Contrast Constructions Pty Ltd v Allen & Anor [2020] QCAT 194
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Contrast Constructions Pty Ltd v Allen & Anor [2020]
QCAT 194
PARTIES: CONTRAST CONSTRUCTIONS PTY LTD
(applicant)
v
REECE ALLEN
(first respondent)
CHANTELL TAYLOR
(second respondent)
APPLICATION NO/S: BDL219-19
MATTER TYPE: Building matters
DELIVERED ON: 21 May 2020
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
ORDERS: The application for miscellaneous matters is
refused.
Contrast Constructions Pty Ltd must file two (2)
copies in the Tribunal and give one (1) copy to
Reece Allen and Chantell Taylor of:
(a) Contrast Constructions Pty Ltd’s statement of
evidence, which must be signed, dated and
page numbered;
(b) the signed, dated and page numbered
statement from each witness to give evidence
for Contrast Constructions Pty Ltd at the
hearing including any experts; and
(c) any documents referred to in a statement of
evidence which must be identified, explained
and attached to the appropriate witness
statement, by:
4:00pm on 18 June 2020.
Reece Allen and Chantell Taylor must file two (2)
copies in the Tribunal and give one (1) copy to
Contrast Constructions Pty Ltd of:
-- 1 of 16 --
2
(a) Reece Allen’s and Chantell Taylor’s statement
of evidence, which must be signed, dated and
page numbered;
(b) the signed, dated and page numbered
statement from each witness to give evidence
for Reece Allen and Chantell Taylor at the
hearing including any experts; and
(c) any documents referred to in a statement of
evidence which must be identified, explained
and attached to the appropriate witness
statement, by:
4:00pm on 16 July 2020.
Reece Allen and Chantell Taylor must file in the
Tribunal two (2) copies and give to Contrast
Constructions Pty Ltd one (1) copy of a Schedule of
defective and incomplete work (a Scott Schedule),
by:
4:00pm on 16 July 2020.
Contrast Constructions Pty Ltd must file two (2)
copies in the Tribunal and give one (1) copy to
Reece Allen and Chantell Taylor of Contrast
Constructions Pty Ltd’s signed, dated and page
numbered statements of evidence in reply, by:
4:00pm on 13 August 2020.
Contrast Constructions Pty Ltd must complete the
Scott Schedule and file in the Tribunal two (2)
copies and give to Reece Allen and Chantell Taylor
one (1) copy of the completed Scott Schedule, by:
4:00pm on 13 August 2020.
Reece Allen and Chantell Taylor must file in the
Tribunal two (2) copies and give to Contrast
Constructions Pty Ltd one (1) copy of any
statements of evidence in reply limited to the
counter-application, by:
4:00pm on 27 August 2020.
The matter is listed for a Directions Hearing on a
date and time to be advised.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS
AND IMPLIED CONDITIONS – SETTLEMENT OF
DISPUTES – where respondents contend that the
proceedings should be dismissed for non-compliance with
dispute resolution processes provided for in contract –
-- 2 of 16 --
3
whether dispute resolution clause survived termination of
the contract – power of tribunal to stay proceedings –
whether proceedings should be stayed pending compliance
with dispute resolution provision – where not in the
interests of justice for the proceedings to be stayed - where
no utility in requiring the parties to comply with
contractual dispute resolution process
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT – where
respondents contend that the proceedings should be
dismissed for non-compliance with s 77(2) of QBCC Act –
where compliance achieved before commencement of
proceedings
Queensland Building and Construction Commission Act
1991 (Qld), s 77(2), sch 1B, s 32(1)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 28(3)(b), s 47, s 69(b)
Allen & Taylor v Queensland Building and Construction
Commission [2020] QCAT 63
Dobbs v National Bank of Australasia Ltd (1935) 53 CLR
643
Downer EDI Mining Pty Ltd v Wambo Coal Pty Ltd
[2012] QSC 290
Electricity Generation Corporation v Woodside Energy
Ltd; Woodside Energy Ltd v Electricity Generation
Corporation (2014) 251 CLR 640
Elizabeth Bay Developments Pty Ltd v Boral Building
Services Pty Ltd (1995) 36 NSWLR 709
Ferris v Plaister (1994) 34 NSWLR 474
Iezzi Constructions Pty Ltd v Watkins Pacific (Qld) Pty
Ltd [1994] QCA 49
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty
Ltd [2014] WASC 10
Racecourse Betting Control Board v Secretary for Air
[1944] Ch 114
Richmond v Moore Stephens Adelaide Pty Ltd [2015]
SASCFC 147
Straits Exploration (Australia) Pty Ltd v Murchison
United NL [2005] WASCA 241
WTE Co-Generation v RCR Energy Pty Ltd [2013] VSC
314
Zeke Services Pty Ltd v Traffic Technologies Ltd [2005]
Qd R 563
4D Electrical Qld v Greyburn Pty Ltd [2020] QCAT 74
-- 3 of 16 --
4
REPRESENTATION:
Applicant: Self represented
Respondent: Self represented
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld).
