Bein v Brooks & Anor [2020] QCAT 5
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bein v Brooks & Anor [2020] QCAT 5
PARTIES: JOHN JOSEPH BEIN
(applicant)
v
KEVIN BROOKS
and
MARION SWEET
(respondents)
APPLICATION NO/S: BDL164-19
MATTER TYPE: Building matters
DELIVERED ON: 15 January 2020
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Acting Senior Member Paratz
ORDERS: The application for miscellaneous matters filed by
Kevin Brooks and Marion Sweet on 26 August 2019
(as to striking out the domestic building dispute
application) is dismissed, with no order as to costs.
I direct that:
John Joseph Bein is deemed to have complied with
the provisions of section 77 (2) of the Queensland
Building and Construction Commission Act 1991
(Qld) as to participation in a dispute resolution
process established by the QBCC.
Compliance by John Joseph Bein is waived under
section 61 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) for the filing
of a letter from the QBCC as to participation in a
dispute resolution process.
John Joseph Bein is to advise the Tribunal, and
Kevin Brooks and Marion Sweet, whether he
wishes to proceed with the application for domestic
building dispute, by 4:00 pm on 31 January 2020:
If John Joseph Bean advises the Tribunal, and
Kevin Brooks and Marion Sweet, that he does not
wish to proceed with the application for domestic
building dispute by 4:00pm on 31 January 2020, the
-- 1 of 8 --
2
application for domestic building dispute will be
dismissed upon receipt of such notification.
If John Joseph Bein:
(i) advises the Tribunal, and Kevin
Brooks and Marion Sweet, that he
wishes to proceed with the application
for domestic building dispute by
4:00pm on 31 January 2020, or
(ii) fails to notify the Tribunal, and Kevin
Brooks and Marion Sweet, as to
whether he wishes to proceed with the
application for domestic building
dispute by 4:00 pm on 31 January
2020,
(1) The time for Kevin Brooks and Marion Sweet to
file a Response to the application for domestic
building disputes, as directed by Direction 3 of
the directions made on 5 July 2019, is extended
to 4:00 pm on 21 February 2020, and
(2) The application for domestic building disputes
is to be set for a Directions Hearing at a date and
time to be advised by the Tribunal (not before
21 February 2020).
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where
an application to strike out was brought on the basis of non-
compliance with section 77(2) of the Queensland Building
and Construction Commission Act 1991 (Qld) – where it
was held that the applicant had complied with a process
established by the commission to attempt to resolve the
dispute in accordance with section 77(2) – whether the
filing of a letter from the Queensland Building and
Construction Commission as to participation in a dispute
resolution process is a procedural or a jurisdictional step
Queensland Building and Construction Commission Act
1991 (Qld), s 77(2)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 61, s 100, s 102
REPRESENTATION:
Applicant: Self-represented
Respondent: Aitchison Reid Building and Construction Lawyers
APPEARANCES: This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld).
-- 2 of 8 --
3
REASONS FOR DECISION
[2] Kevin Brooks and Marion Sweet (‘the owners’) filed an application for miscellaneous
matters on 26 August 2019 seeking that the application for domestic building dispute
filed by John Joseph Bein (‘the builder’) on 18 June 2019 be struck out (‘the strike
out application’).
[3] Directions were made at a compulsory conference on 25 September 2019 for the filing
of submissions in relation to the strike out application, and for it to be decided on the
papers.
[4] The basis of the strike out application was alleged non-compliance with section 77 (2)
of the Queensland Building and Construction Commission Act 1991 (‘the QBCC
Act’).
[5] Sections 77 (1) and 77 (2) of the QBCC Act are as follows:
77 Tribunal may decide building dispute
(1) A person involved in a building dispute may apply, as provided under the
QCAT Act, to the tribunal to have the tribunal decide the dispute.
(2) However, the person may not apply to the tribunal unless the person has
complied with a process established by the commission to attempt to
resolve the dispute.
[6] Direction 1 was made by the Tribunal on 19 November 2019 as to John Joseph Bein
providing evidence, by 4:00 pm on 10 December 2019, in relation to whether there
was a process established by the QBCC pursuant to section 77(2) which he had
complied with prior to 18 June 2019, or that there was no process established by the
QBCC to resolve the dispute.
