BGM Projects Pty Ltd v Durmaz [2020] QCA 146
SUPREME COURT OF QUEENSLAND
CITATION: BGM Projects Pty Ltd v Durmaz [2020] QCA 146
PARTIES: BGM PROJECTS PTY LTD
ACN 102 165 328
(respondent/applicant)
v
STEVE DURMAZ
(appellant/respondent)
FILE NO/S: Appeal No 5552 of 2020
SC No 12878 of 2019
DIVISION: Court of Appeal
PROCEEDING: Application to Strike Out
Application for Security for Costs
ORIGINATING
COURT: Supreme Court at Brisbane – [2020] QSC 87 (Brown J)
DELIVERED ON: 30 June 2020
DELIVERED AT: Brisbane
HEARING DATE: 19 June 2020
JUDGES: Morrison JA
ORDERS: 1. The notice of appeal is struck out.
2. The appellant pay the respondent’s costs of and
incidental to the application on the standard basis.
CATCHWORDS: APPEAL AND NEW TRIAL – PROCEDURE –
QUEENSLAND – OTHER MATTERS – STRIKE OUT –
where the respondent/applicant has applied to strike out the
notice of appeal – where in the alternative the respondent/applicant
seeks an order for security for costs – where Durmaz
Corporation purchased a lot in the respondent/applicant’s
development – where the contract of sale included a series of
covenants governing the design and construction of dwellings
on the lot – where Annexures C and D to the contract of sale
were Deeds in favour of the respondent/applicant, executed on
behalf of Durmaz Corporation by the appellant/respondent –
where the appellant/respondent caused Durmaz Corporation to
construct a non-approved shed on the lot – where there was no
challenge to the fact that the shed had been constructed without
approval from BGM, in breach of the building covenants, and
in breach of the order of Applegarth J made on 4 June 2019 –
where Brown J found that it was clear that Durmaz
Corporation had signed the Deeds and agreed to be bound by
the building covenants – where the order against which the
appeal has been brought was that of Brown J – where the order
-- 1 of 7 --
2
was that Durmaz Corporation Pty Ltd cause a constructed shed
on real property to be removed, and pay costs on an indemnity
basis – whether the notice of appeal should be struck out
Uniform Civil Procedure Rules 1999 (Qld), r 371(2)
BGM Projects Pty Ltd v Durmaz Corporation Pty Ltd [2020]
QSC 87, cited
Colgate-Palmolive Co v Cussons Pty Ltd (1993) 46 FCR 225;
[1993] FCA 536, cited
Re Cameron [1996] 2 Qd R 218; [1996] QCA 37, cited
Robertson v Hollings & Ors [2009] QCA 303, cited
von Risefer v Permanent Trustee Co Pty Ltd [2005] 1 Qd R 681;
[2005] QCA 109, cited
COUNSEL: R A Quirk for the respondent/applicant
The appellant/respondent appeared on his own behalf
SOLICITORS: Clinton Mohr Lawyers for the respondent/applicant
The appellant/respondent appeared on his own behalf
[1] MORRISON JA: The respondent has applied to strike out the notice of appeal in
this matter: (i) pursuant to the inherent jurisdiction of the Court on the basis that it is
frivolous, vexatious or an abuse of process; or (ii) pursuant to r 371(2) of the Uniform
Civil Procedure Rules 1999 (Qld) as it does not state briefly and specifically the
grounds of appeal.
[2] In the alternative the respondent seeks an order for security for costs in the sum of
$24,568.70.
[3] The order against which the appeal has been brought was that of Brown J, delivered
on 24 April 2020.1 That order was that Durmaz Corporation Pty Ltd: (a) cause
a constructed shed on real property at Burrum Heads to be removed; and (b) pay costs
on an indemnity basis.
Background matters
[4] A short recitation of the history of this matter assists in understanding the issues on
the current application.
