Elliott v Dyer [2020] QCAT 451
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Elliott v Dyer [2020] QCAT 451
PARTIES: MERLE ELLIOTT
(applicant)
v
ROWAN JOHN DYER
(respondent)
APPLICATION NO/S: BDL008–19
MATTER TYPE: Building matters
DELIVERED ON: 10 November 2020
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Paratz AM
ORDERS: I order that Rowan John Dyer pay the amount of eight
thousand one hundred and eight dollars and twenty
cents ($8,108.20) to Merle Elliott.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF
WORK – REMEDIES FOR BREACH OF CONTRACT –
DAMAGES – where an owner claimed damages to remedy
defects – where the builder gave no evidence in response
to the claims – where the claims were assessed – where
costs were allowed for disadvantaging the other party
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 100, s 102
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] Merle Elliott (the owner) engaged Mr Dyer (the builder) to enclose a verandah at her
house at the Sunshine Coast, commencing on 4 September 2017.
[2] The owner filed an Application for domestic building disputes in the Tribunal on 2
January 2009 seeking damages in the amount of $7,770.00 as the cost of rectification
of defective work by the builder.
[3] The builder filed a response on 30 January 2019 in which he alleged that there was no
contract for works to be carried out; that works were carried out on an as–needs basis
as per the client’s instructions; and disputed the payment of monies made to him.
-- 1 of 4 --
2
[4] Directions were issued by the Tribunal on 17 April 2019 requiring the builder to file
his statements of evidence by 4:00pm on 29 May 2019.
[5] The tribunal received an email from a financial planner on 14 May 2019, which
appeared to have been submitted on behalf of the builder. The email addressed issues
as to non–attendance of the builder at an earlier directions hearing, but did not provide
any Statements of Evidence on behalf of the builder.
[6] The tribunal gave directions on 30 October 2019 requiring the owner to file a signed
statement by 12 November 2019 addressing issues directed to be provided at a
Compulsory Conference which had been held on 17 April 2019. The owner filed
materials on 26 November 2019.
[7] The tribunal also gave directions on 30 October 2019 requiring the builder to file in
the Tribunal, and give to the owner, statements of evidence in response to the material
filed by the owner by 3 December 2019. No statements of evidence were filed by the
builder.
[8] The tribunal also gave directions on 30 October 2019 that the matter would be decided
on the papers, by written submissions from the parties, after 18 January 2020.
[9] These are the reasons in determination of this matter.
The owner’s evidence
[10] The owner filed a statement of evidence from herself dated 7 May 2019.
[11] The owner stated that in the first part of 2017 she had employed a designer to draw
up a plan to enclose a verandah which is opposite the master bedroom at her home.
She said that the designer introduced her to the builder.
[12] The owner described the contract arrangements as follows:1
Rowan (the builder) came to my house on the Saturday he gave me his business
card saying he is a registered builder licensed and building for 30 years, he
wrote me out a quote $10,912.00 I showed him the area and gave him a copy of
the drawing he told me if I paid cash he would do it for $50 an hour.
I was to order the windows and pay for them.
….. In the first week he had to order supplies he would go and get the materials
and ring me and I would put them on my bank card
[13] The owner attached a photocopy of a hand written document which she said was
written by the builder as his quote on 2 September 2017. The document read as
follows:2
Carpenter builder two weeks $4,000
Stacks building supplies $1,193
Suncoast windows $4,828
CRB rock linings internal batts $250
(Subtotal) $10,271
$641
1 Statement of Mel Elliott filed 7 May 2019.
2 Ibid p 2.
-- 2 of 4 --
3
Total $10,912
[14] The owner says that work commenced on 4 September 2017. She says that she made
cash payments to the builder as follows:3
9.9.17 $2,000
12.9.17 $400
29.9.17 $1,000
6.10.17 $800
Total $4,200
[15] The owner says that she paid for materials as follows:4
4.9.17 Stacks Sunshine Coast Warana $54.68
4.9.17 Stacks Sunshine Coast Warana $799.87
7.9.17 Sunshine Mitre 10 Caloundra $969.16
6.10.17 Plaster Warehouse P/L $299.95
28.9.17 Master Warehouse $28.30
4.9.17 Big River Group $854.55
12.9.17 Master Warehouse $271.65
9.10.17 Suncoast Windows $176.00
14.9.17 Stacks building supplies $60.40
27.9.17 Suncoast Windows $4,828.00
Total $8,342.56
[16] An inspection report by a Queensland Building and Construction Commission
Inspector dated 1 March 2018 identified a number of issues which were considered to
be defective building work.
[17] The owner obtained a quote on 10 October 2018 from Dean Butt to rectify defective
works in the amount of $7,770.00.
Discussion
[18] There is undisputed evidence from the owner that a quote in writing was provided by
the builder for the works, and that the builder conducted works accordingly. Whilst
there is no formal building contract in writing, a contract for building works between
the parties was clearly formed.
[19] The owner has claimed for defective works. The report of the Queensland Building
and Construction Commission supports her contentions that there are defects in the
work that was performed. The owner has obtained a quote for rectification of the
works.
[20] The builder has had the opportunity to respond to the claims by the owner, and file
statements of evidence in response. No such material has been filed by the builder.
[21] The total of the cash payments of $4,200 to the builder, and the materials in the amount
of $8,342.56 paid for by the owner, are $12,542.56. That amount is in excess of the
contract price of $10,912.00 which included materials.
3 Ibid p 5.
4 Ibid.
-- 3 of 4 --
4
[22] There are therefore no monies owing to the builder in respect of the works.
[23] The need for rectification, or the cost of the claimed rectification, has not been
challenged by the builder by any evidence.
[24] In the absence of any contrary evidence by the builder, I accept the allegations of the
owner that the work is defective, and accept that the quote is a reasonable cost for
rectification.
[25] I allow the amount of the quote for rectification of $7,770.00 as damages for breach
of contract.
[26] The owner has applied for costs.
[27] Section 100 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
provides that each party usually bears their own costs. Section 102 provides that the
tribunal may make an order for costs if it considers the interests of justice require it to
make the order. Section 102(3)(a) provides that the tribunal may have regard to
whether a party unnecessarily disadvantages another party to the proceeding.
[28] The builder has not responded to the claim in any substantial way, and has put the
owner to the expense of pursuing her claim to a decision. That conduct of the builder
has unnecessarily disadvantaged the owner.
[29] The owner has incurred a filing fee in the Tribunal of $338.20. The application refers
to costs sought of $120.50, but no basis for those costs is identified.
[30] I allow the filing fee as costs to the owner of $338.20.
Conclusion
[31] I am satisfied that the claim by Merle Elliott in the full amount of $7,770.00 is
substantiated.
[32] I allow costs in the amount of $338.20
[33] The total award is $8,108.20
[34] I order that Rowan John Dyer pay the amount of $8,108.20 to Merle Elliott.