Chapel of Angels Pty Ltd v Hennessy Building Pty Ltd & Anor [2020] QCA 219 (2020) 6 QR 38
SUPREME COURT OF QUEENSLAND
CITATION: Chapel of Angels Pty Ltd v Hennessy Building Pty Ltd &
Anor [2020] QCA 219
PARTIES: CHAPEL OF ANGELS PTY LTD TRADING AS
CHAPEL OF ANGELS
ACN 154 327 867
(applicant)
v
HENNESSY BUILDING PTY LTD TRADING AS
HENNESSY BUILDING ACN 117 587 998 IN ITS OWN
CAPACITY AND AS TRUSTEE FOR THE HENNESSY
FAMILY TRUST ABN 45 515 151 376
(first respondent)
JOHN PAUL HENNESSY
(second respondent)
FILE NO/S: Appeal No 4767 of 2019
DC No 4124 of 2014
DIVISION: Court of Appeal
PROCEEDING: Application for Extension of Time
ORIGINATING
COURT:
District Court at Brisbane – [2018] QDC 218; [2018]
QDC 248 (Porter QC DCJ)
DELIVERED ON: 7 October 2020
DELIVERED AT: Brisbane
HEARING DATE: 22 November 2019
JUDGES: Fraser and Philippides and McMurdo JJA
ORDER: The application for an extension of time within which to
apply for leave to appeal is refused with costs.
CATCHWORDS: APPEAL AND NEW TRIAL – PROCEDURE –
QUEENSLAND – TIME FOR APPEAL – EXTENSION OF
TIME – WHEN REFUSED – where the reasons for judgment
were published on 12 November 2018 and the orders were
made on 11 December 2018 – where the applicant filed an
application for an extension of time within which to apply for
leave to appeal out of time, on 3 May 2019 – where a director
of the applicant deposed that the applicant decided not to
appeal but later reconsidered its decision – whether, taking into
account the merits of the proposed appeal, an extension of time
is demonstrably necessary to prevent a substantial injustice
RESTITUTION – CLAIMS ARISING OUT OF INEFFECTIVE
CONTRACTS – UNENFORCEABLE OR VOID CONTRACT
– UNENFORCEABLE CONTRACT – BUILDING
CONTRACTS – where the applicant and the first respondent
-- 1 of 21 --
2
executed a building contract by which the first respondent
undertook to construct a chapel – where the first respondent
held a “builder – low rise” licence which authorised the
construction of buildings in the chapel’s class, excluding
buildings involving Type B construction under the Building
Code of Australia – where the chapel involved Type B
construction – where the contract was therefore unenforceable
by the first respondent under s 42 of the Queensland Building
Services Authority Act 1991 (Qld) as the first respondent did
not hold a contractor’s licence of the appropriate class for all
the building work it undertook to carry out under the contract
– where, by the time the dispute arose, most of the work had
been completed and the applicant had made progressive
payments to the first respondent – where the first respondent
also held a carpentry licence – where the applicant claimed
repayment of the amounts it had paid to the first respondent –
where the first respondent counterclaimed for reasonable
remuneration as restitution for the work it had carried out –
where s 42 limits the amount of remuneration a party can
recover for unlicensed work – whether the first respondent was
entitled to any remuneration for the work it had done on the
chapel – whether the first respondent was entitled to recover
reasonable remuneration, unqualified by s 42, for work that
was within the scope of its carpentry licence
APPEAL AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – POINTS AND OBJECTIONS NOT TAKEN
BELOW – WHEN NOT ALLOWED TO BE RAISED ON
APPEAL – COURSE OF CONDUCT AT TRIAL –
GENERALLY – where the applicant is seeking to raise
arguments in its proposed appeal that it did not raise at the trial
– where, in particular, the applicant seeks to agitate an
argument that a key expert report relied upon by the
respondents at trial should not have been accepted by the
primary judge and contained various inaccuracies – where no
objection was taken to the expert report at trial and it was the
subject of extensive cross examination – whether the proposed
challenges to the expert report could have been met by calling
additional evidence at trial – whether leave to appeal should be
granted to enable the applicant to raise these new arguments
Queensland Building Services Authority Act 1991 (Qld), s 30,
s 42
Queensland Building Services Authority Amendment Act
1999 (Qld), s 21
Queensland Building Services Authority Regulation 2003
(Qld), s 8, s 14, sch 2
Baguley v Lifestyle Homes Mackay Pty Ltd [2015] QCA 75,
applied
Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd
(formerly t/as Stork Food Systems Australasia Pty Ltd)
(2009) 254 ALR 661; [2009] QCA 75, considered
-- 2 of 21 --
3
Cook’s Constructions Pty Ltd v Stork Food Systems Australia
Pty Ltd [2008] QSC 179, cited
Dart Holdings Pty Ltd t/as A Dart & Co v Total Concept
Group Pty Ltd [2012] QSC 158, considered
Mann v Paterson Constructions Pty Ltd (2019) 93 ALJR 1164;
[2019] HCA 32, cited
Marshall v Marshall [1999] 1 Qd R 173; [1997] QCA 382,
considered
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221;
[1987] HCA 5, applied
Peet Ltd & Ors v Richmond (2011) 33 VR 465; [2011]
VSCA 343, cited
Sopov v Kane Constructions Pty Ltd (No 2) (2009) 24 VR 510;
[2009] VSCA 141, cited
Spencer & Anor v Hutson & Ors [2007] QCA 178, applied
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196; [1998]
QCA 417, considered
Water Board v Moustakas (1988) 180 CLR 491; [1988]
HCA 12, applied
COUNSEL: S Taylor for the applicant
P A Travis for the respondents
SOLICITORS: Ohlson’s Lawyers and Barristers for the applicant
Axia Litigation Lawyers for the respondents
[1] FRASER JA: On 6 December 2012 the applicant (“Chapel of Angels”) and the first
respondent (“Hennessy Building”) executed a building contract by which Hennessy
Building undertook to construct a wedding chapel and surrounds at Montville and
Chapel of Angels agreed to pay to Hennessy Building the “Contract Sum” adjusted
from time to time in accordance with the building contract. The building contract
obliged Chapel of Angels to make regular payments on account of the Contract Sum
throughout the progress of the work in response to payment claims by Hennessy
Building. Disputes arose between them after Hennessy Building had completed most
of the work required by the building contract and Chapel of Angels had made
progressive payments on account of the Contract Sum totalling $632,615.64.
[2] Chapel of Angels subsequently claimed repayment of that amount upon the ground
that the building contract was invalid, amongst other claims in proceedings in the
District Court. Hennessy Building defended the claim and counterclaimed for orders
including for money payable to it under the building contract or, if the building
contract were found to be unenforceable by it, for reasonable remuneration as
restitution for the work it had carried out.
