Calmmonth Pty Ltd v AVJennings Properties Limited [2021] QSC 3 [2021] 5 QLR
SUPREME COURT OF QUEENSLAND
CITATION: Calmmonth Pty Ltd v AVJennings Properties Limited
[2021] QSC 3
PARTIES: CALMMONTH PTY LTD IN ITS CAPACITY AS
TRUSTEE OF THE CALMMONTH TRUST
ACN 134 449 988
(plaintiff)
v
AVJENNINGS PROPERTIES LIMITED
ACN 004 601 503
(defendant)
FILE NO: BS 11433 of 2017
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON: 27 January 2021
DELIVERED AT: Brisbane
HEARING DATE: 9 – 11 November 2020
JUDGE: Applegarth J
ORDERS: Subject to any submissions as to the form of order or costs:
1. Judgment for the defendant.
2. The plaintiff pay the defendant’s costs of and incidental
to the proceeding, including reserved costs, to be assessed
if not agreed.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES
– CONSTRUCTION AND INTERPRETATION OF
CONTRACTS – IMPLIED TERMS – GENERALLY – where a
developer undertakes a major residential development in stages
– where a consultant to the developer is entitled to be paid a fee
on the sale of lots – where the consultant is also entitled to an
additional fee if the revenue from the sale of each relevant stage
exceeds the estimated revenue for that stage as set out in a
consultancy agreement – where the development in fact occurred
in different stages to that contemplated by the consultancy
agreement – where the express terms of the consultancy
agreement do not entitle the consultant to an additional fee in
respect of new stages of the development – where the consultant
submits that the agreement contains an implied term entitling it
to an additional fee if the boundary of a relevant stage changed
or an additional stage was added to an overall stage –whether the
consultancy agreement contains the implied term contended for
-- 1 of 27 --
2
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES –
FORMATION OF CONTRACTUAL RELATIONS –
CONTRACT IMPLIED FROM CONDUCT OF PARTIES –
where the parties met to discuss the calculation of fees payable
under a consultancy agreement –consultant disputes that an
agreement to vary the consultancy agreement was reached at the
meeting – where the consultant sent an email following the
meeting confirming that an agreement was reached – whether an
agreement was reached to vary the consultancy agreement
Attorney General of Belize v Belize Telecom Ltd [2009]
1 WLR 1988; [2009] UKPC 10, cited
Australian Securities and Investments Commission v
Hellicar & Ors (2012) 247 CLR 345; [2012] HCA 17, cited
Brambles Holdings Ltd v Bathurst City Council (2001) 53
NSWLR 153; [2001] NSWCA 61, cited
Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd (2001)
117 FCR 424; [2001] FCA 1833, cited
Codelfa Construction Pty Ltd v State Rail Authority of New
South Wales (1982) 149 CLR 337; [1982] HCA 24, cited
Gemmell Power Farming Co Ltd v Nies (1935) 35 SR (NSW)
469, cited
Jones v Dunkel (1959) 101 CLR 298; [1959] HCA 8, applied
Kuhl v Zurich Financial Services Australia Ltd (2011) 243 CLR
361; [2011] HCA 11, cited
Philips Electronique Grand Public SA v British Sky
Broadcasting Limited [1995] EMLR 472, cited
Watson v Foxman (1995) 49 NSWLR 315, cited
COUNSEL: D J Butler for the plaintiff
C A Johnstone, with M Eade, for the defendant
SOLICITORS: Bartley Cohen for the plaintiff
McCullough Robertson for the defendant
[1] AVJennings contracted with the owner of land at Coomera to undertake a large
residential development. Calmmonth was to assist AVJennings in the management
and marketing of the development and, in return, was to be paid certain fees based on
the sale of the developed lots.
[2] The parcel of land subject of this dispute, comprising “super-lots” 1, 4 and 5, was to
be developed in certain numbered stages. Relevant to this dispute are Stages 4 and 9.
[3] Under the consultancy agreement, Calmmonth was to be paid a fee of 2.5 per cent
upon the sale of each individual lot. It might also be paid an additional fee of 33.8
per cent of any difference between the actual gross proceeds for the sale of all lots in
a stage and the estimated gross proceeds set out in “Table A” of the agreement.
[4] The contractual provisions for calculating Calmmonth’s additional fee were premised
on the land being developed, relevantly, in Stages 4a, 4b, 9a, and 9b, and on certain
“Management Lots” being developed as part of Stage 9. The development ultimately
did not proceed in that form. Stage 4, as developed, comprised Stages 4a, 4b and 4c.
-- 2 of 27 --
3
Stage 9 comprised Stages 9a, 9b and 9c. The management lots were “deleted” and
replaced by eight traditional lots across Stage 9.
[5] Calmmonth claims that it is due an additional fee under the agreement in relation to
Stage 4 and Stage 9 of the development, totalling approximately $1.62 million. Due
to the changes in the way the land was in fact developed, the express terms of the
consultancy agreement do not allow Calmmonth to claim the additional fee claimed
by it.
[6] Calmmonth contends that a term should be implied into the agreement providing for
it to be entitled to an additional fee where the boundaries of a sub-stage change, or
where a further sub-stage is included within the boundary of an overall stage.
AVJennings responds that the legal requirements for such a term to be implied are
not proven, and that Calmmonth is therefore not due such an additional fee.1
[7] AVJennings also points to a meeting held between the parties, and correspondence
and conduct following that meeting, by which it contends that an agreement was
reached to vary the consultancy agreement to provide a different arrangement for
Calmmonth’s additional fee. Alternatively, it contends that Calmmonth is estopped
from denying that the consultancy agreement was so varied. Calmmonth denies that
any agreement to vary the consultancy agreement was reached at the meeting or at
any time thereafter.
[8] In attempting to resolve matters, AVJennings paid to Calmmonth an amount which
AVJennings had calculated as the additional fee due on Stage 4, on the basis that
Calmmonth might in future contend that it is entitled to a greater amount. By this
proceeding, Calmmonth now does so.
The issues
[9] The issues are as follows:
(a) Did the consultancy agreement contain the implied term contended for by
Calmmonth?
(b) Was the consultancy agreement between Calmmonth and AV Jennings varied?
(c) If the consultancy agreement was not varied, is Calmmonth estopped from
denying that the consultancy agreement was so varied?
(d) If the consultancy agreement contained no implied term, was not varied, and
no estoppel can be raised, was the sum of money paid by AVJennings to
Calmmonth as an additional fee properly owing under the agreement, or was it
paid to Calmmonth by mistake?
[10] Calmmonth acknowledges that its entire case, and any entitlement to the additional
fee it claims, depends on the existence of the implied term for which it contends.
1 AVJennings accepts, however, that if the Court makes certain findings, it will owe an additional fee
of $51,800.19 to Calmmonth.
-- 3 of 27 --
4
Relevant facts
The Development Rights Agreement
[11] The relevant land was owned by DriftSail Pty Ltd, a company controlled by
Mr Graeme Ingles – an accountant by profession, who was involved in property
development. Mr Ingles proposed to subdivide and develop the land as part of a
development called “Big Sky”, which would comprise five “super-lots”.
[12] During the Global Financial Crisis, Driftsail’s financiers required that Driftsail
undertake the Big Sky development alongside a joint venture partner. Driftsail and
AVJennings entered into discussions concerning super-lots numbered 1, 4 and 5 of
the Big Sky development. They proposed an arrangement whereby Driftsail would
own the land and AVJennings would pay for the construction costs of development
and subdivision.
[13] Mr Ingles incorporated the plaintiff, Calmmonth, in 2008. Calmmonth was to receive
a consultancy fee from AVJennings for marketing the relevant land and assisting
AVJennings in its development. Mr Ingles was the controlling mind of Calmmonth.
[14] On 10 November 2010, Driftsail and AVJennings entered into a Development Rights
Agreement (“DRA”). This provided for AVJennings to carry out the development of
the relevant land and pay the construction costs, with Driftsail retaining ownership.
As payment, AVJennings were to receive a fee of 72.6 per cent of the gross proceeds
on the sale of each lot.
