these issues at Annexure A.
JOINERY DELAY
[186] Overall, the plaintiff submits that the evidence establishes that the delay to practical
completion arose by reason of the Mechanical Direction.64
[187] The defendant contends that the plaintiff or its contractors failed to undertake the
timely installation and delivery of the joinery works. The defendant submits that
there is no entitlement to an extension of time in respect of the alleged joinery delay
as:
(a) the plaintiff did not comply with the notice provisions in clause 34.3(b) of the
Contract; and
(b) the plaintiff was not delayed in reaching practical completion by reason of the
alleged joinery delay.65
[188] Given my findings in these reasons, if this issue needs to be considered further, it
should be addressed as proposed in the further submissions.
BATHROOM DESIGN VARIATION (VP32)
[189] Question two in the list of issues in dispute between the parties is relevant to this
issue:
“2. In respect of the alleged Bathroom Design Variation, whether
[SOC [10], [11], [13]; DEF [11], [12], [13]; R [11], [12], [13],
[14]] whether:
(a) either on a proper construction of the contract or by
operation of a waiver or estoppel, by correspondence
dated 13 July 2015, 5 May 2016 and 12 May 2016
(together or individually), the plaintiff was directed to
undertake a variation of the works in the bathrooms,
within the meaning of clause 1 and clause 36 of the
Contract; and
(b) the plaintiff is entitled to payment for the alleged
variation; or instead
(c) the alleged Bathroom Design Variation resulted in a
reduction to the plaintiff’s scope of works.”
[190] The defendant identifies an additional issue which has not been agreed to by the
plaintiff as follows:
“(d) the plaintiff has complied with the notice provisions contained
in clause 36.1 and clause 20.”
64 Plaintiff’s written closing submissions at [485]-[489].
65 Defendant’s written closing submissions at [315]-[316].
-- 50 of 210 --
51
[191] The relevant issue in respect of quantum is question 14:
“In respect of the alleged Bathroom Design Variation, the price of the
work performed by the plaintiff in carrying out the alleged Bathroom
Design Variation [SOC [13]; Def [13]].”
[192] The parties have also agreed that the following is not in dispute:
“2. In respect of the alleged Bathroom Design Variation:
(a) that the correspondence which is alleged to comprise the
alleged Bathroom Design Direction (consisting of
correspondence dated 13 July 2015, 5 May 2016 and 12
May 2016) was given to the plaintiff attaching drawings
which were marked ‘for construction’ [SOC [10]; Def
[11]];
(b) that the plaintiff performed the bathroom works required
to be undertaken [SOC [11], [12]; Def [12]].”
[193] This claim relates to the supply and installation of certain bathroom fixtures and
fittings which the plaintiff alleges were not within the scope of the Contract. The
plaintiff primarily claims that by correspondence dated 13 July 2015, 5 May 2016 and
12 May 2016, there was an expressed or implied direction for the plaintiff to supply
and install those bathroom fixtures and as a result, this amounted to a variation within
the meaning of the Contract.
[194] The plaintiff claims an amount of $339,441.81 plus GST in respect of this variation.
Mr Watson has provided an expert report on behalf of the plaintiff and values the
claim at $274,314.53 plus GST. Mr Hardiman for the defendant has also prepared an
expert report and values this claim at $289,800.47.
[195] The plaintiff’s primary contention is that the Bathroom Design Variation was a
variation under the Contract pursuant to clause 36.1, and that as a consequence, the
plaintiff is entitled to an assessment of the costs of the variation pursuant to clause
36.4 of the Contract.
[196] Alternatively, if there is no entitlement to the costs of the variation pursuant to clause
36.1, the plaintiff contends that the defendant is estopped from relying on, or has
waived its right to insist upon satisfaction of clause 36.1 of the Contract with respect
to this variation.
[197] The defendant’s position is that the plaintiff is not entitled to an increase in the
contract sum in respect of the alleged bathroom variation as the procedures in clause
36.1 have not been followed. The defendant contends that clause 36.1(f) is not
applicable in the circumstances and that the relevant contractual provision is clause
36.1(g). This clause requires notice to be given within five business days of receiving
a direction to perform the variation. Further, reliance is placed on clause 36.1(h)
which provides that there is no entitlement as a consequence of complying with a
direction for a variation, unless there is entitlement to make a claim under clause 36.1.
-- 51 of 210 --
52
[198] The defendant also relies upon clause 20 as providing a further bar to entitlement.
The defendant contends that clause 20 is also applicable and it similarly contains a
requirement for notice to be given no later than five business days after a direction.
[199] The defendant’s ultimate position is that there is no entitlement as the preconditions
in clause 36.1 and clause 20 have not been complied with.
[200] In order to consider this claim, it is necessary to start with a consideration of what
was required to be built under the Contract. Then, whether there was a change in the
work to be undertaken within the scope of clauses 36.1(a) to (e). Next, it is necessary
to consider whether there was a direction to perform the variation given by the
Superintendent, Tactical, in writing as required by clause 36.1(f) or whether it
amounts to a direction to perform a variation pursuant to clause 36.1(g). Lastly, it is
also necessary to consider whether any relevant notices have been given in
accordance with clause 36.1 and clause 20.
[201] It is not disputed that the plaintiff undertook the work to build and complete the
bathrooms in accordance with the “for construction” design documents. The issue is
whether the plaintiff is entitled to the costs in respect of the alleged additional work
that was required to be carried out.
[202] The additional work claimed by the plaintiff is the additional work associated with
the supply and installation of the additional bathroom fixtures and fittings (Additional
Bathroom Work), including:
(a) the guest room shower screen doors, hinges and towel/handrail;
(b) the stainless steel capping to the bathroom door jamb;
(c) an additional plasterboard wall underneath the vanity; and
(d) extension of the bathroom wall, including the waterproofing, tiling, painting
and skirting.
[203] The claim in respect of this Additional Bathroom Work is the inevitable consequence
of the fact that the design for the bathrooms was not complete at the time of tender
and the Contract being executed. It is apparent from the documents in the Contract
that the final design for the bathrooms was to be undertaken. At the time of tender
and the Contract being executed, indicative preliminary interior design
documentation was included, which was actually for another project, Macquarie Park.
There was also a guest room datasheet specific to the Spring Hill Hotel. As a
consequence of this, the submissions for both parties focus on what was obliged to be
built under the Contract and how the Contract deals with what was actually
constructed in accordance with the “for construction” drawings.
Alleged Direction
[204] The plaintiff points to four documents as the basis for its contention that it was
directed to undertake additional work, including the Additional Bathroom Work.
These four documents are as follows:
-- 52 of 210 --
53
(a) An Aconex transmittal from Joseph Pang Design Consultants (JPDC) to the
plaintiff dated 13 July 2015 attaching “for construction” drawings. This
included drawings relating to the guest room bathrooms.66
(b) An Aconex transmittal from JPDC to the plaintiff dated 5 May 2016 attaching
various “for construction” drawings. These drawings included drawings
relating to the guest room bathrooms.67
(c) Two Aconex transmittals from the defendant dated 12 May 2016 regarding the
status of the “for construction” drawings.68
[205] In order to understand the significance of these documents, it is necessary to consider
the relevant terms of the Contract and also to consider what it was that was required
to be built under the Contract in respect of the guest room bathrooms.
What was required to be built under the Contract?
[206] Annexure Part K of the Contract contains preliminary design documents which
include a number of documents relevant to the guest bathrooms.
[207] Reid Campbell, the architect engaged on the Project, prepared architectural drawings
as part of the preliminary design documents for the Spring Hill Hotel. Annexure Part
K lists the preliminary design documents including, a number of the architectural
drawings under the heading “ARCHITECTURAL – Reid Campbell”. Relevantly,
document A4004 is a document headed “Type 1 & 2 Room Bathroom (Twin &
Queen) Rev. 3”. This drawing,69 shows the architectural design for the queen and
twin room guest room bathrooms, for the 216 guest rooms in this category.
[208] The plaintiff refers to various parts of document A4004 (Type 1 & 2 Room Bathroom
(Twin & Queen) Rev. 3) including notations on the drawing which identify specific
categories of items either to be supplied by the builder, by the client and installed by
the builder or alternatively, supplied and installed by the client (the client being the
plaintiff).
[209] Based on the plaintiff’s analysis of the drawings it is submitted that it is
“uncontroversial” that the defendant was to supply the following items:
(a) the sliding door at the entrance to the bathroom;
(b) the shower door within the bathroom;
(c) the towel rail/handle to the shower door; and
(d) other minor items, such as the toilet roll holder.
[210] In addition to the architectural drawing, Annexure Part K of the Contract also lists
documents under the heading “INTERIOR DESIGN – JOSEPH PANG DESIGN
CONSULTANTS”. Listed are a number of documents with a document reference
starting with “ID” and four documents without that document reference but with the
number “113109”.
66 PRO.001.008.0919.
67 PRO.025.001.2813.
68 PRO.025.001.2978.
69 BUI.001.002.07647.
-- 53 of 210 --
54
[211] Document ID-01-BD is described as “Bathroom Twin Room Issue G”.70 The plaintiff
has also analysed the drawing and submits that the bathroom design is “quite similar”,
although not entirely identical to the design set out in architectural drawing A4004
(Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3).
[212] The plaintiff identifies that the document ID-01-BD does not contain the narration
outlining the position in relation to the various categories of items to be supplied and
installed. There is, however, a notation which states as follows:
“THESE DRAWINGS ARE TO BE READ IN CONJUNCTION
WITH ARCHITECTURAL BASE DRAWINGS & RELEVANT
CONSULTANT DRAWINGS.”71
[213] On the basis of this notation, the plaintiff contends that the consequence of reading
the JPDC document together with the architectural drawing in respect of the bathroom
design would be that the items depicted by the broken lines on the JPDC document
would be items that were to be supplied by the principal, that is, the defendant.
[214] There is an added complication as the documents under the heading “INTERIOR
DESIGN – JOSEPH PANG DESIGN CONSULTANTS” also includes the four
documents which do not carry the reference commencing with “ID” but are all
numbered “113109”. These include a document described as “Guest Room Data
Sheet Rev. A”. The Guest Room Data Sheet lists various fixtures and fittings and
then classifies the various fixtures and fittings by the use of a dot point into Category
1, Category 2 or Category 3.72 These categories then are designated whether they are
to be supplied and installed by the plaintiff or defendant, or supplied by one and
installed by the other.
[215] The Guest Room Data Sheet contains a notation that it is “BASED ON JPDC
INTERIOR DESIGN DRAWINGS”.
[216] Immediately under the documents listed in Annexure K under the heading
“INTERIOR DESIGN – JOSEPH PANG DESIGN CONSULTANTS” there is
another category headed “SPECIALIST LIGHTING - ELECTROLITE”, and under
the documents listed, there is an annotation as follows:
“Note: Interior Design & Specialist lighting documentation included
are for Holiday Inn Express Park but will be adopted for the Spring
Hill Project.”
[217] The plaintiff points to the differences between the categories identified in
architectural drawing A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3)
and the Guest Room Data Sheet. There is a direct conflict between these two
documents as to who is to supply certain fixtures. For example, the shower door and
bathroom sliding door are to be supplied by the defendant in accordance with A4004
(Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3) but under the Guest Room
Data Sheet, these are to be supplied and installed by the plaintiff.
70 PRO.020.001.2058.
71 PRO.020.001.2058.
72 PRO.020.001.2557.
-- 54 of 210 --
55
[218] Annexure Part O of the Contract is also relevant. Annexure Part O deals with
“clarifications” in respect of the WUC. Relevantly, paragraph (x) states as follows:
“It is noted that the ‘Interior Design – Joseph Pang Design Consultants
documentation’ was provided for information and only forms part of
the Contract where specifically and directly referred to within this
Annexure Part O.”
[219] Clause 8.1 of the General Conditions sets out the approach for construction of the
contractual documents and states as follows:
“8.1 Discrepancies
When construing the Contract Documents the following rules of
construction apply:
(a) in the event of any inconsistency between the Contract
Documents:
(i) the formal instrument of agreement and these general
conditions have precedence; and
(ii) the clarifications have precedence over the preliminary
design;
(b) despite the previous subclause 8.1(a):
(i) where inconsistent levels of quality are required, the
higher level of quality shall apply;
(ii) figured dimensions shall take precedence over scaled
dimensions: and
(iii) drawings made to larger scales shall take precedence over
drawings made to smaller scales;
(c) where the requirements of quality or any aspect of WUC is not
expressly specified or depicted, the quality shall be consistent
with the purpose; and
(d) drawings showing particular parts of WUC shall take
precedence over drawings for more general purposes; and
(e) in all cases, the interpretation to be followed by the Contractor
will be as reasonably determined by the Superintendent.
Where the Contractor considers that there is any ambiguity or
discrepancy between the Contract Documents, it shall promptly advise
the Superintendent in writing, who shall, subject to this subclause 8.1,
give the Contractor a direction as to the interpretation to be followed.
Where the Principal or the Superintendent considers that there is any
ambiguity or discrepancy between the Contract Documents, the
Superintendent shall give the Contractor a direction as to the
interpretation to be followed.
-- 55 of 210 --
56
The Contractor shall have no entitlement as a consequence of a
direction given by the Superintendent under this subclause 8.1 which
is consistent with the rules of construction in this clause 8.1.”
[220] The reference to “clarifications” in this clause is a reference to the clarifications set
out in Annexure Part O.
[221] Given the inconsistency between A4004 (Type 1 & 2 Room Bathroom (Twin &
Queen) Rev. 3) and document ID-01-BD, the plaintiff points to this provision as
resolving the inconsistency. The plaintiff contends that as a result of paragraph (x)
in Part O of the Contract, it has the effect that documents classified as “INTERIOR
DESIGN – JOSEPH PANG DESIGN CONSULTANTS” documentation only form
part of the Contract where it is specifically and directly referred to in Annexure Part
O.
[222] Annexure Part O does contain some examples of this in paragraphs (y) and (z). These
deal with tiles to be used in the guest room bathrooms. As a consequence, paragraphs
(y) and (z) of Annexure Part O govern the tiles to be used and override document
“ID-PFSH-001” described as “Finishes Schedule – Issue H”.73
[223] The plaintiff submits that the interior design ID-01-BD document and the Guest
Room Data Sheet are not referred to in Annexure Part O and therefore they contend
that they do not form part of the Contract and do not form part of the WUC.
[224] The defendant contends that the Guest Room Data Sheet was prepared by Tactical,
not JPDC and while it is listed under the heading “INTERIOR DESIGN – JOSEPH
PANG DESIGN CONSULTANTS” it is not caught by “Interior Design – Joseph
Pang Design Consultants documentation” as used in clause 1(x) Annexure Part O.
[225] The defendant also seeks to refer to documents in relation to the tender process
including a tender addendum identified as RFI-03.74 The defendant seeks to rely on
the plaintiff’s tender submission and the evidence of Mr Cook that the Guest Room
Data Sheet was used for the purposes of the plaintiff preparing its price for the
tender.75
[226] There is no direct evidence as to the author of the Guest Room Data Sheet but it does
have the defendant’s logo and states “[p]repared by Tactical Group”.
[227] In response, the plaintiff contends that the Contract itself needs to be construed and
what happened between the tender submission and the execution of the Contract
cannot be used to define the WUC contrary to direct contractual provisions.
[228] The defendant also points to the notation on A4004 (Type 1 & 2 Room Bathroom
(Twin & Queen) Rev. 3) which states:
“GUEST ROOM DESIGN STILL PENDING CLIENT APPROVAL
AND REFER TO INTERIOR DESIGN FOR SETOUT DETAILS.”
73 PRO.017.001.2122.
74 WIT.001.001.0224 at p 0238 [84]-[90]; PRO.020.001.2555; PRO.020.001.2556.
75 PRO.020.001.1559 at p 0011; T1-69, L7-11.
-- 56 of 210 --
57
[229] This contention appears to be a submission that in effect A4004 (Type 1 & 2 Room
Bathroom (Twin & Queen) Rev. 3) is to be interpreted by reference to the interior
design documentation. Based on this argument, the documents listed under the
heading “INTERIOR DESIGN – JOSEPH PANG DESIGN CONSULTANTS”
would have a role not constrained by clause 1(x) of Annexure Part O.
[230] Conversely, the plaintiff submits that the comment on A4004 (Type 1 & 2 Room
Bathroom (Twin & Queen) Rev. 3) does not assist in resolving this issue. In this
respect, the plaintiff points to several factors that tend to support the conclusion
contrary to that contended for by the defendant, including:
(a) The JPDC interior design documents do not address which party was
responsible for providing particular items;
(b) While it is contended that the Guest Room Data Sheet is not part of the JPDC
documents, Ms Fu of JPDC gave evidence under cross-examination that in
effect the Guest Room Data Sheet would not be used on anything other than a
JPDC interior design drawing;76
(c) The notation on the architectural drawing refers to “setout details” as opposed
to furniture, fixtures and equipment details, category details or specifically who
was to supply the item.
[231] The plaintiff contends that “setout details” given its ordinary meaning would be a
reference to layout and not a reference to the provision of items or in fact, the
contractual obligation to provide particular items.
Consideration
[232] The bathroom design was not completed at the time of the tender and this was carried
over into the final Contract.
[233] Construing the Contract as a whole, A4004 (Type 1 & 2 Room Bathroom (Twin &
Queen) Rev. 3) is the primary document having contractual status that assists in
identifying what was to be provided by the contractor in respect of the guest room
bathrooms.
[234] The JPDC interior design documents and the Guest Room Data Sheet can best be
described as “indicative only” given the operation of clause 8.1 in respect of the
hierarchy of documents for construction purposes and also the specific provision in
clause 1(x) of Annexure Part O. They were subject to the interior design being
finalised as applicable to the Spring Hill Hotel.
[235] A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3) itself makes it clear
that even the “layout” of the bathrooms was subject to final approval. However, that
document has the status of a contractual document.
[236] While I accept that the Guest Room Data Sheet is on its face not a JPDC document,
that of itself does not assist in determining the scope of work in respect of the
bathrooms. Clause 1(x) of Annexure Part O in effect deems the “Interior Design
Joseph Pang Design Consultants documentation” referred to in Annexure Part K as
76 T5-58, L10.
-- 57 of 210 --
58
non-contractual documents if they are not specifically referred to in Annexure Part
O.
[237] The use of the word “documentation” is wider than a reference to the JPDC
documents and would be wide enough to cover documents such as the Guest Room
Data Sheet which categorises the information contained in the JPDC interior design
documents.
[238] While the Guest Room Data Sheet may have indicated obligations and liabilities, it
can only have an operation and relevance in respect of its application specifically to
the JPDC interior design documents which are listed in Annexure Part K. It becomes
circular as it can only have significance and application if those documents are in
effect part of the Contract. If they are for information only, while they may assist in
understanding what the Guestroom Data Sheet is referring to, it does not have any
contractual effect as those documents do not form part of the Contract. This tends to
support the conclusion that the operation of the Guest Room Data Sheet is similarly
constrained by clause 1(x) of Annexure Part O.
[239] In these circumstances I make the following findings:
(a) A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3) is the starting
point for the WUC for the 216 guest room bathrooms.
(b) If there was a change to the design as set out in A4004 (Type 1 & 2 Room
Bathroom (Twin & Queen) Rev. 3) such as to change the scope of work in
accordance with paragraphs 36.1(a), (b), (c), (d) or (e), then that would be a
variation to the WUC.
(c) To the extent that A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev.
3) identifies certain items to be supplied by one party, any change to the
obligation to supply any particular item would be a variation to the WUC.77
(d) Document ID-01-BD “Bathroom Twin Room Issue G” and the Guest Room
Data Sheet did not form part of the Contract and were provided for information
only.
[240] It is now necessary to consider whether the correspondence relied upon by the
plaintiff as a direction is a direction within the provisions of the Contract and whether
there is any corresponding entitlement to costs.
Was there a change in the work to be undertaken within the scope of clauses 36.1(a)
to (e)? Was there a direction within clause 36.1(f) or does it amount to a direction
to perform a variation pursuant to clause 36.1(g)?
[241] Clause 36 sets out the procedure to be followed in respect of variations to the WUC.
The procedure is set out in the third paragraph under clause 36.1 in respect of
77 This would equally apply to work that was removed from the scope and to additional work that was
added.
-- 58 of 210 --
59
subparagraphs (f) and (g) and also relevantly, subparagraph (h). The provision
relevantly states as follows:
“The Principal shall only be liable to the Contractor for the price of a
variation calculated in accordance with subclause 36.4 or for an EOT
for a variation where either:
(f) the direction to perform the variation given by the
Superintendent is in writing, expressly states that the direction
constitutes a direction for a variation and identifies the work
the subject of the direction; or
(g) before performing the variation and in any event within 5
business days of receiving the direction to perform the
variation, the Contractor has given the Superintendent a notice
in writing which identifies:
(i) the date the direction was given:
(ii) whether the direction was given orally or in writing;
(iii) the substance of the direction and, if it was in writing, a
copy of the direction must be attached;
(iv) the approximate cost of the variation including a detailed
breakdown calculated in accordance with subclause 36.4;
(v) whether a claim for an EOT will be made as a
consequence of the variation and if so, an estimate of the
period; and
(vi) where the variation relates to the design documents or the
Principal's project requirements, by identifying the
relevant requirement and the change to that requirement.
(h) Except where the Contractor is entitled to make a claim under
this subclause 36.1, the Contractor shall have no entitlement as
a consequence of complying with a direction for a variation.”
[242] Clause 20 of the Contract relevantly states as follows:
“20 Superintendent
…
Except where the Contract otherwise provides, the Superintendent
may give a direction orally but shall as soon as practicable confirm it
in writing. If the Contractor in writing requests the Superintendent to
confirm an oral direction, the Contractor shall not be bound to
comply with the direction until the Superintendent does so.
If the Contractor considers that any direction given by the
Superintendent is given in error or, although not stated to involve a
variation, in fact involves a variation, the Contractor must, before
complying with the direction (but in any event, not later than 5
business days after the direction) notify the Superintendent, in
writing, of this.
-- 59 of 210 --
60
If the Contractor does not give the notice to the Superintendent
within the time specified, the Contractor shall have no entitlement in
respect of the direction and any claims will be absolutely barred.”
[243] It is then necessary to look at the four documents relied upon by the plaintiff as
constituting the direction. The first document relied upon is an email dated 5 May
2016 from Ms Fu of JPDC to Mr Cook of the plaintiff. The Aconex mail attached 45
amended “for construction” design documents.78 The Aconex mail was copied to
representatives of the defendant and also the Superintendent, Tactical.
[244] A number of the attached drawings are relevant to the bathroom design. The plaintiff
identifies six specific documents: ID-01-BD, ID-DT-02, ID-HSH-003, ID-JD-05.3,
ID-PFSH-001 and ID-SSH-002.79
[245] The actual design for the guest room bathrooms is set out in documents ID-01-BD
(this is the “for construction” version) and ID-DT-02. The other documents are
schedules which set out particular items to be installed in other rooms, including guest
room bathrooms. These include more detail including hardware and finishes.
[246] The plaintiff has undertaken a comparison between document ID-01-BD80 and A4004
(Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3). The main differences
identified by the plaintiff between these two drawings (and is dealt with in the witness
statement of Mr Cook) is that the guest room shower screen door is also the bathroom
door, which includes a towel/handrail on the outside of the door. The additional work
that was required by this change includes:
(a) an extension to the bathroom wall (including waterproofing, tiling, painting
and skirting);
(b) stainless steel capping on both sides of the bathroom door jamb;81 and
(c) a plasterboard wall underneath the vanity, with the vanity to be installed by
others.82
[247] Further, drawing ID-JD-05.3 – Doors83 shows the guest room shower screen door as
item GL-01 and the shower door hinges as item H-01. The document marked “ID-
PFSH-001 – Finishes Schedule” then identifies item GL-0184 and item H-01 is
similarly identified in document “ID-HSH-003 – Hardware Schedule”.85 These
documents show that item GL-01 is to be provided by the contractor. This is a change
to what was shown in A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev 3)
which provided that the shower door was a Category 3 item to be supplied by the
defendant.
78 BUI.001.001.69541.
79 BUI.001.001.58481; BUI.001.001.58506; BUI.001.001.58508; BUI.001.001.58523;
BUI.001.001.58524; BUI.001.001.58525.
80 BUI.001.001.58481.
81 WIT.001.004.001 Witness statement of Thomas Cook dated 31 August 2018 at p 0075 [439].
82 BUI.001.001.58481.
83 BUI.001.001.58523.
84 BUI.001.001.58524.
85 BUI.001.001.58508.
-- 60 of 210 --
61
[248] The position in relation to the hinges is less clear. The “for construction” design
documents do not expressly state who is to supply the hinges. The plaintiff supplied
the hinges. The plaintiff claims that this was a variation because A4004 (Type 1 & 2
Room Bathroom (Twin & Queen) Rev. 3) provided that the shower door was a
Category 3 item to be supplied by the defendant. It is contended that this would
include the hinges for the shower screen door. As a result, the plaintiff claims that
the supply of the shower door and the hinges is a variation.
[249] Additionally, the revised configuration of the shower screen door also required
stainless steel capping to be installed to both sides of the bathroom door jamb.
Document “ID-PFSH-001 – Finishes Schedule”86 identifies this capping as item MT-
01. The plaintiff supplied the capping. The plaintiff claims this is a variation as
A4004 (Type 1 & 2 Room Bathroom (Twin & Queen) Rev. 3) did not require this
capping.87
[250] This work was undertaken in relation to 216 of the guest room bathrooms. Overall,
the plaintiff claims in respect of the following work:
(a) procurement of the shower screen glass;
(b) engaging contractors to install the shower screens;
(c) procurement and installation of required material such as shower rails, hinges,
stainless steel door jambs and channels;
(d) engaging contractors to install the nib walls; and
(e) additional painting, tiling and waterproofing.88
[251] The differences between what was required by A4004 (Type 1 & 2 Room Bathroom
(Twin & Queen) Rev. 3) and the “for construction” drawings would be a variation
within clauses 36.1(a) to (e).
[252] It is then necessary to consider whether the plaintiff is entitled to an assessment of its
costs pursuant to clause 36.4 of the Contract. The plaintiff does not seek to rely on
clause 36.1(g) of the Contract. The plaintiff does not contend that it complied with
clause 36.1(g) of the Contract. Rather, the plaintiff’s primary position is an
entitlement to an assessment of costs on the basis of clause 36.1(f) of the Contract.
[253] Subparagraphs (f) and (g) of clause 36.1 are alternatives. If either clause 36.1(f) or
clause 36.1(g) is complied with then the principal’s liability for the price of a variation
is enlivened.
[254] However, the circumstances relied upon by the plaintiff do not naturally sit within the
language of clause 36.1(f). The plaintiff submits that the documents “taken together
or individually, were a direction to undertake a variation within the meaning of clause
1 and clause 36 of the Contract”.89
86 BUI.001.001.58524.
87 See also WIT.001.004.0001 Witness statement of Thomas Cook dated 31 August 2018 at p 0076 [439].
88 See WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at p 0082 [470].
89 Plaintiff’s written closing submissions at [547].
-- 61 of 210 --
62
[255] The plaintiff points to the broad definition of “direction” in clause 1 of the Contract,
where direction is defined to mean:
“includes agreement, approval, assessment, authorisation, certificate,
decision, demand, determination, explanation, instruction, notice,
order, permission, rejection, request or requirement.”
[256] The plaintiff also refers to emails on 11 and 12 May 2016 in respect of the status of
the “for construction” documents. These emails are between Mr Carlin of the plaintiff
and Mr McBirnie of the defendant. The first email states:90
“Jim,
Are you in a position to fully endorse all JPDC documentation ‘for
construction’?”
[257] The 12 May 2016 response from Mr McBirnie states as follows:91
“With the exception of the recent changes to the great room and public
amenities, which are still being priced I believe all other drawings
issued should be ok. I would however need to defer to Amie pending
list of outstanding items to be certain …”
[258] Mr Carlin, in a further response to Mr McBirnie, states as follows:
“Can you please confirm if documents that have been issued are ‘for
construction’ or are still on hold?”92
[259] Mr McBirnie of the defendant responded to Mr Carlin of the plaintiff as follows:93
“Is there genuine confusion or are you trying to make a point that
drawings to be priced shouldn’t be considered for construction?
Guestroom, signage and corridor drawings have been issued for
construction and are not on hold …”
[260] These emails were copied to Mr Collison of the Superintendent.
[261] The plaintiff contends that read together this amounted to a direction for it to proceed
with the works described in the “for construction” drawings and that this amounted
to a direction within the meaning of clause 1.
[262] Even if it is accepted that given the broad definition of “direction” and reading these
documents together this was a direction to perform a variation to the extent that the
drawings changed the scope of WUC, the “direction” could not be said to be “given
by the Superintendent”, did not expressly state that the “direction” constituted a
direction for a variation and did not identify the work the subject of the direction as
required by clause 36.1(f).
90 BUI.001.001.69951.
91 BUI.001.001.69951.
92 BUI.001.001.69952.
93 BUI.001.001.69952.
-- 62 of 210 --
63
[263] In these circumstances, the defendant contends that clause 36.1(f) has not been made
out and there is no entitlement to the additional costs of the variation.
[264] Clause 36.1(g) of the Contract provides a mechanism that could have been followed
by the plaintiff in the current circumstances in order for it to protect its interests and
enliven its ability to claim and be paid for the costs of the variation. The defendant
submits that clause 36.1(g) which could have applied in these circumstances was not
complied with and accordingly no liability for the costs of a variation arises.
[265] The plaintiff makes a number of arguments as to how or why the provisions in clause
36.1(f) have been satisfied. It is submitted that the Superintendent was copied into
all of the emails and while the emails did not expressly identify the work the subject
of the direction, that work was apparent to any person with knowledge of the relevant
drawings. It is in these circumstances that the plaintiff urges a construction of the
Contract adopting “business commonsense”.94
[266] However, I do not consider that this position is persuasive. Firstly, the plaintiff and
the defendant are sophisticated and experienced parties and agreed to be bound by the
terms of the Contract. The Contract is a standard form contract and the terms of the
Contract are not highly unusual or unique in respect of these clauses. The parties
agreed to be bound by clause 36.1 and the consequences set out therein.
[267] Mr Cook on behalf of the plaintiff understood the importance of complying with
clause 36.1 and evidence was given consistent with that.95
[268] Clause 36.1(f) is quite clear in its terms. The construction contended for by the
plaintiff ignores, to a significant extent, the language of clause 36.1(f).
[269] To the extent that there was any confusion which arose by the provision of the “for
construction” drawings and the correspondence between the plaintiff and the
defendant in relation to that, the Contract provided a mechanism which was directly
applicable to those circumstances. The provision in clause 36.1(g) provides an
express mechanism to determine whether a direction has been given to perform a
variation and to obtain certainty from the Superintendent in respect of that work and
to give rise to an entitlement to the price of that variation.
[270] Further, clause 20 also assists with a mechanism for clarification in circumstances
such as that currently being considered. Pursuant to clause 20, if there is an oral
direction or the contractor considers that a direction has been given by the
Superintendent and that it may have been an error, then the contractor is to provide a
notice no later than five business days after the direction and notify certain matters.
[271] The Contract makes it clear that no entitlement arises in respect of the price of a
variation (to be calculated in accordance with clause 36.4) unless it is within clauses
36.1(f) or (g). The words in the chapeau to (f), (g) and (h) state this expressly.
[272] The procedure in clause 20 is subject to the same qualification.
94 Aura Enterprises Pty Ltd v Frontline Retail Pty Ltd (2006) 202 FLR 435 at [40] per Brereton J.
95 T2-51, L25-40.
-- 63 of 210 --
64
[273] To allow for the construction contended for by the plaintiff would make the words in
the chapeau to clauses 36.1(f), (g) and (h) and clause 20 have no effect. Clearly this
could not be what was intended by the parties to the Contract.
[274] The plaintiff also submits that despite there not being compliance with the precise
language of clause 36.1, if viewed from the perspective of a “reasonable recipient”
with knowledge of the terms of the Contract96 and the surrounding circumstances, it
could be found that the requirements of clause 36.1(f) of the Contract had in effect
been met.
[275] These submissions focus on the failure to express that the direction constitutes a
direction for a variation. However, that only addresses part of the deficiencies in
respect of compliance with clause 36.1(f).
[276] Separate to the alternative argument based on estoppel and waiver (dealt with further
below), in respect of clause 36.1(f) the plaintiff seeks to mount an argument that other
variations arose as a consequence of the receipt of “for construction” drawings which
were subsequently approved as variations by the Superintendent notwithstanding that
there was not compliance with the precise language in clause 36.1 of the Contract. In
this respect reliance is placed on the way in which the Superintendent dealt with VP31
and VP38 which are dated 22 June 2016 and 2 December 2016 respectively.
[277] The defendant submits that this argument has no basis particularly in circumstances
where the plaintiff is seeking to rely on “surrounding circumstances” in support of its
argument when these events occurred after it received the Aconex transmittals in the
circumstances of the current claim.
[278] Further, the defendant contends that how the Superintendent chose to assess one
variation in one circumstance does not necessarily have any bearing on how it would
treat another variation in another circumstance.
[279] Reference was made in the evidence to what is commonly referred to as a “do and
charge variation”. The evidence by Mr Malone of Tactical was that this approach
was fraught with danger if the procedure in clause 36.1 was not followed.97 Mr Cook
also gave evidence that he understood the importance of complying with clause
36.1.98 Given the express terms of the Contract, if the procedure under clause 36.1
was not followed then there was a risk that the costs may not have been recovered.99
[280] Alternatively, the plaintiff seeks to rely on estoppel and waiver. In respect of waiver,
the plaintiff contends that the defendant, through the Superintendent, acted in a
manner inconsistent with its rights pursuant to clause 36.1 of the Contract and
accordingly, waived its entitlement to insist on strict compliance with the terms of
clause 36.1 of the Contract in respect of the Bathroom Design Variation. In this
regard the plaintiff relies upon the evidence of Mr Malone in respect of the way that
VP38 and VP31 were dealt with. Both of those variations could be classified as a “do
96 Aura Enterprises Pty Ltd v Frontline Retail Pty Ltd (2006) 202 FLR 435 at [40] per Brereton J;
Diploma Construction Pty Ltd v Marula Pty Ltd [2009] WASCA 229; FPM Constructions Pty Ltd v
Council of the City of Blue Mountains [2005] NSWCA 340; BMD Major Projects Pty Ltd v Victorian
Urban Development Authority [2009] VSCA 221.
97 T4-87, L25-32.
98 T2-51, L25-40.
99 T4-87, L25-32.
-- 64 of 210 --
65
and charge variation” where the difference between the tender drawings and the
construction drawings was calculated and then claimed even though clause 36.1 had
not been strictly complied with. The Superintendent approved the claims in respect
of those variation proposals.100
[281] While those particular claims for costs may have been approved, it is difficult to see
how they could be regarded as a waiver in respect of compliance in relation to clause
36.1 more generally.
[282] Further, the defendant points out that the “surrounding circumstances” of VP31 and
VP38 (dated 22 June 2016 and 2 December 2016) occurred after the alleged
communications in respect of the Bathroom Design Variation. Accordingly, they
could not be relied upon as “surrounding circumstances” in respect of what is sought
to be relied upon to constitute the directions for the Bathroom Design Variation.
[283] Further, clause 43 of the Contract is also relevant to the consideration of the issue of
waiver. Clause 43 states:
“Except as provided at law or in equity or elsewhere in the Contract,
none of the terms of the Contract shall be varied, waived, discharged
or released, except with the prior written consent of the parties.
A party’s failure or delay to exercise a power or right does not operate
as a waiver of that power or right.”
[284] The defendant points to and relies upon the terms of clause 43.
[285] Even if it is accepted that on occasion the Superintendent assessed a variation despite
non-compliance with clause 36.1(f), clause 43 expressly prevents relying upon that
occasion as an election in respect of all variations or specifically the Bathroom Design
Variation.
[286] The plaintiff also seeks to rely on estoppel as an alternative basis for its entitlement
to the costs associated with the alleged Bathroom Design Variation. The plaintiff
expressly relies on the decision of Update Constructions Pty Ltd v Rozelle Child Care
Centre Ltd.101
[287] Priestly JA, with whom Kirby P and Samuels JA agreed, concluded on the
circumstances of that case as follows:
“… I think that what Rozelle’s agent told Mr Dean can fairly be
regarded as a promise to pay for the work irrespective of the formal
requirements of the contract, which encouraged Update to go ahead
with the work without concerning itself with formal contractual
requirements, the appropriate remedy for which would be to prevent
Rozelle from relying on the lack of formal compliance … an estoppel
arose in the present case when the conduct of Rozelle’s agent led
Update (i) to suppose that the requirement of writing under cl 6(b)
would not be enforced, and (ii) to act to its detriment by both not
giving the written notice when it could still have done so, and doing
100 T4-83, L4-17.
101 (1990) 20 NSWLR 251.
-- 65 of 210 --
66
the work; the estoppel being that Rozelle could not after those events
rely on the writing requirement in cl 6(b).”102
[288] The plaintiff points to evidence of Mr Cook as establishing that the plaintiff was
induced by the defendant to assume that it was directed to undertake the works set
out in the “for construction” JPDC drawings.
[289] However, the relevant paragraphs of the statement of Mr Cook do not identify the
basis upon which it is alleged that the plaintiff would be entitled to additional payment
for a variation for undertaking the bathroom works. While it is stated that the plaintiff
relied upon the “representation or assumption” in undertaking the additional works,
it is not clear the precise representation alleged.
[290] While the correspondence confirmed that the “for construction” drawings were “not
on hold” it is difficult to see how that could be regarded as a promise to pay for the
work without the procedures in the Contract being followed. To the extent there was
any ambiguity as to whether that gave rise to an entitlement to be compensated, the
Contract pursuant to clause 36.1(g) and clause 20 provided a mechanism to obtain
that clarity and to crystalise an entitlement to recover the costs. Without following
that procedure there was a risk that there was no entitlement. Further, the plaintiff
has not clearly identified facts establishing a representation promising payment,
which would be necessary to make out an estoppel.
[291] It is precisely this difficulty which the defendant identifies in its submissions as to
why an estoppel is not made out. The defendant contends that the plaintiff does not
plead with any particularity what the representation was. There is no plea that the
defendant represented that the plaintiff would be paid despite the fact that the relevant
Aconex transmittals did not comply with clause 36.1(f) or that the plaintiff did not
need to issue a notice under clause 36.1(g).
[292] Further, in relation to the plaintiff’s reliance upon the case of Update Constructions
Pty Ltd v Rozelle Child Care Centre Ltd, the defendant submits that in that case there
was a clear representation made that should the builder proceed with the additional
work then it would be paid for that additional work. In the circumstances of the
current case, there is no similar representation here. The references in the Aconex
transmittals to “for construction” drawings and a subsequent statement that the
drawings were not on hold, is not a representation in relation to a promise to pay for
undertaking any additional work that was identified by way of those “for
construction” drawings.
[293] On the evidence of Mr Cook and Mr Carlin, it is apparent that the requirements of
clause 36.1 were recognised as important and they needed to be complied with.103 Mr
Carlin, the recipient of the Aconex transmittals, was not called to give evidence. In
these circumstances, the plaintiff has not made out that it was induced to undertake
the work in the “for construction” drawings on the basis of a representation that it
should proceed with the extra work and that the extra work would be paid for.
[294] Clause 20 of the Contract also reinforces this position.
102 See pp 276-7.
103 T2-51, L33-47.
-- 66 of 210 --
67
[295] In the circumstances, whilst it is open for the Aconex transmittals to be characterised
as a direction in accordance with the definition in clause 1 of the Contract and that
the contents of the “for construction” drawings in relation to the guest room
bathrooms changed the scope of the work under the Contract, the plaintiff did not
comply with clause 36.1(f) of the Contract. Accordingly, the defendant is not liable
for the price of the variation.
[296] Further, the plaintiff has not established that there has been an estoppel or waiver.
[297] The answer to questions 2(a), (b) and (d) of the list of issues is “no”.
[298] In respect of question 2(c) of the list of issues in dispute, given my findings in respect
of the Guest Room Data Sheet there is no reduction in the scope of the works. The
defendant did not seek the omitted items by way of counterclaim but merely that it
reduced the scope of any claim by the plaintiff by the application of a credit.
[299] However, if I am wrong about the finding in respect of the Guest Room Data Sheet,
then the amounts identified by the defendant would need to be credited in respect of
the items that were originally to be provided by the plaintiff but were no longer
required by the “for construction” drawings.
[300] Further, if I am wrong about the plaintiff’s ability to claim for the price of the
variation in respect of the guest room bathrooms and the plaintiff is entitled to
payment for the additional bathroom work, then the cost of that work should be priced
in accordance with the valuation of Mr Watson, which is based on the plaintiff’s
assessment of the actual work undertaken.
THE SCHEDULE 3 AND 4 VARIATIONS
[301] The issue in respect of the Schedule 3 and 4 variations is dealt with in question 3 of
the list of issues in dispute:
“In respect of the alleged Schedule 3 (Item 1 only) and Schedule 4
(excluding item 7) Variations, whether:
(a) the plaintiff was directed to undertake variations to the works,
as alleged, within the meaning of clause 1 and clause 36 of the
Contract [SOC [14], [15]; Def [14], [15]];104
(b) the works described in Schedule 3 and Schedule 4 constituted
a variation under the Contract [SOC [15]; Def [15(b)]]; and
(c) the plaintiff is entitled to payment for the alleged variations
[SOC [17], [Sch 3], [Sch 4]; Def [17], [Annex 2]].”
[302] In respect of quantum, question 15 of the list of issues in dispute is also relevant:
“In respect of the Schedule 3 and 4 Variations, the extent to which, if
at all, the plaintiff is entitled to the sums identified in column D of
Schedule 3 and column C of Schedule 4 to the amended statement of
claim [SOC [17]; Def [17]].”
104 Save for Item 1 of Schedule 4.
-- 67 of 210 --
68
[303] The parties have agreed the following as set out in the list of matters not in issue:
“3. In respect of the alleged Schedule 3 Variations:
(a) that the plaintiff is entitled to the amount claimed for
Items 2, 3 and 4; and
(b) in respect of Item 1, that the plaintiff undertook the work
described in Schedule 3 of the amended statement of
claim [SOC [15]; Def [15]].
4. In respect of the alleged Schedule 4 Variations:
(a) that the plaintiff is entitled to the amount claimed for Item
7;
(b) in respect of Item 1, that the plaintiff was directed to
undertake the work described in Schedule 4 of the
amended statement of claim and is entitled [to] payment
of at least $9,130 for Item 1; and otherwise
(c) that the plaintiff undertook the work described in
Schedule 4 of the amended statement of claim [SOC [15];
Def [15]].”
[304] Each of these claims are dealt with below.
Schedule 3 - VP38 – “Ceilings and partition alterations in the Great Room”
[305] Liability for this variation is not in dispute and the quantum of $6,308.51 (plus GST)
is agreed.
[306] The amount is based on the assessment of quantum in the joint expert report of
$60,626.37 (plus GST) less the existing Contract adjustment of $54,317.86 (plus
GST).
[307] The plaintiff is entitled to payment of $6,308.51 (plus GST).
Schedule 3 - VP53 – “Back of House Corridor – second path of egress”
[308] Liability is not in dispute in respect of this variation.
[309] The defendant identifies that the quantum is agreed in the amount of $1,188.00.
However, the plaintiff disputes this position.
[310] The defendant does not make any substantive submissions in respect of this claim.
[311] The plaintiff addresses this claim in its submissions and seeks to explain the
difference in positions.
[312] The defendant’s figure appears to assume that the amount claimed is the difference
between Contract Adjustment (CA) 48105 and Variation Proposal (VP) 53106 and that
105 PRO.001.003.0057.
106 PRO.001.003.0054.
-- 68 of 210 --
69
the plaintiff has been paid the amount in respect of CA48. The plaintiff submits it
has not been paid that amount.
[313] The cost of VP53 is $5,550 (plus GST) which was claimed in Progress Claim No.
24.107
[314] The plaintiff submits that the Superintendent did not certify any cost as payable in
respect of VP53 by Progress Certificate No. 24,108 despite having issued CA48 and
despite VP53 being an approved variation.109
[315] In these circumstances, the plaintiff is entitled to the full amount of $5,555.00 (plus
GST).
Schedule 3 – VP59 – “Admin and luggage change layout and joinery”
[316] Liability is not in dispute and quantum is agreed in the amount of $3,168.00 (plus
GST).
[317] The plaintiff is entitled to the amount of $3,168.00 (plus GST).
Schedule 3 – VP78 – “BWIC for boom gate”
[318] Liability is not in dispute and quantum is agreed in the amount of $1,188.00 (plus
GST).
[319] The plaintiff is entitled to the amount of $1,188.00 (plus GST).
Schedule 4 – VP58 – “BOH (back of house) ceiling”
[320] Liability is not in dispute and the defendant does not dispute that the amount of
$9,130.00 is payable to the plaintiff.
[321] The difference in dispute is $518.56. This is the difference between the assessment
of Mr Watson for the plaintiff in the amount of $10,885.15 and the assessment of Mr
Hardiman for the defendant in the amount of $10,366.59.
[322] The difference is attributable to the 7.5 per cent mark-up for preliminaries and the
rates used.
[323] The defendant submits that there is no proper basis for the inclusion of the 7.5 per
cent for preliminaries. The plaintiff maintains its claim for preliminaries.