[3] The issues at the trial before Porter QC DCJ, so far as they remain relevant in Chapel
of Angels’ application for an extension of time within which to apply for leave to
appeal to this Court, involve the construction and application to the facts of s 42 of
the Queensland Building Services Authority Act 1991 (Qld) (“the Act”).1 Contravention
of s 42 is made an offence by s 42(9). Subsections (1), (3) and (4) of s 42 provide:
1 The relevant version of the Act is in a reprint that was current from 1 January 2011 to 31 October 2013.
The Act has since been renamed the Queensland Building and Construction Commission Act 1991 (Qld).
-- 3 of 21 --
4
“(1) A person must not carry out, or undertake to carry out, building
work unless that person holds a contractor’s licence of the
appropriate class under this Act.
(3) Subject to subsection (4), a person who carries out building
work in contravention of this section is not entitled to any
monetary or other consideration for doing so.
(4) A person is not stopped under subsection (3) from claiming
reasonable remuneration for carrying out building work, but
only if the amount claimed—
(a) is not more than the amount paid by the person in
supplying materials and labour for carrying out the
building work; and
(b) does not include allowance for any of the following—
(i) the supply of the person’s own labour;
(ii) the making of a profit by the person for carrying
out the building work;
(iii) costs incurred by the person in supplying materials
and labour if, in the circumstances, the costs were
not reasonably incurred; and
(c) is not more than any amount agreed to, or purportedly
agreed to, as the price for carrying out the building work;
and
(d) does not include any amount paid by the person that may
fairly be characterised as being, in substance, an amount
paid for the person’s own direct or indirect benefit.”
[4] One of the questions at the trial was whether Hennessy Building held “a contractor’s
licence of the appropriate class” in terms of s 42(1).
[5] Section 30(1) of the Act provides for the issue of a contractor’s licence authorising
the licensee to carry out all classes of building work or to carry out building work of
one or more classes specified in the licence. Section 30(2) provides that contractors’
licences are to be divided into classes by regulation according to whether the licence
relates to all classes of building work or is limited to a specified class or classes of
building work. In the latter case, the classification is to be “according to the class or
classes of building work to which [the licence] relates.” Pursuant to s 30(2), s 14 of
the Queensland Building Services Authority Regulation 2003 (Qld) (“the Regulation”)2
provides that contractors’ licences are divided into the classes specified in schedule 2.
Schedule 2 contains 60 parts, each of which describes a licence class, the scope of
work within that licence class, and the requirements (technical, financial, and
managerial or experience) for that licence class.
[6] Hennessy Building held two contractor’s licences: a “builder – low rise” licence and
a carpentry licence. The scope of work for the “builder – low rise” licence is
described in four paragraphs of item 2 in part 4 of the schedule. Paragraph (1) refers
2 The relevant version of the Regulation is the reprint current as at 28 September 2012.
-- 4 of 21 --
5
to building work on a class 1 or class 10 building. Paragraph (3) refers to the
preparation of certain plans and specifications. Paragraph (4) excludes matters which
are not presently relevant. The directly relevant paragraph provides:
“(2) Building work on classes 2 to 9 buildings with a gross floor area
not exceeding 2000m 2 , but not including Type A or Type B
construction.”
[7] The primary judge held that the chapel was a class 9b building3 which (because it had
a rise in storeys of two) required Type B construction,4 and that “in undertaking under
the Building Contract to construct the Chapel building, Hennessey [sic] undertook to
carry out building work without the appropriate class of license” in breach of s 42(1).5
[8] The primary judge recorded that Hennessy Building admitted that if it did not hold
the appropriate class of contractor’s licence Chapel of Angels was entitled to recover
all of the payments it had made to Hennessy Building under the building contract.6
The primary judge therefore held that Chapel of Angels was entitled to recover
$632,615.64 from Hennessy Building and that Hennessy Building’s counterclaims to
enforce the building contract must fail.7
[9] The primary judge also held that s 42(3) only prohibited recovery of reasonable
remuneration unqualified by s 42(4) for work carried out that was not within the scope
of any licence held by the person carrying out that work, so that work that was within
the scope of any such licence may be the subject of a non-contractual claim which is
unaffected by s 42(4).8
[10] The primary judge therefore held that the law entitled Hennessy Building to recover:
(a) reasonable remuneration for so much of the building work it had carried out
which was within the scope of any licence it held; and
(b) reasonable remuneration, as modified by s 42(4), for so much of the building
work it had carried out which was not within the scope of any licence it held.
[11] The primary judge identified as the only remaining issue upon Hennessy Building’s
counterclaim the identification of the sum to which Hennessy Building was entitled.9
The primary judge concluded that:
(a) The expert report of Mr Carey, a quantity surveyor, permitted the calculation
of the amount to which Hennessy Building was entitled.10
(b) The carpark and external works were within Hennessy Building’s “builder –
low rise” licence and Chapel of Angels made no submission to the contrary.11
(c) Hennessy Building’s carpentry licence authorised a substantial part of the
building work of the chapel (“licensed work”).12
3 The classification is found in the Building Code of Australia.
4 Reasons [106] – [111].
5 Reasons [111].
6 Reasons [127]. See Marshall v Marshall [1999] 1 Qd R 173 at 176 (McPherson JA) and Cook’s
Construction Pty Ltd v SFS 007.298.633 Pty Ltd (formerly t/as Stork Food Systems Australasia Pty
Ltd) [2009] QCA 75 at [49] – [53] (Keane JA).
7 Reasons [128] – [129] and [200] – [201].
8 Reasons [134].
9 Reasons [139].
10 Reasons [157].
11 Reasons [156](a).
12 Reasons [156](b).
-- 5 of 21 --
6
(d) Mr Carey assessed the reasonable remuneration for the construction of the
whole of the works (excluding overheads and profit) at $542,680.51.13
(e) Mr Carey assessed the reasonable remuneration for the work involved in the
construction of the chapel that fell outside the scope of the carpentry licence
(“unlicensed work”) at $26,071.19.14
(f) The reasonable remuneration for the licensed work, excluding overheads and
margin, was $516,609.32 ($542,680.51 - $26,071.19).15
(g) Allocating one half of the figure for overheads attributable to the total cost of
the whole of the works, but excluding any allowance for margin (because it
was precluded in relation to unlicensed work by s 42(4)(b)), the total reasonable
remuneration for the unlicensed work was $27,635.46 (excluding GST).16
(h) Hennessy Building was not entitled to recover any amount for the unlicensed
work because it failed to fulfil the onus upon it of proving either the amount
paid by Hennessy Building in supplying materials and labour for carrying out
the building work (s 42(4)(a)) or the amount agreed as the price for carrying
out the unlicensed work (s 42(4)(c)).17
(i) Adopting as reasonable the figures for overhead and margin assessed by
Mr Carey, the total reasonable remuneration for the licensed work (excluding
GST) was $636,462.67, resulting in an amount inclusive of GST of $700,108.20.18
(j) The net amount due by Chapel of Angels to Hennessy Building was $67,492.88
($700,108.20 - $632,615.32).19
[12] The primary judge therefore ordered:
(a) a declaration to the effect that, by the building contract dated 6 December 2012,
Hennessy Building undertook to carry out building work for which it did not
hold a contractor’s licence of the appropriate class under the Act; and
(b) that Chapel of Angels pay Hennessy Building the amount of $85,989.86 (which
included interest of $18,496.98 on the net sum owing to Hennessy Building of
$67,492.88).
