Allen-Co Holdings Pty Ltd v Gympie Regional Council [2021] QPEC 64 [2023] QPELR 160
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Allen-Co Holdings Pty Ltd v Gympie Regional Council
[2021] QPEC 64
PARTIES: ALLEN-CO HOLDINGS PTY LTD
(appellant)
v
GYMPIE REGIONAL COUNCIL
(respondent)
FILE NO: 1504 of 2020
DIVISION: Planning and Environment
PROCEEDING: Appeal
ORIGINATING
COURT:
Planning and Environment Court, Brisbane
DELIVERED ON: 19 November 2021
DELIVERED AT: Southport
HEARING DATE: 29 September and 9 November 2021
JUDGE: Rackemann DCJ
ORDER: The appeal is allowed in part. The infrastructure charges
notice will be set aside and replaced by one in the terms of
the draft annexed to the respondent’s particularised list of
reasons filed on 24 August 2021. I will invite the parties to
submit appropriate minutes of order.
CATCHWORDS: PLANNING AND ENVIRONMENT – APPEAL – appeal
against an infrastructure charges notice (ICN) – where there
was an error in the calculation of the charge and the ICN
should be set aside and replaced – where debate as to the terms
of the replacement ICN – where a charge may be levied
because the development will place extra demand on trunk
infrastructure – where the adopted charge in the charges
resolution must be used to calculate the levied charge – where
the adopted charge rate for the development is $13,330 – where
the Council asserts this rate should be the basis for the
replacement ICN – where the appellant contends that the rate
of $13,330 should be discounted on the basis that the
development will generate extra demand on some forms of
trunk infrastructure, but not others – whether the charges
resolution should be so construed as to justify the application
of a proportional discount
-- 1 of 12 --
2
LEGISLATION: Planning Act 2016 (Qld) ss 112(1), (3), 113(1), 119, 120, 130
229(a), Sch 1 Table 1 Item 4, Sch 2
Planning Regulation 2017 (Qld) s 52(3)(a), Sch 16
CASES: Toowoomba Regional Council v Wagner Investments Pty Ltd
[2020] QCA 191
COUNSEL: N Loos for the appellant
K Wylie for the respondent
SOLICITORS: Connor O’Meara Solicitors for the appellant
McInnes Wilson Lawyers for the respondent
[1] This appeal relates to an Infrastructure Charges Notice (ICN) given to the appellant
coincident upon the approval of its application for a development permit for
reconfiguring a lot to create a 61-lot sub-division in five stages on land situated at 2110
Gympie Woolooga Road, Widgee. Following representations, the Council issued a
Negotiated Decision Notice with respect to the development approval, but maintained
the ICN.
[2] An appeal against an ICN may only be on one or more of the following grounds:1
(a) the notice involved an error relating to:
(i) the application of the relevant adopted charge; or
(ii) the working out of extra demand, for s 120; or
(iii) an offset or refund; or
(b) there was no decision about an offset or refund; or
(c) if the infrastructure charges notice states that refund will be given
– the timing for giving the refund; or
(d) for an appeal to the P&E Court – the amount of the charge is so
unreasonable that no reasonable relevant local government could
have imposed the amount.
[3] This appeal is on the ground that there was an error in the calculation of the charge
(engaging grounds (a)(i) and/or (ii)). It is common ground that there was an error, such
that the ICN should be set aside and replaced. The debate is as to the terms of the
replacement ICN.
[4] A local government may, by resolution, adopt charges for providing trunk infrastructure
for development.2 A regulation may prescribe development for which there may be an
1 Planning Act 2016 (Qld) (PA) Sch 1 Table 1 Item 4.
2 PA s 113(1).
-- 2 of 12 --
3
adopted charge and a maximum amount for providing infrastructure in relation to that
development.3 The Planning Regulation 2017 (Qld) (the Regulation) sets out, in
schedule 16, the prescribed maximum for development by way of (relevantly for present
purposes) reconfiguring a lot for a range of uses4 in respect of which a local government
may have an adopted charge. No point is taken by the appellant in relation to the specified
maximum amounts.5 The Council adopted charges on 23 November 2017 when its
infrastructure charges resolution (the charges resolution) came into effect. It remains
in effect. An appeal to this Court must not be about the adopted charge.6 The adopted
charge is, for present purposes, immutable.7
[5] The local government must give an ICN if a development approval has been given and
an adopted charge applies to providing trunk infrastructure for the development.8 It is
common ground that is the case in this instance.
