Brisbane Airport Corporation Pty Limited v Arup Pty Limited [2020] QSC 202
SUPREME COURT OF QUEENSLAND
CITATION: Brisbane Airport Corporation Pty Limited v Arup Pty
Limited [2020] QSC 202
PARTIES: BRISBANE AIRPORT CORPORATION PTY
LIMITED
ACN 076 870 650
(plaintiff/respondent)
v
ARUP PTY LIMITED
ACN 000 966 165
(defendant/applicant)
FILE NO: BS 10025 of 2016
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON: 30 June 2020
DELIVERED AT: Brisbane
HEARING DATE: 22 May 2020
JUDGE: Applegarth J
ORDER: 1. Pursuant to r 483(1) of the UCPR, there be a first trial
of all issues other than and separately from those
concerning:
(a) the quantum of the plaintiff’s claimed damages
for the necessary and reasonable work (if any) to
rectify the NAE (being the issues in paragraphs
44, 61, 62, 64, and 65 of the Further Amended
Statement of Claim and the corresponding
allegations in the Amended Defence and the
Reply);
(b) any issues as to the plaintiff’s failure to mitigate
its loss; and
(c) any issues as to betterment to the plaintiff from
the rectification works, and its quantification.
2. Reserve costs.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – SEPARATE DECISION OR
DETERMINATION OF QUESTIONS AND
CONSOLIDATION OF PROCEEDINGS – SEPARATE
DECISION OR DETERMINATION – OF LIABILITY AND
-- 1 of 16 --
2
DAMAGES – where the defendant applies for a separate trial
on liability issues – where the dispute concerns alleged defects
in the design of an airport apron and taxiway where both
liability and quantum are contested – where the quantum case
is in a state of flux due to uncertainties about early rectification
works and altered operational restrictions related to reduced
air traffic during the COVID-19 pandemic – whether a
separate trial on liability would result in savings in time and
costs to both parties – whether a separate trial on liability
would enhance the prospects of resolution – whether a
separate trial on liability would be just and convenient
Uniform Civil Procedure Rules 1999 (Qld), r 483(1)
Advance Traders Pty Ltd v McNab Constructions Pty Ltd
[2011] QSC 212, cited
Byrne v People Resourcing (Qld) Pty Ltd [2014] QSC 39,
cited
Callide Power Management Pty Ltd v Callide Coalfields
(Sales) Pty Ltd (No 3) [2015] QSC 295, cited
Reading Australia Pty Ltd v Australian Mutual Provident
Society (1999) 240 FCR 276; [1999] FCA 718, cited
COUNSEL: G D Beacham QC, with M H Martinez, for the
plaintiff/respondent
S L Doyle QC, with S D McCarthy, for the
defendant/applicant
SOLICITORS: Holding Redlich for the plaintiff/respondent
Schweikert Harris for the defendant/applicant
[1] This is a large and complex case.1 Both liability and quantum are contested. The
present issue is whether or not there should be a separate trial on liability.
Background
[2] In 2002 Brisbane Airport Corporation (“BAC”) entered an agreement with Arup in
relation to engineering consultancy services at the Brisbane airport. By 2004 BAC
had developed a proposal to expand the apron and taxiway of the northern concourse
of the Brisbane International Terminal. The project became known as the Northern
Apron Expansion (“NAE”) project. In the following years Arup provided
geotechnical, engineering and other services to BAC pursuant to certain retainers.
Construction of the NAE commenced in 2006 and was completed in 2008.
[3] In December 2010 BAC first identified significant cracks in the NAE. In the years
that followed, BAC, Arup and others investigated their cause.
1 Some of the issues that existed at the time are identified in Brisbane Airport Corporation Pty Ltd v
Arup [2017] QSC 232.
-- 2 of 16 --
2
[4] On 29 September 2016 BAC sued Arup for negligence and, in the alternative, for
contravention of the Trade Practices Act 1974 (Cth) arising out of alleged
representations in relation to the design of the NAE.
[5] BAC alleges that Arup’s design of the NAE is defective in five respects, and that
extensive works are required to rectify each of those defects.
[6] If Arup is found liable in any one or more of these five respects, then the basis of its
liability and the nature of the defect will be relevant to the extent of rectification
works required to address the particular defect and therefore the quantum of damages
to be awarded to BAC.
[7] A major and contentious aspect of BAC’s quantum claim is the staging of rectification
works. The cost of the rectification scheme which it claims is based upon a proposed
program of work in the cracked area of the pavement (Phase 1 Works) and the
uncracked areas (Phase 2 Works). The sequencing and cost of undertaking this work
depends on operational restrictions that BAC has instructed its experts to assume.
