APGL (Palm Beach) Pty Ltd v Palm Beach Developments Pty Ltd (No 2) [2020] QSC 22
SUPREME COURT OF QUEENSLAND
CITATION: APGL (Palm Beach) Pty Ltd v Palm Beach Developments Pty
Ltd (No 2) [2020] QSC 22
PARTIES: APGL (PALM BEACH) PTY LTD ACN 113 479 744
(plaintiff)
v
PALM BEACH DEVELOPMENTS PTY LTD ACN 101
716 081
(defendant)
FILE NO/S: 11759 of 2018
DIVISION: Trial
PROCEEDING: Claim
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 28 February 2020
DELIVERED AT: Brisbane
HEARING DATE: On the papers
JUDGE: Flanagan J
ORDER: The defendant pay the plaintiff’s costs of the proceedings
to be assessed on the indemnity basis.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – OFFERS OF
COMPROMISE, PAYMENTS INTO COURT AND
SETTLEMENTS – OFFER OF COMPROMISE OR OFFER
TO SETTLE OR CONSENT TO JUDGMENT PURSUANT
TO RULES – MATTERS RELEVANT FOR COURT TO
ORDER OTHERWISE – where the plaintiff obtained an order
no less favourable than its offer to settle – where the defendant
argued that the plaintiff made late substantive changes to its
case – whether the defendant showed that another order for
costs was appropriate in the circumstances
Uniform Civil Procedure Rules 1999 (Qld) r 360
COUNSEL: J W Peden QC with B A Reading for the plaintiff
G D Sheahan for the defendant
SOLICITORS: K & L Gates for the plaintiff
Cronin Miller Litigation for the defendant
-- 1 of 4 --
[1] On 31 January 2020, I made the following orders:
“1. It is declared that the plaintiff is entitled to the amount of
$3 million presently held in the Trust Account of K and L Gates.
2. The Court orders that the amount of $3 million and any interest
that has accrued on that amount be released from the Trust
Account of K and L Gates to the plaintiff in accordance with
cl 2(c) of the deed entered into on or around 9 June 2016.
3. The defendant’s counterclaim is dismissed.
4. The Court will hear the parties as to costs.”
[2] The parties have now provided written submissions in relation to costs.
[3] On 26 September 2019, the plaintiffs made an offer under Chapter 9, Part 5 of the
Uniform Civil Procedure Rules 1999 (Qld) (UCPR) in the following terms:
“1. The Retention Amount and any interest that has accrued on the
Retention Amount be released from the trust account of K&L
Gates to the plaintiff in accordance with clause 2(c) of the Deed.
2. The counterclaim be dismissed.
3. Each party bears their own costs.”
[4] Rule 360(1) of the UCPR provides:
“(1) If –
(a) the plaintiff makes an offer that is not accepted by the
defendant and the plaintiff obtains an order no less
favourable than the offer; and
(b) the court is satisfied that the plaintiff was at all material
times willing and able to carry out what was proposed in
the offer;
the court must order the defendant to pay the plaintiff’s costs
calculated on the indemnity basis unless the defendant shows
another order for costs is appropriate in the circumstances.”
[5] This requires a comparison between the offer to settle and the “order” obtained by the
plaintiff. In the present case, the offer was one in which the plaintiff would be paid
the “Retention Amount” (which was an amount of $3 million) and any interest that
had accrued on the Retention Amount, which was the effect of orders 1 and 2.
Accordingly, the plaintiff has obtained an order that is no less favourable than its offer
to settle.
[6] Under r 360, the Court must order the defendant to pay the plaintiff’s costs calculated
on the indemnity basis unless the defendant shows another order for costs is
appropriate in the circumstances.
