Cheshire Contractors Pty Ltd v Civil Mining & Construction Pty Ltd [2021] QSC 75
SUPREME COURT OF QUEENSLAND
CITATION: Cheshire Contractors Pty Ltd v Civil Mining & Construction
Pty Ltd [2021] QSC 75
PARTIES: CIVIL MINING & CONSTRUCTION PTY LTD
ABN 18 102 557 175
(applicant defendant)
v
CHESHIRE CONTRACTORS PTY LTD
ABN 75 124 700 385
(respondent plaintiff)
FILE NO/S: SC No 571 of 2020
DIVISION: Trial
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland
DELIVERED ON: 9 April 2021
DELIVERED AT: Cairns
HEARING DATE: 12 February 2021
JUDGE: Henry J
ORDERS: 1. The parties are referred to arbitration pursuant to
s 8(1) Commercial Arbitration Act 2013 (Qld).
2. Cairns Supreme Court proceeding 571/20 is stayed.
3. I will hear the parties as to costs, if costs have not
been agreed in the meantime, at 9.15am 28 April
2021 (out of town parties having leave to appear by
telephone or video-link).
CATCHWORDS: ARBITRATION – ARBITRATION AGREEMENT –
DEFINITIONS AND FORM OF ARBITRATION
AGREEMENT – ARBITRATION AGREEMENT AS
GROUND FOR STAY OF COURT PROCEEDINGS – where
the applicant defendant engaged the respondent plaintiff as
sub-contractor for roadwork construction – where the
respondent plaintiff complains it was required to complete
work and incur associated costs beyond that contemplated by
the original agreement – where the respondent plaintiff alleges
it is owed money for this additional work – where the
respondent plaintiff says the applicant defendant should be
estopped by convention from denying that the respondent
plaintiff is entitled to reasonable additional remuneration or
damages or compensation pursuant to ss 236, 237 Australian
Consumer Law for loss suffered as a result of the applicant
defendant’s alleged unconscionable conduct – where the
-- 1 of 17 --
2
respondent plaintiff requests an order in relation to the return
of a bank guarantee – where the applicant defendant relies
upon an arbitration clause in the contract to refer the parties to
arbitration and permanently stay the proceeding – where the
respondent plaintiff contends the matter ought not be referred
to arbitration as its claim does not rely on the contract and
rather arises by operation of law outside the contract – whether
there is an “arbitration agreement” as per s 8(1) Commercial
Arbitration Act 2013 (Qld) – whether the application has been
“brought in a matter which is the subject of the arbitration
agreement” – whether the agreement is “null and void,
inoperative or incapable of being performed” – whether the
matter should be referred to arbitration – whether the
proceeding should be stayed
Australian Consumer Law (Cth), s 20, s 21, s 236, s 237
Commercial Arbitration Act 2013 (Qld), s 7, s 8
Astro Vencedor SA v Mabanaft [1971] 2 QB 588, applied.
Australian Broadcasting Commission v Australasian
Performing Right Association (1973) 129 CLR 99, cited.
Commandate Marine Corp v Pan Australia Shipping Pty Ltd
(2006) 157 FCR 45, distinguished.
CPB Contractors Pty Ltd v Celsus Pty Ltd (2017) 353 ALR 84,
applied.
Duncombe v Porter (1953) 90 CLR 295, applied.
Francis Travel v Virgin Atlantic Airways (1996) 39 NSWLR
160, applied.
Hi-Fert v Kiukiang Carriers (1998) 90 FCR 1, distinguished.
IBM Australia Ltd v National Distribution Services Ltd (1991)
22 NSWLR 466, explained.
Incitec Ltd v Alkimos Shipping Corporation [2004] FCA 698,
cited.
Inghams Enterprises Pty Ltd v Hannigan (2020) 379 ALR 196,
distinguished.
McCann v Switzerland Insurance (2000) 203 CLR 579, cited.
Methanex Motonui Ltd v Spellman [2004] 1 NZLR 95; [2004]
3 NZLR 454, cited.
Re Hohenzollern Actien Gesellschaft and City of London
Contract Corp (1886) 54 LT 596, applied.
Roose Industries Ltd v Ready Mixed Concrete Ltd [1974] 2
NZLR 246, explained.
TCL Air Conditioner v Federal Court (2013) 251 CLR 533,
applied.
Westfield Management v AMP Capital (2012) 247 CLR 129,
applied.
Woolf v Collis Removal Service [1948] 1 KB 11, applied.
Yeshiva Properties No 1 Pty Ltd v Lubavitch Magal Pty Ltd
[2003] NSWSC 615, distinguished.
COUNSEL: M.H Hindman QC for the applicant defendant
-- 2 of 17 --
3
M.A Jonsson QC, with C Taylor, for the respondent plaintiff
SOLICITORS: Clayton Utz for the applicant defendant
O’Connor Law for the respondent plaintiff
Introduction
[1] The applicant defendant, Civil Mining & Construction Pty Ltd (CMC), was
contracted by the Queensland Department of Transport and Main Roads (TMR) as
principal for roadworks construction (the project). CMC sought the aid of a civil
engineering roadworks sub-contractor to perform some of the works.