Consequential orders including orders as to costs were also made.
[13] Chapel of Angels seeks leave to appeal against the order requiring it to pay Hennessy
Building $85,989.86 and against some of the consequential orders made against it.
As I have indicated, the application is out of time. Hennessy Building opposes the
grant of the necessary extension of time and the grant of leave to appeal.
[14] The draft notice of appeal includes 23 grounds of appeal, many of which are in the
nature of arguments. No ground of appeal challenges the premise of Hennessy
Building’s claim that, subject to any appropriate application of s 42(4), it is entitled
13 Reasons [159].
14 Reasons [158].
15 Reasons [159].
16 Reasons [161] – [162].
17 Reasons [163] – [165].
18 Reasons [160] and [166].
19 Reasons [167] – [172].
-- 6 of 21 --
7
to reasonable remuneration by way of restitution for the building work it carried out.20
The following reasons proceed upon the same premise. The proposed appeal
concerns the effect of the Act and Regulation upon the quantum of the counterclaim
for reasonable remuneration. At the hearing of the application Chapel of Angels
abandoned some of the grounds of its proposed appeal and articulated the case it
wished to present on appeal within two broad contentions.
The application for an extension of time
[15] The primary judge’s reasons, which include a general description of the orders
required to give effect to the findings, were published on 12 November 2018. After
hearing the parties about the form of orders to be made, on 11 December 2018 the
primary judge made orders and published reasons concerning interest, costs, and the
form of some of the orders. The period of time for applying for leave to appeal
expired on 10 January 2019. On 3 May 2019 Chapel of Angels filed an application
for leave to appeal and an affidavit by a director of that company, Ms Peek, setting
out reasons for the delay in applying and expressions of opinion about why time
should be extended.
[16] Chapel of Angels communicated its intention to seek leave to appeal in a letter from
its solicitors to Hennessy Building’s solicitors dated 15 April 2019, which was about
three months after the expiry of the time for applying, and the application was commenced
nearly four months after the expiry of the time for applying. The significance of those
periods of three and four months is to be understood in the context that Chapel of
Angels was in possession of the reasons which are sought to be challenged for
a month before time was set running by the pronouncement of the orders.
[17] Ms Peek deposed that Chapel of Angels decided not to appeal on 6 December 2018,
because (to summarise the relevant effect of her evidence) she accepted advice from
its lawyers not to appeal and that a better approach would be to sue former lawyers
for not pleading the case properly. Ms Peek subsequently had second thoughts. She
wrote to the Chief Judge of the District Court about the topic. Consistently with the
advice given by Chapel of Angels’ lawyers she received the unsurprising reply that if
it was maintained that the judgment was affected by error the remedy was to appeal.
A few weeks after receiving that response she retained a new lawyer and put in train
the process which resulted in the ultimate filing of the application.
[18] Chapel of Angels was severely critical of the legal assistance given to it by various
lawyers in the course of the proceedings in the District Court and also in relation to
the question whether or not it should appeal against the primary judge’s decision. It
argues that the quality of its legal advice was such that it should not be regarded as
having made a real decision not to appeal before subsequently adopting a different
view. The lawyers whose conduct is criticised have not been heard in the application
to this Court. The Court could not and should not express a view upon the question
whether Chapel of Angels may have some recourse to any of its former lawyers if the
primary judge’s decision is more disadvantageous to it than ought to have been the
20 Neither of subsections 42(3) and (4) creates a right to recover remuneration; instead, s 42(3) is
“concerned to sterilise any claim which might otherwise be made under a contract or under the
common law by an unregistered builder” and s 42(4) imposes “limitations upon the right of action at
common law which it preserves against the sterilising effect of s 42(3)”: Cook’s Construction Pty Ltd
v SFS 007.298.633 Pty Ltd (formerly t/as Stork Food Systems Australasia Pty Ltd) [2009] QCA 75 at
[38] – [39] (Keane JA).
-- 7 of 21 --
8
case. Chapel of Angels’ arguments supply no reason for doubting that it made
a deliberate decision not to appeal. This is a significant factor against extending time.
[19] In Spencer & Anor v Hutson & Ors21 Keane JA (Williams and Jerrard JJA agreeing)
observed:
“The prescribed time limits for appeals serve the important purpose of
bringing finality to litigation. They are not lightly to be ignored. [Beil
v Mansell (No 1) [2006] 2 Qd R 199 at 207 [38]]. An applicant for an
extension of the time for bringing an appeal must show that there is
good reason for the court to relieve that party of the consequences of
the expiration of the prescribed period for bringing an appeal.
A demonstration that there is a good reason to extend time will usually
involve an explanation for that party’s delay. [Beil v Mansell (No 1)
[2006] 2 Qd R 199 at 207 – 208 [38] – [41]].
… The interests of justice will favour granting an opportunity to avoid
the consequences of a deliberate decision by a party to litigation only
in exceptional cases. [Cf Beil v Mansell (No 1) [2006] 2 Qd R 199 at
207 [38] – [39]].”
[20] In Baguley v Lifestyle Homes Mackay Pty Ltd22 Gotterson JA (McMurdo P and
Douglas J agreeing) expressed agreement with the proposition that where a deliberate
decision not to appeal is made an extension of time to allow such an appeal will be
granted only where it is demonstrably necessary to prevent a substantial injustice.
Gotterson JA observed that “the quality of the merits of the proposed appeal will be
influential in deciding whether an extension of time is required to prevent
a substantial injustice”.
The first contention in the proposed appeal
[21] Before determining whether an extension of time should be granted it is convenient
to discuss the contentions Chapel of Angels would advance in the appeal it seeks
leave to commence.
[22] The first contention in the proposed appeal is that, contrary to the primary judge’s
analysis, a consequence of the conclusion that construction of the chapel was not
within the scope of the “builder – low rise” licence is that none of the building work
Hennessy Building carried out was authorised by its carpentry licence or by its
“builder – low rise” licence. This contention encompasses two distinct arguments.
I discuss Chapel of Angels’ argument about the car park and external works, which
were found to fall within Hennessy Building’s “builder – low rise” licence, in the
section of these reasons addressing Chapel of Angels’ second contention; both of
those arguments involve factual questions.
[23] This section of my reasons addresses Chapel of Angels’ argument that a consequence
of the primary judge’s conclusion that construction of the chapel was not within the
scope of the “builder – low rise” licence is that none of the work Hennessy Building
carried out in the course of building the chapel was authorised by its carpentry licence.
This argument is submitted to involve only the proper construction of the Act and the
Regulation.
21 [2007] QCA 178 at [28] – [29].
22 [2015] QCA 75 at [14] – [17].