[7] The matter has been referred to me to decide, in accordance with direction 2 made on
19 November 2019, whether the application for domestic building disputes should be
dismissed on the basis of failure by the builder to comply with direction 1 made on 19
November 2019.
[8] In order to determine whether to dismiss the application for domestic building
disputes under the directions made on 19 November 2019, it is necessary for me to
determine the strike out application as they relate to the same issue.
[9] The grounds of the strike out application were stated to be a reference to the attached
submissions and affidavit of Ruth Elizabeth Hatten affirmed on 22 August 2019.
[10] The owners seek that the application for domestic building disputes be struck out or
dismissed, and that the builder pay all of the respondents’ reasonable costs up to the
determination of the strike out application.1
[11] The submissions in support of the application to strike out or dismiss were filed on 26
August 2019.
1 Ibid [30], [42].
-- 3 of 8 --
4
[12] The owners submit that the builder did not attach a required notification as to section
77 of the QBCC Act with the application for domestic building dispute:2
[7] The applicant did not attach to the proceeding notification from the QBCC
confirming that the Applicant and the Respondents had engaged in the dispute
resolution process, despite this being a requirement of section 77 of the
Queensland Building and Construction Commission Act 1991 (‘QBCC act’)
and stated on the Tribunal Form 26 application for domestic building disputes.
[13] The owners submit that failure to attach the required notification is fatal to the
proceeding:3
[27] The proceeding ought not to have been commenced prior to the QBCC
dispute resolution process being completed.
[28] The applicant’s failure to comply with the QBCC dispute resolution
process is fatal to the proceeding and cannot be cured after the commencement
of the proceeding or by staying the proceeding.
[14] The submissions of the owner outline their view of the QBCC dispute resolution
process:4
21. The QBCC dispute resolution process ordinarily involves the following:
a) an owner providing notification of the alleged defective building work to
the builder and an invitation for the builder to rectify the alleged defective
building work within a reasonable timeframe;
b) failing a satisfactory response or rectification work performed by the
builder, the owner making a complaint to the QBCC;
c) the QBCC notifying both the owner and the builder of the complaint and
inviting the builder to address the owners items of concern;
d) an initial assessment by the QBCC as to whether the QBCC has
jurisdiction to address the owners items of complaint;
e) notification from the QBCC to the parties that a building inspection has
been scheduled and of the parties rights regarding the inspection and
resulting decisions made after the inspection;
f) an inspection by a QBCC building inspector in the presence of the owner
and the builder and/or any of their representatives;
g) the QBCC determining whether it would be fair, in all the circumstances,
to direct the builder to rectify any defective building work identified
during its inspection and providing the parties with:
i. A detailed building inspection report; and
ii. notification of the review rights and the effect of that decision;
h) a right of a party to review the decision made by the QBCC to direct or
not direct rectification of building work;
2 Submissions of the respondents in support of application to strike out or dismiss proceedings and costs,
filed 26 August 2019, [7].
3 Ibid [28].
4 Ibid [21].
-- 4 of 8 --
5
i) an insurance assessment if the builder fails to rectify work subject of a
direction to rectify.
[15] The builder was directed by Direction 2 made on 25 September 2019 to file in the
Tribunal, and give a copy to the owners, of submissions in response to the strike out
application by 4.00 pm on 16 October 2019.
[16] An email was received by the tribunal on 16 October 2019 from John Vincent Bein
(son) and Patricia Ann Bein (wife), who said that they had been given authority to
attend the compulsory conference on the builder’s behalf, submitting a response on
the builder’s behalf.
[17] The submission of 16 October 2019 on behalf of the builder referred to the history of
the matter:5
We believe that it cannot be struck out as we have done all in our power, for the
past 17 months, to complete this project, to no avail. We did call in the QBCC
for help and direction in the early stages of the problems. We tried to bring
closure by asking the certifier to come and do an inspection. We have been to
the Ombudsman who gave advice for the QBCC to review the situation. The
QBCC review said they couldn’t make the decision and referred back to the
inspectors original decisions. After numerous more attempts to sort this and
after the respondents took the QBCC to channel 7 to expose QBCC negligence,
we received a decision notice from the QBCC to say that they had decided to
allow it to go through the insurance process. We had the chance to respond as
to why we believe this should not happen, which we did respond, which in turn,
once again and for the 2nd time, it went back to QBCC review. This time our
reasons were relevant but still unable to make a decision and then, once again,
back to the inspectors original decision.
