E.J. Cooper & Son Pty Ltd v Townsville City Council & Anor [2021] QPEC 20 [2022] QPELR 433
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: E.J. Cooper & Son Pty Ltd v Townsville City Council & Anor
[2021] QPEC 20
PARTIES: E.J. COOPER & SON PTY LTD
(appellant)
v
TOWNSVILLE CITY COUNCIL
(respondent)
and
CHIEF EXECUTIVE, DEPARTMENT OF
TRANSPORT AND MAIN ROADS
(co-respondent by election)
FILE NO/S: 4894 of 2013
DIVISION: Planning and Environment
PROCEEDING: Appeal
ORIGINATING
COURT:
Planning and Environment Court, Brisbane
DELIVERED ON: 31 March 2021
DELIVERED AT: Brisbane
HEARING DATE: 12, 13, 14, 15, 16, 19, 20, 21, 22 and 23 October 2020, 3, 4
and 6 November 2020 and 11 December 2020 with further
material received to 10 February 2021.
JUDGE: Rackemann DCJ
ORDER: The appeal is dismissed.
CATCHWORDS: PLANNING AND ENVIRONMENT – APPEAL – appeal
against refusal of a development application under the
Integrated Planning Act 1997 – application for a preliminary
approval for a material change of use to develop a large rural
holding into a master planned residential community
supported by other uses – where the development application
also sought a variation to the planning scheme – the operation
of statutory provisions in relation to such applications –
whether the application for a preliminary approval for the
material change of use must be assessed against the
provisions of the Planning Scheme sought to be varied – what
weight should be given to the more recent planning
documents – whether proposal should be refused having
regard to the nature of the proposed uses, its likely impact on
-- 1 of 89 --
2
amenity, potential for reverse amenity impacts, infrastructure
requirements, traffic impacts or having regard to issues of
flooding or stormwater quality - whether the proposal
conflicts with the planning documents – whether the
application ought be approved having regard to
grounds/matters in favour of the proposal – whether there is a
need sufficient to support approval – likely benefits in times
of flood – benefits from stabilizing and rehabilitating eroded
parts of the site – other matters in favour – whether the
development should be approved in part – whether the
variations component of the application should be approved
CASES: Aldi Stores v Redland City Council [2009] QPELR 602
Bell v Brisbane City Council, Gold Coast City Council (2018)
230 LGERA 374
Brown v BCC [2005] QPELR 629
Gold Coast City Council v K & K (GC) Pty Ltd (2019) 239
LGERA 409
Lewiac Pty Ltd v Gold Coast City Council and Another
(2011) 180 LGERA 117
Lipoma Pty Ltd & Anor v Redland City Council & Anor
[2020] QCA 180
Lockyer Valley Regional Council v Westlink Pty Ltd [2013] 2
Qd R 302
Nerinda Pty Ltd v Redland City Council [2019] 1 Qd R 523
Redland City Council v Aldi Stores [2009] QCA 346
Redland City Council v King of Gifts (Qld) Pty Ltd [2020]
QCA 41
Residential Developments Australia Pty Ltd v Brisbane City
Council [1990] QPELR 121
Stockland Development v Sunshine Coast Regional Council
[2014] QPELR 52
Weightman v Gold Coast City Council [2003] 2 Qd R 441
Woolworths Ltd v Maryborough City Council (No 2) [2006] 1
Qd R 273
LEGISLATION: Integrated Planning Act 1997 (Qld) ss 1.3.2, 3.1.6, 3.5.5,
3.5.5A, 3.5.14, 3.5.14A, 4.1.50(1), 4.1.52(1), (2)
Integrated and Other Legislation Amendments Act 2003
(Qld)
Planning Act 2016 (Qld) ss 289(2), 311
Sustainable Planning Act 2009 (Qld) ss 242, 326, 329, 802,
-- 2 of 89 --
3
819
COUNSEL: D Gore QC and M Batty for the appellant
B Job QC, J Ware and T Stork for the respondent
K Buckley for the co-respondent by election
SOLICITORS: Thynne + Macartney for the appellant
Townsville City Council Legal Services for the respondent
Norton Rose Fulbright for the co-respondent by election
-- 3 of 89 --
4
Table of Contents
Background .......................................................................................................................... 6
The Site................................................................................................................................. 7
The Proposal ......................................................................................................................... 7
Statutory Framework .......................................................................................................... 10
The Decision Framework under IPA.................................................................................. 10
Onus and Nature of Appeal ................................................................................................ 18
The Planning Documents ................................................................................................... 19
The Issues ........................................................................................................................... 20
The Conflict/Matters Raised Against the Proposal ............................................................ 21
(i) Residential and Other Urban (Non-rural) Use ........................................................... 21
(a) TPS 2003 ............................................................................................................... 21
(b) CP 2014 ................................................................................................................. 28
(c) NQRP ..................................................................................................................... 31
(d) Conclusion on Residential and Other Urban (Non-Rural) Use ............................. 32
(ii) Landscape Character and Visual Amenity ................................................................ 33
(iii) Ecology .................................................................................................................... 39
(iv) Amenity – Noise ...................................................................................................... 49
(v) Reverse Amenity and Impact on Nearby Rural Land Use ........................................ 49
(vi) Infrastructure ............................................................................................................ 52
(vii) Traffic ..................................................................................................................... 55
(a) Modelling............................................................................................................... 58
(b) Intersection Analysis ............................................................................................. 61
(c) Scope for the Upgrades .......................................................................................... 62
(d) The Reverse Curve ................................................................................................ 64
(e) Conclusion on Traffic ............................................................................................ 65
(viii) Flooding ................................................................................................................. 66
(ix) Stormwater Quality .................................................................................................. 67
(x) Uncertainty ................................................................................................................ 67
Grounds/Matters in Favour of Approval ............................................................................ 68
(i) Need ........................................................................................................................... 70
(ii) The Benefits of the Site and Development from a Flooding Perspective ................. 79
(iii) Sodic Soil/Erosion ................................................................................................... 80
(iv) Other Grounds/Factors in Favour ............................................................................ 83
(v) Appellant’s Summary ............................................................................................... 85
-- 4 of 89 --
5
Conclusion on Material Change of Use Component .......................................................... 85
Approval in Part ................................................................................................................. 86
The Variation Component .................................................................................................. 87
Conclusion .......................................................................................................................... 89
-- 5 of 89 --
6
Background
[1] This is the oldest appeal within this Court. It was commenced in 2013 against the
deemed refusal of a development application made in December 2008. It is more
than 10 years since the development application was subject to public notification.
The approval sought by the appellant is for the purposes of facilitating the future
development of a large rural holding south west of the developed part of
Townsville, within the former Thuringowa Shire, at the foothills of the Pinnacles. It
proposes a master planned residential community, supported by other uses and
facilities.
[2] The delay in progressing the matter was explained in the evidence of the appellant’s
representative, whose statement revealed, amongst other things, that:
(a) the land was purchased, for the purpose of future development in 2007,
in the belief that “common sense dictated” (although the planning
scheme did not) that land at Pinnacles would be next in line for
development;1
(b) the development application was lodged on 23 December 2008;
(c) in 2009 the Council commenced work on a new planning scheme. It
was also, at that time, unsupportive of the development application;2
(d) the appellant, it seems, spent some years unsuccessfully attempting to
persuade the Council that its proposal ought be supported in the new
planning scheme;3
(e) by a letter dated 22 May 2013,4 the Council advised that its concerns in
relation to the ongoing operational and maintenance costs of additional
infrastructure required for the proposal and the absence of need for
additional land to be zoned for urban purposes (or that Pinnacles should
be the next growth front) had not been allayed; the appellant thereupon
chose to institute the subject appeal; and
(f) following the institution of the appeal, many experts were engaged to5
provide advice. The appellant subsequently spent an extended period of
time unsuccessfully attempting to negotiate a resolution. Eventually it
accepted that it would not succeed and with “additional pressure from
the Court to progress the appeal” the matter eventually came on for
hearing.
1 Ex 62 para 12.
2 Ex 62 para 31, 33.
3 Ex 62 paras 34-37.
4 Ex 63 para 38.
5 Ex 62 paras 41-45.
-- 6 of 89 --
7
[3] The extent of delay in this case is quite exceptional. It should not be taken to be a
precedent for the level of patience which this Court will exhibit in respect of delay,
even where matters are large and/or complex.
The Site
[4] The subject site is located at 360 Round Mountain Rd, Pinnacles, Townsville and is
more particularly described as Lot 4 on SP132604. It is a relatively large holding of
1,189ha in area. It is improved with a farm house, fencing, some rural outbuildings
and informal tracks.
[5] The site features a relatively flat plain in the central and eastern parts of the site and
a more elevated section in the foothills of the Harvey Range. There are two main
creeks (Stoney Cr and Middle Cr) which traverse the site in a generally west/east
direction. There are other minor streams.
[6] The site adjoins other rural allotments. There is also some rural/residential sized
allotments a little further to the east. Reflecting its rural location, the site is removed
from urban facilities. The distance from the centre of the site to the supermarket at
Rasmussen was variously described as approximately 8km6 or 6km or more7 by
road. Similarly it is not currently served by other infrastructure to a standard that
would be necessary to support development of the kind intended.
The Proposal
[7] The development application was made under the Integrated Planning Act 1997.
The application sought two things as follows:
(a) a preliminary approval for a material change of use, described in the
development application as a “mixed use residential community
comprising of residential, commercial, light industrial, community and
open space and land uses within 9 separate neighbourhoods, to a
maximum building height of 3 storeys or 12m”, and
(b) a variation to the planning scheme to change the level of assessment for
45 uses (from impact assessable) and to nominate applicable codes for
uses and for the assessment of applications for reconfiguration and for
operational works.
[8] The intention is for development to be guided by a new Pinnacles Development
Plan (PDP). That plan includes codes. One is the Pinnacles District Code (PDC).
The purpose of the PDC is to achieve the Overall Outcomes and objectives for the
PDP area. Its Overall Outcomes contain broad statements of intent. Specific
Outcomes of the PDC provide an intent for each of the Precincts.
6 T6-36.
7 Ex 50 para 14.
-- 7 of 89 --
8
[9] The Residential Precinct intends “primarily” to be a suburban area for a range of
housing types of varying scale and density. That may include a mix of dual
occupancies, multiple dwellings and aged care and retirement villages. Density is to
be generally low (10 dwellings per net hectare) to medium (15 dwellings per net
hectare within “easy walking distance” (defined as 400m)) of Local Centre and
Mixed Use Town Centre Precincts and parkland. Densities are not to exceed the
maximum dwelling yield identified on Map 2 and on subsequent approved DLUPs.
[10] The Mixed Use Town Centre Precinct envisages a single large shopping complex
with retail uses up to 6,000m 2 and offices and commercial premises up to 7,000m 2
.
Possible uses include indoor recreation (cinemas or gyms), education facilities,
restaurant, hotel or short-term accommodation, office, place of worship and medical
centre. It is intended to be “an employment centre for the wider Pinnacles
residential community”.
[11] The Local Centre Precincts are to generally serve catchments of 1,000 to 2,000
households and include convenience shopping, personal services, catering shops,
restaurants, community facilities, healthcare services and offices, and service
stations. Retail uses of up to 200m 2 and up to 800m 2 for offices and commercial
premises are envisaged.
[12] The Light Industry and Enterprise Land Use Precinct is to accommodate a “broad
range” of light industrial, manufacturing and servicing, large-scale retail uses,
storage facilities, distribution centres, sales and hire yards and similar uses. “Retail
showrooms and bulky good land uses” are also envisaged. The area is intended to
act as an employment generator.
[13] The Community Use Precinct is the preferred location for education facilities as
well as possible social and community services, health, recreational and
entertainment facilities. Child care centres, community residences, cultural
facilities, institutional residences, hospitals, retirement villages, medical centres,
and outdoor recreational and places of worship are envisaged. The application
report referred to up to 3 primary schools and 2 high schools.
[14] The Open Space Precinct was intended to incorporate parkland, together with
remnant vegetation, riparian corridors and watercourses with ancillary facilities and
pathways. There have been changes, discussed later, as to what may be done in the
open space precinct.
[15] Another code is the Detailed Land Use Plan Code (DLUP Code) which is provided
for under the PDC. A Detailed Land Use Plan (DLUP) must be approved for each
neighbourhood prior to any application for any further development. A DLUP for
each neighbourhood would be the subject of a code assessable “material change of
use” application, provided it is generally in accordance with the approved PDP. The
DLUP must be assessed against the DLUP Code and the PDP. The DLUP would
establish cadstral boundaries for Precincts, and a framework for the location of land
uses, roads, parks, stormwater drainage and other infrastructure. A DLUP would
-- 8 of 89 --
9
establish “in principle” support for land use areas and criteria for future
applications.
[16] The Overall Outcome for the DLUP Code is that a DLUP is generally in accordance
with the approved PDP including Maps 1 to 4.8 The term “generally in accordance”
is defined in s 4.2 of the DLUP Code. It relevantly includes that precincts
nominated within the DLUP are located as indicated on the approved PDP Map 1
and the probable solutions of the DLUP Code; residential densities and yields do
not exceed those nominated on the approved PDP Map 2; maximum GLA for other
uses do not exceed those nominated in the PDC; the DLUP achieves the Overall
Outcomes within the PDC; and infrastructure of a sufficient capacity is available, or
can be made available for the area the subject of the proposed DLUP. Specific
Outcomes are stated for each of the neighbourhood areas (NH1-NH9).
[17] The proposal is to concentrate development generally into the flatter parts of the
site, whilst retaining the two creeks to which reference has been made. The open
space otherwise is concentrated mainly in the western part of the site. The projected
ultimate residential lot yield was 5,100 lots. That was contained within the
application report itself, and more particularly within the PDP. With changes that
have since been made to the proposal (discussed later), that number of residential
lots is unlikely to be realised if the proposal were to proceed, since the changes have
significantly reduced the extent of land that would be available for development.
[18] The PDP identifies the applicable codes for future development applications within
the PDP area. Those codes are the PDC and DLUP Code as well as certain codes
forming part of the planning scheme. The PDP defines the planning scheme by
reference to the Townsville City Plan 2005 (CP 2005) up to and including
amendment 17 of 2008. On its face the proposal seeks to apply those codes to
development that would take place well into the future. Senior Counsel for the
appellant at one point foreshadowed an application to amend the proposal so that
the relevant codes would be those current from time to time, but later informed the
Court that no such application would be made.
[19] There have been changes to the proposal in the course of the appeal, and more are
foreshadowed or would be required in the event that the Court were to deliver a
judgment indicating that the appeal would be allowed subject to the formulation of
appropriate terms of order. Prior to the hearing the plans were changed to reflect a
seven stage development with, amongst other things:
(a) a reduced development footprint and consequential increase in open
space; and
(b) the introduction of a vegetation and watercourse buffer.
8 and that infrastructure and services technical reports are submitted to demonstrate the need for and
capacity of trunk infrastructure.
-- 9 of 89 --
10
[20] In the course of the hearing a further amended plan was produced, which further
reduced the development footprint and further increased the open space. The
proposal was also changed such that stormwater infrastructure, such as detention
basins, are now to be kept out of the open space areas and are instead to be included
within the development footprint (as are the parks and, indeed any uses save for
road crossings).9 That was to address the difficulty that the open space was
previously being relied on for disparate and potentially conflicting purposes given
its ecological value. Other aspects of the PDP would require attention prior to any
final orders in the appellant’s favour.
Statutory Framework
[21] It has already been observed that the development application was made in 2008,
during the currency of the Integrated Planning Act (IPA). That was superseded by
the Sustainable Planning Act (SPA) which was, in turn, superseded by the Planning
Act (PA).
[22] The appeal to this Court was commenced during the currency of SPA. At the time
SPA commenced, the development application had been made under IPA but not
decided. Accordingly, it was required to be dealt with and decided as if IPA
continued to apply.10 Further, any appeal was required to be heard and decided
under IPA.11 The proceeding having commenced before PA, the position was, for it,
effectively preserved under s 311 of the PA.
[23] It is common ground that if the appeal is allowed and the development application
approved, the approval will take effect as a variation approval for the purposes of
the PA.12
The Decision Framework under IPA
[24] Not all applications for preliminary approvals are for master planned developments
or seek any variation to the effect of the planning scheme, but some are of that kind.
Section 3.1.6 of IPA made provision for preliminary approvals that approved a
material change of use and overrode a local planning scheme instrument in certain
ways. The subject development application was for such an approval and was
subject to impact assessment which, under IPA, was to be carried out pursuant to s
3.5.5. Relevantly, s 3.5.5(2) provided that, if the application was for “development”
in a planning scheme area, the assessment was required to be carried out having
regard to a number of things, including the planning scheme.
[25] “Development” was defined, for the purposes of IPA, in s 1.3.2 to include,
relevantly for current purposes, making a material change of use of premises. The
9 T11-7.
10 s 802 of SPA.
11 s 819 of SPA.
12 A preliminary approval under IPA is taken to be a “preliminary approval to which s 242 applies”
under SPA (s 808(2)) which, in turn, is taken to be a variation approval (s 289(2) of PA).
-- 10 of 89 --
11
application for a preliminary approval for the material change of use was therefore
required to be assessed pursuant to s 3.5.5 having regard to, inter alia, the planning
scheme. That the component of the application which sought approval for the
development was required to be assessed, in the case of impact assessable
applications, pursuant to s 3.5.5 was expressly contemplated by s 3.5.5A(2)(b).
Further, the explanatory notes to the legislation13 that amended IPA to include s
3.5.5A stated, in part, that:
“Although sections 3.5.4 and 3.5.5 establish criteria for the assessment
of all development (including development the subject of an
application under section 3.1.6) the Act currently contains no
guidance about assessing the part of such an application that seeks to
vary the local planning instrument.”
[26] That part of the application which stated the way in which it was sought to vary the
effect of any applicable local planning instrument (the variation) was not making
application for a form of development. That part of the application fell to be
assessed pursuant to s 3.5.5A. By reason of 3.5.5A(2) that part of the application
was required to be assessed having regard to a number of matters including the
consistency of the proposed variations with aspects of the planning scheme, other
than those sought to be varied and the result of the assessment of the “development”
(the material change of use) under, relevantly, s 3.5.5.
[27] Decisions on development applications requiring impact assessment under IPA
were subject to the provisions of s 3.5.14. That included the following provision
(underlining added):
“(2) If the application is for development in a planning scheme
area, the assessment manager’s decision must not–
(a) compromise the achievement of the desired
environmental outcomes for the planning scheme area;
or
(b) conflict with the planning scheme, unless there are
sufficient grounds to justify the decision despite the
conflict.”
[28] As has already been observed, that part of the application which sought a
preliminary approval for the material change of use was for “development” in the
planning scheme area. Accordingly, s 3.5.14(2) applied to a decision on that part of
the application.
[29] Section 3.5.14A made specific provision for decision or applications under s 3.1.6
as follows (underlining added):
13 Integrated and Other Legislation Amendments Act 2003.
-- 11 of 89 --
12
“(1) In deciding the part of an application for preliminary approval
mentioned in section 3.1.6 that states the way in which the
applicant seeks approval to vary the effect of any applicable
local planning instrument for the land, the assessment manager
must–
(a) approve all or some of the variations sought; or
(b) subject to section 3.1.6(3) and (5)–approve different
variations from those sought; or
(c) refuse the variations sought.
[30] It is apparent that that does not refer to the part of the application that seeks a
preliminary approval of the material change of use (that being caught by s 3.5.14),
but rather only applies to the part of the application which sought the variation. That
is clear both from the introductory paragraph in s 3.5.14A(1) and from the nature of
the orders referred to in the subparagraphs. The relevant explanatory note said that
the provision was to compliment s 3.5.5A. It did not contain a similar
conflict/grounds test, but did go on to provide, in part, as follows:
“(2) However–
(a) to the extent development applied for under other parts
of the application is refused, any variation relating to the
development must also be refused; and
(b) the assessment manager’s decision must not
compromise the achievement of the desired
environmental outcomes for the planning scheme area;
and…”
Since the material change of use is development applied for under another part of
the application, s 3.5.14A requires refusal of the variations in the event that the
MCU is refused.
[31] It was submitted, on behalf of the appellant that, although the substance of its
proposal, on any view, flies in the face of the planning scheme in force at the time
the development application was made, s 3.5.14(2) is not engaged in the sense that
there is no relevant conflict, because only a preliminary approval is sought. Reliance
was placed on the reasons of McMurdo JA in Lipoma Pty Ltd & Anor v Redland
City Council & Anor14 when considering the corresponding provisions of SPA
(referred to, for convenience, as the Nerinda point).
[32] In the written submissions it was contended, for the appellant, that the effect of His
Honour’s approach was that, insofar as the identification of conflict with the
planning scheme is concerned, there ought be no assessment of the proposed
14 [2020] QCA 180.
-- 12 of 89 --
13
material change of use against those parts of the planning scheme sought to be
varied. Accordingly it was submitted that no conflict arises in this case. It was
however, acknowledged that s 3.5.5 requires the material change of use to be
assessed having regard to the planning scheme. In that regard Mr Gore QC
contended that, even accepting the approach of McMurdo JA, the planning scheme
provisions remain a relevant consideration, but on the basis of there being a general
discretion as to approval or refusal of the application. That discretion would then be
exercised against the background of the planning scheme being a relevant
consideration, rather than triggering the conflict/grounds test.15 I find it difficult to
see how the provisions could have that effect. Further, it was submitted that when a
preliminary approval is sought, it is inherent that care needs to be taken in applying
the planning scheme as the embodiment of the public interest.
[33] In Lipoma, the Court of Appeal considered an appeal from a decision of this Court
which ultimately refused a submitter appeal against an approval of a development
permit for a reconfiguration and a preliminary approval for a material change of use
for a mixed use development that included a shopping centre. The argument
proceeded on the basis that s 329 of SPA, which contained a conflict/grounds
provision, was engaged. That section fell within Subdivision 3 of Part 5 of Chapter
6 of SPA, dealing with decision rules for applications under s 242.
[34] In his reasons, McMurdo JA expressed the opinion that it was “very arguable” that s
329 was not engaged. He drew a distinction between s 326, which falls within the
decision rules generally, and s 329, which deals with applications under s 242. His
Honour said:
“[95] A decision to grant a preliminary approval, varying the effect
of the scheme in a certain respect, will not cause a conflict
which would engage s 329 in many, and perhaps most cases. If
there would be no conflict between one part of the scheme as
varied and any other part of the scheme, s 329 would not be
engaged.”
