ACP Properties (Townsville) Pty Ltd v Rodrigues Construction Group Pty Ltd & Anor [2021] QSC 45 [2021] 11 QLR
SUPREME COURT OF QUEENSLAND
CITATION: ACP Properties (Townsville) Pty Ltd v Rodrigues
Construction Group Pty Ltd & Anor [2021] QSC 45
PARTIES: ACP PROPERTIES (TOWNSVILLE) PTY LTD
ACN 631 282 203
(applicant)
v
RODRIGUES CONSTRUCTION GROUP PTY LTD
ACN 164 580 401
(first respondent)
AND
WARREN DAVID FISCHER
(second respondent)
FILE NO/S: 12791 of 2020
DIVISION: Trial
PROCEEDING: Hearing
ORIGINATING
COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON: 26 February 2021 (ex tempore)
DELIVERED AT: Brisbane
HEARING DATE: 26 February 2021
JUDGE: Bradley J
ORDERS: THE ORDER OF THE COURT IS THAT:
1. It is declared that the decision of the Second
Respondent dated 6 November 2020 and numbered
935267 is void for want of jurisdiction and of no
effect.
2. The amount paid into Court by the Applicant
pursuant to paragraph 1 of the order of 3 December
2020 (December Order), together with any accretions
thereto, be paid out to the Applicant forthwith.
3. The First Respondent pay the Applicant’s costs of the
issue reserved in the December Order for separate
determination (referred to as the Adjudication
Validity Issue) on the standard basis.
4. The December Order is amended to reflect that the
order was made by Ryan J and not Crow J.
-- 1 of 11 --
2
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
PAYMENT CLAIMS – PAYMENT SCHEDULES – where
the applicant engaged the first respondent to undertake
refurbishment work of a commercial building – where the
applicant challenges the validity of an adjudication decision
made by the second respondent adjudicator under the Building
Industry Fairness (Security of Payment) Act 2017 – whether
an invoice issued by the first respondent contained sufficient
detail to make it a payment claim within the meaning of the
Act – whether two emails from the applicant to the first
respondent constituted payment schedules within the meaning
of the Act – whether the adjudicator’s failure to recognise
either email as a payment schedule is a jurisdictional error that
invalidates the adjudication decision, or, whether the error was
within jurisdiction and does not invalidate the adjudication
decision
Building Industry Fairness (Security of Payment) Act 2017, s
68, s 69, s 82, s 88
Heavy Plant Leasing Pty Ltd v McConnell Dowell
Constructors (Aust) Pty Ltd [2013] QCA 386
KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd &
Ors [2019] QSC 178
Melaleuca View Pty Ltd v Sutton Constructions Pty Ltd
[2019] QSC 226
Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd
[2009] QSC 376; [2011] 1 Qd R 17
T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QCA
381; (2011) 27 BCL 280
COUNSEL: N H Ferrett QC and J P Hastie for the applicant
B E Codd for the first respondent
SOLICITORS: Archibald & Brown for the applicant
Rostron Carlyle Rojas Lawyers for the first respondent
[1] In this case, the applicant (ACP) challenges the validity of an adjudication decision
made by the second respondent (the adjudicator) under the Building Industry
Fairness (Security of Payment) Act 2017 (the Act). There are two grounds.
[2] Firstly, ACP contends that an invoice and its attached documents issued by the first
respondent (RDG) on 4 September 2020 (the RDG Invoice), lacked sufficient detail
to make it a payment claim within the meaning of the Act. If the RDG Invoice is not
a payment claim, then ACP and RDG are agreed that the adjudicator had no
jurisdiction to make the adjudication decision under the Act.
-- 2 of 11 --
3
[3] Secondly, ACP contends the adjudicator failed to recognise two emails from ACP to
RDG (the ACP emails) as payment schedules within the meaning of the Act. The
emails were sent on 4 and 7 September 2020 respectively. There are competing
positions between ACP and RDG about the consequences if one (or both) of the ACP
emails was a payment schedule. ACP contends the adjudicator’s failure to recognise
either as a payment schedule is a jurisdictional error that invalidates the adjudication
decision. RDG contends that, if such an error occurred, it was within jurisdiction and
does not invalidate the decision.
[4] Appropriately, the adjudicator made no submissions, called no evidence and abides
the decision of the court.
[5] By an order of 3 December 2020, Ryan J directed that this issue of the validity of the
adjudication decision be reserved for separate determination.
Background
[6] ACP is the owner of the Townsville Transit Centre, a commercial building. It
engaged RDG to undertake construction work in the form of refurbishing the
building. For the purposes of this application, ACP and RDG are content for the court
to assume that this construction work was undertaken pursuant to a building contract.