[6] A charge may only be levied, by an ICN, for extra demand placed on trunk infrastructure
that the development will generate.9 To levy a charge in accordance with that limitation,
the Council therefore:10
(i) identifies whether the development will generate extra demand on
trunk infrastructure. That is done by identifying relevant trunk
infrastructure and determining whether extra demand will be
placed upon it by the development;11 and
(ii) if so, calculate the levied charge by using the adopted charge.
There is no requirement to put the adopted charge to one side in
order to consider the quantum of the charge to be levied on a first
principles basis, having regard to the extent of extra demand to be
placed upon the relevant trunk infrastructure. The adopted charge
is used, even though it might involve a “broad brush” approach.
[7] The first question is whether the development will generate extra demand on trunk
infrastructure, within the meaning of the PA. That expression is defined to include,
relevantly for present purposes, development infrastructure identified in an LGIP as
trunk infrastructure.12
[8] Development infrastructure is, in turn, defined as follows:
development infrastructure means—
3 PA ss 112(1) and (3).
4 s 52(3)(a) of the Regulation.
5 T1-12.
6 PA s 229(a).
7 Toowoomba Regional Council v Wagner Investments Pty Ltd [2020] QCA 191 at [89].
8 PA s 119.
9 PA ss 119(12)(a) and 120(1).
10 Toowoomba Regional Council v Wagner Investments Pty Ltd supra at [78] and [79].
11 but, subject to s 120(3), not including the matters in s 120(2) of the PA.
12 PA Sch 2.
-- 3 of 12 --
4
(a) land or works, or both land and works, for—
(i) water cycle management infrastructure, including
infrastructure for water supply, sewerage, collecting water,
treating water, stream managing, disposing of waters and
flood mitigation, but not water cycle management
infrastructure that is State infrastructure; or
(ii) transport infrastructure, including roads, vehicle lay-bys,
traffic control devices, dedicated public transport corridors,
public parking facilities predominantly serving a local area,
cycleways, pathways and ferry terminals; or
(iii) public parks infrastructure, including playground equipment,
playing fields, courts and picnic facilities; or
(b) land, and works that ensure the land is suitable for development, for
local community facilities, like—
(i) community halls or centres; or
(ii) public recreation centres; or
(iii) public libraries.
[9] It is agreed, between the parties, that the subject development would generate extra
demand on trunk infrastructure identified in an LGIP as trunk infrastructure. In particular
it is agreed as follows:
“For the purposes of the PA, the LGIP and the 2017 charges resolution,
the development approved by the P & E Court approval will generate
extra demand upon the following trunk infrastructure networks:
(a) transport – trunk roads;
PARTICULARS
(i) trunk roads, future roadworks, trunk road bridges, trunk road bus
shelters, future intersection upgrades, future transport facilities
and future bridge upgrades in the Gympie catchment identified
in maps PFTI-TRD-1 to PFTI-TRD-20.
(b) transport – trunk pathways; and
PARTICULARS
(i) trunk pathway depicted on map PFTI-TPW-63, as well as other
trunk pathways in the Gympie catchment.
-- 4 of 12 --
5
(c) parks and community facilities
PARTICULARS
(i) the community facility and district sports park (Winifred Power
Park) depicted on map PFTI-PCF-63, as well as other parks and
community facilities in the Western Catchment and the Gympie
Urban Catchment.