[324] The issue of the entitlement to preliminaries is discussed in relation to the pricing of
the Schedule 6 variations below. I adopt the same conclusion here and accordingly,
the 7.5 per cent for preliminaries is not recoverable by the plaintiff.
107 BUI.001.001.25669.
108 BUI.001.003.86921.
109 VP53 does not appear on the list of approved variations in the progress certificate.
-- 69 of 210 --
70
[325] In respect of rates:
(a) Mr Watson used rates from the plaintiff’s claim and compared the rates to
Rawlinson’s rates to check for reasonableness of the rates. He also used rates
from VP59 which had been agreed to by the Superintendent.
(b) Mr Hardiman used Rawlinson’s rates, as representing market rates at the
relevant time.
[326] The plaintiff submits that the difference here is so small that it cannot be said that Mr
Watson’s rates are unreasonable. Further the plaintiff contends that Mr Watson’s
rates are more likely to reflect actual costs rather than a theoretical assessment.
[327] The defendant submits that Mr Hardiman’s approach is based on objective market
evidence and provides a sound basis for the Court to assess a fair and reasonable price
for the variation work.
[328] In the circumstances, I find that the rates used by Mr Watson are reasonable. The
rates reflect actual costs and the difference is minor, which also tends to support these
rates being reasonable.
[329] Accordingly, the plaintiff is entitled to the amount of $10,125.72 (plus GST),
adopting Mr Watsons’ approach but the 7.5 per cent for preliminaries is not allowed.
Schedule 4 – VP60 – “Bathroom light switch – off master switch”
[330] Liability and quantum are in issue. The difference between the two quantum experts
is $3,203.89.
[331] The plaintiff claims there was a change in the scope of work due to a direction
pursuant to either clauses 36.1(f) or 36.1(g) of the Contract, or alternatively that the
plaintiff complied with clause 36.2 of the Contract. The plaintiff claims the cost of
the variation pursuant to clause 36.4.
[332] Clauses 36.1(f) and (g) of the Contract have been discussed in relation to the
Bathroom Design Variation above. Clause 36.2 of the Contract states as follows:
“36.2 Proposed variations
The Superintendent may give the Contractor written notice
requesting the Contractor to submit a variation proposal for a
proposed variation.
The Contractor shall provide the following information with the
variation proposal in response to a notice given by the Superintendent
pursuant to this subclause 36.2:
(a) a detailed scope of the proposed variation, including any
drawings or technical details;
(b) a detailed breakdown of the price for which the Contractor
would carry out the proposed variation, including any delay or
disruption costs which may be incurred by the Contractor as a
consequence of the proposed variation;
-- 70 of 210 --
71
(c) the effect, if any, of the proposed variation on the date for
practical completion; and
(d) the expiry period for acceptance of the variation proposal
which shall be not less than 10 business days from the date of
receipt by the Superintendent of variation proposal.
Upon receipt of a variation proposal provided in response to a notice
given by the Superintendent pursuant to this subclause 36.2, the
Superintendent may in the sole discretion of the Superintendent do
any one of the following:
(e) direct the Contractor to provide further information;
(f) accept the variation proposal and give the Contractor a
direction to carry out the variation on the terms contained in
that proposal, in which case a valuation under subclause 36.4
shall not be made and the addition or deduction to the contract
sum shall be the amount contained in the variation proposal;
(g) negotiate different terms with the Contractor upon which the
proposed variation shall be carried out;
(h) give the Contractor a direction to carry out the proposed
variation on the terms contained in the Contract but with a
valuation to be made under subclause 36.4; or
(i) reject the variation proposal, in which case the Principal may
retain another person to carry out the proposed variation the
subject of a notice given by the Superintendent pursuant to this
subclause 36.2.”
[333] Annexure Part K of the Contract includes documents listed under the heading
“SPECIALIST LIGHTING – ELECTROLITE”. A number of documents are listed
including documents which show the layout of a single circuit in each room,
controlled by a master switch.110 Consistent with the construction of the Contract
earlier in these reasons, these documents are contractual documents and identify what
was required to be built by the plaintiff pursuant to the Contract.
[334] The plaintiff also points to evidence contained in emails in July 2016 which confirm
the interpretation of the layout diagrams and also that a variation was requested.
These emails are as follows:
(a) On 7 July 2016, Mr Collison of the Superintendent sent an email to Mr
Meredyth of the plaintiff, copying in others, which stated:
“Grant
I thought the instructions from yesterdays [sic] PCG discussion
on this issue were unambiguous however for clarity purposes,
[the] following is my understanding of the outcomes:
…
110 BUI.001.001.61986; BUI.001.001.61987; BUI.001.001.61988; BUI.001.001.61989. See further
WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at [510].
-- 71 of 210 --
72
Built to issue an estimate of costs for the installation of a light
switch to service the bathroom to Pro-Invest/Tactical to review
and confirm instructions …”
(b) On 11 July 2016, Mr Collison sent an email to Mr Meredyth (copying others)
which stated:
“Grant,
Have you received any cost advice on the proposed bathroom
light switch to enable Pro-Invest to review and confirm
instructions?”
(c) On 19 July 2016, Mr Carlin of the plaintiff sent an email to Mr Malone
(copying others) which stated:
“Hello Sean,
Have had a day of reconciling all things Electrical and
anticipate some variations as requested to flow tomorrow … I
know you are keen to have these …
2. Bathroom light off master switch & other circuitry to
mirrors etc etc
A further request for costs for the installation of a light switch
to service the bathroom ie take the bathroom light off the
master switch. Cost yet to be defined
Also combined with this additional circuitry to mirrors/mirror
demisters etc …”111
(d) On 20 July 2016, the plaintiff submitted VP60 to the Superintendent.112
[335] The plaintiff identifies the following characteristics of VP60:113
(a) was headed “Variation Proposal No. 60”;
(b) identified the request for the variation proposal as being “JPDC For
Construction Documentation as at 19/07/16” and also “Tactical-GCOR-
304”;114
(c) included a description of the proposed variation – “[r]emove bathroom light off
master switch … given occupant complaints experienced in Macquarie park
project”;
(d) included the approximate cost of the variation, including a detailed breakdown
of the cost; and
(e) noted that no extension of time would be claimed as a consequence of the
variation.
111 BUI.001.001.64716.
112 BUI.001.001.68530.
113 BUI.001.001.56060.
114 BUI.001.001.71493.
-- 72 of 210 --
73
[336] VP60 further priced the variation to remove the bathroom light off the master switch
at $9,167.06 (plus GST).115
[337] The plaintiff also relies on correspondence that was provided after VP60 was
submitted.
[338] On 22 July 2016, by Aconex mail sent by Mr Malone and Mr Carlin, the plaintiff was
provided with updated “for construction” drawings from Electro Light.116 Further,
by these mails the plaintiff submits it was instructed to proceed in accordance with
the drawings.
[339] In particular, the plaintiff relies on the following statements in the correspondence:
(a) On 22 July 2016, at 1.15pm from Mr Malone to Mr Carlin which states:
“Chris
We will assess the variation.
The attached updated AFC drawings from Electro Light
capture our requested changes and directions regarding
switching to respective rooms for the Entry Panel, Bedhead
Master Panel, Bathroom Panel. Please proceed in accordance
with these as final AFC documents.”117
(b) On 22 July 2016, at 1.59pm from Mr Malone to Mr Carlin which states:
“Chris
Related to previous transmittal of Electro Light drawings,
please proceed with these works in accordance with the
attached Electro Light AFCs …
We will assess value and revert.”118
[340] The attached drawings required the plaintiff to install an additional electrical circuit
for the bathroom light switch, which required work in addition to the work in the
earlier layout drawings as the circuit could not be looped into the same power feed.119
[341] Mr Cook was cross-examined in relation to the claimed additional work. The position
in relation to requiring an additional circuit for the bathroom light switch was not
challenged on that evidence.
[342] It is apparent from the comparison of the two electrical layout drawings that there
was a change in the scope of work and in the circumstances, I am satisfied that the
plaintiff was required to carry out additional work. This would be a variation within
the meaning in the Contract.
[343] The next issue to consider is whether it constitutes a direction pursuant to clauses
36.1(f) or 36.1(g) of the Contract. The defendant submits that there was no direction
115 See WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at [512].
116 See BUI.001.001.71520; BUI.001.001.71522; BUI.001.001.61912; BUI.001.001.61913.
117 BUI.001.001.71520.
118 BUI.001.001.71522.
119 See WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at [515].
-- 73 of 210 --
74
to do the additional work and there has been non-compliance with clause 36.1(g) of
the Contract.
[344] The defendant does not consider or address in its submissions the application of
clause 36.2 of the Contract.
[345] Clause 36.2 clearly sets out a procedure in circumstances where the Superintendent
requests that the contractor submit a variation proposal. Here the request was made
and VP60 was submitted. Further, VP60 provided the necessary information required
for compliance with clause 36.2.
[346] Further, on the correspondence, the Superintendent indicated that the plaintiff was to
proceed with the works and that the Superintendent “will assess value and revert”. In
these circumstances, clause 36.2(h) applies, that is that the Superintendent indicated
that the contractor was given a variation to carry out the proposed variation on the
terms contained in the Contract but with a valuation to be made under clause 36.4.
[347] In these circumstances, the defendant is liable to the plaintiff for the cost of the
variation calculated in accordance with clause 36.4 of the Contract.
[348] The defendant raises an additional issue in relation to there being “reduced scope”
because the plaintiff was no longer required to install a two-gang switch in the
bathrooms and a D3 bathroom nightlight under the vanity in the bathroom.120
[349] In response to this the plaintiff says that while it was no longer required to install a
two-gang switch in the bathrooms, it was required to install a single-gang switch in
the bathrooms. Accordingly, the cost in relation to this would be similar.
[350] In relation to the alleged removal of the D3 bathroom nightlight, it appears that based
on a comparison of the drawings the nightlight has been removed. The plaintiff
however points to the fact that the defendant offers no expert quantum evidence of
the “reduced scope”. While this was explored with Mr Cook during cross-
examination, there is no evidence of any precision that would assist in calculating the
amount to be offset against the VP60 quantification. The plaintiff contends that in
these circumstances it is not possible for the Court to arrive at a reasonable estimate
for any offset against the amount claimed in VP60. Further, no cost of the alleged
negative variation was pleaded by the defendant.
[351] The defendant claims a negative variation in the amount of $11,826.78 on the
assumption that the D3 nightlight was removed in 216 rooms. The amount claimed
by way of a negative variation exceeds the amount claimed by the plaintiff on either
of the expert assessments. The defendant has not sought to claim the excess by way
of counterclaim but rather relies on the negative variation to reduce the variation to a
nil amount.
[352] As a matter of logic, there is some attraction to the reduction in the scope of work
being setoff against the additional work identified in VP60. The difficulty is that the
scope of the reduction in the work has not been undertaken by any of the experts and
the evidence was sought to be obtained by Mr Cook in cross-examination. The
defendant maintains that it has established to a sufficient degree the scope and costs
120 PLE.001.001.0001.
-- 74 of 210 --
75
in respect of the negative variation. However, I am not satisfied that the evidence
establishes to the requisite level of satisfaction the amount of work involved and the
costs of the specific items. Accordingly, I do not calculate the quantum of the
negative variation to in effect set it off against the quantum of VP60.
[353] In relation to the quantum of VP60, Mr Hardiman on behalf of the defendant assesses
VP60 in the amount of $8,357.93. Mr Watson on behalf of the plaintiff assesses the
quantum as $11,561.82. The difference between the experts is $3,203.89. This
difference is as a result of:
(a) The disagreement about the rates used. Mr Watson has used the plaintiff’s rates
and Mr Hardiman has assessed the rates based on Rawlinson’s rates.
(b) A variation fee of 10 per cent has been added to the variation claim. This
amount is separate. Mr Watson has included this amount on the basis that it
has been accepted by the Superintendent in other variations. Mr Hardiman has
used market rates and does not see a basis for providing a further mark-up
beyond the Rawlinson’s rates in the absence of proof the plaintiff was liable
for it. The defendant points to the plaintiff being unable to produce any
evidence that this was the case.
(c) A 15 per cent mark-up for Builder’s Work in Connection (BWIC) with
electrical services.
[354] In relation to the rates, the rates in this circumstance are very close and, in these
circumstances, it cannot be said that the rates used by Mr Watson are unreasonable.
Accordingly, the quantum of VP60 should be calculated on the basis of the rates used
by Mr Watson.
[355] While the assessment of a variation does not bind in respect of the acceptance of
another variation, in these circumstances and given the small amounts concerned, I
consider that Mr Watson’s approach of including a variation fee of 10 per cent
reasonable in these circumstances.
[356] Further, in relation to the 15 per cent mark-up for BWIC with electrical services, I
consider that in the circumstances, the allowance should be allowed, given the nature
of the works comprising VP60 and the particular evidence provided by Mr Watson
as to the approach of including the allowance.
[357] Overall, I find that Mr Watson’s assessment is not unreasonable and is priced in
accordance with clause 36.4.
[358] The issue of the 7.5 per cent for preliminaries is also relevant to this claim. Given the
conclusion I have reached in respect of preliminaries, the amount for preliminaries is
not recoverable by the plaintiff.
[359] Accordingly, the plaintiff is entitled to the amount for VP60 as claimed less the
amount in respect of the 7.5 per cent for preliminaries.
Schedule 4 – VP64 – “Clipsal colour switchplates as per JPDC finishes schedule”
[360] Liability and quantum are in issue in respect of this variation. The difference between
the two quantum experts is $314.82.
-- 75 of 210 --
76
[361] This claim relates to an alleged direction to change electrical cover plates in guest
rooms from Clipsal custom colour switchplates to brushed aluminium switchplates.
Again, this is alleged to be a change from preliminary design documents to the
hardware schedule issued by JPDC.
[362] The issue between the parties is that the defendant denies there was any direction and
further says that the plaintiff was always required to install the brushed aluminium
switchplates.
[363] Firstly, it is necessary to consider whether the installation of the brushed aluminium
switchplates was a variation within the meaning of clause 36.1 of the Contract and
whether there was a direction issued pursuant to clauses 36.1(f) or 36.1(g) or whether
clause 36.2 of the Contract applied. If liability is established then the costs are to be
assessed pursuant to clause 36.4 of the Contract.
[364] Mr Cook was cross-examined in relation to the Clipsal product guide. Mr Cook did
not prepare VP64 and his evidence is of little assistance in considering this variation.
[365] Similar to the approach taken for other variations, it is necessary to consider what was
required to be built pursuant to the Contract documents and then to consider whether
there has been a change to that position which would amount to a variation.
[366] The Electrical Services Specification is listed as a preliminary design document in
Annexure Part K of the Contract.121 Relevantly, clause 10.1 of the Specification
states:
“Accessories in guest rooms and public areas shall be to interior
designer’s approval, currently nominated as Clipsal Slimline SC2000
range with custom colour face plates …”122
[367] Subsequently, on 5 May 2016, Ms Fu of JPDC sent to the plaintiff an email attaching
revised drawings and schedules for the guest rooms. This included a document
described as Hardware Schedule, ID-HSH-003.123
[368] The Hardware Schedule contains a relevant entry in relation to the switchplates, with
a reference to the “SLIMLINE SERIES SC2000 BRUSHED ALUMINIUM
COVER”.
[369] The plaintiff accepts that the “SLIMLINE SERIES SC2000” includes both metal face
plate covers (including aluminium covers) and moulded plastic face plate covers. The
plaintiff points to an extract from a Clipsal catalogue from around the time of the
variation which was emailed from Mr Carlin to Mr Malone which states as follows:
“Switch Covers only – SC2000 series
In addition to the standard range of covers, covers are also available
in a range of decorative metal finishes.
Metal finishes available are: - Brushed Aluminium Cover …”124
121 BUI.001.002.26977.
122 At p 57.
123 See BUI.001.001.69541 and BUI.001.001.58508.
124 See BUI.001.001.56253; BUI.001.001.68678.
-- 76 of 210 --
77
[370] The plaintiff contends that there are differences in the language used between the
Electrical Services Specification and the Hardware Schedule. The reference in the
Electrical Services Specification is to “custom colour face plates”. The plaintiff
submits that this should be distinguished from references to “metal face plates” or
“decorative metal finishes”. In these circumstances, the plaintiff submits that the
reference in the Electrical Services Specification to “custom colour face plates” was
a reference to the “standard range of colours” in the Clipsal Slimline Series SC2000.
[371] Further, the plaintiff also points to the fact that the brushed aluminium face plates
cannot be described as “custom colour” as it comes in only one option. This is in
contrast to the “custom colour face plates” which are coloured plastic face plates
which can come in a variety of colours and can be custom coloured. This argument
was supported by Ms Fu of JPDC in her evidence.125
[372] The plaintiff also refers to a difference in language used when it submits it was
intended to refer to the entire Clipsal SC2000 range. I consider there is merit in the
submission in respect of the inclusion of the words “with custom colour face plates”
after the reference to Clipsal Slimline SC2000 range. If it was the entire Clipsal
SC2000 range which was being referred to, which would include the brushed
aluminium face plates, there would be no need to include those additional words.
[373] However, by including the words “custom colour face plates”, the construction of
clause 10.1 of the Electrical Services Specification is that it is a reference to the
standard range of covers being the coloured and plastic face plates, not the brushed
aluminium face plates. Accordingly, the brushed aluminium face plates were not
required as part of the original WUC.
[374] It is then necessary to consider the correspondence in relation to the provision of the
Hardware Schedule and whether it can be classified as a direction pursuant to clauses
36.1(f) or 36.1(g) of the Contract or alternatively, within clause 36.2 of the Contract.
[375] The plaintiff relies on correspondence which shows that following a series of requests
for proposals from the plaintiff regarding numerous variations., on 12 July 2016, Mr
Carlin emailed the Superintendent stating:
“We are in continued negotiations with RDE on cost.
And in reality those negotiations are multiple fold across a number of
items that I can list:-
…
2. Colour switch plates (JPDC vs alternatives to be proposed).
Circa $21k x 1.1 = $22,100.00 if JPDC requirements are
firm?”126
[376] The plaintiff also refers to a response from the Superintendent later that day
responding to point two as follows:
“Presume you are flagging this as a potential variation.”127
125 T5-60, L44-45-T5-61, L1-7.
126 BUI.001.001.64657.
127 BUI.001.001.71501.
-- 77 of 210 --
78
[377] Further to this correspondence, the plaintiff submitted VP64A to the Superintendent
on 18 August 2016.128
[378] VP64A provided details including the scope of the proposed variation including
drawings or technical details, a breakdown of the price, stated that the variation would
have no effect on the date for practical completion and provided an expiry period in
accordance with clause 36.2 of the Contract.
[379] Further, on 22 August 2016 the Superintendent instructed the plaintiff to proceed with
the works under VP64A.129
[380] On 15 November 2016, the Superintendent assessed the variation at $0 on the basis
that the product was a Contract requirement.
[381] The defendant contends that there was no direction issued under clauses 36.1(f) or
36.1(g) of the Contract and accordingly they are not applicable. The defendant does
not address the operation of clause 36.2 of the Contract.
[382] Clause 36.2 of the Contract has been complied with except for an express written
notice from the Superintendent to the contractor requesting that the contractor submit
a variation proposal. However, in the circumstances of the correspondence, it is
apparent that a number of variations were being requested in respect of issues such as
this which were arising and it was included as part of that wider process. In these
circumstances it is not necessary for me to determine conclusively whether it is
necessary for an express written notice to be provided before clause 36.2 is enlivened.
In the circumstances, I am satisfied that the Superintendent’s request for a proposal
has been complied with in the circumstances of this variation.
[383] This is particularly so given the email dated 22 August 2016 from the Superintendent
to the plaintiff, which stated as follows:
“Please proceed with works under VP 64.
We will review submitted costs against requirements of the Contract
and revert.”130
[384] This can be classified as fitting within clause 36.2(h) being a direction by the
Superintendent to carry out the proposed variation on the terms contained in the
Contract but with a valuation to be made under clause 36.4. Accordingly, the price
of the variation is to be assessed in accordance with clause 36.4 of the Contract.
[385] The quantum experts in their joint report agree that the price of this variation is in the
amount of $4,197.54 (plus GST), but excluding preliminaries.
[386] The plaintiff claims a total amount including preliminaries of $4,512.35 (plus GST).
[387] Given the finding I have made in relation to the preliminaries claimed not being
reasonable, the plaintiff is entitled to the amount of $4,197.54 (plus GST).
128 See WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at [521].
129 BUI.001.001.71551.
130 BUI.001.001.71551.
-- 78 of 210 --
79
Schedule 4 – VP66 – “Desk lamp hard wired”
[388] Liability and quantum are in issue in respect of this variation. The difference between
the two quantum experts is $2,205.53.
[389] The plaintiff claims that there was a variation on the basis that, under the original
Contract requirement, the defendant was to supply desk lamps that could be plugged
into a wall outlet. Instead, desk lamps were provided that did not have a power cord
and were required to be hardwired.
[390] The defendant denies there was a direction pursuant to clause 36.1 of the Contract
and further contends that no additional work was required to be carried out beyond
that required by the Contract. In part, this is based on the JPDC Guest Room Data
Sheet which was considered in relation to the Bathroom Design Variation above.
[391] Given my previous finding in relation to the Guest Room Data Sheet, reference to
hardwiring in that document is not determinative in respect of this claim.
[392] The plaintiff refers to the Luminaire Schedule which is listed in Annexure Part K of
the Contract under the heading “SPECIALIST LIGHTING – ELECTROLITE”.131
[393] The document shows a picture of a wall mounted desk lamp but does not expressly
state whether the lamps to be supplied by the defendant would have a power cord to
be connected to a general power outlet. The plaintiff contends that the image appears
to be a “Tolomeo Table Mini” lamp. Further, reference is made to the evidence of
Mr Cook and the setup instructions for the lamp which indicate that it is supplied with
a power cord that can be plugged into a general purpose outlet.132 The instructions
show a power cord with a plug.
[394] The plaintiff also contends that the photograph of the desk lamp in the Luminaire
Schedule has a cord hanging down from where it is fixed to the wall. The plaintiff
submits that this is likely to be a power cord for the wall plug. However, this is not
conclusive in itself.
[395] The plaintiff also relies on the fact that the defendant does not deny the plaintiff’s
pleading that the defendant was required to supply the plaintiff with “desk lamps for
the guest rooms with a plug that could be connected to the desk GPO”.133 In these
circumstances the plaintiff relies upon this as an admission of the allegation.
[396] Given that the JPDC Guest Room Data Sheet is not a contractual document and
cannot be relied upon in relation to the obligation under the original Contract terms,
and in the circumstances relied upon by the plaintiff, I find that the plaintiff was to be
supplied by the defendant with a desk lamp for the guest rooms with a plug.
Accordingly, as the defendant supplied desk lamps that had to be hardwired, this
amounted to a variation creating additional work for the purposes of clause 36.1. It
is then necessary to consider whether there was a direction pursuant to clauses 36.1(f)
or 36.1(g) or whether clause 36.2 of the Contract operated in respect of this claim.
131 BUI.001.001.61820 at p 145.
132 BUI.001.001.22200 at p 001.
133 See PLE.001.001.0336 Amended Statement of Claim at p 0363 Schedule 4; PLE.001.001.0001 Third
Amended Defence and Counterclaim at p 0084 of Annexure 2 Item 4.
-- 79 of 210 --
80
[397] On 21 July 2016, the plaintiff submitted VP66.134 VP66 sets out a detailed scope of
the proposed variation, provided a detailed breakdown of the price, stated that the
variation would have no effect on the date for practical completion and provided an
expiry period in accordance with the requirements of clause 36.2. The plaintiff relies
on the following correspondence:
(a) On 21 July 2016, the plaintiff submitted VP66 to the Superintendent for
assessment with the subject line of the email being “VP No. 66 Hardwire desk
lamps as per Instructions …”.
(b) On 22 July 2016, the Superintendent responded and said “[w]e will assess the
variation”.
(c) No further correspondence was received until 17 November 2016 (almost four
months after VP66 was submitted) when the Superintendent assessed VP66 at
$0.135
[398] In these circumstances, the plaintiff submits that the Superintendent stating “[w]e will
assess the variation” and not otherwise corresponding until well after the relevant
works were complete, was a basis for the plaintiff to infer that VP66 had at least been
accepted, subject to a valuation to be made under clause 36.4. This is what ultimately
occurred.
[399] In this regard, the plaintiff submits that clause 36.2 does not require the
Superintendent to act pursuant to clauses 36.2(e) to (i) in writing.
[400] Accordingly, the plaintiff submits that there was a proposed variation pursuant to
clause 36.2 of the Contract such that the defendant is liable to the plaintiff for the cost
of the variation calculated in accordance with clause 36.4 of the Contract.
[401] The defendant’s position is focused on the Guest Room Data Sheet which was listed
under the heading “INTERIOR DESIGN – JOSEPH PANG DESIGN
CONSULTANTS” in Annexure Part K of the Contract. It is on this basis that the
defendant contends that the Contract always provided for provision of desk lamps
that were required to be hardwired and accordingly there was no variation. The
submissions do not address clause 36.2 and whether the requirements were complied
with.
[402] Whilst the form of the request from the Superintendent for a variation proposal is not
entirely clear, the provisions of clause 36.2 appear to have been in operation in respect
of this claim. Further, while the application of clause 36.2(h) requires some inference
to be made, taking a commercial approach to the consideration of the facts, it appears
that clause 36.2 of the Contract has been met and accordingly the defendant is liable
to the plaintiff for the cost of the variation calculated in accordance with clause 36.4
of the Contract.
[403] In respect of the proper cost of this variation pursuant to clause 36.4 of the Contract,
the quantum experts in their joint report have assessed the claim as follows:
(a) Mr Watson values the claim at $9,426.13 (plus GST); and
134 BUI.001.001.68532; BUI.001.001.56062.
135 BUI.001.001.71621.
-- 80 of 210 --
81
(b) Mr Hardiman values the claim at $7,220.60 (plus GST).
[404] The differences between the two valuations are again that Mr Hardiman’s approach
has used Rawlinson’s rates, it includes the imposition of a 10 per cent fee (this is in
addition to the 10 per cent mark-up for profit and overheads), the BWIC 15 per cent
mark-up and also the 7.5 per cent for preliminaries.
[405] Given the work identified as being involved, the BWIC allowance would be
reasonable in the circumstances. The other differences are not significant and it
cannot be said that Mr Watson’s valuation is unreasonable. The plaintiff submits that
the second largest component of the difference between the experts relates to the
subcontractors’ (RDE) claim for preliminaries in the amount of $658.79. Mr Watson
allowed that part of the claim as it was claimed by the subcontractor against the
plaintiff. Reference is also made to the fact that the Superintendent has approved it
in other variations. While its approval in respect of other variations is not conclusive,
it may go to the reasonableness of that cost.
[406] In respect of the differences in rates, these are again not substantial differences and
in the circumstances it is not inappropriate to use the rates relied upon by Mr Watson
in relation to this assessment.
[407] Whilst the defendant also appears to object to the preliminaries on the basis of the
general objection, it is not apparent whether this is in addition to the preliminaries
claimed in respect of the subcontractor.
[408] Overall, I adopt Mr Watson’s approach to the assessment of costs. The plaintiff is
entitled to the amount of $9,426.13 (plus GST) in respect of this claim.
Schedule 4 – VP67 – “Supply and installation of power sockets and wiring for LED
lighting”
[409] Liability and quantum are in issue in respect of this variation. The difference between
the two quantum experts is $12,685.59.
[410] This claim relates to additional work for running of additional cabling for each of the
lights in a “figure 8 configuration” to connect the “< 200mm tail to the termination
point in the ceiling”.
[411] The plaintiff submits that the “figure eight” wiring is where the cable is fed from one
source to another and back again in a loop type fashion which is not typical
installation for lighting. In these circumstances, the plaintiff claims a variation for
additional work to be carried out beyond what was required by the Contract.
[412] In response, the defendant denies there was any direction issued pursuant to clause
36.1 of the Contract and additionally, submits that no additional work was required
to be carried out.
[413] In respect of this claim, the defendant again seeks to rely on the Guest Room Data
Sheet that is referred to in Annexure Part K of the Contract. Given my previous
finding in relation to this not being a contractual document, the same reasoning
applies in relation to this claim in respect of that document.
-- 81 of 210 --
82
[414] It is necessary to consider whether the additional work identified was additional to
that required under the Contract and also whether there was a direction issued
pursuant to clauses 36.1(f) or 36.1(g) of the Contract, or alternatively the operation
of clause 36.2 of the Contract. If an entitlement is made out then the cost is to be
assessed pursuant to clause 36.4 of the Contract.
[415] The plaintiff submits that there was no document that outlined the work under the
Contract in respect of the wiring of LED lights. It is uncontroversial that the
defendant was to supply the LED lights required.
[416] The plaintiff contends that the LED lights provided by the defendant had “an
insufficient tail length” and this does not appear to be specifically responded to by
the defendant.136
[417] The plaintiff refers to the following matters as a basis for which it can be found that
the requirement for “figure eight” wiring was a variation to the work under the
Contract:
(a) “Figure eight” wiring of the LED lights was not part of the original work under
the Contract at all. It is atypical work (consistent with the evidence of Mr
Cook) and the plaintiff was not informed of it until 29 June 2016.
(b) On 29 June 2016, an email was sent from Mr Bradshaw of MBI to Mr Meredyth
which attached “noggin & wiring requirements” for the joinery installation. It
also attached two documents which specifically show that “figure eight” wiring
would be required for the LED lighting installation in both the bathroom and
the kitchen.137
[418] The plaintiff relies upon clause 36.1(g) of the Contract in relation to this variation.
The plaintiff contends that clause 36.1(g) does not require a direction from the
Superintendent but rather it requires a direction to perform a variation and then a
process is set out for confirmation of the direction to perform the variation. The
plaintiff contends that the direction to perform the variation was Mr Bradshaw’s
email.
[419] In addition to the email from Mr Bradshaw dated 29 June 2016, the plaintiff also
refers to and relies on the following correspondence.
(a) Aconex mail dated 12 July 2016 to Mr Collison and Mr Malone in which Mr
Carlin was referring to the LED lights in the context of the “joinery interface”
and stated that this “now requires a hardwired plug. Cost yet to be defined.
But I understand you have instructed these works to proceed.”138
(b) Aconex mail dated 12 July 2016 where Mr Malone responded seeking Mr
Carlin to “clarify if this is a variation, reasoning and where this direction
sits”.139 See Aconex mail dated 22 July 2016 from Mr Meredyth to Mr Malone
attaching VP67 dated 21 July 2016.140
136 PLE.001.001.0336 Amended Statement of Claim at p 0364 Schedule 4 Item 5; PLE.001.001.0001
Third Amended Defence and Counterclaim at pp 0084–5 Item 5.
137 BUI.001.008.5574; BUI.001.008.5578; BUI.001.008.5575.
138 BUI.001.001.64657.
139 BUI.001.001.71501.
140 BUI.001.001.64743; BUI.001.001.13923.
-- 82 of 210 --
83
(c) VP67 provides a detailed scope of the proposed variation and states “supply &
installation of power sockets and wiring for LED lighting in kitchen and
bathroom – refer to MBI advice dated 29th June 2016 …” This document also
included RDE’s variation proposal which cross referenced to Mr Bradshaw’s
email and attachments. VP67 also provided a detailed breakdown of the price,
that the variation would have no effect on the date for practical completion and
an expiry period for acceptance in accordance with clause 36.1(g).
(d) Aconex mail dated 17 November 2016 where Mr Malone provided an
assessment based on the JPDC Guest Room Data Sheet and assessed the
variation at $0.141
(e) Also on 17 November 2016, Mr Cook responded to Mr Malone and stated:
“… As per previous discussions, meetings and correspondence
there is now a requirement to run additional figure 8 cabling to
the connection at the wall as the ‘hardwired remote driver’
does not reach the ceiling space and further to this is not
capable of working as described.”142
[420] On the basis that there is no specific provision in the original Contract document in
relation to the work relating to the installation of the LED lights and that the “figure
eight” wiring is atypical, this amounts to a variation of the work under the Contract.
The plaintiff contends that the requirements of clause 36.1(g) have been complied
with and therefore it is entitled to the cost of this variation to be assessed in
accordance with clause 36.4.
[421] There is an additional difficulty to be considered in relation to this claim and the issue
of whether clause 36.1(g) has been complied with. VP67 was not submitted within
five business days of receipt of the direction, but was rather submitted 10 business
days late.
[422] The plaintiff submits that this had no prejudicial impact on the defendant or the
Superintendent and this is evidenced by the fact that the Superintendent did not
respond to VP67 until 17 November 2016 and by that date, the works had not
commenced.143
[423] Further, the plaintiff submits that the Superintendent did not reject VP67 because it
was not submitted within five business days of the relevant direction but rather, it was
rejected on an erroneous assumption that the JPDC Guest Room Data Sheet was a
contractual document and the Contract required the plaintiff to perform the “figure
eight” wiring. It is submitted that the variation was assessed “on its merits” rather
than whether it had complied with the requirements of clause 36.1(g). In this regard,
the plaintiff also points to the evidence of Mr Malone in cross-examination that in
respect of variations “outside” mechanical issues he attempted to take an “equitable
approach” to their assessment.144
141 BUI.001.001.71622.
142 BUI.001.001.65311.
143 BUI.001.001.71622.
144 T4-85, L15-16.
-- 83 of 210 --
84
[424] However, the defendant refers to the evidence of Mr Malone in his witness statement
that to the best of his knowledge, the plaintiff had never submitted a claim in respect
of this item which met the notice requirements in clause 36 of the Contract.145
[425] The defendant contends that there had been non-compliance with clause 36.1(g)
however that is not expanded upon in the submissions, other than a statement that
“Mr Malone was of the belief that the notice requirement of clause 36 had not been
met by Built” and the reference to the witness statement. The reference to the
transcript in the submissions appears to be more as to whether clause 36.1(f) had been
complied with, that is a direction by the Superintendent. It does not appear to be
directed at the circumstance of at least partial compliance with clause 36.1(g).
[426] The plaintiff contends that it has substantially complied with clause 36.1(g) and that
is sufficient to give rise to its entitlement to the cost of the variation.
[427] It appears that the works did not commence prior to 26 April 2017.146 In these
circumstances, this was not what has been colloquially described as a “do and charge”
variation.
[428] The purpose of the time limit in respect of the notice being provided is to give the
Superintendent the opportunity to make an informed decision as to whether the
variation is required to be performed. Given that the work was not undertaken until
a considerable time after the variation proposal was considered and the
Superintendent did not deal with the variation proposal on the basis that it was outside
of the notice period in clause 36.1(g), I am satisfied that there has been substantial
compliance with the requirements of clause 36.1(g) and in the particular
circumstances of this variation that an entitlement to an assessment of the cost
pursuant to clause 36.4 of the Contract arises.
[429] In respect of quantum, the quantum experts assess this claim as follows:
(a) Mr Watson values the claim at $45,775.49 (plus GST);
(b) Mr Hardiman values the claim at $33,089.89 (plus GST).
[430] The difference between the experts is $12,685.59. The reasons for this difference
include:
(a) A variation fee charged by RDE to the plaintiff for performing the works of 10
per cent. Mr Watson allows this amount but Mr Hardiman does not on the
basis that “Rawlinsons rates are market prices”.147
(b) The BWIC claim by RDE (comprising 15 per cent of the cost of the works).
Mr Hardiman disallows this item on the basis of “no substantiation”. The
plaintiff contends that this item is recoverable as RDE charged the item against
the plaintiff for performing the works.
(c) 7.5 per cent for preliminaries.
145 WIT.001.001.0250 at p 0264 [118].
146 BUI.001.001.71743; BUI.001.001.66358.
147 EXP.001.001.2176 at p 2206.
-- 84 of 210 --
85
[431] Consistent with my finding in respect of preliminaries, the 7.5 per cent for
preliminaries is not recoverable.
[432] In respect of this variation there is no real evidence as to what the BWIC mark-up
would relate to. Mr Cook could not speak to whether it was reasonable. In the
circumstances of this particular variation, the BWIC mark-up is not recoverable.
[433] Another issue in respect of the quantum in this matter is whether kitchen wiring has
also been included in the assessment.
[434] The defendant’s position is that the kitchen wiring should be excluded and
accordingly, the maximum amount should be $8,272.47. This amount excludes the
10 per cent mark-up on the subcontractor’s fee, the 7.5 per cent impost for
preliminaries and the 15 per cent BWIC mark-up.
[435] The plaintiff’s position is that VP67 and the attachments to Mr Bradshaw’s email
include “figure eight” wiring as being required for both the bathroom in respect of
the vanity and the kitchen areas in respect of the mini bar. Further, the plaintiff
submits that its Amended Statement of Claim does not limit its claim to the bathroom
areas and the defendant’s Defence refers to wiring for the kitchen mini bar.148
[436] In these circumstances, it appears reasonable that the assessment include both the
bathroom and kitchen areas as the logic of the claim in respect of both those areas
would be the same.
[437] In the circumstances of this variation, the rates used by Mr Watson are reasonable as
they reflect the requirements of the work undertaken. This includes the
subcontractor’s fees.
[438] The plaintiff is entitled to an amount based on Mr Watson’s approach for both the
bathroom and kitchen areas, less the 15 per cent BWIC mark-up and the 7.5 per cent
for preliminaries. This figure does not appear to have been calculated in the
submissions and the parties should calculate the amount for inclusion in the final
orders.
Schedule 4 – VP73 – “Paint stair soffits/colour contrasting nosings”
[439] Liability and quantum are in issue in respect of this variation. The difference between
the two quantum experts is $435.25.
[440] This claim relates to the plaintiff being required to change the finish of the fire stair
soffits from the ground floor to level 12 to a painted finish.
[441] The plaintiff contends that work under the Contract did not require a finish to be
applied to the fire stairs and the requirement for a painted finish was a change
amounting to a variation.
[442] The defendant’s position is that the painting finish was rectification of a workmanship
issue in relation to work that was in scope. At the trial, witnesses were questioned in
relation to the finish and a photograph was tendered. The photograph of the fire stairs
was taken prior to the disputed painting taking place and shows precast stairs with
148 PLE.001.001.0336 at page 0364; PLE.001.001.0001 at p 0086.
-- 85 of 210 --
86
paint over partial areas. It is submitted that this produced an “unsightly finish” which
was not of the appropriate standard in respect of the Spring Hill Hotel.
[443] This claim requires consideration of what was required work under the Contract and
whether applying a painted finish to the stairs was a variation.
[444] The plaintiff contends that the Reid Campbell drawing A9016 Revision 1 in
Annexure Part K of the Contract is the relevant scope drawing. The Schedule did not
specify any finish to the fire stairs above the basement 2 carpark.
[445] The plaintiff relies upon this for its contention that to apply a finish to the stairs was
a variation. The plaintiff also relies on the following correspondence:
(a) Email on 25 May 2016 from Mr McBirnie to Mr Meredyth, copying others,
which states:
“There is an ongoing discussion about what was included in the
original schedule, but regardless of how that falls out, the
untreated finish won’t be acceptable.
Given we are not painting the wall white, what application would you
suggest here?”149
(b) Response on 25 May 2016 from Mr Meredyth to Mr McBirnie as follows:
“As the rest of the stairs walls and floor are a plain concrete
colour, I would suggest a paint finish in ‘Grey’.”150
(c) Email on 22 July 2016 from Mr Roach of Reid Campbell to Mr Cook which
states:
“… regarding finishes to the fire stair, I would like to determine
the scope of the paint and sealer to the fire stair flights.
Jim McBirnie has indicated to me that the risers should be
painted to the fire stairs and that the external side of the stair
stringer and the stair soffits should also be painted …
I am in the process of updating my internal finishes schedule,
could you please confirm your understanding of the above.”151
(d) Aconex mail from Mark Roach of Reid Campbell to the plaintiff on 4 August
2016 attaching a “revised finishes schedule” which stated that the fire stairs
were to be painted.152
[446] The plaintiff contends that the email of Mr McBirnie of 25 May 2016 was a direction
pursuant to clause 36.1(f) of the Contract and that clause 36.1(f) had been complied
with except for the provision that it expressly state that the direction constitutes a
direction for a variation. The plaintiff submits that the email stating that “the
untreated finish won’t be acceptable” could not be interpreted as anything other than
149 BUI.001.003.10399.
150 BUI.001.003.10398.
151 BUI.001.001.70703.
152 BUI.001.001.71012 and BUI.001.001.60903.
-- 86 of 210 --
87
a direction. It was from the Superintendent and identified the work the subject of the
direction.
[447] The defendant’s position is that there was no direction for additional work under the
Contract and also there was non-compliance with clause 36.1(g) of the Contract. The
email from Mr McBirnie is not clearly a direction as it is ambiguous as to whether it
was, in effect, a notice to rectify a defect. Further, on its face it is not a direction
within clause 36.1(f) of the Contract.
[448] The reference in the email to the untreated finish being unacceptable is consistent
with the identification of defective work that did not meet the necessary standard
imposed under the Contract. The defendant refers to and relies upon clause 2.2(a)(i)
of the Contract in respect of the requirement for the contractor to exercise due care
and skill in carrying out and completing the work under the Contract. Further,
reliance is also placed on clause 29.1 which requires the contractor to use proper and
tradesman like workmanship.
[449] The defendant relies upon the photograph and the evidence from the witnesses to
illustrate that the level of workmanship was not satisfactory in respect of the finish
on the fire stairs. The paint finish that was ultimately applied to the fire stairs was a
rectification of what was an unacceptable finish to bring it up to the requisite standard
of good workmanship.
[450] In the circumstances, I find that the additional work that was required to be
undertaken was rectification work to ensure that the requisite standard of
workmanship was achieved in relation to the finish on the fire stairs. There has also
been non-compliance with the requirements of clause 36.1(g). In the circumstances,
no entitlement arises for the cost associated with the additional work undertaken.
[451] If I am wrong and an entitlement to the cost of the variation arises, then the assessment
should be on the basis of Mr Watson’s assessment less the 7.5 per cent for
preliminaries,153 being the amount of $4,620.00 (plus GST).
Schedule 4 – VP76 – “Additional corridor lighting given flip of rooms”
[452] Liability is not in dispute and quantum is agreed in the amount of $4,435.30 (plus
GST).
[453] There appears to be an amount in respect of preliminaries that is also claimed by the
plaintiff.154 It is not apparent whether this is covered by the general claim for 7.5 per
cent preliminaries or is a different claim. It is not addressed in the defendant’s
submissions.
[454] An amount in respect of preliminaries has not been included. If this needs to be
considered separately to the general position, this should be addressed further and
clarified prior to the final orders being made.
153 Given the conclusion I have reached in respect of the entitlement to the 7.5 per cent preliminaries.
154 Plaintiff’s written closing submissions at [771].
-- 87 of 210 --
88
Schedule 4 – VP114 – “Joinery – Damage to walls by separate contractors”
[455] Liability and quantum are in issue in respect of this variation. The difference between
the two quantum experts is $7,432.39.
[456] This claim relates to work undertaken to rectify and make good finished walls, doors,
waterproofing and tiles that were damaged or broken by separate contractors,
specifically the joinery contractor.
[457] The defendant denies there was any direction pursuant to clause 36.1 of the Contract,
however, the defendant does not dispute that the alleged works were a variation to the
work under the Contract and that the plaintiff performed the works comprising the
variation. However, the scope of the actual work required to be undertaken appears
to be in dispute.
[458] Again, the relevant issue is whether there was a direction pursuant to clauses 36.1(f)
or 36.1(g) of the Contract and if an entitlement to the cost of the variation arises then
the proper assessment pursuant to clause 36.4 of the Contract.
[459] The plaintiff points to evidence of Mr Cook of damage caused by the defendant’s
subcontractors when they were installing the guest room joinery and curtains. The
plaintiff also refers to various correspondence as to the alleged damage.
[460] Further, the plaintiff refers to correspondence between 30 January 2017 and 10 May
2017 between the Superintendent and the plaintiff in relation to a number of defect
registers, directing the plaintiff to rectify the defects that were identified in those
registers.155
[461] These registers of defects included defects that were caused by MBI.
[462] On 14 March 2017, the plaintiff submitted VP114 for additional rectification work
that it was directed to undertake, to repair the damage caused by MBI. This included
a claim for the cost of patching and painting walls and tiling rectification work.156
[463] Further, on 22 March 2017 the Superintendent assessed VP114 at $0 on the basis that
the “variation was not directed by the Superintendent pursuant to clause 36 of the
Contract”.157
[464] The defendant contends that this is an ambit global claim without proper evidence
linking particular damage to the installation of joinery, and without linking particular
damage to particular cost, the claim ought to fail for lack of proof.
[465] Further, the defendant points to the evidence of Mr Cook and submits that he has no
personal knowledge and is not able to give direct evidence of the breakdown of the
hours of work in relation to the alleged damage caused by the joiners.
[466] The defendant submits that the hours referred to by Mr Cook had been supplied by a
third party subcontractor who has not given evidence and there is no evidence about
155 See WIT.001.004.0001 Witness Statement of Thomas Cook dated 31 August 2018 at p 0094.
156 BUI.001.001.68665; BUI.001.001.56238.
157 BUI.001.001.71721.
-- 88 of 210 --
89
the basis upon which that third party says any particular damage was attributable to
the joinery installation.
