Byrne v Wagner Investments Pty Ltd & Ors [2020] QSC 76
SUPREME COURT OF QUEENSLAND
CITATION: Byrne v Wagner Investments Pty Ltd & Ors [2020] QSC 76
PARTIES: Luke Patrick Byrne
(Applicant)
v
Wagner Investments Pty Ltd (ABN 66 011 055 271)
(First Respondent)
And
Wagners Quarries Pty Ltd (ABN 80 092 751 669)
(Second Respondent)
And
Wagners CFT Manufacturing Pty Ltd (ABN 90 099 936
446)
(Third Respondent)
FILE NO/S: BS 3168/20
DIVISION: Trial
PROCEEDING: Originating Application
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 14 April 2020
DELIVERED AT: Brisbane
HEARING DATE: 30 March 2020
JUDGE: Lyons SJA
ORDER: 1. Pursuant to s 31 of the Limitation of Actions Act 1974
(Qld) the period of limitation in respect of the
applicant’s claim for damages for personal injuries
sustained on 26 October 2016 be extended as against
the first, second and third respondents to 13 February
2021
2. Pursuant to s 43 of the Personal Injuries Proceedings
Act 2002 (Qld) (PIPA) the applicant have leave to
commence proceedings against the first, second and
third respondents
3. The proceedings be stayed until the applicant complies
with Chapter 2, part 1 of PIPA
4. Costs in the cause
CATCHWORDS LIMITATION OF ACTIONS – EXTENSION OR
POSTPONEMENT OF LIMITATION PERIODS –
EXTENSION OF TIME IN PERSONAL INJURIES
MATTERS – KNOWLEDGE OF MATERIAL FACTS OF
DECISIVE CHARACTER – WHAT ARE MATERIAL
-- 1 of 16 --
2
FACTS – where the applicant suffered a chemical burn during
the course of his employment as concrete was being poured at
a railway platform – where the injury resulted in a rare and
serious bone infection which lodged in his spine and resulted
in the fusion of two vertebrae – where the applicant has
commenced proceedings to recover damages for injuries
against his employer and against Wagners EFC as the
manufacturer of the concrete – where the applicant’s limitation
period expired on 26 October 2019 – where the applicant has
applied for an extension of time in which to issue proceedings
and leave to commence proceedings against the first, second
and third respondents – where the applicant must show that a
material fact of a decisive nature relating to the right of action
was not within his means of knowledge until a date after the
commencement of the year last preceding the expiration of the
period of limitation for the action in accordance with s 31(2)(a)
of the Limitation of Actions Act 1974 (Qld) – where the
applicant seeks an extension of time against all the respondents
to 13 February 2021 or in relation to the first and second
respondents, at least until 18 April 2020 – whether a material
fact in the context of this application is the identity of the
parties against whom the right of action lies – whether the
identity of the parties against whom the right of action lies was
known prior to the critical date – whether the limitation period
should be extended
Limitation of Actions Act 1974 (Qld), s 30, s 31
Personal Injuries Proceeding Act 2002 (Qld), s 43
Godden v State of Queensland (2016) 78 MVR 120
NF v State of Queensland [2005] QCA 110
Randel v Brisbane City Council [1984] 2 Qd R 276
State of Queensland v Stephenson [2006] HCA 20
Stephenson v State of Queensland [2004] QCA 483
COUNSEL: R Morgan for the Applicant
K Horsley for the First, Second and Third Respondents
SOLICITORS: Shine Lawyers for the Applicant
Moray & Agnew for the First, Second and Third Respondents
This Application
[1] The applicant was injured during the course of his employment on 26 October 2016
as concrete was being poured at a railway platform at Oakey. He now applies for
an extension of time in which to issue proceedings pursuant to s 31 of the Limitation
of Actions Act 1974 (Qld) in respect of the first, second and third respondents.
-- 2 of 16 --
3
[2] The applicant also applies for leave to commence proceedings against the first,
second and third respondents pursuant to s 43 of the Personal Injuries Proceeding
Act 2002 (Qld) (PIPA) with orders that the proceedings be stayed until the applicant
complies with Chapter 2 Part 1 of PIPA.
[3] The applicant seeks an extension of time against all the respondents to 13 February
2021 or in relation to the first and second respondents, at least until 18 April 2020.
The Incident
[4] On 26 October 2016, the applicant was employed as a concreter by Steve Walk
Concreting (SWC) and had been working for several days at the Oakey Abattoir
(OA) constructing a concrete ramp at a railway siding conducted by Queensland
Rail (QR). Wagners was supplying Earth Friendly Concrete (EFC) to the site. He
received an induction by QR in relation to working near a railway line. No other
induction by any other entity was undertaken at the site.