His Honour’s observations were obiter and did not address the different parts of an
application for a preliminary approval. I was informed that His Honour’s
observations were not responsive to any submission made in that case.
[35] As has already been observed, an application for a preliminary approval for a
material change of use may also seek to vary the effect of a local planning
instrument (a variation), but it does more than just seek the variation. It seeks a
preliminary approval for a material change of use (the MCU component). The
legislation distinguishes between the components. Indeed, the assessment of the
MCU component must be had regard to when assessing the variation component16
and the decision on the MCU component can be decisive of the part which seeks the
15 T13-22.
16 s 3.5.5A(2)(b).
-- 13 of 89 --
14
variation, since, as has been observed, in the event that the MCU component is
refused, the variation must also be refused.17
[36] Whilst, in the event the MCU component is approved, the proposed variation is
assessed for consistency only with aspects of the planning scheme other than those
sought to be varied,18 that is not so in relation to the MCU component. That follows
from s 3.5.5A of IPA, which expressly makes s 3.5.5A(2), including the constraint
in sub-paragraph (d), applicable only to “the part” of the application. Section
3.5.5A(1) provides that the relevant “part” is that which is seeking the variation.
The MCU component of the application (the part that seeks approval for
development) is a different part and is assessed, in this case, pursuant to s 3.5.5 as is
expressly contemplated by 3.5.5A(2)(b). That part of the application is for
development in a planning scheme area and so, on the face of the provisions, is
subject to the conflict/grounds test in s 3.5.14(2). It is difficult to see any
justification for reading s 3.5.14(2) as subject to an unexpressed qualification that,
in conducting the conflict/grounds test with respect to the MCU, conflict with those
parts of the planning scheme sought to be varied in the other component of the
application should be ignored.
[37] If the position were otherwise then a proposed material change of use that conflicts
with the planning scheme would have to confront the conflict/grounds provisions in
s 3.5.14 if only a development permit were sought, but would escape such scrutiny
if a preliminary approval was first obtained which also varied the scheme so as to
facilitate the later grant of a development permit (by varying the effect of the
conflicting provisions). I do not consider that the provisions had that purpose or
effect. It has already been noted that variations can only be granted in respect of
development (here an MCU) that is approved. The provisions operate so that, if a
preliminary approval for a material change of use that conflicts with the scheme can
be justified, then approval may also be given to a request to vary the effect of the
local planning instrument that will apply in relation to the subsequent applications
required to ultimately facilitate the development to which a preliminary approval is
being given. In assessing the requested variations consideration will be given to the
extent to which, if made, they would be consistent with the other (non varied)
provisions of the scheme. There is nothing surprising about that.
[38] In Nerinda Pty Ltd v Redland City Council,19 Bowskill J said as follows with
respect to the provisions under SPA:
“[50] Subdivision 3 sets out the “decision rules – application under
section 242.” This subdivision applies in deciding the part of an
application for a preliminary approval that states the way in
which the applicant seeks approval to vary the effect of any
applicable local planning instrument (s 327). The test in s
17 s 3.5.14A(2)(a) of IPA.
18 s 3.5.5A.
19 [2019] 1 Qd R 523.
-- 14 of 89 --
15
329(1)(b) is worded in the same way as s 326 – that the
decision must not conflict with a relevant instrument unless
there are sufficient grounds to justify the decision despite the
conflict. But the meaning of “relevant instrument” is different.
Section 329(2) defines “relevant instrument” to mean a matter
or thing mentioned in s 316(4)(c) or s 316(4)(d), other than a
State planning regulatory provision, that the assessment
manager must have regard to in assessing the part of the
application. Section 316(4)(d) in particular presents quite a
different lens through which to consider the part of an
application which seeks approval to vary parts of the planning
scheme – that is, consistency of the proposed variations with
aspects of the local planning instrument, other than the aspects
sought to be varied.
[51] … apart from the summary at [22] of the Decision, his Honour
does not draw any distinction, in the course of his reasons,
between his analysis of the part of the preliminary approval
which seeks to vary parts of the planning scheme, and any
other part of it (relevantly, the part seeking approval for a
material change of use).
[52] Although the applicant seemed to submit, on this application
for leave to appeal, that there was no basis for any
consideration of conflict with the parts of the planning scheme
that it sought to vary, by its application for preliminary
approval, I am not persuaded that accords with a proper
construction of the provisions. The application for preliminary
approval also sought approval for a material change of use,
which presumably was required to be considered under ss 313
or 314. It does not seem correct to construe the provisions in
such a way that a developer could apply for a preliminary
approval, inter alia, seeking to vary the effect of planning
scheme provisions, so that a different level of assessment
would apply in the future (relevantly, here, code assessment for
a large shop, where impact assessment would previously have
applied) without the assessment manager (or the Court standing
in its shoes) at some point giving consideration to whether that
was an appropriate thing to do, having regard to conflict with
the (unvaried) planning scheme provisions, and whether there
are public interest grounds to approve, despite the conflict.”20
[39] In my respectful view similar observations to those at paragraph 52 of Her Honour’s
reasons apply in relation to the relevant provisions of the IPA. I would have no great
20 See also the footnote to this paragraph of Her Honour’s reasons.
-- 15 of 89 --
16
difficulty with the observations of McMurdo JA in Lipoma if they applied only to
the operation of s 329 in relation to the variation part of an application for
preliminary approval, but they do not cause me to conclude that the MCU
component of the application does not attract the provisions of s 3.5.14 of IPA,
including those in relation to conflict/grounds in relation to the provisions of the
planning scheme including those sought to be varied in the event that the MCU is
approved. In this case however, I would have reached the same conclusion as to the
merits even had I proceeded on the basis that the relevant provisions of the planning
scheme (including those sought to be varied) were simply a matter to have regard to
in the assessment under s 3.5.5 leading to the exercise of a general discretion. In that
regard I would, in this case, have, in any event, placed significant weight upon the
fact that the proposed material change of use flies in the face of the planning
scheme.
[40] I also do not accept that the fact that the application is for a preliminary approval
means that a significantly different level of care needs to be taken in relation to the
application of the planning scheme as the embodiment of the public interest, at least
in relation to assessment of the MCU component. As I have previously observed,
the gravity of conflict between an application for a material change of use and the
planning scheme cannot be put at nought simply because the applicant applies to
vary the effect of a planning scheme so as to obviate the conflict.21
[41] Acknowledging that his client’s proposal is contrary to the applicable planning
instrument, Mr Gore QC likened the development application to an application for
rezoning under older statutory regimes. In my view it is best to focus on the relevant
provisions of the applicable regime but, to the extent that the comparison has any
validity, it should be noted that, under the earlier regime, such approvals were not
there for the asking in relation to development that was prohibited under the
existing zoning. The change from the existing zoning had to be justified and the
statement of intent of the existing zoning was a relevant consideration.22
[42] The respondent alleges that a decision to approve the application would both
compromise the achievement of desired environmental outcomes (DEOs), and
conflict with provisions of the planning scheme (which also include the DEOs23).
The words “compromise” and “conflict” are to be given their ordinary meaning. To
compromise is to clearly threaten, imperil or endanger.24 Conflict means to be at
variance or disagree with.25 Senior Counsel for the appellant did not dispute that
there may be circumstances where a decision would conflict with a DEO (which is
21 Stockland Development v Sunshine Coast Regional Council [2014] QPELR 52 at [19].
22 Residential Developments Australia Pty Ltd v Brisbane City Council [1990] QPELR 121.
23 Lewiac Pty Ltd v Gold Coast City Council and Another (2011) 180 LGERA 117.
24 Brown v BCC [2005] QPELR 629, 631 [9]; Aldi Stores v Redland City Council [2009] QPELR 602,
604 [16].
25 Redland City Council v Aldi Stores [2009] QCA 346 at [17]-[19]; Woolworths Ltd v Maryborough
City Council (No 2) [2006] 1 Qd R 273, 286 [23].
-- 16 of 89 --
17
part of the planning scheme) so as to trigger the conflict/grounds test albeit that
achievement of the DEO was not compromised.26
[43] In a sense, it is now not possible for any decision to compromise the (future)
achievement of a DEO in a planning scheme which ceased to have effect years ago.
It was submitted, for the respondent, that since the development application must be
decided under the old planning scheme, the Court ought approach the compromise
issue as if that scheme were still in place and its DEOs were still current and
capable of being achieved or their achievement capable of being compromised. That
is perhaps another way of saying that the question now is whether it would have had
that compromising effect. That submission is, I consider, correct, but my decision
does not rely on that because, for the reasons discussed later, I am of the view that
the appeal should, in any event, be dismissed even if it is assumed, favourably to the
appellant, that any conflict would not be accompanied by a compromise of the
achievement of the DEOs of the applicable 2003 planning scheme.
[44] In considering whether there are sufficient grounds, reference is often made to the
following three step process described in Weightman v Gold Coast City Council27
per Atkinson J in respect of similar provisions of the then Local Government
(Planning and Environment) Act:
“… the decision maker should:
1. examine the nature and extent of the conflict;
2. determine whether there are any planning grounds
which are relevant to the part of the application which is
in conflict with the planning scheme and if the conflict
can be justified on those planning grounds;
3. determine whether the planning grounds in favour of
the application as a whole are, on balance, sufficient to
justify approving the application notwithstanding the
conflict.”
[45] The provision of IPA refers to “sufficient grounds” rather than “sufficient planning
grounds” and the passage from Weightman must be read subject to that
qualification. Grounds are defined in IPA, as matters of public interest. They do not
include the personal circumstances of an applicant, owner or interested party.28
[46] The consideration of whether grounds are sufficient has been the subject of recent
Court of Appeal authority in Bell v Brisbane City Council29, Gold Coast City
Council v K & K (GC) Pty Ltd30 and Redland City Council v King of Gifts (Qld) Pty
26 T14-29.
27 [2003] 2 Qd R 441.
28 Schedule 10.
29 (2018) 230 LGERA 374.
30 (2019) 239 LGERA 409.
-- 17 of 89 --
18
Ltd.31 Those decisions emphasise the planning scheme provisions as an expression
of public interest, at least in a prima facie way. It was said in K & K that:32
“It is, in general, against the public interest to approve a development
that conflicts with the Planning Scheme. To justify such a
development it must be demonstrated that the desired deviation from
the Planning Scheme serves the public interest to an extent greater
than the maintenance of the status quo. The public interest that is to
be satisfied by the proposed development must be greater than the
public interest in certainty that the terms of a Planning Scheme will
be faithfully applied.”
[47] In Bell, McMurdo JA spoke of cases which might justify approval notwithstanding
conflict.33 Reference was made to cases where relevant circumstances had changed,
or the scheme was based on a factual error or had not anticipated a need for a certain
development in the public interest. Those are examples of where it might be
concluded that the provision with which there is conflict is not, in fact, a reflection
of the public interest.
[48] If the demonstration of sufficient grounds focused only on the point of conflict and
was limited to circumstances in which the conflict could be justified by
demonstration that the relevant provision no longer embodies the public interest
then there would appear to be little scope for the operation of the third limb of the
Weightman test. That limb calls on the decision maker, having considered whether
the conflict could be justified by grounds going to the part of the application in
conflict, to look to see whether the “grounds in favour of the application as a whole
are, on balance, sufficient”. Certainly the third limb must now be read in light of the
more recent Court of Appeal authority and, in particular, its caution against
approaching such provisions on the basis of a general weighing of factors.34
[49] The recent cases have however, not disapproved of Weightman. Further, one of the
examples35 given by the learned President in paragraph 68 of the reasons in K & K
appears to be an example of a third limb consideration. The appellant, in this case,
relied upon some third limb grounds. I have proceeded on the basis that the third
limb of Weightman remains relevant in the consideration of whether there are
sufficient grounds. That limb is not necessarily given any more or less weight.36
Further, as was said in Woolworths Ltd v Maryborough City Council (No 2)37, it
would be a mistake to treat the Weightman formulation as if it were a code.
Onus and Nature of Appeal
31 [2020] QCA 41.
32 At para 67.
33 At para 68.
34 K & K para [48].
35 That involving need satisfied by a non-conflicting component overriding conflict created by another
component.
36 Lockyer Valley Regional Council v Westlink Pty Ltd [2013] 2 Qd R 302 at 322.
37 [2006] 1 Qd R 273 at 286.
-- 18 of 89 --
19
[50] The appeal proceeds as a hearing anew.38 The appellant bears the onus of
establishing that the appeal should be upheld.39 The Court must decide the appeal
on the basis of the laws and policies applying when the application was made, but
may give weight to any new laws and policies the Court considers appropriate.40
The Planning Documents
[51] The development application was made during the life of the Thuringowa Town
Planning Scheme (TPS 2003), which first took effect in 2003. The appeal must be
decided on the basis of that planning scheme, however the Court may give such
weight as it considers appropriate to any new laws and policies.41 The
conflict/grounds provisions discussed earlier only apply in relation to the TPS 2003.
[52] On 27 October 2014 the new Townsville City Plan (CP 2014) commenced. It was
prepared in accordance with SPA, but has subsequently been amended to align with
the PA. That planning scheme has been the subject of various amendments since its
commencement.
[53] The provisions of CP 2014 are, in my view, worthy of considerable weight. They
represent the contemporary expression of the planning intent for the City of
Townsville as a whole (not just the old Thuringowa) in a document that has now
been in force for a considerable period of time. It is appropriate that the provisions
of the document be afforded considerable weight particularly in relation to a large,
long term proposed development of obvious significance in relation to the planning
strategy for Townsville, involving the creation of a substantial new community
composed of a range of urban activities within what is currently a rural part of the
city. As Mr Gore QC himself said “this is a major development which will be a
feature of Townsville for a long time”.42 The appellant points out that the planning
intent of CP 2014 is not markedly different from that in the TPS, but the
continuation of that intent into CP 2014 (notwithstanding the passage of time), and
the provisions now giving effect to it, are of significance.
[54] The appellant complains of the unfairness of affording weight to CP 2014, given
that it commenced well after the lodgement of the development application. It also
points to the expiration of the time for it to now make a development application
(superseded planning scheme). This appeal falls for determination at a time when
CP 2014 is in force and has been for some years, because of the appellant’s failure
to pursue its rights more swiftly. It delayed, for years, in instituting any appeal
against Council’s deemed refusal, whilst trying to influence the content of the new
planning scheme which it knew was then being formulated. It then delayed in the
prosecution of the appeal whilst the planning scheme took effect and continued in
effect for years. That it, in the meantime, let its right to make a development
38 s 4.1.52(1) of IPA.
39 s 4.1.50(1) of IPA.
40 s 4.1.52(2).
41 s 4.1.52 of IPA.
42 T13-99.
-- 19 of 89 --
20
application (superseded planning scheme) pass is a matter for it. I do not consider
that matters of fairness dictate that no or no significant weight be afforded to CP
2014.
[55] The appellant complains that the Council has given other approvals inconsistent
with CP 2014. In particular, it points to the approval of a development referred to as
Wingate. That does not, in my view, create a sufficient justification for this Court to
ignore the provisions of CP 2014, or attach little or no weight to them in relation to
the subject site. The planning strategy, particularly as it relates to the subject site,
has not been shown to have been overtaken or affected in a way that would justify
the subject proposal by reason of the other approvals.
[56] The appellant claims that the reasons for the treatment of its land as rural in CP
2014, particularly with respect to amenity, do not call for refusal. Those matters are
considered later. That might affect the extent or gravity of discord between the
proposal and CP 2014, in a particular respect or respects, but does not justify giving
other than significant weight to the document more generally. The utility of the site
for its zoned purpose is dealt with later in these reasons.
[57] Earlier in 2020 the North Queensland Regional Plan (NQRP) took effect. It is the
pre-eminent plan for the region and is intended to guide planning and decision-
making by all State Government agencies. Its principal aim is to determine how
land use and infrastructure planning can best support economic growth and
population change over the next 25 years and beyond. That aim is identified as
being achieved by, relevantly: “more efficient patterns of development to put an end
to Townsville’s urban sprawl, thereby reducing cost pressures on infrastructure
provision and services”. The plan is intended to guide strategic planning and
decisions including land use planning by both state and local governments; the
assessment of development applications; and infrastructure planning, prioritisation
and funding decisions made by all levels of government, and other infrastructure
agencies.
[58] Given the nature and importance of the subject application, as described earlier,
some weight should be given to NQRP, notwithstanding the complaints of the
appellant (which were in like terms to its objections to weight being afforded to CP
2014). Having regard to how recently the NQRP has been published however,
consideration of matters of fairness are more significant which, in turn, results in me
attaching less weight to it. I would have been loath to refuse the application solely
because of conflict with the NQRP. That is however, not the case. Indeed my
ultimate conclusion would have been no different had no weight been afforded to
the NQRP.
The Issues
[59] The parties tendered an agreed abbreviated list of issues which were the focus of the
hearing. Some of those issues, such as whether weight should be given to the
planning documents which came into effect after the development application was
-- 20 of 89 --
21
made and the extent to which the assessment of the development application is
carried out on the basis of the provisions of the town planning scheme sought to be
varied, have already been addressed. Some of the remaining issues relate to the
variation component of the development application, but the focus of the evidence
and argument was on the MCU component. That will be addressed first. The issues
in that regard went to the extent of conflict between the proposal (subject to
appropriate conditions) and the planning documents, and matters that could satisfy
the conflict/grounds test with respect to conflict with the TPS 2003 or that should be
taken into account when considering the weight to be afforded to the proposal’s
discord with the provisions of the more recent planning documents.43
The Conflict/Matters Raised Against the Proposal
(i) Residential and Other Urban (Non-rural) Use
(a) TPS 2003
[60] Under the TPS 2003 the land was included within the Rural Planning Area and the
Rural 40 sub-area. Unsurprisingly, master planned estates for suburban residential
and other urban development were not contemplated in that area. Residential,
industrial and centres development was promoted in other planning areas. Even Mr
Buckley, the town planner engaged by the appellant, saw the conflict between the
MCU component of the application and at least some provision of the TPS as “very
major”.44
[61] The respondent relied on 4 DEOs namely:
• DEO 1 in relation to nature;
• DEO 4 in relation to city image amenity and lifestyle;
• DEO 5 in relation to economy, and
• DEO 6 in relation to land use patterns.
[62] Of particular relevance in this respect is DEO 6, which is that:
“the city’s land use patterns create cohesive communities that balance
economic, social and environmental considerations”
That is a statement about land use patterns which is expressed at a high level of
generality. It is however, intended to be achieved by strategies set out in s 2.6.2,
which include by establishing the city’s urban growth boundaries to create an
efficient urban form. As is observed later, the proposal is outside those boundaries
and conflicts with that aspect of the strategy to achieve the DEO. The nature, scale
and location of the proposal relative to the intended land use pattern suggest that
43 Or, on the appellant’s case (that the provisions of TPS 2003 are also only a matter to be considered)
with TPS 2003 as well.
44 T11-57.
-- 21 of 89 --
22
approval would have a compromising effect, but with respect to the DEO. There is
conflict with the strategy even if it were assumed, favourably to the appellant, that it
does not go so far as to compromise the achievement of the DEO.
[63] The respondent also drew attention to DEO 5 which is that:
“Economic development in the city is strong, diversified, supports local
employment and enhances quality of life”
That is also an objective which is expressed at a high level of generality. Attention
was directed to the relevant city strategies for the achievement of DEO 5 which
include:
“(a) protecting land and providing an adequate supply of land for
employment generating development (at a local, regional, state
or national scale) and the future expansion of employment
generating land uses in designated locations”
The respondent alleged conflict on the basis that the proposal seeks to facilitate
retail, commercial and industrial development on land that is not in a designated
location. The provision seeks to protect and provide an adequate supply of land in
designated locations. It does not, in terms, say that all employment generating
development must be in designated locations. In any event, the primary issue in
relation to the nature of the land use is whether it is appropriate to allow for a new
master planned community, of the scale proposed, on the subject site,
notwithstanding the provisions of the planning scheme that do not contemplate such
development in this location. If such development is appropriate, then it would be
justifiable, in the community interest, to provide an appropriate level of non-
residential uses to support that community, even if that involved a level of conflict
with this provision.
[64] There was a character statement for the Rural Planning Area in s 3.1.1 of the TPS
2003. It provided, in part, that:
“…
(a) At the Commencement Date, premises within the Rural
Planning Area consisted of:
(i) Rural Development of varying scale and intensity; and
(ii) other development that may be inconsistent with the future
intent for the Rural Planning Area described below.
(b) The Rural Planning Area is intended for Rural Development
that contributes to the amenity and landscape of the area in
particular –
-- 22 of 89 --
23
(i) buildings and structures are sited to protect the amenity
of adjoining premises and contribute to maintaining the
rural landscape;
(ii) Rural Development is located, designed and constructed
to minimise potential adverse environmental impacts;
(iii) development is compatible with the rural landscape or
has a nexus with Rural Development; and
(iv) development is adequately serviced by infrastructure.
(c) Reconfiguring a Lot does not result in –
(i) the fragmentation or alienation of land; and
(ii) the reduction of the capability of the land resource to provide
a Rural Living Area.
…
(f) Development, other than Rural Development, is only located
in the Rural Planning Area where no viable alternative location
exists, and where that development will not detrimentally
affect rural amenity and the rural landscape.
(g) Three sub-areas are identified for the Rural Planning Area
based on land capacity and lot sizes – the Rural 10 sub-area,
the Rural 40 sub-area and the Rural 400 sub-area. These sub-
areas are shown on map 31 and –
…
(ii) the Rural 40 sub-area is intended for agricultural,
aquaculture and animal husbandry on a minimum lot
size of 40 hectares; and
…”
[65] Rural Development was defined to include:
“Agriculture
Animal Husbandry
Aquaculture
Host Farm
Intensive Animal Husbandry
Rural Accommodation Units
Rural Dwelling
Rural Home Occupation
-- 23 of 89 --
24
Rural Industry”
[66] The proposed MCU conflicts with the character statement. Whilst the appellant
contends that the proposal will not detrimentally affect rural amenity and landscape
(matters discussed later), sub-paragraph (b) relates to the intent for “Rural
Development” that contributes in a certain way. The proposal is not for Rural
Development. Sub-paragraph (b)(iii) expressly contemplates development with a
nexus with Rural Development, but the subject proposal has no such nexus. Sub-
paragraph (f) envisages development other than Rural Development only where,
amongst other things, no viable alternative location exists. That has not been
demonstrated to be the case. The proposal does not seek a development approval for
reconfiguration, but the MCU contemplates subdivision of lots to suburban
residential densities, much smaller than those contemplated by sub-paragraph (g)
and not for the uses contemplated and with the effect of alienating the land from
rural use (sub-paragraph (c)). There is conflict even if the appellant’s case on rural
amenity and landscape was accepted (which it is not).
