Bein v Queensland Building and Construction Commission [2021] QCAT 109
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bein v Queensland Building and Construction Commission
[2021] QCAT 109
PARTIES: JOHN JOSEPH BEIN
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR 084-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 9 March 2021
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Paratz AM
ORDERS: The Application to extend time, filed by John
Joseph Bein on 28 February 2020, is dismissed.
The Application to Review a decision, filed by John
Joseph Bein on 2 March 2020, is to proceed having
regard only to the decision of the Queensland
Building and Construction Commission made on
13 February 2020.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – ENDING PROCEEDINGS
EARLY – SUMMARY DISPOSAL – OTHER MATTERS
– whether extension of time to file application for review
can be granted under s 61 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) – effect of
s 86F(1)(c) of the Queensland Building and Construction
Commission Act 1991 (Qld) – whether Tribunal has
jurisdiction to hear the matter
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 61
Queensland Building and Construction Commission Act
1991 (Qld), s 86F
Body Corporate for Alto Gladstone v Queensland Building
and Construction Commission & Anor [2020] QCATA 6
-- 1 of 9 --
2
Campaigntrack Victoria Pty Ltd v The Chief Executive,
Department of Justice and Attorney-General & Ors [2016]
QCA 37
Col Jenkins & Associates v Queensland Building and
Construction Commission [2019] QCAT 117
Eco-Builder Pty Ltd v Queensland Building and
Construction Commission [2018] QCAT 59
Queensland Building and Construction Commission v
Watkins [2014] QCA 172
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondent: QBCC Legal Services
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] John Joseph Bein (‘the builder’) filed an Application to review a decision, in the
Tribunal, on 2 March 2020 (‘the review application’). The application lists three
decisions of the Queensland Building and Construction Commission (‘the QBCC’) as
being sought to be reviewed:
(a) 26 September 2019;
(b) 18 October 2019;
(c) 13 February 2020.
[2] The builder filed an Application to extend or shorten a time limit or for waiver of
compliance with procedural requirement, in the Tribunal, on 28 February 2020 (‘the
EOT application’).
[3] The QBCC filed an Application for miscellaneous matters, in the Tribunal, on 5 May
2020 (‘the limitation application’).
[4] I gave directions on 9 September 2020 that submissions were to be filed in relation to
the EOT application and the limitation application, and that those applications would
be determined on the papers. Those applications have been referred to me for
determination, and these are my reasons and decision in relation to them.
The builder’s submissions
[5] The application for extension of time filed on 28 February 2020 asks the Tribunal to
make the following order:
To grant an extension of time for this to be correctly sorted.
[6] The reasons that the builder states in the Application as to why he considers the orders
sought should be made are as follows:
-- 2 of 9 --
3
1. We have tried from the very beginning to complete this project but,
unable to do so through constant bastardisation from the owners and no
help from QBCC.
2. For the past 12 months John Joseph Bein has been extremely ill due to
the stress that this job has caused him.
Please refer QCAT BDL 164-19
[7] A submission was filed by the builder’s wife on 9 October 2020, together with a large
bundle of documents containing emails, reports and letters, in relation to both the EOT
application and the limitation application.
[8] The submission seeks to address, in a general way, why an application to review the
decisions of 26 September 2019 and 18 October 2019 was not made within 28 days
of each decision.
[9] The submission does not separately address the limitation application.
[10] The submission recounts much of the history of the matter, and a related building
dispute between the builder and the owners which is being heard in the Tribunal (BDL
164-19). The submission refers to various emails and interactions with the QBCC.
[11] The submission says that the builder’s son telephoned the QBCC in mid-to-late
January 2020 to ask what the situation was in relation to the matter and was told that
remedial work had commenced. The subsequent lodging of the application to review
is described as follows:1
We were then left with no alternative but to begin the case against the QBCC.
When we took all the paperwork into QCAT, the lady at the front desk saw the
dates on the Directions to Rectify and said they have expired all except one.
That would be the one that you are needing answers on. Had we of [sic]
understood the process, we would have commenced this action long ago.
Instead we began the action against the owners themselves believing that was
where the problem lay. The problem to us is that it is not just this Direction it is
the whole job. We have been willing from the beginning to complete all the
work that we were responsible for. We have attended every inspection and
advised the QBCC of the results when trying to do the work.