[8] In essence, the operational restrictions relate to the alleged inability to close bays or
taxiways to perform work otherwise than in “off-peak” periods and only allowing the
contractor to work on one front or stage at any one time. As I understand the matter,
the presently proposed rectification plan involves work during off-peak periods and
divides repair areas into conventional and “expedient” construction zones. The
expedient zone is where there will be limited time to place and cure the concrete
before the area must be reopened to aircraft traffic at the end of each construction
shift. That work can only be undertaken during this limited period requiring, at
considerable expense, equipment to be moved in and out of the zone for each shift.
In addition, these time limits require a form of concrete which sets more quickly and
is more expensive. These time and other requirements substantially increase the cost
of rectification.
[9] Arup contends that BAC’s presently formulated quantum claim and its instructions
to its experts are premised on operational restrictions that no longer exist because of
the COVID-19 pandemic.
[10] Arup applies for a separate trial on liability. More precisely, it seeks orders pursuant
to r 483(1) of the UCPR for there to be a trial first of all issues other than and
separately from the following issues:
(a) the quantum of BAC’s claimed damage for the necessary and reasonable work
(if any) to rectify the NAE;
(b) any issues as to BAC’s failure to mitigate its loss; and
(c) any issues as to betterment to BAC from the rectification works, and its
quantification.
(collectively, the “Remaining Issues”).
For simplicity I refer to the application as one for a separate trial on liability.
[11] Arup submits that it is just and convenient to order a separate trial on liability because:
(a) BAC, in light of the COVID-19 pandemic and the resultant reduction in air
traffic, is contemplating performing early rectification work which would result
-- 3 of 16 --
3
in changes to important assumptions underpinning its current quantum
evidence concerning operational restrictions imposed on the works. The extent
of any such work, the extent of any relaxed operational restrictions, the
programming, sequencing and ultimate cost of the works, and the extent of any
remaining issues as to mitigation of loss are all unclear and will not be clarified
so as to permit the preparation of new evidence until a wholly uncertain time
in the future.
(b) Whether or not BAC undertakes early rectification work, the scope and extent
of a trial on the Remaining Issues depend upon the Court’s findings as to
liability. If Arup succeeds at a liability trial, there will be no occasion for a
trial on the Remaining Issues. Assuming some measure of success for BAC, a
liability trial will determine, with certainty, the defects (if any) and the area of
the pavement to which those defects apply. On the other hand, a trial on all
issues now will require the parties to address (at significant cost) a multitude
of rectification possibilities, some of which will be made irrelevant by the
Court’s findings on liability.
(c) Overall, there are good reasons to make the orders sought.
[12] BAC opposes Arup’s application for a separate trial on liability, contending that:
(a) the prospect of time and cost savings is of limited weight – there is uncertainty
whether and to what extent such savings would be achieved, and savings on the
preparation of expert evidence as to quantum will accrue only to Arup (BAC
having delivered its evidence already);
(b) there is a real probability that a separate trial will delay the proceeding as a
whole;
(c) overall, a separate liability trial will inhibit rather than encourage settlement;
and
(d) the separate trial will be lengthy, require the determination of contested factual
issues, and involve experts who will also give evidence in the quantum case.
The issues
[13] The general issue is whether it is just and convenient to make the order. Consistent
with r 5 of the UCPR and the authorities governing applications of this kind, the Court
should ensure the efficient and timely resolution of the case, consistent with doing
justice to both sides.2 I would add that the interests of justice also require
consideration of the appropriate and efficient use of finite judicial resources.
[14] More specifically, the parties’ submissions raise the following issues:
1. Does the current uncertainty as to early rectification work and altered
operational restrictions because of reduced air traffic during the COVID-19
pandemic and its aftermath favour a separate trial on liability over a trial of all
issues?
2 Callide Power Management Pty Ltd v Callide Coalfields (Sales) Pty Ltd (No 3) [2015] QSC 295 at
[44] (“Callide”).
-- 4 of 16 --
4
2. Is a separate trial on liability likely to enhance or reduce the prospects of
resolving the Remaining Issues, and thereby avoid a trial of the Remaining
Issues, or at least reduce its length?
3. Is the prospect of savings of time and costs relied upon by Arup outweighed by
the prospect of a delay in the proceedings as a whole and other disadvantages,
such as the calling of expert witnesses at the separate trials?
Relevant principles
[15] The principles governing the discretion to make an order under r 483 of the UCPR
are not in dispute. They have been canvassed in a number of authorities.3 These
decisions affirm the utility of orders for the determination of a separate question in
appropriate cases.