ACP has identified a report from a quantity surveyor dated 13 September 2019 that
included a detailed cost estimate and a detailed scope of works for what were then
proposed works.
RDG invoice
[7] On 4 September 2020, RDG sent ACP the link to the RDG Invoice it contends is a
payment claim. By the invoice, RDG claimed a total of $237,574.62. Of this amount,
$39,150.80 was for items RDG had not previously invoiced to ACP. The balance of
$198,423.82 was for items that had been the subject of previous invoices delivered
by RDG to ACP.
[8] The newly invoiced items were described in this way:
Description Quantity Unit Price GST Amount AUD
Timesheets/labour on-
charged referred to attached
spreadsheet – no margin
charged
1 $3,805.13 10% $3,805.13
Supplier invoices on-charged 1 $10,871.17 10% $31,786.51
Subtotal $35,591.64
Total GST 10% $3,559.16
Subtotal including GST $39,150.80
[9] The RDG Invoice was accompanied by a series of annexures. These included
timesheets for a number of employees, which stated the times the employees had
worked. They did not identify the nature or type of work undertaken by the
employees during those times.
-- 3 of 11 --
4
[10] RDG also attached a document entitled, “Billable expenses – outstanding”. It listed
a number of subcontractors with an amount for each. The list totalled $31,784.51,
which was the supplier invoices on-charged included in the invoice. RDG attached
supplier invoices from those suppliers included in the list. As might be expected,
each of these invoices identified the supplier and the amount of the invoice. Some
did not identify the work or materials supplied or when this had occurred or where in
the building the construction work was done.
[11] The second part of the RDG Invoice sets out the dates, invoice numbers and amounts
of invoices RDG had issued to ACP between 1 June and 17 August 2020. As noted,
these previously issued invoices total $198,423.82. The RDG Invoice was sent via
email link at 5.03 pm on 4 September 2020.
The ACP emails
[12] At 5.14 pm that same day, Mr Campbell of ACP responded with the first of the
relevant emails, which ACP contends was a payment schedule. He wrote:
“Hi Natalie
I have just had a look at this and appear [sic] there is a gap in
understanding.
I acknowledge RDG has continued to invoice on a cost plus basis but
this was capped at $2.7m +. The additional charges are clearly
overruns from your side for which I am not responsible for as the
project is now 9 months over.
The contract was for $2.7m + GST. The variation is SPNQ in the main
which the QS will review but early discussions with the QS is this will
be less than $100k as there are pluses and minuses (i.e. windows put
in place of doors so the windows get added and the doors get minused).
I have paid nearly $2.8m + GST. So broadly speaking I believe I have
paid in full there may be amounts go either way but these will be small.
Once the SPNQ variations are assessed is the only other charge that
needs pulled out is the cost of airfares and hotel as these are separate
to contract.
Regards,
Stephen Campbell / Managing Director”
[13] The reference to “SPNQ” might be better understood in light of the covering email
which Natalie of RDG forwarded with the link to the RDG Invoice. It read:
“Stephen.
Please see link below with new invoice. I have included all invoices
that have not been reviewed by yourself as Mark mentioned you are
getting a quantity surveyor to review.
My apologies for not having the SPNQ information as asked by
yourself and Mark, as I have had two sick children at home for the last
-- 4 of 11 --
5
two weeks, and I am still awaiting information from Damien Chapman
to complete, I hope to have this next week. Again, my apologies,
Natalie.
[14] After Natalie received Mr Campbell’s 4 September email she responded:
“Stephen
I completely understand what you are saying however Mark instructed
me to send through for your QS. As previously stated I will send
through costings for SPNQ this week.
Natalie”
[15] The second email, which ACP also contends is a payment schedule, was sent at 11.47
pm on 7 September 2020. It was a direct response to the Natalie email set out
immediately above. In it, Mr Campbell wrote:
“Hi Natalie.
Noted. Not sure how relevant for the QS but I will pass as appropriate.
However, do note that my review showed these invoices appeared to
be for works within scope hence part of the $2.7m+ already paid IN
FULL. Whilst I note there were errors made on invoices these are
irrelevant given I have paid the cost of contract already. Invoice errors
do not push up the cost of the contract as you would appreciate. RDG
continued to issue invoices based on Cost plus but having missed the
$2.7m + capped price via your internal systems and as a result I am
clearly well ahead. You should probably be returning the money paid
in advance of works. Hence as previously advised these overruns are
at RDG risk which was also confirmed by the QS.