[15] Under the DRA, AVJennings had the sole right to manage the marketing and sale of
the lots. AVJennings was also entitled to undertake the development in stages, and
could determine those stages, accelerate them, substitute a later stage for an earlier
stage, or change the nature of a stage. The plans included at Schedule 4 of the DRA
provided that Stage 4 was to have 82 lots, while Stage 9 was to have 86 lots. The
Business Plan contained as a schedule to the DRA recorded that the forecast revenue
for the development was $85.3 million.
The consultancy agreements
[16] On 8 November 2010, Calmmonth and AVJennings entered into a consultancy
agreement. By that agreement, Calmmonth was to assist AVJennings in the
development, marketing and sale of the relevant land, and was granted authority to
negotiate sale contracts. The agreement entitled Calmmonth to a fee of 6 per cent of
the gross proceeds resulting from the sale of each lot.
[17] In April 2011, AVJennings advised Calmmonth that its construction costs were likely
to be higher than its original estimate and that the forecast revenue for the
development had reduced from $85 million to approximately $81 million.
[18] Calmmonth and AVJennings recommenced negotiations and a new consultancy
agreement was formally entered into on 20 June 2011, replacing the original
consultancy agreement. The new terms were largely the same, save for a change to
the calculation of Calmmonth’s fee. Calmmonth was entitled to a fee of 2.5 per cent
of the gross proceeds received in respect of sales of the lots, as well as an additional
fee (titled an “Additional Stage Consultancy Fee”), payable if the actual gross
-- 4 of 27 --
5
proceeds of a stage were greater than the originally estimated gross proceeds for the
stage, as set out in a schedule to the agreement.
[19] Clause 6.2(a) of the agreement relevantly provided:
“6.2 Additional Stage Consultancy Fee
(a) [AVJennings] shall also pay to [Calmmonth] in respect
of the services to be provided by [Calmmonth] hereunder
an additional consultancy fee based on a Relevant Stage
(“Additional Stage Consultancy Fee”) if the Actual
Stage Gross Proceeds are greater than the Original Stage
Gross Proceeds. The Additional Stage Consultancy Fee
payable in respect of a Relevant Stage is then the amount
calculated using the following formula:
(Actual Stage Gross Proceeds – Original Stage Gross
Proceeds) x (36.3% - 2.5%)
…
(e) If the number of Lots changes in a Relevant Stage then
the Original Stage Gross Proceeds for the Relevant Stage
in Table A of Schedule 1 shall be amended using the
number of actual Lots in the Relevant Stage and the
original “average price” to determine the revised Gross
Proceeds in Table A of Schedule 1. For the purpose of
this clause Mgt Lot 9A and Mgt Lot 9B are to be
excluded.
(f) If Mgt Lot 9A and Mgt Lot 9B are redeveloped then the
Additional Stage Consultancy Fee will be negotiated
between the parties acting in good faith on a commercial
basis and having regard to the currency of the market at
the time of development. In determining the Additional
Stage Consultancy Fee for Mgt Lot 9A and Mgt Lot 9B,
[Calmmonth] will take into consideration the additional
costs [AVJennings] will incur in the redevelopment.”
[20] A Relevant Stage was defined to mean “the stages for the Lots as set out in Table A
of Schedule 1”. The Original Stage Gross Proceeds referred to the estimated GST
inclusive gross proceeds for all lots in a Relevant Stage as set out in Table A, while
the Actual Stage Gross Proceeds referred to the GST inclusive gross proceeds of the
sale or disposal of the lots in a Relevant Stage.
[21] Table A in Schedule 1 of the agreement is reproduced below.
“TABLE A
Stage
Original Stage Gross Proceeds #
Gross
Proceeds # No. of Lots Average Price
-- 5 of 27 --
6
Stage 3a 9,829,980 45 218,444
Stage 3b & c 10,273,155 44 233,481
Stage 4a 6,864,127 29 237,729
Stage 4b 13,050,127 53 246,229
Stage 9a 10,944,304 44 248,734
Stage 9b 10,610,983 40 265,275
Stage 10 16,628,014 61 272,590
Mgt Lot Stage 9A 1,241,625 1 1,241,625
Mgt Lot Stage 9B 2,384,400 1 2,384,315
Total 81,856,715 318
# Total Revenue is inclusive of GST ”
Re-design of the development
[22] In early 2012, Mr Ingles was advised by AVJennings that the development was
proposed to be redesigned “to create more traditional allotments which can be sold
without the need for prescriptive designs imposed by the planning system”.
AVJennings sent Mr Ingles a memorandum which indicated that the number of lots
proposed for Stage 9 had changed, and included the proposed deletion of the two
management lots.
[23] In September 2012, the Gold Coast City Council approved a change to the relevant
development permit, which had the effect of splitting stage 9 into four smaller stages,
9a, 9b, 9c and 9d, and creating 105 new lots. It also effected the “deletion” of the two
management lots.
[24] Also in September 2012, the Gold Coast City Council issued a Decision Notice which
approved the development of Stage 4 into 82 lots in 3 stages, namely Stages 4a, 4b
and 4c.
[25] In July 2013, the debt owed by Driftsail to its financier was acquired by a third party.
The third party appointed receivers and managers to Driftsail.
[26] In July 2015, Mr Ingles became aware that an application had been lodged on behalf
of Driftsail relating to Stages 4 and 9 of the development. The application sought to
change the development approval for Stage 9 to:
• relocate a proposed park from Stage 4a to Stage 9c,
-- 6 of 27 --
7
• increase the number of lots in Stage 9 from 105 to 110 (including eight lots
variously within Stage 9, which were equivalent to the two original
management lots); and
• remove the proposed Stage 9d, leaving Stage 9 with Stages 9a, 9b and 9c only.
[27] Following these developments, Mr Ingles was informed that a new layout had been
approved for Stage 9 and that an application for a modified layout of Stage 4 was
being prepared.
The August 2015 meeting
[28] Mr Ingles approached Mr Tony Creighton of AVJennings, seeking a meeting in
relation to the consultancy agreement. Mr Ingles’ email of 10 August 2015 said:
“Hi Tony
I would like to have a meeting with you within the next week in
relation to the Calmmonth Agreement. As you are aware I have a copy
of the redesign of stage 9 which shows eight management lots. At the
time of execution of the Calmmonth Agreement there were two
Management Lots known as 9A and 9B. Clause 6.2(f) provides for a
renegotiation between the parties in relation to the Consultancy Fee
should those two lots be redeveloped.
This is a discussion we should have before you go to market on stage
9.
Let me know when you have some time available – I am happy to
come to Brisbane.”
[29] Mr Ingles and Mr Creighton (together with Ms Kathy Conrad, who managed Mr
Ingles’ accounting practice and held a power of attorney for Calmmonth) met in
Brisbane on 20 August 2015, where various alternative proposals for calculation of
an additional fee were discussed. The parties are in dispute as to whether an
agreement was reached at that meeting as to any amendment to Table A of the
consultancy agreement.
[30] Calmmonth’s case, based on Mr Ingles’ evidence, is that the parties did not agree to
a proposal during the meeting, and that the meeting concluded by Mr Creighton
saying something like “why don’t you go away and think about it”. Mr Creighton’s
evidence, and AVJennings’ case, is that the parties did reach an agreed position at the
meeting.
Emails following the August 2015 meeting
[31] On the day following the meeting, 21 August 2015, Ms Conrad, with Mr Ingles’ prior
approval, sent an email to Mr Creighton, copied to Mr Ingles:
“Hi Tony
Thank you for meeting with myself and Graeme yesterday to discuss
amending Table A of the Consultancy Agreement dated 20 June 2011
-- 7 of 27 --
8
between AV Jennings Properties Limited and Calmmonth Pty Ltd (the
Agreement) to incorporate the reconfiguration of stages 4 and 9. The
amendments will be as follows:
1. The Original Gross Proceeds for Stages 4a and 4b are to be added
together to arrive at a total figure for stage 4. This total figure will
then become the Gross Proceeds amount for stages 4a, 4b and 4c
combined.