[5] The applicant states1 that he was standing inside formwork on site when EFC was
poured into that formwork. His boot caught on a piece of reinforcing steel and the
steel penetrated his boot but not his skin. He felt a sharp burning sensation on his
foot. When he removed his boot he saw a damp patch on his sock. He then realised
that he had a chemical burn on his foot as a consequence of concrete entering a hole
in his boot. He states he washed his foot in water from a bucket which contained
concrete residue as there was no fresh running water or any alkaline neutralising
resources available. After washing his foot in the bucket, he put his sock and boot
back on and continued working.
The Injury
[6] The applicant’s foot subsequently became infected and he was placed on antibiotics
and given a medical certificate which indicated that that he was unfit for work for
two weeks. He was subsequently called back to work by his supervisor in mid-
November 2016 and the wound on his foot began to ulcerate from chaffing from his
work boot.
[7] In February 2017, the applicant was experiencing severe back pain and was admitted
to hospital. He was ultimately diagnosed with the rare and serious bone infection
discitis osteomyelitis caused by staphylococcus aureus entering the applicant’s
bloodstream at the site of the burn. It then lodged in his spine and resulted in the
fusion of two vertebrae. Orthopaedic surgeon Dr Leo Zeller’s opinion is that the
source of the infection and likely entry point for the secondary infection is the
wound the applicant suffered as a result of the chemical burn to his foot.2
The History of the Proceedings
[8] The applicant consulted solicitors in relation to compensation on 17 August 2017.
[9] The applicant was notified by WorkCover by letter dated 27 November 2018 that
Dr Zeller had assessed him as having a 23% whole person impairment.
1 Affidavit of Luke Patrick Byrne filed 23 March 2020 at p 3 [13].
2 Affidavit of Roxanne Richards filed 23 March 2020 (court doc 3) at p 3 [10].
-- 3 of 16 --
4
[10] A Notice of Claim for Damages was served on WorkCover on 13 February 20193
and was deemed compliant on 13 March 2019. Accordingly, his limitation period
was preserved.
[11] On 18 April 2019, the solicitors for WorkCover disclosed a number of documents
including the applicant’s timesheets to his solicitors. In the midst of that large
bundle was a document4 with a Wagners logo described as a purchase order. The
company was identified as Wagner Investments Pty Ltd and the document referred
to the supplier as Steve Walk Concreting and the shipping address as Wagners
Quarries Pty Ltd. The buyer was said to be Peter Elwell at Wagner.com.au. The
quantity was described as “one”, and the amount in question was an amount of
$4,695.00. The date of delivery was 25 October 2016.
[12] On 2 May 2019, the applicant’s solicitors requested information from WorkCover’s
solicitors directed to information regarding the EFC. On 11 June 2019, the solicitors
for WorkCover disclosed a safety data sheet for EFC with a print date of 25 August
2017 titled “Material and Supplier Information”. That identified the manufacturer
as Wagners EFC Pty Ltd.
[13] A notice of claim for damages under PIPA was served on Wagners EFC Pty Ltd on
or about 8 July 2019. Part 18 of that Form outlined the reasons why it was
considered that Wagners EFC caused the incident:
“18. DETAIL THE REASONS WHY THE INJURED PERSON
BELIEVES THAT PERSON CAUSED THE INCIDENT
The reasons must particularly identify the step, process or the act/s of the
person that caused the incident and the link to the named respondent (if
different to the person named in response to Q 17):
1. Producing a highly alkaline, caustic and toxic form of concrete with
a high pH and hexavalent chromium [Cr(VI)] which after admixture
with water and through mechanical abrasion produced an
exothermic chemical reaction liable to expose workers to concrete
burns.
2. Failing to provide any or any adequate Material Safety Date Sheets
(MSDS) or labels on the product to the Claimant’s employer to warn
the employer or the Claimant of the high pH and toxicity of the
concrete.
3. Failing to alert the Claimant’s employer or the Claimant to the need
to warn the Claimant of the risk of concrete burns from the high
toxicity of the earth friendly concrete.
4. Failing to warn the Claimant’s employer or the Claimant of the need
for vigilance concerning the Personal Protective Equipment (PPE)
to be used by the Claimant and the need for the employer to be
3 The Affidavit of Roxanne Richards filed 23 March 2020 states that the Notice was served on 13 February
2018 as does RER3 however RER 2 (which was being served) is dated 7 February 2019.
4 RER16 to the Affidavit of Roxanne Richards filed 23 March 2020.
-- 4 of 16 --
5
responsible for the choice of, standard of and monitoring of the PPE
due to the increased risk from the toxicity of the earth friendly
concrete.
