CTP Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber v Queensland Building and Construction Commission [2020] QCAT 307
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: CTP Plumbing and Maintenance Pty Ltd t/as Charlie the
Plumber v Queensland Building and Construction
Commission [2020] QCAT 307
PARTIES: CTP PLUMBING AND MAINTENANCE PTY LTD
T/AS CHARLIE THE PLUMBER
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR345-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 12 August 2020
HEARING DATE: 23 July 2020
HEARD AT: Brisbane
DECISION OF: Member Browne
ORDERS: The Queensland Building and Construction
Commission’s decision of 3 September 2018 is
confirmed.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – where direction to
rectify issued – where decision made that building work
undertaken at the direction of the Commission is not of a
satisfactory standard – whether the time to comply with the
direction was extended – where no physical work done to
rectify the defective work – whether ‘reviewable decision’
– consideration of Tribunal’s review jurisdiction generally
– meaning of ‘building work’ – whether building work
undertaken at the direction of the Commission is of a
satisfactory standard
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 72B, s 86, s 87, Schedule 2,
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 18, s 20, s 21, s 24
Briginshaw v Briginshaw (1938) 60 CLR 336
-- 1 of 11 --
2
CTP Plumbing and Maintenance Pty Ltd t/as Charlie the
Plumber v Queensland Building and Construction
Commission [2019] QCAT 409
JM Kelly (Project Builders) Pty Ltd v Queensland Building
Services Authority [2013] QCAT 502
Kehl v Board of Professional Engineers of Queensland
[2010] QCATA 58
Project Blue Sky Inc v Australian Broadcasting Authority
(1998) 194 CLR 355
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondent: C Low, Legal Officer, Queensland Building and
Construction Commission
REASONS FOR DECISION
CTP Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber installed a hot water
unit (‘the HWU’) at a residential property in Southport, Queensland at the request of
the property’s owner.
Some months after the HWU was installed the property owner complained to the
Queensland Building and Construction Commission (‘the Commission’) about the
work performed by CTP.
On 18 July 2018, and after inspecting the HWU, the Commission issued a direction
to rectify building work to CTP under s 72 of the Queensland Building and
Construction Commission Act 1991 (Qld) (‘the QBCC Act’). Relevantly, a direction
to rectify is a reviewable decision before the Tribunal. The direction to rectify required
CTP to rectify the defective work by a certain date (‘the rectification period’).1
CTP did not apply to the Tribunal to review the Commission’s decision to issue a
direction to rectify nor did it conduct any physical work on the HWU during the
rectification period.
On 3 September 2018, the Commission made a decision that building work
undertaken at the direction of the Commission is not of a satisfactory standard.2
Further to that, the Commission issued an infringement notice to CTP for an offence
under s 73 of the QBCC Act on the basis that CTP has failed to comply with the
direction to rectify. CTP later paid the amount owing by the infringement notice to
State Penalties Enforcement Registry.
CTP now applies to the Tribunal to review the Commission’s decision of 3 September
2018 and seeks final orders that the Commission’s decision be set aside and by way
1 QBCC Act, s 86.
2 Ibid, s 86(1)(f).
-- 2 of 11 --
3
of a substituted decision the Tribunal order that the direction items were rectified to a
satisfactory standard.3
The review application proceeded to a telephone hearing in Brisbane. The
representatives for the parties and the parties’ witnesses gave evidence at the Tribunal
hearing by telephone.4
The Tribunal’s power to review a decision
The present matter before me is CTP’s application to review the Commission’s
decision of 3 September 2018 that building work undertaken at the direction of the
Commission is not of a satisfactory standard. This requires me to conduct a fresh
hearing on the merits in exercising the Tribunal’s review powers under the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘the QCAT Act’).5
In conducting a review, the Tribunal effectively stands in the shoes of the Commission
decision-maker exercising the same powers under the QBCC Act, to produce the
correct and preferable decision.6 It is not necessary for the applicant to establish any
error in either the process or the reasoning that led to the decision and there is no
presumption that the reviewable decision is correct.7
The Commission, as the respondent decision-maker, has a duty to assist the Tribunal
so that it can make its decision. The Commission also has a model litigant role.8 In
assessing the evidence, the Tribunal on review must be satisfied to the required civil
standard on the balance of probabilities that certain factual matters are proven.9
The Tribunal is required to consider the material that was before the decision-maker,
commonly referred to as the ‘section 21 material’, and any fresh or new material
presented by the parties.10
In the present matter, the Tribunal is assisted by a hearing brief prepared by the
Commission that contains a copy of the applicant’s material and the Commission’s
statements of evidence to be relied upon in the review hearing.11
What is the correct and preferable decision?