REASONS FOR DECISION
[1] Contrast contracted with the respondents to build a house. The parties fell into dispute.
Each party purported to terminate the contract. Contrast commenced proceedings in
the tribunal claiming damages for breach of contract.1 The respondents have filed a
response on a ‘conditional basis without accepting the jurisdiction of (the) tribunal to
entertain (Contrast’s) claim’.2
[2] Before filing the response, the respondents filed an application for miscellaneous
matters3 seeking a number of orders including that the matter be listed for a directions
hearing on the basis of the respondents’ assertion that ‘they have (the) right to be heard
in relation to whether or not the tribunal has jurisdiction … and in particular whether
the applicant has complied with s 77(2) of the QBCC Act’.4
[3] The respondents say that Contrast failed to comply with the dispute resolution
provisions in the contract and failed to comply with s 77(2) of the Queensland
Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’) before
commencing the proceedings.
[4] Although the respondents have not applied to amend the orders sought in the
application for miscellaneous matters, the parties have clearly proceeded on the basis
that the respondents seek an order dismissing the proceedings pursuant to s 47 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) or
alternatively staying the proceedings until Contrast has complied with the dispute
resolution provisions of the contract.
Contractual requirements – alternative dispute resolution
[5] Clauses 42.1 and 41.2 of the contract, as varied by special condition 13, provide:
42.1 Notice of Dispute
If a difference or dispute (together called a ‘dispute’) between the parties arises
in connection with the subject matter of the Contract, including a dispute
concerning:
a) a Superintendent’s direction; or
b) a claim:
1 Application for domestic building disputes filed 19 August 2019.
2 Response filed 9 October 2019.
3 Application for miscellaneous matters filed 25 September 2019.
4 Ibid.
-- 4 of 16 --
5
i) in tort;
ii) under statute;
iii) for restitution based on unjust enrichment or other quantum meruit;
or
iv) for rectification or frustration,
or like claim available under the law governing the Contract,
then either party shall, by hand or by certified mail, give the other and the
Superintendent a written notice of dispute adequately identifying and providing
details of the dispute.
Notwithstanding the existence of a dispute, the parties shall, subject to clauses
39 and 40 and subclause 42.4, continue to perform the Contract.
42.2 Conference
Within 14 days after receiving a notice of dispute, the parties shall confer at
least once to resolve the dispute or to agree on methods of doing so. At every
such conference each party shall be represented by a person having authority to
agree to such resolution or methods. All aspects of every such conference except
the fact of occurrence shall be privileged.
If the dispute has not been resolved within twenty eight 28 days of service of
the notice of dispute, either party may refer the dispute to:
(a) the dispute resolution processes administered by the QBCC;
(b) QCAT; or
(c) a court.
Any reference of the dispute to the QBCC is without prejudice to either party’s
right to refer any dispute to QCAT where entitled under Legislative
requirements or otherwise to a court.
[6] As can be readily observed the obligation upon the parties to engage in dispute
resolution was not an onerous one, there being no requirement for a structured dispute
resolution process such as mediation. Clause 42 might be said to reflect no more than
a common sense approach to attempting to resolve disputes arising between parties to
a contract.
[7] While there has been no determination in these proceedings of the issue whether the
contract has in fact been properly terminated by either party, the first issue to address
is whether clause 42 survived a (assumed) valid termination.
[8] In Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd5 Martin CJ in the
Supreme Court of Western Australia held that a dispute resolution clause survived
termination of the relevant contract. The relevant provision considered by Martin CJ
was an arbitration clause. His Honour stated:
An arbitration agreement is generally considered to be a contract independent
of the underlying contract in which it is contained, and for that reason in the
absence of evidence of a contrary intention of the parties, evident in the
language that they have used, survives termination of the underlying contract:
see Ferris v Plaister (1994) 34 NSWLR 474, 484 (Kirby P), 496 - 497
5 [2014] WASC 10.