-- 8 of 21 --
9
[24] The scope of work authorised by a carpentry licence is described in 16 paragraphs of
item 2 in part 16 in schedule 2 of the Regulation. For example, paragraphs (1) and
(2) comprehend the construction and erection of timber and steel wall framing and
roof structures, and non-load bearing internal partition walls, paragraphs (3) and (4)
comprehend the installation of windows and doors including framing and the erection
of ceiling and subfloor framing, paragraphs (13) and (14) comprehend concreting “to
simple forms” including the installation of formwork, reinforcement and concrete,
and the erection and stripping of formwork, and paragraph (15) refers to “Incidental
work of another class”.23
[25] Mr Carey set out in his report the full scope of the work within a carpentry licence
and expressed the opinion, which the primary judge found to be correct, that most of
the work done by Hennessy Building in building the chapel was within the scope of
the carpentry licence. Chapel of Angels’ first contention does not challenge that view
of the facts. Rather, the first contention depends upon a proposition that, upon the
proper construction of the Act, a “trade contractor’s” licence is not an appropriate
class of licence for work within the scope of that licence if that work is part of the
building work carried out to construct or erect a building for which the trade contractor or
another person does not hold the appropriate “builder contractor’s” licence.
[26] Chapel of Angels argues:
(a) The scheme of the Act is that work within a trade contractor’s licence that is
carried out as part of the construction of an entire building must be carried out
under the supervision of a builder who holds the appropriate class of licence
for constructing that building.
(b) To construct a building, the builder is required to hold a builder contractor’s
licence. Section 42(1) of the Act, read in conjunction with the definitions of
“building work” and “building”, forbids the erection or construction of
a building unless the builder holds the appropriate class of licence for that
building (in this case, a building requiring Type B construction).
(c) The carpentry licence is not a builder contractor’s licence. It is a mere trade
contractor’s licence. Such a licence does not authorise the construction of an
entire building. Because Hennessy Building did not hold a builder – medium
rise licence under part 5 in schedule 2 of the Regulation or a “builder – open”
licence under part 6 in schedule 2 of the Regulation (these being the only
licences authorising a builder to build a class 9b building including Type B
construction, such as the chapel), Hennessy Building did not hold a licence of
the appropriate class to carry out any building work on the chapel building.
(d) It is “not possible to apportion lawful work from unlawful work, because in the
context of erecting an entire building where there is … no principal contractor
… the work is either entirely lawful or it is entirely unlawful”.
23 Section 8 of the Regulation provides, in relation to “incidental work of another class”, that a licensee
may carry out or engage another person to carry out building work with a total value of $3,300 or less
that is within the scope of work under a licence class other than the relevant class applicable to the
licensee, is incidental to the building work being carried out under the relevant class, and is carried out
by the licensee or a licensee who holds a licence to carry out the work – other than in relation to work
for which an occupational or fire protection licence is required, which must be carried out by the holder
of a licence to carry out such work.
-- 9 of 21 --
10
[27] Upon the premise that Chapel of Angels may be permitted to advance those
arguments on appeal, Hennessy Building argues (in addition to an argument
mentioned under the next heading):
(a) Subsection 42(1) prevents an unlicensed contractor from bringing an action
upon the contract against the other contracting party.
(b) Subsection 42(3) applies s 42(4) only to qualify any non-contractual entitlement of
a person to reasonable remuneration for the carrying out of building work
without the appropriate class of contractor’s license for that building work.
(c) Hennessy Building is in the different category of a person with no enforceable
contractual entitlement to recover remuneration for the building work it performed
who carried out building work within the scope of a contractor’s licence.
(d) There is no legislative policy of depriving a contractor of a non-contractual
remedy for reasonable remuneration for carrying out building work that it was
licensed to carry out.
Should Chapel of Angels be permitted to argue the first contention on appeal?
[28] Hennessy Building objects to Chapel of Angels being granted leave to argue the first
contention on appeal, on the grounds that it did not argue it at the trial and that, if
such an argument had been made, Hennessy Building might have adduced additional
evidence at the trial.
[29] Chapel of Angels did submit at the trial that the whole of Hennessy Building’s claim
was governed by s 42(4) but it did not support that submission by its present
argument. Contrary to Chapel of Angels’ arguments in this Court,24 it is not common
ground that Hennessy Building did not have an appropriate licence to carry out
building work “in connection with” a Type B structure. The primary judge’s reasons
record that Hennessy Building accepted Chapel of Angels’ argument that the “builder
– low rise” licence permitted it to construct a class 9b building but not including
Type A or Type B construction.25 The primary judge did not refer to any submission
by Chapel of Angels or any concession by Hennessy Building that, if (as Chapel of
Angels contended and the primary judge found) the chapel involved Type B
construction, none of Hennessy Building’s building work on the chapel fell within its
“builder – low rise” licence or its carpentry licence. Chapel of Angels’ present
argument is a departure from the way it conducted its claim in the District Court.
[30] Hennessy Building submits that, if Chapel of Angels’ present argument had been
raised in the District Court, one of Hennessy Building’s arguments in response would
have required a factual investigation bearing upon the scope of its “builder – low rise”
licence. It argues that the concluding phrase in paragraph (2) of item 2 in part 4 of
schedule 2 of the Regulation (see [6] of these reasons) withdraws from the scope of
a “builder – low rise” licence only so much of the building work as is Type A or Type
B construction. At the hearing of the application in this Court counsel for Hennessy
Building handed up an extract from a 2016 edition of the Building Code of Australia
which was submitted to identify particular construction elements required for Type B
construction. A very broad summary of the apparent effect of the document is that it
requires identified elements to be constructed in ways that will comply with fire
24 Transcript 22 November 2019 at 1-4.
25 Reasons [82] – [83].
-- 10 of 21 --
11
resistance level requirements and will limit consequential effects of fire upon the
building’s structural integrity.
[31] The effect of Hennessy Building’s argument is that the scope of its “builder – low
rise” licence comprehended all of the work of constructing the chapel apart from the
work described in the Building Code of Australia as requiring Type B construction.
The location of the concluding phrase at the end of the sentence in paragraph (2) of
item 2 in part 4 of schedule 2 of the Regulation seems more consistent with it
excluding from a “builder – low rise” licence the construction of a class 9 building
for which Type B construction is required. That view also seems to accord with parts
of the extract from the Building Code of Australia, particularly the reference in cl 1.1
to the “minimum Type of fire-resisting construction of a building” and the reference
in cl 4.1 to construction requirements in “a building required to be of Type B
construction”. The same construction seems to be more consistent with the different
categories of builder contractor’s licences under the Act, given that a particular level
of building expertise is presumably required for the identification of the elements of
a building requiring Type A or Type B construction and to fulfil those requirements.
[32] Upon what seems likely to be the correct construction of the Regulation, building the
chapel was not within the scope of Hennessy Building’s “builder – low rise” licence
because the chapel was a class 9 building that included Type B construction. I think
it unlikely that Hennessy Building’s different construction of the Regulation would
be supported by evidence not adduced at the trial, but there remains a possibility that
such evidence, including the relevant edition of the Building Code of Australia and
expert opinion evidence, might do so. That is a factor opposed to a grant of leave to
appeal upon the point. I will return to that issue after discussing the merits of Chapel
of Angels’ first contention upon the assumption that its construction of this part of
the “builder – low rise” licence is correct.