CTP seeks a review of the Commission’s decision made on 3 September 2018 that
building work undertaken at the direction of the Commission is not of a satisfactory
standard (‘the decision’).
Although there is no specific section under the QBCC Act that refers to the
Commission’s power to make the decision, s 86(1)(f) and s 87, when read together,
3 Hearing Brief (‘Exhibit 1’), Response to miscellaneous matters filed by the applicant dated 2 June
2020, Part 11. At the oral hearing, CTP abandoned its application for further orders that the demerit
points incurred as a result of the direction to rectify be reversed and the fine paid be refunded.
4 Tribunal Directions dated 21 May 2020.
5 See QCAT Act, s 18.
6 QCAT Act, s 20.
7 Kehl v Board of Professional Engineers of Queensland [2010] QCATA 58, [9].
8 QCAT Act, s 21.
9 See Briginshaw v Briginshaw (1938) 60 CLR 336, 361-362.
10 The decision-maker must file a written statement of the reasons and any material relevant to the review
pursuant to s 21(2) of the QCAT Act.
11 Exhibit 1.
-- 3 of 11 --
4
clearly provide that the Commission is empowered to make the decision that is now
being reviewed.
In the present matter, the Commission contends and I accept, that a review of the
decision pursuant to s 86(1)(f) of the QBCC Act is limited to circumstances where the
Commission has made a decision that building work undertaken at the direction of the
Commission is or is not of a satisfactory standard.12
Relevantly, on 18 July 2018 the Commission issued a direction to rectify to CTP for
the following non-structural defective work:
The installation of the new hot water unit into the existing services cupboard is
non-compliant with AS3500.4 (Plumbing Code of Australia) and the
Queensland Plumbing & Wastewater Code in that water from the HW unit and
AC to the dwelling is being discharged directly into the safe tray resulting in
pooling of water within the safe tray which is wetting timber packers and
causing rusting to occur – pertains to item 1 on QBCC complaint form.13
The power to issue a direction to rectify work is discretionary. Under s 72, the
Commission may direct a person who has carried out building work that is defective
or incomplete to rectify the building work. In deciding to give a direction under s 72,
the Commission may take into consideration all of the circumstances it considers are
reasonably relevant and, in particular, is not limited to a consideration of the terms of
the contract for carrying out the building work.14 Further to that, the Commission is
not required to give the direction if the Commission is satisfied that, in the
circumstances, it would be unfair to the person to give the direction.15 The
Commission’s Rectification Policy is also relevant to the exercise of discretion and
the decision to issue a direction to rectify under s 72 of the QBCC Act.
In the present matter, CTP contends that it did complete building work during the
rectification period. CTP contends that the Commission extended the rectification
period or time for compliance with the direction to rectify from 20 August 2018 to 30
August 2018.16
In the oral hearing, Ben Scerri, Director submitted on behalf of CTP that the
homeowner refused to allow CTP access to rectify the building work. Mr Scerri
submitted that he presented the homeowner with solutions and made attempts to
contact the homeowner to arrange access. Mr Scerri referred the Tribunal to
s 72AA(2) of the QBCC Act and argued that a person must not obstruct another person
from rectifying the building work. Further to that Mr Scerri argued that the building
work was obstructed by the homeowner and CTP should not be penalised by the
homeowner who did not grant them access to the property. Mr Scerri argued that the
building work was of a satisfactory standard and stated that although CTP did not
make the HWU compliant to start with he tried to do everything right and CTP should
not be held responsible.
