Clarke v Queensland Building and Construction Commission [2020] QCAT 88
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Clarke v Queensland Building and Construction
Commission [2020] QCAT 88
PARTIES: EDWARD CHARLES CLARKE
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR395-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 31 March 2020
HEARING DATE: 17 September 2019
DATE FINAL
SUBMISSIONS
RECEIVED:
19 December 2019
HEARD AT: Brisbane
DECISION OF: Member Olding
ORDERS: The internal review decision of the Queensland
Building and Construction Commission on 9 October
2018 is confirmed.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE
RECTIFICATION OF DEFECTIVE OR INCOMPLETE
BUILDING WORK – where applicant requested notice to
rectify incomplete work – where regulated contract not
signed by builder of no effect – decision not to give notice
to rectify confirmed
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 87; Schedule 1B s 14(2), s 14(10), s 44
APPEARANCES &
REPRESENTATION:
Applicant: N Glen, Senior Lawyer, Queensland Building and
Construction Commission
Respondent: Self-represented
-- 1 of 5 --
2
REASONS FOR DECISION
Latitude Construction Consulting Pty Ltd (‘the builder’) carried out domestic building
work for the applicant, Mr Clarke. The work mainly involved constructing a new
house at the rear of Mr Clarke’s land as well as some work related to an existing house
on the land.
Mr Clarke alleges the builder failed to complete three other agreed items of work
relating to the existing dwelling (‘the disputed works’). The builder says their
contractual arrangements did not require the disputed items to be undertaken.
Mr Clarke asked the Queensland Building and Construction Commission (‘the
Commission’) to issue a direction to rectify to the builder requiring the builder to
complete the work. The Commission declined to issue the direction.
The Commission confirmed that decision on internal review. Mr Clarke has applied
to the Tribunal for review of the internal review decision. 0F
1
Power to issue direction to rectify
The power to direct a person who carried out building work to rectify the work is
found in s 72 of the Queensland Building and Construction Commission Act 1991
(Qld) (‘QBCC Act’) which in accordance with s 72(1) relevantly applies if the
Commission, and thus the Tribunal on review, is of the opinion that the building work
is ‘incomplete’.
There is no definition of ‘incomplete’ for this purpose, but since the disputed works
were not commenced it is not in dispute that, if they were required to be undertaken,
the works were incomplete.
Where s 72 applies because, so far as this matter is concerned, works are incomplete,
the Commission ‘may’ direct the person who carried out the building work to rectify
the work: s 72(2).
The ‘contracts’ issue
There were various ‘contracts’ in evidence. The difficulty is that none of the
‘contracts’ were signed by the builder.
Mr Clarke says that one of them, which includes in his handwriting a reference to the
disputed works, reflects his agreement with the builder. The builder’s representative,
Mr Quinlivan, says that he has never seen this ‘contract’ with the handwritten addition
of the disputed works added. He maintains that, because he did not sign any of the
contracts, there was no written contract, but rather an oral contract the terms of which
were ultimately limited to carrying out work in detailed plans relating to the new
house. Mr Clarke says this is not credible evidence because in fact the builder did
carry out other work relating to the existing house.
The parties approached the matter on the basis that the Tribunal could determine what
were the contractual arrangements between Mr Clarke and the builder. The
Commission submitted that the builder’s version should be preferred and on that basis
it could not be said that the works were incomplete as the builder had not contracted
to carry out the disputed works. Mr Clarke submitted that his account should be
1 The Tribunal’s jurisdiction is found in the Queensland Building and Construction Commission Act
1991 (Qld), s 87.
-- 2 of 5 --
3
accepted and since the disputed works were not carried out a direction to rectify should
be issued.
At the hearing, I noted that s 14(2) of Schedule 1B to the QBCC Act states, in respect
of a level 2 regulated contract,1F
2 that:
The contract must be in written form, dated and signed by or on behalf of each
of the parties to it.
I invited the parties to make submissions regarding the impact of this. Mr Clarke did
not address the issue. In written closing submissions filed after the hearing in
accordance with a direction of the Tribunal, the Commission submitted that the fact
that the ‘contract’ did not comply with s 14(2) did not make it void or unenforceable.
The Commission referred to Schedule 1B, s 44 of the QBCC Act which states:
Unless the contrary intention appears in this Act, a failure by a building
contractor to comply with a requirement of this Act in relation to a domestic
building contract does not make the contract illegal, void or unenforceable.
On this basis, the Commission submitted that s 14(2) does not make the contract void
or unenforceable and the Tribunal could determine the scope of the contractual
agreement between the parties.
However, s 44 is subject to the contrary intention appearing in the Act. In that regard,
s 14(10) of Schedule 1B states:
The contract only has effect if it complies with subsection (2).