[2] CMC entered into a written sub-contract (the contract) with the respondent plaintiff,
Cheshire Contractors Pty Ltd (Cheshire). A dispute has arisen between CMC and
Cheshire, which alleges it is owed money by CMC in connection with the works
Cheshire performed for CMC. Cheshire filed a claim against CMC in this court
seeking money owing in the sum of $1,393,616.80 plus GST, interest thereon and the
return of a bank guarantee.
[3] Rather than file a defence, CMC countered with the present application which relies
upon an arbitration clause in the contract to refer the parties to arbitration and
permanently stay the proceeding.
[4] Cheshire contends the matter ought not be referred to arbitration for reasons including
that its claim does not rely on the contract and rather arises by operation of law outside
the contract.
Background
[5] In carrying out the subcontracted works, Cheshire was obliged by the contract to
comply with the performance requirements of TMR’s specifications. The
specifications required construction under the contract to use only materials that
complied with the material specified therein, and not use any material that did not
comply with the specifications (out of spec material). The specifications of material
anticipated to be found in the earth in the vicinity of works in a project of this kind
will not always meet expectations, resulting in greater than anticipated expense.
[6] During the performance of Cheshire’s work, out of spec material was encountered in
at least 12 locations on the site of the contract works. On eleven occasions CMC
allegedly gave Cheshire a direction on how to integrate or otherwise deal with the out
of spec material.
[7] Cheshire notified CMC of its intention to make a claim arising from the use of out of
spec material. CMC requested Cheshire provide it with a letter upon which CMC
could base a latent condition claim on TMR for the use of out of spec material.
Cheshire complied. This is the genesis of Cheshire’s current complaint, in effect, that
CMC in serving its own interests procured Cheshire to make a claim for remuneration
on a basis different than that contemplated by the contract. Following receipt of that
letter, CMC stated to Cheshire that the letter would not suffice as a variation claim
and suggested amendments to the document. Cheshire amended its out of spec claim
letter accordingly and again submitted it to CMC.
-- 3 of 17 --
2
[8] Cheshire contends the parties consensually departed from the contract by agreeing
that they would progress their dealings on the mutual assumption and convention that
the latent conditions encountered by Cheshire in the course of excavation could not
have been anticipated by them at the time of tender for the contract works. It was
also agreed, allegedly, that the requirement to complete road excavation and road
embankment work operations with out of spec material would need to be reasonably
remunerated additionally to the remuneration already allowed under the contract in
respect of excavation and embankment works. Further, it was allegedly agreed that
CMC would make payment to Cheshire for its work involving use of out of spec
material on a basis consistent with any payment it received from TMR for its claim
to be made on TMR.
[9] In March 2016 CMC made a claim on TMR for use of out of spec material (CMC’s
Latent Condition Claim), seeking payment for it. In April of 2016, CMC again
requested Cheshire to provide further information and Cheshire made a claim on
CMC for payment of Cheshire’s out of spec claim.
[10] During July and August 2016, CMC and TMR engaged in dispute resolution meetings
in regard to CMC’s Latent Condition Claim. In the course of those meetings CMC
and TMR jointly appointed a third-party engineer to independently assess and value
CMC’s Latent Condition Claim.
[11] CMC received an approval and payment from TMR for CMC’s Latent Condition
Claim under the Head Contract, (the TMR Payment). This was the amount of
$2,507,975.00 as certified for payment for two of the applicant’s progress payments
and the amount of $2,597,462.00 approved as ‘variations’ – being $1,643,975.00 for
‘Latent Conditions’ and $953,667.00 for ‘VVA-092 Latent Condition Claim’.
[12] On about 9 November 2016 Cheshire issued a final progress claim for the amount of
Cheshire’s out of spec claim. By letter of 23 November 2016, CMC responded saying
the amount it proposed to pay was $0.00. The letter explained in denying Cheshire’s
claim “for a purported latent condition” it relied upon clauses 2.1.1 and 13 of the
contract’s general conditions. Clause 13 imposed temporal and other requirements
for the submission of claims. Clause 2.1.1 provided:
“2.1.1 The Subcontractor agrees and accepts the obligation to
fully inform itself on site conditions and all documents
furnished by CMC, prior to it tendering for the
Subcontract Works and to fully satisfy itself regarding
all the conditions, risks, contingencies and other
circumstances which might affect its performance of
the Subcontract Works. In particular, the
Subcontractor shall accept the obligation to
thoroughly investigate all matters regarding the
relevant site, surface and sub-surface conditions. No
increase in the Subcontract Sum will be allowed for
the Subcontractor’s failure to ensure that it is fully
informed regarding all the circumstances relating to its
performance of the Subcontract Works. Also CMC
shall not be liable for any additional cost which may
be incurred by the Subcontractor in the event that
different site, surface and sub-surface conditions are
-- 4 of 17 --
3
experienced by the Subcontractor to those which may
be shown in the Subcontract documents provided by
CMC, the information in such documents being
provided by CMC for indicative purposes only.”
(emphasis added)
[13] In short, CMC’s position was that Cheshire’s claim for payment did not conform with
the contract’s temporal requirements and money was not payable under the terms of
the contract because Cheshire assumed the risk of encountering out of spec material.