Consideration
[33] I will refer first to some terms defined in the Act. The first of the ten paragraphs in
the definition of “building work” in schedule 2 of the Act is “(a) the erection or
construction of a building”. The schedule provides only an inclusive definition of
“building”; it includes “any fixed structure”. The word “structure” is not defined.
Stated examples of a fixed structure comprehend a permanent fence, a water tank
connected to the stormwater system for a building, and both an inground swimming
pool and an aboveground pool fixed to the ground. The examples suggest a relatively
broad meaning of “fixed structure” and therefore of paragraph (a) of the definition;
for example, the construction of part of what is to become an entire building may
itself amount to a “building”. One of the other paragraphs in the definition of
“building work”, paragraph (e), refers to “any site work (including the construction
of retaining structures) related to work of a kind referred to above”. The remaining
paragraphs of the definition are not relevant here.26 The definition of “building work”
also provides that it “does not include work of a kind excluded by regulation from the
ambit of this definition.” Numerous exclusions are specified in s 5 of the Regulation.
[34] No paragraph of the definition of “building work” specifically describes trade work
of a kind that is typically involved in the construction of a domestic or commercial
26 They refer, for example, to alterations or repairs of a building, provision of lighting and other services,
preparation of plans or specifications, contract administration, and completed building inspections.
-- 11 of 21 --
12
building such as, for example, brick laying and block laying, carpentry, concreting,
plumbing, glazing, joinery, guttering, and painting and decorating (each of which is
the subject of a trade contractor’s licence). Given that s 30 of the Act authorises
a regulation providing for the issue of licences for carrying out “all classes of building
work” or “1 or more classes specified in the licence”, work described in a trade
contractor’s licence under a regulation made pursuant to s 30 that forms part of the
erection or construction of a building must itself amount to “building work”. It may
do so because it of itself creates a building, or because it merely contributes to the
construction of a building (and in either case is thus within paragraph (a) of the
definition of “building work”), or because it is “(e) any site work (including the
construction of retaining structures) related to work of a kind referred to above”, or
because it falls within both paragraphs.27
[35] It is impossible to be dogmatic about the meaning to be given to the assembly of the
various different concepts within the definition of “building work”. In some cases
work under a trade contractor’s licence (including a carpentry licence) will of itself
produce a building as defined and will be “building work” under paragraph (a) merely
for that reason. In my view paragraph (a) also comprehends work falling within
a trade contractor’s licence that, only in combination with other building work,
produces a building. Paragraph (e) extends the definition of building work to work
upon the same site that does not create or contribute to the creation of a building
described in paragraph (a) but is sufficiently closely related to the work of
constructing that building as to justify treating it as “building work”. Upon this view,
each of Hennessy Building’s carpentry licence and its “builder – low rise” licence
authorised “building work” within paragraph (a) of the definition.
[36] The term “carry out” is defined to mean any of “carry out the work personally”,
“directly or indirectly cause the work to be carried out”, and “provide building work
services28 for the work”. In this case Hennessy Building carried out the building work
personally.
[37] Hennessy Building’s argument derives support from a decision cited by the primary
judge, Dart Holdings Pty Ltd t/as A Dart & Co v Total Concept Group Pty Ltd.29 One
issue in that case concerned the entitlement to payment of a subcontractor who
supplied and installed items largely made of glass in a building being constructed by
others. The subcontractor held a “building – low rise” licence and a carpentry licence
but reliance was placed only upon the carpentry licence. McMurdo J (as McMurdo JA
then was) observed that the limitation in s 42(4) upon the amount which can be
claimed “applies only to the building work for which the contractor did not have the
appropriate licence” and “would not affect the defendant’s entitlement to be paid, upon
a restitutionary basis, for the work which it lawfully performed under its licence.”
[38] As Chapel of Angels acknowledged in the course of argument, no provision of the
Act or the Regulation in terms excludes from the scope of work within a trade
contractor’s licence building work that is not within the scope of a builder contractor’s
27 See Cook’s Constructions Pty Ltd v Stork Food Systems Australia Pty Ltd [2008] QSC 179 at [342]
(Martin J).
28 “Building work services” means one or more of administration, advisory, management, or supervisory
services. It would follow from the primary judge’s conclusions that Hennessy Building was not
entitled to recover remuneration unregulated by s 42(4) for any such service authorised only by its
“builder – low rise” licence. That does not bear upon the present issue.
29 [2012] QSC 158 at [40].
-- 12 of 21 --
13
licence held by a contractor responsible for constructing the entire building. That is
not conclusive. I accept that there is a hierarchy of contractor’s licences, in the sense
that there are numerous trade contractor’s licences that are largely restricted to work
within one identified trade (there are areas of overlap between licences) and there is
a much smaller number of builder contractor’s licences which authorise the
construction of entire buildings of particular classes or kinds. In this context, it is
distinctly arguable that the scheme of the Regulation made under the Act is such that
no trade contractor’s licence authorises the entire construction of a building of a class
or kind described in a builder contractor’s licence. It is not Chapel of Angels’ case,
however, that the work found by the primary judge to be within the carpentry licence
amounted to the entire construction of such a building.
[39] Chapel of Angels’ argument is different and broader. It is that work of the kind
described in Hennessy Building’s carpentry licence that formed part of the construction of
such a building was not within the scope of the carpentry licence because neither it
nor a different person who supervised that part of the work held such a builder
contractor’s licence. That is neither expressed nor implied in the Act or the Regulation.
[40] It is convenient to discuss Chapel of Angels’ argument using terms it used, such as
“trade contractor” and “builder contractor”, but I do not accept that those are relevant
statutory terms in this context. The Act contains a definition of “licensed builder”
(“a person who is a licensed builder under the regulations”) and s 42(12) of the Act
defines “licensed trade contractor” to mean a licensed contractor other than a licensed
builder. Furthermore, s 6 of the Regulation defines a “licensed builder” (a person
who is the holder of a “builder contractor’s licence”) and schedule 3 of the Regulation
defines “trade contractor’s licence” (a licence other than a builder contractor’s
licence). Section 10(1)(a) of the Act requires a board established under the Act to
include a licensed builder and a licensed contractor other than a licensed builder.
Section 42(8A) provides that a consumer who engages one or more trade contractors
to carry out building work does not carry out building work if the consumer does not
provide building works services. (An example of such a case expressed in the
provision is that of a consumer engaging a licensed builder to build and carry out all
building work services for a new residence.) Neither those provisions nor any other
provisions of the Act or Regulation address the consequences of a departure from the
licensing scheme. To address that issue it is necessary to ascertain the meaning
conveyed by the statutory text in its context.
[41] The focus must be upon s 42, since it contains the only provisions that address the
impact upon a contractor’s entitlement to remuneration of a departure from the
licensing scheme.