[467] The plaintiff relies on 11 emails which attach defect registers which include defects
caused by MBI. The plaintiff contends that the emails identified between 30 January
2017 and 10 May 2017 amount to a direction within clause 36.1(f) of the Contract on
the basis that they:
(a) were a direction to perform a variation, as the covering emails direct the
plaintiff to rectify the damage caused by MBI, which was included within the
defect registers;
(b) were given in writing by the Superintendent; and
(c) identified the work the subject of the direction.
[468] However, there was no express statement that the direction constitutes a direction for
a variation within clause 36.1(f) of the Contract.
[469] By the wording of the emails the Superintendent intended the plaintiff to undertake
the work that was set out and identified in the schedules. In these particular
circumstances, I consider that the non-inclusion of a statement that the direction
constitutes a direction for a variation does not render a direction in the email invalid
for the purposes of clause 36.1(f). The unambiguous nature of the emails and the
context within which the direction was provided are sufficient for compliance under
clause 36.1(f) such that liability for the cost of the variation arises.
[470] In relation to quantum to be assessed pursuant to clause 36.4 of the Contract, Mr
Watson does not assess the cost of this variation. Mr Hardiman assesses the cost of
the variation at $7,423.39.
[471] The plaintiff is entitled to the sum of $7,423.39 (plus GST).
SCHEDULE 5 PROVISIONAL SUMS
[472] Question four of the list of issues in dispute states as follows:
“4. In respect of Item 3 of the alleged Schedule 5 provisional sums,
whether:
(a) (a) the plaintiff was directed to undertake the alleged
Provisional Sum Works pursuant to clause 3 of the Contract
[SOC [18]; Def [18], [19]]; and
(b) the alleged Provisional Sum Works were provisional sum
works within the meaning of the Contract [SOC [18]; Def
[18], [19]].”
[473] In respect of quantum, question 16 of the list of issues in dispute states as follows:
“16. In respect of the Schedule 5 provisional sums, the extent to
which, if at all, the plaintiff is entitled to the amounts identified
in column D of Schedule 5 to the amended statement of claim
[SOC [22]; Def [22]].”
-- 89 of 210 --
90
[474] Further, the parties have agreed that the following issue is not in dispute as set out in
paragraph five of the list of matters not in issue:
“5. In respect of the alleged Schedule 5 provisional sums:
(a) (a) that the plaintiff is entitled to the amount claimed for
Items 1 and 2; and
(b) in respect of Item 3, that the plaintiff undertook the work
described in Schedule 5 of the amended statement of
claim [SOC [19]; Def [19]].”
Provisional Sum No 2 – “Joinery to Greatroom”
[475] Liability is not in dispute.
[476] An amount of $129,772.51 (plus GST) has been paid by the defendant.
[477] In this proceeding, the plaintiff claims an additional $3,840.00 (plus GST). This sum
is admitted by the defendant.
[478] Accordingly, the plaintiff is entitled to the amount of $3,840.00 (plus GST).
Provisional Sum No 6 – “Landscaping, irrigation and paving including design,
supply & installation of streetscape trees, grates, kerbing and public artwork”
[479] Liability is not in dispute and the defendant admits this claim.
[480] The Superintendent’s price was $5,020.39 (plus GST) made pursuant to CA59. This
amount has not been paid by the defendant but is admitted by it.
[481] In this proceeding, the plaintiff claims an additional $20,050.39 (plus GST) which is
also admitted by the defendant.
[482] Accordingly, the plaintiff is entitled to the amount of $25,070.78 (plus GST).
Provisional Sum No 8 – “Make good of the Council footpath to Wharf and Henry
Streets”
[483] In respect of this claim, both liability and quantum are in issue.
[484] This claim relates to work performed by the plaintiff making good the Council
footpath to Wharf and Henry Streets. The issues in dispute are whether an Aconex
mail dated 31 October 2016 constitutes a direction pursuant to clause three of the
Contract, whether the provisional sum provided for in the Contract only covered work
that was not already included in scope work and lastly, what was the proper price for
any provisional sum claimable.
[485] Clause three of the Contract provides as follows:
“3 Provisional sums
A provisional sum included in the Contract shall not itself be payable
by the Principal but where pursuant to a direction the work or item
to which the provisional sum relates is carried out or supplied by the
-- 90 of 210 --
91
Contractor, the work or item shall be priced by the Superintendent,
and the difference shall be added to or deducted from the contract
sum without any allowance for profits or overheads.
Where any part of such work or item is carried out or supplied by a
subcontractor, the Superintendent shall allow the amount payable by
the Contractor to the subcontractor for the work or item,
disregarding:
(a) (a) any damages payable by the Contractor to the subcontractor
or vice versa; and
(b) (b) any deduction of cash discount for prompt payment.
If the amount the Principal is required to pay the Contractor pursuant
to this clause 2.10 exceeds the total amount of all provisional sums
included in the Contract, the Principal must also pay the Contractor
an additional amount for profit and attendance calculated as the
percentage stated in Item 13 or elsewhere in the Contract of the
provisional sum excess amount.
The parties acknowledge the contract sum includes an amount for
overheads, profit and attendance for all provisional sums included in
the Contract.”
[486] The plaintiff refers to the definition of “direction” which states as follows:
“includes agreement, approval, assessment, authorisation, certificate,
decision, demand, determination, explanation, instruction, notice,
order, permission, rejection, request or requirement.”
[487] As previously observed, the definition of direction is quite broad. The defendant also
refers to clause 2.1 of the Contract which states as follows:
“The Contractor shall carry out and complete WUC in accordance
with the Contract and directions authorised by the Contract.
Subject to the express provisions of the Contract and the performance
by the Contractor of its obligations pursuant to the Contract, the
Principal shall pay the Contractor the contract sum adjusted by any
additions or deductions made pursuant to the Contract.”
[488] In respect of whether there has been a direction made, the plaintiff relies on the
following correspondence:
(a) On 18 October 2016, the plaintiff sent an email to the Superintendent stating:
“Pursuant to clause 3 and Part P of the general conditions of
contract we hereby submit the following submission of cost
adjustments justified and calculated against the Provisional
Sum allowances of $10,000.00 to make good of the Council
Footpath to Wharf & Henry St.
Scope of works is defined by the attached drawings and back
to back head contract / DA & other authority obligations as
presented in the attached BOQ.
-- 91 of 210 --
92
Expiry period for acceptance is 28/10/2016.”158
(b) The attachment to the Aconex mail was PC No 8 which set out a detailed
description of the pricing for the provisional sum works.159 PC No 8 rev A was
issued when revised in January 2017.160
(c) On 31 October 2016, Mr Malone sent a mail to Mr Carlin and Mr Cook
indicating that the works had been “assessed as WUC” but also directing the
plaintiff to “proceed as such”.
[489] The plaintiff relies on this last correspondence as being a relevant direction. The
plaintiff submits that whilst Mr Malone held the erroneous opinion that the works
were within the scope of the work under the Contract, he directed the plaintiff to carry
out the works. In this respect, the plaintiff contends that the email is a “request”,
“requirement”, “approval” or “demand” within the definition of direction in the
Contract. It is also contended that the plaintiff performed the works pursuant to that
direction.
[490] While it is open for that email to be classified as contended for by the plaintiff, the
second issue in respect of the original scope of work under the Contract, and whether
it needs to be outside of that, is the more substantive issue.
[491] The defendant refers to a plan which is listed in Annexure Part K of the Contract.
This is document C0201. The document is described as “C0201 Siteworks Plan Rev
R2” which is under the heading “CIVIL ENGINEERING – OPUS” in Annexure Part
K of the Contract.
[492] The defendant contends that this siteworks plan identifies work, which was included
in the original scope of work under the Contract. This work does not involve a
direction and does not constitute performance of work identified in the provisional
sum.
[493] The defendant contends that where there is work within the scope of the Contract, it
is covered within the Contract sum and it is not work covered by the provisional sum.
In these circumstances, it is only work which is additional to the scope covered by
the Contract, following on from a direction and which falls within the description of
a provisional sum item which would give rise to an entitlement to compensation in
respect of the provisional sum.
[494] On this approach, work shown in the siteworks plan would be within the scope of the
Contract and no additional compensation would arise. If, however, the defendant
directed different works or additional works (that is, works not notified in a plan or
somewhere in the Contract documents), then that might be work which the
provisional sum would operate in respect of.
[495] Some evidence was led in the statement of Mr Cook and he was also cross-examined
in relation to this work. It is not readily apparent how this work was different to that
envisaged by the Siteworks Plan C0201.
158 BUI.001.001.68578.
159 BUI.001.001.56115.
160 BUI.001.001.56226.
-- 92 of 210 --
93
[496] Construction of the Contract supports the conclusion that work covered by the
provisional sum does not form part of the work under the Contract. It operates such
that the final payment amount will be adjusted to reflect the actual work undertaken
in respect of the work identified in the provisional sum description.
[497] The plaintiff submits that the words of Part P of the Contract in relation to provisional
sum is unqualified and merely states:
“Make good of the Council Footpath to Wharf & Henry Streets.”
[498] However, the Contract provisions need to be read as a whole. There were clearly
aspects in relation to the footpath in Wharf and Henry Streets which were already
specifically addressed in the Contract documents. Accordingly, the provisional sum
needs to be interpreted in a way which recognises that the scope of work covered by
the Contract documents forms part of the work under the Contract. In these
circumstances, work additional to that which fell within the description of “making
good the Council footpath to Wharf and Henry Streets” would be work which would
be subject to a potential direction and claim under the provisional sum procedure.
[499] The specific work identified in document C0201 Siteworks Plan Rev R2 constitutes
work within the scope of the Contract. An amount in respect of that work has already
been included in the Contract sum. To the extent that there is any work outside of
that, which fits the description of “make good of the Council footpath to Wharf and
Henry Streets” then that could be the subject of a claim if a direction was made.
[500] There is no evidence that establishes that the work claimed is other than that which
would be covered under the scope of work as identified in document C0201 Siteworks
Plan Rev R2. In these circumstances, there is no basis for the provisional sum
claimed. Accordingly, the plaintiff is not entitled to recover an amount in respect of
this claim.
[501] If I am wrong and the plaintiff is entitled to recover in respect of the provisional sum
claimed, I accept the submission that the plaintiff has made a claim in respect of the
“network alteration to Telstra pits” and that it should be included in the amount. This
item is identified in Attachment 13 to Mr Watson’s report which is referenced in
Schedule 5 to the Amended Statement of Claim.
[502] Accordingly, if the plaintiff is entitled to an amount in respect of Provisional Sum No
8, the amount of $89,411.34 (plus GST) as assessed by Mr Watson should be adopted.
[503] The only difference between the value assessed by Mr Hardiman and Mr Watson’s
valuation is substantially the amount in respect of that one item.
[504] The amount in the joint expert report of Mr Watson’s assessment is $88,979.82 (plus
GST).
[505] This amount was reduced from the $89,411.34 in Mr Watson’s original report.
[506] The plaintiff is entitled to the revised amount of $88,979.82 if I am wrong and the
plaintiff is able to establish an entitlement to this claim.
-- 93 of 210 --
94
PRICING OF VARIATIONS SCHEDULE 6 - PRELIMINARIES
[507] Question five of the list of issues in dispute relates to claims made in respect of the
Schedule 6 variations and states as follows:
“5. In respect of the Schedule 6 Variations, whether, if priced
pursuant to clause 36.4 of the Contract, the plaintiff is entitled
to payment for an additional 7.5% for preliminaries [SOC [25];
Def [25]].”
[508] In relation to quantum, question 17 of the list of issues in dispute relevantly states as
follows:
“17. In respect of the Schedule 6 Variations, the extent to which, if
at all, the plaintiff is entitled to the amounts identified in
column D of Schedule 6 to the amended statement of claim
[SOC [26]; Def [25]].”
[509] As set out in paragraph six of the list of matters not in issue, the parties have agreed
as follows:
“6. In respect of the alleged Schedule 6 variations:
(a) that the plaintiff was directed to carry out the variation work
described in Schedule 6 [SOC [23]; Def [23]]; and
(b) that the defendant has paid to the plaintiff the certified
amounts set out in column B [SOC [24] Def [24]].”
[510] Schedule 6 of the Amended Statement of Claim lists a number of variations which
have been approved and certified by the Superintendent. It is accepted that the work
has been carried out and the defendant has paid the plaintiff the amounts claimed,
except for the amount identified as representing 7.5 per cent of the certified value of
the variations.
[511] The issue that is in dispute between the parties is whether, on a proper construction
of clause 36.4(d) of the Contract, the plaintiff is entitled to an additional 7.5 per cent
for “preliminaries” on top of the 10 per cent already added on account of profit and
overheads pursuant to clause 36.4 of the Contract.
[512] This issue is also relevant to the Schedule 3 and 4 variations. Those variations in
dispute also include a claim in respect of the 7.5 per cent for preliminaries which is
also disputed by the defendant.
[513] This issue arises in relation to the practical application of clause 36.4(d) which
provides that variations are to be priced on “reasonable rates or prices, which shall
include an amount equivalent to the percentage set out in Item 32A for profit and
overheads”.
[514] The variations listed in Schedule 6 were valued pursuant to clause 36.4(d) of the
Contract using reasonable rates or prices, including a 10 per cent amount in
accordance with Item 32A for profit and overheads.
-- 94 of 210 --
95
[515] The plaintiff submits, and Mr Watson, the quantum expert on behalf of the plaintiff
agrees, that the assessment of the price of the variations should include the additional
7.5 per cent claimed.
[516] Item 32A stipulates that the amount for profit and overheads is 10 per cent. Further,
the quantum experts on behalf of both parties agree that this should be split and
allocated as two per cent for profit and eight per cent for overheads.161
[517] As a consequence of this, the defendant submits that there is no proper basis for
adding the 7.5 per cent for “preliminaries”. The defendant ultimately submits that to
allow this additional 7.5 per cent on each variation would in effect increase the
contractually agreed eight per cent for overheads to a figure of 15.5 per cent for
overheads.
[518] The plaintiff submits that the reasonable rates or prices referred to in clause 36.4(d)
of the Contract does not require actual costs, but rather each variation is to be priced
using “reasonable rates or prices”. Further, it is submitted that it is common for these
types of costs to be charged as a percentage of the overall cost of the variation and
this is entirely orthodox and reasonable. It is also contended that time and resources
will be incurred in relation to the management of variations and there is no reason
why a contractor should not be compensated for the preliminary resources dedicated
to a variation to the WUC.
[519] Both Mr Watson, on behalf of the plaintiff, and Mr Hardiman, on behalf of the
defendant, were questioned in relation to what would be included under the
designation of preliminaries and also whether this was the same or different from the
overhead allowance as provided for in the 10 per cent.
[520] Mr Watson gave evidence of what work would have been required to be undertaken
by the plaintiff in relation to each of the variations, including such things as receipt
of instructions or amended design drawings, reviewing those documents and
informing subcontractors of changes, preparing prices and coordinating with relevant
subcontractors, submitting an agreed price with the Superintendent, instructing the
subcontractor to proceed with the variation, supervising the variation works and
processing a subcontractor’s claim for payment of the variation.
[521] The defendant disagrees with this approach. Firstly, the defendant refers to the
evidence of Mr Cook as indicating that there is no science to the application of a
mark-up of 7.5 per cent and it was just a standard figure that had been applied across
the board to all variations without regard to the particular circumstances of certain
variations.
[522] Additionally, it appears that the 7.5 per cent uplift had not been contemporaneously
claimed in relation to the variation proposals, but it was an additional amount which
has subsequently been sought by the plaintiff. That is, the 7.5 per cent increase was
claimed in Schedule 4 and Schedule 6 of the Amended Statement of Claim as an
addition to that which was claimed in the actual variation proposals.
[523] Further, the defendant points to the evidence of Mr Watson and in particular that he
was instructed to assume that the additional 7.5 per cent added were not overheads.
161 See BUI.001.001.61820 at p 062 and EXP.001.001.2215 at p 2222.
-- 95 of 210 --
96
It is in these circumstances that the defendant contends that Mr Watson’s opinion is
meaningless as that assumption was not separately proven.
[524] It is apparent from the evidence of Mr Watson and from the other evidence in respect
of this claim that the reference to overheads is used in different ways by different
people at different times. However, it is apparent that the amount in respect of
preliminaries is likely to include some onsite overheads. In this regard, Mr Watson
agreed that the Contract price often has built into it preliminaries including the cost
of a project manager, a site manager, a contract administrator and similar people. The
evidence in relation to this claim does not identify any additional resources that were
put on site beyond the ones that were already covered under the Contract.
[525] In these circumstances, it is difficult to be satisfied that the 7.5 per cent on account of
preliminaries is separate from the allowance for overhead within the 10 per cent
allowed for overhead and profit provided for in Item 32A.
[526] There is also the additional issue of whether the 7.5 per cent is a reasonable rate or
price.
[527] Mr Watson expresses an opinion that this “represents an average of the circumstances
which would be encountered for variations” and in his experience it is not unusual.
Mr Watson undertook some cross-checking to check for reasonableness.
[528] However, this approach appears to be rather arbitrary as Mr Watson estimates the
number of hours that would equate to the dollar value of the 7.5 per cent and then
considers whether the number of hours is appropriate to undertake the tasks which
are unidentified but of a general nature of the type that are likely to have been
undertaken.
[529] Mr Hardiman criticises this approach on the basis that there would be daily timesheets
which should record and support the actual cost incurred of doing, for example,
additional design work.
[530] The difficulty with the 7.5 per cent for preliminaries is that:
(a) there is no evidence which identifies with any precision the tasks which it
covers.
(b) there is no evidence to be satisfied that there is no duplication with the overhead
component of the 10 per cent uplift.
(c) there is no evidence that the 7.5 per cent is in any way reflective of the actual
or likely work undertaken in respect of the particular variations. For example,
there is no estimate of the volume of work required for a particular variation
that could be described under the category of preliminaries.
[531] The defendant contends that in these circumstances the 7.5 per cent impost for
preliminaries should not be allowed because:
(a) The amount is less than the eight per cent mark-up that is to be applied for
overheads (as a component of the 10 per cent uplift for profit and overheads).
(b) There is no evidence that any additional resources were required to deal with
any of the variations.
-- 96 of 210 --
97
(c) There has been no analysis of whether there were any individual tasks
undertaken in respect of each variation which ought, independently, be
considered not to be overheads.
(d) There has been no consideration of any individual tasks for each specific
variation.
[532] Given that there is specific provision within the 10 per cent uplift which covers
overheads and there is a lack of detail in relation to the items which would be covered
by the 7.5 per cent uplift for preliminaries, there is a considerable risk that there would
be duplication in respect of these costs. To include this mark-up in these
circumstances would result in a valuation which was unreasonable.
[533] For the reasons identified by the defendant, I find that the plaintiff has not made out
that there is any proper basis to add 7.5 per cent for preliminaries to each variation.
Accordingly, the plaintiff is not entitled to recover the 7.5 per cent by way of
preliminaries in respect of the variations in Schedule 6.
[534] This also applies in respect of the identified variations in Schedules 3 and 4.
OTHER CLAIMS BY PLAINTIFF
[535] The list of issues also identifies the following further issues relevant to the plaintiff’s
claim:
“19. The extent to which, if any, the defendant was entitled to
deduct, from amounts owing to the plaintiff, amounts for:
(a) utility backcharges [SOC [52]–[53A]; Def [33]];
(b) the alleged Vintech Defect [SOC [56]-[57B]; Def [35]–
[35B]].
20. Whether the defendant is liable to the plaintiff for the full
amount claimed pursuant to Progress Claim No.24 submitted
on 2 May 2017 [SOC [57C]–[57H]; Def [35C]–[35H]].
21. The extent to which, if any, the defendant was/is entitled to
have recourse to the unconditional undertaking provided by the
plaintiff to the defendant on 2 May 2016 [SOC [57I]–[57M];
Def [35I]–[35M]].”
[536] The list of matters not in issue relevantly states:
“8. In respect of the Security Bond, that the plaintiff paid to the
defendant the amount of $834,150.68 on 9 May 2019 in
exchange for the Bond being cancelled [SOC [57I][57J]; Def
[35I][35J]].”
[537] The plaintiff addresses these claims in the plaintiff’s written closing submissions
under the heading “Wrongful Set-off / Deductions / Withholding of Payments”.162
162 Plaintiff’s written closing submissions at [872]-[903].
-- 97 of 210 --
98
[538] These claims relate to:
(a) utility backcharges;
(b) amounts wrongfully withheld for defects; and
(c) amounts certified and claimed but unpaid - Progress Claim No 24.
[539] These reasons deal with a number of claims which may affect the amounts the subject
of:
(a) amounts wrongfully withheld for defects; and
(b) amounts certified and claimed but unpaid - Progress Claim No 24.
[540] The parties should consider these claims in light of these reasons and identify any
aspects which remain to be dealt with. Brief further submissions on these issues may
be necessary so they can be expeditiously and efficiently dealt with.
[541] In respect of the utility backcharges, the plaintiff’s written closing submissions
address this claim for $10,025.62. The defendant does not appear to have addressed
this claim in its written closing submissions, reply submissions or oral submissions.
[542] The plaintiff identifies that the amount in dispute comprises:
(a) $5,652.22 being utility charges incurred by the defendant either before the
plaintiff had taken possession of the site or after practical completion was
achieved. The plaintiff says in these circumstances, it is not obliged to
reimburse those amounts.
(b) $3,996.49 being GST incorrectly included on top of some utility invoices. The
plaintiff says GST was not payable as there was no taxable supply.
(c) $377.05 being in respect of invoices other than utility services.
[543] The plaintiff submits that the Superintendent has offset in Progress Claim No 24 an
amount for utility charges including these amounts which the plaintiff was not obliged
to pay.
[544] The plaintiff claims that it is entitled to have the amount of $10,025.62 repaid to it.
[545] As the defendant has not addressed this claim, the parties should consider the claim
in respect of the utility charges as part of the consideration of the amount under
Progress Claim No 24 and any outstanding issues. If the defendant maintains the
position identified in its Defence, then this should be briefly addressed in the further
submissions to be provided. If the defendant does not press its defence to this claim,
that should be notified to the plaintiff and incorporated in the calculations in respect
of the amounts owing arising out of these reasons.
-- 98 of 210 --
99
COUNTERCLAIM – ALLEGED NON-MECHANICAL DEFECTS
[546] Questions nine to 12 of the list of issues in dispute are relevant to the items claimed
by the defendant by way of counterclaim. These issues are as follows:
“9. Whether the works set out in Annexure 4 (items 1 and 4) and
Annexure 6 to the counterclaim are defective works in the ways
described therein [Def [38]; R [41]].
10. Whether the defendant is entitled to recover any costs incurred
in engaging consultants to inspect and advise on non-compliant
defective works and managing rectification of non-compliant
defective works [Def [42](a) & (b); R [41(bc)]].
11. In respect of the additional liquidated damages claim, to what
extent, on a proper construction of the Contract, the defendant
was entitled to an additional claim for liquidated damages [Def
[47], [48], [49], [50], [51]; R [41]].
12. Whether, on a proper construction of the Contract, the plaintiff
breached clause 2.1, subclause 2.2(a), clause 2.6, subclause
8.1(b), subclause 8.5(a), subclause 8.5(b), clause 8.8, clause
11.1, clause 34.10 and clause 35.1 of the Contract [CC [41(a)
to (j)]; R [41(bb)]].”
[547] Further, paragraph nine of the list of matters not in issue also states:
“In respect of the counterclaim, the works set out in items 2 and 3 of
annexure 4 to the third amended defence and counterclaim are
defective in the ways set out therein.”
[548] In respect of the quantum of the counterclaim, paragraph 22 of the list of issues in
dispute is relevant and states as follows:
“22. The cost to the defendant, if any, to rectify any defective works
in Annexure 4 and Annexure 6 to the counterclaim, and to
engage consultants to inspect and advise on non-compliant
defective works and manage rectification of non-compliant
defective works [Def [42], [43]; R [41(bc)]].”
[549] In Annexure four of the defendant’s counterclaim, the defendant sets out four non-
mechanical related defects. The plaintiff has admitted liability (but not quantum) in
relation to Items Two and Three. Liability is in issue for Items One and Four.
[550] Each of these claims are discussed below.
Defect Item One – “Crack in the basement level 2 slab”
[551] In respect of Defect Item One, liability is largely in issue.
[552] The defendant submits that structural drawings prepared on behalf of the plaintiff
required the basement level two concrete slab to be constructed using a dowelled
joint. The basement level two concrete slab was constructed by the plaintiff without
-- 99 of 210 --
100
using a dowelled joint. As a result, the concrete slab developed a significant crack
which allowed water to penetrate through the slab.
[553] The plaintiff admits the allegation that there is a crack in the basement level two slab
and that this is a defect, but otherwise does not admit the allegation. The plaintiff
submits that it is unclear on the pleadings whether the defendant alleges that the slab
is defective because water is able to ingress through the crack.
[554] Mr Prove, engaged by the defendant, produced a rectification detail at the time Defect
Item One emerged. He gave evidence at the hearing as to the steps that needed to be
taken to rectify the crack in the slab. Those steps are set out at paragraph 11.2 of his
report and included installing new dowelled joints.163 Mr Dummett of LJ Building
Services Pty Ltd gave evidence that LJ Building Services Pty Ltd carried out and
completed rectification of the basement level two slab in accordance with Mr Prove’s
rectification detail.164 Mr Dummett gave evidence that he charged the defendant
$18,974 to rectify Defect Item One. The defendant submits that the Court ought to
award the defendant $18,974, plus $6,944 for the preliminaries and builder’s margin
charged (apportioned on a pro-rata basis).165
[555] Mr Dummett’s evidence also included that these costs were fair and reasonable.166
This evidence was not challenged in cross-examination.
[556] The plaintiff submits that, to the extent that any amount is allowed in respect of Defect
Item One, it should be limited to the costs relating to the actual rectification of the
crack, not the cost of works which related to water ingress. The plaintiff submits that:
(a) the defendant has not specifically pleaded that the water which allegedly was
coming through the crack is a defect;
(b) there is no evidence as to the source of the water which was allegedly coming
through the crack, or evidence that the plaintiff is somehow responsible for the
ingress of the water; and
(c) there is no evidence that any part of the plaintiff’s WUC was defective such as
to cause the water ingress through the crack in the slab.
[557] The defendant claims the rectification costs on the basis that pursuant to clause 2.2(a)
of the Contract, the plaintiff was required to carry out and complete the works with
due skill, care and diligence and in accordance with the design documents so that the
works would be fit for purpose.
[558] The basement level two concrete slab was constructed by the plaintiff without a
dowelled joint as required by the plaintiff’s own structural drawings. The defendant
contends that as a result, a significant crack developed in the concrete slab which
allowed water to penetrate through the slab.
163 EXP.001.001.2459 at p 012.
164 WIT.001.001.0462 at p 0005 [4.9].
165 WIT.001.001.0462 at p 0009 [8.2]; PRO.061.001.0070.
166 WIT.011.001.0462 at p 0009 [8.3].
-- 100 of 210 --
101
[559] The rectification work undertaken is identified in the invoice from LJ Building
Services Pty Ltd as including work to rectify the water ingress through the crack in
the slab. This includes:
(a) a trench was lined with geo-fabric;
(b) a new slotted pipe was laid over the full length of the trench and connected to
the existing storm water pipe;
(c) a back flow penetration valve was installed at the junction of the stormwater
pipe and the aggregate line to prevent stormwater coming back up through the
aggregate line; and
(d) the trench was backfilled with drainage stones.167
[560] Annexure four of the Third Amended Defence and Counterclaim is headed “Non-
mechanical services systems defective works” and Item 1 reads as follows:
“Description of work required: The crack in the basement level 2 slab
needs to be rectified so that water cannot enter through the crack.
Description of defects: Basement 2 has a large crack in the slab near
the B2 Maintenance Room. Water is coming up through the crack
into the car park.”168
[561] There is evidence that establishes a link between the incorrect joint being installed
and the water ingress. This includes a memorandum from Mr Prove to Mr Dummett
produced following an inspection of the water leak through the crack.169 Relevantly,
Mr Prove identifies that “[h]ad the joint been installed as the documented [dowelled
joint], a crack is unlikely to have occurred in that location.” In respect of the water
ingress he goes on to conclude:
“Water tends to follow a path of least resistance, in this case, the path
of least resistance is now the crack in the slab on ground.”170
[562] Similarly, as recorded by Mr Dummett in his report annexed to the report of Mr Prove:
“The sawn joint installed was insufficient to transfer vertical load,
created by constant vehicle traffic, across the slab joint to minimise
differential deflection, resulting in a significant crack forming in the
basement 2 slab and providing a path of least resistance for water to
penetrate and enter the building.”171
[563] This supports the reasonableness of the rectification work undertaken as identified as
necessary by Mr Prove to rectify the defect and as undertaken by Mr Dummett.
[564] The evidence establishes that the defendant is entitled to the full amount claimed in
respect of this item on the basis that the plaintiff failed to carry out and complete the
167 Mr Dummett agreed these items of work related to the water ingress through the crack: T13-47; L14-
23.
168 PLE.001.001.0001 at p 0093.
169 Attached to the expert report of Mr Prove EXP.001.001.2459 at p 0053.
170 EXP.001.001.2459 at p 0033.
171 LJ Building Services Pty Ltd Report annexed to the expert report of Mr Prove EXP.001.001.2459 at p
0053 [3.3].
-- 101 of 210 --
102
work with due skill, care and diligence and in accordance with the design documents
so that it would be fit for purpose.
Defect Item Two – “The electrical penetration running through the mechanical
services slab needs to be adequately sealed and protected”
[565] In respect of Defect Item Two, liability is agreed.
[566] Mr Dummett of LJ Building Services Pty Ltd gave evidence that he rectified Defect
Item Two by engaging an electrician to inter alia:172
(a) isolate the electrical services running through the concrete slab;
(b) apply a new layer of polyurethane sealant to the slab penetration;
(c) install a new PVC riser around the new penetration seal; and
(d) install a new metal angle to divert water away from the slab penetration.
[567] Mr Dummett gave evidence that he charged the defendant $3,900 to rectify Defect
Item Two, excluding preliminaries and builder’s margin.173 The defendant submits
that the Court ought to award the defendant the sum of $3,900, plus $1,452 for
preliminaries and builder’s margin (apportioned on a pro-rata basis).
[568] The defendant’s submissions indicate quantum is agreed. The plaintiff does not
address this claim in its submissions.
[569] Based on the evidence of Mr Dummett the quantum of the defendant’s claim in
respect of this item has been established.174
Defect Item Three – “The storm water pipes, and each penetration through which
they run, need to be adequately sealed and waterproofed”
[570] In respect of Defect Item Three, liability is agreed.
[571] Mr Dummett of LJ Building Services Pty Ltd gave evidence that, under his direction,
LG Building Services Pty Ltd rectified Defect Item Three by sealing the junction of
the PVC storm pipe penetrating the slabs with polyurethane sealant, Sikaflex Pro.
[572] Mr Dummett gave evidence that he charged the defendant $250 to rectify Defect Item
Three, excluding preliminaries and builder’s margin.175 The defendant submits that
the Court ought to award the defendant the sum of $250, plus $93 for preliminaries
and builder’s margin (apportioned on a pro-rata basis).
[573] The defendant’s submissions indicate quantum is agreed. The plaintiff does not
address this claim in its submissions.
[574] Based on the evidence of Mr Dummett the quantum of the defendant’s claim in
respect of this item has been established.176
172 WIT.001.001.0462 at p 0006 [5.10].
173 WIT.001.001.0462 at p 0009 [8.2]; PRO.061.001.0070.
174 WIT.001.001.0462 at p 0009 [8.1]-[8.4].
175 WIT.001.001.0462 at p 0009 [8.2]; PRO.061.001.0070.
176 WIT.001.001.0462 at p 0009 [8.1]-[8.4].
-- 102 of 210 --
103
Defect Item Four – “The concrete structure around the basement staircase and
communications hub wall needs to be adequately waterproofed”
[575] Liability and quantum are in issue.
[576] The defendant submits that the basement staircase has water coming through the walls
and pooling on the ground because it has not been adequately waterproofed and does
not have a water control system installed to divert water from the stairs. The
defendant submits that the plaintiff’s failure to design the basement staircase in a way
that avoids water pooling on the ground is a breach of its obligations under clause
2.2(a).
[577] The plaintiff denies that the work is defective. The plaintiff submits that the concrete
structure around the basement staircase and the communications hub are compliant
with the Contract. The site generally experiences overland flow rather than underland
flow due to the site location, the fact that the site does not sit below the water table,
the dense rock site foundations and the slope of the site. The plaintiff installed a false
wall and a waterproofed hob to prevent ingress into the communications hub. This
requires water seeping through the walls to the hob to be pumped out. The plaintiff
submits that the water ingress is not caused by defective work, but by third party
external factors, such as defective neighbouring stormwater systems.
[578] Mr Dummett of LJ Building Services Pty Ltd gave evidence that LG Building
Services Pty Ltd engaged a waterproofing company as a subcontractor to inject the
basement staircase wall with a hydrophilic polyurethane resin to seal the leaking
joints and cracks in the wall to prevent water entering the staircase.
[579] Mr Dummett gave evidence that he charged the defendant $33,903.64 to rectify
Defect Item Four, excluding preliminaries and builder’s margin.177 The defendant
submits that the Court ought to award the defendant $33,903.64 plus $12,623 for
preliminaries and builder’s margin (apportioned on a pro-rata basis).
[580] Mr Dummett gave evidence that the costs were fair and reasonable. This was not
challenged in cross-examination.
[581] Whilst the plaintiff has raised whether the cause of the water ingress was a faulty
stormwater system on a neighbouring property,178 the defendant submits that no
evidence was led by the plaintiff that this was the cause.
[582] The plaintiff points to previous correspondence where this issue has been discussed
and the plaintiff has identified an issue with the neighbouring storm water pit.179
Further, the plaintiff points to the water ingress only occurring during significant rain
events.180
[583] It is difficult to see how this last point raised by the plaintiff addresses the issue of
liability. Brisbane would have significant rainfall events given its geographical
location and the proper design of the firestairs would have to take that into account to
meet the obligations under the Contract.
177 WIT.001.001.0462 at p 0009 [8.2]; PRO.061.001.0070.
178 Mr Cook’s evidence of his “belief” WIT.001.001.0476 at p 0002 [13].
179 See plaintiff’s written closing submissions at [920]-[921].
180 See plaintiff’s written closing submissions at [919].
-- 103 of 210 --
104
[584] The defendant maintains that the evidence establishes:
(a) Water penetrated the staircase wall on a number of occasions.181
(b) The plaintiff had previously taken steps to rectify the water ingress, including
applying an injected treatment.182
(c) Waterproofing was not evident upon Mr Dummett’s inspection.183
(d) There are no spoon drains to divert water away.184
[585] The defendant claims the rectification costs on the basis that pursuant to clause 2.2(a)
of the Contract, the plaintiff was required to carry out and complete the works with
due skill, care and diligence and in accordance with the design documents so that the
works would be fit for purpose.
[586] The defendant contends, that on the evidence, the water coming through the walls of
the staircase and pooling on the ground is a breach of the plaintiff’s obligations under
clause 2.2(a) of the Contract.
[587] Under the Contract the plaintiff was to design and construct fire stairs with due skill,
care and diligence and that would be fit for purpose. In the circumstances, the
defendant contends that this would require the design and construction of fire stairs
that were sufficiently waterproofed so that water could not enter the fire stairs and
also that had drains to divert water. I accept the defendant’s evidence and
submissions in this regard.
[588] The evidence in respect of the quantum of rectification work is not directly challenged
by the plaintiff, whose approach was to deny the work was defective. Further, the
plaintiff submitted that “the rectification works that Built has already performed are
… the best that can be done to stop the water ingress”.185
[589] On the evidence, I am satisfied that the defendant has established that the design of
the basement staircase did not meet the obligations under clause 2.2(a) of the
Contract.
[590] Further, I am satisfied on the evidence of Mr Dummett that the steps undertaken to
rectify the issue were appropriate and the costs were fair and reasonable.
[591] Accordingly, the defendant is entitled to the costs of the rectification work as claimed.
COUNTERCLAIM – ALLEGED MECHANICAL SERVICES SYSTEM
DEFECTS
[592] In Annexure Six of the defendant’s counterclaim, the defendant sets out 19 defects
which have been identified in relation to the mechanical services system. The
defendant claims the cost to rectify each of these defects.
181 WIT.001.001.0471 at p 0004 [3.2]-[3.6].
182 WIT.001.001.0471 at p 0004 [3.4(b)]–[3.9]
183 WIT.001.001.0462 at p 0008 [7.5].
184 WIT.001.001.0462 at p 0008 [7.5].
184 Plaintiff’s written closing submissions at [923].
-- 104 of 210 --
105
[593] Each of the claims are dealt with in turn below.
Defect 1.1 – “Duct bends & detail design”
[594] Liability and quantum are in issue.
[595] The defendant submits that it was a requirement of the tender drawings that the
plaintiff install duct bends that had a radiused throat or a square throat with turning
vanes, combined with offsets and transitions of less than 1:4.186 The defendant
submits that the plaintiff installed a number of duct bends which have a square throat
and radiused outside without turning vanes and transitions greater than 1:4.187 This
contributes to poor air flow performance and the inability of the guest room toilet
exhausts to achieve their required design criteria (see Defect 4.2).
[596] The plaintiff denies that the installed duct work is defective. The plaintiff submits
that the drawings relied on by the defendant were part of the Thwaite design, not the
plaintiff’s alternative proposal. As the detail on the tender drawings did not constitute
a performance requirement of the Thwaite design, there is no basis for the defendant’s
assertion that departure by the plaintiff from the duct bend design and offset and
transition detail on the tender drawings constitutes defective work. The plaintiff
further submits that there is no cogent evidence that a change in the duct design would
result in any particular air flow rate.
[597] Mr Lord’s rectification method is to fit turning vanes to the duct bends.188 Mr
Dowden gave evidence that this would rectify the defect but, in his experience, this
is likely to be more costly than replacing the duct bends by cutting them out and
installing new duct bends.189
[598] The parties’ quantum experts differ as to the proper cost for rectifying Defect 1.1.190
[599] In relation to Mr Dowden’s proposed rectification methodology:
(a) Mr Hardiman has calculated the proper cost to be $45,259.90; and
(b) Mr Watson has calculated the proper cost to be $40,758.07.
[600] The difference between the proper cost calculated by the parties’ quantum experts is
$4,501.83. The difference relates to the need to use a crane to lift the new pieces of
duct work to the roof. Mr Hardiman gave evidence that a crane was necessary
because some of the duct work is quite large, being 2,800mm x 350mm and 1,600mm
x 300mm. Mr Lord accepted that 2.8m x 0.35m and 1.6m x 0.3m duct would be
impractical to bring upstairs. That alone would require a crane.
[601] In relation to Mr Lord’s proposed rectification methodology:
(a) Mr Hardiman calculated the proper cost to be $41,448.68; and
(b) Mr Watson calculated the proper cost to be $24,100.74.
186 BUI.001.001.0157.
187 EXP.001.001.0157.
188 EXP.001.001.0450 at p 0474.
189 EXP.001.001.0512 at p 0552.
190 EXP.001.001.2425 at p 2426.
-- 105 of 210 --
106
[602] The difference between the proper cost calculated by the parties’ quantum experts is
$17,347.94. The difference relates to the amount of time required to fit the turning
vanes. Mr Hardiman gave evidence that a team consisting of one technician and three
labourers would take four hours to fit each turning vane whilst Mr Watson allowed
one technician and one labourer one hour to fit each turning vane.
[603] My earlier findings in respect of the interpretation of clause 1(u) of Annexure Part O
of the Contract are relevant to this claim. The plaintiff was to build its alternative
proposal for the mechanical system on the basis that it meet the “performance
requirement of the tender drawings and specification”. Consistent with my reasoning
in respect of the Mechanical Variation claim, the relevant performance requirements
may be found in the Specification and/or the drawings.
[604] The defendant’s claim is put two ways:
(a) The Contract required the specified air flow rates to be met as part of the
alternative proposal: that it was a performance requirement of the Contract that
the duct bends and transitions be designed and constructed in a way that did
not significantly reduce the air flow pressure in the system, so that the system
could meet the specified air flow rates.
(b) The obligation of due skill, care and diligence in respect of the design and
installation of the ducts pursuant to clause 2.2(a) of the Contract required the
specified air flow rates to be met.
[605] The impact of the different throated ducts was in issue between the parties’ experts.
During the trial it was agreed that the experts would provide a joint report having
regard to the air flow calculations available from the American Society of Heating,
Refrigerating and Air-Conditioning Engineers (ASHRAE). Consideration of the data
available from ASHRAE could assist in resolving the dispute between Mr Lord and
Mr Dowden as to the pressure loss as a result of the bends actually on site.
[606] The joint report was provided to the Court on 16 October 2020.191 The conclusion
reached by both Mr Dowden and Mr Lord is that the output figures derived from the
ASHRAE database closely accord with the figures provided by Mr Dowden.
[607] The defendant submits that as a result Mr Dowden’s evidence should be accepted:
that is, the Court should accept Mr Dowden’s evidence that the installed duct bends
have a significant impact on air flow performance in the mechanical system.
[608] In respect of the dispute between the mechanical services experts as to the effect that
the bends had on the mechanical system’s air flow performance, in light of the joint
report filed on 16 October 2020, I accept the evidence of Mr Dowden. That is, the
pressure loss of using a bend with a square throat and radiused back is analogous to
a square throated bend.
[609] The tender drawings require radiused bends or square throated bends with turning
vanes, thereby indicating a level of air pressure in the mechanical system to maintain
air flow performance. I am satisfied that this constitutes a performance requirement
that was to be met as part of the alternative proposal. By the installation of the square
191 PRO.030.001.001.
-- 106 of 210 --
107
throated ducts without turning vanes the performance requirement has not been met,
constituting a defect as a result of the impact on the air flow performance.
[610] There are two identified methods to rectify this defect.
[611] The first method proposed by Mr Dowden is to replace the duct bends by cutting out
the duct bends and installing new ones.192 There is a dispute as to the quantum
involved in this method:193
(a) Mr Hardiman for the defendant: $45, 259.90.
(b) Mr Watson for the plaintiff: $40, 758.07.
[612] The main difference between the two calculations relates to whether a crane is needed
to lift the duct pieces onto the roof and traffic management. Mr Lord contends that
the pieces could be taken up the stairs: although he did concede that the largest pieces
would require a crane as it would be impractical to bring them up the stairs.194
[613] If the rectification methodology proposed by Mr Dowden is to be adopted, Mr
Hardiman’s calculation of the cost is to be preferred. Taking the duct pieces up the
stairs in a working hotel is not feasible and on Mr Lord’s evidence a crane would be
required for the larger duct pieces in any event.
[614] The second rectification methodology is that proposed by Mr Lord. It involves fitting
turning vanes to each of the square throated ducts. There is also a dispute as to the
quantum involved in this method:195
(a) Mr Hardiman for the defendant: $41,448.68.
(b) Mr Watson for the plaintiff: $24,100.74.196
[615] The difference between the two calculations is as a result of the amount of time
allowed to fit the turning vanes. Mr Hardiman has allowed one technician and three
labourers four hours to fit each turning vane. Mr Watson has allowed one technician
and one labourer one hour to fit each turning vane.
[616] The plaintiff contends that the time allowed in Mr Hardiman’s calculation is
excessive. The defendant points to the scope of work identified by Mr Hardiman in
cross-examination as supporting his time estimate, namely:
(a) removing a portion of the duct (which may be up to 2.4 metres in size);
(b) opening up the duct;
(c) bringing up the turning vanes (which may be 2.4 metres in size); and
192 EXP.001.001.0512 at p 0552.
193 EXP.001.001.2425 at p 2426.
194 T13-5, L25-35.
195 EXP.001.001.2425 at p 2427.
196 The plaintiff’s written closing submissions at [960] and [964] refer to the amount of $17,347.94 as the
calculation of Mr Watson. This appears to be the difference between Mr Hardiman and Mr Watson,
rather than the amount of Mr Watson’s calculation.
-- 107 of 210 --
108
(d) attaching the turning vane by bolting it down inside the duct work, with each
vane needed to be bolted down to reduce vibrations.197
[617] Mr Hardiman also gave evidence during cross-examination, as to the number of men
required, including for health and safety reasons given the size of the ducts
involved.198
[618] The defendant also points to Mr Dowden’s view that it takes quite a bit of work to
retrospectively fit turning vanes to the duct work and that ordinarily, it is more
economic to simply replace the defective duct bend.199 This corroborates the
closeness of Mr Hardiman’s estimate on the second method to his estimate on the first
method.
[619] In respect of the second rectification method, the approach of Mr Hardiman is to be
preferred on the calculation of the costs involved. While there is some uncertainty
as to the labour and time required, I consider the approach of Mr Hardiman is
reasonable and considers the various relevant factors which may impact on the time
and labour required.
[620] The difference between the two rectification methodologies using Mr Hardiman’s
calculations is $3,811.22. This difference is not significant.
[621] While Mr Dowden does accept the second methodology would be an acceptable
solution,200 his proposed rectification approach was the first methodology. In the
reply report he concluded the decision as to which method could be left to the
contractor, but his view was “more site labour would be involved, at additional cost,
therefore this may not be economical”.
[622] Balancing the objective of rectifying the defect in respect of the rate of air flow and
the costs associated with the rectification work, I consider that the first methodology
is preferable. There is a greater level of certainty as to the costs involved between the
two quantum experts.
[623] Accordingly, the defendant’s claim for rectification of Defect 1.1 in Annexure Six in
the Counterclaim is allowed in the amount of $45,259.90 (plus GST) being Mr
Dowden’s rectification methodology and Mr Hardiman’s assessment of the costs.