12 Exhibit 1, Written submissions of the respondent, Tab 12, p 2.
13 Ibid, Tab 9, p 18.
14 QBCC Act, s 72(3).
15 Ibid, s 72(5).
16 Exhibit 1, Tab 9, p 27.
-- 4 of 11 --
5
Mr Scerri’s evidence that he presented the homeowner with solutions is important
because although CTP did not perform any physical work on the HWU during the
rectification period, CTP contends that it did undertake building work. In response,
the Commission submits that if there is no building work undertaken such as physical
work at the direction of the Commission, there can be no reviewable decision. The
Commission invites the Tribunal on review to make a preliminary finding as to
whether the works, if any, were carried out at the direction of the Commission.17
Preliminary issue – is there a reviewable decision?
The Commission contends and I accept that the Tribunal’s jurisdiction is limited to a
consideration of whether building work was undertaken at the direction of the
Commission within the period of compliance specified in the direction to rectify.18
That said, the Commission contends the Tribunal is required to make a preliminary
finding as to whether the works, if any, were carried out at the direction of the
Commission. The Commission submits that where there is no building work
undertaken at the direction of the Commission, there can be no decision whether same
is or is not of a satisfactory standard.19
The Commission’s preliminary issue of whether there is a reviewable decision was
previously considered by the Tribunal prior to the hearing of CTP’s review
application.20 Relevantly, on 25 October 2019 the Tribunal dismissed the
Commission’s application for miscellaneous matters (to dismiss CTP’s review
application) filed on 13 September 2019 having found that there is an arguable case
that CTP undertook building work in response to the direction to rectify.
Notwithstanding, the Commission now asserts in the present matter that the Tribunal
made its earlier decision without the benefit of evidence and only relying upon written
submissions filed by the parties.21 In the present matter the Commission maintains its
position that the application to review should be dismissed on the basis that the
decision of 3 September 2018 is not a decision that falls within the ambit of s 86(1)(f)
of the QBCC Act.22
In addressing the preliminary issues, the Commission identifies a number of questions
to be answered by the Tribunal as to what work was ‘directed’ by the Commission;
whether any building work was undertaken by CTP during the rectification period in
response to the direction to rectify; and what is the rectification period. If I find that
CTP did undertake building work during the rectification period, the Commission
contends that the building work undertaken at the direction of the Commission was
not of a satisfactory standard.
What work was directed by the Commission?
I find that the defective work to be rectified by CTP is the work outlined in the
direction to rectify issued by the Commission on 18 July 2018.23 I accept the
17 Exhibit 1, Tab 12, p 13.
18 Ibid, Tab12, p 14.
19 Ibid.
20 CTP v Plumbing and Maintenance Pty Ltd t/as Charlie the Plumber v Queensland Building and
Construction Commission [2019] QCAT 409; see Exhibit 1.
21 Ibid.
22 Exhibit 1, Tab 12, p 27.
23 Ibid, Tab 2, p 66.
-- 5 of 11 --
6
Commission’s contention that the work ‘directed’ by the Commission was the
satisfactory rectification of the defective work or a resolution acceptable to both CTP
and the homeowner.24
CTP does not dispute that the installation of the HWU was defective and that the
direction to rectify issued by the Commission required CTP to rectify the defect. Mr
Scerri gave evidence at the hearing on behalf of CTP about the installation of the
HWU and the direction to rectify. Mr Scerri accepted, when questioned, that rectifying
the defect requires CTP to have undertaken physical work. Mr Scerri stated that the
Commission suggested various methods to rectify the installations that were
noncompliant.