2. The 2 Management Lots which were included in stage 9 at the time
of signing the Agreement have been broken into 8 different lots,
namely lots 937, 947, 959, 967, 969, 983, 984 and 997, these 8 lots
will be referred to in the amended Table A as “Mgt Lots Stage 9”
and the Gross Proceeds for these 8 lots will be equal to the total of
the Original Gross Proceeds for Mgt Lot Stage 9A and Mgt Lot
Stage 9B in the original Table A.
3. The Original Gross Proceeds for stages 9a and 9b are to be added
together to arrive at the total figure for stage 9 of $21,555,287.
This total is to be divided by the original 84 lots at the average lot
price for stage 9 of $256,611. The average lot price is then to be
multiplied by 102 (being the total of the reconfigured lots (110)
less the 8 Mgt Lots stage 9 referred to above) (sic). The result of
this calculation, $26,174,277, is to be the Gross Proceeds amount
for stages 9a, 9b and 9c combined.
Set out below is the amended Table A. I have attached a soft copy of
the original Table A and the Amended Table A for your reference.
Table A – Amended
Stage Original Stage Gross Proceeds #
Gross Proceeds # No of Lots Average price
Stage 3a 9,829,980 45 218,444
Stage 3b & c 10,273,155 44 233,481
Stages 4a, 4b & 4c 19,944,254 82 243,223
Stages 9a, 9b & 9c 26,174,277 102 256,611
Stage 10 16,628,014 61 272,590
Mgt Lots Stage 9 3,626,025 8 453,253
Total 86,475,705 342
# Total Revenue is inclusive of GST
-- 8 of 27 --
9
Please confirm that this is your understanding of the agreement
we reached on Thursday.
Regards
Kathryn Conrad
On behalf of Calmmonth Pty Ltd under Power of Attorney dated 25
May 2011” (emphasis added)
[32] Following this email, the parties corresponded as follows:
(a) On 21 August 2015, Mr Creighton emailed Ms Conrad, copying Mr Ingles:
“Thanks Cathy (sic),
I will review this over the weekend and revert back on Monday.”
(b) On 26 August 2015, Ms Conrad emailed Mr Creighton:
“Hi Tony
Have you had a chance to review the amendments yet?”
(c) On 26 August 2015, Mr Creighton replied to Ms Conrad’s email, copying Mr
Ingles:
“Hi Kathy
Not as yet I will look at it tomorrow”
(d) On 28 August 2015, Ms Conrad emailed Mr Creighton, copying Mr Ingles:
“Hi Tony
How did you go with the perusal of our figures, are you happy with
everything.”
(e) On 31 August 2015, Ms Conrad emailed Mr Creighton, copying Mr Ingles:
“Hi Tony
I haven’t heard from you, the figures are exactly those we agreed on
at our meeting.
If we don’t hear from you we will assume that you are happy.”
(emphasis added)
(f) On 31 August 2015, Mr Creighton replied to Ms Conrad’s email, copying
Mr Ingles:
“Sorry guys
Just did not get to it last week I will pick it up agin (sic) when I return
an (sic) two weeks time”
-- 9 of 27 --
10
[33] On 31 August 2015, Mr Creighton suffered an accident while skiing, breaking his
pelvis. He spent a period in hospital recovering from the accident and dealing with
other health complications.
[34] The parties are in dispute as to whether the correspondence following the August
2015 meeting evidences a variation to Table A of the consultancy agreement.
The development as it occurred
[35] The development was completed as follows:
(a) The land originally comprising Stages 4a and 4b, consisting of 82 lots, was
developed in Stages 4a, 4b and 4c, consisting of 91 lots in total;
(b) The land on which original Stages 4a and 4b were to be developed was
substantially the same land that was actually developed into Stages 4a, 4b and
4c;
(c) The land originally comprising Stages 9a, 9b, Management Lot 9A and
Management Lot 9B was developed in Stages 9a, 9b and 9c, consisting of 110
lots in total;
(d) The two original management lots were deleted, and the land on which they
were originally to be developed was included as part of Stages 9a, 9b and 9c;
and
(e) The land on which original Stages 9a, 9b, Management Lot 9A and
Management Lot 9B were to be developed was substantially the same land that
was actually developed into Stages 9a, 9b and 9c.
[36] AVJennings earned total gross proceeds of $23,892,360 from its development of
Stage 4.
[37] AVJennings earned total gross proceeds of $27,525,680 from its development of
Stage 9.
Payments made to Calmmonth
[38] AVJennings has paid to Calmmonth a base fee of 2.5 per cent of the gross proceeds
from the sale of:
(a) each lot in Stages 4a, 4b and 4c; and
(b) each lot in Stages 9a, 9b and 9c (including the eight lots which were equivalent
to the original management lots).
[39] The parties corresponded from September 2016 regarding Calmmonth’s entitlement
to an additional fee for Stage 9 of the development. Calmmonth maintained that
because Stage 9 was not constructed in accordance with the plan as at the time of the
consultancy agreement, the appropriate approach to calculate the additional fee
payable on Stage 9 was to compare the revenue from the sale of all of Stage 9, as
constructed, with the original gross proceeds estimate for that stage as set out in
-- 10 of 27 --
11
Table A of the consultancy agreement. AVJennings did not accept that Calmmonth
was entitled to any additional fee in respect of Stage 9.
[40] From February 2017, the parties also corresponded regarding Calmmonth’s
entitlement to an additional fee for Stage 4. In attempting to “settle” the amount,
AVJennings undertook calculations and arrived at a figure of $651,513.07 (plus GST)
as the additional fee payable on Stage 4. These calculations used the average price
per lot for Stage 4a in Table A of the consultancy agreement, and multiplied that by
the number of lots in Stage 4c, to arrive at an estimate of the original proceeds for
Stage 4c, which formed part of the overall original stage gross proceeds estimate for
Stage 4. Actual proceeds had to exceed that amount in order for an additional fee to
be payable to Calmmonth.
[41] Mr Ingles did not agree with AVJennings’ methodology for calculating the additional
fee payable for Stage 4, but requested that AVJennings’ calculated amount of
$651,513.07 be paid to Calmmonth “on the basis that we can have a further discussion
in relation to my concerns regarding the calculation of this figure”.
[42] On 24 April 2017, AVJennings paid to Calmmonth an amount of $651,513.07 (plus
GST) as the additional fee payable for Stage 4 of the development. This was
expressly paid without prejudice to Calmmonth contending that it was entitled to a
greater amount. AVJennings acknowledged that Calmmonth reserved its rights to
dispute that amount.
Calmmonth’s implied term case
[43] Calmmonth contends that a term should be implied into the consultancy agreement
that where AVJennings “changed the boundaries of a Relevant Stage or included
further stages within the boundary of the overall stage of which Relevant Stages were
a part”, the Additional Stage Consultancy Fee would be calculated by applying the
formula in cl 6.2(a) “to the difference between Actual Stage Gross Proceeds and
Original Stage Gross Proceeds for the overall stage of which the altered Relevant
Stages were part”.
[44] As set out above, cl 6.2(a) of the consultancy agreement entitled Calmmonth to an
additional fee if the actual stage gross proceeds for each “Relevant Stage” exceeded
the original stage gross proceeds for the stage, as set out in Table A.
[45] It is to be recalled that Table A, as agreed on 20 June 2011, did not specify any
original stage gross proceeds for either Stages 4c or 9c of the development. Such
stages were not contemplated by the parties at the time the consultancy agreement
was entered into. Unless Table A was amended to provide original stage gross
proceeds figures for Stages 4c and 9c, Calmmonth would have no express entitlement
to an additional fee for these new stages. Hence its reliance on an implied term.
