Century Mining Limited v Department of Environment and Science [2021] QLC 3
LAND COURT OF QUEENSLAND
CITATION: Century Mining Limited v Department of Environment and
Science [2021] QLC 3
PARTIES: Century Mining Limited
ACN 006 670 300
(appellant)
v
Department of Environment and Science
(respondent)
FILE NO: EPA032-20
PROCEEDING: Appeal against internal review decision under the
Environmental Protection Act 1994
DELIVERED ON: 2 February 2021
DELIVERED AT: Brisbane
HEARD ON: Submissions closed 22 January 2021
HEARD AT: Heard on the papers
PRESIDENT: FY Kingham
ORDERS: 1. The appeal is allowed.
2. Pursuant to sections 530(1)(b) and 300 of the
Environmental Protection Act 1994 (Qld), the
Respondent’s decision dated 28 January 2020 that the
estimated rehabilitation cost (ERC) for
environmental authority EPML00888813 (EA) is
$230,465,718 (excluding GST) for the ERC period of
28 January 2020 to 27 January 2023 is set aside and
substituted with the following decision:
a. the required amount of ERC for the EA is
$183,916,150.06 (excluding GST); and
-- 1 of 7 --
2
b. the ERC period for the EA is 28 January 2020
to 27 January 2023.
CATCHWORDS: ENERGY AND RESOURCES – MINERALS –
ENVIRONMENTAL PROTECTION LEGISLATION –
where the miner appealed the estimated rehabilitation cost
fixed under s 300 the Environmental Protection Act 1994 –
where the Department of Environment and Science (and the
Court on appeal) must have regard to the guideline issued
under s 550 of the Environmental Protection Act 1994 when
calculating the estimated rehabilitation cost – where the
guideline provides an approved calculation methodology –
where the agreed ERC amount does not adopt the approved
calculation methodology in all respects – whether an ERC
amount not calculated strictly in accordance with the
approved calculation methodology complies with the
guideline – where the Court found that it did – where the
Court allowed the appeal and made the orders proposed by
the parties
Environmental Protection Act 1994 s 298, s 300, s 524, s
527, s 528, s 530, s 550
Department of Environment and Science, Guideline
ESR/2018/4425: Estimated rehabilitation cost under the
Environmental Protection Act 1994 (Version 2, 2018) 1.
Citigold Corporation Limited v Chief Executive,
Department of Environment and Heritage Protection (No.
5) [2016] QLC 62, cited
Origin Energy Electricity Ltd v Queensland Competition
Authority [2014] 1 Qd R 216, applied
Rathborne v Abel (1964) 38 ALJR 293, applied
APPEARANCES: Not applicable
[1] Miners in Queensland must provide security for mine rehabilitation by paying an
amount determined by the Department of Environment and Science as the estimated
rehabilitation cost (ERC) to fulfill their obligations.1
[2] Century Mine is an open cut zinc and lead mine in North-West Queensland. Mining
in the pit ceased in 2015. Since 2018, Century Mining Limited has been re-processing
tailings to recover zinc.
1 Environmental Protection Act 1994 Ch 5 Part 14 (‘EPA’).
-- 2 of 7 --
3
[3] DES decided the amount of the ERC for Century Mining’s activity was $230,465,718,
a decision it confirmed after internal review on 28 February 2020. Century Mining
contended the ERC should be $173,271,205.71 and appealed the review decision to
this Court.2
[4] The appeal is by way of rehearing, unaffected by the review decision.3 In exercising
this jurisdiction, the Court has the same powers as DES,4 and may confirm the review
decision, set it aside and substitute another decision, or set it aside and return the
matter to DES, with any directions the Court considers appropriate.5
[5] The parties have proposed consent orders which set aside the review decision and
substitute another decision for a different agreed amount. The Court stands in the
shoes of DES in this appeal and must consider whether to make the proposed ERC
decision.
[6] Early in the appeal, the parties settled a list of matters on which they agreed and the
real and substantial issues in dispute. This clarified and defined the dispute. During
the pre-hearing steps, a number of issues were resolved and only two key issues
remained.
[7] The first key issue relates to the design of the covers for the waste rock dump and the
tailings storage facility. The covers are required to prevent environmental harm
caused by seepage of potentially acid forming material contained in the waste rock
dumps and tailings storage facilities. Century Mining proposed a design for the covers
that, initially, DES did not accept.
[8] To assist the Court to resolve the issue about the design of the covers, the parties
proposed to call evidence from expert witnesses. I directed the appeal to Court
Managed Expert Evidence.6 The expert witnesses provided a Joint Expert Report for
the Court. In the JER they agreed that Century Mining’s cover design would meet the
company’s environmental obligations, provided it met certain design requirements.
2 Ibid s 524.
3 Ibid s 527.
4 Ibid s 528.
5 Ibid s 530.
6 Then governed by Practice Direction 3 of 2018 (since repealed and replaced by Practice Direction 6
of 2020).
-- 3 of 7 --
4
[9] The second key issue is about the calculation of the ERC amount. In making the ERC
decision, DES must have regard to the guideline issued under s 550 of the
Environmental Protection Act 1994.7 So must the Court in making the decision on
appeal.
[10] DES has published an ERC Guideline which “…describes the arrangements for
estimated rehabilitation cost under the Environmental Protection Act 1994.”8
Amongst other things, the guideline states an approved calculation methodology.
