BSO Network Inc & Anor v EMClarity Pty Ltd (No 2) [2021] QSC 73
SUPREME COURT OF QUEENSLAND
CITATION: BSO Network Inc & Anor v EMClarity Pty Ltd (No 2) [2021]
QSC 73
PARTIES: BSO NETWORK INC
(first plaintiff)
&
APSARA NETWORKS INC
(second plaintiff)
v
EMCLARITY PTY LTD
ACN 88 139 128 180
(defendant)
FILE NO: BS12112 of 2019
DIVISION: Trial Division
PROCEEDING: Originating Application, continued as if commenced by way
of Claim
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 9 April 2021 (restricted to the parties)
28 July 2021 (redacted version for publication)
DELIVERED AT: Brisbane
HEARING
DATES:
20 – 23 July 2020, 19 August 2020; 21 and 22 October 2020
(further written submissions)
JUDGE: Ryan J
ORDERS: The parties having agreed upon a less redacted version
for publication of my Reasons delivered on 9 April 2021, I
now publish those less redacted Reasons.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – PARTICULAR PARTIES – PRINCIPAL
AND AGENT – CREATION OF RELATIONSHIP OF
AGENCY – FORMATION AND PROOF OF AGENCY –
-- 1 of 136 --
2
where alleged principal wholly owned subsidiary of alleged
agent – where alleged principal undisclosed to other
contracting party – whether holding company negotiating “on
behalf of” subsidiary created agency relationship
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – IMPLIED
TERMS – whether contract an unconditional contract for
supply of goods or a development contract, with supply to
follow only if development successful – where, if an
unconditional contract for supply, the contract was silent as to
when the goods were to be delivered – whether a term
requiring delivery within a reasonable time ought to be
implied – determination of period of reasonable time –
whether there had been failure to supply the goods within a
reasonable time
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – REPUDIATION AND NON-
PERFORMANCE – REPUDIATION – DELAY AND
PROVISIONS AS TO TIME – where defendant agreed to
supply goods to second plaintiff – where defendant then
unilaterally implemented a “Quality Review” of all its
products and a pause on shipping until the review was
complete – where defendant informed plaintiffs about Quality
Review and pause on shipments but would provide no
information to plaintiffs about when the review might be
completed – where defendant cancelled orders for
components for second plaintiff’s product –– whether
conduct of defendant repudiatory
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – where contract between first
plaintiff and defendant contained obligation of confidence –
where plaintiffs’ competitor acquired defendant – where,
prior to acquisition, during due dilignce, defendant provided
redacted versions of plaintiffs’ confidential information to
plaintiffs’ competitor – where, after acquisition, defendant
provided un-redacted copies of plaintiffs’ confidential
information to plaintiff’s competitor – whether confidential
information provided in breach of contractual obligation of
confidence – whether contractual exceptions to obligation of
confidence applied
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – whether equitable obligation of confidence
co-exists with contractual obligation of confidence – whether,
-- 2 of 136 --
3
if co-existing, equitable obligation broader in scope than
contractual obligation
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – where competitor of plaintiffs acquired
defendant – where, during due dilignce, prior to acquisition,
defendant provided redacted versions of the plaintiffs’
confidential information to the plaintiffs’ competitor – where,
after acquisition, defendant provided un-redacted copies of
the plaintiff’s confidential information to the plaintiff’s
competitor – whether confidential information provided in
breach of equitable obligation of confidence
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – contractual obligation of
confidence – contractual exclusivity terms – whether
defendant likely to breach contractual obligation of
confidence or exclusivity terms of the contract
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – whether defendant likely to breach equitable
obligation of confidence
Apotex Pty Ltd v Les Laboratoires Servier (No 2) [2012]
FCA 748
Astea (UK) v Time Group [2003] EWHC 725
Bell Group Ltd (in liq) v Westpac Banking Corp (No 9)
(2008) 39 WAR 1
BP Refinery (Westernport) Pty Ltd v Shire of Hastings
(1977) 180 CLR 266
Brambles Holdings Ltd v Bathurst City Council(2001) 53
NSWLR 153
Branwhite v Worcester Works Finance Ltd [1969] 1 AC 552
Bridlington Relay Ltd v Yorkshire Electricity Board [1965]
Ch 436
Byrne v Australian Airlines Ltd (1995) 185 CLR 410
Coco v AN Clarke (Engineers) Ltd [1969] RPC 41
Coghlan v Pyoanee Pty Ltd [2003] QCA 146 [2003] 2 Qd R
636
Colonial Mutual Life Assurance Society Ltd v Producers and
Citizens Cooperative Assurance Co of Australia Ltd (1931)
46 CLR 41
Commissioner of Taxation v Sara Lee Household & Body
Care (Australia) Pty Ltd (2000) 201 CLR 520
Commonwealth Bank of Australia v Barker (2014) 253 CLR
169
Corporate Farming Pty Ltd v Eden Bay Pty Ltd (Unreported,
Supreme Court of Western Australia, Murray J 28 January
1992).
-- 3 of 136 --
4
Curwen & Ors v Vanbeck Pty Ltd [2009] VSCA 284
Dan v Barclays (1983) 46 ALR 437
Del Casale v Artedomus (Aust) Pty Ltd [2007] NSWCA 172
Faccenda Chicken Ltd v Fowler [1985] 1 All ER 724
Freeman & Lockyer (a firm) v Buckhurst Park Properties
(Mangal) Ltd [1964] 2 QB 480
Gold Coast Oil Co Pty Ltd v Lee Properties Pty Ltd [1984]
QSCFC 85 [1985] 1 Qd R 416
Gold & Copper Resources Pty Ltd v Newcrest Operations
Ltd [2013] NSWSC 281
Global Advanced Metals Pty Ltd v Metallurg Inc [2017]
WASCA 188
GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty
Ltd [(1986) 40 NSWLR 631
Hart v MacDonald (1910) 10 CLR 417
Hick v Raymond & Reid [1893] AC 22
Kazakstan Wool Processors (Europe) Ltd v Nederlandsche
Credietverzekering Maatschappij NV [2000] CLC 822
King Tide Company Pty Ltd v Arawak Holdings Pty Ltd
[2017] QCA 251
Koompahtoo Local Aboriginal Council v Sanpine Pty Ltd
(2007) 233 CLR 115
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd
(1989) 166 CLR 623
Links Golf Tasmania Pty Ltd v Sattler (2012) 213 FCR 1
Maynard v Goode (1926) 37 CLR 529
Moorgate Tobacco Co Ltd v Philip Morris Ltd (No 2) (1984)
156 CLR 414
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104
Neeta (Epping) Pty Ltd v Phillips (1974) 131 CLR 286
Optus Networks Pty Ltd v Telstra Corporation Ltd (2010)
265 ALR 281
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537
Questband P/L v Macquarie Bank Limited [2009] QCA 266
Rossiter v Miller (1878) 3 App Cas 1124
Sequel Drill & Blast P/L v Whitsunday Crushers P/L [2009]
QCA 218
Saltmann Engineering Co Ltd v Campbell Engineering Co
Ltd [1963] 3 All ER 413
Shawton Engineering v DGP International [2006] BLR 1
Streeter v Western Areas Exploration Pty Ltd (No 2) 92011)
278 ALR 291
Streetscape Projects (Aust) Pty Ltd v City of Sydney (2013)
85 NSWLR 196
Tate v Freecorns Pty Ltd [1972] WAR 204
Telina Developments Pty Ltd v Stay Enterprises Pty Ltd
[1984] QSCFC 43 [1984] 2 Qd R 585
Weemah Park Pty Ltd v Glenlaton Investments Pty Ltd
[2011] QCA 150 [2011] 2 Qd R 582
-- 4 of 136 --
5
COUNSEL: D O’Brien QC with F Lubett and L Wick for the plaintiffs
G Beacham QC with G Coveney for the defendant
SOLICITORS: Johnson Winter & Slattery for the plaintiffs
Ashurst Australia for the defendant
[1] On 9 April 2021 I delivered my Reasons in this matter. Because of the commercial
sensitivity of the subject matter, publication at large of my Reasons was limited to a
heavily redacted version of them.
[2] Since that time the parties have agreed that a less redacted version of my Reasons may be
published at large. They are attached and marked “Annexure A”.
-- 5 of 136 --
6
ANNEXURE A
-- 6 of 136 --
7
SUPREME COURT OF QUEENSLAND
CITATION: BSO Network Inc & Anor v EMClarity Pty Ltd (No 2) [2021]
QSC 73
PARTIES: BSO NETWORK INC
(first plaintiff)
&
APSARA NETWORKS INC
(second plaintiff)
v
EMCLARITY PTY LTD
ACN 88 139 128 180
(defendant)
FILE NO: BS12112 of 2019
DIVISION: Trial Division
PROCEEDING: Originating Application, continued as if commenced by way
of Claim
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 9 April 2021
DELIVERED AT: Brisbane
HEARING
DATES:
20 – 23 July 2020, 19 August 2020; 21 and 22 October 2020
(further written submissions)
JUDGE: Ryan J
ORDERS: The parties are directed to confer about the next steps in
this litigation and to contact my associate by no later than
23 April 2021 with agreed draft directions or orders; or a
request for a date for a review of the matter.
Until further order, I will restrict publication of these
reasons to the parties and to their solicitors and counsel
(subject, in the case of the defendant, to the orders made
-- 7 of 136 --
8
by Brown J on 27 November 2019, and varied by me on 4
August 2020).
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – PARTICULAR PARTIES – PRINCIPAL
AND AGENT – CREATION OF RELATIONSHIP OF
AGENCY – FORMATION AND PROOF OF AGENCY –
where alleged principal wholly owned subsidiary of alleged
agent – where alleged principal undisclosed to other
contracting party – whether holding company negotiating “on
behalf of” subsidiary created agency relationship
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – IMPLIED
TERMS – whether contract an unconditional contract for
supply of goods or a development contract, with supply to
follow only if development successful – where, if an
unconditional contract for supply, the contract was silent as to
when the goods were to be delivered – whether a term
requiring delivery within a reasonable time ought to be
implied – determination of period of reasonable time –
whether there had been failure to supply the goods within a
reasonable time
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – REPUDIATION AND NON-
PERFORMANCE – REPUDIATION – DELAY AND
PROVISIONS AS TO TIME – where defendant agreed to
supply goods to second plaintiff – where defendant then
unilaterally implemented a “Quality Review” of all its
products and a pause on shipping until the review was
complete – where defendant informed plaintiffs about Quality
Review and pause on shipments but would provide no
information to plaintiffs about when the review might be
completed – where defendant cancelled orders for
components for second plaintiff’s product –– whether
conduct of defendant repudiatory
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – where contract between first
-- 8 of 136 --
9
plaintiff and defendant contained obligation of confidence –
where plaintiffs’ competitor acquired defendant – where,
prior to acquisition, during due dilignce, defendant provided
redacted versions of plaintiffs’ confidential information to
plaintiffs’ competitor – where, after acquisition, defendant
provided un-redacted copies of plaintiffs’ confidential
information to plaintiff’s competitor – whether confidential
information provided in breach of contractual obligation of
confidence – whether contractual exceptions to obligation of
confidence applied
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – whether equitable obligation of confidence
co-exists with contractual obligation of confidence – whether,
if co-existing, equitable obligation broader in scope than
contractual obligation
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – where competitor of plaintiffs acquired
defendant – where, during due dilignce, prior to acquisition,
defendant provided redacted versions of the plaintiffs’
confidential information to the plaintiffs’ competitor – where,
after acquisition, defendant provided un-redacted copies of
the plaintiff’s confidential information to the plaintiff’s
competitor – whether confidential information provided in
breach of equitable obligation of confidence
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – contractual obligation of
confidence – contractual exclusivity terms – whether
defendant likely to breach contractual obligation of
confidence or exclusivity terms of the contract
EQUITY – GENERAL PRINCIPLES – equitable obligation
of confidence – whether defendant likely to breach equitable
obligation of confidence
Apotex Pty Ltd v Les Laboratoires Servier (No 2) [2012] FCA
748
Astea (UK) v Time Group [2003] EWHC 725
Bell Group Ltd (in liq) v Westpac Banking Corp (No 9)
(2008) 39 WAR 1
-- 9 of 136 --
10
BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977)
180 CLR 266
Brambles Holdings Ltd v Bathurst City Council(2001) 53
NSWLR 153
Branwhite v Worcester Works Finance Ltd [1969] 1 AC 552
Bridlington Relay Ltd v Yorkshire Electricity Board [1965]
Ch 436
Byrne v Australian Airlines Ltd (1995) 185 CLR 410
Coco v AN Clarke (Engineers) Ltd [1969] RPC 41
Coghlan v Pyoanee Pty Ltd [2003] QCA 146 [2003] 2 Qd R
636
Colonial Mutual Life Assurance Society Ltd v Producers and
Citizens Cooperative Assurance Co of Australia Ltd (1931)
46 CLR 41
Commissioner of Taxation v Sara Lee Household & Body
Care (Australia) Pty Ltd (2000) 201 CLR 520
Commonwealth Bank of Australia v Barker (2014) 253 CLR
169
Corporate Farming Pty Ltd v Eden Bay Pty Ltd (Unreported,
Supreme Court of Western Australia, Murray J 28 January
1992).
Curwen & Ors v Vanbeck Pty Ltd [2009] VSCA 284
Dan v Barclays (1983) 46 ALR 437
Del Casale v Artedomus (Aust) Pty Ltd [2007] NSWCA 172
Faccenda Chicken Ltd v Fowler [1985] 1 All ER 724
Freeman & Lockyer (a firm) v Buckhurst Park Properties
(Mangal) Ltd [1964] 2 QB 480
Gold Coast Oil Co Pty Ltd v Lee Properties Pty Ltd [1984]
QSCFC 85 [1985] 1 Qd R 416
Gold & Copper Resources Pty Ltd v Newcrest Operations Ltd
[2013] NSWSC 281
Global Advanced Metals Pty Ltd v Metallurg Inc [2017]
WASCA 188
GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty
Ltd [(1986) 40 NSWLR 631
Hart v MacDonald (1910) 10 CLR 417
Hick v Raymond & Reid [1893] AC 22
Kazakstan Wool Processors (Europe) Ltd v Nederlandsche
Credietverzekering Maatschappij NV [2000] CLC 822
King Tide Company Pty Ltd v Arawak Holdings Pty Ltd
[2017] QCA 251
Koompahtoo Local Aboriginal Council v Sanpine Pty Ltd
(2007) 233 CLR 115
-- 10 of 136 --
11
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd
(1989) 166 CLR 623
Links Golf Tasmania Pty Ltd v Sattler (2012) 213 FCR 1
Maynard v Goode (1926) 37 CLR 529
Moorgate Tobacco Co Ltd v Philip Morris Ltd (No 2) (1984)
156 CLR 414
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104
Neeta (Epping) Pty Ltd v Phillips (1974) 131 CLR 286
Optus Networks Pty Ltd v Telstra Corporation Ltd (2010)
265 ALR 281
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537
Questband P/L v Macquarie Bank Limited [2009] QCA 266
Rossiter v Miller (1878) 3 App Cas 1124
Sequel Drill & Blast P/L v Whitsunday Crushers P/L [2009]
QCA 218
Saltmann Engineering Co Ltd v Campbell Engineering Co
Ltd [1963] 3 All ER 413
Shawton Engineering v DGP International [2006] BLR 1
Streeter v Western Areas Exploration Pty Ltd (No 2) 92011)
278 ALR 291
Streetscape Projects (Aust) Pty Ltd v City of Sydney (2013)
85 NSWLR 196
Tate v Freecorns Pty Ltd [1972] WAR 204
Telina Developments Pty Ltd v Stay Enterprises Pty Ltd
[1984] QSCFC 43 [1984] 2 Qd R 585
Weemah Park Pty Ltd v Glenlaton Investments Pty Ltd [2011]
QCA 150 [2011] 2 Qd R 582
COUNSEL: D O’Brien QC with F Lubett and L Wick for the plaintiffs
G Beacham QC with G Coveney for the defendant
SOLICITORS: Johnson Winter & Slattery for the plaintiffs
Ashurst Australia for the defendant
-- 11 of 136 --
12
Table of Contents
Overview .................................................................................................................................. 16
The parties ................................................................................................................................ 20
The terminology of wireless networks ..................................................................................... 21
The provision of wireless network services in the NJ Equity Triangle ................................... 22
Key individuals ........................................................................................................................ 22
Agreements between BSO, McKay Brothers and EMClarity .................................................. 24
Events leading up to McKay Brothers’ acquisition of EMClarity ........................................... 24
BSO informed of the takeover and the “Quality Review” ....................................................... 26
The parties’ cases ..................................................................................................................... 27
The relief claimed by the plaintiffs .......................................................................................... 28
Credibility issues ...................................................................................................................... 29
Structure of these reasons ......................................................................................................... 29
Relevant background facts ....................................................................................................... 30
2017 – 2018: Discussions between Mr McGowan and Dr Baines ....................................... 30
The agency issue .................................................................................................................. 31
The W Band Radio Development Agreement – key terms .................................................. 32
Milestone 1: The “kick off” ................................................................................................. 39
Milestone 2: The Preliminary Design Report (August – November 2018) ......................... 40
Milestone 3: Commencement of final design (November 2018 – January 2019) ............... 41
The critical correspondence ..................................................................................................... 42
Late January 2019 ................................................................................................................ 42
February/March 2019 ........................................................................................................... 45
Observation about the operation of the WBRDAT .............................................................. 51
Late March and April 2019 .................................................................................................. 52
BSO’s/Apsara’s “new” (or alternative) strategy .................................................................. 53
Delivery estimates ................................................................................................................ 54
Quotes including statements about delivery times ............................................................... 55
Purchase orders .................................................................................................................... 57
Invoices (May/June 2019) .................................................................................................... 58
Observation about payment terms ........................................................................................ 58
Observation about warranty terms ....................................................................................... 59
Mr Boyle’s invitation to the W Band Project Meeting ............................................................ 60
Delays from July 2019 ............................................................................................................. 60
-- 12 of 136 --
13
BSO informed of McKay Brothers’ acquisition of EMClarity ................................................ 63
Status of development and production of a W Band radio ...................................................... 65
Cancellation of orders for components .................................................................................... 66
Progress of the Quality Review ................................................................................................ 66
Issue 1: Did BSO enter into the WBRDAT as agent for Apsara (the undisclosed principal) or
in its own capacity? .................................................................................................................. 67
Discussion and conclusion ................................................................................................... 69
Issue 2: Did Apsara and EMClarity enter into agreements in May and June 2019, for the
supply of E Band and W Band radios? .................................................................................... 72
Plaintiffs’ submissions ......................................................................................................... 72
Defendant’s submissions ...................................................................................................... 74
Plaintiffs’ submissions in reply ............................................................................................ 75
Discussion ............................................................................................................................ 75
Principles .......................................................................................................................... 75
What was to happen to the WBRDAT if new agreements were made? .......................... 76
Was a varied WBRDAT the agreement which made good commercial sense? .............. 78
Inferences to be drawn from the parties’ communication and other conduct .................. 80
Inferences to be drawn from conduct after the 2019 Agreements ................................... 86
Conclusion............................................................................................................................ 88
Issue 3: Alternatively to Issue (2), was the W Band development agreement varied? ............ 88
Defendant’s submissions ...................................................................................................... 89
Plaintiffs’ submissions ......................................................................................................... 89
Discussion ............................................................................................................................ 90
Conclusion............................................................................................................................ 91
Issue 4: Did the Supply Agreements (or the WBRDAT as varied) contain an implied term that
the E Band and W Band radios would be supplied within a reasonable time? ........................ 91
Discussion and conclusion ................................................................................................... 91
Issue 5: If there was such an implied term, what was a “reasonable time” for the supply of the
radios? ...................................................................................................................................... 92
Plaintiffs’ submissions ......................................................................................................... 92
Defendant’s submissions ...................................................................................................... 93
Discussion ............................................................................................................................ 94
Practical guidance from the authorities ............................................................................ 94
Applying that practical guidance...................................................................................... 97
Meaning of delivery of the radios within a reasonable time in the circumstances of this
case ................................................................................................................................... 97
-- 13 of 136 --
14
The use of estimates ......................................................................................................... 97
Conclusion.......................................................................................................................... 101
Issue 6: Did EMClarity breach the implied term by failing to supply the E Band and W Band
radios within a “reasonable time” being by October 2019, or alternatively 31 January 2020, 6
May 2020 or at the latest the date of the trial? ....................................................................... 101
Issue 7: Was a Quality Review in the terms instituted by EMClarity permitted by the terms of
the 2019 Agreements or the WBRDAT? ............................................................................... 101
Issue 8: Was the Quality Review a genuine and/or necessary review of the E Band or W Band
products? Or was it a “go-slow” in order to prioritise the interest of McKay
Brothers/disadvantage the plaintiffs? ..................................................................................... 102
Plaintiffs’ submissions ....................................................................................................... 102
Defendant’s submissions .................................................................................................... 104
Discussion and conclusion ................................................................................................. 104
Issue 9: By subjecting the order of W Band and E Band radios to the Quality Review, and/or
delaying the development and shipment of the order, did EMClarity breach the terms of the
Supply Agreements or the WBRDAT? .................................................................................. 106
Issue 10: Was EMClarity’s conduct, in subjecting the order of W Band and E Band radios to
the Quality Review, and/or delaying the development and shipment of the order a repudiation
of the 2019 Agreements or the WBRDAT? ........................................................................... 106
Plaintiffs’ submissions ....................................................................................................... 106
Defendant’s submissions .................................................................................................... 108
Plaintiffs’ reply ................................................................................................................... 108
Discussion and conclusion ................................................................................................. 109
Issues 11 – 16: Breaches of confidence - Overview .............................................................. 110
Issue 11: Were the “W-Band project, the terms of the WBRDAT, the Customer Material
under the WBRDAT, the Alternative Strategy, the Quote and the Purchase Orders” (together,
the “Material”) confidential? .................................................................................................. 112
Issue 12: Was the Material disclosed to McKay Brothers? ................................................... 114
Invitation to meeting about the W Band Project and following emails – was confidential
information disclosed? ....................................................................................................... 114
The redacted material – was confidential information disclosed? ..................................... 115
The redacted copies of the WBRDAT ........................................................................... 115
The redacted Quote and Purchase Orders ...................................................................... 116
The un-redacted material – was confidential information disclosed? ................................ 117
Issue 13: Was there a contractual obligation under the WBRDAT to keep the Material
confidential and not disclose it to McKay Brothers? ............................................................. 117
Issue 14: Was there an equitable duty of confidence to keep the Material confidential and not
disclose it to McKay Brothers? What is the scope of any such equitable duty? ................... 118
-- 14 of 136 --
15
The equitable obligation or duty of confidence ................................................................. 118
Whether contractual and equitable obligations of confidence co-exist? ............................ 118
Del Casale v Artedomus (Aust) Pty Ltd [2007] NSWCA 172 .......................................... 118
Streetscape Projects (Aust) Pty Ltd v City of Sydney (2013) 85 NSWLR 196 ................. 120
Optus Networks Pty Ltd v Telstra Corporation Ltd (2010) 265 ALR 281 ........................ 121
Academic text ..................................................................................................................... 123
The parties’ arguments ....................................................................................................... 123
Discussion and conclusion ................................................................................................. 125
Issue 15: Was the contractual duty breached? ....................................................................... 126
Issue 16: Was the equitable duty breached?........................................................................... 128
The equitable duty of confidence ....................................................................................... 128
The plaintiffs’ submissions ................................................................................................ 129
The defendant’s submissions ............................................................................................. 129
Discussion and conclusion ................................................................................................. 129
Issue 17: Does BSO/Apsara hold a belief that EMClarity will further delay the
development/shipment of the radios? Is that belief reasonable? ........................................... 130
Issue 18: Does BSO/Apsara hold a belief that EMClarity will, in the future, breach the
confidentiality provisions of the WBRDAT or the equitable duty of confidence? Is that belief
reasonable? ............................................................................................................................. 130
Discussion and conclusion ................................................................................................. 135
Issue 19: Does BSO/Apsara hold a reasonable belief that EMClarity will, in the future, breach
the exclusivity provisions of the WBRDAT or the 2019 Agreements? ................................. 135
-- 15 of 136 --
Overview
[1] In broad terms: the plaintiffs claim that the defendant failed to perform its contractual
obligations, under four contracts, to supply certain products to Apsara Networks within a
reasonable time, or alternatively, repudiated the contracts. The defendant contends that
the contracts are contracts for development and supply. Supply is conditional upon
successful development. There has not yet been successful development. Therefore, the
contractual obligation to supply products has not yet arisen and the contracts have not
been breached.
[2] Nineteen issues were presented for my determination. My conclusions as to each are
stated briefly in the table below.
[3] Critically, I have concluded that the second plaintiff and the defendant entered into
contracts in pursuance of which the defendant agreed unconditionally to supply products
to the second plaintiff; which the defendant has repudiated by manifesting an intention to
perform the contracts only “if and when” it suited the defendant to do so. Whether the
second plaintiff has or will terminate the contracts was not an issue for me.
Issues Conclusion
W Band Development Agreement
1. Did BSO enter into the W Band Radio
Development Agreement as agent for
Aspara (the undisclosed principal), or
in its own capacity?
BSO entered into the W Band Radio
Development Agreement in its own
capacity.
Supply Agreements
2. Did Apsara and EMClarity enter into
agreements in May and June 2019, for
the supply of E Band and W Band
radios?
Yes.
3. Alternatively to (2), was the W Band
Radio Development Agreement
varied?
No – Apsara and EMClarity entered into
new agreements and the W Band Radio
Development Agreement was terminated.
Implied Terms
-- 16 of 136 --
17
4. Did the Supply Agreements (or the W
Band Radio Development Agreement
as varied) contain an implied term that
the E Band and W Band radios would
be supplied within a “reasonable
time”?
The Supply Agreements (referred to by
me as the 2019 Agreements) are
unconditional agreements to supply
radios, which contained an implied term
that the radios would be delivered within
a reasonable time.
5. If there was such an implied term, what
was a “reasonable time” for the supply
of those radios?
On the evidence, it was impossible for me
to determine, on a reasoned basis, and
without speculating, the date upon which
a reasonable time for the supply of E Band
or W Band radios would elapse.
6. Did EMClarity breach the implied
term by failing to supply the E Band
and W Band radios within a
“reasonable time”, being by 30
October 2019, or alternatively 31
January 2020, 6 May 2020 or, at the
latest, the date of trial?
It was tempting to conclude that there had
been a failure to supply by, at the latest,
the date of trial. But I was concerned that
such a finding would involve speculation.
On the evidence I was not able to answer
this question.
The Quality Review
7. Was a Quality Review in the terms
instituted by EMClarity permitted by
the terms of the Supply Agreements or
the W Band Radio Development
Agreement?
The Supply Agreements did not permit
the “Quality Review”.
It was unnecessary for me to answer the
question whether the W Band Radio
Development Agreement permitted the
Quality Review.
8. Was the Quality Review a genuine
and/or necessary review of the E Band
or W Band products? Or was it a “go-
slow” in order to prioritise the interests
of McKay Brothers / disadvantage the
Plaintiffs?
The plaintiffs acknowledged that it was
unnecessary for me to make a finding that
the Quality Review was in effect a sham.
I was not prepared to make an
unnecessary finding.
-- 17 of 136 --
18
9. By subjecting the order of W Band and
E Band radios to the Quality Review,
and/or delaying the development and
shipment of the order, did EMClarity
breach the terms of the Supply
Agreements or the W Band
Development Agreement?
Having found that EMClarity breached
the Supply Agreements by repudiation, I
did not need to reach a finding on this
issue.
Repudiation
10. Was EMClarity’s conduct, in
subjecting the order of W Band and E
Band radios to the Quality Review,
and/or delaying the development and
shipment of the order a repudiation of:
(a) the Supply Agreements?
(b) the W Band Radio Development
Agreement?
EMClarity repudiated the Supply
Agreements.
EMClarity and BSO terminated the W
Band Radio Development Agreement.
Confidentiality
11. Were the W Band Project, the terms of
the W Band Radio Development
Agreement, the Customer Material
under the W Band Radio Development
Agreement, the Alternative Strategy,
the Quote, and the Purchase Orders
(together the Material) confidential?
The W Band Project, the terms of the W
Band Radio Development Agreement and
the Customer Material under the
agreement were “Confidential
Information” as defined in the agreement.
The Alternative Strategy, the Quote and
the Purchase Orders were information and
documents in relation to which equity
would impose obligations of confidence.
12. Was the Material disclosed by
EMClarity to McKay Brothers?
There was disclosure of BSO’s
information, including “the Material” but
not all of the disclosed information was
confidential.
-- 18 of 136 --
19
13. Was there a contractual obligation
under the W Band Radio Development
Agreement to keep the Material
confidential and not disclose it to
McKay Brothers?
Yes – in so far as the W Band Project, the
terms of the W Band Radio Development
Agreement and the Customer Material
was concerned.
14. Was there an equitable duty of
confidence to keep the Material
confidential and not disclose it to
McKay Brothers? What is the scope of
any such equitable duty?
Yes – in relation to the Alternative
Strategy, the Quote and the Purchase
Orders.
As to the balance of the Material, to which
a contractual obligation of confidence also
applied, the law goes both ways – but
regardless, the equitable duty would not
operate to convert disclosure which was
authorised by the contract into
unauthorised disclosure.
15. Was the contractual duty breached? No.
16. Was the equitable duty breached? Yes.
Apprehended breach
17. Does BSO/Apsara hold a belief that
EMClarity will further delay the
development/shipment of the radios?
Is that belief reasonable?
Yes.
18. Does BSO/Apsara hold a belief that
EMClarity will, in the future, breach
the confidentiality provisions of the W
Band Radio Development Agreement
or the equitable duty of confidence? Is
that belief reasonable?
Yes.
-- 19 of 136 --
20
19. Does BSO/Apsara hold a belief that
EMClarity will, in the future, breach
the exclusivity provisions of the W
Band Radio Development Agreement/
Supply Agreements? Is that belief
reasonable?
I have found that the W Band Radio
Development Agreement is at an end –
which means exclusivity ends in
accordance with clause 2.
EMClarity has repudiated the Supply
Agreements. The second plaintiff may
choose to terminate the Supply
Agreements. The exclusivity provisions
do not survive termination. It is preferable
to defer the answer to this question until
the second plaintiff has indicated whether
it will elect to terminate the Supply
Agreements.
[4] An outline of the evidence and my reasons for these conclusions follow.
[5] My conclusions do not resolve matters between the parties, but they will inform the next
steps of this litigation.
[6] The parties are directed to confer about the next steps and to contact my associate, by no
later than 23 April 2021, with agreed draft directions or orders; or a request for a review
of the matter.
[7] At this stage, I will restrict publication of these reasons to the parties and to their solicitors
and counsel (subject, in the case of the defendant, to the orders made by Brown J on 27
November 2019, and varied by me on 4 August 2020).
The parties
[8] BSO Network Inc (BSO), the first plaintiff, is an American company which provides IT
and telecommunications services globally. Since December 2017, Apsara Networks
Inc, the second plaintiff, has been one of its wholly owned subsidiaries.
[9] BSO provides wireless network services to the New York Stock Exchange (NYSE), the
NASDAQ1 and the Chicago Board Options Exchange (CBOE). These three exchanges
1 The National Association of Securities Dealers Automated Quotations System Stock Market.
-- 20 of 136 --
21
are in a geographical area known as the New Jersey (or NJ) Equity Triangle.2 Mahwah,
Carteret and Secaucus (towns in NJ) are the three “points” of the triangle.
[10] BSO’s major competitor in the market for wireless services in the NJ Equity Triangle is
McKay Brothers.3
[11] EMClarity, the defendant, is a Brisbane-based company with global reach, which
designs, develops, produces and supplies microwave and millimetre wave radio
technology.
[12] McKay Brothers acquired EMClarity in September 2019. Thus, BSO’s major competitor
in the NJ Equity Triangle market acquired the company which was the source of the radios
they each needed to provide wireless network services in that market.
The terminology of wireless networks
[13] Some understanding of terminology is necessary to understand these reasons.
[14] Radio waves travel across different frequencies of the radio spectrum – known as bands.
Radio wave frequency is measured in hertz. In the USA, the Federal Communications
Commission (FCC) is responsible for granting licences to entities to permit them to
transmit information using radio waves in certain bands with assigned frequencies.
[15] Bands are enabled through radio technology.
[16] A network is a medium for radio wave communication.
[17] A path is the connection between two points in a network. The word “path” might also
be used to describe a shorter segment (a “hop”), which, together with other segments,
makes up an overall circuit.
[18] High frequency trading networks are designed to create the most efficient path possible
between (for example) the NYSE, NASDAQ and CBOE, to enable financial market
participants to automate the collection of pricing information and action (such as to buy
or sell securities) in accordance with a participant’s trading strategy.
[19] Two of the most important features of a network are its latency and its bandwidth.
Generally, the lower the latency, the faster the data may be sent from one place to another.
2 There are other financial markets and trading houses within or near the NJ Equity Triangle.
3 Although Mr Boyle for the defendant was not prepared to describe BSO as McKay Brothers’ major competitor,
Mr McGowan was not challenged on the proposition that they were. Also, as I have indicated below, where
there was a conflict in the evidence between Mr Boyle and another witness, I preferred the evidence of the
other witness.
-- 21 of 136 --
22
The higher the bandwidth, the greater the volume of data which may be transmitted over
a network.
[20] The use of millimetre wave spectrum bands for the provision of fixed, point to point,
wireless services allows for lower latency than a fibre connection. (Before it acquired
Apsara, BSO operated a fibre optic network.)
[21] The amount of spectrum available within a particular band also affects network
performance. Bands with fewer users are generally better because there is less signal
interference.
The provision of wireless network services in the NJ Equity Triangle
[22] Apsara specialises in the provision of wireless networks to financial markets, including
those in the NJ Equity Triangle.