[5] The applicant, BGM Projects Pty Ltd (“BGM”) is the developer of “On the Beach”
at Burrum Heads. The contracts for the sale of individual lots in the development
included a series of covenants governing the design and construction of dwellings on
those lots. The introductory words of the covenants were as follows:
“This Covenant is an agreement between the Developer, BGM
Projects Pty Ltd (“BGM Projects”), who is committed to providing
a quality residential environment, and the Buyer who intends to
construct a dwelling. This Covenant defines the quality of the
completed project, both environmentally and aesthetically.
Many items will reflect the design requirements of the Fraser Coast
Regional Council, whilst others reflect the ‘liveability’ vision of the
1 BGM Projects Pty Ltd v Durmaz Corporation Pty Ltd [2020] QSC 87.
-- 2 of 7 --
3
completed project and are a natural product of the unique beachfront
and lakeside topography.
Buyers may take comfort in the knowledge that their investment is not
devalued by an ill-balanced mix of poorly designed houses or
temporary dwellings.”
[6] On 7 September 2018 Durmaz Corporation Pty Ltd purchased a lot from an existing
owner, Mr Smith. The contract of sale included Special Condition 2 in these terms:
“2.(a) The buyer acknowledges that every person that purchases land
at On the Beach (of which the land sold in this contract forms
part) is required to comply with the attached Community
Development Standards and Building Covenant Conditions;
(b) The buyer agrees to sign the attached Continuation of Covenant
and to be bound in all respects by the said covenants from date
of settlement of this contract.
(c) The buyer agrees to cause any person to whom he sells the land
to complete and sign a notification in the same terms and deliver
it to BGM Projects Pty Ltd.”
[7] The covenants were Annexure A to that contract. Annexures C and D were Deeds in
favour of BGM, executed on behalf of Durmaz Corporation by Mr Durmaz.
[8] On 31 March 2019 Mr Durmaz placed a caravan on the property, indicating that he
intended to live in it. Despite being told that having a caravan was in breach of the
building covenants, Mr Durmaz stated he would not remove it.
[9] On 1 April 2019 Mr Durmaz informed BGM’s contract administrator that he intended
to build any house he wanted on the property, and did not intend to submit any
building plans to BGM for approval, or to otherwise comply with the building covenants.
[10] By 22 May 2019 BGM became aware that Mr Durmaz had commenced construction
works for a shed. Following objection by BGM, the solicitors for each side
corresponded about the failure to obtain approvals under the building covenants.
Mr Durmaz, for Durmaz Corporation, said it would undertake in writing to comply
with the building covenants. That undertaking was supplied to BGM.
[11] Subsequently, Mr Durmaz caused a concrete slab to be poured, without approval.
Applegarth J granted an interlocutory injunction restraining any further construction
work in breach of the building covenants and without approval.
[12] Mr Durmaz subsequently sought approvals from BGM but they were rejected on
various grounds. The order of Applegarth J was not varied to permit construction to
proceed.
[13] A couple of months later Mr Durmaz informed BGM that he no longer owned the
property, as Durmaz Corporation had sought to transfer the property to Mr Durmaz’s
brother, without requiring the brother to sign the Deeds which would bind him to the
building covenants. As a result, a further injunction was obtained to prevent the
transfer of title from being registered. Those orders were made by Bowskill J on
28 August 2019, by consent.
-- 3 of 7 --
4
[14] Subsequently, Mr Durmaz caused Durmaz Corporation to proceed to construct a non-
approved shed, notwithstanding the injunction of Applegarth J. Mr Durmaz’s
position was that the Deeds binding Durmaz Corporation to the building covenants
were illegal, given that a number of other owners had allegedly not signed similar
Deeds. He alleged that there had been misrepresentations by BGM in relation to the Deeds.