[16] The starting point is that generally all issues of fact and law in a matter should be
determined at one trial. The ultimate question is whether it is just and convenient to
make an order for separate determination. A cautious approach should be adopted in
deciding to order a separate trial.4
[17] Granting an order for determination of a separate question can avoid the necessity for
a lengthy trial, or reduce a trial’s length. However, care must be taken in ensuring
that having separate trials of different issues is not productive of delay, additional
expense, appeals and uncertainty.5 If the effect would be to prolong rather than
shorten the litigation, this will be a factor tending against the determination of a
separate question.6
[18] An order for the determination of a separate question may be just and convenient
where the separate determination will contribute both time and cost savings by
substantially narrowing the issues in dispute, or where the separate determination
could lead to disposal of the action or settlement of the litigation.7 An order may also
be appropriate to avoid the necessity for a lengthy trial or at least to reduce the
expected length of a trial.8
[19] Determination of a separate question at a preliminary trial is unlikely to be just and
convenient where there is a significant overlap of factual and legal issues at both
stages of the hearing. This is especially so if the same witnesses will need to be called
at both hearings of the proceedings, particularly if the Court is asked to form a view
as to the credibility of such witnesses.9
[20] The prospect of a significant saving of time and cost, while a relevant consideration,
is not determinative. In a case such as this, a decision about whether it is just and
convenient to make an order under r 483 involves a balancing exercise, weighing
factors that favour an order against factors which do not. The third issue which I have
identified above involves this kind of weighing process.
3 Reading Australia Pty Ltd v Australian Mutual Provident Society (1999) 240 FCR 276 (“Reading”) at
279-280; Advance Traders Pty Ltd v McNab Constructions Pty Ltd [2011] QSC 212; Byrne v People
Resourcing (Qld) Pty Ltd (“Byrne”) [2014] QSC 39.
4 Callide at [46].
5 Byrne at [3], citing Perre v Apand Pty Ltd (1999) 198 CLR 180 at 332 [436].
6 Reading at 280 [8].
7 Reading at 279 [8].
8 Byrne at [3].
9 Reading at 280 [8].
-- 5 of 16 --
5
[21] That balancing exercise is undertaken on the basis of what is known at the time of the
application and what can be reliably predicted at that time about the future course of
events. Assumptions about matters such as prospective savings and the expected
timing of trials may be falsified. In such an event, it may be possible, if an order for
separate trials is shown to no longer have the utility originally expected, for the order
to be vacated and for the trial to proceed to determine all issues. Pragmatic
considerations in such a case and the interests of justice may lead to a different order
being made and for the trial of all issues to be conducted in the conventional way, or
in brackets of evidence. This may be so if it is just and convenient to have a bracket
of evidence on liability, followed by a bracket of evidence on quantum. A suitable
but not lengthy separation between those parts may facilitate the orderly preparation
and efficient conduct of the second part of the trial, and also allow settlement to be
explored in the light of the evidence given in relation to liability.
[22] The practice of ordering separate trials and then later vacating that order should be
rare, since it undermines the finality of decisions and may be productive of
unnecessary costs. However, changed circumstances which clearly falsify
assumptions upon which an order for a separate trial were made may make it just and
convenient to revisit the making of such an order in the light of significantly changed
circumstances. They may require a new balancing exercise to be undertaken to decide
whether it remains just and convenient to have separate trials.
Alleged defects and their proposed rectification
[23] As noted, BAC alleges that Arup’s design of the NAE is defective in five respects.
Its case is that these alleged defects involved a breach of duty and that each defect
requires extensive rectification works. The following table, which is based upon the
evidence of BAC’s expert, identifies the alleged defect and BAC’s case as to the
required rectification works.
Alleged Defect in the statement of claim Element of BAC’s pleaded rectification
works
Arup specified 400mm for the concrete
thickness of the panels, whereas BAC
alleged that it ought to have been 520mm
(par 48(a))
A combination of 525m thick panels, with
640mm thick expedient concrete in zones
where there will be limited time to place
and cure the concrete before it must be
reopened to aircraft traffic at the end of
each construction shift
Arup did not adequately compact the sand
subgrade (par 48(b)) permitting it to
become further compacted under aircraft
loads
Sand improvement works to increase the
density of the lower 1 metre of sand by the
use of polyurethane resin grout injections
in two stages – the cracked area of the
pavement (Phase 1) and the uncracked
area of the pavement (Phase 2).
Additionally, the inclusion of sub-surface
drainage is said to become “critical”
because the polyurethane injections
reduces the permeability of the sand and
so that water does not back-up in the
upslope portions of the NAE
-- 6 of 16 --
6
Arup did not specify sub-soil drainage
(par 48(c))
A new unlined open drain along the
eastern edge of the NAE, subsoil
perimeter drains in the Phase 1 area, and
the use of a joint sealant to impede the
entry of surface water
Arup specified panel sizes (length x
breadth) of approximately 7m x 7m
whereas it ought to have specified
dimensions of no greater than 6m (par
48(d))
Replacement of the concrete panels with
5m x 5m panels
For the panels on the eastern edge of the
NAE, Arup specified reinforcing tie-bars
of 36mm diameter at 375mm centres,
whereas it ought to have specified 16mm
diameter bars at 750-760mm centres (par
48(e))
Specification of 16mm bars at 750-760mm
centres
Arup’s case on potential costs savings
[24] Counsel for both parties helpfully prepared a trial plan based on certain working
assumptions about the presentation of lay and expert evidence. Their estimate is that
a separate liability trial will take 15 days and a separate quantum trial will take 16 and
a half days. The evidence from Arup is that a trial on the Remaining Issues which
occupies 16 days will cost it alone approximately $1.9 million. The cost to BAC of
conducting a 16 day trial on the Remaining Issues has not been estimated, however,
is likely to be substantial.