It would not be too difficult to understand the QBCC position, if the builder
John Joseph Bein had of [sic] been a rogue builder but a man of then 74 years
when the work commenced, now 77 years, with over 60 years experience [sic]
in the trade and 43 years as a registered builder with no blemishes to his record
and also willing to complete any work that is responsible for in this situation, is
very difficult to understand.
[12] The builder refers to the awareness of the matter by the QBCC, and addresses his
knowledge of the appropriate procedure as follows:2
John Joseph Bein has over 60 years experience [sic] in the trade with no marks
against his name. All the work that he was responsible for would have been
completed to all professional standards. It was unable to be completed due to
bullying abusive stand-over behaviour of the clients. The QBCC were notified
1 Submission of John Joseph Bein filed 9 October 2020, p 3.
2 Ibid p 5.
-- 3 of 9 --
4
of the impending problem in April 2018 when John Joseph Bein called into the
office of the QBCC to notify them of the problems that he was having. All
documents and correspondence are in the file BDL164-19.
John Joseph Bein did not understand that there was a protocol to be followed
within the QBCC system, as his intention was always to, complete the work. He
asked for help many times as to how this could be done. He was also fighting
to save his own life at the time as he was being treated for an aggressive case of
non-hodgkin’s lymphoma, followed by two heart attacks. Being the honest man
that he is, this put an enormous amount of stress on his life.
[13] The submission concludes as follows:3
A lengthy explanation to the question regarding a request for an Extension of
Time.
We are sorry for that but do not know how else to explain a very difficult
situation.
Submissions of the QBCC
[14] The QBCC filed a submission on 30 October 2020 in relation to the EOT application.
It notes that it appears that the builder seeks to extend the time to review various
antecedent decisions made by the commission throughout the course of the dispute
including the matter as a whole, and submits as follows:4
For reasons further developed in the Limitation Application, the Commission
submits that the only decision capable of review in this proceeding is the
Commission’s decision about the scope of work dated 13 February 2020. The
Commission submits that the other decisions contained in the Application to
review a decision are not capable of review, by virtue of section 86F(1)(c) of
the Queensland Building and Construction Commission Act 2009 [sic] (as over
28 days have elapsed since those decisions were served on the Applicant).
[15] The QBCC filed the limitation application on 5 May 2020, and sought the following
order:
The application to review a decision filed on 2 March 2020 is amended so that
the decision under review is the decision of the Commission dated 13 February
2020, about the scope of works to be undertaken under the statutory insurance
scheme to rectify or complete Tribunal work.
[16] The QBCC filed submissions in support of its limitation application together with that
application on 5 May 2020, and further submissions on 30 October 2020. The later
submissions say that the QBCC relies on the limitation application and the initial
supporting submissions.
[17] A summary of the key events relevant to the matter is set out in the QBCC
submissions.5 It is useful to set those events out as background information. I will edit
the summary to provide a concise review of the events:
3 Ibid p 6.
4 Submissions of the QBCC, 30 October 2020, p 1.
5 Submissions of the QBCC, 5 May 2020, p 4 to 6.
-- 4 of 9 --
5
(a) 19 February 2018 – the builder and the owners enter into a contract for the
renovation of a dwelling at Mango Hill in the state of Queensland in the amount
of $150,000.
(b) 25 July 2018 – the owners lodge a noncompletion claim with the QBCC.
(c) 20 August 2018 – the QBCC decides the owners had validly terminated the
contract at the default of the builder.
(d) 15 October 2018 – the QBCC advises the builder that it had identified items of
defective work.
(e) 21 November 2018 – the QBCC gives the builder a Direction to Rectify and/or
complete work No. 0104088.
(f) 26 July 2019 – the QBCC allows the owners’ claim for noncompletion and
defective work under the statutory insurance scheme.
(g) 31 July 2019 – the QBCC prepares a scope of works to be undertaken under the
statutory insurance scheme.
(h) 26 September 2019 – following an internal review, the QBCC confirms the
scope of works.
(i) 15 October 2019 – the QBCC notifies the owners that the claim under the
scheme is approved in the amount of $82,250.25.
(j) 12 February 2020 – the insurance consultants to the QBCC, Sedgwick, request
approval for a number of variations to the scope of works to be undertaken under
the statutory insurance scheme. These relate to a kitchen bi-fold window
(Variation 6) and a rumpus sliding door (Variation 7).
(k) 13 February 2020 – the QBCC makes a decision about the scope of work to be
undertaken under the statutory insurance scheme, and approves the variation to
the scope of works as to Variation 6 and Variation 7.