[18] An email was sent to the builder from Cornelius Koen, Building Inspector, Resolution
Services, QBCC on 29 March 2019 which referred to his role on behalf of the QBCC:6
Dear John Bein,
Case Number: 484349
Inspection Address: 16 Pratincole Close, Mango Hill, Qld 4509
Inspection date and time: Wed. 10/04/2019 at 12:00 pm
I am a specialist QBCC building inspector who will be investigating the
complaint received from Kevin Broocks [sic].
I am here to help both parties resolve the dispute fairly and impartially.
I have a copy of the written notice given to you by the owner listing the
concerns. The QBCC has also emailed you a list of these items, as provided in
the owner’s complaint, to make sure you are fully aware of exactly which items
are in dispute.
What happens next?
5 Submission on behalf of John Joseph Bein, filed 16 October 2019, P 1.
6 Email from QBCC dated 29 March 2019, included in the bundle of documents filed by John Joseph
Bein on 9 December 2019.
-- 5 of 8 --
6
1. You will be invited to attend my inspection of the complaint items on the
above date. I will send you a letter confirming the date and time and explain
what to expect.
2. You have a chance to self-assess the complaint items now and fix any
defective work before the inspection date. If the dispute is resolved now, there
were likely be no need for an inspection and this case will be closed.
3. If the inspection proceeds and I find defective work, the next step in our
process will be to issue a formal notice (called a Direction to Rectify) giving
you 28 days to fix the work.
Act now before it’s too late. You can avoid receiving a Direction to Rectify.
[19] The QBCC issued 3 separate Directions to Rectify between 17 January 2019 and 2
May 2019. Between 28 February 2019 and 13 June 2019 it decided that all the
direction items for those directions had not been completed to a satisfactory standard.7
[20] On 26 July 2019 the QBCC decided to allow the affected party’s claim for non-
completion and defective work under the statutory insurance scheme.
[21] The QBCC issued an amended claim for debt to the builder for $85,250.25 dated 15
October 2019.
[22] In Redding v Simmons,8 the Appeal Tribunal discussed the scope of a ‘dispute process’
as referred to in section 77(2) and whether it was confined only to mediation as to
defective work:9
[14] But is there a mediation process to deal with building disputes that involve
contractual issues other than defective workmanship? Logically, section 77 (2)
leaves open the possibility that the QBCC may not have provided a ‘process’ to
mediate every kind of building dispute. But neither the Act nor the available
evidence offers a clear conclusive answer.
[23] The Appeal Tribunal went on to note that ‘resolving building disputes’ may relate to
issue of a rectification order:10
[18] The focus here is upon substandard work, but ‘Resolving Building
Disputes’ may relate to the QBCC’s relatively long-standing power to issue
rectification orders, rather than to the more recent mediation power now in
question.
[24] The Appeal Tribunal referred to the wording of the QCAT website as to a letter about
participation in a dispute resolution process from the QBCC before making a
commercial domestic building dispute application to QCAT, that ‘applications cannot
be accepted at QCAT without this letter from the QBCC’,11 but did not refer to a
jurisdictional basis for doing so.
[25] The requirement for a letter from the QBCC to accompany an application for a
domestic building dispute is a procedural step adopted by the Tribunal, and referred
to on its website, and on the Application Form for domestic building disputes, rather
than a jurisdictional step under the QBCC Act.
7 QBCC Decision notice, 26 September 2019, p 1.
8 [2016] QCATA 100.
9 Ibid [14].
10 Ibid [18].
11 Ibid [22].
-- 6 of 8 --
7
[26] The Tribunal has power under section 61 of the QCAT act to provide relief from
procedural requirements.
[27] It is clear that Mr Koen, on behalf of the QBCC, outlined a process to attempt to
resolve the dispute, and that, if the dispute was not resolved, he would issue a
Direction to Rectify.
[28] The builder participated in the procedures leading to the issue of the Directions to
Rectify on 2 May 2019 before he filed the Application for domestic building disputes
on 18 June 2019.