[14] In February 2020 Cheshire gave notice of dispute seeking referral to mediation
pursuant to clause 12 of the contract which in part provides:
“12. Disputes
12.1 Early resolution
It is mandatory that the Parties comply with this clause before a
dispute or difference is referred to mediation. Disputes or
differences arising between the Parties shall be negotiated between
the Parties with the bona fide intention of resolution without
unreasonable delay. …
12.3 Settlement of unresolved disputes or differences
12.3.1 If disputes or differences arising between the Parties cannot
be resolved pursuant to clause 12.1 then either party shall
refer such disputes or differences to a CMC Director and in
the case of the Subcontractor means (sic) a Company
Director or Partner of the Subcontractor of the respective
Parties in writing. Within 7 days of receipt of the written
referral of such disputes or differences to Company
Directors, Directors shall meet or otherwise confer to hold
good faith discussions in an effort to resolve the disputes or
differences by amicable agreement.
12.3.2 Should the parties fail to reach agreement in accordance with
clause 12.3.1 the Parties agree that the disputes or
differences shall within 14 days from the receipt of the
written referral pursuant to clause 12.3.1 be referred to
mediation. Either party may refer the dispute or difference
to ACDC in writing requesting the appointment of a
mediator. The mediation shall be conducted in accordance
with the Australian Commercial Dispute Centre (“ACDC”)
mediation Rules and Procedures, and the Chairperson of the
ACDC or the Chairperson’s nominee will select the
mediator and determine the mediator’s remuneration. The
Parties agree that the costs of any mediator appointed shall
be borne equally between the Parties.” (emphasis added)
[15] It will be relevant later in these reasons that where clause 12 refers to “disputes or
differences” such references are to the description at the outset of clause 12.3.1,
namely “disputes or differences arising between the Parties”.
-- 5 of 17 --
4
[16] A mediation proceeded on 4 August 2020 but was unsuccessful. Cheshire did not
further pursue the dispute resolution process.
[17] Cheshire complains it was required to complete work and incur associated costs
beyond that contemplated by the originally contracted Subcontract Works. By
making and pursuing what was in effect CMC’s out of spec claim, Cheshire alleges
it lost the opportunity to make an alternative claim for damages or remuneration under
and in compliance with the contract. Cheshire argues CMC is, or ought to be,
estopped by convention from denying that Cheshire is entitled to reasonable
additional remuneration in respect of excavation and embankment works. Cheshire
claims it is entitled to payment by CMC in the sum of $1,393,616.80 plus GST as
reasonable remuneration for works done by the respondent or alternatively, the same
sum as damages or compensation pursuant to ss 236, 237 Australian Consumer Law
(Schedule 2 Competition and Consumer Act 2010 (Cth)) for loss suffered as a result
of CMC’s allegedly unconscionable conduct.
[18] Further, Cheshire seeks an order that CMC return a bank guarantee issued by Westpac
Banking Corporation in the sum of $48,430.41 or that the applicant notifies Westpac
Banking Corporation that Cheshire’s bank guarantee has been lost and that the
applicant no longer has any interest in that guarantee. Cheshire provided the
guarantee as security in satisfaction of clause 7.7.1 of the contract. The defects
liability period under the contract expired on 21 October 2016. By a letter dated 9
November 2016, Cheshire requested CMC to return the remaining security. It is
alleged CMC has not made a call on the bank guarantee, has failed or refused to
release to Cheshire the bank guarantee and failed or refused to confirm that the bank
guarantee has been lost but is no longer required.
[19] The ensuing reasons will, for ease of explanation, consider whether the present
application should succeed on the premise that the claim is for relief based on estoppel
by convention or statutory unconscionable conduct and does not seek the additional
order about the bank guarantee. Having done so the reasons will then return to the
fact the claim also seeks the order about the bank guarantee and consider whether that
makes a difference to the outcome otherwise of the application.
The legislated obligation to refer to arbitration
[20] In bringing its application to refer the parties to arbitration and stay the proceeding,
CMC contends it and Cheshire are parties to an arbitration agreement under the
contract and the matters the subject of the proceeding fall within the ambit of that
arbitration agreement.
[21] If that contention is correct the court is obliged to refer the parties to arbitration
pursuant to s 8(1) Commercial Arbitration Act 2013 (Qld) (the Act) which provides:
“8 Arbitration agreement and substantive claim before court
(1) A court before which an action is brought in a matter which
is the subject of an arbitration agreement must, if a party so
requests not later than when submitting the party’s first
statement on the substance of the dispute, refer the parties to
arbitration unless it finds that the agreement is null and void,
inoperative or incapable of being performed.” (emphasis
added)
-- 6 of 17 --
5
[22] CMC’s application has met the timeframe stipulated by s 8(1) so the determinative
questions arising from the remaining elements of s 8(1) are:
(a) Is there an “arbitration agreement”?
(b) Is CMC’s Supreme Court claim “brought in a matter which is the subject of the
arbitration agreement”?
(c) Should this court find the agreement “null and void, inoperative or incapable
of being performed”?
As will become apparent from reasons below, the answers to those questions are,
respectively, yes, yes and no.
Definition of an arbitration agreement
[23] Section 7 of the Act relevantly defines an arbitration agreement as follows:
“7 Definition and form of arbitration agreement
(1) An arbitration agreement is an agreement by the parties to
submit to arbitration all or certain disputes which have arisen
or which may arise between them in respect of a defined
legal relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an
arbitration clause in a contract or in the form of a separate
agreement. …” (emphasis added)
[24] The term “defined legal relationship”, used in s 7(1), is not defined by the Act.