[46] The five requirements for a term to be implied in fact are well settled:
(a) The implied term must be reasonable and equitable;
(b) The implied term must be necessary to give business efficacy to the contract,
so that no term will be implied if the contract is effective without it;
(c) The implied term must be so obvious that “it goes without saying”;
-- 11 of 27 --
12
(d) The implied term must be capable of clear expression; and
(e) The implied term must not contradict the express terms of the contract.2
[47] Any implication of a term must be based on the parties’ presumed intention at the
time of the agreement, had they turned their mind to the matter in question.3 Courts
are generally slow to imply a term into a concluded agreement, especially where the
parties have devised a comprehensive and detailed contract to govern their relations.4
[48] In Philips Electronique Grand Public SA v British Sky Broadcasting Limited, Sir
Thomas Bingham MR (as Lord Bingham then was) said:
“The courts’ usual role in contractual interpretation is, by resolving
ambiguities or reconciling apparent inconsistencies, to attribute the
true meaning to the language in which the parties themselves have
expressed their contract. The implication of contract terms involves a
different and altogether more ambitious undertaking: the interpolation
of terms to deal with matters for which, ex hypothesi, the parties
themselves have made no provision. It is because the implication of
terms is so potentially intrusive that the law imposes strict constraints
on the exercise of this extraordinary power…
The question of whether a term should be implied, and if so what,
almost inevitably arises after a crisis has been reached in the
performance of a contract. So the court comes to the task of
implication with the benefit of hindsight, and it is tempting for the
court then to fashion a term which will reflect the merits of the
situation as they then appear. Tempting, but wrong…
And it is not enough to show that had the parties foreseen the
eventuality which in fact occurred they would have wished to make
provision for it, unless it can also be shown either that there was only
one contractual solution or that one of several possible solutions would
without doubt have been preferred.”5
Submissions
[49] Calmmonth’s proposed implied term is submitted to allow “the possibility of
additional commission on the facts as they actually occurred”, by entitling it to the
additional fee if the actual gross proceeds for Stages 4 or 9, as a whole, exceed the
estimated original stage gross proceeds for that stage as a whole. That is, application
of the implied term would require Calmmonth’s additional fee for Stage 4 to be
calculated on the aggregate proceeds of each lot in Stages 4a, 4b and 4c. The same
can be said for the application of the implied term to any additional fee payable on
Stage 9.
2 Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337
(“Codelfa”) at 347.
3 Codelfa at 345-346.
4 Codelfa at 346.
5 [1995] EMLR 472 at 481-482.
-- 12 of 27 --
13
[50] Calmmonth’s argument for an implied term starts with the proposition that the parties
intended that it would be capable of earning an additional fee on the entirety of the
land. As the land which was actually developed in Stages 4 and 9 had substantially
the same “footprint” as the land contemplated when the consultancy agreement was
entered into, Calmmonth submits that the parties must have intended that Calmmonth
was capable of earning additional fees on the entirety of the land.
[51] Calmmonth submits that this conclusion is fortified by the terms of cl 6, which
provide for both base and additional fees “in respect of services to be provided” by
Calmmonth under the agreement. If both the base fee and additional fee are payable
in respect of the same services on the same land, this is said to evidence that the
parties intended that the additional fee was also capable of being earned on the whole
of the land. Calmmonth also submits that it would be an odd result if the agreement
allowed for a base fee on all of the lots, but prevented Calmmonth from earning an
additional fee on some lots.
[52] AVJennings submits that Calmmonth’s implied term case “seeks to compare actual
revenue for a certain number of lots with forecast revenue for a smaller number of
lots”, therefore recasting the additional fee “from being one dependent upon the
comparison of the sale price of each lot with the average forecast price per lot, to one
being calculated by reference to stages and a fixed price per landmass”. This is said
to impermissibly focus on the concept of land, instead of the concept of lots upon
which the consultancy agreement is premised. It is also said to erroneously assume
that, at the time of executing the consultancy agreement, the parties had agreed to fix
the boundaries and forecast revenue for each stage of the development “for all time,
regardless of what happened within such boundaries”.
[53] Calmmonth’s case is that it is obvious that the parties would have agreed to it
receiving an additional fee based upon the estimated revenue from the sale of stages
that no longer existed in that form because the boundaries of a relevant stage had been
changed or further stages had been included within the boundary of the overall stage.
[54] The essence of AVJennings response is that it is not obvious that it would have agreed
to such a formula for the payment of an additional fee, which relied on estimated
revenue for the sale of lots in stages which were no longer to be developed in those
stages, and irrespective of changes to the internal layout of the development of Stages
3, 4, 9 and 10.
What did the agreement provide?
[55] A starting point in considering the parties’ submissions is what the agreement
provided. This permits one to identify the things about which they did not make
provision and which might be the subject of an implied term.
[56] The agreement provided in cl 6.1 for AVJennings to pay Calmmonth a “Consultancy
Fee” equal to 2.5 per cent of the gross proceeds received in respect of a sale or
disposal of “the Lots”.
[57] As noted in [19], the agreement provided in cl 6.2 for an “Additional Stage
Consultancy Fee” which was “based on a Relevant Stage” if the Actual Stage Gross
Proceeds were greater than the Original Stage Gross Proceeds. Under cl 6.2(a) the
Additional Stage Consultancy Fee payable “in respect of a Relevant Stage” is the
-- 13 of 27 --
14
amount calculated using a formula. It amounts to 33.8 per cent of the difference
between the Actual Stage Gross Proceeds and the Original Stage Gross Proceeds of
the Relevant Stage.
[58] Clause 6.2(e) applies if the number of lots changes “in a Relevant Stage”. In that
event, the Original Stage Gross Proceeds for the Relevant Stage in Table A is
amended using the number of actual lots in the Relevant Stage and the original
“average price” to determine the revised gross proceeds.
[59] Clause 6.2(f) provides that if management lots 9A and 9B are redeveloped then the
Additional Stage Consultancy Fee will be renegotiated between the parties in good
faith on a commercial basis and having regard to the currency of the market at the
time of the development. In doing so, Calmmonth is to take into consideration the
additional costs AVJennings will incur in the redevelopment.
[60] Attention to the terms of cl 6.2(a) identifies that the additional consultancy fee is
“based on a Relevant Stage”. Clause 6.2(e) also uses the term “Relevant Stage”. The
agreement defines a “Relevant Stage” to mean “the stages for the Lots as set out in
Table A of Schedule 1.”
[61] Calmmonth’s submissions on the implied term issue start with the proposition that
the parties intended that Calmmonth would be capable of earning an additional fee
“on the entirety of the land”. A more precise statement is that the additional
consultancy fee was based on the sale of a Relevant Stage. Clause 6.2(c) made
provision for the payment of the Additional Stage Consultancy Fee at the end of the
month in which the sale of the last lot for a Relevant Stage had settled. The notion of
a “Relevant Stage” is central to the operation of cl 6.2, including the calculation of
any Additional Stage Consultancy Fee and its payment.
[62] AVJennings submits that, having regard to the definition of “Relevant Stage” by
reference to stages in Table A, a “Relevant Stage” could comprise, as the
circumstance requires, either sub-stages or what Calmmonth calls in its proposed
implied term an “overall stage”. The implied term contended for by Calmmonth uses
the undefined term “overall stage”, for example, in referring to the proceeds “for the
overall stage of which the altered Relevant Stages were part.”
[63] The changes specifically provided for in cl 6.2.(e) and cl 6.2(f), as well as the changes
which are the subject of the implied term proposed by Calmmonth, arise in the context
of the DRA which entitled AVJennings to undertake the development in stages and
to, among other things, determine the stages and change the nature of a stage.
The variety of possible changes
[64] AVJennings was authorised to make a wide variety of changes to the development
which would have implications for Calmmonth’s income by way of its 2.5 per cent
consultancy fee in respect of a sale or disposal of a lot or by way of any Additional
Stage Consultancy Fee pursuant to cl 6.2. Some of the wide variety of changes can
be mentioned by way of illustration.
[65] One would be the redesignation of lots into different Relevant Stages. To take a
hypothetical example based upon Stage 3 of Table A, as appears in [21], Stage 3
consisted of a total of 89 lots. Suppose there was no change to the number of lots and
-- 14 of 27 --
15
the external boundaries of Stage 3 and the boundaries of the 89 lots in it also remained
unchanged. However, for marketing or some other purpose the 45 lots designated as
Stage 3a were redesignated as Stage 3a (with 23 lots) and Stage 3aa (with 22 lots),
with Stages 3b and 3c remaining the same. The result of the change would be that
there were now four, rather than three, Relevant Stages of what Calmmonth would
describe as an “overall stage”. The four stages might have been renumbered 3a, 3b,
3c (being the lots formerly described as 3b) and 3d (being the lots formerly described
as 3c). Nothing had changed on the ground in terms of boundaries of the lots in Stage
3, and there was no change in the number of lots in Stage 3. Instead, on one view,
AVJennings had included a further stage “within the boundary of the overall stage of
which the altered Relevant Stages were a part” (to use the language of its proposed
implied term).