In my view, that is an unequivocal expression of an intention that is contrary to the
general principle in s 44. A contract that is does not have effect is of no effect and
therefore ‘void or unenforceable’. Thus the general rule in s 44 is displaced by this
specific rule that level 2 regulated contracts are only of effect if in writing, signed by
or on behalf of both parties and dated.
I therefore conclude that any ‘contract’ between Mr Clarke and the builder is of no
effect. It follows that I cannot turn to a contract to determine whether the disputed
works were incomplete.
Should a notice to rectify or remedy be given?
When deciding whether to give a direction, the Commission, and therefore the
Tribunal on review, is not limited to consideration of the contract. Section 72(3)
states:
In deciding whether to give the direction, the commission may take into
consideration all of the circumstances it considers are reasonably relevant and,
in particular, is not limited to a consideration of the terms of the contract for
carrying out the building work (including the terms of any warranties included
in the contract).
I doubt that the particular application of the general rule in s 72(3) encapsulated in the
statement that the Commission ‘is not limited to a consideration of the terms of the
contract’ contemplates consideration of what would have been a contract but for a
purported contract being void and of no effect. As the word ‘contract’ in that part of
2 It is not disputed that the monetary amounts under either version of the alleged ‘contract’ mean it
would be a level 2 regulated contract.
-- 3 of 5 --
4
the subsection is preceded by the definite article, the more natural reading is that it
contemplates that where there is such a contract the Commission is not limited to
consideration of the terms of the contract.
Nevertheless, under s 72(3) the Commission, and therefore the Tribunal on review,
may take into consideration all circumstances that it considers are reasonably relevant.
Although the provision says that such circumstances ‘may’ be taken into
consideration, it is difficult to envisage a circumstance that would be reasonably
relevant but not appropriately be taken into consideration. I approach my task on the
basis that I should take into consideration any circumstance that is reasonably relevant
to whether to give a notice to rectify.
What is reasonably relevant must be determined in the context of the matter under
consideration. This is not a case where work has been commenced and from that
circumstance it might be inferred that the work was incomplete. Nor is it a case where
the intended agreement between an owner and a builder is clear, but the agreement
has been rendered unenforceable by failure to comply with the requirement for a
written contract that is signed and dated. 2F
3 The terms of the arrangement between the
parties are hotly contested.
On the view that I have taken what would have been the contractual arrangements but
for s 14(10) is not a relevant circumstance to take into consideration. Accordingly, it
is not necessary or appropriate to make findings regarding the intended terms of the
‘contract’.
In the end, I am left with this. Whether building work that has not been commenced
is incomplete can only be tested against the contract between the owner and the
builder. Here, by force of s 14(10), there is no contract. The contractual documents
not being signed by both parties are of no effect. There is no other means of
determining whether the work is complete or not complete.
In those circumstances, I am unable to determine whether the work is incomplete and
it follows that I am unable to be satisfied that the power to give a direction to rectify
is enlivened.
The alternative of considering what would have been the contract but for s 14(10)
would not be coherent with the QBCC Act as a whole. If, for example, I were to
determine that the builder would have been bound to carry out the disputed work 3F
4 but
for s 14(10), and give a direction to rectify requiring the work be carried out, that
would be tantamount to enforcing what the Parliament has unequivocally stated to be
of no effect and thus unenforceable – a level 2 regulated contract not signed by both
parties.
Mr Clarke may consider this result to be unfair, especially since he says he signed the
alleged contract but the builder, who should be familiar with relevant legislative
requirements, did not. As the Commission observed, the builder may have committed
an offence by undertaking the work without a signed contract; however, it is no part
of the Tribunal’s role to comment on that.
More to the point, level 2 regulated contracts are significant contracts. The statutory
requirement for them to be in writing, dated and signed by or on behalf of both parties
3 I make no observation regarding how, if at all, s 72(3) would apply in either such circumstances.
4 Lest there be any doubt, I confirm that I make no such finding.
-- 4 of 5 --
5
is there for a self-evident reason – to minimise disputes, of which the current matter
is an example, about the terms of such contracts. There is obviously a consumer-
protection element to the evident policy of the legislation, but there is also a broader
public interest in the minimisation of disputes the resolution of which, through
publicly-funded mechanisms such as the Commission’s and Tribunal’s review
processes, comes at a cost to the general public. It is prudent for owners entering into
significant arrangements with builders to ensure they have a written contract signed
by both parties and dated. Parliament’s plain intention is that owners or builders who
fail to observe that requirement do so at their peril.
For these reasons, I must confirm the internal review decision.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2020/088