Defect 2.1 – “Air conditioning – simultaneous heating and cooling”
[624] Liability is in issue, but quantum is agreed if liability is established and depending on
the appropriate rectification methodology.
[625] The defendant submits that it was a performance requirement of the tender drawings
and the Specification that the air conditioning system designed and installed by the
plaintiff be capable of performing the Independent Heating/Cooling Function on the
ground floor.
197 T13-8, L13-38.
198 T13-9, L13-30.
199 EXP.001.001.0512 at p 0552.
200 EXP.001.001.0512 at p 0552.
-- 108 of 210 --
109
[626] The plaintiff denies that the alleged defect constitutes defective work. The plaintiff
submits that the ground floor system is not defective as there was no performance
requirement of the Thwaite design which required the plaintiff to install a system
which provided simultaneous heating and cooling to the FCUs in all spaces.
[627] Mr Dowden and Mr Lord propose different rectification methods.201 Mr Dowden
proposes that the ground floor mechanical system ought to be rectified by changing
the current two-pipe system to a three-pipe system to enable independent heating and
cooling.202 Mr Lord proposes to increase the number of condenser units being
installed in each area with a consequent increase in the number of power supplies and
outdoor units to be installed and maintained.203
[628] The parties’ quantum experts agree that the proper cost of rectifying Defect 2.1 is:
(a) $151,201.57 to $151,203.09 if Mr Dowden’s proposed rectification
methodology is adopted; or
(b) $53,087.01 if Mr Lord’s proposed rectification methodology is adopted.
[629] Both parties agree that the outcome of this claim will be largely determined by the
decision in relation to the Mechanical Direction claim.
[630] In respect of the Mechanical Direction claim, as set out earlier in these reasons, the
proper construction of the Contract is that the plaintiff was required to design and
install an air conditioning system allowing mode control in each guest room, with the
ability for occupants of individual guest rooms to select temperatures utilising the
heating or cooling system independently of other guest rooms.
[631] In respect of this claim, it is necessary to construe the Contract in relation to the
plaintiff’s obligation in respect of the ground floor air conditioning system.
[632] The relevant provisions of the Contract, tender drawings and the Specification are set
out in the reasons relating to the Mechanical Variation. In addition, the provisions of
the Specification relevant specifically to the ground floor air conditioning system are
in clauses 2.2.5 to 2.2.8 and state as follows:
“2.2.5 FOH GF AIR CONDITIONING AHU-PN, AHU-PW +
AHU-C
• The perimeter zones in the public areas shall each be air
conditioned by a system comprising ceiling mounted AHU
which supplies conditioned air to the perimeter zone via
thermally insulated sheet metal duct work connected to ceiling
mounted linear grilles via flexible duct work
…
• The AHU shall include CHW and HHW coils
2.2.6 BOH GF AIR CONDITIONING FCU-GC, FCUGW, FCU-
GN
201 EXP.001.001.0512 at pp 0553-6.
202 EXP.001.001.0512 at pp 0555-6.
203 EXP.001.001.0512 at pp 0553-5.
-- 109 of 210 --
110
• The back of house areas shall be air conditioned by a system
comprising multiple ceiling mounted FCUs each of which
supplies conditioned air to the spaces via thermally insulated
sheet metal duct work connected to ceiling mounted grilles via
flexible duct work.
…
• The FCU shall include CHW and HHW coils
2.2.7 MEETING ROOMS GF AIR CONDITIONING FCU-M1
+ FCU-M2
• The 2 meeting rooms shall each be individually air conditioned
by systems comprising ceiling mounted FCU which supplies
conditioned air to the spaces via thermally insulated sheet metal
duct work connected to ceiling mounted grilles via flexible duct
work
…
• The FCU shall include CHW and HHW coils
2.2.8 KITCHEN GF AIR CONDITIONING FCU-K
• The kitchen shall be spot cooled by a system comprising ceiling
mounted FCU which supplies conditioned air to the kitchen
area via thermally insulated sheet metal duct work connected to
ceiling mounted grilles via flexible duct work.
…
• The FCU shall include CHW and HHW coils”
[633] For the reasons articulated in respect of the Mechanical Direction claim, the language
of clause 1(u) of Annexure Part O required that the performance requirements in the
tender drawings and specifications be met even though a VRF air conditioning system
was being provided rather than a four-pipe chiller (heat recovery) type system.
[634] The requirements in clauses 2.2.5 to 2.2.8 of the Specification are consistent with that
interpretation. The system being capable of providing independent heating and
cooling to specific areas on the ground floor is a performance requirement that the
plaintiff had to meet under clause 1(u) of annexure Part O of the Contract.
[635] The use of “conditioned” air in respect of each area is relevant to arriving at this
construction. On the plaintiff’s case “unconditioned air” is used to moderate
temperature. This is clearly not what was intended.
[636] For the reasons explained earlier in these reasons, a consistent interpretation of the
Contract is the proper construction of the Contract in respect of the ground floor air
conditioning system.
[637] On the proper construction of the Contract, the plaintiff was required to design and
install an air conditioning system allowing mode control in each of the specified areas
on the ground floor, with the ability to select temperatures utilising the heating or
cooling system independently of other areas on the ground floor.
-- 110 of 210 --
111
[638] While not relevant to the construction task, the expert evidence of both Mr Dowden
and Mr Lord is consistent with the interpretation of the requirements of clauses 2.2.5
to 2.2.8 as indicating a requirement for the ground floor to have independent heating
and cooling in different areas.204 The defendant points to this evidence in support of
its contention. The construction of the Contract is a question for the Court. However,
the view expressed by the experts provides a degree of comfort that the construction
arrived at is not inconsistent with a technical understanding of the Specification.
[639] Having construed the Contract in respect of the requirements for the ground floor air
conditioning system, it is necessary to consider whether the installed ground floor air
conditioning system is defective.
[640] The plaintiff installed a two-pipe Toshiba VRF system on the ground floor. The
defendant contends that the air conditioning system is defective because it is unable
to simultaneously heat and cool as required by the Contract.
[641] As the air conditioning system installed on the ground floor did not comply with the
Contractual requirements it is defective. The plaintiff is liable for the remedial action
needed to rectify the defect.
[642] Two different rectification methods are proposed:
(a) Mr Dowden proposes changing the ground floor air conditioning system from
the two-pipe system to a three-pipe system, similar to the work that was already
undertaken in respect of the guest room air conditioning system. These
modifications would enable independent heating and cooling as required by the
Contract.
(b) Mr Lord proposes that the number of condenser units installed in each area be
increased (with a consequential increase in the number of power supplies and
outdoor units).
[643] The defendant submits that Mr Dowden’s proposal should be preferred as:
(a) it is a tried and tested method of rectification of this defect;
(b) it maximises utilisation of existing equipment (including fan coil units, controls
and power supplies);
(c) it maintains heating and cooling capacities of currently installed fan coil units;
and
(d) it utilises refrigerant pipework lengths within the manufacturers’ acceptable
limits.
[644] Mr Lord in cross-examination accepted that Mr Dowden’s proposal was not
unreasonable and would provide the required independent heating and cooling
capability.205
[645] The plaintiff submits that Mr Dowden’s proposal is “unreasonable, unnecessary and
disproportionate”. The plaintiff relies on the evidence of Mr Lord in relation to the
204 EXP.001.001.0012 at pp 0157-0158; T8-33, L9-13; T8-85, L44-T8-89, L14.
205 T8-96, L27-36.
-- 111 of 210 --
112
cost and disruption of the proposal and that “[t]here is an easier way to achieve the
same result”.
[646] The plaintiff contends that Mr Lord’s methodology ought to be preferred. In this
regard the plaintiff points to the evidence of Mr Lord that given the layout of the
ground floor, even if less flexibility in the air conditioning is offered, it is not likely
to have any significant effect.206
[647] The defendant opposes Mr Lord’s proposed rectification method and points to the
following:
(a) The proposal was incomplete and had not been fully costed.
(b) Mr Lord did not inspect the Spring Hill Hotel (as Mr Dowden had done) leading
to issues in the proposed design.
(c) The proposal is a “patch-work” solution which “strays significantly from the
Tender Drawings and Specification.”
(d) The proposal does not actually provide for independent heating and cooling in
all of the required areas. In particular, it does not provide for independent
heating and cooling in each of the offices or individual meeting rooms.207
(e) The design would need to be modified but the extent of the modifications was
not clear and the extra cost involved was also not known.
[648] The rectification method proposed by Mr Dowden is reasonable and the resulting
modified system will meet the contractual requirement for independent heating and
cooling. Mr Dowden’s proposal should be adopted to rectify the defective work.
[649] The quantum experts are essentially in agreement about the value of the work using
Mr Dowden’s method, with a difference of under $2. In these circumstances, the
slightly higher value of $151,203.09 of Mr Hardiman should be used.
[650] Accordingly, the defendant is entitled to the amount of $151,203.09 for the
rectification of Defect 2.1.
Defect 2.2 – “Air conditioner – air commissioning”
[651] Liability is in issue but the parties agree on quantum if liability is established.
[652] The defendant submits that the test results issued by Testing and Maintenance
Solutions (TMS) demonstrate that only one out of the four Air Handling Units
(AHUs) tested on the ground floor achieved the air flow rate specified on the as-built
drawings the plaintiff produced at the end of the Contract. The defendant submits
that the low air flow rates leads to a reduction in air conditioning performance and
poor temperature control.
[653] The plaintiff denies that the defect as alleged exists. The plaintiff submits that clause
2.1.1.10 of the Specification does not require the AHUs to achieve any particular air
flow rate. Rather, clause 2.1.1.10 requires only that there be “[t]esting and
206 T8–93, L7-26.
207 EXP.001.001.0512 at pp 0554-0555. See also T8-92, L39-T8-94, L2; T8-94, L42-T8-96, L2.
-- 112 of 210 --
113
commissioning of all installed systems to NEBB standards”, and that commissioning
figures are provided for approval. The plaintiff further submits that testing and
commissioning of the ground floor air conditioning system has been performed and
that testing demonstrated that the systems have the capacity to provide sufficient
heating and cooling to the spaces served.
[654] Mr Dowden has proposed a method to rectify Defect 2.2 which was not addressed by
Mr Lord. Mr Lord has not provided an alternate proposal for rectification.
[655] If liability is established, the parties’ quantum experts agree that the cost to rectify
Defect 2.2 is $2,400.
[656] The defendant’s claim relies on:
(a) Clause 2.2 of the Contract, in that the plaintiff was required to carry out and
complete the design in accordance with the “Principal’s project requirements”,
including that the Spring Hill Hotel be fit for purpose.
(b) Clause 2.2(a)(i), in that the plaintiff was required to complete the work with
due skill, care and diligence.
(c) The requirement to meet the performance requirements of the tender drawings
as required by clause 1(u) of Annexure Part O of the Contract.
[657] The defendant points to the plaintiff’s as-built drawings which show the design air
flows and also the test results conducted by TMS and submitted by the plaintiff. The
defendant contends that the test results show that only one in four of the AHU’s tested
on the ground floor achieved the air flow rate specified on the as-built drawings.208
[658] Further, clause 2.1.1.10 of the Specification provides that “[t]esting and
commissioning of all installed systems to NEBB Standards and provision of
commissioning figures for approval.” The defendant contends that the requirement
of the NEBB Standard is that all air flows must be within 10 per cent of the design
quantities, which has not been met here.
[659] The defendant relies on the TMS test results showing that only one AHU achieved an
air flow rate within 10 per cent of the specified air flow rate: AHU-PN at 94 per cent
of its design rate.209 Further, AHU-PW achieved an air flow rate of only 53 per cent
of its design rate.210
[660] The TMS test results show that none of the AHUs achieved their designed outside air
flow rate, measured as between 19 to 48 per cent of the required design rate.211
[661] Mr Dowden’s evidence included:
(a) Low supply air flow rates leads to a reduction in air conditioning performance,
below specified requirements, leading to poor temperature control in various
zones.
(b) Low outside air flow rates will lead to poor indoor air quality.
208 EXP.001.001.0012 at p 0177.
209 EXP.001.001.0012 at p 0231.
210 EXP.001.001.0012 at pp 0232-0234.
211 EXP.001.001.0012 at p 0159 and pp 0231-0234.
-- 113 of 210 --
114
[662] It is in these circumstances, that the defendant submits that a mechanical system that
cannot meet its design air flow rates is not fit for purpose, was not completed with
due skill, care and diligence as required by the Contract and failed to meet the
performance requirements contained in the tender drawings.
[663] The defendant has established that the air flow rates do not meet the designed rates
shown in the plaintiff’s own as-built drawings in accordance with the NEBB
Standards. This is a sufficient basis for the claim to succeed on the basis of not being
fit for purpose and not completed with due skill, care and diligence. Defect 2.2 has
been established by the defendant.
[664] It may be that the performance requirements contained in the tender drawings are a
further basis, however, on the submissions and evidence identified in respect of this
defect claim this is not clearly established. In the circumstances, it is not necessary
to consider this further given the defect has been established.
[665] Accordingly, the defendant is entitled to the cost of rectifying Defect 2.2 in the
amount of $2,400.
Defect 2.3 – “Substation air intake”
[666] Liability is in issue but the parties have agreed on quantum if liability is established.
[667] The defendant submits that tender drawing M04 demonstrates that the outside air
intake is required to be connected to an outside air louvre.212 The defendant also
submits that clause 3.1 of the Specification requires compliance with AS 1668.2.
Clause 2.3 of AS 1668.2 requires air to be taken from outside the Spring Hill Hotel.
The defendant submits that the outside air intake is located inside the loading dock
behind the roller door.213 As a result, the outside air intake is sucking in pollutants
from trucks in the loading dock.
[668] The plaintiff denies that the work is defective. The plaintiff submits that there is no
evidence that the requirements of tender drawing M04 were a performance
requirement. The plaintiff further submits that the requirement to achieve outside air
was achieved. The duct work was extended to sit behind the roller door. There is no
practical difference between the design and the duct work built. The duct draws air
from outside through the grilled roller door, just as it would through louvres.
Accordingly, the ability to draw outside air is not affected.
[669] Mr Dowden has proposed a method by which to rectify Defect 2.3 which was not
addressed by Mr Lord. Mr Lord has not provided an alternate proposal for
rectification.
[670] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 2.3 is $9,833.64.
212 EXP.001.001.0012 at pp 0160 and 0217.
213 EXP.001.001.0012 at pp 0160 and 0444.
-- 114 of 210 --
115
[671] The evidence in respect of this claim includes the following:
(a) Mr Dowden:
“The substation outside air intake is installed in the loading dock
behind the roller door.
The substation outside air intake is not connected to an outside
air grille, leading to intake of pollutants from trucks in the
loading dock.”214
(b) Mr Lord:
“… none of this is good practice, in my opinion … We shouldn’t
have been drawing air from the garbage room through the
loading dock. We shouldn’t be taking outside air from the
loading dock to go into the substation. Neither of those
outcomes is good practice, nor do I believe that they actually
comply with the design criteria. Both the Thwaite design and
the design – if this red thing is what’s installed on site, that too
is not compliant … I don’t think you can say that the loading
dock is an acceptable source of air quality.”215
[672] On the evidence, the defendant has established Defect 2.3 on each of the bases
identified. Accordingly, the defendant is entitled to the amount of $9,833.64 in
respect of Defect 2.3.
Defect 2.4 – “Office – carpark ventilation noise”
[673] Liability is in issue, but the parties agree on quantum, if liability is established.
[674] The defendant submits that the carpark ventilation fan is creating excessive noise in
the back of house office. In this way, the mechanical system is not fit for purpose.
[675] The plaintiff denies that the defect as alleged exists.216 The plaintiff submits that the
carpark exhaust fans are fit for purpose. Attenuators were installed and all systems
have tested as compliant. The plaintiff further submits that the carpark exhaust fans
are only run at maximum speed in an emergency or when the emergency system is
tested approximately twice per year. In either case, the offices will be evacuated.
Accordingly, there is no material impact on the back of house office.
[676] Mr Dowden has proposed a method by which to rectify Defect 2.4 which was not
addressed by Mr Lord. Mr Lord has not provided an alternate proposal for
rectification.
[677] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 2.4 is $3,606.35.
214 EXP.001.001.0012 at p 0160; EXP.001.001.0012 at p 0444.
215 T9-54, L45-T9-55, L8.
216 PLE.001.001.0143 at p 0083.
-- 115 of 210 --
116
[678] The defendant relies on the evidence from Mr Dowden in respect of this claim which
includes:
“The back of house office is located above the carpark exhaust fan
location and the carpark exhaust duct passes over the office in the
ceiling space. Excessive noise is experienced in the office when the
carpark exhaust fans are run at maximum speed.
Attenuators have been installed in an attempt to rectify previously
notified defects, however excessive noise is still experienced in the
office area at times when the fans run at maximum speed”.217
[679] The plaintiff points to there being no evidence of actual noise levels or evaluation of
the noise levels by any particular standard. In this respect, the plaintiff contends that
the defect claim is unsubstantiated.
[680] On the basis of the evidence identified and relied upon in respect of this claim, this
defect has not been established. Accordingly, the defendant is not entitled to the
rectification costs claim in respect of Defect 2.4.
Defect 4.2 – “Guest room & maids room exhausts”
[681] Liability and quantum are in issue in respect of this claim.
[682] The defendant submits that clause 3.2 of the Specification requires compliance with
AS 1668.2. AS 1668.2 requires that bathroom and toilet exhausts located in hotels
achieve an air flow rate of 25 litres per second per room. The defendant also submits
that the same requirement is specified in tender drawing M09. Tender drawing M06
requires that each maid room exhaust achieve an air flow rate of 100 litres per second
per room. Neither the Specification nor AS 1668.2 provides the air flow rates for the
maid rooms.
[683] The defendant submits that the test commissioned by Mr Dowden and conducted by
Mr Visser demonstrated that the guest room toilet exhausts and maid room exhausts
do not achieve the specified air flow rates.218
[684] The plaintiff denies that the alleged defect constitutes defective work.219 The plaintiff
submits that earlier tests obtained from Remtech and TMS indicate that air flow
results were satisfactory. The plaintiff submits that there is no cogent evidence that
the earlier results were not accurate. The plaintiff further submits that the results
obtained by Mr Visser are not accurate, as Mr Visser allowed insufficient time before
taking a reading.
[685] Mr Dowden’s rectification method is to gain access to the toilet exhaust risers and
have each one sealed (if necessary) by a qualified sheet metal worker.220 Mr Lord’s
proposed rectification method is to spray an atomised sealant “Aeroseal14” into the
mechanical system. The sealant can only be applied by one company known as
Aeroseal.221
217 EXP.001.001.0012 at p 0161.
218 EXP.001.001.0012 at p 0204.
219 PLE.001.001.0143 at pp 0083-4.
220 EXP.001.001.0512 at p 556.
221 EXP.001001.0512 at pp 557-8.
-- 116 of 210 --
117
[686] The parties’ quantum experts differ as to the proper cost for rectifying Defect 4.2.
[687] In relation to Mr Dowden’s proposed rectification methodology:
(a) Mr Hardiman calculated the proper cost to be $664,306.69;
(b) Mr Watson calculated the proper cost to be $376,727.68.
[688] The difference between the proper cost calculated by the parties’ quantum experts is
$287,579.01. The difference relates to the number of walls that need to be demolished
to seal the risers and the number of man hours to conduct this work. Mr Hardiman
gave evidence that 226 walls would need to be removed and eight man hours would
be needed per room.222 Mr Watson gave evidence that 143 walls would need to be
removed and two man hours would be needed per guest room and a further eight
hours per riser in the maid rooms.223
[689] In relation to the rectification methodology proposed by Mr Lord, the parties’
quantum experts agree that the proper cost to rectify Defect 4.2 is $56,980.
[690] The defendant relies on clause 1(u) of Annexure Part O of the Contract that the
alternative proposal for the mechanical services system be installed on the basis that
it meets “the performance requirement of the tender drawings and specification”.
Consistent with the reasoning in respect of the Mechanical Direction claim, the
specific requirements set out in the tender drawings and the Specification were to be
met by the plaintiff.
[691] This would include the air flow rates for the guest room and maid rooms specified in
the tender drawings. Further, clause 3.2 of the Specification provides that the
mechanical services system must comply with certain Australian Standards, including
AS 1668.2 in respect of mechanical ventilation for acceptable indoor-air quality.224
[692] In respect of the guest rooms, Appendix B of AS 1668.2 and tender drawing M09
(Mechanical Services Typical Guest Room Layout)225 both require an air flow rate of
25 litres per second per room.226
[693] In respect of the maid rooms, the required air flow is not specified in the Australian
Standard, but is shown on the tender drawings. Tender drawing M06 (Mechanical
Services Level 2-11 Layout)227 requires that each maid room exhaust is to achieve an
air flow rate of 100 litres per second per room.228
[694] Consistent with the reasoning in respect of the Mechanical Direction claim, these are
performance requirements of the tender drawings and the Specification and the
plaintiff was required to design and install a system that met these requirements.
222 EXP.001.001.2425 at p 2430; PRO.071.016.0004.
223 EXP.001.001.2425 at p 2430.
224 BUI.001.002.34972 at p 031.
225 PRO.071.015.0001 at p 0007.
226 PRO.071.015.0001 at p 0006.
227 PRO.071.015.0001 at p 0008.
228 There is some evidence that this was later modified to 70 litres per second per room.
BUI.001.001.24769 at p 011.
-- 117 of 210 --
118
[695] The defendant relies on the testing undertaken by Mr Visser, who Mr Dowden
engaged to undertake independent air flow testing, to establish that the requirements
were not met. Mr Visser was cross-examined in respect of his testing approach and
it was put to him that his test results were not accurate as the tests were undertaken
too quickly.
[696] Mr Visser’s evidence was credible, logical and methodical and he answered all
questions put to him in a professional manner. He is highly experienced in
undertaking tests of this nature and is certified and accredited in the area. I accept the
evidence of Mr Visser as to his testing methodology and the accuracy of his test
results.
[697] The plaintiff seeks to rely on the TMS test results but no witness was called to explain
the test results or the basis on which the tests were undertaken. There is considerable
uncertainty as to what was tested by TMS. In these circumstances, the TMS test
results cannot be used in direct comparison to the evidence of the test results given
by Mr Visser.
[698] The tests results of Mr Visser show:229
(a) 48 guest room toilet exhausts were tested,230 being a sample of 21 per cent.
Only five of the tests achieved a design air flow rate within 10 per cent of the
required 25 litres per second per room. Consequently, on average 90 per cent
of the guest room toilet exhausts did not achieve the required air flow rates.
(b) 12 maid room exhausts were tested, being 100 per cent. None of the maid room
exhausts achieved a design air flow rate within 10 per cent of the required 100
litres per second per room or 70 litres per second per room.
[699] The test results clearly establish that the air flow rates in the guest rooms and the maid
rooms do not comply with the requirements of the tender drawings and the
Specification (including AS 1668.2).
[700] On the evidence, the defendant has established Defect 4.2. It is then necessary to
consider quantum.
[701] Two different rectification methods are identified. Further, there is a considerable
dispute as to the proper costs of the method proposed by Mr Dowden.
[702] The defendant contends that the Court should accept Mr Dowden’s proposal for
rectification as it is a “tried and tested method for the rectification of this kind of
defect” and will avoid any risk to the fire dampers located in the duct work.
[703] The plaintiff contends that Mr Dowden’s proposal is “unreasonable, unnecessary and
disproportionate given the available alternative methodology”. Further, the plaintiff
submits that the required work for Mr Dowden’s proposal is “invasive and
disruptive”.
229 Test results commence at EXP.001.001.0012 at p 0204. See also defendant’s written closing
submissions at [58] for summary.
230 Of the 226 guest rooms.
-- 118 of 210 --
119
[704] Mr Dowden’s rectification proposal requires the demolition and reinstatement of the
bathroom walls of each of the guest rooms. This is required to provide access to the
toilet exhaust risers to enable each one to be resealed.
[705] In contrast, Mr Lord’s rectification proposal is for the atomised sealant “Aeroseal 14”
to be applied to the exhaust and supply air risers. Mr Lord’s evidence is that this is a
“conventional method” and “tried and tested”. Mr Lord also is of the opinion that it
is a simpler and cheaper proposal and also deals with both air supply and air
extraction.231
[706] There is considerable disagreement in relation to the second proposal, including:
(a) how long the Aeroseal coating would last;
(b) whether it met the standard specified in the tender drawings and the
Specification; and
(c) the risk of damage or interference with fire dampers in the duct work.
[707] The plaintiff submits that Mr Lord has addressed all of these concerns in his evidence
and the second rectification proposal should be preferred over Mr Dowden’s
proposal.
[708] Conversely, the defendant submits that while Mr Dowden accepted the Aeroseal
method may contribute to satisfactory air flow, the other concerns remain and as a
result Mr Dowden’s rectification proposal should be preferred.
[709] The evidence before the Court does not assist in resolving all of these areas of
disagreement.
[710] I have accepted the evidence of Mr Dowden as to the defective performance of the
guest rooms and maid room exhausts. The rectification proposal identified by Mr
Dowden includes:
“The walls and ceilings should be removed to gain access to toilet
exhaust riser … Toilet exhaust riser ducts should be inspected
internally to assist in identifying leakage paths and check cleanliness.
Any debris present should be removed. Toilet exhaust riser ducts
should be sealed to reduce leakage … The air systems should be re-
balanced, adjustments made to the heat exchange units and test
figures submitted … The walls and ceilings should be re-instated
…”232
[711] Considering all of the evidence in respect of this claim, the rectification proposal of
Mr Dowden addresses the defects in the work undertaken by the plaintiff and
maintains as close as possible what would have been the original work if the
contractual requirements were carried out in the first place. Accordingly, I accept Mr
Dowden’s proposed solution in respect of the rectification work.
[712] In relation to quantum, the cross-examination of Mr Hardiman highlighted that there
is considerable uncertainty as to how many walls need to be demolished and
231 EXP.001.001.0450 at pp 0475-6.
232 EXP.001.001.2279 at p 2292.
-- 119 of 210 --
120
reinstated and the labour required to undertake the work. The calculations used by
Mr Watson assess what work needs to be undertaken for the necessary access and
also seek to minimise unnecessary work which would not assist in achieving the
rectification of the defect. On balance, I prefer the assessment of costs of Mr Watson
in respect of Mr Dowden’s rectification proposal.
[713] In these circumstances, I consider that the defendant is entitled to the costs of the
rectification of Defect 4.2, which should be assessed in accordance with the costing
undertaken by Mr Watson.
Defect 4.3 – “Level 1 to 12 outside air supply”
[714] Liability is in issue but the parties agree on quantum if liability is established.
[715] The defendant submits that tender drawing M10 requires that the outside air flow rate
on each floor is 50 litres per second.233 It is unclear what air flow rates are being
achieved, as the level one to 12 outside air supply system has been configured in a
way which does not allow for the air flow rates to be measured at each floor.234 The
defendant submits that the air flow rates are a performance requirement and the ability
to measure air flow rates should be held to form part of that performance requirement.
[716] The defendant further submits that section 12 of the Specification requires
commissioning of the mechanical system. This requirement cannot be met, as the
installed system cannot be commissioned. Once Defect 4.3 is rectified, test results
will need to be submitted in accordance with clause 2.1.1.10 of the Specification
which requires testing and commissioning to NEBB Standards.235
[717] The plaintiff denies that the defect as alleged exists.236 The plaintiff submits that the
ability to measure air flow rates at each floor is not a requirement of the Contract and
it is not necessary to test air flow rates at each floor to obtain adequate measurements
using the NEBB guidelines. The plaintiff submits that it complied with the Contract
by causing the outside air supply flow to be tested in accordance with the NEBB
standards at each HRV unit and at the top of each supply riser.
[718] Mr Dowden proposes that Defect 4.3 should be rectified by installing additional duct
work to facilitate air flow measurements from the supply air dampers. This involves
removing parts of the ceiling and conducting reinstatement work once the work is
complete.237 Mr Lord proposes that Defect 4.3 may be rectified by measuring the
riser air flow at a point between each riser take-off and, by deduction, identifying how
much outside air has been delivered.238
[719] The parties’ quantum experts agree that the proper cost to rectify Defect 4.3 is:
(a) $760 to test and balance the system; and
(b) $40,857.90 to install the additional duct work (including associated work) to
facilitate air flow measurement from the supply air dampers.
233 BUI.001.002.34983; EXP.001.001.0512 at p 0545.
234 EXP.001.001.0163.
235 EXP.001.001.0162.
236 PLE.001.001.0143 at pp 0084-5.
237 EXP.001.001.0012 at p 0163.
238 EXP.001.001.0512 at pp 0559-60.
-- 120 of 210 --
121
[720] Consistent with the reasoning in respect of the Mechanical Direction claim and the
other defect claims in respect of air flow rates, the air flow rate specified in the tender
drawing is a performance requirement. Further, the ability to measure air flow is an
inherent requirement in the overall system design and also to meet the commissioning
requirements in section 12 of the Specification.
[721] As identified by Mr Dowden, the tender drawings and the Specification require the
mechanical services system to be “balanced and commissioned to ensure satisfactory
performance”.239 It is necessary therefore to be able to measure the air flow rates on
each guest room floor. This would also be consistent with the obligation for “due
skill, care and diligence” pursuant to clause 2.2(a)(i) and being fit for purpose.
[722] In these circumstances, the inability to measure air flow rates for each floor is a defect.
Once there is the ability to undertake measurements then compliance with the
specified air flow rates needs to be considered.
[723] Mr Lord proposes that the defect can be rectified by measuring the riser air flow at a
point between each riser take-off and then deducing how much outside air has been
delivered. Mr Dowden’s evidence is that this proposal is not feasible and in any event
would require significant wall demolition and reinstatement to achieve the necessary
access.
[724] Mr Dowden’s proposal is for the defect to be rectified by installing additional duct
work to facilitate air flow measurements. This requires removal of parts of the ceiling
and reinstatement work once the work is completed. This work has been costed by
the quantum experts.
[725] I accept the defendant’s submission that Mr Dowden’s proposal should be preferred
as Mr Dowden attended site and also considered the feasibility of both methodologies.
Further, any demolition and reinstatement work that may be required under Mr Lord’s
proposal has not been fully considered nor costed.
[726] In the circumstances, the defendant is entitled to an assessment of the rectification
work in accordance with Mr Dowden’s proposed rectification of the defect in the
amount of the agreed quantum, being $760 to test and balance the system and
$40,857.90 for the additional duct work.
Defect 4.4 – “Guest room toilet exhaust risers – fire rating”
[727] Senior Counsel for the defendant indicated during closing oral submissions that this
defect claim was not being pressed.240
Defect 4.5 – “Guest room fan coil unit – interface with occupancy controls”
[728] Liability and quantum are in issue.
[729] The defendant submits that clause 2.2.21 of the Specification requires that “[t]he
guest rooms shall have standalone electronic controls to operate each FCU serving
the room and shall be interfaced with the guest room energy management system
(turns FCU ON-OFF).” The energy management system is referred to as the Vintech
239 EXP.001.001.0512 at p 0545.
240 T14-54, L35-40.
-- 121 of 210 --
122
energy management system. The purpose of the system is to automatically turn the
air conditioning off when a guest leaves the room and automatically turn the air
conditioning on when they enter or remain in the room. The defendant submits that
the mechanical system’s FCU does not properly interface with the Vintech energy
management system. As a result, the Vintech energy management system can turn
the FCU system off but it cannot turn it back on after inactivity.
[730] The plaintiff denies that the defect as alleged exists. The plaintiff submits that the
defendant directed the plaintiff to install the Vintech energy management system.241
There is no identified defect in the installation work carried out by the plaintiff, or in
any of the other equipment installed by the plaintiff in respect of the Vintech energy
management system. The plaintiff submits that there is no evidence that the Vintech
energy management system operates in any way other than how the system is
designed to operate.
[731] Mr Dowden has proposed that the guest room FCU and Toshiba controls interface to
the Vintech energy management system should be modified to enable the air
conditioning system to automatically turn on and off. Before this work can be carried
out, a 600mm x 900mm piece of the ceiling in each guest room will need to be
removed, and then reinstated after the system has been modified.242 Mr Lord did not
propose an alternate methodology.
[732] The parties’ quantum experts disagree as to the proper cost to rectify Defect 4.5:
(a) Mr Hardiman assessed the proper cost to be $95,425.11; and
(b) Mr Watson assessed the proper cost to be $71,651.60.
[733] The difference between the proper cost calculated by the parties’ quantum experts is
$23,773.51. The reason for the difference is that Mr Hardiman allowed 1.5 hours per
room for a technician to modify the controls interface whilst Mr Watson allowed 0.5
hours per room.
[734] The defendant describes the defect in Item Nine of Annexure Six to the Counterclaim
as follows:
“The interface with the energy management (Vintech) system has the
ability to turn the guestroom fan coil units off, but does not have the
ability to turn them on, contrary to this specified requirements.”
[735] Clause 2.2.21 of the Specification states:
“The guest rooms shall have standalone electronic controls to operate
each FCU serving the room and shall be interfaced with the guest
room energy management system (turns FCU ON-OFF)”.
[736] The difficulty with this defect claim is that while it is clear that the air conditioning
may turn off automatically but not restart when a guest moves within their room, the
cause of the issue is not clearly established on the evidence.
241 WIT.001.004.0001 Witness Statement of Thomas Cook at p 0083; T7-76, L11-12.
242 EXP.001.001.0512 at pp 0560-1.
-- 122 of 210 --
123
[737] The defendant contends that it is the interface between the mechanical system and the
Vintech energy management system which is the defect. Further the defendant points
to the evidence of Mr Dowden that “adjustments” by Toshiba and Vintech have
previously been made and this resolved the issue.243
[738] However, there is no evidence of what the plaintiff is alleged to have done or not done
to cause this problem.
[739] The plaintiff installed the Vintech energy management system as directed. There is
no evidence that the Vintech energy management system operates other than as it was
designed to do. There is no evidence that the installation by the plaintiff was faulty.
[740] The difficulty is highlighted by a lack of evidence as to precisely what work a
technician would do to rectify the issue.
[741] The lack of precision about identifying the actual cause of the issue and the
“adjustments” that need to be made to rectify the issue results in there being
insufficient evidence to establish this as a defect.
Defect 4.6 – “Guest floor lift lobbies – moisture damage to ceilings and dripping
air conditioning grills”
[742] Liability and quantum are agreed.
[743] The defendant submits that the mechanical system is leaking condensation from the
air conditioning grills causing moisture damage to plasterboard ceilings. A
mechanical system that leaks condensation and causes damage to plasterboard
ceilings is not fit for purpose. The defendant further submits that this is a breach of
clause 2.2(a)(i) of the Contract.
[744] The plaintiff admits the existence of the defect alleged.
[745] Mr Dowden has proposed that the roof top heat recovery units be commissioned and
controlled to ensure that the supply air is dehumidified and sufficiently cooled to
prevent condensation.244 Mr Lord did not propose an alternate rectification
methodology.
[746] The parties’ quantum experts agree that the proper cost to rectify Defect 4.6 is $5,130.
[747] The defendant is entitled to the amount of $5,130 in respect of Defect 4.6.
Defect 5.1 – “HX-1, HX-2 filter installation”
[748] Liability is in issue but the parties have agreed on quantum, if liability is established.
[749] The defendant submits that clause 4.5.1 of the Specification requires that service
access to change the filters be from the dirty side of the filters. Access to the filters
is poor and the filters are removed by sliding out rather than by removal from the
dirty side.245
243 EXP.001.001.0512 at pp 0546-7.
244 EXP.001.001.0012 at p 0165.
245 EXP.001.001.0012 at p 0166.
-- 123 of 210 --
124
[750] The plaintiff denies that the defect as alleged exists.246 The plaintiff submits that full
access to the filters was enabled by duct work modifications to the filter plenums and
construction of a platform ladder for service access to HX-1. The filters were
replaced and upgraded and gauges were fitted for pressure drop readings.247 The
plaintiff submits all rectification work has been completed and access is adequate for
the proper maintenance of the filters.
[751] Mr Dowden has proposed that Defect 5.1 may be rectified by modifying the filters so
that access can be gained from the dirty side of the filters. Mr Lord has not provided
an alternate proposal for rectification.
[752] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.1 is $3,232.95.
[753] Senior Counsel for the defendant in closing oral submissions recognised the difficulty
with this claim arising out of the rectification work that the plaintiff has already
undertaken.248 Whilst Mr Dowden observed the problem with the access to the filter,
there is no clear evidence on whether the work done, including the platform ladder,
fully addresses the concerns.249
[754] Mr Dowden’s report is based on inspections in October 2017 and March 2018.250 In
the report to the Superintendent dated 28 June 2018 the plaintiff lists the rectification
work as completed.
[755] Given the rectification work that has already been completed by the plaintiff to enable
access to HX-1251 and there being no evidence that this has not adequately addressed
access for the maintenance of the filters, this defect has not been established.
Accordingly, the defendant is not entitled to the costs claimed in respect of the defect
rectification work for Defect 5.1.
Defect 5.2 – “Roof mounted duct work – water pooling”
[756] Liability is in issue but the parties agree on quantum, if liability is established.
[757] The defendant submits that clause 2.2.12 of the Specification requires duct work
exposed to the weather to be constructed with a graded top surface to prevent pooling
of water. The ducts exposed on the roof have not been constructed with graded top
surfaces. As a result, water is pooling on the duct work and rust stains are forming.
[758] The plaintiff submits that clause 2.2.12 of the Specification relates to the specific
system designed by Thwaite and is not a performance requirement of the plaintiff’s
alternative proposal. Accordingly, there has been no failure to comply with the
Contract.
246 PLE.001.001.0143 at p 0088.
247 BUI.300.001.0010 at p 16.
248 T14-55, L17-23.
249 Whilst there are questions about the filters in the context of the testing undertaken by Mr Visser, the
rectification work and access does not appear to have been put directly to him in cross-examination.
250 EXP.001.001.0012 at p 0019.
251 BUI.300.001.0009; BUI.300.001.0010 at p 0015.
-- 124 of 210 --
125
[759] Mr Dowden proposes that Defect 5.2 may be rectified by constructing a graded cover.
Mr Lord has not provided an alternate proposal for rectification.
[760] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.2 is $0.00 on the basis that it is included in the quantum for other
defects.
[761] Clause 2.2.12 of the Specification relevantly states:
“All duct work on the roof shall be internal acoustic type and cross
broken so that no water is able to accumulate on the flat surfaces. All
flanged joints and the flexible discharge joints shall be covered in
sheet metal to stop water pooling and to provide UV protection.”
[762] Consistent with the reasoning in respect of the Mechanical Direction claim, clause
1(u) of Annexure Part O required the plaintiff to install the alternative proposal for
the mechanical system on the basis that the performance requirement of the tender
drawings and the Specification were met. The requirement in clause 2.2.12 was a
requirement that the plaintiff needed to meet.
[763] The evidence of Mr Dowden is that the ducts on the roof have not been constructed
with graded top surfaces and as a result water is pooling and rust stains are forming.
The evidence establishes that is defective work on the basis that the requirement of
the Specification has not been met, it is not fit for purpose and/or it has not been
undertaken with due skill, care and attention.
[764] However, there is no additional loss caused by this defect and accordingly the
defendant is not entitled to any additional cost specifically in respect of this defect.
Defect 5.3 – “Insulation on roof duct work”
[765] Liability is in issue but the parties agree on quantum if liability is established.
[766] The defendant submits that clause 2.2.12 of the Specification requires all duct work
on the roof to be internal acoustic type,252 and that tender drawing M08 requires the
insulation to be 75mm thick.253 Internal acoustic type duct work refers to sheet metal
duct work with sound attenuating insulation contained on the inside. The defendant
submits that 75mm of internal acoustic type duct work has not been provided for in
relation to the supply air duct work from HX-1 and HX-2 to the risers.
[767] The plaintiff denies that the work is defective.254 The plaintiff submits that the
Contract, including the alternative proposal, does not require all insulation to be
installed inside the duct. To the extent that the Specification sets out a performance
requirement, there is no evidence that the relevant performance relates to anything
other than noise attenuation. The method by which noise attenuation is achieved is
not a requirement of the Contract. The plaintiff submits that, in any event, the
insulation to the duct work includes internal insulation. The insulation fulfils its
purpose of noise attenuation and is not defective.
252 BUI.001.002.34972 at p 023.
253 BUI.001.002.34981.
254 PLE.001.001.0143 at p 0089.
-- 125 of 210 --
126
[768] Mr Dowden has proposed that Defect 5.3 be rectified by replacing the non-compliant
roof ducts with 75mm internal acoustic duct work. Mr Lord agreed with Mr
Dowden’s proposed methodology.
[769] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.3 is $14,757.64.
[770] The defendant points to clause 2.2.12 of the Specification for the requirement that
“[a]ll duct work on the roof shall be internal acoustic type”. Further the defendant
refers to tender drawing M08 for the requirement that the insulation be 75mm thick.
[771] The evidence of Mr Dowden is that the insulation installed on the duct work is 50mm
external insulation.255 Mr Lord accepted that the insulation installed was not internal
acoustic insulation.256
[772] The plaintiff denies that the work is defective and makes submissions that the
insulation installed is adequate to achieve noise attenuation.
[773] However, this fails to address the concerns raised by the defendant in respect of the
longevity of the external installation. Internal acoustic type insulation has
“significantly better longevity” due to the protection from the elements. This is
evident from the photographs taken by Mr Dowden, with the external insulation
already showing damage from exposure to weather.257
[774] The duct work on the roof is non-compliant in that it is not internal acoustic type with
a minimum thickness of 75mm. Consistent with the reasoning in respect of the
Mechanical Direction claim, clause 1(u) of Annexure Part O of the Contract required
that the mechanical services system meet the performance requirement of the tender
drawings and the Specification. This work does not and is defective.
[775] Accordingly, the defendant is entitled to the cost of replacing the non-compliant roof
ducts with 75mm internal acoustic duct work. This cost is agreed in the amount of
$14,757.64.
Defect 5.4 – “HX-1, HX-2 condensation traps omitted”
[776] Liability is in issue but the parties agree on quantum if liability is established.
[777] The defendant submits that clause 3.2 of the Specification requires compliance with
AS 3666 – “Air handling and water systems of buildings – Microbial control”. Clause
2.9.1 of AS 3666 requires drain lines to be trapped to seal against air flow. The
defendant submits that heat recovery units HX-1 and HX-2 do not have condensate
traps installed to allow condensate to drain. As a result, there is a retention of water
in the internal drain trays and water overflow into the compressor, resulting in
microbial growth inside the machine.258
255 EXP.001.001.0012 at p 0179.
256 T9-87, L11-29.
257 EXP.001.001.0012 at p 0167; EXP.001.001.0512 at p 0549; EXP.001.001.0012 at pp 0445-0446.
258 EXP.001.001.0012 at pp 0167-8.
-- 126 of 210 --
127
[778] The plaintiff does not admit this allegation. The plaintiff submits that none of the
plaintiff’s witnesses were cross-examined about this issue and the Court should not
accept on the balance of probabilities that there is a defect.
[779] Mr Dowden has proposed that Defect 5.4 be rectified by installing condensate traps
with graded pipework for both heat recovery units.259 Mr Lord has not provided an
alternate proposal for rectification.
[780] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.4 is $767.90.
[781] Clause 3.2 of the Specification identifies the requirement for compliance with AS
3666. Equally design to meet this requirement would be required by clause 2.2(a)(i)
of the Contract, requiring the work to be undertaken with due skill, care and diligence,
as well as clause 2.2 to be fit for purpose.
[782] Mr Dowden gave evidence that he observed that there were no condensate traps
installed on HX-1 and HX-2 to allow condensation to drain. He also gave evidence
that this is resulting in retention of water in the internal drain trays and water into the
compressor, resulting in microbial growth inside the machine.260
[783] The evidence establishes that the requirement relates to the quality of air circulated
throughout the Spring Hill Hotel and non-compliance with the requirements results
in the system not being fit for purpose.
[784] In these circumstances, the defect has been established and the defendant is entitled
to the cost to rectify the defective work being $767.90.
Defect 5.5 – “Water in HX-1 isolating switch”
[785] Liability is in issue but the parties agree on quantum, if liability is established.
[786] The defendant submits that clause 3.2 of the Specification requires compliance with
AS 3000 “SAA Wiring Rules”. Clause 1.5.4.4 of AS 3000 requires that electrical
equipment be protected by enclosures to suit the environmental conditions.261 The
defendant submits that Mr Dowden observed water running out of the electrical
power isolating switch on the exterior of the HX-1 heat recovery unit on the roof.
[787] The plaintiff does not admit this allegation. The plaintiff submits that none of the
plaintiff’s witnesses were cross-examined about this issue and the Court should not
accept on the balance of probabilities that there is a defect.
[788] Mr Dowden proposes that Defect 5.5 be rectified by replacing the isolating switch,
junction boxes, switch housing and conduits before sealing these items to prevent the
ingress of water. Mr Lord has not provided an alternate proposal for rectification.
[789] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.5 is $1,298.00.
259 EXP.001.001.0012 at pp 0167-8.
260 EXP.001.001.0012 at pp 0167-0168.
261 EXP.001.001.0012 at p 0168.
-- 127 of 210 --
128
[790] Based on the evidence of Mr Dowden and the requirement to comply with AS 3000,
there is sufficient evidence to be satisfied that the work undertaken by the plaintiff is
not fit for purpose and is defective.