5. Failing to warn the Claimant’s employer or the Claimant of the need
to ensure that if the Claimant experienced a concrete burn that
appropriate sanitation was to be immediately made available in the
form of cold, clean water, a pH neutral or slightly acidic soap, the
use of a mildly acidic solution such as diluted vinegar or a buffering
solution to neutralise caustic residues on the skin.
6. Failing to warn the Claimant’s employer or the Claimant that if wet
concrete entered the Claimants [sic] boot the boot was to be
regarded as contaminated and ought not to be worn further.
7. Failing to minimise the Cr(VI) content or other toxicity of the
concrete by using slag in place of or blended with clinker or by
adding ferrous sulphate.”
[14] WorkCover’s solicitors joined Wagners EFC Pty Ltd as a contributor on or about
12 July 2019 on the basis it was the manufacturer and supplier of the concrete. The
Notice of Contribution by the applicant’s employer SWC was directed towards
Wagners EFC and no other Wagners entity.
[15] On 27 August 2019, the solicitors for EFC forwarded a letter to the solicitors for the
applicant in the following terms:
“We confirm that our client considers itself a proper respondent with
respect to particulars 1 and 7 of question 18 in your client’s notice of
claim for the purposes of section 10 of the Personal Injuries
Proceedings Act 2002 (Qld) (PIPA). Our client does not consider that
it is a proper respondent to particulars 2 to 6 of question 18, and requests
that these particulars be struck out of your client’s notice of claim. This
is on the basis of our client’s role purely as manufacturer of the subject
concrete with no day-to-day or contractual relationship with Mr Byrne
or his employer.”5 (italics my emphasis)
[16] On 11 February 2020, the solicitors for the applicant sent the following letter to the
solicitors for EFC which read:6
“Pursuant to section 27(1)(a) and section 27(1)(b) of the Personal
Injuries Proceedings Act 2002 (PIPA), we ask that your insured provides
us with the following information:-
1. Please provide a list of the chemical constituents contained in the
Environmentally Friendly Concrete (EFC) being supplied to STEVE
WALK CONCRETING in Toowoomba on or about 26 October
2016 to include the specified amounts in each batch of concrete
including the acidity and/or alkaline components in each ingredient.
5 RER10 to the Affidavit of Roxanne Richards filed 23 March 2020.
6 RER14 to the Affidavit of Roxanne Richards filed 23 March 2020.
-- 5 of 16 --
6
2. In relation to the chemical constituents contained in each batch of
EFC Concrete being supplied to STEVE WALK CONCRETING in
Toowoomba on or about 26 October 2016 please answer the
following:-
(a) Does each batch of EFC Concrete contain exactly the same
levels of alkalinity and/or acidity?
(b) Does each batch of EFC Concrete contain exactly the same
measured amount of constituents?
(c) Where is the fly ash sourced and what constituents are
contained within the fly ash used for EFC Concrete?
(d) Where is the blast furnace slag sourced and what constituents
are contained within the blast furnace slag used for EFC
Concrete?
(e) Please provide copies of all documents relating to the
constituents of the EFC Concrete.
3. In terms of the testing of the EFC concrete being supplied to STEVE
WALK CONCRETE in Toowoomba on or about 26 October 2016,
please specify:-
(a) Who is responsible for testing the concrete?
(b) Where is the testing undertaken?
(c) Please advise exactly what is involved in the testing of the
concrete.
(d) From testing of the product, have any risks been identified in
relation to use of the EFC product?
(e) Please provide any photographs or relevant documents relating
to testing of the EFC Concrete.
4. In relation to risks associated with the EFC Concrete being supplied
to STEVE WALK CONCRETING in Toowoomba on or about
26 October 2016, please specify:-
(a) What are the risks associated with the EFC product coming
into contact with skin?
(b) What precautions are recommended for persons using the EFC
product in terms of PPE and/or measures for protection against
skin contact?
(c) What measures are recommended for persons coming into
direct contact with the EFC product?
(d) Please advise of any identified risks associated with using the
EFC product.
(e) Please provide any documents provided to suppliers and/or
consumers in relation to risks and precautions when using the
EFC product.
-- 6 of 16 --
7
(f) Please provide any documentation specifying risks associated
with using the EFC product.”