[67] There was also a Rural Planning Area Code, the purpose of which was to ensure
that development within the Rural Planning area is consistent with the character of
the Rural Planning area described in the character statement. The respondent drew
attention, in particular, to the following performance criteria (and their acceptable
solutions).
PART A
Performance Criteria
Acceptable Solutions for Self-
Assessable and Assessable
Development
CHARACTER AND BUILT FORM
P2. A separation distance between
Rural Development and Sensitive
Receptors is provided to prevent
adverse impacts of spray drift, odour,
noise, smoke, dust, vibration and ash
A2. The separation distance between a
Sensitive Receptor and Rural
Development is at least –
(a) for the Rural 10 sub-area, the Rural
40 sub-area and the Rural 400 sub-area
–
(i) 300m for aerial chemical spray drift;
and
(ii) 100m for ground applied spray
drift; and
(iii) 300m for odour; and
(iv) 300m for long term day time noise
-- 24 of 89 --
25
(6am – 10pm).
(b) for the Rural 10 sub-area –
(i) 60m for intermittent noise and 500m
for long term night time noise (10pm –
6am); and
(ii) 150m for dust, smoke and ash.
(c) for the Rural 40 sub-area and the
Rural 400 sub-area, 40m for
intermittent noise.
PART B
Performance Criteria Acceptable Solutions for Assessable
Development Only
LOT SIZE
P5. The proposed Rural Living Area
maintains farm holdings capable of
sustainable production in terms of –
(a) capability of the land to support the
development;
(b) provision of services;
(c) suitability for the development;
(d) availability of water suitable for the
development, and
(e) sustainability of proposed
development practices.
A5. Lot sizes are at least –
(a) 10 hectares in the Rural 10 sub-
area; or
(b) 40 hectares in the Rural 40 sub-
area; or
(c) 400 hectares in the Rural 400 sub-
area.
AMENITY
P6. Development, other than Rural
Development, is only located in the
Rural Planning Area where no viable
alternative location exists.
A6. No acceptable solution prescribed.
P7. Development will not detrimentally
affect the existing and future rural
amenity and landscape of the Rural
Planning Area, taking into account –
(a) the manner in which the proposed
A7. No acceptable solution prescribed.
-- 25 of 89 --
26
development will affect the desired
future character of the area; and
(b) the degree of impact on the area.
The proposal seeks to facilitate45 subsequent subdivision that is in obvious conflict
with P546 (Lot size). There has been no demonstration of the no viable alternative
location test in P6 (Amenity). In the appellant’s written submissions conflict with
the code was acknowledged47 (subject to the Nerinda point). P5 and P6 were
described as “blunt” provisions. They are provisions of clear intent with which the
proposal conflicts. Compliance or otherwise with P2 and P7 is discussed later in
relation to character/amenity impacts.
[68] The TPS 2003 also included an Urban Growth Boundaries Code, which was
supported by a map of the urban growth boundaries. The subject site is beyond
those boundaries. The purpose of the code was as follows:
“Urban Growth Boundaries Code
Purpose: The purpose of this code is to ensure:
(a) development occurs in an orderly, efficient and cost effective
manner;
(b) the community is provided with a reasonable level of
infrastructure service;
(c) Council Infrastructure and State Government Infrastructure is
coordinated and provided in an orderly, efficient and cost effective
manner;
(d) areas outside the City’s Urban Growth Boundaries are retained
for economic, social and environmental purposes such as
agricultural land, visual and natural resource protection, significant
water catchments and World Heritage Areas; and
(e) development within the City’s Urban Growth Boundaries –
(i) does not prejudice premises for urban development in the
long term;
(ii) creates vibrant and liveable communities; and
(iii) provides an example for sustainability in the City.”
45 subject to further approvals.
46 The land is suitable for grazing although its productive value is low.
47 paras 204-207.
-- 26 of 89 --
27
[69] Matters relating to efficiency and cost effectiveness are discussed later, but the
proposal is in conflict with sub-paragraph (d) in that the land falls within the area
outside the urban growth boundary and is not to be retained for purposes such as
those nominated.
[70] The performance criteria and acceptable solutions in the code include the following:
PART A
Performance Criteria Acceptable Solutions for Self-
Assessable and Assessable
Development
P1. Urban development –
(a) occurs in an orderly, efficient and
cost effective manner;
(b) maintains a reasonable level of
service to the existing community; and
(c) provides infrastructure in an
orderly, efficient and cost effective
manner.
A1. Urban development occurs within
the defined Urban Growth Boundaries
defined on map 5.6.
P2. Areas outside the City’s Urban
Growth Boundaries are retained for
non-urban development.
A2. No acceptable solution prescribed.
PART B
Performance Criteria Acceptable Solutions for Assessable
Development Only
P2. Areas outside the City’s Urban
Growth Boundaries are retained for
non-urban development.
A2. No acceptable solution prescribed.
P1 relates to matters which are discussed later, but, in any event, the proposal is in
conflict with P2. The written submissions for the appellant acknowledged conflict
with this code (subject to the Nerinda point) and described P2 as a “blunt”
provision.48 It is a provision of clear intent with which the proposal conflicts.
[71] For the reasons given, the MCU component conflicts with the TPS 2003 in relation
to the use to which the land is intended to be put. That at least49 triggers the
conflict/grounds test. That conflict will be even stronger if some other issues are
48 paras 204, 208.
49 assuming, favourably to the appellant, that it does not amount to a compromise of DEO’s.
-- 27 of 89 --
28
determined against the appellant, but the degree of conflict is strong and major in
any event and my ultimate decision is not dependent on establishing further conflict.
(b) CP 2014
[72] The proposal, in relation to land use, also flies in the face of CP 2014. Under that
planning scheme the site is included in the Rural Zone. CP 2014 contains a Rural
Zone Code the purpose50 of which is to:
“(a) provide for a wide range of rural uses including cropping,
intensive horticulture, intensive animal industries, animal
husbandry, animal keeping and other primary production
activities;
(b) provide opportunities for non-rural uses that are compatible
with agriculture, the environment, and the landscape character
of the rural area where they do not compromise the long-term
use of the land for rural purposes; and
(c) protect or manage significant natural features, resources, and
processes, including the capacity for primary production.”
and the “particular purpose” of which is to “ensure”:
“(a) the productive capacity of all rural land and opportunities to
diversify and add value to rural production are maximised,
within the ecological constraints of the land;
(b) the character and landscape values of non-urban land are
maintained; and
(c) urban or rural residential development does not expand into
rural zoned land.”
[73] Matters in relation to landscape character, natural features and ecological constraints
are considered later, but even putting those to one side, the proposal flies in the face
of the particular purpose of the code which is quite limited in terms of the type of
non-rural uses envisaged in the zone. The purpose speaks of non-rural uses that are
compatible with certain things “where they do not compromise the long term use of
the land for rural purposes”. The particular purpose seeks to ensure that urban
development does not expand into the zone.
[74] The site is within a grazing precinct. The code contains performance outcomes and
acceptable outcomes that include:
PO20 AO20
50 s 6.6.1.2.
-- 28 of 89 --
29
Reconfiguration is limited to reflect the
suitability of the land for primarily
grazing purposes and to protect water
quality and ecological and landscape
values.
The minimum lot size in the precinct is
400ha.
The site has been, and is being, used for grazing. The proposal would facilitate
reconfiguration which does not reflect the suitability of the land for grazing,
although, it should be acknowledged, that while suitable for grazing, its rural
productive value for that purpose is low.51
[75] The containment of growth of urban development is a matter to which the CP 2014
is otherwise directed. That is unsurprising, given that urban sprawl has been a
feature of Townsville’s development in the past.
[76] The strategy framework of CP 2014 sets the policy direction for the planning
scheme and forms the basis for ensuring that appropriate development occurs within
the planning scheme area for the life of the planning scheme.52 Theme 3.3, which
relates to “shaping Townsville”, states that the planning scheme allocates land for
housing, business and community uses, sufficient to meet Townsville’s need for at
least 25 years.53 It earlier states54 that the planning scheme designates sufficient
land supply for future greenfield development and that “the city will not grow
outwards beyond the areas designated in the foreseeable future”.
[77] Against that background, the city shape and housing element55 contains a specific
outcome in relation to “city shape and urban containment” which provides, in part,
as follows:
“(1) The growth of Townsville will occur within the city’s existing
urban and rural residential areas, and in areas identified for urban
expansion through the Emerging community zone. Urban and rural
residential development does not occur outside land identified for
these purposes.”
The application flies in the face of this by proposing urban development outside the
land identified for such purposes.
[78] The relevant land use strategies include:56
“Zoning designations closely reflect the strategic intentions
regarding the extent of urban growth. Development outside these
areas will not be supported.
51 T11-80.
52 s 3.1(1).
53 s 3.3.1(1).
54 s 3.2.5.
55 s 3.3.2.
56 S 3.3.2.2.
-- 29 of 89 --
30
Major greenfield areas are included in the Emerging community
zone to facilitate master planning and orderly development in
accordance with best practice neighbourhood planning principles for
accessibility, density, land use mix, street networks and lot
configuration…”
The proposal is for major greenfield development for urban purposes outside the
emerging community zone or any other zoning designation consistent with such
intent.
[79] The specific outcomes for the strong and connected community element57 include
that “non-urban land is protected to define the edges to the city and to protect non-
urban landscape values. Urban and rural residential development does not occur in
rural areas”. The land use strategies in support of that include58 that “a primary
strategy implemented through the planning scheme is the containment of urban
growth within the designated area”. The description of the strategy as a “primary
strategy through the planning scheme” is an indication of its significance in the
context of the document. The proposal flies in the face of those provisions.
[80] The transport, accessibility and mobility element59 and the integrated infrastructure
planning and provision element60 link the city shape to the optimum transport
outcomes61 and most efficient provision of infrastructure.62 The proposal is not for a
site that is serviced or currently planned to be serviced with transport and other
infrastructure. The appellant’s proposal to provide infrastructure is considered later,
but the traffic outcomes, whilst acceptable, are not optimum and the provision of
infrastructure not efficient.
[81] The land use strategies for the natural assets element63 include the statement that
“the city scape and settlement pattern has been determined to avoid further
expansion of urban or rural residential development beyond existing developed
areas. This will avoid increasing pressures on environmentally important values”.
The proposal does not accord with that strategy.
[82] The land use strategy in support of the sustainability element provides, in part, that
the city shape and settlement pattern established under the planning scheme
provisions underpins the growth of a more sustainable Townsville in which
transportation and fossil fuel use will be better managed. That is yet another
illustration of the importance CP 2014 places on the city shape and settlement
pattern (including appropriate land use).
57 s 3.4.4.1(4).
58 s 3.4.4.2.
59 s 3.3.5.
60 s 3.3.6.
61 s 3.3.5.1(2).
62 s 3.3.6(2) – see also s 3.3.6 linking land use and development pattern to the efficient and cost
effective provision of infrastructure.
63 s 3.5.2.2.
-- 30 of 89 --
31
[83] The industrial land element includes a specific outcome64 that industrial
development does not expand beyond areas zoned for industrial purposes or
identified as industry area on the strategic framework maps. The proposed material
change of use includes an industrial component on land beyond that zoned or
identified for industry. If the proposal were otherwise justified however, (which for
the reasons stated herein it is not) it may have been appropriate to permit an
industrial component within the new community.
[84] The natural economic resources element contains specific outcomes which seek to
avoid further fragmentation of rural land, even when there is a lack of viability.65
The proposal seeks to facilitate urban development which would not only fragment
rural land, but alienate the subject site from rural use.
[85] The proposal is in strong conflict with CP 2014 by reason of the nature of its
proposed use for the subject site which is fundamentally at odds with the clear
strategy of the planning scheme particularly in relation to the shape of the city and
the direction of further urban development. That is a mater to which I attach
significant weight.
(c) NQRP
[86] The NQRP is based on an expected growth in population in the region and, in
particular, in Townsville. In the “context” part of the document it is said that
Townsville’s urban sprawl will be put to an end.66 Goal 3 is liveable, sustainable
and resilient communities that promote living in the tropics. There is, in that regard,
a discussion in relation to Townsville of, amongst other things, an urban
consolidation policy to prevent the continuation of an inefficient and expensive
development pattern and of the lack of need, based on current supply, for residential
development to continue outside of Townsville’s existing urban area. The relevant
regional outcome adopted in the NQRP is as follows:
“3.1 The development pattern for the North Queensland region delivers
consolidated and efficient growth for urban areas.”
[87] The regional policies in support of that outcome include the following policy which
is specific to Townsville:
“3.1.5 Townsville’s urban residential development is to be contained within
the Townsville Urban Area. Urban residential development within the
Townsville Urban Area does not occur outside land identified for
these purposes.”
The Townsville Urban Area is identified in Map 6 and is based on the existing
extent of land zoned for urban purposes in the Townsville City Plan (2014), the
64 s 3.6.2.1(5).
65 s 3.6.4.1(3).
66 Ex 9 pg 9.
-- 31 of 89 --
32
priority infrastructure area under the Local Government Infrastructure Plan and land
adjoining these zones that have been approved for urban purposes. It does not
extend to the subject site.
[88] Whilst the appellant may argue about efficiency67 (a matter discussed later in the
context of infrastructure), its proposal does not constitute a consolidation and does
involve urban residential development outside of the urban area contrary to policy
3.1.5. The proposed use flies in the face of the NQRP. That is a matter of weight. I
have already dealt with the weight that I am prepared to afford the NQRP. In this
case, the conflict simply serves to reinforce the ultimate conclusion which I have
otherwise reached.
(d) Conclusion on Residential and Other Urban (Non-Rural) Use
[89] The proposal to use the subject site for residential development at suburban
densities and for other urban uses conflicts with all relevant planning documents. It
conflicts with TPS 2003, triggering the conflict/grounds provision and also with the
more recent planning documents which are a matter of weight. Mr Buckley did not
cavil with the proposition that the identification of where urban development is and
is not to occur is an important planning objective of planning schemes. So much
appears from the following exchange under cross-examination:68
MR JOB: The conflicts that I think you acknowledge – sorry. I’ll put
it this way: one of the conflicts involves the fact that what is
proposed here is a large urban form of development in a location
where the planning instruments – all three of them – indicate urban
development is not to occur?---Correct.
And that’s an imported [sic] planning objective; the identification of
where urban development is and is not to occur?---Yes. Spatially
planning schemes convey that.
[90] Mr Buckley sought to call in aid the fact of past urban approvals as, in some way,
helping to justify continuing that sprawl, by approval of the subject application. As
Mr Perkins pointed out however,69 the planning documents have provided a policy
response which seeks to prevent that. Mr Buckley seemed to acknowledge that in
the following exchange which occurred during Mr Buckley’s testimony:70
HIS HONOUR: Mr Buckley, if you go to page 2 of your individual
report?---Yes.
At paragraph 14 is where you talk about Townsville conveying a
sprawl-like phenomenon?---Yes.
67 as discussed later, the assumption of the obligation to provide or pay for the cost of infrastructure
does not mean that its provision is efficient.
68 T11-32.
69 T11-95.
70 T11-43.
-- 32 of 89 --
33
In forming your views did you take it that the town plan encourages
that, or discourages that sprawling further or is neutral about it?---
Well, to answer the – there’s two parts of your question, your
Honour. The scheme, I think, seeks to arrest it, yes, by limiting the
amount of areas it shows as preferred urban. So that’s probably a fair
call about the current scheme. But the – a lot of the spread out nature
of Townsville is historical, and – and some of that would be in
accordance with planning policies. Some would just predate planning
schemes. But the growth of Upper Ross I’m reasonably familiar with
from living in the north in the eighties and, you know, it just appears,
in my – my observation as a planner, just to get more concentrated
and more – a reality, if you like, of that urban frontier.
But do you accept that approval of this proposal would lead to some
continuation of sprawl?---Yes. That – the sprawl, as indicated by
what comments I’ve said, your Honour, is not unusual in the context
of Townsville historically and what’s on the ground.
[91] Mr Perkins rightly saw the application as seeking approval for an initiative or
strategy at odds with, and dilutive of, the planned strategy for urban development in
the planning documents.71 Whilst there are other alleged conflicts (discussed later),
I consider the conflict in relation to the land use to be serious and, indeed, sufficient
to be decisive because, for the reasons given later, I do not find the matters raised to
justify approval to be persuasive, or sufficiently persuasive, to cause me to allow the
appeal and grant the development approval. Insofar as the TPS 2003 is concerned,
that is either on the basis of satisfaction of the conflict/grounds test (which I find not
to be satisfied) or on the basis of exercising a discretion having given consideration
to the relevant provisions of TPS 2003 in assessing the application, as the appellant
submitted is appropriate in the case of an application for a preliminary approval.
The provisions of the subsequent planning documents have, as I have indicated,
been treated as a matter of weight.
(ii) Landscape Character and Visual Amenity
[92] Reference has already been made to the provisions of TPS 2003 for the Rural
Planning Area that relate to amenity and landscape. DEO 4 is also of relevance. It
provides as follows:
“2.4.1 DEO 4
The City’s valuable features, built environment and land use pattern
result in a distinct sense of place and local identity, and are vibrant,
safe and healthy, with access to community and cultural facilities and
services.
The city strategies in supporting that DEO include:
71 Ex 34 para 160.
-- 33 of 89 --
34
2.4.2 City Strategies
DEO 4 is intended to be achieved by –
(a) protecting or enhancing the City’s natural and built
environment as an integral part of the City’s Landscape
Character Types.
(b) reinforcing the City’s character through effective siting,
design and layout of development that –
(i) reflects community expectations;
(ii) promotes safety and security;
(iii) reflects local and desired character;
(iv) enhances local identity and lifestyle;
(v) contributes to the formation of a sense of place; and
(vi) responds to the City’s tropical climate.”
…
[93] CP 2014 contains specific outcome 3.4.4.1 and the associated land use strategy
3.4.4.2 extracted earlier, which set their face against development such as is
proposed in rural areas.
[94] The purpose of the Rural Zone Code, which has previously been set out, refers to
the opportunities for non-rural uses which are compatible with, amongst other
things, the landscape character of the rural area and includes a particular purpose
that the character and landscape values of non-urban land are maintained.
[95] Issues of this kind were addressed in the evidence of Mr McGowan, who was called
by the appellant. His report summarised his opinion as follows:
“48 The assessment undertaken to inform this statement revealed
that, while the proposed development would change the
appearance and character of the subject site, that change would
not be detrimental in terms of the overall values and quality of
the local visual environment. Furthermore, the provision of
open space and landscape buffers across the site and at the
edges of the site will ensure the amenity of adjoining
properties will be appropriately maintained.
49 Regarding the provisions referenced in the relevant reason for
refusal:
-- 34 of 89 --
35
a) the proposed development can be seen to satisfy P1 (in so
far as it relates to visual amenity concerns) and P7 of the Rural
Planning Area Code;
b) while it is not rural development, the proposed development
will achieve an appropriate level of compatibility with the
rural landscape remaining in the area, as sought by the
character statement referenced in the Purpose of the Area
Code; and
c) while the development would not satisfy P6 nor item (f) of
the character statement for the Rural Planning Area, the
consequence of this non-compliance is not significant in terms
of visual amenity concerns. The non-compliance is technical,
does not result in any unacceptable impacts and therefore
should not result in refusal of the proposal.”
[96] In forming his opinions, Mr McGowan was influenced by the proposed retention of
a large area of open space, including the parts of the site he thought of most value
(the main waterways and the slopes) and the concentration of development on the
lower, flatter areas of the site, to which there is limited visibility from beyond the
site. He did not think that the proposed development would make any positive
contribution to the rural landscape, but considered that it would not offend it.72
[97] These issues were also considered by the town planners. Mr Buckley thought the
development would reinforce the city’s character and sense of place because it
would be the logical “bookend” of the Upper Ross urban corridor, rather than a new
front or corridor.73 Mr Perkins, on the other hand, did not see the proposed large
scale urban development of land in the rural land use category as reinforcing
planned local and desired city character, reflecting community expectations or
contributing to the planned sense of character.74 Further, he pointed out that the
proposal involves the large scale urbanisation of rural land, which he did not regard
as consistent with the provisions of the character statement75 for the Rural Planning
Area or the Rural Planning Area Code76 in relation to rural landscape character and
rural character and amenity. He rejected Mr Buckley’s bookend argument, pointing
out that the site does not adjoin nor is immediately adjacent to urban development
that either exists or is planned for77 and to which it would provide a bookend. I
found that to be persuasive.