I have seen the SPNQ list sent through by Mark earlier today. I have
raised that their approvals were to be in writing so I will go digging
for approvals as a number of things on the list are not their works but
works already covered under the contract to which I have advised
Mark. However I will check what I have on record now I have a view
of what he considers included. To prevent any argument the QS will
be provided the list Mark has sent through and make a determination
on each item separately as to whether these were part of the scope or
otherwise and if otherwise he will provide a costing based upon the
additional works less allowed works, that is the plus and minus.
I personally do not see the logic in your trying to apply a costing as
Mark and I had agreed (I thought) that the QS would issue the report
and costings which I was happy to abide by. Nonetheless I appreciate
you have to do as instructed. But I am highlighting that I will not be
acting upon anything sent to me until the QS has finalised the report
which will also include gap to scope or works left to complete and an
early stage defects report. I would also like to state for the record the
delays as to instructing the QS have been the result of RDG not issuing
they’re considered view until today (I have been requesting since
June) and not on my end. Furthermore give my conversation with the
-- 5 of 11 --
6
QS included all of the list of the SPNQ works sent through today I am
more than comfortable with my stated position based upon the QS
advice that these variations will be sub $100k. Which also happens to
be the figure provided to me by Mark at the time, which was the basis
of the loan amount for the project $2.7m build + 100k variations =
$2.8m financed amount.
I would appreciate you splitting out the flights and Marks
accommodation for me as there will be extra here I think but small yet
as mentioned I am actually well ahead at this point but these will be
valid.”
[16] ACP did not pay any amount to RDG in respect of the RDG Invoice.
[17] On 15 October 2020, RDG applied for an adjudication under the Act. On 29 October
2020 ACP gave RDC and the adjudicator a document described as an adjudication
response.
[18] On 6 November 2020, the adjudicator delivered the decision. In it, the adjudicator
concluded that the RDG Invoice was a valid payment claim for the purposes of the
Act and that neither of the ACP emails was a payment schedule for the purposes of
the Act.
Was there a valid payment claim?
[19] The first issue is whether the RDG Invoice was a payment claim. ACP contends that
the invoice was not a payment claim because it did not meet the requirement in section
68(1)(a) of the Act that it be a document that “identifies the construction work or
related goods and services to which the progress payment relates”.1
[20] In written and oral submissions, counsel for ACP have identified a number of bases
upon which they contend that the RDG Invoice contained insufficient detail. I have
been taken to many of the attachments to the invoice. The submissions may be
considered in this way:
(a) First, that the RDG Invoice failed to identify the specific nature or type of work
undertaken by the employees, for whom timesheets were attached and an
amount was claimed.
(b) Secondly, that some of the supplier invoices attached to the RDG Invoice
lacked detail as to the work done or the materials supplied.
(c) Thirdly, the RDG Invoice and its attachments had insufficient detail as to where
within the building, and when in time, the work was undertaken.
(d) Fourthly, there was no explanation as to how the work claimed in the RDG
Invoice related to the QS report obtained before parties entered into the
contract.
1 Section 68(1)(a) provides that a payment claim for a progress payment, is a written document that
identifies the construction work or related goods and services to which the progress payment relates.
-- 6 of 11 --
7
(e) Finally, the inclusion of all the previous invoices in this new invoice gave rise
to an oppressiveness, as a large amount of material had to be processed in a
small amount of time, which ought not to be tolerated by the court.
[21] As to the first submission, the inclusion of the timesheets and their relevant amounts
in the RDG Invoice was plainly an assertion that the work done by those of its
employees at those times, on those days, for those hours, was work on the project. I
understand the complaint to be about the extent that the information did not allow
ACP to know, with precision, which parts of the project the employees were working
on, on each of those days, or during each of those hours.
[22] The total sum involved ($3,805.13) is relatively modest in the scale of the project. At
this distance, providing the days worked, the employees working and their hours each
day, in respect of such a modest amount seems sufficient detail to reasonably identify
the basis of the claim and allow ACP to reasonably comprehend and form a judgment
as to whether that amount claimed should be paid or should be rejected, in whole or
in part, perhaps on the basis that it might be, to some extent, work outside the scope
of the contract.2
[23] The second complaint concerns the supplier invoices. In most of the supplier invoices
to which I was taken, the supplier identifies the type of work in which they were
engaged, and identifies the work, material or services they were supplying and the
amount for each of those. It is true that a few supplier invoices are quite scant as to
detail. If any is so lacking in detail as to make it insufficient, then the RDG
submission, about whether a payment claim is void as a whole when some of the
work, goods or services for which payment is claimed is sufficiently identified and
some is not and whether that might be dealt with by way of severance, would be of
relevance. Because of the view I have formed about other matters in the case, it is
unnecessary to go to the level of examining further each of the supplier invoices
attached to other invoices attached to the RDG Invoice for the sufficiency of detail it
contains.