[10] It follows that a charge may be levied for the extra demand placed on trunk infrastructure
by the development. Attention then turns to the charges resolution in order to identify
the adopted charge to be used in calculating the charge to be levied.
[11] The charges resolution applies to the entirety of the local government area13 but, as it
may do by reason of s 114(2) of the PA, sets different adopted charges for development
in different parts of the local government area. Part 3 of the charges resolution deals
with the adopted charge rate. It does so by reference to different kinds of development.
It distinguishes between development by way of reconfiguration of a lot (s 3.1) and
development by way of a material change of use. Insofar as the latter is concerned, it
further distinguishes between a material change of use for residential development
(s 3.2) and for non-residential development (s 3.3).
[12] The relevant development, in this case, is reconfiguring a lot. That is dealt with in s 3.1
of the charges resolution which provides as follows:
“The adopted infrastructure charge for reconfiguring a lot is the amount
stated in for residential (three or more bedroom dwelling) in Table 2 less
any credit identified in 4.2.”
[13] Table 2 appears in s 3.2 of the charges resolution and, as its heading states, sets out the
adopted infrastructure charge for material changes of use for residential development.
The adopted charge rate for residential (three or more bedroom dwelling) varies
depending upon the location of the development. For Imbil and Kilkivan (within which
the subject site is located) the rate is $13,330 per dwelling. The effect of s 3.1, read with
Table 2, is that the adopted charge rate for reconfiguring a lot in Imbil and Kilkivan is
$13,330 per lot, less any credit. That figure is, indeed, what the Council asserts should
be the basis for the replacement ICN.14 The ICN the subject of the appeal utilised a
figure of $15,839, which Council concedes is wrong.
[14] The appellant acknowledges that the correct starting point is the rate of $13,330 per lot,
but contends that the rate should be discounted. Although s 3.1 does not expressly
provide for any discount, the appellant contends, in effect, as follows:
13 s 2.1 of the charges resolution.
14 It acknowledges that credit should be given for the one dwelling currently on site.
-- 5 of 12 --
6
(i) The statutory limitation that a charge may only be levied for extra
demand on trunk infrastructure should be read as a limitation with
respect to each kind of trunk infrastructure. In that regard it points
to the definition of development infrastructure extracted above to
submit that the legislation requires the charges resolution to adopt
charges which facilitate charges being levied by reference to
amounts for extra demand on the relevant constituent components
of trunk infrastructure, being the four broad types of development
infrastructure (water cycle, transport, public parks and local
community facilities) referred to in the definition (rather than the
five networks in the charges resolution);
(ii) The charges resolution refers to five trunk infrastructure networks,
namely transport, public parks, stormwater, water supply and
sewerage;
(iii) Whilst it is accepted that the development will generate extra
demand on some forms of trunk infrastructure, it is also agreed that
it will not generate extra demand upon other forms of trunk
infrastructure referred to in the charges resolution, namely trunk
water, sewerage or storm water infrastructure (all of which are
forms of water cycle management infrastructure);
(iv) In the absence of the application of a discount to the rate of
$13,330, the replacement ICN, as contended for by the Council,
would impermissibly impose a charge for networks upon which the
appellant’s development would generate no additional demand,
and
(v) The charges resolution should therefore be applied or construed in
such a way as to afford a level of discount to avoid that
consequence. That can be done by reference to a certain table in the
charges resolution.
[15] In order to better appreciate that argument and how the appellant contends the discount
ought be quantified, it is necessary to say something more about the charges resolution.
It has already been observed that the charges resolution deals with different kinds of
development in different sections. It also deals with each of those kinds of development
in different ways. Development by way of a material change of use for non-residential
development is dealt with in s 3.3. It contains Tables 3 and 4 which apply to different
localities. The latter applies to the area within which the subject site falls. The table has
six columns. The first lists the adopted infrastructure charge category. The second lists
the planning scheme use definitions which correspond with the relevant category. The
third describes a relevant unit of demand (per square metre GFA). Columns four, five
and six set out the rate (dollars per unit of demand) for each of the five trunk
-- 6 of 12 --
7
infrastructure networks referred to in the charges resolution.15 This facilitates a network-
by-network calculation of the charge. The charges resolution then provides, in effect,
that the water supply and/or sewer charges will not apply where development is not
serviced by water or by both of those networks, as the case may be.
