Alluvion Property Pty Ltd v MDP Developments Pty Ltd [2020] QCAT 73
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Alluvion Property Pty Ltd v MDP Developments Pty Ltd
[2020] QCAT 73
PARTIES: ALLUVION PROPERTY PTY LTD
(applicant)
v
MDP DEVELOPMENTS PTY LTD
(respondent)
APPLICATION NO/S: BDL105-19
MATTER TYPE: Building matters
DELIVERED ON: 11 March 2020
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
ORDERS: Application for miscellaneous matters filed 3 July
2019 refused.
Proceeding dismissed.
The parties must file and exchange submissions on
costs of the proceedings within 14 days of the date
of this decision.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT - where
applicant is not a party to the contract – where applicant
does not assert claim in negligence, nuisance or trespass –
whether QCAT has jurisdiction
COURT PRACTICE & PROCEDURES – AUSTRALIA
– QUEENSLAND CIVIL PRACTICE – QCAT
LEGISLATION - Queensland Civil and Administrative
Tribunal Act 2009 (Qld), s 47 – where respondent seeks to
have the applicant’s claims in QCAT struck out for want
of jurisdiction – whether applicant’s application should be
struck out pursuant to s 47
COURT PRACTICE & PROCEDURES – AUSTRALIA
– QUEENSLAND CIVIL PRACTICE – QCAT
LEGISLATION - Queensland Civil and Administrative
Tribunal Act 2009 (Qld), s 52 – where applicant
commenced proceedings in QCAT – where applicant seeks
to amend claim and transfer QCAT proceedings to the
-- 1 of 8 --
2
Magistrates Court – whether appropriate case to transfer
proceedings to Magistrates Court
Property Law Act 1974 (Qld), s 55
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 47, s 52(2)
Queensland Building and Construction Commission Act
1991 (Qld), s 1, s 4(1)(a), s 4(8), s 75, s 76, s 77(1), sch
1B, sch 2
Uniform Civil Procedure Rules 1999 (Qld)
Black, G. D Toowoomba Resort Pty Ltd [2007] QCCTB
122
David Securities Pty Ltd v Commonwealth Bank of
Australia (1992) 175 CLR 353
Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232
CLR 635
M & J Gray Investments Pty Ltd v AMP Pacific Fair Pty
Ltd & Ors [2010] QCAT 454
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
REPRESENTATION:
Applicant: Self-represented
Respondent: R Champney, solicitor of Redchip Lawyers
APPEARANCES: This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
MDP Developments Pty Ltd (‘MDP’), contracted with Ruby RG Pty Ltd (‘Ruby’) to
undertake building work. Alluvion Property Pty Ltd (‘Alluvion’), was not a party to
the building contract. Alluvion was however a joint venture partner with MDP.
Alluvion has filed an application for commercial building disputes in which it claims
an amount of $49,300.01 from MDP.1 Alluvion says that the amount claimed is ‘To
repay the monies owed, costs and damages … that were misrepresented by MDP
Developments as payments that were required to be made under the contract.’2
MDP has filed an application to dismiss the proceedings.3 MDP says that Alluvion
was not a party to the building contract, that Alluvion is a party to a joint venture
agreement with Ruby, that Alluvion has no authority to bring the present proceedings
and that the proceedings disclose no cause of action against MDP.4
1 Application for commercial building disputes filed 3 April 2019.
2 Ibid.
3 Application for miscellaneous matters filed 11 June 2019.
4 Affidavit of Mathew Pitman filed 11 June 2019.
-- 2 of 8 --
3
Alluvion has filed an application to amend its initiating application and seeking to
transfer the proceedings to the Magistrates Court. Alluvion says that the amendment
is necessary to properly articulate its cause of action against MDP. The proposed
amendment details a claim for money paid by Alluvion to MDP under what is said to
be a mistake of fact. No further particulars are provided. Alluvion says that the
Tribunal does not have jurisdiction in respect of the dispute and that the proceedings
should be transferred to the Magistrates Court which, says Alluvion, does have
jurisdiction.
MDP opposes the application to transfer the proceedings on the basis that the Tribunal
does not have jurisdiction to hear and decide the dispute and that the claim by Alluvion
is bound to fail, wherever the proceeding is heard.5
Consideration
[6] The relevant enabling Act for the purpose of this proceeding is the Queensland
Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’).