[98] In the course of his testimony, Mr McGowan:
72 T5-53.
73 Ex 34 para 120, Ex 43 para 19.
74 Ex 34 para 123.
75 Ex 34 para 126.
76 Ex 34 para 127.
77 T11-74.
-- 35 of 89 --
36
(a) confirmed that the proposed development would itself not appear as
rural in character, but rather as suburban development.78 In my view
that is not insignificant because the site is itself a large holding within
the area, such that the approximate north-south dimension of the
development would be up to 4.4km and up to 2.5km east-west;79
(b) described one of the qualities of the current “sense of place” as an
“openness” bordering on “emptiness” with dispersed built forms and
structures;80
(c) described the “local identity” in the Rural Planning Area as
substantially the same, but would factor in landscape features;81
(d) conceded that the development would not result in openness or
emptiness, insofar as the developed parts of the site are concerned;
(e) conceded that the siting, design and layout of the development does not
reflect the local rural character that exists;82
(f) conceded that if a rural landscape is sought, then the outcome would be
compromised;83
(g) having suggested that the development would appear as a logical and
sensitive extension of suburban and rural residential development,84
acknowledged that there was a break between the site and nearby rural
residential development, such that there would be no continuous
extension85 (something which Mr Perkins also pointed out86) and that
suburban development to the north-east is some 8.5km away.87 Further
it became evident that there was little about the design of the proposal
that was sensitive, aside from its location on the flatter parts of the
site.88 The logic he relied upon was that all land up to the edge of the
range ought be allowed to be developed.89 There is, of course, no
warrant in the planning documents for urban or suburban development
or for a character or landscape of that kind to sprawl out to the edge of
the range;
78 T5-38, T5-30.
79 T5-34.
80 T5-48.
81 T5-48, 49.
82 T5-50.
83 T5-49.
84 Ex 42 para 44 and T5-30.
85 T5-30.
86 T11-75.
87 T5-29.
88 T5-32, 33.
89 T5-33.
-- 36 of 89 --
37
(h) accepted that, notwithstanding Mr Buckley’s description of the site as a
bookend, there is further undeveloped land to the south-east that forms
part of the sub-coastal plain;90
(i) agreed that development on the more elevated parts of the site would be
visible from Moncrieff Road, and also from Laudham Road.91 It would
also be visible from the Lake Ross wall walking track, in respect of
which car parking areas, to facilitate access to the wall for locals and
tourists, are available. From that viewpoint, more of the site would be
visible, including the upper parts and some of the lower parts.92 The
evidence associated with reservoirs came later from Mr Gould (who
had not discussed it with Mr McGowan93), but they will likely be
visible also;
(j) was asked about the impacts of substantially increased traffic upon
visual amenity and character. He agreed that busy traffic can be
unpleasant.94 The external roads to be upgraded presently have low
traffic volumes, and consequently would have a rural character.95 Some
of the houses on those sites are quite visible to the roads.96 The increase
in traffic volumes by reason of the development will be very
substantial. I accept that those increases would occur over time, but
they will incrementally contribute to a change in character;
(k) also acknowledged that the implementation of the development would
result in an area of land which is not currently illuminated becoming
noticeably illuminated.97 Obviously, that would not have a rural
character.98 He agreed that would be an adverse impact.99 Further,
street lighting, if installed on the upgraded local external roads, would
also represent a material change to the existing rural character of that
locality. So too would the visible presence of traffic movements on
those roads at night;100
[99] In those circumstances I am satisfied that:
(i) the proposed development would lead to a dramatic change of character
of the subject site, particularly in those parts to be developed;
90 T5-34, 35.
91 T5-38, 39.
92 T5-39.
93 T8-24.
94 T5-41/1-14.
95 T5-41/25-32.
96 T5-41/34-39.
97 T5-45/35 to T5-46/6.
98 T5-46/24.
99 T5-46/25-27, although he did not think that would be significant.
100 T5-46/33-39.
-- 37 of 89 --
38
(ii) Mr McGowan’s work demonstrates that the topography and siting of
the proposed development is such that the visibility of the developed
parts of the site from beyond the site would be more limited than might
otherwise be the case, but
(iii) having regard to the matters which emerged during Mr McGowan’s
testimony, the development would nevertheless also have some adverse
impact beyond its borders in ways which, viewed collectively, are not
insignificant.
[100] I did not find Mr Buckley’s “bookend” argument persuasive. It has already been
observed that there is further land beyond the subject site. Further, as Mr Perkins
pointed out,101 a bookend seems to imply that something is located at an end point
of something. Here the proposed development would not build upon, or extend
from, any like existing development. It is separated from the nearest urban or
suburban development.
[101] The proposal at least conflicts with, if not compromises the achievement of, the
DEO. The developed parts of the site would detract from the achievement of a built
environment and land use pattern with a distinct sense of place and local identity. It
is at odds with what exists, is planned or would reasonably be expected. At best it
attempts to minimise external views to most of itself. It does not avoid conflict.
[102] Insofar as the Rural Planning Area character statement is concerned, the proposal
conflicts with sub-paragraph (b). It may be recalled that subparagraph (b) appears to
relate to rural development or to development that has a nexus with rural
development. The proposal is neither in character. Even putting that to one side and
even acknowledging the attempts to contribute to the maintenance of the rural
landscape and achieve a level of compatibility with the rural landscape by hiding the
development areas, as much as it can, from the outside world, it fails to achieve
compatibility or to contribute to maintenance of the rural landscape when regard is
had to what would be observed from within the large site. Even putting that to the
side, there remains sufficient impact (ie on appreciation beyond the site) to conclude
(as I do) that the provision is not satisfied.
[103] The proposal also conflicts with the Rural Planning Area Code because, for the
reasons already discussed it proposes development:
(i) within the Rural Planning Area that is not consistent with the character
of the Rural Planning Area described in the character statement and so
conflicts with the purpose of the code; and
(ii) that would detrimentally affect the existing and future rural amenity
and landscape of the Rural Planning Area and so conflicts with P7. The
manner in which it would have that effect has been discussed. The
degree of impact on the area would, I am satisfied, be significant.
101 T11-74, 75.
-- 38 of 89 --
39
[104] As for CP 2014, which is a matter of weight, for the reasons already discussed, the
proposal conflicts with:
(i) specific outcome 3.4.4.1(4) because it does not protect non-urban land
in order to, amongst other things, protect non-urban landscape values;
(ii) s 6.6.1.2 of the purpose of the Rural Zone Code in that:
o it proposes non-rural uses that are not compatible with the
landscape character of the rural area, and
o is inconsistent with the maintenance of character and landscape
values
o is inconsistent with PO20 in that it contemplates subsequent
subdivision which is not limited to reflect, amongst other things,
landscape values.
My conclusion on this issue supports the ultimate conclusion which I would have
reached in any event in relation to the appeal.
(iii) Ecology
[105] Unsurprisingly, the planning documents contain provisions which seek to respect
ecological values. DEO 1 of TPS 2003 is that important regional ecosystems
maintain the integrity of, and contribute to, a healthy, safe and liveable city
environment. It directs the reader to map 2 which shows the site with important
regional ecosystems and with habitat corridors. The mapping appears to be
indicative and the ecological experts agreed that map 2 does not provide a
reasonable representation of the ecological features of the site. Their work provides
evidence of the values and their location within the site. The DEO is to be achieved
by a number of city strategies including designing and integrating infrastructure and
development to minimise the potential adverse impacts on the city’s natural
environment.102
[106] The respondent pointed to provisions applicable to the Rural Planning Area in TPS
2003 which require rural development to minimise potential adverse environmental
impacts. The proposal is not however, for development of that kind.
[107] The purpose of the Natural Areas Code in TPS 2003 is:
“Purpose: The purpose of this code is to –
(a) conserve, maintain and enhance natural areas to protect
Biodiversity values, which include ecosystem, species
and genetic diversity;
(b) protect and manage important areas, processes and
species; and
102 s 2.1.2(c)
-- 39 of 89 --
40
(c) maintain or establish Habitat Corridors between the
Hillsides and Escarpments and the Coast.”
[108] P1, P2 and P3 of that code refer to environmental corridors, habitat corridors and of
concern regional ecosystems identified on map 5.2. The mapping does not coincide
with the evidence of the ecologists and accordingly the respondent did not rely on
those provisions.
[109] The purpose of the Urban Growth Boundaries Code in TPS 2003 states that areas
outside the city’s Urban Growth Boundaries are retained for, amongst other things,
environmental purposes. The inclusion of the site on the environmental mapping
suggests that is a relevant purpose, at least in part.
[110] As already noted CP 2014 provides, in s 3.5.2.2, in setting out land use strategies for
the natural assets element, that avoiding further expansion of urban or rural
residential development beyond existing designated areas will avoid unnecessary
pressure on environmentally important values.
[111] Ecological considerations are of relevance to the Rural Zone within which the site is
included in CP 2014. The Rural Zone Code’s statement of purpose includes that it is
to “protect or manage significant natural features, resources and processes”.103 The
overall outcomes include that “the environmental…values of all rural land are
maintained”.104 Further, P020, which relates to the grazing precinct in which the site
falls required reconfiguration to be “limited to…protect…ecological…values.”
[112] The purpose of the Natural Assets Overlay Code is to:
(a) protect areas of environmental significance, and the ecological
processes and biodiversity values of terrestrial and aquatic ecosystems;
(b) maintain ecosystem services and other functions performed by
Townsville’s natural areas; and
(c) protect water quality, ecosystem health and the natural hydrological
functioning of waterways, wetlands and their riparian areas.
It is said that the purpose of the code will be achieved through the following overall
outcomes:
(a) development avoids or minimises direct and indirect impacts on areas
of environmental significance and their associated ecological functions
and biophysical processes;
(b) development provides for the protection or enhancement of a linked
network of habitat areas, including maximising opportunities for
rehabilitation and restoration of degraded ecosystems, ecological
103 56.6.1.2(1)(c)
104 56.6.1.2(3)(f)
-- 40 of 89 --
41
communities, remnant vegetation and connecting corridors wherever
possible;
(c) development, including infrastructure, is located and designed to
maintain or enhance ecological functions including facilitation of
wildlife movement for native terrestrial and aquatic species and native
and migratory avian species;
(d) the water quality values and ecological functions of wetlands,
waterways and their riparian areas and buffers are protected or
enhanced;
(e) development maintains, protects or enhances the natural hydrological
regime and functioning of waterways and wetlands, including surface
and ground waters and their interaction;
(f) fragmentation of remnant vegetation and habitat areas is avoided to
maintain ecological function and biodiversity values, and to maintain or
increase the resilience of natural assets to threatening processes,
including climate change; and
(g) development incorporates appropriate buffering and mitigation
strategies to avoid or minimise potential damage to natural areas and
other environment assets.
[113] The performance outcomes and acceptable outcomes include the following:
PO11
Corridors and linkages are provided to
supplement and create additional
ecological corridors and habitat
linkages along waterways, drainage
lines, ridgelines, coastlines and other
areas where possible.
No acceptable outcome is nominated.
PO12
Development facilitates unimpeded use
and movement of terrestrial and aquatic
fauna that are associated with or are
likely to use an ecological corridor as
part of their normal life cycle by:
(a) ensuring development, including
roads, pedestrian access and in-stream
structures, does not create barriers to
the movement of fauna along or within
ecological corridors;
No acceptable outcome is nominated.
-- 41 of 89 --
42
(b) providing effective wildlife
management infrastructure to direct
fauna to locations were wildlife
movement infrastructure has been
provided to enable fauna to safely
negotiate a development area; and
(c) separating fauna from potential
hazards through the use of appropriate
barriers and buffers.
PO16
Development provides a buffer to a
waterway, in order to:
(a) protect or enhance habitat values,
connectivity and other ecological
processes and values;
(b) protect water quality and aquatic
conditions;
(c) maintain natural micro-climatic
conditions;
(d) maintain natural hydrological
processes;
(e) prevent mass movement, gully
erosion, rill erosion, sheet erosion,
tunnel erosion, stream bank erosion,
wind erosion, or scalding; and
(f) prevent loss or modification of
chemical, physical or biological
properties or functions of soil.
Any setbacks or other areas required
for bushfire management, safety,
recreation, maintenance or any other
purpose, are provided in addition to a
vegetated buffer provided for
ecological purposes.
No acceptable outcome is nominated
where in an urban residential zone or
centre zone.
Elsewhere (including the Emerging
community zone, Rural residential zone
or industry zones):
AO16
Other than where cropping for forestry
for wood production, a development-
free buffer is provided and maintained,
extending from top of the bank of a
waterway and with a minimum width
of:
(a) where in the Wet Tropics bioregion:
(i) stream order 1 to 4: 25m; or
(ii) stream order 5 and above:
50m;
OR
(b) in all other regions (Brigalow Belt
North Bioregion or the Einasleigh
Uplands Bioregion):
(i) stream order 1 or 2: 25m; or
(ii) stream order 3 or 4; 50m; or
(iii) stream order 5 and above:
100m;
Editor’s note – Natural assets planning scheme
policy no. SC6.9 contains Figure SC6.9.1
-- 42 of 89 --
43
which identifies stream orders and bioregions.
This information may also be obtained from the
relevant state agency.
Editor’s note – Where a development requires
multiple buffers to be established by this code
to protect watercourses, corridors, wetlands or
core habitat, the greatest distances required by
this code will prevail to the extent of any
inconsistency.
[114] The ecological features of the site and their location within the site were the subject
of examination by the ecology experts. Mr Agnew (called by the appellant), in
particular, implemented field studies involving 27 survey person days over a three
month period. Dr Watson (called by the respondent) agreed that the work done by
Mr Agnew105 was comprehensive.106 The work ultimately led to the production of
an Ecological Features Plan (EFP) for the site.
[115] The experts agreed that, subject to some exceptions, the EFP “provides a reasonably
accurate description of the ecological features existing on the subject site, limited
only by the scale of mapping”.107 Given the field surveys, Mr Agnew’s evidence is
that the EFP would be accurate to within a matter of meters.108 In the second
ecology JER Dr Watson stated that if development be allowed on the site then the
EFP should be used as a constraints basis for the development layout.109 The EFP
was also referred to in the fourth ecology JER as “the agreed description of the
extent of ecological values across the site (limited only by scale)”.110
[116] The EFP shows a number of ecological features across the site. As Dr Watson fairly
acknowledged, he agreed with Mr Agnew that the proposed master plan retains the
highest conservation priorities of the site.111 In particular, it is proposed to retain
habitat type 1, located in the western part of the site and the west/east corridors
provided along the two major watercourses of Stoney and Middle Creeks that link
to it. They are the most important ecological features112 in the circumstances,
including having regard to the Harvey Range which lies to the west.113
[117] In his testimony, Dr Watson was critical of the width of the proposed corridors to be
retained along Stoney and Middle Creeks. The proposal was subsequently changed
to provide corridors of no less than 250m at any point, to accord with what Dr
105 and by Dr Hassall.
106 T5-4.
107 Ex 17 pg 10.
108 T4-26.
109 Ex 17 pg 16, para 6.3.
110 Ex 19 pg 6, para 24
111 T5-3.
112 Agnew T4-36, T4-38, 39, Watson T 5-13.
113 T4-36.
-- 43 of 89 --
44
Watson had attested was his preference.114 Dr Watson had indicated that would
resolve his concerns regarding corridors in an east/west direction.115
[118] Dr Watson had also indicated that such a change would not completely resolve his
residual concerns. He referred, in particular, to other drainage lines identified either
on the EFP or yet to be identified by later ground truthing. He also referred to the
need to ensure that the resolution of non-ecological values did not compromise the
ecological outcome. He nevertheless thought it possible to resolve the ecological
issues.116
[119] The proposed master plan does not retain all of the ecological features shown on the
EFP. There are a number of streams/drainage lines (1st , 2nd and 3rd order) shown on
the EFP. The master plan does not include all parts of all streams in the open space.
That did not trouble Mr Agnew, because he saw the exclusion of the lower order
streams/drainage lines as insignificant in relation to retention of the key ecological
features and biodiversity values of the site.117 He regarded the large mapped area of
remnant vegetation dominating the western part of the land and the riparian
environments associated with Stoney and Middle Creeks, which are to be retained,
as standing in clear contrast to the balance of the site.118 He described the
streams/drainage lines or parts thereof to be developed as more like linkages along
drainage lines, which are distinctly different from the characteristics and values of
Stoney and Middle Creek and the remnant vegetation on the western part of the site.
He agreed with the characterisation of his view as being that they are linkages, but
not as high quality as Stoney and Middle Creeks.119
[120] In JER2 Mr Agnew said120 that, whilst he agreed with the overarching objective of
retaining and protecting the fauna habitat and habitat values on the site, in his view
the “key requirements” were centred on the retention, buffering and management of
the remnant vegetation in the west and the riparian environments associated with
both Stoney and Middle Creeks. Dr Watson, on the other hand, was not prepared to
accept the loss of values associated with the lower order streams or parts thereof
shown on the EFP and the north/south connections they provide.121 He pointed out
that all are identified as ecological features on the EFP. He was also looking for the
protection of other drainage lines that might later be identified by ground
truthing.122
[121] In relation to unmapped streams, Dr Watson drew attention to a passage in the
second ecology JER where it states that, while watercourses as per VMA vegetation
114 T5-11.
115 T5-11.
116 T5-11.
117 Ex 19 pg 5, para 20.
118 Ex 37 pg 2.
119 T4-38, 39.
120 Ex 17 pg 13.
121 Ex 19 pg 4 para 18, Ex 48 pg 71.
122 T5-11.
-- 44 of 89 --
45
supporting mapping were included in the EFP, that mapping does not represent all
the watercourses and drainage lines across the site and that detailed site based
ground truthing and mapping is necessary to accurately map their location.123 As
has already been acknowledged, Dr Watson had however, in the same JER, said that
the EFP should be used as a constraints map for the development layout. Further, in
his testimony, he said that it is perhaps unnecessary for all of the streams to be
retained. He agreed that he was not troubled by the fact that some would be
developed. When questioned about what he thought might be required to maintain a
north/south connection, he pointed to what he described as two or three major
drainage lines or linkages in the south of the site and said that there might be more
protection and rehabilitation of those.124 He went on to suggest that, if he had been
advising, he might have suggested 3 or 4 x 100 metre wide corridors in the south.
[122] Subsequent to Dr Watson’s evidence the master plan was changed to retain more of
the water courses/drainage lines in the southern area such that there are now to be 5
connections to the south western boundary with dimensions of 100m or more.
Further, there have been changes in the north to increase setbacks from the mapped
watercourses. Those changes now provide for the retention of many (although not
all) of the watercourses/drainage lines throughout the site, both in the north and the
south, to provide linkages, including north/south linkages, in addition to the
retention of the watercourses of highest significance (Stoney Creek and Middle
Creek) and the east/west corridor they provide to/from the remnant vegetation to the
west. The changes were obviously responsive to the evidence of Dr Watson.
[123] In contending that the proposal, even as now changed, conflicts with the various
provisions extracted earlier which relate to impact on ecological values, the
respondent contended that the planning provisions are not concerned with only
protecting “key features” of ecological value as was Mr Agnew’s focus. Reference
was also made to what were referred to as uncertainties in relation to what is
proposed in relation to rehabilitation and dedication of open space, although there
remains the opportunity to address matters by conditions (or in later approvals).125
[124] I accept that consideration should be given to the ecological features of the site
beyond those considered by Mr Agnew to be the key features. That does not mean
however, that every drainage line on the site must be retained. As has already been
observed, even Dr Watson was prepared to concede that not all the lower order
watercourses/drainage lines necessarily must be retained. He was not troubled by
the prospect of some being developed. Some extent of loss of those features can be
accepted as insignificant and so as not inconsistent with a conclusion that, insofar as
the retention of open space is concerned, what is now proposed is consistent with
the maintenance of ecological value and the minimisation of impact.
123 Ex 48 pg 7, para 7.
124 T5-14.
125 Subject to argument, that may be by conditions of an approval of the application and/or in later
approvals.
-- 45 of 89 --
46
[125] The loss of land providing habitat and/or corridor/linkage and/or biodiversity value
is not the only potential ecological impact of the proposal. As Dr Watson said, there
is a need to ensure that the resolution of other issues does not adversely affect the
ecological outcome. There were two issues which the agricultural land use experts
agreed required resolution, but with respect to which the ecologists had not
considered the consequences of the required measures.
[126] The need to manage feral animals, including pigs, was recognised by both the
ecology experts and the agricultural land use experts. Current management practices
for the control of feral animals such as wild pigs will have to change.126 In his
testimony, Mr Sutherland proposed an electric fence around the perimeter of the site
to completely enclose the site, including open space areas in steep parts of the site.
Mr Thompson explained that such fences can be successful, in the control of feral
animals, by channelling them to a place where they can be trapped and destroyed.
He had never seen the measure used in a residential estate before and explained that
the fencing must be distanced from the estate itself, but, for maintenance reasons, he
would not put it so far back as to be on the perimeter of the site where it is steep.127
The appellant embraced that. Mr Thompson saw the fencing as being in the “large
residual green area” and that may, he acknowledged, have consequences for the
design of the works in the green space.128
[127] This evidence came after the ecologists’ evidence was concluded. They were not
recalled. There was no evidence from them as to the extent to which (if at all) such
fencing would also affect native fauna or have any other ecological impact. In the
course of oral submissions Mr Gore QC did not cavil with my suggestion that that
was unsatisfactory.129
[128] The site is affected by severe erosion associated with sodic and highly dispersive
soils. The hardening of the catchment that would result from development as
proposed, would increase runoff and the velocity,130 duration and frequency of
flooding in all events131 thereby potentially worsening the erosion hazard and
sediment export from the site. It is proposed to undertake works to stabilise and
rehabilitate those areas. Both Mr Sutherland and Mr Thompson132 gave evidence
that this would involve work in the watercourses, including armouring (rock lining).
Mr Thompson, whose evidence I prefer as to the extent of what is likely to be
required, testified that “quite a lot” of armouring would be required and reshaping
the bed. Whilst Mr Sutherland, at one point, suggested that the works could fit with
what the ecologists seek,133 there was no evidence from the ecologists about the
126 Ex 26 pg 3.
127 T10-72.
128 T10-76.
129 T14-32, 33 – in these footnotes T14 refers to the hearing on 11/12/2020 which, on the transcript, is
erroneously recorded as day 1.
130 although Mr Collins thought that a no significant worsening of velocity could be achieved – T3-51.