[791] In the circumstances, the defendant is entitled to the cost to rectify this defect in the
amount of $1,298.00.
Defect 5.6 – “HX-1, HX-2 filter gauges defective”
[792] Liability is in issue but the parties agree on quantum, if liability is established.
[793] The defendant submits that clause 4.5.1 of the Specification requires pressure gauges
to be installed across air filters, adjusted, and marked ‘Filter Dirty – Replace’ at the
appropriate pressure. The defendant submits that the gauges are not reading correctly
and are not correctly zeroed.262
[794] The plaintiff does not admit this allegation. The plaintiff submits that there is no
cogent evidence adduced by the defendant in support of Defect 5.6. Specifically, Mr
Dowden did not give any evidence of checks undertaken by him of the gauges and
did not provide any explanation of the measurements recorded by TMS. Mr Visser
did not provide any such evidence. The plaintiff submits that the Court should not
accept on the balance of probabilities that there is a defect.
[795] Mr Dowden proposes that Defect 5.6 be rectified by having a controls technician
calibrate and zero the gauges and check for compliance with the manufacturer’s
recommendations. Mr Lord has not provided an alternate proposal for rectification.
[796] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.6 is $760.00.
[797] There is evidence from Mr Dowden that the pressure tests conducted by Mr Visser
demonstrate that the gauges were not reading correctly and Mr Dowden also
personally observed that the gauges were not correctly zeroed.263
[798] Further, the test results also show a significant difference between the measured
results and the readings from the gauges. Only one gauge read correctly.264
[799] It is in these circumstances that the defendant submits that gauges which do not
accurately record the status of the filters are not fit for purpose. Additionally, the
defendant contends that accurate gauges are a performance requirement as they are
required to indicate when filters need to be checked and changed.
[800] There is also evidence from Mr Lord in cross-examination, including:
(a) “I think if you look at the gauges, the gauges are all over the place and – and,
potentially, damaged or wrong, or full of dirt.”
(b) “… there’s something clearly wrong with the gauge”.
262 EXP.001.001.0012 at pp 0168-9.
263 EXP.001.001.0012 at p 0168.
264 HX-2 (Toilet Exhaust Filter). EXP.001.001.0012 at p 0205.
-- 128 of 210 --
129
(c) “But can I suggest to you those [sic] – the readings from the gauges there
indicate to you that they are not operating properly?—The … gauge readings
make no sense, yes. I would agree with that assertion.”
(d) “I would perhaps even go stronger, that they are operating defectively”.
(e) … I think the gauge readings there make no sense; I think the gauges there are
defective”.265
[801] There is sufficient evidence to establish that there is a defect in respect of the gauges
and the rectification work proposed by Mr Dowden is reasonable.
[802] Accordingly, the defendant has established an entitlement to the cost of rectifying
Defect 5.6 in the amount of $760.00.
Defect 5.7 – “HX-2 – water pooling in outside air duct”
[803] Liability is in issue but the parties agree on quantum, if liability is established.
[804] The defendant submits that clause 6.5.1 of the Specification requires “[d]ucts exposed
to weather to be constructed with graded top surface to prevent pooling of water”.266
The defendant submits that implied in clause 6.5.1 is a requirement that water does
not enter the duct. The defendant submits that Mr Dowden observed water pooling
in the HX-2 heat recovery outside air intake duct. The presence of water in the duct
will lead to increased humidity in the air intake, exacerbating problems with excess
moisture in the corridors.267
[805] The plaintiff does not admit this allegation. The plaintiff submits that it inspected the
roof duct work in a heavy rain event in March 2018. Most of the duct had no pooling
of water and the plaintiff installed graded sheet metal capping to the sections of
affected duct work. The plaintiff submits that the Court should not accept on the
balance of probabilities that there is a defect.
[806] Mr Dowden proposes that Defect 5.7 be rectified by weatherproofing the outside air
intake duct to prevent the ingress of water and installing trapped drainage provisions
at the bottom of the duct to ensure that any water is drained from the duct.268 Mr Lord
has not provided an alternate proposal for rectification.
[807] If liability is established, the parties’ quantum experts agree that the proper cost to
rectify Defect 5.7 is $1,298.00.
[808] The defendant in oral submissions clarified that there may be a misunderstanding by
the plaintiff in respect of this claim. The basis of the defendant’s claim is that there
is water inside the duct, not pooling on the outside of the duct.269
265 T9-42, L19–T9-43, L11.
266 BUI.001.002.34972 at p 053.
267 EXP.001.001.0012 at p 0169.
268 EXP.001.001.0012 at p 0169.
269 T14-56, L27-30.
-- 129 of 210 --
130
[809] The evidence of Mr Dowden is as follows:
“Water was observed pooling in the HX-2 outside air intake duct, to a
depth of about 20mm. This indicates that rainwater is making its way
into the duct.
The presence of rainwater in the duct will lead to increased humidity
in the air intake, exasperating problems with excess moisture in the
corridors ...”270
[810] The design and installation of the outside air duct allowing water to enter and pool in
the duct is clearly in breach of the requirement that it be fit for purpose and designed
with due skill, care and diligence.
[811] The evidence establishes the defect and accordingly, the defendant is entitled to the
cost of rectifying the defect in the amount of $1,298.00.
Defect 6.1 – “As installed drawings (O&M manuals)”
[812] Liability and quantum are in issue.
[813] The defendant submits that clause 12.7 of the Specification requires the plaintiff to
supply to the defendant post contract drawings that accurately represent the actual
installations.271 The defendant submits that as-built drawings M07 Mechanical
Services Levels 2-10 Typical Layout and M09 Mechanical Services Roof Layout
contain a number of inaccuracies.272
[814] The plaintiff denies that the work is defective.273 The plaintiff submits that the as-
installed drawings are true and accurate representations of the actual installations.
Alternatively, to the extent that any information is omitted from the drawings, the
plaintiff submits the inaccuracies are minor and the drawings comply or substantially
comply with the Contract.
[815] Mr Dowden proposed that Defect 6.1 be rectified by employing a draftsperson to
accurately depict the duct work configuration and equipment installed on site in the
as-built drawings. Mr Lord has not provided an alternate proposal for rectification.
[816] The parties’ quantum experts disagree as to the proper cost to rectify Defect 6.1:
(a) Mr Hardiman assessed the proper cost to be $12,000.00; and
(b) Mr Watson assessed the proper cost to be $1,200.00.
[817] The difference between the proper cost calculated by the parties’ quantum experts is
$10,800.00. The reason for the difference is that Mr Hardiman based his calculation
on the cost of a technical consultant for 10 days whilst Mr Watson based his
calculation on the cost of a technical consultant for one day.
270 EXP.001.001.0012 at p 0169.
271 BUI.001.002.34972 at p 096.
272 EXP.001.001.0012 at pp 169-70.
273 PLE.001.001.0143 at p 0091.
-- 130 of 210 --
131
[818] The difficulty with this claim is that Mr Dowden’s evidence relates to inaccuracies in
two drawings but the claim is wider than that. Mr Dowden’s evidence is as follows:
“The Levels 1-12 typical floor drawing … does not show the correct
location and configuration of the toilet exhaust fire dampers, toilet
exhaust grilles, outside air ducts to guestrooms.
Similarly, the Roof drawing … shows the incorrect location of HX-
1, does not show extended air intake ducts to HX-1 and HX-2, and
does not show installed configuration of KEF-1, SPF1A and SPF
1B”.274
[819] Clearly the inaccurate drawings would not be fit for purpose and should be corrected.
[820] To the extent that the claim is wider than the identified drawings, there is not
sufficient evidence to establish the defect.
[821] Mr Watson has costed the time it would take to rectify the omissions identified by Mr
Dowden.
[822] Accordingly, the defendant is entitled to the cost of rectifying as-built drawings M07
and M09 in the amount of $1,200.00.
Defect 6.2 – “O&M manual content”
[823] Liability and quantum are in issue.
[824] The defendant submits that clause 12.8 of the Specification lists the requirements for
the Operating and Maintenance (O&M) manuals, including “satisfactory
performance tests”.275 The defendant submits that the O&M manuals do not contain
the requisite commissioning data for guest room FCUs, ground floor FCUs, guest
room toilet exhaust system, guest room and levels one to 12 outside air supply system
and refrigerant pipework including extra refrigerant quantities added.276 The
defendant submits that there is no evidence these items had been commissioned,
tested and balanced.277
[825] The plaintiff denies that the work is defective.278 The plaintiff submits that the O&M
manuals do not omit any required information. Alternatively, to the extent that any
information is omitted, the plaintiff submits the inaccuracies are minor and the O&M
manuals comply or substantially comply with the Contract.
[826] Mr Dowden proposed that Defect 6.2 be rectified by:279
(a) carrying out testing and commissioning of the above items after the required
rectification had been carried out and including the results in the O&M manual;
and
274 EXP.001.001.0012 at p 0169.
275 BUI.001.002.34972 at p 097.
276 EXP.001.001.0012 at p 0170.
277 EXP.001.001.0012 at p 0170.
278 PLE.001.001.0143 at p 0091.
279 EXP.001.001.0012 at p 0170.
-- 131 of 210 --
132
(b) searching for the refrigerant pipework test results (if they exist) and including
them in the O&M manuals.
[827] Mr Lord has not provided an alternate proposal for rectification.
[828] The parties’ quantum experts disagree as to the proper cost to rectify Defect 6.2:
(a) Mr Hardiman assessed the proper cost to be $12,000.00; and
(b) Mr Watson assessed the proper cost to be $1,200.00
[829] The difference between the proper cost calculated by the parties’ quantum experts is
$10,800.00. The difference arises because Mr Hardiman based his calculations on
the cost of a technical consultant for 10 days whilst Mr Watson based his calculation
on the cost of a technical consultant for one day.
[830] To the extent that the O&M manuals do not include “satisfactory performance tests”
the O&M manuals would not be fit for purpose. This commissioning data is an
important aspect of monitoring the overall performance of the system and is clearly
identified in clause 12.8 of the Specification.
[831] The defendant has established Defect 6.2 and is entitled to the costs of the rectification
work.
[832] The difficulty with the assessment of costs by both quantum experts is that the
assessment is based on imprecise information. As it is not clear whether the plaintiff
ever undertook the required testing, further commissioning data may be required.
Providing an estimate of the costs of obtaining that data and preparing the updated
manuals is akin to estimating the length of the proverbial piece of string.
[833] Mr Dowden’s rectification work identified in the right hand column of
EXP.001.001.0012 at page 170 at point two identifies the need to undertake “testing
and commissioning”. In the cross-examination and re-examination of Mr Hardiman
there was some confusion as to what Mr Hardiman had included in his estimate. In
re-examination Mr Hardiman was asked to clarify exactly what he had costed and he
responded as follows:
“Ten days of work. It’s … an allowance. I mean, it is … future work
as opposed to [a valuation] of works being carried out. It was an
allowance of 10 days which was an allowance I thought was
reasonable of two weeks for carrying out any … necessary testing to
get the results that are required to include in the O and M manual.
And then completion of the O and M manuals themselves.”280
[834] Leave was granted to the plaintiff to re-open cross-examination of Mr Hardiman. Mr
Hardiman’s evidence included:
(a) “I’ve allowed in my report what I thought was a reasonable, I suppose,
guesstimate of how long it would take somebody to complete those reports
based upon my experience in other projects, how long these things take.”281
280 T13-30, L30-37.
281 T13-32, L8-10.
-- 132 of 210 --
133
(b) “What about testing the operation of individual heating control mechanisms in
the rooms? – As I said, I didn’t break it down into that much detail. I allowed
two weeks for the whole exercise.”282
(c) “And you’re just making it up, aren’t you? You’re just – this is just trying to
justify your 10-day estimate which you – where you haven’t referred in any of
your reports – whether your first report, the joint report or your reply report –
to this requirement to actually carry out testing or any allowance for carrying
out of testing? – As I say, I spoke to Mr Dowden, I understood what was
required to complete the O and M manuals. I then made a calculation in my
head as to roughly how long I would expect that to take on a normal process of
work and allowed 10 days. It’s ... not a scientific number; I have to accept that
…
(d) But, in fact, you’ve got no clue – you can – how long it would … take to go
around to the rooms and check the Vintech system?—No, but …
(e) Whether it’s a few or 10 days? --- But …. I allowed what … I believed to be a
reasonable allowance for that type of work”.283
[835] Mr Watson’s estimate of one day is unreasonably low and I do not accept that as a
reasonable estimate of the cost of the rectification work.
[836] Mr Hardiman’s cost is based on his estimate of the likely costs based on his
experience. While this evidence is less than perfect, I prefer the evidence of Mr
Hardiman in respect of the reasonable cost of the rectification work given what is
identified by Mr Dowden as to the scope and extent of the work involved.
[837] On the evidence the defendant has established Defect 6.2 and the defendant is entitled
to the costs of the rectification work based on the estimate provided by Mr Hardiman
in the amount of $12,000.00.
DEFENDANT’S CLAIM FOR ADDITIONAL LIQUIDATED DAMAGES
[838] In respect of the quantum of the counterclaim, paragraph 23 of the list of issues in
dispute is relevant and states as follows:
“23. The extent to which, if any, the defendant is entitled to further
amounts for liquidated damages [Def [51]; R [41(bi)]].”
[839] The list of matters not in issue as agreed between the parties relevantly states:
“7. In respect of liquidated damages, that the Date of Practical
Completion certified by the Superintendent was 3 March 2017
[SOC [42]; Def [29]].”
[840] The defendant seeks payment of the amount of $196,623.31 (plus GST) by way of
additional liquidated damages calculated as a result of the correction of an error in
calculating the date for practical completion.
282 T13-32, L19-21.
283 T13-32, L26-42.
-- 133 of 210 --
134
[841] Clause 34.7 of the Contract provides that the defendant is entitled to liquidated
damages for every day after the date for practical completion to and including the
date of practical completion. The rate is specified in Item 29 of Annexure Part A of
the Contract, namely $14,044.53 per day.
[842] The date for practical completion is specified in Item 7 of Annexure Part A of the
Contract, namely 1 September 2016. This date may be adjusted as a result of any
extensions of time granted by the Superintendent under the Contract.284
[843] The Superintendent, Tactical, certified on 9 March 2017 that:
(a) The date for practical completion was 10 November 2016.
(b) The date of practical completion was 3 March 2017.
(c) The period between the date for practical completion and the date of practical
completion is 113 days.
(d) The total value of liquidated damages due and payable by the plaintiff to the
defendant is $1,587,032 (plus GST).285
[844] On 13 March 2017, the liquidated damages amount was deducted from amounts due
to the plaintiff for Progress Claim No 24. Further, on 20 March 2017 the defendant
set-off that sum from moneys certified as otherwise being due and payable to the
plaintiff.286
[845] The defendant’s claim is made on the basis that subsequently to this, an error by the
Superintendent in calculating the adjusted date for practical completion was
identified. The defendant contends that in calculating the adjusted date for practical
completion a five day work week was used when a six day work week should have
been used.
[846] The defendant points to the Contract as contemplating a six day work week, as
evidenced by:
(a) the Contract Baseline Program in Annexure F, which shows activities were
programmed on all days except Sundays.287
(b) the Brisbane City Council Approval Package Ref A003851963 listed in
Annexure Part K, permitted work to be performed on Mondays to Saturdays.288
[847] Further, the defendant relies on evidence that shows that work was carried out on a
six day work week, including:
(a) Mr Cook, the project manager on site, stated in cross-examination that work
was done six days a week “as much as possible”.289
284 Clause 34 of the Contract.
285 PRO.001.001.1749.
286 PLE.001.001.0336 at p 0348 [46]-[47]; PLE.001.001.0001 at p 0040 [31].
287 The defendant refers to the example of EXP.001.001.0858 at p 1046.
288 BUI.001.001.61820 at p 141; PRO.071.005.0002.
289 T3-27, L38-40.
-- 134 of 210 --
135
(b) Mr King’s as-built prepared from primary documents (such as site diaries)
shows work was carried out Mondays to Saturdays.290
(c) A number of extensions of time claims by the plaintiff were made on the basis
of a six day work week.291
[848] Mr King in his report gives evidence in relation to the Superintendent’s extension of
time register (Register). Mr King explains from his consideration of the Register, the
counting of days in the Register was done on the basis of a five day work week.292
[849] On the basis of the Register, the date for practical completion was to be adjusted by
44.5 working days. The Superintendent had arrived at an adjusted date of 10
November 2016 using a five day work week. Using a six day work week, the adjusted
date of 27 October 2016 is arrived at.293
[850] On 20 May 2019, the Superintendent provided the plaintiff with a further progress
certificate pursuant to clause 37.2 of the Contract correcting the error. The
Superintendent certified:
(a) The correct adjusted date for practical completion is 27 October 2016
calculated on the basis of a six day work week.
(b) The period between the correct adjusted date for practical completion and the
date of practical completion (3 March 2017) is 127 days.
(c) The total value of liquidated damages due and payable is $1,783,655.31 (plus
GST).294
[851] Clause 37.2 of the Contract relevantly states:
“At any time and from time to time, the Superintendent may by a
further progress certificate correct any error which has been
discovered in any previous progress certificate.”
[852] The defendant contends that the natural and ordinary meaning of this clause permits
the correction to be undertaken, resulting in the additional amount of liquidated
damages claimed.295
[853] The plaintiff’s position in response is that the defendant is not entitled to the
additional amount of liquidated damages for a number of reasons.
[854] The first basis that the plaintiff relies on is that the plaintiff is entitled to an extension
of time caused by the Mechanical Direction and as a result no liquidated damages
would be payable. This basis is not made out given my findings in respect of the
plaintiff’s claim in respect of the Mechanical Direction claim.
290 EXP.001.001.0858 at pp 944 [277] and 962 [316].
291 BUI.001.001.71465; BUI.001.001.63006; BUI.100.003.8934; BUI.100.004.0417;
BUI.001.001.61822; BUI.001.001.71410.
292 EXP.001.001.0858 at pp 0880-3 [68]-[80]; see EXP.001.001.0858 at p 0880 [72].
293 EXP.001.001.0858 at p 0882 [75].
294 PRO.060.001.0095.
295 The amount claimed is the difference between the sum already set-off and the corrected amount.
PLE.001.001.0001 at p 0054 [51].
-- 135 of 210 --
136
[855] Secondly, the plaintiff contends that the defendant is not able to adjust the date for
practical completion to an earlier date as it purports to do. The plaintiff points to Item
7(a) and clause 34.5 of the Contract as allowing the date to be extended only, not
shortened to an earlier date. The plaintiff submits that the ability to rectify errors
pursuant to clause 37.2 is subject to what the Contract allows.
[856] Consequently, the plaintiff’s position is that the defendant cannot after the Spring Hill
Hotel has reached practical completion assert that the date for practical completion
was earlier.
[857] This contention was addressed in more detail in the plaintiff’s submissions in respect
of its claim for an extension of time.296 In support of its contention that the date for
practical completion cannot be adjusted after it has been certified the plaintiff refers
to:
(a) The definition of the “date for practical completion” in clause 1 of the Contract.
The relevant date is the date in Item 7(a) or “if any EOT for practical
completion is directed by the Superintendent or allowed in any dispute
resolution procedure or litigation, it means the date resulting therefrom”.
Based on this meaning, the plaintiff submits that the “date for practical
completion” is the date specified or extended, and it does not allow the date to
be extended and then brought back again.
(b) Clause 34.5 of the Contract provides for the Superintendent to grant an
extension of time, within 14 days of a claim or in the exercise of the unilateral
discretion to grant an extension of time. In the clause there is no reference to
revising an extension of time once granted. Once granted, the Superintendent
is functus officio in relation to the exercise of the discretion.
(c) The Contract does not provide for an amended extension of time and
consequently the Superintendent does not have power to do so.297 The final
paragraph of clause 37.2 is a specific provision enabling errors in progress
certificates to be corrected. There is no similar provision in respect of
extensions of time.298
(d) The parties must “work towards the date for practical completion, as extended
from time to time”. The contractor may, for example, accelerate work to avoid
liquidated damages. The plaintiff submits “[i]t would be a perverse result if, a
long time after practical completion, the date could be moved to an earlier date
and the contractor told that, unfortunately, liquidated damages were payable
because the contractor had not achieved this new date”.
[858] The third basis that the plaintiff relies on is that the defendant has not established on
admissible evidence that in fact the Superintendent failed to take into account work
done on Saturdays in determining the adjusted date for practical completion of 10
November 2016.
296 Plaintiff’s written closing submissions at [372].
297 In support of this contention the plaintiff refers to the decision of RB Burden Ltd v Swansea Corp
[1957] 3 All ER 243 at 250 per Lord Radcliffe, but acknowledges that case related to a payment
certificate. The reasoning in this case is of no real assistance in determining the current issue.
298 The plaintiff identifies that progress payments are always on account, so the specific provision in
clause 37.2 is not surprising.
-- 136 of 210 --
137
[859] In response the defendant submits that the words “it means the date resulting
therefrom” in the definition of date for practical completion makes it clear that the
actual date for practical completion is a “mathematical function” of the number of
days that have been directed by the Superintendent or allowed by the Court.
[860] The defendant submits that it is the number of days extension of time that is certified,
not the adjustment of the date for practical completion. That is, once an extension is
allowed (by the Superintendent or the Court) the date for practical completion results
from the calculation of the number of days allowed.
[861] The defendant contends, that the correction issued on 20 May 2019 was a correction
to the certification of the amount of liquidated damages on the basis that the proper
date for practical completion was always 27 October 2016. It did not change the
number of days extension that had been certified previously and was not a correction
to the date for practical completion.
[862] In respect of the issue of admissible evidence, the defendant relies on the liquidated
damages certificate issued by the Superintendent on 20 May 2019 that was admitted
into evidence for a hearsay purpose and was not objected to by the plaintiff. The
certificate relevantly states:
“Our certification of liquidated damages issued on 9 March 2017
applied a 5 day working week to the calculation of liquidated
damages. We are now aware that this was issued in error and that a
6 day working week applies.
…
A total of 44.5 business days were approved as at 6 October 2016.
Applying a 5 day working week, the date for practical completion
was calculated as 10 November 2016. Correctly applying a 6 day
working week, an additional approved EOT falls on each consecutive
Saturday such that the adjusted date for practical completion was 27
October 2016.”299
[863] There is some logic in the defendant’s approach in respect of the extension of time
being in respect of time. An extension is granted in respect of days delay to the work
under the Contract in accordance with clause 34.3. Applying the definition of “date
for practical completion” the adjusted date is the date “resulting … therefrom” the
extension of time.
[864] Extensions of time have been granted and the number of days previously granted is
not in dispute. It is the identification of the “date” resulting from the extensions which
is relevant. The two different dates arise from a counting error – determined by
whether Saturdays are included in a work week.
[865] The difficulty with the defendant’s claim arises from how the defendant is seeking to
correct the error.
[866] On 9 March 2017, the Superintendent certified the amount of liquidated damages
pursuant to clause 34.7. This used the date for practical completion of 10 November
299 PRO.060.001.0095.
-- 137 of 210 --
138
2016 and calculated the period of 113 days for the purposes of calculating the amount
of liquidated damages. This notice did not purport to certify the date for practical
completion and clause 34.7 did not give the Superintendent power to do so.300
[867] Based on this certification by the Superintendent, the certified amount of liquidated
damages was deducted from amounts due to the plaintiff for Progress Claim No 24
and the defendant set-off that sum.
[868] On 20 May 2019, the Superintendent sought to correct the error by issuing a further
progress certificate pursuant to clause 37.2. Pursuant to clause 37.2 a progress
certificate is to set out the “calculations employed to arrive at the amount which is
due from the Principal or the Contractor”, including amounts the Principal may be
entitled to deduct pursuant to the Contract.
[869] The final paragraph of clause 37.2 contains a power for the Superintendent to issue a
further progress certificate correcting any error in a previous progress certificate.
[870] This provision in clause 37.2 may assist if there was an error on the face of the
progress certificate itself: for example, if there had been a transcription error between
the amount certified as payable as liquidated damages in the Superintendent’s
certificate dated 9 March 2017 and the figure set-off or deducted in the progress
certificate on 13 or 20 March 2017. Clause 37.2 may assist in correcting the incorrect
figure to the correct figure.
[871] The defendant seeks to deploy the error correction provision in clause 37.2 to in effect
correct the certification of the amount of liquidated damages due and payable. But
that certification is done under clause 34.7 of the Contract: a completely different
provision in the Contract. Clause 34.7 provides:
“If WUC does not reach practical completion by the date for practical
completion, the Superintendent shall certify, as due and payable to
the Principal, liquidated damages in Item 29 for every day after the
date for practical completion to and including the earliest of the date
of practical completion … ”
[872] Clause 34.7 of the Contract provides a mechanism to adjust the amount of liquidated
damages if an extension of time is granted after the liquidated damages have been
paid or set-off: the amount is to be repaid. This mechanism does not assist in the
current circumstances.
[873] Clause 34.7 does not include any provision for an adjustment in the amount of
liquidated damages calculated as a result of an error by the Superintendent.
[874] The purported correction of the progress certificate on 20 May 2019 did not operate
to correct the underlying certification of the amount of liquidated damages due and
payable by the plaintiff to the defendant. The amount stated in the 9 March 2017
certification is the amount that remains due and payable. It has not been altered.
[875] In these circumstances, the defendant’s claim for additional liquidated damages based
on the error in the calculation of the date for practical completion must fail.
300 PRO.001.001.1749.
-- 138 of 210 --
139
INTEREST
[876] The plaintiff claims an entitlement to interest at the rate prescribed by s 67P of the
Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act).
Schedule Eight to the Amended Statement of Claim sets out the interest on the
amounts claimed by the plaintiff.
[877] Section 67P of the QBCC Act provides:
“(1) This section applies if—
(a) the contracting party for a building contract is required to
pay an amount (the progress amount) to the contracted
party for the building contract; and
(b) the progress amount is payable as the whole or a part of
a progress payment; and
(c) the time (the payment time) by which the progress
amount is required to be paid has passed, and the progress
amount, or a part of the progress amount, has not been
paid.
(2) For the period for which the progress amount, or the part of the
progress amount, is still unpaid after the payment time, the
contracting party is also required to pay the contracted party
interest at the penalty rate, as applying from time to time, for
each day the amount is unpaid.
(3) In this section—
penalty rate means—
(a) the rate made up of the sum of the following—
(i) 10% a year;
(ii) the rate comprising the annual rate, as published
from time to time by the Reserve Bank of Australia,
for 90 day bills; or
(b) if the building contract provides for a higher rate of
interest than the rate worked out under paragraph (a)—
the higher rate.”
[878] Alternatively, the plaintiff claims an entitlement to interest on the rate prescribed by
the Contract. Item 35 of Annexure Part A of the Contract provides an interest rate of
10 per cent per annum as the interest rate on overdue payments, pursuant to clause
37.5.
[879] Clause 37.5 states:
“Interest in Item 35 shall be due and payable after the date of default
in payment.”
-- 139 of 210 --
140
[880] The plaintiff proposes that further submissions be made as to specific amounts
payable by way of interest following the decision of the Court in respect of liability
and quantum.
[881] The defendant also proposes that further submissions should be made with respect to
the amounts payable by each party for interest after the Court has determined liability
and quantum on the claim and counterclaim.
[882] In respect of the counterclaim, the defendant claims interest under s 58 of the Civil
Proceedings Act 2011 (Qld).
[883] Directions will be made to provide for further submissions from both parties,
including submissions on the appropriate rate of interest arising out of the findings
on liability and quantum in these reasons.
NEXT STEPS
[884] Once the parties have had an opportunity to consider these reasons, the parties are to
confer to agree on a timetable for directions on the following:
(a) the parties confer and agree on the headings and structure (agreed form) of
further submissions to be provided as to the appropriate orders to be made in
light of these reasons.
(b) each party is to provide further written submissions in the agreed form, not
more than 25 pages (including attachments).
[885] The draft directions should be provided to my Associate. If draft directions cannot
be agreed, then each party is to provide draft directions and a brief explanation for
the disagreement.
[886] If the parties consider that any additional findings of fact are required at this stage,
these should be identified in the written submissions. The written submissions should
also address interest and costs.
-- 140 of 210 --
141
ANNEXURE A – MECHANICAL VARIATION, COSTS, DELAY,
EXTENSION OF TIME AND LIQUIDATED DAMAGES
Plaintiff’s claim for costs of carrying out the Mechanical Variation
[887] If I am wrong about the construction of the Contract and the notice dated 11 August
2016 constitutes a direction for a variation in respect of the mechanical works within
the meaning of clauses 1 and 36 of the General Conditions, then it is necessary to
consider whether the plaintiff would be entitled to the costs of the variation and also,
whether it would be entitled to an Extension of Time (EOT).
[888] The plaintiff claims the costs of the variation, an EOT and delay damages.
[889] The defendant accepts that if the Mechanical Direction was a direction to undertake
a variation then the plaintiff would be entitled to the cost component of the variation.
However, the defendant does not accept that the plaintiff would be entitled to an EOT
and delay damages.
[890] There are three questions in the list of issues which are relevant to these
considerations, questions six, 13 and 18. Question six is as follows:
“6. In respect of the alleged Mechanical Delay:
(a) the extent to which, if at all, the Mechanical Direction
caused a delay to practical completion [SOC [27]; Def
[26]; R [28]]; and, if so
(b) to what extent, on a proper construction of the Contract,
the plaintiff was entitled to an extension to the Date for
Practical Completion [SOC [30]; Def [26], [27]; R [28],
[29]]; and
…”
[891] The defendant has identified an additional question relevant to this issue which is not
agreed to by the plaintiff:
“(c) whether the plaintiff’s extension of time claim dated 28
October 2016 or otherwise complied with the requirements in
clause 34.3 of the Contract [SOC [29]; Def [26(c)]; R [28(c)]]”.
[892] Questions 13 and 18 are agreed as follows:
“13. In respect of the alleged Mechanical Variation [SOC [9]; Def
[10]]:
(a) the price of the work performed by the plaintiff in
carrying out the alleged Mechanical Variation; and
(b) whether, (and if so to what extent) the plaintiff is entitled
to costs of delay as part of the price of the Variation [SOC
[32]; Def [27]].
…
-- 141 of 210 --
142
18. In respect of the alleged delay to Practical Completion:
(a) the extent to which, if any, the costs claimed were:
(i) costs incurred by the plaintiff by reason of the
delay; and
(ii) costs which the plaintiff is entitled to recover on a
proper construction of the Contract, [SOC [32]; Def
[27]];
(b) the extent to which, if any, the defendant is entitled to
have deducted, from amounts owing to the plaintiff,
amounts for liquidated damages [SOC [42], [48]; Def
[29], [31]; R [31], [33]].”
[893] On the basis that the Mechanical Direction was a direction to the plaintiff to undertake
a variation in respect of the mechanical works, within the meaning of clause one and
clause 36 of the Contract (Mechanical Variation), it is necessary to consider the terms
of clause 36. Clause 36 states as follows:
“36.1 Directing variations
The Contractor shall not vary WUC except as directed in
writing.
The Superintendent, before the date of practical completion,
may direct the Contractor to vary WUC by any one or more of
the following which is nevertheless of a character and extent
contemplated by, and capable of being carried out under, the
provisions of the Contract (including being within the
warranties in subclause 2.2):
(a) increase, decrease or omit any part including the
omission of any part of WUC with a view to retaining a
third party to perform that part of WUC either prior to or
after the date of practical completion (with no liability to
compensate the Contractor for any loss of profit);
(b) change the character or quality;
(c) change the levels, lines, positions or dimensions;
(d) carry out additional work;
(e) demolish or remove material or work no longer required
by the Principal.
The Principal shall only be liable to the Contractor for the price
of a variation calculated in accordance with subclause 36.4 or
for an EOT for a variation where either:
(f) the direction to perform the variation given by the
Superintendent is in writing, expressly states that the
direction constitutes a direction for a variation and
identifies the work the subject of the direction; or
-- 142 of 210 --
143
(g) before performing the variation and in any event within
5 business days of receiving the direction to perform the
variation, the Contractor has given the Superintendent a
notice in writing which identifies:
(i) the date the direction was given:
(ii) whether the direction was given orally or in
writing;
(iii) the substance of the direction and, if it was in
writing, a copy of the direction must be attached;
(iv) the approximate cost of the variation including a
detailed breakdown calculated in accordance with
subclause 36.4;
(v) whether a claim for an EOT will be made as a
consequence of the variation and if so, an estimate
of the period; and
(vi) where the variation relates to the design documents
or the Principal's project requirements, by
identifying the relevant requirement and the change
to that requirement.
(h) Except where the Contractor is entitled to make a claim
under this subclause 36.1, the Contractor shall have no
entitlement as a consequence of complying with a
direction for a variation.
(i) Where the Contractor wishes to make a claim for an EOT
as a consequence of a variation, in addition to the notices
it is required to give under this subclause 36.1, the
Contractor shall give all notices required under clause
34.
…
36.4 Pricing
The Superintendent shall, as soon as possible, price each
variation using the following order of precedence:
(a) prior agreement;
(b) applicable rates or prices in the Contract;
(c) rates or prices in a schedule of rates or schedule of prices,
even though not Contract documents, to the extent that it
is reasonable to use them; and
(d) reasonable rates or prices, which shall include an amount
equivalent to the percentage set out in Item 32A for profit
and overheads,
and any deductions shall include an amount equivalent to the
percentage set out in Item 32B for profit but not overheads,
-- 143 of 210 --
144
That price shall be added to or deducted from the contract
sum.”
[894] Clause 36.4 sets out the price of a variation for which the principal is liable.
[895] Expert reports have been prepared on behalf of both parties and provided to the Court
in relation to calculating the value of the Mechanical Variation in accordance with
clause 36.4 of the Contract. Mr Watson has prepared a report on behalf of the plaintiff
and Mr Hardiman has provided a report on behalf of the defendant.
[896] Mr Bell has also provided an expert opinion in relation to the calculation of delay,
costs and delay damages. This issue is dealt with by Mr Hardiman on behalf of the
defendant.
[897] The quantum of the plaintiff’s claim in respect of the Mechanical Variation is the total
of $2,076,392.25 (plus GST) being:
(a) $1,074,577.25 (plus GST) in respect of the costs of the Mechanical Variation;
and
(b) $1,001,815 (plus GST) being delay damages as a consequence of the critical
delay caused by the Mechanical Variation, on the assumption of 117 days of
critical delay.301
[898] The defendant submits that the plaintiff is entitled to:
(a) a maximum of $831,833.36 (plus GST) for the cost of the variation;
(b) the return of liquidated damages at a daily rate equal to the extension of time
granted; and
(c) Nil delay damages.
[899] It is convenient to firstly deal with the costs of the variation first, followed by the
claim for an EOT and lastly, delay damages.
Costs of the variation
[900] Helpfully, the experts have prepared a joint report and this highlights the areas of
difference between the two positions.302
[901] The plaintiff relies on the 11 August 2016 direction to undertake the work outlined in
it pursuant to clause 36.1. Further, the plaintiff relies on a notice issued by it pursuant
to clause 36.1(g) of the Contract.303 This notice was given before performing the
work and was given within five business days of receiving the direction. This notice
identified the approximate cost of the Mechanical Variation as required by clause
36.1(g).
301 See plaintiff’s written closing submissions at [6]-[7].
302 Attachment A to EXP.001.001.2176 Joint Expert Report pp 2-8.
303 BUI.001.001.25031.
-- 144 of 210 --
145
[902] It is not contentious that if the Mechanical Direction was a variation pursuant to clause
36.1 of the Contract the requirements of clause 36.1 have been complied with,
therefore, an entitlement to an assessment of the costs of the Mechanical Variation
pursuant to clause 36.4 of the Contract would arise.
[903] Both parties agree that the relevant subparagraph of clause 36.4 is subparagraph (d)
that the valuation is to be priced using “reasonable rates or prices”.
[904] The plaintiff in its submissions has helpfully identified that the difference between
the experts’ assessment is the sum of $242,743.89.304 The differences between Mr
Watson and Mr Hardiman are in relation to the following items:
“(a) Credit $8,984.27 – Credit contract works not required or
incorporated ($211,000 vs $202,015.73);
(b) $103,147.68 – Additional works – 3 pipe mechanical system,
upgrading current, pipework, FCUs, condensers, heat exchange
units, electrical and ductwork, and BWIC ($1,010,368.78 vs
$907,221.10);
(c) $34,576.50 – demolition ($39,456 vs $4,879.50);
(d) $42,498.23 – ceilings and partitions ($47,305.18 vs $4,808.96);
(e) $6,685.73 – tiling ($6,685.73 vs nil);
(f) $8,400 – electrical ($11,125 vs $2,725);
(g) $516.19 – fire ($1,400 vs $883.81);
(h) $1,695.24 – hydraulics ($2,800 vs $1,104.76);
(i) $31,487.57 – BWIC (Builder’s work in connection)
($48,902.26 vs $17,414.69) (relating to x-ray scanning, crane
hire and road closure);
(j) $179.69 – builder’s profit and overheads on deductions (2%)
($4,220 vs $4,040.31);
(k) $22,900.71 – builder’s profit & overheads on additions (10%)
($117,254.30 vs $94,353.58).”305
[905] It is necessary to consider each of these in turn.
Credit – contract works not required or incorporated due to Mechanical Variation
[906] This concerns a credit allowance for works not required because of the Mechanical
Variation. Mr Watson arrives at a credit of $211,000. Mr Hardiman arrives at a credit
of $202,015.73.
[907] In its written closing submissions, the plaintiff has indicated that it is prepared to
accept the credit proposed by Mr Hardiman for the purposes of the quantification of
the Mechanical Variation.306 That is the amount of $202,015.73.
304 Plaintiff’s written closing submissions at [158]-[159].
305 Plaintiff’s written closing submissions at [159].
306 Plaintiff’s written closing submissions at [164].
-- 145 of 210 --
146
[908] Mr Hardiman’s assessment is based on an approach of going to market prices and
applying them to measured quantities to arrive at an objectively reasonable sum.
[909] In the circumstances of the concession by the plaintiff and the fact that there is no
evidence to suggest that Mr Hardiman’s assessment is other than a reasonable
approach, I find the negative valuation in the amount of $202,015.73.
Additional works – three-pipe mechanical system
[910] The next item is described as “[a]dditional Works – 3 Pipe Mechanical System –
upgrading current pipework, FCUs, Condensers, Heat Exchange Units, Electrical and
Ductwork, and BWIC”.
[911] Mr Watson’s assessment for this item is $1,010,368.78 and Mr Hardiman’s is
$907,221.10. The difference between the experts is $103,147.68.
[912] This work relates to the actual work required to convert the two-pipe VRF system to
a three-pipe VRF system.
[913] The original VP57 claim was in the amount of $963,800. Mr Watson has undertaken
an assessment based on the original VP57.
[914] In respect of this item Mr Hardiman has taken the approach which is described as the
“Rawlinson’s approach”, namely, going to market prices and applying them to
measured quantities to arrive at an objectively reasonable sum. The defendant
submits that this is a more robust approach.
[915] By comparison, Mr Watson has used the amounts in the plaintiff’s VP57, which in
turn was based on quotations obtained from Batec (at the time the variation proposal
was prepared).
[916] In particular, reliance is placed on a quotation from Batec dated 17 October 2016.307
That quotation contained a number of “lump sum” figures for particular items which
have been used by Mr Watson in respect of specific work items. Mr Watson in his
analysis identifies that there were some adjustments made between that final
quotation and VP57. It is on this basis that Mr Watson has assumed that the costs set
out in VP57 were the amounts ultimately agreed between the plaintiff and Batec for
the supply of those particular items.
[917] Mr Watson’s report explains his basis for this approach, including that the assessment
of a reasonable rate or price must have regard to the circumstances under which the
works are undertaken. In the circumstances that this particular variation arose, one
relevant circumstance is that obtaining competitive quotations was not really a viable
option given that the work had to proceed as expeditiously as possible. It is in these
circumstances that it is argued that using the rates quoted by the subcontractor who
was onsite was appropriate.
[918] The plaintiff submits that Mr Hardiman’s approach and arriving at rates and quantities
to arrive at a valuation is not appropriate. In particular it submitted that this approach
does not take into account the fact that the conversion of the two-pipe VRF system to
307 BUI.001.003.58590; BUI.001.003.058591.
-- 146 of 210 --
147
a three-pipe VRF system was not typical, had to occur quickly and in the middle of
construction happening around it, as it was a congested construction site that was
nearing completion. A further relevant practical consideration pointed to by the
plaintiff was that it could only really be completed by the mechanical contractor who
was already on site, that is Batec.
[919] It is in these particular circumstances that the plaintiff submits that Mr Hardiman
identifying alternative prices that may be cheaper or other construction
methodologies does not reflect the realities of the work that needed to be done.
[920] The most substantive difference between the two experts is the approach to the
valuation of labour. Mr Watson adopts a figure of $267,520 for labour. The original
VP57 included a claim of $178,000 in respect of labour.
[921] Mr Hardiman adopts a value for labour of $78,119.04, but it needs to be
acknowledged that this is only a portion of the labour cost. This is because at another
place in the valuation undertaken by Mr Hardiman, a rate is used which covers not
only the supply of a new refrigerant pipe, insulation and pipe supports but also
includes the labour for the installation. The amount for that item totals $224,369.77
but does not identify the portion that relates to labour. This is to be contrasted with
the figure for the pipe identified by Mr Watson which is $134,000 but does not include
labour.
[922] An issue came up during the cross-examination of Mr Hardiman in relation to this
calculation of the supply of a new refrigerant pipe, insulation and pipe supports.
During the questioning by Counsel for the plaintiff, Mr Hardiman was taken to
schematic drawings and was asked questions that appeared to infer that Mr
Hardiman’s approach was incorrect as he had not factored in that certain pipes needed
to be removed which may have previously been installed for the two-pipe system and
to, in effect, install three-pipes. Objections were taken to this approach at the time
and I gave an indication that out of fairness to the witness, the basis for the
questioning should be clarified. This invitation to do so was not taken up.
[923] Mr Cook’s witness statement is the evidence relied upon by the plaintiff in respect of
the work that was undertaken. There is no suggestion in Mr Cook’s statement that
the existing two-pipe system that had been partially installed had to be removed
entirely as part of this process. I do not make any findings adverse to Mr Hardiman’s
evidence in this regard based on the cross-examination that occurred in respect to this
aspect of the valuation exercise.
[924] The defendant submits that Mr Watson’s amount for labour of $267,520 is an
unreasonable overestimate of the cost. The defendant points to the following
particular matters as evidence of this:
(a) On 4 August 2016, Batec gave a price breakdown for a three-pipe air
conditioning system which included $75,000 for the labour component.308
(b) On 15 September 2016, a second estimate had come from Batec which
increased the labour to $88,000 for the installation of a three-pipe system.309
308 WIT.001.001.0002 at p 0045 [268]; BUI.001.003.61318.
309 BUI.001.002.44139.
-- 147 of 210 --
148
(c) Mr Cook went back to Batec and asked it to revisit the pricing because he did
not think the labour allowance would be sufficient for the work required.310
(d) On 15 September 2016, a third estimate was received which increased the
labour to an amount of $171,000.311
(e) Mr Cook, in his witness statement, maintained his view that the figure in VP57
was reasonable and fair for labour.312
[925] Mr Watson’s current valuation of the labour component is approximately $90,000
greater than the third estimate received from Batec in September 2016.
[926] Mr Watson’s figure is arrived at based on the general statements contained in Mr
Cook’s witness statement. It does not involve any detailed analysis of
contemporaneous documents such as timesheets or site diaries.
[927] The difficulty is also compounded by the fact that Mr Cook stands by his estimate of
$178,000 for labour but it is his statement which is relied upon by Mr Watson to
justify the calculation of the higher value.
[928] The criticisms made about the labour figure identified by Mr Watson are justified.
[929] At paragraph [234] of the defendant’s written closing submissions an alternative
position is proposed if I am satisfied that it is appropriate to use Mr Watson’s figure
as a starting point. It is proposed that the overall figure should be reduced to
$911,360.78. This adopts the labour figure of $178,000 calculated by Mr Cook. It is
submitted that while this is a broad approach, it reflects the unsatisfactory nature of
Mr Watson’s evidence and the unreasonableness of his calculation of the labour costs.
[930] Given the concerns raised in relation to the estimate of the labour costs in Mr
Watson’s calculation, this compromise approach appears to arrive at a reasonable
value for this item. It considers the difficulties of evaluating and comparing the
labour costs of Mr Hardiman where there is only a portion which is direct labour costs
and the other portion is covered in the supply and installation rate in relation to the
new refrigerant pipe.
[931] In these circumstances I find the amount in relation to this item is $911,360.78. This
takes into account Mr Watson’s concerns about the realities of the work being
undertaken on site and the need to undertake the work in a short timeframe but also
adjusts the overall figure to take into account the issues identified in relation to the
labour costs component.
Demolition
[932] As identified in the joint expert report, the amount in dispute in relation to this item
relates to the cost of demolition for levels seven to 12.
[933] Mr Hardiman arrives at a value of $4,879.50. Mr Watson arrives at a value of
$39,456. The differential is $34,576.50.