[7] The Tribunal may decide a building dispute.6 A building dispute means a domestic
building dispute, a minor commercial building dispute or a major commercial building
dispute.7 A domestic building dispute means a claim or dispute arising between a
building owner and a building contractor relating to the performance of reviewable
domestic work or a contract for the performance of reviewable domestic work; or a
claim or dispute in negligence, nuisance or trespass related to the performance of
reviewable domestic work other than a claim for personal injuries.8
[8] Reviewable domestic work means domestic building work.9 Domestic building work
includes the erection or construction of a detached dwelling.10 Domestic building
work does not include excluded building work.11 A building contractor includes a
person who carries out building work or manages the carrying out of building work.12
Building work is defined.13 Building work does not include work of a kind excluded
by regulation.14
5 Respondent’s submissions filed 25 July 2019.
6 Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’) s 77(1).
7 Ibid sch 2.
8 Ibid.
9 Ibid.
10 Ibid sch 1B, s 4(1)(a).
11 Ibid sch 1B, s 4(8).
12 Ibid sch 2.
13 Ibid.
14 Ibid.
-- 3 of 8 --
4
[9] A commercial building dispute means a claim or dispute arising between a building
owner and a building contractor relating to the performance of reviewable commercial
work or a contract for the performance of reviewable commercial work; or a claim or
dispute in negligence, nuisance or trespass related to the performance of reviewable
commercial work other than a claim for personal injuries.15 Reviewable commercial
work means tribunal work other than reviewable domestic work.16
[10] Tribunal work has the meaning at s 75 and s 76 of the QBCC Act.
[11] The description of the building works in the contract includes, ‘Keep the existing
house and build two new dwellings at the rear.’17
[12] It is not clear from the material before me whether the building work undertaken by
MDP related to a detached dwelling18 and was therefore domestic building work, or
whether the building work was reviewable commercial work. If the building work
referred to in the contract involved the construction of a duplex or two single detached
dwellings, then it seems to me that the work was probably domestic building work.
[13] It is uncontentious that Alluvion was not a party to the building contract. Alluvion and
Ruby were parties to a Joint Venture Agreement (‘JVA’).19 Pursuant to the JVA, the
parties agreed to develop the property at which the subject building work was
performed. Under the JVA, Ruby was the property owner and Alluvion was the
developer. By clause 5.1 of the JVA the business and operations of the joint venture
were controlled by the Project Committee. The Project Committee comprised a
representative of Ruby and a representative of Alluvion. Among other things the
Project Committee was empowered to make decisions about ‘the builder and the terms
of the Building Contract’. By clause 19.3 of the JVA, Ruby was required to ‘do all
acts and things and sign all documents reasonably required to facilitate the
construction, titling of the Building Works …’ Among other things, Ruby was
required to sign the building contract.
[14] After completion of the building works, by clause 21 of the JVA, Alluvion was
required to take the necessary steps to register the community titles scheme
established in accordance with the Body Corporate and Community Management Act
1997 (Qld) and complete the development.
15 QBCC Act sch 2.
16 Ibid.
17 Residential Building Contract – Level 2 (‘Building Contract’) dated 16 January 2017.
18 QBCC Act sch 1B, s 1, s 4(1)(a).
19 Affidavit of Mathew Pitman filed 11 June 2019, exh MDP-1.
-- 4 of 8 --
5
[15] The obligations arising out of the performance of the building work relating to the
development were, under the JVA, Ruby’s obligations. The JVA did not require the
building contract to be entered into in the joint names of Alluvion and Ruby. Under
the terms of the JVA, Alluvion’s role was to ‘provide Project Management Services
to the Joint Venture.’20 Details of the ‘Project Management Services’ are contained in
an annexure to the JVA. The specified services include ‘day to day co-ordination and
liaison with the Builder’ and ‘contract management’.21 ‘Builder’ is defined in the JVA
as ‘the builder agreed upon by the Parties to be engaged to carry out the construction
work for the Building’.22 Contract management is not defined in the JVA.