[29] The procedures followed by the building inspector, and participated in by the builder,
accord with the procedures which the submissions of the owner (set out earlier in these
reasons) describe as ‘the QBCC dispute resolution process’.
[30] The submissions on behalf of the owners referred to the need for compliance with a
‘proceeding notification from the QBCC’ as to section 77(2) of the QBCC Act. That
is not what the section requires.
[31] Section 77(2) of the QBCC act requires a person to comply with ‘a process established
by the commission to attempt to resolve the dispute’.
[32] The builder has therefore ‘complied with a process established by the commission to
attempt to resolve the dispute’ as referred to in section 77(2) of the QBCC Act,
notwithstanding the absence of a letter to that effect from the QBCC.
[33] As the basis of the application to strike out is upon a failure to comply with section
77(2) of the QBCC Act, that application must fail, and is dismissed.
[34] It is the practice of the Tribunal to deem compliance with section 77(2) where issues
as to compliance are determined, and I will make such a direction.
[35] Whilst it is not explained why a letter has not been provided by, or obtained from, the
QBCC, as to participation in a dispute resolution process, I am satisfied that the
builder has complied with the intent of s 77(2), and has participated in a dispute
resolution process provided by the QBCC, prior to bringing his application for
domestic building disputes, and that it would be unfair for his application to be struck
out on that procedural basis only.
[36] I accordingly waive compliance under section 61 of the QCAT Act for the filing of a
letter from the QBCC, which will resolve the Directions made on 19 November 2019.
[37] The basic rule in the Tribunal (section 100 of the QCAT Act) is that each party bears
their own costs, unless the Tribunal considers the interests of justice require otherwise
(section 102(1) of the QCAT Act). As the application to strike out has been found to
be not supported on jurisdictional grounds, and as no other grounds were relied on for
the application to strike out, I do not consider the interests of justice require the
making of an order as to costs, and I make no order as to costs.
[38] I note that reference has been made to the builders personal situation in the material,
and in light of the period of time that has elapsed since the last steps were taken in this
matter, before the parties are required to take further steps, I will direct that the builder
advise the Tribunal whether he wishes to proceed with the application for domestic
building disputes.
[39] If the builder advises that he does not wish to proceed further, the matter will be
dismissed without further proceedings.
-- 7 of 8 --
8
[40] If the builder advises that he does wish to proceed further, or fails to so advise, the
owners will be given time to file a response, and the matter is then to proceed to a
Directions Hearing.
Orders and Directions
[41] The orders are:
1. The application for miscellaneous matters filed by Kevin Brooks and Marion
Sweet on 26 August 2019 (as to striking out the domestic building dispute
application) is dismissed, with no order as to costs.
[42] I direct that:
2. John Joseph Bein is deemed to have complied with the provisions of section 77
(2) of the Queensland Building and Construction Commission Act 1991 (Qld)
as to participation in a dispute resolution process established by the QBCC.
3. Compliance by John Joseph Bein is waived under section 61 of the Queensland
Civil and Administrative Tribunal Act 2009 (Qld) for the filing of a letter from
the QBCC as to participation in a dispute resolution process.
4. John Joseph Bein is to advise the Tribunal, and Kevin Brooks and Marion
Sweet, whether he wishes to proceed with the application for domestic building
dispute, by 4:00 pm on 31 January 2020.
5. If John Joseph Bein advises the Tribunal, and Kevin Brooks and Marion Sweet,
that he does not wish to proceed with the application for domestic building
dispute by 4:00pm on 31 January 2020, the application for domestic building
dispute will be dismissed upon receipt of such notification.
6. If John Joseph Bein:
i. advises the Tribunal, and Kevin Brooks and Marion Sweet, that he
wishes to proceed with the application for domestic building dispute
by 4:00pm on 31 January 2020; or
ii. fails to notify the Tribunal, and Kevin Brooks and Marion Sweet, as
to whether he wishes to proceed with the application for domestic
building dispute by 4:00 pm on 31 January 2020,
(1) the time for Kevin Brooks and Marion Sweet to file a response to the
application as directed by Direction 3 of the directions made on 5 July 2019
is extended to 4:00 pm on 21 February 2020, and
(2) the application for domestic building disputes is to be set for a Directions
Hearing at a date and time to be advised by the tribunal (not before 21
February 2020).
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2020/005