[18] The QBCC submits that the Review Application refers to three separate decisions
involving a scope of works under the statutory insurance scheme.
[19] It submits that section 86 of the Queensland Building and Construction Commission
Act 1991 (Qld) (‘the QBCC Act’) contemplates one reviewable decision per
application to the Tribunal and refers to the decision in Body Corporate for Alto
Gladstone v Queensland Building and Construction Commission & Anor.6
[20] The QBCC submits that a decision about the scope of works to be undertaken under
the statutory insurance scheme is not reviewable if 28 days have elapsed since the
decision was served on the building contractor, pursuant to section 86F(1)(c) of the
QBCC Act. It submits as follows:
6 [2020] QCATA 6, [73].
-- 5 of 9 --
6
21. In Queensland Building and Construction Commission v Watkins7 the
Queensland Court of Appeal held, in relation to an analogous section to the
present section 86F of the QBCC Act, that the relevant section:
… In prescribing that QCAT must not review decisions of the nature
described in the section if 28 days have elapsed since the relevant
decision or direction, makes it correct to conclude that it is a mandatory
provision having substantive rather than procedural effect.
22. It is well-settled, and has been held by the Tribunal on a number of
occasions, that the discretion to grant procedural relief, including an extension
of time, under section 61 of the QCAT Act may not be exercised in respect of
the mandatory time limitations imposed by section 86F of the QBCC Act.
23. Accordingly, and noting section 86F(1)(c) of the QBCC Act, both the
decisions of 26 September 2019 and 18 October 2019 are out of time, and are
now not reviewable by this Tribunal.
24. In the review application, the applicant also raises issues in relation to the
quantum of the claim. Noting section 86(1)(a) [sic] of the QBCC Act, a decision
to recover an amount is not reviewable.
25. In the commissions [sic] submission, the only decision capable of review
identified by the review application is the decision about the scope of works
dated 13 February 2020 (as detailed by Variation 6 and Variation 7).
[21] The QBCC refers to previous decisions in relation to the jurisdiction of the Tribunal
in a review of a decision about the scope of works to be undertaken under the statutory
insurance scheme, and notes that the Tribunal has previously held that a scope of
works review does not involve an examination of ‘issues of liability, surrounding
issues of fault, or the cause of [the defects].’8
[22] The QBCC submits that the scope of the review proceedings should be limited to a
consideration of whether the work to be performed in relation to the kitchen bi-fold
window and rumpus sliding door is reasonable and necessary.
Discussion
[23] Section 86F(1)(c) of the QBCC Act refers to decisions that are not reviewable
decisions:
86F decisions that are not reviewable decisions
(1) The following decisions of the commission under this Act are not
reviewable decisions under this subdivision –
(a) …..
(b) …..
(c) A decision about the scope of works to be undertaken under the
statutory insurance scheme to rectify or complete Tribunal work if
28 days have elapsed since the decision was served on the building
7 [2014] QCA 172, [16].
8 Col Jenkins & Associates v Queensland Building and Construction Commission [2019] QCAT 117,
[26].
-- 6 of 9 --
7
contractor and the contractor has not, within that time, applied to
the Tribunal for a review of the decision;
…
[24] The Tribunal has power under section 61 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld) (‘the QCAT Act’) to extend a time limit fixed for the start of
a proceeding by an enabling Act in certain circumstances. That section provides as
follows:
61 Relief from procedural requirements
(1) The Tribunal may, by order –
(a) extend a time limit fixed for the start of a proceeding by this Act
or an enabling Act; or
(b) extend or shorten a time limit fixed by this Act, an enabling Act or
the rules; or
(c) waive compliance with another procedural requirement under this
Act, an enabling Act or the rules.
[25] The application of section 61 of the QCAT Act was considered by the Court of Appeal
in Campaigntrack Victoria Pty Ltd v The Chief Executive, Department of Justice and
Attorney-General & Ors.9 Applegarth J. noted that the jurisdiction of the Tribunal
was limited by a provision in an enabling Act that acted as a prohibition:10
[34] The Appeal Tribunal’s reliance on Watkins was misplaced. That case
concerned a provision of the Queensland Building Services Authority Act
1991 (Qld) which relevantly provided: “The Tribunal must not review
the following decisions of the authority …” Dr Forbes, the member of
QCAT who dealt with a related matter, concluded that the prohibition
defined and limited the jurisdiction of the Tribunal. He stated: “It is not
merely a procedural rule that may be relaxed under section 61 of the
QCAT Act”. The matter before this Court was an appeal from an
adjournment of an application for summary judgment. The respondent to
that appeal did not challenge the decision of QCAT or make a submission
contrary to its effect. Douglas J, with whom McMurdo P and Morrison
JA agreed, did not question the correctness of the decision of QCAT and
concluded that the relevant provision which prohibited the Tribunal from
reviewing certain decisions of the Authority if 28 days had elapsed since
the relevant decision or direction had a “substantive rather than
procedural effect”.