[25] Arup notes that if it succeeds entirely on the liability issues, there will be no occasion
for a trial on the Remaining Issues. That is said to be a powerful consideration in
favour of a separate trial being ordered.
[26] Next, Arup submits that if a liability trial establishes some but not all of the alleged
defects, then the relevant defects will be identified and the aspects of the rectification
work and associated direct and indirect costs for alleged defects in respect of which
liability is not found should fall away. Its argument is that the multitude of
rectification possibilities will be reduced by the Court’s findings on liability to a
certain and defined set of issues. The length of, and the legal costs associated with,
the trial of the Remaining Issues should reduce accordingly.
[27] Arup also submits that BAC may succeed only in respect of its case on the current
cracking but fail to establish that the balance of the pavement will not last the 40 year
design life. On that basis, the area of the rectification works would be identified (and
limited to the cracked bays), and the scope of the works would be determined by the
extent of defects found to have caused the cracking.
[28] Pavement thickness is not alleged to be a cause of the current cracking, whereas it is
alleged to be a cause of the future cracking. If the Court found that pavement
thickness was the only defect, then conceivably some aspect of the Phase 2 Works
would be required, but not any of the Phase 1 Works.
[29] The expected life of the pavement and the resultant contention (and assessment) as to
betterment is submitted by Arup to likely vary depending upon what rectification
-- 7 of 16 --
7
work is found to be reasonably necessary in light of the defects (if any) found on the
issue of liability.
[30] In general, Arup submits that a trial on liability will determine, with certainty, the
defects (if any) and the area of the pavement to which those defects apply.
[31] On the other hand, if there is one trial on all issues, the parties’ experts will be required
to consider and address:
(a) Arup’s rectification scheme for monitoring and replacing cracked panels only
when necessary;
(b) the rectification works if each of BAC’s alleged defects is established;
(c) the rectification works if one or a combination of alleged defects are found (but
not all of them);
(d) the rectification works if both the Phase 1 Works and Phase 2 Works are
required, in circumstances where one or the other may (depending upon
liability findings) not be required;
(e) the cost of the works applicable to each of the possible rectification scenarios;
and
(f) the impact of the (presently uncertain) operational and staging restrictions
applicable to each of the possible rectification scenarios.
[32] BAC responds to Arup’s arguments about potential savings by acknowledging the
potential time and cost savings that may result from having issues of liability tried
first. If, for example, Arup was to succeed on liability (either at trial or on appeal),
both parties would be saved the costs of preparing for and conducting a quantum trial
which is estimated to take 16 and a half days. However, BAC submits that the extent
of time and cost savings pointed to by Arup are uncertain and that this diminishes the
weight of this consideration. For example, there is no estimate of how much time or
cost would be saved if Arup’s experts were required to consider some but not all of
the elements of BAC’s rectification design. BAC suggests that the savings may be
relatively small if the experts will have to consider two or three of the five elements.
The cost savings which would occur if all liability issues were determined against
BAC must be balanced against the uncertain amount of savings if BAC succeeds on
all or most of its defect claims.
[33] BAC also contests Arup’s argument that there are multiple “rectification scenarios”
which will be reduced in number with consequential significant savings if there is a
separate liability trial. According to BAC, rather than there being multiple
“rectification scenarios”, there is rectification work comprising various elements and,
depending upon the Court’s finding on liability, Arup may not be liable for the cost
of all of the elements. BAC submits that, in that event, it will be necessary to exclude
certain costs, for example, by the excision of parts of the expert evidence where costs
have been differentiated between each element of the rectification design. It gives
the example that if BAC failed on the contention regarding the thickness of the
concrete (the first row in the table), the cost of additional concrete to make thicker
panels would be removed from the quantum award.
[34] Some of BAC’s submissions in this regard have force. However, I am not presently
satisfied that Arup’s arguments about a liability trial reducing a multitude of
-- 8 of 16 --
8
rectification possibilities are answered by the possibility of undertaking a simple
excision exercise. There may be a different rectification program and methodology,
depending upon the relevant defect that is found, and what is required to rectify it. It
is not apparent to me that the method or program for carrying out works if all of the
defects are established in respect of the whole of the area would be the same program
or methodology that might apply to address fewer defects or defects over a smaller
area.
[35] The most demonstrable costs savings relate to a possible confining of BAC’s case on
quantum in a geographic sense to the area of current cracking if it fails to establish
that the balance of the pavement is defective and will not last a 40 year design life.