[66] A different scenario is the kind of change which in fact occurred in respect of Stage
4 where the land that was to comprise Stages 4a and 4b was developed as Stages 4a,
4b and 4c. Stage 4 retained substantially the same “footprint” but now comprised a
total of 91 lots instead of the 82 lots provided for in Table A. Also, it was not possible
to tell which lots in the revised development corresponded with the lots that, at the
date of the consultancy agreement, were proposed to be developed in Stages 4a and
4b. Stage 4 as a whole had the same footprint, but its internal layout and the lots
inside it were entirely different.
[67] Another possible, hypothetical change would be a change to the external boundaries
of the “overall stage”. Depending upon the circumstances, this change might occur
with or without a change to the total number of lots in the overall stage or the total
number of lots within a Relevant Stage.
[68] In summary, it is possible to imagine a large number of potential changes to the
Relevant Stages, with or without a change in the number of lots within a Relevant
Stage. Some changes would be insubstantial and not alter the lots being sold or the
cost of developing them. The risk and the reward to AVJennings would be essentially
the same. Other changes would be more substantial and come at a greater cost to
AVJennings, with a different risk–reward equation.
[69] The issue is whether it is obvious that AVJennings would have agreed to have the
same formula apply to each and every change where the boundaries of a sub-stage
changed or a further sub-stage was included within the boundary of a stage.
Calmmonth’s case in greater detail
[70] Calmmonth’s case is that cl 6.2(e) only operates when the “number of lots changes in
a Relevant Stage”. The Relevant Stages are those set out in Table A, being Stages
4a, 4b, 9a, 9b and Management Lot 9A and Management Lot 9B. According to
Calmmonth, cl 6.2(e) is premised on the Development proceeding with the number
of “sub-stages provided in Table A”. Clause 6.2(e) is said to not apply if the number
of “sub-stages” (or more precisely the number of Relevant Stages) within Stage 4 or
9 is changed. On this argument, because Stages 4c and 9c were not provided for in
Table A, cl 6.2(e) is not capable of applying to them. Similarly, cl 6.2(e) is submitted
to not govern what happens “if the boundaries of a sub-stage (i.e. a Relevant Stage)
changes”. According to Calmmonth, cl 6.2(e) “only deals with an increase or
decrease in the number of lots within a sub-stage”. In other words, it only deals with
an increase or decrease in the number of lots within a Relevant Stage.
-- 15 of 27 --
16
[71] Calmmonth pleads that the agreement contemplated that the number of lots could be
changed within a Relevant Stage, in which case clauses 6.2(e) or 6.2(f) would apply,
as the case may be. It also pleads that the agreement:
• did not contemplate the addition of any stage other than the Relevant Stages; and
• did not contemplate changes to the boundaries of any Relevant Stage.
Is the proposed implied term the only contractual solution, or the one of several
contractual solutions that would without doubt have been preferred?
[72] I shall assume, consistent with Calmmonth’s pleaded case, that the agreement in
respect of the payment of an Additional Stage Consultancy Fee did not contemplate
the addition of any stage other than the Relevant Stages and did not contemplate
changes to the boundaries of any Relevant Stage. I will also assume the correctness
of its argument that the implied term contended for by it does not contradict the
express terms of clauses 6.2(e) and 6.2(f) because neither contractual term was
intended to “cover the field” that would otherwise be occupied by the implied term.6
[73] Calmmonth still must establish the other requirements for implying a term.
Importantly, the implied term must be so obvious that it “goes without saying”. The
point arises when the parties have omitted to make express provision for some event
because they have not fully thought through the contingencies.7 The term sought to
be implied must be so obvious as to go without saying. This requirement is tested by
asking whether an officious bystander would have replied “Of course” if asked if the
term needed to be implied.8
[74] It is not enough to show that had the parties foreseen the eventuality that in fact
occurred they would have wished to make provision for it. Calmmonth accepts the
correctness of the statement in Philips Electronique as to the requirement of
obviousness. Lord Bingham stated:
“[I]t is not enough to show that had the parties foreseen the eventuality
which in fact occurred they would have wished to make provision for
it, unless it can also be shown either that there was only one contractual
solution or that one of several possible solutions would without doubt
have been preferred.”9
[75] The issue is not whether a term was needed. The issue is whether the term contended
for by Calmmonth is the obvious one that would have been agreed to by the parties.
[76] I am not persuaded that Calmmonth has shown that the implied term contended for
by it was the only one contractual solution or the one of several possible solutions
that would, without doubt, have been preferred.
[77] If the parties had contemplated AVJennings changing the boundaries of a Relevant
Stage or including further stages within the boundary of the “overall stage of which
Relevant Stages were a part” (with or without a change in the number of lots within
6 Gemmell Power Farming Co Ltd v Nies (1935) 35 SR (NSW) 469 at 476-477.
7 Attorney General of Belize v Belize Telecom Ltd [2009] 1 WLR 1988 at [25].
8 Codelfa at 346-347 citing Shirlaw v Southern Foundaries (1926) Ltd [1939] 2 KB 206 at 227.
9 [1995] EMLR 472 at 482.
-- 16 of 27 --
17
a Relevant Stage), then a number of contractual solutions were possible. One solution
would be similar to the solution found in cl 6.2(e) if the changes were expected to
alter the number of lots in a Relevant Stage. Another was a solution similar to
cl 6.2(f) in which, depending on the nature of the change, provision would be made
for the Additional Stage Consultancy Fee to be negotiated between the parties “acting
in good faith on a commercial basis having regard to the currency of the market at the
time of development”, and taking into consideration the additional costs AVJennings
would incur as a result of the change. Another possibility was the kind of agreement
that was allegedly struck on 20 August 2015. Another possibility was the kind of
clause contended for by Calmmonth as an implied term.
[78] As the passage quoted from Philips Electronique makes clear, the question of whether
a term should be implied arises after a crisis has been reached in the performance of
the contract and the Court should not act with the benefit of hindsight. It should not
fashion a term which will reflect the merits of the situation as they appear at that time.
[79] The relevant inquiry in this case is not what term would have been agreed by the
parties or been regarded as obvious to an officious bystander years after the contract
was formed and when the parties were called upon to address a gap in the contract in
respect of a situation which had in fact developed with various specific changes to
Stages 4 and 9.
[80] In this case the issue is not what the parties would have agreed to fill a gap in the
contract after a dispute arose when AVJennings changed the boundaries of a Relevant
Stage or included further stages within the boundary of the overall stage of which
Relevant Stages were a part, or did both of those things. That issue would arise in
respect of a particular change made in different market conditions and which
presented different opportunities and risks. In that concrete, later factual situation, a
party would be inclined to seek a term which best suited its commercial interests at
that time. This would, in turn, involve a consideration of the amount of Calmmonth’s
expected base consultancy fee (at a rate of 2.5 per cent) upon the sale of lots and also
its prospects of obtaining an Additional Stage Consultancy Fee based on a Relevant
Stage and what that additional fee might be.
[81] The relevant issue is whether the implied term contended for by Calmmonth would
have been the obvious provision had the parties (or more precisely, an officious
bystander) addressed the contingencies for which specific provision had not been
made. This is assessed at the time the contract was agreed. At that time there were a
wide range of possible, future changes, either to the boundaries of a Relevant Stage
or by the inclusion of a further stage within the boundary of the overall stage, or both.
Some of the changes would come at an increased cost to AVJennings. Any particular
change to the boundaries of a relevant stage or to include a further stage would carry
different risks and different potential rewards, depending upon many factors,
including market conditions at the time the change was made. It is not obvious that
the implied term contended for by Calmmonth would have been the only contractual
solution, or the one of several contractual solutions that would have been preferred
by the parties. AVJennings might have sought a greater reward for a greater risk.