-- 5 of 16 --
6
(Mahoney JA), 500 - 501, 503 - 504 (Clarke JA); Harbour Assurance Co (UK)
Ltd v Kansa General International Insurance Co Ltd [1993] QB 701, 723 - 724
(Hoffman LJ); Heyman v Darwins Ltd [1942] AC 356, 374 - 375 (Macmillan
LJ); Bremer Vulkan Schiffbau & Maschinenfabrik v South India Shipping Corp
Ltd [1981] AC 909, 998 (Scarman LJ); Rizhao Steel Holding Group v Koolan
Iron Ore [165] (Martin CJ). In Heyman v Darwins , Lord Macmillan said:
“[A]n arbitration clause in a contract … is quite distinct from the other
clauses. The other clauses set out the obligations which the parties
undertake towards each other … but the arbitration clause does not
impose on one of the parties an obligation in favour of the other. It
embodies the agreement of both parties that, if any dispute arises with
regard to the obligations which the one party has undertaken to the other,
such dispute shall be settled by a tribunal of their own constitution. …
[W]hat is commonly called repudiation or total breach of a contract,
whether acquiesced in by the other party or not, does not abrogate the
contract, though it may relieve the injured party of the duty of further
fulfilling the obligations which he has by the contract undertaken to the
repudiating party. The contract is not put out of existence, though all
further performance of the obligations undertaken by each party in favour
of the other may cease. It survives for the purpose of measuring the
claims arising out of the breach, and the arbitration clause survives for
determining the mode of their settlement. The purposes of the contract
have failed, but the arbitration clause is not one of the purposes of the
contract (373 - 374).”6
[9] Martin CJ observed:
Construction of a commercial agreement to the effect that provisions for the
resolution of disputes, such as by arbitration, do not survive termination of the
agreement would be inconsistent with the approach indicated in the authorities
to which I have referred. That is because it will commonly be the case that
parties will disagree as to whether their contract has been terminated and if so,
as to the consequences of termination. In such a circumstance, the conclusion
that the dispute resolution provisions of the contract depend upon the
determination of the question of whether the contract has been terminated is
manifestly inconvenient. For example, the parties might wish to refer such a
dispute to arbitration, or may be required by their contract to refer such matters
to arbitration as a condition of the exercise of any right to commence legal
proceedings. But a decision of the arbitral tribunal to the effect that the contract
has been terminated would deprive the arbitral tribunal of jurisdiction and
prevent any award being made to give effect either to the termination or its
consequences. This would in turn create an incentive for the parties to first
determine, in a court, whether the contract remained on foot before then
invoking its provisions relating to the resolution of disputes in the event of an
affirmative answer to that question. However, that course would itself be
inconsistent with their expressed desire to utilise particular mechanisms for the
resolution of their disputes, and with the assumption that the parties intended
that their disputes could be resolved in a single forum.7 (emphasis added)
6 Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10, 42.
7 Ibid 47.
-- 6 of 16 --
7
[10] Martin CJ relied upon, inter alia, Ferris v Plaister8 where the New South Wales Court
of Appeal considered whether an arbitration clause survived termination of a contract
based upon an allegation of fraud where it was asserted that such a contract was void
ab initio. In Ferris the court found that an arbitration clause is a ‘self-contained
contract’.9 This ‘separability principle’10 was central to Martin CJ’s decision in
Pipeline Services.
[11] In Elizabeth Bay Developments Pty Ltd v Boral Building Services Pty Ltd11 Giles J in
the New South Wales Supreme Court considered the enforceability of a contractual
provision requiring the parties to refer a dispute to mediation. Giles J stated:
Although the construction management contract and the building contract had
come to an end, one way or another, in the middle of 1994, it was common
ground that the provisions for mediation survived in the same manner as the
provisions for arbitration.12
[12] The mediation provision under consideration in Elizabeth Bay Developments was in
quite different terms to clause 42 of the contract between Contrast and the
respondents. The provision considered by Giles J required the parties to first engage
in mediation and, if the dispute could not be resolved, the dispute would then be
referred for arbitration.
[13] In Downer EDI Mining Pty Ltd v Wambo Coal Pty Ltd13 Martin J considered that there
was no relevant difference, in principle, between expert determination clauses and
dispute resolution clauses.14 In Downer the contract required the parties to comply
with the dispute resolution procedure set out in the contract and provided that ‘a party
may not commence court proceedings concerning a (d)ispute’ unless, inter alia, the
party complied with the dispute resolution clause.15 The clause required the parties to
engage in a process, commenced by the delivery of a dispute notice, to attempt to
resolve the dispute by negotiation. If the negotiations were unsuccessful, and
depending upon the quantum of the dispute, the contract required the referral of the
dispute for expert determination.