[42] Before October 1999 s 42 of the Act did not include the introductory phrase in s 42(3)
(“Subject to subsection 4,”) or any provision corresponding with s 42(4). Those parts
of s 42 were added by an amendment that took effect on 1 October 1999.30 In relation
to the original form of s 42, in Marshall v Marshall31 McPherson JA referred to the
“principal target of the statutory prohibition” as being “[s]ubstandard workmanship
and materials”, one method of achieving that object being preventing “incompetent
and unlicensed builders from doing building work, and penalising them if they do
so”;32 McPherson JA also observed (in relation to the statutory insurance scheme for
30 Queensland Building Services Authority Amendment Act 1999 (Qld), s 21 and SL No 226 of 1999, s 1.
31 [1999] 1 Qd R 173 at 176 – 178.
32 I have added the emphasis here and in subsequent paragraphs, except where the contrary is indicated.
-- 13 of 21 --
14
residential construction work) that it would “go far to diminish the funding available
for the statutory insurance scheme if unlicensed builders were able to receive and
retain money for doing residential construction work without complying with these
provisions [requiring a building contractor to pay an insurance premium] and with
the licensing requirements of the Act”.
[43] In Sutton v Zullo Enterprises Pty Ltd33 this Court approved the reasons given by
McPherson JA in Marshall v Marshall34 for the conclusion in relation to s 42(3) in
the form it was in before the 1999 amendments “that an unlicensed builder is by
s 42(3) not entitled to receive or retain money paid for doing building work”.
[44] In Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd (formerly t/as Stork Food
Systems Australasia Pty Ltd),35 Keane JA discussed the purpose of the 1999 amendments.
As Keane JA observed, under the original form of s 42, s 42(3) disentitled “an
unlicensed builder from receiving or retaining any payment on any basis for any
building work performed by it” (emphasis in original). The purpose of the 1999
amendments was explained in the Explanatory Notes and the Minster’s second
reading speech. Each refers to Sutton v Zullo Enterprises Pty Ltd. The Explanatory
Notes state that the decision “potentially allows considerable injustice, such as
deliberate recruiting of subcontractors from interstate and legally escaping from any
obligation to pay for work performed”, and that:
“Unlicensed contracting will, of course, remain an offence committed
by the contractor, but the principle that a builder or owner should not
be able to enrich themselves through signing on unlicensed
contractors is enshrined in this clause.
This clause amends s 42(3) and inserts a new subsection 42(4) to
provide an unlicensed contractor with a limited statutory right to
recover money which would otherwise be unavailable because of the
Zullo decision. The new provisions will allow an unlicensed
contractor to claim reasonable recovery of moneys actually expended
for the supply of materials and labour, other than the contractor’s own
labour and profit. …
The new provision in s 42(4)(iii) also prevents an unlicensed
contractor unreasonably incurring costs and claiming for recovery
under this provision. …”
[45] Similarly, the Minister stated in the second reading speech that the decision in Zullo
Enterprises “opens the door for unjust enrichment of unscrupulous developers and
builders, potentially encouraging them to engage unlicensed contractors” and that:
“The Bill rectifies this situation by allowing unlicensed contractors to
recover any moneys that they have reasonably spent while performing
building work. But unlicensed contractors cannot recover any profit
or receive any more than the contract price specified in the purported
contract. They will also be penalised for the offence of operating
without a licence.”
33 [2000] 2 Qd R 196 at 204 [8], 206 [16].
34 [1999] 1 Qd R 173 at 176 – 178.
35 [2009] QCA 75 at [54].
-- 14 of 21 --
15
[46] Keane JA concluded that the extrinsic material showed that the 1999 amendments
“were concerned to limit the scope of the operation of [s 42(1) and s 42(3)] by
reference to a limited right to reasonable remuneration in an unlicensed builder”, the
mischief at which the 1999 amendments were directed being “the denial of all
remuneration to an unlicensed builder”.36
[47] Those matters do not support Chapel of Angels’ argument. They are consistent with
Hennessey Building’s argument, it being inapt to describe as “unlicensed” a person
who carries out building work whilst holding a contractor’s licence that comprehends
part of that work.
[48] More importantly, the statutory text does not attribute the significance to the
distinction between a builder contractor’s licence and a trade contractor’s licence
which is required by Chapel of Angels’ first contention. It is apparent from the
discussion in [33] – [35] that s 42(1) cannot be read in conjunction with the definitions
of “building work” and “building” as a prohibition upon any “building work” done in
connection with the erection or construction of any “building” unless the person
carrying out that work holds a builder contractor’s licence of the class appropriate for
the construction of the completed building. The holding by a person of a builder
contractor’s licence is not a criterion of the operation of s 42(1). Nor does such
a licence prohibit anything. The relevant result of a person holding that or any other
class of contractor’s licence is instead that the person is unaffected by the prohibitions
in s 42(1) in relation to work described in the licence.
[49] It is necessary to bear in mind that s 42(1) contains two “separate and distinct
prohibitions”.37 In relation to the second prohibition, s 42(1) itself prevents a person
who undertook by a contract to carry out building work from enforcing the contract
if that person did not hold the appropriate class of licence for any inseverable part of
that building work.38 In relation to the present issue though, the relevant part of
s 42(1) is only the prohibition that “a person must not carry out … building work
unless that person holds a contractor’s licence of the appropriate class under this Act”.
Subsections 42(3) and 42(4) are concerned only with the consequences of
a contravention of that prohibition and, importantly, “it is the [building] work actually
performed which is relevant for the purposes of s 42(3) and s 42(4)”.39 It is also necessary
to bear in mind that the relevant prohibition in s 42(1) is contravened – and therefore
s 42(3) and s 42(4) operate – only where a person carries out building work without
holding “a” contractor’s licence of the appropriate class for that building work.
[50] Where a person who holds more than one contractor’s licence carried out building
work, a conclusion that the building work did not fall within the scope of one of the
contractor’s licences says nothing relevant about whether the person contravened the
prohibition upon carrying out building work without a contractor’s licence of the
appropriate class under the Act. In order to prove a contravention of that prohibition
it is necessary to identify the building work allegedly carried out without a licence of
the appropriate class and to prove that none of the licences held by the contractor was
36 [2009] QCA 75 at [57].
37 Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196 at 202 [3] (per McPherson JA, with whose
reasons Jones J agreed).
38 Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196 at 202 – 203 [4] (McPherson JA); Dart Holdings
Pty Ltd t/as A Dart & Co v Total Concept Group Pty Ltd [2012] QSC 158 at [39] (McMurdo J).
39 Dart Holdings Pty Ltd t/as A Dart & Co v Total Concept Group Pty Ltd [2012] QSC 158 at [15]
(McMurdo J).
-- 15 of 21 --
16
of an appropriate class for that work. If one of a number of contractor’s licences
authorised some of the building work carried out by the contractor, the only conduct
of the contractor in carrying out building work that could be proved to contravene the
prohibition is the contractor’s conduct in carrying out building work that does not fall
within the scope of that licence.