[17] In response to that request the solicitors for EFC disclosed on 13 February 2020 the
document entitled “Material Safety Data Sheet” dated 10 December 2012. That
document disclosed that EFC was manufactured and supplied by Wagners CFT
Manufacturing and on page 2 stated:
“This product is more alkaline than normal concrete and thus has an
increased risk of tissue damage. Highly alkaline and thus irritant and
corrosive. The amount of tissue damage depends on the length of
contact. Eye Contact could result in corneal damage and blindness. Skin
contact can produce inflammation which is characterised by itching,
burning, reddening or occasional blistering (chemical burn)...”7
[18] Also included in the document was the following toxological information:8
“Contact with plastic EFC concrete will cause severe irritation and
possible chemical burns, cement dermatitis and dry skin. EFC plastic
concrete and mortars are strongly alkaline (pH of 13). Strong alkalines,
like strong acids, are harmful or caustic to the skin. This may produce
alkali burns.”
[19] I observe that this information is different to the information previously provided in
relation to the constituents of EFC and is a document prior in time to the one
disclosed on 11 June 2019 which was dated post the incident. It also disclosed for
the first time that EFC was manufactured and supplied by a different Wagners entity,
namely Wagners CFT Manufacturing.
[20] On 13 February 2020 a compulsory conference was convened. The affidavit of Ms
Richards for the applicant is in the following terms:
“27. On or around the afternoon of 13 February 2020 a compulsory
conference was convened in relation to this matter. It was during
this conference that Moray and Agnew Lawyers confirmed that
Wagner EFC Pty Ltd were in fact not the supplier of the EFC
concrete and that it appeared from the Purchase Order that the
EFC was supplied by Wagners Quarries Pty Ltd and that Wagner
Investments Pty Ltd was likely to be the head contractor or
principal on the worksite where the claimant was injured.
28. On or about 13 February 2020 it was revealed by Moray and
Agnew Lawyers that this information was to be found within a
Purchase Order that existed and was in the middle of a large
bundle of documents labelled ‘employment records’ consisting of
the Applicant’s timesheets which was disclosed by email to my
firm from Hede Byrne and Hall Solicitors and received by the
Applicant’s solicitors on 18 April 2019. Exhibit ‘RER16’ to this
7 RER15 to the Affidavit of Roxanne Richards filed 23 March 2020 (page 2 of the “Material Safety Data
Sheet” dated 10 December 2012).
8 RER15 to the Affidavit of Roxanne Richards filed 23 March 2020 (page 5 of the “Material Safety Data
Sheet” dated 10 December 2012).
-- 7 of 16 --
8
affidavit is a true copy of the purchase order disclosed to Shine
Lawyers on 18 April 2019.
29. I believe that the inclusion of that Purchase Order in that
disclosure at that time and in that context was probably
inadvertent because it did not relate to any allegation made by the
Applicant against the employer.
30. On or about 13 February WorkCover’s solicitors confirmed for
the first time their belief that the Oakey Abattoir loading ramp
construction site was under the control of Wagner Investments
Pty Ltd. It was only at that time that it was understood that a
Wagners entity or entities had the dual characters of being the
supplier of the EFC and having overall control of the site.
31. Moray and Agnew also stated that the Material Safety Data Sheet
dated 10 December 2012 which is part of Exhibit ‘RER13’ was
the correct Material Safety Data Sheet for EFC, and that Wagner
CFT Manufacturing Pty Ltd was a former name of Wagners EFC
Pty Ltd.”
[21] On 20 February 2020 the solicitors for WorkCover served a Contribution Notice on
Wagner Investments Pty Ltd and on 25 February 2020 on Wagners Quarries Pty
Ltd. I also note the content of the letter of 20 February 2020 from the solicitors for
WorkCover to the applicant. In that letter, the solicitors outlined the name of the
entity which had employed the applicant as Steve Walk Concreting. It also attached
correspondence from the solicitors for Wagners EFC and advised:
“2. We are instructed that the employer simply provided labour to the
job at the Oakey abattoir. This is corroborated by the email from
Gearoid Connolly to the employer dated 21 September 2016 where
Wagners invited the employer to quote to do works at the site. The
employer is requested to supply labour to excavate the footing,
level crusher dust, place plastic etc. and pour and finish concrete
of the footing and top slab. Wagners supplied all of the materials
for the job, including concrete, except the boxing which the
employer provided.
The employer says that a Wagners entity, possibly Wagners
Investments Pty Ltd, was the principal contractor on the site, and
was therefore responsible for site inductions, the provision of first
aid facilities and water infrastructure. This assumption is based on
the information contained in the purchase order dated 25 October
2016.
3. The employer did not purchase the concrete used at the site. The
purchase order dated 25 October 2016 was for the supply of labour
by the employer to Wagners Investments Pty Ltd on the site.
4. The purchase order and email from Mr Connolly to the employer
comprise the only documentation of the agreement between the
employer and Wagners Investments Pty Ltd for the supply of
-- 8 of 16 --
9
labour by the employer at the site. There is no contract for the
supply of concrete to the employer.