[16] The essential requirement for a person to be a ‘building owner’ under the QBCC Act
is that they are a person for whom building work is to be, is being or has been carried
out.23
[17] Alluvion is referred to in the building contract as supplying the plans, specifications
and foundations data. Ms Hollie Layton, a director of Alluvion, is identified in the
building contract as Ruby’s agent. The building contract provides that the agent is to
act on the owner’s behalf with respect to the administration of the contract and the
performance of the owner’s obligations under the contract.24 It seems tolerably clear
on the material before me that the building contract was entered into by Ruby in
accordance with, and to facilitate, the JVA.
[18] The parties have not yet filed their statements of evidence. The Tribunal is not a
pleadings jurisdiction. It is the statements of evidence that, to a large extent, perform
the functions of pleadings in articulating, particularising and clarifying the issues in
dispute. In the absence of statements of evidence there is something of a lack of clarity
in relation to the issues.
[19] MDP’s evidence, limited as it is, is that it was not aware of the existence of the JVA
at the time the building contract was entered into. Alluvion has filed no evidence.
[20] I would make the observation that it is a curious feature of the proceeding that Ruby
is not a party nor has Alluvion taken any steps to join Ruby.
[21] Neither party has referred me to any relevant authority in QCAT or any predecessor
tribunal addressing the issue as to the jurisdiction of the tribunal in respect of a dispute
between a builder and a person who was not a party to the building contract but who
asserts an interest in the building works pursuant to a separate agreement with the
owner.
[22] In Black, G. v Toowoomba Resort Pty Ltd (‘Black’)25 the former Commercial and
Consumer Tribunal was required to decide a dispute between a builder (Black) and an
owner (Toowoomba) in relation to a contract for the construction of a townhouse
20 Building Contract cl 4.1(1).
21 Ibid annx B.
22 Ibid cl 1.1(9).
23 QBCC Act sch 2. This is so in respect of both commercial building disputes and domestic building
disputes.
24 Building Contract cl 29.11.
25 [2007] QCCTB 122.
-- 5 of 8 --
6
development. The evidence before the tribunal was that the owner was a joint venturer
with other persons who were not parties to the proceedings.
[23] The tribunal found:
On the evidence, the respondent, when entering into the building contracts was
doing so on behalf of, and to facilitate, the joint venture arrangements. The
transfer of the units to one of the joint venturers affects no change in the nature
of the respondent’s loss, which is synonymous, at all relevant times, with the
loss suffered by the joint venture. It is not, as the applicant submitted, a different
loss (or no loss) that the respondent has suffered as a result of the transfer of the
units.26
[24] Black27 is clearly distinguishable on its facts. Firstly, the parties to the proceedings
were the parties to the building contract. Secondly, the issue was not one of the
jurisdiction of the tribunal to hear and decide the claim, but rather the recoverability
of damages for defective building work claimed by the owner who was a joint
venturer. Black has no application in the present case.
[25] As I have observed, Alluvion was not a party to the contract. Alluvion does not seek
to rely upon s 55 of the Property Law Act 1974 (Qld) and in any event it is difficult to
apprehend how s 55 would have application in the present case. The only claim by
Alluvion against MDP is one in restitution. It seems to me that any claim for
restitutionary relief as sought by Alluvion against MDP effectively seeks to
redistribute the risks and the rights and obligations for which provision was made by
the contract between Ruby and MDP.28 The contract between Ruby and MDP clearly
stipulates the available remedies in the event of a breach. Whether and to what extent
the terms of the contract exclude the availability of common law and other remedies
is relevant only to the rights of the parties to the contract.
[26] The rights and obligations of Alluvion, such as they are relating to the building work,
are governed by the JVA. Those are rights and obligations as between Alluvion and
Ruby. Alluvion was not the builder and, pursuant to the JVL, Alluvion was required
to facilitate a building contract between the builder and Ruby. Ruby was required to
do all acts and things and sign all documents reasonably required to facilitate the
building works. As I have observed, the obligations as between the builder and Ruby
in respect of the building works were exclusively Ruby’s.
26 Black, G. v Toowoomba Resort Pty Ltd [2007] QCCTB 122.
27 Ibid.
28 Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635.