When questioned about the installation of the HWU and whether CTP knew at the
time of completing the work that the work (on the HWU) was noncompliant, Mr Scerri
stated that before completing the work for the homeowner he pointed out that the
existing work, prior to CTP installing the HWU, was not compliant in that the waste
pipe from the existing HWU was non-compliant. Mr Scerri stated that the homeowner
refused to allow CTP to do the work necessary to make the HWU compliant because
he, the homeowner, did not want to pay for the work. Mr Scerri stated that the
homeowner was aware of the requirements and stated that in hindsight he (Mr Scerri)
should have walked away but instead he did the work for the homeowner as requested.
It is open for me to find that CTP was required to rectify the defective work as
identified in the direction. CTP did not exercise its review rights to review the
direction to rectify decision. Further to that, at the oral hearing of the application, Mr
Scerri accepted when cross-examined by the Commission that the direction to rectify
required CTP to rectify the defects and when asked if he understood from the direction
that immediate action was required Mr Scerri replied, ‘Yes’.
What is the rectification period?
The Commission says that CTP was required to comply with the direction to rectify
by 20 August 2018 being the date stipulated in the direction to rectify dated 18 July
2018. The Commission acknowledges that there is a dispute as to whether the
rectification period was extended by the Commission to 30 August 2018 on the basis
of an email sent to CTP by Darren Girling, Building Inspector for the Commission,
purporting to approve an extension of time to 30 August 2018.25 The relevant extract
from the email dated 23 August 2018 sent by Mr Girling to CTP is as follows:
…QBCC has taken into consideration all your circumstances and in best
interests of achieving a desirable outcome for everyone involved QBCC has
approved an EOT for CTP to comply with the DTR to the 30 th August 2018.
After which time if the matter has not been resolved by way of agreement or
rectification works QBCC will issue a FTR and infringement notice. This is on
the basis that all attempts by CTP have been made to gain access to the premises
and the owner grants reasonable access within the timeframe.26
The Commission concedes that there were discussions between Mr Girling and Mr
Scerri as to a potential extension of time. The Commission says, however, that CTP
did not request an extension of time either verbally or in writing before 20 August
24 Exhibit 1, Tab 12, [18].
25 Ibid, p 22.
26 Ibid, Tab 9, p 27.
-- 6 of 11 --
7
2018. Further to that, the Commission says that Mr Girling did not have the power to
grant an extension to the direction period under s 72B of the QBCC Act and Mr
Girling’s purported extension to the direction period was of no effect.
The Commission’s contentions raise a question as to the validity of the extension of
time that involved the exercise of the Commission’s power under s 72B of the QBCC
Act. As held by the High Court in Project Blue Sky Inc v Australian Broadcasting
Authority27 an act done in breach of a condition regulating the exercise of a statutory
power is not necessarily invalid and of no effect. Whether it is depends upon ‘whether
there can be discerned a legislative purpose to invalidate any act that fails to comply
with the condition’.28 The High Court said:
An act done in breach of a condition regulating the exercise of a statutory power
is not necessarily invalid and of no effect. Whether it is depends upon whether
there can be discerned a legislative purpose to invalidate any act that fails to
comply with the condition. The existence of the purpose is ascertained by
reference to the language of the statute, its subject matter and objects, and the
consequences for the parties of holding void every act done in breach of the
condition. …29
In the present matter, I do not consider that Parliament would intend to render void
every purported extension of time for a contractor to comply with a direction to rectify
properly issued by the Commission under s 72 of the QBCC Act in circumstances
where, such that exist in this matter, the Commission considers that the extension is
desirable for everyone involved to extend the time for compliance.