5. No contract exists beyond the purchase order and email from
Mr Connolly.”9
Should the Limitation Period be Extended?
[22] In addition to his claims against his employer for failing to provide a safe work
system and against Wagners EFC for manufacturing the EFC and not providing
warnings as to its properties to the applicant’s employer or the applicant, the
applicant now wishes to pursue claims against Wagners Quarries Pty Ltd, Wagner
Investments Pty Ltd and Wagners CFT Manufacturing Pty Ltd.
[23] The applicant has clearly already commenced proceedings to recover damages for
injuries against his employer and against the manufacturer of the concrete. The
plaintiff’s limitation period expired on 26 October 2019. On 26 February 2020, the
applicant’s solicitors served a PIPA notice of claim on the first and second
respondents.
[24] The applicant wishes to claim against all the respondents notwithstanding the fact
that the relevant limitation period has expired. In order for the applicant to be
successful in his application he must show that a material fact of a decisive nature
relating to the right of action was not within his means of knowledge until a date
after the commencement of the year last preceding the expiration of the period of
limitation for the action.10
[25] The applicant argues that a material fact in the context of this application is the
identity of the parties against whom the right of action lies, namely the first, second
and third respondents and that 13 February 2020 is the pivotal date in this regard.
[26] The respondent argues that it is clear that Wagners EFC Pty Ltd was not the
contractor of the site or the supplier of the EFC, and argues that the applicant had
no reason to think that this should be so, and did not take reasonable steps to find
out whether it was so before the expiration of the limitation period. The respondent
argues that the applicant could have pursued the claims against the first, second and
third respondents before the limitation period expired but chose not to.
[27] The respondents argue they had conveyed on 27 August 2019 that Wagners EFC
was the manufacturer of the concrete and nothing more and that essentially the
applicant should have made further enquiries as to the actual contractual
arrangements at the abattoir and the identity of the head contractor at the site.
[28] The respondent also argues that the “Purchase Order” bearing the Wagners logo
previously referred to, recorded the existence of the first and second respondent and
was a document which had been disclosed to the applicant by WorkCover in a
bundle of documents in April 2019.
[29] The relevant principles are set out in ss 30 and 31 of the Limitation of Actions Act
1974 (Qld):
9 RER35 to the Affidavit of Roxanne Richards filed 3 April 2020.
10 Limitation of Actions Act 1974 (Qld) s 31(2)(a).
-- 9 of 16 --
10
“30 Interpretation
(1) For the purposes of this section and sections 31, 32, 33 and 34—
(a) the material facts relating to a right of action include the
following—
(i) the fact of the occurrence of negligence, trespass,
nuisance or breach of duty on which the right of action
is founded;
(ii) the identity of the person against whom the right of
action lies;
(iii) the fact that the negligence, trespass, nuisance or
breach of duty causes personal injury;
(iv) the nature and extent of the personal injury so caused;
(v) the extent to which the personal injury is caused by the
negligence, trespass, nuisance or breach of duty;
(b) material facts relating to a right of action are of a decisive
character if but only if a reasonable person knowing those
facts and having taken the appropriate advice on those facts,
would regard those facts as showing—
(i) that an action on the right of action would (apart from
the effect of the expiration of a period of limitation)
have a reasonable prospect of success and of resulting
in an award of damages sufficient to justify the
bringing of an action on the right of action; and
(ii) that the person whose means of knowledge is in
question ought in the person’s own interests and taking
the person’s circumstances into account to bring an
action on the right of action;
(c) a fact is not within the means of knowledge of a person at a
particular time if, but only if—
(i) the person does not know the fact at that time; and
(ii) as far as the fact is able to be found out by the person—
the person has taken all reasonable steps to find out the
fact before that time.
(2) In this section—
appropriate advice, in relation to facts, means the advice of competent
persons qualified in their respective fields to advise on the medical,
legal and other aspects of the facts.
31 Ordinary actions
(1) This section applies to actions for damages for negligence,
trespass, nuisance or breach of duty (whether the duty exists by
virtue of a contract or a provision made by or under a statute or
-- 10 of 16 --
11
independently of a contract or such provision) where the damages
claimed by the plaintiff for the negligence, trespass, nuisance or
breach of duty consist of or include damages in respect of personal
injury to any person or damages in respect of injury resulting from
the death of any person.
(2) Where on application to a court by a person claiming to have a
right of action to which this section applies, it appears to the
court—
(a) that a material fact of a decisive character relating to the
right of action was not within the means of knowledge of the
applicant until a date after the commencement of the year
last preceding the expiration of the period of limitation for
the action; and
(b) that there is evidence to establish the right of action apart
from a defence founded on the expiration of a period of
limitation; the court may order that the period of limitation
for the action be extended so that it expires at the end of 1
year after that date and thereupon, for the purposes of the
action brought by the applicant in that court, the period of
limitation is extended accordingly.