-- 6 of 8 --
7
[27] In these circumstances it would, in my view, be to introduce an unacceptably elastic
construction of the QBCC Act to accept that a party to a joint venture agreement, in
circumstances such as presently pertain, is a person for whom building work was, is
being, or is to be, carried out and hence, a building owner for the purposes of the
QBCC Act. This view is reinforced where, as here, the builder says it had no
knowledge of the joint venture arrangement at the time the building contract was
entered into with Ruby.
[28] There are other hurdles facing Alluvion. It seeks the recovery of monies paid under a
mistake of fact. In the document ‘Claim’ attached to the originating application,
Alluvion says that it paid monies to MDP it was not required to pay.29 Alluvion says
that this occurred as a result of it not reviewing certain invoices before payment ‘due
to a prior friendship’.30
[29] Since the decision of the High Court in David Securities Pty Ltd v Commonwealth
Bank of Australia,31 there is no distinction to be drawn between payments made under
a mistake of law and payments made under a mistake of fact. Underpinning this is the
‘unifying concept’ of unjust enrichment adopted by the High Court in Pavey &
Matthews Pty Ltd v Paul.32 A ‘voluntary’ payment (that is, one made in satisfaction
of an honest claim) is not recoverable on the ground of mistake. A payment is
voluntary if the payer chooses to make the payment even though he or she believes a
particular law or contractual provision requiring the payment is, or may be, invalid,
or is not concerned to query whether payment is legally required, or if the payer is
prepared to assume the validity of the obligation, or is prepared to make the payment
irrespective of the validity or invalidity of the obligation, rather than contest the claim
for payment.
[30] It seems to me therefore that, aside the question of the jurisdiction of this tribunal to
hear and decide the matter, the claim as presently framed by Alluvion faces a number
of challenges.
[31] MDP seeks to have Alluvion’s application dismissed. Section 47 of the Queensland
Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) is a summary
judgment power. The power conferred by s 47 should only be exercised in those cases
where it is clear that a party has no real prospects of success and there is no need for
a hearing. For MDP to be successful in the application for summary dismissal, I must
be satisfied that Alluvion has no real prospect of success in the proceedings.
29 Applicant’s claim filed 3 April 2019.
30 Ibid.
31 (1992) 175 CLR 353.
32 (1987) 162 CLR 221.
-- 7 of 8 --
8
[32] I am satisfied the tribunal does not have jurisdiction to hear and decide the matter.
The proceedings brought by Alluvion are misconceived and should be dismissed.
[33] Alluvion says that the proceedings should be transferred to the Magistrates Court.33
[34] The Tribunal may, if the Tribunal considers it does not have jurisdiction to hear all
matters in a proceeding, order the transfer of the matter or matters to a court of
competent jurisdiction.34
[35] I am not satisfied that it is appropriate to transfer the proceedings to the Magistrates
Court. The application filed by Alluvion does not articulate a cause of action in a form
in any way harmonious with the Uniform Civil Procedure Rules 1999 (Qld). In M &
J Gray Investments Pty Ltd v AMP Pacific Fair Pty Ltd & Ors35 then QCAT President
Alan Wilson J stated:
[14] Procedural difficulties will arise here if M & J’s application to QCAT is
transferred to the Supreme Court. Despite substantial verbiage and attachments,
it is not in a form which would constitute an adequate pleading. Because it was
filed before the lessors’ action was commenced in the Supreme Court, it is also
unresponsive and on any view M & J, or both parties, would be required to re-
plead if the QCAT application was simply transferred to the Court.
[15] It is not, then, a matter in which a transfer to the Court can be readily or
comfortably facilitated. It is not impossible that, had M & J’s legal
representatives turned their minds to the matter, appropriate directions may
have been fashioned but, in the absence of any attempt to do that, the better
course is to simply dismiss the QCAT proceeding and allow M & J to seek its
relief in the present Supreme Court action (or elsewhere if it chooses).
[36] The proceedings should be dismissed and I order accordingly. Alluvion may
commence proceedings in another place by filing a properly articulated and
particularised pleading.
[37] I also order that the parties file and exchange submissions on costs.
33 Application for miscellaneous matters filed 3 July 2019.
34 Queensland Civil and Administrative Tribunal Act 1991 (Qld) s 52(2).
35 [2010] QCAT 454, [14]-[15].
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2020/073