[14] It should be noted however that in Downer EDI the contract had not been terminated
and the question of whether the dispute resolution provision survived termination did
not arise for consideration. Martin J’s statement that there was no relevant difference
in principle between expert determination clauses and dispute resolution clauses was
a reference to the consideration of the principles relevant to granting a stay of
proceedings while the parties complied with their contractual obligations to engage in
a dispute resolution process.
8 (1994) 34 NSWLR 474.
9 Ibid 501.
10 Ibid.
11 (1995) 36 NSWLR 709.
12 Ibid 715.
13 [2012] QSC 290.
14 Ibid [8].
15 Ibid [6].
-- 7 of 16 --
8
[15] In McDonald v Dennys Lascelles Ltd,16 Dixon J stated:
When a party to a simple contract, upon a breach by the other contracting party
of a condition of the contract, elects to treat the contract as no longer binding
upon him, the contract is not rescinded as from the beginning. Both parties are
discharged from the further performance of the contract, but rights are not
divested or discharged which have already been unconditionally acquired.
[16] Contractual provisions may survive termination however it must be apparent from the
terms of the agreement and of the particular provision that it is intended to continue
governing the relations of the parties even after the rest of the contract is gone.17
Contractual rights and obligations that may survive termination include those arising
when there is a breach of contract (eg clauses obliging a party to pay compensation or
damages for breach); obligations ancillary to the main purpose of the contract (eg
arbitration clauses, choice of forum clauses); and clauses regulating the secondary
obligations of parties (eg liquidated damages clauses).
[17] As has been outlined, arbitration clauses are an example of a contractual provision
that survive termination. Clause 42 is not however an arbitration clause.
[18] Whether clause 42 survives termination is a question of construction of the contract.
There is no express provision in the contract providing for the survival of specific
clauses in the event of the contract being terminated. In Richmond v Moore Stephens
Adelaide Pty Ltd 18 the Full Court of the Supreme Court of South Australia stated:
The general rule … can be expressed as a single rule: termination of a contract
discharges those obligations of a party that are not contingent upon its
subsistence or future events dependent on its subsistence or future obligations
discharged by its termination. Whether an obligation is or is not contingent in
this sense is to be determined as a matter of construction of the contract.
[19] The nature of a contractual provision may lead to a construction that the obligation is
not contingent and survives termination of the contract.
[20] Clause 42 provides for a notice to be given by a party in the event of a ‘dispute’. The
contract defines a ‘dispute’ as ‘a difference or dispute (together called a ‘dispute’)
between the parties … in connection with the subject matter of the Contract.’ The
definition is a broad one and potentially captures disputes across a wide spectrum
including disputes of a relatively minor nature through to disputes that may result in
termination of the contract. Upon giving a notice of dispute the parties are obliged to
engage in what may be best described as an informal dispute resolution process. After
28 days, a party may, inter alia, commence proceedings in the tribunal.
[21] Clause 42 does not provide for a well defined, structured dispute resolution process
in which the parties are required to participate and from which agreement might come.
Aside the requirement for the delivery of the dispute notice and the stipulated time
periods, clause 42 leaves dispute resolution entirely in the hands of the parties in an
informal and unstructured way. Unlike the various authorities to which I have referred,
clause 42 does not require the parties to proceed to a formal mediation or other dispute
resolution process. It should be noted that any requirement for parties to engage in
16 (1933) 48 CLR 457.
17 Iezzi Constructions Pty Ltd v Watkins Pacific (Qld) Pty Ltd [1994] QCA 49.
18 [2015] SASCFC 147, [197].
-- 8 of 16 --
9
arbitration would fall foul of the prohibition on arbitration clauses found in the QBCC
Act. 19
[22] Clause 42 required that the parties confer to resolve the dispute or to agree on methods
of doing so. The parties were only required to meet once and without the assistance
of a third party. If the dispute was not resolved the parties were at liberty to proceed
to litigation. Such a process was not one through which a dispute about whether
termination by one of the parties was valid was likely to achieve any meaningful
outcome.
[23] On a proper construction of the contract, clause 42 provided for an informal dispute
resolution process to enable the parties to attempt to resolve issues relating to the build
as and when those issues arose. There is nothing in clause 42 that leads to the
conclusion that, on a proper construction of the contract, the clause was intended to
survive termination. To construe clause 42 so as to require the parties to engage in
what could be described as a potentially very brief and very informal alternative
dispute resolution process before proceeding to formal litigation, in the context of a
purported termination of the contract, would be to give the clause a significance it was
not intended to have. Such a construction would be commercially nonsensical for the
reasons I have outlined.20 It follows that compliance or otherwise by Contrast with
clause 42 is irrelevant to Contrast’s entitlement to commence these proceedings.