However, costs savings are likely to arise in preparation for and in the conduct of a
quantum trial if an earlier liability trial identifies the defects (if any) for which Arup
is liable. This will focus attention on the steps required to rectify that defect. It will
make the quantum case less complex and is likely to substantially reduce the length
of the trial of quantum issues and the legal costs associated with preparing for it.
[36] I conclude that there will be a substantial saving of time and costs if liability is
resolved entirely in Arup’s favour (either at trial or on appeal). If, however, Arup is
found liable in respect of some but not all of the alleged defects, then there will still
be a substantial, albeit uncertain, costs saving. If Arup is found liable in respect of
all the defects then the costs savings in respect of any quantum trial will be far less.
However, on any scenario under which Arup is found liable for at least some defects,
a separate trial may have other benefits in facilitating settlement, which I will later
address.
[37] I am persuaded that Arup’s proposal will reduce the costs to the parties of preparing
for a trial on all issues in which experts and others will be required to consider a
multitude of rectification possibilities. The substantial costs of a quantum trial may
be avoided altogether. However, if the liability trial finds Arup liable in some respects
then there is likely to be a significant saving of costs in preparation for and in the
conduct of a trial of the Remaining Issues.
[38] BAC argues that the identified savings that will result in relation to the preparation of
expert evidence as to quantum will only accrue to Arup, BAC having delivered its
evidence already. As a result, it submits that any time and costs savings would accrue
disproportionately to Arup. BAC would enjoy some time and costs savings if the
quantum trial was truncated. It acknowledges that there would be a similar benefit in
the reduction in the use of the Court’s time.
[39] I am not persuaded that the fact that BAC has already incurred significant costs in
preparing its quantum evidence, whilst Arup has yet to deliver much of its quantum
evidence, makes it unjust to make an order which is likely to achieve an overall costs
saving. To the extent that Arup would save the costs of preparing quantum evidence
in the coming months, that saving may eventually accrue to BAC’s benefit if Arup
succeeds entirely on liability or successfully defends some parts of BAC’s claim. In
any case, it does not deflect from the broader point of the potential costs savings to
both parties of avoiding or at least reducing a quantum trial which is estimated to take
16 and a half days.
[40] Further, and for reasons to be explored in connection with the next topic, some of the
costs which BAC has incurred in preparing its case on quantum may be wasted if
-- 9 of 16 --
9
earlier and different rectification work is undertaken as the result of a reduction in air
traffic.
[41] I conclude that a separate trial on liability has the prospect of resulting in substantial
savings of time and costs. The costs savings are likely to be in the order of millions
of dollars if a quantum trial is avoided altogether. They are still likely to be significant
if the rectification issues become focused and reduce in number in the light of findings
on liability.
The case on quantum is in a state of flux
[42] Arup argues that the current uncertainty as to early rectification work and altered
operational restrictions because of reduced air traffic favours a separate trial on
liability. According to Arup, the extent of evidence required for a trial on the
Remaining Issues depends upon the presently uncertain extent of (and in any event,
controversial) operational restrictions imposed on the performance of any
rectification works.
[43] As noted, the reduction in air traffic as a result of the COVID-19 pandemic has
prompted BAC to contemplate early rectification work. The extent of any such work,
the extent of any relaxed operational restrictions and, as a result, the ultimate cost of
the works remain uncertain. Arup argues that these matters will not be clarified so as
to allow for the preparation of evidence until a wholly uncertain time in the future.
[44] At the time of the hearing before me on 22 May 2020, BAC had been carefully
considering whether it would be able to undertake certain rectification work on the
NAE with the rectification of defective slabs occurring whilst aircraft movements on
them are reduced. Such an early rectification plan had the benefit of minimising the
need for complex staging requirements to ensure minimal interruption to the
operation of the airport. A decision on the early rectification plan involved many
considerations. At the time of the hearing of the application I was advised that if the
early rectification plan proceeded it would require a number of stages of approvals
and planning processes, like any other project undertaken at the airport.
[45] I indicated that I would be prepared to receive further evidence if a decision was made
to proceed with the early rectification plan. A supplementary affidavit filed on 11
June 2020 indicated that BAC’s Chief Executive Officer had endorsed the early
rectification plan to proceed to the “design and approval phase”. BAC is preparing
its procurement strategy and tender documents to engage a contractor. It is currently
negotiating with a party to develop a concept design. If the final design is progressed,
there will be an initial tender for works. Approval will be required from BAC’s Board
for the capital expenditure. BAC currently expects that the final design for
construction will be completed by the end of September 2020 and currently expects
to finalise a construction contract in either October or November 2020.
[46] Of course, unexpected developments may prompt BAC to alter its plan to undertake
early rectification. However, assuming it proceeds as expected, new quantum
evidence will be required. The current assumptions underpinning BAC’s expert
evidence and quantum evidence will be altered. However, until at least the
construction contract is awarded in late 2020, no-one will know the extent of the
works expected to be undertaken, their programming and the extent of any relaxed
operational restrictions.