[23] BSO’s acquisition of Apsara allowed it to compete in the market for wireless network
services in the NJ Equity Triangle and other financial capitals.
[24] The primary spectrum allocations in the NJ Equity Triangle include the E Band and the
W Band.4 The E Band has a large number of users and is highly congested (causing a
propensity for greater signal interference). BSO’s current network is the overcrowded E
Band. (Upon BSO’s acquisition of Apsara, Apsara’s E Band licence was transferred to
BSO.)
[25] There are few users of the W Band in the NJ Equity Triangle so it does not suffer from
the same congestion or interference issues as the E Band. However, there is less spectrum
available in the W Band than in the E Band. [redacted]
Key individuals
[26] The table below identifies the key individuals associated with BSO, Apsara and McKay
Brothers.
Callum McGowan Director of Radio Frequency Networks at BSO.
Mr McGowan had been the Director of Network Engineering
at Apsara since 2012. He joined BSO when it acquired
Apsara in December 2017.
Michael Ourabah Sole Director of Apsara and the Chief Executive Officer of
BSO and Apsara.
4 There is another primary spectrum allocation known as the V Band which is irrelevant to this matter.
-- 22 of 136 --
23
Emmanuel Pellé Chief Operating Officer and Senior Vice President of BSO.
Mr Pellé has held these roles since March 2016.
His responsibilities include reviewing and approving BSO’s
entry into major or significant contracts.
Dr Peter Baines Chief Executive Officer of EMClarity.
Dr Baines has held this role since January 2019. In late
February 2019, he was also appointed Managing Director and
Company Secretary of EMClarity.
Prior to his appointment as CEO, he had been the General
Manager of EMClarity since 1 June 2017.
Notwithstanding changes in his title, Dr Baines agreed that he
was (as General Manager) and is (as Managing Director) the
“face for [actual or potential] customers” when negotiating a
contract.
David White Head of Operations at EMClarity (with “Operations”
comprising production, installation and support).
Dr Ashoka Halappa Chief Engineer at EMClarity.
Dr Halappa replaced James McDougal as Chief Engineer in
March 2019.
Dr John Ness Chairman and Executive Director of EMClarity.
Barry Dench Production Quality Manager at EMClarity.
-- 23 of 136 --
24
Timothy Boyle Mr Boyle joined McKay Brothers as a director in December
2016 and holds the title of Director of Operations.
He became a director of EMClarity following McKay
Brothers’ acquisition of it on 27 September 2019.
Dr Stephane Tyc; Dr
Robert Meade; Paul
Kennard
Directors of McKay Brothers who were appointed to the
board of EMClarity after McKay Brothers’ acquisition of it.
Agreements between BSO, McKay Brothers and EMClarity
[27] The services provided by BSO and McKay Brothers in the NJ Equity Triangle require the
radios which EMClarity is in the business of developing, producing or supplying. These
radios are classified by their band and include LMDS, E Band and W Band radios.
[28] LMDS and W Band radios have the potential for better performance in the NJ Equity
Triangle (in terms of speed and clarity) than E Band radios.
[29] Obviously, a competitor in the market for the delivery of wireless network services to the
NJ Equity Triangle will gain an advantage if they acquire and deploy “better” radio
technology than others in the market.
[30] In 2016, with a view to gaining a competitive edge in the market for wireless network
services in the NJ Equity Triangle, McKay Brothers entered into an agreement with
EMClarity, in pursuance of which EMClarity agreed to develop and supply LMDS radios
to McKay Brothers.
[31] In June 2018, with a view to gaining a competitive edge in the same market, BSO entered
into an agreement with EMClarity, in pursuance of which EMClarity agreed to develop
and, assuming successful development, supply W Band radios to BSO (the “W Band
Radio Development Agreement”).
[32] In 2019, after further negotiations with BSO, EMClarity entered into four agreements to
supply W Band and E Band radios to Apsara (the “2019 Agreements”). The
characterisation and effect of these four agreements are contentious.
[33] For obvious reasons, each competitor wished to keep confidential the timing of, fact of,
and detail of, their agreement with EMClarity for the development of radio technology.
Events leading up to McKay Brothers’ acquisition of EMClarity
-- 24 of 136 --
25
[34] In May 2019, Tim Boyle (of McKay Brothers) was sent by EMClarity, by mistake, an
invitation to a “W Band Project Meeting”. On 28 May 2019, Mr Boyle contacted Dr
Baines and asked him whether EMClarity was pursuing a W Band radio. His email read
–
Hi Peter –
Is EM Clarity pursuing a w-band radio? I built these once upon a time in the
US, and am quite interested in their possible commercialization.
[35] Then followed a series of emails between them.
[36] Dr Baines told Mr Boyle that EMClarity were “looking into it” –
Hi Tim,
Yes, we are looking into that.
Your previous experience with W-band sounds interesting. How far did you
get with that?
[37] Mr Boyle said he “[g]ot a couple [of] links working in the field”. He continued (my
emphasis) –
… 10Gbps OOK. Tricky thing was getting band flatness when I was being
lazy about modulation schemes because of latency aversion.
Lots of licencing risk in the US which was uncomfortable at the time.
Would love to talk through product interest there. You’re nearly
competing with FSOs at 100+GHz from a reliability and beamwidth/tracking
perspective.
[38] On 30 May 2019, Dr Baines told Mr Boyle that he could not discuss the details of the
Band project (my emphasis) –
Interesting approach you took.
Unfortunately, I can’t discuss the details of our project. It’s under
disclosure. In fact I shouldn’t even have acknowledged we were looking at
this band but I knew we had made a slip-up with a meeting invite sent to you
when it was supposed to be internal only.
[39] On 2 June 2019, Mr Boyle asked Dr Baines whether there was a way they could work
together on a W Band radio (my emphasis) –
We’re looking at rebooting my past efforts in this regard, if there’s a way
we can work together here instead of my using who I did previously, I would
be interested in talking about it.
[40] On 3 June 2019, Dr Baines said that he did not think they could “from our side”.
-- 25 of 136 --
26
[41] The next day, 4 June 2019, McKay Brothers approached Dr Baines about acquiring
EMClarity. On BSO/Apsara’s case, the timing of McKay Brothers’ interest in the
acquisition of EMClarity was not a coincidence: it was triggered by their belief that
EMClarity was developing a W Band radio for a competitor.
[42] Relevant to that misdirected invitation is the following evidence from BSO’s Mr
McGowan –
On or about 27 July 2019, I met with Timothy Boyle of McKay Brothers in
Chicago. We had been working on a separate (unrelated) project together and
he had earlier contacted me and asked if I wished to have a coffee catch-up
with him, to which I agreed. In the conversation on 27 July 2019 we discussed
the industry in general and as part of that I said words to the effect “I know
you guys [by which I meant McKay Brothers] are doing a fair bit in 28Ghz.”
Mr Boyle said words to the effect “I understand someone’s going to be doing
something in W Band”. I was surprised by this statement. It was not clear to
me whether Mr Boyle knew that BSO had engaged EMC to develop W Band
radios. I suspected at the time that he was “fishing” for confirmation that
BSO was looking at W-Band technology. Mr Boyle went on to ask me if I
wanted at [sic] job with McKay Brothers in the RF space. I responded with
words to the effect “what kind of position do you have in mind”, to which he
responded with words to [sic] effect “whatever you want, you can write your
own cheque”.
[43] McKay Brothers purchased EMClarity on 27 September 2019.
BSO informed of the takeover and the “Quality Review”
[44] On 8 October 2019, EMClarity informed BSO that it had been taken over by McKay
Brothers. EMClarity informed BSO that it had decided to undertake a “Quality Review”
of EMClarity’s processes and products and that there would be, therefore, a “pause” on
all shipments of radios.
[45] EMClarity did not tell BSO when it expected its Quality Review to conclude or when it
expected to supply radios to Apsara.
[46] EMClarity is yet to supply any radios to Apsara. In fact, it cancelled orders for the parts
required to build the radios.
[47] BSO/Apsara contend that, having learnt that EMClarity was pursuing a W Band radio for
BSO/Apsara, McKay Brothers acquired EMClarity and implemented a sham quality
review which was designed to cause EMClarity to prioritise its LMDS radios over the
radios ordered by Apsara – thereby assuring McKay Brothers a competitive advantage in
the NJ Equity Triangle.
-- 26 of 136 --
27
The parties’ cases
[48] At the core of the plaintiffs’ case are allegations of breach and repudiation of supply
agreements between EMClarity and Apsara.
[49] In general terms, the plaintiffs’ case is that in May/June 2019, the W Band Radio
Development Agreement was replaced by four new agreements between Apsara and
EMClarity, in pursuance of which EMClarity agreed to supply to Apsara a mix of E Band
and W Band radios (referred to by me as “the 2019 Agreements”; referred to by the
plaintiffs as “the Supply Agreements”).5 The 2019 Agreements did not state the date by
which the E Band and W Band radios were to be supplied. BSO/Apsara submit that the
law would therefore imply a term that the radios were to be supplied within a reasonable
time.
[50] The plaintiffs’ primary case is that the 2019 Agreements are separate from the W Band
Radio Development Agreement and ought to be simply construed as contracts to supply.
In the alternative, the plaintiffs’ case is that the W Band Radio Development Agreement
was varied by the 2019 Agreements between Apsara and EMClarity to “take out the
notion of development [and instead] … to actually deliver the radios”.
[51] In its defence, EMClarity notes that –
there are two stages or phases of the W Band Radio Development Agreement: the
development stage and the production and supply stage; and
its production and supply obligations under the W Band Radio Development
Agreement were conditional upon successful development of the W Band radio.
[52] EMClarity submits that –
the agreements between it and Apsara in May/June 2019 were not “new”
agreements to supply radios – rather, they were variations of the W Band Radio
Development Agreement;
the 2019 Agreements varied only the production and supply phase of the W Band
Radio Development Agreement;
the 2019 Agreements had no effect on the development phase of the W Band Radio
Development Agreement;
the 2019 Agreements concerned what EMClarity would deliver to Apsara after, and
only if there were, a successful development phase; and
5 I have chosen a neutral defined term. The plaintiffs’ selection of the term “the Supply Agreements” reflects
their contention that the 2019 Agreements required the defendant to supply W and E Band radios, within a
reasonable time.
-- 27 of 136 --
28
the development phase has not concluded.
[53] EMClarity says that, although the hope may have been that the variations made to the W
Band Radio Development Agreement by the 2019 Agreements would achieve truncated
delivery times for the supply of the “product”, supply of the product was always subject
to the successful completion of the development stage. Both parties “sign[ed] on to” the
risk that development might not be successful. Also, the Quality Review was genuine.
[54] EMClarity argues that the W Band Radio Development Agreement, including as varied,
is a contract of a class different from the class of contracts into which reasonable time
terms are implied. It is a research/development and supply contract which anticipates
uncertainty in the research/development stage.
[55] Further, the implication of a reasonable time term for delivery of the W Band radios is
inconsistent with the express terms of the W Band Radio Development Agreement, which
included a term that time estimates were non-binding. Even if a “supply within a
reasonable time” term were implied, the quantification of that reasonable time had to take
into account that the W Band radio is a sophisticated product which is difficult to produce
to its required specifications.
The relief claimed by the plaintiffs
[56] By their amended originating application the plaintiffs seek, as final relief, orders –
(i) requiring specific performance by EMClarity of the agreements to supply W Band
and E Band radios;
(ii) restraining EMClarity from taking any steps to deliver or supply to McKay Brothers
(or any of its related entities) “the Product”, as defined in the 8 June 2018 W Band
Radio Development Agreement; that is the W Band 92-95 GHZ low latency radio;
and
(iii) permanently restraining EMClarity from disclosing information about the ‘Product’
or the ‘Project’ and other specified related matters to McKay Brothers or its related
entities.
[57] In the alternative to orders for specific performance, the plaintiffs seek a declaration that
EMClarity has repudiated the W Band Radio Development Agreement; “and further and
in the alternative” the W Band Supply Agreement and the E Band Supply Agreement.
[58] The plaintiffs also seek damages for breach of the agreements, equitable compensation
for breach of confidence, and any other order the Court sees fit to make.
[59] The trial before me concerned the question of the defendant’s “liability” only.
-- 28 of 136 --
29
Credibility issues
[60] Four witnesses were called to give evidence – two for each side. Their examination in
chief was by way of affidavits.
[61] The cross-examination of the plaintiffs’ two witnesses, Emmanuel Pellé and Callum
McGowan, left me with no concerns about their credibility. Nor was I concerned about
any aspect of their affidavit evidence.
[62] The defendant called Peter Baines and Timothy Boyle.
[63] Insofar as his oral testimony was concerned, I found Dr Baines a careful witness who
appeared to be replying truthfully, though not expansively, to the questions asked of him.
However, as will appear below, I found some of the claims in his affidavit to be inherently
incredible.
[64] I found Mr Boyle an unimpressive witness. For example, I found that he deliberately
minimised his understanding of McKay Brothers and BSO/Apsara as competitors in the
NJ Equity Triangle market. And I found his evidence about his knowledge of Mr
McGowan’s employment untruthful. I formed the view that he understood the “line” he
had to hold (to benefit the defendant’s case) and that he tailored his evidence to hold that
line.
[65] Mr Boyle’s performance in the witness box caused me to have serious reservations about
the assertions he made in his affidavit – especially those which were completely in the
defendant’s interests.
[66] Overall, I considered the contemporaneous documents, such as emails, notes of
conversations or minutes of meeting, to provide the most reliable evidence of relevant
matters.
Structure of these reasons
[67] It will be apparent from the above that one of the critical issues for me to decide is
whether, in 2019 –
the parties varied the 2018 W Band Radio Development Agreement, retaining its
development stage but altering the products which were to be supplied in pursuance
of it, assuming successful development; or
BSO and Apsara entered into new agreements which required EMClarity to supply
W Band and E Band radios to Apsara unconditionally.
[68] The determination of that issue has a significant impact on the “supply within a reasonable
time” and repudiation issues. It also bears upon the confidentiality issues.
-- 29 of 136 --
30
[69] The parties’ accepted that I was to determine this critical issue having regard to the
context in which the parties dealt with each other before and after their 2018 and 2019
agreements.
[70] My identification and analysis of relevant communication and conduct follows. I then
deal with each of the 19 issues in turn.
Relevant background facts
2017 – 2018: Discussions between Mr McGowan and Dr Baines
[71] In early 2017, it was rumoured that McKay Brothers was developing a lower-latency
network in the NJ Equity Triangle. At that time, Mr McGowan worked for Apsara, which
was interested in competitively “refreshing” its network. Mr McGowan was aware that
the radios which EMClarity developed and produced could, with some adaptation, be
used in the provision of ultra-low latency circuits between stock exchanges. He began to
deal with Dr Baines in about June 2017. At the time, EMClarity’s E Band radios were
subject to “exclusivity arrangements” which meant that they could not be supplied to
Apsara. Accordingly, Dr Baines and Mr McGowan discussed other options, including
the development of a new radio in W Band.
[72] After BSO acquired Apsara, Mr McGowan made it clear to BSO’s board that, to remain
competitive, it had to develop an ultra-low latency, high capacity, wireless network. With
the board’s approval, he continued discussing a W Band network with Dr Baines, having
informed Dr Baines that BSO had acquired Apsara. I accept that Mr McGowan made it
clear to Dr Baines that his objective was to develop a better network than McKay
Brothers’ network and that a W Band product was necessary (from BSO’s point of view)6
for it to do so.
[73] On 10 February 2018, Mr McGowan told Dr Baines, in effect, that the success of the new
network was vital to BSO and that BSO needed to deploy it within the next six months.
[74] On 14 March 2018, Dr Baines sent a proposal to Mr McGowan describing a certain
approach to the development (which would involve a third party) and stating, in effect,
that, on that approach, development time would be six months. Dr Baines told Mr
McGowan that the work was not considered “high risk” and elaborated on the reasons
why that was so. He proposed a “preliminary design phase” which would “quickly” prove
the design approach. He said the preliminary design phase “would take one month from
the placement of order”.
[75] Mr McGowan continued to negotiate with Dr Baines and, ultimately, Dr Baines sent Mr
McGowan a final proposal on 20 April 2018. The proposal (entitled “Information and
Pricing for BSO Networks Ultra-Low Latency W Band Equipment in 92-95 GHZ Band”)
6 In his affidavit, Mr Boyle expressed a negative opinion about a W Band product.
-- 30 of 136 --
31
included the following (my emphasis). I note the optimistic tone of this proposal when it
comes to time frames and its description as “low risk” –
[redacted]
[76] The offer also included exclusivity on certain terms.7
[77] BSO’s board determined to proceed with the proposal on 3 May 2018. An agreement
reflecting the proposal, entitled the “W Band Radio Development Agreement Terms” was
executed by BSO and EMClarity on 14 June 2018 (referred to in these reasons as the “W
Band Radio Development Agreement” or the WBRDAT).
The agency issue
[78] It is expedient to mention now that agency is an issue in the plaintiffs’ alternative case.
[79] The plaintiffs contend that BSO acted as Apsara’s agent – Apsara being its undisclosed
principal – in the formation of the WBRDAT. The defendant urged me to conclude that
the plaintiffs had never discussed agency prior to the formation of the WBRDAT and that
BSO contracted with EMClarity on its own behalf.
[80] The plaintiffs evidence about their “agency” discussions included the following in Mr
McGowan’s affidavit (my emphasis) –
Given the significant value of the investment that Apsara and BSO were
making with EMC and the size of the payments that needed to be made up
front, BSO’s management was concerned to manage the cash flow. I had a
number of discussions about the staged payments with Mr Ourabah and Mr
Pellé, including the tax implications and accounting treatment of the
payments. Over a number of conversations with Mr Ourabah and Mr
Pellé it was agreed that the W Band project would be paid for and owned
by Apsara, although BSO, as Apsara’s parent company, would continue
with the negotiations on its behalf.
[81] In his affidavit, Mr Pellé said (my emphasis) –
As BSO’s Director of RF, Mr McGowan was responsible for negotiating the
technical requirements and terms of an agreement to develop W Band radios.
As COO, my role was to provide direction and support to Mr McGowan in
negotiating the agreement and, along with Mr Ourabah, provide high-level
approval of the terms and pricing of the agreement. I was also ultimately
responsible for signing the contract. In that regard, I discussed with Mr
Ourabah and Mr McGowan and the effect of what was said was that
7 And technical detail.
-- 31 of 136 --
32
Apsara would pay for and own the product developed under the contract
but that BSO would execute the contract on behalf of Apsara.
…
I executed the W Band Radio Development Agreement … on behalf of BSO
on 8 June 2018 …
The agreement was executed … in the name of BSO but with the
intention that Apsara would be the end user of the services (and owner
of the assets, being the W Band radio product) and pay for these services
accordingly. I had discussions with Mr Ourabah and Mr McGowan in which
this was discussed. During the course of the [W Band Radio Development
Agreement], Apsara has paid the invoices issued to it under that agreement,
and also invoices issued in respect of the supply of certain E Band radios
issued in connection with the [W Band Radio Development Agreement]. This
expenditure is recorded in Apsara’s accounts.
The W Band Radio Development Agreement – key terms
[82] The following terms of the W Band Radio Development Agreement are the important
ones in this case (my emphasis). The “Customer” is the first plaintiff.8
[redacted]
…
Agreed Terms
1 Project
…
Research
1.4 The parties acknowledge and agree that the outcome of research
projects such as the Project cannot be guaranteed. However,
individual component technologies required to increase the likelihood
of the Project’s successful conclusion have been proven to a large
degree … Design activity including simulation modelling and the use
of other methods will identify potential critical points of failure which
can then be designed out. Prototype manufacture and unit/system
testing in a lab environment will provide measurement data to uphold
forecast performance indicated by modelling to indicate early in the
Project how likely a successful conclusion will be. EMC does warrant
that it has the requisite engineering capability to undertake the Project
8 The “Customer” was defined in the schedule to the WBRDAT as “BSO Networks LLC”. That is an error – there
is no such entity.
-- 32 of 136 --
33
in a competent and professional manner and that it will manage the
Project in a way which aims to identify risks and issues that can be
mitigated by regular review and decision making by EMC and
Customer.
1.5 The estimated completion dates in the Project Plan (and any other
estimated dates provided to Customer by EMC) are estimates only
and are not binding on EMC.
…
2 Exclusivity
[redacted]
If any one of these criteria is false then the Exclusivity does not apply.
2.3 EMC agrees not to accept any orders or ship any product, which would
contravene the Exclusivity criteria, to other customers while
Exclusivity applies.
2.4 Exclusivity starts when Customer places its order for the NRE [non-
recurring engineering] development and the [redacted], and makes the
defined payments according to the Sale Terms.
…
2.6 Exclusivity may be extended for periods of 12 months at a time by
either: -
(a) Placing an order for a subsequent batch of [redacted] …
(b) Placing one or more orders for EMClarity in-house products
where the combined total of said orders is at least [redacted], and
with the payment terms of each order being the same as the Sale
Terms, and where delivery on all such products ordered must be
within the coming 12 months and EMC accepts the order; or
(c) Making a payment of [redacted].
…
3 Acceptance
3.1 Unless Customer and EMC mutually agree to modify the Acceptance
Criteria for documentation, design information, tests and performance
measurements … prior to the commencement of work of each
Milestone as described in the Schedule, such Acceptance Criteria shall
be the basis upon which Customer shall have no less that fourteen (14)
days to conduct Acceptance testing (where applicable) following
delivery of such Milestone. Notwithstanding the foregoing, the
Customer and EMC shall negotiate and agree in good faith on
acceptable variances to the Acceptance Criteria for the documentation,
-- 33 of 136 --
34
design information, tests and performance measurements that need to
be achieved to meet the Milestone, based upon Customer’s stated
performance objectives and network specifications. Any such mutually
agreed upon changes shall be the basis for Customer’s Acceptance
testing once such changes are memorialized in writing executed by
EMC and Customer in a relevantly amended Milestone Payment
Deliverables in the Schedule.
…
5 Term and termination
…
5.4 Termination due to failure of Development Stage of Project (Before
Acceptance of Milestone 4)
(a) The parties may terminate this agreement up to the Acceptance of
Milestone 4 by mutual written agreement if the parties conclude
that the Project cannot be successfully completed.
(b) The parties may mutually agree to delay the project up to the
Acceptance of Milestone 4 at any time by written agreement if
the parties conclude that a reasonable external cause, such as for
example a delay in sourcing input components, warrants a delay
to work and Milestones.
(c) Customer may terminate this Agreement up to the end of
Milestone 4 for Good Reason.
…
7 Confidential Information
Obligations of confidence
7.1 Each party agrees to keep confidential, and not to use or disclose, other
than as permitted by this agreement, any Confidential Information of
the other party before or after entry into this agreement.
Exclusions
7.2 The obligations of confidence in clause 7.1 do not apply to Confidential
Information:
(a) that is required or requested to be disclosed by applicable law …
(b) that is in the public domain otherwise than as a result of a breach
of this agreement or other obligation of confidence by the
receiving party; or
-- 34 of 136 --
35
(c) that is already known by, or rightfully received, or independently
developed, by the recipient of that Confidential Information free
of any obligation of confidence.
Restrictions on disclosure
7.3 Each party may use and disclose Confidential Information of the other
party only:
(a) with the prior written consent of the other party; or
(b) to that party’s directors, agents, professional advisors, employees,
contractors and permitted sub-contractors solely for the exercise
of rights or the performance of obligations under this agreement;
or
(c) to auditors, lenders (or potential lenders), investors (or potential
investors) of such party.
…
9 Amendments to the Project
9.1 The parties may agree on changes to the Project, Project Plan and the
Fees in writing from time to time.
…
14 Definitions and Interpretation
…
Confidential information means the terms of this agreement, including any
pricing information, and in the case of EMC, includes EMC Material and in
the case of Customer includes Customer Material.
...
Project means the project described in the Schedule.
Project Plan means the project plan specified in the Schedule.
…
Schedule means the W-BAND RADIO DEVELOPMENT AGREEMENT
SCHEDULE, as it (or any portion thereof) may be amended and/or restated
in writing by the parties from time to time. For the avoidance of doubt, in the
event of any conflict between the terms of this agreement and the terms of the
Schedule, the terms of the Schedule shall control and govern.
…
Customer Material means any material provided by or to which access is
given by Customer to EMC for the purposes of this agreement, including
documents, equipment, reports, algorithms, technical information, know how,
-- 35 of 136 --
36
studies, plans, charts, drawings, calculations, tables, trademarks, logos,
schedules and data stored by any means.
[83] The Schedule described the Project as follows –
The project involves developing and then providing a production batch
of a new radio for use by the Customer to provide communications
services. This Schedule is subject to the terms and conditions of the W
BAND Radio Development Agreement Terms. Any terms used but not
defined herein shall have the meanings as set forth therein.
The target specification of the new radio is provided in this Schedule. The
concept design for the radio on which the quote for the project works is
illustrated in the Sales Quote.
The project will be in 3 stages.
Stage 1: Will be for preliminary design which prototypes digital IF up
conversion (to E Band) on a two-hop repeat and proves SNR and
jitter expected, with report provided. The parties may mutually
agree upon deviations that are necessary to meet agreed
requirements.
On completion of the preliminary design the Customer can at their
discretion choose to discontinue the project if it believes the
project will not fill operational requirements. If the Customer
wants to continue to the next stage of detailed design, the
Customer will pay Milestone 3.
Stage 2: Will be conducted if the Customer decides to continue with the
development after Stage 1. Prior to start the customer must pay
Milestone 2. In this stage, EMC will develop and test the modem
and W band up and down converters and conduct FCC
compliance testing.
On completion of the detailed design the Customer can choose to
discontinue the project. If Customer wants to continue to the next
Stage, it must order the production radios and pay the production
deposit payment.
Stage 3: [redacted]
[84] [redacted]
[85] The Project Plan was as follows –
-- 36 of 136 --
37
Milestone Estimated
completion date
(Month)
Milestone
Payment
(excluding GST
and any other
taxes, customs
duties, levies or
imposts) (US$)
1. Signing of this agreement for
Conduction of Preliminary Design Work
M0 [redacted]
2 Submission of Preliminary Design
Report
M0 + 1 [redacted]
3 Commencement of Final Design M0 + 1 [redacted], in
advance on
acceptance of
Milestone 2
4 Successful Design Review of Final
Design
M0 + 6 [redacted]
Total of the development [redacted]
5 [redacted] Production Order M0 + 6 [redacted]
6 Factory Acceptance testing of
[redacted]
Order
M0 + 9 [redacted]
7 Acceptance on Delivery in USA M0 + 10 [redacted]
Total of the Production lot [redacted]
[86] The Schedule also included the “Milestone Payment Deliverables” as follows –
-- 37 of 136 --
38
Milestone Deliverables – Milestone Payment Acceptance
1 Signing of this
agreement
Signed contract (this agreement) and approval to conduct
preliminary design.
Customer must accept and pay EMC’s Invoice for
Milestone 1 prior to work starting on preliminary design.
2 Preliminary Design
Review
Delivery of a report describing the successful prototyping
of digital IF up conversation (to E-band) on a two-hop
repeat and proving SNR and jitter expected.
3 Commencement of
Final Design
Customer must Accept Milestone 2 prior to work starting
on the Final design. Customer can discontinue further
work prior to making such payment and forfeit
Milestones 1 and 2 payments.
4 Final Design
Review
Successful review of the finished design.
Customer must Accept Milestone 4 prior to work starting
on the Production Build. Customer can discontinue
further work prior to making such payment and forfeit
Milestone 1, 2 and 3 payments.
5 [redacted]
Production Order
Kick off payment on approval by Customer to begin
[redacted] batch build.
Customer must accept EMC’s Invoice Milestone 5 prior
to work starting on manufacture of the Production Units
in accordance with the Sale Terms.
6 Factory
Acceptance Testing
Successful testing of the [redacted] order to production
specification.
-- 38 of 136 --
39
of [redacted]
Production Order Customer must Accept Milestone 6 prior to shipment in
accordance with the Sale Terms.
7 Acceptance on
Delivery
Final Acceptance on delivery of production units to
Customer Depot in USA.
Acceptance and final payment on invoice will be in
accordance with the Terms of Sale.
[87] A document entitled “Exhibit A – to W Band Development Agreement Product Offer
Terms” stated that the price (for the product) was [redacted]. The “Payment Terms”
were –
60% of batch price on order, 30% of batch price on completion of Factory
acceptance testing and packaged ready for shipping and 10% on Acceptance
of Delivery. No agreement for supply of follow-on batch orders exists
between EMClarity and Customer until (1) EMClarity has received an official
purchase order from Customer, (2) EMClarity has returned a purchase order
confirmation to customer with an invoice for the kick-off payment, and (3)
the customer has paid any product kick-off payment into EMClarity’s bank
account in accordance with the invoice where applicable.
[88] These payment terms correspond to the Milestone 5, 6 and 7 payments – which are in the
amount of 60 per cent, 30 per cent and 10 per cent of “batch price” respectively.
Milestone 1: The “kick off”
[89] The invoice for Milestone 1 was originally issued by David Watson of EMClarity to BSO.
Mr McGowan asked Mr Watson to re-issue the invoice to Apsara – which he did.
According to Mr McGowan, the request to re-issue the invoice to Apsara was consistent
with BSO’s determination that Apsara would be the corporate entity within the BSO
group which would “own” the project and the radios supplied in pursuance of the
WBRDAT.
[90] On 19 July 2018, Dr Baines chased Mr McGowan for the “kick-off payment”. He said,
“We will do our best to accelerate the development so would appreciate it if BSO could
also keep the milestone/payment side moving as well”. In emails to Dr Baines about
payment on 30 July and 2 August 2018, Mr McGowan referred to the project coming out
of the Apsara books.
-- 39 of 136 --
40
[91] Apsara paid the Milestone 1 invoice on 6 August 2018.9 After the receipt of the Milestone
1 payment, EMClarity began work on the Proof of Concept prototype.
Milestone 2: The Preliminary Design Report (August – November 2018)
[92] Progress to Milestone 2 involved testing a prototype for “digital IF10 conversion” for an
E Band radio. If digital IF conversion could not be achieved for an E Band radio, then it
could not be achieved for a W Band radio.
[93] On 19 August 2018, Dr Baines told Mr McGowan that EMClarity expected the “whole
development to be finished some time in the first quarter next year”.
[94] On 11 September 2018, Dr Baines told Mr McGowan that if he were to visit EMClarity
in October 2018, he would be able to “inspect the modem working on the lab bench
showing up conversion to E-Band and simulation of a two hop link (first milestone in the
development plan)”. If things went “well”, he might be able to see “a W-Band prototype”.
[95] On 9 October 2018, Mr McGowan went to EMClarity’s premises. A “Proof of Concept
Prototype” was tested for him but it was not successful. Based on that test, Mr McGowan
was of the view that BSO/Apsara would not see the first production of the W Band radios
until “early Q2 of 2019”.
[96] On 1 November 2018, Mr McGowan emailed Dr Baines and asked him whether there
was “any news of a graceful recovery from the bench test failure” (of 9 October 2018).
He also said, “I really need to see some forward progress here”.
[97] In reply, Dr Baines told him that he believed that the recovery was “virtually done”. He
said that the error rates for “data passing over RF” were “better than the spec” and that
EMClarity was “only a couple of days away” from sending Mr McGowan the preliminary
design report for RF at E Band. Dr Baines expressed positive views about the future
progress of project.
[98] The Preliminary Design Test Report – that is, the deliverable for Milestone 2 – was sent
by Dr Baines to Mr McGowan on 15 November 2018. Dr Baines informed Mr McGowan
that the preliminary design feasibility study had been “useful in determining the design
approach for the W Band product, to rule out some approaches that won’t deliver the
result and confirm those that support the goals”. He continued –
We’ve shown data being transmitted over RF at 64QAM within the error rate
specs, and have justification to believe that continuing with the W-Band
product development is feasible.
9 While he communicated his approval to proceed with the agreement, Mr McGowan does not believe that he
communicated a formal approval as required by the “Milestone 1 Deliverables” – nor was he requested to.
10 Intermediate Frequency.
-- 40 of 136 --
41
[99] “QAM” – quadrature amplitude modulation – is a way of representing digital signals as
analogue signals so that they can be transmitted through the air. The number before the
“QAM” is related to data throughput: the higher the QAM, the higher the radio’s data
throughput. “64QAM” was one of the target specifications in the WBRDAT. Before the
execution of the WBRDAT, EMClarity had never achieved a digital IF conversion with
a 64QAM modulated signal in the E Band or the W Band.
Milestone 3: Commencement of final design (November 2018 – January 2019)
[100] In accordance with the WBRDAT, EMClarity was next to work on the “Final Design” in
pursuance of Milestone 3. The Milestone 3 payment was to be paid in advance.
[101] In November 2018, Mr McGowan and Dr Baines discussed the Preliminary Design Test
Report and relevant technical matters. Between late November 2018 and March 2019, at
Mr McGowan’s request, EMClarity prepared path analyses and latency calculations for
BSO.
[102] A “path analysis” involves a prediction of signal strength in certain specified
circumstances and the likely interruption of signal transmission due to atmospheric
moisture. A “latency calculation” (at its simplest) is a calculation of the time it takes for
a signal to travel through the air. These analyses and calculations are relevant to the
design of a network. Dr Baines understood that their results would assist BSO in deciding
whether to proceed with W Band development.
[103] On 21 December 2018, Mr McGowan emailed Dr Baines (copying in Mr White and Mr
Dougal), requesting an update, including on the build timeline. The replies he received
did not include an update on the build timeline but did include the latest path analysis and
calculations.
[104] On 9 January 2019, Mr McGowan emailed Dr Baines, asking for an update on the “state
of the production phase”. He told Dr Baines that he had management “yelling” at him
that the project was “super late” putting them “significantly behind the competition”. Dr
Baines proposed a “conference call with the guys to go through the material we sent just
before Christmas”.