[16] The adopted charge for a material change use for residential development is dealt with
in s 3.2 and is calculated on a different and more broad brush basis. The section does
not nominate a rate for each type of infrastructure network. Rather, it applies various
units of demand (depending on the type of the residential use) to various specified
amounts of money (depending on the location) to arrive at the charge. The adopted
charge is however, reduced as follows:
(i) 25 per cent where the development is serviced by water but not by
sewer, or
(ii) 45 per cent where the development is not serviced by either water
or sewer.
[17] The provision as to a discount is introduced by a paragraph that commences “the
proportional network split is generally in accordance with Table 1”. Table 1, which
immediately follows the provision about the discount is as follows:
Network Total trunk infrastructure
network value
Proportional split
Water $93,116,531 26%
Sewer $74,639,643 21%
Stormwater $10,282,077 3%
Transport $101,528,418 29%
Parks $74,593,012 21%
[18] The provision as to the discount and Table 1 to which it refers, are both contained within
s 3.2 of the policy dealing with the adopted infrastructure charge for a material change
of use for residential development. Those provisions are obviously not of general
application. For example, the discount is dealt with in an entirely different way in s 3.3.
Further, s 3.1 makes no mention either of any discount, or of Table 1. The purpose of
including Table 1 appears to be to give some explanation for the derivation of the
discount provision in s 3.2, although the quantum of the discount for having no
connection to water and/or sewer does not match precisely the proportional split for those
items in Table 1.
15 water supply and sewerage are both in column 4, whilst transport and public parks are each in column 5.
-- 7 of 12 --
8
[19] Notwithstanding the above however, the appellant contends that s 3.1 of the charges
resolution should be read or applied so as to include the “proportional network split”
referred to in s 3.2 and particularised in Table 1, to facilitate a network by network
proportional discounting of the charge otherwise set by s 3.1. The consequence, for
which it contends, is a discount of 50 per cent to reflect the fact that its development will
not generate additional demand on trunk infrastructure for water (26 per cent), sewer (21
per cent) or storm water (3 per cent). Alternatively, it submits that it should, at least,
receive the 45 per cent discount that would be applicable if its development fell under
the discounting provisions in s 3.2. The appellant submitted that the approach for which
it contends is consistent with construing the charges resolution purposively and in light
of the statutory limitation in s 120 of the PA as to what a charge may be levied for.
[20] It is difficult to find any justification on the face of the charges resolution for the
construction contended for by the appellant. As has already been observed:
(i) The charges resolution sets the adopted charge rates in three
distinct sections.
(ii) Each of those sections deals with different development under
different headings.
(iii) Each of the sections sets the adopted rate in different ways.
(iv) Two of the sections deal with discounts, but in different ways,
whilst the section that applies to the subject form of development
makes no reference to any discount.
[21] It is difficult to reach the conclusion that the above distinctions are anything other than
intended. It is particularly difficult to accept that the charges resolution should be
construed as requiring or permitting the adopted charge to be identified, for the purposes
of calculating the charge to be levied in relation to a reconfiguration of a lot, by reference
to Table 1 in circumstances where the table:
(i) appears in s 3.2, which deals with a material change of use for
residential development, but even then only as information as to
what the “proportional network split” is “generally” in accordance
with;
(ii) is not adopted, even in s 3.2, for quantifying the discount, since the
discounts adopted are slightly different to the proportional splits
for water and sewer in the table, and
(iii) is neither referred to within s 3.1 nor adopted by it, notwithstanding
that s 3.1, which deals with a different type of development,
otherwise expressly adopts one aspect of another table (Table 2) in
s 3.2.