131 T3-51, Ex 47 pg 63, paras 15, 16.
132 T10-57, T-10-71.
133 T10-56, 57.
-- 46 of 89 --
47
impact of such measures from an ecological perspective.134 That was so
notwithstanding that the need for comment from the ecologists about the impacts of
erosion or of protection works to prevent erosion was raised by Mr Clark in
stormwater JER3.135
[129] There are other consequences of development. Bringing urban development, as
proposed, to the site necessarily brings some threats to ecological values. As Dr
Watson explained, the development brings more people and more activity to the site
including more traffic, lighting and noise. This gives rise to the prospect of “edge
effects”, including the potential for the escape of exotic flora. More vehicle
movements also brings a greater risk of collision with native fauna. The fauna has
less opportunity to move freely without added threats in the landscape.136 Domestic
animals would also be a threat unless they are effectively controlled.137 Mr Agnew
accepted that the development would bring such threats.138
[130] The use of the land for rural activities, also has some impact, or potential for impact,
but the site has the values found by the ecologists notwithstanding its use for
grazing. Mr Agnew acknowledged that development of the land as proposed would
be associated with a “wider sweep of negative impacts”.139 Further the ecologists
acknowledged the increasing awareness of sustainable farming and grazing
practices.140 In this context it is unsurprising that both Mr Agnew and Dr Watson
expressed the opinion, which I accept, that keeping the site as a rural holding is a
preferable outcome, from an ecological perspective, than permitting it to be
developed as proposed.141
[131] Mr Gore QC sought, in the course of re-examination of Mr Agnew, to recover
something of Mr Agnew’s concession in this regard. He asked Mr Agnew to assume
that the habitat in the western part of the site would, if the proposal proceeded, be
dedicated to a public body, but that that would not occur if the land remained as a
rural holding. Asked about how he would rank the options on that assumption, Mr
Agnew did describe the dedication as superior, but on the basis that it was
accompanied by a management plan to be implemented with the application of
additional resources.142 It should be noted, in this respect that, while Mr Agnew
assumed dedication to an agency prepared to assume responsibility for ongoing
maintenance, no detailed proposal for dedication has been formulated and no
agency prepared to accept the dedication has been identified. Dr Watson pointed out
134 T13-75, 76.
135 Ex 14 pg 7 para 10b.
136 Watson T5-2, 3.
137 T4-60, 61.
138 T4-61-63.
139 T4-63.
140 T4-57, T5-2.
141 Agnew T4-63, Watson Ex 48 p 73, T5-3.
142 T4-73.
-- 47 of 89 --
48
that dedication of the ecologically significant areas would be accompanied with
quite a sizeable burden for any body accepting the dedication.143
[132] Asked then to consider the proposal with such a dedication, Mr Agnew said it (the
dedication) would be a “positive association” with the proposed development and
agreed with the proposition that it would be an “acceptable ecological outcome”.
None of that however, takes away from the point that the proposed development
would, even assuming the dedication of part or all the open space, bring ecological
threats to the site to a greater extent than if it was retained as a rural holding. I
accept Dr Watson’s evidence that the proposed conversion of a large area to urban
development cannot be considered to be a good ecological outcome144 and that
keeping the land in its rural use is preferable from an ecological perspective.145
[133] It was rightly pointed out, for the appellant, that it is well established that this Court
traditionally approaches the assessment of a development proposal on the basis of
what is acceptable, rather than what is utopian. That general approach must
however, take account of the provisions of the planning documents. This is not a
site where urban development is contemplated.
[134] It has already been observed that, pursuant to TPS 2003, the site is beyond the urban
growth boundary. Further, as has also been observed, CP 2014 states that the city
shape and settlement pattern has been determined to avoid expansion of urban or
rural residential development beyond designated areas and that “this will avoid
increasing pressures on environmentally important values”. The evidence
demonstrates that the site does indeed have ecological values and that the proposed
development would bring pressure upon those values, such that, even with the
mitigation measures proposed (including open space retention/dedications,
rehabilitation and management), it is not to be preferred, from an ecological
perspective, to the retention of the land as a rural holding. That might not, of itself,
warrant refusal (putting to one side the gaps in the evidence on specific matters
discussed above) but it underscores the public interest in adhering to the duly
adopted planning strategy.
[135] Whilst the most recent edition of the master plan appears to set aside sufficient open
space (assuming appropriate rehabilitation, dedication and management) assuming
development of the site for urban purposes is otherwise acceptable, the gap in the
evidence concerning the ecological impacts of measures proposed by the
agricultural land experts means that I am left short of being satisfied that the
proposal would satisfy those planning provisions, referred to earlier, which relate to
ecological impacts and respect for values. Further, the fact that the type of
development proposed would constitute a greater ecological threat compared with
the retention of the land as a rural holding underscores the public interest in
adhering to the planning strategy with respect to land use.
143 T4-75.
144 Ex 48 para 32.
145 T5-3.
-- 48 of 89 --
49
(iv) Amenity – Noise
[136] The potential noise impact of some controversy related to the generation of traffic
movements. Mr King accepted that the substantial increase in traffic on nearby
roads external to the site would create a change in the ambient noise
environment.146 That change would however, occur gradually, over many years, as
the development progresses, rather than in a sudden and dramatic way. Accordingly
it is unlikely to be perceived as a nuisance (assuming that road traffic noise impacts
are assessed against appropriate standards in later applications). The change in the
ambient noise environment by reason of the substantial increase in traffic external to
the site is however, likely to have some eroding effect on the rural character and
amenity of the area through which the road network passes, even though that impact
is one that would occur in an incremental way.
[137] This is not a case where noise impact in and of itself warrants a refusal of the
application. Rather the noise impact would contribute, to some extent, to the way in
which the proposal would impact upon the rural character and amenity of the area
(although that contribution is not something on which my ultimate conclusion
depends).
(v) Reverse Amenity and Impact on Nearby Rural Land Use
[138] The site is surrounded by lots which have, or may in the future have, land uses to
which the proposed residential uses on the subject site might have some sensitivity.
To the east-south-east of the site lie rural lots ranging from 230 to 340 ha used for
grazing (with one used for a solar farm). South-east of the site lies rural living uses
(mainly associated with equine uses) on 40 ha lots. To the immediate north lies rural
living type uses on 40-80 ha lots. A quarry lies to the north west. There is an
obvious concern not to place sensitive land uses, such as residential uses at
suburban densities, where they might be adversely affected by adjoining or nearby
legitimate uses of a different kind (here a quarry and rural uses) with the potential
for creating a nuisance for the former or a constraint for the latter. Increasing the
number of sensitive receptors tends to increase the potential for complaint.147 Some
people are, of course, more sensitive than others and it is not unknown for
residential development adjourning rural activities to generate complaint even when
buffers are established to comply with requirements.148
[139] The respondent drew attention to:
• DEO 5 of the TPS and, in particular, City Strategy 2.5.2(b)(iii) which
speaks of protecting primary industries;
146 T3-29, 30.
147 T3-24.
148 T3-25.
-- 49 of 89 --
50
• DEO 6 of the TPS and, in particular, City Strategy 2.6.2(c) which
speaks of protecting land from encroachment by incompatible
development;
• P2 of the Rural Planning Area Code (extracted earlier) which seeks
provision of a separation distance between Rural Development and
Sensitive Receptors to prevent adverse impacts of spray drift, odour,
noise, smoke, dust, vibration and ash;
• S 3.3.2.1(2) of CP 2014, which speaks of urban uses being adequately
buffered from nearby rural land, and
• S 6.6.1.2(b) of CP 2014 which speaks of providing opportunities for
non-rural uses that are compatible with, amongst other things,
agriculture and do not compromise the long-term use of the land for
rural purposes.
[140] These matters were the subject of consideration by Mr King (engaged by the
appellant) and Ms Richardson (engaged by the respondent), who produced a joint
report with no areas of disagreement. Mr King also produced a separate report for
the hearing and testified at the hearing.
[141] In their joint report, the experts agreed that:
(a) existing quarry operations do not pose a significant constraint to the
proposed development, although more detailed investigations should be
done as part of the application process for each stage, to determine if
additional noise mitigation measures and/or revised buffers are
required;
(b) whilst dust impact assessment reports should also be done for
development applications for future stages of the proposed
development, practicable dust mitigation solutions are likely to be
available;
(c) the location of a certain air strip does not constrain future residential
development;
(d) certain separation buffers would need to be incorporated in order to
comply with those specified in the Rural Planning Area Code in
relation to noise and spray drift.
[142] The appropriate buffers for spray drift vary depending upon whether the spray is
applied at ground level or by air. The existing situation is such that the buffers can
be readily incorporated. Mr King’s evidence was that a minimum buffer of 25m and
a maximum of 50m would presently be sufficient, but that there should be a further
assessment when later applications are made.149 Accordingly, the proposal is to
149 Ex 35 para 22, T3-22.
-- 50 of 89 --
51
frame the variation part of the approval in such a way as to require the appropriate
buffers to be decided at the time of future applications in relation to each stage. That
is, in my view, appropriate.
[143] As was pointed out for the respondent, it is at least possible that this might lead to a
not insignificant reduction in development yield. Mr King accepted, for example,
that the separation distance for aerial spraying is a minimum of 300m.150
Accordingly he had shown on Figure 1 to his appeal reports151 a range of setback
lines being 50m, 100m (relevant setback to ground applied spray) and 300m. Mr
King added that reduced buffers might be acceptable if they are vegetated.152
[144] The effect of the proposal on agriculture in the area was also assessed by Mr
Sutherland (engaged by the appellant) and Mr Thompson (engaged by the
respondent). Having described the subject site and the surrounding rural uses they
agreed, in their joint report, as follows:
“The proposed master plan would result in the fragmentation of these
rural and rural living scale land uses. Current management practises
such feral animals [sic], weed control strategies, pasture management
involving the use of fire and farm biosecurity strategies which are
currently appropriate on these larger-scale rural zone lots will have to
be adjusted to avoid conflict with the proposed non rural uses.”
[145] Mr Sutherland recommended a buffer of 40m to agricultural land and a perimeter
electrified fence for the control of feral animals. The buffer may, of course, need to
be wider to take account of the recommendations of other experts. As has already
been observed, Mr Thompson did not believe it desirable for the fence to follow the
boundary in the steeper parts of the site. He suggested, persuasively in my view,
that it would be better located to fit within an overall feral animal control program
and in a place where it is most likely to be easily maintained. As has been noted, the
ecologists were not asked to consider whether they had any concerns about the
electrified fence.
[146] Insofar as buffers are concerned, it was pointed out, for the appellant, that
conditions of approval can be prepared that provide for the future assessment of the
proposed development, at the development permit stage, which require particular
buffers to agricultural uses to be provided, in the event that those nearby agricultural
uses change in the future.
[147] There would be some adjustment potentially required by neighbours if the proposal
proceeded. Although Mr Sutherland had agreed, in the joint report, that adjustments
would be required, he appeared to find it difficult, in the course of his testimony, to
150 T3-27.
151 Ex 35 pg 12.
152 T3-29.
-- 51 of 89 --
52
explain the detail of that. His testimony in this respect was less than helpful,153 but
Mr Thompson was able to be of greater assistance.
[148] Feral animals such as pigs, could not be baited or shot from a distance, as is
currently the case. As Mr Thompson pointed out, the proposed fencing should be
designed in conjunction with neighbours to direct the animals to a place where they
are trapped for eradication. The most economical pelletised weed control agent
would no longer be appropriate.154 There would need to be improved systems for
burning155 and additional attention to prevention of biosecurity breaches by, for
example, someone straying onto a property.156 The proposal would therefore, be of
some consequence for surrounding rural uses, but the impacts are in the nature of
adjustments and are not, in my view, undue. Mr Thompson accepted that buffers
could be put in place to minimise the reverse amenity impacts.157 Wild animal
management fencing can be implemented along the lines he suggested.
[149] For the reasons given, I am of the view that the proposal can be carried out in a way
that adequately protects primary industries in adjacent rural land and does not
compromise their long term use for rural purposes. Whilst the proposed use may be
potentially incompatible in this rural area, any reverse amenity conflict of these
kinds158 can, I am satisfied, be adequately addressed in the ways indicated,
including by the provision of appropriate buffers to be finally determined as part of
subsequent development approvals. The proposed development ought not be refused
on this basis.
(vi) Infrastructure
[150] The planning documents are, unsurprisingly, concerned with ensuring that
development is provided with infrastructure in an efficient and cost effective
manner. In that regard:
(i) City strategy 2.6.2(b)(iv), in support of DEO 6 of TPS 2003,
provides that the DEO is intended to be achieved by, amongst
other things, establishing the city’s urban growth boundaries to
create an efficient urban form by, amongst other things,
establishing a land use pattern that is consistent with the
location and capacities of existing infrastructure items, plans
and programs of service providers.
(ii) The Urban Growth Boundaries Code in TPS 2003 includes the
following purpose:
153 see T10-62-65.
154 T10-73.
155 T10-74.
156 T10-72.
157 T10-74.
158 impacts on visual amenity and character are considered elsewhere.
-- 52 of 89 --
53
“(c) Council infrastructure and state government
infrastructure is coordinated and provided in an orderly,
efficient and cost effective manner”
And the following performance criterion:
“P1. Urban Development
(c) Provides infrastructure in an orderly, efficient and cost
effective manner”.
(iii) The strategic framework in CP 2014 includes the following
provisions in relation to the “integrated infrastructure planning
provision” element159:
“City Shape
(1) Land use and development patterns support the efficient
and cost-effective provision of infrastructure and
community facilities.
(2) The city shape and activity centres hierarchy describes
in the strategic framework establish the basis for the
most efficient provision of infrastructure to meet
community needs over 25 years. In particular, it
minimises the dilution of infrastructure investment
across multiple development fronts. While upgrades will
be required in the infill developments areas, these costs
will be less than those that would be involved in
continued outward expansion of the urban area”.
(iv) One of the actions identified in the Regional Plan as required
to achieve its principal aim is “more efficient patterns of
development to put an end to Townsville’s urban sprawl,
thereby reducing cost pressures on infrastructure provision and
services”.
[151] The land, the subject of the proposal, is not serviced by the infrastructure needed for
the proposed development. The Council has no plans to provide the
infrastructure.160 The land is outside the priority infrastructure area (PIA) and the
current Local Government Infrastructure Plan (LGIP).161 The proposal is for urban
development of presently unserviced rural land so as to expand the urban area in a
way not contemplated by Council’s infrastructure planning. It is at odds with the
land use pattern referred to in the strategy in support of DEO 6 of TPS 2003.
159 s 3.3.6.
160 T8-12.
161 T8-13.
-- 53 of 89 --
54
[152] The appellant’s proposal is, in effect, to relieve Council of the cost of the provision
of infrastructure. In that regard, it proposes as follows:
(i) It will (in addition to constructing internal roads) upgrade the
external local road network in accordance with the
infrastructure agreement it has entered into with the State
(discussed later). This would ultimately require it to treat with
the respondent in its capacity as the local road authority.
(ii) It will provide water infrastructure internally and to connect to
the Council’s main at Kelso. Supply for phase 1 of the
development would be by extension from Kelso. An on-site
reservoir storage would be provided in phase 2 and 3.
(iii) An on-site sewage collection, treatment and disposal system is
proposed, to be funded by a body corporate for the life of the
development. Presumably the body corporate’s responsibility
would include the connections from each property within the
development.
(iv) The provision of local and district parks.
[153] The proposed development might also have potential to affect the efficiency of
provision of other services or facilities (eg garbage collection), but they were not the
focus of attention.
[154] It was pointed out, for the respondent, that meeting the cost of providing
infrastructure, over and above that which exists or is planned, in order to facilitate
the unplanned conversion of part of the rural area to urban use does not obviate the
consequent financial burden upon the Council. Whilst the Council might get the
infrastructure (at least the water and road upgradings – the sewage being retained by
a body corporate) at no cost, it then assumes the maintenance and, ultimately,
replacement costs associated with that (upgraded) infrastructure.
[155] There was more debate, amongst the experts and the lawyers, about whether it was
fair to have regard to maintenance and replacement costs of infrastructure, or
infrastructure upgrades, provided at no capital cost to the Council. It was noted that
the planning scheme provisions speak of provision of infrastructure, rather than its
maintenance. It seems to me however, that the respondent is right to point out that
permitting development to occur where it cannot be provided with infrastructure in
an orderly, efficient and cost effective way, has financial implications beyond the
initial capital outlay.
[156] Reference was made to the fact that the creation of lots generates more rate revenue.
That may be so, but that will occur whether new lots are created on a site such as the
-- 54 of 89 --
55
subject or on sites which align with infrastructure planning. Mr Gore QC, in oral
submissions, acknowledged weakness in the rates argument.162
[157] There was debate about attempts to quantify the operating/renewal costs and
compare them to other developments. It is unnecessary for me to dwell on the detail
of that. Ultimately Mr Gould appeared to accept that the proposed development
costs in this regard would be at least higher than others.163 In any event there are
clearly costs associated with the infrastructure to be provided to this development
notwithstanding that the capital costs will be met. In oral submissions, Mr Gore QC
said, in effect, that he had instructions to submit to a condition for his client to cover
operating/renewal costs.164
[158] It was pointed out, by the respondent, that, in addition to the cost matters discussed
above, there is a further planning dimension. As Mr Gould confirmed, existing
infrastructure within the urban area has spare capacity to accommodate further
residential development within that area.165 Development outside the planned urban
area has the potential to consume some of that spare capacity and/or divert
development from areas planned to make use of the spare capacity. For example,
insofar as traffic is concerned, Mr Trevilyan persuasively argued166 that it would be
desirable, from an infrastructure delivery standpoint, to have development occur
closer to Townsville first.
[159] The proposal is discordant with the planning documents with respect to
infrastructure. That does not cease to be so just because the developer is prepared to
meet the capital and operational/renewal costs of the required infrastructure. It still
sits uneasily with the planning documents and a sound planning approach of
marrying new development with existing and planned infrastructure. I accept Mr
Perkins’ evidence to the effect that what is proposed is not orderly and efficient.167
That tends against approval of the development application, although my ultimate
conclusion is not reliant on that.
[160] Mr Gore QC, in the course of oral submissions,168 adopted the position that whilst
covering the costs might not make his client’s proposal comply, it takes the “sting”
out of the conflict, such that the Court ought not refuse the development application
on this ground if it were otherwise minded to allow the appeal. That it relieves the
cost consequences is a consideration, but it is still contrary to the planning strategy.
In any event, for the reasons stated herein, I am not otherwise minded to allow the
appeal.
(vii) Traffic
162 T14-42.
163 T8-65, 66.
164 T14-42.
165 T8-16.
166 T12-20, Ex 32 pg 9 para 55.
167 T11-75.
168 T14-43.
-- 55 of 89 --
56
[161] The respondent contends that the traffic impacts of the proposal have not been
shown to be satisfactory and that a decision to approve the development application
would conflict with the following provisions of TPS 2003:
(i) strategy 2.6.2(d) for DEO 6 which refers to developing and
maintaining a transport network considering frictional,
functional and impact characteristics which amongst other
matters, improves accessibility; facilitates efficient and
convenient access and mobility within and through the City for
all transport and travel modes and reflects the road function
and protects areas from inappropriate traffic movements;
encourages walking and cycling through the provision of
direct, safe and secure routes to local facilities such as shops
and schools; and
(ii) General Development Code paragraphs (a) and (b) of the
purpose of the transport part of the code (s 5.5.3) which refer
to development providing for the efficiency and safety of the
transport network; convenient access and movement of,
relevantly, private vehicles, cyclists and pedestrians; and
(iii) Performance criteria P1 (a), (b), (c), (d) of that code, which
provide as follows:
“P1. The City’s transport network comprises an integrated
hierarchy of roads, bikeways, public transport routes and
pedestrian paths that safely and efficiently serves the needs of
the community.
The transport network
(a) has design features, that convey the primary
function of each type of road and encourages
driver behaviour, speeds, access, acoustic
environment and traffic volumes that are
appropriate to that function;
(b) encourages walking and cycling and a safe
environment for pedestrians;
(c) provides a high level of internal accessibility
within neighbourhoods and appropriate external
connections for vehicles, pedestrian, and cycle
movements;
(d) deters through traffic from neighbourhood areas
and creates safe conditions for local road users,
pedestrians and cyclists.”
-- 56 of 89 --
57
[162] The development is proposed to have road access to the north via the local road
network of Sterritt Road, Laudberg Road, Allambie Lane and Beck Drive to the
State-controlled road network. It has already been observed that the appellant has
entered into an infrastructure agreement with the State that it will upgrade the local
road network and the access to the State-controlled Ring Road. The conditions of
that agreement include as follows:
“1.1 The Proponent agrees that:
(1) it will limit the development of the Development Land
to no more than 1,000 Residential Lots until such time
as the following road works have been constructed to the
Department’s satisfaction:
(a) the Beck Drive / Townsville Ring Road Upgrade;
and
(b) the duplication of Beck Drive to a four lane
divided form (from Allambie Lane to the
Townsville Ring Road).
(2) it will carry out the following external road works prior
to obtaining approval for a plan of subdivision or the
commencement of use of the first developed Residential
Lot the subject of the Requested Approval:
(c) Upgrade of Laudberg Road from an unsealed road
to a two-lane collector Type C plus 4 bridges (2 x
10m span and 2 x 25m span);
(d) Upgrade of Sterritt Road (from the development
to Allambie Lane) from an unsealed road to a
two-lane collector Type C; and
(e) Upgrade Allambie Lane (from Sterritt Road to
South Beck Drive) from a two-lane Collector type
C to Sub Arterial Type B plus 2 bridges (1 x
200m span and 1 x 50m span); and
(3) it will limit the development of the Development Land
to no more than 5,100 Residential Lots.”
[163] It may be noted that clause 1.1(1) does not oblige the appellant to undertake the
works with respect to Beck Drive and its intersection with the Ring Road. The
evidence is to the effect that Beck Drive will likely be upgraded in any event.
[164] The upgrades would have the effect of carrying traffic from the proposed
development to the preferred access point of the State-controlled road network. The
agreement also required a very substantial financial contribution of $26,295,600 (to
-- 57 of 89 --
58
be indexed), payable in stages, for the upgrade of road infrastructure to mitigate the
impact of the development on the State-controlled road network.
[165] In the course of the appeal it was put to Mr Collins (the appellant’s flooding and
stormwater expert) that it would be desirable for the local roads to be upgraded to a
Q100 standard. The appellant, by Mr Gore QC, indicated it would accept a
condition to that effect.169 Mr Collins’ evidence is that upgrades to that standard
could be achieved without significant adverse affect to other properties, although it
appears from Mr Gould’s evidence (discussed later) that an alternative to Beck
Road will likely be necessary for flood free access. A condition as to upgrading to a
Q100 standard is supported by the co-respondent by election.
[166] Should the proposal proceed then there would need to be provision for public
transport. Infrastructure for that (e.g. bus stops and stopping/turning bays) can be
provided. The appellant volunteered that a condition of approval could require it to
provide private bus services to existing public transport stops until such time as a
critical mass of population is established to cause the development to be serviced by
public transport.
[167] The traffic evidence was unduly complicated. There were seven joint reports
completed over many years, with the identity of the traffic engineers undergoing
change in the meantime. There were also statements of evidence for the hearing as
well as substantial evidence in chief, which made the evidence something of a
moving feast of the kind which has thankfully become rare in recent times.