-- 10 of 16 --
10
[47] Therefore, BAC’s quantum case is in a state of flux and is likely to remain uncertain
for a substantial period.
[48] It is unclear whether BAC intends to perform some or all of the rectification work it
pleads. The operational restrictions which its experts have been asked to assume for
the purpose of their evidence on rectification and the cost of rectification cannot be
safely assumed in the light of changed circumstances. It seems wasteful of time and
costs for the parties to prepare for a trial involving quantum issues which are founded
upon assumed operational restrictions that reflect a substantial component of the costs
of rectification. Proceeding to a liability trial avoids a large waste of time and costs
which would be incurred by addressing not only a multitude of rectification
possibilities, but also rectification scenarios based on operational restrictions which
are likely to be altered and replaced by an early rectification plan.
[49] BAC submits that if it decides to proceed with the early rectification work, then the
quantum case becomes simpler and this in fact favours having a trial on all issues in
2021. It argues that if a contract is awarded in late 2020 then it will be the contract
price and the actual cost that will determine the basis for its quantum case. There will
be an actual contract cost based upon actual staging restrictions. It submits that the
matter would still be capable of being tried in 2021, although not as early as a liability
trial could be conducted.
[50] I accept that the letting of a contract to undertake certain rectification works is likely
to alter and simplify BAC’s quantum case. However, a number of issues will remain,
possibly until after a contract is awarded and a proposed program of works is fixed.
[51] In opposing the present application BAC points out that a liability trial will not resolve
the current controversial issues concerning the staging of rectification and the extent
to which operational restrictions and their cost can be mitigated. However, even if a
contract is let in October or November 2020 which defines the extent of rectification
work and its staging, there remains a real prospect that the staging of works and
operational restrictions will remain an issue. Just as Arup presently argues that
BAC’s current quantum fails to work around assumed operational restrictions, there
is a prospect that a similar issue will arise in respect of an early rectification plan.
[52] In any event, even if these matters do not emerge as substantial issues after an early
rectification plan is adopted, the fact that BAC’s case on quantum is in a state of flux
favours, in my view, an order for a separate trial on liability. If a contract is let with
a different program of works than that assumed for the purpose of assessing quantum
in this case, then this will require consideration by experts on both sides. Arup is
likely to require disclosure of documents in relation to the program of works, the
occupation of premises and departure lounges and the extent to which then known
and reasonably predicted operational restrictions affect the undertaking of early
rectification works.
[53] In my view, the uncertainties presented by the changed operational environment and
the processes involved in awarding any contract for early rectification works makes
it very unlikely that a trial of quantum issues can be conducted in 2021.
[54] More generally, it seems entirely wasteful of costs to require Arup to respond to
BAC’s current case on rectification and quantum when, in all likelihood, changes in
operations at the airport and an early rectification plan will require BAC to
substantially amend its quantum claim.
-- 11 of 16 --
11
[55] I conclude on the first substantial issue that the current uncertainty as to early
rectification work and altered operational restrictions because of reduced air traffic
during the COVID-19 pandemic and its aftermath favours a separate trial on liability.
Will a separate trial prolong the proceeding as a whole?
[56] If a separate trial on liability (and any appeal therefrom) resolves the issue of liability
entirely in Arup’s favour then that will shorten the proceeding as a whole by obviating
the need for a trial of the Remaining Issues, currently estimated to take 16 and a half
days.
[57] If a separate liability trial resolves liability issues in BAC’s favour, then it may
facilitate resolution of the Remaining Issues by way of settlement so as to obviate the
need for a separate trial of the Remaining Issues. It will at least shorten the length of
any trial of the Remaining Issues. However, a separate trial on liability creates the
real prospect that the proceeding as a whole will be delayed.
[58] BAC estimates the length of the proceeding under different scenarios as follows:
Year/month Separate trial of liability Trial of all questions
2021
March Trial on liability
June Judgment Trial
December Appeal Judgment
2022
March Decision on appeal
July Appeal
December Trial on quantum Decision on appeal
2023
March Judgment
September Appeal
December Decision on appeal
Obviously, this table is based upon assumptions about the availability of trial dates
and that appeals are likely. The parties accept that a decision on liability is likely to
be appealed because of the substantial quantum that would either follow a finding on
liability, or be unrecoverable because of a dismissal of the liability case. A substantial
judgment on quantum also carries the likelihood of an appeal.
[59] The table helpfully prepared by BAC necessarily relies upon fairly general estimates
and, save in a few respects, Arup does not dispute that it provides a foundation for
-- 12 of 16 --
12
comparison. Arup does, however, contest the table’s assumption that a trial on all
issues could be prepared between now and June 2021. This is submitted to be a very
optimistic estimate, particularly because of the early rectification issues which will
require a revised round of pleadings, disclosure and expert reports. Even on the
existing directions, certain expert reports will not be finalised until 30 September
2020. If, as must be presently assumed, BAC proceeds with its early rectification
work, then the preparation of quantum evidence could not usefully commence until
the scope of the work and the operational assumptions, including operational
restrictions, are known. These are unlikely to be known until late 2020 at the earliest.