[24] The tribunal has a power to stay proceedings if it is in the interests of justice to do
so.21 Even if I am wrong however about the effect of termination of the contract on
clause 42, for the reasons that follow I would nevertheless conclude that it is not in
the interests of justice for the proceedings to be stayed pending compliance by the
parties with the contractual dispute resolution process.
[25] The parties’ contractual entitlements and obligations regarding termination are to be
found in clause 39 of the contract. Where the contractor is said to be in substantial
breach of the contract, the principal is obliged to give a notice to show cause as to
why, inter alia, the contract should not be terminated.
[26] The respondents relied upon various grounds in the notice given to Contrast: failure
by Contrast to use materials or standards of work required by the contract; failure by
Contrast to proceed with due expedition and with delay and failing to carry out the
work with reasonable diligence and ensure that the works reached practical
completion by the agreed practical completion date; overclaiming/claiming payment
to which Contrast was not entitled.
[27] As I have observed, after purporting to terminate the contract, the respondents made
a claim under the Home Warranty Scheme for non-completion of the contract works.
A further claim was subsequently made by the respondents following acts of
vandalism at the building site. The QBCC rejected the respondents’ claim. The
respondents commenced the review proceedings. The tribunal confirmed the decision
of the QBCC, finding that the respondents had not lawfully terminated the contract.22
19 Queensland Building and Construction Commission Act 1991 (Qld) sch 1B, s 32(1).
20 Electricity Generation Corporation v Woodside Energy Ltd; Woodside Energy Ltd v Electricity
Generation Corporation (2014) 251 CLR 640.
21 4D Electrical Qld v Greyburn Pty Ltd [2020] QCAT 74.
22 Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63.
-- 9 of 16 --
10
[28] It is well established that courts and tribunals will, generally speaking, hold the parties
to a contract to the terms of the bargain they have struck, including contractual
mechanisms for dispute resolution. In Racecourse Betting Control Board v Secretary
for Air23 it was held:
… the court makes people abide by their contracts and … will restrain a plaintiff
from bringing an action which he is doing in breach of his agreement with the
defendant that any dispute between them shall be otherwise determined.
[29] Clause 42 of the contract as modified by special condition 13 is a product of the
parties’ agreement and the law does not discourage parties from resolving their
differences through alternative dispute resolution.24 Accepting for present purposes
that clause 42 survives termination, the failure by Contrast to comply with the dispute
resolution provisions of the contract does not render the proceedings liable to be struck
out but rather to be stayed until such compliance has been achieved.25
[30] The authorities dealing with adjudication clauses in contracts are relevant in
considering the effect of clause 42 and whether the proceedings should be stayed.
[31] In Zeke Services Pty Ltd v Traffic Technologies Ltd,26 Chesterman J, referring to the
power of the court to stay proceedings where the parties had agreed to a means for
dispute resolution, stated:
The discretion whether or not to grant the stay is obviously wide. The starting
point for a consideration of its exercise is that the parties should be held to their
bargain to resolve their dispute in the agreed manner. This factor was
emphasised by the House of Lords in Channel Tunnel, by the High Court in
Dobbs and Huddart Parker Ltd v The Ship Mill Hill and Her Cargo (1950) 81
CLR 502 (an arbitration case) and by Gillard J in Badgin. However, a stay will
not be granted if it would be unjust to deprive the plaintiff of the right to have
his claim determined judicially or, to put it slightly differently, if the justice of
the case is against staying the proceeding. The party opposing the stay must
persuade the court that there is good ground for the exercise of the discretion to
allow the action to proceed and so preclude the contractual mode of dispute
resolution. The onus is a heavy one. The court should not lightly conclude that
the agreed mechanism is inappropriate.
[32] In Downer EDI Mining Pty Ltd v Wambo Coal Pty Ltd27 Martin J stated:
In Straits Exploration (Australia) Pty Ltd v Murchison United NL the Western
Australian Court of Appeal was concerned with the operation of an expert
determination clause but, in doing so, also considered the effect of a dispute
resolution procedure. Wheeler JA, in giving the judgment of the court, said:
“[14] There is increasingly, as a matter of commercial practice, a
tendency of parties to provide for the determination of some or all
disputes by reference to an expert. There are a number of reasons for that
course, including informality and speed; suitability of some types of
disputes for determination by persons with particular expertise; privacy;
and a desire to resolve disputes in a way which may be seen as reasonably
23 [1944] Ch 114, 126.
24 Downer EDI Mining Pty Ltd v Wambo Coal Pty Ltd [2012] QSC 290, [9] citing Dobbs v National
Bank of Australasia Ltd (1935) 53 CLR 643, 652.