The parties might simply have left the matter to be the subject of further agreement
in a form similar to cl 6.2(f), which provided for account to be taken of the market at
the later time and any additional costs to AVJennings.
-- 17 of 27 --
18
[82] If the parties, at the time of negotiating the terms of the consultancy agreement, had
thought through the contingencies about which provision had not been made and the
contingencies of AVJennings changing the boundaries of a Relevant Stage or
including a further stage within the boundary of an overall stage, then they would
have been required to contemplate a wide variety of potential changes, with the
various changes having implications for anticipated gross proceeds. The changes
would also have implications for the assessment of risks. The changes may have
involved additional costs for AVJennings or costs savings.
[83] In my view, it is not obvious that the parties would have agreed that Calmmonth be
paid an additional fee based on the forecast sale of stages that existed at an earlier
point in time, and regardless of the developer’s ingenuity in changing the internal
layout of the development, the boundaries of stages, or the total number of lots in the
overall stages, thereby increasing the revenue from the sale of lots. On Calmmonth’s
implied term case, in addition to its base fee on the sale of each lot, it would be entitled
to an additional fee calculated on the estimated revenue from a different and
superseded development.
[84] A critical issue is whether it is obvious that the parties would have agreed to such a
term for the calculation of an additional fee if the parties had contemplated the
possibility that the development did not proceed in accordance with Table A because
the internal layout of the development would be altered by changes to the boundaries
of a relevant stage, the inclusion of further stages within the overall stage, or both.
Many such changes would be apt to alter the development and the revenue which the
new stages would be expected to generate.
[85] Why would AVJennings necessarily be prepared to pay Calmmonth an additional fee
based on the difference between:
(a) the revenue which was originally expected to be generated from a development
that was to no longer proceed in those stages, and
(b) the revenue actually generated from the sale of stages with different
boundaries, different internal layouts and a different number of lots?
[86] It is possible that AVJennings would have agreed to a provision in the form of the
implied term for which Calmmonth contends. But it is far from obvious that the
parties would have agreed to such a term if the prospect of changes to the boundaries
of the stages in Table A or the inclusion of further stages within a relevant stage had
been contemplated and discussed.
[87] I shall assume that Calmmonth is correct and that cl 6.2(e) does not apply to a change
in the number of lots in a Relevant Stage which results from a change in the
boundaries of a Relevant Stage or the inclusion of further stages “within the boundary
of the overall stage of which Relevant Stages were a part.” If it did, then cl 6.2(e)
would contradict the proposed implied term. My assumption that cl 6.2(e) does not
apply to such a change does not render it irrelevant to the implied term case. This is
because changes falling within the proposed implied term which increased the
number of lots would pose a similar issue as arises under cl 6.2(e) of arriving at an
amended Original Stage Gross Proceeds based on an increased number of lots.
-- 18 of 27 --
19
[88] If there was a shared expectation that an increase in the number of lots would result
in the total gross proceeds for all the lots in the stage also increasing, then this would
have implications for the amount of the base fee, and also implications for any
additional fee which AVJennings might be prepared to negotiate. An increased,
amended Original Stage Gross Proceeds by virtue of a new provision would reduce
the potential amount of any additional consultancy fee.
[89] This is not to say that the parties would have been content to provide for any change
in the number of lots as a result of changes to boundaries or the inclusion of further
stages within an “overall stage” to be addressed in the same way as cl 6.2(e) addressed
a change in the number of lots. It simply is to highlight that a change which resulted
in an increase in the number of lots (but which did not fall within cl 6.2(e)) was one
of a number of contingencies about which the parties would need to provide, and that
it is not obvious that the provision would have been in the form of the proposed
implied term.
[90] A wide variety of potential changes fall within the proposed implied term. Some
would have limited implications for the development of stages that were the subject
of Table A. Many other changes would have a wide range of implications for the
gross proceeds of sub-stages, overall stages and the overall development of Stages 3,
4, 9 and 10. They also would have implications for the costs to AVJennings of
undertaking such a changed development. Depending on the particular change to the
development and its consequences in terms of potential proceeds and costs,
AVJennings might have sought a provision different to the implied term proposed by
Calmmonth to reflect the risks and rewards involved in the changes to the
development made by it. It is not obvious that the parties would have agreed to a
single formula to calculate the additional fee which would apply to such a wide
variety of changes.
[91] Given the variety of potential changes, it has not been shown that there was only one
contractual solution, being the term for which Calmmonth contends. The variety of
potential changes to boundaries or the inclusion of further stages within the boundary
of an overall stage suggests that there were several possible solutions, including
leaving the matter to be the subject of further agreement in the context of a specific
change. Clause 6.2(f) serves to identify a provision which left the additional fee to
be negotiated, having regard to the current market at the time of the change and the
additional costs of the change, as one of a number of possible solutions.
[92] Calmmonth’s submissions accept that it is not enough for it to show that had the
parties foreseen these contingencies they would have wished to make provision for
them. It must show either that there was one contractual solution or that one of the
several possible solutions would, without doubt, have been preferred. I am not
persuaded that the solution contended for by Calmmonth would, without doubt, have
been preferred.
[93] In the circumstances, the implied term contended for by Calmmonth is not so obvious
that it goes without saying. An officious bystander would not have replied “Of
course” if asked whether a provision in those terms needed to be implied.
-- 19 of 27 --
20
Conclusion on Calmmonth’s implied term case
[94] Calmmonth has not established the requirement of obviousness. It therefore has
failed to establish the implied term contended for by it.
Was Table A of the consultancy agreement amended?
[95] This issue turns on:
(a) whether there was any agreement reached at the August 2015 meeting to amend
the terms of Table A; or
(b) whether there was any agreement reached to amend the terms of Table A after
the meeting, by a combination of verbal and written communications and
conduct.
[96] It is common ground that at the meeting, Mr Ingles and Mr Creighton did agree to:
(a) add Stages 4c and 9c to an amended Table A; and
(b) calculate the “average price” to be inserted into an amended Table A by adding
together the estimated gross proceeds for Stages 4a and 4b, as listed in Table
A, and dividing that result by the number of lots contemplated for Stages 4a,
4b and 4c (that is, 82), with that result to be applied as the average price to each
of Stages 4a, 4b and 4c.
Relevant evidence
[97] Calmmonth maintains that no agreement to amend Table A (as regards both Stage 4
and Stage 9) was reached at the meeting. Mr Ingles’ evidence is that the meeting
ended with Mr Creighton saying something like “why don’t you go away and think
about it”.
[98] Mr Ingles’ and Mr Creighton’s oral evidence confirmed that an agreement was
reached at the meeting in respect of Stage 4. Mr Creighton explained that that
approach was dictated by cl 6.2(e) of the consultancy agreement:
“… under [clause] 6.2(e) of the existing agreement that we had in
place, we had to take the average price for the original number of lots,
and multiply it by the new number of lots … which was 82. … the
reason we put in 4c, was because the agreement was silent on 4c, and
that was important to [Mr Ingles], at the time.”
[99] As for Stage 9, Mr Ingles maintains that there was no agreement reached about the
calculation of an additional fee.
[100] It will be recalled that by the time of the meeting, the two management lots originally
contemplated as part of Stage 9 had been ‘deleted’ and replaced with 8 traditional lots
across Stages 9a, 9b and 9c.
[101] Mr Ingles and Mr Creighton agree that two different approaches to calculate the
additional fee payable on Stage 9 were advanced at the meeting:
-- 20 of 27 --
21
• Mr Creighton suggested that the estimated gross proceeds for the two original
management lots be added together to form the estimated gross proceeds of the
eight replacement lots, in an amended row of Table A, to be called
“Management Lots Stage 9”. The average price for those new “management
lots” would then be calculated by dividing the total of the estimated gross
proceeds for the two original management lots by eight.
• Mr Ingles suggested that the average price for Stage 9 be calculated by adding
together the estimated gross proceeds of Stages 9a and 9b, then dividing that
number by the original number of lots in Stage 9 (that is, 84). To this, Mr
Creighton had suggested that the average price arrived at on Mr Ingles’ method
be multiplied by the total number of lots contemplated in Stage 9 at that time,
less the eight lots replacing the management lots (that is, 102).
