Apex Outdoor Pty Ltd v Cross River Rail Delivery Authority (No 2) [2021] QLC 10
LAND COURT OF QUEENSLAND
CITATION: Apex Outdoor Pty Ltd v Cross River Rail Delivery Authority
(No 2) [2021] QLC 10
PARTIES: Apex Outdoor Pty Ltd
ACN 155 560 535
(applicant)
v
Cross River Rail Delivery Authority
(respondent)
FILE NO: AQL123-20
PROCEEDING: Application for costs
DELIVERED ON: 17 March 2021
DELIVERED AT: Brisbane
HEARD ON: Submissions closed 25 February 2021
HEARD AT: Heard on the papers
PRESIDENT: FY Kingham
ORDER: 1. The costs of this application be reserved until the
claim is determined.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – where the Court refused
an application that would prevent the respondent from calling
evidence from a nominated expert – where the respondent
sought costs under s 27A of the Land Court Act 2000 on
grounds that it successfully resisted the application – where
the applicant submitted that costs are governed by s 27 of the
Acquisition of Land Act 1967 – where the Court held that s
27 of the ALA provides an additional constraint on its
discretion to award costs – where the Court held that costs
should be reserved pending final determination of the claim
Acquisition of Land Act 1967 s 27, s 27(1), s 27(2)
Land Court Act 2000 s 27A
Haber v Chief Executive, Department of Main Roads (2005)
26 QLCR 49; [2005] QCA 123, applied.
-- 1 of 3 --
2
Lim v Moreton Bay Regional Council (No 2) [2019] QLC 22
McDonald v Department of Transport & Main Roads (No. 2)
[2016] QLC 8, cited.
APPEARANCES: Not applicable
[1] Apex Outdoor Pty Ltd claims compensation for the value of its loss of opportunity to
construct and operate a digital advertising billboard on leased land in the Brisbane
CBD, which was resumed for the Cross River Rail project.
[2] On 11 February this year, I refused an application by Apex for orders that would have
prevented Cross River Rail Delivery Authority from calling evidence from one of its
nominated experts.
[3] Cross River Rail seeks its costs of the application. Apex seeks an order that the costs
be reserved until the final determination of its compensation claim. It submitted that
the question of costs is governed by s 27 of the Acquisition of Land Act 1967 (ALA).
Apex argued it is common practice to reserve costs in interlocutory applications until
the claim is finalised, and that there are no special circumstances that would require
the Court to adopt a different approach for this application. The concern addressed by
the application was a legitimate one. Apex did not conduct the application in such a
way as to impose an unnecessary burden on Cross River Rail.
[4] Cross River Rail did not address s 27 of the ALA. It submitted costs should be
awarded under s 27A of the Land Court Act 2000 (LCA). On that basis, it should have
its costs because it successfully resisted the application and did not act unreasonably
in doing so.
[5] Section 27A of the LCA is as follows:
27A Costs
(1) Subject to the provisions of this or another Act to the contrary, the Land
Court may order costs for a proceeding in the court as it considers
appropriate.
(2) If the court does not make an order under subsection (1), each party to
the proceeding must bear the party’s own costs for the proceeding.
-- 2 of 3 --
3
[6] Apex argued s 27A of the LCA is excluded by s 27 of the ALA, which is “a provision
of …another Act to the contrary”.1 I accept that submission. 27A of the LCA
(formerly s 34 of that Act) provides the Court with an unfettered discretion as to costs.
Section 27 of the ALA imposes an additional constraint.2 As such, I consider it is a
provision to the contrary.
[7] Section 27 provides:
27 Costs
(1) Subject to this section, the costs of and incidental to the hearing and
determination by the Land Court of a claim for compensation under this
Act shall be in the discretion of that court.
(2) If the amount of compensation as determined is the amount finally
claimed by the claimant in the proceedings or is nearer to that amount
than to the amount of the valuation finally put in evidence by the
constructing authority, costs (if any) shall be awarded to the claimant,
otherwise costs (if any) shall be awarded to the constructing authority.
(3) Subsection (2) does not apply to any appeal in respect of the decision
of the Land Court or to costs awarded pursuant to section 24(3) or
section 25(3).
[8] The effect of s 27(2) is that, if the Court decides to award costs, it can only award
them to an applicant if its final claim is closer to the Court’s compensation award than
is the constructing authority’s valuation evidence.3 Otherwise costs must be awarded
to the constructing authority.
[9] That constraint favours Apex’s argument that costs should be reserved to the final
determination of its claim. The formula imposed by s 27(2) is necessarily directed to
an assessment after the claim is determined. It is arguable that the Court could order
costs of an interlocutory application under s 27(1). However, that was not argued by
Cross River Rail. It seems to me that the usual practice relied upon by Apex is
consistent with s 27 of the ALA. There is good sense in reserving the question of costs
to the final determination of the claim, and I so order.
1 Lim v Moreton Bay Regional Council (No 2) [2019] QLC 22 at [4]; see also McDonald v Department
of Transport & Main Roads (No. 2) [2016] QLC 8 at [9].
2 Haber v Chief Executive, Department of Main Roads [2005] QCA 123 at [17].
3 Ibid at [19].
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2021/010