[105] According to his affidavit, in fact, Dr Baines found “bizarre” Mr McGowan’s question
about the “production stage” because there could be no production without a working
prototype (Milestone 3) and BSO had not then indicated whether it wished to proceed to
Milestone 3 or not. He said that, having submitted the “Milestone 2 Report”, the “ball
was in BSO’s court on whether it wanted to proceed with Milestone 3 or not”.
[106] On 11 January 2019, Dr Baines, Mr Dougal and Mr White (all from EMClarity) had a
telephone conversation with Mr McGowan. They discussed the calculations and “fade
margins”. A “fade margin” is a measure of how much excess signal strength is predicted
at a receiver radio under normal conditions. According to Dr Baines, Mr McGowan
considered that the fade margin in contemplation was not high enough to meet BSO’s
requirements.
-- 41 of 136 --
42
[107] According to Dr Baines, he told Mr McGowan during this telephone conversation that if
he wanted to “get on” with the production phase, then EMClarity had to get the
development done first. But, he said, “I did not say to Mr McGowan that the question in
his email to me of 9 January 2019 … was “bizarre” because I did not want to say anything
to upset Mr McGowan, who was a representative of EMC’s customer, BSO”.
[108] I find remarkable the suggestion that Dr Baines was unwilling to remind Mr McGowan
that development had to precede production so as not to “upset” him. Dr Baines and Mr
McGowan are mature, well-educated, professional representatives of their companies.
They were in discussions about the progress of an expensive agreement for the
development and supply of a new product which, by its terms, hinged upon EMClarity’s
ability to develop such a product. I find unpersuasive Dr Baines’ explanation as to why
he did not more forcefully remind Mr McGowan of the need for development (indeed
successful development) before production.
[109] On 14 January 2019, Dr Baines sent an email to Mr McGowan and others attaching “the
cut down path analysis and latency calc” for BSO’s network.
[110] [redacted]
[111] On 17 January 2019, Dr Baines and Mr McGowan spoke again about the path analyses
and latency calculations. They discussed the antenna sizes needed to yield the desired
performance of the network. Mr McGowan sent Dr Baines details of the maximum
antennas permitted at relevant sites.
[112] According to Dr Baines, at the failed demonstration and in telephone calls after the
delivery of the Milestone 2 Report, Mr McGowan said words to the effect that the
development project was “pretty risky”. I note that Mr McGowan said something similar
in an email to Dr Baines on 29 January 2019 (“95G is still high risk”) referred to below.
The critical correspondence
[113] In the paragraphs under this heading, I have considered the (mostly email) discussions
between Dr Baines and Mr McGowan which ultimately led to the 2019 Agreements. All
emphases in the quoted extracts under this heading are mine.
Late January 2019
[114] On 29 January 2019, Mr McGowan emailed Dr Baines, attaching a pdf of “39 band” and
asking whether that band was anything EMClarity could make use of.
[115] The email chain continued:
From Dr Baines to Mr McGowan –
[redacted]. The amount of spectrum that is designated in this document
would make it tight – only 1.4GHz for A and B – but could just be do-able.
-- 42 of 136 --
43
I had previously had my eye on this band because I am aware that at least one
of the big Telcos has a chunk of the spectrum in this band – thinking of 5G
fronthaul/backhaul.
From Mr McGowan to Dr Baines –
…
I think you and I might need to toss the options around a little. 95G is still
high risk.
[116] On 30 January 2019, Dr Baines sent Mr McGowan a spreadsheet showing the
recommended W Band configuration and budget under cover of an email which said –
…
We’ve finished looking at what configuration would suit a W-Band network
and I have attached that. This gives good fade margins on all hops, and
includes our recommended antenna sizing.
…
Happy to go into the risks in different options. We’ve put quite a lot of work
into the 95G development so that has to be seen as mitigating some of the
risks there, versus starting from scratch in a different band [that is, the
39GHz].
[117] On 31 January 2019, Mr McGowan emailed Dr Baines, copying in Mr Pellé, informing
him that BSO had lost a customer on the Apsara network –
We have just received notice of our first service cancellation due to
competitive pressure. We believe that the new network will be extremely
competitive, and in fact I think we can retain our market leadership.
However, this is not a good position to be in, especially as going into this
project we expected to be deploying radios now. This would bolster our
story and potentially delay some of the further terminations we expect.
As discussed we really do need to accelerate this programme and start
getting product in the field. What is the current timeline for deliveries?
[118] According to his affidavit, Dr Baines found Mr McGowan’s statements about
“accelerating” the program and starting to get product “in the field” “bizarre” because the
development project was not at production phase and BSO had not yet indicated its
acceptance of Milestones 2 and 3. Dr Baines said that he said nothing to Mr McGowan
about how “bizarre” his statements were because he did not want to “upset” him. I find
that assertion incredible. It was, according to Dr Baines, his second experience of Mr
McGowan saying “bizarre” things.
-- 43 of 136 --
44
[119] While Dr Baines made much of the “design challenges” experienced by EMClarity in his
affidavit, his correspondence with Mr McGowan in 2019 about the project and the
prospect of its success was positive – including in his reply (below) to the “bizarre” email
about getting product “in the field”. In his reply, Dr Baines acknowledged the delay and
proposed an “out-of-left-field” alternative, that is, deploying E Band radios –
Hi Callum,
I agree with you that this new network will be extremely competitive. It
will be based on world leading technology – no-one else will have a high
data throughput, ultra low latency solution in this band, to the best of our
knowledge. You will have a high performance system in clear spectrum.
Yes, we are late compared to where we wanted to be at this time. The
clock started with the initial payment on 6 August 2018. We therefore had
planned to be at the final design review milestone early February 2019. In
reality, we are round about milestones 2 and 3 at the moment. We have
completed the preliminary design work, we have a solid design
specification to achieve good network performance which has been
modelled, and we know what the product cost will be.
Realistically, if BSO confirms the design specification and the accurate
costs then we are looking at another three months to complete the
development. The original plan had five months between milestones 2/3 and
completion of design but we have anticipated those decisions being made
and have already done some work in the final design. I don’t want to create
too much of an overhang there because strictly speaking we need your
confirmation to proceed.
Once we have a design completed, the nominal lead time on production units
is three months from order. This doesn’t necessarily have to be sequential
with the design phase as certain of the longer lead time parts can be
ordered in advance.
I suggest we have a call to discuss this as soon as you are available.
The options as I see them are:
1. Confirm the design specification, the proposed network design, and the
product costing and we proceed with the next phases of development.
2. Consider an alternative. This has come out of left field – [redacted]
has advised that they will not be renewing the exclusivity on our E-
band products. You may wish to consider our E-band radios for your
network but spectrum licenses could be an issue. Our 5Gbps radio
needs 2.1 GHz of channel and the 10Gps radio needs 4.2Ghz.
Anyway, let’s have a call as soon as possible to discuss this.
We are committed to doing our best to support BSO with a world leading
network.
-- 44 of 136 --
45
Kind regards,
Peter.
[120] Nothing in this reply suggests any doubt about the successful development of the W Band
radio or its production – it is all positive, although it conveyed that development and
production would take several months. Indeed, by his use of phrases like “strictly
speaking” and “nominal” lead times, Dr Baines was, in my view, conveying that the
caution built into the WBRDAT was unnecessary including because EMClarity had
“modelled” a “solid design specification to achieve good network performance”;
anticipated that the design specification would be confirmed; and done some work on the
final design.
[121] In my view, it is more likely that Dr Baines said nothing in this reply about Mr
McGowan’s “bizarre” statements because he was, as at January 2019, either –
genuinely confident of EMClarity’s ability to deliver on the design and prototype;
or
motivated to minimise any difficulty EMClarity was having, or might have, with
the project to encourage BSO to progress it.
[122] Using E Band radios (as proposed in option 2) had not been an option at the time BSO
entered into the WBRDAT because they were then exclusive to [redacted]. Once they
were available as an option, Mr McGowan considered that their use would be a “viable
solution to improving BSO’s current networks simultaneously with developing the new
W Band network”.
February/March 2019
[123] On 1 February 2019, Dr Baines provided to Mr McGowan (and Mr Pellé) the path
analysis utilising the E Band radios.
[124] Between 1 and 6 February 2019, Mr McGowan and Dr Baines discussed (via telephone
and email) the E Band radios; BSO’s requirements; and BSO’s strategy for integrating
them with, or instead of, W Band radios, including the adaptations BSO would need to
make to its network. Their discussions focused on ways to reduce latency in the E Band,
as reflected in the email correspondence between Mr McGowan and Dr Baines (copying
in Mr Pellé) on 4, 5 and 6 February.
[125] There is nothing in this correspondence which suggests that the supply of E Band radios
is dependent upon any aspect of development of the E Band radios, which presumably
had been previously deployed exclusively by [redacted] –
[redacted]
-- 45 of 136 --
46
[126] On 5 February 2019, Dr Baines sent Mr McGowan and Mr Pellé an “apples for apples”
comparison of the latencies on the “MAH-CAR path”11 using W Band and E Band. In
his email, Dr Baines encouraged BSO to progress the WBRDAT. He said –
[redacted]
[127] In his reply on 6 February 2019, Mr McGowan (copying in Mr Pellé) said (excluding
some technical detail) –
[redacted]
I’ve even said to you if you need to buy some units in I am happy to issue
POs to cover. Let me know what you need to do.
[128] In the next email in the chain, Dr Baines set out options to reduce latency as follows –
[redacted]
[129] On 7 or 8 February, Mr McGowan and Dr Baines spoke over the telephone. Mr
McGowan told Dr Baines that option 2 (that is, the development of another product:
[redacted]) was not feasible. He had only considered purchasing the existing (16QAM)
E Band radios on the basis that they could be immediately deployed.
[130] In his email to Mr McGowan (copying in Mr Pellé) on 8 February 2019, Dr Baines
discussed the notion of developing and producing units concurrently and indicated that
EMClarity “believed” it could “have working product” of W Band and E Band radios
in three months. He said –
We seem to be on the same page with respect to the options. Number 2 will
be a lot more fruitful and will really give BSO something unique in the
market.
We’ve been thinking about the timelines and believe that we can have
working product of both W-band and E-band in about three months if
we push the go button now. We’ve been working out how we can do both
converter developments in parallel …
We normally advise that production orders can be filled in 3 to 4 months from
receipt of order. In the past, we have normally completed development
then the customer has placed their production order, so the development
and production timelines add together. With your interest in purchasing
devices … early, then we could build the quantity of pre-production units
you need for the first path in the design phase so when development is
completed and they have passed compliance testing we can ship these
units to you for deployment, saving a lot of time. The production unit
11 That is the path from Mahwah to Cartaret.
-- 46 of 136 --
47
design revision level may change once the design is complete but this can be
effectively managed with the right selection of spares being carried.
We suggest we get this all under way now by advancing to the final design
stage. I’ve attached here the two invoices related to milestones 2 and 3
under the contract, for the W-band development. We have raised these
on Apsara Networks as per the commercial vehicle you instructed us to use
last time.
We should talk about your interest in purchasing long lead time components
in advance, as well as your intentions for equipment purchasing over the rest
of the triangle and in other jurisdictions, because I am thinking about
offering you that we will develop the E-band converters/new radio at our
cost, provided there will be enough business in it for both of us.
[131] This email does not contemplate anything other than the successful design of W Band
radios. It proposes building deployment-ready units in the design phase – conveying
confidence about EMClarity’s ability to design radios which would work, even if some
revision of their design might be required.
[132] To this email, Mr McGowan replied (on Saturday, 9 February 2019) –
I think I’ve missed something.
What E-Band development? I thought this was off the shelf.
[133] On Monday, 11 February 2019, Mr McGowan arranged for the Milestone 2 and 3
payments to be paid (as per the WBRDAT). He spoke to Dr Baines about “the utility of
the E-Band radios in BSO’s existing network”.
[134] On 12 February 2019, Dr Baines emailed Mr McGowan (copying in Mr Pellé). Dr Baines
said (after providing some technical information including about the hand off between
the “W-Band and the current E-Band radios”) –
With time being of the essence for your project, I think we really need to
advance through the current milestones, and get on with the final
development phase, at least for the W-band development.
I note your comment about the development of an [redacted] adding more
risk. While there are always unknowns with development of a new product,
I do think we have mitigated some of the bigger risks in the preliminary
design work that has been done. If we build some 16QAM E-Band radios
for you now you may wish to replace them in the future with [redacted].
No change of antennas would be needed.
[135] After further correspondence about technical matters, Mr McGowan arranged to be in
Brisbane on 27 February 2019.
-- 47 of 136 --
48
[136] On 13 February 2019, by email, Dr Baines asked Mr McGowan for his “thoughts on
proceeding with the W-Band development”. Dr Baines said, “We are sitting at the
point where we need BSO’s confirmation to do that and payment of the next invoices for
the development”. Mr McGowan replied, “We’re going ahead with W-band. I’ve
submitted the invoices for processing and payment. E-band is giving me grief, however”.
Their exchange continued –
[redacted]
[137] In my view, in this exchange, Dr Baines implies that E Band 16 QAM radios were
“proven” in the relevant environment (by not suggesting otherwise) and available to be
shipped “in short order”.
[138] Dr Baines provided the quote for the 16QAM radios, as foreshadowed, on 14 February
2019. It was introduced with the following, “Callum, Please receive below our quotation
for the Exomux E-Band Ultra Low Latency links with associated accessories”. Its
payment terms were “50% on order, 30% on completion of Factory acceptance testing
and packaged ready for shipping and, 20% on Acceptance of Delivery”. I note that this
quote was issued to Mr McGowan at “BSO Networks” (plural) – which is not the first
plaintiff’s name. The parties did not explore whether Dr Baines’ reference to BSO
Networks was significant (because, for example, he intended it to reflect his
understanding of Apsara’s involvement in the project).
[139] The quote was in a certain format which Mr McGowan found helpful. On 15 February
2019, he asked Dr Baines to provide a quote for the W Band equipment in the same
format. That quote “for the Exomux W-Band Ultra Low Frequency links with associated
accessories” was provided on 26 February 2019. It was addressed to Mr McGowan of
“BSO Networks”. The payment terms were identical to those above.
[140] On 27 February 2019, Mr McGowan (and another) met with Dr Baines in Brisbane to
discuss the progress of the project.
[141] On 4 March 2019, Mr McGowan told Dr Baines that he had approval to make the
Milestone 2 and 3 payments. In reply, Dr Baines thanked him and said “All our stuff for
you is coming together. Should be able to send it in the next day or so”.
[142] On 5 March 2019, Mr McGowan asked Dr Baines for his “notes from last week”. He
continued, “I want to start screwing together the project plan on our side. Any ETA on
the final design?” In reply, Dr Baines provided his notes and said that the path analysis
was “expected to be ready by the end of our day today” including the equipment for the
final design. I note Dr Baines’ statement that he understood the reference to “final
design” above was not a reference to the final design of a radio or radio prototype – but
rather a reference to the final design of BSO’s network.
[143] The notes of the 27 February 2019 meeting included the following –
…
-- 48 of 136 --
49
[redacted]
BSO is willing to pay for both these developments. Action – EMC to quote
for these.
…
[redacted]
[144] There was a further exchange of emails about technical matters – including emails internal
to EMClarity. On 7 March 2019, David White emailed Dr Baines about his latency
calculations and said, “Going through this process has also raised several other questions
that need to be answered by BSO for us to complete the production build”. I note the
reference to the “production build”.
[145] On 8 March 2019, Dr Baines emailed Mr McGowan “latency tables with some drawings
that assist in understanding the interfacing and modes”. He continued –
[redacted]
[146] Reading this email, in the context of the notes of the meeting above, it seems that the
development of the implementation of the [redacted] was something which had not been
contemplated when the W Band Radio Development Agreement had been negotiated –
hence the reference to BSO’s willingness to pay for it in the meeting notes and Dr Baines’
foreshadowing a quote for it.
[147] On 11 March 2019, in the course of emails between Dr Baines and Mr McGowan
discussing technical matters, Dr Baines’ answers to some of Mr McGowan’s questions
refer to EMClarity’s being able to deliver “today” certain options for the W Band project;
and the latency available “now” in relation to the W Band development –
Actually the latency will be equal in both directions. In the cells that have
Comments we discuss the ULL options. We’ve only included the options
that we can deliver today (including the W-band project) in the actual
latency numbers. Other options are possible and are under investigation.
We are confirming feasibility and will quote for them. The Comments
describe the additional latency gains that are expected when these new
features are delivered.
…
The latency calcs advise what is available now (including the W-band
development). [redacted] The latency reflects the more conservative
approach.
[148] Dr Baines’ affidavit does not elaborate on this email.
[149] Apsara paid the Milestone 2 and 3 invoices on 12 March 2019.
-- 49 of 136 --
50
[150] In his affidavit, Dr Baines says that, before 12 March 2019, EMClarity had undertaken
some work on “component selection and refinement” for a “W Band Functional
Prototype”. He says that, after receipt of the Milestone 2 and 3 payments, EMClarity
began working on the design of the W Band Functional Prototype (Milestone 3). He says
there are two stages for the process of developing a functional prototype, namely, the
design stage and the development stage. To develop a functional prototype, EMClarity
needed to order and receive the components for it. A functional prototype establishes
whether or not a stable design has been developed for (in this case) a W Band radio (to
specifications). He says –
… a successful W-Band Functional Prototype is a necessary precursor to the
production of W-Band Radios. A developed and built W-Band Functional
Prototype that passes testing would also then provide the model or template
for production of any W-Band Radios …
[151] He states in his affidavit that (as at the date of it) the design and development of the W
Band Functional Prototype had not been finalised. That remains the case.
[152] Returning to the relevant chronology, Dr Baines sent the “Network Equipment Quote” to
Mr McGowan on 14 March 2019 under cover of an email which recommended that BSO
“issue[] purchase orders and make[] initial payment for this equipment as soon as possible
to manage the delivery timelines”. He continued –
Lead times in the industry are generally stretching out right now. A large
number of the parts used had a 12-14 week lead time, and some even longer.
If we order right now we will be able to start production (having already
received all parts) immediately after the design and prototypes are
finished. If BSO waits until the prototyping phase is complete this will
impact delivery by adding another 3 months.
I’ll be on leave in NZ for the next two weeks but will still be responding to
emails so we can keep this moving.
[153] Dr Baines also explained that EMClarity was working on –
[redacted]
[154] The quote itself was introduced by the following, “Please receive below our quotation for
the equipment needed for the network configuration we have agreed, comprising a
mix of ExoMux E-Band and W-Band Ultra Low Latency links with associated
accessories”. The quote was sent to Mr McGowan of “BSO Networks”.
[155] The radios were identified as follows –
[redacted]
[156] [redacted]
-- 50 of 136 --
51
[157] The “Terms and Conditions” of the quote included the following –
…
4) No agreement for supply exists between EMClarity and customer
until (1) EMClarity has received an official purchase order from
Customer, (2) EMClarity has returned a purchase order from
Customer and an invoice for the first part payment, and (3) the
customer has paid the first part payment into EMClarity’s bank
account in accordance with the invoice.
5) Payment Terms. 60% on order; 30% on completion of Factory
acceptance testing and packaged ready for shipping and, 10% on
Acceptance of Delivery.
6) EMClarity’s test plans for Production Factory acceptance testing will
be defined by EMClarity to ascertain functionality of components and
systems to specification. Customer may request limited additional
compliance tests during final testing. Customer may not unreasonably
withhold payment once final testing has been successfully completed in
a way that demonstrates products are in accordance with specification.
Customer accepts that testing every product to specification is not
warranted and type of sample testing within batches is suitable to prove
batch or supply compliance.
…
7) New product and Extended Warranty terms are in accordance with the
addendum below.
[158] [redacted]
[159] I note that Dr Baines’ email referred to production occurring “after the design and
prototypes were finished” (emphasis added). However, it contained nothing to suggest
that production was conditional upon there being successful design or the construction of
a successful functional prototype.
[160] In the course of other emails discussing technical matters, Dr Baines informed Mr
McGowan (on 14 March 2019) that the power consumption details he had provided for
the ExoMux E Band were “accurate” but the power consumption details for the W Band
were “+-20%” “based on current design”. He continued, “We are looking at ways to
further reduce these but unknown at the moment. This will be worst case”.
Observation about the operation of the WBRDAT
[161] Under the WBRDAT, Milestones 1 – 4 are the development milestones, which operated
in the following way.
-- 51 of 136 --
52
[162] If, after –
making the “kick off payment” (Milestone 1);
reviewing the preliminary design (Milestone 2); and
paying [redacted] USD,
the Customer wished EMClarity to commence the final design, then it had to pay
[redacted] USD “in advance” (the Milestone 3 payment).
[163] If the Customer was satisfied with the final design, and wished the Production Build to
commence, then it was required to pay Milestone 4 ([redacted] USD). The “Deliverable”
for Milestone 4 (“Final Design Review”)12 is expressed as follows (my emphasis) –
Successful review of finished design.
Customer must Accept Milestone 4 prior to work starting on the
Production Build. Customer can discontinue further work prior to making
such payment and forfeit Milestone 1, 2 and 3 payments.
[164] The production milestones commenced with Milestone 5.
[165] [redacted]
[166] [redacted]
[167] Under the WBRDAT, EMClarity would not begin work on the Production Units until the
Milestone 5 payment was made; and it would not ship the units until the Milestone 6
payment was made.
[168] Neither Dr Baines nor Mr McGowan expressly referred to Milestones 4, 5, 6 or 7, or
(expressly or implicitly) to their requirements or to their payment, in the discussions
leading up to the 2019 Agreements.
Late March and April 2019
[169] On 27 March 2019, David White emailed Mr McGowan and asked for certain details to
enable him to complete a path analysis and advise on the correct radios for each hop of
the [redacted].
12 I note the use of “Final Design” here.
-- 52 of 136 --
53
[170] On 28 March 2019, Mr McGowan sent to Dr Baines (copying in Mr Pellé) an email with
the subject line “Price requirements”. It read –
[redacted]
[171] On 29 March 2019, Mr White sent Mr McGowan the updated path analysis for the W
Band path. The path analysis was introduced in this way: “This report is an analysis of
the following proposed BSO networks using EMClarity E-Band and W-Band radios…”
[172] Dr Baines sent Mr McGowan a “cost optimised proposal for D1 and D2”, under cover of
an email which included the following –
The 64QAM W-band radios have a materially higher cost to produce than the
E-band radios [for technical reasons].
We would be pleased to give you pricing at these discounted rates on all
the radios you need for the full network, if you order the equipment
required for the full network triangle before 1 April.
David is working out the delivery timeframes for D1, assuming your order is
placed before the end of this quarter. We will advise those in the formal quote
(see below) but you can be assured that we would do everything in our
power to expedite delivery.
We would recommend stocking spares of at least one of each variant or radio
…
If you accept this discounted pricing then we will produce a quotation for the
full network equipment at the discounted rates.
[173] I note that, obviously in response to Mr McGowan’s statements that he needed the
64QAM within three months and the 16 QAMs “immediately”, Dr Baines said that he
would advise Mr McGowan on timeframes in the “formal quote”.
BSO’s/Apsara’s “new” (or alternative) strategy
[174] Mr McGowan set out the BSO/Apsara strategy in an email to Dr Baines and David White
on 4 April 2019 –
[redacted]
[175] [redacted]
[176] After further clarification, a BoM (I assume “Bill of Materials”), dated 5 April 2019, for
the four phases was prepared and sent to Mr McGowan. The BoM comprised “a mix of
ExoMux E-Band and W-Band Ultra Low Latency links with associated accessories”.
[177] I infer, from emails between Dr Baines to Mr Pellé on 9 April 2019, that Mr Pellé had
some concerns about EMClarity’s quote. To “make it work” for Mr Pellé, Dr Baines
-- 53 of 136 --
54
created a new quote, which included “exclusivity for BSO in the use of this W-band
equipment”. He followed up with an email on 10 April 2019, with other options,
including –
..
2 [redacted]
3 I will offer a further 5% discount on the total price of the equipment
you purchase for this network, provided you order the full network now, and
also that you agree to limit the exclusivity to six months when we ship the
first W-band units to you.
[178] Mr Pellé emailed Dr Baines on 16 April 2019 (after being asked for his thoughts on Dr
Baines’ options) with the following (errors as per original) –
Peter
To be honest with you, I am not comfortable with these #give and taken
choice (Price vs Exclusivity). Callum hardly championed you internally and
we feel trapped between price and exclusivity. May be we shall have done
an RFP [I assume, “Request for Proposal”] and put supplier in competitions
as price points does not work in our current revenue/cost model
best
Emmanuel PELLÉ
[179] I infer, from emails between Dr Baines and Mr McGowan between 17 and 22 April 2019,
that Mr Pellé ultimately indicated that he would accept EMClarity’s quote on certain
terms.
Delivery estimates
[180] On 24 April 2019, Mr McGowan emailed Dr Baines the network build sequence and
asked for Dr Baines’ “best estimate” for deliveries. Mr McGowan said (omitting
technical details) –
[redacted]
[181] Dr Baines gave the following delivery estimates in an email dated 26 April 2019 –
Hi Callum,
OK, here are our most up to date thoughts on timing of deliveries.
Timing Estimates
These assume that we complete the contractuals and you place your
orders next week.
Phase 1 Delivery: 9 Weeks – 1 July 2019
-- 54 of 136 --
55
Phase 2 Delivery: 9 Week E-Band – 1 July 2019, 22 Weeks W Band (after
design complete) 30 Sep 2019
Phase 3 Delivery: 22 Weeks W-Band (After design complete) 30 Sep 2019
Phase 4 Delivery: 22 Weeks W-Band (After design complete) 30 Sep 2019
We expect the development of the prototype W-band 64QAM to be
finished in 8 weeks. We could build an extra prototype link and then you
could install that one. The risk in this is that this one link is a little bit of an
orphan compared to the others that will be delivered, but when you think
about [sic], the differences would only be minor hardware ones, if any, and it
would be fully compatible when it comes to modem software and control
software, so it’s actually not a bad option. If we went down this route, and
I like the idea, then the possible delivery on phase 2 W-band might be 10-11
weeks ARO for the 1 link, meaning mid July. That means you would have
the equipment for the first two phases in July.
As I mentioned when we last spoke, we anticipated the demand for long lead
time items with our suppliers and have placed our orders. This is a large
financial commitment and will have to be confirmed by 8 May Aus time (7
May in USA). If we had to delay or re-order then we go back to standard lead
times, meaning an additional 7 weeks. This impacts the delivery of the E-
band units and the first W-band link.
If we can confirm everything next week then the way we will arrange
production is to build all of the W-Band MODEM halves at the same
time as building the E-Band links then with the W-Band design complete
building the W-Band components and adding to the unit.
I am also working on the contractuals as I promised Michael and Emmanuel.
I will give you a new quote reflecting what you have put below on the phases
and also a contract containing all of the terms we have collectively been
discussing.
[182] Nothing in that email suggested that EMClarity had any doubts about being able to
complete the design or build the W Band components.
Quotes including statements about delivery times
[183] Dr Baines provided an updated quote (to match BSO/Apsara’s changes) on 2 May 2019.13
[184] The quote was addressed to Mr McGowan of “BSO Networks”. It was broken into the
phases of the “overall project”, reflecting “your deployment strategy”. It identified the
13 The quote was dated 30 April 2019.
-- 55 of 136 --
56
radios (and related accessories) to be supplied at each phase and proposed an amount to
be held as spares. The quote also included other tasks to be performed by EMClarity,
[redacted], which tasks were “included in this overall project”. In its “terms and
conditions”, it included a certain “Exclusivity/First Right of Refusal Condition”. I note
that the WBRDAT did not cover the implementation of the ULL protocol in the 64QAM
W Band radios.
[185] Dr Baines’ email, accompanying the quote, set out the expected delivery times for each
of the phases on the assumption that “we complete the contractuals and you place your
orders next week”. It included the following note on “Phase 2 W Band delivery” (my
emphasis) –
We expect the development of the prototype W Band 64QAM to be
finished in 8 weeks. We will be building an extra prototype link to achieve
this timing for Phase 2 and you can install that one.
[186] [redacted]
[187] The email continued –
We will have to confirm by 8 May Aus time (7 May in USA) with our
suppliers on the high value long lead time items. If we had to delay or re-
order then we go back to standard lead times, meaning an additional 7 weeks.
This impacts the delivery of the E-band units and the first W-band link.
…
Given our lead times and wanting to get this delivered for you as soon as
possible, receipt of your order will be the trigger to build. That’s when
we will have to commit with our suppliers. Usually our trigger to ship is
passing FAT [Factory Acceptance Testing]. Is that what you had in mind?
…
To manage the request from Michael, for BSO to pay 50% this year and 50%
next year, we will need all orders placed together and the first 50% paid at
that time …
[188] I note Dr Baines’ statements in his emails of 26 April 2019 and 2 May 2019 that he
expected the development of the prototype W Band 64QAM to be finished in eight weeks.
Although it is hard, on the evidence, to know, this statement seems inconsistent with Dr
Baines’ affidavit evidence – especially at paragraphs 118-126 – which paints a picture of
painstaking progress in the development of such a prototype.
[189] On 4 May 2019, Mr McGowan directed Apsara’s accountants to prepare purchase orders
for the first three phases of the quote as above.
[190] The final quote, for the supply of E Band and W Band radios plus spares, was dated 10
May 2019. This version included a revised exclusivity term (in clause 12(f)), after the
-- 56 of 136 --
57
intervention of Mr Ourabah. The exclusivity offered by the quote initially was in these
terms (my emphasis) –
f) [redacted]
[191] Mr Ourabah pointed out that his understanding was that “any spend in excess of
[redacted] USD per year with EMClarity would cound [sic] for ensuring we extend our
exclusivity in these geographies, as per the initial PO I had signed for the R & D. Can
you please amend accordingly?”
[192] Mr Ourabah’s understanding reflects one of the exclusivity conditions under the
WBRDAT – namely that stated in clause 2.6(b), which extended exclusivity of the
relevant product under the WBRDAT (the W Band 92-95 GHZ low latency radio
developed during the Project) for 12 months upon BSO placing one or more orders for
EMClarity in-house products where the combined total of the said orders is at least
[redacted].
[193] The paragraph was then amended as follows (my emphasis) –
f) Exclusivity. BSO shall have exclusive access in a given calendar year
to the Product in the Application in the Territory while the total of all
purchases from EMClarity exceed [redacted] in that calendar year.
[194] “Product” in the quote is defined as “64QAM W-band radio with latency less than one
micro second”.
[195] After that amendment to the exclusivity paragraph, Mr Ourabah told Dr Baines that it was
“all good” and that Mr McGowan would proceed.
Purchase orders
[196] The Quote also included the following clause 4 –
No agreement for supply exists between EMClarity and customer until (1)
EMClarity has received an official purchase order from Customer, (2)
EMClarity has returned a purchase order confirmation to customer and an
invoice for the first part payment, and (3) the customer has paid the first part
payment into EMClarity’s bank account in accordance with the invoice.
[197] On 11 May 2019, Mr McGowan emailed two purchase orders (in Apsara’s name, on
Apsara’s letterhead) to Dr Baines for phases 1 and 3. He indicated that phase 2 was “on
hold” and explained that he realised he needed equipment from phase 2 for phase 3, but
wanted to “firm up the timing and deployment plan first”. He said he might reallocate
equipment from phase 2 and would need to realign the quote accordingly.
[198] In his affidavit, Mr McGowan explained that Apsara placed its purchase orders before
seeing the finished prototype “to ensure that we would have all of the necessary
-- 57 of 136 --
58
components available to minimise delays, given that much of the componentry had a long
lead-time”. For what it is worth, Mr McGowan said he understood from Dr Baines’
communication that the W-Band radio had reached the ready-for-production stage, but
EMClarity needed an injection of cash to source the materials to produce it.
[199] In his affidavit, Dr Baines says that he “suggested to Mr McGowan that these orders be
placed, ahead of the final design for the W-Band Functional Prototype being completed
and tested, because of long lead times for some of the parts that I thought would ultimately
be required to manufacture W-Band radios”. He continued, “I did not suggest to Mr
McGowan that these orders be placed because EMC was ready to start production of W-
Band radios”. He also said that he made no communication to Mr McGowan to the effect
that W Band radios had reached the ready for production stage. That is probably right:
his emails suggested that the development of the W Band radios would take eight weeks.
However, his statement about obtaining parts which he thought would ultimately be
required to manufacture the W Band radios is not consistent with any uncertainty about
EMClarity’s ability to come up with a successful design and prototype. Nor did Dr Baines
say anything about what EMClarity would do with the parts if it could not achieve a
successful design or prototype. In my view, even though Dr Baines did not suggest that
EMClarity was immediately ready to start production of W Band radios, he conveyed that
production of W Band radios was in fact going to happen.
[200] Mr McGowan emailed Dr Baines the purchase order for phase 2 on 16 May 2019. On 20
May 2019, Dr Baines chased Mr McGowan for the phase 4 payment –
Any update on the initial payment?
Also just waiting on your order for phase 4 to complete the deal we agreed.
[201] Apsara sent the purchase order for phase 4 on 7 June 2019.
Invoices (May/June 2019)
[202] Having received the purchase orders, EMClarity issued Invoices to Apsara (in US
dollars) –
[redacted]
[203] The invoice amounts were 50 per cent of the amount of each purchase order, in
accordance with the quotes’ payment terms of “50% due on order, 50% due on January
31st, 2020”.
[204] [redacted]
Observation about payment terms
[205] The quotes’ payment terms were more absolute than the production lot payment terms
under the WBRDAT. Under the WBRDAT –
-- 58 of 136 --
59
the Customer was required to indicate that it was satisfied with the “final design”
for the W Band, and to make the relevant payment, before EMClarity would
commence the production build;
the Customer had to then pay the kick off payment (60 per cent of the total) before
EMClarity would commence the production build; and
there had to be successful factory testing of the ten piece order before the second
payment (30 per cent of the total) was due.
[206] Apsara’s obligation to pay under the quotes did not depend on “BSO Networks” being
satisfied with the final design or there being, from “BSO Networks’” point of view,
successful factory acceptance testing.