The purpose of the QBCC Act is, amongst other things, to regulate the building
industry and to achieve a reasonable balance between the interests of building
contractors; and consumers and to provide remedies for defective building work.30
In the present matter, the Commission properly issued a direction to rectify building
work to CTP on 18 July 2018. It is apparent from the email sent by Mr Girling dated
23 August 2018 to CTP that Mr Girling was satisfied that the extension was, as stated,
‘a desirable outcome’. The Commission concedes that there were discussions between
Mr Girling and CTP about the extension of time. Indeed, the unchallenged evidence
of Mr Scerri on behalf of CTP is that there were emails and telephone calls exchanged
between Mr Girling and Mr Scerri during the period from 18 July 2018 when the
direction to rectify was issued to 23 August 2018 when the rectification period was
purportedly extended by the Commission.31 Further, the Commission does not dispute
that by email dated 23 August 2018, CTP was notified that the time for compliance
with the direction to rectify was extended. It is open for me to find on the evidence
that the rectification period was extended to 30 August 2018.
I do not consider it necessary to determine whether, as contended by the Commission,
the Commission’s purported extension of the rectification period was of no effect.
Here, the Tribunal in exercising its review functions is required to consider the matter
afresh and to arrive at the correct and preferable decision. The Tribunal does not have
27 (1998) 194 CLR 355.
28 Ibid, 388-9.
29 Ibid.
30 QBCC Act, s 3.
31 Exhibit 1, Tab 8.
-- 7 of 11 --
8
any broad discretionary powers or ‘general jurisdiction’ as resides in the Supreme
Court. The Tribunal’s review jurisdiction is enlivened because CTP has filed an
application to review the Commission’s decision of 3 September 2018 pursuant to
s 86(1)(f) of the QBCC Act.32
The Tribunal is required to conduct the review in accordance with the QCAT Act and
the enabling Act and, amongst other things, may perform the functions conferred on
the Tribunal by the QCAT Act or the enabling Act under which the reviewable
decision being reviewed was made; and has all of the functions of the decision-
maker.33 The orders that may be made by the Tribunal on review, as provided under
s 24 of the QCAT Act, are to confirm or amend the decision; set aside the decision
and substitute its own decision; or set aside the decision and return the matter for
reconsideration to the decision-maker for the decision, with the directions the Tribunal
considers appropriate.34
Was any building work undertaken by CTP during the rectification period?
CTP says that it attended to the following during the rectification period:
(a) Undertaking review of the relevant codes;
(b) Providing professional advice to the homeowner regarding the options available
to rectify the alleged defect;
(c) Seeking instructions from the homeowner on his preferred decision;
(d) Making offers to carry out the work discussed and seeking access albeit
unsuccessfully, to the homeowner’s property; and
(e) Attending the homeowner’s property to inspect the HWU, take measurements
and to work out solutions suitable for rectification.35
CTP relies on an email sent to the homeowner dated 15 August 2018 by which it
proposed three solutions to finalise the HWU installation.36 CTP also relies on,
amongst other things, an email sent to the homeowner dated 26 August 2018
requesting access to the property.37
Turning firstly to the preliminary issue raised by the Commission as to whether any
building work was undertaken by CTP at the direction of the Commission. ‘Building
work’ is defined under Schedule 2 of the QBCC Act and includes, amongst other
things, the preparation of plans or specifications for the performance of building work,
or contract administration carried out by a person in relation to the construction of a
building designed by the person.38 Further to that, as submitted by the Commission,
Schedule 2 of the QBCC Act defines ‘undertake to carry out’ to mean enter into a
32 Exhibit 1, Tab 1.
33 QCAT Act, s 18.
34 Ibid, s 20.
35 See Exhibit 2. Mr Scerri gave oral evidence at the hearing about his attendance on 13 August 2018 at
the homeowner’s property to inspect the HWU.
36 Exhibit 1, Tab 8.
37 Ibid.
38 QBCC Act, Schedule 2 (definition of ‘building work’ paras (f) and (fa)).
-- 8 of 11 --
9
contract to carry out the work, submit a tender to carry out the work or make an offer
to carry out the building work.