-- 8 of 12 --
9
[22] It is unnecessary to adopt the highly strained construction contended for by the
appellant in order to read the charges resolution or to apply it harmoniously with s
120 of the PA. The premise of the appellant’s argument is that the charge now
contended for by the Council would impermissibly impose a levy for demand
placed on each and every one of the trunk infrastructure networks referred to in the
charges resolution when its development will, in fact, only generate demand on
some. Indeed counsel for the appellant, in the course of argument,16 accepted that
his submission depended upon the $13,330 rate, as applied to reconfiguration of a
lot, being a charge for all five of the networks referred to in the charges resolution
in accordance with the proportional split the Court was being asked to apply in
order to arrive at the discount sought by the appellant. He contended that is to be
inferred from the charges resolution read as a whole.17 The charges resolution does
not so provide.
[23] Section 3.1 does not adopt a charge by reference to discrete infrastructure networks.
Rather, it adopts a single charge for development of a particular kind, namely
reconfiguring a lot.18 Because of s 120 of the PA, that can only be construed and
applied to levy a charge in relation to development of that kind which generates
extra demand on trunk infrastructure.19 Where, as here, the development does so,
the adopted charge is as provided for in s 3.1, by reference to the specified part of
Table 2. The quantum of the adopted charge in relation to development by way of
reconfiguring a lot is not divisible or dependent upon the type or types of trunk
infrastructure upon which the development will generate extra demand.20 The
quantum of the charge is the same irrespective of the type or number of networks
upon which the extra demand will be generated. It is, arguably, the broadest of
broad brushes, but that is different from saying that the charge when levied is for
extra demand on each and every one of the infrastructure networks in accordance
with the proportional split in Table 1.
[24] It was submitted, for the appellant, that the legislation does not contemplate a
“global charge” of this kind which, it was said, would take meaning away from s
120(1). It has already been observed that the appellant placed reliance on the
definitions of ‘trunk infrastructure’ and ‘development infrastructure’ to submit that
there must be differentiation between the components of trunk infrastructure. The
charges resolution does not do that in relation to development by way of
reconfiguring a lot. This appeal cannot be about the adopted charge. The
appellant’s submissions, in this regard, are something of a veiled attack on the
adopted charge under the guise of a submission on the proper interpretation of the
charges resolution.
16 T1-44, 45.
17 T1-46.
18 It may be noted that Sch 16 of the Regulation, in setting the prescribed amounts, does so by reference to
amounts for trunk infrastructure not for particular kinds of trunk infrastructure.
19 See Toowoomba Regional Council v Wagner Investments Pty Ltd supra at [103].
20 It was not suggested that PA s 115(4) is applicable.
-- 9 of 12 --
10
[25] In any event, the definition of trunk infrastructure, when read with that for
development infrastructure informs the parameters of what a charge may be levied
for, rather than mandates the structure of the charges resolution. It might be, as
counsel for the appellant points out, that the limitation in s 120(1) of the PA is
relatively undemanding in circumstances where the charges resolution adopts a
charge which is applied in the context of development of a specified kind whenever
there is extra demand placed on any trunk infrastructure, but that does not mean
that s 120(1) is robbed of meaning. Further, s 120 of the PA does not, in my view,
require the adopted charge in s 3.1 of the charges resolution to be applied or to be
construed as applying, without discount, only in circumstances where the subject
development would generate extra demand on each and every one of the networks
referred to in the charges resolution.
[26] The appellant sought to call in aid the statement of purpose in the charges resolution
which is as follows:
“The purpose of the resolution is to assist with the implementation of the
applicable local planning instruments by stating the following:
(a) An adopted charge for the purpose of determine [sic] a levied charge for
funding part of the establishment cost of the following trunk infrastructure
networks:
(i) Transport network;
(ii) Public parks network;
(iii) Storm water network;
(iv) Water supply network;
(v) Sewerage network.
(b) Other matters relevant to the adopted charges.