[24] As to the third and fourth grounds of criticism of the RDG Invoice, these proceed on
an assumption that, in order to provide sufficient detail to amount to a payment claim,
it was necessary for RDG to correlate the work in each supplier invoice,
subcontractor’s invoice, and timesheet to an item in the QS report. ACP submitted
this was necessary to allow the claim to be reconciled to a specific contractual
obligation. I reject that submission. A payment claim must provide sufficient
identification of the work for which payment is claimed. The requirements for a
payment claim under the Act do not pick up contractual requirements entered into
between parties. They do not require a claimant to go to the level of detail which ACP
here appears to demand.
[25] Finally, the inclusion in the RDG Invoice of all previous invoices, which had been
issued but had not been the subject of any earlier payment claim, was not, in my view,
oppressive. The work involved in considering and responding to a payment claim is
undoubtedly considerable in many cases. For contracts for building work of the order
of $2.7 million, like this one, a principal party should ordinarily expect to have to
exert itself to monitor, review and consider payment claims against the contract and
2 See: T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd (2001) 27 BCL 280; [2010] QCA 381 at [31]-[41].
-- 7 of 11 --
8
against other information it has relevant to the progress, sufficiency, completeness
and quality of the work.
[26] The short timeframes imposed by the Act call for resources to be available to address
these matters when payment claims are made. The fact that ACP had all of these
previous invoices over periods preceding the issue of the RDG invoice – some for up
to three months - is an additional factor that leads me to conclude that the inclusion
of the previous invoices in the RDG Invoice was not oppressive in the sense identified
by White J in Neumann Contractors3 and by Brown J in KDV Sport.4
[27] For all of these reasons, I am not persuaded that the invoice issued by RDG was
insufficiently detailed to be a payment claim within the meaning of the Act.
Were there valid payment schedules?
[28] The second question is whether either or both of the emails of 4 and 7 September
2020 was a payment schedule for the purposes of the Act.5
[29] The complaint RDG agitated here today, having been raised before the adjudicator,
is that the emails failed to state the amount of the payment, if any, that ACP proposed
to make.6 And, if ACP proposed to make a payment of less than the amount claimed
in the RDG Invoice, then ACP failed to state why the amount proposed to be paid
was less.7
[30] RDG’s submissions on this question proceed on a reading of the emails which I do
not consider to be reasonably open. In my view, in each of the emails Mr Campbell
made very clear that he considered no amount was payable under the contract in
respect of the RDG invoice and that ACP proposed to pay no amount. He explained
his reasons for this position in simple terms. He asserted that the contractual
arrangement was capped at a specific amount and that ACP had already paid RDG an
amount in excess of that cap.
[31] The interpretation of the emails is complicated by the references throughout them to
two other matters: one is “the SPNQ information” and the other is flights and
accommodation.
[32] As to the first, RDG urges that the court should interpret the emails on an assumption
that the RDG Invoice included claims for a variation to the contract for the “SPNQ”.
If that assumption were to be made, then RDG seeks to persuade the court to read the
4 September 2020 email as if it left open the prospect that ACP would pay a further
amount to RDG for the SPNQ work. In my view, the assumption is not sufficiently
established by the email trail for the court to act upon it. The emails from Natalie
tend to show that the SPNQ information was still being assembled at the time the
RDG Invoice was sent and that, even after the invoice was sent, it was still being put
together.
3 Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd [2011] 1 Qd R 17 at [29].
4 KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd & Ors [2019] QSC 178 at [49].
5 s 69
6 s 69(b).
7 s 69(c).
-- 8 of 11 --
9
[33] Even if the assumption RDG proposes could be made, the email of 4 September could
not be clearer. In it, Mr Campbell says that he has already paid about $100,000 more
than the capped price that he asserts applies under the contract for the work. And he
observes that his discussions with the quantity surveyor are to the effect that the
amount of the SPNQ variation, when it is finally assessed, will be less than $100,000
so that no further amount will be payable from ACP to RDG.
[34] As to the cost of airfares and accommodation, in the 4 September email, Mr Campbell
asserts that these are “separate to contract”. And, in the 7 September email, he refers
to them as “extra”. For RDG, it is asserted that these costs are amounts payable under
the contract. I note that the adjudicator appears to have formed the same conclusion.