The Commission whilst acknowledging that the definition of building work is broad
submits that only physical work on the HWU could be capable of rectifying the
physical defects.39 The Commission raises the same issues and maintains the same
position previously advanced in its application to dismiss the review proceeding that
was considered by the Tribunal on 25 October 2019. As discussed above the Tribunal
found, amongst other things, that it is arguable that CTP undertook building work in
response to the direction to rectify and dismissed the Commission’s application. The
QBCC did not exercise its appeal rights to challenge the Tribunal’s decision nor its
findings made. That said, I acknowledge the Tribunal’s findings about whether CTP
undertook building work in response to the Commission’s direction to rectify.
Relevantly, the Tribunal found that it is arguable that CTP undertook building work
during the rectification period.
Notwithstanding the Tribunal’s earlier findings, the Commission’s submission as to
whether there is a reviewable decision on the basis that building work was not
undertaken, misapprehends the Tribunal’s review function. The Tribunal has
jurisdiction to deal with matters it is empowered to deal with under the QCAT Act or
an enabling Act.40 In this matter, the Commission does not dispute that the decision
of 3 September 2018 was properly made under the QBCC Act and that CTP was
entitled to bring the application to review the decision. Further to that, it is a matter
for the Tribunal to determine its own jurisdiction. Relevantly, s 18 of the QCAT Act
provides that the Tribunal may exercise its review jurisdiction if a person has, under
the QCAT Act, applied to the Tribunal to exercise review jurisdiction for a reviewable
decision. As discussed above, the Tribunal on review is required to consider all of the
evidence afresh exercising the same powers as the Commission under the QBCC Act
to arrive at the correct and preferable decision. I find that there is a reviewable decision
before me properly made under the QBCC Act on 3 September 2018 and CTP is
entitled to review the decision, an application to review having been properly filed in
the Tribunal within the required time.
Was any building work undertaken at the direction of the Commission of a satisfactory
standard?
CTP relies on emails sent to the homeowner about the defective work and Mr Scerri’s
evidence that he engaged in discussions with Mr Girling of the Commission about the
defective work. CTP also says, and I accept, that it attended the property during the
rectification period to take measurements and to assess the defective work. CTP’s
submission about attending the homeowner’s property is supported by Mr Scerri’s
oral evidence given at the hearing.
I accept Mr Scerri’s evidence that he sent an email dated 15 August 2018 to the
homeowner offering a number of solutions in an attempt to reach a resolution about
the defective work. I do not accept, however, Mr Scerri’s evidence that Mr Girling
gave CTP advice or instructions about how to rectify the defective work.
39 Exhibit 1, Tab 12, p 26.
40 See JM Kelly (Project Builders) Pty Ltd v Queensland Building Services Authority [2013] QCAT 502.
-- 9 of 11 --
10
At the hearing, Mr Scerri was unable to direct me to any emails or correspondence
that he said prove that Mr Girling gave CTP advice or instructions about how to rectify
the defective work.
At the oral hearing, Mr Girling gave evidence to the effect that there were several
conversations between himself and Mr Scerri about the defective work but disputed
when questioned that he would ever suggest that work be done in a certain way to
rectify the defective work. Mr Girling’s evidence that the Commission does not give
advice or make recommendations about how to rectify the work is supported by Mr
Girling’s email sent to CTP dated 13 August 2018. In the Commission’s email to CTP
dated 13 August 2018, Mr Girling advises Mr Scerri that the Commission does not
give instructions on how to rectify or comply with the defective work as detailed in
the direction to rectify.41 I accept Mr Girling’s evidence that he did not give Mr Scerri
or CTP advice or make recommendations about how to rectify the defective work.
I am not satisfied based on the evidence before me that CTP has undertaken building
work at the direction of the Commission to a satisfactory standard. I accept Mr Scerri’s
evidence that CTP provided the homeowner with solutions to reach a resolution about
the defective work. I am not satisfied, however, based on the evidence before me, that
the steps taken by CTP such as, as contended by CTP, undertaking review of the
codes, providing professional advice and presenting solutions to the homeowner,
seeking instructions, making offers and attending the property to take measurements
and to assess the work, mean that the building work the subject of the direction to
rectify has been satisfactorily rectified.