25 Straits Exploration (Australia) Pty Ltd v Murchison United NL [2005] WASCA 241.
26 [2005] Qd R 563, [21].
27 [2012] QSC 290, [10], [14]-[15].
-- 10 of 16 --
11
consistent with the maintenance of ongoing commercial relationships.
The law has long recognised that those are proper considerations to which
the Court should give appropriate weight, and that it is desirable therefore
that parties who make such a bargain should be kept to it. The tendency
of recent authority is clearly in favour of construing such contracts,
where possible, in a way that will enable expert determination
clauses to work as the parties appear to have intended, and to be
relatively slow to declare such provisions void either for uncertainty
or as an attempt to oust the jurisdiction of the court. A considerable
number of cases demonstrating this trend are collected in the reasons for
decision of Einstein J in Heart Research Institute Ltd v Psiron Ltd [2002]
NSWSC 646 at [16] - [33]. (See also Australian Pacific Airports
(Melbourne) Pty Ltd v Nuance Group (Australia) Pty Ltd [2005] VSCA
133 at [50] and Zeke Services Pty Ltd v Traffic Technologies Ltd [2005]
QSC 135 at [21].)
[15] The effect of a valid expert determination clause, however, is not to
oust the jurisdiction of the court, but to limit, in some circumstances, the
matters which the court can consider. Prior to the conclusion of the
expert determination procedure - that is, prior to the making of a
determination - any party to a contract containing such a clause
remains free to sue upon the contract, unless the contract itself makes
compliance with some form of dispute resolution procedure a
condition precedent to the enforcement of rights under the contract.
In relation to the latter type of contract, the effect of the clause is not
to invalidate an action brought in breach of it, but to provide a
defence and to "postpone" but "not annihilate the right of access to
the court" (Freshwater v Western Australian Assurance Co Ltd [1933]
1 KB 515 at 523 per Lord Hanworth MR). The latter type of clause is not
in issue here, however. Where a contract contains a dispute resolution
clause, and a party who has not first proceeded in accordance with
that clause sues on the contract, the court has, however, a jurisdiction
to stay the proceeding so as, in a practical sense, to force the party to
fall back upon the contractual procedure. The circumstances in which
a stay will be granted are considered in Jacobs, Commercial Arbitration:
Law and Procedure (2001), at [12.49/5] - [12.49/8]. There are no
proceedings on the agreement in the present case, and it is therefore not
necessary to consider those principles.” (emphasis added)
…
In this case, there is no provision for arbitration – the parties are to attempt to
solve their problems through discussion at increasing levels of responsibility.
In the absence of resolution, the matter may be referred to an expert or the
parties can litigate.
The burden on the parties to an application to stay proceedings was considered
by Chesterman J. He said:
“[21] ... However, a stay will not be granted if it would be unjust to
deprive the plaintiff of the right to have his claim determined judicially
or, to put it slightly differently, if the justice of the case is against staying
the proceeding. The party opposing the stay must persuade the court that
there is good ground for the exercise of the discretion to allow the action
to proceed and so preclude the contractual mode of dispute resolution.
The onus is a heavy one. The court should not lightly conclude that the
agreed mechanism is inappropriate.
-- 11 of 16 --
12
[22] Ordinarily I would think that that onus can be discharged only by
showing that, in the particular case, the dispute is not amenable to
resolution by the mechanism the parties have chosen. This consideration
includes the procedure, if any, for which the parties have contracted, and
the qualification of the expert or referee to embark upon the
determination of the dispute. ...” (footnotes omitted, emphasis added)
[33] In WTE Co-Generation v RCR Energy Pty Ltd,28 Vickery J of the Supreme Court of
Victoria summarised the relevant principles in relation to contractual dispute
resolution provisions expressed to be a pre-condition to litigation:
1. The general rule is that equity will not order specific performance of a dispute
resolution clause, notwithstanding that it may satisfy the legal requirements
necessary for the court to determine that the clause is enforceable. This is
because supervision of performance pursuant to the clause would be untenable.
2. The Court may, however, effectively achieve enforcement of a dispute
resolution clause by default, by ordering that a proceeding commenced in
respect of a dispute subject to the clause, be stayed or adjourned until such time
as the process referred to in the clause, is completed. What is enforced by this
means is not co-operation and consent of the parties but participation in a
process from which consent might come.
3. A circumstance which will operate to preclude the ordering of a stay on this
ground arises where the particular dispute resolution clause is determined to be
unenforceable, as where for example, the clause is found to be uncertain.