Arbitration clause 12.3.3
[25] The purported arbitration agreement is here said to be in the form of clause 12.3.3 in
the contract. It falls within clause 12 about dispute resolution, earlier passages of
which are quoted above. Following the mediation clause at 12.3.2, clause 12.3.3
provides:
“12.3.3 If the disputes or differences have not been settled
within six (6) weeks (or such other period as may be
agreed to in writing between the parties) after the
appointment of the mediator, the disputes or
differences shall be referred to arbitration by either
Party in accordance with and subject to The Institute
of Arbitrators and Mediators Australia (Queensland
Chapter), Rules for the Conduct of Commercial
Arbitrations. In any arbitration both Parties shall be
entitled to be legally represented. The parties shall
appoint an arbitrator within 7 days of referral to
arbitration. If the Parties fail to agree on the identity of
the arbitrator, the Parties agree that the President, for
the time being of the Institute of Arbitrators and
Mediators Australia, is on written request from a Party
to appoint an arbitrator to hear and determine the
disputes or differences. The Parties agree that they will
-- 7 of 17 --
6
not be able to proceed to arbitration unless clause
12.3.2 has first been complied with.” (emphasis
added)
[26] It is not suggested in the present context that the above use of the term “differences”
additionally to “disputes” carries any significance. These reasons will approach
consideration of the matter on the basis a difference is a form of dispute and refer for
convenience to disputes rather than to both disputes or differences.
Consideration
[27] Cheshire argues the purported arbitration agreement at clause 12.3.3 does not meet
that aspect of the definition at s 7(1) of the Act which speaks of an agreement to
submit to arbitration disputes which have arisen or which may arise between the
parties “in respect of a defined legal relationship”. It argues clause 12.3.3 fails to
define the requisite “disputes or differences” to which it refers by reference to any
identified legal relationship, whether contractual or otherwise, and so, absent the
articulation of a defined legal relationship within clause 12.3.3, it cannot be an
arbitration agreement.
[28] In support of its argument that the defined legal relationship, if there is one, must be
ascertainable from the purported arbitration clause, Cheshire referred to the following
observation by French CJ and Gageler J in TCL Air Conditioner v Federal Court:1
“[P]arties who enter into an arbitration agreement for commercial
reasons ordinarily intend all aspects of the defined relationship in
respect of which they have agreed to submit disputes to arbitration to
be determined by the same arbitral tribunal.”2
[29] However, that passage does not suggest a requirement that the defined relationship
must be ascertainable from the arbitration clause considered in isolation. Such a
requirement would be contrary to orthodox principles of construction, particularly
that the whole of the relevant instrument is to be considered in construing its
meaning.3 Clause 12.3.3 falls for interpretation in the broader context of the
document as a whole, which is that it is a clause within a contract. Clause 12.3.3’s
references to the “The Parties” is to the parties to the contract, that is, CMC and
Cheshire. They have a defined legal relationship in that they are parties to a contract.
[30] This answers only part of Cheshire’s argument. Cheshire complains that clause
12.3.3 does not contain any description of the nature of the disputes so as to indicate,
consistently with the s 7 definition, that they are disputes arising between the parties
in respect of their defined legal relationship as parties to the contract. The purported
agreement says nothing as to the nature of the disputes other than that they are
disputes arising between the parties. For this reason, Cheshire contends clause 12.3.3
fails to meet the s 7 definition of an arbitration agreement.
[31] In support of that argument Cheshire emphasised referral to arbitration causes the
significant result of denying the right of adjudication by a court. In submitting that
1 (2013) 251 CLR 533.
2 (2013) 251 CLR 533, 550 [16].
3 See for instance the oft-cited observations on this principle by Gibbs J in Australian Broadcasting
Commission v Australasian Performing Right Association (1973) 129 CLR 99, 109.
-- 8 of 17 --
7
ought not occur unless it is clear the denial was intended, Cheshire cited the following
observation of Fullagar J in Duncombe v Porter about a general principle of
interpretation:4
“Rights which exist at common law or by statute are not to be regarded
as denied by words of dubious import. Before any such denial is
accepted, it must appear with reasonable clarity from the language
used that the denial is intended.”5
[32] In the present case, it is implausible having regard to the language of clause 13.3.3
that no denial at all was intended. It is the breadth of that denial which is the real
issue.
[33] In considering whether the language of clause 13.3.3 is sufficiently clear to deny
Cheshire the court-based pursuit of its claim it is necessary to consider the meaning
of the clause in the context of the contract in which it appears. These reasons earlier
concluded the legal relationship of CMC and Cheshire is a defined one, namely the
relationship of parties to a contract. Such a relationship is defined not merely by the
contract’s specific provisions as to the legal rights and obligations existing between
the parties but also by the general law applicable to such contracting parties. Indeed,
it has been observed it will be sufficient to constitute a defined legal relationship
between parties if there exists a relationship which gives rise to “the possibility that
one is entitled to some form of legal remedy against the other”.6
[34] It is a reasonable inference, premised upon the circumstance that clause 12.3.3 forms
part of the contract into which the parties entered, that the disputes to which it refers
are, at least, disputes in respect of the rights and obligations conferred and imposed
by that contract. Cheshire would argue even this inference goes too far and CMC
would argue it does not go far enough.
[35] Three relevant general principles of interpretation tell against Cheshire’s argument.