[51] Chapel of Angels’ argument that it is not possible to “apportion lawful work from
unlawful work” is no more than an assertion. Its argument did not identify any
provision of the Act or Regulation that supports it. The contrary view is suggested
by various matters in addition to those mentioned in the preceding paragraph: the Act
allows for different classes of “contractor’s licences”; that term comprehends builder
contractor’s licences authorising the construction of buildings and trade contractor’s
licences authorising various kinds of trade work commonly carried out as part of the
construction of buildings; the Act makes no distinction relevant to the present issue
between a builder contractor’s licence and a trade contractor’s licence; and the target
of the original form of s 42(1) and the limitations upon the right to reasonable remuneration
in s 42(4) introduced by the 1999 amendments was an “unlicensed” contractor.
[52] Because Hennessy Building held two contractor’s licences, the primary judge’s
conclusion that one of those licences, the “builder – low rise” licence, did not
authorise it to build the chapel is insufficient to establish that Hennessy Building
contravened the prohibition in s 42(1) upon carrying out building work when it did
not hold a contractor’s licence of the appropriate class. It is necessary also to examine
Hennessy Building’s carpentry licence. It was a contractor’s licence of the
appropriate class for the part of the building work described within the scope of that
licence it carried out in building the chapel. By carrying out that part of the work
Hennessy Building did not contravene the prohibition in s 42(1) against carrying out
“building work” without a licence of the appropriate class, regardless of whether or
not that part of the work, or the balance of the work required to complete the
construction of the chapel, was within the scope of its “builder – low rise” licence.
[53] Such a construction is not an encouragement to contractors to carry out building work
without a licence or licences that authorise all of that work. In this kind of case the
building contract is unenforceable by the contractor in relation to the unlicensed work.
Where (as in this case and as is commonly the case) the promise to carry out the
unlicensed work is not severable from the balance of the contract, the contractor is
unable to enforce the contract at all. Any non-contractual right the contractor may
have to recover reasonable remuneration for the unlicensed work is restricted by
s 42(4) and the contractor is exposed to prosecution for an offence for contravening
at least one of the two prohibitions in s 42(1). From the consumer’s perspective the
results of this construction also do not seem obviously unreasonable. The consumer
may be found liable to pay reasonable remuneration not limited in accordance with
s 42(4) only in relation to the benefit the consumer has obtained as a result of the
contractor carrying out building work for which it held a licence of the appropriate
class, and the consumer will benefit from the limits in s 42(4) in respect of any work
for which the contractor did not hold a licence of the appropriate class.
[54] The construction I prefer does not preclude account being taken of any real detriment
suffered by a consumer as a result of a contractor carrying out building work in a case
of this kind. Chapel of Angels did not argue that it suffered any such detriment or
seek to have any such detriment taken into account in the valuation of Hennessy
Building’s claim, but there may be a real detriment in some cases. An example may
-- 16 of 21 --
17
be given by reference to s 47 of the Act, which was mentioned in the course of
argument. It applies in a case in which “building work is carried out on land by
a person who is not licensed to carry out that building work” and “the land is offered
for sale within 6 years after completion of the building work”. Section 47(1) provides
that in such a case “the vendor must, before the contract of sale is signed by the
purchaser, give the prospective purchaser a notice containing details of the building
work and a warning in the form required by regulation”. Section 47(2) provides that
if such notice is not given, “the vendor will be taken to have given the purchaser
a contractual warranty (which operates to the exclusion of any inconsistent provision
of the contract of sale) that the building work was properly carried out.” It is not
difficult to accept that the market value of land encumbered by a building part of
which was constructed in the absence of a required licence might be adversely
affected by the operation of s 47. A consumer also may suffer a real detriment merely
because, for example, it is likely to be known to potential purchasers that all or some
building work was done on the consumer’s land without a necessary licence.
[55] That detriment of that kind may be taken into account in the valuation of a
restitutionary claim by the contractor against the consumer is suggested by a passage
in Deane J’s reasons in Pavey & Matthews Pty Ltd v Paul:40
“The tendency in some past cases to see the rationale of the right to
recover remuneration for a benefit provided and accepted under an
unenforceable contract as contract or promise rather than restitution
has tended to distract attention from the importance of identifying the
basis upon which the quantum of the amount recoverable should be
ascertained. What the concept of monetary restitution involves is the
payment of an amount which constitutes, in all the relevant circumstances,
fair and just compensation for the benefit or ‘enrichment’ actually or
constructively accepted. Ordinarily, that will correspond to the fair
value of the benefit provided (e.g. remuneration calculated at
a reasonable rate for work actually done or the fair market value of
materials supplied). In some categories of case, however, it would be
to affront rather than satisfy the requirements of good conscience and
justice which inspire the concept or principle of restitution or unjust
enrichment to determine what constitutes fair and just compensation
for a benefit accepted by reference only to what would represent a fair
remuneration for the work involved or a fair market value of materials
supplied. One such category of case is that in which unsolicited but
subsequently accepted work is done in improving property in
circumstances where remuneration for the unsolicited work calculated
at what was a reasonable rate would far exceed the enhanced value of
the property. More relevant for present purposes is the special category
of case where restitution is sought by one party for work which he
has executed under a contract which has become unenforceable
by reason of his failure to comply with the requirements of
a statutory provision which was enacted to protect the other
party. In that category of case, it would be contrary to the general
notions of restitution or unjust enrichment if what constituted fair
and just compensation for the benefit accepted by the other party
were to be ascertained without regard to any identifiable real
40 (1987) 162 CLR 221 at 263 – 264.
-- 17 of 21 --
18
detriment sustained by that other party by reason of the failure of
the first party to ensure that the requirements of the statutory
provision were satisfied.”
[56] The passage I have emphasised is consistent with academic and judicial statements
to the effect that in analogous circumstances the measure of the restitution is the value
of the benefit to the defendant, which may but will not necessarily be the same as the
reasonable cost incurred by the plaintiff in supplying the benefit.41
[57] My conclusion is that the primary judge did not misconstrue the Act in the way for
which Chapel of Angels contends in holding that s 42(4) did not apply to Hennessy
Building’s non-contractual claim for reasonable remuneration for the building work
within the scope of its carpentry licence it carried out in the course of constructing
the chapel.
The second contention in the proposed appeal
[58] Chapel of Angels’ second contention is that the primary judge erred in quantifying
Hennessy Building’s claim for the licensed work by failing to compare each component of
that claim with the scope of work authorised by Hennessy Building’s carpentry
licence and instead simply accepting Mr Carey’s expert report as concluding that issue
in favour of Hennessy Building. Chapel of Angels also seeks to agitate arguments that
Mr Carey’s report contains various arithmetical errors, inaccurate descriptions of
work, misstatements of the costs of some work, references to invoices when there
were only estimates, the inclusion as extras or provisional cost adjustments of the cost
of work which was within an original quote, costs for items of work admitted to be
not claimable, and inappropriate allocation as carpentry of work that wholly or partly
fell outside the carpentry licence and within another class of licence.