4. Dispute resolution clauses in contracts should be construed robustly to give
them commercial effect. The modern approach to the construction of
commercial agreements is generally to endeavour to uphold the bargain by
eschewing a narrow or pedantic approach in favour of a commercially sensible
construction, unless irremediable obscurity or a like fundamental flaw indicates
that there is, in fact, no agreement.
5. Honest business people who approach a dispute about an existing
contract will often be able to settle it. If business people are prepared in the
exercise of their commercial judgment to constrain themselves by reference to
express words that are broad and general, but which nevertheless have sensible
and ascribable meaning, the task of the court is to give effect to and not to
impede such solemn express contractual provisions. Uncertainty of proof does
not detract from there being a real obligation with real content.
6. A dispute resolution clause in a contract, consistently with public policy in
promoting efficient dispute resolution, especially commercial dispute
resolution, requires that, where possible, enforceable content be given to
contractual dispute resolution clauses.
7. The trend of recent authority is in favour of construing dispute resolution
clauses where possible, in a way that will enable those clauses to work as the
parties appear to have intended, and to be relatively slow to declare such
provisions void either for uncertainty or as an attempt to oust the jurisdiction of
the court.
8. The court does not need to see a set of rules set out in advance by which the
agreement, if any, between the parties may in fact be achieved. The process
need not be overly structured. However, the process from which consent
28 [2013] VSC 314, [39].
-- 12 of 16 --
13
might come must be sufficiently certain to be enforceable. A contract which
leaves the process or model to be utilized for the dispute resolution ill defined,
or the subject of further negotiation and agreement, will be uncertain and
unenforceable.
9. An agreement to agree to another agreement may be incomplete if it lacks the
essential terms of the future bargain.
10. An agreement to negotiate, if viewed as an agreement to behave in a
particular way, may be uncertain, but is not incomplete. The relevant question
is whether the clause has certain content.
11. An obligation to undertake discussions about a subject in an honest and
genuine attempt to reach an identified result is not incomplete. (footnotes
omitted) (emphasis added)
[34] In opposing a stay, Contrast must persuade the tribunal that there are good grounds
for the exercise of the discretion to allow the action to proceed and so preclude the
contractual mode of dispute resolution. In exercising the discretion to order a stay of
the proceedings, a relevant consideration is whether a stay the effect of which would
be to require the parties to engage in the contractual dispute resolution process, would
be of any utility. It is relevant also to consider whether the process outlined in clause
42 is one from which a resolution of the dispute might come, whether the conduct of
the parties has been such that they will approach the process with the necessary
goodwill to attempt to resolve the dispute, and whether the process is sufficiently
structured to provide a framework within which the parties may resolve the dispute.
[35] By the time the present proceedings had been commenced a number of events had
transpired: the respondents had purported to terminate the contract and lodge a claim
with the QBCC under the Home Warranty Scheme; the respondents had made a
complaint to the QBCC about defective building work; the QBCC had dismissed the
defective building work complaint on the basis that the respondents had denied
Contrast access to the works; the review proceedings had been listed for a hearing in
the tribunal. During the course of these events the parties had every opportunity to
engage in discussions with a view to attempting to resolve the issues in dispute
between them. That they did not, speaks to the utility of requiring them to engage in
a further, informal, dispute resolution process.
[36] The respondents say, inter alia, that they ‘intend to hold (Contrast) to their bargain,
including the dispute resolution provisions’.29 The respondents’ submissions convey
no apparent willingness to negotiate in a meaningful way to achieve a resolution of
the dispute. Rather, the submission reinforces a perception that the respondents are
focussed less upon resolving the dispute than creating obstacles to the continuation of
the present proceedings. It is evident that the respondents have actively taken various
points in pursuing their entitlements. The respondents’ conduct, before and during the
review proceedings, supports this view:
(a) The respondents contended that, while Contrast responded to the respondents’
Show Cause Notice delivered under the contract on the due date, the response
was not delivered by 5:00pm. The tribunal found to the contrary in the review
proceedings;30
29 Respondents’ submissions filed 29 October 2019, [87].
30 Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63, [51].
-- 13 of 16 --
14
(b) The respondents made no apparent attempt to negotiate with Contrast after
terminating the contract and before making the claim under the Home Warranty
Scheme. The respondents purported to terminate the contract on 21 November
2017. They made a claim under the Home Warranty Scheme on 5 December
2017. At no stage did the respondents give to Contrast a notice under clause 42
of the contract;
(c) The respondents vigorously contested the review proceedings with the tribunal
finding:
The applicants have filed a significant volume of evidence in this
proceeding, much of which was repetitive. They also filed lengthy
submissions after the three day hearing and again, they contain evidence
as well. The final submissions in reply in particular go far beyond a
response to the Commission’s submissions. It has been an onerous task
to sift through the material to try and discern the substantive issues going
to whether the contract was properly terminated.31
(d) The respondents’ have appealed the decision of the tribunal in the review
proceedings.32
[37] Finally, and perhaps most relevantly, there is the fact that the parties participated in a
compulsory conference in the tribunal on 19 November 2019. The purposes of a
compulsory conference include promoting a settlement of the dispute the subject of
the proceeding.33 The dispute was not resolved at the compulsory conference.