Therefore, I accept Arup’s submission that BAC’s table is excessively optimistic as
to when a trial on all issues could be prepared and heard.
[60] If a separate liability trial is ordered and if liability was not established following any
appeal, then the whole proceeding might end, according to this timetable, in around
March 2022. If there is a trial on liability followed by a trial on quantum in late 2022,
followed by an appeal from the quantum judgment, the whole proceeding might end
in late 2023. If, however, there is a trial of all issues, followed by an appeal, then the
proceedings would be likely to end sometime later than BAC estimates. On a very
optimistic view, any appeal might be decided by late 2022. It is more likely that the
proceeding would end with a decision on an appeal in early 2023. This would be
earlier than the alternative separate trials scenario which would have a decision on
appeal concerning quantum in late 2023.
[61] Therefore, I accept that there is a real prospect that a separate trial will delay the
proceeding as a whole as well as some prospect that a separate trial may, depending
on its outcome, lead to the whole proceeding ending earlier than for a trial on all
issues. The former seems a more likely prospect. Therefore, the risk of prolongation,
overall, tends to favour a trial on all issues.
Which course is more likely to enhance the prospects of resolution?
[62] Arup submits that an order for a separate trial will, as a consequence of any trial on
liability, increase the prospects of settlement. The parties have already conducted a
mediation over a couple of days, assisted by a joint expert report on liability. Arup
submits that the outcome of a trial on liability, even if there is an appeal, is likely to
make settlement easier to achieve. Without a trial of liability issues, the parties are
likely to remain diametrically opposed on their assessment of liability.
[63] In response, BAC submits that Arup has not delivered its quantum evidence and if it
was not required to deliver its quantum evidence until mid to late 2022, there would
be no capacity for the parties to meaningfully engage on quantum, there being no
alternative case on rectification and no alternative quantum. BAC accepts that while
a judgment on liability would remove one significant point of contention, it would
leave the highly contentious issue of quantum standing in the way of any settlement.
It argues that the prospect of a trial on all issues ought to have the effect of focusing
both parties on the risk of an adverse outcome, and is therefore more likely to lead to
a settlement.
[64] Both parties’ arguments have merit. I infer that the parties have been unable to
resolve the matter to date because they have significantly different assessments of
BAC’s prospects on liability and also the realistic quantum of its claim. As a general
rule, if parties have different assessments of prospects on both liability and quantum,
then this makes a case much harder to settle than if they have a broadly similar view
-- 13 of 16 --
13
on at least one of those issues. Although the provision of Arup’s expert evidence may
better inform both parties on the issue of quantum, the lines of disagreement are
essentially known to each other by virtue of the pleadings and their current evidence.
I apprehend that a major issue in relation to quantum are the assumptions about
operational requirements upon which BAC’s case is based. Those operational
requirements have changed in the light of reduced air traffic and therefore the parties
must await the evolution of BAC’s revised case on quantum in the light of those
changed circumstances and the distinct possibility of early rectification work.
[65] BAC correctly accepts that a trial on liability (and any appeal from it) will have an
effect on settlement because it will remove that significant issue between the parties.
It seems unlikely that the evidence on quantum will be available until well into 2021.
In my view, the prospects of settlement will be enhanced if there is a liability trial as
soon as reasonably possible, ideally in the first half of 2021. For the reasons already
discussed, if liability is established on a certain basis then this will inform the defects
for which Arup is legally liable and focus the case in relation to rectification costs for
which it is liable.
[66] Overall, I consider that a separate trial on liability is likely to enhance the prospects
of resolving the Remaining Issues by settlement. If the resolution of liability issues
does not result in a settlement of the case, it will at least narrow the remaining issues
and reduce the cost of preparing for a trial of the remaining issues and that trial’s
length.
Other issues
[67] Arup submits and BAC accepts that there is no overlap of issues of substance in the
proposed two stages of hearing. As noted, counsel for the parties have agreed a trial
plan based on all issues presently in dispute. There is only one topic that is common,
namely the work performed by way of maintenance on the cracked panels. That topic
is relevant to contributory negligence and also to the quantum trial as the factual basis
for a reduction in damages.
[68] This is not a case in which the honesty of any witness is likely to be an issue.
However, if separate trials are ordered the expert engineers (Dr Rollings and Mr
Woodman) and one lay witness for BAC will need to give evidence at both trials.
There is no overlap of Arup’s lay witnesses. Although their honesty is not likely to
be in issue, the need to recall the two experts is a factor against the making of an
order. That factor is not, however, of the same significance as a case in which credit
issues arise. Moreover, as I mentioned at the hearing of this application, it occurs to
me that the task confronting an expert witness in having to give evidence over a
number of consecutive days both in relation to the adequacy of the design (liability
issues) and the rectification issues (quantum) is significant, as is the task upon the
cross-examiner. The effective presentation of the experts’ evidence and the effective
exploration of different aspects of their evidence might be enhanced somewhat by the
expert not being required to give continuous evidence on all issues.
