Bayside Air Conditioning Services Pty Ltd v Doyle [2020] QCATA 31
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bayside Air Conditioning Services Pty Ltd v Doyle [2020]
QCATA 31
PARTIES: BAYSIDE AIR CONDITIONING SERVICES PTY
LTD
(appellant)
v
KEVIN DOYLE
(respondent)
APPLICATION NO/S: APL164-19
ORIGINATING
APPLICATION NO/S:
MCDO 133/18 (Cleveland)
MATTER TYPE: Appeals
DELIVERED ON: 11 March 2020
HEARING DATE: 2 March 2020
HEARD AT: Brisbane
DECISION OF: Member Gordon
ORDERS: Leave to appeal is refused. This means that the appeal
fails.
CATCHWORDS: APPEAL AND NEW TRIAL – PROCEDURE –
QUEENSLAND – WHEN NO APPEAL LIES – where the
appellant effectively seeks a review of the decision made
below – whether a misunderstanding of the Adjudicator
was significant enough to undermine the decision made –
whether any reasonably arguable grounds of appeal
APPEARANCES &
REPRESENTATION:
Appellant: Self-represented
Respondent: Self-represented
REASONS FOR DECISION
This is an appeal from a decision by an Adjudicator in MDCO 133/18 (Cleveland)
which was consolidated with Q76/18 (Cleveland) by an order made by the tribunal on
13 December 2018.
-- 1 of 3 --
2
The dispute between the parties concerned the installation of air conditioning
components by Bayside Air Conditioning Services Pty Ltd in Mr Doyle’s house. Mr
Doyle did not pay Bayside’s invoice for $1,433.301 and so Bayside brought a minor
civil dispute application to try to recover this amount from Mr Doyle. In response to
the claim, Mr Doyle brought a claim against Bayside for damages for $5,402. This
was for the cost of rectification works. He alleged that Bayside failed to install a
hinged grille on the return air duct as it was contractually obliged to do (one that could
readily be opened to maintain the filters behind) and he had also to pay a builder to
correct the size of the opening for the supply air grille in the bulkhead because the
wrong dimensions were given by Bayside to the builder.
Both sides put a fair amount of documentation before the tribunal, and then attended
before the Adjudicator on 7 February 2019. The Adjudicator heard evidence and
submissions that day and read the documentation. What happened at the hearing can
be seen from a transcript of the hearing which has been obtained by the Appeal
Tribunal.
The Adjudicator did not immediately make a decision, but reserved it for further
consideration. Then on 5 June 2019 a final decision was delivered in writing to the
parties, with reasons following later.
The Adjudicator found that the contractual obligations between the parties arose from
a course of dealing between them. Bayside would obtain approvals for each aspect of
work, and then carry out the work in accordance with instructions from Mr Doyle.2
The Adjudicator found that it was an essential term of the contract between the parties
that the return air grille be hinged to provide easy access to the filters behind to allow
them to be cleaned.3 The Adjudicator found that Bayside’s failure to achieve that was
a breach of contract and that Mr Doyle was entitled to an award of $3,410 being the
reasonable cost of removing the existing removable core grille and replacing it with a
hinged grille as required by the contract.
Mr Doyle also succeeded in the second part of his claim. The Adjudicator found that
the cut-out dimensions given by Bayside to the builder for the supply air grille in the
bulkhead had been incorrect, with the result that Mr Doyle had to pay the builder to
correct the size of the opening.4 He was awarded $540 which was the cost of this
work.
As for Bayside’s invoice for $1,433.30, the Adjudicator found that none of this was
payable by Mr Doyle because it either related to the defective work, or to work that
was not in fact done following a justified termination of the contract.5
Part of Mr Doyle’s claim against Bayside failed. This was in respect of damage to the
cupboard door. The Adjudicator found that there was insufficient evidence to
substantiate that claim.6
1 Invoice 35875.
2 Reasons, [25].
3 Reasons, [30].
4 Reasons, [52].
5 Reasons, [39] and [42].
6 Reasons, [53].
-- 2 of 3 --
3
Grounds of appeal
The grounds of appeal are various, but are largely a restatement of the points made
before the Adjudicator, with a request to the Appeal Tribunal to find in Bayside’s
favour instead of Mr Doyle’s favour. This approach cannot succeed. These appeals
are not an opportunity for a party to try to improve on the decision below by seeking
a second opinion. Instead, it is necessary to show that it is just for the appeal to
succeed because of an error of law of the decision maker or a material error in the
factual findings.
Although some fresh evidence was submitted by Bayside in the appeal, there was no
formal application as required by the directions made by the Appeal Tribunal for such
evidence to be accepted by the Appeal Tribunal. At the appeal hearing, whether or
not Bayside was seeking the acceptance of fresh evidence was examined with Mr Platz
who was acting as Bayside’s representative. Again no formal application was made
for the Appeal Tribunal to accept any fresh evidence. Any such application would
require Bayside at least to show that the evidence now sought to be put before the
Appeal Tribunal could not, with due diligence, have been put before the Adjudicator
for the original hearing. It would appear that this could not be shown.
At the hearing of the appeal, and as raised in his written submissions, Mr Platz did
however identify an error in the Adjudicator’s factual findings. The Adjudicator said
that the other air conditioning grilles in the house were hinged.7 It was pointed out by
Mr Platz that this was incorrect. The other grilles, upstairs at least, were held by clips
and were not hinged. Mr Doyle agreed that the Adjudicator did misunderstand this,
and this also appears from the transcript of the hearing.
So the question is whether the misunderstanding was significant enough to undermine
the decision reached by the Adjudicator. The central issue before the Adjudicator was
whether to accept Mr Doyle’s evidence that the contractual agreement was for a
hinged air return grille in the downstairs of the house, and whether that was ever
changed. The Adjudicator found corroboration for Mr Doyle’s evidence about this in
the written materials.8 And as explained in the hearing, the only grille which needed
to be hinged was the air return grille because that was the grille for which access was
needed behind for cleaning.9 It was therefore unimportant and irrelevant to the central
issue whether the other grilles were hinged or clipped. In the circumstances, the
Adjudicator’s misunderstanding about the fixing of those grilles did not undermine
the decision reached.
Leave to appeal refused
In the circumstances there is no arguable ground of appeal. In these types of appeal,
leave is required in order to launch an appeal. I refuse leave to appeal. This means
that the appeal fails.
7 Reasons, [11], [26] and [29].
8 Reasons, [26].
9 Transcript, 1-19 line 46.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2020/031