The first, already noted, is that the whole of the relevant instrument is to be considered
in construing its meaning. The second is commercial contracts should be construed
to give effect to their commercial purpose.7 This contract’s purpose was the
performance of paid works, which supports the interpretation that disputes about
payment should be caught by clause 12.3.3. The third interpretive principle is that
arbitration clauses should not be construed narrowly.8 On this point, in Incitec Ltd v
Alkimos Shipping Corporation9 Allsop J, as he then was, observed:
“The clear tide of judicial opinion as to arbitration clauses, where the
fair reading of them is not confined, is to give width, flexibility and
amplitude to them.”10
4 (1953) 90 CLR 295.
5 (1953) 90 CLR 295, 311.
6 Methanex Motonui Ltd v Spellman [2004] 1 NZLR 95, 121 [85]; endorsed on appeal [2004] 3 NZLR
454, 471 [62].
7 See for example, McCann v Switzerland Insurance (2000) 203 CLR 579, 589.
8 See for example, Francis Travel Marketing Pty Ltd v Virgin Atlantic Airways Ltd (1996) 39 NSWLR
160, 165; Commandate Marine Corp v Pan Australia Shipping Pty Ltd (2006) 157 FCR 45.
9 [2004] FCA 698.
10 [2004] FCA 698, [36] (citations omitted).
-- 9 of 17 --
8
[36] The application of these principles compels the inference that the disputes to which
clause 12.3.3 refers are, at least, disputes in respect of the rights and obligations
conferred and imposed by the contract in which the clause is found. But how much
further does it reach, if at all?
[37] CMC’s argument at its most extreme would in effect have it that clause 12.3.3’s
reference to disputes arising between the parties encompasses any disputes arising
between them. However, there is nothing in the contract to fuel the objective
attribution of such a free form intention, unconstrained by the context of the contract
within which it is found and the limits of the legal relationship it defines.
[38] CMC relied upon some cases in which clauses referring “all disputes” (or disputes
described in similarly broad language) to arbitration were upheld, despite the
uncertain breadth of their description.11 Significantly, none of these cases suggest
the range of such disputes is to be regarded as unlimited by the context of the source
document. To the contrary, the clauses in those cases were read down to conform
with that context.
[39] The cases in this field vary in articulating the degree or nature of connection the
dispute must have with that context. However, some common threads can be
identified.
[40] In Re Hohenzollern Actien Gesellschaft and City of London Contract Corp12 the
contract, for the supply of locomotives and boilers, provided for arbitration of “[a]ll
disputes”. Payment was conditional upon the purchaser’s engineer’s certification that
the locomotives and boilers had been received in working order. Certification was
not forthcoming and it was optimistically argued there was no dispute because
certification was a condition precedent to entitlement under the contract. Lord Esher
MR observed:
“Now, of course “all disputes” cannot mean disputes as to matters that
have no relation at all to the contract. But I think that those words are
to be read as if they were “all disputes that may arise between the
parties in consequence of this contract having been entered into”. I
think that, as my brother Mathew pointed out in the court below, there
being all these clauses in the contract as to any of which a dispute
might arise, this last clause was added to settle them all.”13 (emphasis
added)
[41] In Woolf v Collis Removal Service14 the arbitration clause related to “any claims upon
or counterclaim to any claim made by the contractors”. The plaintiff claimed
damages for a breach of contract and or negligence because of loss and damage of
goods stored in a location other than the warehouse which the plaintiff had contracted
with the defendants to have the goods stored at. The decision to stay the action
pursuant to s 4 Arbitration Act 1889 was upheld on appeal, Asquith LJ observing:
11 Applicant’s submissions in reply [15]; Roose Industries Ltd v Ready Mixed Concrete Ltd [1974] 2
NZLR 246 (and other cases cited therein).
12 (1886) 54 LT 596.
13 (1986) 54 LT 596, 597.
14 [1948] 1 KB 11.
-- 10 of 17 --
9
“The arbitration clause in the present case is, as to the subject matter
of claims within its ambit, in the widest possible terms. That clause is
not, in terms, limited to claims arising “under” the contract. It speaks
simply of “claims”. This, of course, does not mean that the term
applies to claims of every imaginable kind. Claims which are entirely
unrelated to the transaction covered by the contract would no doubt be
excluded; but we are of opinion that, even if the claim in negligence is
not a claim “under the contract”, yet there is a sufficiently close
connexion between that claim and that transaction to bring the claim
within the arbitration clause, even though framed technically in tort.”15
(emphasis added)
[42] In Astro Vencedor SA v Mabanaft,16 there was a claim in tort for wrongful arrest of a
chartered ship, which arrest had occurred to secure damages allegedly owed in
connection with a claim the shipowner had wrongfully stopped discharging oil during
the charter contract. The claim about stopping the oil was caught by the arbitration
clause, which covered “[a]ny dispute arising during the execution of this charter-
party”. The issue was whether the claim in tort was also within the scope of the
arbitration clause. Lord Denning MR, with whom the rest of the court agreed,
concluded it was, observing the arrest was “the follow-up to” and “so closely
connected to” the claim about stopping the oil as to be within the scope of
arbitration.17 This approach echoes Lord Asquith’s test of sufficiently close
connection in Woolf. Its reference to the chain of causal connection likewise echoes
Lord Esher’s test of consequential connection in Hohenzollern.