On a fair reading of CTP’s email dated 15 August 2018 sent to the homeowner, the
‘solutions’ identified by CTP would require the homeowner to, as stated by CTP in
the email, incur charges for extra work, or would result in supply issues to the hot
water or require the homeowner to arrange for work to be done by a new installing
plumber.42 Further, CTP’s email dated 15 August 2018 does not request access by the
homeowner to the property to perform any work.
Although CTP requested access to the property from the homeowner by email dated
26 August 2018, CTP stated in the email that access to the property is required to
confirm measurements and amongst other things and as stated in the email that should
installation of the HWU not be achievable, CTP is ‘happy to look at other requests
that the client is willing to accept including removal of the [HWU] and refund of
payment made for plumbing work’.43
It is open for me to find on the evidence that CTP’s offers of solutions to the
homeowner were, as contended by the Commission, vague and equivocal suggestions
of rectification methods.44 Further to that, the building work remained defective in
that the HWU remained noncompliant with Australian Standards as at 30 August
2018, the date by which CTP was to rectify the defective work. The unchallenged
evidence of the homeowner is that he arranged for another plumber to replace the
existing HWU in or about March 2019.45
41 Exhibit 1, Tab 9, 21.
42 Ibid, Tab 3.
43 Ibid, Tab 10, p 54.
44 Ibid, Tab 12, p 28.
45 Ibid, Tab 10, [28].
-- 10 of 11 --
11
I have carefully considered CTP’s submission that it installed the HWU at the
instruction of the homeowner and that CTP has been denied natural justice because of
the homeowner’s refusal to grant CTP access to the property to enable rectification.
Although, I have some sympathy for CTP’s submission that it installed the HWU at
the instruction of the homeowner, this does not excuse CTP as a licensee from its
responsibility to comply with relevant standards and building codes. Relevantly, s 72
of the QBCC Act deems CTP to be responsible for the work performed and the
Commission issued a direction to CTP to rectify the work on 18 July 2018.
As discussed above, CTP did not exercise its review rights in relation to the direction
to rectify decision of 18 July 2018. Indeed, the evidence of Mr Scerri on behalf of the
CTP is that CTP accepts the work performed including the installation of the HWU
did not comply with the relevant standards. Further, I am not satisfied that the
homeowner refused CTP access to the property such that the works could not be
rectified. Mr Scerri gave evidence at the hearing that the homeowner granted CTP
access to the property in August 2018 and on 13 August 2018, Mr Scerri inspected
the HWU. There is also evidence before me that the homeowner was willing to give
CTP access. In an email sent by the homeowner dated 29 June 2018 to Mr Scerri the
homeowner states, ‘we can grant you access to the unit anytime next week…’.46
I am satisfied and find accordingly that CTP has had sufficient time to attend to
rectification of the defective work, an extension of time to rectify the work having
been granted by the Commission to 30 August 2018.
I have considered CTP’s submission that the Commission reopened the homeowner’s
complaint after he amended the date that he (the homeowner) became aware of the
non-compliance thereby meeting the timeframe for lodging a complaint.47 As
discussed above, the Commission’s decision to accept the homeowner’s complaint
and to issue a direction to rectify on 18 July 2018 is not under review in the present
matter. More importantly, the time to review the direction to rectify decision has
expired. A review of the decision to issue a direction to rectify under s 72 of the QBCC
Act would have involved a consideration of relevant matters such as whether it was
unfair to CTP to give the direction.
The correct and preferable decision having considered all the evidence and
submissions before me is that building work undertaken at the direction of the
Commission is not of a satisfactory standard. I order that the Commission’s decision
of 3 September 2018 is confirmed.
46 Exhibit 1, Tab 10, p 47.
47 Ibid, Tab 11.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2020/307