310 WIT.001.001.0002 at p 0045 [302].
311 BUI.001.003.62181.
312 WIT001.001.0002 at p 0064 [365].
-- 148 of 210 --
149
[934] It is common ground between the parties that the difference is largely explained by
the date used by each expert as the relevant date for the valuation. Mr Watson valued
the demolition as at 14 October 2016 and Mr Hardiman valued the demolition as at
26 August 2016.
[935] The 26 August 2016 date used by Mr Hardiman is based on the 11 August 2016 notice
having been given and that by the 23 August 2016 the decision of a three-pipe system
had been finalised. The date of 26 August 2016 is the first date after the Mechanical
Variation that photographic evidence of the progress of the works was available for
this analysis to be undertaken.313
[936] The plaintiff contends that the difference should be resolved in favour of the plaintiff
if the Court finds it was reasonable for the plaintiff to order the condensers on 14
October 2016. Conversely, the difference could be resolved in favour of the
defendant if the Court finds that the plaintiff should have done so immediately after
11 August 2016.
[937] Alternatively, the defendant contends that because of the 11 August 2016 Mechanical
Variation, the defendant should not have to pay for the construction works which
obviously would have to be demolished when the alternative system was ultimately
installed. In those circumstances, Mr Hardiman’s figure should be adopted.314
[938] I do not consider that the submission made by the plaintiff in respect of the timing of
the ordering of condensers is the critical issue. It is more persuasive that the direction
was given on 11 August 2016, the decision was finalised by 23 August 2016 and by
26 August 2016, there is evidence of the progress actually on site.
[939] Even if it was reasonable for the plaintiff not to order the condensers until 14 October
2016, it may not logically be consistent that it was reasonable for work to continue
where it was obvious that it would need to be demolished for the installation of the
alternative system, particularly where the design was already finalised by 23 August
2016. Further, even if the issue of the brand of the condenser was outstanding, it still
did not justify work being undertaken which would need to be later demolished to
undertake the installation of the alternative system.
[940] In these circumstances, I consider that the appropriate figure in relation to the
demolition costs is Mr Hardiman’s valuation, being $4,879.50.
Reinstatement works
Ceilings and partitions reinstatement
[941] This work relates to the reinstatement after demolition of the work. The difference
between the experts is $42,498.23. Mr Watson’s valuation is $47,305.18 and Mr
Hardiman’s valuation is $4,808.96.
[942] A similar issue arises here in relation to the date of assessment. Mr Watson assesses
the value as at 14 October 2016 and Mr Hardiman assesses the value as at 26 August
2016.
313 EXP.001.001.1621 at p 2148.
314 Defendant’s written closing submissions at [239].
-- 149 of 210 --
150
[943] For the reasons outlined above in relation to the demolition work, I consider that it is
not reasonable for the defendant to have to pay for reinstatement of work undertaken
after 26 August 2016, after which time the design of the three-pipe system had been
finalised and the relevant work inevitably had to be demolished.
[944] I find the cost of this item as that assessed by Mr Hardiman, $4,806.96.
Tiling reinstatement
[945] This item relates to the reinstatement of demolished tiling. Mr Watson’s value is
$6,685.73 and Mr Hardiman’s value is nil.
[946] The similar issue in relation to the date of assessment arises in relation to this
reinstatement. Where the reinstatement relates to work undertaken after 26 August
2016, at which time the design of the three-pipe system had been finalised, it is not
reasonable that the defendant be required to pay the costs associated with that work.
[947] The value for this item is nil.
Electrical reinstatement
[948] The electrical reinstatement is a different issue. Mr Watson values the work required
at $11,125 and Mr Hardiman values it at $2,725. This relates to reinstating fire
proofing for electrical penetrations.
[949] There appears to be some discrepancy between the submissions made by the plaintiff
and the defendant in relation to this item.
[950] The defendant identifies that Mr Watson agreed that the methodology applied by Mr
Hardiman was acceptable and refers to Transcript Day 11 page 59 lines 1-2. The
defendant points to the exchange between Mr Watson and the defendant’s counsel at
Transcript Day 11 page 63 commencing at line 42 as supporting Mr Watson
ultimately agreeing with the approach of Mr Hardiman. That is, Mr Watson and Mr
Hardiman are effectively in agreement of the valuation of $2,075 as shown on page
seven of Attachment A to the joint report.315
[951] Conversely, the plaintiff’s submissions maintain that Mr Hardiman’s methodology
for valuing this item should not be accepted and that Mr Watson’s assessment should
be allowed.
[952] Mr Watson had previously allocated a value of $8,400 in respect of the costs of
reinstating fire proofing for electrical penetrations. Mr Hardiman allowed nil for that
component. Given the exchange at trial, it appears that the reasonable cost in relation
to this item should be the amount of $2,075, which takes into account the reduction
of $8,400 from Mr Watson’s figure.
[953] The value of this item is $2,075.
315 Defendant’s written closing submissions at [243]-[244].
-- 150 of 210 --
151
Fire ratings reinstatement
[954] Mr Watson’s valuation of this item is $1,400 and Mr Hardiman’s valuation is
$883.81. The difference between them is an amount of $516.19.
[955] The plaintiff’s submission in relation to this item is that Mr Watson has adopted the
plaintiff’s claim rate whereas Mr Hardiman has used Rawlinson’s approach.
[956] The plaintiff further relies on its submissions in relation to Mr Watson’s assessment
being reasonable rates. The plaintiff also relies on its arguments about the applicable
rates being those which are a reasonable rate in the particular circumstances that the
works are being undertaken. In this regard, the plaintiff repeats its arguments in
relation to the additional works undertaken in respect of the installation of the three-
pipe system.
[957] Conversely, the defendant contends that this item should be assessed in the same
manner as the electrical reinstatement works. That is, the amount relates to the
100mm sleeve issue and once that amount is taken into account then effectively Mr
Hardiman and Mr Watson are in agreement as to the figure of $883.81.
[958] In these circumstances, and given the evidence that was given at trial by Mr Watson,
I consider that the assessment of the reasonable amount for this item is $883.81
consistent with the figures shown at page seven of Attachment A to the joint report.
[959] The value of this item is $883.81.
Hydraulics reinstatement
[960] In relation to this item, Mr Watson arrived at a value of $2,800 and Mr Hardiman
arrived at a value of $1,104.76. The difference between them is $1,695.24.
[961] The plaintiff contends that the difference is explained by Mr Watson adopting the
plaintiff’s claim rate whereas Mr Hardiman used the Rawlinson’s approach. In this
regard, the plaintiff relies on its previous submissions in relation to the
appropriateness of using a rate in the particular circumstances of the work being
undertaken.
[962] Conversely, the defendant contends that this item turns on whether 26 August 2016
or 14 October 2016 is the appropriate date from which to quantify this work. If the
appropriate date is 26 August 2016 then the figure should be $1,104.76. If it is 14
October 2016, the amount should be Mr Watson’s figure of $2,800.
[963] Consistent with the approach taken in relation to the previous reinstatement work, by
26 August 2016 the design for the three-pipe system had been finalised and it is not
reasonable that work undertaken after that date, which then had to be demolished and
reinstated, should be paid for by the defendant. In the circumstances, the appropriate
figure is that of Mr Hardiman being $1,104.76.
BWIC
[964] In relation to this item, Mr Watson has allowed the sum of $48,902.26. Mr Hardiman
has allowed the sum of $17,414.69. The difference between the experts is a sum of
$31,487.57.
-- 151 of 210 --
152
[965] This item includes road closure for craneage, craneage to lift plant to roof,
mobilisation and de-mobilisation, traffic control during crane days and x-ray scanning
core holes. Each of these items will need to be considered further.
Item 128 – “Core holes – 200mm through to 210mm post tension slab"
[966] There are two items within this item which are agreed between the experts. In relation
to Item 128 “Core holes – 200mm – through to 210mm post tension slab”, the experts
agree an amount of $5,544.
Item 127 – “Core holes – 200mm through to 700mm post tension slab”
[967] In relation to Item 127 “Core holes – 200mm – through to 700mm post tension slab”,
the experts agree an amount of $3,354.
Item 132 – “Road closure for craneage”
[968] In respect of Item 132 “Road closure for craneage”, Mr Hardiman arrived at a figure
of $235 and Mr Watson arrived at a figure of $2,600. The defendant submits that
there is a rate in the Contract for this sub-item and that where it exists it should be
used. Mr Watson agreed with this.316
[969] The defendant contends that craneage should only be needed for one day.
[970] However, the plaintiff points out that Mr Hardiman agreed in cross-examination that
it was not unreasonable to allow for a two day road closure to allow for things
including weather or other contingencies.
[971] In the circumstances, it would be appropriate to allow two days at Mr Hardiman’s
figure which would be an amount of $470.
Item 129 – “Craneage to lift plant to roof”
[972] In respect of Item 129 “Craneage to lift plant to roof”, there is a similar dispute as to
whether one or two days should be allowed. Mr Hardiman expresses the view that
the Contract sum includes craneage for one day and this had not been expended
because the original units had not been delivered to site. In these circumstances, Mr
Hardiman allows one additional day.
[973] Mr Watson has used two crane days. This results in the difference of opinion in
respect of this component.
[974] Mr Hardiman’s figure is $2,144 based on one day and lifting of 12 additional units.
[975] Mr Watson provides a figure of $13,600 for this item.
[976] The defendant also points out that only six of the 12 additional condensers had to be
lifted to the rooftop, whereas the other six were to be lifted to level one.
[977] Under cross-examination, Mr Watson agreed that without restrictions, it was possible
that the lift could occur in one day.
316 T11-36, L43-44.
-- 152 of 210 --
153
[978] In the circumstances, I consider that an appropriate value in relation to this item would
be the adoption of Mr Hardiman’s rate of $2,144, but allowing a two day lift period
to take into account various contingencies and the fact that it needed to be done in the
particular circumstances of the work being undertaken on the site. While the cost of
lifting the original 12 units was already covered in the original Contract sum, the fact
that this was additional work and was being done in an expedited process, the
allowance of two days to complete this work would be reasonable in all of the
circumstances.
[979] Accordingly, the value in relation to Item 129 is $4,288.
Item 130 – “Mobilisation and de-mobilisation”
[980] In respect of Item 130 Mr Hardiman’s position is that nil should be allowed on the
basis that the original Contract sum included mobilisation and de-mobilisation of
equipment to lift the original 12 units. Mr Watson was of the opinion that this may
depend on whether the original condensers were to be lifted by a fixed tower crane or
a mobile crane. If it was the latter there would be no additional cost. However, Mr
Watson was unable to assist further in relation to the resolution of the costs with
respect to this issue.
[981] In the circumstances, where this was included in the original Contract sum and Mr
Watson is not able to conclusively address this issue given that he did not have access
to contemporaneous documents, it is appropriate that nil be awarded in relation to
Item 130.
Item 131 – “Traffic control during crane days”
[982] The defendant contends that the amount of $2,212.59 should be awarded on the basis
of Mr Hardiman’s figure and only one day being necessary.
[983] There is a difference in rates between Mr Hardiman and Mr Watson. Mr Hardiman
has adopted an average value based on the plaintiff’s claimed rate and a preliminary
cost. It is difficult to understand Mr Hardiman’s basis for arriving at the rate.
[984] In the circumstances, I consider it reasonable to adopt the rate identified by Mr
Watson and to allow for two days consistent with my previous findings. In the
circumstances, the appropriate amount for Item 131 is $5,850.36.
Item 126 – “X-ray scanning core holes”
[985] In relation to Item 126 “X-ray scanning core holes”, Mr Watson has arrived at a figure
of $8,500 and Mr Hardiman, a figure of $3,925.10.
[986] Mr Watson’s figure adopted the plaintiff’s claim amount and Mr Hardiman sought an
independent quotation at or about the time of preparing his report.
[987] The plaintiff criticises Mr Hardiman’s use of a rate obtained years after the Spring
Hill Hotel was completed and also identifies that the rate is subject to the same
difficulties previously addressed in the plaintiff’s submissions in that it does not take
into account the practical realities of the particular circumstances of the work being
undertaken on site. Further, it is contended by the plaintiff that Mr Hardiman did not
in fact know what was required to perform the x-ray scanning.
-- 153 of 210 --
154
[988] For example, one of the differences between the two experts was the time allowed to
move from hole to hole. Mr Watson assessed 90 minutes per hole and Mr Hardiman
assessed a 30 minute time estimate with 15 minutes to move from hole to hole.
[989] However, the plaintiff points to the cross-examination of Mr Hardiman where he
agreed that he did not have a proper basis to conclude that each hole could be x-rayed
in 45 minutes. Further, it was established in the cross-examination that he did not
know how large the machine was, how it was attached or how the scan was
performed. In all of these circumstances, the plaintiff contends that it was reasonable
to use the quote obtained by the plaintiff of $250 per scan.
[990] While there is considerable uncertainty in relation to Item 126, I consider that the
figure of Mr Watson of $8,500 is reasonable in the circumstances.
Summary
[991] The following is a table summarising the findings in respect of the quantification of
the Mechanical Variation. As some of these figures have been recalculated, some of
the figures will need to be further calculated in order to get to the ultimate figure for
quantum in relation to the Mechanical Variation.
Item Amount
Credit – contract works not required or incorporated due
to Mechanical Variation
-$202,015.73
Additional Works - Three-Pipe Mechanical System -
upgrading current pipework, FCUs, Condensers, Heat
Exchange Units, Electrical and Duct Work and BWIC
$911,360.78
Demolition $4,879.50
Ceilings and Partitions (reinstatement work) $4,806.96
Tiling (reinstatement work) NIL
Electrical $2,075
Fire $883.81
Hydraulics $1,104.76
BWIC [TBA]
Consultants (agreed between experts) $4,500.00
Builders Profit & Overheads on Deductions (2%) [TBA]
Builders Profit & Overheads on Additions (10%) [TBA]
Total [TBA]
[992] For completeness, the parties are invited to undertake these additional calculations so
that the summary of the quantification of the Mechanical Variation can be completed.
[993] Once the final figure is calculated, this will be the answer in respect of question 13(a),
namely the price of the work performed by the plaintiff in carrying out the alleged
Mechanical Variation.
-- 154 of 210 --
155
Delay and the Mechanical Variation
[994] There are two further claims that need to be considered in respect of the Mechanical
Variation: is the plaintiff entitled to an extension of time and is the plaintiff entitled
to any delay damages?
[995] The first step is to consider whether the plaintiff is entitled to an extension of time as
a result of the Mechanical Variation and, if so, what extension of time should be
granted?
[996] If the plaintiff is entitled to an extension of time, it is then necessary to consider
whether the plaintiff is entitled to delay damages and the amount of any delay
damages?
[997] Lastly, it is necessary to consider the effect of any extension of time on the liquidated
damages which the defendant has withheld.
Is the plaintiff entitled to an extension of time due to the Mechanical Variation?
[998] There are a number of aspects to be considered, including:
(a) Clause 34, and in particular clause 34.3, and how it applies in the current
circumstances.
(b) The factual circumstances of the Mechanical Variation and some factual
matters that occurred after the Mechanical Direction was given.
(c) The expert evidence analysing the delay and the differences in approach.
[999] Clause 34 of the General Conditions deals with time and progress. Clause 34 states
as follows:
“34.1 Progress
The Contractor shall ensure that WUC reaches practical completion
by the date for practical completion.
34.2 Notice of delay
A party becoming aware of anything which will probably cause delay
to WUC shall promptly give the Superintendent and the other party
written notice of that cause and the estimated delay.
34.3 Claim
The Contractor shall be entitled to such EOT for carrying out WUC
(including reaching practical completion) as the Superintendent
assesses, if:
(a) the Contractor is or will be delayed in reaching practical
completion by a qualifying cause of delay;
(b) the Contractor gives the Superintendent, within 14 days of
when the Contractor should reasonably have become aware of
that qualifying cause of delay occurring, a written claim for an
-- 155 of 210 --
156
EOT evidencing the facts of causation and of the delay to WUC
(including extent);
(c) the qualifying cause of delay was beyond the reasonable control
of the Contractor and affects the critical path of the activities
required to complete WUC as shown on the approved
construction program;
(d) the Contractor or others for whom it is responsible did not
contribute to the cause;
(e) the Superintendent is satisfied that WUC was actually delayed;
(f) the Contractor has taken all reasonable steps to mitigate the
effect of the delay; and
(g) if the qualifying cause of delay is an industrial action or
industrial dispute, the industrial action or industrial dispute:
(i) is either:
(A) of a state-wide or nation-wide character and is not-
specific to the site or the Contractor; or
(B) an illegal industrial action;
(ii) affects WUC; and
(iii) has not been caused by an act or omission of the
Contractor on any other site on which the Contractor is
engaged.
If further delay results from a qualifying cause of delay evidenced in
a claim under paragraph (b) of this subclause, the Contractor shall
claim an EOT for such delay by promptly giving the Superintendent a
written claim evidencing the facts of that delay.
…
34.5 Extension of time
Within 14 days after receiving the Contractor’s claim for an EOT, the
Superintendent shall give to the Contractor and the Principal a written
direction evidencing the EOT so assessed. If the Superintendent does
not do so, there shall be a deemed assessment and direction for an EOT
as claimed.
Notwithstanding that the Contractor is not entitled to or has not
claimed an EOT, the Superintendent may at any time and from time to
time before issuing the final certificate direct an EOT. The
Superintendent is under no obligation to exercise this discretion
reasonably, fairly or for the benefit of the Contractor.
…
-- 156 of 210 --
157
34.7 Liquidated damages
If WUC does not reach practical completion by the date for practical
completion, the Superintendent shall certify, as due and payable to the
Principal, liquidated damages in Item 29 for every day after the date
for practical completion to and including the earliest of the date of
practical completion or termination of the Contract or the Principal
taking WUC out of the hands of the Contractor.
If an EOT is directed after the Contractor has paid or the Principal has
set off liquidated damages, the Principal shall forthwith repay to the
Contractor such of those liquidated damages as represent the days the
subject of the EOT.
The Contractor acknowledges that the liquidated damages provided
for in this subclause are a genuine pre-estimate of the Principal’s loss
and not a penalty.
If Item 29 is not completed or completed by words which indicate that
liquidated damages shall not apply to the Contract (whether by the use
of the words ‘nil’, ‘not applicable’ or otherwise), the Contractor shall
indemnify the Principal for any loss, damage, cost or expense suffered
or incurred by the Principal by reason of the Contractor’s delay in the
execution of WUC including the Contractor’s failure to bring WUC to
practical completion by the date for practical completion.
If the liquidated damages provide for in this subclause 34.7 are found
to be unenforceable for any reason, the Contractor shall indemnify the
Principal for any loss, damage, cost or expense suffered or incurred
by the Principal by reason of the Contractor’s delay in the execution
of WUC including the Contractor’s failure to bring WUC to practical
completion by the date for practical completion.
…
34.9 Delay damages
For every day the subject of an EOT for a compensable cause, the
Contractor shall be entitled to give the Superintendent a claim for
delay damages reasonably and necessarily incurred by the Contractor
by reason of that compensable cause. The Principal must pay the
amount of the delay damages certified by the Superintendent pursuant
to this subclause 34.9.
The maximum amount payable by the Principal to the Contractor for
every day the subject of an EOT for a compensable cause is the actual
cost incurred by the Contractor up to the maximum specified in Item
31A.
Nothing in this subclause 34.9 shall oblige the Principal to pay delay
damages for:
(a) the costs of delay which have already been included in the value
of a variation or any other payment under the Contract; or
-- 157 of 210 --
158
(b) any qualifying cause of delay which is not a compensable cause
of delay.
The amount payable by the Principal to the Contractor under this
subclause 34.9 is the agreed damages payable by the Principal to the
Contractor and is in full satisfaction of all claims which the
Contractor may make or bring against the Principal arising in
connection with all and any delay or disruption however caused or
encountered by the Contractor in the execution of WUC.
…”
[1000] The defendant contends that if the Mechanical Direction was a direction to undertake
a variation, the plaintiff would be entitled to the cost of the variation but would not
be entitled to an extension of time. It is contended that while the Mechanical
Variation would be a qualifying cause of delay under clause 34.3, the plaintiff would
not be entitled to an extension of time for the following reasons:
(a) the plaintiff failed to give the Superintendent a written claim for an extension
of time within 14 days of reasonably becoming aware of the Mechanical
Direction;
(b) the plaintiff contributed to the cause of the delay by failing to provide shop
drawings of the mechanical system in breach of clauses 8.3 and 8.8 of the
Contract; and
(c) the plaintiff failed to take reasonable steps to mitigate the effect of the delay,
including by failing to order the additional plant it needed to comply with the
Mechanical Direction within a reasonable period of time.
[1001] The plaintiff’s position is that:
(a) The notice delivered on 26 August 2016 was within time.
(b) It was delayed in reaching Practical Completion by 117 days, until 7 March
2017.
(c) Mr Bell’s delay analysis should be preferred to Mr King’s analysis as he adopts
the correct methodology pursuant to the Contract, namely a prospective delay
analysis.
(d) Further, a number of assumptions relied upon by Mr King are not established.
For example, the plaintiff did not act unreasonably in not ordering the
mechanical plant for the conversion of the alternative proposal to a three-pipe
system immediately following the Superintendent’s instructions on 11 August
2016, 16 August 2016 and 17 September 2016.
[1002] If it is necessary to consider whether the plaintiff is entitled to an extension of time,
these reasons set out my findings in respect of the following issues which are in
dispute between the parties:
(a) Did the plaintiff give the Superintendent a written claim for an extension of
time within 14 days of reasonably becoming aware of the Mechanical Direction
as required by clause 34.3(b)?
(b) What is the correct delay analysis methodology pursuant to the Contract?
-- 158 of 210 --
159
(c) Did the plaintiff fail to take reasonable steps to mitigate the effect of the delay,
including by failing to order the additional plant it needed to comply with the
Mechanical Direction within a reasonable period of time?
(d) Did the plaintiff contribute to the cause of the delay by failing to provide shop
drawings of the mechanical system in breach of clauses 8.3 and 8.8 of the
Contract?
(e) Should the Christmas shutdown of 17 days at the end of 2016 and the beginning
of 2017 be excluded from any delay period?
[1003] I will deal with each of these in turn.
[1004] The plaintiff’s submissions set out extracts from correspondence leading up to the
Superintendent’s instructions on 11 August 2016, 16 August 2016 and 17 September
2016. Factually, this is largely not in dispute and it is not necessary to repeat it all
here.
[1005] If the Mechanical Direction was an instruction to undertake a variation then these
issues arise. For ease of reference, in this section of my reasons, the “Mechanical
Variation” refers to this scenario (if my primary findings are found to be incorrect).
[1006] Written notice of claim within 14 days
[1007] Clause 34.3(b) of the Contract requires the plaintiff to give the Superintendent a
notice “within 14 days of when the Contractor should reasonably have become
aware” of the qualifying cause of delay occurring. The notice is required to set out
certain information.
[1008] The plaintiff served a notice on 26 August 2016.317 The contents of the notice are not
in dispute. The issue is whether the notice was delivered out of time.
[1009] The defendant contends that the plaintiff became aware of the qualifying cause of
delay on 11 August 2016 when it received the Mechanical Variation, and accordingly
the notice was due on 25 August 2016 (being 14 days after becoming aware).
[1010] The plaintiff contends that the 14 day time limit in clause 34.3(b) only runs from
“when the Contractor should reasonably have become aware of that qualifying cause
of delay”. Notwithstanding that the evidence at the trial proves that the plaintiff
became aware of the Mechanical Variation on 11 August 2016, the plaintiff’s position
is that the plaintiff should reasonably have become aware on or after 12 August 2016
and therefore the plaintiff complied with clause 34.3(b) of the Contract by delivering
its notice on 26 August 2016.
[1011] It is necessary to consider the evidence in respect of this issue in some detail and also
to consider how this evidence unfolded at the trial. In summary:
(a) The plaintiff opened its case on the basis that the Mechanical Variation email
was sent after business hours and did not come to the attention of the plaintiff
until the next day. Accordingly, the plaintiff should have been aware of the
direction at the earliest on 12 August 2016.318
317 BUI.001.001.66766.
318 T1-33, L18-30.
-- 159 of 210 --
160
(b) In initial cross examination, Mr Cook gave evidence that included319 that he
recalled receiving the Mechanical Variation on the day it was sent and he was
in the site office when he received the direction.320
(c) Senior Counsel for the defendant called for the plaintiff to produce internal
emails of “Built emailing this to other members of Built on the evening of 11
August 2016”.321 The following day the plaintiff produced some documents in
response which were dated 12 August 2016.
(d) In re-examination, Senior Counsel for the plaintiff sought to take Mr Cook to
a document that he had not been taken to in cross-examination. Objection was
taken to this as it did not arise out of the cross-examination.322
(e) Senior Counsel for the plaintiff conceded that “[that] side of the bar table
weren’t aware of these matters” and wanted to take the witness to the
documents to test his memory.323
(f) It was submitted that this was a “crucial point”. Ultimately, to enable the issue
to be appropriately dealt with, the plaintiff was allowed to re-open evidence in
chief, with the defendant having a further right of cross-examination on the
issue.
(g) In further evidence in chief, Mr Cook gave evidence that:
(i) He circulated the direction the following morning after receiving it.
(ii) The following morning was the first time he would have been able to get
to his computer.
(iii) He saw the direction the night before most likely on his phone or from
home, not on his computer.
(iv) He did not think he was at work when he first saw the direction.
(v) He discussed the direction with Mr Meredyth by a phone call or a text
message.324
(h) Senior Counsel for the defendant then further cross-examined Mr Cook and
ultimately Mr Cook gave evidence that.
(i) He was in the office when he received the Mechanical Variation. He had
a positive recollection of being at the office.
(ii) He would have shown Mr Meredyth the direction on the evening of 11
August 2016, if Mr Meredyth had not received it independently.325
[1012] The plaintiff concedes that the Court must accept the evidence of Mr Cook that he
was in the site office when he received the direction but should give little weight to it
given Mr Cook’s poor recollection of the precise details of the events.326
319 This evidence will be set out in more detail later in these reasons.
320 T2-5, L18-21.
321 T2-5, L37-38.
322 T3-29, L16-19; T3-29, L21-23.
323 T3-32, L35-46.
324 T3-37, L1-24.
325 T3-48, L1-T3-51, L2.
326 Plaintiff’s written closing submissions at [289].
-- 160 of 210 --
161
[1013] The defendant’s position is that the evidence of Mr Cook must be considered in the
particular context of the period leading up to the Mechanical Variation being actually
received by Mr Cook on 11 August 2016. This context was put to Mr Cook in the
witness box and is as follows:
(a) As early as 10 June 2016, the plaintiff was aware that there may be an issue
with the two-pipe system not providing the Independent Heating/Cooling
Function.327
(b) By an email on 14 June 2016, the Superintendent advised the plaintiff that the
Independent Heating/Cooling Function was “non-negotiable and is in
accordance with the original design intent”.328
(c) On or about 15 June 2016, Mr Cook took Mr Van Grootel of Thwaite around
the site.329
(d) By an email on 20 June 2016, the Superintendent asked the plaintiff whether
the mechanical system had the ability to perform the Independent
Heating/Cooling Function.330
(e) Mr Cook accepted that by 20 June 2016 it was clear that a “difference of
opinion” had arisen between the Superintendent and the plaintiff as to whether
the Independent Heating/Cooling Function was required by the Contract. This
was taking into account all the emails referred to in paragraph 225 of Mr
Cook’s witness statement.331
(f) On 11 July 2016, the Superintendent issued “Superintendent Instruction No
9”.332 Mr Cook accepted that:
(i) The reference to the Superintendent not receiving information to support
the plaintiff’s claim that the two-pipe system complied with the Contract
was a reference to the above request by the Superintendent.333
(ii) The Superintendent indicated that the intent of the original design was to
allow guests to have independent heating and cooling and Mr Cook
understood that to be the Superintendent’s position.334
(g) In mid-July 2016, the plaintiff went to Batec and Cushway Blackford seeking
information about how they would go about changing the two-pipe system to a
three-pipe system as this is what the plaintiff believed the Superintendent and
the defendant wanted.335
(h) On 14 July 2016, Batec sent through its initial cost estimate for changing the
two-pipe system to a three-pipe system and Batec’s engineers were already
looking at the design of a three-pipe system.336
327 See T1-78, L26-T1-79, L3; WIT.001.001.0002 at p 0035 [207]; BUI.001.001.71783;
BUI.001.001.62025.
328 See T1-79, L8-40; WIT.001.001.0002 at p 0035 [213]-[214]; BUI.001.001.71450.
329 T1-79, L46-47.
330 T1-80, L31-T1-81, L10; WIT.001.001.0002 at p 0037 [225]; BUI.001.001.71468.
331 T1-81, L45-T1-82, L2.
332 T1-82, L15-20.
333 T1-82, L25-34.
334 T1-84, L7-8.
335 T1-84, L41-45; WIT.001.001.0002 at [2].
336 T1-85, L4-29; WIT.001.001.0002 at p 0040 [244]; BUI.001.002.43899; BUI.001.002.43900.
-- 161 of 210 --
162
(i) On 15 July 2016, the plaintiff met with Batec and Cushway Blackford to
finalise its response to “Superintendent Instruction No 9”337 and emailed the
Superintendent that same day.338
(j) Mr Cook’s evidence was that from this time the issue escalated.339
(k) On 26 July 2016, the plaintiff sent an email to the Superintendent.340
(i) In the email the plaintiff requested a direction on how the plaintiff was
to proceed regarding the guest room heating and cooling issue discussed
in earlier correspondence. Mr Cook agreed this was in the email.341
(ii) Mr Cook’s evidence in his witness statement was that “[w]e made this
request because Built believed that what was asked for deviated from the
contract requirements (which we thought was for a 2-pipe system).”342
(iii) This demonstrated that the plaintiff regarded a direction to move to a
three-pipe system as a variation as early as 26 July 2016.
(l) On 30 July 2016, a further email was sent by the plaintiff to the Superintendent
attaching schematics of a three-pipe system which the plaintiff had developed
together with Batec.343 Mr Cook accepted in evidence:
(i) The plaintiff was again seeking a direction from the Superintendent as to
how the defendant wanted to proceed.344
(ii) It was the second occasion where the plaintiff had asked for a direction
of this kind.345
(m) Mr Cook admitted in cross-examination that the plaintiff was waiting on a
direction:
“So you were, I take it, anticipating that – or you were asking
for, and you really wanted a direction? – We were asking for
clarity, yes.”346
(n) On 1 August 2016, the Superintendent emailed the plaintiff asking for time and
cost impacts to upgrade the system to a three-pipe system by way of
introduction of branch boxes, pipework upgrades and condenser
reconfiguration.347
337 T1-85, L31-T1-86, L22; WIT.001.001.0002 at p 0041 [252]-[253]; BUI.001.001.66727 and
documents in Attachment Schedule 11.
338 T1-86, L24-30; WIT.001.001.0002 at 0042 [254].
339 WIT.001.001.0002 at p 0037 [225].
340 T1-88, L5-T1-89, L2; WIT.001.001.0002 [260]; BUI.001.001.64767.
341 T1-88, L28-33.
342 WIT.001.001.0002 at 0043 [260].
343 T1-89, L4-10; WIT.001.001.0002 at p 0044 [264]-[265]; BUI.001.001.64792; BUI.001.001.14214;
BUI.001.001.14215.
344 WIT.001.001.0002 at p 0044 [264].
345 T1-89, L4-7.
346 T1-89, L9-10.
347 T1-89, L12-16; WIT.001.001.0002 at p 0044 [267]; BUI.001.001.71529; BUI.001.001.61918;
BUI.001.001.61919; BUI.001.001.61920.
-- 162 of 210 --
163
(o) Mr Cook gave evidence that by this time the plaintiff had looked at ways it
could upgrade the two-pipe system to a three-pipe system.348
(p) On 4 August 2016, Batec emailed the plaintiff attaching a further estimate of
the cost of converting the two-pipe system to a three-pipe system.349
(q) On 5 August 2016, the plaintiff sent an email to the Superintendent with a
response by the plaintiff to the request for time and cost implications to upgrade
to a three-pipe system.350 The email provides:
(i) A program time of six weeks to procure the branch boxes.
(ii) “80 days from site instruction received Thursday 11th August to complete
extends to Friday 18th November completion (Practical completion 3rd of
November)”.
(iii) “Total Time implications (EOT) 13 Days”.
(r) Mr Cook gave evidence that the email was referring to an 80 day period if the
direction was received on 11 August 2016.351
(s) On 11 August 2016, Mr Cook sent a further email to the Superintendent.352 Mr
Cook accepted:
(i) This email was the plaintiff again pressing for a direction.353
(ii) The email stated that “The Contract requires that Built comply with such
a direction.”
(iii) If a direction was given under the Contract, the plaintiff was required to
comply with it. That was Mr Cook’s view as project manager.354
(iv) Parallel without prejudice discussions could take place at the same
time.355
[1014] The defendant submits that it is critical that this background context is kept in mind
when consideration is given to the receipt of the Mechanical Variation. The receipt
of the 11 August 2016 notice was raised with Mr Cook in this context in cross-
examination as follows:
“Thank you. Can I take you to paragraph 272 of your statement:
Later on 11 August Built received from Tactical attaching a
notice which was said to be a notice to rectify defective work
pursuant to clause 29.3.
Do you see that?---Yes.
348 T1-89, L21-22.
349 T1-89, L24-T1-90, L14; WIT.001.001.0002 at p 0045 [268]; BUI.001.003.61317.
350 T1-90, L18-47; WIT.001.001.0002 at p 0045 [269]; BUI.001.001.64823 and the documents in
Attachment Schedule 12.
351 T2-3, L11-25.
352 T2-3, L27-T2-4, L24; WIT.001.001.0002 at p 0045 [271]; BUI.001.001.64850.
353 T2-3, L31-32.
354 T2-3, L39-40.
355 T2-4, L21; T2-4, L24-25.
-- 163 of 210 --
164
Now, I’ve taken you through your statement. On multiple occasions,
you had been saying, ‘You’ve got to give us a direction’. You agree
with that proposition?---Yes.
And on the 11th and on the 5th of August you said, ‘We need a
direction by the 11th of August’?---Correct.
And you were waiting on the 11th of August for the direction?---
Yes.”356
[1015] Mr Cook then gave evidence that:
(a) When the Mechanical Variation came through he was waiting for it and saw
it.357
(b) He immediately telephoned other people at the plaintiff. This was likely to
have been his commercial manager (either Mr Peter Lincoln or Mr Cameron
Davidson) and general manager (Mr David Vincenzino).358
(c) Mr Meredyth would have been in the office with him. He would have had
direct contact with him.359
(d) He was in the site office when he received the Mechanical Variation.360
(e) It was inevitable that he would have spoken to Mr Meredyth and shown him
the Mechanical Variation as he was in the office with him.361
[1016] The defendant also points to evidence going to Mr Cook’s state of mind in respect of
delay and a potential extension of time claim, including as follows:
(a) As at 5 August 2016:
(i) The email from the plaintiff to the Superintendent of 5 August 2016
refers to 80 days from the site instruction received on 11 August 2016
and a time implication of “EOT 13 days”.362
(ii) It was within Mr Cook’s state of mind that there may be a requirement
for an extension of time if a direction was given on 11 August 2016.363
(iii) Mr Cook was the author of the email and he had shown it to his
commercial manager and general manager before sending it.364
(b) As at 11 August 2016:
(i) Mr Cook appreciated that if a direction was given it would be a
qualifying event that caused a delay.365
356 T2-4, L26-39.
357 T2-4, L41-43.
358 T2-4, L45-T2-5, L1; T2-5, L3-15.
359 T2-5, L17-18.
360 T2-5, L20-21.
361 T2-5, L26-29.
362 WIT.001.001.0002 [269]; BUI.001.001.64823.
363 T2-6, L40-46.
364 T2-6, L40-46; T2-7, L1-5.
365 T2-7, L20-29; T2-8, L5-10.
-- 164 of 210 --
165
(ii) Mr Cook held the view that it was likely to have an EOT result, as had
been foreshadowed some days earlier.366
[1017] Following this evidence the issue arose that resulted in leave being granted for the
plaintiff to reopen evidence in chief from Mr Cook.
[1018] Mr Cook’s further evidence in chief included as follows:
“Did you think it was important to circulate this notice quickly, or was
that not of particular importance to you?---Yes, I dare say – it’s 7 –
around that time would’ve been the first time I would’ve been able to
get to my computer the following morning.
When you saw – I think you said you saw the mechanical direction
the previous night. I think that was your evidence?---Yes.
So you would’ve been at your computer at that point?---No, most
likely on my phone or from – from home. Not on my computer.
I see. So is it the case that you don’t think you were actually at work
when you first saw that mechanical direction?---I believe so, yes.
I think you gave some evidence yesterday that I think you discussed
it with Mr Meredith [sic] on the evening of the 11th of August; do
you recall that?---I do recall that, yes.
Can you explain, if you weren’t at work, how did you discuss it with
Mr Meredith?---A phone call or a text message.”367
[1019] Mr Cook was also taken to an email from himself to Mr Gary Stagnitta dated 12
August 2016 at 7.10am.368 The email attaches the 11 August 2016 direction and
states:
“How do you want to proceed with the attached?
Let me know if we need to make a meeting or if you wish to discuss
anything.”
[1020] Mr Cook gave evidence including as follows:
(a) Mr Stagnitta was the plaintiff’s national commercial manager at the time.
(b) Mr Stagnitta was overseeing nationally all contracts; all the requirements and
commercially.369
(c) The email was copied to numerous people as he considered it important that
the direction be circulated to those people.370
366 T2-7, L20-29; T2-8, L5-10.
367 T3-37, L5-24.
368 BUI.001.003.09334.
369 T3-36, L38-40.
370 T3-36, L45-46.
-- 165 of 210 --
166
[1021] The plaintiff also relies on two further documents in respect of this issue:
(a) A meeting invitation sent from Mr Brett Mason scheduling a meeting to occur
on 12 August 2016 at 11am. This was sent to various people at the plaintiff
including the general counsel, Mr Andrew Lonsdale.371
(b) Mr Cook’s acceptance of the meeting invitation.372
[1022] Mr Cook gave evidence in re-examination about these documents as follows:
(a) Mr Mason was the managing director of the Built Group, including the
plaintiff.373
(b) He recalled attending the meeting.374
(c) At the meeting the effect of the Mechanical Direction was discussed.375
(d) Moving forward from the meeting, notices were to be prepared advising that a
number of items were incorrectly addressed in the Mechanical Direction.376
[1023] Mr Cook was then cross-examined again by Senior Counsel for the defendant. Mr
Cook was stepped through his evidence and asked to confirm it.377
[1024] Critical to his evidence regarding receipt of the Mechanical Variation is the following
exchange:378
“See, I then asked you:
Okay. So you were in the office. You recall being in the office when
you received this?
And you answered:
The site office, yes.
I asked for your actual recollection, and you gave it. That was the
truth when you gave that evidence, wasn’t it?---Yes.
You were at the site office?---I can’t recall exactly where I was, but
– yes. That’s what I said. Yes.
Well, you volunteered to me in the prior answer that you were in the
office and that’s why you would’ve thought Mr Meredith [sic]
would’ve been there with you. You see, I didn’t ask – suggest to you
you were in the office. You volunteered it; correct?---Correct.
And I asked you – I wanted to make sure that I understood your
question, so I asked for your actual recollection:
You recall being in the office when you received this?
371 BUI.001.003.75583.
372 BUI.001.003.72575.
373 T3-37, L45-46-T3-38, L1-7.
374 T3-38, L9-39.
375 T3-38, L45-46.
376 T3-39, L4-7.
377 T3-45, L23-T3-53, L3.
378 T3-48, L1-T3-51, L2.
-- 166 of 210 --
167
And your answer was:
The site office, yes.
That is your recollection, isn’t it?---Yes.
…
I’m not reading from the transcript now, but I’m – you’ve given your
recollection that you were in the site office and you’ve confirmed that
you were; correct?---Yes.
What I’m suggesting to you is that you have a recollection that Mr
Meredith [sic] was also in the site office at the time the 11th August
2016 notice was received?---That could be it, yes.
Now, yesterday I think it’s fair – I did ask you questions whether you
recalled showing him the document and - - -
HER HONOUR: Is that Mr Meredith [sic] you’re referring to, Mr - -
-
MR SULLIVAN: Yes. I’ll read out that question. And I said:
And you spoke to Mr Meredith [sic]. I take it he was present with
you. Do you recall speaking to him about it?---I can’t recall. I
can’t recall.
So you gave evidence you didn’t have a positive recollection, but then
you said – I said:
It’s inevitable that you would have spoken to him about it, isn’t it?
And your answer was, “Yes”?---Correct.
You stand by that evidence?---Yes.
Thank you. And then I said:
And it’s inevitable you would have shown him the document as
well, wouldn’t you?
And your answer was:
If he didn’t receive it himself, yes.
Do you stand by that evidence?---Yes.
And it’s – can I suggest to you it’s the case it is inevitable that if he
didn’t receive it independently, that you would have shown him that
document on that occasion on the evening of 11 August 2016?---Yes.
Okay. Why? Why then did you change your evidence today about
being at home?---It was just based on the time of the 11th. It was an
assumption that at that time I would typically be at home.
Right. Even though you accept now you’ve got a positive recollection
of being at the office?---I do, yeah.”
-- 167 of 210 --
168
[1025] The plaintiff contends that:
(a) The plaintiff needed to consider the Mechanical Direction and form a view as
to whether it constituted a variation and whether it would be likely to delay
practical completion. As the Mechanical Direction was only delivered at
7.20pm the plaintiff contends it was entirely reasonable to consider the
Mechanical Direction in detail and obtain input from all relevant personnel.
That could reasonably be expected to occur on 12 August 2016, at the earliest.
(b) The meeting on 12 August 2016 was the first occasion when Mr Mason, the
plaintiff’s managing director, and Mr Lonsdale, the plaintiff’s general counsel,
were able to discuss the Mechanical Direction and its potential effect on the
progress of the work under the Contract.
(c) The time when Mr Cook first saw the notice is not the time at which the plaintiff
should reasonably have become aware of the qualifying cause of delay.
(d) When time begins to run is an objective question and it does not depend on
when the contractor in fact became aware of the relevant matter.
[1026] The defendant contends that:
(a) The plaintiff’s contention should be rejected for the following reasons:
(i) Mr Cook was the project manager and he was the person who sent
correspondence on behalf of the plaintiff seeking a direction by 11
August 2016.
(ii) Mr Cook was waiting at the site office on the evening of 11 August 2016,
as he was anticipating a direction.
(iii) There is no basis in the Contract for it being the board of the plaintiff
who must be reasonably aware.
(iv) Mr Cook as project manager was the appropriate person to send the
direction to and he received it on 11 August 2016 and consequently the
plaintiff became aware of the qualifying cause of delay occurring on 11
August 2016.
(v) On the balance of probabilities, it is open for the Court to conclude that
Mr Meredyth and the other identified members of senior management of
the plaintiff became aware of the qualifying cause of delay occurring on
11 August 2016.
(b) Mr Cook received the Mechanical Variation in the context identified above. In
particular, having on three prior occasions requested a direction, having had
contractors consider what could be installed, having considered costs estimates
and time impacts and having the belief that if a direction was given then the
plaintiff had to comply with it.
(c) On 11 August 2016, a Thursday, Mr Cook requested a direction, was waiting
for that direction in the office, received the direction and read it.
(d) Mr Cook appreciated that the direction would be a qualifying cause of delay
likely to give rise to a need for an extension of time.
-- 168 of 210 --
169
[1027] On 12 August 2016, an email was sent pursuant to clause 34.2. This was not a notice
pursuant to clause 34.3(b).
[1028] The notice sent on 26 August 2016 was outside the 14 day period if time started to
run on and from 12 August 2016 (that is day one is 12 August and day 14 is 25
August).
[1029] The defendant submits:
(a) Clause 34.3 is in mandatory terms and requires strict compliance. If one of the
subclauses is not satisfied then the Contractor is not entitled to an extension of
time.
(b) Courts have held that provisions of this kind should be enforced according to
their terms, even though the consequences for non-compliance with strict
notice provisions may be severe.379
(c) In the subcontract between the plaintiff and Batec, the plaintiff assessed
liquidated damages against Batec as the work was not completed by November
2016.380 Mr Cook gave evidence that this was because Batec had not sought an
extension of time arising from the Mechanical Variation.381 The liquidated
damages claim assessed by the plaintiff exceeded the total amounts Batec
claimed.
[1030] In the case of Australian Development Corporation Pty Ltd v White Constructions
(ACT) Pty Ltd,382 Giles CJ was considering an extension of time clause which was
substantially similar in its terms to clause 34.3 of the Contract. His Honour relevantly
stated:
“The contract called for practical completion by particular dates
subject to extensions of time. Any extension of time was for specified
cause, cause which had to be beyond the control of ACT, and for a
period equal to the delay to ACT. The time by which the date for
practical completion should be extended was to be determined by
ADC, and it was therefore necessary that ADC be in a position
rationally to assess the existence of a cause of delay, whether it was
a cause of delay of one of the specified kinds, whether it was beyond
the control of ACT, and what the extent of the delay to ACT was.
Imposing the notification requirement upon ACT was a deliberate
and important part of the mechanism for determining the time by
which the date for practical completion should be extended. It was in
mandatory terms ("shall notify") equivalent to the mandatory terms
imposed on ADC ("shall determine the time") …
379 Port Jackson Stevedoring Pty Ltd v Salmond & Spraggon (Australia) Pty Ltd (1978) 139 CLR 231 at
238 (Barwick CJ); Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11
BCL 360 at 364 (Bollen CJ, with whom Prior and Duggan JJ agreed); Australian Development
Corporation Pty Ltd v White Constructions (ACT) Pty Ltd & Ors (1996) 12 BCL 317 at 339 (Giles
CJ).