[43] In Roose Industries Ltd v Ready Mixed Concrete Ltd,18 a contract for the supply of
metal chips and so-called “all-in” materials referred to both categories in a number of
its clauses, but the clause relating to quality mentioned metal chips only. The
purchaser sought a declaration or alternatively rectification in order to require the
“all-in” materials to conform to the same standard specification as for metal chips.
An arbitration clause applied to “[a]ny dispute which may arise between the parties
to this agreement”. However the primary judge refused a stay of the action to permit
arbitration on the basis the arbitrator would have no jurisdiction to order rectification,
that being “clearly outside the arbitration clause”. That decision was reversed by the
New Zealand Court of Appeal which observed:
“In our view, the court should restrict the operation of such a wide
clause no further than necessary, and on that reasoning should exclude,
in the words of Asquith LJ in Woolf v Collis Removal Service …, only
claims which are entirely unrelated to the commercial transaction
covered by the contract. Here, the essential question in dispute is
whether the parties intended that the “all-in” materials should be
required to conform to the standard specification. That seems to be
very much a question arising out of that commercial transaction. With
great respect …, we cannot agree that the particular dispute is not
within the arbitration clause.”19 (emphasis added)
15 [1948] 1 KB 11, 18.
16 [1971] 2 QB 588.
17 [1971] 2 QB 588, 595.
18 [1974] 2 NZLR 246.
19 [1974] 2 NZLR 246, 249.
-- 11 of 17 --
10
[44] In IBM Australia Ltd v National Distribution Services Ltd,20 IBM agreed to supply
systems integration services, including IBM hardware and software. A dispute arose
regarding the suitability of the hardware and software which manifested as an alleged
breach of the Trade Practices Act 1974 (Cth) for misleading or deceptive conduct.
The relevant arbitration clause was expressed to govern “any controversy or claim
arising out of or related to this agreement or the breach thereof”. In concluding there
was no basis to exclude from arbitration claims arising under the Trade Practices Act,
Handley JA observed the words “related to this agreement or the breach thereof”
should not be read down, noting:
“These words can only have been added to include within the
submission claims other than in contract such as claims in tort, and
restitution, or in equity. I can see no basis for excluding claims arising
under statutes which grant remedies enforceable in or confer powers
on courts of general jurisdiction.”21
[45] In the same case, after engaging a lengthy review of the authorities, Kirby P observed:
“From the foregoing trend of authority, both in Australian and
overseas courts, it can be seen that an arbitration clause, expressed in
the language of the clause here under consideration, is not to be
narrowly construed. It is sufficiently wide to include claims for
rectification and for relief on the ground of misrepresentation or
mistake. … Whilst it is true that the conduct complained of as being
in breach of the Trade Practices Act (Cth) is alone sufficient to enliven
the provisions of that Act and whilst such provisions do not depend
upon the agreement of the parties, such considerations do not
determine the simple question posed. That question is whether the
misrepresentations alleged are “related to this agreement or the breach
thereof”. It is enough to say that, in this case, it was open to …
determine that the relationship was made out on the pleadings.”22
(emphasis added)
[46] In Francis Travel Marketing Pty Ltd v Virgin Atlantic Airways,23 an agency
agreement between an English principal and an Australian agent for air passenger
transport contained an arbitration clause referring “[a]ny dispute or difference arising
out of this Agreement” to arbitration. The dispute arising was a claim for damages
for breach of contract, alternatively equitable damages “arising out of an
unconscionable departure from representations and/or a common assumption made
and induced by the defendant”. A clause of the agreement had provided the
agreement could be terminated at any time on three months’ notice, however it was
allegedly subsequently promised or represented by the English principal there would
be no termination until the end of 1995. Notwithstanding this, the English principal
gave notice of termination in 1994. The English principal’s alleged representation
was said to have induced a common assumption that there would be no termination
until the end of 1995 and was also said to have been a representation involving
misleading or deceptive conduct under the Trade Practices Act. The primary issue
for determination by the New South Wales Court of Appeal was whether the claims
20 (1991) 22 NSWLR 466.
21 (1991) 22 NSWLR 466, 487.
22 (1991) 22 NSWLR 466, 477.
23 (1996) 39 NSWLR 160.
-- 12 of 17 --
11
concerning the purported termination having regard to the alleged representation,
estoppel and misleading conduct gave rise to a dispute or difference arising out of the
agency agreement.
[47] Gleeson CJ, with whom Meagher JA and Sheller JA agreed, distinguished Allergan
Pharmaceuticals Inc v Bausch & Lomb Inc24 where Beaumont J held an arbitration
clause did not cover a dispute under the Trade Practices Act, the agreement merely
being part of the background to the alleged contraventions so that the dispute did not
arise out of it. Gleeson CJ observed:
“In the present case the alleged contravention of the Act arose out of
a representation concerning the duration of the agreement, and the
appellant’s claims concern its purported termination. The agreement
is not merely the background to the dispute. The dispute is about the
agreement, and its performance, and whether it was properly and
lawfully brought to an end.”25
[48] That reasoning has the effect that a dispute pursuing rights said to arise outside a
contract should nonetheless be regarded as arising out of or closely connected with
the contract where the dispute turns upon whether or not the parties’ rights are
constrained by the strict operation of the terms of the contract. The present case
appears to involve just such a dispute, in that CMC relies upon the strictures of the
contract’s payment provisions in contending Cheshire is not owed more, whereas
Cheshire relies on CMC’s conduct to ground a right to further payment
notwithstanding the contractual provisions upon which CMC relies.