[15] The dispute came before Brown J on 27 November 2019. There was no challenge to
the fact that the shed had been constructed without approval from BGM, in breach of
the building covenants, and in breach of the order of Applegarth J made on
4 June 2019.
Proceedings before Justice Brown
[16] Justice Brown made a number of findings which are not the subject of challenge in
the present appeal. They were: BGM was entitled under the Deeds to enforce them;2
Durmaz Corporation was aware of the building covenants and the construction was
carried out without approval, in breach of the covenants and in breach of the order by
Applegarth J;3 Mr Durmaz accepted that he had constructed the shed notwithstanding
that he was aware of the injunction made by Applegarth J, and knowing he did not
have permission to do so under the building covenants;4 and Durmaz Corporation
proceeded on notice that BGM would take further legal action to restrain the breach,
and knew of the wrongful nature of Mr Durmaz’s acts in constructing the shed.5
[17] Mr Durmaz contended that not all owners had signed Deeds binding them to the
building covenants, and therefore the covenants were illegal. He also contended that
BGM had engaged in misleading conduct. However, Brown J found that he had
presented no evidence to support those allegations, nor had he sought an adjournment
to do so. In any event, her Honour found that it was clear that Durmaz Corporation
had signed the Deeds and agreed to be bound by the building covenants.6 The orders
made were that Durmaz Corporation remove the shed and pay costs on an indemnity basis.
Consideration
[18] There are quite a number of substantial obstacles confronting success in this appeal.
I will attempt to summarise them.
[19] First, the orders of Justice Brown were made against Durmaz Corporation, not
Mr Durmaz personally. However, it is Mr Durmaz, personally, who is the appellant.
The appeal is incompetent as the party the subject of the challenged orders is not
a party to the appeal.
[20] Secondly, the Notice of Appeal states the grounds to be: “… all grounds appeal based
on the misrepresentation of contract for covernant [sic]”. The only articulation of the
grounds appears in the outline filed by Mr Durmaz. That included these points:
(a) he was asked to enter into a deed of covenant before the purchase commenced
and agreed “with the belief that there was no ill intention by the contract”;
(b) soon after, two things became apparent; one was that “my proposed build was
not allowed for any reasonable reasons given to me”; and the second was that
2 Reasons below at [38].
3 Reasons below at [39]-[42].
4 Reasons below at [44].
5 Reasons below at [52].
6 Reasons below at [54].
-- 4 of 7 --
5
he “later learned from other residents that not everyone had entered into
a signed deed of covenant”;
(c) that was “a misrepresentation of the so called covenant and continued to this
day, no purchaser was ever informed of this fact before signing and entering
into a contract that has no value as a proposed product”;
(d) he had recently found a file of a Mr Lee, “who had no contract of covenant in
purchase nor did the previous owner”; after the case before Brown J he had
sought access to that file; and
(e) his contention was that: “this whole event has been about the developer and his
years of continuing efforts to impede upon residents, harass and hinder by
almost all means in an effort to protect the contracts survival and preservation
against litigation, when the first non signatories appeared instead of advising
residents of the estate of the new situation with the contracts now to be varied
and changed so that it may suit the new reality on the ground”; and “BGM
Projects Pty Ltd continued to misrepresent the contracts and impede upon
residents with the illegal misuse of the contracts causing individuals personal
and financial hardship and harm”.
[21] Thus, as developed during oral submissions before me, Mr Durmaz has articulated
only one ground as the basis for the appeal. It is that the developer, BGM, had made
a material misrepresentation in the introductory words of the community
development standards and building covenant conditions. Specifically it was in the
sentence: “Buyers may take comfort in the knowledge that their investment is not
devalued by an ill-balanced mix of poorly designed houses or temporary dwellings.”
The contention advanced was that there was evidence that some other lot owners were
not bound to the covenants as they were not included in their contracts of sale, thereby
making the assertion that all owners were bound, and the assertion that buyers could
take comfort that their investment would not be devalued, misleading or deceptive.
[22] The central difficulty with that contention is that Mr Durmaz said that he only
discovered the existence of other lot owners who were supposedly not bound by the
covenants, a number of months after the contract between Mr Smith and Durmaz
Corporation was completed. In the course of oral submissions before me, Mr Durmaz
accepted that he had no contact with the developer at the time Durmaz Corporation
entered into its contract with Mr Smith, and completed the purchase. Thus, there was
nothing actually said or done by BGM at the time of the purchase, to Mr Durmaz or
to Durmaz Corporation.