(3) This section applies to an action whether or not the period of
limitation for the action has expired—
(a) before the commencement of this Act; or
(b) before an application is made under this section in respect of
the right of action.”
[30] As Counsel for the applicant has outlined in his submissions, for an applicant to
succeed, it must prove three elements which were discussed by Macpherson J in
Randel v Brisbane City Council.11 In essence those three factors are:
(a) The existence of material fact or facts unknown before the relevant date;
(b) The facts must be of a decisive character; and
(c) All those facts were not within the applicant’s means of knowledge until after
the relevant date.
[31] As Justice Davies held in Stephenson v State of Queensland:12
“Thus the question is not when all material facts came within the
means of knowledge of the applicant. It is when all material facts of
a decisive character relating to the right of action came within his
means of knowledge.”
[32] Significantly, it was held that one cannot have the means of knowledge of material
facts of a decisive character at a time when those material facts do not have that
11 [1984] 2 Qd R 276 at 277.
12 [2004] QCA 483 at 5–6 [13].
-- 11 of 16 --
12
character. The High Court ultimately held,13 on the appeal from the decision of the
Queensland Supreme Court, as follows:
“The better view is that the means of knowledge (in the sense given
by par (c) of s 30(1)) of a material fact is insufficient of itself to propel
the applicant outside s 31(2)(a). For circumstances to run against the
making of a successful extension application, the material fact must
have a ‘decisive character’. Whether the decisive character is
achieved by the applicant becoming aware of some new material fact,
or whether the circumstances develop such that facts already known
acquire a decisive character, is immaterial. It is true to say, as the
plaintiffs submit in their written submissions, that in a sense none of
the material facts relating to the applicant's right of action is of a
decisive character until a reasonable person ‘knowing those facts and
having taken the appropriate advice on those facts, would regard
those facts as showing’ the features described in sub-pars (i) and (ii)
of s 30(1)(b). Whether that test has been satisfied at a particular
point in time is a question for the court.
[33] Counsel for the respondent argues that the applicant always knew that there were
other parties involved in the works at the abattoir and that there was possibly more
than one of the Wagners companies involved with the site and the provision of the
EFC. Accordingly, whilst the identity of those other parties may not have been
known, the respondent argues that those facts were within the applicant’s means of
knowledge and that the issue of the knowledge is assessed from the perspective of
the applicant. Reliance in this regard is placed on the decision in NF v State of
Queensland:14
“It is to be emphasized [sic] that s 30(1)(c) does not contemplate a
state of knowledge of material facts attainable in the abstract, either
by the exercise of ‘all reasonable steps’, or by the efforts of a
reasonable person. It speaks of a state of knowledge attainable by an
actual person who has taken all reasonable steps. The actual person
postulated by s 30(1)(c) as the person who has taken all reasonable
steps, is the particular person who has suffered particular personal
injuries. Whether an applicant for an extension of time has taken all
reasonable steps to find out a fact can only be answered by reference
to what can reasonably be expected from the actual person in the
circumstances of the applicant …”
[34] The respondent argues that if Wagners EFC was not the head contractor of the site
or the supplier of the EFC, then the applicant had no reason to think that this should
be the state of affairs and took no reasonable steps to find out whether it was so
before the expiration of the limitation period. It is also argued that if the material
fact is that one of the respondents was the manufacturer of the EFC, Counsel for the
respondent argues that that is not so, and there is no evidence that it is so. It argues
that it is admitted that Wagners EFC Pty Ltd manufactured the EFC. The respondent
argues that in truth, the applicant seeks to make new claims against new parties and
argues that these are claims the applicant could have pursued before the limitation
13 State of Queensland v Stephenson [2006] HCA 20 at 9 [29].
14 [2005] QCA 110 at 11 [29].
-- 12 of 16 --
13
period expired but chose not to. The respondent argues that the applicant seeks to
have these claims bought out of time because the parties he wishes to add have a
similar name to the parties against whom he chose to claim.
[35] The respondent also argues that the question of what amounts to all reasonable steps
to find out a fact depends on the nature of the relevant fact and that where a simple
enquiry is required, that failure is enough to amount to a failure to take reasonable
steps. The respondent accepts that sometimes the relevant fact is more involved and
could not be ascertained without legal assistance. Such a failure to ask may not
amount to a failure to take reasonable steps. The respondent relies on Randel v
Brisbane City Council15 in this regard and argues that the identification of the other
parties involved in the site involved nothing more than asking either the employer
or Wagners EFC Pty Ltd. Accordingly, it is argued that the decisive material fact
was easily capable of ascertainment by the applicant if he had taken reasonable steps
to do so.