[168] The evidence of Mr Williams (the traffic engineer called by the co-respondent by
election) understandably was more focussed on the effectiveness of the
infrastructure agreement in safeguarding the State-controlled road system. The
difference between Mr Douglas (called by the appellant) and Mr Trevilyan (called
by the respondent) focussed more on the local road network and whether the
appellant had yet done enough work to demonstrate that a preliminary approval was
appropriate from a traffic perspective.
[169] There were ultimately four areas of debate in relation to traffic as follows:
(i) Whether the modelling/analyses was appropriate.
(ii) Whether the analysis of intersections ought to have been of wider
compass.
(iii) Whether the proposed upgrades to Beck Drive are inappropriate and
unable to be carried out.
(iv) Whether the proposal would render the reverse curve on Sterritt and
Laudberg roads unsafe.
(a) Modelling
169 T3-55.
-- 58 of 89 --
59
[170] The respondent claims that the impact of the proposal on the road network has not
been appropriately modelled. The evidence refers to a number of models or
modelling exercises.
[171] Modelling was undertaken by the DTMR to inform the planning of the Ring Road 5
project, including a new interchange at Beck Drive. All the traffic experts agreed, in
the sixth traffic JER, that the outputs from the modelling appeared to indicate that
the proposal could proceed up to 5100 lots on the basis of upgrades to Beck Drive
(and the ramps onto the Ring Road), Laudberg Road, Sterritt Road and Allambie
Lane. It was also agreed that a suite of works on local roads and at local
intersections would likely be required.170
[172] Mr Trevilyan raised a concern about what seemed to be a very low trip generation
rate used in the model. All the experts agreed that further investigation was
required. Subsequently, the traffic engineers consulted the custodian of the
Council’s traffic model for the area (which does not include the subject proposal).
That revealed that both models shared the same base parent demographic and trip
generation rates per household (from ABS data) and were calibrated to traffic count
data.
[173] The appellant commissioned additional modelling from Bitzios which updated the
DTMR modelling in relation to road upgrades. The results suggested that the
proposal can proceed to 5100 lots with, amongst other things, the upgrading of Beck
Drive to 4 lanes, with the first 1000 lots being able to proceed with Beck Drive in its
current 2 lane form. The assumed trip generation rate was 3.54.171
[174] Mr Trevilyan did not regard any of the models as “fit for purpose” to understand the
operation of the access corridor, and maintained his concern that the development,
as represented in the model, was not generating enough external vehicle
movements. The debate ultimately focused on the latter point.
[175] Notwithstanding the fact that the DTMR and Council models used the same trip
generation rates, Mr Trevilyan rightly maintained that the assumed trip generation
rate was inappropriate to apply in assessing the impact of the proposal on the local
road network, particularly in the early stages of the development. As he pointed out,
the rate of vehicle movements that are generated beyond the site will vary
depending on the extent of facilities within the development. The greater the range
of facilities available within the development, the fewer trips will be generated
beyond the development for the purpose of accessing facilities. As Mr Douglas
conceded in cross-examination,172 “for the first smaller number of lots the trip
generation rates will be higher and they’ll taper off as it becomes more self-
contained”.
170 Ex 32 pg 4.
171 T9-83, T9-85, Ex 33 pg 54.
172 T9-83.
-- 59 of 89 --
60
[176] Similarly, the greater the number and range of facilities provided within the local
catchment served by the local road network (external to the site) within which the
development is located, the fewer trips will involve use of the State-controlled road
network beyond that catchment. As Mr Williams observed in the course of cross-
examination,173 the traffic generation from the development to/from the most
immediate local road may be higher, at a localised level, but the numbers reduce as
the traffic is distributed to facilities within the catchment. Accordingly a lower rate
may be appropriate for assessing the impacts on the Townsville Ring Road, for
example. There was no substantial challenge to Mr Williams’ evidence that the
modelling was fit for purpose from a State-controlled network point of view.174
[177] The consequence of the above is that whilst the trip generation rate of 3.54 may be
appropriate for assessing the impact of the proposal on the State-controlled road
network, particularly once the development is more self sustaining,175 it is not
appropriate for use in assessing the impact of the proposal at a more local level in
the early stages when fewer facilities are provided. Mr Douglas accepted that the
assumed rate was likely to be an understatement in the early years176 and, in
particular, that the traffic generated from the first 1000 lots (Stage 1) was likely to
be higher than projected by the rate assumed in the model.177 Indeed for the ultimate
development to get down to a rate of 3.54 requires a full master planned community
with its attendant facilities.178
[178] Mr Douglas pointed out that only a preliminary approval was being sought and
there are plenty of opportunities to conduct more traffic studies to get actual traffic
generation rather than forecasting it.179 He suggested that the concern about the
generation rate could be accommodated by limiting the first stage to say 650 lots
(instead of 1000), with actual traffic surveys better informing subsequent
applications.180 Alternatively, bringing forward the upgrading of Beck Drive,
(which is the only road upgrading proposed to be required after the development
commences) would overcome the need to restrict stage 1 to 650 lots for capacity
reasons.181
[179] On the basis of the above evidence I am satisfied that the modelling demonstrates
that, from a capacity perspective, development is unlikely to have an undue
detrimental affect on the State-controlled road network.182 I am also satisfied that
the modelling provides a satisfactory basis for concluding, at least for the purposes
173 T9-97.
174 T9-96.
175 Mr Trevilyan would use a rate of 4.25 upd for the total development, but the likely generation rates
are not an exact science.
176 T9-85.
177 T9-86, T9-88.
178 T9-88.
179 T9-89.
180 T9-86, T9-89.
181 T9-90.
182 Noting that the appellant is to pay a financial contribution to mitigate the impacts on the State-
controlled road network.
-- 60 of 89 --
61
of a preliminary approval, that the development, once completed, will, subject to the
various road upgradings, be serviced by the identified local road network (between
the site and the Ring Road) with sufficient capacity. I am further satisfied that Beck
Drive, in its current form, has some spare capacity to accommodate some
development generated traffic, but I do not accept that it has been demonstrated that
Stage 1 of the proposal can appropriately proceed to 1000 lots in advance of an
upgrade of that road. I accept the submission for the appellant (consistent with the
approach of Mr Douglas), that to the extent further modelling (and road upgrades
consequential upon that modelling) is required, it can appropriately be addressed at
the development permit stage. Any preliminary approval should therefore, be on
terms which are consistent with that opportunity being reserved to that stage.
(b) Intersection Analysis
[180] Mr Trevilyan was also rightly concerned that the appellant had not, at least initially,
carried out a SIDRA analysis of the likely performance of affected intersections
(and the identification of any required upgrades). In JER7 he said it was very
unusual for any assessment not to include at least some SIDRA modelling at key
locations.183 He maintained that this ought to have been done for intersections
within the “impact assessment area” or “zone of influence” of the development,
defined, relevantly for intersections, as all intersections where any peak hour
movement is increased by 5% or more.
[181] Mr Douglas accepted Mr Trevilyan’s premise184 and responded by carrying out, in
his appeal report, SIDRA intersection modelling for what he described as every
substantial intersection south of Harvey Range Road. In so doing he believed he had
done the exercise to the extent necessary. He made the point that Harvey Range
Road, the Ring Road and Thurringowa Road/Riverway Drive are State-controlled
roads and “once you get to those three roads, you’ve – you’ve effectively diffused
the vast majority of the traffic”.185
[182] The analysis was carried out for the 1000 lot and the full development scenarios and
resulted in the conclusion that, for both scenarios, all intersections that would
meaningfully service the development will operate within acceptable limits given
the assumed road upgradings. The 1000 lot scenario would be affected by the
generation rate issue discussed earlier, but, as has been observed, the analysis
supported the full development scenario as well.
[183] Insofar as other intersections are concerned, Mr Douglas said that to assess all
minor T intersections where passing traffic increased by greater than 5% would be
an “endless exercise,”186 not done in the assessment of some other large
183 Ex 33 pg 8 para 25.
184 T9-74.
185 T9-74.
186 T9-73.
-- 61 of 89 --
62
developments with similarly wide ranging traffic impacts.187 Having considered the
busier intersections and found them to work satisfactorily, he did not see the benefit
in assessing all the minor intersections and looking at those further afield that are
remote from the locality. He thought that was particularly so at the preliminary
approval stage, bearing in mind that “there’s a lot of other moving parts here” and
that the exercise is based on 2030 forecasts.188
[184] Mr Trevilyan was not persuaded that further intersections ought not have been
analysed. He pointed out that the Riverway Drive/Ross River Road intersection was
not analysed, even though the impact on it is more than 5%. It should be
acknowledged that is the intersection of 2 State-controlled roads,189 and the
appellant has entered into an infrastructure agreement with the co-respondent which
includes substantial monetary contributions to fund the upgrade of road
infrastructure to mitigate impact on the State-controlled road network. Whilst an
untied monetary contribution does not necessarily mean that a given intersection
will perform satisfactorily, I am, in the particular circumstances of this case,
prepared to put some weight upon the fact that the appellant has come to terms with
the co-respondent by election, as the road authority, in relation to works and
monetary contributions given that only a preliminary approval is sought and that a
concern about this particular intersection was not raised in cross-examination of the
traffic engineers for either the appellant or co-respondent by election.190
[185] Mr Trevilyan made the point that the impact on local roads and other intersections
does not necessarily stop when development generated traffic arrives at the State-
controlled road system and that the successful operation of busier intersections does
not ensure that there is no undue impact on minor intersections, which have less
infrastructure. Whilst these points have some validity, it seems to me that sufficient
work has been done for the preliminary approval stage, given that the terms of any
preliminary approval should be such that further analysis is required at the
development permit stage.
(c) Scope for the Upgrades
[186] The scope for constructing the road improvements, to an appropriate design, was a
matter of debate.
[187] The road upgrades contemplated by the infrastructure agreement have already been
referred to. The appellant also volunteered that it would accept a condition that all
road upgrades conditioned to be undertaken by it, be constructed to a Q100 flood
immunity standard.
187 T9-74.
188 T9-74.
189 T9-93 where the State-controlled roads are identified.
190 Mr Williams’ evidence was that, with the proposed network improvements, the State-controlled road
network would adequately cater for development traffic. He also referred to the financial
contribution obligation (Ex 33 pg 7 para 21). No point was put to him about this particular
intersection on the State-controlled road network.
-- 62 of 89 --
63
[188] It has already been noted that the infrastructure agreement does not necessarily
require the appellant to undertake the upgrading of Beck Drive and that an
upgrading of that road to a four lane sub-arterial road will occur at some time in the
future in any event. The debate about the scope for that upgrading proceeded on the
assumption that it is provided by the appellant in consequence of the development.
[189] Mr Douglas had concept drawings prepared of intersection layouts affecting the
SIDRA layouts to demonstrate the feasibility of upgrading Beck Drive without
resumption of private property. At trial further drawings were produced.191 The
evidence demonstrated that there are a number of constraints, relating to various
“pinch points” along the road reserve associated with the upgrading of Beck Drive
to a 4 lane Type B sub-arterial road. The consequence is that, absent the consent of
land owners of adjacent land, compromises would be required in relation to the
Council’s standard drawing design for a Type B sub-arterial road. This includes that
services will need to be built over, or a pathway in the verge compromised.192 It was
submitted, for the respondent, that this compromise approach is inappropriate.
[190] Mr Trevilyan’s objection to the proposal, in this respect, was largely a matter of
principle. Whilst, as Mr Douglas pointed out,193 it is not uncommon for roads and
intersections to be provided, including by the Council itself, in forms which
represent a variation or compromise of standard design drawings, Mr Trevilyan
considered that development of a greenfield site should occur where such
compromises are not necessary.194 Whilst I appreciate his point, which perhaps
serves to further underscore that the subject site is not one which sits at ease with
the existing and planned infrastructure, I also take Mr Douglas’ point that the road
network is not within an entirely greenfield area195 and there is need for some level
of compromise in the road upgradings, including in Beck Drive which will have to
be upgraded in any event. The need for some compromise would not cause me to
refuse the application if approval was otherwise justified.
[191] Mr Trevilyan identified two potential safety concerns. One relates to the reverse
curve where Laudberg Road turns into Sterritt Road. That is discussed later. The
other relates to the upgrading of the roundabout at the intersection of Beck Drive
and Gouldian Avenue, which, as shown on a preliminary design, was criticised by
Mr Trevilyan as creating safety issues because:
(i) A northbound vehicle would be able to travel through the roundabout
without deviation, and
(ii) Cyclists are not provided for on the through carriageway on the eastern
side.
191 Ex 68.
192 T9-5.
193 T9-72.
194 T10-25, 26.
195 T9-72.
-- 63 of 89 --
64
[192] Those criticisms of the preliminary design were not explored in cross-examination
of Mr Douglas (who gave evidence prior to Mr Trevilyan). In the course of cross-
examination Mr Trevilyan acknowledged that Beck Drive will need to be upgraded
to 4 lanes in the future in any event and so a solution would have to be found to
achieve that. He acknowledged that, although ‘very difficult’ in his view, it is, in an
engineering sense, possible.196 That included overcoming the issues with Goudlian
Avenue, although it might require some additional land. It is however, something
that, in the circumstances, will have to be confronted in any event given the
inevitable need to upgrade the road.197 In the circumstances it does not call for a
refusal of this application.
[193] The offer to provide the road upgradings to a Q100 flood immunity standard is
discussed later in the context of ground/matters in support of approval.
(d) The Reverse Curve
[194] The remaining safety issue relates to the reverse curve at the junction of Laudberg
Road and Sterritt Road. Currently there are two right angled turns where the roads
meet. That is not appropriate in the context of the likely volumes from the proposed
development. The proposal is for it to be replaced with a reverse curve. A reverse
curve is a section of road consisting of two different curves turning in opposite
directions. There was debate about whether the development access would still be
inappropriate in the circumstances.
[195] Reverse curves are not an unknown feature of road systems and are specifically
dealt with in Austroads, to which the traffic engineers had recourse. They are not
however, a desirable design response. Indeed Austroads states “reverse curves
should be avoided wherever possible” before going on to acknowledge that “there
are situations where designers have no choice but to use them for example, in hilly
or mountainous terrain or where physical constrains that influence the alignment are
present”.
[196] Here, the use of a reverse curve is only a necessity if it is assumed that the
development must proceed and obtain its access from the local road network along
the identified route. On that assumption, it is necessary to address the unsafe
interplay between the two roads in question before addition of the significant
additional volumes associated with the development. Within the limits of the road
reserve, the only identified option is the reverse curve. The first point made by Mr
Trevilyan is that this is not so much a case of having to design a road around
physical constraints as it is a case of observing that the road reserve corridor does
not measure up to one that would be expected to service urban development such as
is proposed.
196 T12-26.
197 T12-27.
-- 64 of 89 --
65
[197] There was also some debate about the adequacy of what could be achieved if a
reverse curve solution were accepted. Mr Douglas did a concept design to indicate
what could be achieved, assuming an operating speed environment of 70km/hr and
advisory signs at each end of the reverse curve of 60km/hr. Mr Trevilyan took issue
with the design. He pointed to that part of Austroads which provides:
“Desirably, reverse curves should not be used unless there is
sufficient distance between the curves to introduce full
superelevation of the two curves”.
[198] For an operating speed of 70km per hour the length of superelevation development
from normal cross fall to required superelevation rounds up to 55m. Two lots of
55m is required because there are two superelevations. The debate between Mr
Trevilyan and Mr Douglas was as to whether the whole of that 110m is to be
provided in the straight between the two curves. Mr Trevilyan acknowledged that
there was nothing in Austroads, other than the above quote, commencing with the
word “desirably” which mandated his approach. He also acknowledged that his
concerns could be met if the operating speed could be reduced. He thought that
would be problematic, because the natural speed on the straight approach would
lead to higher speed. He did not however, seem strong on his view that the proposal
was unacceptable from a safety perspective. He described the proposal, if speeds
were to be reduced, as falling below a “fuzzing line” of acceptability in what he
described as a “grey area”.198 Mr Douglas took the view that advisory signs of 50 or
55km per hour for the reverse curve would not preclude higher speed signs
otherwise, there being nothing unusual about such a speed zoning arrangement.
[199] The final decisions about the speed environment will be made by the Council, as the
road authority. The evidence satisfies me that whilst the need to employ a reverse
curve solution means that the road network leading to/from the subject site is less
than desirable to service the proposed development, a reverse curve would not be an
unacceptable solution to the difficulty of traffic generated by the development
having to negotiate the junction of those two roads.
(e) Conclusion on Traffic
[200] For the reasons given I have concluded that:
o The development is unlikely to have a detrimental effect on the
capacity of the State-controlled road network.
o The development, once completed will, subject to the various road
upgrades, be serviced by an external local road network with sufficient
capacity.
198 T10-31.
-- 65 of 89 --
66
o It has not been demonstrated that Stage 1 of the proposal, to 1000 lots,
could appropriately proceed in advance of the Beck Drive upgrade.
o Any preliminary approval ought be on terms that requires further
modelling (and any consequential upgrades) at the development permit
stage.
o Sufficient work has been done with respect to the likely impact of the
proposal on the performance of intersections to support a preliminary
approval on terms that would require further analysis at the
development permit stage.
o Whilst achieving the upgrades would not be without difficulty and
would require some compromise of design standards, the difficulties do
not appear to be insurmountable, nor is the need for some compromise
(leaving the reverse curve to one side) unduly disturbing.
o That the development traffic would need to use a route with a reverse
curve is less than desirable, but not unacceptable in the circumstances.
[201] Whilst I take Mr Trevilyan’s point to the effect that the need for some compromise
in design standards and the use of a road system with a reverse curve is
symptomatic that the site is not an ideal greenfield site as one might expect where
the road network has been planned with a development in mind, the proposed access
route, subject to upgrades, is not inappropriate for the purposes of the grant of a
preliminary approval.
(viii) Flooding
[202] The proposal is for the development to have appropriate flood immunity and for the
external road upgrades to be to a Q100 standard. The respondent did not rely on
flooding issues as a basis for refusal of the application.
[203] Insofar as the impacts of the development are concerned, it was ultimately agreed
that suitable on site detention could be provided through detailed design and further
refinement of the layout to ensure no adverse downstream flooding impacts
occur.199 The appellant would accept a no worsening condition.
[204] Insofar as the access routes are concerned, Mr Collins considered it desirable for
critical access/egress routes to have a Q100 flood immunity and that is what is now
proposed. In his view, the required upgrades could be conditioned to ensure that the
final design did not result in adverse impact on other properties. In relation to
Laudberg Rd, Sterritt Rd and Allambie Lane to its intersection with Beck Drive,
upgrading to Q100 will involve the use of box culverts and bridges the particulars of
which had been considered by Mr Gould.200 Modelling of that showed some afflux,
199 Ex 14 pg 4 para 9.
200 T8-32 to 34.
-- 66 of 89 --
67
with which Mr Clark took issue, but he accepted that there would be a solution. His
reservation was as to the practicalities of a solution, once presented, from a civil
engineering perspective given considerations such as the width of the road reserve.
[205] The road reserve in Allambie Lane is very wide and can readily accommodate
substantial table drains and bridges.201 Sterritt and Laudberg roads have a narrower
reserve but there is no sufficient reason for undue concerns about them. Mr
McAnany was of the opinion that the works in Laudberg Road (which would
include bridges and culverts) could not all fit within the road reserve. Mr Gould (the
appellant’s civil engineer) agreed that there are a limited number of adjoining
properties in Laudberg Road that would require their driveways to be reconstructed
to the elevation of Laudberg Road.202 That is not however, necessarily an
insurmountable obstacle.
[206] The part of the upgrades which Mr Gould did have a concern about was Beck Drive
which, in his view (which I accept), cannot practically achieve a Q100 standard
because of the depth of flood over that road.203 That problem can however, be
overcome by raising a section of Allambie Lane between Beck Drive and Riverway
Drive (the latter of which is already at Q100) to achieve a flood free access.204 Mr
Gould’s evidence, which I accept, is that that involves a minor lift and is not a
significant engineering undertaking.205 Mr Collins had not modelled the impact of
that raising, but it would appear to be unlikely to cause insurmountable problems
given the minor nature of the work required.
[207] I do not consider that there are any flooding issues in relation to the development or
the upgrading of the external roads which warrant a refusal of the application for a
preliminary approval.
(ix) Stormwater Quality
[208] The respondent does not rely on stormwater quality as a reason for refusal. It is
common ground that there is adequate space for water quality measures to meet
relevant standards and objectives. In those circumstances it is unnecessary for me to
descend further into the detail of the evidence. The site is affected by severe
erosion. This is discussed later as it was a matter which the appellant sought to turn
to its advantage by an offer to undertake works to stabilise and rehabilitate the
affected areas.
(x) Uncertainty
[209] It was submitted, for the respondent, that a level of uncertainty surrounds the
proposal. Insofar as that affects the assessment of the issues relating to the material
201 Ex 38 p 48.
202 T8-34.
203 T8-39.
204 T4-5, 6.
205 T8-10.
-- 67 of 89 --
68
change of use it has been dealt with in the discussion of the various issues. There
was also reference to a level of uncertainty arising in relation to the text of the
proposed variations and in relation to their application in the context of the changed
plans. As I have observed, there would be a need to revisit the variations in the
event that the Court were to deliver reasons indicating an intention to approve the
application.
Grounds/Matters in Favour of Approval
[210] In opening the appellant’s case Mr Gore QC said that this is a “grounds case”.206 In
the written submissions delivered at the conclusion of the case it was conceded that,
if the Nerinda point was put to one side, conflict with the TPS 2003 necessarily
follows, at least as regards the Rural Planning Area Code and the Urban Growth
Boundaries Code. I have already dealt with the nature and extent of the conflict.