That is relevant because, in applying for an ERC decision, the applicant must state
the amount they consider to be an estimate of the total cost, for the ERC period, of its
rehabilitation and environmental obligations, “worked out in compliance with the
methodology decided by the chief executive.”9
[11] Relevantly for this appeal, the guideline contains the following statement in the
approved calculation methodology about estimates for facilities containing
potentially acid forming material:10
Criteria for calculating ERC—Calculate 100% rehabilitation liability
The total rehabilitation liability reflects the total potential costs to rehabilitate
significantly disturbed land, to achieve compliance with environmental conditions
of the EA and the EP Act. The total rehabilitation liability must:
…
• include the following activities and costs:
(f) estimates determined using the ‘high risk rate’ in the department’s ERC
calculator for mine waste structures (such as waste rock/overburden dumps,
tailings dams, heap leach pads) that:
• contain Potentially Acid Forming material or
• have observed contaminated seepage that is capable of causing
environmental harm
[12] The original and review decisions included ‘high risk rate’ estimates for the waste
rock dumps and tailings storage facilities in accordance with the approved calculation
methodology.
7 Ibid s 300(5)(b).
8 Department of Environment and Science, Guideline ESR/2018/4425: Estimated rehabilitation cost
under the Environmental Protection Act 1994 (Version 2, 2018) 1.
9 EPA s 298(2)(c).
10 Department of Environment and Science, Guideline ESR/2018/4425: Estimated rehabilitation cost
under the Environmental Protection Act 1994 (Version 2, 2018) s 2.3.2.
-- 4 of 7 --
5
[13] The ERC amount now agreed by the parties modifies the ERC calculations to replace
the ‘high risk rate’ estimate with the agreed estimated cost of implementing the design
requirements specified in the JER.
[14] The purpose of a guideline made under s 550 is “to provide guidance”.11 As the Court
stands in the shoes of DES in deciding the appeal, I must consider what weight to
give to the ERC Guideline, and the approved calculation methodology, in making my
decision on the appeal.12 Considering the application of the guideline to this mine is
a fundamental element in making my decision.13
[15] On one view, the ERC amount does not comply with the ERC Guideline, because it
does not adopt the approved calculation methodology in all respects. However, the
purpose of the approved calculation methodology is to guide the applicant in
complying with the application requirements of s 298 of the EPA.
[16] The guideline states:14
All EA holders must use the most recent version of the department’s ERC
calculator to calculate their ERC, unless the method or rate to estimate ERC
is prescribed in an ERA standard (refer to section 2.3.1 of this guideline).
[17] I could find no statement in the guideline that suggests that DES, in making the ERC
decision, must slavishly apply the amount arrived at using the approved calculation
methodology. That is not surprising, because to so bind DES would remove any
discretion as a decision maker.
[18] That would be inconsistent with the decision-making process provided for in the
guideline. It contemplates the ERC decision may be influenced by several
considerations. Section 2.5.1 identifies several criteria that “must be considered” in
making the ERC decision. One criterion is “any relevant rehabilitation plans, reports,
evaluations and assessments”. It follows that a relevant report could affect the ERC
amount decided by DES and, on appeal, this Court.
11 EPA s 550(1).
12 Rathborne v Abel (1964) 38 ALJR 293 at 295; Origin Energy Electricity Ltd v Queensland
Competition Authority [2014] 1 Qd R 216 at [90].
13 Citigold Corporation Limited v Chief Executive, Department of Environment and Heritage
Protection (No. 5) [2016] QLC 62 at [92].
14 Department of Environment and Science, Guideline ESR/2018/4425: Estimated rehabilitation cost
under the Environmental Protection Act 1994 (Version 2, 2018) at 2.3.2.
-- 5 of 7 --
6
[19] The JER is a site-specific consideration of a proposed method to manage the risk of
seepage of potentially acid forming material. As such, it is a relevant report that the
Court must consider in making the ERC decision.
[20] The ERC calculator assumes capping using two capillary breaks.15 The Century Mine
is located in an area with a semi-arid climate. In the JER, the expert witnesses agree
that “a single, thicker capillary break would be more effective than two capillary
breaks,”16 given the location of the mine.
[21] Given the requirement in s 2.5.1 to take a relevant report into account, I consider an
ERC amount that is not calculated strictly in accordance with the approved calculation
methodology complies with the ERC Guideline. On that view, there is no tension
between the guideline and the orders proposed by the parties.
[22] In any case, if there is, the ERC Guideline, as a statutory instrument, must yield to
the Act. The EPA requires DES to decide the amount of the estimated cost of:
(a) rehabilitating the land on which the resource activity is carried out; and
(b)preventing or minimising environmental harm, or rehabilitating or restoring the
environment, in relation to the resource activity.17
[23] It requires DES to have regard to the guideline in making that decision. It does not
require DES to make a decision to adopt the amount arrived at using the approved
calculation methodology.
[24] In making the ERC decision on this appeal, I prefer the unanimous expert assessment
of the best method, on this mine, to prevent seepage of the material contained in the
waste rock dumps and tailing storage facilities over a default assumption about
capping design embedded in a calculator adopted by the Chief Executive to assist an
applicant to prepare their application.
[25] I am satisfied I can make the orders proposed by the parties and that the agreed ERC
amount satisfies the requirements of s 300(1).
15 Joint Expert Report of Dr David Williams, Mr Peter Scott, Mr Andre Kemp and Dr Alan Robertson
dated 3 December 2020 (‘JER’), p 20.
16 JER at 1.1.4 p 37.
17 EPA s 300(1).
-- 6 of 7 --
7
Orders:
1. The appeal is allowed.
2. Pursuant to sections 530(1)(b) and 300 of the Environmental Protection Act 1994
(Qld), the Respondent’s decision dated 28 January 2020 that the estimated
rehabilitation cost (ERC) for environmental authority EPML00888813 (EA) is
$230,465,718 (excluding GST) for the ERC period of 28 January 2020 to 27
January 2023 is set aside and substituted with the following decision:
a. the required amount of ERC for the EA is $183,916,150.06 (excluding GST);
and
b. the ERC period for the EA is 28 January 2020 to 27 January 2023.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2021/003