[7] The defendant submits that the appropriate order for costs is that the plaintiff have its
costs on the standard basis and limited to the costs of the four day trial, or alternatively
-- 2 of 4 --
2
to the costs of “the failure to fund issue”. This is submitted to be the appropriate costs
order because:
“(a) the late substantive changes in APGL Palm Beach’s pleaded
case, which raised for the first time the issue that loans from
‘APGL Parent Co’ amounted to ‘Development Costs’ for the
purposes of the Development Agreement (Development Costs
Issue);
(b) the evidence for the first time of the principal factual witnesses
for APGL Palm Beach, Mr McMahon and Taylor (in affidavits
delivered to the solicitors for PBD the Friday before trial) that
the Master Income Statement provided to the defendant prior to
the commencement of the proceeding in 2016 was ‘incorrect’ in
its recording of the treatment of APGL Parent Co Loans and the
references to APGL Palm Beach’s and PBD’s equity in the
project (Loans v Equity Issue);
(c) the absence of any prior identification to PBD, other than on the
Friday before trial, that ‘outstanding Development Costs’ for
the purposes of clause 11 of the Development Agreement
(governing the priority of payments out of the Net Proceeds of
Sale of the Project), included repayment of loans to APGL
Parent Co.”1
[8] In my view, for the purposes of r 360(1), the defendant has failed to show that another
order for costs is appropriate in the circumstances. As identified in the Reasons,2 the
primary issue at trial was whether the plaintiff or the defendant was entitled to part or
the whole of the amount of $3 million. The resolution of that issue turned upon the
proper construction of the Development Agreement. Properly construed, the
Development Agreement did not permit any repayment to the defendant in
circumstances where the Total Development Costs of the Project exceeded the Net
Proceeds on the Sale of the Project. As early as 24 March 2016, Mr McMahon for
the plaintiff informed Mr Whitelaw for the defendant that “… the attached ‘project to
date’ accounts and projections indicate there will be no Return payable to PBD…”.3
Attached to the email of 24 March 2016, among other documents, was the first
iteration of the Master Balance Sheet and Master Income Statement.
[9] Consistent with the advice in the email of 24 March 2016, the plaintiff’s claim and
statement of claim (which has never been amended from its original filing date of
16 November 2018) asserted that as at 30 June 2018, the Total Development Costs of
the Project exceeded the Net Proceeds on the Sale of the Project by approximately
$26 million. The plaintiff correctly submits that its case has always been that the
defendant, as a mezzanine financier, was not entitled to any repayment of the PBD
Loan Contribution following the sale of the Project.4 The changes to the plaintiff’s
case identified by the defendant were in response to amendments to the defendant’s
counterclaim. I accept the plaintiff’s submissions that the defendant first raised the
issue of whether or not repayment of loans to APGL Parent Co were Development
1 Defendant’s Submissions on Costs, paragraph 13 (footnotes omitted).
2 APGL (Palm Beach) Pty Ltd v Palm Beach Developments Pty Ltd [2020] QSC 2, [1].
3 APGL (Palm Beach) Pty Ltd v Palm Beach Developments Pty Ltd [2020] QSC 2, [31].
4 Plaintiff’s Submissions on Costs, paragraph 11.
-- 3 of 4 --
3
Costs within the meaning of the Development Agreement.5 This was an allegation
made by the defendants one week prior to trial. By the plaintiff’s amended reply and
further amended answer filed 17 October 2019, it was pleaded in response that the
repayment of loans from APGL Parent Co were Development Costs within the
meaning of the Development Agreement. This did not, in my view, constitute a “late
substantive change in the plaintiff’s case”, but rather a response to late amendments
made by the defendant, as reflected in its amended defence and further amended
counterclaim filed 18 October 2019.
[10] The defendant submits that the Master Income Statement was shown to be “incorrect”
only after the late service of the affidavits of Mr McMahon and Mr Taylor. This
submission ignores that prior to the commencement of the proceedings, the plaintiff
provided the defendant with a copy of all the transactions in the general ledger for the
plaintiff from inception of the Project to 30 June 2018 that evidenced an
inter-company loan account between APGL Parent Co and the plaintiff, which was
conceded by Mr Whitelaw in cross-examination.6 Further, as correctly submitted by
the plaintiff, it was the defendant’s witness, Grant Williams, who made the allegations
about the defendant’s intention to seek to rely on the bottom 12 rows of the Master
Income Statement as being relevant to the issue of the meaning of terms in the
Development Agreement.7 Mr McMahon’s affidavit sworn 11 October 2019 was
sworn and provided in response to the affidavit of Mr Williams.8
[11] The defendant’s submissions also ignore the fact that the defendant made significant
amendments to its own case.9 Further, the defendant’s pleaded case in relation to
“the failure to fund issue” failed at every turn.10
Disposition
1. The defendant pay the plaintiff’s costs of the proceedings to be assessed on the
indemnity basis.
5 Plaintiff’s Submissions on Costs, paragraph 14(d).
6 Plaintiff’s Submissions on Costs, paragraph 17(c); Exhibit 10, affidavit of Michael James Taylor filed
9 September 2019, paragraph 14(a); Transcript of Proceedings 16 October 2019, 3-13, lines 9-35.
7 Plaintiff’s Submissions on Costs, paragraph 17(d).
8 Plaintiff’s Submissions on Costs, paragraph 17(e).
9 Plaintiff’s Submissions on Costs, paragraphs 18 and 19.
10 APGL (Palm Beach) Pty Ltd v Palm Beach Developments Pty Ltd [2020] QSC 2, [61].
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2020/022