Observation about warranty terms
[207] I note the difference between the “Standard Warranty or Warranty Included in the
Purchase Price” in the WBRDAT and the “New Product Warranty” term in the quotes.
[208] Under the WBRDAT, the warranty included the following (my emphasis) –
Customer understands that First Production hardware as delivered in the
Project and anticipated in the Schedule will not be fully mature and may
experience faults and outages above that considered normal for product
in general availability. Customer will work with EMC to help to quickly
identify and remedy faults including providing onsite resources for testing,
fault diagnosis and module replacement, and providing engineering level
remote access for diagnosis and software/firmware repair and reconfiguration
by remote EMC staff. Although EMC will endeavour to ensure that this
settling in period is as short as possible, the Customer accepts that this higher
than normal level of support activity may continue for more than 3 months
after first installation. During this period of introduction of prototype or pre-
production equipment into the field, Customer will work with EMC to find
solutions to any and all issues rather than exercising its rights to return and
replacement.
[209] Under the quotes, the warranty was as follows (my emphasis) –
New Product Warranty
New Product Warranty is 24 months from delivery date and includes spares
service on terms described below.
New Product Warranty does not include fault diagnosis or field replacement
work unless separately contracted.
New Product Warranty does include general phone-based engineering
support for all operational, installation and fault diagnoses issues. This
-- 59 of 136 --
60
support is provided without limitation during office hours … Requests for
support are managed through EMS support ticketing and response tracking
systems.
Warranty includes (at Customer request) monitoring of the equipment within
the EMC NOC at Tennyson. This is the preferred level of support for greatest
operational efficiency.
Spares Service
EMC/EMS have been supplying microwave link products since 1999 and
continue to support equipment deployed since then. For in-full-production
products, EMC holds multiple spares for all major electronic parts and will
ship a replacement spare (at customer cost) on the same day of a confirmed
failure during the new product warranty period …
In the case of multiple failures of the same component within a very short
period of time …EMClarity may not be able to immediately supply spares of
individual units but will provide a priority repair and return module service
…
EMClarity guarantees to provide spares support for all equipment supplied
for a period not less than 10 years from date of shipment.
As a requirement of providing spares through the spares service, the customer
is required to return the failed unit (at customers [sic] cost). EMClarity will
repair this unit and hold it as part of its spares stock.
Extended Warranty Maintenance Contract (Optional)
… EMC offers an extended maintenance option …
[210] The differences between the warranties offered are obvious. The WBRDAT anticipated
more than the usual number of faults and outages. The 2019 Agreements do not.
Mr Boyle’s invitation to the W Band Project Meeting
[211] Meanwhile, on 19 May 2019, unbeknownst to BSO/Apsara, Tim Boyle was sent the
invitation to a “W-Band Project Meeting” as discussed above.
Delays from July 2019
[212] On 24 July 2019, Dr Baines provided Mr McGowan with an update on delivery times.
He said (my emphasis) –
…
When we negotiated the equipment purchase at the beginning of May,
we were signalling an expected delivery of late July, if the orders were
-- 60 of 136 --
61
placed at that time, including the up-front payments being received at the
same time. That represented a compressed delivery time of 12 weeks.
The way things worked out with the purchase orders and the initial payments,
it was 20th June when the last stage was locked in … [and] some of our orders
couldn’t be confirmed until we had the full network locked in.
Nevertheless, we will still be able to achieve a 12 week time frame. We
plan to start shipping you your E-Band links for the first phase beginning
mid September, and the other phases will follow progressively. The first
W-Band units are expected to be on their way to you from early
November.
Along the way, we have encountered some engineering issues that have now
been addressed … [T]he end result is there is increased stability in the design
of the product destined for BSO. We also had to deal with some component
obsolescence …Again, I’m pleased this has been dealt with before we
have shipped anything to you.
…
Davis and Joey are in NJ at the moment and will reach out to you to see if
they can catch up. I think it’s good if we can work as closely as possible on
the details of the network configuration as it may impact upon the
configuration of the equipment we are producing for you.
[213] In his affidavit, Dr Baines says that, at the time of composing this email (July 2019), he
believed that EMClarity had fixed the engineering issues which it had encountered with
W Band radios but that in fact, the changes made in July 2019 did not solve the problems.
It is not clear from Dr Baines’ affidavit when EMClarity realised that the issues had not
been solved but regardless they were not raised with Mr McGowan. The significant point
is that Dr Baines believed they had been fixed and that EMClarity had a workable design
for the W Band radios.
[214] Dr Baines and Mr McGowan discussed Mr McGowan receiving training from EMClarity
for the E and W Band radios. Mr McGowan also wished to undertake factory acceptance
testing of the radios. On 26 July 2019, Mr McGowan informed Dr Baines that it would
suit him to visit EMClarity in the second week of September 2019 and that his proposed
agenda included inter alia confirming the radio performance is “as expected” and
understanding the “eccentricities” of the new equipment.
[215] From EMClarity’s perspective, supplier “issues” arose causing delay; requiring the
postponing of Mr McGowan’s visit and pushing out the expected date for delivery of
product. On 20 August 2019, Mr White told Mr McGowan that planning for the worst
would mean delivery of the first radios in the first week of October 2019, which would
mean radios available for training purposes in the last week of September. However, by
30 August 2019, Dr Baines informed Mr McGowan that things were looking “a bit tight”
for the last week of September. He continued (my emphasis) –
-- 61 of 136 --
62
If we are looking at the third or fourth week of October then we should
already have a number of E radios built and some of the first W radios
assembled, so we would suggest the second half of October. It would be a
very productive visit at that time.
[216] Mr McGowan pushed back, reminding Dr Baines (in an email dated 30 August 2019) that
Dr Baines told him “just this Tuesday” that shipments would begin at the end of
September but now there was a supplier delay. The reference to “this Tuesday” seems to
be a reference to a telephone call between Dr Baines, Dr Halappa and Mr England, all of
EMClarity, and Mr McGowan on 28 August 2019 (although that was a Wednesday),
during which Dr Baines said14 “words to the effect that EMC ‘hoped to start shipping the
first E Band radios at the end of September’”.
[217] EMClarity provided explanations for the delay and, on 3 September 2019, Mr White
suggested that he could train Mr McGowan in the USA –
… I’ll be in the USA in the 2nd week of October. By the time I get back to
Australia you would have received your first shipment of links. If you
wish I could do the training in the USA and in fact help you with your first
link …
Let me know if that works any better for you so we can get you up and
running ASAP.
[218] After further discussions, it was agreed that Mr McGowan’s training would be at
EMClarity’s premises in Brisbane on 16 – 18 October 2019. The itinerary suggested by
Mr White included Mr McGowan looking at the W Band prototypes and the E Band radio
terminal on day 1. As things turned out, Mr McGowan was unable to travel to Australia
on those dates.
[219] Other email correspondence suggests that EMClarity was working towards delivering
radios to BSO/Apsara and was prepared to bear the risk of any issues with their design.
On 20 September 2019, in an email from Mr White to Dr Halappa, Mr White said (my
emphasis) –
[redacted]
[220] There is evidence of EMClarity pursuing their suppliers, in the months after the 2019
Agreements, for the components necessary to enable them to produce radios for
BSO/Apsara. For example, Barry Dench sent a purchase order to [redacted] on 4 June
2019 and asked for the “ETD” (I assume, estimated or expected time of delivery). He
asked again for delivery details on 12 June 2019 and 19 June 2019. He was told, on 22
June, that the “scheduled ship date” was 28 August 2019 but that that was subject to
change, based on material availability and lead-times from [redacted] suppliers. Mr
Dench sought an update on the shipment on 15 September 2019 and was told it had been
14 According to his affidavit.
-- 62 of 136 --
63
“revised” to 31 October 2019, “due to one of the materials”. Mr Dench replied (on 16
September 2019) (my emphasis) –
[redacted]
This is a 2 month delay? This [sic] have major consequences for us, it will
seriously affect our ability to supply our customer on time. Is there
anything at all that can be done to bring this order forward?
[221] [redacted] said that she had “reached out” to see if anything could be done but the tone
of her email (dated 17 September 2019) suggested it was unlikely. Then, on 10 October
2019, she informed Mr Dench that “unfortunately” the “ship date” had been “revised”
again. She continued –
… It is currently December 16th. The supplier of one [sic] the parts (carrier)
has been asked to perform a test, and if it passes, the supplier will be able to
confirm the delivery date. We do apologise for the inconvenience this news
presents.
Your business is important to us and we will work to improve this shipment
date as opportunities present themselves.
[222] Mr Dench replied –
Hi [redacted]
This has now been moved out three months? This will mean that we fail to
deliver our commitment to our customers and as such will incur financial
losses. Is there anything that can be done to improve please?
[223] After McKay Brothers’ acquisition of EMClarity, this order, and others were cancelled.
[224] Also consistent with an intention to supply the radios after the May 2019 Agreements: on
9 September 2019, Mr White informed Mr McGowan that he had some E Band antennas
ready to ship. They were received (in the USA) on 5 October 2019.
BSO informed of McKay Brothers’ acquisition of EMClarity
[225] On 8 October 2019, by way of a telephone call, Dr Baines, in the presence of others from
McKay Brothers (namely, senior executives Dr Stephane Tyc and Dr Robert Meade), told
Mr McGowan and Mr Ourabah that McKay Brothers had acquired EMClarity.
[226] In the course of the telephone call, according to Mr McGowan, Dr Meade said that McKay
Brothers was not happy with the quality of the products being delivered; McKay Brothers
-- 63 of 136 --
64
would begin a quality assessment project; shipments of radios had been stopped; and it
was not known how long the pause on shipments would last.15
[227] Mr McGowan asked what confidential information EMClarity had given to McKay
Brothers. Dr Baines said that McKay Brothers had been given a “name-reacted” copy of
the WBRDAT before their acquisition of EMClarity and an un-redacted copy afterwards.
Mr Meade said that BSO could assume that anything discussed with Dr Baines would be
shared as well. (According to Dr Baines, Dr Meade said “shared with himself and Dr
Tyc”.) Dr Baines recalled saying words to the effect that EMClarity would need to
consider how it could delete or destroy BSO’s confidential material. Dr Baines said
neither Mr McGowan nor Mr Ourabah responded to that statement.
[228] Mr McGowan asked for formal written notice of the audit. He was told that his request
would be taken “under advisement”.
[229] Mr McGowan knew that EMClarity was looking for investors, but he was surprised at the
acquisition.
[230] Dr Baines had a separate telephone conversation with Mr Ourabah on 8 October 2019.
During that conversation he said that he understood that McKay Brothers’ acquisition of
EMClarity could be unfortunate or inconvenient for BSO. Mr Ourabah asked Dr Baines
when he would get his radios. Dr Baines said that he believed BSO would get its radios,
but he was not sure when. For what it’s worth, Dr Baines said that he did not say that he
was “embarrassed” during that conversation (as put to him).
[231] On 18 October 2019, Dr Baines told Mr McGowan that he was “able” to tell him that the
Board of EMClarity passed a resolution confirming the pause of all shipments of radios
pending a review of product quality and production processes. He continued –
The first phase of the review is to create a quality plan. There is no ETA
available at this time as to when the quality plan or review will be completed.
I will ensure you get any further news as soon as it is available.
[232] I note that Dr Halappa assumed that the prototype builds were going ahead for W Band
radios, notwithstanding the Quality Review, as revealed in this email from Barry Dench
to David White, dated 23 October 2019 –
Hi David
Can I have some direction on the wombat production, as we don’t all seem to
be on the same page. As far as I am aware we [sic] awaiting a review from
McKay before proceeding with anything else (as notified by Peter/yourself),
15 I note that Dr Baines disagreed with Mr McGowan’s recollection of the conversation, but only to the extent
of suggesting that Dr Meade did not say “McKay Brothers was not happy …” or “McKay Brothers would start
…”. Rather, according to Dr Baines, Dr Meade said, “we are not satisfied with the quality of products being
delivered” and “we would be starting a quality review”.
-- 64 of 136 --
65
but Ashoka is asking who is and when are we doing the prototype builds for
W Band.
We have heaps of components that need to be purchased for this, and
depending on who does it, what we buy.
[redacted] If we purchase for the prototype, do we buy these components at
the same time as it would make economical sense?
Please advise how you would like me to proceed.
Kind regards
Barry Dench
[233] On 4 November 2019, it seems that the intention was that Dr Halappa would complete
the prototype for the purposes of the Quality Review. An email from Mr White to Mr
Dench and Dr Baines said, (my emphasis) –
Barry
After speaking with Peter we’ve confirmed that we will build the [redacted]
Wombat prototype terminals as originally planned. These prototypes are
also subject to the quality review, however this will be most successful
after these units are built which is why we should proceed despite the
current hold. The main change is that for now we will NOT be ordering
additional components for the production. The reason for this is that despite
the customer’s request that we fast-track the production, we feel we can only
provide a quality product by first prototyping and then going to
production. Additional production components will be ordered after the
prototype design has been confirmed experimentally and the quality review
on the design has been completed.
Please proceed and order the components required to complete the prototype
units….
[234] Of particular significance is that this email acknowledges the customer’s request for fast-
tracked production and a change in EMClarity’s approach from one which
accommodated fast track production to one involving first prototyping, then producing.
Status of development and production of a W Band radio
[235] Notwithstanding the intention stated in November 2019 to build a W Band prototype,
development of the prototype ceased.
[236] Dr Baines’ affidavit sets out the detail of that which must occur to complete development
and, assuming the achievement of a functional prototype, the slow and laborious process
of production thereafter.
-- 65 of 136 --
66
Cancellation of orders for components
[237] Dr Baines says in his affidavit that, after McKay Brothers acquired EMClarity, the
EMClarity board asked him to review, and cancel if possible, orders for component parts
which had not been fulfilled and to determine whether it was possible to return any
inventory which had been acquired but which was not likely to be used in a final design
“based on the findings of the Quality Review”.
[238] Notwithstanding the implication in that statement that there were “findings” of the
Quality Review which identified inventory which would not be required, as Dr Baines
acknowledged in his affidavit, the Quality Review is travelling more slowly than
expected. It is difficult to understand how then he was meant to identify inventory which
was not likely to be used. Regardless, he states that the board’s preference is to issue
fresh purchase orders when the parts are required and the specifications for the parts are
settled.
[239] In accordance with the board’s preference, on 16 January 2020 Barry Dench cancelled
the [redacted] order which he had been chasing for months, explaining –
Unfortunately our business circumstances have changed significantly over
the past few weeks, and as such our management have directed that we put
production qty’s [sic] of W Band product on hold.
As a result of this directive, please accept this “request for cancellation” …
[240] Whilst taking care not to place too much weight upon it, I note the reference to
“production quantities” being put “on hold” in this email, which is consistent with
Mr Dench’s understanding that EMClarity was about to embark upon the production of
W Band product.
[241] [redacted] was not told the real reason for the cancellation. Instead, by email dated 9
March 2020, Mr Watson from EMClarity told [redacted] that their client had decided to
postpone the development program indefinitely.
[242] [redacted], another supplier, was told something similar on 9 March 2020 –
Due to lengthy delays in connection with the delivery of parts for a project,
the customer has delayed the project indefinitely. As a result we no longer
require items … and request that the order be cancelled …”
Progress of the Quality Review
[243] As at the date of his affidavit, 11 June 2020, Dr Baines reported that the work on the
LMDS issues was “progressing well”, but taking longer than expected. He detailed
“further issues” which had been encountered with LMDS radios. In June 2020, Dr Baines
believed that it was “likely that addressing E Band issues would be completed by around
the end of 2020”. He said that because LMDS and E Band radios had some features
common to W Band radios he expected Quality Review work on LMDS and E Band
-- 66 of 136 --
67
radios would “progress the development” of W Band radios. He provided no other
information about the expected resumption of development of the W Band radio.
[244] Having outlined that relevant evidence, I will turn now to the issues.
Issue 1: Did BSO enter into the WBRDAT as agent for Apsara (the undisclosed
principal) or in its own capacity?
[245] The plaintiffs’ primary case was one which treated the 2019 Agreements as agreements
between EMClarity and Apsara; to be construed independently of the WBRDAT. If the
plaintiffs were successful in their primary case, then the WBRDAT was essentially
irrelevant, no matter who the parties to it were or the capacity in which they contracted.
[246] The plaintiffs had to rely upon the concept of agency to advance their alternative case:
that is, that the 2019 Agreements, made between EMClarity and Apsara, varied the
WBRDAT, to which EMClarity and BSO were parties, in such a way as to allow the
parties to ignore the development aspect of it. It was only if BSO had been acting as
Apsara’s agent in the formation of the WBRDAT that an agreement between EMClarity
and Apsara could vary the agreement between EMClarity and BSO.
[247] Although the plaintiffs have succeeded in their primary case, I will express my views
about agency in case it becomes relevant.
[248] The plaintiffs submitted that Apsara was BSO’s “undisclosed principal”. They observed
that the “doctrine” of the undisclosed principal was difficult to understand but submitted
that that was not a reason not to apply it (of course). It was described in Freeman &
Lockyer (a firm) v Buckhurst Park Properties (Mangal) Ltd [1964] 2 QB 480 by Diplock
LJ as follows (my emphasis) –
An “actual” authority is a legal relationship between principal and agent
created by a consensual agreement to which they alone are parties. Its scope
is to be ascertained by applying ordinary principles of construction of
contracts, including any proper implications from the express words used,
the usages of the trade, or the course of business between the parties. To
this agreement the contractor is a stranger; he may be totally ignorant of
the existence of any authority on the part of the agent. Nevertheless, if
the agent does enter into a contract pursuant to the “actual” authority, it does
create contractual rights and liabilities between the principal and the
contractor …
[249] The plaintiffs submitted that the evidence of Mr McGowan and Mr Pellé (at [77] – [80])
established that BSO, as agent, entered into the WBRDAT on behalf of Apsara, as the
undisclosed principal. They submitted that I ought to find that Apsara and BSO each
“manifested assent” to BSO acting on Apsara’s behalf to enter into a contract with
EMClarity.
-- 67 of 136 --
68
[250] The defendant submitted, inter alia, that the plaintiffs’ witnesses’ evidence that Apsara
would “own” any W Band equipment and would be the “end user” of it did not make out
a conferral of authority by Apsara upon BSO which would allow BSO to enter into
contractual relations with EMClarity on Apsara’s behalf. Further, the phrase “on behalf
of” was not an expression which was capable only of meaning that BSO acted as Apsara’s
agent. The plaintiffs had to show that the functions entrusted to BSO were those of
representing Apsara so that it stood in its place, acting in its right, and not acting in any
independent capacity (referring to Colonial Mutual Life Assurance Society Ltd v
Producers and Citizens Cooperative Assurance Co of Australia Ltd (1931) 46 CLR 41 at
48 – 50).
[251] The defendant also submitted that Mr McGowan’s evidence under cross-examination
was inconsistent with the agency asserted. Mr McGowan’s evidence was as follows (my
emphasis) –
MR BEACHAM: All right. So your point in paragraph 9316 is that you
discussed BSO acting on behalf of Apsara. That’s correct --- Yes.
Have a look then … [at] page 10 of Mr Piesiewicz’s affidavit. Have a look
at subparagraph (e) there? --- Okay.
And it says there that BSO, through Apsara, issued purchased orders for the
non-recurring [engineering] …? --- Yes.
All right. I suggest to you that that’s inconsistent with what you say in
paragraph 93 of your affidavit. In fact, it’s the opposite? --- No.
You don’t accept that? --- It’s very consistent. I mean, Apsara is 100 per cent
owned entity of BSO. Apsara is an operating entity and actually has no staff.
All the staff of Apsara are BSO’s staff. So BSO is the owner of Apsara and
whatever Apsara owns and, therefore, can negotiate on behalf of Apsara.
…
… The only point I’m making in paragraph 93 of my affidavit is the reporting
structure of Apsara through to BSO.
MR BEACHAM: Would it be fair to say that in your mind you see no
distinction between BSO and Apsara at all? --- I think I’ve explained that.
Apsara is an operating entity. I’m employed by BSO to make Apsara work.
End of story.
16 Paragraph 93 of Mr McGowan’s affidavit is repeated here for convenience: “Given the significant value of
the investment that Apsara and BSO were making with EMC and the size of the payments that needed to be
made up front, BSO’s management was concerned to manage the cash flow. I had a number of discussions
about the staged payments with Mr Ourabah and Mr Pelle, including the tax implications and accounting
treatment of the payments. Over a number of conversations with Mr Ourabah and Mr Pelle it was agreed
that the W-Band project would be paid for and owned by Apsara, although BSO, as Apsara’s parent company,
would continue with the negotiations on its behalf.”
-- 68 of 136 --
69
…
Well it [the plaintiffs’ reply to the defence] says:
In carrying out the acts in 1(a) above, Apsara acted as the plaintiff’s
agent.
That is, BSO’s agent. I suggest to you that’s inconsistent with what you say
in paragraph 93 of your affidavit? --- No.
You understand that what this reply is saying is that Apsara did something
on behalf of BSO? --- Yes.
And what you’re saying in paragraph 93 of your affidavit is that BSO
continue with negotiations on behalf of Apsara. That’s the inconsistency
I’m putting to you? --- Again, I don’t – I don’t see the inconsistency.
All right? --- Apsara is an operating entity of BSO.
[252] In the context of questions about invoices in Apsara’s name, Mr McGowan’s evidence
was as follows –
Now … if the contract has been negotiated on behalf of Apsara by BSO, that
would be the time to say it, wouldn’t it, by way of explanation as to why the
invoice was different? --- Are you implying as part of the contract
negotiations or - - -
Well, no. This comes after the contract. You say - - -? --- Right, but you said
– could you repeat your question, please.
Sorry. It was unclear. You don’t say in that email, “Please change to Apsara
Network, because we negotiated the contract on behalf of Apsara”? ---
Correct.
And that’s because you didn’t negotiate the contract on behalf of Apsara? ---
The contract was negotiated by BSO for BSO’s entities.
Discussion and conclusion
[253] The most common way in which a relationship of agency arises is in pursuance of the
express or implied assent of both principal and agent. To create an agency relationship,
it is not necessary that there be a legally binding contract of agency, but there must be an
instruction or request from the principal to the agent to do “something” and the agent’s
undertaking to do that something. Bare assertions by an alleged agent that they are acting
for an alleged principal are not enough. There must be conduct on the part of the alleged
principal from which an agency relationship might be inferred.
[254] Generally, the existence of agency is grounded in intention. And whether an agency
relationship exists is to be determined objectively.
-- 69 of 136 --
70
[255] The parties need not to have used the language of agency for the law to infer an intention
to create an agency relationship. The parties may not even appreciate the legal concept
of agency but may nevertheless create an agency relationship: see Branwhite v Worcester
Works Finance Ltd [1969] 1 AC 552. As Dal Pont explains in The Law of Agency17 (at
4.7, footnotes omitted, my emphasis) –
An intention to create an agency may be manifested ‘simply by placing
another in a situation in which, according to the ordinary rules or law, or …
according to the ordinary usages of mankind, that other is understood to
represent and act for the person who has so placed him’. It need not involve
a positive act by the principal, but may be created by the principal’s
acquiescence. Jordan CJ explained this in Bonette v Woolworths Ltd as
follows:
Evidence that a person is purporting to do acts on behalf of a principal
in some capacity in such circumstances that the knowledge and
approval of the principal may fairly be inferred is evidence that the
principal has authorised him to act in the particular capacity. If
there is evidence justifying such an inference, it justifies the further
inference that the person has authority to do such acts as would be done,
as a matter of ordinary business practice, by a person acting in such a
capacity.
[256] The agent’s authority is derived from the principal, also as explained by Dal Pont (at 4.12,
footnotes omitted, my emphasis) –
The essence of an agency relationship … is that the agent be in some way,
however minor, authorised to act on behalf of the principal. For this
purpose, authority can be ‘express’, being specific authorisation given by
express words whether oral or written to engage in a particular form of
conduct, and/or ‘implied’ being authority inferred from both the conduct of
the parties and the circumstances of the case, the latter including the office or
position in which the agent is placed.
A useful starting point in addressing whether a person has authorised
another to do one or more acts on his or her behalf is to consider on whose
benefit or in whose interest it was intended that the act(s) should be done.
The scope of this authority determines the extent to which the agent’s actions
can, without personal liability for so doing, impact on the principal’s affairs.
It moreover determines the scope of the legal obligations and entitlements
between the agent and the principal per se.
[257] The relationship between a holding and subsidiary company is not prima facie one of
principal and agent (although the plaintiffs in the present case assert that the holding
company was the agent of the subsidiary). That one company controls another may throw
17 3rd Edition, 2013.
-- 70 of 136 --
71
some light on the issue of agency, but is not decisive. A close analysis of the facts must
be made to identify the true relationship: Tate v Freecorns Pty Ltd [1972] WAR 204 at
208. Agency will arise if the proper inference to be drawn from the facts is that one
company is carrying on the business of the other and on behalf of the other.
[258] “Agency” was not discussed, in name or conceptually, by Mr McGowan, Mr Ourabah
and Mr Pellé. And there is no evidence of Apsara formally authorising BSO to act as its
agent in negotiations over the WBRDAT. However, as Dixon J observed in Colonial
Mutual Life at 50, the language used to create the purported agency relationship is not
decisive (citations omitted, my emphasis) –
Some of the difficulties of the subject arise from the many senses in which
the word “agent” is employed. “No word is more commonly and constantly
abused than the word ‘agent’. A person may be spoken of as an ‘agent’ and
no doubt in the popular sense of the word may properly be said to be an
‘agent’, although when it is attempted to suggest that he is an ‘agent’ under
such circumstances as create the legal obligations attaching to agency that use
of the word is only misleading” … Unfortunately, too, the expressions
“for”, “on behalf of”, “for the benefit of” and even “authorize” are often
used in relation to services which, although done for the advantage of a
person who requests them, involve no representation.
[259] In my view, Mr McGowan’s oral testimony reflected BSO’s sense of autonomy, and its
power of, and control over, Apsara when it came to the WBRDAT. BSO decided to use
Apsara as a “vehicle” for tax and accounting purposes in the conduct of its own business,
as pursued through the WBRDAT.
[260] I acknowledge that one may interpret Apsara’s making of the milestone payments as
manifesting its knowledge and approval of the agency arrangement. And I acknowledge
that, because of their holding company/subsidiary relationship, it could be said that both
companies would benefit from the task undertaken by BSO. However, having taken into
account that –
BSO described Apsara as the “operating company” which owned the assets for the
NJ Equity Triangle network;
BSO used Apsara’s network to deliver services to its clients;
The decision to proceed with EMClarity’s April 2018 proposal was BSO’s;
It was BSO which determined that the best way to structure things, from cash
flow, accounting and tax perspectives, was for Apsara to “own” the project and to
be the end user of the developed product; and
Clearly, on the evidence, BSO (via Mr McGowan in particular) did not think of
Apsara as its principal – although I acknowledge that BSO’s understanding of the
legal arrangement between them is not determinative,
-- 71 of 136 --
72
I am not satisfied to the requisite standard that BSO acted as Apsara’s agent in the
formation of the WBRDAT.
Issue 2: Did Apsara and EMClarity enter into agreements in May and June 2019,
for the supply of E Band and W Band radios?
Plaintiffs’ submissions
[261] The plaintiffs submitted that, although the WBRDAT provided for production and supply
of W Band radios, conditional upon their successful development, “the parties” entered
into new agreements in May and June of 2019 for the unconditional supply of E Band and
W Band radios. The plaintiffs submitted that the establishment of the new agreements
fell within the traditional framework of contract formation –
There was an invitation to treat by EMClarity – by way of its Quote to BSO for
the supply of radios (and associated equipment and accessories);
Four offers were then made to purchase the radios as per the Quote – by way of
Apsara’s issuing four purchase orders; and
Those offers were accepted – by way of EMClarity issuing invoices to Apsara and
accepting part payment from Apsara (as per the terms of the Quote).
[262] The plaintiffs submitted that there was no confusion about the entity to whom EMClarity
was to supply the radios, namely Apsara, even though the Quote was sent to BSO. Clause
4 of the Quote provided that a contract for supply would be formed between EMClarity
and the “Customer” when the Customer did certain things.18 Apsara, as the Customer,
did those things thus creating a contract for supply to it.
[263] In support of this argument, the plaintiffs relied upon Rossiter v Miller (1878) 3 App Cas
1124 at 1147, in which Lord O’Hagan observed as follows –
The parties to a contract in writing must, no doubt, be specified, but it is not
necessary that they be specified by name. The whole course of decision and
practise shews that it is not. If they are so indicated, by description or by
reference, as to be ascertained, or certainly ascertainable, the exigency of the
statute in that respect is satisfied. Here the vendors are called proprietors, and
described as proprietors in possession. There could be no mistake as to their
ownership of the premises to be conveyed, and their identity for all practical
purposes was as clearly and unequivocally established as if their names and
designations had been set out in the conditions of sale.
[264] As I understood the plaintiffs’ argument, it was that “the Customer” referred to in the
quote was, or could be, Apsara. And there could be no mistake about the entity with
18 That is, issued a purchase order and paid the relevant invoiced amounts.
-- 72 of 136 --
73
whom EMClarity in fact contracted to supply the equipment listed in the Quote. that is,
Apsara.
[265] The plaintiffs submitted that, even though the development of the W Band radio was
discussed by the parties before the 2019 Agreements were made, the 2019 Agreements
did not contain a term which suggested that supply was conditional upon development.
While, from EMClarity’s perspective, it might have been unwise not to include such a
term, it was not included and the parties were to be held to the unconditional bargain
which they struck. In any event, the conduct of EMClarity post the 2019 Agreements
suggested nothing other than that it was working towards the delivery of the radios to
Apsara.
[266] The plaintiffs referred me to well-known authorities about the construction of commercial
contracts including Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015)
256 CLR 104. The plaintiffs also referred to the decision of the Queensland Court of
Appeal in Watson v Scott [2016] 2 Qd R 484 in which the Mount Bruce principle was
restated as follows –
[E]vidence of surrounding circumstances is admissible to assist in the
interpretation of a contract only if the language is ambiguous or susceptible
of more than one interpretation; it is not admissible to contradict the language
of the contract when it has a plain meaning …
[267] Referring to Bell Group Ltd (in liq) v Westpac Banking Corp (No 9) (2008) 39 WAR 1 at
[2665], the plaintiffs observed that it was important to draw a distinction between –
deciding whether a contract exists at all – and if it does, what are its terms; and
construing or interpreting the terms of a contact known or admitted to be in
existence.
[268] The former often requires consideration of the wider circumstances and the conduct of
the parties. The latter does not permit recourse to extrinsic evidence where the identified
terms of the contract are plain and unambiguous in their meaning.
[269] The plaintiffs submitted that there was no ambiguity about the terms of the 2019
Agreements. Determined objectively, by reference to the terms of the Quote (especially
clauses 4 and 7) and the Purchase Orders, and bearing in mind the purpose to be secured
by the transaction, the key obligation imposed upon EMClarity was to supply W Band
and E Band radios to Apsara. They submitted –
clause 4 of the Quote referred specifically to an agreement for supply;
nothing in any of the terms of the Quote suggested EMClarity had any discretion
or option about carrying out its obligation to supply;
the Quote did not refer to the WBRDAT; the concept of development; or supply
being conditional upon the successful completion of a final prototype;
-- 73 of 136 --
74
nor were there any qualifications on supply introduced by the written terms of the
2019 Agreements and the court ought not to find the existence of such
qualifications by a process of construction.
[270] The plaintiffs submitted that the 2019 Agreements impliedly discharged19 the WBRDAT.
It did not matter that the Quote did not expressly provide for discharge or termination of
the WBRDAT: the question was whether the parties had that intention. The plaintiffs’
position, in summary, outlined in oral submissions, was that it was “implicit, when you
consider the supply agreements over the top of those development agreements, that what
they were doing was discharging that and entering into their final contract, saying, ‘Yes.
Now I can supply you radios. Send me a purchase order, I’ll send you an invoice, pay
me some money and you’ll get some radios at the end of the day’. That’s what’s been
concluded”.
Defendant’s submissions
[271] EMClarity submitted that there were no new agreements formed between it and Apsara
in 2019. Rather, there was an agreement between BSO and EMClarity, in terms of the
Quote, to vary the WBRDAT by altering the products that were to be delivered under it
(and its price and exclusivity terms) but only after the development phase. EMClarity
noted that, in deciding whether a later contract terminated an earlier one, the determining
factor was the parties’ intention.20 It submitted that I would find that the parties intended
to vary, rather than “rescind” (I assume EMClarity meant terminate), the WBRDAT
because only variation would ensure that existing rights remained protected.
[272] In more detail, EMClarity argued –
the “All good … Callum will proceed” email from Mr Ourabah on 10 May 2019,
signified the point at which BSO and EMClarity had reached agreement on the
terms of the quote;
the agreement was entered into by BSO in its own right;
the purchase orders issued by Apsara – a separate entity – could not have had any
bearing upon the arrangements being made to alter the contractual obligations
between BSO and EMClarity;
there was no basis for concluding that the parties intended to create a new,
separate, agreement between Apsara and EMClarity as the creation of a new,
separate agreement between Apsara and EMClarity would leave completely
19 Not rescinded.
20 Commissioner of Taxation v Sara Lee Household & Body Care (Australia) Pty Ltd (2000) 201 CLR 520, per the
majority of the High Court at [22] – [24]; Dan v Barclays (1983) 46 ALR 437, per Wilson and Dawson JJ at 448
Coghlan v Pyoanee Pty Ltd [2003] 2 Qd R 636 per McPherson JA said at [5], after citing Sara Lee.
-- 74 of 136 --
75
unanswered the issue of what was then to happen with the W Band Radio
Development Agreement between BSO and EMClarity;
there should thus be a finding that there was a contractual agreement reached
between BSO and EMClarity, in terms of the Quote; and
it made “good commercial sense” that –
o BSO and EMClarity agreed on the terms of the Quote which altered the
products that would be delivered when the development phase of the W Band
Radio Development Agreement concluded (and some other associated terms,
such as exclusivity and price); and
o Apsara, as the entity paying the money, issued a purchase order to formally
request an invoice and invoices were issued to it in response.