[211] The appellant’s case with respect to grounds to justify approval and/or matters to
take into account in favour of approval narrowed and/or was given new focus in the
course of submissions. The written submissions on behalf of the appellant set out 18
grounds. In the course of oral submissions however, the Court was informed that
some of those were not pressed. The rest were ranked, in order, as of primary,
secondary or marginal importance. The appellant did not seek to categorise the
grounds by reference to whether they fell within the second or third limbs of the
Weightman approach, but that is unnecessary. The importance of the ground
depends of what it is rather than where it falls in the Weightman approach.207
[212] The primary grounds are as follows (adopting the paragraph numbering from the
appellant’s submissions):
(a) the site is unsuitable for agriculture, and has low suitability for grazing;
(b) given the sodic soils issue, it is unlikely that the cost of remediation
could be borne by a grazing operation, whereas the appellant is
prepared to fund such measures as part of the proposed development,
with consequential benefits in the public interest, as the soils are
currently carried down stream with detrimental effects;
(c) there is a town planning, community and economic need for the
proposed development,
(g) approval of the proposed development would provide an opportunity
for a place of refuge to be developed, particularly in respect of flood
inundation, for residents of the proposed development and also those
residents of the Upper Ross Corridor;
206 T1-18.
207 Lockyer Valley Regional Council v Westlink Pty Ltd [2013] 2 Qd R 303 at 323.
-- 68 of 89 --
69
(h) the proposed development is protected, unlike other land in the
Council’s local government area, from flood, storm tide inundation and
the effects of a dam break scenario;
(p) approval of the proposed development will result in the restoration and
protection of waterway corridors on the land;
(q) approval of the proposed development would result in the dedication of
land of significant ecological value of significant size;
[213] The secondary grounds are as follows:
(d) the proposed development would contribute to housing affordability;
(f) approval of the proposed development would enhance residential
choice and diversity;
[214] The marginal grounds are as follows:
(e) approval of the proposed development would contribute to “self-
containment” in the Upper Ross catchment;
(i) approval of the proposed development would allow residents to “age in
place”;
(j) approval of the proposed development will generate significant
employment;
(l) the proposed development provides an opportunity to masterplan a
significant development thereby ensuring the orderly and efficient
delivery of infrastructure, services and facilities;
(o) approval of the proposed development will adopt a number of
sustainability measures;
[215] The appellant’s case with respect to the development’s promotion of the public
interest was ultimately reduced to the following summary:
“The proposal will convert the land from its presently low or non-
existent potential for rural uses into land that is well suited for and
will be well utilized for residential and ancillary purposes, for the
benefit of much large number of community members than currently
benefits from the land’s zoning and potential uses, in association
with other benefits that would probably or certainly not be enjoyed if
the status quo where maintained:
(a) the remediation of a significant and worsening soil
erosion and dispersion problem;
-- 69 of 89 --
70
(b) the provision of an opportunity for a place or refuge for
other members of the community in time of flood
inundation;
(c) the restoration and protection of waterway corridors on
the land;
(d) the dedication for public purposes of land of significant
ecological value and of significant size;
(e) the provision of residential choice and diversity in a
competitive market for many decades.”
[216] The above raises a number of issues for consideration.
(i) Need
[217] Whilst only a preliminary approval is currently sought for the material change of
use, it is nevertheless appropriate to consider whether a need has been established to
support an approval of the application in order to facilitate (subject to further
approvals), the provision of the development it proposes within a reasonable
planning horizon. It is not in dispute that Townsville will require further
development, including further residential development. The central question is
whether a need has been established to support an approval for such development to
occur on the subject site, contrary to the planning documents, rather than in the
locations provided for pursuant to those documents.208
[218] It has already been observed that the current planning documents proceed on the
basis that there is already sufficient land set aside for greenfield development. In
particular CP 2014 asserts that the plan allocated sufficient land for housing,
business and community uses, sufficient to meet Townsville’s need for at least 25
years209 and, more specifically, that the planning scheme designates sufficient land
supply for future greenfield development well beyond the requirements of the next
few decades.210 Consistently with that, both CP 2014 and NQRP adopt a planning
strategy of directing development to the areas already set aside. The proposal is in
obvious conflict with that strategy.
[219] The evidence of the need experts did not establish that there has been any serious or
substantial erosion in the factual basis underlying the planning strategy such as to
call for an approval to facilitate (subject to further approvals) a large additional
master planned development on the subject site. The evidence revealed that
population growth has slowed in Townsville in recent years, such that the
projections upon which the CP 2014 was based have proved to be “more
208 See Gold Coast City Council v K&K (GC) Pty Ltd (2019) 239 LGERA 409 at 47-48.
209 s 3.3.1(1).
210 s 3.2.5.
-- 70 of 89 --
71
aspirational about the growth” than had been planned for in the planning scheme.211
Similarly, there has been a reduction in the rate of sales of vacant land. The
supplementary need JER contained population projections on a ‘low’, ‘medium’ and
‘high’ growth basis, which took account of official projections prepared for 2018. In
his trial report Mr Duane reported that since 2018, ABS resident population
projections would indicate that Townsville’s population growth has slowed and that
even the low series projections for 2021 might not be reached. Whilst the experts
agreed that north Queensland economies can fluctuate rapidly in terms of major
projects and consequently population and dwelling growth,212 there is nothing to
suggest a change in circumstances which would trigger the need to provide for the
development of more land, beyond that provided for in the planning scheme, for
residential development.
[220] There is a very substantial land bank for the future supply of residential lots. In the
supplementary need JER the experts agreed that there would be about 35,000
dwellings available within the market and potentially up to 40,000-45,000 taking
into account other broadhectare land.213 Having regard to the population projections
(ie the ones that may not be met for 2021), it was agreed that Townsville has a
current residential land supply in excess of the planning scheme’s 25 years on the
basis of the medium projection of population growth.214 Mr Duane reported that “at
a broad level, therefore, the Townsville market has a level of supply in keeping with
most major metropolitan areas based on medium series projection, but is at the
lower end for a high population base scenario.”
[221] Not only does the planning scheme provide for the supply of future residential
development, it expressly acknowledges the need to keep its strategy under review.
Whilst stating that the scheme sets out the Council’s intention for future
development over the next 25 years, it also says that it will be reviewed
periodically, in accordance with the Act, to ensure that it “responds appropriately to
the changes of the community at a local, regional and State level”.215 More
specifically it states that the Council will monitor the supply of new land for
residential development to ensure at least 10 years land supply is available and to
prevent land supply placing any pressure on housing affordability.216
[222] Mr Duane argued that there may be a need to provide further land because, by the
time the Council reviews the planning scheme, the supply of land might have fallen
significantly below 20 years of supply. He pointed to the significant lead times for
major new released areas in order to opine that to allow the stock of available land
to decline until it is potentially replenished on a 10 year review is not appropriate,
from an economic point of view to ensure a healthy and functional residential
211 T6-16.
212 Ex 24 pg 23.
213 Ex 24 para 45.
214 Ex 24 para 47.
215 s 1.1.
216 s 3.3.2.2.
-- 71 of 89 --
72
market in Townsville. He said that within the next 10 year period, as supply is used
up, there will be a need to appropriately plan for further supply to make sure that
there is a 25 year horizon going forward.217 That is not a proposition which has
significant application in this instance.
[223] The review of the planning scheme is due in 2024, much sooner than 10 years from
now and as Mr Duane acknowledged,218 there is no reason to fear that, by 2024,
there will be significantly less than 20 years supply. I also accept the evidence of Mr
Coghlin in paragraph 57 of the supplementary need JER as follows:
“57. GC notes that Townsville has a current residential land supply
of 25 years under a medium demand scenario. Therefore:
a. There is sufficient residential supply throughout Council’s 25
year planning horizon.
b. The existing land supply will extend well beyond the typical
life of the planning scheme, therefore giving Council ample
time to designate additional land for residential development
well ahead of need, if required.
c. Supply is broadly-based. It currently includes 33 residential
estates with more than 29,000 available lots (Table 4). In
addition, there are proposals for a further 11 residential estates
containing more than 5,000 lots (Table 5).
d. In GC’s opinion, the current land supply is so substantial that
it is highly unlikely to compromise a healthy functioning
market for the foreseeable future.”
[224] There being no convincing case with respect to the need for a greater quantum of
land to be set aside now for a new master planned residential development, the
appellant’s case, with respect to need, focused more on qualitative matters, in the
sense of what the proposal would add, for the community benefit, over and above
simply more land for development.
[225] Paragraph (f) of the appellant’s secondary grounds relates to the enhancement of
choice and diversity. It was argued that the proposal would increase choice in the
residential market in circumstances where there is a concentration of ownership of
the future supply of residential land and where much of the future growth is
expected to occur in one development, namely Elliot Springs, which is located
15kms south-west of the CBD and is planned to cater for over 10,000 lots and over
26,000 people by completion around 2057.
217 T6-22.
218 T6-24.
-- 72 of 89 --
73
[226] Mr Duane put forward a hypothetical scenario in which, depending upon the
demand for residential lots and the number supplied by Elliot Springs (assumed at
up to 300 lots per year) over the next decade, the supply in other estates might be
consumed relatively quickly, such that, by 2031, 50% of the then future available
land supply would be in the one estate (Elliot Springs), something that he did not
regard as healthy. Given lead times for large estates he considered that longer term
planning (for additional land such as the subject site) should occur now. He would
regard having an additional large estate, such as that proposed, better and more than
two better still.219 In my view, Mr Coghlin persuasively answered Mr Duane’s
concerns in the following paragraphs of the supplementary JER:
68. GC disagrees with GND’s conclusions for the following reasons:
a) The forecast Elliot Springs rate of development is speculation
based on an estimated completion date almost 50 years away,
and an assumed constant rate of lot releases. Lot development
is more likely to be based on overall demand and levels of
competition at any given time, both of which are likely to
fluctuate. The actual lot production each year is likely to be
determined mainly by level of demand.
b) In any event, there is an estimated 34,223 lots currently
available (Table 8). Assuming absorption of 1,400 lots a year,
there is some 24 years of existing supply. It is therefore clear
that Council will have ample opportunity at a more appropriate
future time to address any required changes to residential land
supply in the long term.
71. GC notes that excluding Elliot Springs (Eastern Rural), in 2018
there was an estimated 23,653 lots available (Table 8). Even under
the assumptions used by GND of absorption of around 1,100 lots a
year outside of Elliot Springs (medium series forecast), as at 2018
there was around 21 years of supply outside of Elliot Springs, which
is well beyond the typical life of a planning scheme.
73. GC concludes that in view of the number and variety of
residential land developments and developers outside of Elliot
Springs, and the number of proposed residential estates outside of
Elliot Springs, residential supply in the Townsville region does not
risk being too concentrated in a single development.
[227] Of relevance to the point made by Mr Coghlin in paragraph 68(b) is the fact that the
next review of the planning scheme is now just a few years away. That is of
significance because Mr Duane’s concern was about what might occur after 2031 in
relation to choice if no further supply is made available as a result of any review of
219 T6-29.
-- 73 of 89 --
74
the Council.220 He clarified that his preference for planning to start ‘now’, is to be
understood as within the next few years, such that a review in 2024 that resulted in
immediate action would be within that realm.221
[228] Insofar as the point made by Mr Coghlin in paragraph 73 is concerned, the evidence
shows222 that the current future supply of lots comes from a range of growth
districts223 and is composed of a number of estates, offering a range of lot sizes,
brought to the market by a range of developers at a range of price points.
[229] For the above reasons, I am not persuaded that there is a need to approve the subject
application in order to provide, at this point in time, for the future development of
an additional master planned community on the basis of enhancing choice and
diversity.
[230] It was also contended that the development is needed to make a meaningful
contribution to housing affordability in Townsville which is the subject of
paragraph (d) of the appellant’s secondary grounds. It was pointed out, for the
appellant, that Townsville is rated as “seriously unaffordable” by international
standards. As Mr Coghlin pointed out however, most Australian cities are rated as
“severely unaffordable” and Townsville remains one of the most affordable cities
within Australia, being third only to Gladstone and Rockhampton as the most
affordable among 24 surveyed Australian cities. Indeed the evidence is of house
prices in Townsville having been in decline since 2011. More specifically, the
Upper Ross Corridor has become more affordable.224 That does not mean that
housing affordability is not a matter to be concerned about, but it puts the issue in
perspective.
[231] As Mr Coghlin pointed out, there is no sufficient basis to conclude that any
affordability difficulty in relation to land in Townsville is the result of a lack of
supply, since there is an existing abundant residential land supply. The addition of
yet further supply is unlikely to have a significant impact on affordability.225 There
is no realistic likelihood of a shortage of available lots within any reasonable
planning horizon such as to provoke the need for more supply in the hope of
improving affordability.
[232] Mr Duane saw some potential benefit, in terms of affordability, in the provision of
competition and choice at a future point in time when supply is more reliant on
Elliot Springs. That harks back to his concern about the potential concentration of
supply on Elliot Springs, with which I have already dealt and rejected on the basis
of Mr Coghlin’s evidence to the effect that future supply is broad based and the
Council will have ample opportunity, at an appropriate future time, to address any
220 T6-28, 29.
221 T6-26.
222 Ex 24 table 4.
223 Ex 24 table 8.
224 Ex 24 paras 81, 82.
225 Ex 24 para 83.
-- 74 of 89 --
75
required changes to residential land supply, in the long term, such that there is no
need for concern about the healthy function of the market for the foreseeable future.
[233] Whilst that is sufficient to dispose of the issue it might also be observed that the
extent to which (if at all) the proposed development may provide price competition
in the future, so as to improve affordability, is unknown. Whilst choice may often
provoke competition, the extent of that competition and its potential effect on the
price of lots and so on affordability may obviously be affected by several factors. It
might be affected by the development costs of the lots in respect of a proposal
which, as has been observed, is proposing to assume significant obligations
including, but not limited to, with respect to the provision of infrastructure and the
remediation of erosion. It will obviously depend on market circumstances at the
time and decisions about how lots within the development, which Mr Vassallo
enthused provided the opportunity to set a new standard,226 are positioned in that
market.
[234] For the reasons given I do not consider that it has been demonstrated that there is
any significant need to approve the subject development application in order to
address housing affordability issues in Townsville.
[235] It was submitted that there is a need for the proposed development in circumstances
where the proposal is appropriately located in that it is “near” the urban growth
boundary pursuant to CP 2014 and would be accessible from various institutions
and facilities in the broader area. Even if that were accurate it would not, in my
view, add much to the need case. It relates more to the suitability of the site in the
event that development were permitted outside the areas planned for pursuant to the
planning documents. In any event the proposal would not represent a logical
extension of the urban growth boundary. In that regard I accept the evidence of Mr
Perkins to which I have already referred about the separation of the site from
existing urban development. Further, the argument seems to be one of justifying an
extension of urban sprawl, against which the planning documents set their face.
Further, Mr Coghlin pointed out that the site is more distant from community
infrastructure than most other new and approved residential estates,227 although it is
better placed than Elliot Springs.228 The development relies on providing facilities
in order to achieve an appropriate degree of self sufficiency. Indeed, the appellant
seeks to make a virtue of the proposal to provide facilities in an area which it
otherwise submits is lacking infrastructure.229
[236] It was contended that “more importantly”230 the proposal would, over time, not only
provide its own facilities, but would provide facilities that would assist in ensuring
that the Upper Ross Corridor is better provided for and more self-sufficient. That is
226 Ex 62 para 19.
227 Ex 23 pg 63.
228 T7-12.
229 Appellant’s submissions para 242.
230 Appellant’s submissions para 242.
-- 75 of 89 --
76
relevant to paragraph (e) of the appellant’s marginal grounds. There are a number of
things to note about that proposition.
[237] Firstly, there are some retail and other facilities, including education facilities in the
broader area,231 the site’s proximity to which the appellant otherwise relies on to
assert the suitability of its location.
[238] Secondly, in the first need JER, the experts agreed that, absent approval of the full
residential development, there is no need for the other uses.232
[239] Thirdly, the evidence about need for non-residential facilities is that found in the
second supplementary JER, which speaks of how much residential development
must occur within the development itself in order to justify the provision of those
facilities. The focus on the non-residential uses needing to be justified by
development on the subject site (rather than in the Upper Ross Corridor more
generally) is understandable given that, as Mr Duane agreed, the site is tantamount
to one sitting at the end of a very large cul-de-sac, such that the trade area for any
retail facilities on the subject site would be largely confined to the site itself.233
[240] Fourthly, the evidence demonstrates that it will take a long time for residential
development on the subject site to justify substantial retail and education
facilities.234 In the meantime the development would, far from assisting to make the
broader area more self-sufficient, simply be adding lots at a location remote from
facilities. As Mr Perkins said in the planning JER “early residents will be left in an
isolated, under-serviced and car-dependent fringe location, contrary to the goal of
all contemporary urban planning in Australia”.235
[241] Insofar as the last point is concerned, the need experts agreed, in the second
supplementary JER as follows:
“Retail Facilities
15. A convenience centre anchored by a 500sq.m convenience store with five
to six speciality shops requires around 3,000 – 3,500 persons. This would
be supportable around year ten of the development.
16. A full-line supermarket based centre of around 6,000 sq.m with a range of
other uses usually requires around 8,000 – 9,000 persons. This would be
supportable around year 23 of the development.
231 Ex 23 para 103.
232 Ex 23 pg 11 para 12.
233 T6-33.
234 being the only non-residential facilities about which there was any specific evidence about
need/timing.
235 Ex 34 para 98.
-- 76 of 89 --
77
17. Over time as the population increases the centre could be developed to a
larger size and up to 10,000 – 12,000 sq.m of uses most likely as a guide by
around year 30.
Education Facilities
18. A childcare centre is typically provided at one place for every three
children aged 0 – 5 years of age. Consequently, assuming children 0 – 5
years of age up 10%-12.5% of the population around 300 children would
be required for the first childcare centre. This would be required by year 8-
10. After that time frame, childcare centres could be provided every six to
seven years.
19. Primary schools typically target around 400 – 500 students supporting
children aged 5 – 11 years. Assuming 10%-12.5% of the population is aged
5 – 11 years and increasing over time, the first primary school is likely to
be demanded by year 15.
20. It is understood that the typical threshold for a new high school in an urban
area is a population of around 1,200 students aged 11-17. Assuming
students aged 11 – 17 are 10%-12% of the development’s population, a
high school would be expected by around year 26 – 30.”
[242] It should be noted that, if anything, those predictions in terms of the years at which
those facilities would be supportable are optimistic, since they are based on an
occupancy rate of 3 residents per dwelling, which is an average for single lot
dwellings and is decreasing over time.236
[243] Accepting that evidence, those who would come to live in the first lots developed
would have to wait a decade before even a convenience centre was supportable.
Even Mr Duane acknowledged that it would be undesirable if nothing was provided
for 10 years.237 A full line supermarket would not be supportable for almost a
quarter of a century. Currently, the nearest full line supermarket is as Mr Coghlian
opined (and I agree), undesirably remote.238 The typical threshold for a primary
school is unlikely to be reached before 15 years, with the threshold for a high school
being more than a quarter of a century away, if it ever materialises.
[244] The reservation about whether the typical threshold for a secondary school will ever
be met is because the experts put that around 26-30 years which is when they
assume that 3300 to 4000 lots will have been developed, sold and occupied. Whilst
the initial proposal was for the development to achieve up to 5100 lots, the evidence
suggests that will no longer be achievable. There is uncertainty around what lesser
number could ultimately be provided.
236 T6-36, T7-5.
237 T6-42.
238 T7-5.
-- 77 of 89 --
78
[245] There is a decrease in likely lot yield as a consequence of changes to the proposal,
which have already been noted, particularly so as to address the ecological issues.
This has resulted in a decrease in the developable area and the need to set some of
that aside for things such as for example, buffers and storm water treatment areas
now proposed to be within those areas. As has already been noted in the context of
agriculture experts, there is also the possibility of greater buffers being required at
the development permit stage.
[246] There has been a loss of around a third of the developable area from 711 ha to 445
ha - a loss of some 265 ha. If the yield of 5100 lots from the 711 ha were accepted
and then reduced in proportion to the reduced developable area, the yield would be
around 3200 lots. That is however, a crude exercise. Mr Perkins carried out a more
detailed analysis of the latest plan to estimate that there would be approximately
250 ha of land for residential lots. That however, did not allow for the 50 m
ecological buffer or the 40 m agricultural buffer. Both parties, in submissions,
adopted an additional reduction to 200 ha to take account of that. That is a net area
(excluding roads). Assuming it is mostly used for 600m 2 lots (but some 450m 2 as
well) produces a yield of 3444 lots, which is towards the bottom end of the
threshold for a secondary school. It also suggests that the development will be
nearing completion before there is justification for a secondary school. Of course,
even those predictions may turn out to be optimistic if less land can be given over
for lots because the agriculture buffer needs to be wider or the infrastructure (eg
stormwater treatment devices) within the developable area larger.
[247] Fifthly, whilst it would be logical to suggest that a large master planned community
should include a range of uses so as to achieve an appropriate degree of self-
sufficiency, there has been no specific evidence about the need for the many other
urban uses contemplated by the application or when, if they are needed, they might
be realised.
[248] For the reasons discussed, I am not satisfied that there is a significant need for the
development application to be approved so as to provide facilities which would be
used by those in the broader area. The non-residential facilities, particularly the
retail and educational facilities of which there was some evidence, would primarily
serve the residents of the development itself and be reliant on a sufficient population
such that the facilities will be a long time coming with the consequence that, in the
meantime, the development would do more to locate people in a location remote
from facilities than it would to benefit the wider area.
[249] It was contended that there is a need for the proposed development in circumstances
where, unlike the subject site, much of the future land supply set aside for
development in Townsville is significantly flood affected. That is relevant to
paragraph (h) of the appellant’s primary grounds which is dealt with later and does
not significantly assist the appellant.
-- 78 of 89 --
79
[250] For the reasons given I do not consider that there is any significant need to support
approval of the subject development application. I do not consider that the appellant
has made out paragraph (c) of its primary grounds.
(ii) The Benefits of the Site and Development from a Flooding Perspective
[251] The development:
(i) would be substantially flood free and, indeed, have immunity to the
extent that it would be suitable for the provision of a refuge for use in
times of flood.239 It would also not be subject to cyclonic storm tide
and can be engineered to achieve immunity from dam failure.
(ii) could be carried out in a way that does not adversely impact on others,
from a flooding perspective.
(iii) can (subject to a qualification discussed below) be conditioned to
require the proposed external road upgradings to be of a Q100 standard,
so as to provide flood free access, at least to that standard.
[252] From the above the appellant advances two of its primary grounds/matters in favour
approval, namely ground (g) which relates to the benefit to be obtained from having
a flood refuge on the site and ground (h) which relates to the sites’ suitability, from
a flooding perspective, relative to other land in Townsville.