[102] Mr Creighton explained in evidence that his suggestion to multiply Mr Ingles’
average price figure by 102 was consistent with applying cl 6.2(e) of the consultancy
agreement.
[103] Mr Ingles maintains that he did not agree with that suggestion, and that the meeting
concluded as regards Stage 9 with Mr Creighton saying “why don’t you go away and
think about it”. Mr Creighton’s evidence was that although Mr Ingles at first did not
agree, once they had “talked about it for a while”, Mr Ingles “did agree to it because
he understood that we were using the clause in the agreement of 6.2(e) in accordance
with the agreement. So then we agreed on it.”
[104] Ms Conrad’s handwritten notes taken at the meeting on 20 August 2015 are in
evidence. They include the following, which tend to suggest agreement having been
reached at the meeting consistent with Mr Creighton’s proposal:
“ Stage 4 agree total sale proceeds spread over whole stage
82 lots”
“ Add the 2 “c”s into consultancy no.s”
“ 9 split out M.D. lots (pink 8) leaves with 110 lots
21,555,287 ÷ 84 x 102 =”10
[105] Ms Conrad was originally included in the Trial Plan as a witness to be called by
Calmmonth at trial and the original trial was adjourned because of her non-
availability due to work pressures. As it eventuated, Ms Conrad was not called to
give evidence. No explanation has been offered by Calmmonth for Ms Conrad not
having been called as a witness.
[106] It is to be recalled that Ms Conrad’s email, following the meeting in August 2015, set
out a range of amendments to Table A of the consultancy agreement and concluded:
“Please confirm that this is your understanding of the agreement we
reached on Thursday.”
10 The tick marks were included beside these parts of Ms Conrad’s notes.
-- 21 of 27 --
22
[107] In a follow up email sent on 31 August 2015, Ms Conrad again asserted that there
was an agreement reached at the meeting:
“… I haven’t heard from you, the figures are exactly those we agreed
on at our meeting…”
[108] As set out from [32] above, these emails were part of a series of email correspondence
between Mr Creighton and Ms Conrad following the meeting. In response to follow
up messages from Ms Conrad, Mr Creighton advised first that he had not had a chance
to review the amendments, and then later (after his admission to hospital, and while
on pain killers), that he “did not get to it” but would pick it up again when he returned
in two weeks’ time.
[109] Mr Ingles in evidence explained that the reference to the “agreement reached on
Thursday” in Ms Conrad’s initial email was an attempt by him to “lock” AVJennings
into an agreement whereby Calmmonth would earn an additional fee on Stage 4, but
“sacrifice” any additional fee on Stage 9. This is said to have been done in
circumstances where:
(a) there was no agreement reached during the meeting for the amendment of Table
A regarding both Stages 4 and 9;
(b) Mr Ingles was concerned that AVJennings may take the position that no
additional fee was payable to Calmmonth for either Stage 4c or Stage 9c,
because neither was included in the original Table A;
(c) Mr Ingles considered that Stage 4 was likely to be worth more in additional
fees than Stage 9; and
(d) Mr Ingles was willing to earn no additional fees on Stage 9 if an agreement
could be reached on Stage 4.
[110] Mr Creighton explained in evidence that between his emails of 26 and 31 August
2015, he had looked at Ms Conrad’s figures and formed the view that they were
consistent with what had been agreed at the meeting. His lack of affirmative response
to Ms Conrad’s emails during that period was explained by his being occupied on
other projects before going on leave, and also wanting, as a courtesy, to first brief his
internal team on what had been agreed and how the agreement would be administered.
He was not able to brief his team before going on leave, and thereafter was admitted
to hospital.
[111] Mr Creighton concedes that his 31 August email stating that he “just did not get to it
last week”, sent from hospital, was “probably incorrect”, as he was suffering from a
broken pelvis and was under the influence of pain killers when he sent it.
Mr Creighton maintains that he was comfortable with the figures as set out in
Ms Conrad’s 21 August 2015 email and that they reflected the agreement reached at
the 20 August 2015 meeting.
[112] During 2016 and 2017, Calmmonth issued invoices to AVJennings for its 2.5 per cent
base fee for various lots on the development. Those invoices included lots within
Stages 4c and 9c, along with the eight lots which replaced the original management
lots.
-- 22 of 27 --
23
[113] As outlined at [42], AVJennings paid to Calmmonth a figure of $651,513.07 (plus
GST) in April 2017 as the additional fee payable for Stage 4. Mr Creighton’s email
to Mr Ingles in March 2017 explaining the calculation of this payment was as follows:
“… We don’t understand your position of how we calculated the
Revised Gross Proceeds for stage 4 as the Consultancy Agreement is
quite clear. The only issue is stage 4C which was not contemplated by
the agreement. AVJennings has taken a generous approach and
applied the lower of the average to the two sub stages (being Stage 4A
$237,729).
As the agreement is not prescriptive as to how the revised proceeds for
stage 4C are to be determined we could have used the average of the
whole stage being $243,222 or stage 4b $246,229 (being by far the
larger stage). Either of these approaches would reduce the payment to
Calmmonth to $586,517.96 or $550,954.59 respectively…”
[114] The agreement which, on AVJennings’ case, was reached at the August 2015 meeting
would have required AVJennings to use the average price for Stages 4a and 4b
together. Taking either of the latter two approaches would have reduced the amount
of the additional fee payable to Calmmonth.
[115] During discussions relating to Calmmonth’s claim for additional compensation,
AVJennings sent a letter on 9 May 2017 to Calmmonth’s lawyers which referred to
Ms Conrad’s 21 August 2015 email, stating that:
“Your interpretation is also completely contradictory to your client’s
previous interpretation set out by your client in its email to us of 21
August 2015 (attached). I refer you to paragraph #3 of that email in
relation to stage 9 which specifically acknowledges the requirement
for adjustment as we have set out in previous correspondence, and
which also provides your client’s calculation of the adjusted original
proceeds amount.” (emphasis added)
[116] In a later letter on 30 May 2017, AVJennings referred to “the position agreed by
your client in a meeting in 2015 which was confirmed by your client’s email to us
of 21 August 2015” (emphasis added).
Relevant principles
[117] Whether a binding agreement was reached is to be determined objectively, and will
depend on the parties’ words and conduct, viewed in context.11 The evidence of
witnesses and their contemporaneous views as to what happened can assist in
understanding what, objectively, is likely to have occurred. As Allsop J explained in
Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd:
“The objective theory of contract does not mean that one only looks at
the transcript to see what was said. One looks to witnesses and any
other evidence to assist in understanding how it was said, with what
manifest intention and in what context. For such a task the expressions
of view of the participants are evidentiary matters which can be taken
11 Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd (2001) 117 FCR 424 at 512.
-- 23 of 27 --
24
into account in assessing what in fact happened and thus in assessing
that ultimately objective question.”12
[118] The parties’ subsequent conduct, although not admissible to answer a question of
construction, is admissible in determining whether a contract was formed.13
Application of principles
[119] Mr Ingles’ evidence that no agreement was reached at the August 2015 meeting is
contradicted by a near-contemporaneous document: Ms Conrad’s letter sent on behalf
of Calmmonth. That letter was written by a participant in the meeting. Its terms were
approved by Mr Ingles. It is compelling evidence that an agreement was reached at
the meeting.
[120] Mr Ingles did not impress me as a witness. His recollection of what was said seemed
poor and reconstructed to suit his interests.14
[121] Calmmonth did not call Ms Conrad to give evidence. She would be expected to be a
witness called by Calmmonth. The rule in Jones v Dunkel is enlivened.15
[122] The failure to call Ms Conrad allows an inference to be drawn that her evidence would
not have assisted Calmmonth’s case.16 Importantly, the rule in Jones v Dunkel does
not allow an inference to be drawn that Ms Conrad’s evidence would have been
positively adverse to the plaintiff’s case.17 If there is sufficient evidence upon which
to conclude that Calmmonth’s case (of no agreement having been reached at the
meeting) is otherwise proved, the absence of evidence from Ms Conrad cannot be
used to diminish that proof.18
[123] In my view, the evidence leads to the conclusion that an agreement was reached at
the meeting to amend Table A of the consultancy agreement. Alternatively, the fact
of the agreement is proven by what was said at the meeting and the parties’ words
and conduct shortly after it.