380 PRO.052.004.0226.
381 T2-28, L18.
382 (1996) 12 BCL 317 at 339.
-- 169 of 210 --
170
In my opinion, therefore, in the absence of timely notification as
required by article 4.4.1 ACT was not entitled to extension of the date
for practical completion.”
[1031] A similar conclusion was reached in Opat Decorating Service (Aust) Pty Ltd v Hansen
Yuncken (SA) Pty Ltd,383 where Bollen J (Prior and Duggan JJ agreeing) stated:
“Let me look at cl 31(b). It begins by speaking of circumstances in
which the parties contemplate that the appellant might want an
extension of time within which to complete work. The parties when
negotiating the contract, knowing the exigencies of the trade, agreed
that some such circumstances might arise. What should be done about
it? They answered this question by saying that the notice should be
given by the appellant to the respondent, by subcontractor to
contractor. They decided something about the time within which
notice should be given. What did they decide? They decided that it
should be given within fourteen days after the cause of delay arose.
They knew the exigencies of the trade. They knew what practical
questions or issues would arise when notice was given. They knew
when it was best for the notice to be given. They fixed on that
fourteen day period. And they meant the clause which emerged from
these deliberations to be effective within its terms. That is to say they
meant what cl 31(b) says to be the position. They meant to bind
themselves to it.”
[1032] In these circumstances, the defendant contends that:
(a) Clause 34.3(b) of the Contract required notice from the plaintiff of its claim for
an extension of time evidencing facts of causation and the extent of delay to
the WUC by 25 August 2016.
(b) As notice was not given by that date, the plaintiff is not entitled to:
(i) An extension of time or delay damages which are dependent upon the
extension of time claim.
(ii) Return of any liquidated damages set-off by the defendant for late
completion.
[1033] In respect of Mr Cook’s evidence, I accept his evidence that was given initially in
cross-examination and which was confirmed in his further cross-examination. He
was at the site office on the evening of 11 August 2016 and received the Mechanical
Direction. This is also consistent with the earlier correspondence from the plaintiff
that calls for a direction by that date. It is consistent with that position, that Mr Cook
received the Mechanical Direction and then provided an update to others that night.
[1034] When considered in the context of the events leading up to that point in time, the
plaintiff was in a position to consider and respond to the Mechanical Direction within
the time period in the Contract. The submission that the time the plaintiff “should
reasonably have become aware of a qualifying cause of delay” was not until 12
August 2016 is also not persuasive given the identified context and the evidence of
Mr Cook. The timing was exactly what the plaintiff asked for.
383 (1994) 11 BCL 360 at 364.
-- 170 of 210 --
171
[1035] This is also supported by the evidence of Mr Cook that multiple notices were given
by the plaintiff on 12 August 2016, including:384
(a) a notice under clause 20 of the Contract that the plaintiff considered the
Mechanical Direction was in error or was a direction for a variation.385
(b) a notice under clause 34.2 of the Contract that the Mechanical Direction was
likely to cause delay to the WUC.386
(c) a notice under clause 41.2 of the Contract that the plaintiff would make a claim
as a request of the Mechanical Direction.387
(d) a notice of dispute under clause 42 of the Contract in relation to the Mechanical
Direction.388
(e) a notice under clause 36.1 of the Contract that the Mechanical Direction
constituted a direction to perform a variation.389
[1036] Whilst the Mechanical Direction may not have been exactly what the plaintiff wanted,
on the balance of probabilities the evidence supports the conclusion that the plaintiff
was anticipating receipt of a notice on the evening of 11 August 2016 and on
becoming aware of the Mechanical Direction took steps under the Contract promptly
on 12 August 2016.
[1037] In all of these circumstances, the evidence on the balance of probabilities, supports
the conclusion that not only did the plaintiff actually become aware of the qualifying
cause of delay on 11 August 2016, it also “should reasonably” have become aware
that same day.
[1038] The plaintiff contends that the board of the plaintiff was the relevant decision maker
of the plaintiff and this issue is to be considered based on when the board should have
reasonably become aware of the qualifying cause of delay. I do not accept that
proposition. It is contrary to the requirements of the Contract. The parties could have
factored a requirement for notice to the board into the Contract but did not do so.
[1039] If it is necessary to consider the plaintiff’s entitlement to an extension of time in
respect of the Mechanical Variation, I make the following findings:
(a) For the purposes of clause 34.3(b) of the Contract, the plaintiff “should
reasonably have become aware” of the qualifying cause of delay occurring on
11 August 2016 when the Mechanical Direction was received.
(b) Consequently, pursuant to clause 34.3(b), any written claim for an extension of
time was due by 25 August 2016, being 14 days after (a).
(c) The plaintiff gave notice of a written claim for an extension of time on 26
August 2016, being 15 days after (a).
384 WIT.001.001.0002 at p 0046 [280].
385 BUI.001.001.68752; BUI.001.001.25027.
386 BUI.001.001.66753; BUI.001.001.25028.
387 BUI.001.001.66754; BUI.001.001.25029.
388 BUI.001.001.66755; BUI.001.001.25030.
389 BUI.001.001.66756; BUI.001.001.25031.
-- 171 of 210 --
172
(d) Consequently, the plaintiff’s notice of a written claim for an extension of time
was outside the contractually stipulated period.
[1040] In these circumstances, the plaintiff is not entitled to an extension of time.
Delay analysis methodology
[1041] This issue concerns whether the Contract permits a prospective or a retrospective
delay analysis. This is of significance as different approaches have been used by the
experts engaged by the parties to undertake an analysis of the delay:
(a) Mr Bell uses a prospective delay analysis in his report relied upon by the
plaintiff.390
(b) Mr King uses a retrospective delay analysis in his report relied upon by the
defendant.391
[1042] The difference between the two approaches was commented on by Flanagan J in Civil
Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd.392
In that case, the two approaches were described as follows:
“[643] … [The prospective approach] methodology involved him
undertaking the following steps:
(a) he considered the statused program that was issued prior
to the commencement of the alleged delay;
(b) he determined the criticality (or otherwise) of the
relevant activity prior to the delay occurring;
(c) he reached an opinion as to the impact to the delay on
the date for practical completion by introducing a delay
activity into the program to model the claimed delay;
and
(d) he considered any programs that were produced during
the period that the delay was occurring to determine
whether the criticality of the relevant activity was
maintained.
(a) …
[645] … [The retrospective or the “as-planned” v ‘as-built”]
methodology …:
(a) determined that the [relevant activity] was on the
critical path during the period of the claimed delay;
(b) determined which work activities within the [relevant
activity] were on the actual critical path;
390 EXP.001.001.0705.
391 EXP.001.001.0858.
392 [2017] QSC 85.
-- 172 of 210 --
173
(c) compared the planned and actual duration for the
[relevant activities] which were on the actual critical
path …”.
[1043] The appropriate methodology is governed by the terms of the Contract.393
[1044] Clause 34.3 of the Contract relevantly states:
“The Contractor shall be entitled to such EOT for carrying out WUC
(including reaching practical completion) as the Superintendent
assesses, if:
(a) the Contractor is or will be delayed in reaching practical
completion by a qualifying cause of delay;
… ” (emphasis added)
[1045] The plaintiff contends that the Contract requires a prospective delay analysis based
on the words “is or will be delayed”. The plaintiff submits that this conveys current
or ongoing delay which would be prospective.
[1046] The plaintiff relies on the decision in CMA Assets Pty Ltd Formerly Known as CMA
Contracting Pty Ltd v John Holland Pty Ltd (No 6)394 in support of its submission.
The clause being considered included the words “is or will be delayed” and Allanson
J concluded that the language is prospective.
[1047] The plaintiff also points to other parts of the Contract which support this construction,
including:
(a) Clause 34.2 requires a notice of delay to be given when a party becomes “aware
of anything which will probably cause delay” and the notice is to identify the
cause and “the estimated delay”.
(b) Clause 34.3(c) refers to the qualifying cause of delay affecting “the critical path
of the activities required to complete WUC as shown on the approved
construction program”.
(c) The final paragraph of clause 34.3 requires an update of the length of delay
“[i]f further delay results”.
(d) Clause 32.2(b) provides that the “approved construction program will be used
by the Contractor and the Superintendent to … assess delays and any EOT.”
(e) Clause 32.2(c) requires the plaintiff to issue a revised approved construction
program within 5 business days of “being notified of an EOT being granted
under the Contract”.
[1048] The plaintiff recognises that clause 34.3(e) may arguably suggest a retrospective
analysis of delay by the words “the Superintendent is satisfied that WUC was actually
delayed”. However, the plaintiff submits that this requires the work under the
contract to be delayed, not practical completion. Consequently, the plaintiff contends
393 Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd [2017] QSC 85
[663].
394 [2015] WASC 217.
-- 173 of 210 --
174
that this is not relevant to delay methodology, but that the Superintendent must be
satisfied of some actual delay.
[1049] However, the plaintiff’s position is that even if clause 34.3(e) allows a retrospective
methodology, the Contract requires a prospective analysis for delay longer than 28
days due to clause 34.5. Clause 34.5 requires the Superintendent to assess the delay
within 14 days of receiving the claim for an EOT, which in turn is required to be
given within 14 days of when the contractor should reasonably have become aware
of the qualifying cause of delay occurring. If this does not occur, then there is a
deemed direction for the EOT claimed.
[1050] As the delay caused by the Mechanical Variation was longer than 14 days, the
plaintiff contends that only a prospective approach to delay analysis can be applied.
[1051] Flanagan J in Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export
Terminal Pty Ltd395 construed “has been or will be actually delayed in achieving
Practical Completion” as permitting both a prospective and retrospective delay
analysis.
[1052] The plaintiff points to two differences between the clause in that case and clause 34
in the Contract:
(a) Clause 34.3 uses the words “is or will be delayed” which is prospective
language in contrast to “has been or will be”.
(b) Clause 34.5 requires an assessment within 14 days or there is a deemed
direction for the EOT claimed. Without such a provision it was open to do a
retrospective assessment of delay once the delay had ended but that is not
possible under the current Contract.
[1053] The defendant submits that on a proper construction of clause 34.3 of the Contract, it
is open to the Court to use either methodology to determine the entitlement to an
extension of time but that Mr King’s analysis should be preferred.
[1054] The defendant accepts that clause 34.3 is “oddly drafted” in that it mixes tenses: the
Superintendent must be satisfied that the plaintiff “is or will be” delayed in reaching
practical completion and that the WUC was “actually delayed”.
[1055] The defendant also refers to and relies on the decision of Flanagan J in Civil Mining
& Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd396 in support
of its construction.
[1056] The defendant submits that Flanagan J had to consider a similar extension of time
provision with mixed tenses and his Honour concluded:
“[657] The issue is whether the Contract permits both a prospective
and retrospective delay analysis. WICET submits that Mr
King’s retrospective delay analysis in respect of Delay Event
9 using an ‘as planned’ v ‘as built’ analysis is not permitted
by clause 35.5 of the Contract.
395 [2017] QSC 85 at [658].
396 [2017] QSC 85.
-- 174 of 210 --
175
[658] In my opinion the better view is that the Contract permits both
a prospective and retrospective delay analysis.
[659] Paragraph 3 of clause 35.5 provides that:
‘If the Contractor is or will be delayed in reaching
Practical Completion … and within 28 days after the
delay occurs the Contractor gives the Principal’s
Representative a written claim … the Contractor shall be
entitled to an extension of time for Practical
Completion.’
Clause 35.5 further provides:
‘The Contractor will only be entitled to an extension of
time for Practical Completion pursuant to this Clause if
–
(B) the Contractor –
(5) demonstrates to the satisfaction of the Principal that
the Contractor has been or will be actually delayed
in achieving Practical Completion.’
[660] The use of the disjunctive ‘or’ gives the Contractor a choice
to demonstrate that either it has been actually delayed or it
will be actually delayed in achieving Practical Completion.
The past tense “has been” as CMC submits, contemplates
looking backwards, after the delay event has expired, to
demonstrate that (with knowledge of hindsight) the
Contractor has actually been delayed in achieving Practical
Completion. CMC further submits that the retrospective
approach is particularly appropriate if the activity delayed
occurs towards the end of the project, such that the time at
which the claim for the extension comes to be assessed is after
Practical Completion has been achieved.
…
[662] … The use of the words ‘has been … actually delayed’
addresses past delay permitting or indeed inviting
retrospective analysis. A Contractor would be entitled to an
extension of time for Practical Completion if it demonstrates
either a past or future delay. Further as CMC correctly
submits, WICET’s construction does not give the word
‘actually’ any work to do.”
[1057] Based on this approach, the defendant submits that clause 34.3 of the Contract permits
either a prospective or retrospective analysis to be performed. That is, the words
“‘will be delayed’ invite a prospective analysis, the words ‘is .. delayed’ and ‘was
actually delayed’ invite a retrospective analysis”.
[1058] The defendant also addresses the plaintiff’s argument in respect of clause 34.5 that a
prospective analysis is required where the delay is greater than 14 days. The
defendant submits that this argument is incorrect.
-- 175 of 210 --
176
[1059] Clause 34.5 of the Contract provides that the Superintendent is to assess the
contractor’s extension of time claim within 14 days of receiving it. Otherwise, the
clause provides that there is a deemed assessment of the EOT claimed.
[1060] The defendant submits that the current exercise is totally different. The issue before
the Court is determining the plaintiff’s entitlement (if any) to an extension of time
well after the expiration of the alleged delay event and also well after practical
completion was achieved. The defendant submits that clause 34.5 cannot operate to
place the Court in the “shoes of the superintendent at the time of assessment” to
determine the plaintiff’s entitlement to an extension of time now.397
[1061] Reference is again made to the decision of Civil Mining & Construction Pty Ltd v
Wiggins Island Coal Export Terminal Pty Ltd.398 In that case Flanagan J also had to
consider a clause, similar to clause 34.5 of the Contract, which stated:
“If the Contractor is entitled to an extension of time for Practical
Completion the Principal’s Representative shall, within 28 days after
receipt of the notice of the number of days extension claimed, grant
a reasonable extension of time. If within the 28 days the Principal’s
Representative does not grant the full extension of time claimed, the
Principal’s Representative shall before the expiration of the 28 days
give the Contractor notice in writing of the reason.”399
[1062] At paragraph 756 his Honour accepted that the appropriate extension of time on an
as-planned as-built analysis was 111 days. The existence of the clause extracted
above requiring an assessment of a claim within 28 days, did not prevent this
conclusion.
[1063] Importantly, the defendant contends that regardless of the methodology used, clause
34.3 provides that the delay must be calculated by reference to “the critical path …
as shown on the approved construction program”. This issue is further discussed
below.
[1064] The language used in clause 34.3 of the Contract is consistent with the language
considered by Flanagan J in Civil Mining & Construction Pty Ltd v Wiggins Island
Coal Export Terminal Pty Ltd and a similar construction of the contractual provision
should be adopted here.
[1065] Accordingly, it is open on the proper construction of clause 34.3 of the Contract for
either a prospective or a retrospective methodology to be used to determine the
entitlement to an extension of time.
Reasonable steps to mitigate delay
[1066] Clause 34.3(f) states “the Contractor has taken all reasonable steps to mitigate the
effect of the delay”. Accordingly, pursuant to the Contract, the plaintiff is only
entitled to an extension of time if it took all reasonable steps to mitigate the effect of
the delay.
397 Defendant’s written closing submissions at [179]-[183].
398 [2017] QSC 85.
399 [2017] QSC 85 at 271.
-- 176 of 210 --
177
[1067] The question is, therefore, whether the plaintiff failed to take all reasonable steps to
mitigate the effect of the delay caused by the Mechanical Variation by not ordering
the mechanical plant necessary for the three-pipe conversion on or immediately after
11 August 2016.
[1068] The defendant’s contention is that the plaintiff did not place the order for the
necessary mechanical plant until 14 October 2016 and that it was unreasonable for
the plaintiff not to have done so earlier.
[1069] The defendant identifies the effect is as follows:
(a) A delay of 64 calendar days, between 11 August 2016 and 14 October 2016,
claimed to be caused by the plaintiff’s failure to order the mechanical plant
following the Mechanical Variation.
(b) A further delay of 17 calendar days as the delay occurred during the Christmas
shutdown period, 18 December 2016 to 3 January 2017.
[1070] The defendant’s position is that if the mechanical plant was ordered shortly after the
Mechanical Variation there would have been no delay to the works or alternatively,
if it had been ordered earlier than 14 October 2016 there would have been a reduction
in the period of critical delay.
[1071] The plaintiff contends that it did not act unreasonably in not ordering the mechanical
plant:
(a) On or immediately after 11 August 2016 – The plaintiff’s position is that while
it accepts it did not order the mechanical plant, it was not unreasonable as:
(i) The design of the three-pipe system was not finalised.
(ii) Toshiba was not an approved manufacturer and at that stage Toshiba
condensers were proposed to be used for the three-pipe conversion.
(iii) The Mechanical Variation from the Superintendent suggested there may
be other issues with performance requirements of the Mechanical
Services System that needed to be addressed that went beyond the mode
control requirement.400
(b) On or immediately after 16 August 2016 – The plaintiff’s position is that while
it accepts it did not order the mechanical plant, it was not unreasonable as:
(i) The design was still to be reviewed by the defendant’s mechanical
consultant.
(ii) The correspondence suggested further discussions would take place,
including a dispute resolution meeting on 18 August 2016.401
(c) On or before 22 August 2016 – The plaintiff’s position is that while it accepts
it did not order the mechanical plant, it was not unreasonable as there was still
a further “submission” to be considered, which was to be provided by the
plaintiff in respect of the proposed conversion.402
400 BUI.001.001.61926.
401 PRO.017.001.0922.
402 BUI.001.001.71548.
-- 177 of 210 --
178
(d) By 24 August 2016 – as the design still had not been finalised and discussions
were on-going with the Superintendent and the mechanical consultants.403
(e) As at 31 August 2016 – it was not unreasonable as it was still proposed to use
plant manufactured by Toshiba as part of the upgrade which was not an
approved manufacturer.404
(f) Prior to 14 October 2016 – the plaintiff refers to correspondence between 16
September and 14 October 2016 in respect of uncertainty in relation to Toshiba
and the work under the direction.405
[1072] On 14 October 2016, the plaintiff indicated it would implement the direction on the
assumption “there is no objection to Toshiba as equipment manufacturer”.406 The
plaintiff submits that this was the plaintiff taking a substantial financial risk in the
best interests of the Spring Hill Hotel. This was done to minimise delay as much as
possible.
[1073] In all of these circumstances, the plaintiff contends that it did not act unreasonably at
any point up until 14 October 2016 in not ordering the mechanical plant for the
conversion to a three-pipe system.
[1074] The defendant relies on a number of matters to establish the failure to take reasonable
steps, including the following:
(a) On 10 June 2016 the Superintendent first notified the plaintiff that it was
concerned that the mechanical system could not perform the Independent
Heating/Cooling Function.407
(b) On 20 June 2016 the Superintendent requested that the plaintiff “confirm that
the two-pipe system has the ability to enable each room to call for cooling or
heating independently of other Guestrooms”.408
(c) On 12 July 2016 the Superintendent issued “Superintendent Instruction No 9”
which stated:409
“Pursuant to Clause 29.3 of the Contract and as discussed /
requested in PCG Meeting No.13, we have not received
information to support the Contractor’s claim that the 2 pipe
mechanical system complies with the Contract. The
Superintendent considers any responses to date provided
Without Prejudice (as attached) as completely insufficient.
403 BUI.001.001.66457; WIT.001.004.0001 at [295]-[296].
404 BUI.001.001.71561.
405 BUI.001.001.15390; BUI.001.001.71572; BUI.001.001.65012; BUI.001.002.43897;
BUI.001.003.72664; BUI.001.001.65035; BUI.001.001.71576; BUI.001.001.67957;
BUI.001.001.66778; BUI.001.001.25054; BUI.001.001.71580; BUI.001.001.61945;
BUI.001.001.25054; BUI.001.001.65095; BUI.001.001.61946; BUI.001.001.71582;
BUI.001.001.61948; BUI.001.001.71583; BUI.001.001.65105; BUI.001.001.71584;
BUI.001.001.61950; BUI.001.001.65130; BUI.001.001.71587.
406 BUI.001.001.65149.
407 BUI.001.001.71783; WIT.001.001.0002 at p 0035 at [208], [210].
408 BUI.001.001.71468; WIT.001.001.0002 at p 0037 at [225].
409 BUI.001.001.61891.
-- 178 of 210 --
179
…Should sufficient information not be received within 5 days,
and Pursuant to Clause 29.3(c), the Superintendent will require
the Contractor to takes all steps to replace and reconstruct the
mechanical system in accordance with the Contract.
Key Issues for Contractor Response:
…
2. The guest rooms are required to be heated and cooled.
Built have proposed a VRF heat-pump type system based
on the FCUs on a condensing unit being on the same
façade and hence able to be either all heating or cooling.
In this scenario no additional electric heaters are required
however all the FCUs on a condensing system will heat
OR cool simultaneously. This is not the intent of the
original design as the intent was to allow the occupant to
select their own temperature and that may require some
heating whilst others on the same condensing system may
require cooling. This is a loss of amenity.” (emphasis
added)
(d) Mr Cook gave evidence including:
(i) Following “Superintendent Instruction No 9”, from 14 July 2016 the
plaintiff worked with Batec and Cushway Blackford to identify how it
could change the two-pipe system to a three-pipe system so that it could
perform the Independent Heating/Cooling Function.410
(ii) Whilst the plaintiff maintained that the alternative proposal complied
with the Contract it knew the defendant disagreed and in parallel the
plaintiff progressed a design of a three-pipe system.411
(e) By 30 July 2016 the plaintiff had developed a detailed schematic of the three-
pipe system, which was then further developed.412
(f) On 1 August 2016, the Superintendent emailed the plaintiff requesting that it
confirm the time and cost implication to upgrade the mechanical system to a
three-pipe system in accordance with the schematic sent on 30 July 2016.413
(g) On 5 August 2016, the plaintiff sent to the Superintendent a breakdown of the
time and costs that would be incurred and further said it would need a direction
by 11 August 2016 if those estimates were to be achieved.414
(h) On 11 August 2016, the Superintendent issued the Mechanical Variation.
(i) On 12 August 2016, the plaintiff issued a notice of dispute pursuant to clause
42 of the Contract requiring the parties to commence without prejudice
discussions.415
410 WIT.001.001.0002 at p 0040 [242]; T1-85, L28-29.
411 WIT.001.001.0002 at pp 0041-0049 [247]–[296]; T1-86, L11-22.
412 BUI.001.001.14214; WIT.001.001.0002 at p 0044 at [264]–[265]. This schematic was not the same
as what was ultimately installed.
413 BUI.001.001.71529; WIT.001.001.0002 at p 0044 [267].
414 BUI.001.001.64823 with attachments; WIT.001.001.0002 at p 0045 at [269].
415 BUI.001.001.25030; WIT.001.001.0002 at p 0046 [280(d)].
-- 179 of 210 --
180
(j) Mr Cook gave evidence that the plaintiff was obliged to act on the Mechanical
Variation whilst the without prejudice discussions were happening in
parallel.416
(k) From 11 August 2016 the plaintiff continued to develop the three-pipe system
it had been developing since 14 July 2016, in circumstances where there was a
direction from the Superintendent to rectify the defective two-pipe system to
facilitate the performance of the Independent Heating/Cooling Function.417
(l) Mr Cook gave evidence that the design for the three-pipe mechanical system
was finalised on 23 August 2016, including the number and type of condensers
and branch boxes.418
[1075] Mr Cook was cross-examined about whether the plaintiff could have placed the order
for the condensers on 23 August 2016 and whether that was a reasonable step in the
circumstances. Mr Cook’s evidence was that he did not believe so, as the Mechanical
Variation did not allow the plaintiff to use Toshiba equipment.419
[1076] The defendant submits that this should not be accepted where:
(a) The plaintiff ultimately did use Toshiba equipment;
(b) On or about 14 October 2016, Batec ordered the Toshiba condensers;
(c) The design had been finalised since 23 August 2016;
(d) Whilst without prejudice discussions had been occurring as to whether or not
Toshiba was “approved”, contractually the plaintiff was required to carry out
the Mechanical Variation;
(e) Nothing between 11 August 2016 and 14 October 2016 changed that position;
(f) On multiple occasions the Superintendent confirmed that the Mechanical
Direction was “current and valid”.420
[1077] The defendant submits “at the very least” it was reasonable to contact Toshiba on 23
August 2016 and make some sort of arrangement for the condensers to be available
at a later date, particularly where the plaintiff knew the condensers were time
sensitive. This was not done.
[1078] In these circumstances, the defendant contends:
(a) Pursuant to clause 34.3(f) the plaintiff is not entitled to an extension of time for
the whole period claimed as it failed to take all reasonable steps to mitigate the
effect of the delay.
(b) Alternatively, the plaintiff should have placed the order for the condensers on
23 August 2016 and accordingly, any extension of time would be limited to 62
days (which excludes the Christmas shutdown period as discussed further
below).
416 T2-11, L27-40.
417 Defendant’s written closing submissions at [149].
418 T2-13, L36-T2-14, L14; PRO.071.001.0004.
419 T2-17, L5-13.
420 16 August 2016, 31 August 2016 and 17 September 2016.
-- 180 of 210 --
181
[1079] Clause 34.3(f) requires the plaintiff to have taken all reasonable steps to mitigate the
effect of the delay. Even acknowledging that the plaintiff may have had justification
for arguing its position in respect of the requirements of the Contract and the
direction, the requirement of “reasonable steps” may result in a need for the plaintiff
to have acted at an earlier point in time.
[1080] Here, the parties were clearly taking entirely opposing positions from the time the
Mechanical Direction was given as to whether it was an instructed variation or not.
There are strong factors which point towards the need to have taken steps, particularly
where the plaintiff was aware of the likely effect of any delay. By 5 August 2016,
the plaintiff estimated a six week timeframe to procure the branch boxes and an 80
day impact on completion. It was in this context that the plaintiff pressed the
defendant for a direction, resulting in the Mechanical Direction.
[1081] From that time onwards, the plaintiff acting reasonably would have been aware that
the delay would increase if steps were not taken to order the necessary equipment.
[1082] The design for the three-pipe mechanical system was finalised on 23 August 2016,
which included the number and type of condensers and branch boxes.
[1083] Accordingly, a contractor acting reasonably would have taken steps to mitigate the
delay at least by 23 August 2016 when the design was finalised.
[1084] Whilst the plaintiff says the use of Toshiba was still uncertain, that did not mean that
the plaintiff was entitled to take no steps. Reasonable steps would include
considering arrangements to reserve condensers so they were available. This is
particularly so given the awareness that the condensers were time sensitive.
[1085] It is clearly open that the plaintiff should have taken reasonable steps to mitigate the
effect of delay from 11 August 2016 when the Mechanical Direction was received. It
was clear that the procurement time for the necessary equipment was a key factor in
the delay. Pursuant to clause 34.3(f), this would result in the plaintiff not being
entitled to an extension of time for the whole period claimed.
[1086] However, I accept that until the design was finalised, arguably it was not reasonable
to be required to place orders for equipment as the number of branch boxes and
condensers was not known.
[1087] If it is necessary to consider the operation of clause 34.3(f) of the Contract, I find that
the plaintiff should have placed the order for the condensers no later than 23 August
2016. Placing the order for the condensers after that was a failure to take all
reasonable steps to mitigate the effect of the delay.
Contribution to cause of delay
[1088] The defendant contends that the plaintiff contributed to the cause of delay by failing
to provide detailed shop drawings of the mechanical system prior to construction.
[1089] Even if the plaintiff overcomes the hurdle of the notice provision in clause 34.3(b) of
the Contract, the defendant submits that the plaintiff is still not entitled to an extension
of time because of the operation of clause 34.3(d).
-- 181 of 210 --
182
[1090] Clause 34.3(d) provides that “the Contractor or others for whom it is responsible did
not contribute to the cause”. As each of the subclauses needs to be satisfied, if the
plaintiff did contribute to the cause of the delay then the claim for an extension of
time must fail.
[1091] The relevant provisions relied upon by the defendant are:
(a) Clause 8.3 of the Contract which states:
“8.3 Contractor-supplied documents
The Contractor shall submit the proposed design documents to the
Superintendent within the time periods specified in Item 17 and, in
any event, not later than 20 business days before the Contractor
proposes to issue those design documents for construction.”
(b) Item 17 of the Contract provides that the design documents are to be supplied
“Prior to WUC contained in those design documents being undertaken”.
[1092] Consequently, the defendant submits that the plaintiff was required to submit design
documents to the Superintendent no later than 20 business days before the plaintiff
proposed to issue those documents for construction.
[1093] Further, the defendant relies on clause 8.8 of the Contract which provides as follows:
“8.8 Shop Drawings
The Contractor shall prepare shop drawings as part of the design
documents which shall:
….
(b) include layouts and details of all plans, equipment and
installation, including plinths and bases, penetrations, pipework
and valves, ductwork, registers and grilles, conduit runs,
control and power wiring, chases, cores and penetrations (as
applicable);
…
(f) show sufficient information to enable the Superintendent and
other appropriate consultants to check that the equipment can
be installed, operated, adjusted and maintained in the manner
for which the system, into which they are to be incorporated,
was designed …”
[1094] Clause 8.8 operates to provide an opportunity for the Superintendent to consider the
drawings and to notify of any amendments. It enables the Superintendent to
understand how the trades and services will operate, including the mechanical
services system.
-- 182 of 210 --
183
[1095] Reading clauses 8.3 and 8.8 together, shop drawings would need to be issued
approximately six weeks before installing the duct work.421 Mr Cook also agreed that
a period of six weeks was reasonable.422
[1096] The defendant estimates that the shop drawings should have been provided to the
Superintendent for at least level one by 3 November 2015.423 This is based on:
(a) The mechanical works were to be installed from the ground up in accordance
with the Baseline Program in Annexure Part F of the Contract.424
(b) The guest rooms on level one had “rough-in” to commence on 15 December
2015.425
[1097] The plaintiff did not provide any shop drawings of the mechanical system to the
Superintendent.426
[1098] A request was made by Thwaite to the plaintiff on 2 December 2015 for shop
drawings to be provided so that outstanding items in respect of the mechanical system
could be closed out.427
[1099] On 10 December 2015, the Superintendent repeated the request.428
[1100] On 7 June 2016, the Superintendent was requesting the shop drawings be provided
“as a matter of urgency”. The email states:
“On the basis that mechanical services are being roughed in to
numerous levels, workshop drawings should be readily available and
it would be appreciated if you could arrange for them to be issued for
our review as a matter of urgency”.429
[1101] The defendant contends that as late as July 2016 the plaintiff had not provided shop
drawings despite the fact that the mechanical work was 25 to 30 per cent complete
and the plaintiff had progressed mechanical rough-in works up to levels six, seven
and eight.430
[1102] The defendant’s position is that had the shop drawings been provided for level one
by 3 November 2015 prior to the installation of the mechanical services system as
required, then the defendant would have become aware that the mechanical system
being installed could not perform the Independent Heating/Cooling Function.
421 Mr King gave evidence that based on his experience a period of two weeks after the shop drawings
had been issued would be needed to manufacture the mechanical duct work before commencing
construction. EXP.001.001.0858 at p 0898 [140].
422 T1-78, L1-3.
423 EXP.001.001.0858 at p 0899 [147]. The reference in Mr King’s report to 2016 should be a reference
to 2015.
424 BUI.001.001.61820 at p 0103; EXP.001.001.0858 at p 1046.
425 Activity 377; EXP.001.001.0858 at p 0899 at [147].
426 WIT.001.001.0224 at p 0232 [48]; WIT.001.001.0002 at p 0030 [167]-[169].
427 BUI.001.001.71393 at p 0001.
428 BUI.001.001.71393.
429 PRO.017.001.1160 at p 0002.
430 WIT.001.001.0002 at p 0033 [195]–[196].
-- 183 of 210 --
184
[1103] The effect on delay, is that the defendant submits that the Mechanical Variation would
have been issued around late 2015, rather than 11 August 2016, avoiding the critical
delay now claimed.
[1104] The plaintiff in response to this allegation says that the defendant’s contention is not
supported in a number of respects, including:
(a) On 10 June 2016, the plaintiff provided schematics for the air conditioning
system.431
(b) The piping systems disclosed by the piping schematics were materially
identical to those reviewed by Thwaite before the Contract was executed on 29
April 2016.432
(c) The plaintiff says as a result Thwaite and the defendant knew that the
alternative proposal was for a two-pipe VRF heat pump system, which did not
provide independent heating and cooling to individual rooms.
(d) The non-provision of shop drawings could not be said to have contributed to
the defendant or Thwaite not being aware that the alternative proposal did not
provide for independent heating and cooling to individual rooms.
(e) No one from Thwaite was called to give evidence and a Jones v Dunkel433
inference should be drawn that the evidence of Mr Thwaite or Mr Van Grootel
would not have assisted the defendant.434
[1105] In response the defendant submits:
(a) None of the correspondence states that the alternative proposal could not
perform the Independent Heating/Cooling Function.
(b) The evidence does not support the plaintiff’s attempt to impute knowledge that
the two-pipe VRF system could not by virtue of its design provide the
Independent Heating/Cooling Function.
(i) Mr Collison of the Superintendent was called by the defendant. His
evidence was that:
(A) at the time of the Contract formation he knew the alternative
proposal was a two-pipe VRF heat pump system.
(B) he did not know that a two-pipe VRF heat pump system could not,
as a matter of design, perform the Independent Heating/Cooling
Function; and
(C) he did not know that the alternative proposal offered by the
plaintiff could not perform the Independent Heating/Cooling
Function.435
431 BUI.001.001.71436; BUI.001.001.67836; BUI.001.001.26910; BUI.001.001.26911;
BUI.001.001.26912; BUI.001.001.26913; BUI.001.001.26914.
432 Plaintiff’s written closing submissions at [212].
433 (1959) 101 CLR 298.
434 Plaintiff’s written closing submissions at [212].
435 T4-23, L34-T4-34, L22.
-- 184 of 210 --
185
(c) There is no evidence that pre-contractually the Superintendent knew the
alternative proposal could not perform the Independent Heating/Cooling
Function.
(d) The defendant did not call Mr Paul Davis who was the technical director pre-
Contract as he had passed away.436
(e) Mr McBirnie took over from Mr Davis and was responsible for the day to day
management of the Spring Hill Hotel on behalf of the defendant. Mr McBirnie
had no understanding of technical matters in respect of the mechanical services
system.437 Further, there is no evidence that prior to June 2016 anyone told Mr
McBirnie that the alternative proposal did not provide the Independent
Heating/Cooling Function.
[1106] Further, in respect of the plaintiff’s contention that Thwaite had this knowledge and
a Jones v Dunkel inference should be drawn as Mr Thwaite and/or Mr Van Grootel
were not called to give evidence, the defendant submits:
(a) A Jones v Dunkel inference is only available if there is evidence that Mr
Thwaite and Mr Van Grootel knew that the alternative proposal could not
perform the Independent Heating/Cooling Function. That is not the case here.
(b) Mr Thwaite and Mr Van Grootel were available to both parties. A Jones v
Dunkel inference cannot operate where a witness is available equally to both
parties.438
(i) Thwaite was engaged as independent mechanical consultants by the
Superintendent, not the defendant.
(ii) Mr McBirnie gave evidence that the last time he had anything to do with
Mr Thwaite or Mr Van Grootel was a few years ago.439
(c) Even if Thwaite had the alleged knowledge (which has not been proven),
Thwaite did not tell the Superintendent, who consequently did not tell the
defendant.
[1107] The defendant submits that the plaintiff cannot seek to use a Jones v Dunkel inference
to, in effect, fill gaps in the evidence.440
[1108] The case of Shum Yip Properties v Chatswood Investment & Development441 confirms
that:
“… The making of a Jones v Dunkel inference depends upon the
closeness of the relationship of the absent witness with the party who
did not call him.”
436 WIT.001.001.0275 at [5].
437 T6-18, L14-15.
438 Claremont Petroleum NL v Cummings (1992) 110 ALR 239 at 259.
439 T6-16, L30-37.
440 In the matter of Azmac Pty Limited (in liquidation) [2020] NSWSC 204 [49] (Rees J); Ronchi v
Portland Smelter Services Ltd [2005] VSCA 83 [81] (Nettle JA); Cook’s Constructions Pty Ltd v Stork
Food Systems Australia Pty Ltd [2008] QSC 179 [51]-[52] (Martin J).
441 [2002] NSWSC 13 at [64] per Austin J.
-- 185 of 210 --
186
[1109] Clause 34.3(d) of the Contract requires consideration of whether the plaintiff
contributed to the cause of the delay. Clause 8.3 of the Contract requires design
documents to be provided to the Superintendent 20 days in advance of being issued
for construction.
[1110] Further, clause 8.8 of the Contract requires shop drawings to also be provided to
enable the Superintendent to be able to check them clearly, these provisions provide
an opportunity for the Superintendent to consider the design drawings and to notify
any amendments. This includes the opportunity to understand how equipment and
services are to be installed, including the mechanical services system.
[1111] Here, shop drawings should have been provided by at least 3 November for level one.
No shop drawings of the mechanical services system were provided to the
Superintendent, despite request.
[1112] This is a design and construct contract and clearly, further design work was to be
undertaken by the plaintiff. This included the mechanical services system. In this
context, prompt provision of design documents and shop drawings in advance is a
critical component of the contractual objections. This enables the Superintendent to
consider the design and shop drawings and then to take appropriate steps under the
Contract. This may be to approve the design, to amend the design, to require the
design to be redone to comply with the Contract or even to vary the Contract to allow
the proposed design to proceed.
[1113] Without the provision of the design drawings and shop drawings sufficiently in
advance the process under the Contract is not engaged. The Contract clearly
envisages the design process being an on-going dialogue and ultimately requiring
approval.
[1114] Non-compliance with these clauses is established. The issue is whether this non-
compliance contributed to the cause of the delay.
[1115] This largely turns on whether the Superintendent had knowledge that the alternative
proposal could not perform the Independent Heating/Cooling Function. There is no
direct evidence that the Superintendent knew.
[1116] The plaintiff contends that Thwaite had this knowledge and seeks a Jones v Dunkel
inference as Mr Thwaite and Mr Van Grootel were not called to give evidence.
However, I do not consider that such an inference is open in the circumstances of this
case. I accept the defendant’s submissions in this regard. In particular, there is no
evidence that either Mr Thwaite or Mr Van Grootel knew that the alternative proposal
could not perform the Independent Heating/Cooling Function and this would need to
be present to support an inference.
[1117] In the circumstances, I find on the balance of probabilities that the failure to provide
the design documents and shop drawings in advance to the Superintendent as required
by the Contract contributed to the cause of the delay.
[1118] If the issue with the air conditioning system had been identified earlier then steps
could have been taken. This is particularly so if the shop drawings had been provided
for level one by 3 November 2015, as this was prior to the installation of the
mechanical services system.
-- 186 of 210 --
187
[1119] I accept that if the design documents and shop drawings had been provided at this
time, the Mechanical Variation could have been issued in late 2015 or early 2016 and
the consequential delay could have been substantially mitigated.
[1120] Accordingly, if it is necessary to consider the plaintiff’s entitlement to an extension
of time, for the purposes of clause 34.3(d) I find that the plaintiff contributed to the
cause of delay by the failure to provide design documents and shop drawings as
required by clause 8.5 and clause 8.8 of the Contract.
Christmas shutdown
[1121] Mr King’s report reduces the delay by 17 days on the basis of a “Christmas shutdown”
period at the end of December 2016 and at the beginning of January 2017. This is in
dispute between the parties.
[1122] While this is raised in Mr King’s report, the plaintiff objects to the assumption on the
basis that there is no further explanation provided for it.442
[1123] The joint report of Mr Bell and Mr King further refers to it as being the period Mr
King claims to be the on-site Christmas shutdown.443
[1124] The plaintiff points to the lack of an explanation as to why the manufacturers of the
condensers would have had a similar shutdown as the site work.444
[1125] In cross-examination, Mr King referred to this being based on his knowledge of
shutdown periods in New Zealand manufacturing. However, the plaintiff submits
that this evidence should not be accepted.
[1126] This is particularly so due to the lack of precision and detail in the evidence. The
plaintiff points to the following evidence of Mr King as illustrating this:
(a) Typically all manufacturing factories in New Zealand shutdown from just
before Christmas through until mid-January.445
(b) In New Zealand everything shuts down for nearly three weeks.446
(c) There was a code in New Zealand, applicable to manufacturing, which
mandates the shutdown period.447
[1127] On further questioning on this last point, Mr King said he could not say it applied to
every manufacturing plant in New Zealand, he did not know if it had the force of law
and ultimately he did not think it had the force of law.448
[1128] As to the actual impact of the delay claimed, Mr King could not say whether the
manufacture of the condensers had been completed by Christmas 2016 so it remains
unclear whether the shutdown would have had any impact or not.449
442 EXP.001.001.0858 at [259].
443 EXP.001.001.1325 at p 1338. See also T11-18, L43.
444 EXP.001.001.1325 at p 1338.
445 T11-19, L1-4-T11-20, L18.
446 T11-19, L9-10.
447 T11-19, L29-39.
448 T11-19, L41-47-T11-20, L1-7.
449 T11-19, L20.
-- 187 of 210 --
188
[1129] The plaintiff submits that if the shutdown did extend to the middle of January 2017,
it is not likely that the manufacture of the condensers could have been completed after
that date and then shipped to Brisbane and delivered to site by 28 January 2017.450
[1130] The plaintiff submits that the exclusion of 17 days for the Christmas shutdown has no
validity and should be rejected.
[1131] In respect of the exclusion by Mr King of 17 days for the Christmas shutdown, I find
that there is insufficient evidence to establish the basis for this conclusion.
[1132] Accordingly, if it is necessary to consider the plaintiff’s entitlement to an extension
of time, I find that the 17 day period from the end of December 2016 and the
beginning of 2017 should not be excluded on the basis identified by Mr King in his
report.
Claim for EOT
[1133] It is necessary to consider the competing delay analysis reports of Mr Bell and Mr
King. Their opinions, however, must be considered in light of the findings set out
above.
[1134] These reasons set out certain findings in respect of the delay analysis, but it may be
necessary for further consideration to be given to the calculation of the delay period
and any extension of time in light of all the reasons.
[1135] Mr Bell’s report uses a prospective delay analysis. The plaintiff summarises the
approach adopted by Mr Bell to assess delay as follows:
“(a) First, Mr Bell identifies the program statused immediately prior
to the delay event. Mr Bell then reviews that program to ensure
that it is reasonable to be used and, if not, make necessary
corrections to the program (this is referred to as the Baseline
Program). This Baseline Program is then used to determine the
forecast date of practical completion prior to the delay event;
(b) Second, Mr Bell impacts the Baseline Program with the delay
event and determines the revised forecast date of practical
completion, having regard to clause 34.5 of the Contract (this
is referred to as the Impacted Program);
(c) Third, Mr Bell calculates the difference between the forecast
date of practical completion in the Baseline Program and in the
Impacted Program. The difference is the delay period for the
delay event;
(d) Fourth, Mr Bell analyses the delay period pursuant to clause
34.4 of the Contract for any overlapping delay that may be a
non-qualifying cause of delay. If such a delay is identified, it is
apportioned accordingly; and
450 Plaintiff’s written closing submissions at [390(d)].
-- 188 of 210 --
189
(e) Fifth, the delay period resulting from the delay is added to the
then current date for practical completion to determine a
revised date for practical completion.”
[1136] In line with the first step above, Mr Bell identified the plaintiff’s Status Program dated
1 August 2016451 as the “current program” that existed prior to the Mechanical
Variation on 11 August 2016.
[1137] Mr Bell then makes a series of corrections to the Status Program dated 1 August 2016
before adopting it as his Baseline Program.452 These corrections were identified as
arising out of the following:
(a) The installation of mechanical and hydraulic plant and equipment on the roof
was to commence on 11 August 2016.
(b) The date for practical completion was 11 November 2016.
(c) The handover of levels 11 and 12 was to occur on 14 and 16 November 2016,
after the date of practical completion, as a result of errors in sequencing.
[1138] As a result, the date of practical completion was changed to 17 November 2016. The
extension of the date in effect reduces any delay.
[1139] The corrected program is referred to as the “Corrected Status Program 1 August
2016”.453 Mr King agrees with these corrections and the change to the date for
practical completion.454
[1140] The next step is that Mr Bell impacted the Corrected Status Program 1 August 2016
with the additional activities required as a result of the Mechanical Variation, namely:
(a) 1 week mobilisation period for design and ordering of plant and equipment,
with two crews: one crew working levels one to six, and one crew working
levels seven to 12.
(b) 12 week procurement period for the condensers, with a further 12 days for
installation.