[27] It may be accepted that the purpose of levying charges, in accordance with the charges
resolution, throughout the local government area is to obtain money to fund ‘part’ of the
establishment costs of the nominated networks. It does not follow however, that the
charges resolution is properly construed or applied as if it adopted differential rates on a
network-by-network basis or was subject to a discounting mechanism for development
by way of reconfiguration of a lot, so that development that places extra demand on one
kind of trunk infrastructure is levied a different amount to that which places extra
demand on another or others. It also does not follow that by setting a single adopted
charge the charges levied are for something other than the extra demand placed on trunk
infrastructure that the development will generate.
[28] That the amount of $13,330 where applied in s 3.2 is subject to a discount of 25% or
45% where water or water and sewer is not connected supports the proposition that,
-- 10 of 12 --
11
where applied without discount in the context of development by way of a material
change of use for residential development, it is levied for extra demand placed on trunk
infrastructure that includes extra demand on those two networks. It does not follow
however, that the same applies where the figure is used for a different form of
development, dealt with in a different section of the policy and in circumstances where
there is no discount or breakdown of the charge on a network-by-network basis.
[29] It was also submitted that to use Table 1 in the manner contended for by the appellant
would be consistent with s 2.1 of the charges resolution which provides, in part, as
follows:
“But where development is outside the priority infrastructure area shown
in the LGIP, Council will assess the impact of the development upon the
trunk networks.”
[30] The location of development outside of a priority infrastructure area (PIA) is also
referred to in s 2.3 as follows:
“2.3 Development inconsistent with assumptions about future
development
Development is inconsistent with the assumptions about future
infrastructure in the local government infrastructure plan (LGIP)
if:
…
(c) the location of development – the premises is located
outside the priority infrastructure area (PIA) as identified
in the LGIP; or
…”
[31] As counsel for the respondent pointed out, the reference to the Council assessing the
impact of development where premises are located outside of the PIA is likely explained
by the fact that s 130 of the PA permits the imposition of a development condition
requiring the payment of extra trunk infrastructure costs (after taking into account levied
charges for the development), in certain circumstances, for premises that are completely
or partly outside the PIA. In any event, there was no evidence before the Court which
would permit an assessment of the impact of the development upon the trunk networks
on a first principles basis and I do not consider that the provision should be construed or
applied as an obstacle to a charge being levied on the basis of the adopted charges in part
3 of the charges resolution. Further, I do not consider that the provisions justify adopting
the rate in accordance with s 3.1 of the charge resolution subject to a discounting regime
grafted onto it by reference to either Table 1 or the discounting provisions of s 3.2. That
is not a necessary or proper application of the charges resolution.
-- 11 of 12 --
12
[32] The appellant might well feel aggrieved that the application of the charges resolution
leads to a levied charge which is of the same quantum as that which would be levied in
respect of reconfigurations which placed extra demand upon a different number of the
trunk infrastructure networks referred to in the charges resolution. Others might feel
aggrieved by the adoption, for all development by way of reconfiguration of a lot that
generates extra demand on trunk infrastructure, of the amount specified in Table 2 for
residential (3 or more bedroom dwelling) even where the reconfiguration is not to
facilitate a use of that kind. Such grievances are not uncommon where broad brush
approaches are taken. The appellant did not directly attack the validity of the charges
resolution and, as has been observed, the appeal may not be about the adopted charge.
Further, the appellant did not attempt to advance the unreasonableness ground of appeal
and no sufficient evidentiary basis was laid for it in any event. It has also been noted that
the statutory scheme involves specified maximum charges for development, including,
relevantly, reconfiguration (which are specified in schedule 16 of the regulation as
‘global’ amounts ie not by reference to components of infrastructure) in respect of which
a local government may have an adopted charge and there was no issue about the
maximum charge.
[33] For the reasons given, the ICN should be replaced with one which levies a charge in the
manner proposed by the respondent. The parties agree that, in those circumstances, the
replacement should be in the terms of the draft ICN annexed to the respondent’s
particularised list of reasons filed on 24 August 2021.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2021/064