[49] In this respect both the present case and Francis Travel are distinguishable from Hi-
Fert v Kiukiang Carriers,26 on which Cheshire placed reliance. In that matter the
issue of current relevance was whether a cargo owner’s claims met the requirement
of the arbitration clause of the charter contract that they arose from the contract. The
claims alleged the charterer of a vessel conveying the cargo had engaged in misleading
and deceptive conduct, made negligent misrepresentations and breached collateral
warranties. Those claims related to conduct said to have induced the cargo owner to
have entered into an addendum contract. The Full Court of the Federal Court
considered the alleged loss would not have been suffered but for the entry into the
addendum contract, as distinct from the charter contract, and concluded the claims did
not arise out of the charter contract.27 In contrast, in the present case there is only said
to be one contract and the work performed by Cheshire would not have been
performed but for the entry into that contract.
[50] Cheshire also relied upon Inghams Enterprises Pty Ltd v Hannigan,28 where the New
South Wales Court of Appeal reversed a primary judge’s determination that a claim
for damages for breach of contract fell within the scope of the arbitration subclause
of the dispute resolution clause in the contract. The clause was relevantly worded as,
“the Dispute concerns any monetary amount payable and/or owed by either party to
the other under this Agreement” (emphasis added). The New South Wales Court of
Appeal concluded Mr Hannigan’s claim for unliquidated damages was not a claim
24 (1985) ATPR 40-636.
25 (1996) 39 NSWLR 160, 166-167.
26 (1998) 90 FCR 1.
27 (1998) 90 FCR 1, 17, 22 (per Emmett J with whom Branson J agreed and Beaumont generally agreed).
28 (2020) 379 ALR 196.
-- 13 of 17 --
12
for an amount payable or owed “under” the contract. Meagher JA, agreeing with Bell
P, observed:
“The distinction between monetary amounts which are payable or
owed “under a contract” and remedies which arise by operation of law
is a recognised and meaningful one. Whereas ‘liquidated damages’
are recoverable in satisfaction of a right of recovery created by the
contract itself and accruing by reason of breach, unliquidated damages
for breach of contract are compensation assessed by the court in
accordance with common law principles for loss occasioned by
breach. …
It follows that the notified dispute does not concern a monetary
amount payable or owed by Inghams to Mr Hannigan under their
agreement and accordingly it is not a dispute referred to arbitration by
clause 23.6.1.”29
[51] That conclusion was an inevitable result of the arbitration clause’s specific
confinement to disputes concerning any monetary amount payable or owing “under”
the agreement. The present clause has no such specificity. There is nothing in it to
suggest it ought to be read down as applying only to amounts payable under the
contract as distinct from amounts payable by operation of law. Indeed, the parties’
decision to impose no qualification on the nature of the disputes referred to in clause
12.3.3 of the contract supports a liberal width being given to the degree of connection
the disputes should have with the contract in order to come within the clause’s reach.
[52] Section 8 of the Act directs attention to the matter which is the subject of Cheshire’s
claim in the Supreme Court. That matter might be stated in various ways but at its
most fundamental it is the question of whether Cheshire should be paid more than it
already has been for works it was contracted to perform. Admittedly, that question
arises out of the conduct relied upon to raise an entitlement to payment other than
pursuant to the contract. But it is also, to adopt the language of Roose Industries,
very much a question arising out of the commercial transaction to which the contract
gave rise.
[53] A dispute about the question is a dispute arising between the parties out of the
commercial relationship created by the contract. But for that relationship, Cheshire
would not have been performing the works for CMC for which it seeks more payment.
The connection between the contract and the performance of the work gives the
dispute the degree of close and consequential connection with the contract which is
contemplated by authorities such as Hohenzollern, Woolf and Astro Vencedor.
Further, consistently with the quality contemplated in Francis Travel, the dispute
turns upon whether or not the parties’ rights are constrained by the strict operation of
the terms of the contract or whether events between the parties should found a right
to payment beyond the terms of the contract. These features in combination compel
the conclusion that Cheshire’s claim has been brought in a matter which is the subject
of an arbitration agreement.
[54] That conclusion must result in the application succeeding, unless the court finds the
arbitration agreement is null and void, inoperative or incapable of being performed.
Cheshire argued clause 12.3.3 is inoperative.
29 (2020) 379 ALR 196, 245 [150] – [151] (citations omitted).
-- 14 of 17 --
13
[55] In part that argument relied upon the same arguments unsuccessfully advanced in
contending the clause is too vague or uncertain to meet the s 7 definition. In support
of that contention Cheshire additionally cited Yeshiva Properties No 1 Pty Ltd v
Lubavitch Magal Pty Ltd,30 apparently as an example of a case considering reference
to “all” disputes where such language was considered too uncertain to leave the matter
to arbitration. However, consideration of that matter does not assist by parity of
reasoning because its relevant facts were considerably vaguer than the present case,
including the absence of a formal document and lack of intention to be bound until
such a document was executed. For reasons already given as to the proper
interpretation of clause 12.3.3, the clause was not so vague or uncertain that
contractual effect ought not be given to it.