(c) 5 week procurement period for the branch boxes, with a further 14 days for
instalment over 12 floors.455
[1141] The Impacted Program456 produced from this exercise results in a delay of 107 days,
with a forecast date of practical completion of 4 March 2017.457 Mr Bell considers
that this is critical delay as the final commissioning/testing cannot be carried out until
the condensers are installed.458
451 BUI.001.001.14712.
452 EXP.001.001.0705 at [71]-[73].
453 Attachment 6 to Mr Bell’s Report EXP.001.001.0705.
454 EXP.001.001.0858 at [175].
455 EXP.001.001.0705 at [77].
456 Attachment 7 to Mr Bell’s Report EXP.001.001.0705.
457 EXP.001.001.0705 at [79].
458 EXP.001.001.0705 at [81(c)].
-- 189 of 210 --
190
[1142] The plaintiff claims a total of 117 days. This is as a result of the actual date of delivery
of the condensers being 10 days later than forecast, with their delivery to site on 28
January 2017.459
[1143] In respect of the additional 10 days:
(a) Mr Bell considers that the plaintiff would have been entitled to an additional
EOT of 10 days for the further delay in the delivery of the condensers and he
prepared a further Impacted Program reflecting this.460
(b) The plaintiff’s EOT claim submitted on 28 October 2016 was rejected by the
Superintendent.461 The plaintiff submits that while it could have submitted a
further EOT claim for the 10 days pursuant to the last paragraph of clause 34.3
of the Contract, it was futile in circumstances where the Superintendent had
already decided the Mechanical Variation was not a qualifying cause of
delay.462
(c) Mr Bell was cross-examined in respect of this issue but the plaintiff contends
that the cross-examination was misconceived. The approach is still prospective
and is consistent as it is the calculation of a “forecast date of practical
completion”.463
(d) The forecast date of practical completion under the further Impacted Program
is 14 March 2017, with 117 calendar days of delay compared to the Corrected
Status Program 1 August 2016.
[1144] The defendant is critical of the approach taken by Mr Bell.
[1145] The first criticism is the use of a prospective delay analysis methodology. The
defendant submits this is theoretical by its very nature: it captures “likely effects” at
the time the delay event occurred, as opposed to the actual delay that resulted from
the delay event.
[1146] Mr Bell was aware there were issues with the methodology he adopted,464 but he gave
evidence that he thought he was compelled to adopt the prospective analysis due to
clauses 34.3 and 34.5 of the contract.
[1147] On the basis that the defendant says either methodology was open under the
Contract,465 the defendant submits a retrospective analysis is the most appropriate
methodology to adopt, particularly given the context in which the assessment of the
entitlement must be made. That is, assessing the entitlement over four years after the
delay event occurred by calculating the actual delay to the WUC by reference to
contemporaneous project documents and the approved construction program as
updated from time to time subsequent to the Mechanical Variation.466
459 BUI.001.002.31204.
460 Attachment 8 to Mr Bell’s Report EXP.001.001.0705.
461 BUI.001.0001.09841; BUI.001.001.61955.
462 Plaintiff’s written closing submissions at [367].
463 Plaintiff’s written closing submissions at [367].
464 EXP.001.001.0705 at p 0725 [48]-[49].
465 This position is consistent with my finding earlier in these reasons.
466 Defendant’s written closing submissions at [184].
-- 190 of 210 --
191
[1148] Mr King described the comparison of the two approaches as follows:
“Why look in the crystal ball when you can read the book?”467
[1149] The defendant’s second criticism is that Mr Bell failed to do his analysis in
incremental windows, which was contrary to the requirements of the Contract. This
also is said to exacerbate the theoretical nature of the analysis.
[1150] Clause 34.3(c) refers to the qualifying cause of delay affecting the “critical path …
as shown on the approved construction program”. Clause 1 defines “approved
construction program” to mean:
“(a) the original approved construction program set out in Annexure
Part F; and
(b) any revised approved construction program approved by the
Superintendent from time to time pursuant to subclause 32.2”.
[1151] Clause 32.2 relevantly includes as follows:
“(b) The approved construction program will be used by the
Contractor and the Superintendent to:
(i) convey information to the Superintendent about the
construction and commissioning of the Works;
(ii) measure and report on the progress of the Works towards
meeting the date for practical completion; and
(iii) assess delays and any EOT.
(c) The Contractor must revise the approved construction
program and issue 3 hard copies and a compact disc containing
an editable electronic version of the approved construction
program in Microsoft Project format of the revised approved
construction program to the Superintendent within 5 business
days after:
(i) the last day of each month; and
(ii) being notified of an EOT being granted under the Contract.
…
(e) Each revised approved construction program submitted to the
Superintendent must be based upon information current at the
time of submission prepared in the form of a computer
generated critical path network logic chart presented as a
cascade diagram showing:
(i) the sequence and duration of all activities and identifying
activities constituting the critical path and the
interrelationship between activities including design,
documentation, procurement, construction commissioning
467 EXP.001.001.0858 at p 0894 [118].
-- 191 of 210 --
192
and finalisation activities and including float for activities
not on the critical path …
…
(g) Within 15 business days after receipt, the Superintendent must
review a revised approved construction program to assess
conformity with the presentation and technical requirements
specified in subclause 32(g) and either:
(i) approve the revised approved construction program, or
(ii) request the Contractor in writing to amend the revised
approved construction program.
If the revised approved construction program is approved by the
Superintendent, the Contractor must submit to the Superintendent the
approved construction program in the format described in subclause
33(c) indicating the date of the program within 5 business days of the
approval by the Superintendent …” (emphasis added)
[1152] What is encompassed by the “approved construction program” is therefore the
original approved program, which is then updated by the plaintiff within 5 business
days at the end of each month and after being notified of an extension of time. The
result is that the approved construction program was regularly updated and was to be
used for progress reporting and to assess extensions of time.
[1153] The defendant submits the requirements of clauses 1 and 32.2 of the Contract have a
consequential effect in that the delay analysis must be done incrementally, regardless
of which method is used.468
[1154] An incremental review is also consistent with good industry practice. In support of
this contention the defendant points to:
(a) Core Principle 7 of the Society of Construction Law Delay and Disruption
Protocol which states:
“7. Incremental review of EOT
Where the full effect of an Employer Risk Event cannot be
predicted with certainty at the time of initial assessment by the
CA, the CA should grant an EOT for the then predictable effect.
The EOT should be considered by the CA at intervals as the
actual impact of the Employer Risk Event unfolds …”469
(b) Keith Pickavance in the text “Delay and Disruption in Construction Contracts”
states:
“Unless the omission to be impacted is of short duration, say
less than four weeks long, it will rarely be appropriate for the
duration of the omission to be impacted in full from its
commencement. For omissions, or failures to perform lasting
468 Defendant’s written closing submissions at [167].
469 PRO.071.012.0009 at p 0032.
-- 192 of 210 --
193
longer than four weeks, a ‘windows’ approach to its impacting
should normally be adopted.”470
(c) PJ Keane’s text “Delay Analysis in Construction Contracts” states:
“Inserting fragnets [activities] with excessive durations
(spanning several updating cycles) will effectively override
progress achieved during that entire period and will not allow
the base programme to account for any delays due to
concurrent events, lack of progress or logic changes
implemented in the relevant monthly updates. This might
prevent potentially critical delay events from emerging as
critical until the conclusion of the fragnet. Every attempt
should be made to make the fragnets as discrete as possible so
the impact of each event can be limited to the period of time
being analysed. Breaking events into bite-sized chunks for
analysis is one of the reasons the TIA [time impact analysis]
approach is known as being labour intensive and technically
complex. The longer the fragnet, and the longer the duration
between each base programme, the more prospective and
theoretical the results will be.
If the TIA is used prospectively, the analysis will produce
‘likely effects’ of delays. If the fragnets are as discrete as
possible, limited to durations less than a single updating cycle
(i.e. 30 days), and if those fragnets rely on actual durations, the
results are going to be closer to the actual effect of delay
experienced and mitigated from progress update to progress
update.”471
(d) Andrew Burr in his text “Delay and Disruption in Construction Contracts”
identifies that where a schedule is updated on a regular basis for example
monthly, then that can be used for the relevant “window”. Further, this
approach provides “the only way in which the true effect of an event can be
analysed to take account of all its consequential effects and concurrency during
the course of a building contract”.472
[1155] Mr King’s view is that it is necessary to incrementally review delay over successive
programs because the critical path may change resulting in an incorrect view on the
extent of the critical delay.473
[1156] Mr Bell assumed that the Status Programs provided to him were Approved
Construction Programs but then proceeds to use the 1 August 2016 Program (which
he corrected) to impact the delay. This is despite two or three programs per month
being prepared by the plaintiff in the period after the Mechanical Variation.474
470 PRO.071.012.0008 at p 0003; EXP.001.001.0858 at [127].
471 PRO.071.012.0007 at p 0002.
472 PRO.071.012.0006 at p 0003 [15.162-6].
473 The float values of activities may also change. EXP.001.001.0858 at [127].
474 EXP.001.001.0705 at p 0782.
-- 193 of 210 --
194
[1157] The defendant contends that the use of the single Corrected 1 August 2016 Program
was contrary to the Contract and also contrary to accepted practice. It also increases
the prospective and theoretical nature of the analysis.
[1158] The third criticism of Mr Bell’s approach is that he has selectively mixed a
prospective and retrospective approach, which has the effect of increasing the period
of delay.
[1159] This issue concerns the delivery of the condensers:
(a) 107 days was inserted into the corrected 1 August 2016 Program for the
delivery of the condensers. This was based on the plaintiff’s estimate, with
the condensers having a delivery date of 16 January 2017.475
(b) But the condensers were actually delivered on 28 January 2017, 10 days
later.476
[1160] Mr Bell adjusted the date arrived at by the prospective time impact analysis by
retrospectively impacting the program with the 10 additional days. The defendant
submits that this is not appropriate.
[1161] The defendant says Mr Bell either must accept the date originally arrived at or he
should account for all subsequent progress after the Mechanical Direction. He cannot
select one activity and retrospectively use it. This may result in an over calculation
of delay as there is no consideration of other activities that could reduce the delay or
entitlement to an extension of time.477
[1162] The defendant submits that Mr King’s analysis should be preferred for the following
reasons:
(a) The retrospective as-planned as-built analysis is not theoretical, it is “grounded
in reality”.
(b) Mr King uses a “windows” analysis and assessed the extent of delay by
reference to the approved construction program as revised by the plaintiff from
time to time (as required by the Contract).478
(c) This analysis shows that the façade works “slipped” beyond 16 August 2016
as shown on the corrected 1 August 2016 Program until 8 November 2016
when the condenser delivery fell on to the critical path. This is not considered
in Mr Bell’s analysis.479
(d) The slippage in the façade works was due to the plaintiff’s failure to perform.480
(e) Mr Bell agreed that the façade works were unaffected by the Mechanical
Direction.481
475 EXP.001.001.0705 at p 0735 [78].
476 EXP.001.001.1325 at p 1333.
477 Defendant’s written closing submissions at [194]–[195].
478 EXP.001.001.0858 at pp 0894-7 [116]–[117], [124] and [134].
479 EXP.001.001.0858 at pp 0921-0940 [193]-[258].
480 EXP.001.001.0858 at pp 0929-0940 [212]–[217], [223]–[224], [240]–[243] and [258]–[263].
481 T10-51, L44-T10-52, L39; T10-56, L23-T10-59, L43.
-- 194 of 210 --
195
[1163] The defendant’s ultimate position is:
(a) 62 days of delay, if the plaintiff should have ordered the condensers on 23
August 2016 when it finalised the three-pipe design; or
(b) a maximum of 81 days of delay, if the condensers were ordered after 14
October 2016.
[1164] If the condensers were ordered:
(a) on 17 August 2016, there would have been no critical delay.
(b) prior to 14 October 2016, there would be a reduction in the period of critical
delay.
[1165] The issue of the Christmas shutdown period arises if the condensers should have been
ordered by 23 August 2016. The defendant contends that the date for installing and
commissioning would fall on 23 December 2016 in the Christmas shutdown period.
This would further push it out to 9 January 2017. That is an additional 17 days plus
the original six days, but the critical delay should be 62 days.
[1166] The plaintiff is critical of Mr King’s approach, including as follows:
(a) Mr King attempts to bring the date for practical completion forward to 27
October 2016. The plaintiff maintains that to do this is wrong.
(b) Mr King makes certain assumptions about when the shop drawings should have
been received.
(c) Mr King calculates dates when the plaintiff was expected to deliver
construction programs.
(d) At paragraph 168 of Mr King’s report, Mr King makes certain assumption,
namely that:
(i) The plaintiff should have ordered the mechanical equipment on 18
August 2016, which is wrong.
(ii) Only limited work on the mechanical system occurred between 12
August 2016 and 29 September 2016. The plaintiff submits this is
imprecise and refers to the statement of Mr Cook as to the work that was
done in this period.482
(iii) On 29 September 2016, the plaintiff instructed Batec to continue with
the two-pipe system. This is correct. However, Mr King goes on to
assume “[t]he effect of this was that follow-on trades would in turn be
installing redundant work from 29 September to 14 October 2016 which
would need to be removed”. The plaintiff says this is wrong as far as it
suggests that the “redundant work” is the plaintiff’s responsibility.
(iv) On 14 October 2016, the plaintiff instructed all subcontractors that the
mechanical system was being changed and to stop work in the affected
areas. This is correct.
482 WIT.001.004.0001 at [280]–[316].
-- 195 of 210 --
196
(e) Mr King forms the view that by 14 July 2016 the plaintiff was 42.5 days behind
schedule. This is said to be based on a comparison of the Impacted Program
and the approved construction program.483 The plaintiff raises a number of
points in response, including:
(i) Being behind at a point in time is not determinative that practical
completion will not be reached by the date for practical completion as
the works could be accelerated to achieve it.
(ii) Mr King seems to accept that the plaintiff was scheduled to achieve the
adjusted date for practical completion of 17 November 2016.484
(iii) The critical path shifted to the installation of the mechanical plant on the
issuing of the Mechanical Variation. As a result other activities,
including the level 13 roof slab pour, gained float such that any delay to
that activity was no longer critical.
(iv) The Status Programs of 3 September 2016 and 27 September 2016 were
incorrect as they do not show any reference to the Mechanical Variation.
They cannot therefore be relied upon in any retrospective analysis.
(v) A fundamental defect in Mr King’s analysis is that he uses a Status
Program dated 18 October 2016 to assess the effect of the Mechanical
Variation. This could only be used as the starting point if the program
did not already include delay resulting from the Mechanical Variation.
The plaintiff contends that it did.
(A) Mr King fails to address what Mr Bell says at B11 of the joint
report that the programs prior to 26 October 2016 do not contain
any activities relating to the changes required by the Mechanical
Variation and as a consequence there is no reliable critical path in
those programs.
(B) The key issue is where the critical path would be if they did
contain the activities required by the Mechanical Variation.
(C) If the procurement of the mechanical plant was critical, then the
previous critical activities were no longer critical. This would
include the activities relating to the façade, which then had in
effect plenty of time to be completed.
(D) The delay caused by the Mechanical Variation commenced well
before 18 October 2016.485 The 1 August 2016 program was the
last program which was unaffected by the Mechanical Variation.
This is evident when looking at the dates scheduled for the
mechanical installation which has a “slip” of 63 days for the early
finish dates and 32 days for the late finish dates. This was because
the work could not advance until a decision was made on the
mechanical system to be installed. This issue was not addressed
by Mr King.
483 EXP.001.001.0858 at p 0921 [188].
484 EXP.001.001.0858 at [196]-[197].
485 WIT.001.004.0001 at [282], [283] and [311].
-- 196 of 210 --
197
(E) The 32 day delay by the 18 October 2016 program should be added
to the 83 days assessed by Mr King as the delay to the date for
practical completion, resulting in a delay of 115 days using Mr
King’s approach properly applied.
(f) As a result of the issue with the 18 October 2016 program, the plaintiff contends
that even if a retrospective analysis is used, when it is properly applied it
validates Mr Bell’s conclusion. That is:
(i) Mr Bell concludes 117 days of delay.
(ii) If apply Mr King’s corrected analysis:
(A) If assess the effect on the date for practical completion, 112 days
of delay.
(B) If assess the effect on the particular activity, 115 days of delay.
[1167] The plaintiff is also critical of the analysis undertaken by Mr King to effectively
reduce the delay of 83 calendar days486 to zero. This includes:
(a) Using the specific activity in the 18 October 2016 program that was delayed.
The activity had a late finish date and Mr King uses that date to calculate 81
calendar days of delay (from the late finish date of 8 November 2016 to 28
January 2017). Mr King provides no reason for this conclusion.
(b) That the mechanical plant should have been ordered much earlier.487
(c) Taking into account a Christmas shutdown of 17 days.488
[1168] If it is necessary to consider the plaintiff’s claim for an extension of time and it is
necessary to consider the expert reports in respect of the analysis of the delay. I make
the following findings:
(a) Consistent with my earlier findings under the Contract it is open to consider a
prospective or a retrospective delay analysis.
(b) Mr King’s incremental delay analysis is to be preferred as it more closely
accords with the requirements of the Contract in clauses 1, 32.2 and 34.3(c).
(c) Mr King’s analysis needs to be further considered in light of the other findings
in these reasons, including in respect of the Christmas shutdown period.
Delay Damages
[1169] The plaintiff claims that the defendant is liable to the plaintiff for an amount of
$1,001,815 plus GST for delay damages in respect of the Mechanical Variation. To
get to the point that this claim needs to be considered, the plaintiff needs to establish
that:
486 The 18 October 2016 program has a date for practical completion of 16 December 2016. If the 26
October program is adjusted for the actual date of plant procurement, the scheduled date for practical
completion is 9 March 2017. The difference between the two due to the Mechanical Variation is 83
days.
487 See separate discussion of issue.
488 See separate discussion of issue.
-- 197 of 210 --
198
(a) the requirement to do the work set out in the Mechanical Direction was a
variation under the Contract;
(b) the plaintiff performed the work;
(c) the variation caused a delay to the date for practical completion; and
(d) the plaintiff is entitled to an extension of time under clause 34.3 of the Contract
of 117 days, as claimed by the plaintiff or another period as established on the
evidence.
[1170] If I am wrong and the plaintiff is entitled to the costs of the Mechanical Variation and
the extension of time, I briefly deal with the claim for delay damages.
[1171] Clause 34.9 of the Contract deals with delay damages and states as follows:
“For every day the subject of an EOT for a compensable cause, the
Contractor shall be entitled to give the Superintendent a claim for
delay damages reasonably and necessarily incurred by the Contractor
by reason of that compensable cause. The Principal must pay the
amount of the delay damages certified by the Superintendent pursuant
to this subclause 34.9.
The maximum amount payable by the Principal to the Contractor for
every day the subject of an EOT for a compensable cause is the actual
cost incurred by the Contractor up to the maximum specified in Item
31A.
Nothing in this subclause 34.9 shall oblige the Principal to pay delay
damages for:
(a) the costs of delay which have already been included in the value
of a variation or any other payment under the Contract; or
(b) any qualifying cause of delay which is not a compensable cause
of delay.
The amount payable by the Principal to the Contractor under this
subclause 34.9 is the agreed damages payable by the Principal to the
Contractor and is in full satisfaction of all claims which the
Contractor may make or bring against the Principal arising in
connection with all and any delay or disruption however caused or
encountered by the Contractor in the execution of WUC.” (emphasis
added)
[1172] Item 31A states:
“Maximum amount of delay costs (clause 34.9)
$$13,148.00 per day excluding profit and overheads”. (emphasis
added)
[1173] Whilst the submissions from the parties and the expert reports consider the approach
to delay damages in relevant texts and authorities, the starting point has to be the
interpretation of the contractual provision.
-- 198 of 210 --
199
[1174] A “compensable cause” is a defined term and includes a direction to undertake a
variation. It is not established if it is a direction to rectify defective work.
[1175] The key aspects of the provision are that the plaintiff must establish the costs claimed:
(a) are actual costs incurred;
(b) are reasonable;
(c) are necessary; and
(d) by reason of the “compensable cause”.
[1176] There is a dispute between the parties in respect of the requirement for the costs to be
reasonably incurred. The plaintiff says that the defendant’s pleading does not plead
that the costs are not reasonable and therefore the defendant is precluded from running
that as a positive case. The defendant in response says that it is squarely raised on
the pleading and in any event the onus is on the plaintiff to establish reasonableness
in order to come within clause 34.9.
[1177] Paragraph 27(f)(ii)(1)(a) of the Third Amended Defence and Counterclaim states:
“The Plaintiff’s claim for delay damages does not include any actual
costs for time related site overheads which were reasonably and
necessarily incurred by reason of the alleged Mechanical Direction”.
[1178] This pleading identifies that the defendant contends that the costs claimed did not
meet the requirement of being actual costs that were reasonably and necessarily
incurred. This put the plaintiff on notice that reasonableness was in issue.
[1179] Paragraph 27(f)(ii)(1)(b) of the Third Amended Defence and Counterclaim then
states:
“In the premises of the matters pleaded in paragraph 27.f.ii.1.a the
Defendant, pursuant to clause 34.9 of the Contract is not obliged to
pay to the Plaintiff any additional delay damages for its site
overheads;
Particulars
A. Section 6.2.42 to 6.2.46 of the Expert Report of David
Hardiman dated 5 April 2019.”
[1180] The plaintiff contends that the Hardiman Report identified in the particulars only
addresses “actually” and “necessarily” and does not refer to “reasonably”.
[1181] The defendant’s pleading may operate to preclude it from being able to run a positive
case that the costs were not reasonable. But by the pleading in paragraph
27(f)(ii)(i)(a) the plaintiff is put to proof of reasonableness. This is also a requirement
of clause 34.9 in any event and the onus is on the plaintiff to establish that the
requirement of reasonableness is met.
[1182] The pleaded defence and the plaintiff’s claim itself are consistent with the plaintiff
being put to proof of the reasonableness of the costs claimed. This is what the
defendant does.
-- 199 of 210 --
200
[1183] There is also a dispute between the parties as to how Item 31A operates. It stipulates
the maximum amount of delay damages. That is the actual costs incurred can be
claimed up to that maximum amount (subject to the other requirements being met).
[1184] Item 31A states the maximum figure as “$13,148.00 per day excluding profit and
overheads”. It is not contentious between the parties that the reference to “overheads”
in Item 31A is a reference to offsite overheads.
[1185] What is contentious is whether the provision excludes profit and offsite overheads
from being recoverable at all (as contended for by the defendant) or whether the
maximum cap does not include profit and offsite overheads, and they are recoverable
and are in addition to the maximum cap (as contended for by the plaintiff).
[1186] The plaintiff submits that the words “excluding profit and overheads” must be given
some work to do. Objectively read, it is submitted that the words mean that the parties
did not intend for profit and overheads to be included within the “maximum specified
in Item 31A”. That is, these words do not limit the recoverability of profit and
overheads and simply results in profit and overheads not being constrained by the
maximum.
[1187] The defendant contends that clause 34.9 and Item 31A read together exclude the
recovery of offsite overheads. The defendant submits that in the context of delay
damages, profit and overheads are not generally considered to be types of costs which
are claimable. But this does not focus on the language of the section but rather on
general principles.
[1188] The defendant further submits that profit and overheads are in the same category.
Profit is not an “actual cost” and offsite overheads are not costs which are “necessarily
incurred” by reason of any particular delay to a particular project (unless they are
dedicated offsite overheads). The difficulty with this submission is that it is applying
the words in the first paragraph of clause 34.9, rather than giving any work to the
words in Item 31A.
[1189] I find that the correct construction of clause 31A is that contended for by the plaintiff,
namely that profits and overheads are not included within the “maximum specified in
Item 31A”. It is not to be construed to make profit and overheads not recoverable
pursuant to clause 34.9. However, the position contended for by the defendant may
ultimately be reached in any event by the consideration of, and operation of,
“reasonably” and “necessarily” in respect of particular costs claimed.
[1190] The operation of the third paragraph of clause 34.9 is also contentious between the
parties. The plaintiff submits that the third paragraph is “self-explanatory” but the
parties are in dispute as to whether any delay damages already included in the cost
element of the alleged variation are to be deducted from any entitlement to delay
damages.
[1191] Clause 34.9 relevantly states that “[n]othing in this subclause … shall oblige … to
pay delay damages for … the costs of delay which have already been included in the
value of a variation or any other payment under the Contract”. The provision is
clearly directed at avoiding particular costs being recovered twice.
-- 200 of 210 --
201
[1192] The plaintiff contends that the costs recoverable under clause 36.4(d) being the 10 per
cent on account of “profit and overheads” for the variation are a different category of
“profit and overheads” to what is claimed under clause 34.9.
[1193] The basis for this includes that the costs of the variation are not dependent on whether
there has been any delay. The plaintiff submits that the price of a variation, including
any uplift, is entirely separate from the damage caused by the delay by reason of the
variation. The price of the variation is determined by the work required by the
variation, not the delay period that follows. As a result, the plaintiff submits there is
no automatic entitlement to recover delay costs where there is an uplift on account of
overheads in the price of a variation.
[1194] Further, the plaintiff contends that whether there is a need to nevertheless deduct from
any amount of delay damages the amount included under clause 36 for overheads
depends on what the amount for overheads covered. That is, for example, what did
the eight per cent uplift for overheads compensate the plaintiff for.
[1195] The plaintiff’s position is that the eight per cent uplift is entirely unrelated to delay
damages and compensates the plaintiff for overheads “expended responding to, and
managing, the variation itself”. This is in a different category to compensation to the
plaintiff for the prolonged overheads it incurred as a consequence of the 117 (or other
period established on the evidence) critical delay.
[1196] As the eight per cent overhead component of the variation cost is not related to the
delay incurred, or even if there is a delay, the plaintiff ultimately contends there
should be no deduction of the amount of overheads included in the variation cost.
[1197] The defendant contends there should be a deduction to avoid the plaintiff “double
dipping”.
[1198] This issue depends on the correct construction of the words “the costs of delay” which
have already been included in the value of a variation. It is clear that if an amount
relates to “the costs of delay” then it should be excluded.
[1199] Clause 36.4 sets out how the “price” of a variation is to be calculated. There is a
hierarchy of options with the last option (d) stating:
“reasonable rates or prices, which shall include an amount equivalent
to the percentage set out in Item 32A for profit and overheads”.
[1200] That is the relevant provision applied in respect of the assessment of costs for the
Mechanical Variation being considered in this matter.
[1201] Where a variation results in a “deduction” clause 36.4 specifies that the percentage in
Item 32B applies “for profit but not overheads”. Items 32A and 32B state as follows:
(a) “32A Variations, the percentage for profit and overheads for additions
(subclause 36.4)
10% of the cost of the work comprising the variation.”
(b) “32B Variations, the percentage for profit for deductions (subclause 36.4)
-- 201 of 210 --
202
2% of the cost of the work comprising the variation”.
[1202] There is nothing in these provisions to suggest there is an automatic overlap and that
the eight per cent uplift for overheads includes “costs of delay”. However, it may
depend on the particular costs claimed and also what is included in the “reasonable
rates and prices” as opposed to just a consideration of the uplift for overheads.
[1203] Some rates may include components which would not be recoverable. For example,
clause 36.4 also provides for the price of a variation using:
“(a) prior agreement;
(b) applicable rates or prices in the Contract;”
[1204] If these are used to arrive at the price of a variation, consideration would have to be
given as to whether any amount was “the costs of delay” and therefore not recoverable
as part of any delay damages.
[1205] Some assistance is also provided from a consideration of other parts of clause 36 in
respect of variations. Clause 36.1 sets out procedures for variations and states that
the principal shall only be liable to the contractor for the price of a variation calculated
in accordance with subclause 36.4. Under clause 36.1(g) before performing the
variation a notice is to be given identifying “the approximate cost of the variation
including a detailed breakdown calculated in accordance with subclause 36.4”.
[1206] In contrast clause 36.2 provides an alternative variation procedure where the
superintendent may give the contractor notice requesting a variation proposal be
submitted by the contractor. Certain information is to be provided as part of the
variation proposal including:
“(b) a detailed breakdown of the price for which the Contractor
would carry out the proposed variation, including any delay or
disruption costs which may be incurred by the Contractor as a
consequence of the proposed variation”.
[1207] Clause 36.2 then sets out various options open to the superintendent following receipt
of a variation proposal. These include:
“…
(f) accept the variation proposal and give the Contractor a
direction to carry out the variation on the terms contained in
that proposal, in which case a valuation under subclause 36.4
shall not be made and the addition or deduction to the contract
sum shall be the amount contained in the variation proposal;
(g) negotiate different terms with the Contractor upon which the
proposed variation shall be carried out;
(h) give the Contractor a direction to carry out the proposed
variation on the terms contained in the Contract but with a
valuation to be made under subclause 36.4 …”
[1208] Clause 36.2(b) requires that delay and disruption costs be included in the variation
proposal. If that variation proposal is accepted under clause 36.2(g) the price in the
-- 202 of 210 --
203
variation proposal becomes the price of the variation. As a result, the price of the
variation would include “delay costs”. Therefore, if a claim for delay damages was
also made under clause 34.9 then those “delay costs” would not be recoverable as part
of the delay damages.
[1209] This is an example of how paragraph (a) of the third paragraph of clause 34.9 may
operate.
[1210] The practical difficulty in the current matter is identifying with precision what is
included in the price of the variation and isolating any cost of delay which is included.
There is no direct evidence that there is any component which is a “cost of delay”.
[1211] The eight per cent uplift in the price of the variation is to be interpreted as onsite
overheads in respect of the actual work done for the variation unless there is evidence
that all or part is a “cost of delay”. In the absence of any such evidence, the eight per
cent uplift in the price of the variation does not need to be deducted from any delay
damages.
[1212] There are two further issues in dispute between the parties:
(a) Whether the claimed onsite overhead costs are actual costs reasonably and
necessarily incurred by reason of the Mechanical Variation?
(b) Whether the claimed offsite overhead costs are actual costs reasonably and
necessarily incurred by reason of the Mechanical Variation?
[1213] Firstly, dealing with the claim in relation to onsite overhead costs.
[1214] The plaintiff’s quantum expert, Mr Bell, undertook the following analysis to arrive at
the amount claimed for onsite overhead costs:
(a) From the plaintiff’s job costs (being the plaintiff’s cost records for the Spring
Hill Hotel) Mr Bell used the cost codes to identify costs which were an onsite
overhead and time related in the period of the claimed critical delay, 4 October
2016 to 28 January 2017.
(b) Mr Bell then calculated the average daily time related cost rate from the
identified onsite actual costs based on calendar days for each month in the
period of critical delay.
(c) Mr Bell then applied the average daily time related onsite cost rate to the
number of critical delay days claimed (117) in each of the months.
(d) In undertaking this exercise, Mr Bell arrived at the average daily time related
cost rates for onsite overheads, which are less than the maximum of $13,148.00
per day.
[1215] The defendant objects to this approach on a number of bases, including:
(a) Mr Bell only analysed whether the costs recorded were time-related overhead
in nature and whether it fell within the period of critical delay. He did not
analyse primary documents such as invoices and time sheets to determine
whether the costs were reasonably and necessarily incurred by reason of the
Mechanical Variation.
-- 203 of 210 --
204
(b) In respect of “reasonableness”, Mr Bell’s only evidence on this in cross-
examination was “contractors seldom spend money they don’t have to”. He
also confirmed this was speculation as he had not separately investigated
whether the costs were reasonably incurred.489
(c) In respect of “necessarily incurred by reasons of the Mechanical Direction”,
Mr Bell in cross-examination gave evidence that all he did was identify whether
the costs were incurred during the delay period and did not go beyond that task
to consider whether they were incurred in the period because of the Mechanical
Variation as opposed to other work in the period.490
[1216] The defendant refers to overhead labour costs as an example491 of the deficiencies in
Mr Bell’s analysis. Mr Bell was questioned about the costs incurred for Mr Meredyth
in his role as “Project Manager”. The total costs for Mr Meredyth for the period were
included in the delay costs. Mr Bell did not examine timesheets to see if he was
managing any other work in this period. While Mr Meredyth was on site during the
period that arose due to the claimed critical delay from the Mechanical Variation,
there is no evidence of what Mr Meredyth was doing on site, in particular whether he
was involved in the Mechanical Variation or other work.492
[1217] The defendant submits that identifying onsite overhead costs incurred in the delay
period is not sufficient to prove an entitlement to delay damages under clause 34.9,
in circumstances where:
(a) The plaintiff led no evidence that each of the onsite costs it claims would have
ceased but for the claimed delay.
(b) Further, or alternatively, the plaintiff provided no explanation as to why any
expenditure, after the relevant date, was solely related to work required by the
Mechanical Direction.
(c) The plaintiff did not lead any evidence that the costs were reasonably incurred
or necessarily incurred by reason of the Mechanical Direction.
(d) In respect of overhead labour costs there was no attempt to identify the
functions undertaken during the period of delay to only claim costs necessarily
incurred by reason of the delay event.
[1218] Overall, the defendant submits that the plaintiff has not addressed the causation
requirement of costs necessarily incurred by reason of the compensable cause, in this
case the Mechanical Variation. Merely identifying overhead costs incurred during
the period of critical delay is not enough. There must be a causal connection between
the compensable cause of delay and the costs incurred.
[1219] The plaintiff’s response to these criticisms includes:
(a) If it is accepted that the Mechanical Variation caused 117 days of critical delay,
the Spring Hill Hotel would have achieved Practical Completion 117 days
earlier, with the consequence that the plaintiff’s onsite overheads would have
been demobilised 117 days earlier.
489 T9-105, L11-22.
490 T10-12, L4-16.
491 Overhead labour costs are a large portion of the costs claimed.
492 T10-14, L29-T10-15, L9.
-- 204 of 210 --
205
(b) It is incorrect to calculate the daily onsite overhead cost based on the costs
incurred over the last 117 days of the project.
(c) It is irrelevant that it is not possible to attribute the site overheads to the
particular work encompassed by the Mechanical Variation. The point is, were
it not for the delay caused by the Mechanical Variation, the plaintiff would
have had 117 days fewer of costs related to onsite overheads. That is, onsite
costs would not otherwise have been incurred.
(d) The plaintiff doing other work at the same time does not mean that the costs
arising because of the longer duration of the project are not attributable to the
delay.
[1220] The difficulty with the plaintiff’s proposition is highlighted by the consideration of
the onsite labour costs claimed in respect of Mr Meredyth. There is no consideration
of what Mr Meredyth was doing on site during this period. He may have been doing
work totally unrelated to the Mechanical Variation. He may have been doing a
mixture of work and some component may have related to the Mechanical Variation.
The plaintiff would only be entitled to the costs in respect of Mr Meredyth if they
were reasonably and necessarily incurred by reason of the Mechanical Variation. On
the evidence, it is established that he was on site during the period of critical delay.
But it is not established that the costs for his labour were “by reason of the Mechanical
Variation”.
[1221] On the evidence it is not possible to be satisfied that the onsite overhead costs claimed
were reasonably and necessarily incurred by reason of the Mechanical Variation as
required by clause 34.9. The plaintiff has not established an entitlement to the costs
under clause 34.9 of the Contract. Accordingly, if it is necessary to consider the claim
in respect of delay damages, this part of the plaintiff’s claim must fail.
[1222] Dealing with the claim in relation to offsite overhead costs.
[1223] The plaintiff contends that there is no reason in principle why it is not entitled to its
offsite overheads.
[1224] Further, the plaintiff submits that there was no evidence that the offsite costs were
costs that would have necessarily been incurred irrespective of the delay to the Spring
Hill Hotel.493 This, however, does not address the relevant contractual requirement.
[1225] Mr Bell’s methodology to quantify the plaintiff’s daily offsite overheads is set out in
paragraph 57 of his report.494 Mr Bell’s method included:
(a) Consideration of the plaintiff’s financial records for the financial years ending
30 June 2016 and 30 June 2017, as they span the time that the work was
performed under the Contract and also the delay period.
(b) Identification of certain actual corporate expenses and revenues and then
calculated a percentage of total expenses to total turnover, as representing the
percentage for offsite overheads for those financial years.
493 Plaintiff’s written closing submissions at [445].
494 EXP.001.001.1518.
-- 205 of 210 --
206
(c) Calculation of an average percentage of 3.16 per cent for the period of the
project.
(d) A daily rate for offsite overheads is then calculated as $2,088 per calendar day.
[1226] Mr Bell’s report also contains some further comments on the approach including:
(a) The percentage is an “all up” percentage, which takes into account revenues
from both contract works and variation works. Mr Bell considers that this
approach is more conservative as a lesser percentage is obtained than if
revenues from variation margins were deducted from the calculation. In any
event, variation margins cannot be identified from the details provided.495
(b) The daily rate for offsite overheads was calculated using the Emden formula.
Mr Bell notes that this formula is a refinement on the Hudson formula in that
it utilises actual head office overheads/profit percentage. The Hudson formula
uses allowances for head office overheads which the contractor included in its
tender for the contract.496
[1227] The plaintiff claims an amount for all overheads of $1,040,106, which includes both
onsite and offsite overheads. The amount claimed for onsite overheads is
$794,433.00. The plaintiff’s submissions do not separately indicate the figure for
offsite overheads, but logically this should be $245,673 (being the difference between
the two figures).497
[1228] The defendant contends that the plaintiff’s claim for offsite overheads is flawed for
the same reason that its claim for onsite overheads is flawed: that is, the plaintiff has
not proved the costs were reasonably and necessarily incurred by reason of the
Mechanical Variation.
[1229] The defendant identifies that Mr Bell has calculated, using the Emden formula, the
average head office overhead and profit percentage that was achieved overall in the
contractor’s business and then applied that to the period of delay. As acknowledged
by Mr Bell in cross-examination, this is an apportionment of actual offsite overhead
costs incurred by the plaintiff in running its business to the period of delay.498
[1230] The defendant submits that this claim is not for additional offsite overheads incurred
by reasons of the Mechanical Variation. It is a claim for a portion of the total running
costs of the plaintiff equal to the period of delay.499
[1231] The defendant recognises that under clause 34.9 additional head office costs may be
recoverable as offsite overheads where they were incurred by reason of the variation.
But costs “to run the contractor’s business that cannot be recovered by projects, due
to delayed completion and hence reduction in turnover, that is, a loss of opportunity
to recover” would not be recoverable.500
495 EXP.001.001.1518 at [57(b)].
496 EXP.001.001.1518 at [57(d)].
497 Plaintiff’s written closing submissions at [473]-[475].
498 T10-24, L15-25.
499 Defendant’s written closing submissions at [305].
500 Description taken from Robert Gemmell’s text “Quantification of Delay and Disruption in
Construction and Engineering Projects” PRO.071.013.0006 at pp 0003-0006.
-- 206 of 210 --
207
[1232] The defendant relies on clause 47(c) of the Contract as the basis for this second
category of offsite overhead costs being not recoverable. Clause 47(c) states:
“The Principal shall not be liable to the Contractor for consequential
or indirect loss whether arising out of or in connection with the
Contract, under statute, in tort (for negligence or otherwise) or any
other basis in law or equity.”
[1233] Clause 1 defines “consequential and indirect loss” as follows:
“means any loss of income, loss of revenue, loss of profit, loss of
financial opportunity, loss of business or loss of business opportunity,
loss of contract, loss of goodwill, loss of use, loss of production or
failure to realise anticipated savings (whether the loss is direct or
indirect)”.
[1234] The defendant submits that as a result of clause 47(c) the defendant is not liable for
any consequential or indirect loss, which is the true character of the plaintiff’s claim
for offsite overheads.
[1235] Senior Counsel for the defendant cross-examined Mr Bell in respect of this issue,
including as follows:501
“Built’s claim for offsite overheads is for costs incurred to run its
business, but these costs are not costs directly chargeable to this
project?---That’s – that’s a fair assessment, yes.
Do you agree that in the abstract some offsite overheads may be
dedicated overheads, that is, head office overheads dedicated to
supporting onsite resources in a particular project?---They could be.
But you haven’t identified any dedicated offsite overheads in this
case?---No. I haven’t given any detail of what the overhead costs are
comprised of.
Now, have you identified any dedicated offsite heads that increased
as a result of a mechanical direction?---No.
…
I understand what you’re saying, but these are costs that would have
been incurred, in any event, regardless of the project?---I don’t know
that.
Well, you don’t know otherwise, do you?---No, I don’t.
And you cannot – there’s no basis, or nobody’s provided you any
basis to suggest that these are dedicated offsite overhead costs?---I –
I have not got any information about whether they would be described
in that particular fashion in the way that Mr Gemmell does.
Okay. See, what I’m going to suggest to you is, in the absence of that
evidence, you can’t say, one way or the other, anything other than
501 T10-25, L33-45-T10-27, L12-29.
-- 207 of 210 --
208
that the head office had costs in running its business?---That – that’s
probably a fair assumption. Yes.
And you haven’t got any basis – you don’t have any – sorry – you
don’t have any basis to suggest that those costs would have been
incurred in any event, regardless of the mechanical direction?---I
don’t have any insight into what the basis of the incurring of those
costs was.”
[1236] In light of this evidence from Mr Bell, the defendant says that the claim for offsite
overheads is “properly characterised as a claim for the loss of opportunity to earn
revenue from other work to support its offsite resources because it[s] onsite resources
remained on site longer because of the delay”.502
[1237] This contention is supported by the evidence of Mr Hardiman that the Emden formula
used by Mr Bell is an accepted method for calculating overheads for a loss of
opportunity claim.503 Such a claim is precluded by clause 47(c) of the Contract.
[1238] The defendant alternatively contends that, even if the claim was not precluded under
clause 47(c), the plaintiff has not established on the evidence that it lost an
opportunity to earn additional revenue to support its offsite overhead resources.
[1239] The Plaintiff maintains that Mr Bell’s calculations should be accepted by the Court,
including on the basis that:
(a) The Emden formula is entirely orthodox.
(b) Mr Bell has specific expertise as a delay expert and in delay costing. Mr
Hardiman has more general expertise as a quantity surveyor.
(c) The plaintiff’s claim for daily costs of overheads, both onsite and offsite, does
not exceed the ‘maximum specified in Item 31A”, being $13,148.00 per day.
(d) The right to claim delay damages expressly conferred by clause 34.9 is not
subject to the limitation in clause 47(c) of the Contract.504
(e) Authorities support the recoverability of offsite overheads without
consideration of evidence establishing the loss of opportunity (along the lines
of, “[b]ut for this, we would have gone out and got this other contract”).505
[1240] Again, the difficulty in relation to this claim for offsite overheads is whether the
amount claimed satisfies the contractual requirement in clause 34.9. The question
must be asked in respect of the costs claimed in relation to offsite overheads: are they
costs reasonably and necessarily incurred by reason of the compensable cause, being
the Mechanical Variation)?
[1241] The evidence establishes that the amount claimed by the plaintiff in respect of offsite
overheads is a portion of the total running costs of the plaintiff’s business for the
period of the delay. There has been no attempt to find a causal connection with the
502 EXP.001.001.1621 at p 1691 [6.2.54]; PRO.071.013.0006 at p 0004.
503 T13-2, L45-T13-3, L3.
504 T15-33, L10-18.
505 T15-33, L34-45; Alfred McAlpine Homes North Ltd v Property and Land Contractors Ltd (1995) 76
BLR 59 at 70; J F Finnegan Ltd v Sheffield City Council (1988) 43 BLR 124 at 134-135.
-- 208 of 210 --
209
Mechanical Variation. It is a purely mathematical exercise – a daily rate of offsite
overheads costs has been calculated and then multiplied by the number of days in the
delay period.
[1242] Equally, there has been no attempt to establish that these costs were reasonable and
necessary. It is again a purely mathematical exercise – calculations have been
undertaken based on categories of corporate expenses, with no evaluation of the costs
incurred.
[1243] The plaintiff has the onus of establishing an entitlement to delay costs pursuant to
clause 34.9. It has provided evidence in support of its claim but that evidence is not
focused on the contractual requirements of clause 34.9. The Contract sets out clearly
and unambiguously that the recoverable costs are costs that are reasonably and
necessarily incurred “by reason of that compensable cause”. Global claims are not
sufficient.
[1244] On the evidence it is not possible to be satisfied that the offsite overhead costs claimed
were reasonably and necessarily incurred by reason of the Mechanical Variation as
required by clause 34.9. The plaintiff has not established an entitlement to the costs
under clause 34.9 of the Contract. Accordingly, if it is necessary to consider the claim
in respect of delay damages, this part of the plaintiff’s claim must fail.
Liquidated damages
[1245] The last issue to be considered if the Mechanical Variation is established is the effect
of any extension of time on the liquidated damages which the defendant has withheld.
[1246] If an extension of time is ultimately granted than a corresponding adjustment to the
amount of liquidated damages will need to be made.
[1247] One unresolved issue remains: whether any adjustment to the liquidated damages
uses the date for practical completion of 10 November 2016 or whether the “correct”
date for practical completion of 27 October is used as the starting point for any
adjustment as a result of an extension of time?
[1248] While the defendant’s claim for additional liquidated damages arising out of its
attempt to correct the error was not allowed, it may be open, or even appropriate, to
use the revised date in any adjustment of the liquidated damages by the Court.
[1249] The defendant’s claim was unsuccessful due to an inability to correct the error as
there was no provision in the Contract to allow that to occur.
[1250] There is evidence as to the error in Mr King’s report506 and also in the liquidated
damages certificate issued by the Superintendent on 20 May 2019.507
[1251] The definition of “date for practical completion” in clause 1 envisages the date for
practical completion being adjusted as a result of litigation: “if any EOT for practical
completion is … allowed in any … litigation, it means the date resulting therefrom”.
506 EXP.001.001.0858 at pp 0880-0883.
507 PRO.060.001.0095 which was admitted into evidence and can be relied upon for the truth of its
contents.
-- 209 of 210 --
210
[1252] The submissions of the parties in relation to the error in the date for practical
completion were directed at the defendant’s claim. It may be appropriate that further
submissions be provided on this issue if an extension of time is ultimately granted
and the date for practical completion needs to be identified for the purposes of
working out the period for liquidated damages to be calculated.
-- 210 of 210 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2021/224