[36] The respondent therefore argues that the fact was within his means of knowledge in
the relevant sense and that accordingly the applicant fails to satisfy the requirements
of s 30(2)(b) of the Act. The respondent argues that it is not for the entity against
which a claim has been advanced to nominate all others it may have perceived had
an involvement. The respondent argues that the named party has an obligation to
respond to the claim made against it as required by PIPA and that it has discharged
this obligation in this regard.
[37] The evidence indicates that the applicant was aware of and believed he had a cause
of action against his employer and a cause of action against the manufacturer and/or
supplier of the concrete due to its toxicity and the lack of any warnings. He claimed
against both his employer SWC and Wagners EFC, the makers of the concrete.
[38] It would seem clear on the material before me that the only visible entities other
than the applicant’s employer SWC were the OA and QR. The applicant clearly
considered that he was working for his employer who was a concreting contractor
and that his employer was engaged by the abattoir or QR. I can see no basis to
conclude as the respondent contends, that the applicant should have known that
there was a head contractor in charge of the site who would have had overall
responsibility in relation to the concreting works.
[39] In my view the “Purchase Order” document relied upon to sustain that assertion is
obscure and indeed in many ways misleading. There is very little information on
that document, particularly if it is argued that it is a contract for the supply of labour
by SWC to Wagner Investments Pty Ltd. Would a contract for the supply of labour
by a number of workers over a number of days be accurately described as a purchase
order for one item at a fixed price? It is difficult in my view to draw the inference
from that document that Wagner Investments Pty Ltd was the head contractor for
the works at the abattoir and that in that capacity had engaged SWC to supply labour
to it. On the face of it I do not consider that the purchase order would alert the
applicant to that possibility. I consider that it was reasonable in the circumstances
for the applicant to believe that his employer had directly dealt with the client either
OA or QR and that there was no head contractor. None was observed by him at the
site, and none was mentioned by the employer.
15 [1984] 2 Qd R 276.
-- 13 of 16 --
14
[40] Furthermore, after the claim was made against the employer, the employer did not
direct attention to the proposition that someone other than Wagers EFC had supplied
the concrete to the site or that any Wagners entity had any involvement at the site.
Clearly there was another entity apart from Wagners EFC that had a role at the site
particularly in relation to workplace health and safety, but even now, as the applicant
points out, the employer’s letter is vague about the precise contractual arrangements.
[41] It is also significant in my view that the second safety data sheet disclosed on 13
February 2020 is in the name of the third respondent, namely Wagners CFT
Manufacturing Pty Ltd and not Wagners EFC.
[42] Having considered the two documents, in my view the warnings expressed in the
safety data sheet dated 2012 are in stronger terms. I can understand that there was
no earlier enquiry by the applicant concerning any entity other than Wagners EFC
as a manufacturer given that there was specific admission by Wagners EFC that they
were the manufacturer.
[43] There can be no doubt that initially the applicant only advanced a claim for damages
against his employer and Wagners EFC, the entity it believed to be the
manufacturer. Whilst Counsel for the respondent argues that the applicant and his
lawyers knew the other parties were involved, in my view it is not sustained by the
material before me. It would seem clear that his state of mind was that the person
who was contracted to do the concreting work was his employer, and there was no
indication that anyone, other than his employer, would have been in charge of
concreting protocols on the site. It is not common ground in my view that the
applicant knew that there was a head contractor.
[44] I have had regard to the statements of principle as considered by Mullins J (as her
honour then was) in Godden v State of Queensland16 as follows;
“[43] The plaintiff’s position is that, even if he knew, in general terms, that
there could have been subcontractors at the site at the relevant time
which were undertaking site works, he had no basis on which to make a
damages claim against any subcontractor until he knew the identity of
the subcontractor and that the second defendant claimed there was a
relevant contract with such subcontractor. It is relevant that, even though
the proceeding was commenced against the second defendant in May
2011, it was not until two and onehalf years later that the second
defendant suggested to the plaintiff that the fifth defendant was the on
site earthworks contractor prior to the accident.
[44] There is no dispute about the principles to be applied in an application
under s 31(2) of the Act. The plaintiff bears the onus of proving he is
entitled to an extension of the limitation period. Putting aside the
limitation issue, the plaintiff must show there is evidence to establish the
right of action against the fifth defendant. What that entails was
explained in Wood v Glaxo Australia Pty Ltd [1994] 2 Qd R 431 at 434-
435:
16 (2016) 78 MVR 120 at 129.