[35] This Court in Watkins was considering a very different kind of statutory
provision to the kind of time period or time limit recognised by s
473(5)(b) and s 511(1)(a)(i) of PAMDA. As the Appeal Tribunal in this
matter acknowledged, s 511(1)(a)(i), when read together with s
473(5)(b), is not couched as a prohibition, as the provision was in
9 [2016] QCA 37.
10 Ibid, [34] and [35].
-- 7 of 9 --
8
Watkins. The provision in Watkins was a prohibition upon the Tribunal
which, in the words of Dr Forbes “defines and limits the jurisdiction of
the Tribunal”.
[26] Applegarth J. further noted that a modifying section in an enabling Act which
indicates that section 61 of the QCAT Act does not apply, prevails over section 61 of
the QCAT Act:11
[49] Section 61 will not apply if the enabling Act indicates otherwise, for
example, by stating that the period cannot be extended, that s 61 of the
QCAT Act does not apply to empower the Tribunal to extend the time,
or that an application must be brought in a certain time, failing which the
Tribunal shall not decide the application. Where an intent to preclude an
extension of time under s 61 is evident, there will be an inconsistency
between the modifying provision and s 61 so that the modifying provision
prevails in accordance with s 7 of the QCAT Act.
[27] The power of the Tribunal to extend time under section 61 of the QCAT Act therefore
applies to procedural requirements only and does not apply where an explicit
provision of an enabling Act provides that a time period cannot be extended as a
substantive provision.
[28] I accept the submissions of the QBCC that section 86F(1)(c) of the QBCC Act is a
substantive provision, as it provides that a decision of the type described in section
86F(1)(c) of the Act is not a reviewable decision. As the decision itself is not
reviewable, then there can be no availability to extend time to review such a
decision.12
[29] The builder did not file an application to review either of the first two decisions
referred to in his Review Application within 28 days of the decisions being served
upon him.
[30] The builder has submitted that he did not earlier file applications to review those
decisions as he did not understand ‘the QBCC system’, had personal health issues,
and was involved in a building dispute with the owners. Those may be matters which
would be relevant in an application to extend a procedural requirement but are not
relevant in relation to a substantive requirement.
[31] Accordingly, the Tribunal does not have jurisdiction in the circumstances to extend
the time for filing applications to review in relation to the decisions made on 26
September 2019, and 18 October 2019, and the application to review those decisions
must be dismissed.
[32] The application to review the decision of 13 February 2020 was filed on 2 March
2020, which is within the 28 day period provided for in section 86F(1)(c), and
therefore no extension of time is required in relation to that application, and that matter
may proceed.
[33] The QBCC has filed a separate application to amend the application to review a
decision, the limitation application. The effect of that application is to seek the same
11 Ibid, [49].
12 See also Eco-Builder Pty Ltd v Queensland Building and Construction Commission Pty Ltd [2018]
QCAT 59.
-- 8 of 9 --
9
outcome as results from the failure of the application to extend time to review the
decisions of 26 September 2019 and 18 October 2019. That application must
consequently succeed.
[34] The builder has enunciated numerous grievances he holds in relation to the actions of
the owners and the QBCC. He has referred to his long history in the building industry,
which he says is unblemished. Those matters, whilst of great personal significance to
him, do not affect the clear provisions of the QBCC Act in relation to the review of
decisions as to the scope of works under the statutory insurance policy and cannot
affect the outcome of these applications.
[35] I order that:
The Application to extend time, filed by John Joseph Bein on 28 February 2020,
is dismissed.
The Application to Review a decision, filed by John Joseph Bein on 2 March
2020, is to proceed having regard only to the decision of the Queensland
Building and Construction Commission made on 13 February 2020.
[36] The matter will now proceed, in accordance with Direction 7 given on 9 September
2020, to a Directions Hearing, at a time and date to be advised to the parties by the
Registry, for the making of further directions in relation to the progress of the
Application to Review a decision.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2021/109