[59] Mr Carey’s report:
(a) recites that he had been appointed “as an independent and impartial quantity
surveying expert to assist the Court in determining a ‘fair and reasonable
valuation’ of matters requested on [the building contract]”;
(b) recites his relevant experience, including 40 years in the construction industry
including as the owner of a consulting firm of professional quantity surveyors
for 25 years, owning of his own construction company for some years, and his
board positions in large construction companies;
(c) recites his qualifications relevant to his report;
(d) describes the documents he considered, which include contract drawings and
quotations and invoices provided by Hennessy Building;
(e) refers to him having “inspected the site, measured where appropriate off
drawings, inspected quotations and invoices”;
41 See J Carter, K Mason and G J Tolhurst, Mason & Carter’s Restitution Law in Australia, 3 rd ed (2016)
at [137], [1415] and [1425]; Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221 at 227 (Mason
and Wilson JJ), 263 (Deane J); Mann v Paterson Constructions Pty Ltd (2019) 93 ALJR 1164 at [92]
– [95], [100] (Gageler J), [190], [201] – [204] (Nettle, Gordon and Edelman JJ); Maxcon Constructions
Pty Ltd v Vadasz [2016] SASCFC 119 at [84] (Peek, Blue and Lovell JJ); Peet Ltd & Ors v Richmond
(2011) 33 VR 465 at 485 [105] (Nettle JA, Neave JA and Rudd AJA agreeing); and Sopov v Kane
Constructions Pty Ltd (No 2) (2009) 24 VR 510 at 518 [25] (Maxwell P, Kellam JA and Whelan AJA).
-- 18 of 21 --
19
(f) sets out assessments and calculations in which he describes the relevant work,
often by reference to invoices or other documents; and
(g) expresses opinions about the appropriate characterisation of items of such work
which support the primary judge’s findings summarised in [11] of these reasons.
[60] The primary judge observed:
(a) The calculation of the amount to which Hennessy Building was entitled was
dealt with in some detail in Mr Carey’s report.
(b) Chapel of Angels did not file any expert report in reply and led no evidence
about the correct restitutionary measure in respect of the work undertaken by
Hennessy Building.42
(c) Chapel of Angels complained at the trial about reliance upon Mr Carey’s
report, but it was not unfair for Hennessy Building to rely upon Mr Carey’s
report in circumstances in which:
(i) that report had been in Chapel of Angels’ possession for at least five
months before commencement of the trial;
(ii) over a month before the trial commenced Hennessy Building gave notice
of its reliance upon the report as providing particulars of the sum claimed
if it was found that it had carried out unlicensed building work;
(iii) no objection was taken to the report at the trial, and it was cross examined
upon extensively.43
[61] Chapel of Angels did not deliver an expert report or plead any of the points it now
seeks to agitate in relation to Mr Carey’s report in the District Court. At the trial it
did not adduce any evidence in support of them, put them to Mr Carey in cross
examination, or make any submissions in support of them to the primary judge. If
they had been raised Hennessy Building might have adduced additional evidence and
addressed additional arguments to seek to meet the points. The failure to raise these
points at trial occurred in the context of a very long history of the proceeding in the
District Court and concerted attempts by the primary judge to ensure that both parties’
cases were properly prepared for trial. The proceeding in the District Court occupied
about five years, commencing on 20 October 2014. After the applicant had delivered
three or four iterations of its claim and statement of claim, on 8 March 2018, the
matter was listed for a 10 day trial commencing on 10 September 2018. Accordingly,
Chapel of Angels had six months’ notice of the date when the trial would commence.
As the primary judge observed, Mr Carey’s expert report was served on the applicant
on 6 April 2018, more than five months before the trial was appointed to commence.
On four occasions after the matter was listed for trial the primary judge made
directions about steps to be taken in advance of the trial, including directions aimed
at narrowing issues and addressing the evidence to be given at trial.
[62] In these circumstances, I do not accept the proposition underlying Chapel of Angels’
second contention that the primary judge was obliged to elaborate in greater detail
upon his reasons for accepting Mr Carey’s expert opinions. Chapel of Angels should
not be permitted to make the wholesale challenge to Mr Carey’s report it now seeks
42 Reasons [140].
43 Reasons [157].
-- 19 of 21 --
20
to make for the first time on appeal. Whether or not there may be merit in any of the
new arguments is not the real issue; the proper time for investigating the merits was
at the trial, not in an appeal.
[63] In Water Board v Moustakas44 Mason CJ and Wilson, Brennan and Dawson JJ
endorsed previous statements by the High Court “that a point cannot be raised for the
first time upon appeal when it could possibly have been met by calling evidence
below.” As was submitted by counsel for Hennessy Building, if the case now
advocated on behalf of Chapel of Angels had been properly raised in the District
Court, Hennessy Building might have responded to the case by adducing additional
evidence and making additional submissions. An obvious example of that is that if
Chapel of Angels’ had properly pleaded, or its counsel had put to Mr Carey, points
of the kind now sought to be made on appeal Mr Carey might have been able to
explain his opinions upon the points or Hennessy Building might have been able to
meet those points in other ways.
[64] Chapel of Angels also seeks to agitate the aspect of its first contention which
I mentioned in [22] of these reasons. It seeks to argue on appeal that a consequence
of the primary judge’s conclusion that Hennessy Building’s “builder – low rise”
licence did not authorise it to build the chapel is that the same licence did not authorise
it to carry out work on the carpark or external works. The primary judge recorded
that no submission was made to the contrary of his Honour’s finding that the carpark
and external works appeared to be within Hennessy Building’s “builder – low rise”
licence.45 If the submission now sought to be made on appeal had been made at trial,
Hennessy Building might have adduced additional evidence upon the questions
whether that work or part of it was within the described scope of the “builder – low
rise” licence and, if any part of it was not within the licence, whether it fell outside
the definition of “building work” or within one of the exclusions from “building
work” in s 5 of the Regulation.
[65] To grant leave to appeal to enable Chapel of Angels to raise these new arguments
would be to allow it to treat the trial as “little more than a preliminary skirmish”. That
should not be permitted; it is “fundamental to the due administration of justice that
the substantial issues between the parties are ordinarily settled at the trial”.46
Disposition and orders
[66] There being no sensible prospect that the application for leave to appeal would be
granted to permit Chapel of Angels to agitate any of those new arguments on appeal,
it would be futile to grant the extension of time necessary for that application to proceed.
[67] In addition, if Hennessy Building’s construction of the Regulation discussed in [28]
– [32] of these reasons is correct, that would require the matter to be remitted for
a further hearing. For that reason, and because of my conclusion that Chapel of
Angels’ first contention about the construction of s 42 of the Act is incorrect in any
event, I consider it inappropriate to grant leave to appeal upon that issue. That being
so no point is to be served by granting the requested extension of time.
[68] I would refuse the application for an extension of time within which to apply for leave
to appeal, with costs.
44 (1988) 180 CLR 491 at 497.
45 Reasons [122], [126], [156](a).
46 Coulton v Holcombe (1986) 162 CLR 1 at 7.
-- 20 of 21 --
21
[69] PHILIPPIDES JA: I agree with the order proposed by Fraser JA for the reasons
given by his Honour.
[70] McMURDO JA: I agree with Fraser JA.
-- 21 of 21 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2020/219