[253] Ground (h) however, is not a matter upon which I am prepared to place a lot of
weight. Even accepting that the site performs well relative to others, it does not
follow that land which has the benefit of approvals for urban development or which
the planning documents contemplate as being suitable for future development
cannot appropriately be developed for such purposes, with the result that the
proposed development is needed in order to, in effect, take their place in providing
for such development to occur. The evidence does not go so far as to establish that
the planning strategy, as to the provision for future development of this kind, is, in
any substantial way, unsound on the basis of insurmountable flooding constraints
affecting land planned to provide for future development of this kind. It may be
noted that the Council has not made amendments of relevance, in this regard,
following the 2019 flood. I accept that the relative suitability of the site, from a
flooding perspective, is a factor that would weigh in favour of concluding that the
subject site is an appropriate one on which to permit development of this kind in the
event that a location beyond those contemplated by the planning documents was
considered appropriate, but it is not something which weighs heavily in favour of
concluding that a location at odds with the planning strategy in the planning
documents is appropriate in the circumstances.
239 with the majority of lots being above the PMF – Ex 14 pg 3.
-- 79 of 89 --
80
[254] Ground (g) is worthy of some weight. It was a point of agreement, in the 3rd
stormwater JER that, subject to increased flood immunity on access roads and
suitable detailed design, the development would potentially provide significant
benefits to existing flood affected development east and north-east of the subject
site, as a regional evacuation centre for the suburbs of Kelso, Rasmussen and
Condon. As has been noted, it is proposed to have upgrades conditioned on any
approval of the subject application. Accordingly there is the potential for a benefit
of the kind referred to.
[255] There are at least two things to observe about this potential benefit. First, there is
some level of uncertainty about the proposed on-site emergency centre. Mr Collins,
in his appeal report, set out development requirements for adequate emergency
flood management on the site.240 They included an ambulance/fire station (and
functional helipad for helicopter evacuations). This contemplates a commitment
from State agencies. Further, they included a medical centre and a town centre
management structure with a full time on-site manager to act as an emergency flood
manager. In that regard however, there is no fixed timing for the development of the
town centre and the evidence of the need experts suggests that it will be quite some
time before other than modest retail facilities will be provided.
[256] Secondly, the disaster management plan for the Townsville City Council identifies
major evacuation routes. The Ring Road and Riverway Drive are already identified
as major evacuation routes, in times of flood, in this area.241 That is not to say that,
leaving to one side the uncertainty issues, the upgrading of the level of immunity of
roads linking Riverway Drive to the subject site (accepting, as I do, Mr Gould’s
evidence to the effect that upgrading the immunity of Beck Drive is not practicable),
would be of no benefit. It would increase the extent of the road network that has a
Q100 immunity and would provide an option (if and when an evacuation centre is
built) to take refuge on the subject site in a facility not otherwise provided in the
area, rather than use Riverway Drive to access Ring Road to the north (which lies in
an area of the floodplain where flooding - although not necessarily the road - is
generally worse) and from there to an unspecified destination. In assessing the
extent of that benefit however, it is relevant to bear in mind that we are not dealing
with an area that is currently bereft of an evacuation route.
[257] Whilst I accept that ground (g) provides some support to the application I have
ultimately come to the conclusion that it is not a matter, which considered by itself
or in combination with other matters in favour of approval, justifies approval of the
development application.
(iii) Sodic Soil/Erosion
[258] The site contains evidence of severe erosion associated with very sodic and highly
dispersive soils, that are widespread, but particularly concentrated in the north-east
240 Ex 36 pg 46.
241 T4-11.
-- 80 of 89 --
81
and south-east sections of the property. Whilst similar landscapes and soils occur
throughout the coastal plain,242 the extent of erosion on the subject site is
particularly great.243 Mr Thompson ranked it as 5 on a scale of 1 to 5.244 The
proposed master plan shows that most forms of development are included in eroded
areas.245
[259] The extent of the erosion would not prevent the development being realised but, as
Mr Sutherland and Mr Thompson agreed, erosion controls beyond those normally
employed in subdivisions would be required.246 Indeed as Mr Thompson pointed
out,247 extensive rehabilitation and remediation works would be required to
permanently stabilise the affected areas. Mr Sutherland and Mr Thompson gave
some evidence of what that is likely to entail.
[260] Mr Sutherland’s approach, as set out in his appeal report, involved updated soil
testing, mulching, the application of lime or gypsum and seedbed fertiliser,
oversowing a Rhodes Grass based seed mix and placing cane mulch. I accept Mr
Thompson’s evidence however, to the effect that this underestimates the extent of
works required to achieve rehabilitation and does not address the requirements for
severe gullies.248 As he attested (words in brackets added):249
Do you believe it [Mr Sutherland’s proposed solution] to be
feasible?---No I don’t.
Why not?---The level of sodic – okay, there are extensive areas of
these tough clay subsoils that are exposed at the land surface. Simply
dumping a bit of fertiliser and amendment on it, and throwing some
grass seeds on it, won’t really alter the fact that these are very, very
difficult clay soils to deal with. They already have a shape, which is
related to the nature of the sodic soils, that makes it very difficult to
get 5 relatively uniform conditions across the area. You can’t get
away with this, unless you do some degree of physical earthworks.
Now, I’m not talking about physical earthworks that are part of, you
know, a wetland environment, or part of a sedimentation [indistinct]
I’m talking about physical earthworks, to get the topsoil and
immediate subsoil of relatively uniform character, so whatever you
plant in there, whenever you plant it, will come up in a relatively
uniform rate. So that’s my concern with that. Now, that is solely to
do with the areas outside of the immediate eroding stream bed. Inside
the eroding stream bed, that’s an even more serious issue.
242 T12-8.
243 T12-8.
244 T12-8.
245 Ex 26 pg 2.
246 Ex 40 pg 6.
247 Ex 26 pg 2.
248 T12-15.
249 T10-70, 71.
-- 81 of 89 --
82
[261] It has already been noted that Mr Thompson envisaged works in the waterways
including armouring and reshaping. The conclusion is that the issue, whilst not
rendering the site incapable of development as proposed, would require extensive
and expensive works, which, as Mr Thompson point out, ought be done at the
outset.250 Mr Sutherland appeared to be somewhat flummoxed when questioned
about the timing and duration of the process.251 I prefer Mr Thompson’s view as to
when it should occur. Mr Thompson’s evidence was that the cost of rehabilitation
would run into “many millions of dollars”, and that he would not be surprised if it
ran to in the order of tens of millions of dollars.
[262] The appellant sought to turn this constraint into an advantage, in terms of obtaining
an approval. It pointed to the site’s relatively low value for grazing, its high level of
erosion, the fact that the erosion has been on-going and will, without intervention,
continue and the evidence as to the likely high cost of rehabilitation to suggest that
rehabilitation is unlikely to occur if the site remains in its rural state and that there is
a significant benefit to be obtained, in the form of rehabilitation, if the development
proceeds. That is reflected in its primary ground (b).
[263] It was contended, for the respondent, that the appellant ought be given no credit for
its willingness to take on the burden of rehabilitation in circumstances where the
evidence shows that the problem has materially worsened as a result of land
management during the appellant’s ownership of the site. The evidence does not
however, establish that the poor land management practices over that time were the
fault of the appellant (as opposed to a lessee, for example) or that it knew of the
problem and knowingly did nothing about it or what, if any, opportunity it had to
address that matter with the person or entity in occupation of the site. I am not
prepared to make a speculative finding about those matters and so, in the
circumstances, I have not discarded or discounted the potential benefit to be gained
from rehabilitation.
[264] I accept that the rehabilitation would be a benefit. In that regard however, there are
two things to note. First, whilst the appellant’s ground asserts that the soils are
“currently carried down stream with detrimental effects,” the evidence did not
establish the quantum of runoff or the extent of downstream detrimental effect to
date or the likely extent of effect if the erosion problem on the subject site is not
arrested. In the course of oral submissions Mr Gore QC accepted that the extent to
which the erosion creates an environmental problem is, on the evidence,
unknown.252
[265] Secondly, whilst it is reasonable to conclude that a rural use of this land is unlikely
to produce sufficient funds to carry out rehabilitation works costing tens of millions
of dollars as envisaged by Mr Thompson, that does not mean that the erosion
problem will necessarily continue, unabated, if the subject proposal does not
250 T12-10.
251 T10-57, 58, 59.
252 T14-32.
-- 82 of 89 --
83
proceed. Mr Thompson’s evidence, which I accept, was to the effect that, for a
fraction of the cost of rehabilitation, steps could be taken by way of responsible and
appropriate land management practices in the context of a rural use to stabilize (but
not rehabilitate) the site, so as to address the risk of further erosion. In this regard he
spoke of measures that would include decisions about stock, fencing off areas from
access by stock and utilising treatments of some areas of the kind recommended by
Mr Sutherland.253
[266] Mr Thompson put the likely cost of stabilizing the site, in the context of a rural use,
at something in the order of $500,000. He acknowledged that the expenditure would
not bring much of a return to a grazier,254 but would not discount the prospect of
that investment being made. Reference was made to the encouragement owners of
degraded sites get in terms of government grants and regulatory provisions, to
address such issues.255 I have previously noted the evidence of the ecologists as to
the increasing awareness of sustainable farming and grazing practices. I am not
prepared to discount, even on the balance of probabilities, the prospect of the land
being stabilised in the future by the application of more responsible land
management in the context of a rural use.
[267] The evidence falls short of persuading me to find that the site would be consigned to
unarrested erosion into the future in the absence of approval of the subject
development. I am similarly not prepared to find that the site should be regarded as
unsuitable for retention for rural purposes, because of the need to address the
erosion issue. Notwithstanding those observations however, I accept that the
rehabilitation of the site, from an erosion perspective, would be a beneficial
outcome of the proposed development. Ultimately however, I do not consider that it
is a benefit which, considered individually or in combination with other factors,
justifies approval of the application.
(iv) Other Grounds/Factors in Favour
[268] Paragraph (a) of the primary grounds is that the site is unsuitable for agriculture and
has low suitability for grazing. The site is neither good quality agricultural land nor
strategic cropping land256 and is low-potential grazing country.257 The site can
however be, and has been, used for grazing. It should also be recalled that, the
natural economic resources element under CP 2014 contains a specific outcome
which seeks to avoid fragmentation of rural land even when there is a lack of
viability. The site does not lack utility in its zoning under the planning documents.
Further, the purpose of the application of the rural zone (or rural planning scheme)
is not limited to the protection of rural productivity. It includes, for example,
matters of character and landscape value. That is reflected in the provisions of both
253 T12-10, 11, 14.
254 T12-16.
255 T12-9, 10.
256 Ex 26 pg 2.
257 T12-5.
-- 83 of 89 --
84
TPS 2003 and CP 2014 discussed earlier. The zoning/area designation also serves to
constrain the expansion of urban development. The allocation of the land to the
rural planning area pursuant to TPS 2003 is consistent with its location outside the
urban growth boundary. The zoning of the land under CP 2014 is consistent with its
strategy of containment of urban growth. These strategies serve a number of
purposes. For example, CP 2014 links the avoidance of urban development beyond
existing boundaries to avoiding increasing pressure on environmentally important
values.
[269] Paragraph (p) and (q) of the primary grounds relate to the restoration and protection
of the waterway corridors on the land and the proposed dedication of land. The
stabilisation and rehabilitation of the eroded areas have been discussed separately.
These aspects must be seen in the context of the ecological impact of the
development as a whole, which would, as has been observed, introduce new or
increased environmental threats. For the reasons previously given I do not consider
that it has been demonstrated that the proposal represents any significant overall
advantage for the environment. Indeed I have found that it would be preferable to
retain it as a rural holding.
[270] Paragraph (l) of the marginal grounds speaks of the advantage of master planning in
ensuring an orderly and efficient delivery of infrastructure, services and facilities.
Master planning does have that advantage, particularly in relation to the delivery of
infrastructure, services and facilities within the development. In this case the site is
not currently serviced by infrastructure. Issues in relation to the orderly and efficient
delivery of infrastructure to the site have been considered earlier in these reasons.
[271] Paragraph (i) of the marginal grounds relates to the intention to provide for facilities
to allow residents to “age in place”. That would be an appropriate aspect of a new
master planned community, but does not add much in terms of justifying approval
of such a community on the subject site.
[272] Paragraph (j) of the marginal grounds relates to the generation of employment. It
may be accepted that a substantial new master planned development as proposed
would generate employment, but the planning documents make provision for
employment generating development to occur elsewhere. The ground adds little if
anything.
[273] Paragraph (o) of the marginal grounds relates to sustainability measures. Other than
for the sites proximity to gas, electricity and water infrastructure, the things relied
on were the potential to establish a co-generation or tri-generation gas fired power
centre on the site and the development using its own water centre and recycling to
achieve greater water efficiency. Assuming (favourably to the appellant) that there
is a real prospect of these things being realised, they represent positive aspects of
the proposal that might not be achieved in other developments. It is something to
which I have had regard and which warrants some, but not great, weight.
-- 84 of 89 --
85
[274] Paragraph (r) asserts an absence of unacceptable amenity impacts. I have had regard
to my findings on amenity, to the extent they are favourable to the appellant, but
that does not alter my conclusion.
(v) Appellant’s Summary
[275] The summary of the appellant’s grounds/matters in favour of approval commences
with an introductory paragraph before five sub-paragraphs which refer to benefits
which it is said would flow from the proposal but would probably or certainly not
be enjoyed otherwise. Those five matters have already been discussed in these
reasons. The introductory paragraph:
(i) refers to the lands relative unsuitability for rural uses compared with its
suitability for the proposed purposes
(ii) asserts that the proposed purposes would be for the benefit of a much
larger number of community members than currently benefit from the
lands zoning and potential uses
[276] The alleged unsuitability of the land for rural purposes has been discussed and
rejected. The appellant’s proposal is based on only a minority of the site being
suitable for development and then only after works to deal with the erosion issue.
Part of the subject land may be physically suitable for development, but its
suitability from a planning perspective is the subject of consideration of the various
issues otherwise dealt with in these reasons.
[277] As to the number of community members to benefit from the use of the land, it
should not be thought that the benefit to the community, of the land’s retention for
rural use is limited to the small number of people who might occupy the land. I have
already dealt with the utility of the site in its zone. To the extent that the land, under
its rural use, contributes to the broader planning strategy for the city, its benefit to
the community is much broader.
Conclusion on Material Change of Use Component
[278] For the reasons given, the proposed material change of use finds itself starkly at
odds with the planning documents, particular by reason of its urban (non-rural)
nature. That is true of each of the planning documents. The Council’s current
planning scheme which, in my view, is deserving of considerable weight is against
the expansion of urban development into rural zoned land. There is no need, of any
significance, to justify approval of the subject development application. The current
planning scheme, and the planning strategy apparent from its provisions, was based
on the assumption that the document set aside sufficient land for housing,
businesses and community uses to meet Townsville’s needs for at least 25 years.
The evidence in this case shows that nothing has occurred which undermines that
assumption in any way that would call for this site to be approved for development
as proposed. That planning scheme also expressed an intention to monitor the
supply of new land for residential development. The next planning scheme review is
-- 85 of 89 --
86
due in but a few years time. There is ample opportunity for the Council to respond
to any possible future shortage that may appear on the horizon. There is no
sufficient basis otherwise to find that there is a need to support approval of the
application.
[279] The stark departure from the planning strategy with respect to land use coupled with
the absence of any significant need are ultimately the matters of most significance in
the context of this particular case and which point to refusal of the application for a
preliminary approval for a material change of use. There are grounds/matters in
favour of approval some of which I have accepted as having some substance. None
however, considered individually or collectively, alter the conclusion that the
proposed material change of use should be rejected. More specifically, there is
nothing which I regard as passing the conflict/grounds test in relation to the
conflicts I have found with TPS 2003 in relation to the nature of the use, even if
they were assumed to be the only conflicts. I also would conclude that the
application should be refused even if those provisions were a matter simply for
consideration in the assessment under s 3.5.5 prior to a discretionary decision (as
was submitted for the appellant). I have previously indicated the weight I place on
the later planning documents. There are also other matters of conflict/matters raised
against the proposal which I have discussed earlier and which serve to reinforce my
conclusion.
[280] This is a case where rural land was purchased on the speculative basis that it would
be “next in line” to be permitted to be developed, even though the provisions of the
planning scheme gave no basis for such an expectation. Subsequent attempts to
persuade the respondent to draw its new planning scheme in a way which favoured
those aspirations failed, as did attempts to persuade the respondent to support the
subject development application. The relevant planning documents have been
consistent in their treatment of the subject land as part of the relevant broader
planning strategy. The proposal flies in the face of that strategy and I have not been
persuaded that, in the circumstances, the proposed MCU for the site ought be
approved.
Approval in Part
[281] In the event that I was not minded to approve the development in whole (as I am
not) I was asked to consider approving it in part and, in particular, to approve Stage
1, subject to conditions which, amongst other things, would require the dedication
of open space areas. Relatively little argument was directed to it and it is difficult to
see the rationale for such an approval.
[282] Development of Stage 1 alone may reduce the extent of the introduced ecological
threat but it would still offend the planning strategy as to the location of uses
without contributing much in the way of the long term housing stock or facilities
which formed important components of the appellant’s ultimately unsuccessful case
on need and on the benefits of its master planned proposal. Without the balance of
-- 86 of 89 --
87
the development it would be, as Mr Perkins said, “an isolated community that had
no hope of any significant level of self-containment”,258 located contrary to the
planning documents whilst having an even weaker case with respect to need. I am
not minded to grant an approval in part.
The Variation Component
[283] The debate in the case was overwhelmingly focused on the material change of use
component. The variations attracted relatively little consideration.
[284] I have earlier outlined the general nature of the variations sought. In the appellant’s
written submissions it was said that, in addition to variations otherwise identified, it
was proposed to override the Urban Growth Boundaries Code. I have also noted that
there would be a need for revision of the variations in the event that the Court
delivered reasons indicating that the development application would be approved. It
is therefore not possible to deal with the variations in a comprehensive way.
[285] It has already been observed that the assessment of the proposed variations should
have regard to their consistency with other aspects of the planning scheme.259
Further the decision on the variations must not compromise the achievement of the
desired environmental outcomes for the planning scheme area. It was submitted, on
behalf of the respondent, that the variations sought by the appellant would result in
(or would have resulted in) inconsistency between those provisions and the DEO’s.
Had I decided to approve the MCU component of the application then I would have
had to have been satisfied that a decision to approve that component would not have
compromised the achievement of the DEO’s. To the extent that the variations do no
more than is appropriate to provide a framework for future applications for
approvals to implement the MCU, I would then have been minded to allow them
notwithstanding a level of conflict insofar as land use is concerned.
[286] I have previously noted that one of the proposed codes calls up codes from CP 2014
as at a certain date. They are, in that way, to be made applicable for the future of
what would be a large project with a lengthy development period. That brings the
obvious risk of applying codes that are, in the future, out of date or no longer
appropriate. I would have been loath to approve of such a variation. Mr Gore QC
accepted that common experience shows that codes and standards change over
time.260 He initially foreshadowed261 a change to the application, so that the codes
from time to time would apply, but did not proceed with that.262 Ultimately he
submitted that a condition nevertheless might be imposed by the Court which
required assessment against the new provisions (from time to time) even though that
is not what his client requests. He acknowledged that the failure to explore that in
258 T11-79.
259 s 3.5.5A(d).
260 T14-19.
261 T13-46.
262 T14-16.
-- 87 of 89 --
88
the course of the case made it difficult for him to press the submission.263 Had I
been otherwise minded to approve the MCU, I would have sought further assistance
from Counsel in relation to this aspect.
[287] One of the matters to have regard to in assessing the variations is the effect of the
variations on any right of a submitter for following applications, with particular
regard to the amount and detail of the supporting material for the current application
available to any submitters. It was contended, on behalf of the respondent, that
having regard to the length of time that has expired since public notification of the
application, the extent to which the proposal has evolved since that time, the
information not available to submitters and indeed still not available, the estimated
time for the delivery of the development, and the level of uncertainty as to the final
form of the development, the removal of submitters’ rights for subsequent approvals
is not justified.
[288] It is, of course, neither surprising nor unusual for there to be a degree of uncertainty
about the final form of development at the time a preliminary approval is given for a
master planned development such as is proposed here. That does not mean that
changes to levels of assessment, for the purposes of future applications, are
necessarily inappropriate, assuming that the scheme, as varied, would provide for an
appropriate assessment of future applications. That proviso means that a decision
about the levels of assessment ought not be made until there is clarity about the
issue with the codes referred to above and the changes otherwise to the requested
variations.
[289] Whilst I appreciate that the application has been on foot for a long time, the general
nature of the proposal has remained the same, with changes largely made in an
attempt to mitigate concerns. The range of potential uses and the way the master
planning process is proposed to work have not changed. Had I been satisfied that
the MCU ought be given a preliminary approval then I would have been prepared to
entertain changes of levels of assessment appropriate to reflect the fact that the
suitability of the site for the proposed master planned community had been
determined sufficiently to grant that approval.
[290] The range of uses for which a change to the level of assessment has been requested
is broad, but that is not unexpected in relation to a substantial master planned
community proposed in an otherwise rural area and which would need to achieve a
level of self-sufficiency by the provision, within the development, of a range of
uses. The need experts agreed that if there is a need for the residential development
then there will be a need for other components of the master plan.264
[291] The extent to which the respondent takes issue with the proposed changes to the
levels of assessment for that range of uses is unclear. It would seem unlikely, for
example, that there would be opposition, should the MCU component be granted, to
263 T14-21.
264 Ex 23 pg 11 para 12.
-- 88 of 89 --
89
the variation requested so that a detached house in a residential precinct is self
assessable, rather than impact assessable. Had I approved the MCU component I
would, before finally determining the variations, have sought further assistance
from Counsel for the respondent in relation to the extent to which the proposed
changes to the levels of assessment were opposed and the reasons for opposition to
the specific variations sought. It is unnecessary for me to trouble Counsel further in
relation to the variations however, because, having determined to refuse the material
change of use component, I am required by s 3.5.14A(2) to refuse the variation
component as well.
Conclusion
[292] For the reasons given, the appeal is dismissed.
-- 89 of 89 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2021/020