[56] Cheshire’s written outline of argument indicated inoperability would be argued on
the basis that Cheshire’s reliance upon estoppel by convention precluded reliance
upon the contract including the arbitration agreement,31 citing CPB Contractors Pty
Ltd v Celsus Pty Ltd32 and that case’s reference to the Singapore High Court decision
in Dyna-Jet Pte Ltd v Wilson Taylor Asia Pacific Pte Ltd.33 In CPB Contractors,
after referring to Dyna-Jet, Lee J concluded an arbitration agreement will be
inoperative where it has ceased to have effect, though how it may cease to have effect
will vary in individual cases.34 His Honour concluded a construction arbitration
agreement did not cease to have effect by reason of a mediated agreement not
involving the builder or a completion deed clause establishing a further consolidated
arbitration process.
[57] In the present case Cheshire’s reliance upon estoppel by convention merely seeks to
establish a right to payment not provided for by the contract. The pursuit and
existence of such a right does not appear to be inconsistent with the continued
operation of the contract and its arbitration clause.
[58] In oral argument Cheshire’s argument broadened to the submission that its complaints
of statutory unconscionability were non-arbitrable.35 It was argued there is an
implicit public interest dimension to the category of unconscionability relied upon in
ss 20 and 21 Australian Consumer Law. It was highlighted, for example, that those
sections allow the court to have regard to industry codes of conduct (not that such
codes are said to be relevant to Cheshire’s claim). Cheshire placed reliance upon an
observation of Allsop J in Commandate Marine Corp v Pan Australia Shipping Pty
Ltd36 that a common element to the notion of non-arbitrability in the context of
international arbitration is that a sufficient element of legitimate public interest in the
disputed matters makes the enforceable private resolution of the dispute outside the
national court system inappropriate. However, that is not the context with which the
present matter is concerned.
30 [2003] NSWSC 615 [52]; Plaintiff’s outline of argument [18].
31 Plaintiff’s outline of argument [19].
32 (2017) 353 ALR 84, 98-100.
33 [2016] SGHC 238 [166].
34 (2017) 353 ALR 84, 100.
35 T 1-33 L 11 (the submission included reference to the complaint of estoppel by convention
but the argument which developed focussed upon the complaints of statutory unconscionability).
36 (2006) 157 FCR 45, 98.
-- 15 of 17 --
14
[59] It is uncontroversial that, as the plurality observed in Westfield Management v AMP
Capital,37 the policy of the law is against enforcing contractual arrangements which
“operate to defeat or circumvent a statutory purpose or policy according to which
statutory rights are conferred in the public interest, rather than for the benefit of an
individual alone”. However, is also well established it is an implied term of an
arbitration clause that the arbitrator should reach a decision according to the existing
law of the land and should exercise every right and discretionary remedy given to a
court of law.38 Cheshire has not demonstrated how reference to mediation in the
present context would deprive it of the protection of the provisions of the Australian
Consumer Law on which its claim relies. The arbitrator will be obliged to determine
Cheshire’s disputed right to payment considering those provisions to the extent they
are relevant to the facts as found by the arbitrator.
[60] The above analysis demonstrates there is no substance to Cheshire’s arguments as to
inoperability. On the materials presently before the court39 it has not been shown the
court should make a finding pursuant to s 8 that the arbitration clause is inoperative.
[61] If follows s 8 of the Act requires this court to refer the parties to arbitration pursuant
to clause 12.3.3 of their contract.
[62] That conclusion has been arrived at on the premise that the claim is for relief based
on estoppel by convention or statutory unconscionable conduct and does not seek the
additional order about the bank guarantee. Enlarging consideration now to the matter
of the bank guarantee does not alter the conclusion, indeed it fortifies it. In oral
submissions Cheshire’s counsel categorised the foundation of the order as being part
of its unconscionability case.40 That is not apparent from Cheshire’s pleading. In
any event the provision of the bank guarantee was a contractual requirement, so any
dispute as to its return inevitably involves a sufficiently close and consequential
connection with the contract that it is a matter which is subject to clause 12.3.3.
Conclusion
[63] CMC has made good its argument that the parties should be referred to arbitration
pursuant to s 8 of the Act.
[64] CMC’s application also sought a “permanent stay” of Cheshire’s proceeding. In the
present context the integrity of the reference can be safeguarded simply by a stay. It
will in effect operate as a stay of permanent effect unless, in consequence of some
event or decision in the arbitration process, the dispute cannot be determined by
arbitration. Such a development could ground an application to lift the stay.
[65] On the face of it costs should follow the event but I will allow the parties an
opportunity to be heard.
37 (2012) 247 CLR 129.
38 Government Insurance Office v Atkinson Leighton Joint Venture (1981) 146 CLR 206, 234-235, 246-
247.
39 A qualification added in deference to the possibility this court is not presently possessed of all
information which may be put before an arbitrator - see Rinehart v Rinehart (No 3) (2016) 257 FCR
310, 347.
40 T 1-34 L 42.
-- 16 of 17 --
15
Orders
[66] My orders are:
1. The parties are referred to arbitration pursuant to s 8(1) Commercial Arbitration
Act 2013 (Qld).
2. Cairns Supreme Court proceeding 571/20 is stayed.
3. I will hear the parties as to costs, if costs have not been agreed in the meantime,
at 9.15am 28 April 2021 (out of town parties having leave to appear by
telephone or video-link).
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2021/075