[273] Of course, the E Band radios referred to in the Quote did not require development. Nor
did the accessories. In this regard, I acknowledge EMClarity’s concession that its pleaded
variation “would have the effect of creating [in EMClarity] an obligation to deliver [E
Band radios] within a reasonable time”.
Plaintiffs’ submissions in reply
[274] The plaintiffs submitted that I ought to reject the defendant’s characterisation of the 2019
Agreements as agreements to vary the WBRDAT. They said –
[EMClarity] appears to accept that the [2019 Agreements] were created by
virtue of the Quote and Purchase Orders but says that BSO, not Apsara, was
party to those “contractual arrangements”. However, [EMClarity] does not
plead (and has not explained) how BSO in fact “placed” the orders when the
Purchase Orders were in the name of Apsara and made on Apsara letterhead.
For instance, [EMClarity] does not plead that Apsara acted as BSO’s agent in
issuing the Purchase Orders, nor does it plead any additional facts to show
that these orders were “placed” by BSO.
[redacted]
Discussion
Principles
[275] The defendant’s written outline contained the following accurate summary of the
principles relevant to the question whether a contract has come into existence –
Whether a contract has come into existence is determined by reference to the
intention of the parties as disclosed by the language used by the parties which
-- 75 of 136 --
76
is said to constitute the contract. The intention of the parties is determined
objectively. Thus, it is determined by reference to:
(a) what the relevant communications would have conveyed to reasonable
persons in the position of the parties; and
(b) the intention that reasonable people would have had if placed in the
situation of the parties.
…
Evidence of the parties’ prior negotiations and subsequent conduct (that is
conduct subsequent to the alleged contract) is relevant and admissible on the
question of whether they have formed a contract.
An analysis in terms of offer and acceptance is not always necessary to
establish a contract …
[276] Further, as Muir JA explained in Weemah Park Pty Ltd v Glenlaton Investments Pty Ltd
[2011] 2 Qd R 582 at [45] and [46],21 where an exchange of correspondence is relied upon
to establish the existence of a contract, it is not merely the communications alleged to
constitute the offer and the acceptance which are to be looked at. The intention of the
parties is to be objectively ascertained from the terms of the documents when read in the
light of the surrounding circumstances including the chain of correspondence and the
parties’ relevant dealings. The emphasis is on what the relevant communication would
have conveyed to reasonable persons in the position of the parties, rather than on “a
pedantic analysis of language and emphasis on form over substance” (at [49] and [50]).
His Honour referred to Heydon JA in Brambles Holdings Ltd v Bathurst City
Council(2001) 53 NSWLR 153, endorsing statements from other authorities to the effect
that, the relevant test is “whether viewed as a whole and objectively from the point of
view of reasonable persons on both sides, the dealings show a concluded bargain”.
[277] Before considering the objective effect of the relevant communications between the
parties, I will address particular arguments made by the defendant.
What was to happen to the WBRDAT if new agreements were made?
[278] The defendant’s argument, that the suggestion of new agreements made “no sense at all”
because it would leave the question of what was then to happen with the WBRDAT
“completely unanswered”, overlooked the fact that the WBRDAT was a staged
agreement, marked by milestones – the payment of which triggered progress to the next
stage – which anticipated the possibility of termination at the end of several of its stages.
21 Referring to GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd [(1986) 40 NSWLR 631 at 634.
-- 76 of 136 --
77
[279] Relevantly, under clause 5.4(d) of the WBRDAT, the Customer could terminate it “up to
the end of Milestone 4 under the circumstances set forth in the ‘Milestone Payment
Deliverables’ section of the Schedule” (see above).
[280] Apsara made the Milestones 1, 2 and 3 payments. It did not make the Milestone 4
payment – nor was it ever asked to.
[281] At the very least, in a practical sense, the answer to the question: “what would happen to
the WBRDAT if new agreements were made”, was that EMClarity was not obliged to
take any further step under it because the Milestone 4 payment was not made. But in my
view, at or by the time the 2019 Agreements were made, the WBRDAT was or had been
terminated.
[282] As both the plaintiffs and the defendant appreciated, only the parties to the WBRDAT
could vary or terminate it. I have found that the parties to the WBRDAT were EMClarity
and BSO – acting in its own right. EMClarity and BSO did not expressly terminate the
WBRDAT. But –
BSO/Apsara did not make the Milestone 4 payment;
EMClarity did not pursue it;
after Apsara made the Milestone 2 and 3 payments, neither party made any
reference to Milestone 4 or Milestone 5; and yet
the production of W Band radios commenced regardless.
[283] In my view, EMClarity and BSO’s conduct, considered objectively in the circumstances–
reflected a recognition on their part that the WBRDAT had been overtaken by the
2019 Agreements between EMClarity and BSO’s subsidiary;
reflected a common intention that they be discharged from their obligations under
the WBRDAT; and
achieved termination of the WBRDAT under clause 5.4(d).
[284] After termination of the WBRDAT, clause 5.8 of the WBRDAT dealt with the rights and
remedies of the parties and answered the “what would happen to the WBRDAT if new
agreements were made” question.
[285] I am not therefore persuaded by the defendant’s argument that I ought not to find that
new agreements were made because the parties would not have left the WBRDAT, in
effect, “hanging”.
[286] Even if I am wrong, and the creation of new agreements between EMClarity and Apsara
left the WBRDAT “hanging”, it is important to recognise that the 2019 Agreements were
-- 77 of 136 --
78
the product of negotiations between engineers not lawyers. The engineers may well have
reached agreement on terms which were not legally “perfect”. Their agreement may not
have, for example, disposed of loose ends; ensured no reduction in a contracting party’s
former rights; been entirely consistent or cohesive with other relevant contracts or
arrangements; or anticipated or dealt with issues which may have been obvious to
lawyers. But, as the parties in this case acknowledged, contracting parties may reach an
agreement which may be considered, objectively, unsatisfactory.22
Was a varied WBRDAT the agreement which made good commercial sense?
[287] The defendant urged me to find that the WBRDAT had been varied rather than terminated
because variation made “good commercial sense”.
[288] In determining the effect of a commercial contract, courts favour a commercially sensible
construction as a commercially sensible construction is more likely to give effect to the
intention of the parties. Accordingly, I have considered the commercial sense of the
varied WBRDAT.
[289] Paragraph 23 of EMClarity’s defence included assertions that BSO and EMClarity
reached agreement (by way of the Quote) to inter alia –
vary Milestones 5, 6 and 7 “by Phases 1 to 4 of the Alternative Strategy [that is,
the staged rollout of the network deploying E Band and W Band radios]”
(23(a)(i)(A));23
replace the Milestone payments for Milestones 4 to 7 with the sums set out in the
Quote for each phase (23(a)(i)(B));
vary the number and kind of radios to be supplied in the manner set out in the
Quote, subject to completion of Milestones 1 to 4 of the WBRDAT (23(a)(i)(E)).
[290] [redacted]
[291] The replacement of the payments for Milestones 4 to 7 with the sums set out in the Quote
for each phase makes less commercial sense insofar as the replacement of the Milestone
4 payment is concerned.
22 Queen’s Counsel acknowledged in oral submissions that he could not say that it was not an “open possibility”
that Dr Baines and Mr McGowan just did not think about the implications of rescinding the WBRDAT during
their negotiations, and reached a new agreement regardless. However, he submitted that I ought to be very
clear that this was what the parties intended – rather than the more commercially sensible outcome for which
he contended.
23 In final submissions, the defendant admitted to an error in paragraph 23(a)(i)(A) of its defence insofar as that
paragraph referred (wrongly) to Milestones 4 to 7, instead of 5 to 7.
-- 78 of 136 --
79
[292] [redacted]
[293] Under the WBRDAT, BSO was only obliged to make the Milestone 4 payment if there
was a “successful review” of the “finished design” of the W Band radio. If the review
was not successful, then BSO could terminate the project.
[294] Milestone 4 was thus a significant milestone at the critical point of the development stage
of the WBRDAT. The Milestone 4 payment was the final payment for the development
stage of the WBRDAT and it indicated “the Customer’s” satisfaction with the final
design.
[295] The suggestion that the parties agreed to replace the Milestone 4 payment with the
payment required for the first stage of the network rollout implies that the parties agreed
to remove from the WBRDAT a provision which recognised and dealt with the possibility
that EMClarity might not be able to design/develop a “successful” W Band radio, or that
BSO might not be satisfied with the final design. That implication was inconsistent with
the defendant’s case.
[296] The defendant may have intended to refer only to Milestones 5, 6 and 7 in paragraph
23(a)(i)(B) of its defence and the reference to Milestone 4 might have been in error.
However, even on that basis, the varied agreement proposed by the defendant did not
make good commercial sense.
[297] The W Band radio was the critical component of BSO’s new network. If the WBRDAT
was varied only in relation to the equipment to be supplied in pursuance of it, and subject
to the completion of Milestone 4, it made no commercial sense to require the Customer to
pay EMClarity 50 per cent of the total cost of the network’s equipment before it was
asked for the Milestone 4 payment – that is, before it was asked to confirm its satisfaction
with the final design of the W Band radio.
[298] Also, in the context of an agreement to supply which was conditional upon successful
development of one of the products to be supplied, it did not make good commercial sense
for “the Customer” to pay, up front, 50 per cent of the total cost of producing W Band
radios,24 which were still in development, if the parties contracted on the basis that the
success of the development was uncertain.
[299] Even if there were a legitimate need to order, and require the Customer to pay 50 per cent
of the cost of, all of the equipment needed for the whole of the new network up front, it
made no commercial sense not to provide for a refund of the 50 per cent paid (perhaps
less the cost of any equipment used in the pursuit of W Band development) if the
development of W Band radios was not successful.
24 And the rest of the equipment required for the whole of the network.
-- 79 of 136 --
80
[300] I am not persuaded by the defendant’s arguments that the variation it contended for made
good commercial sense.
Inferences to be drawn from the parties’ communication and other conduct
[301] The inferences to the drawn from the parties’ communication and other conduct support
the plaintiffs’ case that BSO and Apsara entered into new agreements in 2019 to
unconditionally supply a network’s worth of radios and associated equipment.
[302] The terms of the Quote did not provide for the possibility that the final design would not
be successfully reviewed. Nor did payments under the Quote complement the milestone
payment regime under the WBRDAT. If the Quote was intended to vary only the
deliverables of the WRBDAT, then one would have reasonably expected some discussion
between the parties of Milestone 4 which signalled success in achieving a suitable final
design for the W Band radio. There was none.
[303] The evidence discussed above reveals that, after a complaint by BSO in January 2019
about the slow speed of the project, Dr Baines encouraged Mr McGowan’s understanding
that, while the development of the W Band radio might take time, it would be successfully
developed.
[304] Dr Baines minimised the need for the stepped, milestone approach of the WBRDAT and
the focus of his conversations with Mr McGowan shifted from a focus on the parties’
obligations under the WBRDAT (particularly BSO’s obligation to make milestone
payments) to a focus on the speed with which W Band radios could be deployed by BSO.
[305] Rather than insisting upon the Milestone 4 payment, conveying BSO’s acknowledgment
that a “successful” W Band radio had been developed, before producing W Band radios,
EMClarity agreed to treat the receipt of an order for W Band radios and other products as
“the trigger to build”. This signalled a move away from a cautious agreement to produce
W Band radios only if they could be successful developed (that is, the WBRDAT) to a
“new” unqualified agreement to build and supply W Band radios, E Band radios and other
equipment.
[306] In more detail, the evidence establishes the following matters.
1. It may be inferred, from Dr Baines’ dealings with Apsara, McKay Brothers and
BSO, that he had a reasonable understanding of the market for wireless networks.
And it may be inferred, from Dr Baines’ educational and occupational background;
his senior role at EMClarity; and his dealings with Apsara, McKay Brothers and
BSO, that he had sufficient commercial nous and common sense to understand the
competitive advantage achieved by those offering network services in the NJ Equity
Triangle who were able to secure new, faster/clearer radios for deployment on their
networks.
2. Whatever Dr Baines subjectively thought of the prospects of success of the W Band
project, his communication with Mr McGowan about it was overwhelmingly
-- 80 of 136 --
81
optimistic – from the very first proposal. He did not ever suggest that the
development of the W Band radio was not feasible. Whatever the reality of the W
Band design challenges (described by Dr Baines in his affidavit), to the limited
extent to which Dr Baines raised them with Mr McGowan, he minimised them.
3. In late January 2019, BSO was not pleased that it had been left in “not a good
position”. It had expected to be deploying EMClarity’s W Band radios in its
network by then and lost a customer to a competitor, presumably because the
competitor was able to offer a “better” network. Under market pressure, BSO
wished to “accelerate” the creation of a new and better network deploying W Band
radios.
4. Dr Baines did not discourage in Mr McGowan an understanding that, while
development was slower than expected, the W Band radios could and would be
successfully developed (including by his silence in the face of statements by Mr
McGowan which he found “bizarre”). In particular, Dr Baines’ email of 31 January
2019 conveyed only that the W Band radio was a valuable reality and that
EMClarity was well placed to provide BSO with “world leading” W Band
technology, which it expected to successfully develop within three months.
5. Dr Baines told Mr McGowan that, while “strictly speaking”, EMClarity needed
BSO’s “confirmation” to proceed with the final design, EMClarity did not
anticipate BSO’s not confirming – further conveying the expected success of the
development project.
6. Dr Baines conveyed that he was so confident in EMClarity’s ability to complete the
final design that production units could be produced during the design phase.
7. Dr Baines also offered an E Band alternative (on 31 January 2019) which could be
deployed “in short order”, which was of interest to BSO and in respect of which
EMClarity prepared, for BSO, path analyses and latency calculations.
8. On 5 February 2019, their recent discussions having been about E Band radios only,
Dr Baines asked Mr McGowan what he needed to feel comfortable “in progressing”
to the next milestone of the WBRDAT – obviously reflecting EMClarity’s desire
to keep BSO engaged in the W Band project.
9. On 6 February 2019, Mr McGowan told Dr Baines that W Band “need[ed] to
happen”. [redacted]
10. Dr Baines’ email of 8 February 2019 implied that EMClarity –
o was confident of its ability to produce successful W Band radios; and
o did not need to take the more cautious, sequential approach.
Those implications arose of the strength of Dr Baines’ –
-- 81 of 136 --
82
(a) stating his belief that EMClarity would have working W Band and E Band
radios in about three months, if the “go button” was “pushed” at that time;
(b) conveying that the W Band radios would be successfully designed and
produced and would pass compliance testing; and
(c) conveying that the “normal” sequential stages, of development/design then
production, were not necessary: and that development/design and production
could occur at the same time.
11. On 12 February 2019, Dr Baines encouraged Mr McGowan to consider [redacted]
(which required development by EMClarity), but indicated that EMClarity was in
a position to build 16QAM E Band radios immediately.
12. On 13 February 2019, Dr Baines told Mr McGowan that EMClarity was “sitting at
the stage” where it needed BSO’s confirmation to proceed with the W Band
development and payment of its next invoices (Milestones 2 and 3) “for the
development”. On 13 February 2019, Mr McGowan told Dr Baines that “we” were
going ahead with W Band.
13. On 14 February 2019, Mr McGowan told Dr Baines that he “need[ed] to put product
into the field now” and that he was in a position to start issuing purchase orders
for product which EMClarity could ship “in short order”. That same day, Dr
Baines sent Mr McGowan a quote for E Band equipment and product information
(broken down in a certain way) – implying that EMClarity was in a position to ship
E Band radios “in short order”.
14. On 15 February 2019, Mr McGowan asked for a similar breakdown of the W Band
equipment. On 22 February 2019, Mr McGowan chased Dr Baines for this
breakdown. The similar breakdown for W Band equipment was sent by Dr Baines
to Mr McGowan on 26 February 2019 in the form of a quote for the W Band links
with associated accessories. The quote said nothing about the supply of W Band
radios being conditional upon their successful development. The WBRDAT
provided only for the ultimate supply/purchase of the “Product” – that is, a
production batch of “W Band 92-95 GHZ low latency radio[s]”. It did not provide
for the supply/purchase of E Band radios, antennas, [redacted] or extended
warranties, which were included in the quote.
15. In February/March 2019, Dr Baines and Mr McGowan communicated about the
various options for BSO’s new network. Their discussions anticipated the
deployment of W Band radios, built by EMClarity, in BSO’s new network.
16. Some of the proposed components of the new network had to be developed by
EMClarity, including the implementation of the [redacted] in the W Band radio.
17. On 8 March 2019, Dr Baines told Mr McGowan that he would translate “all of this”
– that is, all that was proposed for the new network – into a/the Quote which would
-- 82 of 136 --
83
allow Mr McGowan to “push the go button”. The use of the phrase “push the go
button” suggested that a new agreement would commence upon Mr McGowan’s
acceptance of the Quote and payment of 50 per cent of the invoiced amount.
18. The Milestone 2 and 3 payments were made on 12 March 2019 after which
milestone payments under the WBRDAT were not mentioned again. It is
particularly significant that Milestone 4 was not mentioned. Nor was it ever
suggested that BSO had a right to discontinue the project after the development
stage – as had been its right under the WBRDAT.
19. Further discussions about the new network, and the radios required for it, took place
in March 2019.
20. While Dr Baines’ email of 14 March 2019 referred to production following
immediately after “the design and prototypes are finished”, it did not suggest that
production was conditional upon successful design and development of a functional
prototype. Indeed, that email implied that nothing about the design or development
of the prototype would derail delivery of the equipment in accordance with the
timelines which had been discussed, if BSO were to issue purchase orders and make
payments for the equipment “as soon as possible”. Also, nothing was said, after the
Milestone 2 and 3 payments, about BSO’s right to discontinue with the agreement
after the final design stage.
21. The path analyses prepared by EMClarity for BSO were analyses of BSO’s
proposed new network “using EMClarity E Band and W Band radios”. They were
provided without any suggestion or reminder that using W Band radios for BSO’s
new network was conditional upon their successful development.
22. On 29 March 2019, Dr Baines encouraged Mr McGowan to order “the equipment
required for the full network triangle before 1 April 2019” to take advantage of a
certain discount offered by EMClarity.
23. Dr Baines’ email dated 29 March 2019 referred to the cost of producing 64QAM
W Band radios – reasonably implying that EMClarity was able to produce such a
radio at that cost. The email spoke about ‘David” working out delivery timeframes
– reasonably implying that EMClarity was in a position to calculate those
timeframes unburdened by the risk of unsuccessful development of W Band radios.
24. [redacted]
25. Dr Baines and Mr Pellé’s emails in April 2019 are in pursuance of “a deal” which
will work for both of them – consistent with the evolution of a new agreement.
26. Dr Baines’ “best estimates” for delivery of the W Band and E Band radios (as per
his email dated 26 April 2019) conveyed no suggestion that delivery of the W Band
radios (or the E Band radios for that matter) was conditional upon the successful
development of, or creation of a functional prototype for, a W Band radio. While
-- 83 of 136 --
84
the email conveyed that there was a need for EMClarity to “complete” the “design”
of the W Band radios, nothing in the email suggested any uncertainty about
EMClarity’s ability to complete it. Indeed, the email suggested that there was a
way to accelerate the delivery of at least one W Band radio (for use in phase 2) from
September to July 2019 – namely, if EMClarity were to build a second prototype
during the W Band “development”. Also, the second last paragraph of the email
expressed EMClarity’s plan to produce the radios in an unqualified way.
27. The language of Dr Baines’ email of 26 April 2019 is consistent with the parties
entering into a new agreement for the supply of all the equipment required for
BSO’s network which recognised that development of the W Band radio was
ongoing but which assumed successful development. It included the following –
Note on phase 2 W Band delivery.
We expect the development of the prototype W Band 64 QAM to be
finished in 8 weeks. We could build an extra prototype link and then
you could install that one … If we went down this route, and I like the
idea, then the possible delivery on phase 2 W Band might be 10–11
Weeks ARO for the 1 link, meaning mid-July. That means you would
have the equipment for the first two phases in July.
…
If we can confirm everything next week then the way we will arrange
production is to build all of the W Band MODEM halves at the same
time as building the E Band links then with the W Band complete
building the W Band components and adding to the unit.
I’m also working on the contractuals as I promised Michael and
Emmanuel. I will give you a new quote reflecting what you have put
below on the phases, and also a contract containing all the terms we
have collectively been discussing.
One would reasonably expect, under the heading “Note on Phase 2 W Band
delivery”, a statement about the supply of W Band radios being conditional upon
their successful development if that is what the parties intended.
28. The reference to “a contract containing all the terms we have collectively been
discussing” is consistent with the formation of a new agreement. Not once was it
described as a variation of the WBRDAT; nor were there any discussions which
suggested the parties were contemplating a variation of the WBRDAT.
29. The quote dated 30 April 2019 (sent 2 May 2019) and the final Quote, dated 10
May 2019, said nothing about supply of W Band radios being conditional upon
successful development.
30. Dr Baines’ statement, in his email of 2 May 2019, that the trigger to build would be
the receipt of an order, reflects a change from the cautious approach of the
-- 84 of 136 --
85
WBRDAT, which required first the payment of Milestone 4, signifying acceptance
of the final design, then the payment of Milestone 5 to “trigger” or “kick off” the
build.
31. Dr Baines’ email dated 24 July 2019 suggested, without qualification, that E Band
and W Band radios would be delivered in September and November 2019,
respectively. While Dr Baines referred to “engineering issues”, he said nothing to
suggest that those issues might get in the way of successful development of the W
Band radio. Rather, he informed BSO, in effect, that the resolution of those issues
had improved the stability of the “product destined for BSO”.
32. The emails about Mr McGowan receiving training in the W Band and E Band radios
obviously assume the production of those radios.
[307] Drawing together all of the evidence, and in particular the evidence outlined above, and
the inferences to be drawn from it, a reasonable bystander would conclude that EMClarity
first encouraged BSO to stick with it (after BSO lost a client) by alleviating BSO’s
concerns about EMClarity’s delay in producing W Band radios which could be deployed
“in the field”. It did so by –
introducing deployable-at-short-notice E Band radios into the mix;
conveying no doubt about EMClarity’s ability to develop and produce W Band
radios; and
abbreviating the time frame for the delivery of W Band radios by proposing to
produce them in parallel with their development.
[308] A reasonable bystander would have observed that then EMClarity and BSO moved away
from conversations focused on milestone payments, and the development and design of
the W Band radio, to conversations about BSO’s new network as a whole and the radios
and other equipment required for it.
[309] A reasonable bystander would conclude that the conversations about the new network
proceeded on the basis that EMClarity could and would produce the W Band radios
needed for it – without any suggestion that their production was conditional upon
successful development.
[310] The fact that EMClarity did not pursue the Milestone 4 payment before indicating that it
was in a position to supply W Band and E Band radios and other products as per the Quote
is objectively consistent with the parties agreeing to proceed to production and supply in
a manner other than the one provided for under the WBRDAT.
[311] A reasonable bystander would conclude that BSO and EMClarity discharged or
terminated the WBRDAT and that EMClarity and BSO’s subsidiary contracted for the
unconditional supply of all of the equipment needed for BSO’s network.
-- 85 of 136 --
86
[312] It is not necessary for me to reach a view about the reasons why EMClarity was prepared
to move away from the WBRDAT, which gave it (and, for that matter, BSO) protection
against the unsuccessful development of W Band radios, but EMClarity’s reasons may
have included financial ones. In oral submissions, Queen’s Counsel for the defendant
accepted that there were “financial drivers” in the background during Dr Baines
negotiations with Mr McGowan.
Inferences to be drawn from conduct after the 2019 Agreements
[313] The statements and conduct of EMClarity and BSO/Apsara after the 2019 Agreements
were entirely consistent with their obligations under “new” 2019 Agreements, not under
the development stage of the WBRDAT.
[313A] BSO was not required to participate in a “Final Design Review Meeting” in
Brisbane to “sign-off” on the detailed design – something which it was obliged to do
under the WBRDAT –25 before the W Band units would be “on their way”26 to Apsara.
Apsara paid 50 per cent of the total cost of the equipment, and EMClarity embarked
immediately upon acquiring the components required for the whole of the network,
including for the radios which had to be built.
[314] Not once, after the 2019 Agreements were formed, did EMClarity attempt to explain away
any delay on its part on the basis of slow or unsuccessful development. To the contrary
– it blamed its suppliers.
[315] Other conduct of EMClarity after the 2019 Agreements were made, consistent with its
understanding that it had newly agreed to unconditionally supply equipment, including
W Band radios, to Apsara, included –
1. Dr Baines’ reference to the “initial payment” in an email dated 17 May 2019 –
consistent with the formation of a fresh, new agreement, commencing with a first
(that is, “initial”) payment;27
2. Dr Baines’ reference to “the deal we agreed” in a follow up email dated 20 May
2019 – in context, consistent with a recently formed new agreement;
3. Dr Baines’ email of 24 July 2019, which –
(a) referred to negotiating “the equipment purchase” – consistent with EMClarity
and Apsara reaching unconditional agreements to supply;
25 Under “Customer Tasks” in the schedule to the WBRDAT.
26 As per Dr Baines’ email of 24 July 2019.
27 This email is only included in Mr McGowan’s affidavit. A copy of this email is not included in Dr Baines’
affidavit.
-- 86 of 136 --
87
(b) noted that, initially, EMClarity was signalling expected delivery of the
equipment in July – consistent with EMClarity unconditionally agreeing to
supply the equipment;
(c) signalled EMClarity’s intention to ship W Band links from early November,
without mention of the need for successful development – consistent with
EMClarity unconditionally agreeing to supply the equipment;
(d) explained that, whilst EMClarity encountered some “engineering issues”,
those issued had been addressed and there was (as a result of addressing the
issues) “increased stability in the design of the product destined for BSO” –
consistent with EMClarity unconditionally agreeing to supply the equipment;
(e) explained that EMClarity was able to deal with “some component
obsolescence” before it shipped anything – consistent with EMClarity
working towards the shipment of product; and
(f) referred to equipment it is “ producing” – consistent with an unconditional
agreement to supply the equipment;
4. Mr White’s email of 13 August 2019 to Mr McGowan indicating that “everything
else” (apart from a particular supplier) was “on track – consistent with an
unconditional agreement to supply equipment by a certain time;
5. Dr Baines discussing training with Mr McGowan – consistent with EMClarity
producing (workable) equipment unconditionally;
6. The estimates of the time it would take EMClarity to build W Band (and E Band
radios) outlined in Dr Baines’ 30 August 2019 email – inconsistent with a need to
confirm that W Band radios could be successfully developed before they would be
supplied;
7. Dr Baines predicting that a visit by Mr McGowan in October 2019 would be “very
productive” in the sense that he could then be trained in the equipment –
inconsistent with a need to confirm that W Band radios could be successfully
developed before they would be supplied;
8. Other statements by Dr Baines about the expected delivery dates for the W Band
radios (for example, that they would be coming off the production line in
September) – consistent with EMClarity unconditionally agreeing to supply the
equipment;
9. Dr Baines communicating with Mr McGowan about getting him “up and running”
– consistent with EMClarity unconditionally agreeing to supply the equipment;
-- 87 of 136 --
88
10. Mr White and Dr Halappa’s emails in September 2019 in which Dr Halappa
indicated, in effect, that EMClarity was prepared to take the risk of ordering the
parts for the W Band radios required for BSO’s network, even though it had not
built a W Band radio; and
11. Mr White’s email to Mr Dench and Dr Baines, dated 4 November 2019, in which
he said, “… despite the customer’s request that we fast-track the production, we
feel we can only provide a quality product by first prototyping and then going to
production”. This email was consistent with the 2019 Agreements being
agreements to produce without first building a prototype (that is – the fast track);
and then a unilateral decision by EMClarity to change its approach.
Conclusion
[316] I find that the Quote issued to BSO by EMClarity was an invitation to treat – inviting a
request for it to produce and supply all of the equipment BSO needed for its new NJ
Equity Triangle network. Having regard to their previous dealings, and EMClarity’s
awareness of the way in which BSO used Apsara, I find that EMClarity was prepared to
enter into contracts reflecting that invitation with either BSO or its subsidiary, and
ultimately entered into supply agreements with Apsara that were separate to the
WBRDAT.
[317] Applying the principles from Weemah and Brambles Holdings, I find that, objectively
viewed, the circumstances, communications and conduct of the parties reflected their
common intention to move away from a focus on the potential development of W Band
radios under the WBRDAT to a focus on the equipment required for the configuration of
BSO’s new network.
[318] In the context of that “new” focus, I find that BSO and EMClarity terminated the
WBRDAT and that EMClarity and Apsara entered into a new agreement for the
unconditional supply of the equipment needed for BSO’s new network, including W Band
radios, to Apsara.
Issue 3: Alternatively to Issue (2), was the W Band development agreement varied?
[319] As I was not satisfied that BSO acted as Apsara’s agent in the formation of the WBRDAT,
the plaintiffs would not have succeeded in their argument that the 2019 Agreements
varied the WBRDAT so as to remove the development stage of it.
[320] However, I have tested my conclusion that the 2019 Agreements were “new” agreements
independent of the WBRDAT against the defendant’s arguments about the variation
which suited its case – that is, variation of the WBRDAT so as to preserve its development
phase (notwithstanding the plaintiffs’ complaint about the way in which the defendant
pleaded, or did not plead, this variation case).
[321] The defendant’s defence – essentially, that it was under no obligation to supply W Band
radios because successful development had not yet occurred – relied upon my being
-- 88 of 136 --
89
satisfied that the 2019 Agreements varied only Milestones 5 to 7 of the WBRDAT,
leaving the balance of the agreement intact and thereby rendering supply conditional upon
successful development.
Defendant’s submissions
[322] The defendant submitted that the 2019 Agreements did not expressly rescind28 the
WBRDAT, nor did they rescind the WBRDAT by necessary implication. It submitted
that the 2019 Agreements effected a change to the project as anticipated by clause 9.1 of
the WBRDAT. As above, that clause stated, “The parties may agree on change to the
Project, Project Plan and the Fees in writing from time to time”. The “Project Plan” set
out the milestones, their expected completion dates and their respective payment
amounts.
[323] The defendant submitted that rescission of the WBRDAT would have resulted in the
objectively unlikely “jettisoning” of contractual terms which were “obviously valuable to
both parties” (including the benefits conferred by clauses dealing with confidentiality,
intellectual property, the granting of a licence, the limitation of liability, and indemnity).
Also, the 2019 Agreements omitted some of the target specifications of the WBRDAT –
which were important to BSO (such as, for example, the bit error rate specification).
[324] The defendant submitted that the email communications (which were not in any event
pleaded as extrinsic facts) did not support the contention that the 2019 Agreements
rescinded the WBRDAT. Rather, they showed that it was contemplated that the
development of the W Band radio under the WBRDAT would continue in parallel with
ordering parts for the production orders. There was an explicit reference to the parallel
development in Mr McGowan’s email of 24 April 2019 and there was a reference to the
completion of design and the prototyping phase in Dr Baines’ emails of 26 April 2019
and 2 May 2019 reflecting the parallel progress of the WBRDAT.
[325] The defendant submitted that the WBRDAT was varied, from 10 May 2019, but only in
relation to the obligation to supply product. [redacted] The price and exclusivity terms
were also varied, but subject to those variations, the WBRDAT remained on foot.
Plaintiffs’ submissions
[326] The plaintiffs emphasised clause 4 of the Quote and observed that the defendant’s
arguments were “curiously silent” as to the effect of the Purchase Orders, the issuing of
the invoices and the [redacted] paid by Apsara to EMClarity. In oral submissions,
Queen’s Counsel for the defendant submitted that I could find that there were no new
agreements for supply made in May/June 2019, notwithstanding clause 4 of the Quote –
referring to authorities which said that the parties may waive those sorts of requirements.
28 Although the defendant used the words “rescind” and “rescission”, I assume it meant “terminate” and
“termination”.
-- 89 of 136 --
90
[327] The plaintiffs complained about the defendant’s pleaded case on the variation for which
it contended, which I will not repeat, and submitted that the defendant’s argument about
variation was bound to fail in any event. If I held up a lens to the circumstances, I would
not discern a mutual intention to vary the earlier development agreement by the terms of
the Quote. The plaintiffs relied on the decision of Bond J in King Tide Company Pty Ltd
v Arawak Holdings Pty Ltd [2017] QCA 251 in which his Honour discussed the
circumstances in which a contract might be inferred from the acts and conduct of the
parties and emphasised the need to take care to ensure that the objective assessment of
the relevant conduct in all of the circumstances unequivocally pointed to the existence of
a contract in the terms alleged.
Discussion
Would termination of the WBRDAT jettison its valuable terms?
[328] The defendant’s argument that terminating the WBRDAT would have “jettisoned” its
valuable terms overlooks the fact that the WBRDAT preserved valuable rights post
termination.
[329] Clause 5.8 of the WBRDAT provided that a party’s accrued rights or remedies were not
affected by termination. Clause 5.9 provided that termination or expiry of the WBRDAT
“would not affect clauses 5.8, 6, 7, 8 or 13, the warranty, extended warranty and escrow
provisions” of the WBRDAT, or “any other provision of the agreement which is expressly
or by implication intended to come into force or continue on or after the termination or
expiry”. Clause 6 dealt with intellectual property and the licencing of customer material.
Clause 7 dealt with obligation of confidence. Clause 8 dealt with limitation of liability
and indemnification. Clause 13 dealt with general matters including the laws governing
the agreement; the effect of representations; and interest accruing on overdue amounts.
The point is that termination would not have resulted in the jettisoning of terms which
were beneficial to the parties.
The significance of differences in the specifications
[330] Although I am able to compare the specifications as per the WBRDAT with the
specifications as per the Quote and note the differences, the evidence does not allow me
to reach any conclusion about the importance, or otherwise, of the omission of certain of
the WBRDAT specifications in the Quote. I note though that there were many discussions
about technical matters prior to the drafting (and revising) of the Quote. I infer that the
specifications for the equipment were informed by those discussions and that the Quote
was for equipment which met BSO’s technical needs.