[38] Whilst the respondents were entitled to pursue the review proceedings, in my view
their position in relation to the termination of the contract and what flows therefrom
is clearly so entrenched as to make any prospect of a negotiated resolution of matters
with Contrast unlikely, at least through the mechanism provided for in clause 42.
Having been unable to resolve the dispute in a compulsory conference, it seems almost
inevitable that any informal dispute resolution process will produce no result other
than to prolong the present proceedings.
[39] There is, in my view, no reasonable prospect of the dispute resolution process pursuant
to clause 42 of the contract achieving any useful outcome. I am therefore satisfied
that, had clause 42 survived termination of the contract, Contrast has met the ‘heavy
onus’ of establishing why a stay of the proceedings should be refused.
Section 77(2) of the QBCC Act
[40] The respondents contend that Contrast failed to comply with s 77(2) of the QBCC Act
before commencing the proceedings.
[41] Section 77(2) provides that a person involved in a building dispute may not apply to
the tribunal to have the tribunal decide the dispute unless the person has complied
with a process established by the commission to attempt to resolve the dispute.
31 Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63, [147].
32 Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) s 28(3)(b) – the tribunal
may inform itself in any way it considers appropriate. The filing of the appeal is a matter of public
record.
33 Ibid s 69(b).
-- 14 of 16 --
15
[42] It is reasonably clear on the material before the tribunal that:
(a) A building contract dated 17 February 2016 was entered into between the
parties;
(b) The respondents purported to terminate the contract on 21 November 2017;
(c) Contrast purported to terminate the contract on 1 December 2017;
(d) The respondents subsequently made a claim under the Home Warranty Scheme
in respect of incomplete building works;
(e) On 20 March 2018 the QBCC wrote to Contrast and advised it had decided the
respondents had not properly terminated the contract and they had no
entitlement to pursue a claim under the Home Warranty Scheme;
(f) The respondents commenced proceedings in the tribunal seeking a review of the
QBCC decision (the review proceedings);
(g) On 12 April 2018 the QBCC wrote to Contrast referring to ‘the defective
building dispute’ at the respondents’ property, noting that as the respondents
had not provided Contrast with reasonable access to the site to rectify the defects
the ‘current case’ was closed. The letter also advised Contrast that it had
‘participated in the QBCC’s dispute resolution process as prescribed by
legislation …’;
(h) On 28 June 2019 the QBCC wrote to Contrast advising that:
(i) the dispute between the parties related to a building contract had been
terminated;
(ii) the dispute was outside the scope of the QBCC’s Early Dispute Resolution
process;
(iii) Contrast had participated in the QBCC’s dispute resolution process as
prescribed by legislation;
(i) On 19 August 2019 the present proceedings were commenced;
(j) On 4 November 2019 the QBCC wrote to Contrast advising that it had ‘reached
the end of (the QBCC’s) dispute process’;
(k) On 27 February 2020 the tribunal decided the review proceedings and
confirmed the original decision by the QBCC;
(l) On 2 March 2020 the QBCC wrote to Contrast advising that their letter of 28
June 2019 contained a typographical error (that error being the reference to the
male respondent as the builder) and enclosing a further letter dated 20 March
2020 (in the same terms as the letter of 28 June 2019) correcting the error.
[43] I am satisfied that the ‘dispute resolution process as prescribed by legislation’ referred
to in the letters from the QBCC to Contrast dated 12 April 2018 and 28 June 2019
(noting the subsequent clarification by the QBCC regarding the contents of the latter
correspondence referred to above) is a reference to ‘a process established by the
commission’ as referred to in s 77(2) of the QBCC Act.
[44] In circumstances where the QBCC is satisfied that a party to a building dispute has
complied with a process established by the commission for the purposes of s 77(2),
-- 15 of 16 --
16
what form that process might take, and whether parties to a building dispute have
complied with such a process, is a matter for the QBCC.
[45] I am satisfied that Contrast complied with s 77(2) of the QBCC Act before
commencing the proceedings.
Conclusion
[46] The respondents’ application for miscellaneous matters is refused. I will make
directions for the matter to proceed in the usual manner.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2020/194