BGM Projects Pty Ltd v Durmaz Corporation Pty Ltd [2020] QSC 88
SUPREME COURT OF QUEENSLAND
CITATION: BGM Projects Pty Ltd v Durmaz Corporation Pty Ltd [2020]
QSC 88
PARTIES: BGM PROJECTS PTY LTD
(Applicant)
v
DURMAZ CORPORATION PTY LTD
(Respondent)
FILE NO/S: BS No 5934 of 2019
DIVISION: Trial Division
PROCEEDING: Application
DELIVERED ON: 24 April 2020
DELIVERED AT: Brisbane
HEARING DATE: 27 November 2019
JUDGE: Brown J
ORDER: The Respondent pay the Applicant’s costs of and incidental
to the Application, including the appearances on 4 June
2019 and 27 November 2019, as agreed, and failing
agreement, to be assessed on an indemnity basis.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – GENERAL MATTERS
– INDEMNITY COSTS – where an injunction was granted
prohibiting the pouring of a concrete slab – where costs were
reserved – where the respondent poured the concrete slab with
the knowledge of the injunctive order – whether costs should
be awarded on an indemnity basis
Colgate-Palmolive Co v Cussons Pty Ltd (1993) 46 FCR 225,
followed
COUNSEL: S Keim SC with R Quirk for the Applicant
The Second Respondent appeared on his own behalf and for
the First Respondent
SOLICITORS: Clinton Mohr for the Applicant
The Second Respondent appeared on his own behalf and for
the First Respondent
[1] BGM Projects Pty Ltd (BGM) seeks the costs of its application including costs
reserved before Applegarth J on an indemnity basis on the basis it is entitled to final
relief by way of removal of the shed in Brisbane Supreme Court File 12878/19.
-- 1 of 3 --
2
[2] In the judgement for the related proceeding 12878/19, I have set out the relevant
background to this matter and made findings that the Building Covenants were
binding upon Durmaz Corporation Pty Ltd (Durmaz Corporation). In that
proceeding I have refused to order the removal of the concrete slab, the pouring of
which gave rise to the injunctive relief granted by Applegarth J on 4 June 2019. At
the time of that hearing, his Honour reserved the costs.
[3] However, I am satisfied that the concrete slab was poured contrary to an undertaking
given by Mr Durmaz on behalf of Durmaz Corporation on 28 May 2019 not to
commence construction without approval of the building plans by BGM. The
evidence establishes that Durmaz Corporation was bound by the Building Covenants
and did not seek the consent of BGM to construct the shed. As such, Durmaz
Corporation was in breach of the requirements of the Building Covenants after being
informed by BGM’s solicitors of its obligation to seek consent, and that the
dimensions provided for the concrete slab did not comply with Clause 2.15 of the
Building Covenants. The correspondence of BGM’s solicitors placed the
Respondents on notice that BGM would seek an injunction if Durmaz Corporation
proceeded with construction works without BGM’s approval and that BGM would
seek indemnity costs prior to seeking the interim injunction. Durmaz Corporation has
not taken any action to seek the removal of the Court’s order of 4 June 2019 either on
the basis of compliance with the Building Covenants or to contest BGM’s entitlement
to seek injunctive relief. I have found in proceeding 12878/19 that BGM was entitled
to bring an application for such relief. It is appropriate that BGM have its costs of,
and incidental to, the Application for an interim injunction before Applegarth J on 4
June 2019.
[4] Consistent with the principles for awarding indemnity costs in Colgate-Palmolive Co
v Cussons Pty Ltd1 I am satisfied that it is appropriate to order that the costs of the
application made on 4 June 2019 be paid by Durmaz Corporation on an indemnity
basis given that I am satisfied that Durmaz Corporation, through Mr Durmaz, did pour
the concrete slab notwithstanding:
(a) that he had been advised that he was required to comply with the Building
Covenants;
1 (1993) 46 FCR 225.
-- 2 of 3 --
3
(b) that he was required to obtain approval of BGM for construction pursuant to
clause 6 of the Building Covenants; and
(c) that he had been advised through his solicitors that the shed did not comply
with the dimensions specified in clause 2.15 of the Building Covenants; and
(d) it had given an undertaking to first seek the approval of BGM for its plans as
required by clause 6 of the Building Covenants and having been placed on
notice that an injunction would be sought together with indemnity costs if he
proceeded with construction works.
Order
[5] I order that the Respondent pay the Applicant’s costs of and incidental to the
Application, including the appearances on 4 June 2019 and 27 November 2019, as
agreed, and failing agreement, to be assessed on an indemnity basis.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2020/088