-- 14 of 16 --
15
‘One way in which the onus has been expressed is that the applicant
must demonstrate something like a prima facie case. The evidence
need not at the stage at which the application is brought be in a form
which would be admissible at trial and it may indeed be hearsay. It
will not be possible to predict whether the plaintiff’s evidence will
prevail at trial when it will be subjected to challenge and forced to
confront the opposing evidence of the defendant, but it is probably
accurate enough to say that an applicant will meet the requirement
imposed by s 31(2)(b) if he can point to the existence of evidence
which it can reasonably be expected will be available at the trial and
which will, if unopposed by other evidence, be sufficient to prove
his case.’
[45] I have evaluated the evidence to establish the plaintiff’s right of action
against the fifth defendant, taking into account the foreshadowed
amendment to the statement of claim. Leaving aside the fifth defendant’s
argument that it is fatal to the plaintiff’s claim that he has not complied
with the MAIA, there is otherwise enough in the material to point to
evidence that satisfies the test in s 31(2)(b) of the Act.
[46] How s 30 of the Act applies to the discharge by the plaintiff of the onus
in respect of s 31(2)(a) of the Act was explained in State of Queensland
v Stephenson (2006) 226 CLR 197 in the judgment of Gummow, Hayne
and Crennan JJ at [25]:
‘The ascription to material facts of the character of “decisive” looks
to the response of an actor. It is here that the exegesis supplied by
par (b) of s 30(1) comes into play. The court is to consider the
response of “a reasonable person” in the manner explained in that
paragraph. The particular claimant is to enjoy the advantage
conferred by the provision in s 30(1) for the making of an extension
order only by satisfaction of criteria which look to the response of a
reasonable person. In this way, s 30(1) assists and controls an
understanding of the compound conception in s 31(2).’
[47] The effect of the ‘compound conception’ or composite expression
‘material fact of a decisive character relating to a right of action’ was
further explained by the plurality in [29]:
‘The better view is that the means of knowledge (in the sense given
by par (c) of s 30(1)) of a material fact is insufficient of itself to
propel the applicant outside s 31(2)(a). For circumstances to run
against the making of a successful extension application, the
material fact must have “a decisive character”. Whether the decisive
character is achieved by the applicant becoming aware of some new
material fact, or whether the circumstances develop such that facts
already known acquire a decisive character, is immaterial. It is true
to say, as the plaintiffs submit in their written submissions, that in a
sense none of the material facts relating to the applicant’s right of
action is of a decisive character until a reasonable person “knowing
those facts and having taken the appropriate advice on those facts,
-- 15 of 16 --
16
would regard those facts as showing” the features described in sub-
pars (i) and (ii) of s 30(1)(b). Whether that test has been satisfied at
a particular point in time is a question for the court.’
[48] The plaintiff had taken all reasonable steps to find out if there were other
parties against whom he should claim for damages for personal injury
by serving his notice of claim under the PIPA on the second defendant
and then commencing this proceeding against the second defendant. It is
difficult to see how the plaintiff should have foreseen the need to
ascertain whether there was any subcontractor undertaking on site
earthworks leading up to the date of the accident, when the matter was
not disclosed by the second defendant until after the failed mediation.”
[45] Counsel for the respondent argues that no question was asked in relation to the
identity of the party who was the head contractor. In my view, it is significant that
Wagners EFC knew the true state of affairs and did nothing to dissuade the applicant
of his view that the concrete was supplied to SWC as the employer, as evidenced by
the letters of 13 and 20 February 2020.
[46] I consider that a material fact in the context of this application is the identity of the
parties against whom the right of action lies, namely the first, second and third
respondents and that 13 February 2020 was indeed the pivotal date in this regard
because it was on this date that the Material Safety Data Sheet dated 10 December
2012 was disclosed and it was the date that the fact of a likely identity of a head
contractor was revealed.
[47] I consider therefore that the applicant has satisfied the requirements of ss 30 and 31
of the Limitation of Actions Act and the limitation period should be extended to 13
February 2021 against all respondents.
Orders
[48] I make orders in the terms of paragraphs 1(ii) and (iii), 2, 3 and 4 of applicant’s
originating application as follows:
(1) Pursuant to s 31 of the Limitation of Actions Act 1974 (Qld) the period of
limitation in respect of the applicant’s claim for damages for personal injuries
sustained on 26 October 2016 be extended as against the first, second and third
respondents to 13 February 2021.
(2) Pursuant to s 43 of the Personal Injuries Proceedings Act 2002 (Qld) (PIPA)
the applicant have leave to commence proceedings against the first, second
and third respondents.
(3) The proceedings be stayed until the applicant complies with Chapter 2, part 1
of PIPA.
(4) Costs in the cause.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2020/076