[69] The fact that the liability trial will be lengthy and involve contested factual issues
makes ordering a separate trial less attractive than it would be if the prior, separate
determination involved a point of law such as an issue of contractual interpretation or
some other point of law. Nevertheless, where there is hardly any overlap between
issues of liability and quantum and the trials can be separated, the unfortunate
-- 14 of 16 --
14
requirement for the experts to give evidence at both trials is not said to be
determinative of the application.
[70] BAC does not submit that it will be prejudiced by any delay that results from having
separate trials. It does not contend that it cannot afford the cost of rectification and
there is no suggestion that Arup could not meet any judgment, including interest. The
possibility of being compensated by an award of interest for delay is not a complete
answer. Justice is best achieved by the expeditious resolution of issues without delay.
That said, this is not a case in which evidence is likely to be lost through some
additional delay. It should be recalled that although cracks were identified in
December 2010, it was not until 29 September 2016 that BAC commenced these
proceedings. The proceeding having been delayed in its commencement, and having
had a necessarily complex interlocutory course, further delay is undesirable.
However, in the overall scheme of matters, and in the current state of flux concerning
BAC’s quantum, the additional delay, if any, produced by an order for separate trials
is not so prejudicial to BAC as to make it unjust or inconvenient to order separate
trials.
Is the prospect of savings of costs and time by ordering separate trials
outweighed by the prospect of a delay in the proceedings as a whole and other
disadvantages?
[71] On balance, I consider that the interests of justice and doing justice to both parties
favours ordering a separate trial on liability. That course carries the prospect of
significant costs savings. Such a course will resolve liability (subject to any appeal
on liability). By that time BAC’s quantum case will be clearer than it presently is or
is likely to be for some substantial time until at least a contract for early rectification
works is let and the program of works and their cost is assessed, pleaded and
considered by Arup. One apparent reason as to why the proceedings have not settled
to date is because of uncertainty on issues of both liability and quantum. A separate
trial on liability, preferably conducted in the first half of 2021, will remove one
significant element of uncertainty and thereby help facilitate resolution of the
Remaining Issues by settlement or a shortening of any quantum trial.
[72] Some factors weigh in favour of having a trial of all issues. However, with BAC’s
quantum case in a state of flux, such a trial is unlikely to be ready for some substantial
time. In my view, it is just and convenient to conduct a liability trial before then. The
prospect of savings of time and costs, and also facilitating settlement, favours a
separate trial on liability. These considerations, in my view, and the other matters
relied upon by Arup outweigh the risk that a separate trial will delay the conclusion
of the proceeding as a whole and the other disadvantages to which BAC points.
[73] The uncertainty injected in relation to quantum by the prospect of early rectification
work and its significant implications for the preparation and conduct of a trial on
quantum favour a separate trial on liability. It would be wasteful of costs and time to
require Arup to prepare evidence, including expert evidence, in the coming months
to respond to BAC’s case on quantum as presently pleaded and formulated. That case
is bound to change because of altered operations at the airport and the real prospect
of early rectification work. The need to avoid wasted costs on quantum issues which
are almost certain to change is a factor which strongly favours ordering a separate
trial on liability.
[74] Overall, I conclude that it is just and convenient to order a separate trial on liability.
-- 15 of 16 --
15
Other matters
[75] If the assumptions upon which this decision is based are falsified by subsequent
events and there is a significant change in circumstances, it may be possible for a
different decision to be made concerning the trial of the Remaining Issues. If, for
example, quantum issues suddenly became clearer or narrowed to a significant extent
so as to allow a quantum trial to be conducted in 2021, then the Court would be open
to reviewing the staging of the trial. However, as presently advised, the parties should
proceed on the basis that there will be separate trials and seek any further directions
which are required in order to have the matter set down for a 15 day liability trial in
the first half of 2021.
[76] Subject to any submissions as to the form of order, there will be an order for a separate
trial in the terms of Arup’s application.
[77] On the question of costs, my preliminary view is that the costs of and incidental to
the application should be costs in the proceedings or at least Arup’s costs in the
proceedings so as to reflect its measure of success in obtaining orders which were
opposed. BAC sought its costs in the event the application was dismissed.
[78] Presently I intend to reserve costs. If the parties agree an appropriate order as to the
costs of the application, then I will make such an order. Otherwise, either party may
seek to make short oral submissions on costs at the next review. The costs of the
application will remain reserved until the issue is raised at any review hearing or at
the conclusion of the trial, at which point the parties and the Court will be better
informed as to whether predictions made by the parties in their submissions were
justified.
[79] The parties should submit any agreed directions to progress the matter to a trial. If
they cannot agree directions then I will review the matter on the earliest mutually
convenient date.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2020/202