It may well be correct. But the proposals from Mr Campbell to pay these amounts
when they are separated out or, to use his words, pulled out, is expressly on the basis
that they are not amounts due under the contract but are “separate to contract”. His
proposal or offer to pay any amount that might be established for such flight and
accommodation costs could not reasonably be read as an assertion that he would pay
them under the contract pursuant to the RDG Invoice in a way that conceded them
for the purposes of the processes under the Act.
[35] In all the circumstances, each of the ACP emails was a payment schedule. The
adjudicator’s conclusion to the contrary was in error.
Consequences for the adjudicator’s error
[36] The adjudicator accepted RDG’s submissions that both emails from Mr Campbell
were not payment schedules. As a consequence the adjudicator considered he was
obliged not to consider them and not to consider any adjudication response provided
by ACP in deciding the adjudication application. In both these respects the
adjudicator was in error. Section 88(2)(d) of the Act required the adjudicator in
deciding the adjudication application to consider the payment schedules, and the
adjudicator also wrongly excluded the adjudication response because of the first
erroneous decision.
[37] For RDG it was contended that the court could regard these as being errors within the
adjudicator’s jurisdiction. As I understood this submission, it was made on the basis
that the adjudicator had, in fact, considered the emails for the purpose of deciding
whether either was a payment schedule and that his consideration of the emails for
that purpose meant that there was compliance with section 88(2)(d):
“In deciding an adjudication application, the adjudicator is to consider
the following matters only - …
(d) the payment schedule, if any, to which the application relates,
together with all submissions, including relevant documents,
that have been properly made by the respondent in support of
the schedule”.
[38] It is plain from the adjudicator’s decision that he considered the emails only for the
purpose of deciding whether either or both was a payment schedule. Having decided
they were not, the adjudicator determined the adjudication application without
consideration of the payment schedule documents and, of course, without
consideration of an adjudication response.
-- 9 of 11 --
10
[39] The error was one which affected the exercise by the adjudicator of his jurisdiction
to determine the adjudication application. I do not accept the submission that the
error was one within jurisdiction. It was an error that led the adjudicator to act
contrary to the obligations set out in subsection 88(2). The failure to consider the
payment schedules in deciding the adjudication application was a jurisdictional error
because:
“The adjudicator lacked authority to decide an adjudication
application, where a payment schedule existed and was relied on by
the respondent to the application, other than by reference to that
payment schedule.”8
[40] As Brown J explained more recently in Melaleuca View:
“Section 88(2) of the Act provides that the adjudicator is to consider,
amongst other things, the payment schedule and an adjudication
response, unless it is prohibited from being taken into account by the
operation of s 82. The determination of whether or not there is a
payment schedule as provided for under the Act determines the scope
of the adjudicator’s jurisdiction, since its existence or absence
determines what the adjudicator may have regard to when making a
determination.
The language of s 88, which prescribes the “only” matters the
adjudicator is to consider in making a decision and excludes
consideration of an adjudication response in the absence of a payment
schedule having been given in accordance with s 76, supports the
contention that the determination of whether or not a document
constitutes a “payment schedule” is a jurisdictional fact. That fact is
one that must be determined prior to considering the matters provided
under s 88(2) of the Act and the making of any decision. While an
adjudication can still proceed in the absence of a payment schedule,
the scope of the decision-making process that is undertaken by the
adjudicator is determined by the presence or absence of a payment
schedule. The effect of a finding that no payment schedule has been
provided is that the respondent is precluded from making any response
in opposition to the claimant before an adjudication is made. Unlike
the 2004 Act, there is not a further opportunity to provide a payment
schedule after notice has been given of the claimant’s intention to
apply for adjudication of the payment claim. The language of s 88 and
the legislative scheme whereby a party is precluded from having its
adjudication response considered as part of the adjudication support
the conclusion that the existence of a payment schedule is a
jurisdictional fact. I find that the determination of whether the 19
February email constitutes a payment schedule is a jurisdictional
fact.”9
[41] The adjudicator’s failure to consider the payment schedules in deciding the
adjudication application, and the adjudicator’s consequential refusal to consider an
8 Heavy Plant Leasing Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [2013] QCA 386 at [59]
(Muir JA).
9 Melaleuca View Pty Ltd v Sutton Constructions Pty Ltd [2019] 226 at [43]-[44] (footnotes omitted).
-- 10 of 11 --
11
adjudication response, have the consequence that the adjudicator’s decision is void
for want of jurisdiction and so is of no effect.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2021/045