Did the defendant’s proposed variation make commercial sense?
[331] I have already analysed the suggested variation for its commercial sensibility under the
previous heading. That analysis also supports my conclusion that the WBRDAT was not
varied by any agreement between any of the parties in 2019.
-- 90 of 136 --
91
Conclusion
[332] Having considered the defendant’s submissions in support of its argument that the
WBRDAT, though varied, remained on foot, I remain of the view that the parties reached
a new agreement which required EMClarity to unconditionally supply W Band radios
(and other equipment) to Apsara.
Issue 4: Did the Supply Agreements (or the WBRDAT as varied) contain an
implied term that the E Band and W Band radios would be supplied within a
reasonable time?
[333] The defendant did not suggest that I would not imply a “supply within a reasonable time”
term into the 2019 Agreements, if I found them to be unconditional agreements to supply
equipment, including W Band and E Band radios. Its primary challenge to the implication
of a “supply within a reasonable time” term was based on the premise that the WBRDAT
had been varied by the 2019 Agreements but that its development stage remained in place.
The defendant argued that it was not appropriate to impose a “reasonable time” term upon
the development part of the WBRDAT because there was uncertainty around new
development;29 production of the W Band radio was conditional upon its successful
development; therefore it was not appropriate to imply a term that the radios would be
supplied within a reasonable time.
[334] The defendant submitted that, even if the reasonable time obligation was considered by
reference only to the production/delivery stage of the WBRDAT, the assessment of a
reasonable time would need to take into account the time it would take to successfully
develop the products which required development.
Discussion and conclusion
[335] Because I have found that the parties’ 2019 negotiations culminated in new agreements
for the unconditional supply of W Band radios and other products, I do not need to
consider the implication of a reasonable time term into any stage of the WBRDAT.
[336] I consider that a “supply within a reasonable time” term ought to be implied into the 2019
Agreements.
[337] I have reached that conclusion taking into account the parties’ positions as well as relevant
legal principles including that the implication of a term as a matter of law into contracts
of a certain type involves “a search, based on wider considerations, for such a term as the
nature of the contract might call for, or as a legal incident of this kind of contract”. To
imply a term, it must be “necessary” – in that without it, the enjoyment of the rights
conferred would be “rendered nugatory, worthless, or … seriously undermined”: per
Kiefel J in Commonwealth Bank of Australia v Barker (2014) 253 CLR 169 at [56]. It is
29 Counsel for the plaintiff indicated that she would not take issue with the defendant’s contention that a court
would not imply a reasonable time term into a development/research contract.
-- 91 of 136 --
92
not enough, to imply a term, for the court to consider it a reasonable one, a fair one, or
one the parties would have agreed to had it been suggested to them. The court is not
entitled to re-write the bargain to achieve what it thinks would be a more reasonable result
(Kazakstan Wool Processors (Europe) Ltd v Nederlandsche Credietverzekering
Maatschappij NV [2000] CLC 822 at 831).
[338] The 2019 Agreements were unconditional agreements to supply the equipment listed in
the purchase order. I agree with the plaintiffs that the implication of a term that the
equipment would be supplied within a reasonable time was straightforward. I find that
as a matter of law, EMClarity was obliged to supply the E Band and W Band radios to
Apsara within a reasonable time.
[339] Also, in my view, the “supply within a reasonable time” term should be implied as a
matter of fact, because its implication satisfied the test outlined in BP Refinery
(Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266. It was -
reasonable and equitable to both parties because circumstances outside of
EMClarity’s control could be taken into account;
necessary to give business efficacy to the contract because without it the
obligation to supply was open-ended and the defendant would be under no
contractual imperative to progress the work;
obvious;
capable of clear expression; and
not inconsistent with a term of the agreement – indeed, it had to be implied
because there was no time limit term.
Issue 5: If there was such an implied term, what was a “reasonable time” for the
supply of the radios?
[340] I found this a difficult issue because of the state of the evidence.
Plaintiffs’ submissions
[341] The plaintiffs submitted that a reasonable time for the supply of W Band radios had
elapsed by, at the latest, the date of trial; alternatively, 31 January 2020 (the due date for
final payment of the equipment); or 6 May 2020 (the date upon which the Amended
Statement of Claim was filed). In the case of E Band radios, the plaintiffs submitted that
a reasonable time for their supply had elapsed by any of the above dates or, at the earliest,
30 November 2019.
[342] Relying on, inter alia, Maynard v Goode (1926) 37 CLR 529 at 538 – 539, the plaintiffs
submitted that estimates given about when the radios would be delivered; or what was
-- 92 of 136 --
93
foreseeable; or what the parties contemplated; were relevant to a court’s assessment of
reasonable time.
[343] The plaintiffs submitted that I should therefore assess reasonable time by reference to the
various estimates for delivery given by Dr Baines or Mr White which included estimates
that E Band radio would be delivered as soon as 1 July 2019, and W Band radio as soon
as 30 September 2019. They also included more conservative estimates that E Band
radios would be shipped by mid-October and W Band units would be “on their way” from
early November.
[344] The plaintiffs submitted that I ought to place significant weight upon these estimates. Dr
Baines admitted that his estimates were carefully considered ones – formulated after
consultation with EMClarity’s engineers. And EMClarity had contemporary experience
of LMDS radio development and was therefore in a position to give reliable estimates.
[345] In support of their 31 January 2020 date, the plaintiffs relied upon Dr Baines’ evidence
that EMClarity’s usual practice was to require final payment upon delivery and that the
31 January 2020 was selected because it was anticipated that delivery would be completed
by that date.
[346] The plaintiffs submitted that the following considerations were irrelevant –
the facts known to the defendant (the party in breach) but not disclosed to the
plaintiff which would impact upon their ability to perform the contract;
the defendant’s decision to prioritise other work; and
the impossibility or impracticability of supplying the products which the contract
obliged the defendant to supply.
Defendant’s submissions
[347] The defendant submitted that EMClarity’s estimates were of little use: they were too
optimistic and unguarded. Further, the plaintiff had not established a basis for using them
in the calculation of a reasonable time – including because the assumptions upon which
the estimates were based had not been identified, or proved. The plaintiffs were inviting
me to guess.30
[348] Relying on Hart v MacDonald (1910) 10 CLR 417, the defendant submitted that, if the
plaintiffs wished to rely upon estimates, then they had to prove that the assumptions upon
which the estimates were based persisted at the relevant time. That had not been done;
30 It argued also that clause 1.5 of the WBRDAT did not permit the estimates to be used in the calculation of a
reasonable time. For reasons I have already given, this clause of the WBRDAT is irrelevant to the reasonable
time question.
-- 93 of 136 --
94
therefore the estimates were not available to assist the plaintiff and there was little other
evidence upon which the court could base its calculation of reasonable time.
[349] Further, the defendant submitted, a reasonable time had not yet elapsed having regard to–
the ongoing nature of the Quality Review;
the unavailability of parts/supplier delays; and
the risks associated with the development of new technology which were
disclosed to the plaintiff.
Discussion
[350] What is “reasonable time” is a question of fact, the answer to which depends upon the
circumstances including the context in which the contract was made (Hick v Raymond &
Reid [1893] AC 22).
[351] The relevant considerations which govern the reasonableness of the time taken must be
determined as at the date of the contract (per Connolly J held in Telina Developments Pty
Ltd v Stay Enterprises Pty Ltd [1984] 2 Qd R 585, cited by Fraser JA in Sequel Drill &
Blast P/L v Whitsunday Crushers P/L [2009] QCA 218 at [17]).
[352] What is reasonable will fall to be assessed by reference to circumstances as at the date on
which the obligation to be performed falls, viewed in context of the contract as a whole
(Byrne v Australian Airlines Ltd (1995) 185 CLR 410 at 450). But a party is not entitled
to justify its delay by relying upon the materialisation of a risk which that party was
contractually obliged to bear (Sequel Drill & Blast at [17]). And the circumstances which
are relevant in determining a reasonable time do not include those which were under the
control of the party performing the services (Sequel Drill & Blast at [17]).
[353] The limit of a reasonable time is determined by reference to what is fair to both parties
(Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537 at 567-8). A relevant fact
is delay by the party complaining about the lapse of time (Laurinda Pty Ltd v Capalaba
Park Shopping Centre Pty Ltd (1988 – 1989) 166 CLR 623 at 638-9).31
Practical guidance from the authorities
[354] Hick v Raymond & Reid and Maynard v Goode are worth considering in further detail for
the practical guidance they provide about a court’s approach to this issue.
31 From the extract of the reasons of the primary judge in Questband P/L v Macquarie Bank Limited [2009] QCA
266, referred to by Fraser JA at [32].
-- 94 of 136 --
95
[355] In Hick v Raymond & Reid, Hick’s ship was chartered by the respondents to transport
grain from a certain European port to London. In London, the respondents were obliged
to unload the grain (that is to “discharge the cargo”). Because the bill of lading did not
specify the time within which the discharge was to be completed, the respondents were
obliged to discharge the cargo within a reasonable time.
[356] The ship arrived in London on 14 August 1889. Unloading began on 16 August and
proceeded with “due despatch” until 20 August 1889, when the labourers unloading the
grain went on strike. Their strike lasted until 16 September 1889. Unloading was
completed on 18 September 1889. Were it not for the strike, the cargo would have been
discharged within six days. The appellant sued the respondents for wrongful detention
of his ship for an unreasonable time.
[357] At first instance, the respondents were held to have failed to discharge the ship within a
time that was reasonable “under ordinary circumstances”, and judgment was entered
against them. That decision was reversed on appeal by the Court of Appeal. The decision
of the Court of Appeal was affirmed by the House of Lords.
[358] Lord Herschell LC at 28-30 said that the answer to the question whether the appellant had
proven that a reasonable time had been exceeded was dependent upon what was
reasonable under the existing circumstances, as long as any extraordinary circumstances
were not the respondent’s fault (my emphasis) –
The respondents … contend that the question is not what time would have
been necessary or what time would have been reasonable under ordinary
circumstances, but what time was reasonable under existing
circumstances, assuming that, in so far as the existing circumstances
were extraordinary, they were not due to any act or default on the part
of the respondents.
… I would observe, in the first place, that there is of course no such thing as
a reasonable time in the abstract. It must always depend upon circumstances.
Upon “the ordinary circumstances” say the learned counsel for the appellant.
But what may without impropriety be termed the ordinary circumstances
differ in particular ports at particular times of the year. As regards the
practicability of discharging a vessel they may differ in summer and winter.
Again, weather increasing the difficulty of, though not preventing, the
discharge of a vessel may continue for so long a period that it may justly be
termed extraordinary. Could it be contended that in so far as it lasted beyond
the ordinary period the delay caused by it was to be excluded in determining
whether the cargo had been discharged within a reasonable time. It appears
to me that the appellant’s contention would involve constant difficulty and
dispute, and that the only sound principle is that the “reasonable time”
should depend on the circumstances which actually exist. If the cargo has
been taken with all reasonable despatch under those circumstances I think the
obligation of the consignee has been fulfilled. When I say the circumstances
which actually exist, I, of course, imply that those circumstances, in so far as
-- 95 of 136 --
96
they involve delay, have not been caused or contributed to by the consignee
…
[359] In Maynard v Goode, a question for the court was whether repudiation, on the basis that
a transfer of land had not happened within a reasonable time, was lawful.
[360] Goode entered into a contract to sell a block of land to A, with possession to be given on
“on or before” 7 March 1924. On 1 February 1924, Goode entered into a contract to buy
a block of land from C on the condition that the transfer of his block to A “[went] through
in reasonable time”. C repudiated his contract with Goode and, on 11 February 1924, he
agreed to sell his block of land to M.
[361] There were some issues with the transfer of Goode’s land to A and it was not successfully
registered until 22 July 1924.
[362] On 19 May 1924, Goode successfully sued C for specific performance of the contract of
1 February 1924. That decision was affirmed.
[363] At 538 – 539, Isaacs J explained why the primary judge was correct in concluding that
the transfer had gone through in reasonable time. I note his Honour’s emphasis on the
knowledge of the parties at the date of the contract (footnotes omitted, my emphasis) –
The … only question … is whether the stipulation was fulfilled. The learned
primary Judge held that it was fulfilled. I agree with him. The question of
what is “reasonable time” is always relative; that is, it means “a
reasonable time under the circumstances” (Postlethwaite v Freeland and
Hick v Raymond) … Construction of the contract is not affected by
circumstances subsequent, but only by those which are contemporaneous
with its creation. What, then, were those circumstances here? … [They
included that] [t]he transfer of the purchaser’s block, though the terms of
Goode’s contract were not disclosed to C and are not fully disclosed now, was
necessarily subject to the requirements of [relevant legislation]. Both
parties, therefore, knew that official procedure was necessary with,
possible, unexpected delay. They must have contemplated that delivery of
possession might take place before the purchaser’s block was transferred in
law. Possession was to be given “on or before the seventh day of March
1924”. Looking, for this purpose, at the position of the parties as they
reciprocally stood on 1st February 1924, the date of the contract, the words
“in reasonable time” should be interpreted as meaning within such time as
might enable the purchaser with ordinary despatch to comply with any
possible requirements of the law and administration of the [relevant
legislation], but not such delay as to cause or threaten prejudice to the
position of the vendor under the contract. The transfer was actually
registered on 18th June 1924. The circumstances establish a bona fide
endeavour to get it through much earlier, but the exigencies of law and official
requirements brought the matter down to the date mentioned. The position of
-- 96 of 136 --
97
the vendor was not actually or potentially affected by the lapse of time, and
the stipulation should therefore be held … to have been substantially
performed. It follows that at no time could the vendor lawfully repudiate.
Applying that practical guidance
[364] Approaching Issue 5 in a similar way, on the basis of the correspondence and
communications between Dr Baines and Mr McGowan, I find that when the 2019
Agreements were formed, the parties knew that BSO wished to have product “in the field”
relatively quickly. The parties knew that the W Band and E Band radios had to be built,
and that that would take some time. And I infer, on the basis of their knowledge of the
industry, and common sense, that they knew there might be delays in the supply of
component parts for the builds of the W Band and E Band radios, adding to the build
time.
[365] The correspondence between Dr Baines and Mr McGowan revealed that they knew that
there was a need for “development” of W Band radios (but not the 16QAM E Band radios)
before they could be built. I infer, from their knowledge of the industry, and common
sense, that they contemplated that the speed of development might be affected by issues
encountered during the development process. However, consistently with my Issue 2
conclusions, I do not find that the parties contemplated the possibility of unsuccessful
development in the formation of the 2019 Agreements. EMClarity was obliged to carry
the risk of unsuccessful development of the W Band radios.
Meaning of delivery of the radios within a reasonable time in the circumstances of this
case
[366] Guided by the approach of the authorities above, delivery of the radios within a reasonable
time in this case means delivery within such time as would allow EMClarity to build the
radios “with ordinary despatch”, allowing for reasonable delays in the supply of
components and, in the case of the W Band radios, reasonable delay in its development,
but not such delay in the time taken to develop or build it as to prejudice the position of
Apsara as the owner of the “new” network which BSO wished to have in the field.
[367] That invites the question “what is ‘ordinary despatch?’”. In this context, the estimates
given by Dr Baines and Mr White are relevant.
The use of estimates
[368] The defendant relied upon Hart v MacDonald for its submission that I could not rely upon
the estimates because the assumptions which underpinned them were not established, nor
was it established that those assumptions held true at the time by which reasonable time
was said to have elapsed.
[369] It is worth considering Hart v MacDonald in detail. MacDonald entered into a contract
to build a dairy plant and butter factory on Hart’s land. The plant was to be paid for by
-- 97 of 136 --
98
the proceeds of sale of the defendant’s cows’ butter. After the contract was made, the
land suffered drought. There was insufficient feed for the cows and they were unable to
produce butter, or enough butter, to pay for the plant. MacDonald sued to recover the
cost of the plant. On the conditions existing at the date of the contract, a reasonable time
had elapsed for the production of enough butter to pay for the plant. MacDonald was
successful at first instance and that decision was affirmed on intermediate appeal. It was
reversed in the High Court because the plaintiff had failed to discharge his onus of proof
that a reasonable time had elapsed for Hart to fulfil her promise to pay for the plant. The
relatively lengthy extracts from the judgments which follow illustrate the court’s
approach to the question of whether a reasonable time has lapsed and emphasise the
importance of the onus.
[370] At page 421 – 426, Griffith CJ said (my emphasis) –
It was a condition precedent of the plaintiff’s right to recover that a reasonable
time should have elapsed to enable the defendant [Hart] to produce butter
from the proceeds of which payment could be made for the plant, and on this
issue the onus of proof was on the plaintiff. The question whether it had or
had not elapsed was a question of fact depending on the particular
circumstances of the case. In the case of some contracts mere lapse of time
might be sufficient proof. The circumstances of each case must be
considered. The material circumstances in this case were that the
defendant intended to embark upon the enterprise of dairying in a part of
New South Wales which is subject to droughts. It was in the contemplation
of both parties when the contract was entered into that dairying should be
carried on by means of the natural grasses. Different considerations might
apply to a contract couched in similar terms with reference to a well watered
part of England. The material conditions which actually prevailed are
another element to be regarded in determining whether a reasonable
time had elapsed for the fulfilment of the contract. The burden being
upon the plaintiff to prove what these conditions were, he endeavoured
to discharge it. The only oral evidence which he offered relevant to this
point was of a conversation that took place between a witness for the plaintiff
called Anderson and the defendant and her husband before the contract was
made. At this conversation Anderson said that he thought that a pound of
butter per cow per day would be a fair average yield, and that his estimate
would be twelve and a quarter boxes per week for 100 cows. Hart said,
turning to the defendant (sic), “you can safely make it fourteen boxes.”
Anderson said: “On that basis they could have paid for the plant in 8 to 9
months.” That is said to be some evidence that 8 or 9 months would have
been a reasonable time for payment. Very likely it was, if that was all that
had to be considered. But that assumed an average season. It is suggested
by the plaintiff that an ordinary good season should be assumed to have
continued unless the contrary is shown, but I am not sure that that is so. The
plaintiff also tendered a batch of correspondence that passed between the
parties, from which it appeared that the defendant had continually informed
the plaintiff that in consequence of drought it had been impossible to do any
-- 98 of 136 --
99
dairying, and that there was not sufficient natural feed to allow the cows to
produce milk, and that the plaintiff never disputed the truth of these
statements. This correspondence continued up to a week or two before the
action was brought …
…
[At first instance] [t]he defendant … adduced evidence the effect of which, if
believed, was to show conclusively that under the actual conditions it was
quite impossible to start a dairy except by adopting extraordinary measures
which were never in the contemplation of the parties to the contract. Upon
the plaintiff’s own evidence, then, which was strongly corroborated by
evidence for the defence, it appears that at the date of commencing the action
a reasonable time for payment had not elapsed ...
[371] At 428, O’Connor J, agreeing with Griffith CJ, said (my emphasis) –
It may be conceded that it is physically possible to carry out dairying, so long
as it is physically possible to obtain feed for the cows … [T]he contract must
be construed with reference to the circumstances and conditions in the
contemplation of the parties at the time they enter into it. Here both
parties were dealing with one another on the basis of what would be the
method adopted of producing butter by an ordinarily competent farmer in that
part of the country, and it was stipulated that the machinery should be paid
for out of the butter so produced. One necessary foundation for a contract of
that kind is that the country is in such a condition as to produce sufficient
grass for dairying to be carried on in the ordinary way, by using the natural
growth of grass. If after the dairy began working a dry time came, there
might be imposed on the defendant an obligation to make some special
effort to keep things going. But the obligation to start the dairy must be
based on the assumption that the country is in such a condition that an
ordinarily prudent man would be justified in starting the dairy with some
reasonable prospects of producing marketable butter on a business footing. It
is clear that the onus was upon the plaintiff to prove the contract and that a
breach had been committed by the defendant. The breach alleged was that
under the circumstances then existing the defendant did not commence and
carry on the business of dairying. But she was not bound to commence and
carry on the dairy unless under the conditions then existing dairying could be
reasonably carried on. In order, therefore, to establish a breach the plaintiff
was bound to prove that conditions existed under which dairying could
reasonably be carried on. It may be that mere prima facie evidence of that
fact would change the onus, and cast upon the defendant the burden of
excusing herself, but in order to constitute a prima facie case the plaintiff
must give some evidence to show that the defendant in not staring the dairy
has acted unreasonably.
-- 99 of 136 --
100
[372] His Honour found that on the evidence, it would have been unreasonable to expect the
defendant to start the dairy or attempt to carry it on under the conditions then existing.
[373] Isaacs J said (at 431 – 432) –
… a writing dealing with a matter of business must be considered in a
“reasonable and business manner” …
Thus reading the present agreement, it is plain the parties meant that there
should not be an immediate out-and-out sale for a price instantly payable, but
that the plant itself should assist the purchaser to pay for it. The factory was
to be started, butter was to be manufactured from milk produced by the
purchaser’s cows and the proceeds were to be appropriated to pay for the
plant.
No doubt that necessarily involved an undertaking – on the principle stated
above – that the purchaser would commence factory operations – but when
and in what circumstances?
The fact that she was not expected to pay for the machine independently of
the proceeds of the butter of course negatives any assumption that she was to
do so in circumstances of drought, when no sane dairy farmer would think of
operating. Consequently the reasonable time which the law interweaves into
such an agreement necessitates an inquiry as to whether, after the erection of
the plant, natural conditions were such as would not merely sustain the
appellant’s cows alive but enable them to produce milk. The necessity of
establishing that fact must be borne in mind throughout. Of course, the
respondent cannot prove the breach alleged without establishing that fact by
some means …
[374] His Honour considered that the evidence led was to the effect that under favourable
conditions, the plant would be paid for in eight to nine months. But that did not satisfy
the onus which rested upon the respondent. In other words, the respondent was bound to
show that those favourable conditions came into being. Substantially, the evidence led
was against him.
[375] I find the estimates given by Dr Baines and Mr White reliable and considered ones. I
infer that they were based on assumptions about “ordinary” development/build times and
“ordinary” supplier delays.
[376] I am prepared to proceed on the basis that the starting points for the calculation of a
reasonable time for the delivery of the E Band and W Band radios, assuming “ordinary”
“conditions”, are the most conservative estimates given – that is, the date for the payment
of the balance of the invoices, 31 January 2020.
[377] In my view, EMClarity acted with “reasonable despatch” in the months immediately after
the 2019 Agreements were made, until it was acquired by McKay Brothers. Until its
acquisition, EMClarity was reasonable in its attempts to develop the W Band radio (with
-- 100 of 136 --
101
a view to building first a prototype and then the others required for the network) and in
building the E Band radios.
[378] EMClarity disclosed no issues with the development of W Band radios which impacted
upon the build and therefore there could be no postponement of the date upon which
reasonable time would elapse for that reason.
[379] EMClarity’s internal correspondence of 20 September 2019, conveyed that it was aiming
for delivery of the W Band radios by January 2020. However, emails a few days earlier
between Mr Dench and [redacted] established that a certain part would not be shipped
until 16 December 2019. This meant that the radios could not be delivered by 31 January
2020.
[380] I am prepared to proceed on the basis that there was an extraordinary delay in the delivery
of these components, for reasons outside EMClarity’s control, and that EMClarity acted,
at least at this point, with reasonable despatch in response to this supplier delay (even
though they did not cancel that order and seek out another supplier). I am therefore
prepared to proceed on the basis that this supplier delay postponed the date upon which a
reasonable time for delivery would have elapsed beyond 31 January 2020. But, on the
evidence, it is impossible for me to nominate a date in the future, at which a reasonable
time for delivery would elapse, in any reasoned way.
[381] Reasonable inferences about timing, which might have been available to me based on the
date upon which components were actually delivered, are not available because the
defendant cancelled its orders for relevant components. No other evidence was called on
this issue. Nor does the evidence assist me with alternatives to the suppliers originally
engaged.
Conclusion
[382] It is tempting to conclude that a reasonable time for delivery had elapsed by the date of
trial, but I am concerned that to so conclude would involve some speculation on my part.
[383] However, as will appear below, in my view, after EMClarity was acquired by McKay
Brothers, it clearly manifested an intention to repudiate the 2019 Agreements.
Issue 6: Did EMClarity breach the implied term by failing to supply the E Band
and W Band radios within a “reasonable time” being by October 2019, or
alternatively 31 January 2020, 6 May 2020 or at the latest the date of the trial?
[384] I am unable to answer the question whether EMClarity failed to deliver the radios within
a reasonable time because on the evidence I am unable to identify the date upon which a
reasonable time for supply would have elapsed without speculating.
Issue 7: Was a Quality Review in the terms instituted by EMClarity permitted by
the terms of the 2019 Agreements or the WBRDAT?
-- 101 of 136 --
102
[385] No. The 2019 Agreements were straightforward agreements to supply equipment on
certain terms within a reasonable period of time. A Quality Review was not permitted by
the 2019 Agreements.
[386] In my view, the WBRDAT was terminated and superseded by the 2019 Agreements.
There is therefore no need for me to consider whether a Quality Review was permitted
by the WBRDAT.
Issue 8: Was the Quality Review a genuine and/or necessary review of the E Band
or W Band products? Or was it a “go-slow” in order to prioritise the interest of
McKay Brothers/disadvantage the plaintiffs?
[387] The plaintiffs acknowledge that it is not necessary for me to make a finding about the
genuineness or necessity of the Quality Review to find that EMClarity repudiated the
2019 Agreements. However, the plaintiffs seek such a finding on the basis that it would
–
demonstrate the reasonableness of the beliefs held by the plaintiffs regarding
EMClarity’s apprehended breaches; and
provide a further basis upon which I might find that EMClarity repudiated the
2019 Agreements.
Plaintiffs’ submissions
[388] The plaintiffs submitted that I should infer that the Quality Review was a sham, designed
to slow down the development and production of the plaintiffs’ radios, to achieve for
McKay Brothers a competitive advantage. They submitted that that inference was
available on the basis of certain facts including (but not only) that –
before 8 October 2019, there was no indication that there were any issues with
either the E Band or the W Band radios other than minor ones which were
resolved;
before the takeover, EMClarity had never considered a Quality Review and Dr
Baines agreed that ceasing the production of radios for an indeterminate period of
time for any type of quality review would be “commercial suicide”;
Dr Baines was not consulted about the Quality Review – rather he was required to
implement it by the directors of McKay Brothers who were on EMClarity’s board;
Mr Boyle did not say that McKay Brothers acquired EMClarity because it was a
profitable business in its own right. The main driver for the acquisition of
EMClarity by McKay Brothers was “to make sure EMClarity focused on and gave
complete priority to the LMDS radios”, implying that it was not invested in the
quality of radios for other EMClarity customers;
-- 102 of 136 --
103
the Quality Review was in reality only a review of the LMDS product. The
evidence was to the effect that the “EMClarity Advisory Committee” resolved to
prioritise the review of the McKay Brothers’ LMDS radios. Dr Baines’ notes
indicated that the W Band radios were not considered a priority at all;
it was made clear to Dr Baines that he was under no pressure to accelerate, or
work on the radios the subject of, the 2019 Agreements;
McKay Brothers’ did not produce any documents which identified the reasons for
the implementation of the Quality Review, its conduct, management and progress,
or status. The plaintiffs asked me to infer (for reasons which I will not detail) that
McKay Brothers was aware of the existence of relevant documents, but chose to
withhold them because they would not assist its case.
[389] The plaintiffs asked me to draw a similar conclusion about the absence of evidence of the
ongoing nature of the Quality Review. They observed that no minutes of the Advisory
Committee’s meetings had been tendered. All that was tendered were Dr Baines’ notes
of October 2019, November 2019 and February 2020. Dr Baines’ evidence was that the
central document for recording the progress of the Quality Review was a document called
the “Quality Issues Register”. However, that document shows that issues were only
populated in the register from the end of November 2019 – after the commencement of
the proceedings. The Quality Review Team updated the document until the end of
January 2020 but it had not been updated since 28 January 2020.
[390] Also, on 5 December 2019, well after the proceedings had been commenced, and after
BSO filed its statement of claim, Dr Baines sent an email to the Quality Review Team
which said –
…In the issues tracker can we please ensure that any issues that relate to W-
band are explicitly tagged as such. This most likely will apply to issues in
common across shared modules, say for instance modem boards, because as
yet there is no data from testing W-band in either the lab or the field. Let’s
make it clear and explicit which product families each issue applies to in our
documents and records.
I am sure you can work out why I am making this request.
…
[391] That email revealed, according to the plaintiffs, a desire to generate “evidence” of the
genuineness of the Quality Review.
[392] Further, there was an absence of evidence that the Quality Review had been imposed
indiscriminately on all of EMClarity’s customers.
[393] Finally, the plaintiffs submitted that EMClarity failed to call a number of critical
witnesses in connection with the Quality Review and a “Jones v Dunkel inference” could
be therefore drawn against the defendant.
-- 103 of 136 --
104
Defendant’s submissions
[394] The defendant submitted that the plaintiffs’ arguments overlooked a body of objective
evidence which showed that the Quality Review was being undertaken at a cost to
EMClarity, in that it was not selling radios. I interrupt here to note that whilst the Quality
Review and the pause on shipments obviously came at a cost to EMClarity, that fact was
unlikely to have been lost on EMClarity’s directors. Indeed, Mr Boyle admitted that he
was aware of the risk of litigation over the decision to pause shipments. It is reasonable
to infer that the decision to pause shipments was expected to yield a greater benefit to
EMClarity/McKay Brothers than its cost.
[395] The defendant submitted that the problems with the LMDS and W Band radios were real.
[396] It emphasised that the suggestion that the Quality Review was a sham was not put to any
witness. It made other arguments to rebut the suggestion that I ought to draw Jones v
Dunkel inferences against it, which I will not detail here, but which listed the matters
about which Dr Baines and Mr Boyle had not been cross-examined.
Discussion and conclusion
[397] I am not prepared to make a finding in this case which is unnecessary.
[398] And even if a finding were necessary, I would have found it difficult to make one because
I was not assisted by cross-examination which explicitly put the plaintiffs’ case.32
Sometimes, it got close. For example, Queen’s Counsel for the plaintiff referred Dr
Baines to his email of 5 December 2019. Dr Baines agreed that the reason he was making
the request to explicitly tag W Band issues was because he wanted issues with W Band
radios to be documented. He could not recall “exactly” whether the McKay Brothers’
directors on EMClarity’s board told him to do so. He couldn’t say that it was true that,
prior to the litigation commencing, EMClarity had not been generating lists of W Band
radio defects.
[399] He was then asked the following question and gave the following answer –
The reason you were doing it was because you wanted to have some
documents that you could point to to say that there were issues with W Band
radios. That’s right, isn’t it? --- To make it clear, yes. I mean we understood
internally, because of commonality in modules, that it’s likely a certain issue
would apply to W Band in the same way it applied to, say, LMDS or E Band.
[400] However, it was not suggested to Dr Baines that he had made the request so that there
would be a note of a problem with W Band which could be relied upon in this litigation
as false evidence of a genuine quality review of W Band radios. Nor was it expressly put
32 I have borne in mind of course the need to ensure that the rule in Browne v Dunn is not misapplied cf Curwen
and Others v Vanbreck Pty Ltd (2009) 26 VR 335.
-- 104 of 136 --
105
to Dr Baines that the Quality Review was a sham. I therefore do not have the benefit of
his answer to those sorts of questions.
[401] The plaintiffs submitted, in effect, that it was suspicious that Dr Baines was not consulted
about the Quality Review. If, by “consulted”, the plaintiffs meant that his views about it
were not sought before the decision to implement it was made, then it is probably right
that his views were not sought.
[402] Dr Meade and Dr Tyc spoke with Dr Baines about the possibility of a “fulsome” review
of EMClarity’s design and manufacturing processes during his meeting with them on 2
October 2019. But Dr Baines was told at the same meeting that Dr Meade and Dr Tyc
were of the view that the right thing to do was to pause production and conduct a
comprehensive review of EMClarity’s products and processes and asked to implement it.
[403] It is clear from Dr Baines’ affidavit that the scope of the review was influenced by Dr
Meade and Dr Tyc. The motivation for the Quality Review included McKay Brothers’
issues with its LMDS radios and other customers’ issues with E Band radios. It was not
prompted by concerns about the W Band radio in development. And there was no
implementation of the plan, stated in November 2019, to build W Band prototypes for the
purposes of their submission to the Quality Review.
[404] I note the report to the EMClarity Board date 15 January 2020. Some of the report has
been redacted. But I assume it relates to LMDS and E Band radios. The report suggests
a genuine need for a Quality Review of those radios. It states that: 31 of the 36 links
shipped between July 2018 and October 2019 had been returned for repairs; and the E
Band failure rate had been approximately 60 per cent. The report identifies pervasive
issues, from design to quality control of the components.
[405] It is however a surprise that the Quality Issues Register has not been updated since the
end of January 2020. It is also a surprise that there are no minutes of the meetings of the
Quality Review Advisory Committee.
[406] I do not accept Mr Boyle’s evidence that it “did entertain” the “mind” of the EMClarity
board to have a conversation with Apsara about the way in which their radios could be
supplied in the near future (after the “pause” on shipping). Mr Boyle’s suggestion that
the board did not have a chance to discuss matters with Apsara because litigation was
commenced is unpersuasive. There was nothing stopping the board from discussing the
Quality Review with Apsara before it was implemented – especially if the board
genuinely believed it was in Apsara’s interests. Mr Boyle said that he appreciated the
risk of litigation ensuing upon the implementation of the Quality Review. Litigation
might have been staved off by discussions with Apsara beforehand. If anything, the
commencement of litigation might have been expected to motivate EMClarity to discuss
matters with Apsara (through their lawyers).