[23] Thus, if there was any misleading statement, it was confined to the sentence which
said that buyers “may take comfort in the knowledge that their investment is not
devalued by an ill-balanced mix of poorly designed houses or temporary dwellings.”
Those words are more aspirational than promissory. They do not, in my view, imply
that all lot owners will be bound by the covenants for all time. Even if there were
some owners who, for a variety of reasons, ended up with contracts that did not bind
them to the building covenants, that does not mean that the statement in the covenants
themselves was misleading.
[24] Mr Durmaz referred, without evidence, to the fact that there might be upwards of a
dozen owners who had purchased from mortgagees who had entered into possession.
He referred to these as liquidation sales. He asserted, again without evidence, that
those sales did not involve binding the purchaser to the covenants.
-- 5 of 7 --
6
[25] Mr Durmaz had extracted from an archived court file some documents in proceedings
between BGM Projects Pty Ltd and Ms Barnard and Mr Lee, the owners of Lot 93.7
As best can be gleaned from those documents, principally an executed “Terms of
Settlement” document between those parties:
(a) BGM sought to enforce the building covenants against Ms Barnard and Mr Lee
on the basis that they bound them, or ran with the land; BGM disputed
construction work done on Lot 93;
(b) Ms Barnard and Mr Lee disputed the binding effect of the covenants, and
disputed that the covenants ran with the land;
(c) the parties agreed that the existing structures could remain, with modifications; and
(d) Ms Barnard and Mr Lee agreed that the covenants touch, concern and run with
the land, and they were bound by them in the future.
[26] Even if those documents were admissible, they do not assist Mr Durmaz’s contention.
Plainly, BGM contended that the owners were bound by the covenants, regardless of
whether they were in the contract of sale. So much can be inferred from the recorded
contention, and acceptance, that the covenants touch, concern and run with the land.
[27] Thirdly, even if there was some form of misrepresentation, it is difficult to see how it
sounds in any particular relief. Durmaz Corporation did not act under any
misapprehension at the time it purchased the land, and was fully aware of the fact that
Mr Smith (the vendor) was bound by the covenants, and bound to contract for the sale
of the land on the basis that the covenants would continue. To that end Durmaz
Corporation executed the Deeds. Even if the misrepresentation could be characterised as
misleading or deceptive conduct, on the basis that contrary to what was represented,
in fact not all owners were bound, it does not follow that the relief would result in the
excision of the covenants from the contract or alternatively injunctive relief
preventing BGM from enforcing them. The estate consists of 200 developed lots,
159 of which have been sold, and 90 houses having been built. Within that broad
band of owners, the fact that a few might not be bound by the covenants does not
render any statement made in the introductory section of the building covenants
document misleading or deceptive.
[28] For these reasons I have come to the conclusion that the appeal has no realistic
prospects of success. Its pursuit is vexatious and an abuse of process. Consequently,
it should be struck out.8 That makes it unnecessary to deal with the application for
security for costs.
[29] BGM seeks indemnity costs in the event that the notice of appeal is struck out. I am
not persuaded that that is an appropriate order in the circumstances. True it is that the
appeal is wrongly constituted and Durmaz Corporation is not the appellant. Also it
is true that the articulated ground of appeal has no merit. However, the manner in
which the appeal has been brought and conducted, to the extent that it has, does not
warrant an order for indemnity costs.9
[30] I order:
7 Supreme Court of Queensland, BS 3069/2015.
8 von Risefer v Permanent Trustee Co Pty Ltd [2005] 1 Qd R 681 at [9]-[11].
9 Robertson v Hollings & Ors [2009] QCA 303, [6]; Colgate-Palmolive Co v Cussons Pty Ltd (1993)
46 FCR 225; Re Cameron [1996] 2 Qd R 218, 220.
-- 6 of 7 --
7
1. The notice of appeal is struck out.
2. The appellant pay the respondent’s costs of and incidental to the application on
the standard basis.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2020/146