[124] Calmmonth submits that there was no agreement reached during the meeting,
because:
(a) Ms Conrad’s email on 21 August 2015 was an attempt by Mr Ingles to “lock
in” an agreement, rather than confirming that an agreement had already been
reached;
(b) Mr Creighton, nor anyone else at AVJennings, ever confirmed their agreement
with the amended calculations in Ms Conrad’s email;
12 (2001) 117 FCR 424 at 512.
13 Brambles Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153 at 163-164.
14 Watson v Foxman (1995) 49 NSWLR 315 at 318-319.
15 (1959) 101 CLR 298 at 308, 312, 320-321.
16 Kuhl v Zurich Financial Services Australia Ltd (2011) 243 CLR 361 at 384-385.
17 Kuhl v Zurich Financial Services Australia Ltd (2011) 243 CLR 361 at 385; Australian Securities
and Investments Commission v Hellicar & Ors (2012) 247 CLR 345 at 413.
18 Australian Securities and Investments Commission v Hellicar & Ors (2012) 247 CLR 345 at 414.
-- 24 of 27 --
25
(c) AVJennings subsequently used a different methodology to the one allegedly
agreed upon at the meeting when calculating the additional fee due on Stage 4;
and
(d) Subsequent correspondence from AVJennings sought to deny its obligation to
pay an additional fee by reference to the terms of the consultancy agreement,
rather than by any alleged agreement at the meeting.
[125] There are references in Ms Conrad’s contemporaneous emails to an agreement having
been reached at the meeting. These emails were reviewed by Mr Ingles and he
discussed them with Ms Conrad before they were sent. On Mr Ingles’ version of
events, he allowed emails to be sent which falsely claimed that an agreement had been
reached. I consider that to be improbable. Rather than falsely assert that an
agreement had been made when it had not been, it is more probable that the emails
told the truth.
[126] I do not find his explanation that the emails were drafted in order to “lock”
AVJennings into a proposal which had not been agreed convincing.
[127] If the agreement alleged by AVJennings (as documented in Ms Conrad’s email of
21 August 2015) provided Mr Ingles with benefits that he wished to “lock in”, then
he would have wished to “lock in” those matters by agreeing to the proposal at the
meeting.
[128] He controlled Calmmonth and did not need to report back to a superior and gain their
approval before reaching an agreement. He assessed the proposal to be, on balance,
a good one for his company in the circumstances and had an interest in concluding
the agreement at the meeting. He had Ms Conrad at the meeting as a witness of what
had been agreed at it.
[129] In the days and weeks that followed the meeting and Calmmonth’s confirmatory
email, Mr Ingles did not resile from the proposition that an agreement had been
reached at the meeting.
[130] Mr Creighton presented in the witness box as a thoughtful and careful witness. He
made appropriate concessions and acknowledged that, with the benefit of hindsight,
he wished that he had taken the short time required back in August 2015 to send an
affirmative response to Ms Conrad’s emails. I agree with AVJennings’ submission
that although it is inescapable that Mr Creighton did not provide an affirmative
response, by the same token, neither Mr Ingles nor Ms Conrad confirmed to
AVJennings that their “agreement” as set out in Ms Conrad’s email was off the table.
That is so in a context where Ms Conrad had previously said that failing any response
from AVJennings, they would assume that AVJennings was happy.
[131] Mr Creighton’s explanation for not responding affirmatively is understandable in the
circumstances. He was busy. The matter was not contentious. He had other more
pressing things to prioritise before going on leave. He then suffered serious injuries
and was hospitalised.
[132] Calmmonth also relied on the fact that Mr Ingles took a file note of the meeting, in
contrast to Mr Creighton not having done so. Mr Creighton’s cross-examination is
said to be largely consistent with the contents of Mr Ingles’ file note as regards the
-- 25 of 27 --
26
differing proposals discussed at the meeting, showing that Mr Ingles’ file note was
accurate. I accept that that is the case, but in circumstances where the real dispute is
not the differing proposals put forward at the meeting, but rather the outcome of the
meeting, I do not consider that Mr Ingles’ file note supports his assertion that no
agreement was reached. Further, although Mr Ingles’ file note does not record any
complete agreement having been reached at the meeting, Ms Conrad’s file note is
consistent with Mr Creighton’s recollection that an agreement was reached.
[133] In the absence of any evidence from Ms Conrad as to the basis on which the meeting
concluded and the drafting of the emails, and with the benefit of her handwritten notes
from the meeting which include tick marks and references to an agreement, I infer
that her evidence, if given, would not have assisted Calmmonth in proving that no
agreement was reached at the meeting.
[134] The other features relied upon by Calmmonth to contend that no agreement was
reached do not displace the probative force of Calmmonth’s contemporaneous
documents and Mr Creighton’s evidence that an agreement was reached.
[135] Mr Creighton was directed in cross-examination to his calculations for the additional
fee payable to Calmmonth on Stage 4, undertaken in early 2017. He accepted that
his methodology for performing those calculations and some parts of his email were
inconsistent with the agreement which AVJennings contends had been reached at the
August 2015 meeting. However, his explanation that AVJennings was adopting a
more generous approach is understandable when viewed in the context of the parties
attempting to reach a commercial resolution.
[136] The other correspondence relied upon by Calmmonth is the 9 May 2017 letter from
AVJennings to Calmmonth’s lawyers, which referenced Calmmonth’s “previous
interpretation set out by [Calmmonth] in its email to us of 21 August 2015”. The
reference to a “previous interpretation” rather than an “agreement” is submitted to
tend against a finding of an agreement. That phrase must be viewed in the context of
the email as a whole, which also included a reference to a later part of Ms Conrad’s
21 August 2015 email setting out Calmmonth’s calculations and acknowledging the
requirement for an adjustment in relation to Stage 9. I consider that the phrase
“previous interpretation” was a poor use of language, rather than an
acknowledgement that no agreement had been reached at the August 2015 meeting.
That conclusion is supported by a further letter from AVJennings three weeks later
which referred to “the position agreed by [Calmmonth] in a meeting in 2015 which
was confirmed by [Calmmonth]’s email to us of 21 August 2015”.
[137] For completeness, I note that AVJennings’ submissions rely on invoices issued by
Calmmonth for its 2.5 per cent base fee in respect of Stages 4c, 9c, and the eight lots
in place of the original management lots. They are said to be subsequent conduct on
the part of Calmmonth evidencing an agreement having been reached at the meeting
to amend Table A. This conduct seems to me to be equivocal. The invoices are
reflective of the base fee due under cl 6.1(a) of the consultancy agreement to
Calmmonth on the sale of a lot within the land at Big Sky. That entitlement arose
regardless of whether Table A was amended in the respects alleged by AVJennings.
[138] For these reasons, I find it more probable than not that an agreement was reached at
the meeting on 20 August 2015 to amend Table A of the consultancy agreement in
the terms contained in Ms Conrad’s email of 21 August 2015.
-- 26 of 27 --
27
Conclusion and orders
[139] My conclusion that the consultancy agreement was varied makes it unnecessary to
consider the alternative estoppel arguments, or AVJennings’ counterclaim.
[140] Calmmonth having failed to establish the implied term which was essential to its case,
its claim should be dismissed.
[141] Calmmonth did not advance an alternative claim for $51,800.19, being the amount
which AVJennings acknowledges it owes Calmmonth pursuant to cl 6.2(a) in relation
to the Stage 9 management lots. To this figure is added GST pursuant to cl 6.2(b).
AVJennings pleads that it is liable to pay that sum upon Calmmonth rendering an
invoice, but submits that Calmmonth has not done so.
[142] There seems insufficient justification to give judgment for that amount when it has
not been claimed, but has been acknowledged.
[143] There does not appear to be any reason as to why costs should not follow the event.
Subject to any submissions as to the form of the order or costs, I propose to order:
1. Judgment for the defendant.
2. The plaintiff pay the defendant’s costs of and incidental to the proceeding,
including reserved costs, to be assessed if not agreed.
-- 27 of 27 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2021/003