[407] It is of concern that EMClarity has not informed Apsara about the progress of the Quality
Review or its expected timetable. Dr Baines’ notes of the meeting of the Quality Review
-- 105 of 136 --
106
Advisory Committee on 29 October 2019 list W Band radios as the third priority of the
review and include the following question –
Tell BSO will be > one year?
But BSO were not told anything.
[408] I reject Mr Boyle’s evidence to the effect that McKay Brothers/EMClarity did not
appreciate that ceasing production of Apsara’s radios would generate an “obvious
commercial advantage” to McKay Brothers. The advantage was obvious. I reject his
evidence that he did not accept that any delay in the rollout of Apsara’s new network
would advantage McKay Brothers. The advantage was obvious. I reject his evidence
that it was never made clear to Dr Baines to give priority to the LMDS radio during the
Quality Review. Dr Baines’ notes of 29 October 2019 (see below) makes the priority
obvious.
[409] Sham or not – it is clear that the Quality Review delivered an advantage to McKay
Brothers.
Issue 9: By subjecting the order of W Band and E Band radios to the Quality
Review, and/or delaying the development and shipment of the order, did
EMClarity breach the terms of the Supply Agreements or the WBRDAT?
[410] This issue relates to the plaintiffs’ arguments that Apsara was entitled to terminate the
2019 Agreements because –
EMClarity had breached the condition that the radios (and other equipment) the
subject of the 2019 Agreements would be supplied within a reasonable time;
or
if the implied term was not a condition, EMClarity’s conduct was otherwise
repudiatory because it amounted to a sufficiently serious breach of an innominate
term as to give rise to Apsara’s right to terminate the 2019 Agreements
[411] In my view, the evidence falls more easily into a repudiation narrative, rather than an
actual breach narrative. Indeed, in my view, EMClarity’s repudiatory conduct is
indisputable. It is not therefore necessary for me to reach a conclusion about Issue 9.
Issue 10: Was EMClarity’s conduct, in subjecting the order of W Band and E
Band radios to the Quality Review, and/or delaying the development and shipment
of the order a repudiation of the 2019 Agreements or the WBRDAT?
Plaintiffs’ submissions
-- 106 of 136 --
107
[412] The plaintiffs submitted that EMClarity clearly repudiated the 2019 Agreements by
implementing the Quality Review, ceasing development of the W Band prototype,
pausing all shipping and cancelling orders for relevant components. This conduct easily
met the description of repudiatory conduct spelt out in the authorities. It was conduct
which, as per Koompahtoo Local Aboriginal Council v Sanpine Pty Ltd (2007) 233 CLR
115 –
evinced EMClarity’s unwillingness to perform its obligations under the 2019
Agreements; or
evinced EMClarity’s intention to fulfil its obligations under the 2019 Agreements
only in a way that was substantially inconsistent with those obligations.
[413] Alternatively, the totality of EMClarity’s conduct evinced a clear intention to carry out
its obligations under the 2019 Agreements only if and when it suited EMClarity.
[414] Either way, the plaintiffs submitted, the conduct fell clearly within the conduct described
as repudiatory in the following statements of principle in Laurinda, at 658 – 659, per
Deane and Dawson JJ; and Gold Coast Oil Co Pty Ltd v Lee Properties Pty Ltd [1985] 1
Qd R 416, at 420, per Connolly J, with whom Thomas and Derrington JJ agreed.
[415] In Laurinda, their Honours said (my emphasis) –
It is not necessary for repudiation of a contract that the repudiator make plain
that he will never perform his contractual obligations at all. What Lord
Dunedin described as an assumption of ‘a shilly-shallying attitude in regard
to the contract’ and what Lord Shaw of Dunfermline called ‘procrastination
… persistently practiced’ can, in some circumstances, reach the stage of
repudiation even though accompanied by assurances of ultimate performance
at some future time … ‘the question whether the stage has been reached when
procrastination or non-performance’ constitutes repudiation is essentially one
of fact. That question will, as has been said, only be properly answered
in the affirmative when procrastination or non-performance has marked
the stage of conveying to a reasonable person, in the situation of the other
party, repudiation or disavowal either of the contract as a whole or of a
fundamental obligation under it.
[416] In Gold Coast Oil, his Honour said (my emphasis) –
… the situation is altogether otherwise where the other party has evinced an
intention not to be bound by the contract. This intention is to be judged from
the acts of the party and is made out where a reasonable man would infer that
that party does not intend to take the contract seriously and that he is
prepared to carry out his part of the contract only if and when or, as I have
recently had occasion to say, if and as it suits him. When such an intention
is shown the innocent party is entitled to rescind …
-- 107 of 136 --
108
[417] In oral submissions, counsel for the plaintiffs clarified that their arguments about
repudiation did not change whether the Quality Review was genuine or not, but that all
that had occurred by the time of trial was a review of the LMDS radios – rather than a
review of all of EMClarity’s radio products and products in development. Further,
internal documents indicated that there was “no hurry” with a review of W Band products.
Defendant’s submissions
[418] The defendant submitted that repudiation was a serious matter and not something to be
lightly found or inferred, relying on, inter alia, Laurinda at 643 (per Brennan J) and 657
(per Deane and Dawson JJ).
[419] The defendant framed the repudiation question in this case as follows: whether a
reasonable business person in the position of the plaintiffs would conclude that EMClarity
had, by undertaking the Quality Review or otherwise not delivering radios, placed itself
in a position where it did not intend to, or was not able to, perform its obligations under
the relevant contracts.
[420] The defendant’s detailed arguments boiled down to the following –
The plaintiffs’ repudiation claim fell to be determined on the basis of the general
allegation that there had been sufficient delay as to allow the court to conclude that
there had been repudiation.
Such a conclusion was rare in the case of a contract in which time was not of the
essence (relying on Neeta (Epping) Pty Ltd v Phillips (1974) 131 CLR 286 at 302).
Where time is not of the essence, and where the party said to be in breach by delay
is nevertheless making an effort to perform the contract, it is intrinsically difficult
for the other party to establish a fundamental breach (relying on Shawton
Engineering v DGP International [2006] BLR 1 at [32] per May LJ).
The gross and protracted delay necessary to establish repudiation had not been
made out because the plaintiffs failed to prove that a reasonable time had expired
or that the Quality Review was not genuine or necessary or otherwise.
“… [I]f considerable work has been done in performance of a party’s contractual
obligation and what is alleged to amount to a repudiation is not a flat refusal to
perform, but an indication of an intention to continue to perform at a speed
considered by the other party to be unreasonably slow, it may be very difficult to
conclude that in those circumstances what is being offered will deprive the other
party of substantially the whole benefit of the contract”: Astea (UK) v Time Group
[2003] EWHC 725 at [151] per Seymour QC.
Plaintiffs’ reply
-- 108 of 136 --
109
[421] In reply, the plaintiffs submitted that I was not simply dealing with slow progress, I was
dealing with no progress. There had been a total cessation of development of the W Band
radios and the shipping of any product, and prioritisation of a competitor’s radios. Dr
Baines’ evidence went only as high as saying that the work presently being done during
the Quality Review might benefit future projects. At the least, there was evidence of
EMClarity’s “shilly-shallying” approach to its obligations. Further, there had been
repudiation of the WBRDAT because of the cessation of development.
Discussion and conclusion
[422] The internal documents to which the plaintiffs referred included notes made by Dr Baines
during an “EMC Advisory Committee” meeting on 29 October 2019. Those notes listed
the Quality Reviews’ priorities as follows –
*Priority 1. LMDS
2. Quality on E-band
3. W-band not at all Q 3, Q 4
next year or later
[423] Dr Baines clarified under cross-examination that the McKay Brothers’ directors on
EMClarity’s board made it clear to him that the priorities were as above.
[424] The evidence revealed that EMClarity said nothing to the plaintiffs about –
the expected duration of the Quality Review, or its progress – despite many
requests for this information;
when the plaintiff might expect the resumption of development/production;
its intention with respect to the components it had ordered; or
its intention with respect to the substantial amount of money already paid by
Apsara.
[425] Mr Boyle admitted that the defendant was aware that the implementation of the Quality
Review might expose it to litigation – yet it did nothing to stave off that risk, including
by discussing the review with BSO/Apsara before it was implemented, providing a
timeframe for it, or keeping BSO/Apsara up to date with its progress.
[426] Nothing in the evidence suggested that the defendant was making any effort to perform
the 2019 Agreements to supply W Band, or for that matter, E Band radios. Development
of a functional W Band prototype has ceased. Apsara’s E Band radios are not being build.
Orders for components have been cancelled. And the review of the W Band product is
not a priority for EMClarity at all.
-- 109 of 136 --
110
[427] Whilst the result of the Quality Review (assuming it is continuing) might ultimately be to
the benefit of the development of W Band radios, that is not its purpose. The instruction
in Dr Baines email of 5 December 2019 is concerning.
[428] The 2019 Agreements were straightforward agreements to supply certain products within
a reasonable period of time. They did not contemplate an indefinite delay in the
development or delivery of products whilst a Quality Review – genuine or otherwise – of
an indefinite duration was undertaken.
[429] Applying the approach contended for by the defendant, I find that the defendant’s conduct
in –
implementing the Quality Review, which contemplates a review of W Band
product as its lowest priority and in respect of which there is no end in sight;
ceasing the development of a W Band prototype;
ordering an indefinite pause on shipments of products; and
cancelling orders for component parts,
viewed objectively, would convey to a reasonable person that EMClarity had repudiated
its obligations under the 2019 Agreements by manifesting an intention to perform them
only if and when it suited EMClarity.
[430] Having earlier found that the WBRDAT was terminated, it is unnecessary for me to
consider whether it was repudiated by the defendant.
Issues 11 – 16: Breaches of confidence - Overview
[431] The plaintiffs’ pleadings and their written submissions about these issues left me a little
confused and almost nothing was said in oral submissions about them.
[432] The WBRDAT contained clauses imposing a contractual duty or obligation of confidence
upon EMClarity in relation to “Confidential Information” as defined in the WBRDAT.
The term “Confidential Information” included “Customer Material”, also defined under
the WBRDAT. By clause 5.9 of the WBRDAT, the contractual obligation of confidence
survived the termination of the WBRDAT.
[433] The plaintiffs plead, in clause 7A of the Amended Statement of Claim, that an equitable
duty of confidence attaches to the W Band project, the terms of the WBRDAT and the
Customer Material particularised in the pleading.
[434] The “W Band project” was defined in the plaintiffs’ Amended Statement of Claim in
these terms –
-- 110 of 136 --
111
Prior to June 2018, the First Plaintiff entered into discussions with the
Defendant to develop new radio equipment utilising the W-band (95GHz),
which was to be deployed into a wireless network of the Plaintiffs’ design.
[435] The W Band Project falls within the definition of “Customer Material” because it was
“material” provided by BSO for the purposes of guiding the terms of the WBRDAT.
[436] The equitable duty of confidence pleaded in paragraph 7A co-exists with the contractual
duty of confidence.
[437] [redacted]
[438] The Alternative Strategy was revealed by the Quote and the Purchase Orders.
[439] In paragraph 30C(c) of the Amended Statement of Claim, the plaintiffs assert that “the
Duty of Confidence owed by the defendant extended to the Alternative Strategy, the
Quote, the Purchase Orders and the W-Band and E Band Supply Agreements”. The Duty
of Confidence that was “extended” was the equitable duty pleaded in paragraph 7A of the
Amended Statement of Claim.
[440] As I understand the plaintiffs’ case, they plead that a contractual and an equitable
obligation of confidence attaches to all of the Material and that both were breached.
[441] They plead, at paragraph 45(a) of the Amended Statement of Claim, that the defendant
breached clause 7 of the WBRDAT in providing information to McKay Brothers which
disclosed “the existence of the W-band Project, the terms of the W-band Development
Agreement, the confidential Customer Material, and further the Alternative Strategy, the
Quote and the Purchase Orders” (my emphasis).
[442] The pleadings thus imply that the contractual duty of confidence under the WBRDAT
attached to the Alternative Strategy, the Quote and the Purchase Orders. But that material
does not obviously fall within the definition of Confidential Information under the
WBRDAT.
[443] At paragraph 45(b), the plaintiffs plead that the defendant breached the equitable duty of
confidence by providing the same information as that recited in paragraph 45(a) to McKay
Brothers.
[444] The plaintiffs asserted three instances of the disclosure of confidential information by
EMClarity to McKay Brothers –
The first by way of EMClarity’s sending an invitation to the W Band Project
meeting to Mr Boyle and the emails between Mr Boyle and Dr Baines which
followed it.
-- 111 of 136 --
112
The second by way of EMClarity providing redacted copies of the WBRDAT, the
Quote and the Purchase Orders to Mr Boyle during McKay Brothers’ due diligence.
The third by way of EMClarity providing un-redacted copies of the WBRDAT, the
Quote and the Purchase Orders to EMClarity’s “McKay Brothers affiliated
directors” – Mr Boyle, Mr Kennard, Dr Meade and Dr Tyc – on 27 September 2019,
after McKay Brothers’ acquisition of EMClarity.
[445] It seems that the plaintiffs’ position is that, in breach of clause 7 of the WBRDAT and
the equitable duty of confidence –
As to the first instance above, EMClarity disclosed to Mr Boyle that it was
developing a W Band radio for BSO; and
As to the second and third instances above, EMClarity disclosed to Mr
Boyle/McKay Brothers that it was developing a W Band radio for BSO and BSO’s
Alternative Strategy.
[446] The defendant’s position is that the contractual obligations of confidence – including the
“carve outs” in clause 7.2 and 7.3 of the WBRDAT – applied, and that its disclosure to
Mr Boyle/McKay Brothers of any of the Material was authorised by the carve outs.
[447] Further, the defendant submitted, any co-existing equitable obligation of confidence was
subject to the same carve outs.
[448] The plaintiffs denied any such constraint on the equitable obligation of confidence.
Issue 11: Were the “W-Band project, the terms of the WBRDAT, the Customer
Material under the WBRDAT, the Alternative Strategy, the Quote and the
Purchase Orders” (together, the “Material”) confidential?
[449] The answer to the question whether “the W Band project, the terms of the WBRDAT and
the Customer Material under the WBRDAT” are “confidential” is simply “yes” in
accordance with the relevant definitions of Confidential Information and Customer
Material in the WBRDAT.
[450] I am also of the view that the Alternative Strategy, revealed by the Quote and Purchase
Orders, is confidential – even though that material does not fall within the definition of
“Customer Material” under the WBRDAT without unnaturally straining the language of
the definition.
[451] The essential attribute of confidential information is “relative secrecy”. Information will
not have the necessary quality of confidence if it is something which is public property
-- 112 of 136 --
113
or public knowledge. The “fairly undemanding”33 “test” from Coco v AN Clarke
(Engineers) Ltd [1969] RPC 41 at 47 – 8, per Megarry J is whether the information –
has the necessary quality of confidence about it; and
has been imparted in circumstances importing an obligation of confidence.
[452] As to communicating the information in circumstances importing an obligation of
confidence, Megarry J said at 47 – 48 (my emphasis) –
However secret and confidential the information, there can be no binding
obligation of confidence if that information is blurted out in public or is
communicated in other circumstances which negative any duty of holding it
confidential. From the authorities cited to me, I have not been able to derive
any very precise idea of what test is to be applied in determining whether the
circumstances import an obligation of confidence … It may be that that hard-
worked creature, the reasonable man, may be pressed into service once more;
for I do not see why he should not labour in equity as well as at law. It seems
to me that if the circumstances are such that any reasonable man standing in
the shoes of the recipient of the information would have realised that upon
reasonable grounds the information was being given to him in confidence,
then this should suffice to impose upon him the equitable obligation of
confidence. In particular, where information of commercial or industrial
value is given on a business-like basis and with some avowed common
object in mind, such as a joint venture or the manufacture of articles by
one party or the other, I would regard the recipient as carrying a heavy
burden if he seeks to repel the contention that he was bound by an
obligation of confidence … I doubt whether equity would intervene unless
the circumstances are of sufficient gravity; equity ought not to be invoked to
protect trivial tittle-tattle, however confidential.
[453] The statements in bold above are apposite here.
[454] In my view, BSO’s [redacted], was commercial information of high value to BSO, which
was not otherwise in the public domain. It was intended as the means by which
BSO/Apsara would gain a competitive edge against their rivals in the NJ Equity Triangle.
Any reasonable person would have appreciated that any edge would be lost were the
alternative phased network rollout not treated as confidential information. The
information was communicated to EMClarity “on a business like basis”: EMClarity was
the entity which BSO would engage to produce or supply the equipment required for the
Alternative Strategy.
33 As per Campbell JA in Del Casale v Artedomus (Aust) Pty Ltd [2007] NSWCA 172 at [103].
-- 113 of 136 --
114
Issue 12: Was the Material disclosed to McKay Brothers?
Invitation to meeting about the W Band Project and following emails – was
confidential information disclosed?
[455] The plaintiffs submitted that there was, in the invitation and the emails which followed
it, sufficient information to disclose the fact that EMClarity was working on a W Band
project for a customer; especially because of Dr Baines’ statement that it was “under
disclosure” which Mr Boyle would have understood as a reference to its being subject to
a non-disclosure agreement with a customer.
[456] The plaintiffs asserted that EMClarity’s customers were “primarily” those in the high
frequency trading market. The plaintiffs submitted that a reasonable person with
knowledge of EMClarity’s customers would conclude that the customer, impliedly
referred to in the emails, was “very likely” to be a competitor of McKay Brothers in the
high frequency trading market space. The plaintiffs did not go so far as to submit that a
reasonable person would have deduced from the invitation and the emails which followed
it that EMClarity was working on a W Band radio for BSO.
[457] The defendant submitted that the definitions of Confidential Information and Customer
Material in the WBRDAT were exhaustive definitions, which meant that not everything
with a remote connection to the WBRDAT or the work being performed under it was
confidential. The fact that EMClarity was working on a W Band project was not a term
of the WBRDAT. Nor was the concept of the W Band confidential – it was a matter of
public record. Further, it was nothing more than speculation to suggest that a reasonable
person would have concluded that the customer was “very likely” a competitor of McKay
Brothers.
[458] In my view, the terms of the WBRDAT would encompass broadly the fact that EMClarity
was developing a W Band radio for BSO (as well as its specific terms). However, I am
not persuaded that anything confidential was disclosed by the sending of the invitation or
in the emails which followed.
[459] While it was careless for EMClarity to send the invitation to Mr Boyle and unprofessional
of Dr Baines to have said anything more about a W Band project to Mr Boyle, I am not
persuaded on the evidence that a reasonable person would have concluded that the
customer to whom Dr Baines referred was “very likely” a competitor of McKay Brothers.
Nor would a reasonable person have concluded that that competitor was BSO.
[460] The relevant evidence about EMClarity’s customers included Dr Baines’ evidence that
EMClarity was a “world leader” in the production of E Band and W Band radios for “high
frequency trading data markets”. But, he said, it also provided those products to “military
and defence forces” and “telecommunication companies”.
[461] Other relevant evidence included the material about EMClarity in the “Plaintiffs’
Additional Tender Documents” bundle. That material refers to EMClarity’s introducing
a product for “ultra-fast financial trading applications” but nothing suggested that this
-- 114 of 136 --
115
product was EMClarity’s dominant product or that it was provided to customers
deploying it in the NJ Equity Triangle only. Indeed, the material claims that EMClarity
supplied ultra-low latency wireless communications to “network operators around the
world”. It also boasts a range of customers from the military, telecommunications,
government and resources sectors.
[462] I am not persuaded on the evidence that EMClarity’s primary work was the production
of radios for the NJ Equity Triangle high frequency trading market – which undermines
the plaintiffs’ argument that Mr Boyle would have assumed the customer to be one of its
competitors.
[463] Even if I were to conclude that EMClarity’s primary business was in the NJ Equity
Triangle, at best for the plaintiffs, EMClarity providing the invitation and the emails to
Mr Boyle might have caused Mr Boyle to speculate that EMClarity was working on a W
Band project for one of its competitors. Mr McGowan thought he was fishing for
information about who the customer was. But I am not persuaded that the information
conveyed by the invitation and the emails following it disclosed that EMClarity was
working on a W Band project for deployment in the NJ Equity Triangle – let alone that it
was working on a project for BSO. I am not persuaded that confidential information was
conveyed via the meeting invitation or the emails which followed.
The redacted material – was confidential information disclosed?
[464] For the purposes of due diligence, EMClarity provided to Mr Boyle –
a redacted the copy of the WBRDAT (redacted by using a black pen to obscure
certain details); and
a redacted, executed copy of the WBRDAT; and
a copy of the Word versions of the Quote and Purchase Orders which omitted
certain information which was contained in the originals.
The redacted copies of the WBRDAT
[465] The plaintiffs submitted that the redactions to the WBRDAT were ineffective: the
obscured details (such as the name of the customer) were still visible through the black
ink. That may be right. But regardless, there was no redaction (or attempt) of Mr
McGowan’s name as the “Customer Representative” in the schedule to the WBRDAT.
Mr Boyle understood that Mr McGowan was associated with BSO and Apsara. The
redactions were not effective to disguise and keep confidential the fact that BSO had
asked EMClarity to develop a W Band radio with certain specifications. Also, the
disclosure of the schedule to the WBRDAT, and the disclosure of the date upon which
the WBRDAT was signed, conveyed the expected timing of the production of W Band
radios. EMClarity disclosed confidential information via the provision of the copies of
the WBRDAT to Mr Boyle.
-- 115 of 136 --
116
The redacted Quote and Purchase Orders
[466] The redacted Quote omitted, inter alia, the name of the customer (“BSO Networks”) and
replaced it with “Customer B”. It omitted the recital that the customer had settled on a
“phased deployment strategy”.
[467] The redacted Quote listed a large amount of equipment. It referred to the “overall project”
and made reference to latency savings. It stated that the prices quoted were in US dollars.
And it nominated the territory (for the purpose of exclusivity) as “New Jersey, Chicago,
Toronto, London, Sydney”.
[468] The four separate redacted Purchase Orders listed the equipment necessary for each
separate phase of the rollout but did not, in terms, reveal that each Purchase Order related
to a separate phase.
[469] EMClarity submitted that the plaintiffs had not established that the provision of the
redacted versions of the Quote and Purchase Orders to McKay Brothers during due
diligence disclosed the Alternative Strategy or sufficient information as to allow McKay
Brothers to deduce the alternative strategy. EMClarity submitted that all that was
disclosed was the fact that orders of a certain quantity of E Band and W Band radios and
associated equipment had been made. The defendant also submitted that whether McKay
Brothers might deduce the alternative strategy from the documents was irrelevant. The
focus was on the nature of the information disclosed, and whether it was confidential.
[470] I found the question whether there had been disclosure of the Alternative Strategy, by
way of the provision of the redacted Quote and Purchase Orders, difficult. The following
email correspondence between Mr Boyle and Dr Baines about the disclosed documents
is also relevant –
(a) Mr Boyle emailed Dr Baines with the subject line “wband” and said:
“is the exclusivity really just a 200K per year again?”
(b) Dr Baines responded: “No, that’s been superseded by the terms in the
Quote document (same folder).”
(c) Mr Boyle said: “Interesting. Seeming then we could sell a 32 QAM w-
band radio that’s otherwise identical. And this would not involve
ROFR or break exclusivity. Same with a 128QAM, or a QPSK w-band
etc. So is that development agreement unexecuted and that exclusivity
language has never been enforceable?”
[471] The reference to “exclusivity” in (a) is a reference to a term of the WBRDAT. As above,
by failing to redact Mr McGowan’s name from the WBRDAT, it was disclosed to Mr
Boyle, and thereby to McKay Brothers, that BSO or Apsara had entered into an agreement
with EMClarity to develop a W Band radio.
[472] EMClarity told Mr Boyle (via (b) above) that the WBRDAT had been “superseded” by
the terms of the Quote.
-- 116 of 136 --
117
[473] On one view, the content of the Quote, and the information that the WBRDAT had been
superseded, conveyed to McKay Brothers that the development of W Band radios for
BSO/Apsara had reached the point where the radios could be built. Also, the volume and
nature of the equipment listed in the Quote and Purchase Orders may have conveyed that
a network utilising W Band and E Band was in contemplation, for deployment in territory
which included New Jersey and Chicago. [redacted]
[474] With some hesitation, I have concluded that, while the provision of the redacted
documents came very close to disclosing the Alternative Strategy, it fell just short of
doing so. However, the Alternative Strategy was later disclosed to the McKay Brothers
affiliated directors of EMClarity.
The un-redacted material – was confidential information disclosed?
[475] The plaintiffs assert that the provision of the un-redacted Quote and Purchase orders to
the McKay Brothers affiliated directors of EMClarity disclosed the existence and content
of the proposed phased roll out to McKay Brothers. That is undoubtedly true, and the
defendant does not suggest otherwise.
Issue 13: Was there a contractual obligation under the WBRDAT to keep the
Material confidential and not disclose it to McKay Brothers?
[476] The short answer is “yes” as per the terms of the WBRDAT for the “Material” covered
by it – that is the W-Band project, the terms of the WBRDAT, and the Customer Material
under the WBRDAT; but not the Alternative Strategy, the Quote and the Purchase
Orders”.
[477] The plaintiffs’ position in submissions seemed to be that the contractual obligations of
confidence did not apply to the strategy and those documents (although this seems
inconsistent with its pleading). The defendant’s position was that it did.
[478] On the basis that the 2019 Agreements were separate to the WBRDAT, it seems to me
that the strategy and those documents would only be covered by the contract if they fell
within the definition of “Customer Material”. “Customer Material” is limited to material
provided by BSO for the purposes of the WBRDAT.
[479] When it came to the question of whether there had been the disclosure of confidential
information by way of sending the meeting invitation and the emails which followed it,
the defendant’s position was that the definitions of Confidential Information and
Customer Material were exhaustive. Not everything with a remote connection to the
WBRDAT, or the work performed under it, was confidential. Nor was information
gained by EMClarity during the course of working in pursuance of the WBRDAT, which
was not provided by BSO, or to which access was given by BSO, for the purposes of the
WBRDAT, within the definitions.
[480] Applying the defendant’s own arguments, it is stretching the language of the contract too
far to suggest that a discussion about an alternative to the WBRDAT and the documents
-- 117 of 136 --
118
reflecting that alternative were provided for the purposes of the WBRDAT – even if the
discussion related to the WBRDAT and the work to be performed under it.
[481] In my view, the contractual obligation of confidence therefore covered the W-Band
project, the terms of the WBRDAT and the Customer Material. It did not cover the
Alternative Strategy, the Quote and the Purchase Orders.
Issue 14: Was there an equitable duty of confidence to keep the Material
confidential and not disclose it to McKay Brothers? What is the scope of any such
equitable duty?
The equitable obligation or duty of confidence
[482] Equity enforces a duty not to misuse information that is disclosed in circumstances giving
rise to an obligation of confidence, as confirmed in Moorgate Tobacco Co Ltd v Philip
Morris Ltd (No 2) (1984) 156 CLR 414. Of the equitable obligation not to misuse
confidential information, Deane J said (at 437 - 438, footnotes omitted, my emphasis) –
It is unnecessary, for the purposes of the present appeal, to attempt to define
the precise scope of the equitable jurisdiction to grant relief against an actual
or threatened abuse of confidential information not involving any tort or
any breach of some express or implied contractual provision, some wider
fiduciary duty or some copyright or trade mark right. A general equitable
jurisdiction to grant such relief has long been asserted and should, in my view,
now be accepted: see The Commonwealth v John Fairfix & Sons Ltd. Like
most heads of exclusive equitable jurisdiction, its rational basis does not lie
in a proprietary right. It lies in the notion of an obligation of conscience
arising from the circumstances in or through which the information was
communicated or obtained. Relief under the jurisdiction is not available,
however, unless it appears that the information in question has the “necessary
quality of confidence about it” (per Lord Greene MR, Saltman) and that it
is significant, not necessarily in the sense of commercially valuable … but in
the sense that the preservation of its confidentiality or secrecy is of substantial
concern to the plaintiff …
Whether contractual and equitable obligations of confidence co-exist?
[483] In the present case, the parties argued about whether an equitable obligation of confidence
could arise when a contractual obligation of confidence was in existence – referring me
to competing authorities. I will refer first to the authorities, and then to the parties’
submissions about them.
Del Casale v Artedomus (Aust) Pty Ltd [2007] NSWCA 172
[484] Del Casale concerned the obligations of confidence of employees. Artedomus was the
sole importer of modica stone into Australia. Its best-selling product was a modica stone
-- 118 of 136 --
119
it called “Isernia”, which was obtained from the Ragusa district in Sicily. Although it
could be readily ascertained that modica stone came from the Ragusa district, the source
of Isernia and the fact that it was modica stone could not be easily ascertained..
Artedomus emphasised to the appellants, Del Casale and Savini, whom it employed, that
the source of Isernia was not to be disclosed.
[485] Ultimately, Del Casale and Savini resigned from Artedomus. Del Casale agreed that he
would “keep confidential any commercially sensitive information he may be in
possession of or have become aware of during his employment” and not compete with
Artedomus for three years.
[486] Del Casale set up a business called Stone Arc and Savini became a director of it. They
travelled to Italy and, the primary judge found, used confidential information (that Isernia
was obtained from the Ragusa district) to rapidly locate alternative suppliers of Isernia.
[487] A question for the primary judge was whether the information about the source of Isernia
was protected without an agreement. The primary judge found that it was. On appeal, it
was submitted that, in the absence of a contractual agreement, the information did not
have the degree of confidentiality that would attract protection after employment had
ended.
[488] The appeal judgment relevant to the present matter is Campbell JA’s. His Honour found,
inter alia, that there had been no relevant breach of the obligation of confidentiality. In
analysing relevant authority about “trade secrets”, Campbell JA mentioned that the
judgment of Goulding J in Faccenda Chicken Ltd v Fowler [1985] 1 All ER 724, made
reference to the judgment of Lord Green MR in Saltmann Engineering Co Ltd v Campbell
Engineering Co Ltd [1963] 3 All ER 413 at 415. His Honour considered that worth
mentioning because, inter alia, Saltman was concerned solely with an equitable
obligation of confidence, but Goulding J applied it where the only cause of action sued
on was for breach of contract. His Honour continued (my emphasis) –
[117] … That was recognised by counsel and the Court in the Court of Appeal, as
one of the submissions made to the Court of Appeal is recorded as being:
“… though the obligations of an employee [concerning confidence]
were based on an implied term of the contract of service, this was
immaterial because the scope of the implied term was coextensive with
the obligations imposed by equity on a person to whom confidential
information was entrusted in circumstances where no contact existed
between the parties.”
[118] If there was a contractual obligation that covered the topic, there would,
of course, be no occasion for equity to intervene to impose its own
obligation. This was recognised by Megarry J in [Coco] when he said at 47:
“In cases of contract, the primary question is no doubt that of
construing the contract and any terms implied in it. Where there is
no contract, however, the question must be one of what it is that suffices
to bring the obligation into being …”
-- 119 of 136 --
120
[489] His Honour concluded that while the information was given in confidence, and there was
an obligation of confidentiality around it, it was information of a nature which a
reasonable and honest person could have been, at the least, in doubt about whether he or
she was entitled to use it after leaving Artedomus.
Streetscape Projects (Aust) Pty Ltd v City of Sydney (2013) 85 NSWLR 196
[490] Del Casale was referred to in obiter remarks in Streetscape. Streetscape was an appeal
from the decision of the primary judge that it had breached: its contract with the council
of Sydney; fiduciary duties it owed to the council; and its duty of confidentiality.
[491] Streetscape and the council were parties to an agreement which included confidentiality
clauses under which Streetscape was not to use the Intellectual Property of the council
other than for the purposes of their agreement.
[492] The Court of Appeal found that, because the primary judge had wrongly refused to admit
certain evidence, the issues of the existence and breach of an equitable duty of confidence
were to be remitted to the Equity Division for re-trial.
[493] In discussing the equitable duty of confidence, Barratt JA, with whom Meagher and Ward
JJA34 agreed, referred to Del Casale in the context of considering whether the equitable
duty could co-exist with a contractual one. His Honour said (citations omitted, my
emphasis in bold) –
[149] The licence agreement contained detailed confidentiality provisions …
[150] There is a question whether an equitable duty of confidence arises
against one party and in favour of another where those parties have given
and received contractual promises of confidentiality creating equal or
greater protection of the same subject matter. The Full Court of the
Federal Court, in Optus … decided that the two kinds of obligation could co-
exist (reference was there made to an earlier case in which a contractual duty
was described as “parasitic upon” the equitable duty: Australian Medic-Care
Company Ltd v Hamilton Pharmaceuticals Pty Ltd) …The contrary view was
taken by Gordon J in Coles Supermarkets Australia Pty Ltd v FKP Ltd …,
citing the observations of Campbell JA in Del Casale … at [118] that, if there
is a contractual obligation covering the topic, there is no occasion for equity
to intervene to impose its own obligation (Campbell JA as a judge of the
Equity Division, has expressed similar views in AG Australia Holdings Ltd v
Burton … and Mid-City Skin Cancer & Laser Centre Pty Ltd v Zahedi-Anarak
…). The approach preferred by Gordon J and Campbell JA accords
with the residual nature of the equitable duty as recognised by Deane J
in Moorgate … at 437 – 438. Deane J referred to “the equitable jurisdiction
to grant relief against an actual or threatened abuse of confidential
34 As her Honour Justice Ward was then known.
-- 120 of 136 --
121
information not involving any tort or any breach of some express or implied
contractual provision, some wider fiduciary duty or some copyright or trade
mark right” (emphasis added). It is also consistent with the notion of equity’s
“supplementing” role discussed above in relation to fiduciary duties.
[494] However, the question of the co-existence of contractual and equitable duties of
confidence did not arise in Streetscape because the proceedings were fought on the basis
of co-existing contractual and equitable duties, and that position was not challenged on
appeal.
Optus Networks Pty Ltd v Telstra Corporation Ltd (2010) 265 ALR 281
[495] Optus argued before the primary judge that Telstra had –
breached the provisions of an “access agreement” which, by clause 15, restricted
the disclosure and use of Confidential Information as defined therein;
breached the duty of confidentiality which it owed to Optus; and
engaged in unconscionable conduct under the Trade Practices Act.
[496] The primary judge allowed the contract claim but dismissed Optus’ claim in equity
because the contract dealt with the obligation of confidence exhaustively. Optus
successfully appealed against that decision.
[497] The primary judge said (paragraph numbers from the primary judgment, quoted in [27]
of the judgment of the Full Court, my emphasis) –
[4] … where, as here, there is not only a contract between the parties, but a
contract which, in its terms, defines “Confidential Information” on an
exhaustive basis … and regulates the obligations of each party in relation
to the Confidential Information of the other party on a comprehensive
basis … there is, in my view, no reason for the intervention of equity for
the simple reason that there is no need for its intervention to achieve justice
between the parties for conduct which is common to both the finding of
breach of contract and the ground relied upon for equitable intervention.
[5] Moreover, the conclusion expressed at [4] above is reinforced where, as here,
the contract contains a provision such as cl 16.1 …
[6] In these circumstances, I decline to find any breach of a duty of confidentiality
owed by Telstra to Optus overlapping or concurrent with my finding of
Telstra’s breach of contract.
[498] Clause 16.1 stated what it called a “General Principle” –
Save to the extent that another provision of this agreement expressly provides
for (or expressly excludes or limits) a remedy, a liability or a form of
-- 121 of 136 --
122
compensation in relation to an act, omission or event, this clause 16 shall
regulate the liability (whether arising in contract, in tort, under statute or in
any other way and whether due to negligence, wilful or deliberate breach or
any other cause) of a party to each other party under and in relation to this
agreement and in relation to any act, omission or event relating to or arising
out of this agreement.
[499] In deciding whether the access agreement excluded equitable obligations of confidence,
the Full Court (in a joint judgment) studied the terms of the agreement in detail.
[500] The Full Court found that, although “Confidential Information” was defined in an
exhaustive fashion, it did not indicate an intention to exclude equitable obligations. Nor
did a clause which comprehensively regulated the obligations of each party in relation to
Confidential Information. Indeed, Clause 15.6 pointed in the other direction. It stated
(my emphasis) –
Each party acknowledges that a breach of this clause 15 by one party may
cause another party irreparable damage for which monetary damages would
not be an adequate remedy. Accordingly, in addition to other remedies
that may be available, a party may seek injunctive relief against such a
breach or threatened breach.
[501] An account of profits was an obvious other remedy.
[502] Clause 20.22 was also relevant. Generally, it provided that the rights, powers and
remedies provided in the agreement were not exclusive of the rights, powers or remedies
provided by law independent of the agreement. Further, clause 16.8 anticipated other
proceedings.
[503] The Full Court held that clause 16.1 did not reinforce the primary judge’s view that the
intervention of equity was excluded by the agreement. The primary judge had thereby
erred.
[504] The Full Court then considered Telstra’s reliance on the observations of Gordon J in
Coles, where her Honour rejected an argument that equitable and legal obligations of
confidence could coexist, relying on Del Casale. The Full Court found that Campbell
JA’s statement in Del Casade did not apply in Optus because the contractual obligations
did not “cover the topic”. Optus wished to seek an account of profits and the clauses of
the contract permitted it to do so.
[505] After considering other authority, the Full Court said at [37] (my emphasis) –
… the access agreement (in particular clauses 15.6 and 20.22) preserves
equitable rights. We can discern no reason why parties cannot agree that
one who claims that its confidential information has been misused can elect
to sue either for damages for breach of contract under clause 15 or for an
account of profits under clauses 15.6 and 20.22.
-- 122 of 136 --
123
[506] More generally, the Full Court observed that the notion that no equitable duty of
confidence arises where there is a comparable contractual duty was “opposed to much
authority”, which it listed.
Academic text
[507] The learned authors of Equity: Doctrines & Remedies,35 acknowledge the significance of
the terms of a contract and that which may be gleaned from them about the availability
of recourse to equitable remedies.
[508] At [42-050] they state (some footnotes omitted, my emphasis) –
The subject of this chapter is the jurisdiction in equity to restrain breaches of
confidence – not in the auxiliary jurisdiction as an aid to contractual rights,
but in the exclusive jurisdiction where the plaintiff has no legal rights. Where
there is a contract then it is necessary to look to its express words or necessary
implication. Those legal rights may be sufficient, and indeed they may
exclude recourse being had to equitable concepts [here, the authors refer to
Campbell JA in Del Casale at [118]]. However, just as contract may be (and
often is) the source of a fiduciary obligation, contractual provisions are apt to
be highly significant in determining whether information has the necessary
quality of confidence, and was imparted in circumstances importing an
obligation of confidence, so as to attract equitable intervention. Indeed,
where contracting parties have made elaborate provision to protect
information regarded by them as confidential, there is often no good reason
to conclude that they should have been taken to excluded equitable principle.
For example, not lightly should parties be taken to have denied recourse
to an account of profits in the event of a misuse of information which is
both inherently confidential and which is protected by their contract.
Thus, a Full Court of the Federal Court has confirmed that ‘the notion that no
equitable duty of confidence arises where there is a comparable contractual
duty is opposed to much authority [referring to Optus at [38]] and has
approved Dean’s statement that ‘[e]quitable protection … may be used in
preference to an existing contractual obligation, or alongside a contractual
obligation [referring to R Dean, The Law of Trade Secrets, 2nd ed, Lawbook
Co, Sydney 2002, [2.55]].
The parties’ arguments
[509] As I understood things, the plaintiffs relied upon an equitable obligation of confidence to,
in effect, override clause 7.3 of the WBRDAT.
35 Heydon, Lemming and Turner, Meaghaer, Gummow & Lehane’s Equity: Doctrines & Remedies, 5th ed,
LexisNexis Butterworths, 2015.
-- 123 of 136 --
124
[510] The plaintiffs submitted that “the only circumstances in which equitable and contractual
obligations cannot co-exist is where the contract ‘covers the topic’ and evinces an
intention that ‘equitable principles are excluded’ and the contract provides all of the
necessary remedies to deal with the conduct to which a party is exposed”.
[511] The plaintiffs submitted that Optus demonstrated that such a conclusion should not be
readily drawn, even where parties have entered into complex and detailed commercial
contracts. They continued, “The mere “codification” of certain matters, for example, by
defining what is treated as confidential for the purpose of a contract, does not demonstrate
an intention to exclude the Court’s equitable jurisdiction”.
[512] The defendant, who wished to rely upon clause 7.3 of the WBRDAT, submitted that only
the contractual obligation applied, and even if there were room for an equitable obligation
of confidence, it was no broader than the contractual one.
[513] The defendant acknowledged that the cases which suggested that no equitable obligation
arose where a contractual obligation of confidence exists (for example, Del Casale) were
questioned in Optus. However, it observed that Streetscape was a unanimous decision of
the New South Wales Court of Appeal which considered Optus but decided to “follow”
Del Casale. It submitted that “Optus expresses doubt about Del Casale but does not
decline to follow it in a reasoned way. In Optus, the express terms of the contract
contemplated the availability of equitable remedies, which is a feature not present in the
[WBRDAT]”.
[514] The defendant submitted that I ought to follow the reasoned position of the Court of
Appeal in Del Casale and Streetscape rather than the obiter of the Full Court and conclude
that because the WBRDAT included obligations of confidence, no co-existing equitable
obligation of confidence arose. And even if there were room for a co-existing obligation
of confidence, the defendant submitted that it was no wider than the contractual obligation
(which was tempered by clause 7.3), referring to Coco at 590, at which Megarry J said
that, in cases of contract, the primary question was no doubt one of construing the contract
and its terms.
[515] The defendant elaborated on these submissions further and made the following points –
The authorities which concluded that contractual and equitable obligations could
co-exist did not support the proposition that the equitable obligation could extend
further than the contractual one or be inconsistent with it;
The residual nature of equity was at least consistent with the proposition that any
co-existing equitable obligation ought not to be inconsistent with, or broader than,
the contractual one;
A conclusion that any equitable obligation was limited by, and had to conform to,
the relevant contract was consistent with the position in the cognate area of
fiduciary duties (referring to Hospital Products Ltd v United States Surgical
Corporation (1984) 156 CLR 41 at 97);
-- 124 of 136 --
125
The WBRDAT exhibited an intention to exclusively define the parties’ rights and
obligations on the topic of confidentiality – including by way of its definitions of
“Confidential Information” and “Customer Material”. Also, clause 13.6 provided
that the WBRDAT embodied “the entire agreement between the parties related to
the subject matter hereof”. Such a clause was thought to have supported the
application of Del Casale in Gold & Copper Resources Pty Ltd v Newcrest
Operations Ltd [2013] NSWSC 281.
[516] The authorities which stated that the equitable obligation ought to go no further than the
contractual one included Corporate Farming Pty Ltd v Eden Bay Pty Ltd, an unreported
decision of the Supreme Court of Western Australia on 28 January 1992, in which Murray
J held as follows –
I think it is the law that in circumstances where there is a contractual
relationship between the parties a duty of confidentiality may nonetheless
arise in equity and be owed by one party to the other …
But as I understand the law, such an equitable duty may be relied upon where
it would result in a position consistent with that provided for by the contract
or where the contract is silent on the matter, but not to give a party a remedy
in circumstances where the result would be directly inconsistent with the
contractual arrangements.
Discussion and conclusion
[517] Streetscape expressed a preference for Del Casale and noted its consistency with Deane
J in Moorgate but the issue of the co-existence of contractual and equitable obligations
did not arise because of the way in which the parties had proceeded on appeal.
[518] In Optus, the access agreement clearly contemplated remedies for breach of its terms
beyond those provided in the contract. Whilst expressing doubt about the approach in
Del Casale, the Full Court resolved matters by reference to the terms of the parties’
agreement.
[519] Other authorities to which I was referred go either way.
[520] My preference is for the approach in Del Casale, because of its consistency with
Moorgate.
[521] But assuming that the correct approach is one which permits a co-existing equitable
obligation of confidence, the more relevant question is whether that equitable obligation
supersedes or overrides clause 7.3.
[522] The authorities to which I was referred emphasised the significance of the contract. The
parties here were free to agree that certain conduct would not amount to a breach of the
obligation of confidence. In my view, the equitable obligation would not operate to
convert contractually authorised disclosure into unauthorised disclosure. In other words,
-- 125 of 136 --
126
in my view, paying due regard to the parties’ agreement, where certain disclosure would
not amount to a breach of contract because it is authorised by clause 7.3, equity would
not intervene to render that same conduct a breach of a broader equitable obligation.
Issue 15: Was the contractual duty breached?
[523] The defendant asserts that none of the Customer Material, which EMClarity received
from BSO (including the Site Location Data and the Path Analyses Information), was
disclosed to McKay Brothers. The plaintiffs have made no submissions to me about the
provision of Customer Material in breach of contract. I will therefore say nothing more
about it.
[524] With respect to the provision of the ineffectively redacted, and un-redacted, copies of the
WBRDAT, the defendant relies upon clause 7.3 of the WBRDAT. The defendant also
observes that, because of clause 7.3, it was under no obligation to redact, or attempt to
redact, the WBRDAT before providing it to Mr Boyle during due diligence.
[525] The defendant pleads that McKay Brothers was a potential investor from 15 July 2019
and an investor from September 2019. Therefore, EMClarity was entitled to disclose
copies of the WBRDAT36 to Mr Boyle and to the McKay Brothers affiliated directors.
The plaintiffs made no submissions to the contrary in the context of the contractual
obligation.
[526] It follows that the disclosure of the WBRDAT during due diligence was authorised by
clause 7.3(c) and the disclosure of the WBRDAT to the McKay Brothers affiliated
directors was authorised by clause 7.3(b).
[527] In reaching agreement on the terms of the WBRDAT, the parties could have anticipated
a potential investor rival – but did not do so. In this context, the defendant referred to
Global Advanced Metals Pty Ltd v Metallurg Inc [2017] WASCA 188 at [90], in which
the Court of Appeal of Western Australia rejected a submission that a disclosure clause
should be read to provide for an unexpressed limit on disclosure to “trade rivals”. I found
this authority useful.
[528] Metallurg is a wholly owned subsidiary of “AMG” which is the holding company for a
global group of metallurgical and engineering companies (“AMG Group”). Global is a
tantalum company. Tantalum is a metal. Global is the holding company for a global
group of other tantalum companies (“Tantalum Group”).
[529] Metallurg acquired shares in Global and became a party to a Shareholder Deed which, by
clause 7.1, granted “Relevant Shareholders” access to Global’s books and records.
Clause 7.2 of the deed required the person accessing/inspecting the books and records to
sign a confidentiality agreement. Clause 4.1 of the Shareholders Deed also provided that
a Relevant Shareholder agreed not to use Confidential Information in a way which would
36 Ineffectively redacted, and un-redacted.
-- 126 of 136 --
127
damage or be likely to damage the Tantalum Group. Clause 16.3 of the Shareholders
Deed imposed obligations of confidence upon Relevant Shareholders.
[530] Metallurg made several requests for access to, and inspection of, Global’s books and
records – in accordance with clause 7.1 of the Shareholder Deed. Global resisted
Metallurg’s requests for access/inspection. It was concerned about allowing access
because certain entities in the AMG Group carried on business in competition with
entities in the Tantalum Group. Attempts to come up with an arrangement which would
impose confidentiality obligations on Metallurg were unsuccessful. Metallurg
commenced proceedings seeking orders which would allow it the access it sought;
including a declaration that it was entitled to access Global’s books and records under the
Shareholders Deed.
[531] Global argued that, if Metallurg’s request for access and inspection were met, then
commercially sensitive information belonging to the Tantalum Group would be obtained
by a trade rival – thereby destroying the confidence in that information. The information
would inevitably be deployed to the commercial disadvantage of the Tantalum Group,
even if Metallurg agreed not to use it to Global’s disadvantage, because it would remain
in the knowledge of the AMG Group. Metallurg argued that the clause 7.1 should operate
in accordance with its terms and not be read down in the manner contended for by Global.
[532] The primary judge preferred Metallurg’s construction of the Shareholders Deed.
[533] On appeal, it was argued that the primary judge erred in finding that the Shareholders
Deed conferred, in effect, an unfettered right upon a Relevant Shareholder, being a trade
rival, to access and use the Tantalum Group’s commercially confidential information for
a permitted purpose. It was argued that it was inherently unlikely that Global contracted
to provide commercially sensitive information to a Relevant Shareholder/trade rival,
protected only by confidentiality undertakings which were, in the context of trade rivals,
practically worthless.
[534] The appeal was dismissed by way of a judgment of the Court. It was held that the primary
judge had not erred in his construction of clause 7.1 including because Global’s
construction of clause 7.1 sought to incorporate into it concepts such as “trade rivals” and
“commercially sensitive information” which had no foundation in the clause read on its
own or in the context of the instrument as a whole. Nor did the primary judge’s
construction of the clause produce commercial inconvenience. It was plainly in the
interests of shareholders to acquire relevant information. The language of the instrument
did not treat differently, or make an exception for, a Relevant Shareholder who was also
a trade rival. The Court said, at [91] and [93] –
Where there is nothing in the terms of the Shareholders Deed or in the
mutually known background circumstances to indicate that the parties
contemplated that the Relevant Shareholder may be, or become, a trade rival,
the commercial operation of a suite of measures for the provision of relevant
information to a Relevant Shareholder, and for the protection of Confidential
Information, cannot be assessed by singling out that particular eventuality.
-- 127 of 136 --
128
…
As to the objective factual matrix, the fact that cl 7 had its origins in an earlier
deed in which none of the Relevant Shareholders was a competitor of the
other tends against, rather than in favour, of Global’s construction. That is
because it makes it less likely that, objectively, the parties to the Shareholders
Deed, prior to the execution of the Assumption Deed by Metallurg, intended
that cl 7 be read as subject to the kind of limitation for which Global now
contends …
[535] Nothing in the WBRDAT suggests that, when it comes to the disclosure of confidential
information, potential investors or directors who are trade rivals are to be treated
differently from potential investors or directors who are not trade rivals.
[536] But of course, the situation does not end with clause 7.3. Clause 7.4 applies. It states –
If either party discloses Confidential Information under clause 7.3, that party
must ensure that such information is kept confidential by the person to whom
it is disclosed and if disclosed under clause 7.3(b), is only used for the
purposes of performing the project under this agreement.
[537] In short, EMClarity did not breach clause 7 of the WBRDAT by providing the WBRDAT
to Mr Boyle or the McKay Brothers affiliated directors because that disclosure was
authorised.37 But once in the hands of Mr Boyle or the McKay Brothers affiliated
directors, they were obliged to keep it confidential and not misuse it.
Issue 16: Was the equitable duty breached?
[538] The equitable duty of confidence attaches to the Alternative Strategy, the Quote and the
Purchase Orders.
The equitable duty of confidence
[539] A claim that there has been a breach of the equitable duty of confidence has four elements,
namely –
the alleged confidential information must be identified with specificity;
the information must have the necessary quality of confidence;
the information must have been received by the defendant in circumstances
importing an obligation of confidence; and
37 The plaintiffs also pleaded that two emails, sent in late 2019, involved breaches of confidence. The plaintiff
made no submissions about these emails and I will say nothing more about them.
-- 128 of 136 --
129
there must be actual or threatened misuse of the information without the plaintiffs’
consent.
The plaintiffs’ submissions
[540] The plaintiffs submitted that the information disclosed in the Quote and Purchase Orders
was highly sensitive information about how “Apsara” intended to upgrade its network. It
was information which was not otherwise in the public domain. The circumstances in
which that information was communicated to EMClarity clearly imported an obligation
of confidence. Its disclosure to McKay Brothers amounted to a misuse of that
information. EMClarity was aware that McKay Brothers and BSO/Apsara competed in
the NJ Equity Triangle. It would have been “abundantly clear” to EMClarity that
disclosure of the Alternative Strategy could have “potentially disastrous consequences”
for BSO/Apsara.
The defendant’s submissions
[541] The defendant submitted that the allegation of breach fell to be determined “by reference
to the obligations and exceptions in the contractual framework”. No other facts pleaded
could be argued to broaden the obligation. There was no allegation that the commercially
sensitive/valuable information was communicated to EMClarity and no allegation that
EMClarity knew this was the case. Nor were these propositions put to Dr Baines in cross-
examination.
[542] The defendant also submitted that it would be a wholly surprising result if an equitable
obligation imposed upon EMClarity prevented it from disclosing the Alternative Strategy
to its own directors. The defendant further submitted –
The Plaintiffs seek to make something of the fact that [EMClarity] was
acquired by McKay Brothers. Having regard to the fact that [EMClarity] was
working on a LMDS product for McKay Brothers, and had been actively
seeking investment in the company since at least July 2017, which Dr Baines
had raised with representatives of both McKay Brothers and BSO, this does
not have the sinister connotation which is suggested by the Plaintiffs. The
provision of agreements to which EMClarity was a potential investor in
confidential due diligence and to the New Directors following their
appointment was entirely consistent with commercial practice, a practice that
is expressly recognised by way of clause 7.3 of the Agreement.
Discussion and conclusion
[543] I find the first three elements of the “breach of the equitable duty of confidence” claim
established.
[544] The Alternative Strategy was of commercial significance to BSO/Apsara. Mr McGowan
(and EMClarity) had spent some time settling it. It had the necessary quality of
-- 129 of 136 --
130
confidence. It was the way in which BSO hoped to achieve a competitive advantage in
its NJ Equity Triangle market, and after it lost one customer, it was likely to have been
concerned about losing more.
[545] The commercial risk to BSO/Apsara in the disclosure of the Alternative Strategy to the
McKay Brothers’ affiliated directors is obvious. Indeed, I infer from the fact that
EMClarity redacted, or attempted to redact, the documents provided to Mr Boyle during
due diligence, it appreciated the need to treat the Alternative Strategy as confidential.
[546] I find that EMClarity breached its equitable obligation of confidence when it disclosed
the Alternative Strategy to the McKay Brothers affiliated directors.
[547] I appreciate that EMClarity’s board, post the McKay Brothers’ takeover, may have had a
legitimate reason for wishing to understand EMClarity’s contractual obligations. But
there were ways in which EMClarity could provide relevant information to its board –
including its new members – while at the same time abiding by its equitable duty of
confidence insofar as the Alternative Strategy was concerned. Those ways included
providing the board with redacted documents, or engaging an independent third party to
summarise them in such a way as to protect the confidentiality of the Alternative Strategy.
Issue 17: Does BSO/Apsara hold a belief that EMClarity will further delay the
development/shipment of the radios? Is that belief reasonable?
[548] Mr McGowan and Mr Pellé believe that there will be a further delay in the development
and shipment of the radios.
[549] It follows from my finding that EMClarity has repudiated the 2019 Agreements that I
consider it reasonable to believe that EMClarity will further delay the development and
shipment of Apsara’s radios.
[550] Additionally, Dr Baines gave evidence to the effect that it was made clear to him that
there was to be no discussion with BSO/Apsara about the supply of their radios. Nor was
any pressure placed on EMClarity to accelerate work on the 2019 Agreements.
Issue 18: Does BSO/Apsara hold a belief that EMClarity will, in the future, breach
the confidentiality provisions of the WBRDAT or the equitable duty of confidence?
Is that belief reasonable?
[551] I am satisfied that BSO/Apsara believes that one or the other of these breaches will occur.
[552] The plaintiffs urged me to find the belief reasonable, in the light of the disclosure which
had already taken place and notwithstanding what Dr Baines and Mr Boyle have said will
occur especially when there has been no undertaking not to disclose confidential
information offered by them.
-- 130 of 136 --
131
[553] According to Mr McGowan, during the telephone call informing him that McKay
Brothers had acquired EMClarity, when he asked Dr Baines about the confidential
information which had been given to McKay Brothers, Mr Meade told him to assume that
anything discussed with Dr Baines would be shared “with them as well”.
[554] Dr Baines, who acknowledged during the call that he had supplied BSO’s confidential
material to McKay Brothers, said EMClarity would need to consider how “practically” it
could return BSO’s confidential material or how it could be deleted or destroyed.
[555] Dr Baines said in evidence that he was aware of EMClarity’s obligations of confidence
under the WBRDAT in respect of Confidential Information and Customer Material and
that he intended to continue to perform and observe those observations on behalf of
EMClarity.
[556] It is worth considering Mr Boyle’s affidavit evidence in some detail because of its
relevance to this issue and to Issue 19.
[557] In his affidavit, Mr Boyle said that McKay Brothers received its first batch of LMDS
Radios from EMClarity in July 2018. McKay Brothers did its own testing to supplement
EMClarity’s in-house testing. McKay Brothers found the batch of LMDS radios to have
pervasive and severe issues, which varied from radio to radio, which may have been
caused by manufacturing variances. In Mr Boyle’s experience, the volume and impact of
the issues McKay Brothers was experiencing with the LMDS radios was unusually high.
His affidavit elaborates upon this issues.
[558] In January 2019, Mr Boyle sent representatives from McKay Brothers to EMClarity to
“oversee trouble shooting” of the LMDS radios.
[559] In around May of 2019, EMClarity informed McKay Brothers that it had identified the
root cause of many of failures of the LMDS radios – namely, the digital modem board.
After fixing that issue (in October 2019), according to Mr Boyle, the LMDS radios were
still not performing to the standard expected. The persisting issues could not be put down
to typical “teething”. According to Mr Boyle, the LMDS radios have downtime every
day and did not meet the specifications of the agreement between McKay Brothers and
EMClarity to develop the LMDS radios.
[560] Mr Boyle is negative about W Band. He says that McKay Brothers has no commercial
incentive to prevent BSO from moving into it. However, his opinion of W Band, as
expressed in his affidavit, is inconsistent with his interest in W Band as expressed to Dr
Baines in their conversations in May and June of 2019.
[561] His explanation for his inquiries of Dr Baines about W Band are not persuasive. He says
(in his affidavit) that he had previously looked into the development of a W Band radio
but the project did not progress because he was not satisfied of the technical capabilities
of a W Band radio. He said he had a “personal curiosity” in someone else trying to
develop it. He continued –
-- 131 of 136 --
132
… Given my assessment that it was technically inferior to both E-Band and
28GHz Band radios, I was interested in why EMC thought there was a case
that made it worth investing in W-Band development. I was also concerned
that EMC was spreading itself thin developing a W-Band product when there
were ongoing problems with McKay Brothers’ LMDS Radios, and that this
might delay McKay Brothers receiving fully functional LMDS Radios.
For those reasons, on 28 May 2019, I emailed Dr Peter Baines … to enquire
whether EMC was developing a W-Band radio …
…
Although I was interested in hearing about EMC’s work in W-Band …
McKay Brothers was not pursuing a W-Band project at that time and had no
intention to do so. Part of my role at McKay Brothers requires me to
continually research and evaluate any and all technologies in all bands. My
enquiry to Dr Baines was something of a fishing expedition … it was not of
interest to McKay Brothers … My only interest in pursuing the topic with Dr
Baines was seeking an understanding of what the product map was for EMC,
and ensuring that existing resources were not being used up on more complex
and costly projects in new bands when the existing radios being delivered to
McKay Brothers were experiencing unresolved issues. From Dr Baines’
reply it was apparent to me that he was not going to provide any further
information, so I did not pursue the matter of W-Band any further.
[562] Frankly, had Mr Boyle been “only” interested in the deployment of EMClarity’s
resources and any diversion from the LMDS radios, then it is reasonable to expect he
would have raised that matter directly with Dr Baines. He did not need to know details
about the W-Band project to express his concern that EMClarity’s resources were not
being deployed for the benefit of McKay Brothers.
[563] Mr Boyle explained the reasons behind McKay Brothers’ acquisition of EMClarity as
follows –
Dr Baines mentioned to him in around August 2018 that he was interested in
obtaining further funding for EMClarity;
They had several conversations about the matter in late 2018/early 2019;
“In around June 2019” Dr Baines told him that there was a potential buyer for
EMClarity’s parent company, E M Solutions (EMS);
The potential buyer did not have an existing interest in the high frequency trading
(HFT) market and might not be interested in maintaining EMClarity’s
commercialisation efforts in the HFT market;
-- 132 of 136 --
133
He was concerned that, if the acquisition went ahead, and EMClarity ceased its
HFT operations, then it would not be available to fix McKay Brothers LMDS
radios (which were significantly underperforming);
He raised his concerns with Dr Baines, who asked him to “just put in a bid” for
EMClarity;
McKay Brothers was interested in acquiring EMClarity to ensure continuity of
supply and support for its LMDS radios; and
He also “believed that McKay Brothers could help [EMClarity] identify and
pursue opportunities to commercialise its products with telecommunications
providers.
[564] McKay Brothers moved quickly because it wanted to ensure that its acquisition of
EMClarity was completed before EMS was acquired.
[565] Dr Baines’ evidence is to similar effect – Mr Boyle was concerned about what the
acquisition of EMS meant for the future of EMClarity and Dr Baines suggested that if he
was concerned about that, he should buy EMClarity.
[566] Mr Boyle said that he had no interest in the plaintiffs’ Customer Material nor any use for
it. He said that McKay Brothers was not interested in W Band nor would be it a substitute
for McKay Brothers LMDS network.
[567] The defendant noted that neither Dr Baines nor Mr Boyle were challenged about their
statements. However, in my view, their self-serving evidence is of little weight. Also, as
I have said earlier, Mr Boyle was an unimpressive witness. I do not accept his evidence
that his interest in W Band was unrelated to his role at McKay Brothers. The content of
his emails to Dr Baines about it was to the contrary.
[568] As for Dr Baines, I find that he was aware of confidentiality issues around the WBRDAT
and the Alternative Strategy – which is why he provided, or attempted to provide,
redacted versions of them during due diligence. And why he was concerned about how
EMClarity might delete or destroy or “practically” return BSO/Apsara’s confidential
information after its acquisition by McKay Brothers.
[569] But it is clear from the evidence that Dr Baines does as he is told by the McKay Brothers
affiliated directors – who are four of the six directors of EMClarity. For example, he had
to “clear” any communications with Apsara through the McKay Brothers affiliated
directors.
[570] The defendant reminded me of the court’s cautious approach to these matters. It referred
me to Apotex Pty Ltd v Les Laboratoires Servier (No 2) [2012] FCA 748 at [42], where
Bennett J said (my emphasis) –
-- 133 of 136 --
134
A quia timet injunction may be granted if the applicant can show that what
the respondent is threatening and intending to do will cause imminent and
substantial damage to the applicant. The degree of probability of future injury
to the applicant is not an absolute standard. The likelihood of the conduct
occurring must be weighed against the degree of seriousness of the injury, the
inconvenience to the respondent and the requirements of justice between the
parties. However, it must be shown that there is some likelihood that the
conduct will occur.
[571] The defendant observed that the onus was on the plaintiffs to establish that the conduct
which might occur was such as was likely to amount to an actionable breach of the
relevant agreement. Also, the damage had to be “imminent” in the sense that the remedy
sought was not premature.
[572] The defendant submitted that the court ought not to conclude that there was a reasonable
basis for fearing a breach of EMClarity’s obligations having regard to the evidence that
–
According to Mr Boyle, McKay Brothers has no interest in W Band;
even though there were McKay Brothers directors on EMClarity’s board, that
provided no basis for an inference that EMClarity might breach its obligations of
confidence – the court should presume the directors would act in accordance with
their duty (to EMClarity);
no conflict is to be assumed just because directors hold positions on boards of
competitor companies (citing Links Golf Tasmania Pty Ltd v Sattler (2012) 213
FCR 1 at [562] – [563]; Streeter v Western Areas Exploration Pty Ltd (No 2)
92011) 278 ALR 291 at [69]);
EMClarity had put in place protective measures to secure the Customer Material,
including containing it in password protected computers; and proposing that it not
be disclosed to the McKay Brothers directors – who would excuse themselves
from board discussions about the material (which is “above and beyond” what is
required) – and this evidence was not challenged, nor were these measures
suggested to be inadequate;
EMClarity’s refusal to undertake not to disclose confidential information was not
a matter which supports an inference that it intended to breach its obligations of
confidence (EMClarity provided other potential explanations for its refusal to give
the undertaking).
[573] The defendant also submitted –
The fact that [EMClarity] does not intend to disclose any Confidential
Material is an important consideration, because in quia timet proceedings the
court will not grant an injunction to compel a defendant to do something
-- 134 of 136 --
135
which it appears willing and able to do without the imposition of an order of
the court (citing Bridlington Relay Ltd v Yorkshire Electricity Board [1965]
Ch 436 at 445). The corollary is that “… the Court never grants an injunction
on the principle that it will do the defendant no harm if he does not intend to
commit the act in question”.
Discussion and conclusion
[574] I note the voluntary measures which EMClarity has put in place to protect the
confidentiality of the Customer Material. But, on the evidence, Dr Baines and EMClarity
do as they are told by the McKay Brothers affiliated directors, who control the board,
including by not following through on the intention to build a W Band prototype for
submission to the Quality Review.
[575] On the evidence, McKay Brothers is making no concessions to BSO/Apsara – nor would
I expect it to. While it is not necessary for me to make a finding about the sham nature
of the Quality Review, I find that McKay Brothers is happy to take whatever advantage
it can from it – including the advantage to be gained by requiring EMClarity to prioritise
the review of its LMDS radios over anything else.
[576] It is reasonable to assume that McKay Brothers wishes to obtain or maintain dominance
in the NJ Equity Triangle market for its network services. If the LMDS radio issues are
as significant as claimed, then it is reasonable to assume that McKay Brothers will explore
alternatives, including those which involve matters touching upon the Customer Material.
While W Band (or a mix of W Band and E Band) might not be something McKay Brothers
“intends” to consider now – that may change.
[577] The McKay Brothers affiliated directors will control EMClarity’s response to its
exploring alternatives to LMDS for McKay Brothers. EMClarity is thereby at risk of
breaching the duty of confidence it owes to BSO/Apsara insofar as information about
proposed network paths, layouts and design and know-how generally is concerned.
Issue 19: Does BSO/Apsara hold a reasonable belief that EMClarity will, in the
future, breach the exclusivity provisions of the WBRDAT or the 2019 Agreements?
[578] I accept that BSO/Apsara believes that McKay Brothers will use their control of
EMClarity to seek to commercially exploit the W Band radio designs in breach of the
exclusivity conditions of the WBRDAT and the 2019 Agreements.
[579] The plaintiffs argued that such a belief is reasonable having regard to –
Mr Boyle’s interest in re-booting McKay Brothers’ efforts with W Band
technology;
Mr Boyle’s emails to Dr Baines regarding the commercialisation of the W Band
radio and how to get around the exclusivity provisions of the WBRDAT; and
-- 135 of 136 --
136
the uncertainty around McKay Brothers’ LMDS network.
[580] The defendant submitted that there was no basis for the finding sought. There had been
no breach of the exclusivity conditions; there was no W Band product in existence – not
even a prototype; Dr Baines gave evidence that EMClarity had no intention of entering
into an agreement to supply anyone else with a W Band prototype or radio; according to
Mr Boyle, McKay Brothers has no interest in a W Band radio (although Mr Boyle himself,
in his personal capacity might have been interested) and has taken relevant steps to secure
its right to use the LMDS frequency over at least the medium, if not long, term; the
Quality Review is genuine and not a deliberate slowing down of the production of W
Band radios – and even if it were a sham, it does not follow that it would lead to a concern
that EMClarity would supply W Band radios to someone else.
[581] I have found that the WBRDAT has been terminated under clause 5. Exclusivity under
the WBRDAT only applies while it is not terminated.
[582] The operation of the exclusivity provision of the 2019 Agreements is a long way off.
They “start” only when the last W Band link ordered is “commissioned in the production
network and accepted as functioning according to specification”. That may never happen.
The exclusivity provisions of the 2019 Agreements do not survive termination. In my
view, it is preferable to defer the answer to this question until the second plaintiff has
indicated whether it will elect to terminate the 2019 Agreements.
-- 136 of 136 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2021/073